DFA CAFR REPORTING PROJECT PROJECT MANAGEMENT PLAN (PMP) EXECUTIVE SPONSORS –TOM CLIFFORD, DFA SECRETARY; RON SPILMAN, CONTROLLER; DARRYL ACKLEY, DOIT SECRETARY PROJECT MANAGER – RENAE HERNDON, ACTING DFA STATEWIDE FINANCIAL ACCOUNTING AND REPORTING BUREAU CHIEF ORIGINAL PLAN DATE: NOVEMBER 11, 2014 REVISION DATE: JUNE 16, 2015 REVISION: 3.0

Transcript of Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting...

Page 1: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

DFA CAFR REPORTING PROJECT

PROJECT MANAGEMENT PLAN (PMP)

EXECUTIVE SPONSORS –TOM CLIFFORD, DFA SECRETARY; RON SPILMAN, CONTROLLER; DARRYL ACKLEY, DOIT SECRETARY

PROJECT MANAGER – RENAE HERNDON, ACTING DFA STATEWIDE FINANCIAL ACCOUNTING AND REPORTING BUREAU CHIEF

ORIGINAL PLAN DATE: NOVEMBER 11, 2014REVISION DATE: JUNE 16, 2015

REVISION: 3.0

Page 2: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

REVISION HISTORY............................................................................................................................................. III

PREPARING THE PROJECT MANAGEMENT PLAN................................................................................................. IV

ABOUT THIS DOCUMENT................................................................................................................................... IV

PROJECT OVERSIGHT PROCESS MEMORANDUM – DOIT, JULY 2007.................................................................................... IV

1.0 PROJECT OVERVIEW...................................................................................................................................... 1

1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT....................................................................................................11.2 FUNDING AND SOURCES...........................................................................................................................................21.3 CONSTRAINTS........................................................................................................................................................31.4 DEPENDENCIES.......................................................................................................................................................31.5 ASSUMPTIONS...................................................................................................................................................41.6 INITIAL PROJECT RISKS IDENTIFIED.............................................................................................................................4

2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE.............................................................................7

2.1 STAKEHOLDERS......................................................................................................................................................72.2 PROJECT GOVERNANCE STRUCTURE...........................................................................................................................8

2.2.1 Describe the organizational structure – Org Chart....................................................................................82.2.2 Describe the role and members of the project steering committee...........................................................82.2.3 Organizational Boundaries, interfaces and responsibilities.......................................................................9

2.3 EXECUTIVE REPORTING............................................................................................................................................9

3.0 SCOPE......................................................................................................................................................... 10

3.1 PROJECT OBJECTIVES............................................................................................................................................103.1.1 Business Objectives.................................................................................................................................103.1.2 Technical Objectives................................................................................................................................10

3.2 PROJECT EXCLUSIONS............................................................................................................................................103.3 CRITICAL SUCCESS FACTORS...................................................................................................................................10

4.0 PROJECT DELIVERABLES AND METHODOLOGY.............................................................................................11

4.1 PROJECT MANAGEMENT LIFE CYCLE........................................................................................................................114.1.1 Project Management Deliverables..........................................................................................................124.1.2 Deliverable Approval Authority Designations..........................................................................................134.1.3 Deliverable Acceptance Procedure..........................................................................................................13

4.2 PRODUCT LIFE CYCLE.......................................................................................................................................144.2.1 Technical Strategy...................................................................................................................................144.2.2 Product and Product Development Deliverables.....................................................................................154.2.3 Deliverable Approval Authority Designations..........................................................................................164.2.4 Deliverable Acceptance Procedure..........................................................................................................16

5.0 PROJECT WORK........................................................................................................................................... 17

5.1 WORK BREAKDOWN STRUCTURE (WBS)..................................................................................................................175.2 SCHEDULE ALLOCATION -PROJECT TIMELINE..............................................................................................................18

Major Project Deliverable and Performance Measure.....................................................................................18Due Date..........................................................................................................................................................18Project Phase....................................................................................................................................................18Hyperion Functional Lead.................................................................................................................................19TOTAL...............................................................................................................................................................19

5.3 PROJECT BUDGET.................................................................................................................................................20Major Project Deliverable and Performance Measure.....................................................................................20Due Date..........................................................................................................................................................20

REVISION: 1.0 DOIT-PMO-TEM-020 i OF vi

Page 3: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Project Phase....................................................................................................................................................20Hyperion Functional Lead.................................................................................................................................21TOTAL...............................................................................................................................................................21

5.4 PROJECT TEAM....................................................................................................................................................225.4.1 Project Team Organizational Structure...................................................................................................225.4.2 Project Team Roles and Responsibilities..................................................................................................23

5.5 STAFF PLANNING AND RESOURCE ACQUISITION................................................................................................245.5.1 Project Staff.............................................................................................................................................245.5.2 Non-Personnel resources.........................................................................................................................24

5.6 PROJECT LOGISTICS.........................................................................................................................................245.6.1 Project Team Training.............................................................................................................................25

6.0 PROJECT MANAGEMENT AND CONTROLS....................................................................................................25

6.1 RISK AND ISSUE MANAGEMENT..............................................................................................................................256.1.1 Risk Management Strategy.....................................................................................................................256.1.2 Project Risk Identification........................................................................................................................266.1.3 Project Risk Mitigation Approach............................................................................................................266.1.4 Risk Reporting and Escalation Strategy...................................................................................................266.1.5 Project Risk Tracking Approach...............................................................................................................276.1.6 ISSUE MANAGEMENT..............................................................................................................................27

6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V...........................................................................................286.3 SCOPE MANAGEMENT PLAN..................................................................................................................................28

6.3.1 Change Control........................................................................................................................................286.4 PROJECT BUDGET MANAGEMENT............................................................................................................................30

6.4.1 Budget Tracking......................................................................................................................................306.5 COMMUNICATION PLAN........................................................................................................................................30

6.5.1 Communication Matrix............................................................................................................................306.5.2 Status Meetings.......................................................................................................................................316.5.3 Project Status Reports.............................................................................................................................31

6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS).....................................................................................316.6.1 Baselines.................................................................................................................................................326.6.2 Metrics Library........................................................................................................................................32

6.7 QUALITY OBJECTIVES AND CONTROL..............................................................................................................326.7.1 quality Standards....................................................................................................................................326.7.3 Agency/Customer Satisfaction................................................................................................................34

6.8 CONFIGURATION MANAGEMENT...................................................................................................................346.8.1 Version Control........................................................................................................................................346.8.2 Project Repository (Project Library).........................................................................................................34

6.9 PROCUREMENT MANAGEMENT PLAN............................................................................................................35

7. 0 PROJECT CLOSE........................................................................................................................................... 35

7.1 Administrative Close...................................................................................................................................357.2 Contract Close............................................................................................................................................35

REVISION: 1.0 DOIT-PMO-TEM-020 ii OF vi

Page 4: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

REVISION HISTORY

REVISION NUMBER DATE COMMENT

1.0 11/11/2014 Initial Document

2.0 11/17/2014 Revisions for PCC meeting

3.0 6/16/2015 Revisions for PCC meeting

REVISION: 1.0 DOIT-PMO-TEM-020 iii OF vi

Page 5: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

PREPARING THE PROJECT MANAGEMENT PLAN

The workbook for preparation of the Project Management Plan is built around helping the project manager and the project team to use the Project Management Plan in support of successful projects. Please refer to it while developing this PMP for your project.

