Experience with PADEP, CEM Phase I Approval Under Rev 7 ARIPPA Technical Symposium July 27, 2005 Jim...

28
Experience with PADEP, CEM Phase Experience with PADEP, CEM Phase I Approval Under Rev 7 I Approval Under Rev 7 ARIPPA Technical Symposium ARIPPA Technical Symposium July 27, 2005 July 27, 2005 Jim Carroll & Ron Baker Jim Carroll & Ron Baker EcoChem Analytics EcoChem Analytics

Transcript of Experience with PADEP, CEM Phase I Approval Under Rev 7 ARIPPA Technical Symposium July 27, 2005 Jim...

Experience with PADEP, CEM Experience with PADEP, CEM

Phase I Approval Under Rev 7Phase I Approval Under Rev 7

ARIPPA Technical SymposiumARIPPA Technical Symposium

July 27, 2005July 27, 2005

Jim Carroll & Ron BakerJim Carroll & Ron Baker

EcoChem AnalyticsEcoChem Analytics

2

2

Presentation OverviewPresentation Overview

• Project Scope• Hardware Description• Project Schedule• Application Experience• Interaction with the

Department• Recommendations• CEM Supplier

Perspective

3

3

CEM Project ScopeCEM Project Scope

• Install new stand alone CEMS enclosure

• Install two (2) new EcoChem MC3 multi-component analyzer packages

– NOx, SO2, CO, CO2, O2

• Two (2) new sample handling systems– Probes– Sample lines– Sample pumps

4

4

CEM Project Scope ( Cont’d)CEM Project Scope ( Cont’d)

• New DAS by ESC for PA STEMS (Part 60) and NOx Budget (Part 75) reporting

• Maintain use of existing stack flow monitors in new system

• Maintain use of existing Opacity Monitor (near term)

5

5

New EnclosureNew Enclosure

6

6

Heated Probe AssemblyHeated Probe Assembly

7

7

Heated Sample LineHeated Sample Line

Non-heated tubes (PFA-PTFE)

1. Calibration Gas (from calibration cylinder and solenoid valves to probe)

2. Isolation Air (isolation of probe from flue gas during calibration & temperature failures)

3. Blowback air (used for purging probe)

Heated tubes (185°C PFA)1. Sample gas from probe to

analyzer2. Spare

Heating element

Insulation

Power for probe

Power for sample line heating and temperature sensors

8

8

Heated PumpHeated Pump

9

9

CEM CabinetsCEM Cabinets

10

10

CEM Cabinet InteriorCEM Cabinet Interior

11

11

MC3 ConfigurationMC3 Configuration

Gas Range Interval

CO 0-200 PPM, 0-3000 PPM

SO2 0-150 PPM, 0 - 400 PPM

NOx 0-160 PPM

O2 0-25%

CO2 0-20%

H2O 0-30%

12

12

Touch Screen DisplayTouch Screen Display

13

13

Real-Time Strip ChartReal-Time Strip Chart

14

14

Project ScheduleProject Schedule

• Prelim Meeting - August 2003• New CEM Spec Issued –

August 2004• EcoChem Selected – Sept 2004• PO issued/Order placed – Sept

2004• Teleconference with PADEP –

Sept 2004• Phase I Submittal – Oct 2004

– Included a listing of project milestones (testing)

15

15

Project Schedule (Cont’d)Project Schedule (Cont’d)

• Phase II Submittal – Nov 2004• FAT Testing – Jan 2005• Installation/Commissioning –

Feb 2005• Phase I and II Status Request –

Feb 22• PADEP Response – Feb 24,

2005• Proposed Certification –

March 16, 2005• New Schedule Proposed –

March 17, 2005

16

16

Project Schedule (Cont’d)Project Schedule (Cont’d)

• Performance Testing – April 2005• RATA Testing – April 13 & 14, 2005• Phase I Approval – April 18, 2005• Submittal of Performance Testing

Data – May 2005• Submittal of Part 75 Certification

EDRs – May 2005• EDR Certification Data – App’d in

10 days • Phase III Acknowledgement Letter

– June 2, 2005 (Response by July 2, 2005)

• Certification is currently pending

17

17

Application ExperienceApplication Experience

• Opted to utilize the electronic Phase I forms

• Theory: Electronic submittal may expedite the approval process (Not!)

