Extension of multi-commodity closed-loop supply chain ...Extension of multi-commodity closed-loop...
Transcript of Extension of multi-commodity closed-loop supply chain ...Extension of multi-commodity closed-loop...
ORIGINAL PAPER
Extension of multi-commodity closed-loop supply chain networkdesign by aggregate production planning
Leena Steinke1 • Kathrin Fischer1
Received: 30 June 2015 / Accepted: 17 October 2016 / Published online: 14 November 2016
� The Author(s) 2016. This article is published with open access at Springerlink.com
Abstract In this work the influence of production and
capacity planning on decisions regarding facility location,
distribution quantities and component remanufacturing
(and vice versa) in a closed-loop supply chain network
(CLSCN) with multiple make-to-order products is studied.
A mathematical model, the facility location, capacity and
aggregate production planning with remanufacturing
(FLCAPPR) model, for designing the CLSCN, for planning
capacities at the facilities and for structuring the production
and distribution system of the network cost-optimally, is
formulated. It consists of a facility location model with
component remanufacturing over multiple time periods,
which is extended by capacity and production planning on
an aggregate level. The problem is solved for an example
set of data which is based on previous CLSC research in
the copier industry. In a numerical study the effect of the
extended planning approach on the decision to process
returned products is determined. Furthermore, the
FLCAPPR model is solved for different returned product
quantities and numbers of periods in the planning horizon
to study the influence on the network design and on the
procuring, production and distribution quantities. It turns
out that decisions regarding the locations of and the
capacity equipment at facilities and decisions regarding the
production and distribution system are interdependent;
therefore, they have to be managed jointly. Furthermore, it
is shown that the decision to process returned products and
use remanufactured components in the production does
depend not only on the costs, but also on the quantity of
returned products and the length of the planning horizon.
Keywords Closed-loop supply chain management �Network design � Remanufacturing � Reverse logistics �Aggregate production planning � Capacity planning
1 Introduction
Supply chains with product recovery differ, depending on
the characteristics of the product, the recovery activity
which is used and whether this activity is done by the
original equipment manufacturer or a third party [6]. In
general, supply chains with product recovery can be dis-
tinguished into open-loop and closed-loop supply chains
(CLSC). If there is hardly any connection of the forward
and return product flows, the supply chain is open-loop and
the forward and reverse product flows are managed sepa-
rately. The forward product flow can be described by the
traditional supply chain management theory, and the
reverse product flow is planned independently by reverse
supply chain management [25]. If the forward and return
product flows are related, e.g. customers supply their used
products as production inputs, the supply chain is closed-
loop. In this case, often an integrated management of both
flows is necessary to achieve an optimized CLSC; for
further details see [8, 9].
In this work, a supply chain is studied which is closed by
component remanufacturing. Remanufacturing is also
This article is part of a focus collection on ‘‘Robust Manufacturing
Control: Robustness and Resilience in Global Manufacturing
Networks’’.
& Leena Steinke
Kathrin Fischer
1 Institute of Operations Research and Information Systems,
Hamburg University of Technology, Schwarzenbergstr. 95,
21073 Hamburg, Germany
123
Logist. Res. (2016) 9:24
DOI 10.1007/s12159-016-0149-4
called value-added recovery, since it describes a series of
operations which restore the value of a product after usage
[11]. A supply chain with remanufacturing is extended by
the following activities: collecting, cleaning and testing
returned products. Then, remanufacturable products are
disassembled into components, which are remanufactured,
e.g. repaired or refurbished. After testing these compo-
nents, they are reassembled and sold in secondary markets
as remanufactured items or reintegrated to the original
supply chain and used as as-new items [11], as in the
supply chain studied in this work. High-value products, e.g.
copiers and automobiles, are suitable for component
remanufacturing. A further discussion of product charac-
teristics that enable remanufacturing can be found in [18].
Whether the supply chain is open- or closed-loop, pro-
duct recovery forces supply chain management (SCM) to
consider a reverse product flow. In addition to the planning,
realization and control of all operations, production,
inventory and distribution quantities and information flows
from the product origin to the point of consumption, all
problems concerning the way back through the supply
chain, i.e. after consumption, have to be considered in a
SCM with product recovery. These decision problems can
be differentiated regarding their planning horizon: some
are made on a yearly basis and determine the framework
for decisions, which are made on a weekly or monthly basis
[26]. Then again, these decisions constrain the operational
decisions, which occur every day [20].
The network design, decisions regarding the product and
material programme, supplier selection, collection strategy,
take-back arrangements and supply chain coordination are
strategic decision problems and belong to long-term plan-
ning. Decision problems regarding inventory management
and production planning are tactical and have a mid-term
planning horizon. Operative decision problems, as disas-
sembly planning, material requirement plans, scheduling
and routing in the remanufacturing shop have a short-term
planning horizon [4, 5, 7, 28].
In order to achieve an optimized CLSC the tactical
planning has to be considered by strategic management
[14, 21, 26]. Long-range forecasts of aggregate product
demand are the input for strategic planning [5]. They are
used by the mathematical model developed in this work to
derive a cost-optimally network design, i.e. cost-optimal
facility locations and capacity equipment, with cost-opti-
mal procuring, transportation, production and storage
quantities. The quantities are planned on an aggregate
level; therefore, fluctuations of data are neglected and the
modelling approach is deterministic.
In the facility location problem (FLP), facilities are
located and quantities of goods are allocated and dis-
tributed in the network a cost-optimal way, e.g. in [2]. In
the special case of a CLSN with reverse product flows
these models support the procuring decision, i.e. when to
recover returned products and use them as production
inputs, as well, e.g. in [8, 9].
In the literature so far, location/allocation models in a
CLSCN consider opening costs of product recovery facil-
ities, but costs for volume capacity and costs for installing
technology or hiring workforce for the operations at the
respective facilities of the network, especially for product
recovery operations, are neglected. However, to determine
a cost-optimal procurement policy, i.e. to decide when to
recover returned products and use the resulting items as
production inputs instead of new items procured from
suppliers, these costs have to be included.
Since remanufacturing is a labour-intensive operation
(see [13] for an extended discussion), labour hour costs are
relevant for the decision to process returned products. The
well-established aggregate production planning (APP)-
framework is used to plan the production and workforce at
facilities cost-optimally in this work. In APP, the length of
the planning horizon is usually between 6 and 24 months
[3] and quantities are planned on an aggregate level. In the
following this APP-approach is described and a multi-pe-
riod facility location problem extended by capacity and
aggregate production planning is developed.
The consideration of different product compositions,
component remanufacturing and component commonality
is possible with this modelling approach, and the influence
of different return rates can be investigated. Hence, dif-
ferent realistic SC settings can be captured.
The rest of the paper is organized as follows: relevant
selected literature regarding network design and aggregate
production planning is presented and discussed in the next
section. Here, the differences between other contributions
and the approach taken in this work are also discussed. The
CLSCN and the production planning problem are presented
in detail in Sect. 3. Afterwards the planning problem is
described mathematically in Sect. 4. In Sect. 5, it is solved
for an example data set and the results are presented.
Furthermore, a sensitivity analysis is performed and
selected results are discussed in Sect. 5, too. Finally, con-
clusions and possibilities for further research are stated.
2 Literature review
Networks with product recovery are mathematically opti-
mized by extending the classical Warehouse Location
Problem (WLP) to capture reverse product flows. Mostly
these problems are described by Mixed Integer Program-
ming (MIP) and Mixed Integer Linear Programming
(MILP) models. In the following, selected papers are dis-
cussed, which present the state of research, and have
influenced this study. A more detailed review of network
24 Page 2 of 23 Logist. Res. (2016) 9:24
123
design literature concerning supply chains with product
recovery is offered in [1].
As one of the first, Marin and Pelegrin [19] study a
network with reverse product flows: customers get products
at plants and return them to plants. The objective is to find
the optimal plant location and shipping quantities, such that
the costs for opening facilities and for transportation are
minimized. Marin and Pelegrin’s [19] model is an unca-
pacitated Facility Location Problem (FLP), whereas the
other models discussed in the following are capacitated
FLP.
Following [19], in this work it is assumed that customers
return their products to those facilities from which the
products are distributed. Unlike [19], in the network stud-
ied here, these facilities are not plants, but facilities for
distribution and collection of products, called distribution
and collection centres (DCCs). Furthermore, in [19] a
single product type is considered, whereas in this work
multiple product types are studied.
A remanufacturing network with multiple product types
is examined by Jayaraman et al. [15]. Used products are
shipped from collection zones to remanufacturing centres,
where they can be remanufactured or stored. Remanufac-
tured products are distributed, i.e. are used to fulfil cus-
tomer demand, or stored. The shipping quantities between
collection zones, customers and remanufacturing/distribu-
tion locations are to be determined optimally; the objective
is cost minimization.
In this work, following [15], it is assumed that returned
products can be stored at remanufacturing centres. As in
[15], the storage capacity at remanufacturing facilities is
assumed to be limited. Additional to storage capacities,
capacities for operations at facilities are planned in this
work, too.
Operative capacity equipment is studied by Schultmann
et al. [24]. The model by [24] allocates the optimal operative
capacity equipment to open facilities of an existing reverse
supply chain. The capacity at facilities is needed for opera-
tions, as e.g. inspection and sorting, of multiple product
types. The objective is to minimize costs, caused by capacity
equipment, production and distribution quantities.
Unlike in [24], in this work a closed-loop system is
studied, i.e. in addition to reverse product flows, forward
product flows are considered. Fleischmann et al. [8] and
Fleischmann et al. [9] study such a closed-loop system as a
three echelon network, consisting of warehouses, plants
and test centres, where products are recovered. These
facilities have to be located optimally, and the quantities of
the forward and reverse product flows of the network are to
be determined such that costs for opening, transport and for
unsatisfied demand and not-collected returned products are
minimized under capacity limitations for the product flows
between facilities of different network echelons.
Salema et al. [23] extend the model from [9] to study
multiple product types. Furthermore, in [23] the product
flow capacity at facilities is limited by maximum and
minimum capacity bounds for the facilities.
As in [9, 23], the CLSCN studied in this work has three
facility levels. Here, the three facility levels of the CLSCN
are DCCs, plants and suppliers and remanufacturing cen-
tres, both delivering components to plants. The production
system of the CLSCN consists of two stages: at the first
stage components are delivered from remanufacturing
centres or from suppliers to plants, where they are assem-
bled to products. This way, component remanufacturing,
unlike product remanufacturing as in [9, 15, 19, 23], with
different product and component types and component
commonality in the assembly of different product types can
be modelled.
In contrast to [9, 15, 23], the capacity for storage and
product and component flows at facilities are decision
variables, i.e. have to be determined out of a parameter
range and induce costs. In addition, capacity for the oper-
ations at facilities is determined by the model stated in this
work. Hence, the influence of different capacity types on
the facility location decisions and on the decision to pro-
duce, remanufacture, store or distribute is studied.