ABOUT THIS DOCUMENT

Project Oversight Process Memorandum – DoIT, July 2007

“Project management plan” is a formal document approved by the executive sponsor and the Department and developed in the plan phase used to manage project execution, control, and project close.

The primary uses of the project plan are to document planning assumptions and decisions, facilitate communication among stakeholders, and documents approved scope, cost and schedule baselines.

A project plan includes at least other plans for issue escalation, change control, communications, deliverable review and acceptance, staff acquisition, and risk management.

“Project manager” means a qualified person from the lead agency responsible for all aspects of the project over the entire project management lifecycle (initiate, plan, execute, control, close). The project manager must be familiar with project scope and objectives, as well as effectively coordinate the activities of the team. In addition, the project manager is responsible for developing the project plan and project schedule with the project team to ensure timely completion of the project. The project manager interfaces with all areas affected by the project including end users, distributors, and vendors. The project manager ensures adherence to the best practices and standards of the Department.

Project product” means the final project deliverables as defined in the project plan meeting all agreed and approved acceptance criteria.

“Product development life cycle” is a series of sequential, non-overlapping phases comprised of iterative disciplines such as requirements, analysis and design, implementation, test and deployment implemented to build a product or develop a service.

REVISION: 1.0 DOIT-PMO-TEM-020 iv OF vi

Page 6: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

1.0 PROJECT OVERVIEW The Project Overview sets the stage for the details of the project and begins the “story” of the project and plan.

1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECTNMSA 1978, Section 6-5-4.1 requires the Financial Control Division (FCD) of the Department of Finance and Administration (DFA) to compile a comprehensive annual financial report (CAFR) on behalf of the State of New Mexico. FCD currently prepares the CAFR utilizing an extraordinarily manual and archaic process. FCD manually compiles financial data from 143 business units and 1,200 funds to prepare the annual CAFR. The current process is inefficient, error-propone and untimely. During the 2014 Legislative Session, FCD requested and received funding for an automated financial reporting software package. The financial reporting software will integrate existing data sources residing in SHARE (FIN and HCM) into a single, secure financial reporting platform. Once the data has been collected, the CAFR team can prepare various financial statements and narrative disclosures utilizing the automated financial reporting software, which will enhance data integrity, transparency, timeliness, security, oversight, controls and audit trails over the CAFR compilation process.

The current manual process used in compiling the CAFR is archaic, extraordinarily cumbersome and manual. The overall process increases the risk of uncontrolled, multiple versions of spreadsheets and unsecured text documents, which in turn lead to data integrity issues, audit concerns and inefficiency. Numerous individuals are involved in the compilation of the CAFR and the data is derived from numerous multiple sources; complex procedures are required to reconcile numbers with little or no controls in place and limited audit trails.

The existing process makes it difficult for management to review the status of the CAFR. Furthermore, it is difficult or impossible for auditors to confirm that proper controls were in place, and that the appropriate levels of approvals were given during the CAFR compilation process. The process also relies on Agencies audit reports to prepare the CAFR. The State of New Mexico spends approximately $5 to $7 million dollars annually on individual agency audits. The use of financial reporting technology will aid in eliminating the need for individual agency audits and potentially save the state millions of dollars annually by automating the CAFR compilation process.

Hyperion is a web-based financial consolidation and reporting application and is part of the Oracle product family. It has delivered integration with PeopleSoft FSCM (SHARE Financials). Hyperion provides finance organizations the ability to consolidate and report financial results in order to meet regulatory and management reporting requirements. The State of New Mexico purchased Hyperion as the selected application for CAFR preparation. DoIT will host and support the Hyperion application.

PAGE | 1

Page 7: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

CAFR Reporting: The requisite financial reporting information for the CAFR will be loaded into Hyperion and the CAFR preparation will be performed in Hyperion.

Benefits of using Hyperion include: Automated and streamlined CAFR compilation processes: this provides security,

period-to-period information rollover, audit trails and workflows, which drive an efficient, effective and timely CAFR preparation process.

Direct integration of SHARE data sources: the financial data reported in the CAFR matches the source data.

Improved transparency and oversight: this provides a clear and comprehensive assessment of the State of New Mexico's financial condition in a timely manner.

Enhanced Internal controls and audit processes: this provides a comprehensive set of embedded internal controls to verify and validate that proper steps are being followed and that the financial data is credible and reliable. Specific disclosures can be linked directly to supporting documentation for easy reference. Edit checks, used-based security and continuous controls monitoring eliminate the risk of material weaknesses and help achieve a clean audit opinion.

Business rules and validation: this creates business rules and schedules tests against those rules to prevent errors during the aggregation of financial data In the CAFR.

Reduced workload for CAFR personnel through more efficient processes: Reduction in overtime hours and reduced CAFR preparation time.

The project will focus on the following business processes:

PROCESS DESCRIPTION

Annual CAFR Preparation The creation of the State’s CAFR through the consolidation of financial information from SHARE, BANNER, and Excel Spreadsheets.

1.2 FUNDING AND SOURCES

SOURCE AMOUNT ASSOCIATED RESTRICTIONS

APPROVERS

FY 2014-16 – L14 2S C63 S007 I005 - DFA SPECIAL APPROPRIATION

$500,000.00 NONE RICKY BEJARANO

FY 2015 – SECTION 5, ITEM #11 – DFA SPECIAL

$1,224,200 NONE

PAGE | 2

Page 8: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

SOURCE AMOUNT ASSOCIATED RESTRICTIONS

APPROVERS

APPROPRIATION

1.3 CONSTRAINTSConstraints are factors that restrict the project by scope, resource, or schedule.

NUMBER DESCRIPTION

C-001 AVAILABILITY OF THE APPROPRIATE TEAM MEMBERS FROM DOIT, DFA, AND OTHER AGENCIES TO PARTICIPATE ON PROJECT

C-002 COMPLETION OF THE PROJECT WITHIN THE FUNDING APPROPRIATIONS PERIOD

1.4 DEPENDENCIESTypes include the following and should be associated with each dependency listed.

Mandatory dependencies are dependencies that are inherent to the work being done. D- Discretionary dependencies are dependencies defined by the project management team. This may also

encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle.

