Factors affecting construction cost performance (IJCEBE).pdf

6
International Journal of Civil Engineering and Built Environment Vol.1, No.1, 2014; ISSN 2289-6317 Published by YSI Publisher 30 Factors affecting construction cost performance in project management projects: Case of MARA large projects Aftab Hameed Memon 1 , Ismail Abdul Rahman 1 , Mohd Razaki Abdullah 2 ,Ade Asmi Abdu Azis 3 1 Faculty of Civil and Environmental Engineering, University Tun Hussein Onn Malaysia, Malaysia 2 Majlis Amanah Rakyat (MARA) 3 Universiti Tun Hussein Onn Malaysia, 86400 Parit Raja - Batu Pahat Corresponding Author:[email protected] Abstract Aim of Study This study has focused on investigating procurement strategies adopted in MARA large construction projects. It also identified various factor affecting construction cost performance of MARA large construction projects. Need of Study Very rarely MARA projects are finished within estimated project cost. For improving cost performance, it is very important to identify the reasons affecting cost performance of MARA projects. Hence, there is a need of study in understanding the reasons and factors affecting project cost performance of construction projects. Research Approach The project was carried out through interviews and survey using the questionnaire among the personnel involved in handling MARA large projects. Gathered data was analyzed statistically using SPSS software package. Research Findings This study revealed that fluctuation in price of the material, cash flow and financial difficulties faced by contractors, shortage of site workers, lack of communication between parties, incorrect planning and scheduling by contractors are most severe factors while frequent design changes and owner interference are least affecting factors on construction cost performance in MARA large projects. Limitations This study was limited to large construction projects administrated by Majlis Amanah Rakyat (MARA) Malaysia. Importance and Contribution This study has highlighted various issues causing poor project performance in MARA large projects. Ranking of the factors will enable the MARA engineers for taking appropriate actions in improving the performance of cost in construction projects. Keywords: Construction Industry, Construction Cost, MARA Projects, Cost performance, Cost Overrun I. INTRODUCTION In recent years, Malaysian construction industry has recorded an average growth rate of 0.7% [1] compared to GDP growth of 5.46%. However, the industry is facing a lot of challenges in achieving satisfactory cost performance [2-4]. Government formed MARA (Majlis Amanah Rakyat) to strengthen the Bumiputera (Malays and other indigenous Malaysians) in the areas of business and industry. MARA currently placed under the Rural and Regional Development Ministry after briefly controlled by the Entrepreneur and Cooperation Development Ministry plays an important role in implementing the government policy. MARA has spent about RM 12 billion in its development since 1 st Malaysian plan [5]. A portion of this allocation was spent on construction. The major issue in MARA large construction project is the delay in completing its projects. An interview with Tech Art Executive Director revealed that more that 90% of large MARA construction project experienced delay since 1984. Most frequent effects of delay in MARA projects are time overrun and cost overrun. Studies revealed that time and cost overrun has a linear relationship with each other [6]. Keeping construction projects within estimated costs and schedules requires sound strategies, good practices, and careful judgment. To the dislike of owners, contractors and consultants, however, many projects experience extensive delays and thereby exceed initial time and cost estimates. This problem is more obvious in the traditional or adversarial type of contracts in which the contract is awarded to the lowest bidder, which is the strategy in the majority of public projects in developing countries [7]. In order to manage and control construction projects, there are various procurements strategies being adopted. Most popular strategies include traditional, management, integrated services and in-house teams [8]. These strategies contain various methods of managing projects as shown in Table 1. TABLE I. TYPES OF PROCUREMENT METHODS &THEIR VARIATIONS Procurement Strategy Methods/Techniques Procurement Strategy Traditional Lump Sum System/Traditional System/ Design- Bid- Build/Open Tender Contracts Negotiated Contracts Best Value Procurement Incentives Contracts Management Construction Project Management/Contract Management Construction Management at Risk/Management Contracting Integrated Design and Build Turnkey System

description

actors affecting construction cost performance (IJCEBE).pdf

Transcript of Factors affecting construction cost performance (IJCEBE).pdf

  • International Journal of Civil Engineering and Built Environment Vol.1, No.1, 2014; ISSN 2289-6317 Published by YSI Publisher

