EXECUTIVE SUMMARY › writereaddata › ... · Parallel Taxi Track. The area earmarked for the...
Transcript of EXECUTIVE SUMMARY › writereaddata › ... · Parallel Taxi Track. The area earmarked for the...
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron
and Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
EXECUTIVE SUMMARY
Surat Airport is located on Magdalla - Dumas Road towards the famous Dumas Beach on
the South-West part of the city, approximately 20kms from the city center.
The Airport currently serves Surat city with a population of 6 million and serves the South
Gujarat region with an overall population of 12 million, Besides the intrastate connectivity
provided by Surat based NSOP, with Ahmedabad, Amreli, Bhavnagar and Rajkot; the city
has had limited air connectivity, for many long years, until recently. The new airport
terminal was inaugurated in the year 2009 and licensed by the DGCA as aerodrome for
public use in 2011 as per the ICAO guidelines. Air India, the National carrier had started its
operation since May, 2007 and remained the sole service provider to STV, until February,
2012 when SpiceJet a Private LCC, provided the desperately needed additional
connectivity. However, the service of SpiceJet came to an abrupt end; when one of the
aircraft hit a wandering buffalo on the runway while take-off resulting in immediate &
indefinite termination of service in late 2014. Although with scanty connectivity provided
by Scheduled Airlines, the airport otherwise has been patronized regularly by Charter
Services of MNCs from Hazira, VVIP Movements (PMOI), State Government (CMGUJ),
Air force(C 17 Globe master), Indian Navy, Coast Guard, Heliport for Pvt. operators, Pilot
Training Academy and lately by a Non Scheduled Operator - Ventura Air Connect, which
is a NSOP based out of Surat. Taking in view severe ramifications of the buffalo-hit on the
runway, major renovation and up-gradation work was taken up in 2015 and in a span of
three painstaking years; remarkable developments have been made till date. The airport
renovation consisting of periphery walls, to runway repair & extension, aero-bridge
installation etc.; pending few tasks almost all of the measures for a safe & secure
functioning of the airport, more or less has now been achieved. Hopefully with Extended
Passenger Terminal being added in the next two years, Surat Airport seems to be taking to
wings over the seven seas and should be all set to achieve a fully fledged International
Status by year 2019 with a capacity to handle more than a Million passengers yearly and a
ranking among top 30 busy Airports in India.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron
and Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
As part of the airport development process, the AAI proposed Holistic Development of
Surat Airport Including Extension of Terminal Building, Apron and Construction of
Parallel Taxi Track.
The area earmarked for the proposed extension of terminal building is about 17,035 m2, for
Apron (including Shoulder, GSE & Shoulder converted to apron) is 34,940 m2 and for
construction of Parallel Taxi Track (including Shoulder) is 91535 m2 within the existing
airport premises. There is no additional requirement of land for the proposed
developmental works. The construction work will be done in the land abutting the existing
airport. Thus, the same requires prior Environmental Clearance under the provisions of EIA
Notification, 2006 and subsequent amendments. The same shall be categorized under item
7 (a) of Schedule - Gazette Notification as Category A project.
Project Brief:
The project involves extension of terminal building, Apron and construction of parallel
taxi track. The total area of the existing airport is 784.37 Acres. The details of the
proposed development are summarized as under:
Table 1.1: Project Summary
S No. Description Revised Details
1. Project cost Rs. 353.25 Cr.
2. Location Latitude: 21° 7' 3.57" N
Longitude: 72° 44' 42.93" E
3. Plot area 106770 sq. m.
4. Ground Coverage (achieved) 13710 sq. m. (12.9 %)
(Terminal + Canteen + ESS)
5. Total Built Up Area 26250 sq. m. (25520 m2 + 130 m
2 + 600m
2)
6. Green Area 35950 sq. m. (33.7 %)
7. Road and Open Area (excluding surface
parking area)
41385 sq. m. (38.7 %)
8. Surface parking Area 15725 sq. m. (14.7 %)
9. No. of Floors G +1
10. Height of Building 17.8 m
11. Area of Apron ((including Shoulder, GSE &
Shoulder converted to apron )
34940 sq. m.
12. Parallel Taxi Track Area (including Shoulder) 91535 sq. m.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron
and Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
13. Water demand 531 KLD (Domestic)
14. Power requirement Connected Load:-
(Existing : 2000 KW; Proposed : 2045 KW)
Maximum Demand:-
(Existing : 1016 KW; Proposed : Not Avail)
Transformer:-
(Existing: 3x500 kVA; Proposed : 3x1600
kVA)
15. Back up source Existing:- 3x 250 kVA
Proposed:- 3x 1000 kVA
16. Renewable Source of Energy (Solar) 200 KW Solar Power Systems
17. Solid waste generation 1414 kg/day
Table 1.2: Project facilities (Total after expansion)
S. No Particulars Existing Proposed Expansion Total
1. Land Area
i. Total Land Area 784.37 Acres NIL 784.37 Acres
2. Runway Details
i. Runway
Length/dimension
2906 M NIL 2906 M
ii. Runway shoulders 7.50 M NIL 7.50 M
iii. Runway strip
Dimension
3026 M x 300 M NIL 3026 M x 300 M
iv. RESA Dimension 90 M x 240 M 90 M x 240 M
v. Runway lights Runway edge lights
(Double ckt) –
160+160=320 nos.
NIL
320 nos.
