Facilities Management Redesign
Transcript of Facilities Management Redesign
Appendix B
Facilities Management Redesign
Draft Commissioning Plan
Version 2.0
Facilities Management Redesign
Page 2 of 17
Document Set
: Commissioning Plan
Title : Facilities Management Redesign
File Name : FM Outline Commissioning Plan
Synopsis : This document sets out the justification for undertaking the redesign of the delivery of Facilities Management based on the estimated cost and benefits provided.
Current Issue: Status : Draft
Version
Number
: 2.0
Issue Date :
Author :
Approver : Signed :
Copied to :
Changes History:
Issue No.
Date Author Principal Changes
Facilities Management Redesign
Page 3 of 17
Table of Contents
1 INTRODUCTION ........................................................................................... 4
1.1 PURPOSE OF THIS DOCUMENT .................................................................... 4 1.2 SCOPE ..................................................................................................... 4
1.3 CHALLENGES ............................................................................................ 7
2 SUMMARY ..................................................................................................... 8
3 BENEFITS EXPECTED .................................................................................... 8
4 OPTIONS ...................................................................................................... 9
5 COSTS AND TIMESCALES ............................................................................ 10
6 BENEFITS REALISATION ............................................................................ 11
7 RISKS ......................................................................................................... 11
8 DEPENDENCIES .......................................................................................... 12
APPENDIX A. OTHER LOCAL AQUTHORITY DELIVERY MODELS ......................... 13
APPENDIX B. CURRENT ORGANISATION STRUCTURE OF FM ............................ 15
APPENDIX C. TIMELINE .................................................................................. 156
APPENDIX D. PROPOSED MANAGEMENT STRUCTURE ..................................... 157
Facilities Management Redesign
Page 4 of 17
1 Introduction
1.1 Purpose of Document
The purpose of this document is to provide the justification for undertaking a
redesign of Facilities Management and associated services based on the options appraisal and the anticipated financial and service improvement benefits to be
gained.
1.2 Scope
Current Service There is no simple, single definition of the role of FM as it varies across
organisations according to their specific needs and culture. At WSCC the FM Team have adopted an essentially pragmatic working definition which can be summarised as ‘ensuring a working environment in its buildings portfolio
which enables the council (and its partners) to deliver effective and responsive services’. This can be amplified further in terms of a hierarchy of priorities to:-
Ensure statutory compliance
Ensure buildings are clean, safe & secure
Promote a welcoming & comfortable space for staff, clients & visitors
Promote a positive image of the council through the interaction of people with the council’s buildings
The FM Team place a specific priority in their work for services with vulnerable clients; both adults and children, as in these service areas the
interaction of people with the physical space and associated services is important. As FM is an integrative discipline involving many disparate
activities there is no simple measure of performance. The FM Team view the critical success factors for their service as:-
Minimising risks to WSCC from breaches of statutory compliance – as these are a potential liability to the council both in terms of cost and
reputation
Providing a ‘comfortable’ environment for staff, clients and users – measured both formally and informally through building user feedback.
The current service delivery model for FM could be described as ‘a mixed economy with a strong informed client role with use of external contracts where
these represent value for money’. The emphasis of the FM Team is on policy, specification, management and monitoring; but with light touch monitoring
supplemented by building users’ feedback on service quality and incipient issues. An area based approach has been adopted with 5 areas. In each area a
comprehensive, integrated service is provided through a dedicated Lead Building Surveyor, Engineer & Facilities Manager. These roles are pivotal in the service
providing the expertise and capacity across the broad range of FM activities and strong ‘on-the-ground’ customer focus through to building users to understand service needs, quality, and responsiveness and to help to identify any emerging
issues. The area teams make use of the council’s office hubs in the respective
Facilities Management Redesign
Page 5 of 17
areas as well as working flexibility. The Area Facilities Managers (AFMs) undertake a multiplicity of roles and there is also an intention for them to act in
a capacity to resolve problems and undertake small, immediate work jobs as appropriate.
