F ACTORS THAT D ETERMINE V ARIATION IN E STIMATIES

27
Prof Awad S. Hanna

description

F ACTORS THAT D ETERMINE V ARIATION IN E STIMATIES. Purpose of An Estimate. To know in advance the expected cost in varying degree of accuracy, at different phases of the project. Owner's Purpose of Estimate. 1.Making investment decision in the conceptual stage. - PowerPoint PPT Presentation

Transcript of F ACTORS THAT D ETERMINE V ARIATION IN E STIMATIES

Page 1: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Page 2: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

To know in advance the expected cost in varying degree of accuracy, at different phases of the project.

Page 3: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

1. Making investment decision in the conceptual stage.

2. Negotiate and finalize the contract at the implementation phase.

3. To implement cost control measures.

Page 4: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

1. Determine project cost and profit.

2. To Implement cost control measure.

3. To develop data base for that can be used for future project.

Page 5: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

1. Provide the owner with probable estimate.

2. Evaluate alternatives.

Page 6: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Contractor’s Estimator Determines actual cost

of project for bidding purposes.

Has detailed company cost data for labor and equipment.

Knows which construction methods are to be used.

Has knowledge of actual materials suppliers to be used and quantity discount prices.

Engineer’s Estimator Determines expected

cost. Does not know who will

receive award, therefore does not know contractor’s exact resource costs. Does not know actual labor rates.

Must assume probable construction methods to be used.

Does not know who project supplier will be. Must use local list prices.

Page 7: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

1. Preliminary

2. Unit price

3. Assembly or Conceptual Cost

4. Detailed estimate

Each phase of a project life cycle requires a different type of estimate--each estimate requires different types of information.

20%

15%

10%

5%

Accuracywithin

Preliminary

Unit Price

Assembly

Detailed

5min 1hour 1day 3 weeks

Time

2 Million dollars building

Page 8: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

“”“”

A cost prediction based solely on size and/or capacity of a proposed project.

Before any engineering or design is completed.

Rely on broad data from already executed similar projectrelate cost in dollar to the main

capacity/size parameternumber of beds in hospitalsquare feet of office spacenumber of students in school

Page 9: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

AdvantageousAllows a quick determination of the

feasibility of a project

A quick screening on alternatives, etc. (e.g., should it be a concrete building or a steel building !).

Purpose:

1. Ranking alternatives

2. Evaluate economics and financial feasibility

3. As a check on more detailed estimates

Page 10: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Parking Garage$15.0/sq. ft or $4500/parking space

High School$80 to 110/sq. ft or $40,000/ student

seat Medical Centers

$90 to 130/sq. ft

Page 11: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Unit prices are obtained from data on projects already performed.Cost of labor, material, and equipment for

all units of work are added together and divided by the number of units involved.

Page 12: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

____________________________________________________________

Work Item Estimated Quantity Unit Price Total___________________________________________________________

_Site Preparation 50,000 sq. yd $ 7

$ 350,000Earth Excavation 100,000 cu.yd. $ 12

$ 1,200,000Paving 50,000 sq.yd. $ 8

$ 400,000 Total bid price

$ 1,950,000___________________________________________________________

_

Page 13: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Performed when conceptual design decisions are being made.

Work package concept can be used to determine the element or assembly to be studied

We need a breakdown of cost of a completed project into its functional elements to:1. Find the relationship between element cost and project

cost

2. Distribution of cost between constituent elements (sq. feet of _____)

Page 14: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Elemental Estimate AnalysisGross floor Area = 250,000 ft2

Page 15: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Prepared after drawings and

specification are completed. Requires a complete quantity takeoff

based on drawing and the complete set of contract documents

Need information on labor rate "productivity", material cost, cost of renting or purchasing equipment

Page 16: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

1. Time

We base our estimate on the cost of existing projects that were built in the past

Price-level changes over time We need to project costs of future projects

Many organizations publish construction cost data on regular basis: US Department of Commerce US Department of Labor ENR Turner Construction Company Handy-Whitman Utilities

Page 17: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Cost Indices Published by R.S. Means and ENR Used to update old cost information

Uses1. To update known historical costs for new

estimates2. To estimate replacement cost for specific assets3. To provide for contract escalation

Limitations

1. They represent composite data, average of many projects.

2. They fail to recognize technological changes.3. There is a reporting time log.

Page 18: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

To update old cost information to current date

cost of new facility = cost of old facility x

To predict future cost

F = P (1 + i)

F = future cost P = present cost i = predicted rate of cost escalation per periodn = number of periods (years)

new cost indexold cost index

n

Page 19: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Some factors affecting cost in

different locations are:

1. Transport cost

2. Taxes

3. Labor supply and local productivity

4. Codes and local inspection

Construction costs also vary in different regions of the USA.

