Exported on: 03/05/2009 13:44 CST by: Simmons, James

download Exported on: 03/05/2009 13:44 CST by: Simmons, James

of 62

Transcript of Exported on: 03/05/2009 13:44 CST by: Simmons, James

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    1/62

    ANO Jan-09

    Exported on: 03/05/2009 13:44 CSTBy: Simmons, James

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    2/62

    Table of ContentsPage

    ANO Unit-1 Jan-09 1

    ANO Unit-2 Jan-09 2

    ANO Unit-1 Jan-09 3

    ANO Unit-2 Jan-09 4

    ANO Unit-2 Jan-09 5

    ANO Unit-1 Jan-09 6

    ANO Unit-2 Jan-09 7

    ANO Unit-1 Jan-09 8

    ANO Unit-2 Jan-09 9

    ANO Unit-1 Jan-09 10

    ANO Unit-2 Jan-09 11

    ANO Unit-1 Jan-09 12

    ANO Unit-1 Jan-09 13

    ANO Unit-2 Jan-09 14

    ANO Unit-2 Jan-09 15ANO Unit-1 Jan-09 16

    ANO Unit-1 Jan-09 17

    ANO Unit-2 Jan-09 18

    ANO Unit-2 Jan-09 19

    ANO Unit-1 Jan-09 20

    ANO Jan-09 21

    ANO Jan-09 23

    ANO Jan-09 24

    ANO Jan-09 25

    ANO Jan-09 26

    ANO Unit-1 Jan-09 27

    ANO Unit-2 Jan-09 29

    ANO Unit-2 Jan-09 31ANO Unit-1 Jan-09 32

    ANO Unit-1 Jan-09 33

    ANO Unit-2 Jan-09 34

    ANO Unit-1 Jan-09 35

    ANO Unit-2 Jan-09 36

    ANO Unit-2 Jan-09 37

    ANO Unit-1 Jan-09 38

    ANO Unit-1 Jan-09 39

    ANO Unit-2 Jan-09 40

    ANO Unit-1 Jan-09 41

    ANO Unit-2 Jan-09 42

    ANO Unit-2 Jan-09 43

    ANO Unit-1 Jan-09 44

    ANO Unit-2 Jan-09 45

    ANO Unit-1 Jan-09 46

    ANO Jan-09 47

    ANO Jan-09 48

    ANO Jan-09 49

    ANO Jan-09 50

    ANO Jan-09 51

    ANO Jan-09 52

    ANO Jan-09 53

    ANO Jan-09 54

    ANO Jan-09 55

    ANO Jan-09 56

    ANO Jan-09 57

    ANO Jan-09 58

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    3/62

    ANO Jan-09 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    4/62

    ANO Unit-1

    PI TitleINPO Index

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-- AFW/RHR 10 10

    -- Capability Factor 12.77 12.64

    -- Chemistry 5 5

    -- CRE 5.96 5.94

    -- EDG 10 10

    -- Est. Fuel Defects 2 2

    -- Forced Loss Rate 15 15

    -- Fuel Reliability 8 8

    -- HPSI 10 10

    -- Unplanned Scrams

    Rate

    10 10

    -- TISA 5 5

    INPO Index 93.72 93.58

    YTD Goal 96

    EOY Estimate 93.9

    EOY Goal 96

    This performance indicator has a value of 0 to 100 and is calculated from a weighted combination of ten overall WANO performanceindicator values and INPO specified date periods.

    Green >= 96White >= 94Red < 94

    ata Source OwnerBrad Berryman

    AnalyzerSteve Coffman

    Year2009est Test2

    1 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    5/62

    ANO Unit-2

    PI TitleINPO Index

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-- AFW/RHR 10 10

    -- Capability Factor 15 15

    -- Chemistry 5 5

    -- CRE 10 10

    -- EDG 10 10

    -- Est. Fuel Defects 0 0

    -- Forced Loss Rate 15 15

    -- Fuel Reliability 8 8

    -- HPSI 10 10

    -- TISA 5 5

    -- Unplanned ScramsRate

    10 10

    INPO Index 90 98

    YTD Goal 96

    EOY Estimate 98

    EOY Goal 96

    This performance indicator has a value of 0 to 100 and is calculated from a weighted combination of ten overall WANO performanceindicator values and INPO specified date periods.

    Green >= 96White >= 94Red < 94

    ata Source OwnerBrad Berryman

    AnalyzerSteve Coffman

    Year2009est Test2

    2 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    6/62

    ANO Unit-1

    PI TitleCapability Factor

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecCapability Factor- YTDTarget

    85.48 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.

    Capability Factor -Month

    43.55 98.14 74.24

    Capability Factor YTD 85.29 98.14 86.80

    Cycle Average 90.21 90.10 88.74

    EOY Projections 85.50 96.00

    EOY Goal 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00

    Projections 88.20 96.00

    The ratio of available energy over a given period to reference energy generation over the same period, expressed as a percentage. Bothenergy generation terms are determined relative to reference ambient conditions. Available energy generation is the energy that couldhave been produced under reference conditions considering only limitations within control of plant management. Reference energygeneration is the energy that could be produced if the unit operated continuously at full power under reference ambient conditionsthroughout the period. Reference ambient conditions are environmental conditions representative of the annual mean ambient conditiofor the unit.

    For a non-outage year, Target is 96. Red = Target.Target for outage year based on duration. 96 * (outage days - 365) / 365.

