Exploring the Design Space of the Dry Configuration of the …duncanlm/ZESTTR_TEDP.pdf · 2012. 7....
Transcript of Exploring the Design Space of the Dry Configuration of the …duncanlm/ZESTTR_TEDP.pdf · 2012. 7....
Exploring the Design Space of the Dry Configuration of the
Nanoparticle Field Extraction Thruster in Microgravity
Team ZESTT Reflight (Zero-g ElectroStatic Thruster Testbed Reflight)
Test Equipment Data Package
Institution:
University of Michigan
Student Space Systems Fabrication Laboratory
Space Research Building
2455 Hayward St.
Ann Arbor, MI 48109
University of Michigan Faculty Advisor: Professor Brian Gilchrist
Electrical Engineering and Space Systems
(734) 763-6230
University of Michigan Principal Investigator:
Thomas Liu
Aerospace Engineering
(720) 984-4481
Team Contact: Mike Huang
Junior, Electrical Engineering
(248) 974-0597
2
Change Page
Version Date Authority signature Description
First Submission May 5, 2010 Brian Gilchrist
Thomas Liu
3
Quick Reference Sheet
Principal Investigator: Thomas Liu, Brian Gilchrist
Contact Information:
Thomas Liu
1320 Beal Ave., 1052 FXB
Ann Arbor, MI 48109
(720) 984-4481
Mike Huang
45499 Irvine Dr
Novi, MI 48104
(248) 974-0597
Experiment Title: Exploring the Design Space of the Dry Configuration of the Nanoparticle Field
Extraction Thruster in Microgravity
Work Breakdown Structure (WBS): Integrated Systems Tests – Present – June 3th
; Flight Readiness
Review – June 4th
; Packing Completion/Travel to Ellington Field – June 15th
Flight Date(s): June 17th
-26th
Overall Assembly Weight (lbs): 366.4lbs
Assembly Dimensions (L x W x H): 59” x 24” x 28”
Equipment Orientation Requests: Long axis aligned with plane’s axis
Proposed Floor Mounting Strategy (Bolts/Studs or Straps): Bolts/Studs for chassis frame, straps for
individual component mounting to chassis frame
Gas Cylinder Requests (Type and Quantity): 1 Nitrogen K-Bottle (for ground testing)
Overboard Vent Requests (Yes or No): No
Power Requirement (Voltage and Current Required): 115V 60Hz, 20A
Free Float Experiment (Yes or No): No
Flyer Names for each Proposed Flight Day: Flight Day One: Vritika Singh, Dave Chen, John
Orlowski; Flight Day Two: Mike Huang, Duncan Miller, Nathan Van Nortwick
Camera Pole and/or Video Support: One camera pole requested for overall flight experiment
observation
4
Table of Contents
1 Flight Manifest .................................................................................................................................. 9
2 Experiment Background ................................................................................................................... 9
3 Experiment Description .................................................................................................................. 10
3.1 M-2 Thruster Prototype ............................................................................................................. 11
3.2 Induction Charge Detector ........................................................................................................ 11
3.3 Faraday Probe ........................................................................................................................... 13
3.4 Experiment Operation .............................................................................................................. 14
4 Equipment Description ................................................................................................................... 14
4.1 Vacuum System ........................................................................................................................ 14
4.1.1 Vacuum Chamber .............................................................................................................. 15
4.1.2 Viewports .......................................................................................................................... 16
4.1.3 High Voltage Feedthroughs ............................................................................................... 16
4.1.4 Instrumentation Feedthroughs........................................................................................... 17
4.1.5 Gate Valve ......................................................................................................................... 18
4.1.6 Leak Valve ......................................................................................................................... 19
4.1.7 Exhaust Filtration .............................................................................................................. 20
4.1.8 Thruster Prototype and Probe Mount ................................................................................ 20
4.1.9 Mounting Vacuum Chamber to Chassis ............................................................................ 21
4.1.10 Vacuum Chamber Certification ......................................................................................... 22
4.2 Pumping System ....................................................................................................................... 22
4.2.1 Piston Roughing Pump (Ground use only) ....................................................................... 23
4.2.2 Turbo Pump and Controller (Turned off in flight) ............................................................ 24
4.2.3 Pressure Gauge and Controller ......................................................................................... 24
4.3 Humidity Mitigation ................................................................................................................. 25
4.3.1 Heat (Ground use only) ..................................................................................................... 25
4.3.2 Nitrogen Purging (Ground use only)................................................................................. 27
4.4 Electrical Equipment ................................................................................................................ 28
4.4.1 Master Kill Switch ............................................................................................................ 28
4.4.2 DC Power Supply.............................................................................................................. 29
4.4.3 High Voltage System ......................................................................................................... 29
4.4.4 Piezo System ..................................................................................................................... 31
4.5 Data Acquisition System .......................................................................................................... 33
4.6 Extra Ground Equipment.......................................................................................................... 34
4.7 Chassis Layout and Flyer Positioning ...................................................................................... 35
5
4.8 Special Handling Requirements ............................................................................................... 35
4.9 Free Float Experiment .............................................................................................................. 36
5 Structural Verification ..................................................................................................................... 36
5.1 Analysis Method....................................................................................................................... 36
5.1.1 Free Body Diagrams ......................................................................................................... 36
5.1.2 Component Specifics ........................................................................................................ 36
5.1.3 Minimum Margin of Safety Table ..................................................................................... 41
6 Electrical Analysis........................................................................................................................... 41
6.1 Schematic ................................................................................................................................. 41
6.2 Outside Chamber Wiring .......................................................................................................... 41
6.2.1 High Voltage Wiring ......................................................................................................... 42
6.2.2 Piezo Drive Line Wiring ................................................................................................... 43
6.3 Vacuum Side Wiring ................................................................................................................. 43
6.4 Electrical Load Analysis ........................................................................................................... 43
6.5 High Voltage Discharging ........................................................................................................ 44
6.6 Electrical Kill Switch ............................................................................................................... 45
6.7 Loss of Electrical Power........................................................................................................... 45
6.8 MATLAB Automation Scheme ................................................................................................ 45
7 K-Bottle ........................................................................................................................................... 47
8 Laser Certification........................................................................................................................... 48
9 Parabola Details and Crew Assistance ............................................................................................ 48
10 Institutional Review Board (IRB) ................................................................................................... 49
11 Hazard Analysis .............................................................................................................................. 49
11.1 Integrated Hazard Analysis ...................................................................................................... 49
12 Tool Requirements .......................................................................................................................... 58
13 Photo Requirements ........................................................................................................................ 58
13.1 Photographers ....................................................................................................................... 58
13.2 S-Band Downlink ................................................................................................................. 58
13.3 Fixed Camera Poles .............................................................................................................. 58
13.4 Product Format and Quantities of Imagery .......................................................................... 58
14 Aircraft Loading .............................................................................................................................. 59
14.1 Ground Equipment ................................................................................................................ 59
14.2 Hardware Manipulation Strategy .......................................................................................... 59
14.3 Weights and Loading ............................................................................................................ 59
15 Ground Support Requirements........................................................................................................ 59
6
15.1 Power .................................................................................................................................... 59
15.2 K-bottles ............................................................................................................................... 59
15.3 Chemicals ............................................................................................................................. 59
15.4 Building Access .................................................................................................................... 59
15.5 Tool Requirements ................................................................................................................ 60
16 Hazardous Materials ....................................................................................................................... 60
17 Material Safety Data Sheets ............................................................................................................ 60
18 Experiment Procedures Documentation.......................................................................................... 60
18.1 Equipment Shipment to Ellington Field ............................................................................... 60
18.2 Ground Operations ................................................................................................................ 60
18.3 Loading/Stowing ................................................................................................................... 60
18.4 Pre-Flight .............................................................................................................................. 60
18.5 Take-off/Landing .................................................................................................................. 61
18.6 In Flight ................................................................................................................................ 61
18.7 Prior to First Parabola ........................................................................................................... 61
18.8 2-G Period ............................................................................................................................. 61
18.9 Reduced Gravity Period ........................................................................................................ 61
18.10 Turnarounds .......................................................................................................................... 62
18.11 Emergency Procedures, Precautions, and Contingencies ..................................................... 62
18.12 Post Flight ............................................................................................................................. 62
18.13 Off-Loading .......................................................................................................................... 62
18.14 Emergency/Contingencies .................................................................................................... 63
References ............................................................................................................................................... 64
Appendix A: Exceptions/Deviations/Waivers ......................................................................................... 65
Appendix B: Isopropyl Alcohol MSDS .................................................................................................. 67
Appendix C: Acetone MSDS ................................................................... Error! Bookmark not defined.
Appendix D: Compressed Nitrogen Gas MSDS ...................................... Error! Bookmark not defined.
Appendix E: 5 Micron Silver Coated Particles MSDS ........................................................................... 78
Appendix F: RTV Silicone MSDS .......................................................................................................... 81
Appendix G: Conductive Epoxy (Part A) MSDS ................................................................................... 89
Appendix H: Conductive Epoxy (Part B) MSDS ................................................................................... 93
Appendix I: Vacuum Chamber Leak Check Certification ...................................................................... 97
Appendix J: Welding Certification .......................................................................................................... 98
7
Table of Figures
Figure 1: M-2 Prototype .......................................................................................................................... 11 Figure 2: ICD prototype cross section view
4 ......................................................................................... 12
Figure 3: ICD differential signal amplification circuitry ....................................................................... 13
Figure 4: ICD with Faraday Probe ......................................................................................................... 13 Figure 5: Faraday Probe amplification circuitry .................................................................................... 14 Figure 6: A CAD model of 12" spherical chamber with attached flanges/feedthroughs ....................... 15 Figure 7: Kodial glass viewport from Kurt J. Lesker Company ............................................................ 16 Figure 8: Single pin HV feedthrough from Kurt J. Lesker Company .................................................... 17
Figure 9: Barrel connectors used to make wire connections on the vacuum side of electrical
feedthroughs ............................................................................................................................................ 17 Figure 10: A BNC feedthrough will be used for piezo lines going in and out of the vacuum chamber 18
Figure 11: 50 pin, D-Sub connector used for instrumentation connections to and from vacuum chamber
................................................................................................................................................................. 18 Figure 12: Aluminum gate valve from Pascal Technologies .................................................................. 19
Figure 13: Leak valve used to vent and nitrogen purge the vacuum chamber ....................................... 19 Figure 14: A picture of the Ahlstrom Grade 142 glass microfiber filter with 3um pore size taken under
an optical microscope.............................................................................................................................. 20
Figure 15: Left: thruster and probe mount rod welded to 8" flange Right: thruster prototype and probe
assembled on the mount rod .................................................................................................................... 21
Figure 16: The chamber mounted to the 6061 Al plate .......................................................................... 22 Figure 17: The pumping system consists of the turbo pump and piston pump mounted to a 4.5” CF
after the gate valve .................................................................................................................................. 23
Figure 18: The XtraDry 150-20 roughing pump will be used to pump dowm from atmosphere to 0.2
Torr .......................................................................................................................................................... 23 Figure 19: Varian Turbo-V 70 LP pump and controller ......................................................................... 24 Figure 20: PKR 251 Compact FullRange Gauge and Controller........................................................... 25
Figure 21: A bake-out heater tape will allow the vacuum chamber to be baked-out at a set temperature
to speed up the pump down process ........................................................................................................ 26
Figure 22: Variable AC power supply to power the bake-out heater strip ............................................. 26 Figure 23: Pump down curves for normal air, humid air, and humid air with heat ............................... 27 Figure 24: Over pressure burst valve from Accu-Glass Products, Inc. on a 1.33”CF that will be
attached to a 6” CF using a reducer flange ............................................................................................. 28 Figure 25: AC power strip and Master Kill Switch ............................................................................... 29 Figure 26: Keithley 2400 Sourcemeter .................................................................................................. 29 Figure 27: HVRack front panel .............................................................................................................. 29
Figure 28: HVRack D-Sub control interface ......................................................................................... 30 Figure 29: PD-1301 Piezo driver front panel ......................................................................................... 31 Figure 30: Piezo switch box with Pearson coil ...................................................................................... 32 Figure 31: Piezo control feedback scheme ............................................................................................ 32
Figure 32: Top: 2.5X preamp for piezo driver Bottom: 10Hz low pass filter ........................................ 33 Figure 33: Left: NI USB 6218 Right: NI USB 6259 DAQs .................................................................. 33 Figure 34: Panasonic Tough-book ......................................................................................................... 34 Figure 35: Chassis layout and flyer positioning .................................................................................... 35 Figure 36: 80/20 beam cross section ...................................................................................................... 37 Figure 37: Beam distribution: 1515 beams shown in blue. 1530 beams shown in green. 1010 beams
8
shown in red ............................................................................................................................................ 37 Figure 38: Aircraft mounting brackts span the width of the chassis ...................................................... 38
Figure 39: Electrical schematic .............................................................................................................. 41 Figure 40: HV Cap on 2.75" flange ....................................................................................................... 42 Figure 41: In-vacuum D-Sub cable with PEEK connector and Kapton wire, the non-terminated side
will have quick disconnects to connect to the ICD and Faraday Probe8 ................................................. 43
Figure 42: High voltage discharging time constant ............................................................................... 45 Figure 43: MATLAB automation scheme .............................................................................................. 46 Figure 44: Schematic of nitrogen purging pressure system ................................................................... 47
List of Tables
Table 1: Flange Usage ............................................................................................................................ 15
Table 2: Extra Ground Equipment ......................................................................................................... 34 Table 3: Component Mounting .............................................................................................................. 38
Table 4: Mass Budget ............................................................................................................................. 39 Table 5: Current Load Chart ................................................................................................................... 44 Table 6: NI USB 6218 ............................................................................................................................ 45
Table 7: NI USB 6259 ............................................................................................................................ 46 Table 8: Nitrogen purging pressure vessel design specifications ........................................................... 48
9
1 Flight Manifest
Each flight day will require three flyers: one to run the MATLAB automation of the experiment and
two to monitor the equipment.