3. Type of Aircraft handling
i. Type of Aircraft AE320/AE321/B737
4. Apron Details
i. Dimension 30,012 Sqm 24,435 Sqm 54,447 Sqm
5. Taxiway Details
i. Dimension 2 Nos 23 x 200 M PTT – 30x2906 M 2 Nos 23 x 200 M
PTT – 30 x 2906 M
6. Terminal Building
i. Area 8474 Sqm 17046 Sqm 25500 Sqm
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron
and Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
ii. Capacity Peak Hour 500 Domestic
Passenger
700 Dom. + 600 Int. 1800 (1200 Dom. +
600 Int.)
iii. Car Parking 250 carpark 250 car park + 200 scooter 500 car park + 200
scooter
7. Navigation Aids
i. DVOR DVOR No change Same as before
ii. PAPI PAPI No change Same as before
8. Other Facilities
i. Isolation Bay 1. Isolation Apron &
link taxi light- 40 no.
No change Same as before
ii. ILS (Instrument
Landing System)
NIL NIL NIL
iii. Approach lights 1. SAPL-04 (Elevated
type)-17 no.
2. SAPL-22( Inset type
–due to displaced
threshold by 615 m)-
17 nos.
No change Same as before
9. AAI staff Accommodation
i. Residential Quarter N/A N/A N/A
ii. CISF Barrack/police Available No Change Same as before
********************
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
INTRODUCTION OF THE PROJECT
2.1 Identification of Project and Project Proponent
Surat Airport (IATA: STV, ICAO: VASU) is an International airport located in Magdalla,
Surat in the western Indian state of Gujarat with a total area of 784.37 ha. It is the second
busiest airport in Gujarat after Ahmedabad in terms of both aircraft movements and
passenger traffic. It was awarded the custom-notified status on 9 June 2018. The airport
currently caters to scheduled airline services across major destinations in India as well as
non schedule private aircraft and is also home to a flying training school.
The new Surat airport terminal building was inaugurated by Union Minister of State for
Petroleum Mr./Ms. Dinsha Patel in the year 2009. The terminal building is equipped with
CCTV cameras, two baggage carousels in the arrivals hall and one hand baggage X-ray
machine, among other modern facilities like two air bridges with Visual Docking
Guidance System, two elevators and two escalators, and seating lounge. Coffee Culture
and other shops have been added. As part of the airport development process, the AAI
proposed Holistic Development of Surat Airport Including Extension of Terminal
Building, Apron and Construction of Parallel Taxi Track.
The area earmarked for the proposed extension of terminal building is about 17,035 m2,
for Apron (including Shoulder, GSE & Shoulder converted to apron) is 34,940 m2 and for
construction of Parallel Taxi Track (including Shoulder) is 91535 m2 within the existing
airport premises. There is no additional requirement of land for the proposed
developmental works. The construction work will be done in the land abutting the existing
airport.
Airports Authority of India (AAI) was constituted by an Act of Parliament and came into
being on 1st April 1995. AAI under the Ministry of Civil Aviation is responsible for
creating, upgrading, maintaining and managing civil aviation infrastructure in India.
AAI is planning to take up the works of development of Terminal Building, Apron and
Construction of Parallel Taxi Track of Airport is categorized under item 7 (a) of Schedule
- Gazette Notification dated Sept. 14th
, 2006 and its subsequent amendment thereafter.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
The existing facility & other details are as follows:
S. No Particulars Details
A. General Information
1. Latitude & Longitude of Aerodrome
Reference Point (ARP–WGS 84)
21°06'58'' N 72°44'31'' E
2. Suitability Type –C Aircraft
3. Aircraft operations
(Scheduled/Non-scheduled)
Scheduled & Non-schedule
4. Other Airports in the vicinity
(within 150 Km radius)
Vadodara, Daman {Cost, Guard} Bhavnagar,
B. Airport land area & utilization
1. Total land area (Acres) 784.37
C. Aerodrome Data (Air side)
1. Aerodrome elevation / Reference Temp 29 Ft / 420C
2. Aerodrome Reference Code (ARC) 4C
3. Aerodrome traffic density Medium
4. Type of traffic permitted Schedule flight / Non-schedule flight, Training
flight/ o/f
5. Aerodrome rescue & fire fighting category
(ARFF)
VII
D. Runway
1. Runway operations 04/22
2. Runway Dimension 2906M x 45 M
3. Runway strip dimension 3026M x 300 M
4. Runway Strength (PCN) 73/R/B/W/T : 71/F/C/W/T
5. Runway surface Flexible and Rigid
6. Runway shoulder 7.5 M on Both side
7. Runway End Safety area (RESA) 240 X 90 M – both end
E Terminal Building
1. Area 8474 Sq. m.
2. Capacity Peak Hour 500 Domestic Passenger
3. Car Parking 250 carpark
F. Apron Details
1. Dimension 122 x 246 M
2. Capacity 5 Parking base
3. PCN 62/R/C/W/T
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
G Taxiway Details
1. Width 23m
2. PCN 62/R/C/W/T
3. Shoulder 3.5 meter both side
H. Navigation Aids
1. DVOR DOVR
2. PAPI PAPI @ 04 and 22
I AAI Staff Accommodation
Residential Colony Not Available
CISF Barrack Accommodation / Police Available
J. Other Facilities
1. Instrumental Landing system DVOR-DME APP. Runway/22 available
2. Residential Colony Not available
3. Runway Light Facilities Available
1. Runway edge lights (Double ckt)-
160+160 nos.
2. Turning pad lights (Double ckt)-37 no.
3. Threshold lights (Double ckt)
a. Elevated for Rwy-04-32 nos
b. Inset Type for Rwy-22- 20nos
c. Wing bar elevated- 20 nos
4. Runway End light(Double ckt)-24 nos
5. PAPI-04 &22-2 sets
6. Link Taxi edge lights (Taxi-A, B&D)-70
no.
7. Apron Edge lights (Main apron &
isolation bay)-40 no.