E-External dependencies are dependencies that involve a relationship between project activities and non-project activities such as purchasing/procurement

NUMBER DESCRIPTION TYPE M,D,E

D-001 ONE NON-PRODUCTION HYPERION ENVIRONMENT, DEDICATED TO THE PROJECT, NEEDS TO BE MADE AVAILABLE FOR THE PROJECT

M

D-002 AGENCY AND COMPONENT UNITS WILL REQUIRE MODIFICATION TO THEIR PROCESSES AND INTERFACES

M

PAGE | 3

Page 9: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

1.5 ASSUMPTIONSAssumptions are planning factors that, for planning purposes, will be considered true, real, or certain.

NUMBER DESCRIPTION

A-001 AGENCIES AND COMPONENT UNITS WILL BE ABLE TO MEET DEADLINES ASSOCIATED WITH THE PROJECT

A-002 DOCUMENTATION AND TRAINING REQUIRED WILL BE COMPLETED BY THE PROJECT TEAM

A-003 HYPERION DELIVERED PROCESSES AND FUNCTIONALITY WILL BE USED WHENEVER POSSIBLE

1.6 INITIAL PROJECT RISKS IDENTIFIEDIn this section identify and describe how each risk will be managed. Include the steps that will be taken to maximize activity that will result in minimizing probability and impact of each risk.

Risk 1

A delay in procuring or contracting could push delivery dates into contention with the timeline for producing the Fiscal Year 2015 CAFR.

Probability: Possible Impact: High

Mitigation Strategy: Procure and contract in a timely manner in order to start the project in June 2015.Contingency Plan: Revise planned delivery dates in order to accommodate procurement delays.

PAGE | 4

Page 10: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Risk 2

Reliance on outsourced resources to accomplish project goals

Probability: Expected Impact: Outside consultants bring industry expertise and best practices. Costs are increased.

Mitigation Strategy: Critical project tasks include State resources for knowledge transfer. Agency leadership will closely monitor and manage outside contractor teams.Contingency Plan: Monitor situation closely and utilize all functionality available. Hire contractors for only short term needs.

Risk 3

Availability of State staff with the requisite capacity and capabilities.

Probability: Expected Impact: Schedule will be delayed, costs may increase and project may not receive the thought and testing required for smooth transition into production/implementation.

Mitigation Strategy: Supplement DFA staff with subject matter experts. Examine current CAFR staff pertaining to capacity and capability. Exercise appropriate staffing actions to build the team (e.g., hire additional staff, train current staff).Contingency Plan: Monitor closely the workload and personnel assignments. Utilize outside resources if budget will accommodate.

Risk 4

Maintaining project focus as a priority in light of the numerous SHARE projects and initiatives that are underway.

Probability: Possible Impact: MediumNeed to limit focus to AR only and avoid temptation to expand functionality.

Mitigation Strategy: Define resource commitments during the project planning process. Monitor resource availability and commitment levels across multiple projects, which may compete for resources.Contingency Plan: Obtain additional funding to expand scope to include additional functionality.

Risk 5

Organizational readiness and staff flexibility

Probability: Possible Impact: High

Mitigation Strategy: Communicate early and often. Include staff in the project and provide adequate training.Contingency Plan: Back-fill key State resources in order to allow staff to participate in the project.

PAGE | 5

Page 11: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Risk 6

Agencies and Component Units are unable to meet technical development deadlines

Probability: Possible Impact: High

Mitigation Strategy: Communicate early and often. Include staff in the project and provide adequate training. Provide information to technical staff as early in the project as possible.Contingency Plan: Obtain additional technical resources.

Risk 7

Availability of Hyperion environments and infrastructure at the onset of the project.

Probability: Possible Impact: High

Mitigation Strategy: The contract with the selected systems integrator includes two months of hosted environments.Contingency Plan: Revise planned delivery dates in order to accommodate contract delays.

Risk 8

Scope changes may impact the timely completion of project task or cause rework.

Probability: Possible Impact: High

Mitigation Strategy: Identify and monitor scope changes, and follow the change control process. Closely monitor and manage scope changes that may impact the schedule and/or budget.Contingency Plan: Monitor situation closely to limit scope change. Revise planned delivery dates in order accommodate scope changes approved by the appropriate parties.

PAGE | 6

Page 12: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE

The Project Organization describes the roles and responsibilities of the project team. It also identifies the other organizational groups that are part of the project and graphically depicts the hierarchical configuration of those groups. It exists to clarify interaction with the project team.

2.1 STAKEHOLDERSList all of the major stakeholders in this project, and state why they have a stake. . Stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be positively or negatively affected as a result of project execution or project completion. They may also exert influence over the project and its results.

NAME STAKE IN PROJECT AGENCY TITLE

DARRYL ACKLEY OVERALL RESPONSIBILITY FOR STATE SYSTEMS

DOIT CABINET SECRETARY

RON SPILMAN OVERALL RESPONSIBILITY FOR FINANCIAL REPORTING AND CONTROLS (FINANCIAL ACCOUNTING, CASH, AND AP CONTROLS)

DFA STATE CONTROLLER

TOM CLIFFORD OVERALL RESPONSIBILITY FOR CONTROL AGENCY

DFA CABINET SECRETARY

RENAE HERNDON OVERALL RESPONSIBILITY FOR FINANCIAL ACCOUNTING AND REPORTING

DFA ACTING DFA STATEWIDE FINANCIAL ACCOUNTING AND REPORTING BUREAU CHIEF

TBD STATE AGENCIES REPRESENTATIVES

VARIOUS AGENCIES

PAGE | 7

Page 13: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

2.2 PROJECT GOVERNANCE STRUCTURE2.2.1 DESCRIBE THE ORGANIZATIONAL STRUCTURE – ORG CHART

2.2.2 DESCRIBE THE ROLE AND MEMBERS OF THE PROJECT STEERING COMMITTEE

Members of the Steering committee members not yet finalized but will include the Stakeholders listed in 2.1 along with the State Treasurer (or his representative). Membership will reflect the organizations that will be affected by the New Mexico Statewide Immunization Information System Hosting, Maintenance, and Support Project.The Steering Committee is chartered to provide governance over the direction and support of the project and is chaired by the Project Director Ron Spilman. The Steering Committee member responsibilities include:

Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus detail of project Assist with issue resolution for issues requiring escalation to the Committee Review project funding and expenditures Champion the project Contribute to lessons learned

PAGE | 8

Page 14: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

2.2.3 ORGANIZATIONAL BOUNDARIES, INTERFACES AND RESPONSIBILITIES

Use this section to describe any special considerations regarding contact between the project team, the project manager, and individuals from various organizations involved in the project: Boundary, interface and responsibilities at the interface

The Project Team will work closely with the Department of Information Technology for contracting and amendment review and approval, project status reporting, and technical oversight.

