Harlan High School
Facilities Construction
NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION
March 2017
2014 BOND PROJECTS
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL)
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 Construction Status: 93% Complete Project Scope – New 2800 Student High School
Site grading, utilities and landscaping in progress. Interior CMU walls, drywall framing, electrical, plumbing, and HVAC installation in progress. Window installation, interior painting, exterior brick veneer and roofing in progress. Concrete drives and parking areas in progress. Punch in progress.
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Feb. 20, 2017)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (February 28, 2017)
KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY)
Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – Guido Construction GMP - $24,640,000.00 Construction Period – March 7, 2016 – May 26, 2017 Construction Status: 60% Complete Project Scope – New 800 Student Elementary School
Masonry, brick, MEP ductwork and roofing are ongoing.
KALLISON ELEMENTARY SCHOOL Front Entrance
KALLISON ELEMENTARY SCHOOL Aerial (February 24, 2017)
KALLISON ELEMENTARY SCHOOL Aerial (February 24, 2017)
KALLISON ELEMENTARY SCHOOL (February 28, 2017)
KALLISON ELEMENTARY SCHOOL (February 28, 2017)
KALLISON ELEMENTARY SCHOOL (March 1, 2017)
KALLISON ELEMENTARY SCHOOL (March 1, 2017)
GROSENBACHER AREA ELEMENTARY (Prototype of Boldt ES and Cole ES)
Architect – Noonan Rittiman Project Architect – John Rittiman NISD Project Manager – Tom Curiel Contractor – DL Bandy Construction Amount - $22,465,000 Tentative Construction Period – March 2017 – May 2018 Project Scope – New 800 Student Elementary School (Prototype of Boldt ES and Coles ES)
General Contractor approved at February Board. Contract negotiations ongoing.
ADDITIONS AND RENOVATIONS
PROJECTS IN PROGRESS
GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – McGoldrick Construction Co. Construction Amount - $3,750,000.00 Construction Period – June 2016 – June 2017 Construction Status: 50% Complete Project Scope – New Administration Building
Installing roof, interior walls and masonry, HVAC, plumbing and electrical.
GLENOAKS ELEMENTARY (Rendering of Front Elevation)
GLENOAKS ELEMENTARY Administration Upgrades (February 2017)
GLENOAKS ELEMENTARY Administration Upgrades (February 2017)
GLENOAKS ELEMENTARY Administration Upgrades (February 28, 2017)
NORTHSIDE ACTIVITY CENTER RENOVATIONS
Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – O’Haver Contractors Co. Construction Amount - $5,319,485.00 Tentative Construction Period – February 2017 – January 2018 Project Scope – Addition/Renovation
Notice to Proceed issued March 3, 2017. Contractor is mobilizing on site.
PAUL TAYLOR FIELD HOUSE RENOVATIONS
Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – Stoddard Construction Management, Inc. Construction Amount - $3,400,000.00 Tentative Construction Period – February 2017 – August 2017 Project Scope – ADA Interior/Exterior Renovations Notice to Proceed issued. Site Mobilization and Demolition in Progress.
PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017)
PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017)
PAUL TAYLOR FIELD HOUSE RENOVATIONS (March 1, 2017)
2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – CGC General Contractors Construction Amount - $1,293,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – New Security Lobby for (9) Elementary Schools:
Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES General Contractor approved at January Board Meeting. Contract negotiations ongoing.
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2017
HOLMES HS FINE ARTS - AUDITORIUM
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – Bartlett Cocke Construction Budget - $27,000,000.00 Tentative Construction Period – June 2017 – December 2018 Project Scope – Fine Arts Building Replacement
Site and Demolition Construction Documents issued February 28, 2017. Portables relocation complete. Portable renovation in progress. MDF relocation in progress.
BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $4,040,000.00 Tentative Construction Period – June 2017 – May 2018 Project Scope – Administration Upgrades, Bus/Student Walkway Canopy
Modifications Construction Documents in progress.
COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work
Architect – Huckabee Architects Project Architect – Jeff Rodriquez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $2,000,000.00 Tentative Construction Period – June 2017 – October 2017 Project Scope – Window Upgrades and ADA Work Proposal Opening February 21, 2017. Contractor submitted for March Board Approval.
GLASS ELEMENTARY Window Upgrades / ADA Work
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,500,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Window Upgrades and ADA Work Schematic Design and Master Plan in progress.
GLENOAKS ELEMENTARY - Window Upgrades / ADA Work
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $1,100,000.00 Tentative Construction Period – June 2017 – December 2017 Project Scope – Window Upgrades and ADA Work
Schematic Design approved by Board in January. Construction Documents issued March 6, 2017. Proposals to be received on March 29, 2017.
GLENOAKS ELEMENTARY Library and Classroom Building
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $10,000,000.00 Tentative Construction Period – June 2018 – December 2018 Project Scope – Library and Classroom Building
Schematic Design in progress.