    30

    Factors affecting construction cost performance in project management projects: Case of MARA

    large projects

    Aftab Hameed Memon1, Ismail Abdul Rahman1, Mohd Razaki Abdullah2,Ade Asmi Abdu Azis3 1Faculty of Civil and Environmental Engineering, University Tun Hussein Onn Malaysia, Malaysia

    2Majlis Amanah Rakyat (MARA) 3Universiti Tun Hussein Onn Malaysia, 86400 Parit Raja - Batu Pahat

    Corresponding Author:[email protected]

    Abstract

    Aim of Study This study has focused on investigating procurement strategies

    adopted in MARA large construction projects. It also identified various factor affecting construction cost performance of MARA large construction projects.

    Need of Study Very rarely MARA projects are finished within estimated project

    cost. For improving cost performance, it is very important to identify the reasons affecting cost performance of MARA projects. Hence, there is a need of study in understanding the reasons and factors affecting project cost performance of construction projects.

    Research Approach

    The project was carried out through interviews and survey using the questionnaire among the personnel involved in handling MARA large projects. Gathered data was analyzed statistically using SPSS software package.

    Research Findings This study revealed that fluctuation in price of the material, cash

    flow and financial difficulties faced by contractors, shortage of site workers, lack of communication between parties, incorrect planning and scheduling by contractors are most severe factors while frequent design changes and owner interference are least affecting factors on construction cost performance in MARA large projects.

    Limitations This study was limited to large construction projects

    administrated by Majlis Amanah Rakyat (MARA) Malaysia.

    Importance and Contribution This study has highlighted various issues causing poor project

    performance in MARA large projects. Ranking of the factors will enable the MARA engineers for taking appropriate actions in improving the performance of cost in construction projects.

    Keywords: Construction Industry, Construction Cost, MARA Projects, Cost performance, Cost Overrun

    I. INTRODUCTION In recent years, Malaysian construction industry has

    recorded an average growth rate of 0.7% [1] compared to GDP growth of 5.46%. However, the industry is facing a lot of challenges in achieving satisfactory cost performance [2-4]. Government formed MARA (Majlis Amanah Rakyat) to

    strengthen the Bumiputera (Malays and other indigenous Malaysians) in the areas of business and industry. MARA currently placed under the Rural and Regional Development Ministry after briefly controlled by the Entrepreneur and Cooperation Development Ministry plays an important role in implementing the government policy. MARA has spent about RM 12 billion in its development since 1st Malaysian plan [5]. A portion of this allocation was spent on construction. The major issue in MARA large construction project is the delay in completing its projects. An interview with Tech Art Executive Director revealed that more that 90% of large MARA construction project experienced delay since 1984. Most frequent effects of delay in MARA projects are time overrun and cost overrun. Studies revealed that time and cost overrun has a linear relationship with each other [6].

    Keeping construction projects within estimated costs and schedules requires sound strategies, good practices, and careful judgment. To the dislike of owners, contractors and consultants, however, many projects experience extensive delays and thereby exceed initial time and cost estimates. This problem is more obvious in the traditional or adversarial type of contracts in which the contract is awarded to the lowest bidder, which is the strategy in the majority of public projects in developing countries [7]. In order to manage and control construction projects, there are various procurements strategies being adopted. Most popular strategies include traditional, management, integrated services and in-house teams [8]. These strategies contain various methods of managing projects as shown in Table 1.

    TABLE I. TYPES OF PROCUREMENT METHODS &THEIR VARIATIONS

    Procurement Strategy Methods/Techniques

    Procurement Strategy

    Traditional Lump Sum System/Traditional System/ Design- Bid- Build/Open Tender Contracts Negotiated Contracts Best Value Procurement Incentives Contracts

    Management Construction Project Management/Contract Management Construction Management at Risk/Management Contracting

    Integrated Design and Build Turnkey System

  • ww

    In-hou

    Inbuild/Manaprocu(1) exProjeperfothis sprojeconstbudgethis consifocusstratecollec

    II. A. B

    Prconstthat adistinprocumana

    1) applieA clicivil the cproduselectspeciappoiof othto gechoosVariavalueUSAnegotnegotto UKConsadminrelatiand F