Flight crew: Mike Huang ([email protected])
Junior Electrical Engineering
Vritika Singh ([email protected])
Sophomore Aerospace Engineering
David Chen ([email protected])
Senior Electrical Engineering
Duncan Miller ([email protected])
Freshman Aerospace Engineering
John Orlowski ([email protected])
Junior Atmospheric Oceanic and Space Sciences
Nathan Van Nortwick ([email protected])
Freshman Aerospace Engineering
Ground crew: David Liaw ([email protected])
Graduate student Electrical Engineering
David Yu ([email protected])
Graduate student Aerospace Engineering
2 Experiment Background
The Nano-particle Field Extraction Thruster (NanoFET) is currently under development at the
University of Michigan in collaboration with ElectroDynamic Applications (EDA). Development
started in 2005 as a projected funded by the NASA Institute for Advanced Concepts (NIAC). NanoFET
electrostatically charges micro/nano-particle propellant utilizing an electric field to accelerate them
through a series of gate electrodes at varying electric potentials. As a result, NanoFET has a variable
specific impulse, a measure of propellant usage efficiency, which can be adjusted by changing the
magnitude of the applied electric field. Particles are pushed against a charging sieve in the form of a
constant force spring. A piezoelectric ceramic (piezo) mounted against the charging sieve provides the
energy necessary to overcome cohesion forces between particles and adhesion forces between the
particles and sieve. Due to the particle’s size, particle-particle cohesive forces cause the particles to
clump together, inhibiting their ability to pass through the sieve. Particles also tend to adhere to the
sieve and reservoir walls. The piezo provides an inertial kickoff to overcome these forces, thus
allowing the particles to be subjected to the applied electric field and accelerated to create thrust1. By
10
varying the piezoelectric actuation frequency and thus changing the rate at which layers of particles are
kicked off the sieve, one can control the overall thrust generated.
As shown in Equation 1, NanoFET’s specific impulse (Isp) is proportional to the charge to mass ratio of
each particle. The particle charge (q) is controlled by the applied charging electric field2.
(1)
Variable specific impulse and variable thrust provides NanoFET with a large range of operating
capabilities, thus allowing the optimal configuration to be selected for specific maneuvering tasks3.
NanoFET also has several proposed terrestrial uses beyond space propulsion, including sub-dermal
injection and dry printing applications.
The 2008-2009 ZESTT group designed and tested the first generation NanoFET macro-scale prototype
(M-1). This year, the ZESTT Reflight team has shifted focus to developing the diagnostic tools
necessary to measure the current generation and future generation NanoFET performance
characteristics. Traditionally, NanoFET testing has relied on Particle Tracking Velocimitry (PTV) data
using a laser and fastcam to measure particle velocity. However the particle exhaust plume becomes
increasingly difficult to image as the particles continue to scale smaller in size and speed up due to
larger accelerating electric fields. To measure particle velocity, particle charge, and exhaust plume
current density, the ZESTT Reflight team is designing and building an Induction Charge Detector
(ICD) and Faraday Probe. NanoFET’s thrust and specific impulse can then be estimated from these
measured values. By flying the NanoFET thruster along with these diagnostic tools in microgravity, the
ZESTT Reflight team will be validating NanoFET’s feasibility in a vacuum and microgravity
environment, thereby increasing the NanoFET’s Technology Readiness Level and proving diagnostic
capabilities.
The goal of the ZESTT Reflight team is to implement a vacuum testbed for current and future
NanoFET ground and microgravity related experiments. The following are the technical objectives for
the ZESTT Reflight program.
1. Implement a vacuum testbed for characterizing NanoFET prototypes’ performance in laboratory
and microgravity test conditions.
a. Upgrade pumping capability relative to ZESTT (i.e., faster pumpdown times).
b. Maintain low pressure (10-5
Torr) for extended periods in absence of pumping.
c. Prepare and accommodate for humid test conditions
2. Measure emission current and throughput with a Faraday probe.
3. Measure particle charge and time-of-flight with an Induction Charge Detector.
4. Demonstrate piezoelectric feedback control on NanoFET prototypes.
5. Conduct an automated experiment that that is triggered into operation only in microgravity
while collecting data describing emission characteristics.
3 Experiment Description
The microgravity experiment is comprised of a particle emission source, the NanoFET Prototype, and
sensors, ICD and Faraday Probe to be housed in a vacuum chamber. The equipment drives for this
11
experiment are described in detail in Section 4.
3.1 NanoFET Thruster Prototype
One NanoFET thruster prototypes will be flown in flight shown in Figure 1. The polycarbonate spring
block houses the particle reservoir in the form of a syringe and plunger. The particles that are being
loaded into the syringe are 38-45um silver coated glass particles from MO-SCI Specialty Products, see
Appendix E for MSDS. A constant force spring applies backpressure to the plunger, pushing the
particles into the charging sieve.
Figure 1: M-2 Prototype
Beneath the spring block is the sieve block. The sieve is a 60um weaved mesh conductive epoxied to a
washer and clamped between a ceramic spacer and the polycarbonate spacer below it. The sieve will be
charged to 15kV for testing. A grounded acceleration gate is placed 1cm away from the sieve followed
by another grounded gate 1cm below the first gate. Between the two grounded gates is piezoelectric
ceramic, CMAR04, from Noliac. The outer diameter of the ring piezo is 15mm with an inner diameter
of 9mm. The maximum operating voltage is 200V and maximum operating temperature is 200oC with a
Curie temperature of 350oC. In flight, the thruster prototype will be tested with a piezo operated with
various input waveforms ranging between 10 and 12kHz 150V sinusoids. Emission from the thruster
then either strikes the surface of a Faraday Probe, or enters the 300um orifice of the ICD.
3.2 Induction Charge Detector
An Induction Charge Detector prototype is currently on loan from NASA Jet Propulsion Laboratory
(JPL) for characterizing NanoFET’s performance. The ICD prototype consists of two sensor tubes each
connected to electrical ground through a 2GΩ resistor. As a charged particle passes through the 2.5mm
12
diameter sensor tube, a reflective charge is induced on the sensor. The current that passes over the 2GΩ
resistor is measured through an amplifier circuit. After the particle passes through both sensor tubes, it
strikes a collection anode through which the particle discharges over a resistor. The sensors and anode
are supported by an insulating skeleton inside a conductively grounded tube casing that shields the
sensors from electro-magnetic noise. The particle emission plume is spatially filtered by a 300um hole
at the face of the casing aligned axially with the thruster to increase the likelihood of particles entering
the sensor.
Figure 2: ICD prototype cross section view4
The sensor tube voltages are measured differentially, V1-V2, corresponding to the current pulled to the
first sensor as particle passes through and current pulled to the second sensor. The output waveform is
expected to look like a series of three voltage spikes.: the first down, then an up spike approximately
twice the magnitude of the first, then a second down spike. A second output measures the anode
voltage (V3) minus V1. When the particle strikes the anode, the V3-V1 signal will spike and RC decay.
An estimate of particle velocity can be made by dividing the 1.8cm length of each sensor tube by the
time between down to up spikes of the V1-V2 signal. The AD549 amplifiers in the ICD circuitry are low
noise buffers that drive the downstream differential instrumentation amplifiers, IN126s. The INA126s
amplify the differential signals V1-V2 and V3-V1.
13
Figure 3: ICD differential signal amplification circuitry
3.3 Faraday Probe
The Faraday Probe is the collection plate for the particle emission plume. The probe is placed on the
top face of the ICD with a 300um hole in the center to allow for particles to enter the ICD. The plate is
attached to and surrounded by a grounded tube, see Figure 4, such that the unit fits over the ICD and is
screwed into the ICD cap. The grounded tube also serves as additional shielding of the probe from
electro-magnetic noise.
Figure 4: ICD with Faraday Probe
14
As the particle plume strikes the Faraday Probe, particle charge is flows over a 1MΩ resistor, over
which the voltage is measured. This voltage is then passed through three gain stages totaling 1000X
amplification. The net effect of a large number of particle strikes results in a DC shift in the noise floor
through which the total emission current can be measured.
Figure 5: Faraday Probe amplification circuitry
3.4 Experiment Operation
The vacuum chamber will be pumped down to the target level of 10-7
Torr throughout the week leading
up to flight. Pressure is to be held during flight by closing the gate valve between the vacuum chamber
and turbo pump. The pumps are then turned off. In flight, the experiment is automated by a MATLAB
program. At the beginning of flight, high voltage is turned on to supply the charging and accelerating
field to the particles. Upon the entrance of microgravity, the piezo is turned on; the piezo is turned off
after a second of operation. The data from the ICD and Faraday probe are measured by a data
acquisition device and stored to the flight laptop. See Section 6.8 for a detailed explanation of the
MATLAB automation scheme.
4 Equipment Description
The following sections describe the flight and ground equipment to be used at Ellington Field. The
experiment equipment can be divided into four main subsystems: vacuum system, pumping system,
humidity mitigation system, electrical system, and data acquisition system.
4.1 Vacuum System
A vacuum system will aid in producing space-like conditions to test the thruster prototypes. Air drag
greatly reduces particle velocity by an order magnitude (from m/s to cm/s), thus the vacuum system is
an important component of ZESTT Reflight’s experiment in order to gain the most representative data.