2.3 EXECUTIVE REPORTINGMeeting agendas and supporting documentation will be provided using the following software packages: Microsoft Word, Excel, PowerPoint, Outlook and Project. Every attempt will be made to publish documents no later than 2 days prior to the next regularly scheduled meeting. Any meeting called should have an agenda, attempt to start and finish on time. The time allocated to each agenda topic will vary depending on the depth of issues to be covered. Items not able to be covered within the meeting time and accepted to be postponed may be added to the next standing meeting’s agenda or may require a special meeting.

The meeting times and distributions of the meeting minutes for the project are as follows:

Project Team Meetings will be on a regular schedule. The scribe will be assigned by the Project Manager. The project team meetings will be posted in the electronic document libraries by the Project Manager.

Special Session Meetings may be called at the request of the Project Director or Project Manager. A range of issues may require a special meeting of a team, committee or subset. These meetings will be scheduled to accommodate the majority of attendees. The minutes from these meetings will be posted in the document library and e-mailed to all attendees.

Status reports will be used to track progress and issues. Project Team members will provide status reports as requested by the Project Manager. These reports will be in addition to such reports prepared upon request and by other contractors. Monthly DoIT status reports will be submitted by the Project Manager.

Issues and risk management and resolution help to resolve those issues or risks not anticipated during planning process. Issues or risks should be reported at the earliest possible time so that corrective action and risk mitigation can be developed to address with the issue or risk. The corrective action should address both the immediate need and the underlying cause of the issue or risk. The Project Manager will keep an issue and risk tracking log and will work with the Project Team for corrective action.

The Project Manager will maintain an action item list. This action item list identifies the action item, the reference item, the responsible party, solution, and the due and completion dates. Updates may also be reflected in meeting minutes.

PAGE | 9

Page 15: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

3.0 SCOPE

3.1 PROJECT OBJECTIVES3.1.1 BUSINESS OBJECTIVES

NUMBER DESCRIPTION

BUSINESS OBJECTIVE 1

Streamline the consolidation of SHARE and Non-SHARE financial information associated with the preparation of the CAFR.

3.1.2 TECHNICAL OBJECTIVES

NUMBER DESCRIPTION

TECHNICAL OBJECTIVE 1

Utilize Hyperion Reporting to consolidate all of the statewide financial information from multiple sources into the CAFR.

3.2 PROJECT EXCLUSIONS

3.3 CRITICAL SUCCESS FACTORSIdentify the critical success factors for achieving success in this project. Metric are key to understanding the ability of the project to meet the end goals of the Executive Sponsor and the Business Owner, as well as the ability of the project team to stay within schedule and budget. See also section 6.7 Quality Objectives and Controls.

NUMBER DESCRIPTION

QUALITY METRICS 1

Strict adherence to the scope and project plan to meet milestones and deliverables.

QUALITY METRICS 2

Requirements captured, documented and tracked throughout the project are met.

QUALITY METRICS 3

Deliverables and Documentation are provided, approved, and disseminated on a timely basis.

4.0 PROJECT DELIVERABLES AND METHODOLOGY

4.1 PROJECT MANAGEMENT LIFE CYCLE

PAGE | 10

Page 16: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Phase Summary of Phase Key Deliverables

Project Organization and Planning

This phase outlines how the project will be conducted.

Scope Definition Project Plan and schedule Resource Requirements Bi-weekly and Monthly Reports

templates Risk and Issues Log templates Project Management Procedures

document (escalation process, issue resolution process)

Design and Build Configuration, Reports and Workflow

The process, functional, and technical design and build activities will occur in this phase.

Requirements Document Fit / Gap Document-Not Applicable Configuration Design Reports and Workflow Design –

Workflow Design not applicable Process Flow Documentation Configure and Build

System and Acceptance Testing

The testing of the systems and related process, configuration, and other system adjustments will occur in this phase.

Test Plan Testing Defect Tracking Log Test Scripts for Testing Cycles Unit Testing System and Integration Testing User Acceptance Testing Regression Testing

Project Knowledge Transfer and Training

User training, both support and end-user training take place in this phase.

Job Aids-Not Applicable Training Materials Training Delivery Knowledge Transfer

Go-Live Implementation Implementation Plan and Schedule Implementation Issues Tracking Log Cut-over

Support and Project Close-out

On-site Support Off-site Support Transition Plan Close-out Report

4.1.1 PROJECT MANAGEMENT DELIVERABLES

Project Deliverables are work products or artifacts that are driven by the project management methodology requirements and standard project management practices regardless of the product requirements of the project.

PAGE | 11

Page 17: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

4.1.1.1 Project CharterDescription – The initial project deliverable plan will contain the Project Charter. This deliverable may be revised during planning phase.

Deliverable Acceptance Criteria – Sign-off by Project Director, Ron SpilmanStandards for Content and Format –

Use of DoIT Project Charter templateQuality Review -.Peer review for grammar and spelling

Key project team members review for consensus

4.1.1.2 Project Management PlanDescription – The Project Management Plan will be the guide used throughout the Project. The plan will contain the following: Scope Management, Schedule Management, Risk Management, Communications, Change Management, and Roles / Responsibilities of team members. This document will evolve and be updated throughout the project.

Deliverable Acceptance Criteria – Approval by Project Team and Steering CommitteeSign-off by Project Sponsor or Project Director Standards for Content and Format –

Project Management Plan template.Quality Review – Peer review for grammar and spelling.Key project team members review for consensus.

Final review by Project Director and Steering Committee.

4.1.1.1 Executive ReportsDescription – Executive reports will be created based upon a defined and agreed upon schedule but on a bi-weekly basis at a minimum

Deliverable Acceptance Criteria – Sign-off by Project DirectorStandards for Content and Format –

Template to be developed by project teamQuality Review -.Peer review for grammar and spelling.

Key project team members review for consensus.Final review by Project Director and Steering Committee.

PAGE | 12

Page 18: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

4.1.1.1 Issues and Risks LogsDescription – logs will be created and maintained to track issues and risks that arise and are resolved throughout the project. The documents will evolve and be updated throughout the project.