The council has adopted a ‘Corporate Landlord Model’ with centralised budgets for premises related expenditure managed through the FM Team. The FM service
applies generally to all council buildings but in some specific instances there are differing arrangements for schools because of their degree of autonomy. The Fire
Service retains a small FM capacity and some of their building management arrangements are not within the scope of the WSCC FM Team.
The broad ‘direction of travel’ for the FM service is to move towards common standards for major areas of activities which schools can ‘op-in to’.
There is no single definition of FM and no specific model of its scope and activities. FM activities are based on historic ways of doing things,
organisational culture and pragmatic experience of what works well. FM does tend to have a primarily operational focus there is also an important
strategic element to it as FM needs to be consistent to, and supportive of, wider council objectives.
Strategic Operational
FM Strategy &
Support
Hard FM Soft FM Additional FM
Support
Member & Senior
Officer Liaison Condition Surveys Cleaning Space Planning
Policy Development
Building Maintenance
Security Move Management
Statutory Compliance
Governance
M & E Services Waste Disposal
& Recycling
Office Furniture
Contract & Performance
Management
Statutory Compliance
Delivery
Reception Porters
FM Information
Project
Management
Caretaking Events
FM ‘Help Desk’ Carbon Management
Utilities Management
FM Training
PA & Admin Support
Minor Improvements
Catering
Property Review Health & Safety
Suitability Assessments
Grounds Maintenance
Budgets Current budgeted cost of the Service and Staffing Levels for 2013 / 14
Current FTE’s 80 + 2 apprentices
Facilities Management Redesign
Page 6 of 17
Cost of internal staff (salaries) £2.0m as of 2015 (Currently £2.4m)
Hard FM – maintenance £2.64m Soft FM £2.25m
Hard FM –Capital £3.2m Soft FM – Capital £170k
Total Cost of the Service £10.26m
(excluding any internal overheads) Note: the above does not include spend conducted by schools e.g. school meals
service
Note: the anticipated cost savings will be derived from the revenue element of budgets (less retained staff costs). The revenue costs (less retained staff) are currently circa £6.3m.
Service Level Agreement Income
The service currently receives £813k (+£700k from catering services which will reduce following the new outsourced Special Schools Catering contract) per
annum as income from Service Level Agreement (SLA) income from schools. This is diminishing (c £1.2m 2012/13) due to the number of schools that have made their own arrangements or have become academies and changes to the
services that are offered. It is anticipated that the SLA income will continue to fall over future years that may result in the need for further staff reductions to
reflect demand.
Scope of the project This project has been looking at the way in which facilities management services
are provided to the properties of the council with a view to provide recommendations to redesign the current delivery model to generate savings and service improvements. The review has also looked at how other local
authorities provide these services (see appendix A)
The services under review included maintenance and repair (Hard FM) and building support services such as cleaning and catering (Soft FM). The redesign project may include subject to further stakeholder engagement:
FM Helpdesk Catering and Vending
Grounds Maintenance (hard and soft landscape) Logistics e.g. portering, Waste collection and recycling
Cleaning (including “non office” antique) Pest Control
Security Building Reactive and planned maintenance M&E Reactive and planned maintenance (inc backup power systems)
Minor works Internal & External decorating
Locksmiths
Facilities Management Redesign
Page 7 of 17
Signage Lifts & Hoists
PAT testing Car Park management
Alarms Door entry systems Statuary Testing and sampling
Option – Move Management Option - Furniture Management
Option – Transport (pool cars and management of fleet vehicles) Option - Document archiving and storage
Capital works and Building Professional Services have not been included in the review as the market to provide Hard and Soft FM along with Capital Works and
Professional Services is immature with very limited providers able to offer all of these services.
Future state
It is anticipated that the redesign will result in a budget circa £500k for the retained team. See Appendix D for proposed staff structure.
1.3 Challenges
The current mix of in house and multiple contractors leads to a fragmented
approach that does not lend itself to ensuring the maximum economies of scale are being achieved.