The vacuum system consists of the vacuum chamber with flanges/feedthroughs, pumping system, gate
valve, and pressure measurement device. The aimed ultimate pressure for the vacuum chamber is 10-7
15
Torr, but the chamber will be pumped down to at least 10-5
Torr during all testing. All parts installed
into the vacuum chamber will also be allowed to outgas the week prior to flight.
4.1.1 Vacuum Chamber
The vacuum chamber to be used with this experiment is a 12” spherical vacuum chamber from Kurt J.
Lesker Company, shown in Figure 6 below.
Figure 6: A CAD model of 12" spherical chamber with attached flanges/feedthroughs
This spherical chamber is constructed of 3/16” thick, 304 stainless steel, has a volume of about 905 in3
and weight of approximately 52 lbs without flanges, is rated to 10-10
Torr, and is equipped with 11
Conflat Flanges (CF) to accommodate the feedthroughs and vacuum equipment necessary for the
experiment. Of the 11 flanges, four flanges are 2.75” CF, one is 4.5” CF, two are 6” CF, and the final
four flanges are 8” CF. The overall flange usage is shown in the table below.
Table 1: Flange Usage
Flange Usage on 12” Spherical Vacuum Chamber
2.75” Pressure Gauge
2.75” Leak Valve
16
2.75” 4 pin
BNC Feedthrough
2.75” 1 pin High Voltage Feedthrough
4.5” Gate Valve and Pump System
6” Viewport
6” Over pressure burst valve with reducer flange
8” Custom Thruster Mount
8” D-Sub Instrumentation Feedthrough
8” Front Viewport
8” Bottom Viewport
4.1.2 Viewports
Two viewports are mounted on two of the 8” flanges of the vacuum chamber and another to a 6”
flange. These viewports are used instead of blank flanges to reduce mass and provide viewing angles
into the chamber. This viewing capability will aid in monitoring the prototypes during testing and in
watching for high voltage arcing within the chamber. The viewports are made from Kodial glass,
shown below, which has maximum transmission in the visible wavelengths, ensuring visibility of
internal components as well as ultra high vacuum (UHV) compatibility.
Figure 7: Kodial glass viewport from Kurt J. Lesker Company
4.1.3 High Voltage Feedthroughs
One of the available four 2.75” flanges are occupied by a single pin, high voltage (HV) feedthrough.
Each HV feedthrough, shown in Figure 8 below, is rated to 25kV and UHV.
17
Figure 8: Single pin HV feedthrough from Kurt J. Lesker Company
The HV feedthrough will be supplied with 15kV. The feedthrough will be connected to of the sieve
ofthe thruster. On the vacuum side of the HV feedthrough are single stainless steel pins, and barrel
connectors, shown in Figure 9, that will be used to connect wires to this pin.
Figure 9: Barrel connectors used to make wire connections on the vacuum side of electrical
feedthroughs
On the air side of these feedthroughs, ring terminals will be used to secure leads to the HV pin. An ultra
high molecular weight polyethylene (UHMWPE) protective cap will cover the air side of the HV
feedthrough. This is to prevent flyers from coming into contact with HV. See Section 6.2.1 for more
information on the HV cap.
4.1.4 Instrumentation Feedthroughs
Two types of instrumentation feedthroughs are used on the vacuum chamber to make all the
instrumentation connections required inside the chamber. This includes a BNC feedthrough and a D-
Sub feedthrough.
The BNC feedthrough, shown below, will be used for all the piezoelectric signal and ground lines. The
BNC connection was chosen for the piezoelectric lines due to their inherent electrical shielding
properties.
18
Figure 10: A BNC feedthrough will be used for piezo lines going in and out of the vacuum chamber
In addition to shielding, the BNC connectors provide quick, easy, and secure connections for the piezo
leads. The BNC feedthrough is a 2.75” flange with four separate BNC connections. Two of the
available four BNC connections will be used for piezo control lines, and fourth third BNC connection
will be used for all piezo ground/common lines. On the vacuum side, the BNC feedthrough has pins to
which wires will be connected using barrel connectors, shown in the figure above. Each BNC
connection is rated to 500V, 3A, and UHV.
For the ICD, Faraday Probe, and thermocouple lines, a D-Sub connector on an 8” flange, shown below,
will be used.
Figure 11: 50 pin, D-Sub connector used for instrumentation connections to and from vacuum chamber
The D-Sub connector has 50 pins and is double sided. On the vacuum side, wires will be connected to
the D-Sub connector using a vacuum compatible D-Sub cable assembly. See Section 6.3 for more on
the vacuum side D-Sub cable assembly and wiring scheme.
4.1.5 Gate Valve
19
An aluminum gate valve will be attached to the 4.5” CF before the pumping system interface. This gate
valve, shown in the figure below, is manually operated, rated to 10-10
Torr, and has a leak rate of 10-8
std cc/sec.
Figure 12: Aluminum gate valve from Pascal Technologies
The purpose of the gate valve is to seal the vacuum chamber after it has been pumped down to the
desired pressure. This will allow the vacuum chamber to retain the pressure even without continuous
pumping, thus the pumping system will not be required on-board the flight. The goal is to keep enough
pressure overnight that the chamber can easily be pumped back down to the desired pressure right
before flight. Please see Section 18.4 for more details on the use of the gate valve with the pumping
system.
4.1.6 Leak Valve
In order to return the vacuum chamber to atmospheric pressure, a leak valve is installed onto one of the
bottom 2.75” flanges. This is the Nupro SS-4H bellows leak valve pictured below.
Figure 13: Leak valve used to vent and nitrogen purge the vacuum chamber
Not only does this leak valve allow the chamber to vent to atmospheric pressure, but it also allows for
nitrogen purging of the chamber as part of the humidity mitigation plan. Please See Section 4.3 for
more on nitrogen purging and humidity mitigation.
20
4.1.7 Exhaust Filtration
Microparticles are not anticipated to escape into the atmosphere through leaks in the chamber or
through the pumps. This is because only a small amount of particles are used with the prototypes.
Additionally, the microparticles used with these prototypes are not harmful to humans (MSDS
Appendix C).
On the other hand, precautions in the form of filters will be attached to the chamber at several
interfaces, and these filters will also protect equipment from possible contamination by microparticles.
The filters to be used are made of 30um weaved mesh.
Figure 14: A picture of the Ahlstrom Grade 142 glass microfiber filter with 3um pore size taken under
an optical microscope
A filter will be attached to the 2.75” flange between the chamber and pressure gauge, 4.5” flange
between the chamber and the gate valve to protect the pumps, the 2.75” flange between the chamber
and the leak valve, and the reduced 6” flange in front of the over pressure burst valve. Ahlstrom Grade
142 filters were chosen allow maximum air flow rate while still capturing wayward particles.
4.1.8 Thruster Prototype and Probe Mount
One thruster and a ICD/Faraday probe are vertically suspended in the middle of the vacuum chamber.
They attach to a stainless steel hexagonal rod. The rod is welded to the center of a blank 8” flange.
The rod is 7/8” thick with side lengths of ½”. A series of holes is drilled into rod enabling the
attachment of the thruster and ICD/Faraday probe. The thruster and ICD/Faraday probe are attached
to the rod via ¼-20 screws and are easily accessible for ease of attachment. Two handles are welded to
the outside of the 8” inch flange. These allow for the thruster and probe mount to be lifted and held up
for in chamber wiring. This assembly is then inserted into the vacuum chamber through the top 8”
flange. A photograph of the mounting scheme is shown below in Figure 15. See the Structural Analysis
Report for the load analysis conducted on the mount rod.
21
Figure 15: Left: thruster and probe mount rod welded to 8" flange Right: thruster prototype and probe
assembled on the mount rod
The thruster and probes can be seen through the view port flange located near the front of the chassis.
The thruster and probe assembly can be seen in Figure 15.
4.1.9 Mounting Vacuum Chamber to Chassis
The vacuum chamber is mounted to the chassis on a 6061 Aluminum alloy base plate. The plate has a
thickness of 3/8” and dimensions of 14”x16”. The steel bolts will extend through the bottom 8” flange
and plate to keep all components rigidly connected. The plate will be screwed down to the 1530 Lite
and 1515 Lite beams in the center of the chassis bottom.
22
Figure 16: The chamber mounted to the 6061 Al plate
4.1.10 Vacuum Chamber Certification
The 12” spherical vacuum chamber utilized in this experiment is considered a Category D system
according to NASA’s AOD 33897 document, Section 2.3. The flanges on the chamber are the weakest
points on the vacuum chamber. In case of a rupture, the worst case scenario, the vacuum chamber
would simply return to atmospheric pressure, thus does not pose a significant danger to personnel. See
Appendix D for vacuum chamber certification documentation.
4.2 Pumping System
A two stage pumping system will be utilized to pump the vacuum chamber to the desired pressure. The
first stage consists of a piston roughing pump, and the second stage is a turbo pump. A pressure gauge
will be used to measure the pressure inside the chamber and initiate the second stage of pumping at the
right pressure. Shown below is a schematic of the pumping system.
23
Figure 17: The pumping system consists of the turbo pump and piston pump mounted to a 4.5” CF
after the gate valve
The turbo pump will be attached to the gate valve, which is attached to the 4.5” flange on the vacuum
chamber. The piston pump will be attached to the turbo pump using a 0.5” diameter metal tube and
clamps with O-Rings.
4.2.1 Piston Roughing Pump (Ground use only)
The first stage of the pumping system consists of the XtraDry 150-2 piston roughing pump, pictured
below, from Pfeiffer Vacuum with a nominal pumping speed of 7.5 m3/h.
Figure 18: The XtraDry 150-20 roughing pump will be used to pump dowm from atmosphere to 0.2
Torr
This 403 mm by 344 mm by 308 mm pump is completely dry (no oil). The piston pump will be used
until the vacuum chamber achieves a pressure of approximately 0.2 Torr, which takes around 25
minutes to accomplish, at which point the second pumping stage will be initiated. The XtraDry 150-2
24
pump will only be used on the ground. See Section 18 for details on pump and vacuum chamber
operation/procedure.
4.2.2 Turbo Pump and Controller (Turned off in flight)
The second stage of the pumping system consists of the Turbo-V 70 LP, which has a pumping speed of
68 L/sec.
Figure 19: Varian Turbo-V 70 LP pump and controller
The controller associated with the turbo pump starts and stops the pump when appropriate. The
controller initiates operation by ramping up the pump to full speed in 60 seconds or less. The pump is
6.6” in height and 4.5” in diameter. The turbo pump will be started when the vacuum chamber reaches
0.2 Torr, and the roughing pump will remain on while the turbo pump is activated. This pump will only
be used on the ground, however, it will be fly with the vacuum chamber. The controller will not be
flown.
4.2.3 Pressure Gauge and Controller
A micropirani/cold cathode pressure gauge will be used to monitor the pressure within the vacuum
chamber. The micropirani sensor measures from atmosphere to 10-4
Torr. After 10-4
Torr, the cold
cathode sensor takes over measurement and is able to measure to 10-9
Torr. These sensors have been
confirmed to be the most rugged combination of pressure sensors available, thus they are expected to
survive flight. The associated controller displays the pressure reading in real time in Torr
25
Figure 20: PKR 251 Compact FullRange Gauge and Controller
The role of the pressure gauge/controller, as part of the pumping system, is to provide the pressure
reading to signal when the second pumping stage needs to be initiated. The pressure gauge’s
information is also important to notice the ultimate pressure achieved for each test and relating that
pressure to test results, as the pressure impacts the performance of the thrusters.