• Completed forms encompassed 41 pages

• Forms were cumbersome to work with

• Some requested data was not well defined

• Requested more fluff than stuff

18

18

Application Experience Application Experience (Cont’d)(Cont’d)

• Requested data aids in fulfilling the Department’s CEMS database

• ID codes, Result Codes, Source Codes, Analyzer Codes & CEMS Codes are meaningless to the preparer

• It’s difficult to keep them straight!

19

19

Application Experience Application Experience (Cont’d)(Cont’d)

• Regurgitate many of the standards in the CSMM

• Defining the Lowest Monitored Standard (LMS)

• LMES now replaces the old “Span”

20

20

Interaction with DepartmentInteraction with Department

• Phase I Pre-submittal teleconference is beneficial

• Also beneficial to speak with Bob Vollaro of EPA to review Part 75 issues

• There was little or no communication unless we initiated it

• Phone call follow-ups were initiated starting in December

21

21

Interaction with Department Interaction with Department (Cont’d)(Cont’d)

• Exchanged LMES calculations via FAX in January

• They opted not to visit the plant during installation or testing

• Communication via letter stimulated the best response

• The Department is still working to understand all the nuances of Rev 7.

• Their plates are FULL.

22

22

RecommendationsRecommendations

• Schedule an informal pre-submittal conference

• Build a lot of time into your schedule– 1 year from Phase I submittal to

Certification• Submit your project schedule with

the Phase I• Understand & be clear about your

LMES calculations in your Phase I

23

23

Recommendations (Cont’d)Recommendations (Cont’d)

• Keep your project on the radar screen after the Phase I is submitted

• Submit your Phase II early• Correspond with the Dept in

writing about project milestones• Make sure the Dept understands

your Part 75 issues

24

24

CEM Supplier Perspective on CEM Supplier Perspective on PADEP Rev. 7 PADEP Rev. 7

• Awaiting Responses Caused Project Delays

• Phase I Submittal Approval took >4 months

• Rev. 7 Phase I Electronic Version confusing

• Reconciling NOx Budget, Part 60 and PADEP overlapping requirements inefficient

• PADEP Going Thru Transition

25

25

Benefits of More Current CEMBenefits of More Current CEM Beside Simply Meeting Beside Simply Meeting

RegulationsRegulations• Hot-wet system provides

moisture concentrations – assists with auditing tube leaks

• New sample system and automatic audits reduces manual oversight

• Enhanced remote troubleshooting reduces frequency of lengthy E&I staff call-outs

• Convenient format and data access useful management tool

• Avoid total obsolescence

26

26

Operator Interface and Operator Interface and Remote System AccessRemote System Access

• Presents data in larger color screen

• Most functions 1-2 touch screen taps

• Provides meaningful system history to do troubleshooting right at the CEM location (fewer trips back and forth to control room or office)

• Can control the system remotely

Excel PC Anywhere

27

27

A Contrast in Case HistoriesA Contrast in Case Histories

• Removed old system and installed new CEM in three days – during scheduled outage

• No overlap with original CEM• RATA test within 10 days• No “Phase I” submittal

– letter notification• No NOx Budget Issues

Waste Coal Plant – Utah

28

28

EcoChem’s Suggestions EcoChem’s Suggestions for a “Win-Win” CEM Upgradefor a “Win-Win” CEM Upgrade

• Build in sufficient scheduling contingency - allow 9-12+ months depending upon scope

• Allow appropriate overlap with existing CEM – You usually don’t have a choice!

• Don’t forget training and spare parts inventory

• Use experienced CEM integrator & DAS vendor

• Pray for Rev 8 to be more efficient