Example of CRE1 Miniproject Ver.2 Student Edition (1)

download Example of CRE1 Miniproject Ver.2 Student Edition (1)

of 31

Transcript of Example of CRE1 Miniproject Ver.2 Student Edition (1)

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    1/31

    Example of BKF2453 Integrated Miniproject: 50,000 Metric Tonnes per

    Annum Production of Cumene from Alkylation of Benzene

    Instruction

    The reaction stoichiometry undergoes as follows

    1.  C3H6  + C6H6  →  C9H12

    propylene (P) benzene (B) cumene (C)

    2. 

    C3H6  + C9H12  →  C12H18 

    P C p-diisopropyl benzene (PDIPB)

    and the reaction kinetics are based on the power law model

     =   (i)

     =   (ii)

    where both reaction rates are in kmol kgcat-1 s-1, C P is concentration of propylene in kmol m-

    3, C B is concentration of benzene in kmol m-3 and C C  is concentration of cumene in kmol m

    -3.

    The specific rate constants (m6 kgcat

    -1 kmol

    -1 s

    -1) are given by

     = � ∆   (iii)

     = � ∆

      (iv)

    Subscript numbers denote the number of reaction and the values of the parameters can be

    seen in Table 1

    Table 1: parameters of the reaction between from 300 – 350oC and 30 – 40 bar.

    Reaction  Ai  

    (m6 kgcat-1 kmol-1 s-1)

    ∆E i  (kJ kmol-1)

    1 3.5 x 104 -1.04 x 105

    2 2.9 x 106 -1.47 x 105

    The reaction occurs in gas phase with the feed of pure benzene liquid at 28 oC and 1 bar and

    the feed of propylene liquid at the same temperature and 12 bar (from the vapour pressure

    graph, the gaseous propylene liquefied at 10.17 bar for the temperature of 28oC). However

    propylene feed contains 4.8% propane (PA) which does not involve in any reaction with

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    2/31

    continuously as it will accumulate in the reactive unit. Thus, propylene will recycled

    internally and propane will be incinerated so as to generate steam for the process.

    The block flow diagram of the process proposed at level 2 can be seen in Figure 1. F  is molar

    rate of input, P  is molar flow rate of output for the respective components where,

    additionally, the subscript G denotes the outlet gas of unconverted propylene and propane

    and the subscript PA denotes propane.

    Figure 1

    The prices of material involved in the components are as in Table 2.

    Table 2: Physical property and prices of components

    Components Purity (%) Boiling Points (oC) Price/ Cost

    Propylene 95.2 -42.7 $167/kmol

    Benzene 99.9 80.1 $267/kmol

    Cumene 99.9 152.4 $1200/kmol

    PDIPB Not necessary 203 $0.1/kW fuel

    Propane Not necessary -46 $0.1/kW fuel

    Process

    FP, FPA

    FB

    PC

    PPDIPB

    FPA

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    3/31

    Table of Contents

    1. Introduction ....................................................................................................................... 4

    2. Level 2 Decision: Input-Output Structure of the Process Flowsheet ................................ 4

    2.1. Mole Balances in Term of Extent of Reaction ........................................................... 5

    2.1.1. Reaction Selectivity, Yield and Stoichiometry ................................................... 6

    2.2. Economic Potential .................................................................................................... 9

    3. Level 3 Decision: Recycle Structure of the Flowsheet ..................................................... 10

    3.1. Mole Balances for the Reactor ................................................................................ 11

    3.2. Reactor Design ......................................................................................................... 12

    3.2.1. Thermal Effect: Adiabatic or not ..................................................................... 13

    3.2.2. Reactor Design ................................................................................................. 14

    3.2.3. Reactor Cost .................................................................................................... 16

    3.3. Compressor Design and Costs ................................................................................. 16

    3.3.1. Efficiency.......................................................................................................... 17

    3.3.2. Annualized Installed Cost ................................................................................ 17

    3.3.3. Operating Cost ................................................................................................. 17

    3.4. Economical Potential ............................................................................................... 17

    4. References ....................................................................................................................... 18

    5. Appendix A

    6. Appendix B

    7. Appendix C

    8. Appendix D

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    4/31

    1.  Introduction

    Conceptual design should normally start with decision on the mode of operation. Since the

    BKF2453 students do not learn the process economics in attaining right production rate and

    detail qualitative analysis in order to decide either batch or continuous, the mode of

    operation for the projects has thus been set to continuous one. The process runs for 8000 hr

    yearly with the remaining hours are for plant turn-around and cleaning.