4.3 Humidity Mitigation
Humidity is a big concern for this experiment as it poses a challenge to pumping down to the desired
pressure of 10-7
Torr. The accumulation of water on the inner surfaces of the vacuum chamber causes
outgassing during pump down. It may take days to fully dissipate accumulated moisture in the vacuum
chamber to get down to a low enough ultimate pressure, thus mitigation methods were investigated and
are detailed below.
4.3.1 Heat (Ground use only)
One of the simplest ways to dissipate moisture is to energize water molecules by adding heat, causing
the water to vaporize more quickly. Once the water has vaporized, the pumping system can draw out
the water vapor from the chamber. A bake-out heater tape will be wound around the vacuum chamber,
as shown below, to heat the entire chamber during the pump down process.
26
Figure 21: A bake-out heater tape will allow the vacuum chamber to be baked-out at a set temperature
to speed up the pump down process
The heater tape will be supplied voltage using a variable AC power supply, pictured below. This power
supply and heater strip will only be used on the ground as the chamber is pumped down.
Figure 22: Variable AC power supply to power the bake-out heater strip
The bake-out heater strip will be used at around 43o C, to be monitored by a thermocouple and
multimeter, to avoid overheating the pressure gauge which has a maximum operating temperature of
55o C. The pump down curves below show that while exposing the vacuum chamber to one hour of
humid air increases pump down time by about 20 minutes, using the bake-out strips during the pump-
down decreases that time by about 10 minutes.
27
Figure 23: Pump down curves for normal air, humid air, and humid air with heat
While the time to pump down with heat on humid air is still more than time to pump down with non-
humid air (normal air), this time is still less than pumping down with purely humid air, and it is
expected that with nitrogen purging, the pump down time will challenge even the normal air pump
down time.
4.3.2 Nitrogen Purging (Ground use only)
An additional method to lessen the affect of humidity is to purge the vacuum chamber with pure
nitrogen gas. By purging the system with nitrogen, that is bringing the system back to atmosphere from
vacuum by leaking in nitrogen gas instead of regular air, less water molecules are anticipated to enter
and settle on the inner surfaces of the vacuum chamber. This will cause less outgassing during pump
downs, thus reducing the time needed to get down to the desired ultimate pressure.
The equipment needed for this includes a nitrogen K-bottle, regulator, over pressure burst valve, and
hose. The nitrogen K-bottle will have a regulator set at 15 psi (760 Torr) to ensure that the vacuum
chamber is never pressurized. The over pressure burst valve will act as the final check to keep the
vacuum chamber from becoming pressurized, as it will burst between 15-25 psi. This over pressure
burst valve, seen in the figure below, will be mounted on the back 6” flange using a 6” to 1.33” CF
reducer flange.
28
Figure 24: Over pressure burst valve from Accu-Glass Products, Inc. on a 1.33”CF that will be
attached to a 6” CF using a reducer flange
A schematic, table of specifications, and some additional details on the K-bottle and associated parts
are included in Section 7. None of the nitrogen purging equipment will be flown except the leak and
over pressure valve which is already mounted onto the vacuum chamber.
To purge the vacuum system with nitrogen gas, a chamber that has been pumped down to at least 10-7
Torr will be allowed to take in nitrogen instead of air as it climbs back to atmosphere. First the turbo
pump will be turned off while the leak valve is gradually opened to allow nitrogen to leak into the
chamber. While the nitrogen leaks in, the roughing pump will continue to run. During this time period,
air may also leak in, therefore the piston pump and nitrogen will be allowed to run together until the
chamber is full of only nitrogen. After this, the gate valve will be lowered and sealed, and the leak
valve will be closed to maintain the nitrogen inside the chamber. This procedure will occur every time
the vacuum chamber needs to be brought back up to atmospheric pressure after it has been pump down.
4.4 Electrical Equipment
The following sections describe the equipment used in the high voltage system, piezo system, and data
acquisition system.
4.4.1 Master Kill Switch
The master kill switch is the power switch on a Belkin Surge Suppressor AC power strip connected to
aircraft 115V 60Hz power. In flight, this strip will directly power the DC power supplies, high voltage
power supply, piezo amplifier, NI-DAQ 6259, and flight laptop. It is easily accessible to the flyers
since it is placed in front of the vacuum chamber as shown in Figure 25. The DC power source, high
voltage power source, piezo amplifier, and NI-DAQ 6259 will all turn off immediately once the switch
is hit.
29
Figure 25: AC power strip and Master Kill Switch
4.4.2 DC Power Supply
A BK Precision 1761 DC power supply will be used to supply +/-18V power to the ICD/Faraday probe
circuitry. The circuits regulate the +/-18V supply down to +/-15V to provide the nominal voltage level
the circuitry.
Figure 26: BK Precision 1761
4.4.3 High Voltage System
The high voltage power supply that will be used is an UltraVolt HVRack supply and was successfully
flown in the 2008-2009 ZESTT campaign. The UltraVolt HVRack and has four individually
configurable 40kV channels. The front panel, as seen in Figure 27, contains the manual controls for the
HVRack. This includes dials to set the voltage level for each channel as well as dials for DC current
compliance. Additionally, LED displays on the front panel show the voltage and current levels for each
channel. To keep flyers safe during the experiment and away from high voltage while in microgravity,
the high voltage system will be automated by a MATLAB program described in Section 6.8.
Figure 27: HVRack front panel
30
4.4.3.1 High Voltage Flow
The HVRack will be controlled by the flight laptop and DAQ through a 37 pin D-Sub control interface
on the back panel of the HVRack, see Figure 28. Channel A will feed into one of the single pin, high
voltage feedthroughs on the vacuum chamber. Once inside the chamber, the high voltage line will feed
in parallel to the charging sieves of both thrusters. Similarly, channel B will feed through the other
single pin, high voltage feedthrough and to the acceleration gates.
4.4.3.2 High Voltage Control
The HVRack can be controlled via a 37 pin D-Sub connector shown in Figure 28.Pin control and signal
recording are handled by a data acquisition system as described in Section 6.8. Pins 1, 8, 15, and 22
toggle the output on and off of channels A, B, C, and D respectively. A logic 5V signal enables
respective channels and 0V disables the channels. Pins 2, 9, 16, and 23 control the voltages of channels
A, B, C, and D. A 0-5V signal corresponds to 0-43.2kV output. Pins 3, 10, 17, and 24 return the voltage
levels of the channels with a 0-5V signal that corresponds to 0-43.2kV on the channel output. Pins 3,
11, 18, and 24 control the current compliance of each channel with a 0-5V signal corresponding to 0-
108% of the maximum current allowance. Pins 4, 12, 19, and 25 returns the current being sourced out
of each channel with a 0-5V signal corresponding to 0-108% of the maximum current allowance.
Figure 28: HVRack D-Sub control interface
31
4.4.3.3 High Voltage Safety
See Section 6.2.1 for flyer protection scheme from high voltage. This scheme implements an insulating
high voltage cap and RTV Silicone at the high voltage feedthrough interface to insulate the otherwise
exposed high voltage pin. See Section 6.5 for analysis of high voltage discharging.
4.4.4 Piezo System
A PD-1301 piezo amplifier from Nihon Ceratec Co. is a 20X amplifier that will be used to drive the
thruster piezos. The piezo amplifier can provide operational ranges of -10 – 150V output and 2 Arms.
Figure 29: PD-1301 Piezo driver front panel
4.4.4.1 Piezo Switch Box and Pearson Coil
A Pearson coil will be used to measure the current sourced by the piezo amplifier. A Model 110 Pearson
coil from Pearson Electronics Inc. measures current linearly with 0.1Vout/1Ain. By wrapping the
piezoelectric drive line around the Pearson coil ten times, 1Vout/1Ain is achieved. A 1/50X voltage
divider is also built into the piezo switch box that will provide the signal for a piezo feedback control
scheme.
The Pearson coil will be housed in an electrically grounded box to protect other signal lines from the
non-shielded lines inside the box. This box will also contain switches to select which of the two
thruster piezos will be driven.
32
Figure 30: Piezo switch box with Pearson coil
4.4.4.2 Feedback control
A closed loop feedback control scheme as shown in Figure 31 will be used to actuate the piezos. A
microcontroller measures the piezo voltage and current to provide feedback control.
Figure 31: Piezo control feedback scheme
Control of the piezoelectric system will be done with a TI Piccolo microcontroller. The Piccolo has
thirteen, 12bit analog to digital inputs as well as eight pulse-width-modulated (PWM) outputs that,
once filtered, will simulate a function generator. The piezoelectric system calls for four ADC inputs,
one from each of the thruster’s thermocouple sensor outputs, one for piezo voltage, and one for piezo
current. The system will also use one of the PWM outputs that will provide the compensated signal to
the feedback loop of the thruster selected in the piezo switch box. Because the piezo draws a large
amount of power, a thermocouple is used to monitor piezo temperature. This thermocouple is a Fluke
type K thermocouple. The thermocouple measurement will be used to first ensure that the piezo does
not reach a temperature above its maximum operating (200oC) temperature or Curie temperature
(350oC). A temperature to piezoelectric constant mapping will also be used to modify the control signal
to compensate for a varying piezoelectric constant as temperature increases.
A pre-amplification stage is implemented to filter and amplify the thermocouple output. The cutoff
frequency of the filter is 10Hz to ensure that electromagnetic noise from the piezo does not contaminate
33
the temperature reading. This amplification circuit is placed directly on the M-2 spring block inside the
vacuum chamber. A second preamp circuit will be placed between the microcontroller PWM output
and the piezo driver to map the 3V max output of the microcontroller to the 7.5V max input to the
piezo driver.
Figure 32: Top: 2.5X preamp for piezo driver Bottom: 10Hz low pass filter
4.5 Data Acquisition System
The data during flight will be managed using two data acquisition devices provided by National
Instruments. The NI-USB-6259 has a maximum sampling rate of 1.25 MS/s, with 16 analog inputs and
16bit conversion. The NI-USB-6218 has a maximum sampling rate of 250 KS/s, with 32 analog inputs
and 16bit conversion. Both devices accept input signals of -10 to + 10 V.
Figure 33: Left: NI USB 6218 Right: NI USB 6259 DAQs
34
The laptop used in flight is a Panasonic Tough-book 52 Semi-Rugged laptop. This particular model is
designed to withstand shock, dust intrusion and water damage. With regards to flight, the laptop serves
as an information relay between the two DAQ modules and necessary controls via MATLAB, see
Section 6.8. The laptop has 1.8Ghz processing speed, 2Gb SDRAM, 80Gv hard drive, and weighs
7.4lbs.
Figure 34: Panasonic Tough-book
4.6 Extra Ground Equipment
In addition to the equipment listed above, several items will be brought to Ellington Field to serve as
only ground equipment.