All studies discussed above have a single time period
planning horizon. Following [15, 21] consider inventory in
a single time period planning facility location problem and
study the trade-off between storing and distributing prod-
ucts. Further discussions of inventory in distribution net-
works and the interdependence of inventory, transportation
and facility location can be found in [21] and different
approaches to extend facility location problems by inven-
tory management can be found in [26].
In this work, the planning horizon of the CLSCN design
problem is modified to a multi-period setting, as in [22] and
[30]. Pishvaee and Torabi [22] use a multi-objective
approach to combine cost minimization of the CLSCN with
the minimization of delivery tardiness for the single pro-
duct case. In this work, the objective is to minimize costs
and the production and capacity planning problem at open
facilities in a network with multiple commodities is con-
sidered in a MILP-approach.
In this work, a FLP for a closed-loop supply chain with
component remanufacturing is extended by production
planning on an aggregate level, using the idea of APP, as in
Steinke and Fischer [30]. In APPs, the different products
are aggregated to product types and the capacities are not
product specific, but are summarized and stated in common
units, e.g. labour hours. APP is used to determine cost-
optimal manufacturing and storage plans, which match the
limited means in terms of workforce or working stations,
respectively, and production input with forecasted demand
[20]. The planning horizon of an APP can vary; usually it
Logist. Res. (2016) 9:24 Page 3 of 23 24
123
consists of 6–24 months, [3]. In particular, when adjust-
ments of capacities are allowed in each period, the periods
have to be sufficiently long.
Jayaraman [16] studies the production planning problem
of a company, which offers recovered mobile phones for a
secondary market. He states the Remanufacturing APP
(RAPP) model, which minimizes costs by determining the
optimal disassembly, disposal, remanufacturing, procure-
ment and storage quantities under fixed workforce
capacities.
In this work, the approach of [16] is followed to model
the production system. While in [16] the reverse product
flow is managed, here, a closed-loop system is studied, and
the model is extended accordingly, i.e. the remanufactured
components are reintegrated into the original supply chain
instead of being shipped to secondary markets. Moreover,
in contrast to [16], capacities in volume units and labour
hours at facilities are not fixed but can be adjusted over the
planning horizon.
In the RAPP proposed by [16] only one site for
remanufacturing is considered, whereas in this work,
multiple possible facility locations exist. Hence, the APP
for a closed-loop system is integrated into a FLP.
Extending a yearly FLP for a CLSCN with component
recovery by an APP on a monthly basis leads to a model
with extensive solution times. Furthermore, the considered
capacities cannot be adjusted within one month; especially,
decisions regarding the volume capacity are made on a
strategic level. Therefore, also the APP is extended and the
APP is modelled for a strategic, yearly, planning horizon.
With such an extended strategic planning model, deci-
sions regarding the location of facilities and their capacity
equipment for operations and storage can be studied
jointly. Furthermore, different product and component
types are considered and the interdependence of process-
ing, storing and distributing them is examined. Moreover,
by considering capacity costs and operative capacity in
addition to storage capacity, the cost effects of the deci-
sions regarding the returned products, i.e. if they are
remanufactured, stored or disposed, are captured com-
pletely unlike in facility location problems without
capacity and production planning.
Following [9, 19, 23, 30], a fixed relation between
demand and returned products is assumed in this work; the
returned product quantity is determined as a fraction of the
sold product quantity. As in [30], the CLSCN is studied
over multiple time periods, and hence, there is a time lag
between the selling and the returning of a product. In [30] it
is assumed that products are returned by customers after
one period of usage. However, products can stay longer
with the customers, i.e. the residence time of a product,
defined as the number of periods a product is used by a
customer, can be longer. Furthermore, products are
returned not only in a specific period following the buying,
but in all subsequent periods of the planning horizon. In
this work, the model in [30] is extended to capture these
aspects.
Moreover, the FLCAPPR model developed in this work
determines cost-optimal volume capacities and optimal
workforce size at the facilities for every period. In contrast,
in [31] the capacity planning is integrated in a more sim-
plified way, such that overcapacities can occur: whenever a
facility is opened, its volume capacity and workforce are
set to their respective upper limits and adjusted to the
actual required levels only in the last period. Furthermore,
while in [30] total costs are minimized, here discounting is
considered in the objective function, too.
3 Problem description
In this section the network structure of the CLSCN with
component remanufacturing is introduced and the respec-
tive planning problem is described in detail.
The CLSCN consists of nodes, which represent cus-
tomers and facilities with their operations, and arrows,
which show the flows of multiple commodities through the
network, see Fig. 1. There are five different types of nodes:
costumers, DCCs, remanufacturing centres, plants and
suppliers. Customers demand different product quantities
in each period, and they return their products to DCCs in a
later period, i.e. it is assumed that a known fraction of
products shipped to customers in one period is returned in a
later period of the planning horizon. The residence time of
products can be different, but there is a given number of
periods the product has to stay with a customer before it is
returned and considered as remanufacturable. The mini-
mum residence time can be interpreted as the minimum
number of periods a product is in full working condition.
Demand quantities are assumed as deterministic and
known; therefore, the returned product quantities are
deterministic and known, too. Demand is lost whenever it
is not met, i.e. it cannot be backlogged.
The CLSCN consists of three facility levels: DCCs,
plants, remanufacturing centres and suppliers. The latter
are summarized to one level since both provide compo-
nents. Supplier locations are given, whereas the locations
of DCCs, remanufacturing centres and plants have to be
determined. These facilities can be opened in one period
and then remain open or are closed in a later period. It is
assumed that once a facility is closed, it cannot be opened
again.
Capacities at facilities are determined in volume and
labour hours. The volume capacity restricts the volume of
commodity flows passing a facility and, if existent, the
volume of stocked products and components, respectively.
24 Page 4 of 23 Logist. Res. (2016) 9:24
123
The labour hour capacity limits the available hours of the
workforce needed for remanufacturing and assembly at
remanufacturing centres and plants, and for handling
products at DCCs.
Capacity levels at facilities are determined once a
facility is opened and can be adjusted in a later period, i.e.
they can be expanded or reduced in fixed steps in every
period.
The product and component flows through the network
are described by three different types of arrows, see Fig. 1.
The solid arrows show the forward product flows, which
are shipped from plants to DCCs and further to the cus-
tomer locations. The dotted arrows describe the component
flows leaving suppliers or remanufacturing centres,
respectively, to plants. The dashed arrows represent the
reverse product flows, i.e. the flows from customers to
DCCs and from DCCs to remanufacturing centres. In this
CLSCN redistribution is possible, i.e. products and com-
ponents can be shipped between facilities of the same type.
DCCs are bi-directional facilities, because products flow
through DCCs to customers and customers return used
products to DCCs. At DCCs returned products are col-
lected, visually inspected and, afterwards, they are shipped
either to remanufacturing centres or to the disposal unit.
The decomposition of returned products into compo-
nents and the remanufacturing of those components to an
as-new condition is performed at remanufacturing centres.
It is assumed that components can be remanufactured
repeatedly in the planning horizon, i.e. the limited number
of possible remanufacturing cycles for components is not
reached. However, there is a known and constant fraction
of components that cannot be remanufactured to the quality
standards of as-new components with a reasonable given
effort and therefore has to be disposed. Moreover, at
remanufacturing centres it is possible to store returned
products, instead of remanufacturing them immediately.
At plants, components are assembled to products of
different types. Product types differ regarding their com-
bination of components, i.e. at least one component in the
product composition has to be different in different prod-
ucts. Components can be product type-specifically or
commonly used among different product types. They are
shipped from suppliers or remanufacturing centres to plants
and can be held on inventory at plants. No final products
are stored in the studied network and products are assem-
bled only if an order exists (MTO). Since the planning
horizon is strategic, no lead-times for operations or trans-
port are considered.
For each planning period the demand and return product
quantities are known, while facility locations and capacity
equipment at the facilities, as well as procurement, trans-
portation, production and inventory quantities, have to be
determined with the objective of total cost minimization.
To support these decisions, the planning problem is for-
mulated as a MILP, presented in the next section.
4 The facility location, capacity and aggregateproduction planning with remanufacturingproblem
In this section, the planning problem described above, the
Facility Location, Capacity and Aggregate Production
Planning with Remanufacturing (FLCAPPR) Problem, is
stated and explained using the notation listed in Tables 1, 2
and 3, presented below. The model presented here is an
extension of the model given in [30], as described in Sect. 2
above.
Fig. 1 Closed-loop supply chain network
Logist. Res. (2016) 9:24 Page 5 of 23 24
123
The objective function of the FLCAPPR problem mini-
mizes the discounted total costs of the CLSCN over multiple
time periods. As the model combines multi-period facility
location, capacity and aggregate production planning, the
objective function consists of cost terms for opening, running
and closing facilities, for the volume capacity equipment and
the labour force at open facilities, for processing and storing
goods at facilities, for procuring components at suppliers, for
transporting goods in the network and for disposing returned
products and components.