Deliverable Acceptance CriteriaSign-off by Project DirectorStandards for Content and Format

Templates to be developed by project teamQuality ReviewPeer review for grammar and spelling.

Key project team members review for consensus.Final review by Project Director and Steering Committee.

4.1.2 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS

Complete the following table to identify the deliverables this project is to produce, and to name the person or persons who have authority to approve each deliverable.

Detailed Deliverables will be defined as part of the Statement of Work with the Implementation Vendor. They will include, at a minimum, the key deliverables listed in Section 4.1.

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

All All Steering Committee Members

4.1.3 DELIVERABLE ACCEPTANCE PROCEDUREDescribe the process that this project will use for the formal acceptance of all deliverables.

The project will submit the deliverable with a Deliverable Approval sign-off sheet to the steering committee approvers for review and approval.

PAGE | 13

Page 19: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

4.2 PRODUCT LIFE CYCLE “During the project management lifecycle, agencies shall select and implement a phase product development lifecycle methodology approved by the Department.” PROJECT OVERSIGHT PROCESS Memorandum

Phase Summary of Phase Key Deliverables

Initiation and Planning Project scope of work and deliverables identified

Definition of system requirements, work breakdown schedule

Project Charter

Design and Implementation

Development of items and Configuration of SHARE

Implementation Vendor Contract

Design and Configuration Documents

Testing and Training Plan

Testing and training Test Plans

Training Documentation

Training and Deployment

Transition to operations in production environment

Production Cutover Plan

End user training

System Documentation

Conduct Training

Maintenance Maintenance of new systems; project closeout and lessons learned

Maintenance and support plan

Annual maintenance agreements with vendors

4.2.1 TECHNICAL STRATEGY

Discuss the key technical strategies for achieving success in this project.

The key technical strategies for achieving success will be:

Use delivered Hyperion functionality wherever possible

Minimize development work through changes to system configuration and security

Confirm the changes are sustainable by DFA and DoIT

Confirm changes meet usability by the stakeholders

Ensure the changes meets current and future SHARE strategic plans

PAGE | 14

Page 20: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

4.2.2 PRODUCT AND PRODUCT DEVELOPMENT DELIVERABLES

Product Deliverables are work products or artifacts that are driven by the product management methodology requirements and standard project management practices regardless of the product requirements of the project.

4.2.2.1 Functional and Technical Specification DocumentsDescription – These documents are used to describe the functional and technical requirements for the various project requirements

Deliverable Acceptance CriteriaProject Director sign-offStandards for Content and Format

SHARE templatesQuality ReviewPeer review for grammar and spelling

Key project team members review for consensusFinal review by Project Director and Steering Committee.

4.2.2.2 Configuration DocumentsDescription – These documents will contain the changes required to the system configuration for the project.

Deliverable Acceptance Criteria

Project Director sign-off

Standards for Content and Format

SHARE templates

Quality ReviewPeer review for grammar and spelling.

Key project team members review for consensus.

Final review by Project Director and Steering Committee.

PAGE | 15

Page 21: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

4.2.2.2 Security Document and MatrixDescription – These documents will contain the changes required to the system security

Deliverable Acceptance Criteria –

Project Director sign-off

Standards for Content and Format –

SHARE templates

Quality Review – Peer review for grammar and spelling.

Key project team members review for consensus.Final review by Project Director and Steering Committee.

4.2.3 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS

Complete the following table to identify the deliverables this project is to produce, and to name the person or persons who have authority to approve each deliverable.

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

All All Project Director and Steering Committee members

4.2.4 DELIVERABLE ACCEPTANCE PROCEDURE

Describe the process that this project will use for the formal acceptance of all deliverables.

The project will submit the deliverable with a Deliverable Approval sign-off sheet to the steering committee approvers for review and approval.

PAGE | 16

Page 22: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.0 PROJECT WORK

5.1 WORK BREAKDOWN STRUCTURE (WBS)A WBS is a deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Describe the work activities that comprise the work breakdown structure (WBS) or the work packages within the WBS. Identify the WBS element or other work package identifier and provide a general description of the tasks or activities, the definition or objectives, and the milestones and deliverables of each work package.

Use the chart below for highest level presentation, and provide a more detailed WBS as an attachment to this project plan.

Identifier Work Package Description Definition/Objective Milestone/Deliverable

1.0 Initiation Phase This phase defines overall parameters of the project and established the appropriate project management and quality environment required to complete the project.

Project Charter, Initial Risk Assessment, High-level schedule, Approval for next phase.

2.0 Planning Phase This phase identifies the implementation approach, procurement method and establishes all necessary documentation.

Contract Negotiated and Executed, Finalize PCC PMP, Identify State Key Resources. Approval for next phase.

3.0 Implementation Phase This phase deploys the upgraded system to a prepared set of users and positions on-going support and maintenance.

Confirm Schedule

Configuration, Build, Test, Train, and Deploy.

4.0 Closeout Phase This phase closes out the project and completes the Transition to Production.

Closeout report, Transition to Production document, Support

PAGE | 17

Page 23: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.2 SCHEDULE ALLOCATION -PROJECT TIMELINEThe project timeline is a high-level view of project activities with a focus on project milestones. The project timeline does not replace the need for a detailed project schedule and it is to highlight key events such as deliverable due dates and when go/no-go decisions are made.

The table below should provide a high level view of the project time line, or a summary-level Gantt chart can be used to meet the timeline requirement.

Please provide a more detailed project schedule as an attachment to this plan.

A detailed project plan will be provided after an implementation vendor contract is executed

MAJOR PROJECT DELIVERABLE AND PERFORMANCE MEASURE

Budget DUE DATE

PROJECT PHASE

Procure Software: Hyperion software and support

$151,000.00 May 2014 Initiation

Pre-work: Readiness Assessment and Technical Assistance in regards to SHARE configuration.