    2) traditand c

    ww.zwgm.org

    use

    n Malaysian, t/turnkey syagement/Contraurement strategxamine variousects, (ii) identormance in MAstudy include, cts only. Alttructions, but iet of $1 milliostudy, project idered as largeses on projectegies only. Thiction were pers

    RELATED W

    udget Planningrocurement mtruction procesare used to manct advantageurement approagement, integr

    Traditional Ped to ordinaryent employs anengineering wconstruction seuce drawings ated after a clfication. Norminted on fee baher members aet the best posse any suitabations such as e procurement, while variattiated contractstiated contractsK. Sometimes,ultant (PMC) nistering the onship and se

    Figure 2. Management

    tional procuremcomplexity, m

    I

    Self-PerfoIn-House Job-OrderSeparate C

    traditional lumystem and act Manageme

    gies [1, 9]. Thiss procurement tifying factors ARA projects.

    firstly this pathough, it isin a study of Vn were conside

    of budget Re construction s with projectirdly, targeted sonnel of contr

    WORKS

    g and Control method is a strss. There are a anage the proces and disaoaches are wrated services a

    Procurement: B projects of mn architect (fororks or other separately. A and specificatilient is satisfmally, an arcasis as a leade

    and have directssible result, itble variationsdesign-bid-bui, incentives ctions such as s in UK. In Mas are extensive, a client incorinto this procu

    project [9]equence of ope

    t Procuremenment which isanagement pro

    International Jo

    ormance Teams r Contract Contracts

    mp sum systemConstruct

    ent are commos study has beestrategies adopaffecting conHowever, the

    aper focus largs difficult to Vietnam projecered as large p

    RM 5 million project, seconts managemenrespondent in

    ractor firms and

    rategy to mannumber of pr

    cess where eacadvantages. Iidely discusse

    and in house tea

    Basically, this moderate size an

    r a building) ostructures) and designer is hion while contfied with the chitect or enger to coordinatt access to the t is normal fo

    s that suits tild, negotiated ontracts are wopen tender

    alaysia, both oely adopted andrporates Projecurement to assi. The typicaeration is show

    nt: Basically s focusing on ocurement is p

    ournal of Civil

    m, design andion Projec

    only adopted inen conducted topted in MARAnstruction cose limitations oge construction

    define largects with a tota

    projects [10]. Inand above is

    ndly, this studynt procuremenncluded in datad client.

    nage the entireoven strategiesch has its ownInitially, foured; traditionalams [9].

    procurement isnd complexity

    or engineer (forcontractors forired earlier totractors will be

    drawings andgineer will bete the activitiesclient. In order

    or the client toto their plancontracts, bes

    widely used incontracts and

    open tender andd this is similarct Managemenist the client inal contractuawn in Figure 1

    Compared tomoderate size

    preferred to be

    l Engineering a

    31

    d t n o A t f n e

    al n s y

    nt a

    e s n r l,

    s y. r r o e d e s r o n. t n d d r t n al 1

    o e e

    adopted fappointedwhole cois hired substantiawork begdesigner during trelationshand Figur

    Figure 1

    Figur

    Figure 4.

    3) Intprocuremseveral osingle orgprofessioquantity sconsortiumainly adprospecti

    and Built Envir

    for large or comd by client on nstruction procearlier or tog

    al design worgun. The CMduring the d

    the constructihip and sequenre 4.

    1. Typical Contra

    Figure 2. T

    re 3. Typical Con

    Typical Sequen

    tegrated Prment is where other subtasks ganization, oftenals such asurveyors and

    um to provide idopted on techive contractors

    ronment V

    mplex projectsa fee basis to cess. A construgether with thrk is done and

    M (on clients design phase ion phase. Tnce of operati

    actual Relationship

    Typical Sequences

    ntractual RelationsProcurement

    ces of Operations

    rocurement: design and c

    on the projeen a large cont

    as constructioengineers com

    integrated servhnically sophiss have special

    Vol. 1 No. 1, 20

    . A person or corganize and muction managemhe designer bd before any behalf) workand represent