Table 1 Definition of relevant
setsSet Definition
C Set of components, c 2 C
F Set of potential plants, f 2 F
FD F [ Df g, set of potential plants and the disposal unit D
K Set of customer locations, k 2 K
P Set of products, p 2 P
R Set of potential remanufacturing centres, r 2 R
RD R [ Df g, set of potential remanufacturing centres and the disposal unit D
T Set of time periods, t 2 T
V Set of potential DCCs, v 2 V
Z Set of suppliers for components, z 2 Z
Table 2 Definition of relevant variables
Variable Definition
Capyt Number of capacity steps at open facility y in period t (in m3), 8y 2 F [ V [ R; t 2 T
CCapyt Expansion or reduction of capacity steps at facility y in period t (in m3), 8y 2 F [ V [ R; t 2 T
CCapDyt Reduction of capacity steps at facility y in period t (in m3), 8y 2 F [ V [ R; t 2 T
CCapUyt Expansion of capacity steps at facility y in period t (in m3), 8y 2 F [ V [ R; t 2 T
EIfc Quantity of c remaining in the inventory of plant f at the end of the last planning period, 8f 2 F; c 2 C
EIrx Quantity of x remaining in the inventory of remanufacturing centre r at the end of the last planning period,
8r 2 R; x 2 C [ P
EXIywxt Quantity of x transported from facility y to facility w of the same echelon in period t,
8y;w 2 F [ V [ R : y 6¼ w; x 2 C [ P; t 2 T
Hyt 1; if facility y is closed in period t
8y 2 F [ V [ R; t 2 T
0; otherwise
8<
:
Ifct
Quantity of c remaining at plant f at the end of period t, 8f 2 F; c 2 C; t 2 T
Irxt Quantity of x remaining at remanufacturing centre r at the end of period t, 8r 2 R; x 2 C [ P; t 2 T
LCapyt Workforce available at facility y in period t, 8y 2 F [ V [ R; t 2 T
Ukpt
Number of unmet demand for product p of customer k in period t, 8k 2 K; p 2 P; t 2 T
Xyxt Quantity of x processed in facility y in period t, 8y 2 F [ R; x 2 C [ P; t 2 T
Xywxt Quantity of x transported from facility y to facility w in period t, 8y;w 2 FD;V ;RD; Z : y 6¼ w; x 2 C [ P; t 2 T
YyEt 1; if facility y is opened in period t;
8y 2 F [ V [ R; t 2 T
0; otherwise
8<
:
Yyt 1; if facility y is open in period t;
8y 2 F [ V [ R; t 2 T
0; otherwise
8<
:
YCCapUyt 1; if capacity of facility y is increased in
period t; 8y 2 F [ V [ R; t 2 T
0; otherwise
8<
:
24 Page 6 of 23 Logist. Res. (2016) 9:24
123
Table 3 Definition of relevant parameters
Parameters Definition
a Discount rate
acp Number of component c yielded by the remanufacturing of one product unit of p, 8p 2 P; c 2 C
bcp Number of component c needed for producing one unit of product p, 8p 2 P; c 2 C
CapOyt Maximum capacity at facility y in period t (in m3), 8y 2 F [ V [ R; t 2 T
CapUy Minimum capacity at facility y (in m3), 8y 2 F [ V [ R
ccz Unit cost for procuring component c from supplier z, 8z 2 Z; c 2 C
cDEnt Disposal cost (per unit)
cUk Unit penalty cost for unmet demand k, 8k 2 K
cxyw Cost for transportation of a unit x from y to w (per km), 8y;w 2 F;V ;R;K : y 6¼ w; x 2 C [ P
cy Unit cost for processing at facility y, 8y 2 F [ R
dyx Time required for processing a unit of x at facility y, 8y 2 F [ V [ R; x 2 C [ P
e Size of capacity step by which the locations can be extended within one period (in m3)
fcapCostyCost for capacity increase at facility y by one step, 8y 2 F [ V [ R
fcapRevyRevenue for capacity reduction at facility y by one step, 8y 2 F [ V [ R
fy Cost for opening facility y, 8y 2 F [ V [ R
fyt Cost for open facility y in period t, 8y 2 F [ V [ R; t 2 T
gx Volume of one unit of x (in m3), 8x 2 C [ P
hcf Cost per period for holding a unit of c in inventory at plant f, 8f 2 F; c 2 C
hxr Cost per period for holding a unit of x in inventory at remanufacturing centre r, 8r 2 R; x 2 C [ P
LabCapOyt Maximum labour hours available at facility y in period t, 8y 2 F [ V [ R; t 2 T
LabCapUy Minimum labour hours at facility y, 8y 2 F [ V [ R
labccy Hourly cost for workforce at facility y, 8y 2 F [ V [ R
le Labour hours per worker per period
LT Last planning time period, LT 2 T
M Sufficiently large number
mdt Minimum proportion of returned products that has to be disposed after visual inspection at the DCCs in period t, 8t 2 T
mdct Minimum proportion of component c that has to be disposed after disassembly, remanufacturing and testing in period t,
8c 2 C; t 2 T
mr Minimum number of periods before products are returned for remanufacturing
Nkpt Demand of customer k for product p in period t, 8k 2 K; p 2 P; t 2 T
qtkpo Return rate in period t of customer k for product p, sold in period o, 8k 2 K; p 2 P; ðo; tÞ 2 T ; where o� t
sfy Cost for closing facility y, 8y 2 F [ V [ R
shxr Cost for disposing a stored unit of x at remanufacturing centre r at the end of the last planning, period LT, 8r 2 R; x 2 C [ P
shcf Cost for disposing a stored unit of c at facility f at the end of the last planning period LT, 8f 2 F; c 2 C
txyw Distance of y to w (in km), 8y;w 2 F;V ;R;K : y 6¼ w; x 2 C [ P
Logist. Res. (2016) 9:24 Page 7 of 23 24
123
The discounted total costs are described by the follow-
ing objective function (1). For the sake of clarity the
objective function is split up into three different cost
functions. The first cost function presents the costs induced
by multi-period facility location, the second function
includes the costs resulting from capacity planning, and the
costs of aggregate production planning are described by the
third function. Below the functions are introduced followed
by the respective explanations.
min OF ¼ OF1 þ OF2 þ OF3 ð1Þ
with
OF1 ¼X
t2T
��
1=ð1þ aÞt�
��X
r2Rfr � Yr
Et
þX
v2Vfv � Yv
Et þX
f2Fff � Yf
Et
þX
r2Rf rt � Yr
t þX
v2Vf vt � Yv
t þX
f2Ff ft � Yf
t
þX
r2Rsfr � Hr
t þX
v2Vsfv � Hv
t þX
f2Fsff � Hf
t
þX
z2Z; c2C; f2Fðcczf � tczf þ cczÞ � Xzf
ct
þX
r2R; c2C; f2Fccrf � tcrf � Xrf
ct
þX
f2F; v2V ; p2Pcpfv � t
pfv � Xfv
pt
þX
v2V ; k2K; p2Pcpvk � t
pvk � Xvk
pt þX
k2K; p2PcUk � Uk
pt
þX
v2V ; k2K; p2Pcpkv � t
pvk � Xkv
pt
þX
v2V ; r2R; p2Pcpvr � tpvr � Xvr
pt
þ cDEnt ��
X
v2V ; p2PXvDpt þ
X
r2R; c2CXrDct
�
þX
c2C;ðr;sÞ2R:r 6¼s
ccrs � tcrs � EXIrsct
þX
p2P;ðr;sÞ2R:r 6¼s
cprs � tprs � EXIrspt
þX
c2C;ðf ;iÞ2F:f 6¼i
ccfi � tcfi � EXIfict
þX
p2P;ðv;jÞ2V:v 6¼j
cpvj � t
pvj � EXIvjpt
�
In themulti-period FLP studied in thiswork, the facilities can
be opened in one period and in the later periods they can stay
open or are closed. The variables YyEt, Y
yt andH
yt describe the
respective state of a facility. The costs for opening, i.e.
building, a facility, occur just once and are listed in line one
and two. For every period in which a facility remains open it
induces costs; these costs are captured by the terms in line
three. In line four the costs for closing a facility are stated.
The cost terms in the next line are for procuring and
shipping components from suppliers to plants. Costs for
transporting components from remanufacturing centres to
plants are listed in line six.
The transportation costs of the forward product flow, the
flow of products from plants to DCCs and from DCCs to
customers, and the penalty costs for unsatisfied demand are
stated in line seven and eight.
The cost terms in line nine and ten are the shipping costs of
the reverse product flow, i.e. the flow of products which are
returned by customers to DCCs and flow further in the net-
work to remanufacturing centres or to the disposal unit. In the
latter case, costs for disposing occur. The disposal costs for
returned products and remanufactured components are listed
in line eleven. The costs for distributing products or com-
ponents, respectively, on the same facility level are listed in
line 12–15.
OF2 ¼X
t2T
��
1=ð1þ aÞt�
��X
r2RfcapCostr � CCapUr
t
þX
f2FfcapCostf � CCapUf
t þX
v2VfcapCostv � CCapUv
t
þX
r2RfcapRevr � CCapDr
t þX
f2FfcapRevf � CCapDf
t
þX
v2VfcapRevv � CCapDv
t
�
At facilities, certain volume capacities inm3 are available and
they can be increased or decreased within one period. These
adjustments induce costs or revenues, as reflected by the cost
terms in line 1 and 2 or revenues in line 3 and 4, respectively.
OF3 ¼X
t2T
��
1=ð1þ aÞt�
��
X
r2R; c2Ccr � Xr
ct
þX
f2F; p2Pcf � Xf
pt þ le ��X
r2RlabccCostr � LCaprt
þX
f2FlabccCostf � LCapft þ
X
v2VlabccCostv � LCapvt
�
þX
r2R; p2Phpr � Irpt þ
X
r2R; c2Chcr � Irct
þX
f2F; c2Chcf � Ifct
�
þ ð1=ð1þ aÞLTÞ ��
X
f2F; c2Cshcf � EIfc
þX
r2R; p2Pshpr � EIrp þ
X
r2R; c2Cshcr � EIrc
�
24 Page 8 of 23 Logist. Res. (2016) 9:24
123
Remanufacturing components at remanufacturing centres
and assembling products at plants induces costs, see lines
one and two. Labour hours of the workforce are needed for
performing the respective operations at the facilities. The
respective costs occur in every period and are stated in line
2 and 3.
Holding products and components at remanufacturing
centres and holding components at plants induces costs,
which are captured by the cost terms in lines 4 and 5.
The costs stated in lines 1–5 occur in every period,
and hence, these costs have to summed up over the
planning horizon. At the end of the planning horizon the
remaining items on stock at the facilities are disposed,
and the respective cost terms are stated in the last two
lines.
In the following, the constraints of the problem are
presented, but before that, important variables are
explained.
The variables YyEt, Y
yt and H
yt are interrelated. If a facility
is opened in one period, then it is running in this period;
therefore, both variables YyEt and Y
yt take value 1 and H
yt is
zero.
In the next period this facility can be still open, then
Yytþ1 ¼ 1 and Y
yEtþ1 ¼ 0, because the facility is already
opened, and Hytþ1 ¼ 0. However, the open facility can be
closed in t þ 1, then Hytþ1 takes value 1, and
Yytþ1 ¼ Y
yEtþ1 ¼ 0.
It is assumed that a facility cannot be opened again after
it is closed. The constraints (2)–(6) define these
interrelations.X
t2TYyEt � 1 8y 2 F [ R [ V ð2Þ
A facility can be opened just once in the planning horizon.
YyE1 ¼ Y
y1 8y 2 F [ R [ V ð3Þ
If a facility is opened in the first planing period, it is open
in period 1.X
t2T :t� s
ðYyEt � Hy
t Þ ¼ Yys
8y 2 F [ R [ V ; s 2 T : s[ 1
ð4Þ
If a facility is opened and not closed in one of the periods
t� s, where ðs; tÞ 2 T , then the facility is open in period s.
Yyt�1 � Yy
t �Hyt 8y 2 F [ R [ V ; t 2 T : t[ 1 ð5Þ
These constraints indicate the closing of facilities by
comparing the opening indicator variables of two succes-
sive periods.
X
t2THy
t � 1 8y 2 F [ R [ V ð6Þ
Closing of facilities is allowed to happen once within the
planning horizon.
The next set of constraints, constraints (7)–(19), describes
the forward and reverse product flows in the network and the
inventory balance at plants and remanufacturing centres.X
v2VXvkpt þ Uk
pt ¼ Nkpt 8k 2 K; p 2 P; t 2 T ð7Þ
Products are shipped from DCCs to satisfy demand of
customer k for product p in period t. Unsatisfied demand is
captured by Ukpt.
X
v2VXkvpt ¼ 0 8t 2 1; . . .;mr � 1f g; k 2 K; p 2 P ð8Þ
X
v2VXkvpt ¼
Xt
o¼1
�
qtkpo �X
v2VXvkpo
�
8t 2 mr; . . .; Tf g; k 2 K; p 2 P
ð9Þ
After mr periods, products can be returned for the first
time. In period t a proportion of products sold in period o,
qtkpo, is returned to DCCs. Every returned product is col-
lected in DCCs.
