Annex F - Executive Summary of Final Report of the CEIA Study
EXECUTIVE SUMMARY REPORT OF CEIA STUDY FOR GHOGRA … · 2013-04-18 · 1 EXECUTIVE SUMMARY REPORT...
Transcript of EXECUTIVE SUMMARY REPORT OF CEIA STUDY FOR GHOGRA … · 2013-04-18 · 1 EXECUTIVE SUMMARY REPORT...
1
EXECUTIVE SUMMARY REPORT OF CEIA STUDY FOR GHOGRA MEDIUM
IRRIGATION PROJECT
1. GENERAL
The Water Resources Department, state government of Madhya Pradesh
proposes to develop Ghogra Medium Irrigation project. The Gogra Medium
Tank Project is situated near Village Gogra and Ghutwani in Tehsil
Nasrullaganj of District Sehore in Madhya Pradesh. The project site can be
approached by traveling for a distance of 22 km on Narsullaganj Indore road
and than 18 km on Gopalpur Piplani road. The nearest railway station to
project site is Budhni which is located about 55 km from Narsullaganj. The
project shall irrigate an area of 5,300 ha. The project location map is
enclosed as Figure-1.
2. PROJECT DESCRIPTION
The dam will comprise of an ungated waste weir 230 m long on left bank.
The earthen dam will be 2470 m long with a maximum height of 20.23 m in
deepest gorge portion. It is proposed to irrigate an area of about 1350 ha in
Kharif season and 3950 ha of area in Rabi season. The length of main canal
is 5 km. The index map of the project showing the dam and canal network is
enclosed as Figure-2.
The tentative total land required for various project components is of about
534.67 ha. The details are given in Table 1.
Table-1:Details of land to be acquired for the project
Project Name Revenue
Land (ha)
Private
Land (ha)
Forest
land (ha)
Total
(ha)
Dam & Reservoir 184.17 194.00 18.500 396.67
Canal Network - 138 - 138.00
Colony & Approach Road
and other components
Nil Nil Nil -
Total 184.17 332.00 18.500 534.67
3. STUDY AREA
The study area covered as a part of the EIA study is as below (Refer
Figure-3).
• Submergence area
• Area to be acquired for various project appurtenances
2
• Area within 10 km of various project appurtenances including i.e.
canal network, etc. • Gross Command Area
• Catchment Area intercepted at the dam site
4. ENVIRONMENTAL BASELINE STATUS
The baseline status for the above referred categories has been described in
the following sections.
4.1 PHYSCIO-CHEMICAL ASPECTS
4.1.1 Meteorology
The project area of the proposed Ghogra Medium Irrigation project
experiences semi-arid climate characterized by hot summer, pleasant cold
winter and general dryness throughout the years, except during monsoon
season. The year may be divided into four seasons. The summer season lasts
from March to about middle of June, followed by the south-west monsoon
season from mid-June to the end of September. The months of October and
November constitute the post-monsoon or transition period. The winter
season is observed from December to February.
4.1.2 Soils
The pH in soils of the command area lies within the neutral range, i.e. 7.2 to
7.8. The level of Electrical Conductivity indicates the low salt concentration in
the soils. The concentration of Available Potassium, Available Nitrogen and
Available Phosphorus ranged from 289 to 590 kg/ha, 312 to 418 kg/ha, 18 to
35 kg/ha. The concentration of various nutrients indicate moderate to high
productivity. The organic carbon in various samples indicates low to
moderate productivity. The bulk density ranged from 1.12 to 1.30 g/cc. The
porosity ranged from 37 to 52%. A negative correlation between bulk density
and porosity was observed.
4.1.3 Surface Water Quality
The pH level ranged from 6.9 to 7.2 in various seasons. The pH level
indicates that water is in neutral range. The total hardness in various water
samples ranged from 120 to 125 mg/l, 91 to 97 mg/l and 113 to 117 mg/l in
pre-monsoon, monsoon and winter seasons respectively. The total hardness
3
level in surface water samples was well below the permissible limit of 200
mg/l, specified for meeting drinking water requirement. The TDS level ranged
from 274 to 278 mg/l, 250 to 254 mg/l and 271 to 278 mg/l in pre-monsoon,
monsoon and winter seasons respectively. The TDS levels were well below
the permissible limit of 500 mg/l. The EC levels were well below the
permissible limit of 2250 µS/cm specified for irrigation water requirements as
pr IS:2296. This indicates the suitability of water for meeting irrigation and
drinking water requirements.
