EXTRACTION OF URANIUM INDIA
-
Upload
salec-knowle -
Category
Documents
-
view
224 -
download
0
Transcript of EXTRACTION OF URANIUM INDIA
-
7/31/2019 EXTRACTION OF URANIUM INDIA
1/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
Proceedings of the XI International Seminar on
Mineral Processing Technology (MPT-2010)
Editors: R. Singh, A. Das, P.K. Banerjee, K.K. Bhattacharyya and N.G. Goswami
NML Jamshedpur, pp. 628641
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT
PRIMARY AND SECONDARY RESOURCES IN INDIA
N.P.H. Padmanabhan, A.K. Suri1 and S.K. Ghosh1
Bhabha Atomic Research Centre, Hyderabad - 500016, India1Bhabha Atomic Research Centre, Trombay, Mumbai - 400085, India
ABSTRACT
In order to maintain a sustained and planned economic growth rate of 8% in the coming years and to meet the
human development goals including eradication of poverty, India needs to increase her primary energysupply by 3 to 4 times and its electricity generation capacity by 5 to 6 times of the 200304 levels. All effortsare, therefore directed towards enhancing the electricity power generation and also the nuclear powercomponent. The Department of Atomic Energy (DAE) has launched a three stage nuclear power programme
based on utilization of the countrys vast thorium resources to increase the nuclear power componentsignificantly. In order to successfully go to second and third stages of the programme involving thoriumutilization, India has to build and operate adequate number of nuclear power reactors of first stage. These areessentially the pressurized heavy water reactors (PHWRs) burning natural uranium. The rising demand for
uranium in the power reactors requires intensive exploration to look for more workable uranium ore depositsin the country and techno-economic process flow sheets for exploitation. The new deposits require newtechnologies, which need to be developed by sustained R&D efforts.
At present the countrys uranium is produced at the two uranium mills located at Jaduguda and Turamdih,both in Dist. East Singhbhum, Jharkhand and operated by Uranium Corporation of India Limited (UCIL).These plants use acid leaching technique to bring the uranium values into solution. Efforts are on to enhance
the uranium supply by opening up uranium mines at Tummalapalle and Lambapur-Peddagattu (AndhraPradesh), Gogi (Karnataka) and Kylleng-Pyndengsohiong-Mawthab (KPM) (Meghalaya). While Lambapur-Peddagattu and KPM uranium ores can be processed by the well-trodden acid leaching route, some of theother ores like the ones from Tummalapalle and Gogi need to be processed by alkaline leaching because of
the preponderant presence of acid consuming carbonate minerals in the ore. Even though the Meghalaya oreis slated for acid leaching route, the technology to be followed is still to be finalized. Intensive R&D studiesare being carried out in various laboratories of the Department on process development and techno-economicevaluation on these ores. A pilot plant has been set up by Bhabha Atomic Research Centre (BARC) with the
active collaboration of UCIL, Atomic Minerals Directorate for Exploration and Research (AMD) and NuclearPower Corporation of India Limited (NPCIL) to carry out large scale semi-continuous studies on variousores. Revival of gravity plants to recover uranium from copper ores/concentrator plant tailings is also beingcontemplated by UCIL. This paper presents and discusses the R&D effort by the Department in this direction
and the salient features of the Pilot Plant and R&D studies carried out on different uranium ores.
Keywords: Uranium ore, Leaching, Acid leaching, Alkaline leaching, Process flow sheet.
628
-
7/31/2019 EXTRACTION OF URANIUM INDIA
2/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
629
INTRODUCTION
India has been showing in the recent years a very healthy economic growth rate with fast growingeconomy in all sectors. Still the country has to sustain the present growth rate of 810% over thenext 25 years, if it has to eradicate poverty, raise the standard of living of the common man andmeet its human development goals. To achieve a consistent and sustained growth rate of 8%through 203132 and to meet the energy needs of all citizens, India needs, at the very least, toincrease its primary energy supply by 3 to 4 times and, its electricity generation capacity/supplyby 5 to 6 times of their 200304 levels. By 203132 power generation capacity must increase tonearly 8,00,000 MW from the current capacity of around 1,65,000 MW inclusive of all captiveplants
[1](http://www.powermin.nic.in/JSP_SERVLETS/internal.jsp).
