Facilities Subcommittee Meeting
description
Transcript of Facilities Subcommittee Meeting
FACILITIES SUBCOMMITTEE MEETING
Emergency Repair ProgramJune 12, 2012
Presented by: Jamie Iseman, Senior Associate Jack Schreder & Associates
Emergency Repair Program: Summary
June 12, 2012Presented by: Jack Schreder & Associates
Provided 100% funding to repair or replace systems or structures in a condition that posed a threat to the health and safety of students and staff while at school.
Available to schools identified by the CDE as ranked in declines one, two, or three based on the 2006 API and that were newly constructed prior to January 1, 2000.
Eligible projects costs were limited to the minimum work required to mitigate the health and safety hazard, plus application documentation preparation and submittal costs.
3
Funding
June 12, 2012Presented by: Jack Schreder & Associates
Funds were made available annually, and the program operated until $800 million was allocated.
Districts provided project lists with detailed cost estimates and backup documentation to obtain funding upfront.
Once approved, Districts had 12-18 months to complete all projects.
Per ERP regulations, all project savings, as well as interest, are to be: Applied to eligible costs for the project, as approved by
the SAB; or Returned to the State at the same time the LEA submitted
the expenditure report to the OPSC.
WCCUSD ERP Projects
June 12, 2012Presented by: Jack Schreder & Associates
4
Schreder & Associates worked with SGI to identify eligible projects at 19 District sites. The District received $11,699,520 in ERP funding at
12 sites. The District has ERP applications at 2 sites that are
approved but on the unfunded list ($2,081,692). The District has 5 ERP applications, submitted in
October 2008, that are pending processing ($5,357,108).
For all applications that received funding, expenditure reports have been submitted and all project savings (with interest) have been returned to the State.
5
WCCUSD ERP Projects
June 12, 2012Presented by: Jack Schreder & Associates
Status Site Application NumberFunding
Type
OPSC Received
DateSAB Date State Grant
Funded De Anza Senior High 61/61796-00-0111 Grant 09/12/2007 01/30/2008 $132,987
Funded Transition Learning Center 61/61796-00-0113 Grant 09/27/2007 05/28/2008 $835,105
Funded Fairmont Elementary 61/61796-00-0114 Grant 09/27/2007 05/28/2008 $68,756
Funded Coronado Elementary 61/61796-00-0115 Grant 09/27/2007 05/28/2008 $1,168,485
Funded Castro Elementary 61/61796-00-0116 Grant 09/27/2007 05/28/2008 $62,202
Funded Coronado Elementary 61/61796-00-0155 Grant 09/27/2007 05/28/2008 $424,719
Funded Pinole Valley High 61/61796-00-0112 Grant 09/27/2007 06/25/2008 $1,020,128
Funded Crespi Junior High 61/61796-00-0150 Grant 01/29/2008 04/22/2009 $2,405,897
Funded Adams Middle 61/61796-00-0151 Grant 01/29/2008 05/27/2009 $1,232,212
Funded Stege Elementary 61/61796-00-0152 Grant 02/15/2008 08/26/2009 $114,886
Funded Grant Elementary 61/61796-00-0153 Grant 02/15/2008 08/26/2009 $424,972
Funded Richmond High 61/61796-00-0154 Grant 02/15/2008 08/26/2009 $3,809,171
Unfunded List Lake Elementary 61/61796-00-0157 Grant 6/12/2008 2/23/2011 $364,133
Unfunded List Kennedy High 61/61796-00-0158 Grant 6/12/2008 4/27/2011 $1,717,559
Pending - On Workload Nystrom Elementary 61/61796-00-0159 Grant 10/15/2008 Pending $1,407,875
Pending - On Workload Chavez (Cesar E.) Elementary 61/61796-00-0160 Grant 10/15/2008 Pending $62,735
Pending - On Workload Portola Junior High 61/61796-00-0161 Grant 10/15/2008 Pending $858,514
Pending - On Workload Lovonya DeJean Middle 61/61796-00-0162 Grant 10/15/2008 Pending $49,969
Pending - On Workload El Sobrante Elementary 61/61796-00-0163 Grant 10/15/2008 Pending $2,978,015
Total $19,138,320
ERP Audit Process: Required Documentation
June 12, 2012
6
Division of the State Architect (DSA) Approved Plans and Specifications, if required, and any change orders.
For Replacement Projects (pursuant to Regulation Section 1859.323.1), LEAs must retain a cost comparison on file which must include all of the following: Estimate to Repair the system/component . Estimate to Replace the system/component with a Like Kind Material/System. For alternative building material/system replacement projects, the LEA must additionally retain
an Estimate to Replace the system/component with an alternative building material/system. All estimates must be as detailed as possible and no lump sum estimates will be accepted.
Furthermore, the estimates must have been prepared by qualified individuals or firms but are not required to be prepared by the same person(s).
Construction Contract(s) and supporting documentation [pursuant to Public Contract Code (PCC) Section 20111(b)] (if applicable).
Schedule of Values (if applicable). Cost comparison pursuant to Regulations Section 1859.323.1 (if applicable). Purchase Order(s) and/or Purchase Agreement(s) (if applicable). Architect Agreement(s) and Schedule of Fees (if applicable). Qualification Appraisal documents (pursuant to Government Code 4526). Copy of Vendor Invoices (if applicable). Copy of Warrant(s) or Payment Voucher(s) (if applicable). For Force Account Labor Projects [pursuant to PCC Section 20114(a)], the OPSC Force
Account Labor Worksheet or other documentation that contains the following information: Employee name(s). Number of hours each.
ERP Audit Process
June 12, 2012Presented by: Jack Schreder & Associates
7
District staff, SGI, and Schreder met in 2011 to develop a system for responding to ERP audits.
Schreder is currently in the process of collecting all required audit documentation from various sources (District, SGI, architects).
Schreder is preparing a digital and hard copy inventory of all ERP audit documentation for all ERP projects, by site.
Once completed, Schreder will provide both digital and hard copies to the District.
Questions?
Thank You.
June 12, 2012Presented by: Jack Schreder & Associates