FACTORS AFFECTING EMPLOYEE PRODUCTIVITY IN...

download FACTORS AFFECTING EMPLOYEE PRODUCTIVITY IN …eprints.brighton.ac.uk/12220/1/Final_Sept_Redacted.pdf · FACTORS AFFECTING EMPLOYEE ... Literature review of the classical ... Factors

If you can't read please download the document

Transcript of FACTORS AFFECTING EMPLOYEE PRODUCTIVITY IN...

  • FACTORS AFFECTING EMPLOYEE

    PRODUCTIVITY IN THE UAE

    CONSTRUCTION INDUSTRY

    NABIL AILABOUNI

    A thesis submitted in partial fulfilment of the requirements of the University of Brighton for the

    degree of Doctor of Philosophy

    September 2010

    School of Environment and Technology University of Brighton

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    ii

    ABSTRACT

    Reliable productivity rates for construction trades are essential for contractors to accurately estimate the time and cost of construction projects. These rates vary considerably based on the complexity of the structure, project site constraints, and other technical, managerial, social and cultural factors. Predicting the effect of these factors will enhance the ability of the contractor to optimally utilize resources. This research therefore aims to evaluate the most significant factors that affect productivity of key construction activities namely: excavation, formwork, reinforcement, concreting, blockwork, plastering and tiling. The research focuses on the construction industry in the UAE (United Arab Emirates).

    Literature review of the classical management theories and contemporary works on construction productivity led to the identification of four generic factors affecting productivity: Environmental, Organizational, Group Dynamics and Individual Factors. Three questionnaire surveys were undertaken to identify the most significant factors and the magnitude of their effect on productivity. The first survey identified the most significant factors after ranking them according to a severity index. The other two surveys identified the magnitude of the effect of these factors on productivity.

    The research used Chi Square Test for Significance, which identified - Work Timings, Control by Supervision, Group Dynamics, Control by Procedures, Climatic Conditions and Material Availability as the most significant factors affecting productivity. Six sites were selected for data collection for productivity rates of the key construction activities. The significant factors were varied at three ordinal levels that afforded practical variations at site. The increase or decrease in productivity obtained was compared to the actual site average productivity and then subjected to regression analysis using MINITAB 15 Statistical Software. This resulted in the development of a regression model for each of the seven key construction activities.

    Four other construction sites were selected and used for validation of the developed models. The developed models have been used to evaluate the variability in productivity of construction activities and to predict the percentage change in productivity of the selected activities when the underlying variables are varied. Review of the coefficients of the factors in the individual regression models afforded insight into those that most affect productivity of the selected construction activities. This intelligent information can help site management to create favourable conditions on site aimed at enhancing productivity rates and therefore optimal utilization of resources.

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    iii

    TABLE OF CONTENTS

    No Description Page No.

    ABSTRACT ii

    TABLE OF CONTENTS. iii

    1 RESEARCH INTRODUCTION... 1

    1.0 Chapter 1 Introduction. 2

    1.1 Need for Research .. 3

    1.1.1 Gap in Knowledge........ 4

    1.2 Research Aim.. 9

    1.2.1 Research Objectives 9

    1.3 Scope of Research . 9

    1.3.1 Definition of Productivity 10

    1.4 Brief Outline of Research . 12

    1.4.1 Review of Existing Literature and Publications. 15

    1.4.2 Data Collection: Survey for Significant Factors 16

    1.4.3 Data Collection: Surveys for Effect of Significant Factors. 17

    1.4.4 Data Collection: Statistical Tests for Significance using Chi Square 18

    1.4.5 Field Data Collection. 18

    1.4.6 Homogenization of Data 20

    1.4.7 Regression Analysis using MINITAB 15 software 21

    1.4.8 Validation of the Models... 22

    1.4.9 Model Application.. 23

    1.5 Chapters Summaries 24

    1.6 Conclusion... 28

    2 LITERATURE REVIEW 30

    2.0 Chapter 2 Introduction.. 31

    2.1 Management Theories.. 35

    2.1.1 The Classical Approach. 35

    2.1.2 The Human Relations Approach.. 37

    2.1.3 The Systems Approach 38

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    iv

    2.1.4 The Contingency Approach... 39

    2.2 Common Factors in Organizations... 39

    2.3 Theories of Motivation. 41

    2.3.1 Early Theories.. 43

    2.3.2 Modern Theories: Content Theories of Motivation.. 44

    2.3.3 Modern Theories: Process Theories of Motivation......... 49

    2.4 Construction Industry Related Productivity Studies. 52

    2.4.1 Factors Affecting Productivity (A review of contemporary

    publications). 53

    2.4.2 Factors Affecting Motivation of Construction Operatives

    (A review of contemporary publications).. 61

    2.5 Background to the UAE Construction Industry ... 71

    2.5.1 Economic Characteristics of the UAE Construction Industry 71

    2.5.2 UAE Labour Market 77

    2.5.3 Demographic Influence and Cultural Backgrounds 78

    2.5.4 Environmental Conditions.. 79

    2.5.5 UAE Statutory Laws 79

    2.5.6 No Trade Unions.. 80

    2.5.7 UAE National Workplace Employment Relations Survey.............. 81

    2.6 Factors Affecting Productivity in the UAE Construction Industry. 84

    2.6.1 Environmental Factors... 87

    2.6.2 Organizational Factors.. 89

    2.6.3 Group / Team Factors.... 94

    2.6.4 Personal Factors. 95

    2.7 Conclusion .. 97

    3 RESEARCH METHODOLOGY. 99

    3.0 Chapter 3 Introduction....................... 100

    3.1 Outline of Research Methodology 100

    3.2 Development of Methodology. 102

    3.3 Survey Questionnaire Design... 104

    3.4 Identification of the Significant Factors Affecting Productivity in the

    UAE...................................................................................................... 104

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    v

    3.5 Perception Surveys for the effect on productivity

    (Survey Nos 2 & 3). 112

    3.6 Analysis of the Results of the Perception Surveys (2) and (3).. 121

    3.7 Chi-Square Test for Significance 122

    3.7.1 Chi-Square Test for Significance (Internal Perception Survey).. 122

    3.7.2 Chi-Square Test for Significance (External Perception Survey .. 123

    3.8 Field Data Collection 127

    3.8.1 Case Study Company . 127

    3.8.2 Field Data Collection .... 127

    3.9 Technical Factors Affecting Productivity 133

    3.9.1 Type of Projects... 134

    3.9.2 Technical Nature of the Trades 134

    3.10 Conclusion 137

    4 DATA COLLECTION, DATA ANALYSIS AND THE

    DEVELOPMENT OF PRODUCTIVITY EVALUATION MODEL... 139

    4.0 Chapter 4 Introduction.. 140

    4.1 Productivity Model: Overall Versus Individual Construction Trades 141

    4.2 Data Collection and Analysis... 143

    4.3 Definition of Statistical Parameters Used 147

    4.3.1 R2 Coefficient of Determination ...... 147

    4.3.2 d Durbin Watson Statistic ..... 147

    4.3.3 Alpha () Level of Significance........ 148

    4.3.4 p-Value ... 149

    4.4 Model Formulation .. 149

    4.4.1 Homogenization of Field Data.. 150

    4.4.2 Statistical Modelling Using MINITAB 15 Software. 153

    4.5 Regression Models For Productivity of Construction Trades.. 157

    4.5.1 Regression Model for the Excavation Trade. 158

    4.6 Conclusion 180

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    vi

    5 MODEL VALIDATION AND EVALUATION OF VARIABILITY

    OF PRODUCTIVITY ............................ 182

    5.0 Chapter 5 Introduction.. 183

    5.1 Background Considerations. 183

    5.2 Sites Used for Model Validation. 185

    5.3 The Validation of the Model 186

    5.4 Validation Excavation Productivity Model ARS Site .. 191

    5.5 Validation Results .... 198

    5.6 Evaluation of Factors Affecting Productivity.. 201

    5.7 Conclusion ... 205

    6 CONCLUSION................. 207

    6.0 Chapter 6 Introduction.. 208

    6.1 Work Accomplished & Challenges Faced .. 208

    6.1.1 Data Collection Techniques and Accuracy ... 210

    6.1.2 Broad Topic of Construction Productivity and Several

    Factors in Combination .. 211

    6.1.3 Understanding Technical Issues with Productivity Numbers . 212

    6.1.4 Short Term Nature of Construction Projects 212

    6.2 Fulfilment of Research Aim and Objectives ... 213

    6.3 Practical Utilization of Model . 214

    6.4 Possible Improvements in the Model .. 216

    6.5 Conclusion... 220

    6.6 Areas for Future Research .. 227

    REFERENCES 230

    BIBLIOGRAPHY.. 237

    LIST OF APPENDICES.................. 245

    Appendix 1 Master Field Data for Model Formulation ....................... 246 - 263