8. Apron flood lights (main)- 6 nos.
9. Isolation bay- 1 no.
4. Approach Lights Available
1. SAPL-04 ( Elevated type)-17 nos
2. SAPL-22( Inset type –due to displaced
threshold by 615 m)-17 nos
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
2.2 Brief Description of Nature of the Project
AAI is planning the Holistic Development of Surat Airport Including Extension of
Terminal Building, Apron and Construction of Parallel Taxi Track.
Type of project:
The proposed expansion of Airport is categorized as category A under item 7 (a) of
Schedule - Gazette Notification dated Sept. 14th
, 2006 and its subsequent amendment for
preparation of Environment Impact Assessment study and Environment Management
Plan. However general condition is not applicable to this project. This project is
independent and is not linked with other project which may attract directly or indirectly
any provisions of schedule of EIA notification 2006 amended to date.
2.3 Need for the project & its Importance
The passenger traffic at Surat Airport has increased by 250 % from 194688 nos. in 2016-
17 (March to April), to 681465 nos. in 2017-18 (March to April). Similarly, the Air
Traffic Movements (ATM’s) increased by 131.4 % in from 4651 nos. in 2016-17 (March
to April) to 10762 nos. in 2017-18 (March to April).
The passenger handling capacity at Surat Airport in future shall continue to increase. In
view of rapid growth in passenger traffic of over 250 % in 2017-18 & Air craft
movement of over 131.4 % in 2017-18, Surat Airport operational infrastructure needs to
be upgraded to serve the estimated demand of over 2.6 Million Person Per Annum by
2031-32 to be achieved in phases. Improvements in connectivity will effectively
contribute to the economic performance of the wider economy through enhancing its
overall level of productivity.
2.4 Demand Supply Gap
The passenger handling capacity at Surat Airport in future shall continue to increase. In
view of rapid growth in passenger traffic of over 250 % in 2017-18 & Air craft movement
of over 131.4 % in 2017-18, Traffic forecast indicates passenger traffic demand to reach
over 2.6 Million Person Per Annum by 2031-32 to be achieved in phases.
2.5 Imports vs. Indigenous production
Not Applicable as the project is Holistic Development of Surat Airport Including
Extension of Terminal Building, Apron and Construction of Parallel Taxi Track.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
2.6 Export Possibility
Not Applicable as the project is Holistic Development of Surat Airport Including
Extension of Terminal Building, Apron and Construction of Parallel Taxi Track.
2.7 Domestic/ export Markets
Not Applicable as the project is Holistic Development of Surat Airport Including
Extension of Terminal Building, Apron and Construction of Parallel Taxi Track.
2.8 Employment Generation (Direct and Indirect) due to the project
The proposed project will provide direct employment during construction & operation
phase. Local workers will be hired from the nearby areas during construction
phase/workers will be sourced by construction contractor. While during the project
operation stage for the purposes of day-today professional and maintenance works,
additional staff will be required.
*********
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PROJECT DESCRIPTION
3.1 Type of Project:
AAI is planning the Holistic Development of Surat Airport Including Extension of
Terminal Building, Apron and Construction of Parallel Taxi Track.
Project falls under Category “A”, under schedule „7(a)‟ of EIA Notification dated 14th
September, 2006 & amendment made thereafter.
3.2 Location:
The project is situated at Surat - Dumas Rd, near, Magdalla, Gujarat. The airports
reference point is located at latitude 21°06'58'' N and longitude 72°44'31'' E. The Google
map is given in Figure.
Figure: Google Map
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Surat Airport Environmental Setting:
S. No Particulars Details
1. Present Land use at Airport Commercial
2. Nearest Highway/Major Road SH-168: Adjacent to the Airport Boundary
SH-197: 13.0 km towards NNE
SH-170: 12 0km towards ENE
NH-6: 9.2 km towards W
SH-169: 13.9 km towards NNE
3. Nearest Railway Station Surat Railway Station : 14.0 km towards NE
4. Nearest Town/village Daman Airport : 76.0 km towards S
Bhavnagar Airport : 91.2 km towards NW
Vadodara Airport : 144 km towards NNE
5. Seismic Zone Zone III (Moderate Seismic Hazard)
3.3 Details of alternative site:
The proposed project involves Holistic Development of Surat Airport Including
Extension of Terminal Building, Apron and Construction of Parallel Taxi Track. The
construction work will be done in the land abutting the existing airport. Hence, no
alternative sites have been explored.
3.4 Size or magnitude of operation:
Surat Airport is spread over an area of 784.37 Acres. The proposal involves extension of
centrally air-conditioned two level Terminal Building of modular design with all modern
facilities and amenities as per the conceptual layout plan enclosed. The existing terminal
building is capable to handle 250 passengers per hour at Arrival Lounge & 250
passengers per hour at Departure Lounge. The area earmarked for the proposed extension
of terminal building is about 17,035 m2, for Apron (including Shoulder, GSE & Shoulder
converted to apron) is 34,940 m2 and for construction of Parallel Taxi Track (including
Shoulder) is 91,535 m2 within the existing airport premises. There is no additional
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
requirement of land for the proposed developmental works. The construction work will
be done in the land abutting the existing airport.
3.5 Project Description with process details
Details of proposed Facility are as under:
S No. Description Details
1. Project cost Rs. 353.25 Cr.
2. Location Latitude: 21° 7' 3.57" N
Longitude: 72° 44' 42.93" E
3. Plot area 106770 sq. m.
4. Ground Coverage (achieved) 13710 sq. m. (12.9 %)
(Terminal + Canteen + ESS)
5. Total Built Up Area 26250 sq. m. (25520 m2 + 130 m
2 + 600m
2)
6. Green Area 35950 sq. m. (33.7 %)
7. Road and Open Area (excluding surface parking
area)
41385 sq. m. (38.7 %)
8. Surface parking Area 15725 sq. m. (14.7 %)
9. No. of Floors G +1
10. Height of Building 17.8 m
11. Area of Apron ((including Shoulder, GSE &
Shoulder converted to apron )
34940 sq. m.
