Facilities Modernization Program Funded by Measure B Project Report

6
Facilities Modernization Program Funded by Measure B Project Report March 19, 2012

description

Facilities Modernization Program Funded by Measure B Project Report. March 19, 2012. PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road). LAS POSITAS COLLEGE March 19, 2012. Project Team: Architect : WLC Architects / Carducci Landscape Architects - PowerPoint PPT Presentation

Transcript of Facilities Modernization Program Funded by Measure B Project Report

Page 1: Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization ProgramFunded by Measure B

Project Report

March 19, 2012

Page 2: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)

Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction

Project Update:• Project is complete.• DSA Closeout is in progress.

Occupancy: 04/2011

LAS POSITAS COLLEGEMarch 19, 2012

Page 3: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTScience Building, Phase II

Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc

Project Update:• Interior Casework, Lighting and Fume hoods being installed.• Exterior Painting is in progress. Interior Painting is Completed. • Electrical and Data installation and termination is continuing at first and second floors.• Flooring at 2nd floor classrooms completed.• Storefront installation and Glazing Completed.• Stair Treads installed.

Occupancy: 09/2012

LAS POSITAS COLLEGEMarch 19, 2012

Page 4: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTStudent Services & Central Administration

Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction

Project Update:• GFRC installation complete.• Storefront installation has started along with glazing.• Site fine grading is complete.• Building metal panels have to start within 2 weeks.• Sheetrock has started on one side of the walls.• Elevator installation to begin next week.• Roofing is complete.

Occupancy: Spring 2013

LAS POSITAS COLLEGEMarch 19, 2012

Page 5: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTCampus Boulevard Phase I-III

Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: TBD

Project Update:• 100% Design review completed, final design was Approved by DSA February 2012. • Project was Bid on March 13, 2012 and Low Bid Contractor will be Board Approved April 17, 2012

Design Re-Start: 04/2011DSA Permit Approval: 02/2012Construction Start: 05/2012Occupancy: TBD

LAS POSITAS COLLEGEMarch 19, 2012

Page 6: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTPhotovoltaic System Phase II

Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff

Project Update:• Fencing Completed.• Racking System and Array installation is completed.• Inverters and Transformer installed and completed. • New Switchgear tie in during Spring Break.

Operational: February 2012

LAS POSITAS COLLEGEMarch 19, 2012