The BOD and COD values are well within the permissible limits, which
indicates the absence of organic pollution loading. The concentration of
various heavy metals was below the detectable limits, indicating the
suitability of water for meeting domestic requirements. The concentration of
cyanides and phenolic compounds was also below the detectable limits.
The concentration of various heavy metals was observed to be below
detectable limit in various seasons.
4.1.4 Ground Water Quality
pH level in various groundwater samples in various seasons was observed to
be with neutral range (6.5- 8.5), which is within the permissible limit
specified for meeting drinking water requirements.
Chlorides occur in all natural waters in widely varying concentrations,
chlorides is available in natural water, mainly through solvent power of
water, which dissolves chlorides from top soil and deeper formations.
Sulphates ion is one of the major anions occurring in natural water. It is an
important parameter because of its cathartic affect, when it is present in
higher concentration. The concentration chlorides, sulphates, Nitrates and
other anions were found to be within the permissible limits. Likewise,
concentration of various cations like Calcium, magnesium, etc. were found to
be within the permissible limits. In some of the samples, the values of
cations and anions were close to permissible limit.
The TDS level ranged from 326 to 736 mg/l, 291 to 670 mg/l and 320 to 728
mg/l in pre-monsoon, monsoon and winter seasons respectively. The TDS
levels were well above the permissible and cause of rejection limits of 500
4
mg/l and 1500 mg/l respectively. This is also reflected by the fact that the
concentration of various cations and anions as well.
The BOD and COD values are well within the permissible limits, which
indicates the absence of organic pollution loading. The concentration of
various heavy metals was observed to be below detectable limit in various
seasons.
4.1.5 Ambient Air Quality
As a part of the field studies, various ambient air quality locations were
monitored. Based on the findings of the ambient air quality survey,
conducted for various seasons, it can be concluded that the ambient air
quality is quite good in the area.
4.1.6 Noise Environment
The day time equivalent noise level at various sampling stations were
observed to be well within permissible limits specified for residential area.
4.1.7 Land use pattern
The land use pattern of the submergence and command areas is outlined in
Tables 2 and 3 respectively.
Table-2 : Landuse pattern of the submergence area of Ghogra
Medium Irrigation project
Type of land Area
(ha)
Percentage of
Submergence area
Vegetation 25.78 6.50
Grasslands 63.38 15.98
Barren area 45.12 11.38
Agricultural land 188.57 47.57
River/ Water bodies 0.21 0.05
Scrubs 70.38 17.74
Built-up area/Settlements 3.22 0.81
Total 396.67 100.00 Note : Figure in parenthesis indicate percentage.
5
Table-3 : Landuse pattern of the command area of Ghogra Medium
project project
Type of land Area
(ha)
Percentage of command
area
Vegetation 2025 21.91
Grasslands 1014 10.98
Barren land 1143 12.37
Agricultural land 4948 53.55
River/ Water bodies 18 0.19
Exposed Rock 62 0.67
Built-up area 30 0.32
Total 9240 100.0 Note : Figure in parenthesis indicate percentage.
The major landuse category in the submergence area of Ghogra medium
project is agriculture land, as it accounts for about 47.54% of the total area.
The area under vegetation is only 6.5% of the command area. Barren land
and Built-up land/settlements account for about 11.38% and 0.81%,
respectively of the total command area. The area under water bodies is only
0.05% of the command area of Ghogra Medium Irrigation Project
The major landuse category in the command area of Ghogra Medium
irrigation project is agriculture land, as it accounts for about 53.55% of the
gross command area. The area under vegetation is about 22% of the gross
command area. Barren land and Built-up land/settlements account for about
12.37% and 0.32%, respectively of the gross command area. The area
under water bodies is only 0.19% of the gross command area of Ghogra
Medium Irrigation Project.
4.2 ECOLOGICAL ASPECTS
4.2.1 Vegetation
As per Champion and Seth (1968) Classification, the following forest types
were encountered in the project area:
I. Group 5. Dry tropical forests
5AC1b. Southern dry teak deciduous forests
Southern dry teak deciduous forests (5AC1b): Tectona grandis is the
most characteristic species of this type of forest type as recorded from the
project site. The commonly observed tree species are Tectona grandis, Butea
6
monosperm, Lagerstroemia parviflora, Terminellia tomentosa, Adina
cordifolia, Anogeissus latifolia etc. There is usually a thin grass growth which
may appear fairly during the monsoon season, but more or less, soil is
barren throughout the year. Climbers are few and showing xerophytic
characters of adaptation. No Gymnosperm species recorded so far in natural
habitat from the project area. The herbaceous floral species includes
Acalypha indica, Bacopa monnieri, Celosia argentea, Alternanthera sessilis,
Xanthium strumarium, Themeda quadrivalvis, Argemone mexicana, Tribulus
terrestris, Sphaeranthus indicus, Tridex procumbens, and other species.