    The typical con is shown i

    ps under Tradition

    s of Operations

    ships under Manag

    of Management P

    Basically construction, aect, are perfortracting firm. S

    on managers, mbined togethevices. This procsticated projectexperience, or

    014

    company is manage the ment (CM) before any substantial s with the ting client contractual n Figure 3

    nal Method

    gement

    rocurement

    Integrated as well as rmed by a Sometimes,

    architect, er to form a curement is ts of which r time is of

  • ww

    the erespodesigUK, AppaintrodMalarelatiand F

    Figur

    Fig

    4) is sellarge their emploworksubstcontrcentraimple

    B. CC

    projeworldreflecassocdilemdevelthis min devsevercarriematerconstsignifhappematerin theadequpoor [13]. of Ko

    ww.zwgm.org

    essence. It ponsibility througn-build variati

    design and arently, designduced to Mala

    aysia construconship and se

    Figure 6.

    re 5. Typical Con

    gure 6. Typical S

    In House Prolf perform conpublic organizown continu

    oy their ownkers, etc. Howetantial portion ractors for botalized decisionementation.

    Cost PerformanCost Performan

    ct success. Undwide are expcted in the cociated with almma is very seloped countriematter [12]. Thveloping countral factors as ed out worldwrials is a cotruction cost coficant amount ens mostly becrials and manae construction uate ability of cost performanSimilarity, in K

    oushki [14] tim

    I

    provides a sinughout the prion is popularl

    build variatn and buildaysia 1983 [9]ction project.equence of ope

    ntractual Relations

    Sequences of Oper

    ocurement: Banstruction. Norzation or largeuous constructn people sucever, the client

    of the projecth design andn making to in

    nce nce is the fundnfortunately, mperiencing pooost overrun plmost every perious and is fs. It requires

    his problem of ctries. Overrun ihighlighted by

    wide. Among ommon factorompared to the of loss of mat

    cause of lack oagement system

    industry is thpreventing cosnce and led mKuwait it was

    me and cost inc

    International Jo

    ngle point ofroject. Design ly used in USAion is also or turnkey and still wid. The typicaeration is show

    ships under Integra

    ations of Integrate

    asically In housrmally, large c

    e private compation projects h as engineemay choose to

    ct to outside c construction, ntegrate all eff

    damental normmany of constror cost performroblem whichproject [11]. faced in both dcareful attenticost overrun isin cost is occury numerous r

    these, use or which resuestimated cost

    terials during cof availability oms. Further, a he project manst overruns. Th

    many Thai conshighlighted byreases were sig

    ournal of Civil

    f contact andand build or

    A. Similarly inwidely usedsystem was

    dely adopted inal contractuawn in Figure 5

    ated Procurement

    ed Procurement

    se procuremenclients such asanies that havehave directly

    ers, architectso subcontract a

    consultants andbut it retains

    forts in projec

    m of measuringruction projectsmance. This ish now days isCost overruns

    developing andon to improve

    s more rigorousrred because ofresearch worksof low qualityults in highert because of theconstruction. Iof standards formajor problemagers have nohis has resultedstruction to faiy research workgnificant issues

    l Engineering a

    32

    d r n

    d. s n al 5

    nt s e y s, a d s t

    g s s s s d e s f s y r e t r

    m t d l k s

    in privatincrease constraintWhile, thfinancial Besides unpredictof buildincost overmentionefaced in consequerepresentmanagemOverall, recorded payment performan

    III. DAData

    phase focvarious pidentify csurvey waffecting consultanfactors. Athe degrestrongly agree aparticipatStatisticaused to anto rankindata colleis considethan 0.3. more than

    Distriin figure i.e. 21 ouin the cexperienchad 2-5 yexperienc

    and Built Envir

    te residential for these incluts and owners

    he issues to reconditions wethese, desig

    table weather cng materials arerruns [15, 16]. ed that monthlyconstruction p

    ently project fatives highli

    ment is the mostin groundwatwere found pdifficulties, m

    nces, and escal

    ATA COLLECTcollection was

    cused on field sprocurement strcommon causewas conducted

    construction nts and contracA five point likeee of agreeme

    disagree, 2 and 5 stronglted in interviel Package for nalyze the datag the factors. Rected measuredered low and uReliability is c

    n 0.7 [18].

    ibution of respo11. Figure 11

    ut of 36 (58.33%construction ince between 6-1years experiencce less than 2 y

    Figure 7. R

    ronment V

    projects in Kuded frequent s lack of expelated contractoere major contgn changes, conditions; ande frequently ocIn Ghana, co

    y payments difprojects that leafaces overrun ighted that t critical factorter projects opoor contractomaterial proculation of mater

    TION AND ANAs carried out instudy and interrategies adoptees of cost overrd for identifycost performa

    ctors for assesert-scale of 1 to

    ent of each caudisagree, 3

    ly agree. A ews and questSocial Science

    a. Data was chReliability desd using Cronbaunacceptable ifconsidered sati

    ondents in term indicates that

    %) were experindustry, 7 ou10 years, whilece and only 4 (years.