    Electrical Production

    OwnerRandall Walters

    AnalyzerSteve Coffman

    3 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    7/62

    ANO Unit-2

    PI TitleCapability Factor

    Top Decile Top Quartile Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecCapability Factor- YTDTarget

    89.42 96.00

    Capability Factor -Month

    100.00 87.44 94.18

    Capability Factor YTD 92.17 87.44 90.64

    Cycle Average 94.45 94.06 93.73

    EOY Projections 92.17

    The ratio of available energy over a given period to reference energy generation over the same period, expressed as a percentage. Both

    energy generation terms are determined relative to reference ambient conditions. Available energy generation is the energy that couldhave been produced under reference conditions considering only limitations within control of plant management. Reference energygeneration is the energy that could be produced if the unit operated continuously at full power under reference ambient conditionsthroughout the period. Reference ambient conditions are environmental conditions representative of the annual mean ambient conditiofor the unit.

    For a non-outage year, Target is 96. Red = Target.Target for outage year based on duration. 96 * (outage days - 365) / 365.

    Electrical ProductionOwnerRandall Walters

    AnalyzerSteve Coffman

    4 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    8/62

    ANO Unit-2

    PI TitleForced Loss Rate

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecFLR Month 0.00 0.16 5.82

    FLR YTD 0.42 0.16 3.04

    YTD Target 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.7

    EOY Proj 0.42 0.50 0.50

    Unplanned Losses -Month

    0 1067 39607

    Planned Energy Losses-Month

    0 93481 0

    Unplanned Outage Ext 0 0 0

    Cycle Average 0.31 0.30 0.62

    Operating period forced loss rate (FLR) is defined as the ratio of all operating period unplanned energy losses during a given period of timconsidering only the operating period, to the reference energy generation minus energy losses corresponding to planned outages and thpossible unplanned extensions, during the same period, expressed as a percentage.Operating period unplanned forced energy loss during the operating period is energy that was not produced during that period becauseunplanned shutdowns or unplanned load reductions due to causes under plant management control when the unit is considered to be athe disposal of the grid dispatcher. Causes of energy losses are considered to be unplanned if they are not scheduled at least four weekadvance

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    9/62

    ANO Unit-1

    PI TitleForced Loss Rate

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecFLR Month 23.16 0.00 25.67

    FLR YTD 1.49 0.00 12.30

    YTD Target 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.7

    EOY Proj 1.49 0.24 1.97

    Unplanned Losses -Month

    106942 20 145604

    Planned Energy Losses-Month

    229186 11645 672

    Unplanned Outage Ext 18773 1 0

    Cycle Average 0.95 0.95 2.39

    Projections 0.12 0.12 8.00

    Operating period forced loss rate (FLR) is defined as the ratio of all operating period unplanned energy losses during a given period of timconsidering only the operating period, to the reference energy generation minus energy losses corresponding to planned outages and thpossible unplanned extensions, during the same period, expressed as a percentage.Operating period unplanned forced energy loss during the operating period is energy that was not produced during that period becauseunplanned shutdowns or unplanned load reductions due to causes under plant management control when the unit is considered to be athe disposal of the grid dispatcher. Causes of energy losses are considered to be unplanned if they are not scheduled at least four weekadvance

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    10/62

    ANO Unit-2

    PI TitleUnplanned Automatic Scrams

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNumber Scrams -Month

    0 0

    Hours Critical inmonth

    744.00 708.10

    Unplanned AutoScram Rate -Month

    0.0 0.0

    Unplanned AutoScram Rate -YTD

    0.000 0.000

    Unplanned AutoScram Rate -2-yrRolling

    0.000 0.000

    Unplanned AutoScram YTD Goal

    0 0 0 0 0 0 0 0 0 0 0 0 0

    Unplanned AutoScrams-YTD

    0 0

    The number of unplanned automatic scrams normalized to 7,000 hours of critical operation.

    Goals are based on goals set for year to date performance. Green: No unplanned automatic scrams, Red >= 1.

    ata Source OwnerRandall Walte

    AnalyzerSteve Coffman

    7 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    11/62

    ANO Unit-1

    PI TitleUnplanned Automatic Scrams

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNumber Scrams -Month

    0 0

    Hours Critical inmonth

    402.42 744.00

    Unplanned AutoScram Rate -Month

    0.0 0.0

    Unplanned AutoScram Rate -YTD

    0.000 0.000

    Unplanned AutoScram Rate -2-yrRolling

    0.000 0.000

    Unplanned AutoScram YTD Goal

    0 0 0 0 0 0 0 0 0 0 0 0 0

    Unplanned AutoScrams-YTD

    0 0

    The number of unplanned automatic scrams normalized to 7,000 hours of critical operation.

    Goals are based on goals set for year to date performance. Green: No unplanned automatic scrams, Red >= 1.

    ata Source OwnerRandall Walters

    AnalyzerSteve Coffman

    8 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    12/62

    ANO Unit-2

    PI TitleHigh Pressure SystemUnavailability (%)

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecUnavail Planned hrs -Mo

    0 0

    Unavail Unplanned hrs-Mo

    0 0

    Fault Exposure hrs -Mo 0 0

    Total Unavail hrs -Mo 0 0

    Monthly Goal (%) 0 0

    % Unavailability Mo 0 0

    % Unavailability YTD 0 0

    EOY Estimate 0 0YTD Goal 1 1 1 1 1 1 1 1 1 1 1 1 1

    Projections 0 0 0 0 0 0 0 0 0 0 0 0

    Uavail 3-Yr Rolling % 0 0

    The ratio of the hours that the components were unable to perform their intended function to the hours the system was required to beavailable for service. Expressed as a percentage.

    GOALS: Max-Target-Min (0.75 - 1.0 - 2.0)Use 2% which is full credit for INPO IndexGreen

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    13/62

    ANO Unit-1

    PI TitleHigh Pressure SystemUnavailability (%)

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecUnavail Planned hrs -Mo

    0 0

    Unavail Unplanned hrs-Mo

    0 0

    Fault Exposure hrs -Mo 0 0

    Total Unavail hrs -Mo 0 0

    Monthly Goal (%) 0 0

    % Unavailability Mo 0 0

    % Unavailability YTD 0 0

    EOY Estimate 0.11 0YTD Goal 1 0

    Projections 0

    Uavail 3-Yr Rolling % 0 0

    The ratio of the hours that the components were unable to perform their intended function to the hours the system was required to beavailable for service. Expressed as a percentage.

