Extended Duration Warranties, Performance Warranties , and Liquidated Damages in Construction...
description
Transcript of Extended Duration Warranties, Performance Warranties , and Liquidated Damages in Construction...
1
Extended Duration Warranties, Performance Warranties, and
Liquidated Damages in Construction Contracts – What are the Risks?
Presented by: Gene Rash & Rolly ChambersSmith, Currie & Hancock, LLP
May 7, 2013
22
Presenter Biographies• Gene Rash and Rolly Chambers
– Partners in Charlotte, NC office of Smith Currie & Hancock, LLP
• Smith Currie & Hancock, LLP (http://www.smithcurrie.com)– 60 attorneys devoted exclusively to construction and
government contracts– Focus on construction business legal matters– Offices in Atlanta, Charlotte, Ft. Lauderdale, San
Francisco & Washington, D.C.
33
Extended Duration and Performance Construction
Warranties• What will we cover?
– General legal principles for construction warranties
– Extended duration construction warranties – Construction performance warranties– Performance liquidated damages and construction
warranties
44
Extended Duration and Performance Construction
Warranties• Why be concerned about construction
warranties? – Construction warranties shift significant risks to
clients– Financial risk of repairing nonconforming items– Clients may misunderstand the risks involved– You can help by recognizing construction warranty
risks and exploring risk mitigation strategies
55
General Principles for Construction Warranties
• What is a warranty? – Promise that particular statement of fact is true and
may be relied upon by other contracting party• “Standard” construction warranty
– Materials and equipment new and of good quality– Work free from defects in workmanship– Work conforms to requirements of contract – No express time limit
66
General Principles for Construction Warranties
• Contractor will repair defects for 1 year after substantial completion– AIA, ConsensusDocs, EJCDC
• Supplementary conditions may have additional warranty language– Contractor warrants Work “will be free from
defects in materials and workmanship for a period of one year from substantial completion”
77
General Principles for Construction Warranties
• Performance bonds and warranties– Incorporate principal’s construction contract,
including warranty obligations– Surety’s warranty obligations derive from
principal’s warranty obligations – Warranty obligations extend beyond completion– Warranty obligations extend beyond final payment
88
Extended Duration Construction Warranties
• Construction warranties > 1 year• Owner shifts repair risk to contractor for
longer term period– Public owners increasingly looking for extended
duration warranties – Extended duration warranties stretch owner’s
construction dollars
99
Extended Duration Construction Warranties
• Highway construction contracts– State DOT’s face reduced funding– Reduced funding impacts DOT q.c. testing and
inspections– DOT’s require longer duration warranties to cover
risk of correcting quality problems– Pavement warranties can be 3, 5, 7 years
1010
Extended Duration Construction Warranties
• Building construction contracts– Extended warranties for building components (e.g.
roofs, HVAC equipment, etc.)– Warranty durations may be 5,10, 20 years– If contractor goes out of business during extended
warranty period, then performance bond surety will be liable
1111
Extended Duration Construction Warranties
• Extended duration warranties impact contractor bonding– Difficult to estimate future financial obligations to
cover extended warranty repair work– Long term warranty obligations extend long after
contract funds are paid – surety concern– Sureties raise underwriting standards for longer term
coverage
1212
Extended Duration Construction Warranties
• Are there ways to mitigate risks of extended duration warranties?– Assign manufacturer’s long term warranty to owner– Obtain warranty bond separate from performance
bond to cover extended warranty obligations– Limitations through terms of performance bond
• Limit duration of performance bond• Exclude long term warranty language
1313
Construction Performance Warranties
• Contract warranties that concern performance of completed project
• Sustainable (“green”) building– Project will perform at certain level of energy
consumption• Clean energy projects (solar, wind turbine)
– Project will perform at certain level of output
1414
Construction Performance Warranties
“Green” Building• Sustainable buildings are certified to meet
standards for energy and environmental performance– LEED, Energy Star, green building codes
• Federal, state, and local governments – Increasingly incorporate sustainable building
standards in construction contracts– Want construction warranties that completed project
will perform to “green” building standards
1515
Construction Performance Warranties
“Green” Building• AIA Guide for Sustainable Projects (2011)
– Disclaims warranty that project design and construction will perform to “green” building standards
– Owner maintenance and operations after completion affect project’s performance
• But … – >20% of U.S. cities over 50,000 in population had
green building programs in 2009
1616
Construction Performance Warranties
“Green” Building• Federal design-build project - warehouse
– Required design to achieve energy consumption at least 40% below a given baseline (performance)
– Required warranty of project design “through the statute of limitations and statute of repose” (extended duration)
– Required design-builder to furnish performance bond
1717
Construction Performance Warranties
“Green” Building• Federal design-build project - warehouse
– Government’s remedies for breach• Equitable adjustment (deductive change)• Contractor repair or replacement of defective
item at contractor expense (re-design)• Risk mitigation techniques
– Performance bond covering construction work but excluding design
– Design-build performance bond limiting liability for design (e.g. ConsensusDocs 470 (rev. 2011)
1818
Construction Performance Warranties
Clean Energy Projects• Solar cell and wind turbine power projects• Developer financing depends on selling a
given level of output– Investors and lenders want assurance from
developer– Developer shifts performance risk to project
designer and contractor with performance warranties
1919
Construction Performance Warranties
EPC Projects• EPC Contracts
– Engineering, Procurement, and Construction– Type of design-build contract– Commonly used for constructing clean energy or
industrial projects• EPC Contracts include performance
warranties and construction warranties– If project fails to perform to warranted level, then
EPC contractor is obligated to bring performance to the warranted level
2020
Construction Performance Warranties
EPC Projects• Are there ways to mitigate risks of
performance warranties in EPC contracts?– Errors and omissions insurance from designer for
design defects– Performance warranty insurance from manufacturer
of project components (solar cells, turbines, etc.)– Manufacturers warrant output performance of solar
cells or turbines for long term – 12, 15, 25 years– Manufacturer partners with insurance company– Developer can obtain coverage directly
2121
Construction Performance Warranties
Performance Liquidated Damages• EPC contracts may provide for both
construction delay and performance liquidated damages– Performance LD’s do not involve delays in
construction– Performance LD’s involve delays in achieving a
warranted level of output– Developer assesses performance LD’s while output
is below warranted level
2222
Construction Performance Warranties
Performance Liquidated Damages• Are there ways to mitigate risk of
performance LD’s?– Limitation of damages clause can cap an EPC
contractor’s or performance bond surety’s liability for performance LD’s
2323
Extended Duration and Performance Construction
Warranties• Extended duration and performance
construction warranties shift significant risks to contractors and their sureties
• Trend to include such warranties is likely to increase
• Recognizing financial and legal risks and attempting to mitigation them is crucial
2424
Contractual Risk Allocation Provisions
QUESTIONS?If you do not have the opportunity to have your question addressed during the session, you may contact the presenters directly:
Gene Rash & Rolly ChambersCompany: Smith, Currie & Hancock, LLPPhone: 704-334-3459Email: [email protected]: [email protected]: 1023 W. Morehead St., Suite 301
Charlotte, NC 28208