Ifct ¼ Ifct�1 þ
X
z2ZXzfct þ
X
r2RXrfct
þX
i2F:i 6¼f
EXIifct �X
i2F:i 6¼f
EXIfict � Xfct
8f 2 F; c 2 C; t 2 T : t[ 1
ð10Þ
These constraints represent the inventory balance equations
for components at plants.
Irpt ¼ Irpt�1 þX
v2VXvrpt þ
X
s2R:s6¼r
EXIsrpt
�X
s2R:s6¼r
EXIrspt � Xrpt
8r 2 R; p 2 P; t 2 T : t[ 1
ð11Þ
The inventory balance equations for returned products at
remanufacturing centres are stated in (11).
Irct ¼ Irct�1 þ Xrct þ
X
s2R:s6¼r
EXIsrct
�X
s2R:s 6¼r
EXIrsct �X
f2FXrfct
8r 2 R; c 2 C; t 2 T : t[ 1
ð12Þ
Components can be stocked at remanufacturing centres, too.
The inventory balance is determined by the equations (12).
Logist. Res. (2016) 9:24 Page 9 of 23 24
123
Ifc1 ¼
X
z2ZXzfc1 þ
X
r2RXrfc1 þ
X
i2F:i 6¼f
EXIifc1
�X
i2F:i6¼f
EXIfic1 � X
fc1 8f 2 F; c 2 C
ð13Þ
Irx1 ¼ Xrx1 þ
X
s2R:s 6¼r
EXIsrx1 �X
s2R:s 6¼r
EXIrsx1
�X
f2FXrfx1 8r 2 R; x 2 C [ P
ð14Þ
The constraints (13) and (14) define the balance of the
respective inventory at the end of the first period.
IfcLT ¼ EIfc 8f 2 F; c 2 C ð15Þ
IrxLT ¼ EIrx 8r 2 R; x 2 C [ P ð16Þ
Products and components remaining in the respective
inventories at the end of the last planning period, LT, are
captured by (15) and (16).X
f2FXfvpt þ
X
j2V:j6¼v
EXIjvpt �X
j2V :j 6¼v
EXIvjpt
¼X
k2KXvkpt 8v 2 V ; t 2 T ; p 2 P
ð17Þ
Since no inventory at DCCs is allowed, every product
entering a DCC in period t also has to leave it in period t.X
v2VXfvpt ¼ Xf
pt 8f 2 F; t 2 T; p 2 P ð18Þ
There is no product inventory at plants, i.e. every assem-
bled product in a plant in period t is shipped to DCCs in the
same period.X
r2RDXvrpt ¼
X
k2KXkvpt 8v 2 V ; t 2 T ; p 2 P ð19Þ
Every returned product is shipped from DCCs either to
remanufacturing centres or to the disposal unit D.
The constraints (20) and (21) define the disposal quan-
tities in the network.
XvDpt �mdt �
X
k2KXkvpt 8v 2 V ; t 2 T; p 2 P ð20Þ
At least a proportion of mdt of the returned products has to
be disposed in period t, because of failing the inspection at
the DCCs.
mdct � Xrct �XrD
ct 8r 2 R; t 2 T ; c 2 C ð21Þ
After remanufacturing, at least a proportion of mdct of the
components does not comply with the requirements for as-
new components and is disposed.
The following constraint sets, the constraints (22)
and (23), describe the disassembly and assembly
operations at the remanufacturing centres and plants,
respectively.
Xrct ¼
X
p2Pacp � Xr
pt 8r 2 R; t 2 T; c 2 C ð22Þ
The number of as-new components, derived by disassem-
bling returned products and remanufacturing the respective
components, is defined by the equations above.
Xfct ¼
X
p2Pbcp � Xf
pt 8f 2 F; t 2 T; c 2 C ð23Þ
The number of components required for product assembly
at plants is defined by these equations.
At facilities capacity in labour hours and volume are
considered and have to be planned over the planning
horizon. The next sets of constraints, the constraints (24)–
(43), describe the capacity planning.
X
p2PdVp �
X
k2KðXkv
pt þ Xvkpt Þ
!
� le � LCapvt
8v 2 V; t 2 T
ð24Þ
The capacity level in terms of labour hours at facilities is
the product of one worker’s labour hours per period, le,
multiplied by the workforce available in t, determined by
LCapvt for DCCs. The constraints above adhere that the
labour hours needed for handling products at DCCs do not
exceed the available capacity level.X
c2CdRc � Xr
ct � le � LCaprt 8r 2 R; t 2 T ð25Þ
The labour hours used for remanufacturing at a remanufac-
turing centre cannot exceed the respective available capacity.X
p2PdFp � Xf
pt � le � LCapft 8f 2 F; t 2 T ð26Þ
At plants, capacity in terms of labour hours is needed for
assembling products. It is limited by the capacity level at a
plant.
LabCapUy � Yyt � le � LCapyt � LabCapOyt � Yy
t
8y 2 F [ V [ R; t 2 Tð27Þ
The capacity in labour hours at an open facility is restricted
by upper and lower bounds, forced by operations and the
availability of workers.X
c2Cgc � Ifct � e � Capft 8f 2 F; t 2 T ð28Þ
24 Page 10 of 23 Logist. Res. (2016) 9:24
123
The volume capacity at the facilities is a multiple of e. The
volume of components stocked at an open plant cannot
exceed its available volume capacity.X
c2Cgc � Irct þ
X
p2Pgp � Irpt � e � Caprt 8r 2 R; t 2 T
ð29Þ
At an open remanufacturing centre, the volume of stored
products and components has to comply with the volume
capacity.
X
c2Cgc �
X
z2ZXzfct þ
X
r2RXrfct þ
X
i2F:i 6¼f
EXIifct
!
� e � Capft 8f 2 F; t 2 T
ð30Þ
The volume of components flowing into a plant is restricted
by the available volume capacity.X
p2Pgp � Xfv
pt � e � Capft 8f 2 F; t 2 T ð31Þ
The product flow through a plant adheres to the volume
capacity restriction of a plant.
X
c2Cgc � Xr
ct þX
s2R:s 6¼r
EXIsrct
!
þX
p2Pgp�
X
v2VXvrpt þ
X
s2R:s 6¼r
EXIsrpt
!
� e � Caprt
8r 2 R; t 2 T
ð32Þ
The volume of the components and products flowing into a
remanufacturing centre is limited by its volume capacity
restriction.
X
c2Cgc � Xrf
ct þX
s2R:s 6¼r
EXIrsct
!
þX
p2Pgp�
X
s2R:s 6¼r
EXIrspt
!
� e � Caprt
8r 2 R; t 2 T
ð33Þ
The volume of the components and products leaving a
remanufacturing centre has to be less or equal than the
respective capacity level.
X
p2Pgp �
X
f2FXfvpt þ
X
k2KXkvpt þ
X
j2V :j 6¼v
EXIjvpt
!
� e � Capvt 8v 2 V; t 2 T
ð34Þ
The volume of products flowing through a DCC has to
comply with its capacity.
CapUy � Yyt � e � Capyt �CapOyt � Yy
t
8y 2 F [ V [ R; t 2 Tð35Þ
The volume capacity level of a facility is a multiple of
e and is limited by given upper and lower bound.
Capyt � Capyt�1 ¼ CCapyt
8y 2 F [ V [ R; t 2 T : t[ 1ð36Þ
Volume capacity at facilities can be expanded or reduced
within one period.
Capy1 ¼ CCap
y1 8y 2 F [ V [ R ð37Þ
In the first planning period, the number of capacity steps at
a facility is identical to the capacity expansion carried out
in period 1.
CCapyt �CapOyt � YCCapUyt
8y 2 F [ V [ R; t 2 Tð38Þ
The variable YCCapUyt takes value 1, if the respective
variable CCapyt is bigger than zero, i.e. the capacity of
facility y is increased in period t.
CCapyt � CCapUyt �CapOyt � ð1� YCCapUy
t Þ8y 2 F [ V [ R; t 2 T
ð39Þ
Capacity increase is assigned to the variable CCapUyt .
CCapUyt �CapOyt � YCCapUy
t
8y 2 F [ V [ R; t 2 Tð40Þ
The upper capacity bound of a facility limits the capacity
increase.
CCapyt � CCapDyt �CapOyt � YCCapUy
t
8y 2 F [ V [ R; t 2 Tð41Þ
The variable CCapDyt captures the capacity decrease.
CCapDyt � � CapOyt � ð1� YCCapUy
t Þ8y 2 F [ V [ R; t 2 T
ð42Þ
Capacity decrease at a facility cannot be higher than the
respective upper capacity bound.
YCCapUyt � Yy
t 8y 2 F [ V [ R; t 2 T ð43Þ
Capacity can just be increased at an open facility.
Logist. Res. (2016) 9:24 Page 11 of 23 24
123
Ukpt;X
kvpt ;X
vkpt ;X
vrpt ;X
zfct ;X
rct;X
rpt;X
rfct ;X
fvpt;
Xfpt;X
fct;EXI
rsct ;EXI
rspt ;EXI
fict;EXI
vjpt; I
fct; I
rct;
Irpt;EIfc ;EI
rc;EI
rp;Cap
rt ;Cap
ft ;Cap
vt ;CCapU
yt ;
LCaprt ; LCapft ; LCap
vt 2 Zþ 8p 2 P; c 2 C;
r 2 RD; k 2 K; v 2 V ; f 2 FD; z 2 Z; t 2 T
ð44Þ
Unsatisfied demand, the flows of products or components
between different echelons and between facilities of one
echelon, the produced units, the units on stock, the
capacities at the facilities and the capacity increase are
described by positive integer variables.
CCapyt 2 Z 8y 2 F [ V [ R; t 2 T ð45Þ
Variables describing the change of capacities at facilities
are integers and can be positive or negative.
CCapDyt 2 Z� 8y 2 F [ V [ R; t 2 T ð46Þ
The variables that determine the volume capacity decrease
are negative integer variables.
Yy; Yyt ;H
yt ; YCCapU
yt 2 0; 1f g
8y 2 F [ V [ R; t 2 Tð47Þ
Binary variables indicate the opening and closing of
facilities and the capacity increase.
5 Numerical analysis
In this section, the previously stated FLCAPPR model is
solved for an example data set. At first, the example, its
data and the solution are described, and then, the sensitivity
of the network to changes in the data is studied. The
influence of the cost parameters on the decision to
remanufacture is explored. Furthermore, the robustness of
the solution with respect to the quantity of returned prod-
ucts and the length of the planning horizon is examined by
varying the return rate and the number of periods in the
planning horizon. Selected interesting results are discussed.
5.1 Initial setting and solution
In the copier industry, CLSCNs as the one described in
Sect. 3 can be found. At copier manufacturer Xerox, for
example, ’’remanufactured parts are put onto the assembly
line for reuse in brand new copiers’’ [17]. Fleischmann et al
[8] study the facility location problem in a CLSCN of a
European copier remanufacturer for a single-period plan-
ning horizon.