$349,000.00 May 2015 Initiation

Deliverable 1 - Project Management, Organization, Planning and Reporting: Project Management, Plan and Progress Reporting, Bi-Weekly Project Status Meetings , Project Issues and Risk Logs, Monthly Status Reports

$22,500.00 per month less Retainage of $2,2500.00 per

month including GRT

Ending January 29,

2016

Initiation

Deliverable 2- Design for Configuration, Conversion and Reports: Requirements Documents, Configuration Design Document, Reports Design Document, Data Forms Design Document, Data History and Conversion Design Document, Design Walkthrough and Approval Sessions

Not to Exceed $180,000.00 less Retainage of $18,000.00

including GRT

August 14, 2015

Planning

Deliverable 3 - Installation, Configuration, Build and Conversion, Hosted Environment : Configure and Install Software, Configure, Build and Convert Application, End User Security Matrix and Set-up, Hosted Environment, Configuration, Build and Conversion Walkthrough and Approval Sessions

Not to Exceed $200,000.00 less Retainage of $20,000.00 for 2 months including GRT

October 16, 2015

Implementation

Deliverable 4-Testing and Training, Not to Exceed $190,000.00 less January 15, Implementation

PAGE | 18

Page 24: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Develop Test Plan: Unit Testing, System and Integration Testing, User Acceptance Testing, Training

Retainage of $19,000.00 including GRT

2016

Deliverable 5 - Go- Live Implementation, Implementation Plan and Schedule, Implementation Issue Log and Resolution, Implementation

Not to Exceed $120,000.00 less Retainage of $12,000.00

including GRT

January 22, 2016

Implementation

Deliverable 6 - On-Site Support, Closeout Report

Not to Exceed $104,185.00 less Retainage of $10,418.50

including GRT

February 19, 2016

Closeout

Deliverable 7 - Retainage Release, Upon Final Acceptance of all SOW Deliverables

Not to Exceed $97,418.50 Release of Retainage including

GRT

February 19, 2016

Closeout

HYPERION FUNCTIONAL LEAD $232,814.00March 15,

2016 Implementation

TOTAL $1,724,200.00

PAGE | 19

Page 25: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.3 PROJECT BUDGETCosts estimates are the costs applied to an activity in a project by assigning resources with associated rates or fees. Resources can include equipment, material, technology, processing cycles, or people. The total cost is critical and should be consistent with the proposal; include breakdowns as needed. Match these cost estimates with the actual billed amounts. Use an appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or deliverable).

MAJOR PROJECT DELIVERABLE AND PERFORMANCE MEASURE

Budget DUE DATE PROJECT PHASE

Procure Software: Hyperion software and support $151,000.00 May 2014 Initiation

Pre-work: Readiness Assessment and Technical Assistance in regards to SHARE configuration.

$349,000.00 May 2015 Initiation

Initiation: Project Charter, Initial Risk Assessment, High level schedule, Procurement StrategyDeliverable 1:Project Management, Organization, Planning and Reporting

Not to Exceed $22,500.00 per

month

less retainage of $2,250.00

including GRT

Ongoing Services

Beginning Contract

Execution Ending

January 29, 2016

Initiation

Project Management Plan: Schedule, Budget, Communications Plans, and Implementation Procurement

Planning

Vision and Planning Phase: Finalizing scope, project strategies, implementation vendor contracting, IV&V vendor selection, and establishing project logistics

Implementation

Design Phase: Evaluate current business processes and create new business processes. Document the required configuration/processing changes required to implement the designDeliverable 2:Design for Configuration, Conversion and Reports

Not to Exceed $180,000.00 less

Retainage of $18,000.00

Including GRT

August 14, 2015

Implementation

Build and Test: Configuration, processes, and security in accordance with the design documents. Deliverable 3:Installation, Configuration, Build and Conversion

Not to Exceed $200,000.00 less

Retainage of $20,000.00 for 2

months including GRT

October 16, 2015

Implementation

Training: Perform training of State personnel impacted by the projectDeliverable 4 :

Not to Exceed $190,000.00 less

Retainage of $19,000.00

including GRT

January 15, 2016

Implementation

Implement: Move the changes into production environments

Implementation

PAGE | 20

Page 26: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Post Implementation Support, Review and Report, Administrative Close-OutDeliverable 5:

Not to Exceed $120,000.00 less

Retainage of $12,000.00Including GRT

January 22, 2016

Closeout

Support and Project CloseoutDeliverable 6:

Not to Exceed $104,185.00 less

Retainage of $10,418.50

Including GRT

February 19, 2016

Closeout

Retainage ReleaseDeliverable 7 :

Upon Final Acceptance of all SOW deliverables

including GRT

February 19, 2016

Closeout

HYPERION FUNCTIONAL LEAD $232,814.00

Including GRT

March 15, 2016 Implementation

TOTAL $1,724,200.00

PAGE | 21

Page 27: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.4 PROJECT TEAM5.4.1 PROJECT TEAM ORGANIZATIONAL STRUCTURE

Insert a graphical Organization Chart here. The Organizational Structure (OS) is a hierarchical configuration defining levels of program management and may identify all project personnel. The OS should be simple and straightforward. Include role names and people’s names. Consider identifying the core project team by shading their respective boxes on the chart. On complex projects, consider using a second OS to identify core project team. The OS can also be used for management reporting.

The detailed project org chart will be developed after the implementation vendor is selected and the impacted agencies are on-boarded.

PAGE | 22

Page 28: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.4.2 PROJECT TEAM ROLES AND RESPONSIBILITIES

List the team members, their role, responsibility and functional manager. Make sure to include a comprehensive listing including those from the organization managing the project, business members involved to ensure business objectives are met and the vendor members that may have a specific role.

The below resources are the only ones identified and confirmed at this point in time.

ROLE RESPONSIBILITY NAME FUNCTIONAL AREA

SHARE Project Manager

Coordinate all activates for the project within DoIT

Darryl Ackley DoIT/SHARE

DFA Project Manager

Coordinate all activates for the project within DoIT - Review, Approve, and Disseminate project activates related to CAFR Reporting Project

Renae Herndon CAFR

NM DFA CAFR Specialist

Review, Approve, and Disseminate project activates related to CAFR Reporting Project

Will Crespin CAFR

NM DFA SHARE Specialist

Review, Approve, and Disseminate project activates related to CAFR Reporting Project

Stuart Guy SHARE Financials

PAGE | 23

Page 29: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.5 STAFF PLANNING AND RESOURCE ACQUISITIONComplete the chart below identifying the project team members and details concerning their project commitment. Project staff should include State, Contract, Customer (Business Owner), or Vendor team members

Resources will be finalized after implementation vendor contract is executed.

5.5.1 PROJECT STAFF

ResourceCost Estimate

Estimated Hours Availability Skill Set Work Product/Deliverable

DFA CAFR TBD

DFA SHARE TBD

Agency Functional TBD

Agency Technical TBD

SHARE DoIT TBD

5.5.2 NON-PERSONNEL RESOURCES

Use this section to list services or product (HW/SW and such) needed for project

Resource Cost Estimate

Estimated units/hours Availability Source Work Product/Deliverable

TBD

5.6 PROJECT LOGISTICSLogistics describes how the project manager, project team, the business owner/customer and any vendor resources will physically work together. Include anything to do with moving or starting resources. Training specifically related to project team members should be included here.

PAGE | 24

Page 30: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

5.6.1 PROJECT TEAM TRAINING

Describe training if any needed by project team members. This is not to include training for end users, system administrators or business owners; those should be handled within a training document or part of the transition to operations planning.