    GOALS: Max-Target-Min (0.75 - 1.0 - 2.0)Use 2% which is full credit for INPO IndexGreen

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    14/62

    O Unit-2

    PI TitleAux Feedwater/RHR Unavailability (%)

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DFW / RHR Plannedvailable Hrs -Mo

    0 0

    planned Unavailable Hrs - 0 0

    t exposure Hrs -Mo 0 0

    al Unavailable Hrs -Mo 0 0

    vailability - Monthly Goal 0 0

    FW / RHR %vailability -Month

    0 0

    FW / RHR %vailability -YTD %

    0 0

    Y Estimate 0.44 0l YTD % 1 1

    ections 0

    r Rolling Avg 0 0

    e ratio of the hours that the components were unable to perform their intended function to the hours the system was required to be available for servicpressed as a percentage.

    ALS: Max-Target-Min (0.75 - 1.0 - 2.0)een

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    15/62

    O Unit-1

    PI TitleAux Feedwater/RHR Unavailability (%)

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DFW / RHR Plannedvailable Hrs -Mo

    37.63 0

    planned Unavailable Hrs - 0 0

    t exposure Hrs -Mo 0 0

    al Unavailable Hrs -Mo 37.63 0

    vailability - Monthly Goal 5 0

    FW / RHR %vailability -Month

    0 0

    FW / RHR %vailability -YTD %

    0 0

    Y Estimate 0.7 0l YTD % 1 1

    ections 0.4 0

    r Rolling Avg 0 0

    e ratio of the hours that the components were unable to perform their intended function to the hours the system was required to be available for servicpressed as a percentage.

    ALS: Max-Target-Min (0.75 - 1.0 - 2.0)een

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    16/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    17/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    18/62

    ANO Unit-2

    PI TitleFuel Reliability Indicator

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecFRI - Month 3.1E-4 4.3E-4

    FRI Quarterly Average- INPO

    2.1E-4 3.2E-4

    FRI Goal 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0

    Measure of nuclear fuel pin integrity. Derived from steady state offgas activity at SJAE for noble gas fission products corrected for recoirelease and normalized to average linear heat generation rate.

    Green 300

    Data Source

    OwnerPatrick Williams

    AnalyzerAndrew Tate

    Year2009

    15 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    19/62

    ANO Unit-1

    PI TitleFuel Reliability Indicator

    Top Decile Top Quartile Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecFRI - Month 1.0E-6 1.0E-6

    FRI Quarterly Average- INPO

    1.2E-4 1.0E-6

    FRI Goal 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0E-4 5.0

    Measure of nuclear fuel pin integrity. Derived from steady state offgas activity at SJAE for noble gas fission products corrected for recoirelease and normalized to average linear heat generation rate.

    Green 300

    Data Source

    OwnerPatrick Williams

    AnalyzerAndrew Tate

    Year2009

    16 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    20/62

    ANO Unit-1

    PI TitleCollective Radiation Exposure

    Top Decile39

    Top Quartile49

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecMonthly Goal 2 0.4 0.247 0.499 0.766 0.206 0.191 0.277 0.367 0.123 0.262 0.21 0.1

    Monthly RadExposure

    18.934 0.34 0.396

    YTD Goal 89.1 0.4 0.647 1.146 1.912 2.118 2.309 2.586 2.953 3.076 3.338 3.548 3.7

    Collective RadExposure -YTD

    123.971 0.34 0.736

    EOY Estimate 123.97 3.5 3.8

    Annual CollectiveDose - Cycle Value

    84.265 84.333 83.934

    The sum of the total effective does equivalent (TEDE) received by all personnel including contractors and visitors on site. TEDE is the sumthe deep dose equivalent (DDE) and committed effective dose equivalent (CEDE). TEDE, DDE, and CEDE are defined in 10 CFR 20.1003.

    Green:100% AND 110% of station YTD goal

    RP Records

    OwnerDavid Moore

    AnalyzerTim Smith

    UnitCode

    17 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    21/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    22/62

    ANO Unit-2

    PI TitleChemistry Effectiveness Indicator

    Top Decile2.170

    Top Quartile3.590

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecGoal 10 10 10 10 10 10 10 10 10 10 10 10 1

    Cycle CEI Projection 5.03 5.03 5.03 5.03 5.03 5.03 5.03 3.22 3.22 3.2

    Cond 1 AL Chemistry 0.0047 0.0047 0.0047

    Cond 2 FW Fe/Cu 0.0596 0.4650 0.4795

    Cond 3 H2 and Mitg 1.3773 1.3773 2.0463

    Cond 4 Leak-cond 1.4625 1.7105 2.4963

    Cond 5 Cobalt 0.0000 0.0000 0.0000

    Monthly Change to CEI 0.00 0.66 1.47

    Monthly CEI 16 2 5

    Cycle CEI 2.90 3.56 5.03

    An index which uses data elements that collect information on several key primary and secondary chemistry parameters. The data iscollected based mostly on time outside limits along with the maximum value of the parameter during the month. Note: CEI monthly datamust be reported for a station when operated above 10% power for a BWR and 30% power for a PWR anytime during the month (even iless than a full day). Chemistry Effectiveness Indicator (CEI) results will be averaged (with a scaling factor applied) to obtain a reportedrolling cycle results (18 or 24 month cycle)which is used in calculating the INPO Index starting 2008. The monthly change in CEI is therelative change in CEI from the previous month. No points are received if the index is greater than or equal to 35 and full five points arewhen the index is less than or equal to 10. Index = (35-CEI) x 4