Some invasive species were recorded from the project area, viz. Ipomea
carnae, Parthenium hysterophorus, and Cassia tora are recorded in large
number along the road side and in crop land areas.
Floristics
During the floristic survey in the Pre-Monsoon Season, Monsoon Season and
Winter Season, maximum number of plant species recorded from the project
area were from the Monsoon Season. The details are given in Table-4.
Table-4: Different life forms of the plant species recorded in various seasons
Component Number of Species
Pre-Monsoon Monsoon Winter
Trees 23 23 23
Shrubs 19 19 19
Herbs 17 58 29
Climbers 3 4 2
Bamboos 2 2 2
Parasite 1 2 1
Total 65 108 76
4.2.2 Fauna
The project command is virtually devoid of any forests, with high degree of
human interferences. No major wildlife is observed in the area. The
commonly observed faunal species in the area are common Jungle cat,
Jackal,Indian Barking Deer, Nilgai, rats, squirrel, etc.
Amongst the birds commonly observed ,species are Little Egret, Little
Cormorant, Common Teal, Cotton Teal, Black Partridge, Common Quail, Red
Jungle Fowl, Common Pea Fowl, Common Crane, etc.
7
4.2.3 Fisheries
Some important fishes genera which have been identified are Mrigal Cirrhinus
mrigala), Catla (Catala catla), Dudhiya (Labeo dero), Kharpata (Puntius
sophore), Tengar (Sperata oar), Gagra (Rita rita) and Bam (Mastacembelus
armatus).
4.3 SOCIO-ECONOMIC ASPECTS
4.3.1 Demographic profile
The total population of the command area as about 6640. The male and
female population is 3480 and 3160. The number of females per 1000 males
is 908. The percentage of SC and ST Population is 14.7% and 29.8%
respectively. The number of females per 1000 males is 940. The percentage
of SC and ST Population is 14.7% and 29.8% respectively. The overall
literacy rate in the command area tehsils is 52.2 It is observed that total
main workers in the command area are 1920 accounting for about 28.8% of
the total population. Marginal workers account for about 14.3% of the total
population. The remaining (57%) are the dependent population. The
dominant occupation in the area is agriculture.
4.3.2 Agriculture
The total cropped area in command area is 4712 ha. The major agriculture
crops grown in the command area are oil seeds, which is grown over about
47% of the total cropped area. Cereals and pulses are grown over 27.5% and
21.6% of the total cropped area. The cropping pattern is a clear indicator of
the lack of water availability for irrigation in the command area
5. PREDICTION OF IMPACTS
The impacts on various aspects of environment are briefly described in the
following sections.
5.1 IMPACTS ON LAND ENVIRONMENT
Acquisition of land
The land required for various project components is of about 534.67 ha.
About 184.17 ha of Revenue land and 332.00 ha of private land is to be
acquired. About 18.5 ha of forest land is to be acquired for the Based on the
8
ownership status of the land to be acquired, appropriate compensatory
measures have been formulated.
Change in land use pattern
The GCA and CCA of the project are 5250 ha and 4450 ha respectively. The
total area to be irrigated is 5300 ha, which includes 1350 ha in Kharif and
3950 ha in Rabi. This would increase the agriculture production in the
command area and is a significant positive impact. The details of cropped
area during pre-project and project operation phases are given in Table-5.
Table-5: Cropped area during pre-project and project operation
phases
Name of the crop Area under cultivation (ha)
Pre-project Post-project
Kharif
Soyabean 1350 1350
Sub-total(A) 1350 1350
Rabi
Hybrid Wheat - 700
Ordinary Wheat 1900 1200
Gram 2050 2050
Sub-total( B) 3950 3950
Total (A+B) 5300 5300
5.2 IMPACTS ON WATER RESOURCES AND QUALITY
b) Operation Phase
Impacts on downstream users
The total water requirement for irrigation of command of Ghogra Medium
Tank Irrigation project is 13.01 Mm3. The break-up of water availability and
various uses is given in Table-6.