    Respondents worki

    Vol. 1 No. 1, 20

    Kuwait. The mchange orders

    perience in coor, material antributors to cos

    inadequate d fluctuations ccurring factorsntractors and cfficulties is a mad to delay in in cost. Wh

    the poor rs in causing coof Ghana, major managemenurement, poorial prices [17].

    ALYSIS n two phases rviews. It aimeed in MARA prun. In the sec

    fying significaance among cssing significao 5 was adopteuse where 1 r

    3 moderately total of 36 r

    tionnaire survee (SPSS) versi

    hecked for reliacribes the stabach coefficief Cronbach visfactory if Cro

    ms of experienct majority of renced more tha

    ut of 36 (19.e 4 respondent(11.11%) respo

    ing experience

    014

    major time s, financial onstruction. nd owners st increase.

    planning, in the cost s leading to consultants major issue works and

    hile, client contractor

    ost overrun. jor factors

    nt, monthly r technical

    where first ed to assess projects and cond phase, ant factors contractors, ance of the ed to assess represented

    agree, 4 respondents ey process. ion 17 was ability prior bility of the ent value. It value is less onbach is

    ce is shown respondents an 10 years .44%) had s (11.11%)

    ondents had

  • ww

    IV. A. C

    Mlarge traditadoptprojealso classideliveprojenormnorman aconstcontaworthThis speciMARprojesuper

    B. MSt

    procuMARwholemanagrantshowmanashow

    Fig

    Fi

    Figu

    ww.zwgm.org

    RESULTS AN

    Classification ofMARA construc

    projects. Motional procuremting managemcts which are adopting ma

    ification of theery methods act worth less t

    mally consideremally MARA is architect is aptruction at the act with MARh more than R

    large project al knowledge a

    RA is adoptingct and as a mrvise and admin

    MARA Constructudies revealeurement; tradiRA is organizine the project.

    agement procued first before

    w the contractuagement procu

    ws their sequenc

    gure 8. Contractu

    gure 9. Sequence

    ure 10. Contractua

    I

    ND DISCUSSION

    f MARA projecction projects aost of the sm

    ment while the ment procurem

    complex and anagement pre project is basare based on ithan five milli

    ed as a small adopting the tr

    ppointed as tconstruction

    RA. Contrast tRM 5 million is

    normally higand expertise t

    g management matter of factnister the entire

    ction Procuremed that MARtional and m

    ng its own tech. However, if

    urement,approva PMC is app

    ual relationshipurement whilece of operation

    ual Relationship of

    e of Operation of M

    al Relationship of M

    International Jo

    N

    cts are classified inmall projects majority of lar

    ment. In someneed special

    rocurement. Ted on its contrits size and coion ringgit (RMproject. As mraditional procthe leader to site. The lead

    to small projes considered asghly complicatto handle it. Moprocurement ft, MARA enge project.

    ment RA is adoptinmanagement. Fhnical teams tof MARA dec

    val from LPMointed. Figure p of MARA

    e Figure 10 a.

    f MARA Tradition

    MARA Traditiona

    MARA Managem

    ournal of Civil

    nto 2; small andare adopting

    rge projects aree cases, smalknowledge are

    Therefore, theract cost but itsomplexity. TheM 5 million) ismention earliercurement where

    organize theder has direc

    ect, the projecs large projectted and needsost of the timefor this kind ofgages PMC to

    ng 2 types ofFor traditional administer the

    cides to adopM A must be

    8 and Figure 9traditional and

    and Figure 11

    nal Procurement

    al Procurement

    ent Procurement

    l Engineering a

    33

    d g e l e e s e s r, e e t t

    t. s

    e, f o

    f l, e t e 9 d 1

    Figure 1

    C. FactoDurin

    affecting identifiedcommon shown inpurpose. reliability0.776 whorder to iperformanpresentedof matericost perdifficultieShortage were 3rdcontracto

    Fluctthe fluctuconstructaccordingwhile con

    Cash contractodifficultieContractoinfluencesite workbe facedconsultanthis issue

    Shortperceivedrespondendominantrespondensubcontraof the wworkers abetween prevails.