Table 2: Extra Ground Equipment
Ground Equipment Quantity Purpose
Contained 5um Particles 2 Vials Back-Up
Contained 53um Particles 2 Vials Back-Up
Extra Vacuum Chamber Bolts 20 Back-Up
Extra Chassis Bolts 10 Back-Up
Extra Shrink Wrap 1 Roll Back-Up
Extension Cord 4 Power Components
Extra Wire 1 Roll Back-Up
Kapton Tape 2 Rolls Back-Up/Assembly
Blow Dryer 1 Assembly
Exacto-Knife Set 1 Assembly
Extra Copper Gaskets 20 Chamber Assembly
Dremmell Kit 1 Assembly
First Aid Kit 1 Safety
Box Nitrile Gloves 1 Safety/Assembly
Box Masks 1 Safety/Assembly
Box Kimwipes 2 Clean-up
Isopropanol 1 Liter Clean-up
Acetone 1 Liter Clean-up
Copper Barrel Connectors 10 Chamber Assembly
35
Vented Screws 10 Assembly
Extra High Voltage Wire 10ft. Back-Up
USB O-Scope 1 Ground Electrical Diagnostics
Digital Multimeter 2 Ground Electrical Diagnostics
Extra Banana Cable 5 Ground Electrical Diagnostics
Extra BNC Wire 5 Ground Electrical Diagnostics
Extra BNC and Banana Connectors 10 Ground Electrical Diagnostics
Solder 1Roll Back-Up/Assembly
Soldering Iron 1 Back-Up/Assembly
RTV Silicone 1 Tube Back-Up/Insulation
Silver Conductive Epoxy 1 Tube Back-Up/Assembly
4.7 Chassis Layout and Flyer Positioning
Figure 35: Chassis layout and flyer positioning
As indicated in Figure 35, two fliers will be located at the front of the chassis and a third will be
positioned to the left of the chassis. Flier 1 will monitor the pressure gauge controller (shown in
brown). Flier 1 will also periodically check the piezo amplifier (shown in grey). Flier 2’s primary
responsibility is initializing the automation code from the laptop (shown in blue) and switching the
piezo switch box every parabola. Flier 3 will view the thruster firing through the front 8” vacuum
chamber viewport and monitor the HV power supply during flight.
In the off-nominal case that Flier 1 gets ill, Flier 2 will manage the pressure gauge controller, piezo
driver and automation while the piezo switching will fall to Flyer 3. Should Flyer 2 get ill, Flyer 1 will
take over automation and again, Flier 3 will take piezo switching. If Flyer 3 falls ill, Flyer 2 will also
monitor thruster firing.
4.8 Special Handling Requirements
Nitrile gloves and masks should be worn at all time when working with particles. This includes loading
and cleaning of thrusters. When dealing with particles, use slow, steady motion to decrease likelihood
of particles becoming airborne. When not in use, the particles shall be tightly sealed in their vials.
36
During all testing all high voltage lines used must be HV rated wire: XLPE 40kV wire outside of the
chamber and 30kV silicone insulated wire inside the chamber. The high voltage power supply, when
not needed shall be turned off and unplugged.
4.9 Free Float Experiment
This experiment is not a free float experiment.
5 Structural Verification Structural analysis was performed on the chassis beam structure, vacuum base plate, aircraft mounting
brackets, and thruster mounting rod. A combination of finite element analysis (FEA) and hand
calculations using simplified and linearized equations of elastic mechanics of materials was used to
determine the maximum stresses, deformations, and worst-case factors of safety. The full entirety of
this analysis can be found in the Stress Analysis Report submitted accompanying the TEDP. All
structural configurations comply with NASA-specified worst case loading scenarios and have a
minimum factor of safety above 2.
All stress analysis was performed using the setup shown in Figure 35.
5.1 Analysis Method
ANSYS Workbench was chosen to create the mesh and perform analysis on the structure because of its
relatively simple mesh generation setup, and its unique global acceleration loading field. Refer to
section 7.2 of the Stress Analysis Report, for a comprehensive FEA analysis of the chassis beams and
vacuum chamber mounting plate.
5.1.1 Free Body Diagrams
Free Body Diagrams can be found in Section 6.0 of the Stress Analysis Report.
5.1.2 Component Specifics
The chassis is built from three types of 6105-T5 beams differentiated by their cross-sections: 1.5” by
1.5” 1515-Lite beams serve as the four vertical and bottom perimeter beams; the thicker 1.5” by 3”
1530 beams support the vacuum chamber with their increased girth; and the slender 1” by 1” beams
provide further support to the chassis on the middle perimeter and lower interior sections.
37
Figure 36: 80/20 beam cross section
Figure 37: Beam distribution: 1515 beams shown in blue. 1530 beams shown in green. 1010 beams
shown in red
The chassis is 59” in length, 24” wide and 28” tall. All beams are bolted together using 6105-T5
aluminum L-brackets and a combination of 5/16”-18 and 1/4"-20 steel bolts. The only two welds in our
setup are the handles on the top 8” blank vacuum flange, and the thruster mount rod within the
chamber. However, the handles are non-load bearing during flight, and the thrusters are fully enclosed
within the vacuum chamber and thus pose safety hazard to flyers. Welding certification documentation
is also included in the Appendix J.
The chassis will be secured to the aircraft hull at four mounting points via two angled aluminum
brackets that span the width of the chassis as seen in Figure 38. Each bracket interfaces with the aircraft
at two corners and connects with the chassis using five steel bolts. Sections 7.1.2 and Appendix of the
38
Stress Analysis Report details the methods used to obtain a minimum factor of safety of 3.8.
Figure 38: Aircraft mounting brackts span the width of the chassis
All sides of the chassis excluding the front are enclosed with heavy duty plastic insulation sheeting.
This shields from the “kick loads” of 125 lbf over a 2” radius and prevents accidental contact to
components during flight. All components except for the vacuum chamber and dry scroll pump, which
are bolted to the chassis directly, will be fastened in the chassis via Velcro, zip ties, and straps in two
directions to ensure all degrees of freedom are fully restricted. Table 3 outlines component securement.
A random vibration test will be used to verify proper attachment.
Table 3: Component Mounting
Component Mounting Method Mounting Surface
Chamber Mounting Plate 5/16” Steel Bolts 1530 Beams
DC Power Supply Straps Piezo Amplifier
Fan Velcro HV Power Supply
HV Power Supply Straps 1010/1515 Beams
DAQs Velcro 1515 Beams
Laptop Velcro/Zip-ties 1010 Beams
Piezo Amplifier Straps 1010/1515 Beams
Piezo Switch Box Velcro/Straps 1515 Beams
Power strip Zip-ties 1010 Beams
Vacuum Chamber 5/16” Steel Bolts Mounting Plate
Vacuum System-Dry Scroll
Pump
¼” Steel Bolts Mounting Plate
Vacuum System-Pressure Gauge
Controller
Straps, Velcro 1010 Beams
Vacuum System-Pump Controller Straps, Velcro 1010 Beams
The total system mass will not exceed 390.4 lbs with contingency, though we have obtained a mass
waiver of 100 lbs giving us a mass constraint of 400 lbs. However, we have weighed our complete
assembly and we do not expect it to exceed 366.4 lbs.
39
The entire experiment will not exceed 400 lbs of weight. The supporting area footprint of our
experiment is 9.83 square feet; thus, the aircraft floor will not exceed 40.6 pounds per square foot.
Table 4: Mass Budget
Item Quantity
Unit Weight
(lbs) Contingency
Mass with
Contingency
Chassis - 80/20 + Bolts + Hardware 1 73.5 5% 77.18
Chassis - Chamber Mounting Plate 1 5.4 5% 5.67
Probe Setup 1 10 20% 12.00
Shielding Mesh 1 2 20% 2.40
Mounting Rod 1 10 20% 12.00
Thruster 2 2 20% 4.80
Vacuum System - BNC Feedthrough 1 0.6 5% 0.63
Vacuum System - BNC Feedthrough 1 0.6 5% 0.63
Vacuum System - 8" Viewport 2 5.3 5% 11.13
Vacuum System - Chamber 1 51.5 5% 54.08
Vacuum System - Chamber Bolts 1 11.1 5% 11.66
Vacuum System - Converter Flange 1 5.3 5% 5.57
Vacuum System - Copper Gaskets 1 1.3 5% 1.37
Vacuum System - Hose 1 0.6 5% 0.63
Vacuum System - 6" D-Sub 1 6.4 10% 7.04
Vacuum System - Leak Valve 1 2.6 5% 2.73
Vacuum System - 8”Blank Flange 2 11.6 5% 24.36
Vacuum System - Pressure Gauge 1 1.6 20% 1.92
Vacuum System - Gate Valve 1 12 5% 12.60
Vacuum System - HV Feedthrough 2 1.4 5% 2.94
Piezo Switch Box 1 2.2 10% 2.42
DC Power Supply 1 6.9 5% 7.25
Vacuum System - Dry Scroll Pump 1 21.6 5% 22.68 Vacuum Sysem - Pressure gauge Controller 1 2.5 20% 3.00
Master Kill switch 1 2 50% 3.00
Grounding Rod 1 1.5 5% 1.58
HV Power Supply 1 21.6 5% 22.68
NI USB-6255 DAQ 1 2.7 10% 2.97
Piezoelectric Amplifier 1 25.6 5% 26.88
function generator 1 7 10% 7.70
Panasonic Toughbook 1 9 5% 9.45
Chassis - Plastic Wrap 1 0.6 5% 0.63
Wiring 1 10 15% 11.50
Systems Margin 1 10 10% 11.00
Expected Weight w/Contingency
40
Total(lbs.) 323.8 369.135
41
5.1.3 Minimum Margin of Safety Table
Refer to section 2.0 of the included Stress Analysis Report for a comprehensive margin of safety table
for all load bearing components. No factor of safety falls below the 2.0 dictated by NASA
requirements.
6 Electrical Analysis
The follow sections show the schematic and load analysis of the electrical system.
6.1 Schematic
Figure 39 shows a schematic of the electrical layout. The high voltage power supply, piezoelectric
amplifier, DC power supply, laptop, and NI-DAQ 6259 are powered by the aircraft 115V 60Hz power
through a Belkin surge suppressor. The high voltage power supply is used to charge up the accelerating
gates of the thruster. The piezoelectric amplifier drives the thruster piezos while piezo line voltage and
current measurements are made an intermediate piezo switch box. Piezo voltage and current, Faraday
Probe data, ICD data and HV voltage and current data is taken by the DAQs. The entire scheme is
automated by a MATLAB program except switching of the piezos between thrusters which is done
through the piezo switch box.
Figure 39: Electrical schematic
6.2 Outside Chamber Wiring
All wiring besides high voltage and piezo drive lines are both low current and low voltage lines and are
42
carried over either 22 gauge wire or 26 gauge BNC wire.
6.2.1 High Voltage Wiring
The high voltage output of the HVRack will be connected directly to a high voltage feedthrough. The
wire that will be used is 40kV rated XLPE wire. A B110YX10 connecter that is rated for 40kV will be
used to interface the HVRack with the XLPE wire. The XLPE wire is 12 gauge wire. The maximum
current flowing through these wires is on the order of microAmps via a settable current compliance on
the high voltage power supply. A ring terminal will be used to attach the XLPE wire to the high voltage
feedthrough pin. Room Temperature Vulcanizing (RTV) silicone will be used to enclose the exposed
feedthrough pin/ring terminal interface. RTV silicone has a high dielectric constant that will act to
protect the flyers from high voltage during flight.
A high voltage cap will also be used to enclose each of the high voltage feedthroughs from the flyers.
These caps are made of ultra high molecular weight polyethylene (UHMWPE). The maximum voltage
that the high voltage power supply can supply is 40kV. As shown in Figure 40, the high voltage cap has
a 3.5in diameter and 0.25in side wall and top thickness. The caps also have grooves that fit over the
2.75in high voltage flange to ensure that they do not come off during flight. The two halves of the high
voltage cap are screwed together and further held together by Kapton tape. The side wall thickness of
the high voltage caps provides a factor of safety of 14.3 given that the dielectric constant of UHMWPE
is 900kV/cm and the wall thickness is 0.25in. This high voltage cap has flown successfully in the 2008-
2009 ZESTT campaign. The RTV silicone layer provides an additional layer for high voltage protection
with a dielectric strength of 19.7kV/mm. Potential areas subject to a high probability of high voltage
arcing mainly within the M-2 thruster wiring interfaces and in chamber high voltage feedthrough
connector interface will be identified throughout integrated systems tests prior to travel to Ellington
Field and will be coved in 2.7mil thick Kapton tape. Each layer of Kapton tape applied provides an
additional 8,000V dielectric standoff.