In this paper a CLSCN for the copier industry in Ger-
many is to be designed. The product demand is assumed to
be bundled in the fifteen biggest German cities. As in [8]
the total product demand is assumed as 10 units per 1000
inhabitants, where the number of inhabitants is taken from
[29]. Furthermore, it is assumed that demand occurs in
every period of the planning horizon, since, as in [8], one
planning period equates to one year.
Costumers demand two different product types, P1 and
P2. Demand for P1 and P2 is assumed as equally high, i.e.
500 units of P1 and P2 are required, in every period.
It is possible to open DCCs and remanufacturing centres
at the demand locations. Suppliers and possible plant
locations are to be found only in the five biggest German
cities. In Fig. 2 the customer locations with their demand in
product units per planning period are given. Furthermore,
the suppliers and all possible locations for DCCs, reman-
ufacturing centres and plants are shown.
In the initial example used in this work, it is assumed
that demand for P1- and P2-products is known for five
years and remains constant over the planning horizon.
Later on, a sensitivity analysis is presented which includes
a study on the impact of varying the length of the planning
horizon.
The assembly of each product type requires one specific
component, M1 for P1- and M3 for P2-products, and one
component, M2, which is commonly used for both product
types. For simplicity the disassembly process is assumed to
be the reverse of the assembly process.
Fig. 2 Possible facility locations and the location of suppliers and
customers with their respective demand
24 Page 12 of 23 Logist. Res. (2016) 9:24
123
The return rate qtkps, where ðs; tÞ 2 T : s� t, is inde-
pendent of customer location and product type, as in [8].
The multi-period modelling framework of the FLCAPPR
model allows to model a temporal shift between the for-
ward and reverse product flows in the network of t � s ¼mr periods, i.e. a residence time of a product with a cus-
tomer can be defined. In this work a residence time of one
year is assumed. Moreover, following [8] the return frac-
tion is assumed to be 50%, i.e. in the initial setting in this
work, 50% of products shipped to the customers are
returned at the beginning of the following period. There-
fore, for 5 planning periods the return rate is
q1kp1 ¼ q3kp1 ¼ q4kp1 ¼ q5kp1 ¼ q2kp2 ¼ q4kp2 ¼ q5kp2 ¼ q3kp3
¼ q5kp3 ¼ q4kp4 ¼ q5kp5 ¼ 0
and q2kp1 ¼ q3kp2 ¼ q4kp3 ¼ q5kp4 ¼ 0:5.
The other relevant parameters of the initial example and
their values can be found in Table 4. The fraction of the
returned products that has to be disposed, i.e. leaving the
network, is 0.6, as stated in [8]. However, in the CLSCN
studied in this work, returned products and components can
be disposed; therefore, here the sum of the fractions of
returned products md and components mdc that has to be
disposed is set to 0.6, i.e. md ¼ mdc ¼ 0:3. The trans-
portation costs in the network cpvk, c
pkv, c
pvr, c
crf , c
czf and c
pfv
are taken from [8]. It is assumed that the costs for shipping
goods between facilities of the same type are identical; the
distances between the locations are taken from [10].
The cost difference between the procurement costs cczand remanufacturing costs cr is assumed as 10 MU per
component, as described in [8]. Disposal costs cDEnt and
shxy; 8y 2 F [ R; x 2 C [ P are taken from [8] as well.
Following Silver’s [27] recommendations the inventory
holding costs hpr ¼ hcr ¼ hcf ; 8p 2 P; r 2 R; c 2 C; f 2 F are
assumed as 0.25 MU per unit per year.
The opening costs for the facilities, fv, ff and fr; are
taken from [8]. The costs and revenues for capacity
adjustments are based on these costs and assumed as
fcapCosty ¼ fcapRevy ¼ 1000 MU. This assumption is dis-
cussed in the following sensitivity analysis.
The volume capacity can be adjusted in steps of 1000
units. The lower volume capacity limits at facilities are
1000 m3; an open facility has to be equipped at least with
one volume capacity step. The capacity upper bound is
chosen such that one open DCC, remanufacturing centre
and plant is sufficient for the total product or component
flow, respectively.
It is assumed that capacity in labour hours can be
increased or decreased, respectively, by multiples of 1610
h. This results from the following calculation: in Germany
contractual labour hours per week often are 35 h. The
holiday entitlement is six weeks per calendar year.
Therefore, the number of labour hours of one worker per
year is ð52� 6Þ (’’working’’ weeks in a year) � 35 (hours
per week) ¼ 1610 (hours per year), neglecting public
holidays and downtime due to sickness.
The FLCAPPR problem with the described data setting
can be solved by the optimization software Gurobi 6.5.0 on
a two 3.10 GHz Intel Xeon Processor E5-2687W and 128
GB RAM computer in 197.71 seconds. The total dis-
counted costs are 19,534,389.05 MU.
In the solution, only one DCC and one plant are used;
both are located in Berlin and are open during the total
planning horizon. The open facilities and their capacity
equipments in the planning periods can be found in Fig. 3.
In every planning period products are shipped from the
open DCC in Berlin to the customers to meet their demand.
The products at the DCC originate from the plant in Berlin,
where these product quantities are assembled in every
period using components that are delivered from the sup-
plier in Berlin. In Fig. 4 the product and component flows
in the network are depicted.
The workforce and volume capacity at the open plant is
at the same level for every period, see Fig. 3, because in
every planning period the same amount of products and
components, respectively, are processed at the plant.
Since in the second period customers start to return
products at the DCC in Berlin, the workforce and volume
capacity at the DCC is increased from the first to the second
period, see Fig. 3. The customer demand and the amount of
products which are returned by customers remain the same in
the following periods, therefore, the workforce and volume
capacity at the DCC stay at the same level for the remaining
periods of the planning horizon.
Every returned product is collected in the DCC in Berlin
and then disposed. There is no open remanufacturing centre
in the network and no component remanufacturing takes
place in any period.
It is difficult to compare the results of the initial example
with previous studies of FLPs with reverse product flows,
e.g. in [8], since the planning problem is extended in this
work. Hence, additional parameters had to be introduced
and, therefore, the planning problems differ.
However, it is to be noticed that the solution of the
single-period facility location model presented in [8] rec-
ommends to open remanufacturing locations and that
recovered products should be used to meet demand, which
is different from the solution of the initial example of the
FLCAPPR problem in this work. Due to the fact that in the
multi-period approach taken here costs for volume capacity
Logist. Res. (2016) 9:24 Page 13 of 23 24
123
Table 4 Definition of parameter data
Parameter Value
a 0.01
CapOyt 500,000 m3, 8y 2 F [ R; t 2 T
CapOvt 800,000 m3, 8v 2 V ; t 2 T
CapUy 1000 m3, 8y 2 F [ R [ V ; t 2 T
ccz 10 MU per component, 8c 2 C; z 2 Z
cDEnt 2.5 MU per unit
cUk 1000 MU per unit, 8k 2 K
ccyw 0.0030 MU per km, 8c 2 C; y 2 Z [ R; w 2 F
cpvk
0.01 MU per km, 8p 2 P; v 2 V ; k 2 K
cpkv
0.005 MU per km, 8p 2 P; v 2 V ; k 2 K
cpvr 0.003 MU per km, 8p 2 P; v 2 V ; r 2 R
cpfv
0.0045 MU per km, 8p 2 P; v 2 V ; f 2 F
cf 1 MU per unit, 8f 2 F
cr 0 MU per unit, 8r 2 R
dVp 0.5 h, 8p 2 P
dRc 2 h, 8c 2 C
dFp 1 h, 8p 2 P
e 1000 m3
fcapCosty1000 MU, 8y 2 F [ V [ R
fcapRevy1000 MU, 8y 2 F [ V [ R
fr 500,000 MU, 8r 2 R
ff 5,000,000 MU, 8f 2 F
fv 1,500,000 MU, 8v 2 V
fyt 10,000 MU, 8y 2 F [ V [ R; t 2 T
gp 10 m3, 8p 2 P
gc 2 m3, 8c 2 C
hxr 0.25 MU per unit, 8x 2 C [ P; r 2 R
hcf 0.25 MU per unit, 8c 2 C; f 2 F
LabCapOyt 1,000,000 h, 8y 2 F [ V [ R; t 2 T
labccy 15 MU per hour, 8y 2 F [ V [ R
le 1610 h
md 0.3
mdc 0.3, 8c 2 C
mr 1
sfy 50,000 MU, 8y 2 F [ V [ R
shxy 2.5 MU per unit, 8y 2 F [ R; x 2 C [ P
24 Page 14 of 23 Logist. Res. (2016) 9:24
123
and workforce are included which were not considered in
[8] remanufacturing becomes less attractive and according
to the FLCAPPR model, opening a remanufacturing centre
and remanufacturing components is not cost-optimal.
5.2 Sensitivity analysis
In this section the sensitivity of the network structure to
changes in the data is studied. First, the impact of the cost
parameters on the decision to remanufacture is examined.
Then the effect of the return rate on the network design is
studied. Thereafter, the length of the planning horizon is
varied and the influence on the network design and espe-
cially on the remanufacturing decision is discussed.
Due to rather extensive computing times the following
tests were implemented allowing an optimality gap of up to
0:01%. The exceptional cases are marked.
5.2.1 Influence of cost parameters
By extending the FLP to a multi-period planning problem
in which facility locations, capacities and aggregate pro-
duction are optimized, additional cost parameters are
introduced in the objective function. In this section the
impact of these cost parameters on the decision to reman-
ufacture is studied.
Therefore, in the following fcapCostr ; labccr; frt and cr;
8r 2 R; t 2 T , i.e. the cost parameters for volume capacity
and labour hours at the remanufacturing centres, for open
remanufacturing centres and for remanufacturing, are var-
ied, and the results are discussed.
Influence of volume capacity cost parameters
In previous facility location models in networks with pro-
duct recovery, as i.e. in [8], the capacity level of a facility
is assumed as given and it is not cost-optimally determined.
Without taking into account costs for volume capacity,
over-capacities in the network can occur.
Furthermore, the capacity requirements resulting from
the flow of goods in a network with product recovery,
especially the increased capacity requirements induced by
the returned product flow additional to the requirements of
forward product flows, are not considered as costs in the
decision problem. In the FLCAPPR model building up
volume capacity at a remanufacturing centre leads to costs;
it is weighted with fcapCostr ; 8r 2 R, in the objective
function.
In the initial example this cost is assumed as 1000 MU.
Since in the solution of the initial example it is cost-opti-
mal to dispose returned products and procure all compo-
nents from a supplier, now the capacity cost is decreased to
study if it has an impact on the remanufacturing decision.