While coal and other carbon based primary sources will continue to play a significant role in thetotal electricity generation, efforts are also continuously on to augment the electricity generationby nuclear and other means including the renewable energy resources. The Department of AtomicEnergy (DAE) has ambitious plans to improve the contributions of nuclear energy to as much as10% by the year 2020. Indias nuclear power policy is based on utilization of its vast resource of
thorium, which by itself is not fissile, but fertile and can be converted into fissile material byirradiation in fast nuclear reactors. In order to achieve this, the Department of Atomic Energy (DAE)has charted out a three stage programme, which in the third stage culminates into full utilization ofthe thorium resource for supply of sumptuous electricity for significantly long time. However, thiscan be achieved only by effectively and successfully going through the initial two stages.
The strategy has been presented and discussed many times in various international forums andalso in IAEA meetings and conferences. Nevertheless, for the sake completeness, it can be simplystated as construction and operation of (i) an adequate number of Pressurized Heavy WaterReactors (PHWRs) using the natural indigenous uranium and associated fuel cycle facilities in thefirst stage, (ii) Fast Breeder Reactors (FBRs) using plutonium as fuel and backed by suitablereprocessing plants and plutonium based fuel fabrication plants and (iii) Advanced Heavy WaterReactors (AHWRs) in the second stage and AHWRs and thermal breeders in the third stage.
[2]But
both the second and third stages necessarily require operation of adequate number of the first stage
PHWRs for sufficient duration to generate enough fuel material for the second stage. The PHWRsuse natural uranium as fuel with heavy water as the moderator and primary coolant. So the success ofthe Indian nuclear power programme greatly depends on the availability of adequate supply of thenatural uranium resource, its exploitation and judicious utilization. This calls for adequate strengtheningof the front end of the nuclear fuel cycle, which comprises of exploration, exploitation and fuelfabrication stages. Intensive efforts have already been commenced in exploratory activities. Whilemost of the ores can be processed by the conventional acid leaching route, some ores requirealkaline leaching techniques. Since the ores vary widely in their characteristics with respect to thenature of occurrence of uranium mineralization, gangue mineralogy, associated minerals etc., dedicatedR&D efforts are needed for characterization and to develop techno-economically feasible process flowsheets. This paper presents and discusses the activities in this regard undertaken by the department.
R&D ON URANIUM ORES BY ACID LEACHING ROUTE
R&D on Jaduguda uranium ore
The exploration for uranium and other atomic minerals is carried out by Atomic Minerals
Directorate for Exploration and Research (AMD), the exploration agency of DAE, The explorative
-
7/31/2019 EXTRACTION OF URANIUM INDIA
3/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
630
efforts have been initiated seriously from the middle of twentieth century and have resulted in
discovery of uranium-copper mineralization in the Singhbhum Shear Zone (SSZ) and the
subsequent milling for uranium extraction from Jaduguda uranium ore deposit in the SSZ byUranium Corporation of India Limited (UCIL), the exploitation wing of DAE.
The Jaduguda deposit consists of two ore bodies in chlorite-biotite schist of Proterozoic age. Uranium
in the Jaduguda ore is disseminated in the metamorphic rock mainly as uraninite, which is essentially
a combination of tetravalent and hexavalent oxides of uranium in the ore. Dissolution of uranium
is possible in conditions facilitating oxidation of the tetravalent uranium. The process flow sheet
was developed based on intensive R&D laboratory studies carried out at Bhabha Atomic Research
Centre (BARC) and also large scale studies carried out in the Ghatsila Pilot Plant set up especially for
the above purpose. The pilot plant was, however, dismantled after the setting up of the mill at Jaduguda
and commencement of successful production of uranium concentrate as Magnesium Diuranate
(MDU). At that time the pilot plant had lived its purpose and no need was anticipated in future.
The main uranium extraction process followed in Jaduguda mill involves multistage crushing
followed by rod and pebble milling to get about 50% passing through -200 mesh ground material.Dewatering of the ground ore slurry is carried out by thickening followed by filtration. The filter
cake is repulped to the required pulp consistency and is then leached in air agitated Pachuca tanks.
