EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and...
-
Upload
cory-williams -
Category
Documents
-
view
258 -
download
0
Transcript of EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and...
EXCAVATIONEXCAVATION
ExcavationExcavation activity involves use of manual
and mechanical means and interaction of both. Hence, safety aspect to plan involvement and inter action of the same:
Individual ExcavationDeep ExcavationExcavation of TrenchesCannal Excavation
Topic that will be dealt with
Hazards of ExcavationRemedial measuresInspectionsEmergency Response
Collapse of shoring
Falling loads
Excavation hazards
Slip & fall of workmen
Underground utilities
…..Excavation hazards
Vehicular traffic
Adjacent structures
…..Excavation hazards
Access / Egress
Mobile equipment.
…..Excavation hazards
Cave-in / Soil collapse
Improper shoring.
…..Excavation hazards
Excavation HazardsTo sum it up …….
• Cave -in / Soil Collapse•Utilities•Hazardous atmospheres•Adjacent structures•Falling loads•Access/Egress•Vehicle traffic•Mobile equipment
Before going down, check & sides are properly shored.
Inspect for proper shoring
Remedial measures
When working inside trench, location of safe exit to be ascertained.
If you notice any shift in position,stop and investigate.
…..Remedial measures
Use a proper means of access to cross a trench
Barricade the opening
…..Remedial measures
Proper shoring / Benching
During excavation ladder shallbe provided for access / egress.
…..Remedial measures
Use Gumboot while workinginside a trench
…..Remedial measures
Usage of stop blocks to prevent vehicle fall inside a trench
So what should be done prior to Excavation
Check for…..
Soil type & Ground condition
Ground / Surface Water / Water table
Under ground / Overhead utilities
Adjacent buildings
Dynamic (Traffic) load
Preventing Soil Collapse• Soil Classification determines construction
of protective system:
Sloping or benchingShoring
•Timber / Aluminum shoring•Sheet piling
Placing shield between the side of the excavation & the work area.Underpinning
Water Accumulation
• Ground water
• Surface water
• Water table
Soil classification
• Type A - Cohesive soils– Clay, Sandy clay, silty clay, clay loam
• Type B - Cohesionless soils– Silt, Sandy loam, silt loam
• Type C - Water is freely seeping– Gravel, sand,
Types of Soil
• Loose soil like black cotton and sandy soil
• Stiff soil like murrum
• Rock Excavation
ANGLE OF REPOSE
Minimum angle of inclination for free standing soil face for stability
Simple Sloping -Type A Soil
Unsupported Vertically-Sided Lower Portion <12 ft
Unsupported Vertically-Sided Lower Portion <8 ft
Simple Sloping -Type A Soil
Supported or Shielded Vertically-Sided Lower Portion
Simple Sloping
• Type A - 3/4:1 530
• Type B - 1:1 450
• Type C - 1½ :1 340
Greater than 20 feet deep shall be designed
by a registered professional engineer.
Benching
Preventing Soil Collapse
SLOPE / SHORING
Above 5 ft. depth.
1M3 SOIL WEIGHS APP. 1.3 MT
Timber Shoring Installations
Refer to Design Engr.
UtilitiesUnderground Above ground
PERMIT SYSTEM
Hazardous Atmospheres
• Oxygen• CO
• H2S
• Petroleum• Other toxics
Access / Egress
– Ladders - @ every
30mts.
– Ramps
– Stairs cut on earth
STACKING OF MATERIAL ETC.
Other parameters……..
BARRICATION FENCINGILLUMINATION
Mobile Equipment
Vehicle Traffic
»Traffic Control»Traffic Safety Vests
Adjacent Structures
• Ensure structure stability– Shoring– Bracing– Evaluation by
Professional
Excavation Inspections
• Daily Inspections by Competent Person – Start of shift, as needed, following
rainstorms or other hazard-increasing event
• Possible cave-ins• Protective system failure• Water accumulation• Hazardous atmospheres
Excavation Rescue
• Initial Size-up – Type of incident?
• Cave-in, flooding, medical, fire, spill
– Injuries?• Number and type
– Missing personnel?– Chemical (or sewage)
exposures?– Safety of excavation for
rescuers?
Excavation Rescue
• Notify:– Field personnel– SSC = Emergency Coordinator– Fire Department– Police Department– Emergency Medical Services
(EMS)/Hospital
Excavation Rescue
• Stabilize cave-in• Control flooding• Hazardous
Atmospheres?– Ventilate– SCBA– Safety harness and
line– Basket stretcher
Excavation Rescue
DON’T ROLL THE DICE!!!
Excavation Rescues
• The best rescue is the one you never have to make!– Practice proper procedures
• Make sure everything is safe before anybody goes in!
ACCIDENT SUMMARY
Accident Type : Cave-inWeather Conditions : Cloudy and DryType of Operation : ExcavationWas the worksite Inspected Regularly : YesTraining and Education Provided : NoAge & Sex : 32-MaleExperience at this Type of Work : 9 MonthsTime on Project : 2 Weeks
BRIEF DESCRIPTION OF ACCIDENTWorkmen were laying sewer pipe in a trench 15 feet deep. The sides of the trench, 4 feetwide at the bottom and 15 feet wide at the top, were not shored or protected. Soil in thelower portion of the trench was mostly sand and gravel and the upper portion was clay andloam. The trench was not protected from vibration caused by heavy vehicle traffic on the
road nearby. To leave the trench, employees had to exit by climbing over the backfill. Asthey attempted to leave the trench, there was a small cave-in covering one employee to hisankles. When the other employee went to his co-worker's aid another cave-in occurredcovering him to his waist. The first employee died of a rupture of the right ventricle of hisheart at the scene of the cave-in. The other employee suffered a hip injury.