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    23/62

    ANO Unit-1

    PI TitleChemistry Effectiveness Indicator

    Top Decile2.170

    Top Quartile3.590

    Month/YearJan-09

    StatusWhite

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecGoal 10 10 10 10 10 10 10 10 10 10 10 10 1

    Cycle CEI Projection 2.40 8.66 8.66 8.66 8.66 8.66 6.38 6.38 6.38 6.38 6.3

    Cond 1 AL Chemistry 0.0000 0.0000 0.0000

    Cond 2 FW Fe/Cu 0.5491 2.7456 2.9634

    Cond 3 H2 and Mitg 0.1713 0.6054 0.8824

    Cond 4 Leak-cond 0.7184 4.6012 4.8187

    Cond 5 Cobalt 0.0000 0.0000 0.0000

    Monthly Change to CEI 3.72 2.22 0.71

    Monthly CEI 16 8 2

    Cycle CEI 7.19 7.95 8.66

    An index which uses data elements that collect information on several key primary and secondary chemistry parameters. The data iscollected based mostly on time outside limits along with the maximum value of the parameter during the month. Note: CEI monthly datamust be reported for a station when operated above 10% power for a BWR and 30% power for a PWR anytime during the month (even iless than a full day). Chemistry Effectiveness Indicator (CEI) results will be averaged (with a scaling factor applied) to obtain a reportedrolling cycle results (18 or 24 month cycle)which is used in calculating the INPO Index starting 2008. The monthly change in CEI is therelative change in CEI from the previous month. No points are received if the index is greater than or equal to 35 and full five points arewhen the index is less than or equal to 10. Index = (35-CEI) x 4

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    24/62

    ANO

    PI TitleRecordable Injury Rate

    Month/YearJan-09

    StatusRed

    Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNumber of Lost-TimeAccidents (Employee)

    0

    Number of Restricted DutyAccidents (Employee)

    0

    Number of Other Recordablenjuries (Employee)

    0

    Recordable Injury Rate(Employee) - Month

    0 0

    Recordable Injury Rate(Employee) - YTD

    0 0

    Number of Lost-TimeAccidents (Contractor)

    0

    Number of Restricted Duty

    Accidents (Contractor)

    1

    Number of Other Recordablenjuries (Contractor)

    0

    Recordable Injury Rate(Contractor) - Month

    6 4

    Recordable Injury Rate(Contractor) - YTD

    6 4

    Employee Work-Hours 147696 84081

    Contractor Work-Hours 34996 55236

    Total Station Work-Hours 182692 139317

    Total OSHA Recordables 1 1

    Total OSHA Recordables - YTD 1 1

    Recordable Injury Rate -Month

    1 1

    Recordable Injury Rate -YTD 1 1

    Recordable Injury Rate EOYEstimate

    0

    Goal YTD 0 0 0 0 0 0 0 0 0 0 0 0 0

    OSHA Recordable Injury Rate (RIR) - The number of recordable injuries (employees and supplemental personnel) per 200000 person-hours worked based on OccupationalSafety and Health Administration (OSHA) definitions. Includes Restricted Duty Accidents (RDA), Lost-Time Accidents (LTA) and Other Recordable Injuries.

    Goals are Green 0.4 but 0.6

    Safety Dept

    OwnerTim Tullos

    AnalyzerVicki MillsTitle Value

    Number of Restricted Duty Accidents (Contractor) 0

    Number of Other Recordable Injuries (Contractor) 0

    Number of Lost-Time Accidents (Contractor) 0

    21 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    25/62

    Title. Value.Number of Restricted Duty Accidents (Contractor) 0

    Number of Other Recordable Injuries (Contractor) 1

    Number of Lost-Time Accidents (Contractor) 0

    22 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    26/62

    ANO

    PI TitleTotal Industrial Safety AccidentRate (TISA)

    Top Decile Top Quartile Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecEmployee injuriesMonth

    0 0

    Employee YTD Injuries 0 0

    Contractor injuries -Month

    0 1

    Contractor YTD Injuries 0 1

    TISA Month 0.00 1.44

    TISA YTD 0.00 1.44

    TISA YTD GOAL 0 0 0 0 0 0 0 0 0 0 0 0 0

    TISA EOY Estimate 0.00 0.08Cycle Average 0.00 0.05

    This indicator is defined as the number of accidents per 200,000 person-hours worked for personnel assigned to the station includingcontractors that result in: one or more days of restricted work (excluding the day of the accident), one or more days away from work(excluding the day of the accident), and fatalities.

    Set by HQ to etablish Goals for Top Performance Goal Green =0, White>0, Red>0.2.

    ata Source OwnerBrad Berryman

    AnalyzerBrad Berryman

    FleetLink2007

    2

    23 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    27/62

    ANO

    PI TitleCR Inventory

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNew CR's Opened inthe Month (CAT.A,B,C, D)

    564 657

    CR's Closed Duringthe Month (Cat.A,B,C, D)

    517 697

    Number of Open CR'sat Months End

    778 778

    Open CR BacklogTarget - (YTD ONLY)

    750 750 750 750 750 750 750 750 750 750 750 750 75

    Average Number ofOpen CR's - YTD

    65 778

    EOY Goal 750

    EOY Estimate 778

    EOY Goal 750

    EOY Estimate 778

    A measure of the total number of CRs opened and closed during the period being monitored (category A, B, C, D). The backlog consists othe total number of Category A, B, and C CRs that remain open at the end of each period being monitored including CRs with Long Termactions assigned.

