Facilities Modernization ProgramFunded by Measure B
Project Report
April 19, 2010
![Page 2: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/2.jpg)
PROJECT PROGRESS REPORTCollege Center for the Arts
Project Team: Architect: John Sergio Fisher & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: C. Overaa & Co
Project Update:• The exterior siding, stucco and windows are 99% complete.• The interior of the building is 97% complete in segment "B" which is the facility offices and the rehearsal rooms. • The Black Box Theater and the Main Auditorium infrastructure elements are continuing and will be completed this month. • The final concrete walk ways and ramp around the building and the Amphitheater are 98% complete. • The total project is 95% complete.
Occupancy Fall Semester 2010
LAS POSITAS COLLEGEApril 19, 2010
![Page 3: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/3.jpg)
PROJECT PROGRESS REPORTChild Development Center
Project Team: Architect: Beverly Prior ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction Associates
Project Update:• Exterior plaster complete on all buildings. • Installation of sheetrock continues in building B and has started in building C.• Rough grading for the OLEs has begun.
Occupancy Spring 2011
LAS POSITAS COLLEGEApril 19, 2010
![Page 4: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/4.jpg)
PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)
Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction
Project Update:• Underground & electrical utilities are continuing.
Occupancy: 10/2010
LAS POSITAS COLLEGEApril 19, 2010
![Page 5: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/5.jpg)
PROJECT PROGRESS REPORTCollier Creek Storm Water Outfall
Project Team: Engineer of Record: SandisConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction
Project Update:• Storm Drain and Retaining wall installation is complete.• Backfill at retaining wall is on going.
Occupancy: 04/2010
LAS POSITAS COLLEGEApril 19, 2010
![Page 6: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/6.jpg)
PROJECT PROGRESS REPORTScience Building, Phase II
Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: TBD
Project Update:• Added space for 4 classrooms on second floor.• Site layout and floor plan finalized.• Projected submittal to DSA in March 2010.
Occupancy: Fall 2012
LAS POSITAS COLLEGEApril 19, 2010
![Page 7: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/7.jpg)
PROJECT PROGRESS REPORTStudent Services & Central Administration
Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: TBD
Project Update:• 60% design documents were submitted in April• DSA submittal planned for August 2010,• This project will participate in the new DSA Collaborative Process.
Occupancy: Fall 2012
LAS POSITAS COLLEGEApril 19, 2010
![Page 8: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.](https://reader034.fdocuments.in/reader034/viewer/2022052701/56649ec85503460f94bd526e/html5/thumbnails/8.jpg)
PROJECT PROGRESS REPORTCampus Boulevard Phase I-III
Project Team: Architect: RHAA Construction Manager: Parsons BrinckerhoffContractor: TBD
Project Update:• Design stopped to coordinate with SSA design concepts.
Occupancy: Fall 2011
LAS POSITAS COLLEGEApril 19, 2010