Figure 40: HV Cap on 2.75" flange
43
6.2.2 Piezo Drive Line Wiring
The highest gauge BNC wiring that is used with the piezo drive lines are 26 gauge. The wiring gauge in
the piezo switch box carrying piezo drive currents is 22 gauge. The maximum current limitation of the
piezo amplifier is 2rms before overdrive protection is activated and output drops to zero.
6.3 Vacuum Side Wiring
Inside the vacuum chamber, special attention must be taken with selection of wires to ensure both
vacuum compatibility and electrical compliance.
For the piezo lines entering and exiting the vacuum chamber through the BNC feedthrough, a 24AWG,
Kapton insulted, silver plated copper wire was chosen. This wire is able to take up to 4A and 600V, and
is rated to 10-10
Torr. This wire will also be twisted paired for added electromagnetic shielding for the
piezo lines. Please see Section 4.1.1 for more on the BNC feedthrough.
The other instrumentation lines, the signal and ground lines for the ICD and Faraday Probe, will be fed
through the D-Sub feedthrough. This D-Sub feedthrough has a male D-Sub connector on both vacuum
and air sides, thus both sides will make use of a D-Sub cable with a female connector to connect to the
feedthrough. On the vacuum side, a cable assembly with a polyetheretherketone (PEEK) female D-Sub
connector attached to a Kapton insulated ribbon cable with 28AWG wire will connect the diagnostic
instruments to the D-Sub feedthrough. This cable is rated to 600V, 2A, and 10-10
Torr.
Figure 41: In-vacuum D-Sub cable with PEEK connector and Kapton wire, the non-terminated side
will have quick disconnects to connect to the ICD and Faraday Probe8
The high voltage (HV) coming into the vacuum chamber through the high voltage feedthroughs will
flow through a silicone insulated, 12AWG, stranded core, silver plated copper wire once inside the
chamber. This wire is rated to 30KV, 20A, and 10-8
Torr, and will be connected to the pins on the
vacuum side of the HV feedthrough using barrel pins, pictured in Figure 9.
6.4 Electrical Load Analysis
All loads that will be powered by aircraft 115V 60Hz power are shown in Table _. Under maximum
current draw conditions, the total current drawn from the aircraft will be 12.92A which is less than 16A
44
or 80% of the 20A circuit breaker limitation on aircraft power. The total +/- 15V DC power coming
from the DC power supply that will be used to power the instrumentation amplifiers associated with the
ICD, Faraday Probe, and microcontroller/piezo feedback scheme is less than 400mA which is less than
the maximum 1.05A current limitation of the DC power supply.
Table 5: Current Load Chart
Part Max Instantaneous Current
Draw
Supply Voltage
Laptop 0.75 A 115 V 60Hz
DC PS 1.6A 115 V 60Hz
HV PS 0.47 A 115 V 60Hz
Pressure Gauge 0.1 A 115V 60Hz
Piezo
Amplifier
10 A 115V 60Hz
TOTAL 12.92A
20A max outlet current
6.5 High Voltage Discharging
The high voltage system will be discharged directly back to the HVRack. As shown in Figure 42, the
high voltage supply takes 1.29 seconds to discharge 67% of its initial voltage when connected to two
plates similar in capacitance to NanoFET. This configuration was flown successfully during the 2009
ZESTT campaign. As such, no additional discharging mechanisms will be needed. A grounding rod
will be kept on the chassis as a precaution to actively discharge conductive surfaces that may be
suspected to still be charged after high voltage has been turned off.
45
Figure 42: High voltage discharging time constant
6.6 Electrical Kill Switch
In an emergency, only the master kill switch located on the Belkin power strip and located in the front
of the chassis needs to be switched. All component power is routed from this line and all electrical
drivers will discharge back to ground. High voltage will discharge as shown in Figure 42.
6.7 Loss of Electrical Power
In the event of a loss in electrical power, all components are turned off to a safe state. As a precaution a
grounding rod will be kept with the chassis to manually discharge conductive surfaces if needed. A loss
in electrical power to the vacuum pumps will only cause air to slowly leak back into the vacuum
chamber and will not damage any equipment.
6.8 MATLAB Automation Scheme
During flight, all experiment processes will be managed by a MATLAB program providing efficient
experiment operation and data collection, as well as flier safety. MATLAB determines which control
signals are to be sent from the flight computer, while all data collection will be managed by the DAQ
modules and then sent to the computer to be saved. The following tables show the number of samples
collected per signal line.
Table 6: NI USB 6218
Devices Number Sampling (Samples/s)
HV Power Supply Voltage 2 100
HV Supply Currents 2 100
46
Thermocouples 2 100
Accelerometer 1 100
Total Devices 7 700
Table 7: NI USB 6259
Devices Number Sampling (Samples/s)
Piezo Voltage 1 200,000
Piezo Current 1 200,000
ICD 1 200,000
Faraday Probe 1 200,000
Microcontroller Output 1 200,000
Total Devices 7 1.00E+06
To ensure the safety of the flyers as well as the experiment, safety precautions have been implemented
into the MATLAB code. The “Run/Stop” toggle button allows users to easily decide if there is a need
for sampling or if automation needs to be terminated because of danger. The initial button state is
“Run” upon the first click, and automation continues at that point. Another click of the same button will
terminate everything; including the HVPS, piezo system as well as all other controls.
The MATLAB program relies on coercion of three components; those being hardware, data and
programmable operations. The figure below demonstrates the logic behind the automation scheme.
Figure 43: MATLAB automation scheme
47
The automation scheme begins with user input. The only button that the users will have to press in
flight is the Run/Stop button. This will tell the HV power supply, via DAQ analog output signal, what
high voltage levels the M-2 charging and accelerating gates must hold. Once in microgravity, triggered
by the aircraft acceleration signal, the DAQ will tell the microcontroller via digital I/O, what waveform
to generate. Data is then taken on the ICD, Faraday probe signal, piezo current and voltage, and
microcontroller output during the duration of microgravity. Once out of microgravity, the piezo will
turn off due to a zero command from the microcontroller and the saved files will close. At this point the
fliers will have to manually switch on the piezo of the other thruster using the piezo switch box.
Meanwhile the MATLAB program waits for the next microgravity period. This process continues until
the flier presses the Stop button at the end of flight.
7 K-Bottle Team ZESTT Reflight will be bringing a nitrogen K-bottle to Ellington Field. This compressed
nitrogen gas will be used in purging the vacuum chamber as it is brought up to atmosphere from
vacuum to aid in humidity mitigation. The vacuum chamber will never be pressurized above
atmosphere, and an over pressure burst disk installed on the vacuum chamber will work to prevent the
chamber from ever going above 25 psi, although it is expected to burst closer to 15 psi than 25 psi.
Please see Section 4.3.2 for more details on this nitrogen K-bottle. A schematic of this pressure system
and a corresponding design specifications table is shown below.
Figure 44: Schematic of nitrogen purging pressure system
48
Table 8: Nitrogen purging pressure vessel design specifications
Schematic
Reference
Number
Component
Description
MAWP
(psi)
Relief Valve
Setting (psi)
Regulator
Setting
(psi)
Built By Cert.
Test/Calib.
Date
Proof Test-
Certified By
1 Nitrogen K
bottle 2400 N/A N/A Airgas, Inc. unknown On “k”
bottle DOT
sticker
2 Regulator 3000 N/A 15 Victor
Equipment
Co.
unknown unknown
3 Hose 40 N/A N/A Airgas, Inc. unknown unknown
4 Leak Valve N/A N/A N/A Kurt J.
Lesker Co. N/A N/A
5 Stainless
Steel Vacuum
Chamber
15+ N/A N/A Kurt J.
Lesker Co. Jan 29,
2009
Ron Smith,
KJLC
6 Over Pressure
Burst Disk
25 15-25 N/A Accu-Glass
Products, Inc N/A N/A
See Section 4.2 and Section 4.3.2 for additional information on the vacuum system and nitrogen K-
bottle respectively.
8 Laser Certification
No lasers will be used during flight or ground testing at Ellington Field. This section does not apply to
the experiment.
9 Parabola Details and Crew Assistance
A minimum of twenty microgravity periods is required for this experiment, per flight day. These
twenty parabolas will allow each thruster to be tested at least ten times and give enough data for proper
analysis of the M-2 and diagnostic tools. In addition to the minimum twenty microgravity parabolas,
the first two parabolas will be set aside for flyers to adjust to the microgravity and 2g conditions, the
third and fourth parabolas will test MATLAB code function with the onboard accelerometer, and any
other additional parabolas will be evenly distributed among the two M-2 prototypes to gather additional
data. The last few parabolas will be used to perform the secondary outreach experiment suggested by a
pre-college student from our outreach programs.
This experiment is almost completely automated by MATLAB, thus NASA crew member assistance
should not be required. The prototypes will also not need any handling, since they will remain sealed in
the vacuum chamber at all times. The flight crew will only interface with the GUI to initiate MATLAB
49
and monitor instruments and in-chamber conditions during the parabolas. See Section 6.8 for details on
automation.
At the turnaround period, flyers will check for proper function of the background camera and replace
the camera mini disc such that video can be taken for the remainder of the flight. Additionally, another
flight crew member will ensure that data is being stored properly. Thruster prototypes will not be
running during the turnaround time, and the prototypes do not need to be tested in consecutive
microgravity periods, thus time between parabolas is acceptable.
10 Institutional Review Board (IRB)
Neither human nor animal test subjects are part of this experiment, and no biological tests will be
conducted, thus this section is not applicable to this experiment.
11 Hazard Analysis The follow Integrated Hazard analysis contain the hazard analysis involved the ZESTT Reflight
experiment. Controls are designed to mitigate these hazards. Specifically, the high voltage system
posses the largest hazard risk of the ZESTT Reflight experiment. The only high voltage exposed to the
flyers is at the high voltage feedthrough interface. The control to be used is a high voltage cap to be
used as a high voltage standoff between the feedthrough and potential flyer contact. In chamber high
voltage arcing will be controlled by applying layers of Kapton tape to identified areas of potential
arcing. See Section 6.2.1 for details on the high voltage wiring used and dielectric standoff strength of
the high voltage cap and Kapton tape.
11.1 Integrated Hazard Analysis
Date: 5 May 2010
Hazard Analysis of ZESTT Reflight System
Facility: Microgravity Aircraft and Ellington Field, Houston, Texas
Prepared by: Team ZESTT Reflight
Organization: University of Michigan Student Space Systems Fabrication Lab (S3FL)
Risk Assessment Code
RAC Description
1 Unacceptable – All operations cease until hazard is controlled 2 Undesirable 3 Somewhat acceptable with controls
4-7 Acceptable with controls
Severity Class
Class Description I Catastrophic
50
II Critical III Moderate IV Negligible
Probability Codes
Code Description A Likely to occur B Probably will occur C May occur D E
Unlikely to occur Improbable
RAC
Assignment Probability
Severity Class A B C D E
I 1 1 2 3 4
II 1 2 3 4 5 III 2 3 4 5 6
IV 3 4 5 6 7
Hazard Condition Cause Effect Disposition
Before Controls
Controls Verification Disposition
After Controls Electrostatic Discharge
(ESD)
Contact with
exposed wiring or
close conductive
component, likely
near high voltage
Injury to person(s),
damage to
equipment
I/B/1 40kV rated XLPE
wire is used outside of
chamber and 30kV
rated silicone
insulated wire is used
inside chamber. High
voltage caps made of
UHMWPE covers the
high voltage
feedthroughs which is
the most likely place
for HV interacting
with flyers. In
addition, the air side
of the flange will be
covered with RTV
silicone rated to
19.7kV/mm before
the HV caps. All
connectors on HV
lines will be covered
with silicone tape as
well, and these lines
carrying HV will be
routed behind the
equipment on the
chassis where full
panels of plastic wrap
serve as an extra
barrier for people
from HV. Grounding
rod will serve for
manual discharging
Test continuity of
chassis structure to
ground, inspect all wires
designed to carry HV
paying special attention
to the ends to make sure
insulation is intact all
over. Check for
discontinuity between
chassis and HV to
ensure no short circuits
to HV thus unobserved
exist.
