F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

20
f Status and Plans for SRF Facility Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007

Transcript of F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

Page 1: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

f

Status and Plans for SRF FacilityStatus and Plans for SRF Facility

Sergei Nagaitsev

May 18, 2007

Page 2: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 2

f Setting the ScaleSetting the Scale

For ILC: produce 4 to 6 cryomodules in the next 4 years ~ 50 cavities used; additional needed for development and testing

International (ILC/GDE) coordination: S0 ‘tight loop’ task force:

• Process and re-process the inside surface of a limited number of cavities, repeatedly, testing each time… (~100 procedures/year for several years)

• Answers due 08, 09 guidance for a final gradient recommendation

S1 ‘cryomodule’ task force :• 31.5 MV/m OPERATING cryomodule

S2 ‘string test’ task force :• Put it all together• Run ILC-like beam• Various critical tasks

Page 3: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 3

f SCRF Cavity Gradient RDSCRF Cavity Gradient RD

“S0 / S1” GDE charge: Provide the information needed

to make a gradient decision for TDR. Challenge: Cavity surface processing

variability (yield) Secondary: the rest of the fabrication effort

• From the mine to the cryomodule (‘production-like RD’)

Focused charge, well defined deliverable, broad base, expensive task with excellent cost / benefit

US labs are heavily involved but expertise is scattered; Fermilab is playing a “catch-up” game.

Page 4: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 4

f String test (S2)String test (S2)

Charge: Recommend a string test strategy;

Expensive Referendum on the SRF readiness for the ILC Many duplication / competition /

standardization issues between DESY, KEK, FNAL

Cross threaded with mass-production issues, ‘regional interest’ and lab ambitions

R or D? What is the balance?

Page 5: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 5

f

Surface Processing

Cavity Fabrication

Vertical Testing

He Vessel, couplers,

tuner

HPR or reprocess

Horizontal Testing

Cold String Assembly

Pass!

Pass!

Fail!

Fail!

Cavity/CM process and TestingCavity/CM process and Testing

Plan… Develop in labs then transfer technology to industry

Page 6: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 6

f SCRF InfrastructureSCRF Infrastructure

This process requires extensive infrastructure Bare cavities

Fabrication facilities (Electron beam welder, QC, etc) Surface treatment facilities BCP & Electro-polish facilities (EP) Ultra clean H20 & High Pressure Rinse systems Vertical Test facilities ( Cryogenics + low power RF)

Cavity Dressing Facilities ( cryostat, tuner, coupler) Class 10/100 clean room Horizontal Test System (cryogenics and pulsed RF power)

String Assembly Facilities Large class 10/100 clean rooms, Large fixtures

Cryo-module test facilities Cryogenics, pulsed RF power, LLRF, controls, shielding, etc. Beam tests electron source (RF unit test facility at NML)

Page 7: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 7

f Materials & SRF R&D infrastructureMaterials & SRF R&D infrastructure

Quality assurance: Characterization of Nb sheet from vendors Surface properties: oxide layer, inclusions, and scratches (eddy

scanner) Measure material composition (RRR, chemical composition, etc) Measure Nb mechanical properties ( ie crystal structure)

Surface processing studies Electropolish and BCP process studies (single cell programs) Surface contamination studies

Infrastructure: (ANL, TJNL, FNAL, Cornell, MSU, etc…) Labs for handling HF and processing and test of single cells Materials equipment ( RRR measurement, INSTRON, EM microscope,

SIMS.

Weld studies ( e.g. crystal structure, contamination, TIG welding) ILC is helping to upgrade existing national capabilities but much of

this is funded by other sources

Page 8: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 8

fCavity Fabrication

By Industry

Cavity Dressing &Horizontal Testing

@ Fermilab

SurfaceProcessing @ Cornell

SurfaceProcessing

@ Jlab

SurfaceProcessing @ ANL/FNAL

Vertical Testing @ Cornell

Vertical Testing @ Jlab

Vertical Testing @ FNAL

Exists

Developing

U.S. Cavity Processing & TestU.S. Cavity Processing & Test

Page 9: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 9

f FNAL/ANL collaboration Goal: A new joint surface processing facility Clean rooms, BCP, and state of the art EP New Chemistry and Clean rooms operational