    Lack communiaffecting contractopoor manbetween t

    and Built Envir

    11. Sequence of O

    ors Affecting Cong interview p

    project cost pd. Literature s

    factors affecn figure II. The

    Data collectey. Cronbach's Ahich means dataidentify the rannce, data was

    d in table III. Bals is the most

    rformance folles faced by cof site workersmajor factor a

    ors were found

    uation in pricuation of materiion cost. Howeg to client flucntractor ranked

    flow and ors: Contractoes as 2nd factors believe thie other causes kers and ineffecd due to delant and late in may as well se

    tage of site wd by Client. nts. Howevert while contrants claim thatactor seems lar

    works are contare hired by thcontractor and

    of communication between

    factor. Clienor ranked as 4tnagement, selethe contractor a

    ronment V

    peration of MARA

    Construction Coprocess, a totalerformance in

    showed that thcting cost perse factors were

    ed through quAlpha of the gaa collected in anks of factors as analyzed witBased on table

    significant faclowed by Cacontractors as s, lack of comm

    and incorrect pas 4th ranked fa

    ces of materiaial is the most ever, it is very

    ctuation in pricd as 1st.

    financial ors rankled ctor while clieis issue is versuch as site m

    ctive planning aay approval monthly paymettle other issue

    workers: ThisIt is 3rd ran

    , client rankeactors ranked t the problem rgely contributtracted to sub

    hese sub-contrad subcontractor

    nication betwn parties is alsnts ranked thth. Lack of co

    ection of propeand other partie

    Vol. 1 No. 1, 20

    A Management Pro

    ost Performancl of 15 commMRA large pr

    he identified rformance wore investigated f

    uestionnaire waathered data waacceptable for aaffecting constrth SPSS 17. RIII, Fluctuatio

    ctor affecting coash flow and

    second rankemunication am

    planning & schactor.

    als: Table III dominant facto

    y interesting toce was ranked

    difficulties cash flow andent ranked samry critical whemanagement, sand schedulingof work com

    ment from clienes simultaneou

    s factor is signked factor bed this factor

    it as 12th rabetween cont

    te to this causecontractors, m

    actor. If there ar, automatically

    ween parties:so ranked as thhis factor as oordination maer material andes.

    014

    ocurement

    ce mon factors roject were factors are rldwide as for ranking as test for as found as analysis. In ruction cost Results are on in prices onstruction

    d financial ed factors.

    mong parties heduling by

    shows that or affecting

    o know that as 6th rank

    faced by d financial me as 5th. ere it may shortage of g. This may mpleted by nt. Settling

    usly.

    gnificant as by overall r as most ank. Client tractor and e. As most

    most of the are disputes y this issue

    Lack of hird highest

    3rd while ay result in d problems

  • www.zwgm.org International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014

    34

    TABLE II. RANKING OF FACTORS AFFECTING CONSTRUCTION COST PERFORMANCE

    S.No Causes [10]

    [`11

    ]

    [17]

    [19]

    [20]

    [21]

    [22]

    [23]

    [24]

    [25]

    [26]

    [27]

    [28]

    [29]

    [30]

    1 Incorrect planning and scheduling by contractors 2 Fluctuation in prices of materials 3 Frequent design changes 4 Unforeseen ground conditions 5 Inadequate contractor experience 6 Change in the scope of the project 7 Low speed of decisions making 8 Cash flow and financial difficulties faced by

    contractors 9 Contractor's poor site management and supervision 10 Practice of assigning contract to lowest bidder 11 Lack of communication among parties 12 Shortage of site workers 13 Delay in Material procurement 14 Underestimate project duration resulting Schedule

    Delay 15 Incompetent Project team (designers and

    contractors)

