F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
-
Upload
kristopher-lester -
Category
Documents
-
view
215 -
download
1
Transcript of F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
f
Status and Plans for SRF FacilityStatus and Plans for SRF Facility
Sergei Nagaitsev
May 18, 2007
S. Nagaitsev 2
f Setting the ScaleSetting the Scale
For ILC: produce 4 to 6 cryomodules in the next 4 years ~ 50 cavities used; additional needed for development and testing
International (ILC/GDE) coordination: S0 ‘tight loop’ task force:
• Process and re-process the inside surface of a limited number of cavities, repeatedly, testing each time… (~100 procedures/year for several years)
• Answers due 08, 09 guidance for a final gradient recommendation
S1 ‘cryomodule’ task force :• 31.5 MV/m OPERATING cryomodule
S2 ‘string test’ task force :• Put it all together• Run ILC-like beam• Various critical tasks
S. Nagaitsev 3
f SCRF Cavity Gradient RDSCRF Cavity Gradient RD
“S0 / S1” GDE charge: Provide the information needed
to make a gradient decision for TDR. Challenge: Cavity surface processing
variability (yield) Secondary: the rest of the fabrication effort
• From the mine to the cryomodule (‘production-like RD’)
Focused charge, well defined deliverable, broad base, expensive task with excellent cost / benefit
US labs are heavily involved but expertise is scattered; Fermilab is playing a “catch-up” game.
S. Nagaitsev 4
f String test (S2)String test (S2)
Charge: Recommend a string test strategy;
Expensive Referendum on the SRF readiness for the ILC Many duplication / competition /
standardization issues between DESY, KEK, FNAL
Cross threaded with mass-production issues, ‘regional interest’ and lab ambitions
R or D? What is the balance?
S. Nagaitsev 5
f
Surface Processing
Cavity Fabrication
Vertical Testing
He Vessel, couplers,
tuner
HPR or reprocess
Horizontal Testing
Cold String Assembly
Pass!
Pass!
Fail!
Fail!
Cavity/CM process and TestingCavity/CM process and Testing
Plan… Develop in labs then transfer technology to industry
S. Nagaitsev 6
f SCRF InfrastructureSCRF Infrastructure
This process requires extensive infrastructure Bare cavities
Fabrication facilities (Electron beam welder, QC, etc) Surface treatment facilities BCP & Electro-polish facilities (EP) Ultra clean H20 & High Pressure Rinse systems Vertical Test facilities ( Cryogenics + low power RF)
Cavity Dressing Facilities ( cryostat, tuner, coupler) Class 10/100 clean room Horizontal Test System (cryogenics and pulsed RF power)
String Assembly Facilities Large class 10/100 clean rooms, Large fixtures
Cryo-module test facilities Cryogenics, pulsed RF power, LLRF, controls, shielding, etc. Beam tests electron source (RF unit test facility at NML)
S. Nagaitsev 7
f Materials & SRF R&D infrastructureMaterials & SRF R&D infrastructure
Quality assurance: Characterization of Nb sheet from vendors Surface properties: oxide layer, inclusions, and scratches (eddy
scanner) Measure material composition (RRR, chemical composition, etc) Measure Nb mechanical properties ( ie crystal structure)
Surface processing studies Electropolish and BCP process studies (single cell programs) Surface contamination studies
Infrastructure: (ANL, TJNL, FNAL, Cornell, MSU, etc…) Labs for handling HF and processing and test of single cells Materials equipment ( RRR measurement, INSTRON, EM microscope,
SIMS.