    Appendix 2 Master Field Data for Model Validation ......................... 264 - 285

    Appendix 3 Questionnaire Formats Used ............................................ 286 - 294

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    vii

    Appendix 4 Collection of Productivity Modelling Data & Graphs.. 295 - 323

    For Excavation, Formwork, Reinforcement, Concreting,

    Blockwork, Plastering and Tiling Works

    Appendix 5 Collection of Validation Data & Graphs ................................. 324 - 348

    For Excavation, Formwork, Reinforcement, Concreting,

    Blockwork, Plastering and Tiling Works

    Appendix 6 Predicted Productivity for all Possible Combinations

    of Factor Levels ................................................................. 349 - 383

    Appendix 7 Statistical Tables and Definitions ..................................... 384 - 396

    Appendix 8 Project Profiles ................................................................. 397 - 407

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    viii

    LIST OF TABLES CHAPTER 1

    Table 1.1 Construction Trades and Productivity Factors

    for Field Data Collection. 19

    CHAPTER 2

    Table 2.1 Factors Affecting Job Satisfaction... 48

    Table 2.2 Literature Review Matrix: Collection Of Factors Affecting

    Construction Productivity (General) .. 59

    Table 2.3 Motivating Factors in Construction Industry... 63

    Table 2.4 Motivators and De-Motivators Ranked By Workers in Thailand. 64

    Table 2.5 Differences in Project Characteristics with High/Low Productivity 66

    Table 2.6 Literature Review Matrix: Motivating Factors in the Construction

    Industry.. 68

    Table 2.7 Literature Review Matrix: Factors Affecting Construction

    Productivity across Countries 70

    Table 2.8 Construction Industry Characteristics... 76

    Table 2.9 2001 UAE National Workplace Employment Relations Survey

    Results 83

    Table 2.10 Comprehensive List of Factors Affecting Productivity: UAE

    Construction Industry.... 86

    CHAPTER 3

    Table 3.1 Survey(1) Response Reckoner.. 105

    Table 3.2 Significant Factors Affecting Productivity (First 8 within Groups). 110

    Table 3.3 Significant Factors Affecting Productivity in Matrix Form.. 111

    Table 3.4 Significant Factors Affecting Productivity (Fourteen Factors

    with Highest Ranks)... 112

    Table 3.5 Perception Survey (2) (Internal): Summary Results 114

    Table 3.6 Perception Survey (2) (Internal) : Summary Percentages.... 115

    Table 3.7 Perception Survey (2) (Internal): Weighted Averages 116

    Table 3.8 Perception Survey (3) (External): Summary Results 117

    Table 3.9 Perception Survey (3) (External): Summary Percentages 118

    Table 3.10 Perception Survey (3) (External): Weighted Average Result.. 119

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    ix

    Table 3.11 Combined Analysis % Wise Perception Surveys (2) & (3) ... 120

    Table 3.12 Chi-square Computations: Survey Data Productivity Factors

    And Their Effects Internal Survey... 124

    Table 3.13 Chi-square Computations: Survey Data Productivity Factors and

    their Effects External Survey.............. 125

    Table 3.14 Field Variables Using Weighted Averages from Survey 2 & 3 126

    Table 3.15 Sample Sites and Activities under Study for Productivity.. 129

    Table 3.16 Range Of Productivity Values Trade Wise / Site Wise.. 132

    Table 3.17 Factor Levels Used For Data Collection. 133

    CHAPTER 4

    Table 4.1 Brief Profile of Construction Projects Used For Field Data

    Collection. 144

    Table 4.2 Summary of Data Collected and Used For Formulating Model 146

    Table 4.3a Excel Sheet Used For Model Formulation Excavation 159

    Table 4.3b Regression Models Iteration Summary for Excavation 170

    Table 4.4 Final Regression Models... 173

    Table 4.5 Major Productivity Contributing Factors. 174

    Table 4.6 Extracts from Appendix 5-8a: Excavation

    Trade productivity at Various Runs /Levels of Factors.. 179

    CHAPTER 5

    Table 5.1 Construction Sites Used For Model Formulation and Validation 185

    Table 5.2 Validation Data for Excavation - ARS Site... 192

    Table 5.3 Grand Summary of Validation Data and Results.. 200

    Table 5.4 Summary of Productivity Models.. 201

    Table 5.5 Major Productivity Contributing Factors per Construction Trade 202

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    x

    LIST OF FIGURES CHAPTER 1

    Fig. 1.1 Overview of the Research 14

    CHAPTER 2

    Fig. 2.1 Organizational Sub- Systems 40

    Fig. 2.2 Maslows Hierarchy of Needs Pyramid 45

    Fig. 2.3 Factor Model of Construction Labour Productivity. 57

    Fig. 2.4 General Categories of Factors Affecting Productivity. 84

    CHAPTER 3

    Fig. 3.1 Overview of the Research.. .. 101

    Fig. 3.2 Snapshot of Survey (1) Questionnaire. 104

    Fig. 3.3 Extract of Survey (1) Results For Sample Computation.. 107

    Fig. 3.4 Questionnaire Design for Survey 2 & 3... 113

    CHAPTER 4

    Fig. 4.1 Snapshot of Excel Sheet for Model Formulation - Excavation

    Trade. 151

    Fig. 4.2 Flow Chart : Homogenization of Field Data 153

    Fig. 4.3 Grab of Minitab 15 Menu- Stat-Regression- Graphs .. 155

    Fig. 4.4 Flow Chart : Statistical Modelling Using MINITAB 15 Software.. 156

    Fig. 4.5a Iteration 1- Excavation Modelling Graphs 163

    Fig. 4.5b Iteration 2- Excavation Modelling Graphs 165

    Fig. 4.5c Iteration 3- Excavation Modelling Graphs 167

    Fig. 4.5d Iteration 4- Excavation Modelling Graphs 169

    Fig. 4.6a Graphical Representation of Factors affecting Excavation . 175

    Fig. 4.6b Graphical Representation of Factors affecting Formwork 175

    Fig. 4.6c Graphical Representation of Factors affecting Reinforcement 176

    Fig. 4.6d Graphical Representation of Factors affecting Concreting .. 177

    Fig. 4.6e Graphical Representation of Factors affecting Blockwork .. 177

    Fig. 4.6f Graphical Representation of Factors affecting Plastering. 178

    Fig. 4.6g Graphical Representation of Factors affecting Tiling... 178

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    xi

    CHAPTER 5

    Fig. 5.1 Flow Chart Showing Computation of Errors for Validation 186

    Fig. 5.2 Flow Chart Showing Computation of Errors for Validation 189

    Fig. 5.3a Error Chart For Excavation For The 2 Sigma Limits

    (For Minitab 15)......................................... 195

    Fig. 5.3b Error Chart for Excavation For The 15% Band

    (For Minitab 15)..... 196

    Fig. 5.3c Histogram of Errors (For Minitab15) 197

    Fig. 5.3d Scatter plot (For Minitab 15)................................. 197

    Fig. 5.3e Four in One Excavation Validation Graph ... 198

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    xii

    ACKNOWLEDGEMENT

    I would like to express my gratitude and appreciation to my supervisors - Dr.

