FACILITY LOCATION AND LAYOUT
Prepared by , Guided By,
Piyush bhatt Madhuri mam
Swati parmar
Dipak mer
Submitted to,
Department Of Business Administration,
MK Bhavnagar University,
Bhavnagar.
![Page 2: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/2.jpg)
PLANT LOCATION
Every entrepreneur is faced with the problem of deciding the best site for location of his plant or factory.
Plant location refers to the choice of region and the selection of a particular site for setting up a business or factory.
An ideal location is one where the cost of the product is kept to minimum, with a large market share, the least risk and the maximum social gain.
![Page 3: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/3.jpg)
Reason for firm should look for additional or alternate location
To establish new venture
Expansion of existing business
Changes in demand and supply
Company policy on diversification and change of working condition
Changing in government policy
![Page 4: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/4.jpg)
Alternate options open for management
Make or Buy decision
Sub-contract instead of expansion
Expand existing organization
Dispose of the existing plant and build new one
![Page 5: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/5.jpg)
Location analysis
Demographic Analysis
Trade Area Analysis
Competitive Analysis
Traffic analysis
Site economics
![Page 6: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/6.jpg)
Cost Site- A (Rs) Site- B (Rs)
Cost of establishments:
Land and Buildings
350000 250000
Transport facilities
20000 30000
Cost of operations:
Taxes 10000 8000
Labour 100000 70000
Water, power and fuel
10000 80000
Total 490000 438000
Two sites A and B are evaluated in terms of above mentioned two costs as follows:
![Page 7: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/7.jpg)
Factors influencing plant location/facility location
1. General locational factors, which include controllable and uncontrollable factors for all type of organisations.
2. Specific locational factors specifically required for manufacturing and service organisations.
![Page 8: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/8.jpg)
General Locational Factors
1. Proximity to markets
2. Supply of materials
3. Transportation facilities
4. Infrastructure availability
5. Labour and wages
6. Capital
Controllable factors
![Page 9: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/9.jpg)
Uncontrollable factors
1. Government policy
2. Climate conditions
3. Supporting industries and services
4. Community and labour attitudes
![Page 10: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/10.jpg)
Specific Locational Factors for Service Organisation
1. Favorable labor climate
2. Proximity to markets
3. Quality of life
4. Proximity to suppliers and resources
5. Utilities, taxes, and real estate costs
![Page 11: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/11.jpg)
LOCATION MODELS
Various models are available which help to identify the ideal location. Some of the popular models are:
1. Factor rating method
2. Weighted factor rating method
3. Load-distance method
4. Centre of gravity method
5. Break even analysis
![Page 12: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/12.jpg)
1. Factor rating method
The process of selecting a new facility location involves a series of following steps:
1. Identify the important location factors.
2. Rate each factor according to its relative importance,
i.e., higher the ratings is indicative of prominent factor.
3. Assign each location according to the merits of the
location for each factor.
![Page 13: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/13.jpg)
4. Calculate the rating for each location by multiplying
factor assigned to each location with basic factors
considered.
5. Find the sum of product calculated for each factor
and select best location having highest total score.
![Page 14: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/14.jpg)
ILLUSTRATION 1: Let us assume that a new medical facility, Health-care, is to be
located in Delhi. The location factors, factor rating and scores for two potential sites are
shown in the following table. Which is the best location based on factor rating method?
Sl. No. Location factor Factor rating
Rating
Location 1
Location 2
1 Facility utilization 8 3 5
2 Total patient per month 5 4 3
3 Employee preferences 5 5 3
![Page 15: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/15.jpg)
Sl. No. Location factor
Factor rating (1)
Location 1 Location 2
Rating Total Rating Total
1 Facility utilization
8 3 24 5 40
2 Total patient per month
5 4 20 3 15
3 Employee preferences
5 5 25 3 15
Total 69 Total 70
SOLUTION:
![Page 16: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/16.jpg)
2. Weighted Factor Rating Method
In this method to merge quantitative and qualitative
factors, factors are assigned weights based on relative
importance and weight age score for each site using a
preference matrix is calculated. The site with the highest
weighted score is selected as the best choice.
![Page 17: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/17.jpg)
ILLUSTRATION 2: Let us assume that a new medical
facility, Health-care, is to belocated in Delhi. The location factors, weights, and scores
(1 = poor, 5 = excellent) fortwo potential sites are shown in the following table. What is
the weighted score for thesesites? Which is the best location?