The quality of available data can have an impact on optimising service delivery and strategic planning. There could also be a risk associated with being able to
demonstrate statutory compliance. The quality of data can also impact on the contract costs if accurate data is not available as contractors will build in
additional costs to mitigate any perceived risks. With all but one of the options explored, current end dates of contracts may be a
challenge as this could result in some services transferring as and when the current contracts come to an end. In more resent procurements this has been
planned for with the addition of no-fault termination clauses or no guaranteed uptake / expenditure.
As with any change within an organisation it brings with it uncertainty and apprehension from members of staff and as such early consultation and buy in
may be a critical success factor in taking up any of the options moving forward. Linked to this is the possible loss of key staff as they choose to leave rather than transfer. Redundancy liabilities could also be a risk.
Under a new operating model support to schools and other non-council budget
holders will be treated as a sales opportunity by the service provider as the council provides its core function under the intention to be a commissioning council. This could have a political dynamic if the perception is that the council is
not providing suitable support to services that are independent budget holders but are integral to the totality of services provided by the council e.g. education.
Facilities Management Redesign
Page 8 of 17
Future proofing the solution will be a challenge as the contract will be deemed to
be long term in order to allow the service provider to invest in the delivery of the service. The current unknowns are the future size and scope of assets, this will
include ownership, landlord responsibilities etc. The contract will reflect these unknowns in order to take into account the impact of change.
It is important the council has the appropriate skills to manage the preferred option as the delivery of the service will have a direct impact on the council and
its customers. There is a disconnect between the property review process undertaken by the
Capital & Infrastructure Team which identifies whether buildings should be retained or released by the council and activities undertaken by the FM Team.
This may mean that there is risk of maintenance or improvement spend being misdirected on buildings likely to be no longer required by the council
The number of schools that buy back services (for example cleaning contract management) is reducing as more schools opted to carry out these functions
themselves or purchase from elsewhere. The effect this may have on the service would be an underutilisation of staff as demand reduces.
2 Summary
The have been improvements in the delivery of the service (for example the
establishment local hubs), however, the scope for further improvement may be limited without effecting service delivery. Furthermore the current mix of in
house and multiple contractors leads to a fragmented approach that does not lend itself to ensuring the maximum economies of scale are being achieved.
The procurement of a single service provider across all hard and soft facilities management activities is deemed to be the best option to take the service
forward that will achieve cost savings and service improvements.
3 Benefits Expected
Savings - It is anticipated that the implementation of the preferred option will
result in annual savings circa 10% – 15%. The level of savings may be dependent on the expiry date of existing contracts and the time required
procuring and implementing the new operating model. Link to Corporate Vision (Support Economy and Efficient Council) – The new
operating model and supporting contract will be structured in such a way as to allow the council to have influence and insight into the selection of the supply
chain required to deliver the service. In addition, the operating model will facilitate the improved utilisation of staff via for example the use of work
planning ITS systems. With the selection of a service provider that will be in the top tier within the FM
sector, we will be able to access to specialist knowledge and training for our staff
Facilities Management Redesign
Page 9 of 17
(TUPE’d and retained) and have access to latest industry innovation that will improve efficiency and reduce costs.
We will also be able to have access to investment in service delivery processes /
systems working in collaboration with the service provider. This could result in savings and efficiencies and / or income generation and profit share
Operationally we will have a clear definition of responsibilities for each building between landlord and tenant to ensure that the work carried out is the liability of
the council. This will also include improved management of repairs under warrantee / defect liability period.
By removing the day to day operational issues to a service provider the retained management will be able to focus on improved strategic planning and ensuring
statutory compliance The current operating model has very few measures of performance and the
information collated does not always lead to continuous improvement. The new operating model will have a suit of measures that will facilitate continuous
improvement and provide Management Information for example servicing programme adherence and statutory compliance.
4 Options
Option Pros Conns
1 As is Nil cost to implement. Current service standards accepted by end users.
No big impact on staff (any changes will be dept by dept)
Restricted opportunities for savings,3rd party investment, service
improvements and income generation
2 In Source Could be seen as reducing the risk of continuity of
service
Does not fit with council objective of being
commissioner. Cost of service could be higher.