    Kassim Gidado, Mr. Noel Painting and Dr. Phil Ashton from the University of

    Brighton for their patience and support, evaluation and direction and mostly their

    encouragement right from the time I set out the research outline to the final

    submission.

    Then I would thank my partners and employees in Target Engineering

    Construction Co. for their help and participation in the surveys, data collection

    and positive encouragement throughout the study period. I would also like to

    thank the members of my family for their help and support during my study.

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    xiii

    AUTHORS DECLARATION

    I declare that the research contained in this thesis, unless otherwise formally

    indicated within the text, is the original work of the author. The thesis has not

    been previously submitted to this or any other university for a degree and does

    not incorporate any material already submitted for a degree.

    Signed _______________________

    Nabil Ailabouni

    Dated September, 2010

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    xiv

    ABBREVIATIONS

    ARCOM - Association of Researchers in Construction Management

    ERG - Existence, Relatedness and Growth

    GCC - Gulf Cooperation Council

    GDP - Gross Domestic Product

    ILO - International Labour Organization

    MOLSA - Ministry of Labour and Social Affairs, UAE

    OECD - Organization for Economic Cooperation and Development

    PASW - Predictive Analytics Software

    PPCM - Percentage Productivity as Measured

    PPCP - Percentage Productivity as Predicted

    SAS - Statistical Analysis Software

    SPSS - Statistical Package for Social Sciences

    UAE - United Arab Emirates

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    1

    CHAPTER 1 RESEARCH INTRODUCTION

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    2

    CHAPTER 1 RESEARCH INTRODUCTION

    1.0 CHAPTER INTRODUCTION

    Productivity rate of construction trades is one of the elements required to

    accurately estimate time and costs required for the construction processes.

    Projects can be better controlled if the variability in productivity of construction

    trades is known, and actions taken to enhance productivity. This research is,

    therefore, aimed at identifying and evaluating the factors affecting productivity

    of construction trades; developing a construction productivity change model for

    predicting changes in productivity as the underlying factors are varied and using

    this information to create favourable conditions for enhanced productivity.

    This chapter introduces the research title, aim, objectives, and definitions of

    productivity while establishing the need for research against the background of

    productivity of construction trades and its importance in the construction

    industry, with a primary focus on the United Arab Emirates (UAE).

    In fulfilment of the research objectives, a literature review was conducted to

    determine the factors that affect productivity. Having identified the broad factors

    affecting productivity, the most significant factors and quantification of the

    magnitude of their effect in productivity rate were identified utilizing a specially

    designed questionnaire that was distributed to key players in construction

    industry. Field data was collected from six sites of the case study company and

    was used to develop the regression models for key construction activities. The

    models were validated using data from four other sites of the case study

    company.

    After a brief discussion on applicability of the models, the chapter concludes with

    summaries of each chapter to give the reader a general outline of the research.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    3

    1.1 NEED FOR RESEARCH

    Knowing productivity rates of various trades in the construction industry is

    critical for an accurate estimation of the time and cost of a job. An improved

    productivity rate helps contractors not only to be more efficient and profitable

    during project execution, but also helps them to be more competitive during the

    bidding stage of the projects.

    The construction industry in the UAE is a multibillion dollar industry,

    contributing approximately 8% to the UAE Gross Domestic Product (GDP).

    (Reference UAE Yearbook 2009). Until the global economic slowdown affected

    the region, the industry was buoyed by high liquidity owing to the high oil prices,

    government spending and stable political environment. There is a continued

    supply of comparatively cheap labour from the Asian countries. The workforce is

    subject to several influences such as - different management styles, language

    barriers, customs, separation from families, level of supervision, quality of

    accommodation and climate. Such influences have direct impact on productivity

    rates.

    All contractors within the UAE face similar amount of constraints; same

    specifications apply and therefore the bottom line performance of contractors is

    influenced by how effective & well planned, the construction methods are, and

    whether the construction operatives work at optimal productivity levels or not.

    Achieving quantity and quality of results while controlling the inputs is therefore

    a key challenge for all contractors. This research therefore is important as the

    knowledge of factors affecting productivity will aid supervision staff to ensure

    optimal conditions on site; namely ensure favourable factors for achieving

    maximum productivity of operatives on their sites. This would help keeping costs

    within budget, keep employee morale high and help projects to be completed on

    time; help companies run their businesses profitably.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    4

    1.1.1 Gap in Knowledge

    Review of contemporary works on the subject of productivity revealed that the

    studies undertaken generally involved one construction trade (for example

    masonry by some and bricklaying by others) and or one variable at a time (for

    example some studied the effects of only motivation on productivity), some

    studied the variables in isolation without interaction between variables and most

    were generally qualitative rather than quantitative suggesting trends or

    relationship but stood short of quantifying this relation.

    The works of contemporary writers is briefly mentioned in this section leading to

    the identification of the gap in knowledge.

    Herbsman and Ellis (1990) studied the effects of project conditions termed by

    them as Construction Influence Factors on the variation of productivity rates for

    construction items and described the development of a statistical model that

    illustrated quantitative relationships between influence factors and the

    productivity rates. However the study was conducted on past records from site

    and not freshly collected data. They concentrated on the construction influence

    factors classified into technological and administrative factors. These were

    project based conditions. Effects of the company wide environment were not

    considered.

    Further, the influence factors were quantified using three methods: direct, indirect

    using alternate indicators (such as labour turnover for measuring motivation) and

    quantification using non parametric ranking. The non parametric ranking

    involved ranking the elements to a scale of 1 to 10 based on an individuals

    experience, knowledge and judgment. Also the construction industry influence

    factors were based on interviews with various participants in the construction

    industry, determined by a group of experts and not through questionnaires.

    Finally, a stepwise effect of the influence factors was adopted where each of the

    factors was introduced in the model one at a time and the resultant R2 the

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    5

    coefficient of determination - was reviewed for model adequacy. The SAS

    (Statistical Analysis Software) software was used for model formulation. The

    productivity model they presented contained a regression equation that utilized

    the identified influence factors and gave the productivity of the particular

    activity. The study however did not contain validation of the models, and it was

    only suggested that the models could predict the productivity for that activity in

    future projects.

    Sanders and Thomas (1991) in their study of the factors affecting masonry labour

    productivity identified inadequacies in previous similar studies to accurately

    identify the factors. Their methodology involved the data collected from 11

    masonry projects between 1986-1988 in central Pennsylvania. Data collection

    was standardized in a procedures manual for consistency. Data sets were

    converted to equivalent units to take care of different sizes of bricks being laid

    and regression analysis was performed to develop models to relate the

    productivity to the physical characteristics of the masonry units. Potential factors

    identified and used in the models were based on experience, observations and

    data reconciliation procedure. The project related factors identified were work

    type, building elements, construction methods, and design requirements. Further

    analysis of variance was done on each of these factors. The conclusions included

    that 30% improvement is expected if the design is repetitive and 40%

    improvement could be realized if design is improved. Expected percentage

    improvement resulting from each parameter in isolation was suggested; the

    combination effect of all the parameters was not studied.

    Ogunlana and Chang (1998) studied worker motivation on selected construction

    sites in Bangkok, Thailand. Here the data was collected from seven accessible

    high rise building construction sites out of the twenty five selected. A two stage

    questionnaire was used - the first being a list of needs, while the second one

    contained a list of motivators and de-motivators. Further, the needs, motivators

    and de-motivators were ranked by workmen as against those by supervisors and

    a further cross analysis of the combined needs, motivators and de-motivators was

    carried out. The final results showed that the needs of the Thai workers higher

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    6

    pay, better accommodation, good welfare and safety compared lower to the felt

    needs of fringe benefits, good relations and safe sites. It was also proved that the

    needs, motivators and de-motivators of the Thai workers and those of Nigeria

    were similar. The study suggested that motivation methods need to be adjusted

    to the situational effects and the personal traits of the national people. The study

    was limited to few factors.

    Proverbs et al (1998) did a comparative evaluation of reinforcement fixing

    productivity rates amongst the French, German and UK construction contractors.