Table-6: Water availability for 75% dependable year
Month Yield (Mm3) June 1.30 July 4.59 August 8.24 September 3.50 October 0.26 September 0.00 October 0.00 November 0.00 December 0.00 January 0.00
9
Month Yield (Mm3) February 0.00 March 0.00 April 0.00 May 0.00 Total 17.89
The total water requirements of the project is 14.10 Mm3. The water
availability in 75% dependable year is 17.89 Mm3. Thus, sufficient quantity of
water is aviable for meeting requirements of Environmental Flows
Impacts on waterlogging and soil salinity
The total water requirement during Kharif and Rabi seasons is 13.01 Mm3
over an irrigated command of 5300 ha. This works out to an average water
depth of 245 mm. The irrigated water not being utilized 5.99 Mm3. For a
gross command of 5300 ha, the average depth of water infiltrating into the
groundwater works out to 113 mm. The quantum of water not being utilized
is quite small and is not expected to cause any significant problem of
waterlogging.
Changes in water quality due to increased use of fertilizers
With the introduction of irrigation, use of fertilizers is likely to increase, to
maintain the increased levels of production. The drainage system (natural or
man-made) is likely to contain much higher level of nutrients. The climatic
conditions in the project area too is suitable for the proliferation of
eutrophication in the project area. Thus, in the project operation phase, there
will be increased probability of eutrophication in the water bodies receiving
agricultural runoff. As a part of Environmental Management Plan, appropriate
control measures have been recommended.
5.3 IMPACTS ON TERRESTRIAL ECOLOGY
Impacts on vegetal cover
The total forest area to be acquired in the project is 18.5 ha. As a part of
field studies, ecological survey was conducted at two locations in the dam
and reservoir area, which is spread over an area of 396.67 ha. The details of
total species at various sampling sites in submergence area are given in
Table-7.
10
Table-7: Details of floral species at various sampling sites in
submergence area
Site Dominant species Tree
density
(no/ha) Trees Shrubs Herbs
Dam Site Butea monosperma,
Lagerstroemia
parviflora and Tectona
grandis
Ocimum tenuiflorum,
Achyranthes
aspera, Pogostemon
benghalense
Xanthium strumarium,
Ageratum
conyzoides, Cassia tora
Alternanthera
sessilis, Evolvulus
alsinoides
10
Submergence
Area
Tectona
grandis
Achyranthes
aspera, Pogostemon
benghalense,
Lantana camara
Cassia tora,
Evolvulus alsinoides
Xanthium
strumarium
12
It can be seen from Table-7, that Tectona grandis, Butea monosperma were
the dominant tree species. Amongst shrubs, Ocimum tenuiflorum,
Achyranthes aspera, Pogostemon benghalense, Achyranthes aspera, Lantana
camara were the dominant species. The dominant herbaceous species in the
submergence area were Xanthium strumarium, Ageratum conyzoides, Cassia
tora Alternanthera sessilis, Evolvulus alsinoides. The tree density ranged
from 10 to 12 per ha, which is quite low. Normally in a dense forest, tree
density is of the order of 1000-1200 trees/ha. Thus, land to be acquired for
reservoir submergence, tree density is low. No Rare, Endangered or
Threatened species are reported in the project area.
No Rare, Endangered or Threatened species are reported in the project area.
The introduction of irrigation in the area will increase the agriculture
production of the area, leading to the increased availability of fodder as a
result of increased agricultural by products and residues. The increased level
of fodder availability would reduce the presence on existing pasture and
vegetal cover, which is a significant positive impact.
11
Impacts on wildlife
The area to be brought under irrigation within the command area shall be
devoid of forests. The project area is interspersed with settlements and
agricultural land. In such settings large scale faunal population is not
observed. Thus, no significant impact on wildlife is anticipated due to the
project.
The increase in vegetal cover would improve the organic content of the soils.
As a result microbial activity would improve, leading to increase in the type
and number of micro-organisms observed in the soils of the command area.
This in the long run is expected to improve the soil fertility.
5.4 IMPACTS ON AQUATIC ECOLOGY
Impacts on fisheries potential
The proposed project would increase the water availability in the command
area. As a result, there will be increase in potential for tank and pond
fisheries. Currently, within the command area, tank and pond fisheries is in
vogue. With the increased availability of water the tank and fisheries
potential would improve. The average fish yield is of the order of 1 to 2
tonnes/ha/yr in fishing ponds. Thus, with introduction of extensive culture,
the fish production is expected to increase, which is a significant positive
impact.