I/E/4
"K" bottle explosion Improper storage,
cap loose, improper
handling and
Equipment damage,
injury to person(s)
I/C/2 Cylinder will always
be strapped to a wall
or table, and a
Ensure strap(s) holding
cylinder to the
wall/table/vehicle is/are
I/E/4
52
trasportation regulator or cap will
always be on the
cylinder. All safety
procedures regarding
compressed air tanks
will be observed.
During transportation,
the cylinder will be
secured to keep it
from rolling around.
secure and tight, ensure
compliance with
suggested safety
precautions for
compressed air tanks.
Vacuum Chamber
Explosion/Implosion
Chamber rupture or
suddenly acquires
leak, chamber
acquires pressure
differential at 8000ft
cabin pressure due to
malfunctioning
pressure gauge
Injury to person(s),
damage to
equipment, aircraft
damage. If chamber
ruptures due to
higher pressure
inside than the
ambient pressure,
particles may
escape into the
atmosphere.
Otherwise, if
chamber ruptures, it
will likely have an
air flow in and, at
worst, will implode,
thereby not causing
injury to person(s)
though it may
damage equipment
inside the chamber
I/D/3 In the case of a
pressure differential,
installed pressure
burst valve should
burst or puncture
before the chamber
has a chance to
explode. A filter
between the chamber
and burst valve should
keep particles from
escaping in case of
this situation. For
leaks, copper gaskets
are placed between
the flange and
chamber to ensure the
best seal, or o-rings
are used, and
everything is
tightened down as
well as possible.
Inspect vacuum
chamber to be sure
pressure burst valve has
been mounted, and
through viewport, make
sure each flange has a
copper gasket. While
pumping down, ensure
all flanges have been
tightened down using
wrenches, and tighten
down any leaks found.
III/D/5
Chassis comes loose
from aircraft mounting
Improper or loose
mounting to aircraft,
overloading of
mounting brackets
Injury to person(s),
equipment damage
II/D/4 There will be many
points of connection
of the chassis to the
aircraft so if one fails,
there will be others to
hold the chassis to the
Ensure tightness of
mounting bolts, inspect
condition of brackets
and bolts
II/E/5
53
aircraft. The fasteners
will be tightened, and
structural analyses
were used to ensure
the chassis can
withstand adverse
conditions of hyper-g
forces.
Vacuum Chamber mount
comes loose
Bolts not tightened,
overloading of
chamber mount plate
Injury to person(s),
equipment damage
II/D/4 There are many points
of connection on the
mount plate to ensure
chamber will remain
in place even if one
bolt fails. The bolts
will be tightened as
much as possible.
Ensure tightness of
mounting bolts, inspect
condition of brackets
and bolts
II/E/5
Sharp Edges or Pinch-
Points
Structure/equipment
has sharp edges
made from metal or
hard plastic
Increased injury to
person(s) during 2g,
lesser extent of
injury with other
conditions
(microgravity and
1g)
II/A/1 All sharp edges and
corners will be
padded with foam.
The plastic wrap
casing of the chassis
will prevent flyers'
body parts from
entering the chassis
and making contact
with sharp equipment
points and other
objects.
Inspect structure for
sharp point and cover
with foam, ensure foam
has been secured firmly
and coverage is
acceptable, ensure
plastic wrap is in place,
snug, and coverage is
acceptable
III/D/5
High Voltage Arcing Close conductive
material with high
voltage components,
inadequate
insulation, sharp
solder joints and
other sharp metal
points at high
potential
Injury to person(s),
damage to
equipment
II/B/2 Use high voltage rated
insulated wiring;
Have adequate
distance between high
voltage components
and conductive
materials, Automate
experiment to reduce
human interaction
with high voltage
Extensive testing of
high voltage system;
Inspect all circuits and
wiring prior to each
experiment; Rehearse
emergency procedures
including methods of
turning off the high
voltage power supply
and master kill switch
II/D/4
54
components, Design
for proper discharging
of the high voltage
system, Insulate
exposed high voltage
regions, Grounding
rod for manual high
voltage discharging
Heavy Item Drop Poor mounting of
equipment to
structure
Injury to person(s),
equipment damage
II/C/3 Straps will be used to
secure all equipement
to the chassis. Load
analyses of chassis
beams have shown
their ability to
withstand equipment
weight through the
cases outlined by
NASA.
Ensure tightness of
straps and equipment
inside the straps. Make
sure straps are in good
condition. Ensure
correctness of load
analyses.
II/D/4
Handle(s) break during
lift
Weight distribution
over the handles too
large during chassis
lift, improperly
placed handles,
handles not secured
down well
Damage to
personnel and
equipment
II/C/3 Handles will be
positioned after
analysis of chassis to
find best possible
locations. All screws
will be secured down
firmly. A cart will be
used to move chassis
around as much as
possible to minimize
need for lifting.
Inspect tightness of
bolts holding handles
onto the chassis, ensure
handles are in a
comfortable position for
lifters and that
positioning is optimal
for minimizing stress on
each handle
II/D/4
Overheating vacuum
chamber during baking
Heat tape and
temperature not
monitored,
prolonged use of
heat strip
Damage to
equipment, damage
to wire and HV
feedthrough
insulation, injury to
person(s)
II/D/4 A thermocouple
placed on the vacuum
chamber will be used
to monitor the
temperature at all
times. The power
supply for the heat
strip can be turned
down or turned off in
Ensure proper
placement of
thermocouple and that it
has been activated,
ensure the hard stop is
in place, ensure easy
access to off switch of
power supply
IV/D/6
55
the event that the
temperature goes over
40oC, and a hard stop
will be placed on the
power supply at 40V
to prevent going
above this voltage and
increase the
temperature at a
higher rate.
Bent chassis beam due to
lift or flyer hanging onto
it
Stress on beam
during lift or flyers
hanging on to beams
in flight
Weakened structural
support, Injury to
person(s),
equipment damage
II/D/4 Analysis has been
conducted on all
beams with NASA
specified conditions
and have been found
to be safe with 2 or
more FOS. Top and
middle beams, where
flyers are most likely
to hang on, do not
have equipment to
bear. There will also
be foam padding on
the beams so flyers
are not injured in case
of bent beam.
N/A N/A
Airborne Micro-particles Particles leak out of
thruster and out of
vacuum chamber,
mishandling of
particles during
loading into thrusters
Injury to person(s) III/C/4 Vacuum chamber will
be properly sealed at
all flanges, and a filter
will be placed at gate
valve flange and over
pressurization disk
flange. Particles will
be kept sealed in vials
and personnel will be
trained in inserting
particles into the
reservoir properly to
Examine inner vacuum
chamber surfaces
through viewport to
ensure filters are in
place and secured.
While pumping down,
ensure leaks have been
mitigated.
III/D/5
56
keep particles from
being loosed into the
air.
Foreign objects floating
from chassis
Objects lodged in
chassis or on chassis
before flight
Injury to person(s),
equipment damage
III/C/5 Plastic wrap covering
chassis should prevent
accidental placement
of items inside
chassis. Plastic wrap
will also aid in
keeping foreign
objects in chassis
from getting out in
microgravity before
object can be
contained. A thorough
check of the entire
chassis and all
equipment will occur
before flight to ensure
no loose objects.
Ensure no loose objects
on chassis and
equipment, ensure
plastic wrap is in place
and un-ruptured
III/D/5
Shatter-able Materials Object or flyer
impacting equipment
(nothing on the
structure is
particularly shatter-
able besides the
flight laptop)
Injury to person(s),
Equipment damage
III/D/5 Sides of the structure
are covered with
plastic wrap which
has been tested to
survive 125lb kick
loads over 2" radius
and 180 lbf impact at
2m/s. Flyers will be
secured with straps
provided on the
aircraft, and handles
on the structure will
allow flyers to hold on
and keep themselves
from impacting
things.
Inspect plastic wrap and
make sure it is secured
to chassis firmly in all
places before flight.
Make sure handles are
reachable and can be
used easily by flyers.
Ensure straps are
available for flyers to
use near the chassis on
the aircraft.
III/E/6
Isopropanol expelled by
pumps in liquid form
Isopropanol enters
chamber during leak
Equipment damage III/C/4 Roughing pump will
not be used during
Ensure pump is away
from equipment,
III/D/5
57
testing due to
presence of leaks
flight so no alcohol
will ever be spewed in
flight, roughing pump
will be placed as far
away from equipment
as possible during use
remove pump from
aircraft before takeoff
Piezo overheating parts
inside vacuum chamber
due to poor heat transfer
Aggressively driving
the piezo for long
duration of time
Equipment damage
to thruster and
probes, piezo draws
an increasing
amount of current as
temperature
increases
IV/A/3 Overdrive failsafe on
the piezo driver will
prevent piezo current
from exceeding
2Arms. A
thermocouple attached
to the piezo will
monitor piezo
temperature and
maintain a maximum
temperature of 60oC
(below glass transition
temperature of
particles at 68oC)
Monitor the piezo
temperature applying an
aggressive piezo
command to check if the
piezo turns off when it
reachs >60oC
IV/E/7
Electronics overheating Current draw above
expected values
Damage to probe
circuitry
IV/C/5 Extra wires used to
heat sink regulators to
the electrical casing
box and thruster/probe
mount
Check with a
thermocouple
temperature of
regulators with and
without additional heat
sinking
IV/E/7
Batteries N/A N/A N/A N/A N/A N/A
Toxic Chemicals N/A N/A N/A N/A N/A N/A
Raioactive
Substances/Materials
N/A N/A N/A N/A N/A N/A
12 Tool Requirements
Team ZESTT Reflight is planning on bringing several of the tools required for our experiment
including: wire cutters, Allen wrenches, soldering iron and solder, oscilloscope, and digital
multimeters. The team will also make use of the following RGO supplied tools before flight: flyer
straps, velcro, grey tape, scissors, screwdrivers, wrenches, diagonal pliers, and needle nose pliers.
13 Photo Requirements
ZESTT Reflight does not have any special photo requirements, as outlined in the sections below.
13.1 Photographers
No professional photographers are needed.
13.2 S-Band Downlink
The team does not require an S-band downlink.
13.3 Fixed Camera Poles
The ZESTT Reflight Team is requesting the use of one fixed camera pole on which to mount the
overview video camera. This camera will record footage of all experimental activities during the
microgravity flight. The camera pole will need to be placed at a position where the Sony DCR-HC26
mini DV Digital Handycam can oversee the entire structure, experiment, and flyers. No other cameras
will be used, and no other camera poles are needed.
13.4 Product Format and Quantities of Imagery
The Sony DCR-HC26 mini DV Digital Handycam is the only camera that will used with this
experiment during flight testing and will be mounted to the fixed camera pole requested above. This
camera will record footage on 60-minute mini discs with a frame rate of 30 frames per second and a
quality of 0.680 megapixels. The camera’s mini disc will be replaced with an unused disc during the
turnaround period on each flight day. The camera footage will not be synchronized with any other data.