    The productivity rates given by the respective planning engineers formed the

    basis of the research. The planning engineers from each of the 31 contractors

    from UK, 13 contractors from France, and 10 contractors from Germany were

    given a set of project drawings and a questionnaire. Productivity rates of the

    erection of formwork, reinforcement fixing and concrete placing were asked for

    but the paper focused only on one operation - reinforcement fixing for beams,

    columns, floor slabs and for the entire project. The study concluded that

    significant differences existed between the productivity rates used by French,

    German and the UK contractors using coefficients of variation and ranks. No

    models were developed. The study presented a comparison of the rate of

    productivity for specific construction trades but did not suggest how to change or

    improve productivity.

    Mohamed and Srinavin (2002) in their study of thermal environment effects on

    the construction workers productivity argued that further to air temperature,

    relative humidity and wind velocity, additional thermal environment parameters

    should be accounted for to enhance the predictive power of forecasting the

    construction workers productivity. These factors included the mean radiant

    temperature, clothing insulation, and metabolic rate. Amongst the various

    techniques used to determine the effect of climatic conditions on workers

    productivity, the multiple regression technique was commonly used. The study

    resulted into a regression equation developed from data gathered from literature;

    the equations were further validated using correlation analysis. The study was

    devoted only to thermal effects on productivity.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    7

    Chan P (2002) in his study of the factors affecting labour productivity in the UK

    construction industry discussed the various aspects affecting productivity through

    a series of focus group interviews engaged in the Personal Construct Theory

    (PCT). Personal Construct Theory offers the prospect of unlocking the vital

    experience of people and breaks down the barrier between researchers and

    research subjects. This study comprised a series of semi structured hour long

    focus group interviews with construction operatives. The focus group interviews

    had three main stages - construct explication, construct review and construct

    validation. By engaging in the personal constructs of site management staff, four

    key areas were identified as aspects leading to productivity improvements. These

    are planning, teamwork, welfare, and job security. The study did bring in human

    factors affecting productivity levels but did not magnify their contribution and the

    measures to improve them were not discussed.

    Kazaz and Ulubeyli (2006) studied the organizational factors influencing

    construction manpower productivity in Turkish Construction Industry. Data was

    collected using a survey questionnaire with a combination of face to face

    interviews, email responses, and telephone interviews. Statistical methods were

    used to analyze the data using the Relative Importance Index. A rating scale of 1

    to 5 was adopted with 1 being the lowest and 5 being the highest level of effect.

    Using significance intervals, the survey results showed the site management,

    material management, and systematic flow of work were ranked by participants

    as the three most effective organizational factors affecting the productivity. The

    study ends with a detailed discussion on all the factors affecting the productivity.

    No model to measure the effect of these factors on productivity was introduced.

    Aiyetan and Olotouah (2006) studied the impact of motivation on workers

    productivity in the Nigerian Construction Industry. Questionnaires were used in

    the research which addressed the relationship between motivation and

    performance. No other factors were considered. The study was limited to the

    perception survey of the management staff and the operatives. The overall

    recommendations included adjusted salary structure, increased welfare, increase

    in salary; promotion, overtime and holiday with pay financial incentives that

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    8

    increased motivation and therefore the productivity. There was no model

    formulated and only subjective recommendations were given.

    Alinaitwe et al (2007) studied the factors affecting the productivity of building

    craftsmen in Uganda. The survey consisted of a questionnaire to Project

    Managers from selected buildings sites, where they were asked to rank the 36

    factors affecting productivity taking into account effects of time, cost and quality.

    The research resulted in identifying the five highest ranked factors as

    incompetent supervisors, lack of skills, rework, lack of tools / equipment and

    poor construction methods. No model was proposed to measure the effect of

    variability in these factors on the productivity rate. Only a subjective conclusion

    was arrived at suggesting that these factors have an important effect on

    productivity.

    Following a review of the above referred works, a need was therefore felt for a

    study involving multiplicity of factors affecting construction trades and

    establishing a regression model for accurately predicting changes in productivity

    with the aim of increasing the productivity so that time and cost factors are better

    controlled in the project; in other words resources are optimally utilized in the

    project.

    After identifying the broad categories of factors affecting productivity as

    Environmental, Organizational, Group Dynamics and Individual Factors, this

    research for the first time closed in on six factors affecting productivity over

    seven construction trades of excavation, formwork, reinforcement, concreting,

    blockwork, plaster and tiling and attempts to quantify the predicted change in

    productivity vis--vis the change in the factors themselves. These six factors

    selected for modeling including - Timings, Supervision, Group Dynamics,

    Materials, Procedures and Climate; these being selected based on three surveys

    leading to the identification of the most significant factors affecting construction

    productivity in the UAE.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    9

    Similar works involving statistical models giving predicted construction

    productivity for changes in factors such as Work Timings, Level of Supervision,

    Group Dynamics, Control by Procedures, Availability of Materials, Climatic

    Conditions, were not come across during the literature review. In this context,

    this research is thought to be a first of its kind at least in the UAE

    1.2 RESEARCH AIM

    The aim of this research is to evaluate factors that would affect productivity of

    construction trades in order to optimize output.

    1.2.1 RESEARCH OBJECTIVES

    The objectives to fulfill the research aim are:

    a) Identify the factors affecting productivity of the construction industry in

    the United Arab Emirates.

    b) Establish the significance of a selection of construction trades upon the

    productivity of the construction industry in UAE

    c) Develop a methodology for measuring the factors that affect productivity

    of the construction industry in the UAE.

    d) Develop a model for predicting changes in productivity.

    e) Measure the changes in productivity.

    1.3 SCOPE OF RESEARCH

    This research has been conducted at construction sites in the UAE as sources of

    field data, though the research aim and the findings thereof are of a general

    nature.

    The construction industry is characterized by multiple site conditions having

    significant varying effects on the productivity rates of standard construction

    trades. (Herbsman and Ellis, 1990).

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    10

    The literature review provided the basis for classifying the four main categories

    of factors affecting productivity; these being - the Environmental Factors, the

    Organizational Factors, the Group Factors and the Individual Factors.

    Construction trades are subject to a variety of factors that would determine the

    productivity of that trade on the day; to study all of these at the same time, would

    be complex; therefore the research undertakes three surveys to determine the

    significant factors which are more manageable and amenable to study. The most

    significant factors taken for further study include the Work Timings,

    Supervision, Group Dynamics, Procedures, Material, and Climate. The reduced

    number of factors means the construction industry can concentrate on controlling

    them in order to improve the productivity.

    These factors are very much relevant to the UAE economy as construction is the

    predominant activity driving the economy after oil. The construction operatives

    come from diverse background, and the caliber of supervision differs and is based

    on nationality, education and experience. Procedures play an important role in

    controlling the safe execution of the project and therefore affect productivity as

    compliance with procedures would mean safety protection systems in place and

    waiting for clearance or approval. The climate factor is obviously relevant, the

    UAE having a hot humid climate; and the fact that the construction trades of

    excavation, formwork, steel and concreting are out in the open.

    1.3.1 Definition of Productivity

    Different versions of the definition of productivity exist; some are listed in this

    section with discussion leading us to the definition accepted for this research.

    The Organization for Economic Cooperation and Development (OECD, 2001)

    defines productivity as the ratio of a volume measure of output to a volume

    measure of input used.

    As per the OECD, the objectives of productivity measurement include:

    a) Technology - to trace technological changes improvements

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    11

    b) Efficiency to check if maximum output that is physically achievable with

    current technology , give a fixed amount of inputs

    c) Real cost savings a quest to identify real cost savings in production

    d) Benchmarking production processes comparison of productivity measures

    in specific production processes can help to identify inefficiencies.

    e) Living Standards a simple example is per capita income of a country.

    According to Sibson (1994), productivity means doing high quality work with

    great efficiency. In essence it is some output per man hour. Output must be

    saleable and usable and of good quality. Other simple definitions include the

    amount of output per unit of input (labour, equipment, and capital).