Dilute sulphuric acid (at about pH 1.8) is used as the lixiviant in presence of pyrolusite as the
oxidant. The leach slurry is filtered and clarified to get the uranium bearing mother liquor. During the
leaching process, the tetravalent uranium gets oxidized to hexavalent uranium and gets solubilized
in the acid medium and is present as anioninc uranyl sulphate complex. Further purification /
concentration is carried out by ion exchange using an anioninc exchange resin. The eluate from
this stage is first treated with lime to increase the pH to about 3.5, wherein the iron and excess
sulphate present in the system gets precipitated as Iron-Gypsum Cake (IGC). Dewatering is then
carried out and from the clear liquor uranium is precipitated as Magnesium Diuranate (MDU)
using magnesia liquor at a pH of 6.5 to 7. The dried product, known popularly as the Yellow Cake
is packed and sent to Nuclear Fuel Complex at Hyderabad for further purification to nuclear grade
and fabrication into fuel bundles. The flow sheet followed in Jaduguda mill is given schematically
in Fig. 1. The uranium leach recovery from Jaduguda is over 90%. Initially the Jaduguda uranium
mill started with processing only Jaduguda uranium ore; but over the years with the demand for
uranium going up in the country and with the depletion of ore from Jaduguda mines, UCIL opened
up three more mines at Bhatin, Narwapahar and Turamdih located in the vicinity of Jaduguda.[3]
The mill generates two wastes, (i) the solids waste from filter after leaching and (ii) the barren
liquor from ion exchange. The barren liquor is neutralized initially with limestone slurry to ph 4.2
followed by further neutralization to pH 1010.5 by lime slurry. This is mixed with solids waste in
tailings neutralization pachucas to have a final pH of 9.5 to 10 and at this pH the residual uranium,
manganese and other pollutant ions get precipitated and fixed. The neutralized slurry is processed
in Low Intensity Magnetic Separators (LIMS) to recover the magnetite concentrate as an
economic by-product and the non-magnetic product from this stage goes for classification in
hydro-cyclones. The cyclone underflow is pumped to mines as back-fill and the overflow product
is pumped to the tailings pond. The solid fines settle to the bottom of the tailings pond and thesupernatant water is decanted off to the Effluent Treatment Plant (ETP). Although the lime
neutralization in the tailings neutralization takes care of most of the harmful constituents in the
effluent, radium and traces of manganese still remain. Radium is fixed by treatment with barium
chloride and the residual manganese by precipitation at pH 10 with lime.
-
7/31/2019 EXTRACTION OF URANIUM INDIA
4/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
631
Fig. 1: Schematic process flow sheet followed in Jaduguda
and Turamdih uranium mills.[4]
Even after commencement of the commercial production of uranium from the Jaduguda uranium
mill, consistent R&D was being carried out in BARC as well as in the Control, Research and
Development Laboratory (CRDL) of UCIL to sustain the uranium leach recovery and also to take
care of the ore grade variations. It was only due to the consistent R&D efforts by BARC that the
sulphide minerals present in the Jaduguda ore could be advantageously recovered as mineral
concentrates. Jaduguda ore contains minor amounts of sulphide minerals comprising of
chalcopyrite, molybdenite, pyrite and pyrrhotite, millerite and pentlandite (essentially sulphides of
copper, molybdenum, iron and nickel). An attempt was made to recover these sulphide minerals in
the form of marketable concentrates of copper molybdenum and nickel. Based on laboratorystudies in BARC a by-products recovery plant (BRP) was set up which started production in 1974.
Molybdenite and chalcopyrite concentrates were produced and sold. However, this plant had to
close down after nearly 20 years of successful operation due to the dilution of sulphide minerals,
caused essentially by blending of ores from other satellite mines in the Jaduguda plant.
-
7/31/2019 EXTRACTION OF URANIUM INDIA
5/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
632
The R&D efforts also led to augmentation of uranium supply by recovering uranium values from
the copper ores from the mines surrounding Jaduguda. The copper ores mined from the Surda,
Mosaboni and Rakha mines located in the vicinity and processed by the Hindustan CopperLimited (HCL), contain trace amounts of uranium (in the range 0.007 to 0.012% U3O8). Attempts
were made to recover these by processing the tailings from the copper concentrator plants using
simple gravity concentration techniques. These formed a cheap source for uranium and the
uranium recovery plants were being operated by UCIL to produce uranium concentrates, which
were again processed in Jaduguda mill. A lot of research has gone into improving the recovery of
uranium values from the copper plant tailings. These plants were operating till recently, but had to
close down because of the closure of the copper mines at these places. Efforts are on to open up
with the restart of mining activities in these copper mines by HCL.