    Open CRsGREEN =700 and 750

    PCRS

    OwnerBob Eichenberger

    AnalyzerLarry McCarty

    24 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    28/62

    ANO

    PI TitleCR (Cat A&B) Evaluation Performance

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNumber of CR Eval'sClosed - Month

    33 18

    Average Age of ClosedEval's (days)

    21 23

    Evaluation Age Goal 30 30 30 30 30 30 30 30 30 30 30 30 3

    Average Age YTD 1.8 23

    EOY Estimate 21

    EOY Goal 30

    The average evaluation time for Condition Reports (CR) during the month (measured in days). Does not include CRs that do not require aevaluation (e.g. CRs that get closed to work orders, trending, etc.). The age of the more significant CAT A and CAT B evaluations is beingtracked due to their importance and complexity.

    Average age of evaluations to be less than 30 days. Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    29/62

    epartment Plant UnitANO

    PI TitleCR Average Age

    Jan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecCR Average Age 142 150

    CR Average Age Goal 180 180 180 180 180 180 180 180 180 180 180 180 18

    EOY Estimate 142

    EOY Goal 180 180 180 180 180 180 180 180 180 180 180 180 18

    Average Age in days of Condition Reports that were open at any point during the reporting period, not including Condition Reports

    restrained by Refueling Outages.

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    30/62

    ANO Unit-1

    PI TitleEquipment Reliability Index

    Month/YearJan-09

    StatusWhite

    8

    Unplanned PowerRed. / 7000 hrs8

    Post RefuelingOutagePerformance (100Days)0

    Unplanned LCOEntries (SD & < 72hours)4

    Operator WorkArounds2

    High CriticalComponentFailures8

    Safety SystemUnavailability8

    System HealthImprov. Eff.4

    3

    TotalMaintenanceBacklog2

    Deferral of PMs4

    % PMs w/ Maint.Feedback2

    % PMs Compl. in2nd Half of Grace6

    Work WeekSched. Stability6

    Work WeekSched. Adher.6

    Long Range PlImpl. Effect.7

    0

    Chem. Effect. Ind.1

    PM Program Bases2

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-- Long Range Plan Impl. Effect. 7

    -- Forced Loss Rate(%) 8

    -- Unplanned LCO Entries (SD &< 72 hours)

    4

    -- Safety System Unavai labi lity 8

    -- % PMs w/ Maint. Feedback 2

    -- Chem. Effect. Ind. 1

    -- Deferral of PMs 4

    -- Age of Red & Yellow Systems 0

    -- Post Refueling OutagePerformance (100 Days)

    0

    -- PM Program Bases 2

    -- High Critical ComponentFailures

    8

    -- Unplanned Power Red. /7000 hrs

    8

    -- Operator Work Arounds 2

    -- System Health Improv. Eff. 4-- Corr. Maint. Backlog (NO) 3

    -- Total Maintenance Backlog 4

    -- % PMs Compl. in 2nd Half ofGrace

    6

    -- Work Week Sched. Stability 6

    -- Work Week Sched. Adher. 6

    Equipment Reliability Index 83 81

    The goal of the ERI is to improve equipment reliability by use of the best available leading indicators and important lagging indicators in ER (19 Metrics). The ERI provides ahealth assessment of current and future performance, and provides a cross comparison (industry) for strengths/areas of focus.

    FCS goal > 75% (End of 2008) Industry Top Quartile > 86% Green >= 85 White >=50 and < 85 Red < 50

    27 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    31/62

    Equipment Reliability Engineering

    OwnerRandall Walters

    AnalyzerAngela Hartman

    Year2009

    28 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    32/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    33/62

    Equipment Reliability Engineering

    OwnerRandall Walters

    AnalyzerAngela Hartman

    Year2009

    30 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    34/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    35/62

    ANO Unit-1

    PI TitleCapacity Factor

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecCAPACITY Factor -Month

    47.74 102.90

    CAPACITY Factor YTD 90.79 102.90

    CAPACITY Factor- YTDGOAL

    87.53 100.70 100.70 100.70 100.70 100.31 100.06 99.88 99.75 99.64 99.75 99.84 99.

    Capacity Factor EOYEstimate

    83.40 98.00 98.00

    Capacity Factor EOYGoal

    99.91 99.91 99.91 99.91 99.91 99.91 99.91 99.91 99.91 99.91 99.91

    Projections 90.38 89.01

    The ratio of net energy generation produced while the unit is online over a given time period to the maximum dependable capacity (groelectrical output at full power during the most restrictive seasonal conditions, less normal station service loads) over the same time periexpressed as a percentage.

    value for a unit = NEG x 100%/ MDCwhere NEG = net energy generation

    MDC = maximum dependable capacity

    Target for capacity factor is based on the generation from the yearly financial model. Green is less than or equal to target, White is greathan target, and Red is less than 2% under target.

    Electrical production

    OwnerRandall Walters

    AnalyzerSteve Coffman

    32 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    36/62

    ANO Unit-1

    PI TitleNet Generation

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecProjections 0

    Net Generation Month 296923 640046

    Net Generation Yearto Date

    6667457 640046

    Net Generation End OfYear Estimate

    6124046 7323690

    Target GenerationMonth

    424277 626314 565703 626314 606110 614648 594820 614648 614648 594820 626314 606110 626

    Target Generation YTD 6427726 626314 1192017 1818331 2424441 3039089 3633909 4248557 4863205 5458025 6084339 6690449 7316

    Gross electrical output of the unit measured at the output terminals of the turbine generator during the reporting period, minus the norstation service electrical energy utilization, uncorrected for transformer losses.

    Target for capacity factor is based on the net generation used in the financial model. Max=Target +2%, Min= Target-2%. Net Generationgoals are matched to Capacity Factor Goals.

    ata Source OwnerRandall Walters

    AnalyzerSteve Coffman

    33 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    37/62

    ANO Unit-2

    PI TitleNet Generation

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecProjections 0 0 0 0 0 0 0 0 0 0 0

    Net Generation Month 753249 661170

    Net Generation Yearto Date

    753249 661170

    Net Generation End OfYear Estimate

    8060446

    Target GenerationMonth

    735682 734223 663169 734223 710539 726203 702777 726203 726203 94755 734223 710539 734

    Target Generation YTD 735682 734223 1397392 2131615 2842154 3568357 4271134 4997337 5723540 5818295 6552518 7263057 7997

    Gross electrical output of the unit measured at the output terminals of the turbine generator during the reporting period, minus the norstation service electrical energy utilization, uncorrected for transformer losses.