The solution of the initial example stays optimal until
fcapCostr ¼ 400; 8r 2 R. When fcapCostr � 400 MU, no rea-
sonable solutions are obtained. Now, it is optimal to open
every remanufacturing centre in periods 2–5, and volume
capacity is built up in one period and removed in the
•B
Open DCC in every period Open plant inevery period
t CapV1 463,000 m³2 695,000 m³3 695,000 m³4 695,000 m³5 695,000 m³
t CapF1 463,000 m³2 463,000 m³3 463,000 m³4 463,000 m³5 463,000 m³
t LabCapV1 24,150 hours2 35,420 hours3 35,420 hours4 35,420 hours5 35,420 hourst LabCapF1 46,690 hours2 46,690 hours3 46,690 hours4 46,690 hours5 46,690 hours
Fig. 3 Open facilities with their capacity levels
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Open DCC
Open plant
DD
B
HH
HB
H
L
DOE
DU
D
K
F
N
M
S
•
Foward and reverse product flow
Component flow
Fig. 4 Product and component flows in the network
Logist. Res. (2016) 9:24 Page 15 of 23 24
123
following period again and again over the planning horizon
to gain the revenues from the volume capacity decrease,
since fcapRevr ¼ 1000[ 400 ¼ fcapCostr . No returned prod-
ucts are processed at any remanufacturing centre. This
solution is hardly realistic and shows that the parameters
fcapCostr and fcapRevr have to be carefully determined.
Decreasing both parameters fcapCostr and fcapRevr down
to zero has no influence on the network, especially it
remains optimal to dispose every returned product instead
of opening remanufacturing centres and processing
returned products.
Influence of labour hour cost parameter
In previous studies, as in [8], the workforce at facilities
necessary for the respective operations at the facilities is
not considered. However, the decisions to open a reman-
ufacturing centre and to remanufacture components are
interrelated. For remanufacturing, workforce at a remanu-
facturing centre is needed whose labour hours cost money.
In this work, the workforce at facilities induces costs that
are taken into account in the objective function.
It is assumed that a labour hour at the remanufacturing
centre costs labccr ¼ 15 MU, 8r 2 R. The impact of this
cost parameter on the decision to remanufacture is studied
in the following.
It turns out that for every value of labccr [ 0 the
solution of the initial example remains cost-optimal.
However, setting this parameter to zero has an impact on
the network design. Now, it is cost-optimal to open a
remanufacturing centre in the second period additional to
the DCC and the plant in Berlin; the remanufacturing
centre remains open for the remaining periods. The net-
work and the open location with the respective capacity
equipment are shown in Fig. 5.
The total discounted costs are 19,345,018.28 MU. With
no labour hour cost at the remanufacturing centre, returned
products are shipped to the remanufacturing centre. There
returned products are stored or disassembled, and suit-
able components are remanufactured and used for product
assembly at the plant. The processed and stored quantities
are mapped in Figs. 6 and 7, respectively. In period 2-4 the
distribution quantities between the DCC and remanufac-
turing centre are the same, in the last period the reverse
product flow between the DCC and the remanufacturing
centre is lower: less P2-products are transported to the
remanufacturing centre. Since the quantity of products
returned from customers stays the same from the second to
the last period, the quantity of returned P2-products which
are disposed is increased and at the remanufacturing centre
less P2-products are disassembled in period 5. Therefore,
over the total planning period just 24.48% of the compo-
nents instead of the maximal possible 24.5% of the
components used at the plant for product assembly are
from the remanufacturing centre, the other components are
procured from the supplier in Berlin. (The maximum per-
centage results from the limited number of returned prod-
ucts, which in turn results from the return rate.)
The workforce at the remanufacturing centre is set at the
highest possible level in the second until the last period, see
Fig. 8, because workforce induces no labour hour costs
(labccr ¼ 0).
The volume capacity at the remanufacturing centre is
determined cost-optimally at 227,000 m3 for the second
until the fourth period. In the last planning period the
capacity is reduced by one step, thus 1000 m3, to obtain
revenues for capacity reduction. To comply with this
reduced volume capacity the returned product quantity
shipped to the remanufacturing centre is slightly decreased,
as the processed quantities at the remanufacturing centre,
see Fig. 6. Hence, the decisions regarding the volume
capacity level and the processed quantities at the remanu-
facturing centre and the reverse product flows in the net-
work are interrelated.
The capacity equipments of the plant and the DCC in
Berlin stay at the same levels as in the initial example,
because the product flows between the plant and the DCC
and between the DCC and the customers are not influenced
by the labour hour costs at the remanufacturing centre.
Furthermore, if a remanufacturing centre is opened, this
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Open remanufacturingcentre in period 2-5Open DCC Open Plant
DD
B
HH
HB
H
L
DOE
DU
D
K
F
N
M
S
•
Foward and reverse product flowReverse product flowComponent flow
Fig. 5 Network with no labour hour costs for remanufacturing,
labccr ¼ 0; 8r 2 R
24 Page 16 of 23 Logist. Res. (2016) 9:24
123
does not have an impact on the DCC and plant location nor
on their capacity equipment.
Influence of costs for open remanufacturing centres
The FLCAPPR model optimizes the CLSCN over multiple
periods. It is assumed that a facility in this network can be
opened in any period and in the later periods the open
facility can be closed or stay open.
The opening costs are taken from [8] and the cost per
period for an open remanufacturing centre,
f rt ; 8r 2 R; t 2 T , are assumed in the initial example as
10,000 MU. In the initial example no remanufacturing
centre is opened. To study if and how this cost influences
this decision, the cost is decreased until f rt ¼ 0.
At f rt ¼ 0 it is still not cost-optimal to open a remanu-
facturing centre. Hence, decreasing the cost parameter
f rt ; 8r 2 R; t 2 T has no impact on the decision to open a
remanufacturing centre under this data setting.
Influence of remanufacturing cost parameter
As in [8], the difference between the remanufacturing and
procurement costs cr; 8r 2 R and ccz ; 8c 2 C; z 2 Z,
respectively, is assumed as 10 MU, that is cr ¼ 0; 8r 2 R
and ccz ¼ 10 MU; 8c 2 C; z 2 Z. The solutions presented in
[8] recommend remanufacturing of copiers unlike the solu-
tion of the initial example in this work. In this section it is
studied, if and how the remanufacturing costs in relation to
the procurement costs influence the remanufacturing
decision.
The FLCAPPR problem is solved with different values
for cr; 8r 2 R. Since no remanufacturing takes place at
cr ¼ 0; 8r 2 R, just negative values of cr; 8r 2 R are
studied, i.e. remanufacturing a component is subsidized.
For every 0[ cr [ � 30 MU; 8r 2 R the solution
remains the same as described in the solution of the initial
example. From cr ¼ �30 MU; 8r 2 R it is cost-optimal to
remanufacture. Hence, a difference of 40 MU between the
remanufacturing and procurement costs is necessary in
order to make remanufactured components preferable to
procured components. Because costs for volume capacity
and workforce are included in the FLCAPPR model, this
difference has to be bigger than in other studies where
these costs are ignored, e.g. in [8]. At cr ¼ �30 MU ; 8r 2R a remanufacturing centre in Berlin is opened in the
second period and stays open in the remaining periods.
Like in the solution of the initial example a DCC and a
plant in Berlin are open in every planning period. The
network and capacity levels at open facilities are mapped
in Fig. 9. The total discounted costs are 19,346,946.96 MU,
i.e. costs can be slightly decreased.
The capacity level and product flows between the plant
and the DCC and the DCC and the customers remain as in
2 3 4 5Disassembled P1-products 8096 8100 8100 8100Disassembled P2-products 8097 8100 8100 8043Remanufactured M1-components at plant 5667 5670 5670 5670
Remanufactured M2-components at plant 11335 11340 11340 11300
Remanufactured M3-components at plant 5667 5670 5666 5634
0
2000
4000
6000
8000
10000
12000
Period
Fig. 6 Processed quantities at remanufacturing centre,
labccr ¼ 0; 8r 2 R
2 3 4 5Stored returned P1-products 3 2 1 0Stored returned P2-products 2 1 0 0
0
1
2
3
Period
Fig. 7 Stored product quantities at remanufacturing centre,
labccr ¼ 0; 8r 2 R
Open remanu-facturing centrein period 2 - 5Open DCC in every period Open plant inevery period
t CapV1 463,000 m³2 695,000 m³3 695,000 m³4 695,000 m³5 695,000 m³
t CapF1 463,000 m³2 463,000 m³3 463,000 m³4 463,000 m³5 463,000 m³
t CapR2 227,000 m³3 227,000 m³4 227,000 m³5 226,000 m³
t LabCapV1 24,150 hours2 35,420 hours3 35,420 hours4 35,420 hours5 35,420 hourst LabCapF1 46,690 hours2 46,690 hours3 46,690 hours4 46,690 hours5 46,690 hours
t LabCapR2 999,810 hours3 999,810 hours4 999,810 hours5 999,810 hours
B•
Fig. 8 Open facilities with their capacity levels for labccr ¼ 0; 8r 2 R
Logist. Res. (2016) 9:24 Page 17 of 23 24
123
the solution of the initial example, see Fig. 4. However,
there is a product flow between the DCC and the reman-
ufacturing centre in Berlin, as shown in Fig. 5.
From the second until the last period products collected
at the DCC are shipped to the remanufacturing centre. At
the remanufacturing centre the returned products are stored
and disassembled to components and suitable components
are remanufactured. After remanufacturing, the compo-
nents are shipped to the plant. The processed and stored
quantities at the remanufacturing centre are mapped in
Figs. 10 and 11, respectively.
Every remanufacturable returned product and compo-
nent is processed at the remanufacturing centre and then
shipped from the remanufacturing centre to the plant, i.e.
there are no items on inventories at the end of period 5.
In addition to remanufactured components, components
have to be procured from the supplier in Berlin; only
24.5% of the components used in the product assembly are
remanufactured components. Compared to the solution of
the previous section for labccr ¼ 0; 8r 2 R, this fraction is
slightly increased. For cr ¼ �30; 8r 2 R every remanu-
facturable product is processed at the remanufacturing
centre.
There is an interrelation between the decisions to store
and process products and the capacity equipment at the
remanufacturing centre, as the capacity levels at the
remanufacturing centre are adapted to the requirements of
the processed and stored quantities, see Figs. 10 and 11. By
storing products from the second to the fourth period
instead of processing them immediately at the remanu-
facturing centre, less workforce is necessary at the
remanufacturing centre in these periods, see Fig. 9. How-
ever, due to building up inventory at the remanufacturing
centre from the second until the fourth period, more vol-
ume capacity is necessary in the fifth period; in the last
period the capacity has to be increased to comply with the
increased volume requirements. In the last planning period
all items on inventory are processed, therefore, the work-
force in the last period is increased, too, see Fig. 9.
5.2.2 Influence of return rate
The FLCAPPR model is solved with different values for
qtkps; 8 k 2 K; p 2 P; ðs; tÞ 2 T : s� t, i.e. with return rates
from 0 to 1, increasing in steps of 0.1. The respective total
discounted costs and selected decision variable values for
the results can be found in Fig. 12.