A lot of research was carried out to improve the recovery of uranium from the copper ores. It was
found that the recovery was sub-optimal mainly because of the inefficiency of the conventional
shaking tables in recovering very fine and ultra fine uranium values and also the significant
uranium values associated with micaceous minerals. An integrated gravity and high intensity
magnetic separation process flow sheet was developed to address above the problems. While thegravity part included Bartles Mozley Separator (BMS), Cross Belt Concentrator (CBC) and small
diameter hydrocyclone assemblies, the magnetic part included Wet High Intensity Magnetic
Separator (WHIMS). A superconducting high gradient magnetic separator was developed to
effectively separate ultra fine uranium values and micaceous minerals (Fig. 2).
Fig. 2: Superconducting high gradient magnetic separator developed in BARC.
R&D on Narwapahar uranium ore
With the necessity for going for deeper mining in Jaduguda and also due to the depletion of ore in
the Jaduguda mines, the ore from the nearby mines like Narwapahar and Bhatin were also
processed in the Jaduguda mill. The Narwapahar mine is located at a distance of about 12 km from
Jaduguda and is already in production stage. The ore has lower grade than the Jaduguda ore and its
-
7/31/2019 EXTRACTION OF URANIUM INDIA
6/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
633
leachability is also lower. Mineralogically also the ore is not similar to the Jaduguda ore. A
comparison of the mineralogy of the different uranium ores from the various mines of Singhbhum
is given in Table 1. An intensive R&D was called for to enhance the uranium leachability fromthis ore. The studies indicated that the nature of uranium mineralization in the Narwapahar could
be the main reason for its lower leachability. It was found that Narwapahar ore had a higher
content of micaceous minerals in the form of chlorite and biotite with significant uranium
distribution in them (Table 1). Estimation of the uranium distribution in the different mineral
constituents of Narwapahar ore revealed that significant uranium was found to occur as ultra-fine
inclusions within the mica platelets (The figures corresponding to the Methylene Iodide Lights
(MIL) in Table 2). Nearly 35% of the uranium values are distributed in 58% of the micaceous
minerals. Only part of this uranium gets solubilized during the leaching stage and the remaining
part was not probably accessible to the lixiviant sulphuric acid. On the other hand in Jaduguda ore,
the micaceous minerals constituted only about 22% with about 11% uranium distribution. Detailed
grinding and liberation studies were carried out to find out whether finer grinding will lead to
enhanced uranium liberation. It was observed that on fine grinding the liberation did not improve
significantly, the finely ground material posed problems in solid-liquid separation.
Table 1: Typical mineralogical composition of uranium ores from Singhbhum shear zone
MineralJadu-
guda
Narwa-
paharBhatin
Tura-
mdih
Quartz
Chlorite/Biotite
Magnetite
Other Opaques*
Apatite
Tourmaline
Other transparent minerals
68.0
22.0
3.0
1.5
3.0
2.5
36.0
52.7
4.9
0.7
4.7
0.8
0.2
48.2
37.0
3.5
3.5
1.8
6.0
67.0
26.0
3.0
1.7
2.0
0.3
% U3O8
(Chemical assay)0.065 0.047 0.051 0.046
*
Preponderantly indicates sulphide minerals.
Table 2: Distribution of uranium in various density fractions in Narwapahar ore
FractionSp.gr.
range
Weight
%
% U3O8
Distbn.
BRL 3.3 4.4 54.3
Efforts were made to separate out the feebly paramagnetic micaceous minerals in a Wet High
Intensity Magnetic Separator (WHIMS) from the plant tailings and leach out the magnetic fraction
containing uranium using drastic conditions. Studies were also carried out on a superconducting
high gradient magnetic separator, designed, developed and built by BARC, in tandem with
-
7/31/2019 EXTRACTION OF URANIUM INDIA
7/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
634
WHIMS. The laboratory studies did indicate positive and marginal improvement in the uranium
recovery, though cost and benefit analysis was not very favourable for the marginal recovery
improvement. R&D studies are in progress in various ways such as use of ultrasonics and microwavetechnology to get better results.
R&D on Domiasiat uranium ore
The exploratory efforts put up by AMD in finding new uranium ore deposits have yielded a number
of workable deposits. One of the important of these deposits is in the State of Meghalaya with a
substantial resource position at a reasonably high grade of 0.1 % U3O8 at Domiasiat (Kyelleng-
Pyndengsohiong, Mawtahbah KPM Project) and Wahkyn. The mineralization is in a medium to
coarse grained sandstone of the upper Cretaceous and lower Mahadek formation at Meghalaya,
comprising of quartz, feldspar and coaly fragments cemented by clay and carbonaceous matter.