    Target for capacity factor is based on the 2008 financial model for ENS. Max=Target +2%, Min= Target-2%. Net Generation goals arematched to Capacity Factor Goals.

    ata Source OwnerRandall Walters

    AnalyzerSteve Coffman

    34 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    38/62

    ANO Unit-1

    PI TitleOperator Aggregate Impact Index

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecOWA - Non-outage 0

    OWA - Outage 0

    Burdens - Non-outage 1

    Burdens - Outage 0

    CRD's - Non-outage 0

    CRD's - Outage 3

    CRA's - Non-outage 0

    CRA's - Outage 0

    Clearances >90 Days -Non-outage

    1

    Clearances >90 Days -Outage

    0

    Caution Tags >90 Days- Non-outage

    3

    Caution Tags >90 Days- Outage

    0

    Component Deviations>90 Days - Non-outage

    1

    Component Deviations>90 Days - Outage

    0

    OAI - Non-Outage 0.12

    Goal - Non-outage 1 1 1 1 1 1 1 1 1 1 1 1 1

    Total OAI Index 0.23

    The weighted sum of control room deficiencies, operator work arounds, operator burdens, control room annunciators, protectiveclearances > 90 days old, caution/information tags >90 days old and component/valve deviation >90 days olds. Only Non-Outage Cautio

    Tags, Clearances and Component Deviations having Priority 1, 2, or 3 Work Orders are included in the on-line Index.Calculation: Index = 0.34 * (OWA /1) + (0.33) * ((OB + CRD + CRA) / 9) + (0.33) * ((CL + CAUT + COM) / 20)

    Goal is to maintain the on-line Operator Aggregate Impact Index (OAI) less than 1 and the Total OAI less than 1.5.Green: 1.0 and 1.8

    ata Source OwnerRandall Walters

    AnalyzerJames Keys

    35 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    39/62

    ANO Unit-2

    PI TitleOperator Aggregate Impact Index

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecOWA - Non-outage 0

    OWA - Outage 1

    Burdens - Non-outage 0

    Burdens - Outage 1

    CRD's - Non-outage 1

    CRD's - Outage 10

    CRA's - Non-outage 0

    CRA's - Outage 1

    Clearances >90 Days -Non-outage

    2

    Clearances >90 Days -Outage

    1

    Caution Tags >90 Days- Non-outage

    1

    Caution Tags >90 Days- Outage

    0

    Component Deviations>90 Days - Non-outage

    0

    Component Deviations>90 Days - Outage

    4

    OAI - Non-Outage 0.09

    Goal - Non-outage 1 1 1 1 1 1 1 1 1 1 1 1 1

    Total OAI Index 0.72

    The weighted sum of control room deficiencies, operator work arounds, operator burdens, control room annunciators, protectiveclearances > 90 days old, caution/information tags >90 days old and component/valve deviation >90 days olds. Only Non-Outage Cautio

    Tags, Clearances and Component Deviations having Priority 1, 2, or 3 Work Orders are included in the on-line Index.Calculation: Index = 0.34 * (OWA /1) + (0.33) * ((OB + CRD + CRA) / 9) + (0.33) * ((CL + CAUT + COM) / 20)

    Goal is to maintain the on-line Operator Aggregate Impact Index (OAI) less than 1 and the Total OAI less than 1.5.Green: 1.0 and 1.8

    ata Source OwnerRandall Walters

    AnalyzerJames Keys

    36 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    40/62

    ANO Unit-2

    PI TitleUnplanned AOT/LCO Trends

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecUnplanned AOT/LCOTrends

    1 1

    YTD UnplannedAOT/LCO Trends

    1 1

    Monthly Goal 1 1 1 1 1 1 1 1 1 1 1 1 1

    YTD Goal 1 1 2 3 4 5 6 7 8 9 10 11 1

    EOY Goal 12 12 12 12 12 12 12 12 12 12 12 12 1

    For an AOT to be counted by this indicator, it must be unplanned and contains an action statement which requires a plant shutdown if th

    limiting condition can not be cleared.

    Green 1

    OPS LOG

    OwnerRandall Walters

    AnalyzerStephanie Pyle

    37 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    41/62

    ANO Unit-1

    PI TitleUnplanned AOT/LCO Trends

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecUnplanned AOT/LCOTrends

    1 1

    YTD UnplannedAOT/LCO Trends

    6 1

    Monthly Goal 1 1 1 1 1 1 1 1 1 1 1 1 1

    YTD Goal 11 1 2 3 4 5 6 7 8 9 10 11 1

    EOY Goal 12 12 12 12 12 12 12 12 12 12 12 12 1

    For an AOT to be counted by this indicator, it must be unplanned and contains an action statement which requires a plant shutdown if th

    limiting condition can not be cleared.

    Green 1

    OPS LOG

    OwnerRandall Walters

    AnalyzerStephanie Pyle

    38 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    42/62

    ANO Unit-1

    PI TitleTemporary Modifications (Non Outage) Open > 60 days

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNon-Outage TempMods

    1 2

    Outage Temp Mods 2 1

    Total Temp Mods -Month

    3 3

    Non-Outage Goal 4 4 4 4 4 4 4 4 4 4 4 4

    Temporary modifications, such as electrical jumpers, lifted leads, pulled circuit boards, disabled annunciators/alarms, mechanicalumpers/bypasses, and temporary setpoint changes.