Restricted opportunities for savings,3rd party
investment, service improvements and income generation
3 Hard and Soft *TFM geographic
split
Allows for benchmarking between service providers.
Reduces the risk of continuity of service as one service provider could
operate in another’s area.
Reduces savings opportunities.
Increases contract management costs Possible duplication of
effort Possible multiple ITS back
office systems to interface with
Facilities Management Redesign
Page 10 of 17
4 Hard and Soft
TFM
Maximum savings,
efficiencies and income opportunities. Mature market.
Reduced contract management costs.
Reliant on one service
provider
5 Joint Venture The likelihood of staff numbers reducing is limited.
Could rely on finding other public sector work to be sustainable.
Reduced savings opportunities Management costs
increased
6 TFM + Capital and
Professional Services
Link between capital and
maintenance improved - should result in a reduction in the cost of ownership of
assets
Immature Market.
Time to implement may reduce short term savings opportunities.
Cost to implement (may need external consultants)
7 Staff Mutual Retained expertise and site knowledge. Current
service standards accepted by end user. Staff may feel that they
are more involved in the decision making process
Restricted opportunities for savings,3rd party
investment, service improvements and income generation, cost to
implement remains with the council ( e.g. restructure), risks retained
in part by the council
*TFM – Total Facilities Management
The preferred option is to procure a Hard and Soft TFM service provider
as this option will give the greatest overall benefits to the council.
5 Costs and Timescales
Officers time (Procurement, Legal, HR, Project Management and FM) -The cost of
implementation and the on-going management of the service should be limited to officers’ time. It is not anticipated that any investment will be required to
facilitate the change in the FM operating model.
Redundancy Costs – Redundancy costs may need to be factored into the cost of this project, however it is felt that these costs are likely to arise no matter what option is taken forward with regards the FM service, however the preferred
option would seek to ensure that the risk of redundancy payments are passed to the provider and to deliver savings net of the cost of any redundancies.
NEC and contract management training for retained staff – A training programme may be required to support and up-skill the retained team to best
enable them to manage a large single service provider rather than multiple smaller contractors and spot purchases.
Facilities Management Redesign
Page 11 of 17
Appendix C highlights the anticipated timelines to procure and implement the new FM operating model
6 Benefits Realisation
During the project initiation process and throughout the procurement process data will be collected and verified that will establish clear baselines on the
current cost and levels of service. The baselines will be established for all service elements both retained and outsourced.
The contract implementation process will include due diligence of the baseline data in collaboration with the service provider. The outcome of the process will
be the agreement of the baselines. The measures used will include:
Demand Capability
Capacity Quality Cost
Customer Satisfaction
The outturn information will be used to facilitate continuous improvement. The improvements will be collated into a benefits realisation tracker that will be able to report on:
Cashable savings / income received, Non Cashable savings / Service improvements
Cost avoidance
7 Risks
TUPE / Redundancy and pension liabilities – As with any potential outsource the biggest risk is usually linked to the transfer of staff and any redundancies. This
can be mitigated with lessons learnt from other resent outsource projects, including the understanding of the issues within the evaluation of potential
bidders and early engagement at preferred bidder stage to ensure communication and consultation are seamless
Statutory Compliance – the risk associated with statutory compliance has reduced recently with the adoption of an asset database however suitable audits
by technical staff will be required to ensure servicing programmes are agreed and adhered to.
Possible cross over with other contracts e.g. SSO – There are possible areas of crossover with other contracts. Care will be needed during the redesign of the
operating model to ensure no duplication of effort, that all elements of the services are covered and that the links to other contracts are clearly understood
by all. Perceived loss of control and reactiveness – The current service can be very
reactive to requests (e.g. members), this has a hidden cost with regards planned
Facilities Management Redesign
Page 12 of 17
utilisation verses reactive work. The new operating model should be able to be flexible to meet the demands of the customers but in the knowledge that in
some cases this may have an impact on efficiency and therefore costs.