When there are no returned products at all, a plant and
DCC are opened in Berlin, but of course no remanufac-
turing centre is opened. The total discounted costs are
•B
Open remanu-facturing centrein period 2-5Open DCC in every period Open plant inevery period
t CapV1 463,000 m³2 695,000 m³3 695,000 m³4 695,000 m³5 695,000 m³
t CapF1 463,000 m³2 463,000 m³3 463,000 m³4 463,000 m³5 463,000 m³
t CapR2 227,000 m³3 227,000 m³4 227,000 m³5 228,000 m³
t LabCapV1 24,150 hours2 35,420 hours3 35,420 hours4 35,420 hours5 35,420 hourst LabCapF1 46,690 hours2 46,690 hours3 46,690 hours4 46,690 hours5 46,690 hours
t LabCapR2 64,400 hours3 64,400 hours4 64,400 hours5 66,010 hours
Fig. 9 Network with negative remanufacturing costs,
cr ¼ �30; 8r 2 R
Fig. 10 Processed quantities at remanufacturing centre,
cr ¼ �30; 8r 2 R
2 3 4 5Stored returned P1-products 9 8 107 0Stored returned P2-products 89 188 187 0
0
50
100
150
200
Period
Fig. 11 Stored product quantities at remanufacturing centre,
cr ¼ �30; 8r 2 R
24 Page 18 of 23 Logist. Res. (2016) 9:24
123
18, 266, 247.79 MU and, hence, lower than before, as no
transportation and other costs for returned products occur.
For every return rate from 0 to 1, the decision regarding
the opening and the capacity equipment of the plant
remains the same. Moreover, for every return rate no
remanufacturing centre is opened, every returned product is
disposed and every component used in the product
assembly is procured from the supplier in Berlin.
The total discounted costs of the CLSCN increase with
the return rate, see Fig. 12. This cost increase is induced by
higher capacity and by disposal and opening costs due to an
increased quantity of returned products which are collected
in the DCCs and disposed afterwards.
Due to the assumption that returned products have to be
collected at DCCs, the return rate has an influence on the
capacity equipment at the DCC and the opening decision
regarding DCCs, as every returned product flows through a
DCC and requires handling times and space, see Fig. 12.
For a return rate between 0.8 and 1 the volume capacity of
one DCC is not sufficient any more; therefore, a DCC in
Dortmund is opened additional to the DCC in Berlin. The
resulting network with the product and component flows is
displayed in Fig. 13.
From the DCC in Dortmund products are shipped to
customers in Dortmund, Duisberg, Dusseldorf, Essen,
Frankfurt am Main and Cologne in every planning period,
and in the first period the demand of customers in Stuttgart
is met by products from the DCC in Dortmund. The
remaining customers receive their products from the DCC
in Berlin.
Some reverse product flows are different from the for-
ward product flows. Customers in Bremen and Hannover
return their products to the DCC in Dortmund, although
they get products from the Berlin DCC. The other cus-
tomers return their products to the DCC which delivered
the product.
The results show that the reverse product flow influences
the forward product flow and the optimal network
structure, if the quantity of returned products is high, as in
[8]. Therefore, the forward and reverse product flows have
to be planned simultaneously in order to achieve an optimal
network.
Moreover, it turns out that a higher quantity of returned
products increases the total costs, but does not necessarily
result in a network with remanufacturing. There is no
return rate at which it is cost-optimal to open a remanu-
facturing centre and use remanufactured components in the
product assembly under the initial data setting, in particular
for the assumed cost parameters.
Now, it is examined which results occur when it is cost-
optimal to open a remanufacturing centre and to remanu-
facture all suitable components and the return rate is
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1Labour Hours at DCCs in period 1 24150 24150 24150 24150 24150 24150 24150 24150 24150 24150 24150Labour Hours at DCCs in period 2-5 24150 25760 28980 30590 33810 35420 37030 40250 41860 45080 46690Capacity at DCCs in 1 in m3 463000 463000 463000 463000 463000 463000 463000 463000 463000 463000 463000Capacity at DCCs in 2 - 5 in m3 463000 510000 556000 602000 648000 695000 741000 787000 834000 880000 926000Sum of disposed returned products 0 18530 37024 55536 74048 92560 111072 129584 148096 166608 185120Total Cost in MU 18266248 18482777 18792549 19008088 19317860 19534389 19749928 20059700 21562548 21858757 22060733
01000002000003000004000005000006000007000008000009000001000000
0
5000000
10000000
15000000
20000000
25000000
Return rate
Fig. 12 Variation of return rate with cr ¼ 0; 8r 2 R
•
•
•
•
•
•
•
•
•
•
•
•
•
•DD
B
HH
HB
H
L
DOE
DU
D
K
F
N
M
S
•
Foward Product flow
Component flow
Reverse product flow in period 1-5
Foward Product flowin period 1Foward Product flowin period 2-5
Fig. 13 Network with two DCCs for qtkps ¼ 0:8; 0:9; 1f g
Logist. Res. (2016) 9:24 Page 19 of 23 24
123
varied. Therefore, the FLCAPPR model is solved with cr ¼�30; 8r 2 R and for return rates from 0 to 1, increasing in
steps of 0.1. The respective total discounted costs of the
resulting network and selected decision variable values for
the results can be seen in Fig. 14.
The total discounted costs increase with the return rate,
like in the study with cr ¼ 0; 8r 2 R. However, for cr ¼�30; 8r 2 R the cost increase for 0:4� qtkps � 1 is slightly
smaller, see Fig. 15.
At return rates qtkps\0:4, every returned product is
disposed and the network consists of a DCC and plant in
Berlin, as in the solution of the initial example. Unlike in
the study with cr ¼ 0, with cr ¼ �30 an increase of the
return rate has an impact on the decision to open a
remanufacturing centre and to remanufacture components.
For values of qtkps ¼ 0:4 to qtkps ¼ 1, a remanufacturing
centre in Berlin is opened in the second period which stays
open over the remaining planning periods. For these return
rates, the respective maximal possible amount of compo-
nents is remanufactured and used in the product assembly
instead of procured components. Because remanufactured
components are cheaper production inputs than procured
components, for these return rates the total cost increase in
the study with cr ¼ �30 is smaller than for the study with
cr ¼ 0 where no remanufacturing takes place, see Fig. 15.
For 0:4� qtkps � 0:7, it is cost-optimal to ship returned
products from the DCC in Berlin to the remanufacturing
centre in Berlin. The remanufactured components are used
in the product assembly in the plant in Berlin. The network
for these return rates was shown already in Fig. 5.
As can be seen in Fig. 14, the capacity level at the
remanufacturing centre increases with the return rate, i.e.
with the quantity of returned products. Over the planning
periods the capacity levels at the remanufacturing centre
can change, too. This happens when returned products are
stored and remanufactured in a later period, instead of
being remanufactured immediately.
The capacity levels at the DCC increase with the return
rate, too. At qtkps ¼ 0:8; 0:9; 1f g two DCCs, a DCC in
Berlin and Dortmund, have to be opened to have enough
capacity for the returned products, as in the study with
cr ¼ 0. The opening costs for the second DCC cause the
jump in the total costs, see Fig. 15. The location of the
remanufacturing centre and the plant stays at Berlin.
This analysis has shown that opening a remanufacturing
centre and using remanufactured components in the pro-
duct assembly is cost-optimal under specific remanufac-
turing costs and only if the return rate is high enough,
qtkps � 0:4. Moreover, high return rates, qtkps ¼ 0:8; 0:9; 1f g,influence the network design and the distribution system,
whether remanufacturing is cost-optimal or not.
5.2.3 Influence of the number of planning periods
In contrast to previous facility location models with reverse
product flows the FLCAPPR model optimizes the CLSCN
over multiple periods instead of a single period. A period is
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8* 0.9** 1***Labour Hours at rem. centre in 2 & 3 0 0 0 0 51520 64400 77280 90160 103040 115920 128800Labour Hours at rem. centre in 4 0 0 0 0 51520 64400 77280 91770 104650 117530 130410Labour Hours at rem. centre in 5 0 0 0 0 51520 66010 78890 90160 64400 74060 80500Capacity at rem. centre in 2 & 3 in m3 0 0 0 0 182000 227000 272000 317000 363000 408000 453000Capacity at rem. centre in 4 in m3 0 0 0 0 182000 227000 272000 319000 364000 410000 455000Capacity at rem. centre in 5 in m3 0 0 0 0 178000 228000 273000 316000 225000 258000 280000Sum of rem. components 0 0 0 0 72128 90708 108754 126786 131294 148198 163976Sum of disp. ret. products 0 18512 37024 55536 22528 27768 33390 39022 54314 60751 67993Solution times in seconds 33 2530 2211 1739 2486 1368 1833 1641 8634 418270 431468Total cost in MU 18266248 18482777 18792549 19008088 19274525 19346947 19417848 19581710 20991910 21149822 21214104
050000100000150000200000250000300000350000400000450000500000
0
5000000
10000000
15000000
20000000
25000000
Return Rate Interrupted at:* 0,09% ** 0,22% ***0,19%
Fig. 14 Variation of return rate with cr ¼ �30; 8r 2 R
0200000400000600000800000
1000000120000014000001600000
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
MU
Return rate
Cost increase with cr = -30 Cost increase with cr = 0
Fig. 15 Cost increase by variation of return rate with cr ¼ 0; 8r 2 R
and cr ¼ �30; 8r 2 R
24 Page 20 of 23 Logist. Res. (2016) 9:24
123
assumed as one year, and the length of the planning hori-
zon can be interpreted as the product life-cycle. In the
initial example the CLSCN is planned over 5 periods. In
this section, the impact of the length of the planning
horizon on the network is studied; therefore, the number of
periods is varied.
The total discounted costs, the satisfied product demand
and the disposed returned products over a planning horizon
of 2–7 periods are listed in Fig. 16.
It is assumed that demand and return rate remain the
same over the planning horizon. The structure of the
solution of the initial example remains optimal, i.e. the
network stays the same for an increased number of periods
in the planning horizon. Especially, the decision to procure
the components for the product assembly instead of
remanufacturing components stays the same for the dif-
ferent length of the planning horizon under this data
setting.
The capacity costs and the costs for open facilities rise when
the number of periods is increased. Moreover, since products
and components have to be transported, processed and pro-
cured, respectively, these costs increase with the number of
planning periods, too. Hence, the total discounted costs grow
when the planning periods are increased, see Fig. 16.
It is examined if the length of the planning horizon does
not influence the network design and the production and
stored quantities in the network, if remanufacturing is cost-
optimal. Therefore, the FLCAPPR model is solved with
cr ¼ �30; 8r 2 R for planning horizons of 2–7 periods.
The total discounted costs and selected interesting decision
variables are mapped in Fig. 17.
Increasing the planning horizon to six and seven periods
results in the same network as in the solution with 5
periods, which was already described above. In this solu-
tion, remanufacturing takes place at an open remanufac-
turing centre in Berlin, see Fig. 5.