Microcrystalline pitchblende and secondary uranium minerals are associated with coaly fragments
and the clay-carbonaceous cementing matrix. Domiasiat Ore body is situated at a shallow depth of
within 45 M depth from the surface.
Detailed process investigation studies have been carried out on Domiasiat ore samples. Themineralogical analysis of two of the ore samples (high and low grade) received in BARC is givenin Table 3. Bulk of the uranium values (nearly 88%) is associated with carbonaceous matter(organic matter), with some of the pieces assaying as high as 40%. The presence of organic matterin the Domiasiat ore has been derived from the decay of plants and radioactivity is essentially dueto uranium in the form of pitchblende, coffinite and urano-organic compounds. The closeassociation of uranium with the organic matter in Domiasiat ore can be explained as follows:Mobile hexavalent uranium gets fixed at reducing environment provided by the decayingcarbonaceous organic matter. Part of the uranium gets reduced to tetravalent and is precipitated asuraninite. The carbonaceous matter, having a large surface area due to its porous nature adsorbs orexchanges the hexavalent uranium also on its surface without reduction. Probably because of thissignificant amount of uranium from certain blocks was found to solubilize in process water itself.This ore also provided another paradoxical situation in that while part of the uranium values wasfound to get solubilized in process water, the remaining fraction was not solubilized even withvery high acid dosage. Acid requirement upto 200250 Kg/tonne of sulphuric acid was foundnecessary for adequate solubilization, in contrast to 1620 Kg/tonne of acid in the case ofJaduguda ore. Probably the uranyl and U
4+ions get attached to the broken bonds in the
carbonaceous matter present in the ore and get fixed in the myriads of sites within the fine andultra fine pores of the carbonaceous matter. During leaching the reagent is unable to reach the
myriads of uranium sites, leading to lesser uranium leachabilities. Three alternate processes weredeveloped at three different laboratories which involved.
1. Acid pug-cure-leach process (Pugging of ore with 100 Kg/t of H2SO4, and curing at slightly
elevated temperature followed by leaching).
2. Two stage leach process (Leach with 25Kg/t H2SO4 in the first stage and 100 Kg/t in the
second stage) and
3. Leach-grind-float-leach process (Leaching of crushed ore-followed by grinding and flotation
of uranium bearing carbonaceous material and roast-leach of the float).
Extensive laboratory studies on this ore followed by selective large scale tests have indicated that
uranium from this ore can be techno-economically recovered. However, exploitation of this
attractive near-surface deposit is yet to start due to a number of factors, involving relative
-
7/31/2019 EXTRACTION OF URANIUM INDIA
8/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
635
inaccessibility and infrastructural bottlenecks, heavy rain fall throughout the year and also other
socio political reasons. UCIL is now carrying on with the pre-project activities to open the mine
and process the ore at the earliest.
Table 3: Mineralogical composition of Domiasiat ores
% by wt.Mineral Phase
High grade Low grade
Quartz, feldspar and clayey material
Garnet, Zircon, monazite etc.,
Pyrite and marcasite
Galena and chalcopyrite
Rutile/ Anatase, goethite etc.
Bitumen and uranium phases
97.4
0.2
0.5
Tr.
0.2
1.7
98.3
0.2
0.5
Tr.
0.2
0.8
% U3O8 (by Chemical analysis) 0.265 0.113
R&D ON URANIUM ORES BY ALKALINE LEACHING ROUTE
As far as the uranium ore processing was restricted to acid leach route, the laboratory scale batch
studies were being carried out at the laboratories of BARC, AMD and UCIL. But once the number
of operating PHWRs increased, the demand for uranium also rose up significantly, leading to the idea
of opening up those mines not considered due to techno-economic reasons and also to intensify the
exploratory efforts to discover new and exploitable deposits. In this category, the Tummalapalle
uranium ore occurrence, discovered by in late eighties, but not considered for exploitation due to
its low grade and also due to its geological characteristics. However, the ever-increasing demand
for then uranium led to a revisit into the problem and exploitation of this low grade deposit was
taken up as a challenge and development of process technology was taken up in all earnestness
and seriousness. The efforts resulted in developing a novel and environment-friendly processtechnology and also in setting up a pilot plant for carrying out large scale semi-continuous studies
to generate design and scale-up parameters and also for technology demonstration.