Current Skills of FM team (manage 1 large contractor rather than lots of smaller contractors) – The move from multiple small contracts and spot purchases to a single supplier will be a massive cultural change for the retained FM team. As
discussed above, this can be mitigated by suitable training and support. This will also be mitigated by the reduction in complexity due to fewer lines of control and
governance Link to Asset Reduction programme – The size and shape of the WSCC estate is
likely to be in a state of flux especially for the next few years. The contract will therefore have the provision for additions and deletions from the asset register
and a clear cost model that will determine the effect on the contract price Externalisation of expertise – Although there will be a retained team to manage
the service provider at an operational level there could be a perception of loss of expertise. Ownership of data, co-location, collaborative working will all assist
with mitigating any perceived risk
Perceived Impact on local SME’s – At this stage we cannot predetermine the delivery model of any future service provider. The delivery model tends to be a mix of directly employed staff and specialist sub-contractors. The impact on
SME’s can be reduced by including within the contract the same ethos as WSCC with regards the selection and use of local SME’s.
8 Dependencies
Typical dependencies of a project such as this will include:
Current Outsource (SSO) e.g. Helpdesk and Health & Safety On-going projects and programmes e.g. Asset Reduction programme
Current contracts for the supply of FM services – end dates, extension provision and termination clauses.
Capital programme and planning – linked to the total cost of ownership of an asset, standardisation of key building elements and repair under defect liability period / warrantee.
Facilities Management Redesign
Page 13 of 17
Appendix A. Other Local Authorities Deliver Models
Kent County Council Reason for change:-
Statutory compliance – Current management and information seen as a risk to the Authority
Asset Register - gaps in information, long term planning is an opportunity
to improve Fragmented approach to letting of contracts and contract management
Strategy 3 regions Central, East and West.
Different contractor for each area allowing mitigation of risk, continuity of service etc.
Approx. £20m per annum total
First Kent (bed in) then allow others e.g. Boroughs and Districts to join the contract should they wish to do so
PQQ – contractors indicate preferred region in descending order, max of 12 contractors taken forward to the tender stage – 4 bidding for each area
Excludes Capital and professional services Scope very open to add additional areas at a later date Lump sum + Schedule of Rates for unknowns
Competitive Dialogue as little internal experience of TFM – seen as a learning opportunity and ability to innovate
Bespoke contract (similar to NEC TSC) via external legal advice 10%-20% anticipated savings but acknowledge that if a single provider
was selected for the whole county savings would be nearer to 20%
Medway Council
Options considered: Outsource, Traditional FM, Traditional FM plus wider
scope of services e.g. archiving , Joint Venture (JV) JV selected as seen to offer the best fit of savings / income generation
that will protect the employment of current staff The intention is that income will be generated via education and health
partners that will supplement the increased utilisation of current staff
Norse (ex Norfolk CC) was selected as the partner provider to the JV who have currently 27 JV’s with local authorities in the UK
JV has a “pick list” of selectable items Option for SE7 to use this arrangement but it would appear that no EU
procurement was undertaken to select the JV partner.
Savings estimate of 5% year one, 10% year two. Mix of directly employed and SME’s (60/40) Intensive internal visits including finance to establish data room
Note: can add whatever you want to JV via a variation order as seen as public to public – Teckal case,
Not constrained by EU regs therefore greater freedom to include political objectives e.g. local employment e.g. 3 apprentices year 1, then up to 10
80% ownership Norse 20% Medway but profit from income split 50/50 Hampshire County Council
Facilities Management Redesign
Page 14 of 17
Market consultation
A limited market consultation has been carried out, should this commissioning plan be accepted a more detailed market consultation process will be undertaken
as part of the commissioning cycle. The market consultation sort to understand the typical scope of services that
would be included in a Total Facilities Management contract. The results have been reflected in the draft scope of services as at 1.2 above. In addition the
market consultation confirms the limited number of companies in the market of able to offer a combined TFM and Construction and Professional Services offer.
Facilities Management Redesign
Page 15 of 17
Appendix B FM Team Structure Chart
Facilities Management Redesign
Page 16 of 17
Appendix C – Procurement Timeline (draft)
Facilities Management Redesign
Page 17 of 17
Appendix D Proposed Future internal Structure