12. Parallel Taxi Track Area (including Shoulder) 91535 sq. m.
13. Water demand 531 KLD (Domestic)
14. Power requirement Connected Load:-
(Existing : 2000 KW; Proposed : 2045 KW)
Maximum Demand:-
(Existing : 1016 KW; Proposed : Not Avail)
Transformer:-
(Existing: 3x500 kVA; Proposed : 3x1600
kVA)
15. Back up source Existing:- 3x 250 kVA
Proposed:- 3x 1000 kVA
16. Renewable Source of Energy (Solar) 200 KW Solar Power Systems
17. Solid waste generation 1414 kg/day
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Fig: Site Layout Plan of Terminal Buildings
Fig: Layout Plan of Apron
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
3.6 Raw Material required (Quantity & Source), Product & Mode of Transport:
Airport being a service industry doesn‟t process any raw material or deal in production
of products. The proposed project is Holistic Development of Surat Airport Including
Extension of Terminal Building, Apron and Construction of Parallel Taxi Track which
requires general construction materials viz. sand, aggregates, bricks, etc. will be used for
infrastructure (roads, service areas, buildings) development. The raw materials will be
procured from nearby markets as per requirements and transportation facilities will be
provided by construction contractor.
3.7 Resource optimization/recycling & Reuse envisaged in the Project:
The resource optimization is always pre-requisite for any development project. In quest
towards resource optimization in proposed project, the tradition practices are substituted by
modern practices involving water reduction, rain water harvesting, energy conservation etc.
As per the NBC, 2016, the per capita water requirement varies with building type. Measures
have been proposed to reduce the consumption of fresh water through efficient practices and
devices. Some of these practices include:
Regulating flow rate of fixtures used in toilets.
Dual plumbing system
By installations of sensor-based urinals such as magic eye sensor, the water use is
reduced to 0.4 liters per flush.
A normal tap works at a flow rate as high as 20 lpm. Use of low flow faucets along
with other water saving devices such as auto control valves, pressure reducing
devices, aerators and pressure inhibitors for constant flow, magic eye solenoid valve,
and self-operating valves can result in 25 – 50% of water savings.
Rainwater harvesting for ground water recharge.
AAI is following GRIHA (Green Rating for Integrated Habitat Assessment) system for
sustainable and environment friendly design. All the new buildings will be constructed as
per the ECBC (Energy Conservation Building Code) norms and obtain 4 star GRIHA rating.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
3.8 Availability of Water, Energy / Power Requirement & Source:
3.8.1 Population :
S.No. Description Total Population
2031-2032
Total Population
(Total annual passenger
traffic/365)
1 Terminal Building (Passenger Load) 2.6 MPPA 7123
2 Permanent Terminal Building Population
(AAI Staffs)
250
3 Permanent Terminal Building Population
(Food Courts & Other facilities)
200
4 Visitors 712
3.8.2 Water requirement:
The daily consumption of water in Terminal Building during operation phase for
domestic use will be about 531 KLD out of which 301 KLD will be fresh water and 230
KLD will be recycled/treated water. The water requirement for Landscaping, HVAC &
DG cooling will be about 250 KLD (treated water). The water will be met through Surat
Municipal Corporation (SMC) water supply. The details of water requirement and
wastewater generation for operation phase are as follows:
A. Construction phase:
Domestic Water
Domestic water during construction phase for approx 100 nos. of workers will be 5
KLD, which will be met through the construction contractor / from the supply line of
SMC as specified in the contract award. The potable water supplied for construction
workers will be treated to meet the potable water specification by the contractor as per
SMC water quality norms / IS10500. Domestic wastewater will be generated, collected
and retained in the bio toilets provided by construction contractor.
B. Operational Phase:
S. No. Particulars Population Fresh water demand Treated water demand Total water demand
1. Passengers 7123 @40 lpcd: 285 KLD @30 lpcd: 214 KLD 499 KLD
2. Visitors 712 @5 lpcd: 4 KLD @10 lpcd: 7 KLD 11 KLD
3. Airport Staffs 250 @25 lpcd: 7 KLD @20 lpcd: 5 KLD 12 KLD
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
4. Food Courts &
Other facilities
200 @25 lpcd: 5 KLD @10 lpcd: 2 KLD 7 KLD
5. HVAC & DG @10 L/TR for 24 hrs : 216 KLD &
@0.9*3000kVA*6hrs : 16 KLD
(232 KL One Time Requirement
and 70 KLD Daily requirement)
70 KLD 70 KLD
6. Landscaping 35950 m2 (@ 5 ltr/sq.m.) 180 KLD 180 KLD
Total -- 301 KLD 478 KLD 779 KLD
Source: NBC 2016
Water Balance
Fresh water
301 KLD
Passengers
301 KLD
STP treated
water
478 KLD
481 KLD
Waste water
S
T
P
Capacity
600 KLD
Sludge &
evaporation
losses
48 KLD
Recycled/ reused for flushing, landscaping
Daily water demand: 779 KLD
{301 KLD (fresh) + 478 KLD (recycled/ reused water)}
HVAC & DG Cooling
232 KL
240KLD
Food Court
5 KLD
Landscape
180 KLD
9 KLD
228 KLDFlushing
228 KLD
Treated water from
SMC
45 KLD
162 KLD Re-circulated
70 KLD
433 KLD
Airport Staff & Visitors
11 KLD
4 KLD
3.8.3 Power Demand
The total Connected load is (Existing : 2000 KW; Proposed : 2045 KW) and Maximum
Demand:- (Existing : 1016 KW; Proposed : Not Available) at Surat Airport, Surat. The
power supply shall be drawn from existing Torrent Power supply.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
There will be power backup through DG sets of capacity of 1000 kVA (3 nos.) used in
case of power cut or failure. DG set will be provided with an effective safe stack height
for proper dispersion of pollutants that will keep the emissions within the permissible
limit. The fuel required will be HSD (as and when used).