    TABLE III. RANKING OF FACTORS AFFECTING CONSTRUCTION COST PERFORMANCE

    S.No. Factors Overall Client Respondents Contractor Respondents

    Mean S.D Rank Mean S.D Rank Mean S.D Rank

    1 Fluctuation in prices of materials 3.97 0.97 1 3.62 0.87 6 4.47 0.92 1

    2 Cash flow and financial difficulties faced by contractors 3.89 1.21 2 3.90 1.18 5 3.87 1.30 2

    3 Shortage of site workers 3.78 1.12 3 3.95 1.02 4 3.53 1.25 7

    4 Lack of communication among parties 3.78 1.07 3 4.0 0.78 3 3.78 1.07 4

    5 Incorrect planning and scheduling by contractors 3.67 1.12 4 4.29 0.78 1 2.8 0.94 12

    6 Contractor's poor site management and supervision 3.67 1.06 4 4.24 0.70 2 2.87 0.99 11

    7 Delay in Material procurement 3.53 0.94 5 3.33 0.91 9 3.8 0.94 3

    8 Underestimate project duration resulting Schedule Delay 3.47 0.91 6 3.47 0.75 7 3.47 1.13 8

    9 Unforeseen ground conditions 3.39 0.96 7 3.14 0.96 10 3.73 0.88 5

    10 Low speed of decisions making 3.36 0.90 8 3.38 0.80 8 3.33 1.04 9

    11 Inadequate contractor experience 3.36 1.10 8 3.95 0.80 4 2.53 0.92 13

    12 Change in the scope of the project 3.33 0.76 9 3.14 0.65 10 3.60 0.83 6

    13 Practice of assigning contract to lowest bidder 3.28 1.28 10 3.09 1.19 11 3.53 1.34 7

    14 Frequent design changes 3.19 0.95 11 2.90 0.94 12 3.6 0.83 6

    15 Owner interference 2.89 0.95 12 2.8 0.81 13 3.0 1.13 10

  • www.zwgm.org International Journal of Civil Engineering and Built Environment Vol. 1 No. 1, 2014

    35

    V. CONCLUSION Study was carried out to investigate various procurement

    strategies adopted in MARA large construction projects. Results showed that MARA projects are classified as small and large project based on cost of project cost. Project worth contract amount above 5 Million Ringgit were regarded as large construction projects. In order to manage projects, traditional and management procurement strategies are adopted. Also, comprehensive study was conducted to identify the factors affecting construction cost performance. Through a questionnaire survey amongst contractor and client personnel, it was perceived that fluctuation of material prices was the most dominant factor affecting construction cost performance followed by cash flow and financial difficulties faced by contractors. Shortage of site workers and lack of communication between parties were found as third major factors affecting construction cost performance.

    REFERENCES [1] CIMP, Construction Industry Master Plan 2006-2015, CIDB,

    Malaysia [2] CIDB news issue 3, 2007 [3] A. H. Memon, I. A. Rahman, A. A. A. Azis, S. Nagapan, and Q. B. A. I.

    Latif, Time and Cost Perfomance in Construction Projects, IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2012), held on 3-4 December 2012, Kota Kinabalu, Malaysia, 2012

    [4] I. A. Rahman, A. H. Memon, A. T. A. Karim, Relationship between factors of Construction Resources Affecting Project, Modern Applied Science, 7 (1), p. 67-75, 2013

    [5] http://maranet.mara.gov.my/Am/ sejarah_ mara_dari_rida_ke_marahtm [6] M. R. Abdullah, A. A. A. Azis, and I. A. Rahman, Potential effects on

    large MARA projects due to construction delay, International journal of Integrated Engineering (Issue on Civil and Environmental Engineering), 1(2), p. 53-62, 2009

    [7] A. Enshassi, J. Al-Najjar, and M. Kumaraswamy, "Delays and cost overrunsin the construction projects in the Gaza Strip", Journal of Financial Management of Property and Construction, 14 (2), p. 126-151, 2009

    [8] G. Ofori, The Construction Industry; aspects of its economics and management, Singapore University Press, 1990

    [9] K. A. Rashid, Construction Procurement in Malaysia, International Islamic University Malaysia, 2002

    [10] L. Le-Hoai, Y. D. Lee, and J. Y. Lee, Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries,. KSCE journal of civil engineering, 12 (6), p. 367-377, 2008

    [11] N. Azhar, R. U. Farooqui, and S. M. Ahmed, Cost overrun factors in construction industry in Pakistan, First international conference on construction in developing countries (ICCIDC-I, advancing and integrating construction education, research and practice), 2008

    [12] W. J. Angelo, and P. Reina, Mega projects Need More Study Up Front to Avoid Cost Overruns, 2002.