Weld studies ( e.g. crystal structure, contamination, TIG welding) ILC is helping to upgrade existing national capabilities but much of
this is funded by other sources
S. Nagaitsev 8
fCavity Fabrication
By Industry
Cavity Dressing &Horizontal Testing
@ Fermilab
SurfaceProcessing @ Cornell
SurfaceProcessing
@ Jlab
SurfaceProcessing @ ANL/FNAL
Vertical Testing @ Cornell
Vertical Testing @ Jlab
Vertical Testing @ FNAL
Exists
Developing
U.S. Cavity Processing & TestU.S. Cavity Processing & Test
S. Nagaitsev 9
f FNAL/ANL collaboration Goal: A new joint surface processing facility Clean rooms, BCP, and state of the art EP New Chemistry and Clean rooms operational
New Clean Rooms Controls and HF scrubber
Surface Processing @ ANLSurface Processing @ ANL
S. Nagaitsev 10
f
•World knowledge to design new EP system
•Design Review 2/12/07, Under construction
•Plan: Commission late FY07
•Capacity ~ 45 EP cycles per year
•Plan for new HPR system by late 07
New Electropolish facility @ANL New Electropolish facility @ANL
S. Nagaitsev 11
f Fermilab SCRF MAPFermilab SCRF MAP
New Muon Lab:RF unit test facility
MDB:CCII HTSHINS
IB1: VTS
WH
CAF:MP9ICB
IARC
S. Nagaitsev 12
f A new Vertical Test Stand is under Construction at
Fermilab (IB1) Existing 1.8 K Cryogenic plant 125 W at 2 K (250 W intermittent test) RF system based on TJNL VTS RF/DAQ system Current test Stand will be capable of testing ~50 Cavities/yr Commissioning started (cryo), reached 2K, next step: single cavity test Evolutionary upgrades: Thermometry for 9-cells, 2 cavities at a time, 2
top plates, Cryo upgrades: increased pumping capability & purifiers, up to two additional VTS cryostats
Ultimate capacity ~ 264 cavity tests/yr
VTS Cryostat:IB1 New RF &
Control Room
Movable shielding for up to 3 pits
Vertical Test@FNALVertical Test@FNAL
S. Nagaitsev 13
f HTS @ MDB HTS @ MDB
Cryostat complete: ~DESY design but 2 Doors improve access
Extensive MDB cryo modifications [email protected] K 300 KW klystron & modulator is in place and tested Cooled down w/o cavity, 1st cavity test in May
1.3 GHz Cavity in
HTS Cryostat
HTS CryostatInstalled at MDB
DESY C22 VTS @ 17 MV/M
S. Nagaitsev 14
f MDB InfrastructureMDB Infrastructure
RF Power for HTS
Cryogenics transfer lines in MDB
Large Vacuum Pump for 2K
RF Power for HTS
Capture Cavity-II
S. Nagaitsev 15
f CAF: MP9CAF: MP9
Infrastructure: String Assembly Fixtures Clean Vacuum & Leak Check Ultra Pure Gas and Water Ultrasonic Cleaner Cold Mass Assembly Fixture
String Assembly Fixture
1st Cavity being prepared for HTS
MP9 Clean Roomand tooling built in FY06
UltrasonicCleaner
S. Nagaitsev 16
f CAF: ICB Final AssemblyCAF: ICB Final Assembly
Industrial Center Building (ICB) 18,000 ft2
Alignment, Instrumentation, coupler installation, etc Large Vacuum Vessel Assembly Fixture
CAF Goal: Produce R&D quantity Cryomodules (~1/month) Goal: Use infrastructure for tech transfer to industry Will Assemble 1st cryomodule (DESY kit) early fall 07 Also 3.9 GHz!
Cryomodule has1200 parts !
Parts for copy of DESY Assembly fixtureICB cleaned!
S. Nagaitsev 17
f ILCTA_NML@FNALILCTA_NML@FNAL
NML Building
CCM removal: Sep 06
NML: Apr 071st of 2 refrigerators each 60 [email protected]
S. Nagaitsev 18
f Two CMs with beamTwo CMs with beam
The existing building is perfect for testing two cryomodules with ILC-like beam. The building can be extended to fit 3 cryomodules.
S. Nagaitsev 19
f ILC RF unit with BeamILC RF unit with Beam
Construct a new building ~50m away from NML Connect by ILC-like tunnel (2nd RF unit) Upgrade RF system to 10 MW klystron Add larger 300W @ 1.8 K refrigerator New Bldg houses diagnostics, dump, refrigerator
S. Nagaitsev 20
f SummarySummary
Cavities & Cryomodules are cost drivers for ILC SRF R&D requires extensive infrastructure The U.S. is making good use of existing SRF
assets as well as new ANL/FNAL infrastructure to rapidly expand U.S. SRF R&D capabilities
Infrastructure is needed to support: GDE S0, S1, S2, S4 goals U.S. Industrialization of SRF technology
We have made a lot of progress in FY06-07 We have ambitious plans for FY08 and beyond Effort is resource limited