Renewable source of energy in the form of solar will be proposed as per ECBC, 2017 &
Gujarat building Bye Laws 5% of connected load (4045 KW) i.e, 200 KW solar PV
power plant will be established to generate solar power.
3.7.4 STORM WATER MANAGEMENT:
Construction phase
Contaminant Sources Impact Mitigation
Sediment &
Floatables
Streets, lawns, driveways,
roads, construction
activities,
During construction, sediment fencing or other erosion
control devices will be used to mitigate the short-term
adverse impacts of sedimentation.
Oil & Grease Roads, driveways, parking
lots etc.
Oil & Grease trap will be provided to remove oil &
grease, suspended matter, and ensure the quality of water.
Storm water control and rain water harvesting will be done as per the standards laid
down by CGWA & BIS. Following measure will be adopted for the same:
Construction Sequencing: Construction sequencing (involves disturbing only part of a
site at a time to prevent erosion from dormant parts) has been done at site. Grading
activities and construction are completed and soils are effectively stabilized on one part
of the site before grading and construction commence at another part.
Compost Blankets: A compost blanket is a layer of loosely applied composted material
placed on the soil in disturbed areas to reduce storm water runoff and erosion. This
material fills in small rills and voids to limit channelized flow, provides a more
permeable surface to facilitate storm water infiltration, and promotes re-vegetation.
Post Construction Phase:
a. Design:
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
For good design of rainwater harvesting, following points are to be kept under
consideration:
Ideal location with good ground slope.
The location has adequate subsurface permeability of the aquifer to accommodate
maximum recharge of rainwater through injection well.
Rate of filtration should exceed average rainfall intensity.
Clogging of filtration media should be cleaned periodically.
Ground water pollution does not take place.
b. Baseline:
The average annual rainfall (based on last 5 years rainfall data) at Surat station is 1808
mm.
Rain Fall Data (last 5 years):
S. No. Year Annual Average Rainfall
1 2017 1243.7
2 2016 1093.3
3 2015 899.9
4 2014 849.5
5 2013 1958
Total 6044.4 say 6044
Average 1208.8 say 1208
Source: IMD, Surat
c. Calculation of No. of RWH Structures:
The rain water harvesting structures are calculated on the basis of peak intensity of
rainfall recorded as 40 mm/hr considering 15 minutes of peak rainfall. The same has
been done to avoid flooding of the area.
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall
(m/hour) [I]
Total Recharge
[Q = CIA]
(m3/hr)
1. Roof Top 13710 0.85 0.04 466.14
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
2. Landscape 35950 0.15 0.04 215.70
3. Road, Open &Paved area 57110 0.65 0.04 1484.86
Grand Total (1-3) 141365 2166.70
Total Rain Water Flow : 2166.70 m3/hr
Considering 15 minutes of peak rainfall,
Runoff volume : 541.67 m3/hr
Volume of each pit : 100 m3 (5 m x 5 m x 4.5 m)
Total no. of rain water harvesting pits required : Total run-off volume/volume of each pit
: 541.67/112.5
: 4.81 say 5 nos.
Therefore, 5 Nos. rain Water Harvesting pit of size 5 m length x 5 m width x 4.5 m depth
with PVC slotted pipe upto minimum depth of 20 m.
d. Design of Rain Water Harvesting Structure:
The dimensional parameters of Desilting/Settlement chamber would be 3 m (length) x 3
m (width) x 1.30 (depth). In Desilting chamber, 0.30 m depth below outflow is kept for
silt deposition. The filtration tank dimension would be 3 m (length) x 3 m (width) x 1 m
(depth) with 0.15 m dia recharge well of 30 m depth depending upon the formation for
recharge in aquifer through vadose zone.
e. Calculation of annual recharge:
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall [I]
(m/annum)
Total Recharge
[Q= CIA]
(m3/ annum)
1. Roof Top 13710 0.85 1.208 14077.43
2. Landscape 35950 0.15 1.208 6514.14
3. Paved area 57110 0.65 1.208 44842.77
Grand Total (1-3) 106770 65434.34
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting
structure would be 65434.34 m3/ annum.
3.9 Waste Generation & Management
Solid Waste management:
Solid waste generated from the airport mainly comprises of food waste and garbage
waste. Further, small quantities of sludge from STP and other waste are being generated.
The solid waste generated will be first segregated as plastic, glass, paper, and other waste
separately and disposed off as per applicable Rules.
Solid Waste Calculation:
Particulars Population Basis Quantity of waste generated (in kg/day)
Passengers 7123 @0.15 kg/day 1068
Visitors 712 @0.12 kg/day 85.44
Airport Staffs 250 @0.3 kg/day 75
Food Courts &
Other facilities
200 @0.20 kg/day 40
Waste From Aircraft 48 @3 kg/Aircraft 144
Landscaping 8.88 acres @0.2kg/acre/day 1.77
Total 1414.21 Say 1414 kg/day
*Source: NBC 2016
Break Up of Residential Solid Waste:-
Particulars Quantity (kg/day) % Percentage
Biodegradable 671 47.43
Paper 115 8.13
Plastic/rubber 143 9.22
Metal 7 0.5
Glass 1 0.01
Rags 64 4.49
Other 57 4.02
Inerts 356 25.16
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Total 1414 100
Source: Municipal Solid Waste Management Manual-Part-II, CPHEEEO, MOUD, 2016
Bins Particulars Treatment Disposal
Green Compostable waste Collected in green colored bins and sent
to the SMC
Will be sent to municipality
disposal site
White Dry/ recyclable
waste:
No in-situ treatment.