TECHNOLOGY DEMONSTRATION PILOT PLANT (TDPP), JADUGUDA
With the growing demand for the uranium for our PHWR reactors, currently operating and under
construction, it is imperative that the new uranium mines discovered and proved by AMD are
opened up for exploitation. Since the technology used in the Jaduguda mill may not be applicable in all
these cases, the new processes were needed to be developed and this requires apart from in-depth
laboratory studies on process development, large scale tests to confirm the laboratory process and
generate process engineering and scale-up data for effective translation of the laboratory process
to a process technology. Realizing this need, a Departmental pilot plant, christened as Technology
Demonstration Pilot Plant (TDPP) was set up in UCIL premises at Jaduguda with the active
collaboration and participation of BARC, AMD, UCIL and NPCIL. It was planned to have all the
stages present in a generic uranium process flow sheet from ore-to-yellow cake. The UCIL
premise was chosen as the site for the TDPP since all the required infrastructural and other logistic
supports and tailings processing facilities were already readily available there.
-
7/31/2019 EXTRACTION OF URANIUM INDIA
9/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
636
The TDPP has a multistage crushing plant with primary and secondary crushers and screens. The
crushing facility installed in the TDPP is schematically shown in Fig. 3. The crushing plant is
located just outside the process plant and it has its own dust collection system.
Fig. 3: Schematic view of the crushing plant at TDPP, Jaduguda.
The product of the crushing plant is the fine ore, which is stored within the process plant in the
Fine Ore Bin (FOB). The grinding circuit is a ball mill in closed circuit with a rake classifier. The
ground material is stored in ore pits in the wet conditions. For the large scale experiments, the
required ore feed sample is drawn from the ore pits. Since during the initial stages of setting up of
TDPP, process technology development studies were in progress and this ore required alkaline
pressure leaching for maximal uranium leachability. Hence the alkaline pressure leach set up was
planned initially. The post-grinding facilities installed at TDPP process plant includes facilities for
feed preparation, pressure leaching, waste heat recovery, solid-liquid separation, uranium
precipitation as Sodium Diuranate (SDU) and product filtration. The facilities have a batch
pressure reactor (BPR) and 3-compartment cigar type Continuous Pressure Leach Reactor (CLR).
The continuous leach reactor has a spiral heat exchanger to recover the waste heat from the exit
stream of the reactor. The heating of the slurry in both the reactors is done using saturated steam
from an electrode boiler. The batch reactor has a steam coil and the continuous reactor has a steam
jacket. The steam coil in the batch reactor is used for cooling of the slurry after the leaching is
completed. The slurry exits from the continuous reactor and partial depressurizing and cooling
occur in the Spiral Head Exchanger (SHE). The leach slurry is filtered in a Horizontal Belt Filter
(HBF), which has 3-stage counter current wash facility. The pilot plant includes reagent recovery
facilities also. The facilities are schematically presented in Fig. 4.
R&D ON TUMMALAPALLE URANIUM ORE
The strata-bound type uranium mineralization of the Kadapa basin was discovered by AMD
during the later half of 1980s at Tummaplapalle in Andhra Pradesh. A reasonably vast resourcewas estimated at Tummalapalle Rachakuntapalle deposits. Uranium is hosted by dolostone
rocks. This strata-bound mineralization extends over more than 60 kM along the SW margin of the
Kadapa basin. Due to the alkaline matrix of the host rock alkaline leaching technology is the
process option for economic exploitation.
-
7/31/2019 EXTRACTION OF URANIUM INDIA
10/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
637
Fig. 4: Schematic view of ore-to-yellow cake facilities set up at TDPP
for alkaline pressure leach route).
The host rock in the Tummalapalle ore deposit is Phosphatic Siliceous Calcitic Dolostone (PSCD).It was very difficult to identify any discrete uranium phase or mineral in the ore, but ultrafine sized
brannerite and pitchblende have been indicated. The uranium content is confirmed by chemical
and mineralogical analysis. The average chemical assay of the ore sample was found to be 0.042%
U3O8. The uranium mineralization may be due to ultrafine pitchblende and brannerite with minor
-
7/31/2019 EXTRACTION OF URANIUM INDIA
11/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
638
quantities of organo-uranium complexes and suspected coffinite. The uranium association was
found to be mainly with the lighter (
-
7/31/2019 EXTRACTION OF URANIUM INDIA
12/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
639
Fig. 5: Comparison of leachabilities obtained under different process conditions.