5.5 IMPACTS ON NOISE ENVIRONMENT
a) Construction Phase
Noise due to construction equipment
In water resource projects, the impacts on ambient noise levels are expected
due to operation of construction equipment. Based on experience in similar
projects, there could be marginal impacts on the population residing in
proximity to the canal alignment during construction phase as a result of
various activities. However, based on past experience in similar projects, the
impact however, is not expected to be significant.
12
5.6 IMPACTS ON AIR QUALITY
a) Construction Phase
Pollution due to fuel combustion in various equipment
The operation of various construction equipment requires combustion of fuel.
Normally, diesel is used in such equipment. The major pollutant which gets
emitted as a result of diesel combustion is SO2. The SPM emissions are
minimal due to low ash content in diesel. The short-term increase in SO2,
even assuming that all the equipment are operating at a common point, is
quite low, i.e. of the order of less than 1µg/m3. Hence, no major impact is
anticipated on this account.
Fugitive Emissions from various sources
During construction phase, there will be increased vehicular movement. Lot
of construction material like sand, fine aggregate is stored at various sites,
during the project construction phase. Normally, due to blowing of winds,
especially when the environment is dry, some of the stored material can get
entrained in the atmosphere. However, such impacts are visible only in and
around the storage sites. The impacts on this account are generally,
insignificant in nature.
5.7 INCREASED INCIDENCE OF WATER-RELATED DISEASES
Increased incidence of water-related diseases
The association between irrigation development and the incidence of water
related diseases such as malaria, etc is well established. The available data
clearly indicates that the major water related diseases prevalent in the
project area are malaria and gastroenteritis. The preferred environmental
setting for vectors is fresh water open to sunshine or moderate shade. The
habitats for larvae growth are permanent or semi-permanent standing fresh
water such as small ponds, pools, standing agricultural water, permanent or
semi-permanent fresh water such as open stretches or canals. Thus, the
project may create favorable conditions for breeding of new pathogens or
vectors such as mosquitoes, etc. Most of the water-borne diseases can
largely be prevented by adequate hygiene. The experience of various project
confirms the above mentioned hypothesis. In the project area, a sudden
13
spurt in the incidence of malaria is expected, if adequate control measures
are not taken up.
Impacts due to Improvement in availability of water
Improvement in availability of water for various uses, increased agricultural
production, availability of diversified food, strengthening of educational and
health facilities significantly improves public health in the project area. On
the other hand, water resources development also has negative impacts,
since, it could increase the habitat of certain vectors like mosquitoes. Thus,
poorly planned and managed water resources projects could increase the
prevalence of vector-borne diseases like malaria and filariasis.
5.8 IMPACTS DUE TO COMMAND AREA DEVELOPMENT
Increased income Level
The net profit from agriculture production would increase from Rs. 4500 per
ha in pre-project phase to Rs. 29000 per ha in project operation phase. Thus,
the project will play a significant role in poverty alleviation in the project
area.
Improvement in livestock
During project operation phase, food grain production will increase from
4240 tonnes per year to 12680 tonnes per year. The increase in agriculture
byproducts would be of the order of 8440 tonnes per year. Assuming even
50% of agriculture by product is usable as fodder, hence, about 4220 tonnes
of additional fodder would be available. This will reduce the pressure on the
existing forests or vegetation of the area, which is a significant positive
impact.
Employment generation
The introduction of irrigation requires a greater amount of labour in fields.
This would improve the employment scenario not only for the local farmers,
but would also increase the demand for agricultural labour. On average,
labour demand in irrigated and unirrigated field is 200 mandays/year/ha and
100 mandays/ha/year. The employment potential in with out -project phase
for a cropped area of 5300 ha has about 0.53 million which will increase to
1.060 million mandays in project operation phase. Thus, with the increase in
14
the irrigation intensity, manpower requirement in the agriculture sector
would increase by 0.53 million man days per year, which is a significant
positive impact.
6. ENVIRONMENTAL MANAGEMENT PLAN
6.1 ENVIRONMENTAL MEASURES DURING CONSTRUCTION PHASE
Facilities in Labour Camps
It is proposed that it should be made mandatory for the contractor involved
in the construction activities to provide adequate facilities for water supply
and sanitation. It is recommended that the contractor provides living units of
30-40 m2 to each of the labour family involved in the construction activities.
The unit should have proper ventilation.
Water supply
Appropriate water supply sources need to be identified. Proper infrastructure
for storage and if required treatment e.g. disinfection or other units, should
also be provided.
Sewage treatment
The labour population is proposed to be situated in existing colonies. One
community toilet needs to be provided for 20 persons. The sewage from the
community toilets shall be treated in a septic tank.