Collected in white colored bins and sent
to solid waste collection point. Segregated waste will be
handed over to authorized
waste pickers or waste
collectors.
Black Other waste/
Domestic hazardous
waste
No in-situ treatment.
Collected in Black colored bins and
sent to solid waste collection point
Source: Municipal Solid Waste Management Manual, CPHEEEO, MOUD, 2016
Waste water treatment & management:
During operation phase, wastewater generated from Airport premises will be treated in
Sewage Treatment Plant (STP) comprising primary, secondary and tertiary treatment
facilities.
3.10 Schematic representations of the Feasibility drawing which give information of
EIA purpose:
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Fig: Master Plan of Surat International Airport, Surat
*************
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
SITE ANALYSIS
Introduction:
Site analysis is a pre-design research activity which focuses on existing and potential
conditions on and around the building site. It is an inventory of the site factors and
forces, and how they coexist and interact. The purpose of the analysis is to provide
thorough information about the site assets and liabilities prior to starting the design
process. The typical site analysis includes the site location and size, neighborhood
context, zoning, legal aspects, geology, physiographic (natural and man-made
features), hydrology, soils, vegetation, wildlife, climate, culture, pedestrian and
vehicular circulation, access, utilities, historic factors, density, sensory stimuli, and
any other factor deemed appropriate for the particular site. This chapter discusses the
site Profile, landform, and existing land use and drainage pattern. The land details,
climate and meteorological parameters are also described in various sections of this
chapter
4.1 Connectivity:
Surat Airport (IATA: STV, ICAO: VASU) is an International airport located in
Magdalla, Surat in the western Indian state of Gujarat with a total area of 784.37
Acres. It is the second busiest airport in Gujarat after Ahmedabad in terms of both
aircraft movements and passenger traffic.
Particular Details
Nearest Highway/Major Road, SH-168: Adjacent to the Airport Boundary
SH-197: 13.0 km towards NNE
SH-170: 12 0km towards ENE
NH-6: 9.2 km towards W
SH-169: 13.9 km towards NNE
Railway Station Surat Railway Station : 14.0 km towards NE
Public Transport
Plenty of tourist buses, taxis and luxury coaches are available
to and from important cities of the state and that of the
country.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
4.2 Land Form, Land Use & Land Ownership
Presently, the airport is situated on 784.37 Acres. The new airport terminal was
inaugurated in the year 2009 and licensed by the DGCA as aerodrome for public use in
2011 as per the ICAO guidelines. Air India, the National carrier had started its
operation since May, 2007 and remained the sole service provider to STV, until
February, 2012. The land ownership of 784.37 Acres is reserved with Airport Authority of
India.
4.3 Topography
Geomorphologically the district can be divided into two zones, the major portion of it
forms a flat planar topography except for a few rocky features in the extreme southern
portion.
Source: http://en-in.topographic-map.com/places/Ahmedabad-7809992
Fig: Topographical Map of Surat Airport, Surat
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
4.4 Existing Land use Pattern
The land use pattern of the existing airport remains same. The Holistic Development
of Surat Airport Including Extension of Terminal Building, Apron and Construction
of Parallel Taxi Track will be converted into commercial category.
4.5 Existing Infrastructure of Site
Existing infrastructure details are given in Section-2.1.
4.6 Soil Classification
The basaltic lava flows are covered by black clayey to loamy soil. It is in general
ranges in thickness up to one meter. The colour of the soil turns brown due to high
iron content at places. In the piedmont slope area the soil is shallow to moderately
deep, moderate to severely eroded and non calcareous in nature. The texture is silt
clay loam to clay loams. The clay content varies from 30 to 60%. The water holding
capacity of the soil is moderate. In the midland and flood plain areas, the soil is deep
to very deep, light greyish to yellowish brown in colour. The texture is fine clay loam
to sandy loam. The clay content varies from 25 to 60%. In coastal region the soil is
deep to very deep dark grey to black colour. The texture is clay loam to silty loam.
The area is affected by tide as well as leaching of salts from up land forming saline
alkali soils. The content of clay in this is high and permeability is low (mud flats).
(Source:- Ground Water Brochure Surat District Gujarat &
http://www.gujenvis.nic.in/PDF/soil.pdf)
4.7 Climate Data from Secondary Sources
General climate of the district is sub-tropical and is characterised by three well-
defined seasons, i.e. summer - from April to June, monsoon - from July to September,
and winter - from October to March.
Long term normal rainfall (1951-80) for the SURAT IMD station is about 1210 mm
for stations monitored by Govt. of Gujarat. The rainfall data for other stations falling
in the district is available for the period between 1963 to 2012. It is seen that the
average annual rainfall varies between 901.29 mm at Olpad and 1483.3.mm at
Mahuva. The minimum recorded rainfall during these years varied between 378 mm
(Bardoli -1996) and 542 mm (Mahuva –2011). The maximum recorded rainfall varied
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
from 1939 mm (Olpad –1976) to 3529 mm (Mahuva –1970). The Statistical Analysis
of Rainfall Data (1963-2008)
(Source: Ground Water Brochure Surat District Gujarat).
