27thFebruary 2012The Project Manager,
Ministry of Public Works,
P.o box 30743 - 00100,
Nairobi
REF: COMPLETION OF MEDICAL TRAINING CENTREAT KABARNET:VARIATIONS AND RATES ADJUSTMENT
W.P. ITEM NO. D11 RV/BRD 002-JOB NO. 1477J
The above refers.
In line with Clause 21.2, we wish the Project Manager to adjust the rates for items
where the quantity of work done has varied by 25% as the change exceeds 1% of
the Contract Price.
Please find our variations valuation for both Tuition Block and Administration
Block for Kenya Shillings Twenty Nine Million, Five Hundred and Sixty NineThousands, Six Hundred and Ninety Six Only (Kshs.29,569,696.00) for
processing as payment.
Your cooperation and swift action is highly appreciated. Thanks in advance
Qs. Nahinga David
For: Director
Spion Construction CompanyCc: Chief Quantity Surveyor
-
8/13/2019 Excavations in Rock Kabarnet
2/4
2
COMPUTAION OF VARIATIONS IN SUBSTRUCTURE WORKS(TUITION AND ADMINISTRATION BLOCKS)
Preamble: The Contract Bills of Quantities provided for excavation in red soil
on Page ADM/1 and TB/1. However, the excavation to reduce levels and
excavation to receive column bases and strip footings was in hard rock and soft
rock respectively.
In this regard, we seek to confirm the following:-
(i) The volume for excavating surfaces to reduce levels not exceeding300mm in soft rock is 49.42m by 43.89m = 2,169.04 square metres. The
excavation extended to the parking lot, an area of 553.06 square metres
(ii) The rates provided in the Bills of Quantity are for excavating in red soil.The actual case is excavating in hard and soft rock.
(iii) The excavation in hard rock to receive column bases varies from thedescription which provided for excavation in red soil.
(iv) The proposed site for the administration and tuition blocks was on asloppy location calling for substantive excavations exceedingprovisions in the Bills of Quantity by percentages tabulated below.
(v) The Contract provides in Clause 21.2 that:If the final quantity of the work done differs from the quantity in
the Bills of Quantities for the particular item by 25% and provided
the change exceeds 1% of the initial Contract Price, the Project
Manager shall adjust the rate to allow for the change
(vi) For purposes of Clause 21.2, 1% of the Contract Price is Kshs.2,671,414.00
Attached are the site re-measurements and corresponding claims for payment.
-
8/13/2019 Excavations in Rock Kabarnet
3/4
3
Description Provision
in BoQ
(Red soil)
SiteRe-measurements
(Rock)
Contract
Rate
Revised
Rate
Amount
Due
Excavate
surfaces to
reduce levels
Item
ADM/1/B +
TB/1/B
1874sm
(112,440)
(49.42 x 43.89)
+(12.6 x 43.89)
2722 sm
150 400.00 1,088,806
Excavate0.00-1.50m
deep starting
from
reduced
level in hard
rock for
foundations
ItemADM/D +
TB/1
1249 cm
(187,350)
1,314 cm 150 2,000.00 2,628,000
Ditto for
ColumnBases
Item TB/1F
+ ADM/1/F824 cm
(123,600)
1071 cm 150 2,000.00 2,142,000
Extra over
for
excavating
in soft rock
Item
TB/1/H +
ADM/1/H
146 cm
(219,000)
1,633.46 cm 1500 2,000.00 3,266,920
Extra over
for
excavating
in hard black
trap rock
Item TB/1/J
+ ADM/1/J
739 cm
(110,850)
5,480.64 cm 1500 3,000.00 16,441,920
-
8/13/2019 Excavations in Rock Kabarnet
4/4
4
Description Provision
in BoQ
(Red soil)
SiteRe-measurements
(Rock)
Contract
Rate
Revised
Rate
Amount
Due
Backfilling Item TB/1/L
+ ADM/1/L
1,540cm
(154,000)
2034cm 100 300 610,200
Load Wheel
and cartaway
surplus
excavated
material
Item
TB/2/A +ADM/2/A
367 cm
(91,750)
5,467cm 250 500 2,733,500
Change
Column
height
tuition block
from 2.85mto 3.60m
Item
TB/04/m
15.0 CM
(147,000)
20 CM 9,800 9,800 196,000
Ditto-
Formwork
Sides of
Column
TB/3/L 97
SM
(43,050)
123 SM 350 350 43,050
Re-fixing
formwork to
soffits of slab
1198 SM 350 350 419,300
TOTALS
29,569,696