    There are many different ways of measuring productivity. For example, in a

    factory, productivity might be measured based on the number of hours it takes to

    produce a good, while in the service sector, productivity might be measured

    based on the revenue generated by an employee divided by his/her salary.

    Productivity measures could be single factor or multi-factor; the choice between

    them depends on the purpose of the productivity measurement and in most

    instances, on the availability of data. Productivity traditionally, refers to the

    quantifiable ratio between outputs and inputs in physical terms. In the

    construction industry, the quantitative measure widely used in the UAE

    Construction Industry relates to the amount of construction activity for the man

    hours that have been put in.

    For the purpose of this research, productivity is defined as the ratio of output of

    required quality to the inputs for a specific production situation. In the

    construction industry; it is generally accepted as work output per man-hours

    worked. This unit is generally used by most contractors in the UAE. It reflects

    the measure of manual production which is being studied and also gives an

    established factor for comparison over construction trades over time and over

    project sites.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    12

    For example, excavation is measured in cubic meters of soil excavated per man

    hour and plastering is measured in square meters of plaster per man hour.

    Excavation and Plastering are manual operations involving a high degree of

    manual labour and zero or limited mechanized assistance. This is due to the fact

    that cheap labour is available in the country and in some of the projects; hand

    excavation is a must because of the presence of live utilities underground.

    The above definition takes into account quality and efficiency; however,

    effectiveness is not covered by this definition; namely the cost benefit analysis of

    the resources employed versus the output achieved is considered outside the

    scope of this research.

    Every management initiative strives to ensure optimal utilization of resources;

    one way to do this is to increase the productivity that is to seek ways and means

    to increase output.

    Government, politicians, academics and economists all stress the importance of

    productivity because it is an indicator of the general economic health of a

    country. On the other hand, corporate management is concerned with

    productivity because productivity is regarded as a main indicator of efficiency

    when comparisons are made with competitors in local and global markets.

    1.4 BRIEF OUTLINE OF RESEARCH

    The following section briefly explains how the research data was generated,

    analyzed and conclusions drawn from this data; the rationale behind the methods

    chosen, the anticipated problems and how these were tackled during the research.

    According to Fellows and Liu (2003), the critical consideration for selecting a

    most appropriate research method is the logic that links the data collection and

    analysis to yield results and thus the conclusions. Research designs therefore

    must take into account the research questions; determine what data are needed

    and how the data will be organized to maximize the chance of the research

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    13

    realizing its objectives. They highlighted Survey, Experiment, Archival Analysis,

    History and Case Study as the five research styles.

    Research studies in the construction industry are generally conducted through

    experiments, surveys or case studies. Experiments for productivity factors in

    construction would mean long waiting time for results. Surveys through

    questionnaires afforded relative ease of obtaining data for analysis. Random

    sampling allows a small number of people to give opinions and characteristics

    that can be representative of the general population. Alinaitwe et al (2007).

    In section 1.1.1, pg. 3, contemporary works on productivity were outlined briefly

    leading to the identification of gap in knowledge and establishing the need for

    research. The research methods used by the contemporary authors include non

    parametric ranking using face to face interviews, email responses, telephonic

    interviews, focus group interviews, expert opinions, use of questionnaires,

    followed by statistical analysis including significance testing or subjecting to

    multiple regression analysis. Specialist statistical softwares such as SAS, SPSS

    were utilized. Obviously, all these were preceded by a detailed literature review

    of the relevant topics on productivity using classical management theories as well

    as the contemporary writers. This research also undertakes a similar methodology

    which is a combination of the literature review, surveys followed by significance

    testing and finally case study for data collection for both model formulation and

    model validation. The MINITAB 15 software was used for regression analysis

    and modelling. The following subsections give an outline of the methodology

    undertaken for this research.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    14

    Fig. 1.1: Overview of the Research

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    15

    1.4.1 Review of Existing Literature & Publications

    In order to identify the factors affecting productivity in the UAE construction

    industry, it was important to first do a literature review of credible publications

    of works already done in the field and acceptable to the academics. Accordingly

    key authors and notable journals in the field of management and especially

    construction engineering and management were reviewed and the ideology was

    captured in three matrices. The reason for selecting the key authors and journals

    include amongst others, credibility and wide acceptance in the field of

    construction research.

    Key words such as productivity, construction industry, productivity rates, UAE,

    factors affecting productivity were used in search of the documents. The

    literature review was confined to factors that would affect productivity in the

    construction industry only as this was the subject of the research. Further

    productivity in a purely manufacturing set up is different than in productivity in

    construction industry. Manufacturing generally includes mass or continuous

    production, and factories are stationary unlike construction projects with different

    locations and constraints. Productivity rate for other sectors such as financial,

    educational were not considered as part of this research. Accordingly, the

    boundaries of this study are those factors that influence productivity rates in

    construction industry.

    The contemporary works on productivity were reviewed and three matrices were

    established 1) indicating the factors affecting construction productivity, 2)

    indicating the motivational factors affecting construction industry and 3)

    indicating the factors affecting productivity across countries.

    The classical theories, together with the information from these matrices and

    experience of the researcher in the UAE construction industry led to the broad

    categorization of factors affecting productivity of the construction industry in the

    UAE.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    16

    1.4.2 Data Collection: Survey for Significant Factors

    A number of research methods were considered ranging from interviews, survey

    questionnaires, case studies, opinion polls and so on. Survey questionnaires

    though difficult to design, can have wider coverage, are relatively cheap, avoid

    embarrassment for the respondent and carries no interview bias. Interviews are

    time consuming, costly, limited in coverage but can get in-depth probing during

    interviews (Kothari, 2004).

    For this research, the questionnaire and case study were selected as this offered

    the possibility of having wider prospective respondents, elimination of any

    personal bias that might develop during the interview and giving equal chances

    for answering the questions under similar conditions.

    The case study on the other hand was mandatory to provide the huge quantity of

    data that was required for the study especially the model formulation and

    validation later. Also the case study company had 30 years of productivity record

    that could be used for comparison. The company also had undertaken projects

    that were running concurrently, which could be used for data collection.

    Accordingly three research surveys were undertaken. This was followed up by a

    case study on site field data collection for measuring changes in productivity

    leading to the formulation of a model and once again a case study validation of

    data.

    Survey 1 for Significance- The list of factors derived from literature review

    were transformed into a survey questionnaire that was circulated to the key

    industry players engineers, foremen and the operatives themselves. This served

    as the first set of primary data which was analyzed using the Severity Index

    (= Importance Index x Frequency Index). A list of significant factors affecting

    productivity in the UAE construction industry was then established.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    17

    The results of this survey were reported at the PROBE (Post Graduate

    Researchers in the Built & Natural Environment) conference, Glasgow,

    Caledonian University, Scotland, November 20-22, 2007.

    The survey questionnaire had a total of 61 questions and was sent to 500

    participants out of which 238 responded. The questions were formulated from the

    list of significant factors established by literature review. The respondents had to

    answer the questions to a LIKERT scale (Kothari, 2004), as further explained in

    Chapter 3.

    The results were then ranked using the severity index and factors within each of

    the four main categories of Environmental, Organizational, Group and Personal

    Factors were presented.

    Finally the highest ranked 14 factors were presented sorted in descending order.

    Those were ultimately subjected to two more perception surveys Survey 2 and

    Survey 3; results of which led to seven major factors of Timings, Competence of

    supervisors, Salaries, Materials, Systems and procedures, Group dynamics and

    Climatic conditions. The Salaries and Timings factor were merged into one factor

    of Timings making the total factors that will be studied as six factors.

    1.4.3 Data Collection: Surveys for Effect of Significant Factors

    Two more sets of primary data were generated by conducting a perception survey

    of the effect on productivity of the six factor groups; one using participants from

    within the case study contracting company (Survey 2) and second using

    participants external to the company (Survey 3). These were kept separate as the

    results were expected to be different and reviewed at a later stage if required.