4.8 Social Infrastructure Available
The existing social infrastructure in the Surat which is located at about 10 km from
the airport are:
Hospital with ambulance;
Banks;
Post office;
Bus station;
Fire station;
Secondary school;
Police station;
Shopping complex;
Sports infrastructure (Stadium & Camps etc);
Community halls;
Cinema halls; and
Primary health care centers
**************
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PLANNING BRIEF
5.1 Planning Concept
This is a planned airport development project to cater aviation demand as per Master Plan.
The Holistic Development of Surat Airport Including Extension of Terminal Building, Apron
and Construction of Parallel Taxi Track is proposed. Other facilities such as power,
transportation and communication, social infrastructure facilities are already available at
project site as the proposed project lies within Surat Airport, Surat.
5.2 Population Projection
As per current traffic data, the Surat Airport handled 681465 passengers in 2017-18. The
airport is expected to handle 2.6 Million passengers by 2031-32.
5.3 Land use planning
Land use has been categorized based on the following functional groups:
Airfield Dependent: Land uses with the highest location and area priority include those that
are fully within the airfield, or overlapping the airside-landside boundary.
Airport Supporting: Land uses with functional priority include those that are required for
the airport to function. Their location may be on the airside or landside but preferably within
the airport boundary.
Commercial: Land uses that are fully provide non-aviation revenues. These uses have
flexibility of location but should not interfere with the functional operation of Airfield
Dependent or Airport Supporting Land Uses.
Infrastructure & Open Space: These land use areas are determined by the needs of all the
land uses above. Since supporting infrastructure must be within the development areas the
first three groups determine the area required for this group. Open space includes those areas
remaining which cannot be developed.
5.4 Assessment of Infrastructure Demand (Physical & Social)
Social Demand
On the basis of the preliminary site visit, the infrastructure demand in the nearby area is
assessed on the basis of need and priority:
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
The assessment will be identified in the socio economic survey, after the grant of TOR and
will be submitted at the time of final presentation regarding Environmental Clearance.
Physical infrastructure
Physical infrastructure is an important aspect of the site. It determines the quality of life to a
large extent. Physical infrastructure deals with:
Water supply
Electricity
Waste management & treatment
Water supply
The daily consumption of water in Terminal Building during operation phase for domestic
use will be about 531 KLD out of which 301 KLD will be fresh water and 230 KLD will be
recycled/treated water. The water requirement for Landscaping, HVAC & DG cooling will be
about 250 KLD (treated water). The water will be met through Surat Municipal Corporation
(SMC) water supply.
Electricity
The total Connected load is (Existing : 2000 KW; Proposed : 2045 KW) and Maximum Demand:-
(Existing : 1016 KW; Proposed : Not Available) at Surat Airport, Surat. The power supply shall
be drawn from existing Torrent Power supply.
There will be power backup through DG sets of capacity of 1000 kVA (3 nos.) used in case
of power cut or failure. DG set will be provided with an effective safe stack height for proper
dispersion of pollutants that will keep the emissions within the permissible limit. The fuel
required will be HSD (as and when used).
Renewable source of energy in the form of solar will be proposed as per ECBC, 2017 &
Gujarat building Bye Laws 5% of connected load (4045 KW) i.e, 200 KW solar PV power
plant will be established to generate solar power.
Solid Waste management:
Solid waste generated from the airport mainly comprises of food waste and garbage waste.
Further, small quantities of sludge from STP and other waste are being generated. Collection
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
and handling of domestic solid waste is being done in line with the provisions of the Solid
Waste Management Rules 2016.
Waste water treatment & management:
During operation phase, wastewater generated from Surat Airport will be treated in Sewage
Treatment Plant (STP) comprising primary, secondary and tertiary treatment facilities.
5.5 Amenities/Facilities
The following facilities will be available in the airport premises
Baggage handling system
Passenger boarding bridges
Flight information and displays
Sewage treatment facility
Fire fighting system
Security equipments
Restaurant
*********
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PROPOSED INFRASTRUCTURE
6.1 Industrial Area (processing area)
Surat Airport is spread over an area of 784.37Acres. Airports Authority of India (AAI)
Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track. The area earmarked for the proposed extension of
Terminal Building is about 17,035 m2, for Apron (including Shoulder, GSE & Shoulder
converted to apron) is 34,940 m2 and for construction of Parallel Taxi Track (including
Shoulder) is 91,535 m2 within the existing airport premises. The total Built-up area envisaged
for the proposed terminal Building will be 26250.00 m2.
The Brief details are as under:
S No. Description Details
1. Project cost Rs. 353.25 Cr.
2. Location Latitude: 21° 7' 3.57" N
Longitude: 72° 44' 42.93" E
3. Plot area 106770 sq. m.
4. Ground Coverage (achieved) 13710 sq. m. (12.9 %)
(Terminal + Canteen + ESS)
5. Total Built Up Area 26250 sq. m. (25520 m2 + 130 m
2 + 600m
2)
6. Green Area 35950 sq. m. (33.7 %)
7. Road and Open Area (excluding surface
parking area)
41385 sq. m. (38.7 %)
8. Surface parking Area 15725 sq. m. (14.7 %)
9. No. of Floors G +1
10. Height of Building 17.8 m
11. Area of Apron ((including Shoulder, GSE
& Shoulder converted to apron )
34940 sq. m.
12. Parallel Taxi Track Area (including
Shoulder)
91535 sq. m.
13. Water demand 531 KLD (Domestic)
14. Power requirement Connected Load:-
(Existing : 2000 KW; Proposed : 2045 KW)
Maximum Demand:-
(Existing : 1016 KW; Proposed : Not Available)
Transformer:-
(Existing: 3x500 kVA; Proposed : 3x1600 kVA)
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
15. Back up source Existing:- 3x 250 kVA
Proposed:- 3x 1000 kVA
16. Renewable Source of Energy (Solar) 200 KW Solar Power Systems
17. Solid waste generation 1414 kg/day
6.2 Residential Area (non-processing area)
Not Applicable as the project is Holistic Development of Surat Airport Including Extension
of Terminal Building, Apron and Construction of Parallel Taxi Track.