GLENN ELEMENTARY School Building Replacements / Security Lobby
Architect – LPA Project Architect – Mark Oppelt / Lowell Tacker NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $4,800,000.00 Tentative Construction Period – June 2017 – August 2018 Project Scope – Replacement of Buildings Proposal Documents issued February 13, 2017. Proposals to be received March 23, 2017.
KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition
Architect – Pfluger Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $2,200,000.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library Schematic Design approved by Board October 25, 2016. Proposal Opening February 28, 2017. Contractor submitted for March Board Approval.
TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $2,200,000.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library Schematic Design approved by Board October 25, 2016. Proposal Documents issued February 20, 2017. Proposal opening March 22, 2017.
2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS
Architect – Chesney Morales Project Architect – Richard Morales NISD Project Manager – James Evans Contractor – TBD Construction Budget – $117,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Door Hardware for Accessibility
Construction Documents in progress.
2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary
Architect – CWS Architect Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $230,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring Proposal Documents issued February 27, 2017. Proposal opening March 22, 2017.
2017 SUMMER FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS
Architect – Huckabee Architects Project Architect – Jeff Rodriguez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $325,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring Proposals received February 15, 2017. Contractor submitted for March Board Approval.
NEFF MS COMPETITION GYM FLOORING AND BLEACHERS
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $200,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring and Bleachers Proposals Opening March 8, 2017. Contractor submitted for March Board Approval.
2016 GROWTH & IMPROVEMENT
CHILD NUTRITION WAREHOUSE Warehouse Renovation
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Henry Acosta Contractor – Workman Commercial Contract Amount - $5,726,500.00 Construction Period – July 2016 – January 2017 Construction Status: 89% Complete Project Scope – Warehouse Renovation
Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings.
Demo complete, rough-ins in progress. Walk in cooler/freezer floor complete. Office area drywall complete, tape & float (finishes in progress),
new switch gear being installed, new CPS transformer on its way. Walk-in cooler/freezers, walls, racks and ceilings being installed. Condensers set.
CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (March 3, 2017)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (March 3, 2017)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (Feb 16, 2017)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (Feb 16, 2017)
2017 GROWTH & IMPROVEMENT
2017 ATHLETIC AREAS UPGRADES Hobby MS, Pease MS, and Taft HS
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $920,000.00 Construction Period – June 2017 – August 2017 Construction Status: 0% Complete Project Scope – Installation of Athletic Storage Units and Interior
Renovations. Proposals received February 7, 2017. Contractor submitted for March Board Approval.
JORDAN MIDDLE SCHOOL Interior Painting Project
Architect – Noonan Rittimann Project Architect – Noonan Rittimann NISD Project Manager – James Evans Contractor – TBD Contract Amount – $325,000.00 Construction Period – June 2017 – August 2017 Construction Status: 0% Complete Project Scope – Paint Interior of the School.
Construction Documents issued for IDQ March 6, 2017.
ATHLETIC STORAGE BUILDING AT TAFT HS AND JOHN JAY HS
Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – TBD Contract Amount – $90,000.00 Construction Period – June 2017 – July 2017 Construction Status: 0% Complete Project Scope – Installation of Athletic Storage Units. Construction Documents to be issued March 8, 2017.
ROOFING PROJECTS
BOONE ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – Samuel Dean Sheet Metal Inc. Contract Amount – $336,973.00 Construction Period – June – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
CABLE ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Austech Engineering Contractor – Cram Roofing Contract Amount – $199,550.00 Construction Period – June 2016 – August 2016 Construction Status: Complete Project Scope – Roof Repairs & Waterproofing
Project Closeout Complete.
HOWSMAN ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – Beldon Contract Amount – $692,986.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
LEWIS ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Austech Contractor – Empire Roofing Contract Amount – $190,151.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
LINTON ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – ATC Contractors, Inc. Contract Amount – $208,500.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
MAY ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Port Enterprise Contract Amount – $1,678,997.00 Construction Period – June 2016 – October 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project closeout in progress.
TAFT HIGH SCHOOL ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Port Enterprise Contract Amount – $1,632,113.00 Construction Period – June 2016 – December 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project closeout in progress.
VILLARREAL ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Austech Contractor – Samuel Dean Sheet Metal Inc. Construction Budget – $97,090.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
2016 HAIL DAMAGE
ROOFING PROJECTS
BEARD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $566,480.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design. Bids Received. Approved at February Board.
CARNAHAN ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $2,125,200.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement
Project in Design. Bids Received. Approved at February Board.
CLARK HIGH SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $2,490,800.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement
Project in Design. Bids Received. Approved at February Board.
SOUTH TRANSPORTATION HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Contract Amount – $261,920.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement
Project in Design. Submitted for March Board Approval.
STEVENSON MIDDLE SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Contract Amount – $1,904,450.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design. Approved at February Board.
CARLOS COON ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Contract Amount – $1,409,870.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design. Submitted for March Board Approval.
ELROD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Contract Amount – $784,880.00 Construction Period – June 2017– December 2017 Project Scope – Roof Restoration
Project in Design. Bids Received. Approved at February Board.
FERNANDEZ ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Contract Amount – $1,102,400.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design. Submitted for March Board Approval.