    OUTAGE TEMP MOD is interpreted to mean those Temp Mod installed that require an Outage to restore.NON-OUTAGE TEMP MOD is interpreted to mean those Temp Mod installed which can be restored during any Operating Mode.

    Green: 4The Goal is based on Non-outage temp mods

    ata Source OwnerCleve Reasoner

    AnalyzerSteven L Smith

    39 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    43/62

    ANO Unit-2

    PI TitleTemporary Modifications (Non Outage) Open > 60 days

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNon-Outage TempMods

    2 2

    Outage Temp Mods 7 7

    Total Temp Mods -Month

    9 9

    Non-Outage Goal 4 4 4 4 4 4 4 4 4 4 4 4 4

    Temporary modifications, such as electrical jumpers, lifted leads, pulled circuit boards, disabled annunciators/alarms, mechanicalumpers/bypasses, and temporary setpoint changes.

    OUTAGE TEMP MOD is interpreted to mean those Temp Mod installed that require an Outage to restore.NON-OUTAGE TEMP MOD is interpreted to mean those Temp Mod installed which can be restored during any Operating Mode.

    Green: 4The Goal is based on Non-outage temp mods

    ata Source OwnerCleve Reasoner

    AnalyzerSteven L Smith

    40 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    44/62

    ANO Unit-1

    PI TitleNon-Outage Corr. Maint. Backlog

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNon-Outage CorrectiveMaintenance Backlog

    3 3

    CorrectiveMaintenance BacklogYTD Goal

    10 10 10 10 10 10 10 10 10 10 10 10 1

    Non-Outage ElectiveMaintenance Backlog

    295 288

    Corrective Aging 14 21

    The total number of non-outage corrective maintenance work requests (WRs). Defined in EN-WM-100, which is based on INPO-AP-928.

    Goals are Green 10 but 15

    PASSPORT

    OwnerRalph Dodds

    AnalyzerPerry Kearney

    41 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    45/62

    ANO Unit-2

    PI TitleNon-Outage Corr. Maint. Backlog

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNon-Outage CorrectiveMaintenance Backlog

    5 9

    CorrectiveMaintenance BacklogYTD Goal

    10 10 10 10 10 10 10 10 10 10 10 10 1

    Non-Outage ElectiveMaintenance Backlog

    295 285

    Corrective Aging 107 50

    The total number of non-outage corrective maintenance work requests (WRs). Defined in EN-WM-100, which is based on INPO-AP-928.

    Goals are Green 10 but 15

    PASSPORT

    OwnerRalph Dodds

    AnalyzerPerry Kearney

    42 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    46/62

    ANO Unit-2

    PI TitleSchedule Scope Stability

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecActual YTD 92 93

    Goal YTD 92 92 92 92 92 92 92 92 92 92 92 92

    Monthly Actual 92 93

    The percentage of jobs included in the T-6 scope freeze that are still scheduled at the end of T-1. Stability (%) = (number of tasks in the Tschedule that were also in the T-6 schedule / number of tasks in the T-6 schedule) x 100.

    Max-Target-Min (95- 92 - 85)Goals are Green >=92, White ,=85, Red

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    47/62

    ANO Unit-1

    PI TitleSchedule Scope Stability

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecActual YTD 96 97

    Goal YTD 92 92 92 92 92 92 92 92 92 92 92 92

    Monthly Actual 96 97

    The percentage of jobs included in the T-6 scope freeze that are still scheduled at the end of T-1. Stability (%) = (number of tasks in the Tschedule that were also in the T-6 schedule / number of tasks in the T-6 schedule) x 100.

    Max-Target-Min (95- 92 - 85)Goals are Green >=92, White ,=85, Red

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    48/62

    ANO Unit-2

    PI TitleSchedule Scope Adherence

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecYTD Actuals 93.0 92.0

    YTD Goal 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95

    Monthly Actual 95.0 92.0

    The percentage of activities in the schedule actually completed within the execution week against those that were scheduled forcompletion at the schedule freeze point.

    Max-Target-Min 96 - 95 - 90

    Goals are Green >=95, White =90, Red

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    49/62

    ANO Unit-1

    PI TitleSchedule Scope Adherence

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecYTD Actuals 95.0 94.0

    YTD Goal 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95

    Monthly Actual 95.0 94.0

    The percentage of activities in the schedule actually completed within the execution week against those that were scheduled forcompletion at the schedule freeze point.

    Max-Target-Min 96 - 95 - 90

    Goals are Green >=95, White =90, Red

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    50/62

    ANO

    PI TitleSignificant Events

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecSignificant Events -Month

    0

    Noteworthy Events -Month

    0

    Significant Events -YTD

    0

    Noteworthy Events -YTD

    0

    Significant Events -Monthly Goal

    0 0 0 0 0 0 0 0 0 0 0 0

    Significant/Noteworthy Events-Month

    0

    Significant/Noteworthy Events-YTD

    0

    The total number of significant events recorded during the month. Significant/Noteworthy events are defined by INPO 94-001, Rev 1.

    GOAL: Zero Significant Events per month.

    INPO Plant Events Database OwnerAlan Ettlinger AnalyzerSam Cecil

    47 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    51/62

    ANO

    PI TitleStaffing

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecSite Total 775 771

    Contractor Total 176 291

    All utility personnel permanently assigned to the plant, excluding baseline contractors.

    No specific Site goal has been established.

    Human Resources

    OwnerTodd Chilcoat

    AnalyzerDanielle Thompson

    Year

    48 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    52/62

    ANO

    PI TitlePersonnel Error Rate

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNumber of Errors -Month

    1

    Monthly Error Rate 0.05

    Number of Errors - YTD 7

    YTD Error Rate 0.02

    YTD Goal 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.0

    EOY Error RateEstimate

    0.01

    12 Month Rolling ErrorRate

    0.02

    Number of Human Performance Errors as defined by HU-101 a month per 10000 person hours worked.

