    27thFebruary 2012The Project Manager,

    Ministry of Public Works,

    P.o box 30743 - 00100,

    Nairobi

    REF: COMPLETION OF MEDICAL TRAINING CENTREAT KABARNET:VARIATIONS AND RATES ADJUSTMENT

    W.P. ITEM NO. D11 RV/BRD 002-JOB NO. 1477J

    The above refers.

    In line with Clause 21.2, we wish the Project Manager to adjust the rates for items

    where the quantity of work done has varied by 25% as the change exceeds 1% of

    the Contract Price.

    Please find our variations valuation for both Tuition Block and Administration

    Block for Kenya Shillings Twenty Nine Million, Five Hundred and Sixty NineThousands, Six Hundred and Ninety Six Only (Kshs.29,569,696.00) for

    processing as payment.

    Your cooperation and swift action is highly appreciated. Thanks in advance

    Qs. Nahinga David

    For: Director

    Spion Construction CompanyCc: Chief Quantity Surveyor

  • 8/13/2019 Excavations in Rock Kabarnet

    2/4

    2

    COMPUTAION OF VARIATIONS IN SUBSTRUCTURE WORKS(TUITION AND ADMINISTRATION BLOCKS)

    Preamble: The Contract Bills of Quantities provided for excavation in red soil

    on Page ADM/1 and TB/1. However, the excavation to reduce levels and

    excavation to receive column bases and strip footings was in hard rock and soft

    rock respectively.

    In this regard, we seek to confirm the following:-

    (i) The volume for excavating surfaces to reduce levels not exceeding300mm in soft rock is 49.42m by 43.89m = 2,169.04 square metres. The

    excavation extended to the parking lot, an area of 553.06 square metres

    (ii) The rates provided in the Bills of Quantity are for excavating in red soil.The actual case is excavating in hard and soft rock.

    (iii) The excavation in hard rock to receive column bases varies from thedescription which provided for excavation in red soil.

    (iv) The proposed site for the administration and tuition blocks was on asloppy location calling for substantive excavations exceedingprovisions in the Bills of Quantity by percentages tabulated below.

    (v) The Contract provides in Clause 21.2 that:If the final quantity of the work done differs from the quantity in

    the Bills of Quantities for the particular item by 25% and provided

    the change exceeds 1% of the initial Contract Price, the Project

    Manager shall adjust the rate to allow for the change

    (vi) For purposes of Clause 21.2, 1% of the Contract Price is Kshs.2,671,414.00

    Attached are the site re-measurements and corresponding claims for payment.

  • 8/13/2019 Excavations in Rock Kabarnet

    3/4

    3

    Description Provision

    in BoQ

    (Red soil)

    SiteRe-measurements

    (Rock)

    Contract

    Rate

    Revised

    Rate

    Amount

    Due

    Excavate

    surfaces to

    reduce levels

    Item

    ADM/1/B +

    TB/1/B

    1874sm

    (112,440)

    (49.42 x 43.89)

    +(12.6 x 43.89)

    2722 sm

    150 400.00 1,088,806

    Excavate0.00-1.50m

    deep starting

    from

    reduced

    level in hard

    rock for

    foundations

    ItemADM/D +

    TB/1

    1249 cm

    (187,350)

    1,314 cm 150 2,000.00 2,628,000

    Ditto for

    ColumnBases

    Item TB/1F

    + ADM/1/F824 cm

    (123,600)

    1071 cm 150 2,000.00 2,142,000

    Extra over

    for

    excavating

    in soft rock

    Item

    TB/1/H +

    ADM/1/H

    146 cm

    (219,000)

    1,633.46 cm 1500 2,000.00 3,266,920

    Extra over

    for

    excavating

    in hard black

    trap rock

    Item TB/1/J

    + ADM/1/J

    739 cm

    (110,850)

    5,480.64 cm 1500 3,000.00 16,441,920

  • 8/13/2019 Excavations in Rock Kabarnet

    4/4

    4

    Description Provision

    in BoQ

    (Red soil)

    SiteRe-measurements

    (Rock)

    Contract

    Rate

    Revised

    Rate

    Amount

    Due

    Backfilling Item TB/1/L

    + ADM/1/L

    1,540cm

    (154,000)

    2034cm 100 300 610,200

    Load Wheel

    and cartaway

    surplus

    excavated

    material

    Item

    TB/2/A +ADM/2/A

    367 cm

    (91,750)

    5,467cm 250 500 2,733,500

    Change

    Column

    height

    tuition block

    from 2.85mto 3.60m

    Item

    TB/04/m

    15.0 CM

    (147,000)

    20 CM 9,800 9,800 196,000

    Ditto-

    Formwork

    Sides of

    Column

    TB/3/L 97

    SM

    (43,050)

    123 SM 350 350 43,050

    Re-fixing

    formwork to

    soffits of slab

    1198 SM 350 350 419,300

    TOTALS

    29,569,696