Sr No. Location factor Weight Scores
L-1 L-2
1 Facility utilization 25 3 5
2 Total patient per month 25 4 3
3 Average time per emergency trip 25 3 3
4 Land and construction costs 15 1 2
5 Employee preferences 10 5 3
![Page 18: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/18.jpg)
The weighted score for this particular site is calculated by multiplying each factor’s weight by its score and adding the results:
Weighed score location 1 = 25 × 3 + 25 × 4 + 25 × 3 + 15 × 1 + 10 × 5= 75 + 100 + 75 + 15 + 50 = 315
Weighed score location 2 = 25 × 5 + 25 × 3 + 25 × 3 + 15 × 2 + 10 × 3= 125 + 75 + 75 + 30 + 30 = 335
Location 2 is the best site based on total weighted scores.
SOLUTION:
![Page 19: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/19.jpg)
3. Load-distance Method
The load-distance method is a mathematical model used to evaluate locations based on proximity factors. The objective is to select a location that minimizes the total weighted loads moving into and out of the facility. The distance between two points is expressed by assigning the points to grid coordinates on a map. An alternative approach is to use time rather than distance.
![Page 20: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/20.jpg)
Centre of gravity is based primarily on cost considerations. This method can be used to assist managers in balancing cost and service objectives. The centre of gravity method takes into account the locations of plants and markets, the volume of goods moved, and transportation costs in arriving at the best location for a single intermediate warehouse.
4 Centre of Gravity
![Page 21: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/21.jpg)
5. Break Even Analysis
Break even analysis implies that at some point in the operations, total revenue equals total cost. Break even analysis is concerned with finding the point at which revenues and costs agree exactly.
![Page 22: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/22.jpg)
![Page 23: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/23.jpg)
PLANT LAYOUT
![Page 24: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/24.jpg)
Point to consider
1. Meaning
2. Objectives of Plant Layout
3. Principles of Plant Layout
4. Classification of layout
![Page 25: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/25.jpg)
1.Meaning of plant lay-out
According to Moore “Plant layout is a plan of an optimum arrangement of facilities including
Personnel operating equipment storage space material handling equipment and all other supporting services along with the
design of best structure to contain all these facilities”.
![Page 26: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/26.jpg)
2. Objectives of Plant Layout
1.Streamline the flow of materials through the plant.
2. Facilitate the manufacturing process.
3. Maintain high turnover of in-process inventory.
4. Minimize materials handling and cost.
5. Effective utilization of men, equipment and space.
6. Make effective utilization of cubic space.
7. Flexibility of manufacturing operations and arrangements.
8. Provide for employee convenience, safety and comfort.
9. Minimize investment in equipment.
10. Minimize overall production time.
11. Maintain flexibility of arrangement and operation.
12. Facilitate the organizational structure.
![Page 27: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/27.jpg)
3. Principles of Plant Layout
1. Principle of integration
2. Principle of minimum distance
3. Principle of cubic space utilization
4. Principle of flow
5. Principle of maximum flexibility
6. Principle of safety, security and satisfaction
7. Principle of minimum handling
![Page 28: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/28.jpg)
4.Classification of layout
Layouts can be classified into the following five categories:
1. Process layout
2. Product layout
3. Combination layout
4. Fixed position layout
![Page 29: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/29.jpg)
1. Process Layout
Model of process Layout
![Page 30: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/30.jpg)
Advantages of process Layout Flexibility better utilization of production facility Lower investment Increase knowledge of supervisors
![Page 31: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/31.jpg)
Limitation of process Layout
Reduce material handling efficiency Increase in cost Decrease productivity
![Page 32: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/32.jpg)
2. Product Layout
Model of product Lay-out
![Page 33: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/33.jpg)
Advantages of product Layout In-process inventory is less Decrease handling cost Mechanized handling systems Unskilled workers can learn and manage the
production. Manufacturing cycle is short due to
uninterrupted flow of materials.
![Page 34: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/34.jpg)
Limitation of product Layout
Stop entire production Difficult to change product design Required high investment Lack of flexibility
![Page 35: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/35.jpg)
3. Combination Layoutcombination
type of layout for manufacturing different sized gears
![Page 36: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/36.jpg)
4. Fixed Position Layout
Fixed type of position Layout
![Page 37: facility location and planning layout](https://reader038.fdocuments.in/reader038/viewer/2022102621/54c731884a795989488b4595/html5/thumbnails/37.jpg)
Advantages of Fixed position Layout interest and pride in doing the job enlargement and upgrades the skills Flexibility Layout capital investment is lower.