ResourceCost Estimate

Estimated Hours Availability Skill Set Work Product/Deliverable

None required

6.0 PROJECT MANAGEMENT AND CONTROLS

6.1 RISK AND ISSUE MANAGEMENT

Risk: “An uncertain event or condition that, if it occurs, has a positive or negative effect on a project’s objectives.”

Issue: “A point or matter in question or dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.”

Both Risks and Issues can significant impact a project’s success, and both should be handled in similar ways.

6.1.1 RISK MANAGEMENT STRATEGY

Provide a detailed explanation on the strategy for how risks are identified, analyzed/ quantified, mitigated, reported, escalated and tracked. Include the use of tools such as project management software, forms, and templates. A separate risk management plan may also be developed if needed for the project and included as an Appendix to this document. If that is the case, a high level summary of this plan needs to be included here with the specific reference.

PAGE | 25

Page 31: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.1.2 PROJECT RISK IDENTIFICATION

Risk Description Impact Levels: Very High High Medium Low Very Low Probability Levels: 1 2 3 4 5

Certain 1 Expected 2 Likely 3 Possible 4 Unlikely 5

6.1.3 PROJECT RISK MITIGATION APPROACH

We will follow the Risk Management Process below as suggested by DoIT:

6.1.4 RISK REPORTING AND ESCALATION STRATEGY

The regularly scheduled project report will include issue/risk identification for each item.

PAGE | 26

Page 32: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.1.5 PROJECT RISK TRACKING APPROACH

Number   Risk Probability Impact Rating Contingency Plan

Mitigation Plan

1 Example Certain High 0.7125

6.1.6 ISSUE MANAGEMENT

6.1.6.1 Internal Issue Escalation and Resolution ProcessThis internal process is provided for issues that involve project resources, processes, procedures, or methodology that should be resolved within the Division that is responsible for managing the project without affecting the overall project schedule, cost, or quality. This process should be used for improving project processes as the project is executed and where the implementation of such improvements should not be postponed to Lessons Learned during Project Close.

We will follow a Risk/Issue Management Log template similar to the one below as suggested by DoIT:

Issue Log:

Issue No.   Issue  

Person Responsible  

Date Opened - Month/Day/yea

r  Statu

sOpen

Issue FormIssu

e No. (From

Issue

Log)  

Responsible Party (From Issue Log)  

Level (High, Medium, Low)  

Class (Impact Area)  

Date Opened (From Issue Log)  

Date Closed  

Originator  

Status (From issue Log)

Issue (From Issue Log)

Consequence(s)

Resolution

PAGE | 27

Page 33: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.1.6.2 External Issue Escalation and Resolution ProcessThe external process is provided for issues that involve project resources, processes, procedures, or methodology that cannot be resolved within the Division that is responsible for managing the project without affecting the overall project schedule, cost, or quality.

6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&VIndependent Verification and Validation (IV&V) means the process of evaluating a system to determine compliance with specified requirements and the process of determining whether the products of a given development phase fulfill the requirements established during the previous stage, both of which are performed by an organization independent of the development organization. Describe the process that will be employed to meet IV&V requirements.The IV&V plan will:

1. Evaluate and validate that products and deliverables of a given development phase fulfill the requirements and performance outcomes set forth in the scope and project plan.

2. Provide a “close-out” report to the Steering Committee at the end of project

Specific deliverables from the IV&V contract: IV&V Project Management Plan. Initial Review and Risk Assessment. Periodic Review Close-out Report

6.3 SCOPE MANAGEMENT PLANDescribe the process that is going to be used to manage the scope of the project. Make sure to address managing stakeholder expectations.

Most changes to scope are requests that add, change, or delete project objectives or deliverables. Changes in scope, if at all possible, will be avoided and any new objectives and/or deliverables deferred to a follow-on project. Any proposed changes in scope will be analyzed for impacts on the project including schedule, budget and quality. The findings will be presented to the Steering Committee for approval or rejection

6.3.1 CHANGE CONTROL

6.3.1.1 Change Control ProcessChange Control establishes how change will be managed, including capturing, tracking, communicating, and resolving change. Due to much ambiguity regarding change, it is vital that we document and discuss the change process with the executive sponsor.

PAGE | 28

Page 34: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

Project changes will follow a decision making process. These changes include modifications to scope, schedule, budget, and quality. Significant changes of these planning components will be reviewed and approved or disproved by the Steering Committee. If a modification or enhancement to the project has been identified, a change request form will be completed. The Steering Committee will review the request to determine impacts to scope, schedule, budget, quality and resources. The Steering Committee will recommend accepting the change, rejecting the change, or may request additional information. The request will be documented by the Project Manager and if the change is approved, appropriate changes will be made to the Project Management Plan and other project documentation.

6.3.1.2 Change Control Board (CCB)Insert a graphic or textual description identifying the Change Control Board (or function) for this project. The CCB may be an individual or group of individuals authorized to approve changes to the project plan.

The Steering Committee will fill the role of the Change Control Board.

PAGE | 29

Page 35: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.4 PROJECT BUDGET MANAGEMENTCosts estimates are the costs applied to an activity in a project by assigning resources with associated rates or fees. Resources can include equipment, material, technology, processing cycles, or people. The total cost is critical and should be consistent with the proposal; include breakdowns as needed. Match these cost estimates with the actual billed amounts. Use an appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or deliverable).

This will be a deliverable based contract to be negotiated with the Implementation Vendor not to exceed a total of $5 million.

6.4.1 BUDGET TRACKING

The budget will be tracked based upon the deliverables completed.

6.5 COMMUNICATION PLANCommunication planning involves determining the information and communication needs of the stakeholders, executive sponsors, project team and others as needed. The communication plan needs to address who needs what information, when they will need it, how it will be given to them, and by whom. The complexity of the project may require a separate communication plan; however a high level summary of that plan will need to be included here and a reference made to the appropriate Appendix.

6.5.1 COMMUNICATION MATRIX

Meetings Status Reports Other Communications

To Executive Sponsor Monthly Monthly As Needed

To Steering Committee Monthly Monthly As Needed

To Project Director Bi-Weekly Bi-Weekly As Needed

To Project Team Bi-Weekly Receive From Members

As Needed

To Stakeholders As Requested As Requested As Needed

PAGE | 30

Page 36: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.5.2 STATUS MEETINGS

Status Meetings with the core project team will be held on a regular basis. This will include the project manager, project director and vendor project manager. Project Status will be the first agenda item. If needed, special meetings will be called to discuss and address issues.

There are several meetings that will be held on a regular basis throughout the duration of the project.