Restoration of construction sites
Normally the construction sites are left unreclaimed, with construction waste
being left without being properly disposed. In the proposed project, it is
proposed to collect the construction waste from various construction sites,
and disposed off at sites identified in consultation with the district
administration. The various construction sites would be properly levelled. The
levelling or reclamation of various construction sites, should be made
mandatory for the contractor, hence, no additional cost has been earmarked
as a part of the cost to be earmarked for implementation of EMP.
6.2 MAINTENANCE OF WATER QUALITY
In the project operation phase, a colony is likely to be set up. It is proposed
to provide sewage treatment plant in the project colony, cost of which shall
be included in the contract for constructing the project colony.
15
6.3 SUSTENANCE & ENHANCEMENT OF FISHERIES POTENTIAL
The commissioning of the proposed Ghogra Medium Irrigation Project will
increase the water availability in the project command area. It is proposed to
stock the reservoir with fingerlings. Adequate infrastructure in terms of
nurseries, rearing ponds, etc. shall be commissioned.
6.4 CONTROL OF WEEDS ON AGRICULTURE LANDS
Measures against weeds comprise mechanical (cultivation and mowing),
cultural or cropping, biological and chemical means. These include:
- hand weeding
- adopting farming practices that change the conditions in such a way as
to enable plants to complete with weeds
- use of weedicides.
6.5 PESTS CONTROL
Integrated pest management strategy should be followed to reduce the use
of pesticides. In this method, a limited number of insecticidal sprays are
undertaken and simultaneously bio-control agents like pheromones, etc. are
used. The pheromones are organic compounds developed specifically for
each type of pest which are commercially synthesized in the laboratories and
sold in the market.
Integrated pest management strategy shall be followed to reduce the use of
pesticides. In this method, a limited number of insecticidal sprays are
undertaken and simultaneously bio-control agents like pheromones, etc. are
used. The pheromones are organic compounds developed specifically for
each type of pest which are commercially synthesized in the laboratories and
sold in the market.
6.6 TRAINING AND EXTENSION COURSES FOR FARMERS
The change from rainfed to irrigated cropping requires extension, training
and demonstration programmes for farmers. Considering these aspects it is
proposed that the project authorities needs to provide adequate training to
farmers.
16
The training shall include the following aspects of environmental protection:
• Prevention of spread of water related diseases; • Safe use of agro-chemicals, and
• Environmental conservation programmes.
6.7 CONTROL OF AIR POLLUTION
The following measures are recommended:
• The contractor will be responsible for maintaining properly functioning
construction equipment to minimize exhaust.
• Construction equipment and vehicles will be turned off when not used
for extended periods of time.
• Unnecessary idling of construction vehicles to be prohibited.
• Effective traffic management to be undertaken to avoid significant
delays in and around the project area.
• Road damage caused by sub-project activities will be promptly
attended to with proper road repair and maintenance work.
• Identification of construction limits (minimal area required for
construction activities).
• When practical, excavated spoils will be removed as the contractor
proceeds along the length of the activity.
• When necessary, stockpiling of excavated material will be covered.
• Excessive soil on paved areas will be sprayed (wet) and/or swept and
unpaved areas will be sprayed and/or mulched.
• Contractors will be required to cover stockpiled soils and trucks hauling
soil, sand, and other loose materials (or require trucks to maintain at
least two feet of freeboard).
• Contractor shall ensure that there is effective traffic management at
site. The number of trucks/vehicles to move at various construction
sites to be fixed.
• Dust sweeping - The construction area and vicinity (access roads, and
working areas) shall be swept with water sweepers on a daily basis or
as necessary to ensure there is no visible dust.
17
6.8 NOISE CONTROL MEASURES
The contractors will be required to maintain properly functioning equipment
and comply with occupational safety and health standards. The construction
equipment will be required to use available noise suppression devices and
properly maintained mufflers.
The effect of high noise levels on the labour population involved in
construction activities is to be considered as likely to be particularly harmful.
To prevent these effects, it has been recommended by international specialist
organisations that the exposure period of affected persons be limited as
specified in Table-8. Alternatively, they should be provided with effective
personal protective measures such as ear muffs or ear plugs to be worn
during periods of exposure.