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    53/62

    ANO

    PI TitleSourceView NFOM

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNon-capital spending-Month

    13.590 12.471

    Non-capital spending-YTD

    14 12

    Non-capital spending-YTD Goal

    13 12

    Non-capital spending-EOY Goal

    156

    This indicator measures the non-capital spending at the reporting facility, including allocation to headquarters, excluding fuel.

    Green Budget, Red > Target + 2%

    NBM

    OwnerMarla Gardner

    AnalyzerBernice Oscar

    50 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    54/62

    ANO

    PI TitleSourceView Total Capital

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecCapital Spending -Month

    13.636 1.822

    Capital Spending -YTD 13.636 1.822

    Capital Spending YTDGoal

    2.911 3.156

    Capital spending EOYGoal

    79.788

    All costs associated with improvements and modifications made during the reporting year, for which a capital ruling was made. This

    includes design, installation, equipment costs, Misc capital additions, etc. Data is in Millions.

    Green Budget, Red > Target + 2%

    ata Source OwnerMarla Gardner

    AnalyzerBernice Oscar

    51 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    55/62

    ANO

    PI TitleProduction Cost

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecProduction Cost-Month

    47.34 15.92

    Production Cost-YTD 3.95 15.92

    Production Cost-YTDGoal

    17.04

    Production Cost-EOYGoal

    17.04

    The expenditures (numerator) include:1 Site, Headquarters and ESI O&M (excluding power bill at GGNS), 2 Annual fuel costs including

    lease,3 Normalized outage. The generation (denominator) is calculated based on annual generation.

    Green: Monthly Goal is achieved.Red: Monthly Goal is not achieved.

    Green

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    56/62

    ANO

    PI TitleProduction Cost Plus Capital

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecProduction Cost plusCapital-Month

    60.510 22605.000

    Production Cost plusCapital-YTD

    23.310 22605.000

    Production Cost plusCapital-YTD Goal

    22.580

    Production Cost plusCapital-EOY Estimate

    22.960

    The expenditures (numerator) include: 1 Site, Headquarters and ESI O&M (excluding power bill at GGNS), 2 Annual fuel costs includinglease, 3 Normalized outage, 4 New Capital - responsibility view - cash basis. The generation (denominator) is calculated based on annualgeneration.

    Graph is YTD spending versus YTD Goal. Only Red/Green. Green Budget.

    ata Source OwnerMarla Gardner

    AnalyzerCliff Gatlin

    53 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    57/62

    ANO

    PI TitleOvertime Rate - Non-Outage

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecNon-Outage OvertimeYTD

    74523 326673

    Non-Outage OvertimeYTD

    74523 326673

    YTD Non-OutageOvertime Rate (%)v

    5.54 9.56

    YTD Non-OutageOvertime Rate (%)Goal

    3.19 4.56

    EOY Non-OutageOvertime Rate (%)Estimate

    5.94

    EOY Non-OutageOvertime Rate (%)Goal

    3.19

    Overtime cost for the period as a percentage of the base payroll during the period. Overtime includes shift differential but excludespremiums and bonuses. Base payroll includes straight time, holiday, sick leave, vacation, etc. Only Entergy permanent Employees(mgmt & union) are monitored. This % indicator displays the total overtime dollars paid for non-outage, non-capital hours divided bythe straight time dollars paid during the period.

    Green budget, Red > 2% over budget

    ata Source OwnerMarla Gardner

    AnalyzerCliff Gatlin

    54 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    58/62

    ANO

    PI TitleInventory

    Month/YearJan-09

    StatusGray

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecInventory-Month 56.075 59.869

    Inventory-Month Goal 56.400 59.919

    GL Balance Balance of Materials On Hand, Received in 2008, and Reserved to Work Orders for the next refueling outage Balance ofMaterials On Hand, received in 2008 and Reserved to Capital Work Orders Supplemental exclusions (executive level approval required)Adjusted Inventory Balance.

    Common Fleet Goal:

    Green 0% growth and 2% growth

    MPC

    OwnerMichael Little

    AnalyzerAnthony Toney

    Year2009

    55 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    59/62

    ANO

    PI TitleRadwaste Generated

    Month/YearJan-09

    StatusRed

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecRadwaste Generated-Month

    4470.0 2148.0

    Radwaste Generated-YTD

    4470.0 2148.0

    Radwaste Generated-YTD Goal

    5140 1354

    The volume of low-level solid radioactive waste generated indicator monitors progress toward reducing the volume of low-level wastegenerated.

    Goal based on availability of funds (accrual for legacy waste and 2003 waste disposal budget) to process existing radioactive material onsite to determine what is reusable material and what is rad waste. Only Red / Green. Green goal.

    ata Source OwnerDavid Moore

    AnalyzerDon Marvel

    56 of 59

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    60/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    61/62

  • 8/14/2019 Exported on: 03/05/2009 13:44 CST by: Simmons, James

    62/62

    ANO

    PI TitleHazardous Waste Generation

    Month/YearJan-09

    StatusGreen

    Description Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 DecHazardous WasteGeneration - Month

    80 225

    Hazardous WasteGeneration - MonthGoal

    500 600 600 500 500 500 500 500 500 500 500 500 50

    Hazardous WasteGeneration - YTD

    80 225

    Total pounds of hazardous waste generated as a result of plant activities.

    Green: Monthly hazardous waste generation less than or equal to 600 pounds. White:Monthly hazardous waste generation greater than600 pounds but not more than 2200 pounds. Red: Monthly hazardous waste generation greater than 2200 pounds.

    ata Source OwnerTeresa Madeley

    AnalyzerDennis Calloway

    CommitChanges