All meetings are guided by an agenda prepared before the meeting. Notes will be kept during the meeting and documented as minutes which will be reviewed by attendees and corrected as needed. Typically the minute taker is assigned at each meeting and the responsibility is shared by all.

Throughout the course of the project various meetings will be held. Some of the meetings may include, but are not limited to, the following:

PROJECT TEAM MEETINGS

TYPE/NAME FREQUENCY

DAY/TIME DURATION

Project Status Meeting Bi-Weekly TBD 1 Hour

Project Team Meeting Weekly TBD 1 Hour

Leaders Meeting Monthly TBD 1 Hour

6.5.3 PROJECT STATUS REPORTS

Project Status Reports which include reports from the Vendor will be distributed to the Project Sponsor and the Project Director and will be presented at each Steering Committee Meeting. These status reports will be rolled up into the Steering Committee status report and reviewed at each meeting.

6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)The Project Manager and Executive Sponsor define the project metrics that will be used to control the project. Each project will need to have an established metrics program. Metrics are collected for measuring the progress of a project against its planned budget, schedule, resource usage, and error rates, and of establishing a historical database, which will aid in planning and forecasting future projects. At a minimum metrics must be established for time (schedule), cost (budget) and quality.

PAGE | 31

Page 37: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.6.1 BASELINES

Project Area Category Measure

CAFR production Reporting On-time CAFR production and publication

6.6.2 METRICS LIBRARY

The reviewed metrics in various software programs will be versioned by date and stored with project artifacts.

6.7 QUALITY OBJECTIVES AND CONTROLQuality Management includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It includes all activities of the overall management function that determine the quality policy, objectives, quality assurance, quality control, and quality improvement, within the quality system. If a separate Quality Plan is used, include a high level summary in this document and refer to the appropriate appendix.

6.7.1 QUALITY STANDARDS

Describe the agency, industry or regulatory project performance standards that will be followed and assessed by the project. These quality standards will be used to assess whether the quality objectives were achieved.

Identify each of the project quality standards that are directly related to the project and not to the performance of the actual product and/or service. For each quality standard, identify the tracking tool or measure such as number of project reviews or Project Status.

PAGE | 32

Page 38: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

No. Quality Standard Tracking Tool or Measure

1 Project management plan approved and followed • PMP signed off by Steering Committee

• Project status reports

2 Certification to proceed to next phase by DoIT • Approval from DoIT Project Certification Committee and release of funds

3 Project risks documented, mitigated and tracked • Risk Management Log

4 Project issues documented, tracked, and worked to resolution • Issue Log

5 Project is within budget • Project status• Budget management

6 Independent Verification and Validation • Periodic reviews• Respond to

identified issues and risks

7 Project completed based on the original project scope and approved scope changes

• Project Management Plan

• Change Control Process

• Scope Management• Steering Committee

Meeting Decisions

PAGE | 33

Page 39: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

6.7.3 AGENCY/CUSTOMER SATISFACTION

The project manager should assess the on-going sense of the customer agency about how they feel the project is going, and how team members are acting on the project. This feedback would be helpful to the success of the project and the professional growth of the project team members.

Areas of feedback When How Often

Agency awareness Feedback from the agencies and end-users

Monthly

Quality of communications Feedback during the various meetings

At Project Team meetings and Steering Committee meetings; other meetings when held.

Manages project tasks Feedback from Project Sponsor, Steering Committee, Project Director

Monthly

Productive Meetings Feedback from Project Sponsor, Steering Committee, Project Director, Project Team, Testers, Training Attendees, Deployment Users

Monthly and per phase of the project.

6.8 CONFIGURATION MANAGEMENTConfiguration Management determines how project information (files, reports, designs, memos, documents, etc.) will be managed (tracked, approved, stored, secured, accessed, version control, etc.) and owned by (e.g., Agency managing the project or the Customer). Standards and team awareness are critical.

6.8.1 VERSION CONTROL

Documents will be stored on the implementation vendor shared file site which provides version control. If a document needs to be changed or updated, the document must reflect the version control information required in the document. All documents will also be controlled by the revision history log. Entries will be made into the revision history log when changes are made.

6.8.2 PROJECT REPOSITORY (PROJECT LIBRARY)“Provide to the Department all project management and product deliverables. Deliverables shall include but not limited to the project plan, project schedule, initial and periodic risk assessments, quality strategies and plan, periodic project reports, requirements and design documents for entire project. The

PAGE | 34

Page 40: Executive Sponsors –Tom Clifford, DFA Secretary; Ron ... CAFR...  · Web viewDFA CAFR Reporting Project. PROJECT MANAGEMENT PLAN (PMP) Executive Sponsors –Tom Clifford, DFA Secretary;

PROJECT MANAGEMENT PLAN FOR DFA CAFR REPORTING PROJECT

lead agency must make available all deliverables in a repository with open access for the Department to review” PROJECT OVERSIGHT PROCESS Memorandum.

The approved deliverables will be posted to a dedicated section on the DFA website.

6.9 PROCUREMENT MANAGEMENT PLANProjects often have some element of procurement, i.e. the requirement to purchase goods and/or services from outside the organization. The procedures to be used to handle these procurements should be included here. Activities such as a make-or-buy analysis; writing requirements; solicitation planning, evaluation and selection; inspection and acceptance; contract closeout should all be included.

7. 0 PROJECT CLOSEProject Close will always consist of administrative project activities and possibly contractual project activities and an external vendor is employed. Completing both sets of activities is a mandatory step in the project life cycle. Administrative activities complete the internal needs for the Agency/Unit that is responsible for managing the project, such as lessons learned, recording the last hours against the project, and providing transition for the staff to other assignments. Contractual activities meet the contractual needs, such as executing a procurement audit and formal acceptance of the project work products. The closeout will include the completion and approval of deliverables as indicated in the implementation vendor contract.

7.1 ADMINISTRATIVE CLOSE

Administrative Close occurs at both the end of phase and end of project. This closure consists of verification that objectives and deliverables were met. Acceptance is formalized and phase activities are administratively closed out. Administrative closure occurs on a “by-phase” basis in accordance with the WBS and should not be delayed to project end. At that point, the burden of closing is too great and audits inaccurate. The specific project close activities for a given project are contingent on the project’s complexity and size. Project managers should work with the project’s project management consultant to tailored Project Close procedures to compliment the project’s objectives.The final closeout will include the completion of required documentation, the DoIT closeout report and a presentation to the DoIT Project Certification Committee for approval to formally close the project.

7.2 CONTRACT CLOSE

Contract close is similar to administrative close in that it involves product and process verification for contract close.

PAGE | 35