Table-8 : Maximum Exposure Periods specified by OSHA
Maximum equivalent continuous
noise level dB(A)
Unprotected exposure period per
day for 8 hours per day for 5 days
per week
90 8
95 4
100 2
105 1
110 0.5
115 0.25
120 No exposure permitted at or
above this level
The other measures to control noise could be as follows:
• Equipment and machineries should be maintained regularly to keep
the noise generation • Silencers and mufflers of the individual machineries to be regularly
checked;
• Yearly audiometric survey on workers exposed to high noise levels should be undertaken.
7. CATCHMENT AREA TREATMENT PLAN
Silt Yield Index (SYI) method has been used to prioritize sub-watershed in a
catchment area for treatment. The area under very high and high erosion
categories is to be treated at the project proponent cost. In the catchment of
the proposed Ghogra Medium Irrigation Project, there is no area under very
18
high erosion category. Hence, CAT plan has been suggested for high erosion
category as a part of the present EIA study, the expenses of which have to
be borne by project proponents. The area under high erosion category is
4560 ha. The details are given in Table-9.
Table-9 : Area under different erosion categories
Category Area (ha) Percentage
Medium 4290 48.48
High 4560 51.52
Total 8850 100.00
Following Engineering and Biological measures have been suggested for the
catchment area treatment.
1. Engineering measures
- Nallah Bunding
- Contour Bunding
- Angle iron barbed wire fencing
2. Biological measures
- Development of nurseries
- Plantation/afforestation - Pasture development
- Social forestry
The cost required for catchment area treatment shall be Rs. 29.60 million.
8. RESETTLEMENT AND REHABILITATION PLAN
The provisions of the MPPKKVVA - 1985 and NRRP – 2007 have been taken
into consideration, and the best option has been recommended for
preparation of Resettlement and Rehabilitation Plan for the PAFs.
MEASURES FOR REHABILITATION
The following measures are suggested to be extended as rehabilitation
measures to the PAFs losing land:
• Based on past experiences, it is observed that a land for land may not
be available in the command area. Thus it is suggested that
Rehabilitation grant may be extended in-lieu of land to PAFs losing
land.
• In case of a project involving land acquisition on behalf of a requiring
body, the affected families who have not been provided agricultural
19
land shall be entitled to a rehabilitation grant equivalent to 750 days
minimum agricultural wages or such other higher amount as may be
prescribed by the appropriate Government.
• Fishing rights in the reservoirs shall be given to the affected families, if
such rights were enjoyed by them in the affected area;
• Stamp duty and other fees payable for Registration of the land allotted
to the affected families shall be borne by the requiring body.
• Land allotted to the affected families under this policy shall be free
from all encumbrances.
• Land allotted to the affected families under this policy may be in the
joint names of wife and husband of the affected family.
• In case each khatedar in the affected family is allotment of wasteland
or degraded land in lieu of the acquired land, s/he shall be entitled for
a one-time "financial assistance of not less than Rs. 15,000/ha for land
development.
• A provision of Rs. 10,000 per PAFis being kept for a one-time financial
assistance to each khatedar in the affected family for agricultural
production
• Preference to given to atleast one person per affected family in
providing employment in the project, subject to the availability of
vacancies and suitability of the affected person for the employment.
• A provision of Rs. 500/month for 6 months for one person per PAF
shall be given for training.
• Scholarship @ Rs. 500 per month to atleast 1 child per PAF for a
period of 1 year.
• A provision of Rs. 500/month for 6 months for one person per PAF
shall be given to extend other skill development opportunities to
eligible persons.
• Requiring body shall give preference to willing landless labourers and
unemployed affected persons while engaging labour in the project
during the construction phase.
20
• One person from each affected family shall be offered necessary
training facilities for development of entrepreneurship, technical and
professional skills for self-employment.
BUDGET
The total budget for implementation of the Rehabilitation and
Resettlement Plan is Rs. 114.41 million. The details are given in
Table-10.
Table-10: Budget for implementation of the Rehabilitation Plan
S. No. Components of R&R Cost
(Rs.
million)
A Rehabilitation Plan
1. Land required under “land for land” option = 332 ha irrigated land in the command area
2. Land development cost in case wasteland or
degraded land is allotted
10.89
3. Financial assistance for agricultural production 7.26
4. Training to take on suitable jobs 2.18
5. Scholarships 4.36
6. Other Skill Development 2.18
7. Training facilities for development of
entrepreneurship, technical and professional
skills for self-employment
4.36
8. Rehabilitation Grant - in case “land for land” or “jobs in project” are not given
81.68
Sub-Total [A] 112.91
B Project Monitoring & Evaluation [B] 1.50
Total [A+B] 114.41
Payment of compensation of acquired properties
A. Private lands:
SUBMERGENCE AREA • Compensation for irrigated land @ Rs. 12.5 lakh/ha
• Compensation for unirrigated land @ Rs. 6.25 lakh /ha
AREA TO BE ACQUIRED FOR CANAL NETWORK
• Compensation for irrigated land @ Rs. 286411/ha
• Compensation for unirrigated land @ Rs. 157894/ha
In addition compensation for wells and trees will also be paid.