Based on the laboratory studies, a tentative process flow sheet was developed, which was further
tested on large scale batch leaching mode and attempts were made to regenerate most of the
reagents used in leaching and uranium precipitation stages. The special features of this process
technology are counter current leaching and multi-stage counter current washing after filtration ofthe leach slurry and elimination of uranium purifications step. The process technology is a near
zero-waste liquor process. The tentative process flow sheet is given in Fig. 6. The ore is shortly to
be taken up for commercial production.
Fig. 6: Tentative schematic flow sheet for processing Tummalapalle ore.
-
7/31/2019 EXTRACTION OF URANIUM INDIA
13/14
N.P.H. PADMANABHAN, A.K. SURI and S.K. GHOSH
640
SCOPE FOR EXPLOITATION OF OTHER DEPOSITS
A careful study of the distribution of uranium deposits under different categories in the world vis-
a-vis that in India (Table 5) indicates that there is a good scope for finding new uranium deposits
in the categories of Unconformity-related, Quartz-Pebble-Conglomerates and in Breccia
Complex. The exploration strategy is based on the presumption that the uranium mineralization in
India cannot be different from that in the world scene. The efforts have indeed borne fruits in that
indications have been obtained in Kadapa basin in the State of Andhra Pradesh and in Bhima
basins in Karnataka. One of the other promising areas is Rohil- Ghateswar in Rajasthan. Although
India has got more than 3 decades of plant experience in acid leaching technology from Jaduguda
mill and is now perfecting alkaline leaching technology in the exploitation of Tummalapalle
deposit, R&D efforts are absolutely necessary before taking up any ore for exploitation. Realizing
this fact, DAE has set up a Technology Demonstration Pilot Plant (TDPP), Jaduguda for carrying
out large scale studies on the process flow sheet developed in the laboratory and also for
generating process engineering and scale-up parameters for plant design. These are absolutely
essential to avoid any process shocks and surprises in future. The various laboratories of the
different units of DAE, including AMD, BARC and UCIL are well equipped with the necessaryequipment and instrumental facilities and adequate expertise exists in the Department to tackle any
type of uranium ore in the country.
Table 5: Comparison of world and Indian uranium deposits
In World In India
Unconformity-related
Sandstone
QPC
Vein
Breccia complex
Others
27
21
10
8
18
16
7.7
16.4
53.7
22.2
Total 100 100.0
CONCLUSIONS
India has intensified all its efforts to increase the nuclear power component in the countrys
overall electricity generation by well oriented exploration for uranium deposits, increased R&D
efforts to develop techno-economic process flow sheets and successful exploitation of uranium
deposits discovered and proved. In the train of activities R&D for development of economic and
environment-friendly process flow sheets occupies a very significant place. The Department is
fully geared up for tackling any type of uranium ore in the country by excellent laboratory
facilities in its various units and a technology demonstration pilot plant at Jaduguda.
ACKNOWLEDGEMENTSThe authors would like to place on record their sincere thanks to Dr. S. Banerjee, Director, Bhabha
Atomic Research Centre for his keen interest and encouragement.
-
7/31/2019 EXTRACTION OF URANIUM INDIA
14/14
R&D INPUT TO EXTRACTION OF URANIUM FROM DIFFERENT PRIMARY
641
REFERENCES
[1] Integrated Energy Policy: Report of the Expert Committee. Planning Commission
Document, Government of India, 2006, p. 182.
[2] Padmanabhan, N.P.H. and Suri, A.K., Challenges in augmenting the uranium supply
position in India, 2007, In Proceed. International Seminar on Mineral Processing
Technology (MPT-2007), Pub.: Allied Publishers, New Delhi, p. 1.
[3] Gupta, R., 2004, Uranium MiningThe Indian Scenario, 2004, Proceed. National
Workshop on Atomic Mineral Deposits: Their Utility and Impact, Osmania Geology Alumni
Association, Geology Department, Osmania University, Hyderabad, p. 38.
[4] Suri, A.K., Ghosh, S.K. and Padmanabhan, N.P.H., 2008, Proceedings of the DAE-BRNS
biennial symposium on Emerging Trends in Separation Science and Technology (SESTEC-
2008), New Delhi.
[5] Suri, A.K., Padmanabhan, N.P.H. and Ghosh, S.K., Processing technologies for exploitation
of low grade and secondary sources of uranium, Proceed. IAEA technical meeting on
Uranium Small Scale and Special Processing Technologies, Vienna, June 2007.