6.3 Green Belt
Approximately 35950 sq. m. (33.7 %) of the total project area will be under green belt and
plantation. Entire landscaping is irrigated with treated waste water having automatic water
efficient water dispensing system.
6.4 Social Infrastructure
The proposed infrastructure will be identified in the socio-economic survey, after the grant of
ToR and will be submitted at the time of final presentation regarding Environmental
Clearance.
6.5 Connectivity
Surat Airport (IATA: STV, ICAO: VASU) is an International airport located in Magdalla,
Surat in the western Indian state of Gujarat with a total area of 784.37 Acres. It is the second
busiest airport in Gujarat after Ahmedabad in terms of both aircraft movements and
passenger traffic. The connectivity details are as below:
Particular Details
Nearest Highway/Major Road, SH-168: Adjacent to the Airport Boundary
SH-197: 13.0 km towards NNE
SH-170: 12 0km towards ENE
NH-6: 9.2 km towards W
SH-169: 13.9 km towards NNE
Railway Station Surat Railway Station : 14.0 km towards NE
Public Transport
Plenty of tourist buses, taxis and luxury coaches are available
to and from important cities of the state and that of the
country.
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
6.6 Drinking Water Management (Source & Supply of Water)
The daily consumption of water in Terminal Building during operation phase for domestic
use will be about 531 KLD out of which 301 KLD will be fresh water and 230 KLD will be
recycled/treated water. The water requirement for Landscaping, HVAC & DG cooling will be
about 250 KLD (treated water). The water will be met through Surat Municipal Corporation
(SMC) water supply.
6.7 Sewerage System
As per water balance diagram, 577.2 KLD sewage will be generated after the proposed
development at Surat Airport which will be treated in STP of 600 KLD capacity.
6.8 Industrial Waste Management
No Industrial waste will be generated from the project.
6.9 Solid waste Management
Solid waste generated from the airport mainly comprises of food waste and garbage waste.
Further, small quantities of sludge from STP and other waste are being generated. Collection
and handling of domestic solid waste is being done in line with the provisions of the Solid
Waste Management Rules 2016.
6.10 Waste water treatment & management
During operation phase, wastewater generated from Airport will be treated in Sewage
Treatment Plant (STP) comprising primary, secondary and tertiary treatment facilities. The
treated wastewater from the STP will be used for flushing, landscaping and HVAC & DG
cooling.
6.11 Power Requirement & Supply/ Source
The total Connected load is (Existing : 2000 KW; Proposed : 2045 KW) and Maximum
Demand:- (Existing : 1016 KW; Proposed : Not Avail) at Surat Airport, Surat. The power
supply shall be drawn from existing Torrent Power supply.
There will be power backup through DG sets of capacity of 1000 kVA (3 nos.) used in case
of power cut or failure. DG set will be provided with an effective safe stack height for proper
dispersion of pollutants that will keep the emissions within the permissible limit. The fuel
required will be HSD (as and when used).
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Renewable source of energy in the form of solar will be proposed as per ECBC, 2017 &
Gujarat building Bye Laws 5% of connected load (4045 KW) i.e, 200 KW solar PV power
plant will be established to generate solar power.
**************
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
REHABILITATION & RESETTLEMENT (R&R) PLAN
7.1. Rehabilitation & Resettlement (R&R) Plan
Introduction:
Airport Authority of India (AAI) proposes Holistic Development of Surat Airport Including
Extension of Terminal Building, Apron and Construction of Parallel Taxi Track. Surat
Airport is spread over an area of 784.37 Acres. Airports Authority of India (AAI) Holistic
Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track. The area earmarked for the proposed extension of
terminal building is about 17,035 m2, for Apron (including Shoulder, GSE & Shoulder
converted to apron) is 34,940 m2 and for construction of Parallel Taxi Track (including
Shoulder) is 91,535 m2 within the existing airport premises. The total Built-up area envisaged
for the proposed terminal Building will be 26,250.00 m2. The land ownership of is reserved
with Airport Authority of India.
Therefore Rehabilitation and Resettlement (R&R) is not applicable for proposed project.
************
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PROJECT SCHEDULE & COST ESTIMATES
8.1 Likely Date of Start of Construction and Likely Date of Completion
Development/Construction Work shall be started after grant of Environment Clearance from
MoEFCC and consents from GSPCB.
8.2 Project Cost Estimation
Estimated cost of work for Holistic Development of Surat Airport Including Extension of
Terminal Building, Apron and Construction of Parallel Taxi Track & allied works is worked
out to be Rs. 353.25 Crores.
*************
Project : Holistic Development of Surat Airport Including Extension of Terminal Building, Apron and
Construction of Parallel Taxi Track PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
ANALYSIS OF PROPOSAL
9.1. Analysis of the Proposal
The present proposal of Holistic Development of Surat Airport Including Extension of
Terminal Building, Apron and Construction of Parallel Taxi Track. Improvements in
connectivity will effectively contribute to the economic performance of the wider economy
through enhancing its overall level of productivity. The project will boast economic
growth benefitting the whole region through the generation of both direct and indirect
economic value. Airport operations will have a considerable economic and social
impact in surrounding regions.
These benefits extend far beyond the direct effect of an airport’s operation on its
community development to the wider benefits that air service accessibility brings to
business interests and to consumers. The construction and operation of airport will
generate direct employment opportunity, indirectly contributed jobs through supply
chain, enhance induced impact through tourism. Thus the project will prove beneficial
to the area.
.
*********