    The perception survey was needed to establish the magnitude of the effect of each

    of the significant factors following survey 1 and to help establish the field

    variables for data collection. The effect was set at 25% as from practical

    experience in the construction field, changes to the productivity by design is

    seldom.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    18

    The survey results were presented in counts, percentages and weighted averages.

    A combined analysis was also presented, which gave a percentage of the

    respondents establishing the magnitude of the effect of the factors timings,

    supervisor competence, salaries, materials, systems and procedures, group

    dynamics, and climatic conditions for both the internal and the external survey.

    Survey 2 and 3 analysis helped establish the magnitude of the effect of the

    significant factors of productivity; which combined with the results of

    significance testing described in 1.4.4 below, led to the establishing actual field

    controllable factors affecting productivity.

    1.4.4 Data Collection: Statistical Tests of Significance Using Chi Square

    The results of the two perception surveys discussed above were then summarized

    into a Chi Square matrix and tests of significance was conducted for both cases

    separately. The factors were considered statistically significant in both cases.

    The Pearson Chi Square test can be used to check goodness of fit and tests for

    independence. Here the test was used to check for significance or independence.

    These tests whether paired observations on variables expressed in a contingency

    table are independent of each other; in this case the factors affecting productivity.

    1.4.5. Field Data Collection

    Three levels of variations were chosen for each of the seven factors described in

    1.4.2 and 1.4.3 above using the calculated weighted averages. The three levels

    have been chosen to afford a practical mechanism for variation and recording of

    productivity changes. For example,

    Work Timings (T) was varied at : Level 1 - Normal 8 hours work

    Level 2 - 8 hours + 4 hours overtime

    Level 3 - Contract Work, Fixed volumes of

    work done for agreed compensation

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    19

    Thus these three levels helped to establish a mechanism to vary conditions on site

    and record productivity changes. Table 1.1 summarizes the construction trades

    and the seven factor variables chosen for field data collection. These construction

    trades were chosen as they are mostly done manually and offer tremendous scope

    for improvement in productivity; besides being the significant activities at the

    start of the project other than the mechanical, electrical and plumbing services

    coming up later in the project.

    Activitiesunderstudy

    Factorsvariedduringdatacollection

    1 Excavation Timings

    Salaries

    Supervision

    GroupDynamics

    Procedures

    MaterialAvailability

    Climate

    2 Formwork

    3 Reinforcement

    4 Concreting

    5 Blockwork

    6 Plastering

    7 Tiling Table 1.1 Construction Trades and Productivity Factors for Field Data Collection

    The productivity was measured for the seven trades of Excavation (cubic metres /

    man-hour), Formwork (square metres / man-hour) Reinforcement (tonnes / man

    hour), Concreting (cubic metres / man-hour), Blockwork (square metres / man-

    hour), Plastering (square metres / man-hour) and Tiling Works (square metres /

    man-hour).

    As the trades have different units of measurement, the output variable to be

    measured and used in further statistical analysis was the difference in actual

    productivity measured to the average productivity specific to the site, expressed

    as a percentage productivity change. Expressing this as a percentage, achieved

    getting a unit free figure and as such removed the problem of different units of

    measurement.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    20

    The factors taken for data collection from the survey results were reduced to six

    because it was not logical to change the salary during data collection, as this

    would first make the operatives aware of the study, they could then be biased,

    while other operatives not treated equally might not perform their best. Hence it

    was merged with the Timing factor.

    1.4.6 Homogenization of Data

    Data as received from sites was reviewed and outliers were removed to ensure the

    sample readings received represented a normal population. Further the site data

    could include possible errors of recording, possible manipulation, computation

    errors productivity outputs may have been subjected to unaccounted for factors

    such as isolated activities of stoppage, waiting for inspection, unusually confined

    spaces to work, varying complexities of the construction trade itself. The

    technical constraints together with the size and complexity of the structure being

    constructed made it difficult to fix a productivity level and therefore varying

    levels of productivity were seen in the data.

    A total of 1090 data sets were collected from sites. As expected; a wide variation

    of measured productivity was observed. Some of the results seemed abnormal

    and out of bounds, which in statistics are termed as outliers (those data that were

    below the 25th percentile and above the 75% percentile). In this research, a band

    of 40% was applied to retain data for further analysis. So the percentage

    productivity change as measured (PPCM) values were reviewed and any values

    out of 40% of the Site Average were discarded.

    A band of 40% was considered an appropriate band to retain the data to first

    ensure significant number of data sets remain, whilst on the other hand, to ensure

    practical variation expected on site ascribed to the factors described in the last

    paragraph. The band of 40% was selected based on the variations seen in actual

    productivity on site and the known presence of several factors (not subject of this

    study) other than the six ones under study.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    21

    This consideration is also in line with removing of outliers using the first and

    third percentiles, ensuring at least 50% of the data sets more representative of the

    population are used. In this research, total data sets of 1090 was collected as

    against 812 (74 %) data sets used after the discarding those out of the 40%

    band.

    1.4.7 Regression Analysis using MINITAB 15 software

    The MINITAB 15 software was utilized in this research as the researcher had

    previous experience in using it and moreover the MINITAB 15 and the other

    softwares available the Statistical Package for Social Sciences (SPSS) software

    (now rebranded as Predictive Analytics Software (PASW), March 2009) offer

    similar outputs. MINITAB 15 was found simpler to use. Distinctive beneficial

    features of MINITAB include comprehensive and powerful statistical methods,

    effective and editable graphs, and user-friendly interface. MINITAB has been

    used in several textbooks spanning a broad range of categories including

    archaeology, behavioural / social sciences, biological sciences, business, earth

    sciences, engineering, environmental science, general statistics, health science,

    mathematics, quality control, and six sigma topics. (Reference

    www.minitab.com).

    Data sets homogenized as above were then fed into the MINITAB 15 software

    and regression analysis was performed. The output variable was the percentage

    productivity change as measured (PPCM), while the input variables were the

    group factors of 1) Timings, 2) Supervision, 3) Group, 4) Procedures, 5)

    Availability of material and 6) Climate.

    The first attempt was to find an overall model for productivity change. However

    the coefficient of determination (R2) returned was very low for accepting the

    model. The low value of R2 was understandable as there are several factors in

    combination affecting the productivity; and one model may not fit all the trades.

    This problem was overcome by opting for individual models for productivity of

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    22

    six trades considered during data collection, namely Excavation, Formwork,

    Reinforcement, Concreting, Blockwork, Plastering and Tiling.

    The models formulated with a preliminary validation of models were reported at

    the 25th Annual ARCOM Conference, September 7-9, 2009, Nottingham.

    1.4.8 Validation of the Models

    The validation of the models was done using eleven data sets from sites for the

    different activities. Chapter 5 deals with validation. The process of validation

    includes reviewing the data, computing the percentage productivity change as

    measured (PPCM), using the appropriate site averages, using the model for

    computing the percent productivity change as predicted (PPCP) and finally

    computing the error which is the difference between PPCP and PPCM.

    The data retained for final validation against the acceptance band of 15% was

    determined from removing first the outliers within the 2 sigma limits for the

    errors. Sigma is the standard deviation of the readings and from the statistical

    normal curve / distribution study, it is expected that 95% of the values lie within

    2 sigma bands. For the convenience of the reader, 68% lie within the 1sigma

    band, while 99.7 % of the readings are expected to lie within the 3 sigma bands.

    (Mendenhall et al, 2001, pg. 33)

    The reasons for the 15% band are that the regression models chosen were a

    straight line linear regression as against possible curvature or logarithmic

    relationships. Interactions between factors were not considered. After the

    removal of outliers, the regression line fitted was the optimal chosen to give as

    high a value of R2 of over 70%. It was therefore expected that the predicted

    increase or decrease in productivity will also follow a similar trend that is the

    data points are expected to lie within an upper and lower band limits of error.

    Other considerations include the broad range of complex relationships between

    the model and the data, the numerous technical constraints on site with regards to

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    23

    the expected productivity in each of the activities, the subjectivity of the factors

    themselves & therefore the allocation of factor levels chosen for research.