21
9. LOCAL AREA DEVELOPMENT PLAN
The area development activities proposed as a part of the plan given in
following paragraphs:
Upgradation of educational facilities
The following activities are proposed under Local Area Development Plan:
• Up-gradation of school fixtures, equipment • School bus service
Improvement of Public Health Facilities
• Furniture, Beds and other items • Up-gradation of Pathological laboratory
• Up-gradation of operation theater (labor room)
An amount of Rs. 7.5 million is being made for implementation of the LADP
Activities. The details are shown in Table-11.
Table 11: Budget for implementation of Local Area Development Plan
S.
No.
Items Budget
(Rs. million)
1 Construction/ Up-gradation schools in Study Area 5.5
2 Improvement of Public Health Facility 2.0
Total 7.5
10. DISASTER MANAGEMENT PLAN
The following measures have been suggested as a part of the Disaster
Management Plan:
• Dam Safety and Maintenance Manual • Emergency Action Plan (EAP)
• Administration and Procedural Aspects
• Preventive Action
• Communication System • Notifications
• Evacuations Plans and Evacuation Team
• Public Awareness for Disaster Mitigation • Management after receding of Flood Water
22
11. ENVIRONMENTAL MONITORING PROGRAMME
An Environmental Monitoring Programme should be undertaken during
construction and operation phase of the project. The details of environmental
monitoring programme are given in Table-12.
Table-12: Details of Environmental Monitoring Programme
S.
No.
Particulars Parameters Frequency Location
1. Water pH, Turbidity, Total
Dissolved Solids,
Calcium, Magnesium,
Chlorides, Sulphate, Nitrates, Iron, DO,
BOD, COD etc.
Pre monsoon
Season and
Post
monsoon season
Reservoir.
2. Treated Waste Water from
STP
pH, BOD, COD, TSS, and Oil & Grease.
Once every month
Before and after
treatment
from STP
3. Erosion & Siltation
Soil erosion rates, stability of bank
embankment, etc.
Twice a year (pre & post
monsoon
Season)
--
4. Ecology Status of afforestation
programmes
Once in 5 years
--
5. Fisheries Phytoplanktons, zooplanktons,
benthic life, fish
composition
Twice a year
Reserviors.
6. Incidence of water-related
diseases
Cause and control measures for various
diseases
Once in a year
Settlements around
Reservoirs and
in command areas
7 Meteorological
Parameters
Temperature,
rainfall,
humidity, cloud cover, wind speed
and direction, Solar
Insolation
Continuous At a location
close to dam
site
23
12. COST ESTIMATES
12.1 COST FOR IMPLEMENTING ENVIRONMENTAL MANAGEMENT PLAN
The total amount to be spent for implementation of Environmental
Management Plan (EMP) is Rs. 216.74 million. This budget excludes the
compensation to be given for acquired properties. The details are given in
Table-13.
Table-13: Cost for Implementing Environmental Management Plan
S.
No.
Item Cost
(Rs. million)
1. Environmental Management in labour camp 0.60
2. Restoration of Quarry sites 10.60
3. Restoration and Landscaping of construction sites 3.00
4. Water Pollution Control 1.50
5. Air Pollution Control 2.72
6. Bio-diversity conservation Plan 10.81
7. Fisheries Management Plan 20.30
8. Resettlement and Rehabilitation Plan 114.41#
9. Local Area Development Plan 7.50
10. Catchment Area Treatment Plan 29.60
11. Disaster Management Plan 15.0
12. Purchase of meteorological instruments 0.70
Total 216.74 Note:# Excluding cost for compensation of acquired properties
12.2 COST FOR IMPLEMENTING ENVIRONMENTAL MONITORING
PROGRAMME
The cost required for implementation of the Environmental Monitoring
Programme in operation phase is of the order of Rs.2.6 million/year. The
details are given in Table-14.
Table-14: Cost for Implementing Environmental Monitoring
Programme
S. No Item Cost
(Rs. million/year)
1 Water quality 0.10
2 Ecology 1.00
3 Fisheries 1.00
4 Incidence of water related diseases 0.50
Total 2.60