59
14 Aircraft Loading
The following sections outline requirements needed in order to successfully load the test bed and
prototypes onto the aircraft.
14.1 Ground Equipment
A powered lift will be required to load the experiment onto the aircraft.
14.2 Hardware Manipulation Strategy
In accordance with NASA requirements, there will be eight handles for the 366.4lb chassis. This
ensures that no handle will exceed 50 lbs for loading. Two handles will be placed in each corner of the
chassis. The handles will be on the four horizontal middle beams of the chassis. These handles will
assist the fliers with lifting the chassis as well as providing locations for fliers to stabilize themselves
during the zero-g flight. All components will be secured within the chassis and will be entirely
enclosed within the chassis, thus no component will infringe on the chassis volume of 59”x28”x24”.
14.3 Weights and Loading The maximum weight of the entire experiment hardware will be no more than 400 lbs. A factor of
safety of two or more has been ensured for all structural parts, see Structural Report for details. The
total base area of the experiment is 9.83, thus loading onto the aircraft floor will not exceed 40.69
pounds per square feet.
15 Ground Support Requirements
15.1 Power
Ground testing will require access to 115V 60Hz power.
15.2 K-bottles
Team ZESTT Reflight will be delivering Please see Section 7 for details on this Nitrogen k-bottle.
15.3 Chemicals
No chemicals are utilized in this experiment, except for the cleaning chemicals isopropanol and
acetone.
15.4 Building Access
60
Access to the high bay area at Ellington Field is requested for this experiment. This is due to the need
to have a controlled environment with as little humidity as possible for pumping down the vacuum
chamber. Additionally, it is possible that the pumping system may need to be run overnight.
15.5 Tool Requirements
Please see Section 12.
16 Hazardous Materials No corrosive, toxic, or explosive chemicals will be used with this experiment. This experiment will
make use of isopropanol and acetone on the ground only for cleaning purposes, but these chemicals are
not hazardous under normal circumstances. MSDS are provided for these chemicals in Appendix C.
17 Material Safety Data Sheets Please see Appendix C to I for all material safety data sheets. These include MSDS for isopropanol,
acetone, 5 micron particles, compressed nitrogen gas, room temperature vulcanizing (RTV) silicone,
and silver conductive epoxy.
18 Experiment Procedures Documentation
The following sections describe the procedures associated with this experiment and each step of the
microgravity testing program.
18.1 Equipment Shipment to Ellington Field
All of the equipment needed for this equipment, including the chassis and its components, will be
brought to Ellington Field with the team. The team will travel to Houston in vans from Ann Arbor, MI
with the equipment packed and stowed in the back, thus the equipment will not require shipment.
18.2 Ground Operations
The following sections describe the procedures associated with this experiment.
18.3 Loading/Stowing
The following sections describe the procedures associated with this experiment.
18.4 Pre-Flight
During the time before flight, the vacuum chamber will always be purged with nitrogen gas to keep
61
moisture from accumulating inside, which would to additional out gassing. Two days before the first
flight day, the vacuum chamber will begin to be pumped down for the flight. The pumps will be run
overnight if access to high bay is granted, and if not, at the end of each day, the gate valve will be
lowered to seal the chamber from the vacuum pumps. The vacuum chamber will be loaded and fully
pumped down before loading onto the plane the day before flight. Once loaded onto the plane, till the
end of that day, pumping will continue onboard the airplane, but the gate valve will be initiated when
the pumps are disengaged for the night. The morning of flight, the pumps will be reactivated for as
long as possible. Right before flight, the following items will be removed from the plane: piston pump,
turbo controller, heat strip’s power supply, and pump connecting hose. The experiment will then be
ready for flight.
18.5 Take-off/Landing
All loose items will be stored in a duffle bag, which is able to fit in the supplied 1‘x2‘x2’ area or stored
in over head bins. These loose items include: secondary outreach materials, over head camera, two
mini disks for camera, and a clip board with an attached pen. All other equipment will be bolted to the
aircraft or secured to the chassis using straps.
18.6 In Flight
Each part of the microgravity flight required a different set of procedures to ensure the experiment can
be smoothly run throughout.
18.7 Prior to First Parabola
During the first level period, right before the first parabola, the following tasks will be executed:
1. Attach overview camera to the fixed pole, plug it into its power source, load with a fresh mini
disk, activate, and properly position it to view all experimental activities.
2. Perform a check to ensure all components on the chassis are plugged in and turn on the master
kill switch.
3. Turn on the HVPS, laptop, DC power supply, piezo driver, gauge controller, and DAQ.
4. Open MatLab file
5. Flyers position themselves for the start of parabolas
18.8 2-G Period
After each microgravity period:
1. Record the passing of a parabola on the clipboard
2. Flip switch on piezo box
3. Ensure correct MatLab file is still running
18.9 Reduced Gravity Period
During the microgravity period:
1. One flight crew member will monitor the inside of the vacuum chamber for arcs
62
2. One flight crew member will monitor MATLAB
3. One flight crew member will monitor the instruments to ensure proper function
4. Entering into the 2g period will cause MATLAB to stop data collection
18.10 Turnarounds
During the turnaround period:
1. Replace mini disc in overview camera
2. Ensure MATLAB is storing data properly
3. Mitigate any issues that may have arisen during the flight thus far
18.11 Emergency Procedures, Precautions, and Contingencies
The following emergencies may occur:
1. Arcing on the chassis: kill the electricity using the master kill switch immediately
2. MatLab failure: restart computer and MatLab
3. Ill flyer: only one flyer is needed to run the experiment at any time
4. Thruster prototype failure: use other prototype for remaining parabolas
5. Fire: use fire extinguishers and call for NASA crew
6. Loss of vacuum pressure: continue to test in atmosphere
18.12 Post Flight
After the first flight day:
1. Turn off components (not master kill switch)
2. Discharge high voltage
3. Bring piston pump, turbo controller, AC power supply, and pump hose back on board, plug in,
and engage pumps and heat strip to pump back down for flight day two
4. At the end of the day, stop pumps and engage gate valve
5. Retrieve mini disc from camera and other loose items taken on board
6. Insert new mini disc into camera to prepare for flight day two
7. Debrief second flight crew group on problems encountered and changes that need to be made
8. Save data from flight onto backup memory device and clear laptop’s memory
9. Review flight footage to see how testing progressed and notice any other problems that can be
solved for second flight day
10. Overview data taken thus far and see if any problems occurred
18.13 Off-Loading
To unload the chassis structure from the aircraft, a powered lift will be needed. No special
requirements are present for off-loading the experiment. Once off the plane, the chassis will be loaded
into a van to take back to the University of Michigan.
63
18.14 Emergency/Contingencies
Please see Section 18.11 for emergency procedures.
64
References
1 Liu, T., Wagner, G., Gallimore, A., Gilchrist, B., Peterson, P., “Mapping the Feasible Design
Space of the Nanoparticle Field Extration Thruster,” IEPC-2009-004, 31st International Electric
Propulsion Conference, Ann Arbor, MI, 20-24 Sept. 2009.
2 Musinski, L., Liu, T., Gilchrist, B., and Gallimore, A., “Electrostatic Charging of Micro- and
Nano-Particles for Use with Highly Energetic Applications,” Journal of Electrostatics, 4
November 20080, pp. 1-8
3 Liu, T., Musinski, L., Patel, P., Gallimore, A., Gilchrist, B., and Keidar, M., “Nanoparticle
Electric Propulsion for Space Exploration,” Space Technology and Applications International
Forum – STAIF 2007, edited by M. S. El-Genk, American Institue of Physics, Albuquerque,
NM, 2007, pp. 787-94
4 Gamero-Castano, M., “Induction charge detector with multiple sensing stages,” Review of
Scientific Instruments 78, 043301, 11 Apr. 2007.
65
Appendix A: Exceptions/Deviations/Waivers
A 100 lb mass waiver was requested and granted by the Reduced Gravity Office for this experiment.
Please see below for the email transcript granting this mass waiver.
-------- Original Message --------
Subject: RE: Requested Mass Waiver for ZESTT Reflight
Date: Thu, 15 Apr 2010 16:13:21 -0500
From: "Del Rosso, Dominic L. (JSC-CC411)" <[email protected]>
To: Duncan L Miller <[email protected]>, "Goforth, Douglas W. (JSC-AD421)"
Duncan,
If I understand correctly you would like to have an upper limit of #400 for
your experiment, within the same volume envelope. This should not be a
problem as long as you provide lifting and handling provisions as defined
(i.e. no more than #50 per person lift etc.).
Please include this email in your TEDP when submitted.
Thanks
Dom
-----Original Message-----
From: Duncan L Miller [mailto:[email protected]]
Sent: Thursday, April 15, 2010 3:16 PM
To: Goforth, Douglas W. (JSC-AD421)
Cc: Aquilina, Rose M. (JSC-CC)[REDE CRITIQUE NSS JV]; Del Rosso, Dominic L.
(JSC-CC411); Lee, Terry A. (JSC-CC411); Krolczyk, Kevin D. (JSC-CC)[CSC
APPLIED TECHNOLOGIES LLC]
Subject: RE: Requested Mass Waiver for ZESTT Reflight
Douglas~
Thanks for the quick response! Of course. I understand there's a lot on
your plate. I would like to stress though that we won't be able to lay out
a final chassis model and experimental setup without confirmation of a mass
waiver.
Regards,
Duncan
On Thu, 15 Apr 2010 15:04:17 -0500, "Goforth, Douglas W. (JSC-AD421)"
<[email protected]> wrote:
Duncan -
66
We are finishing up a RG flight week today and tomorrow. Would it be
okay if Dom or Terry contacted you on Tuesday or Wednesday of next week?
Douglas Goforth
________________________________________
From: Aquilina, Rose M. (JSC-CC)[REDE CRITIQUE NSS JV]
Sent: Thursday, April 15, 2010 2:49 PM
To: Del Rosso, Dominic L. (JSC-CC411); Lee, Terry A. (JSC-CC411);
Goforth, Douglas W. (JSC-AD421); Krolczyk, Kevin D. (JSC-CC)[CSC APPLIED
TECHNOLOGIES LLC]
Subject: FW: Requested Mass Waiver for ZESTT Reflight
Would someone please contact this student??!!
-----Original Message-----
From: Duncan L Miller [mailto:[email protected]]
Sent: Thursday, April 15, 2010 2:45 PM
To: Aquilina, Rose M. (JSC-CC)[REDE CRITIQUE NSS JV]
Subject: Requested Mass Waiver for ZESTT Reflight
To Whom It May Concern:
At this time, we formally request a 100 lb mass waiver for the Zero-g
ElectroStatic Thruster Testbed Reflight at the University of Michigan. We
have been closely tracking our expected mass and have found that it would
be very difficult to reach the 300lb limit without compromising our
experiment. Our chassis structure was safely flown in June 2009 at 340
lbs
and this year's additional component weight has amounted to a total of
390.4 lbs with contingency.
To account for the added mass, we have lengthened the aircraft mounting
brackets and analyzed the chassis structure under the appropriate
acceleration fields to verify our chassis does indeed comply with NASA
requirements. Both our FEA and hand calculations have shown factors of
safety comfortably above 2.
We have attached CAD models of our chassis design, a mass budget, FEA
solved models in ANSYS and a few sample hand calculations. A more
comprehensive structural report will be included with our TEDP in May.
Thank you,
ZESTT Structures Team