Extension of Time Claim Procedures and Assessment
-
Upload
silentarrow -
Category
Documents
-
view
14 -
download
2
Transcript of Extension of Time Claim Procedures and Assessment
EXTENSION OF TIMECLAIM PROCEDURESAND ASSESSMENTDavid Fabian and Ian Briggs
Minter Ellison
There are a number of areas ofchange to the extension of timeclaim provisions:
EXTENSION OF TIME- QUALIFYING CAUSESOF DELAYClause 35.5 of AS4300 containedquite complicated references tothe types of delays that wouldentitle contractors to claimextensions of time. These lengthyprovisions have been replacedwith a statement that thecontractor will be entitled to claiman extension of time if (inter alia)the contractor 'is or will bedelayed in reaching practicalcompletion by a qualifying causeof delay' (Clause 34.3). 'Qualifyingcause of delay' is widely defined tobe anything other than a breachor omission by the contractor, orindustrial conditions/inclementweather occurring after the Datefor Practical Completion.
EXTENSION OF TIME CLAIM-TIME BARUnder Clause 34.3, the contractoris only entitled to extension of timeclaims if it submits a written claimfor an extension of time 'within 28days of the time when thecontractor should reasonablyhave become aware of thatcausation occurring'.
AS4300 contained a similar timebar, with the contractor beingobliged to give a notice within 28days 'after the delay occurs'.Although the new standard avoidsthe difficulties with establishingwhen the delay 'occurs' it is notclear whether difficulties will nowarise as to when the 'causation'occurs, and there is risk of delay
occurring to more than 28 daysafter causation.
In any event, it is distinctlypossible that these timerequirements are not time bars.That possibility arises because ofthe wording of Clause 41.2.
EXTENSIONS OF TIME ASSESSMENTAssessment of claims is dealt withunder Clause 34.4. According tothe terms of that clause:
• If both qualifying and nonqualifying causes of delay overlap,AS4902 obliges thesuperintendent to apportion delayto WUC according to whether it isnon-qualifying or qualifying causeof delay. This is a change in riskwhich operates in favour of thecontractor, as it leaves open thepossibility of the contractor beinggranted an extension of time evenif it was also delaying the works tosome extent. This conceptreplaces the concept of'concurrency' (Clause 35.5)provisions of AS4300 and AS2124,which have been notoriouslydifficult to apply. However itremains to be seen whether thenew 'apportionment' approach isany easier to administer.
• It is the committee's intentionthat the contractor still 'owns thefloat' although the relevant clauseis not ideal and may give rise todiffering interpretations.
• If the superintendent does notrespond to an extension of timeclaim within 28 days of receiving it,then the extension of time isdeemed to be granted as anassessment and direction (Clause34.5). To challenge the claim, theprincipal will be forced to gothrough the claim provisions (i.e.challenge a direction of thesuperintendent). This is likely tocause difficulties where thesuperintendent complains thatthe claim lacks sufficient detail toenable a proper assessment.
EXTENSION OF TIME- LIQUIDATED DAMAGESAND DELAY DAMAGESUnder AS4902 (Clause 34.7), thesuperintendent is obliged tocertify liquidated damages as dueand payable to the principal. Thiswill create greater certainty as tothe principal's ability to recoverliquidated damages from thecontractor.
Delay costs were dealt with inClause 36 of AS4300.They aredealt with in Clause 34.9 ofAS4902, and AS4902 will lead torecovery of greater amounts thanAS4300. Under AS4902,'delaydamages' are payable forextensions of time arising from a'compensable cause' (i.e. a matterwithin the control of the principalor superintendent). The 'damages'are to be assessed by thesuperintendent and (unlikeAS2124 or AS4300) will includeloss of profit and fixed overheadsrecovery.
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #77 MAY/JUNE 2001 23