Decreasing the planning horizon of 5 periods by just one
period, to 4 periods, changes the network design. Now, it is
cost-optimal to procure every component for the product
assembly from the supplier in Berlin instead of remanu-
facturing components. The resulting network is as in the
solution of the initial example, where only a DCC and plant
in Berlin are opened and both stay open over the planning
horizon.
765432Total satisfied product demand 92560 138840 185120 231400 277680 323960Total disposed returned products 23140 46280 69420 92560 115700 138840Solution times in seconds 700 340 493 198 343 846Total cost in MU 12320122 14748845 17153521 19534389 21891684 24225639
0
50000
100000
150000
200000
250000
300000
350000
0
5000000
10000000
15000000
20000000
25000000
30000000
Number of planning periods
Fig. 16 Variation of planning horizon length with cr ¼ 0; 8r 2 R
2 3 4 5 6 7Total satisfied product demand 92560 138840 185120 231400 277680 323960Total disposed returned products 23140 46280 69420 27768 34808 41838Solution times in seconds 10 646 729 1368 20529 4341Total rem.components used in assembly 0 0 0 90708 113248 135797Total cost in MU 12320122 14748845 17153521 19346947 21482068 23596497
0
50000
100000
150000
200000
250000
300000
350000
0
5000000
10000000
15000000
20000000
25000000
Number of planning periods
Fig. 17 Variation of planning horizon length with cr ¼ �30; 8r 2 R
Logist. Res. (2016) 9:24 Page 21 of 23 24
123
Hence, the number of periods in the planning horizon
has an impact on the network design and the decision to
remanufacture. A multi-period planning approach in con-
trast to a single-period approach, as in [8], for a CLSCN is
useful and leads to new and different results. Therefore, the
relevant number of periods has to be determined and the
network has to be analysed over this planning horizon.
6 Conclusions and future research directions
In this work, the strategic CLSCN design is extended by
capacity and production planning on an aggregate level.
The resulting FLCAPPR model determines the cost-opti-
mal network design, the facility locations and capacity
equipment at open facilities, and the cost-optimal pro-
curement, production and distribution quantities in the
CLSCN over a finite planning horizon consisting of mul-
tiple periods. It is solved for an example from the copier
industry with input data based on previously published
research [8]. Furthermore, possible effects of the extended
planning approach on the network design, especially on the
decision to recover returned products, are studied in a
sensitivity analysis. Thereafter, the robustness of the net-
work design and the production and distribution quantities
regarding the return rate, i.e. the quantity of returned
products, is examined. In a further study the influence of
the planning horizon length is investigated.
Extending a single-period FLP to the FLCAPPR model
leads to new and different results concerning the decision
to remanufacture and the effect of the return rate on the
network. In contrast to a previous study [8], in this setting,
it is cost-optimal to dispose returned products instead of
recovering them and use the resulting components in the
product assembly based on the FLCAPPR model. When
capacity costs, especially labour hour costs at the reman-
ufacturing centre, are included, remanufacturing is cost-
optimal only if the remanufacturing costs are sufficiently
low compared to the procurement costs for new compo-
nents from suppliers. Hence, production costs, in particular
remanufacturing costs, have a large impact on facility
location and capacity equipment decisions. Furthermore,
the interdependence between the capacity equipment at the
remanufacturing centre and the procuring decision, the
processing and storing quantities at the remanufacturing
centre is determined. Hence, these decisions have to be
optimized jointly, as in the FLCAPPR model.
The decisions regarding facility locations and capacity
equipment are robust for low return rates. From return rates
of 40% remanufacturing takes place, if remanufacturing
costs are sufficiently low. Moreover, for high return rates,
rates of 80% and more, the facility location decisions and
the distribution system are changed compared to the results
for lower rates. Therefore, the forward and reverse product
flows in the network have to be planned together.
The multi-period setting of the FLCAPPR model
enables a study of the influence of the planning horizon on
the decision to remanufacture and provides new informa-
tion compared to single-period FLPs, as in [8]. Product
recovery is cost-optimal only if remanufacturing costs are
sufficiently low compared to procurement costs and the
planning horizon is sufficiently long. For the studied data
setting, this means that there has to be product demand for
at least 5 periods, i.e. five years; only then remanufacturing
can be cost-optimal.
Following the CLSC-Management definition in [12], a
CLSCN has to be studied over the total product life-cycle
with consideration of varying demand and returned product
quantities and qualities. Hence, in the future the FLCAPPR
problem should be solved with data sets consisting of
varying demand and returned product quantities in order to
study possible product life-cycle effects.
Moreover, when residence times are longer than one
period, the reverse product flow starts later in the planning
horizon. This can affect decisions regarding the facility
locations and capacity equipment and, therefore, the
remanufacturing decision. Hence, different assumptions
regarding the residence times of products should be
examined in the future.
Linear costs and revenues for adjusting capacity are
assumed here, and the effects of economies of scale and
learning effects gained by higher production quantities and
bigger facilities are not considered. Furthermore, the pos-
sibilities to increase or decrease labour hours at facilities by
overtime or part-time, respectively, is not modelled. These
aspects require further model extensions, but it has to be
noted that the FLCAPPR model is already large scale with
rather lengthy solving times.
Finally, uncertainties regarding the quantity and quality
of reverse product flows are an issue of CLSCM [11–13].
They are not considered here, because an APP framework
is used. However, other approaches integrating uncertain-
ties might be developed; this is left for future research.
Open Access This article is distributed under the terms of the
Creative Commons Attribution 4.0 International License (http://crea
tivecommons.org/licenses/by/4.0/), which permits unrestricted use,
distribution, and reproduction in any medium, provided you give
appropriate credit to the original author(s) and the source, provide a
link to the Creative Commons license, and indicate if changes were
made.
References
1. Akcali E, Cetinkaya S, Uster H (2009) Network design for
reverse and closed-loop supply chains: an annotated bibliography
of models and solution approaches. Networks 53:231–248
24 Page 22 of 23 Logist. Res. (2016) 9:24
123
2. Akinc U, Khumawala BM (1977) An efficient branch and bound
algorithm for the capacitated warehouse location problem. Manag
Sci 23:585–594
3. Akinc U, Roodman GMA (1986) New approach to aggregate
production planning. IIE Trans 18:88–94
4. Bostel N, Dejax P, Lu Z (2005) The design, planning, and opti-
mization of reverse logistics networks, logistics systems: design
and optimization. Springer, New York, pp 171–212
5. Fleischmann B, Meyr H, Wagner M (2015) Advanced planning.
Supply chain management and advanced planning. Springer,
Berlin
6. Fleischmann M, Bloemhof-Ruwaard JM, Dekker R, van der Laan
E, van Nunen JAEE, Van Wassenhove LN (1997) Quantitative
models for reverse logistics: a review. Eur J Oper Res 103:1–17
7. Fleischmann M, Krikke HR, Dekker R, Flapper SDP (2000) A
characterisation of logistics networks for product recovery.
Omega 28:653–666
8. Fleischmann M, Beullens P, Bloemhof-Ruwaard JM, Van
Wassenhove LN (2001) The impact of product recovery on
logistics network design. Prod Oper Manag 10:156–173
9. Fleischmann M, Bloemhof-Ruwaard JM, Beullens P, Dekker R
(2004) Reverse logistics network design. Reverse logistics:
quantitative models for closed-loop supply chains. Springer,
Berlin
10. Google Maps: Google Maps. https://maps.google.com. Version:
2015, checked on: 12.01.2015
11. Guide VDR Jr (2000) Production planning and control for
remanufacturing: industry practice and research needs. J Oper
Manag 18:467–483
12. Guide VDR Jr (2009) The evolution of closed-loop supply chain
research. Oper Res 57:10–18
13. Guide VDR, Jayaraman V, Srivastava R (1999) Production
planning and control for remanufacturing: a state-of-the-art sur-
vey. Robot Comput Integr Manuf 15:221–230
14. Jayaraman V (1998) Transportation. Facility location and
inventory issues in distribution network design. Int J Oper Prod
Manag 18:471–494
15. Jayaraman V (1999) A closed-loop logistics model for remanu-
facturing. J Oper Res Soc 50:497–508
16. Jayaraman V (2006) Production planning for closed-loop supply
chains with product recovery and reuse: an analytical approach.
Int J Prod Res 44:981–998
17. King A, Miemczyk J, Bufton D (2006) Photocopier remanufac-
turing at Xerox UK. A description of the process and
consideration of future policy issues. Innovation in life cycle
engineering and sustainable development. Springer, Dordrecht
18. Lund RT (1998) Remanufacturing: an American resource.
International Congress Environmentally Conscious Design and
Manufacturing, Rochester
19. Marın A, Pelegrın B (1998) The return plant location problem:
modelling and resolution. Eur J Oper Res 104:375–392
20. Nam S, Logendran R (1992) Aggregate production planning—a
survey of models and methodologies. Eur J Oper Res 61:255–272
21. Perl J, Sirisoponsilp S (1988) Distribution networks: facility
location. Transportation and inventory. Int J Phys Distrib Mater
Manag 18:18–26
22. Pishvaee MS, Torabi SA (2010) A possibilistic programming
approach for closed-loop supply chain network design under
uncertainty. Fuzzy Sets Syst 161:2668–2683
23. Salema MIG, Barbosa-Povoa AP, Novais AQ (2007) An opti-
mization model for the design of a capacitated multi-product
reverse logistics network with uncertainty. Eur J Oper Res
179:1063–1077
24. Schultmann F, Engels B, Rentz O (2003) Closed-loop supply
chains for spent batteries. Interfaces 33:57–71
25. Schultmann F, Zumkeller M, Rentz O (2006) Modeling reverse
logistic tasks within closed-loop supply chains: an example from
the automotive industry. Eur J Oper Res 171:1033–1050
26. Shen ZM (2007) Integrated supply chain design models: a survey
and future research directions. J Ind Manag Optim 3:1–27
27. Silver EA (1967) A tutorial on production smoothing and work
force balancing. Oper Res 15:985–1010
28. Souza GC (2013) Closed-loop supply chains: a critical review,
and future research. Dec Sci 44:7–38
29. Statistische Amter des Bundes und der Lander: Gemeindeverze-
ichnis-Sonderveroffentlichung Gebietsstand: 31.12.2011 (Jahr):
Großstadte (mit mindestens 100 000 Einwohnerinnen und Ein-
wohnern) in Deutschland nach Bevolkerung am 31.12.2011 auf
Grundlage des Zensus 2011 und fruherer Zahlungen. https://
www.destatis.de/DE/ZahlenFakten/ LaenderRegionen/Re-
gionales/Gemeindeverzeichnis/ Administrativ/GrosstaedteEin-
wohner.html. Accessed on 01/15/2015
30. Steinke L, Fischer K (2015) Integrated facility location, capacity,
and production planning in a multi-commodity closed supply
chain network. Logistic management. Springer, Berlin
Logist. Res. (2016) 9:24 Page 23 of 23 24
123