    [13] E. Sriprasert, Assessment of Cost Control System: A Case Study of Thai Construction Organizations, M.S. thesis, Bangkok: Asian Institute of Technology, 2000

    [14] P. A. Koushki, K. Al-Rashid, and N. Kartam, Delays and cost increases in the construction of private residential projects in Kuwait, Construction Management and Economics, 23, p. 285-294, 2005

    [15] P. F. Kaming, P. O. Olomolaiye, G. D. Holt, and F. C. Harris, Factors Influencing Construction Time and Cost Overruns on High-rise Projects in Indonesia, Construction Management and Economics, 15 (1), p. 83-94, 1997

    [16] K. D. Chimwaso, An Evaluation of Cost Performance of Public Projects; Case of Botswana, Department of Architecture and Building Services, Gaborone, 2001

    [17] Y. Frimpong, J. Oluwoye, and L. Crawford, Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study, International Journal of project management, 21, p. 321-326, 2003

    [18] S. Meepol, and S. O. Ogunlana, Factors affecting cost and time performance on highway construction projects: evidence from Thailand, Journal of Financial Management of Property and Construction, 11(1), p. 3-20, 2006

    [19] O. J. Ameh, A. D. Soyingbe, and K. T. Odusami, "Significant factors causing cost overruns in telecommunication projects in Nigeria", Journal of Construction in Developing Countries, 15, 2010

    [20] G. Creedy, "Risk factors leading to cost overrun in highway projects". Sidwell, A. C. (Ed.). Proceeding of Queenland University of Technology Research Week International Conference, Brisbane, Australia, 4-8 July, 2005

    [21] S. Jackson, Project cost overrun and risk management, Proceedings of Association of Researchers in Construction Management 18th Annual ARCOM Conference, Newcastle, Northumber University, UK, 2-4 September, 2002

    [22] A. S. T. Chang, "Reasons for Cost and Schedule Increase for Engineering Design Projects", Journal of Management in Engineering, 18 (1), p. 2936, 2002

    [23] Y. A. Al-Juwairah, "Factors Affecting Construction Costs in Saudi Arabia", Thesis of MSc in construction Management, Faculty of the college of Graduate Studies, King Fahad University of Petroleum & Minerals Dhahran, Saudi Arabia, 1997

    [24] A. Enshassi, J. Al-Najjar, and M. Kumaraswamy, "Delays and cost overruns in the construction projects in the Gaza Strip", Journal of Financial Management of Property and Construction, 14 (2), p. 126-151, 2009

    [25] Harisweni, "The Framework for Minimizing Construction time and Cost Overruns in Padding and Pekanbaru, Indonesia", A thesis submitted in fulfilment of the requirements for the award of the degree of Master of Science (Quantity Surveying), Faculty of Built Environment, Universiti Teknologi Malaysia, 2007

    [26] A. Omoregie, and D. Radford, Infrastructure delays and cost escalation: causes and effects in Nigeria, Proceeding of sixth international postgraduate research conference, Delft University of Technology and TNO, the Netherlands. 3rd-7th April., 2006

    [27] N. D. Long, S. Ogunlana, T. Quang, and K. C. Lam, "Large construction projects in developing countries: a case study from Vietnam", International Journal of Project Management, 22, p. 553561, 2004

    [28] M. R. Abdullah, A. A. A. Azis, and I. A. Rahman, Potential effects on large MARA projects due to construction delay, International journal of Integrated Engineering (Issue on Civil and Environmental Engineering) 2009, 1(2): 53-62, 2009

    [29] M. Sambasivan, Y. W. Soon, "Causes and effects of delays in Malaysian construction industry", International Journal of Project Management, 25, p. 517526, 2007

    [30] I. A. Majid Causes and Effects of delays in ACEH Construction Industry, Thesis of MSc in construction management, Faculty of Civil Engineering, University Technology Malaysia, 2006