ENR and Means publishes periodically the indices of local construction costs in the major cities.

Page 20: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

ENR Regional Index

City Cost Index

Boston1120Chicago 1400New York 1700

Page 21: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

As the quantity built increases, the unit cost decreases,

Size Factor =

UCM = Unit Cost Multiplier

UCM = SF

Proposed SizeComparison Size

E - 1

Page 22: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

BuildingsComplex Projects

Project Size

Factor BuildingsComplex Projects

1.175 1.904 0.2 0.235 0.3811.128 1.619 0.3 0.338 0.4861.096 1.443 0.4 0.438 0.5771.072 1.320 0.5 0.536 0.6601.052 1.227 0.6 0.631 0.7361.036 1.153 0.7 0.725 0.8071.023 1.093 0.8 0.881 0.8751.011 1.043 0.9 0.910 0.9391.000 1.000 1.0 1.000 1.0000.991 0.963 1.1 1.090 1.0590.982 0.930 1.2 1.178 1.1160.974 0.900 1.3 1.266 1.1700.967 0.874 1.4 1.354 1.2240.960 0.850 1.5 1.440 1.2750.954 0.829 1.6 1.527 1.3260.948 0.809 1.7 1.612 1.3750.943 0.780 1.8 1.697 1.4230.938 0.774 1.9 1.782 1.4700.933 0.758 2.0 1.866 1.5160.928 0.743 2.1 1.950 1.5610.924 0.730 2.2 2.033 1.6050.920 0.717 2.3 2.116 1.6480.916 0.705 2.4 2.199 1.6910.912 0.693 2.5 2.281 1.7330.909 0.682 2.6 2.363 1.7740.905 0.872 2.7 2.445 1.8150.902 0.662 2.8 2.526 1.8550.899 0.653 2.9 2.607 1.8940.896 0.644 3.0 2.688 1.9330.893 0.636 3.1 2.768 1.9720.890 0.628 3.2 2.849 2.0100.887 0.620 3.3 2.929 2.0470.885 0.613 3.4 3.008 2.0840.882 0.606 3.5 3.088 2.1210.880 0.599 3.6 3.167 2.1570.877 0.593 3.7 3.246 2.1920.875 0.586 3.8 3.325 2.2280.873 0.580 3.9 3.404 2.2630.871 0.574 4.0 3.482 2.297

Use This Side for Unit Cost Multipliers

(UCM Method)

Use This Side for Total Cost Multipliers

(TCM Method)

Page 23: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

0.000

0.500

1.000

1.500

2.000

0.1 1.0 10.0

Size Factor

Un

it P

rice

Co

st M

ult

ipli

er

(UC

M)

Buildings Complex Projects

Page 24: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

0.000

0.5001.000

1.5002.000

2.500

3.0003.500

4.000

0.1 1.0 10.0

Size Factor

To

tal

Pro

ject

Co

st M

ult

ipli

er

(TC

M)

Buildings Complex Projects

Page 25: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Wall height = $10 x 160 x 10 = $16,000= $10.00 of floor area

Bldg. AWall cost = $10 x 160 x 10 = $16,000

= $10.00 of floor areaBldg BWall cost = $10 x 180 x 10 = $18,000

= $11.25 of floor area

Bldg AArea = 15ooft2

Perimeter = 160ft

30’

50’

Bldg BArea =1500ft2

Perimeter=

150ft

40’

40’

10’

15’ 15’

Page 26: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Increased productivity by doing repeated work.Detailed analysis will be discussed

later.

Page 27: F ACTORS THAT  D ETERMINE  V ARIATION IN  E STIMATIES

Prof Awad S. Hanna

Hard to quantify but should be evaluatedQualitySoil conditionWeather ConditionCompetitionProductivity