    The threshold of 15% also makes sense as actual data from time sheets, cost

    control charts and productivity figures from the case study company sites over

    the last 34 years indicate that the maximum increase or decrease in productivity

    would be in the broader range of 40%.

    Further taking into consideration the possible inaccuracies of reporting data itself

    from the sites, and considering the wide variation in productivity measurement on

    sites, the presence of additional technical factors not covered in the models and

    review of the wide variation that was possible in productivity values for the

    construction trades in actual practice; the acceptance criteria for accepting the

    model to be accurate for practical use on site was set at 15%.

    1.4.9 Model Application

    The models can be used by construction personnel Project Managers, Engineers

    and Supervisors to understand the dynamics involved in productivity of the

    construction trades and investigate what best they can do to improve the

    conditions that affect productivity on site.

    The models provide reasonable quantification of the predicted productivity, when

    the underlying factors are varied. The models are to be used judiciously,

    complimented with a thorough understanding of the ground realities on the

    construction site, the demography, age, training and skills of the people

    themselves, the mental situation of the workers, their motivation levels; the

    nature, detail and complexity of the work activities themselves.

    The research and the models underlined therein therefore require the supervisors

    and the site construction management in general understand that their

    responsibility lies in providing favourable conditions of timings, supervision,

    group dynamic, materials, procedures and of course amiable weather bringing out

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    24

    the best in people; thus effectively increasing the output and therefore the

    efficiency and productivity of the works. This will ensure construction operatives

    perform at higher levels of motivation; work produced will be of acceptable

    quality and at a good productivity rate; helping the activities to complete faster

    and therefore the project.

    Limitations if any arise because of simplifying assumptions used in the research,

    the subjectivity of factor levels, the accuracy of the data itself, the existence of a

    combination of several factors besides the significant factors; the possible errors

    of recording and analyzing data, and the presence of human motivation. Thus the

    models need to be used judiciously with caution, understanding the contribution

    of each of the factor variables; but at the same time understanding the ground

    realities of site execution.

    1.5 CHAPTER SUMMARIES

    The outline of the chapters 1-6 is included here to give a summary indication of

    the contents of each chapter.

    Chapter 1 Research Introduction

    Chapter 1 is the introductory chapter to this research work. This chapter

    introduces the research title, aim, objectives, and definitions of productivity

    while identifying the gap in knowledge and establishing the need for research,

    its importance in the construction industry and especially in the United Arab

    Emirates (UAE). This is followed by a brief research methodology applied to

    determine the factors affecting productivity; identify the most significant

    factors using three surveys and then use actual productivity data to establish

    and validate a regression model which can predict productivity changes in the

    construction industry. After a brief discussion on applicability of the models,

    the chapter concludes with summaries of each chapter to give the reader a

    general outline of the research.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    25

    Chapter 2 Literature Review

    Chapter 2 establishes the ground for this research based on the findings of the

    literature review of classical management including theories on motivation,

    together with published literature on subjects related to productivity.

    Motivation theories such as the content theories of Maslow, McGregor,

    McClelland and Herzberg are discussed followed by the process theories

    namely Adams Equity Theory, Victor Vrooms Expectancy Theory and the

    Porter Lawler Model on Motivation vis--vis their application in the

    construction industry.

    This chapter also gives background information and typical characteristics of

    the UAE construction industry, the UAE labour market and survey results of

    workplace employment relations in the UAE, the demography of the

    workforce, the diversity of cultural backgrounds, absence of labour unions,

    and the general environmental conditions of work and statutory laws prevalent

    in the UAE. Further a discussion indicating the similarities and uniqueness of

    conditions elsewhere in the world; and the need for improvement in

    productivity. This discussion helps the reader to understand the context of the

    project construction sites, at which the productivity data will be measured to

    develop the models.

    This is followed by a review of existing publications on productivity by

    contemporary authors; this discussion culminates into matrices of factors

    affecting productivity and motivating factors affecting productivity and finally

    a matrix of factors affecting productivity over several countries.

    These matrices form the basis for a comprehensive listing of the factors

    affecting productivity. The factors affecting productivity are grouped into four

    major categories of Environmental, Organizational, Group Dynamics and

    Personal Factors.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    26

    Chapter 3 Research Methodology

    Chapter 3 details the research methods applied together with a justification of

    their utilization. It outlines the research process starting with the aim, the

    literature review, the three surveys conducted, and the field data collected for

    establishing the models, the MINITAB 15 software used for statistical

    modeling and finally the validation process.

    Further it also discusses the technical aspects of the construction trades

    involved in the field data collection, for which, the productivity models or the

    regression equations will be established. The construction trades of

    Excavation, Formwork, Reinforcement, Concreting, Blockwork, Plastering

    and Tiling Works have been discussed, together with other technical factors

    affecting productivity of these trades. These technical factors are related to the

    complexity of work, location of the site, soil strata, materials used, climatic

    conditions, project specific requirements, and client involvement in the

    project.

    And finally, this is followed up by a brief introduction of the case study on

    one contracting company, whose sites have been used for field data collection

    for establishing the models and their validation.

    Chapter 4 Data Collection, Data Analysis and Development of

    Productivity Evaluation Model

    Chapter 4 deals with the analysis of field data on productivity collected from

    case study projects, removing outliers and subjecting the homogenized data to

    regression analysis using the MINITAB 15 software. Regression models have

    been established with an acceptable threshold of R2, the coefficient of

    determination at 70% and above. Straight Line Regression has been

    considered for practical application of models on the site.

    The six factors affecting productivity which were used for modelling are the

    Work Timings (T), Level of Supervision (S), Group Dynamics (G),

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    27

    Availability of Materials (M), Control by Procedures (P), and the Climatic

    Condition (C). The chapter summarizes the models established for each of the

    seven trades of excavation, formwork, reinforcement, concreting, blockwork,

    plastering and tiling for which the above mentioned factors were purposely

    varied. Validation of the models is discussed in Chapter 5.

    Chapter 5 Model Validation and Evaluation of Variability of

    Productivity

    This chapter deals with the testing and validation of the trade wise

    productivity models established in Chapter 4 using the MINITAB 15

    software. The validation process helps us to determine if the models can be

    practically used to predict productivity changes on construction sites, when

    underlying factors affecting productivity are changed. Eleven data sets were

    subjected to validation by finding out the error in estimating the predicted

    productivity change as against that measured on site. Outliers were removed

    using the two sigma band of control limits on the individual error readings.

    The balance data readings were then checked against the 15% acceptance

    band. Models were accepted if the balance data readings were within this

    band. Validation has been performed on eleven data sets collected from

    ongoing construction sites of the case study contracting company.

    For 2 sigma limits, it is seen that errors obtained between the predicted and

    the actual productivity increase / decrease are within a band of 17.14% to

    38.2% further justifying the initial homogenization range of 40%. Outliers

    were removed using the upper control limits and lower control limits for the 2

    sigma band. Out of the total 11 data sets (1963 Nos); eight data sets passed

    validation as per set procedure. One data set for reinforcement at OAG site

    was accepted on revalidation as only one out of the 42 was out of the

    acceptable band of 15%. The other two sets which were accepted on

    revalidation included data set for concreting and blockwork from the BCC

    site. The revalidation used truncated data band within 20 % of the site

    average. Overall the model validations were accepted indicating that

    productivity models can be used to predict productivity changes within 15%

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    28

    accuracy. The chapter further discusses the evaluation of the factors affecting

    productivity. This is done by considering the coefficient terms of each of the

    factors in the regression equation.

    Chapter 6 Conclusion

    Chapter 6 concludes the research by verifying whether research aim and

    objectives were achieved, the significant problems faced and how these were

    tackled and lists the lessons learnt. The limitations of the research itself are

    discussed and probable areas for future research for improving the accuracy of

    the models are recommended. It is also recommended that site personnel shall

    understand the contribution of the factors and provide favourable conditions

    which lead to enhancement of the productivity of the people, the construction

    trades and therefore of the project.