New Clean Rooms Controls and HF scrubber

Surface Processing @ ANLSurface Processing @ ANL

Page 10: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 10

f

•World knowledge to design new EP system

•Design Review 2/12/07, Under construction

•Plan: Commission late FY07

•Capacity ~ 45 EP cycles per year

•Plan for new HPR system by late 07

New Electropolish facility @ANL New Electropolish facility @ANL

Page 11: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 11

f Fermilab SCRF MAPFermilab SCRF MAP

New Muon Lab:RF unit test facility

MDB:CCII HTSHINS

IB1: VTS

WH

CAF:MP9ICB

IARC

Page 12: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 12

f A new Vertical Test Stand is under Construction at

Fermilab (IB1) Existing 1.8 K Cryogenic plant 125 W at 2 K (250 W intermittent test) RF system based on TJNL VTS RF/DAQ system Current test Stand will be capable of testing ~50 Cavities/yr Commissioning started (cryo), reached 2K, next step: single cavity test Evolutionary upgrades: Thermometry for 9-cells, 2 cavities at a time, 2

top plates, Cryo upgrades: increased pumping capability & purifiers, up to two additional VTS cryostats

Ultimate capacity ~ 264 cavity tests/yr

VTS Cryostat:IB1 New RF &

Control Room

Movable shielding for up to 3 pits

Vertical Test@FNALVertical Test@FNAL

Page 13: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 13

f HTS @ MDB HTS @ MDB

Cryostat complete: ~DESY design but 2 Doors improve access

Extensive MDB cryo modifications [email protected] K 300 KW klystron & modulator is in place and tested Cooled down w/o cavity, 1st cavity test in May

1.3 GHz Cavity in

HTS Cryostat

HTS CryostatInstalled at MDB

DESY C22 VTS @ 17 MV/M

Page 14: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 14

f MDB InfrastructureMDB Infrastructure

RF Power for HTS

Cryogenics transfer lines in MDB

Large Vacuum Pump for 2K

RF Power for HTS

Capture Cavity-II

Page 15: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 15

f CAF: MP9CAF: MP9

Infrastructure: String Assembly Fixtures Clean Vacuum & Leak Check Ultra Pure Gas and Water Ultrasonic Cleaner Cold Mass Assembly Fixture

String Assembly Fixture

1st Cavity being prepared for HTS

MP9 Clean Roomand tooling built in FY06

UltrasonicCleaner

Page 16: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 16

f CAF: ICB Final AssemblyCAF: ICB Final Assembly

Industrial Center Building (ICB) 18,000 ft2

Alignment, Instrumentation, coupler installation, etc Large Vacuum Vessel Assembly Fixture

CAF Goal: Produce R&D quantity Cryomodules (~1/month) Goal: Use infrastructure for tech transfer to industry Will Assemble 1st cryomodule (DESY kit) early fall 07 Also 3.9 GHz!

Cryomodule has1200 parts !

Parts for copy of DESY Assembly fixtureICB cleaned!

Page 17: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 17

f ILCTA_NML@FNALILCTA_NML@FNAL

NML Building

CCM removal: Sep 06

NML: Apr 071st of 2 refrigerators each 60 [email protected]

Page 18: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 18

f Two CMs with beamTwo CMs with beam

The existing building is perfect for testing two cryomodules with ILC-like beam. The building can be extended to fit 3 cryomodules.

Page 19: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 19

f ILC RF unit with BeamILC RF unit with Beam

Construct a new building ~50m away from NML Connect by ILC-like tunnel (2nd RF unit) Upgrade RF system to 10 MW klystron Add larger 300W @ 1.8 K refrigerator New Bldg houses diagnostics, dump, refrigerator

Page 20: F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.

S. Nagaitsev 20

f SummarySummary

Cavities & Cryomodules are cost drivers for ILC SRF R&D requires extensive infrastructure The U.S. is making good use of existing SRF

assets as well as new ANL/FNAL infrastructure to rapidly expand U.S. SRF R&D capabilities

Infrastructure is needed to support: GDE S0, S1, S2, S4 goals U.S. Industrialization of SRF technology

We have made a lot of progress in FY06-07 We have ambitious plans for FY08 and beyond Effort is resource limited