    1.6 CONCLUSION

    This first chapter introduced the thesis title, established the aim, objectives, and

    definitions of productivity while reiterating the need for research against the

    background of productivity of construction trades and its importance in the

    construction industry. The research is aimed at evaluating factors affecting

    productivity of construction trades in order to optimize output. One of the

    objectives of the research is to develop a model that can be used in the

    construction industry to evaluate the percentage change in productivity once the

    underlying parameters (factors) are varied. Hence the model does not measure or

    predict productivity directly; it rather predicts the percentage change of the

    productivity of the studied trades in relation to variation in the variables

    involved. The research methodology was depicted graphically with cross

    reference to chapter numbers. The research undertakes three surveys one to

    establish the significance factors affecting productivity and the other two to

    establish the magnitude of the effect of these factors on productivity. The field

    data was collected using three levels of variation, and regression models for

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    29

    productivity of construction trades were developed. The chapter concludes with

    summaries of each chapter to give the reader a general outline of the thesis.

    ***

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    30

    CHAPTER 2 LITERATURE REVIEW

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    31

    CHAPTER 2 LITERATURE REVIEW

    2.0 CHAPTER INTRODUCTION

    This chapter reviews classical and contemporary theories related to management

    together with published literature on productivity. The content theories of

    Maslow, McGregor, McClelland and Herzberg are discussed followed by the

    process theories namely Adams Equity Theory, Victor Vrooms Expectancy

    Theory and the Porter Lawler Model on Motivation vis--vis their application in

    the construction industry. Those have provided the study with the three matrices

    containing most relevant factors that are believed to affect productivity.

    The previous studies on productivity studied one trade and / or one variable at a

    time, or studied the variables in isolation without interaction between variables.

    Herbsman and Ellis (1990) described the development of a statistical model that

    illustrates the quantitative relationships between the construction productivity

    influence factors (CPIF) and the productivity rates. Most of the other studies were

    qualitative rather than being quantitative.

    The research by contemporary authors has been reviewed which culminates into

    matrices of 1) Factors affecting productivity, 2) Motivating factors affecting

    productivity and finally 3) Matrix of factors affecting productivity over several

    countries.

    These matrices form the basis for a comprehensive listing of the factors affecting

    productivity. The factors affecting productivity are grouped into four major

    categories of Environmental, Organizational, Group Dynamics and Personal

    Factors.

    Organizations and Individuals

    Any organization is composed of individuals (people) who are organized in some

    way or form in order to achieve certain objectives. In a construction company, the

    general organization consists of people in the head office and people at the

    construction site. The objective of a construction company are to first secure a

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    32

    project and then execute it to clients satisfaction, giving value to the client and at

    the same time, making a profit for the company.

    People on site include staff such as the Project Managers, Site Engineers,

    Foremen and Workmen. This research focuses on people on site - the lower tier

    workmen that group of people including skilled, semi-skilled tradesmen and

    labourers.

    Given a construction site, these workmen are either grouped trade wise such as

    carpentry group, masonry group, block or brick layer group etc. or they are

    grouped into multi-skill / multi-trade groups such as a maintenance group, which

    would include a mix of all relevant multi-discipline, multi-trades workmen.

    Most of the construction operatives come from a varied background. They

    normally have an agreed wage rate; but their performance on site, regardless of

    the individuals work or cultural background, is through the process of

    management, whereby the efforts of workmen are coordinated, directed and

    guided towards the project objectives and hence the overall organization goals.

    Mullins (2007) says effective management is the cornerstone of organizational

    effectiveness. He further says that organizations aim can be achieved only

    through the coordinated efforts of human resources.

    The interrelated influences affecting the behaviour of people can be grouped into

    those related to -

    The environment technical and scientific, economic, social and

    cultural, government

    The organization objectives and policy, technology and methods of

    work, formal structure, styles of leadership

    The group structure and functions, role, relationships, group

    influences and pressure

    The individual personality, skills, values and attributes needs and

    expectations.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    33

    Mullins further states that there are a series of mutual expectations of rights and

    privileges, duties and obligations, which although, not formally documented, but

    have an important influence on peoples behaviour. He calls it the psychological

    contract.

    The individual and organizational expectations forming the psychological

    contract listed are significant as most of them affect the performance of the

    individual; they are relevant to all industries, especially the labour intensive

    construction industry. That is the reason - some of these are later grouped into the

    factors affecting productivity.

    The Individuals Expectations of the Organization are:

    Provide safe and hygienic work conditions

    Make every reasonable effort to provide job security

    Attempt to provide challenging and satisfying jobs and reduce

    alienating aspects of work

    Adopt equitable human resource management policies and procedures

    Respect role of trade union officials and staff representatives

    Consult fully with staff and allow genuine participation in decisions

    which affect them.

    Implement best practice in equal opportunity policies and procedures

    Reward staff fairly according to their contribution and performance

    Provide reasonable opportunities for personal development and career

    progression

    Treat members of staff with respect

    Demonstrate an understanding and considerate attitude towards

    personal problems of staff

    On the other hand, the Organizational Expectations of the Individual

    Work to the best of abilities

    Uphold the ideology of the organization and the corporate image

    Work diligently in pursuit of organizational objectives

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    34

    Adhere to the rules, policies and procedures of the organization,

    especially the safety regulations at site

    Respect authority and other colleagues

    Not take advantage of goodwill by management

    Be responsive to leadership influence

    Demonstrate loyalty, not betray trust

    Maintain harmonious relationships with work colleagues

    Not abuse organizational facilities and equipment

    Observe reasonable and acceptable standards of dress and appearance

    Show respect and consolidation to customers and suppliers

    Although it is unlikely that all the expectations of the individual and the

    organizations will be fully met at all times, there is a continual process of

    balancing, explicit and implicit bargaining, until both parties settle out at a

    perceived fair treatment. Several authors have correctly hinted at the dynamic

    nature of the psychological contract, the underlying factors are no guarantee of

    lifetime employment, promotion from within, part time contracts, subcontract or

    outsourcing, retrenchment in light of economic crisis and so on.

    The comprehensive list of factors affecting the productivity on site was arrived at

    by:-

    Review of the classical management theories

    Review of the published literature related to productivity on construction

    sites

    Establishing a Literature Review Matrix listing the factors affecting

    motivation and consequently - productivity

    Experience of the researcher. The researcher has had 38 years of

    construction experience and has moved through the rank over a

    multiplicity of projects, especially in the United Arab Emirates.

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    35

    2.1 MANAGEMENT THEORIES

    The developments in management theories and organizational behaviour can be

    categorized through four approaches:

    The classical approach including scientific management and bureaucracy

    The human relations approach

    The systems approach

    The contingency approach

    2.1.1 The Classical Approach

    The classical approach placed emphasis on planning of work, the technical

    requirements of the organization, principle of management and the assumption of

    rational and logical behaviour. Focus was on clear purpose and an effective

    structure, division of work, clear definition of duties and responsibilities and

    maintaining specialization and coordination; emphasis was on hierarchy of

    management and formal organizational relationships.

    The scientific management emphasized increasing productivity from

    individual workers through the technical structuring of the work

    organization and the provision of monetary incentives as the motivator for

    higher levels of output. The scientific approach is based on the twin goals

    of productivity and efficiency as advocated by Fredrick Taylor. His

    principles of scientific management comprised of three central elements -

    a systematic collection of knowledge about work processes by managers;

    the removal of worker discretion and control over their activities and the

    creation of standard procedures and times for performing certain tasks. He

    saw his methods as benefiting both worker and manager, since the worker

    was encouraged to attain his peak performance and receive payment in

    relation to this, but on the other hand, management obtained increased

    output. (Taylor 1947)

  • Factors Affecting Productivity in the UAE Construction Industry, Nabil Ailabouni, 2010

    36

    Henri Fayol, a mining engineer based his writing on his experience as a

    French coal mining manager. He was concerned with developing a

    universal approach to management and set this out in his Fourteen

    Principles of Management (Fayol 1949). These are:

    Division of Work - more and better work from the same effort

    through the benefits of specialization

    Authority and Responsibility authority brings in responsibility

    and so generates