    2.  Level 2 Decision: Input-Output Structure of the Process Flowsheet

    Raw Material and Impurities Management

    The available raw materials for the process must be sought out from local or overseas

    market. Their prices are usually based on the place of origin (Biegler, Grossmann, &

    Westberg, 1997; Poling, THompson, Friend, Rowley, & Wilding, 2008) (incurring shipment

    cost) and purity. Nevertheless, in this project, they are all readily given for the sake of

    brevity.

    From the project instruction, the benzene liquid is fed to the process in pure form. Thus

    there is no need to pre-treat anything. However, the propylene feed is having 4.8% propane.

    Propane can remain in the feed to the reactor as the composition is relatively low and it is

    considered inert to the reaction. However, propane will be separated from propylene and

    taken out from the process.

    Output Decision

    The raw materials costs normally fall in the range from 33 to 85% of the total processing

    cost, and these costs are essential to be estimated before any other detail is added to the

    design (Douglas, 1988). At this level, the impurity comes from the fresh propylene feed

    which is propane.

    As the rule of thumb in a process design, it is desirable to recover more than 99% of all

    valuable materials. Thus at this level of decision, the mole balances are calculated for the

    overall system in which the limiting reactant is assumed to get fully converted due to the

    recycle. The recycle streams will not appear because it comes out from and goes in again

    into the process, except for the recycle and purge, which is not in this case.

    As referred to the heuristics of the destination code in Table 5.1-3 of the Douglas textbook,

    the destination of products and impurity of the process are classified based on the boiling

    point at the atmospheric pressure of all species in the process as can be summarised in

    Table 2 1

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    5/31

    Table 2.1 Destination Code for Toluene HDA Process

    Components Boiling Point (oC) Destination Code

    Propylene -42.7 RecyclePropane -46 Fuel

    Cumene 152.4 Primary product

    Benzene 111 Recycle

    PDIPB 203 Fuel

    Outlet components exit the process at the ambient condition. From the boiling point, the

    purge stream of propane is in gas phase while both cumene and p-diisopropyl benzene exit

    as in liquid phase. However, cumene is the main product and must exit separately at a

    standard purity to a particular price which, in this case, it is 99.9%. Figure 2.1 shows the

    streams of input and output materials of the process.

    Figure 2.1 Input-Output Stream and the Respective Nomenclatures of the Benzene

    Alkylation Process

    2.1.  Mole Balances in Term of Extent of Reaction

    The benzene alkylation occurs in gas phase with a side reaction of p-diisopropyl benzene

    Process

    1 Propylene, propane 

    2 Benzene 

    3 Cumene 

    4 p-diisopropyl benzene 

    5 propane 

    Process

    F FP , F FPA

    F FB

    F FPA

    PC

    PPDIPB

    (a) 

    (b) 

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    6/31

    Analysis of mole balance follows the extent of reaction method (Felder & Rousseau, 2005).

    The symbols ξ 1 and ξ 2 are used to denote the extents of reaction for the first and second

    reactions (Eq. ( 

    2.1), respectively. The mole balance of all chemical species are generallycomputed using the correlation as follows

    i  =   + ξ where i   is molar flow rate of the species i and νI  is the stoichiometric coefficient. Hence,the final flow rate from Figure 3.1 can be summarised as in Table 2.2.

    Table 2.2 Mole Balance for the Second Level of Decision

    Species Inlet Change Outlet

    Benzene F FB - ξ 1  0 Propylene F FP - ξ 1 - ξ 2  0 Cumene 0 ξ 1 - ξ 2  PCp-diisopropyl benzene 0  ξ 2  PPDIPB

    In total, other than PC , there are 5 unknown variables. Information available to solve thosevariables can be detailed based on the material and energy balance textbook as follows

    (Felder & Rousseau, 2005)

    Number of unknown variables in the process 4

    2 Independent reactions +2

    4 equation of extent of reactions -4

    Composition of inert propane in the feed and purge (4.8%) -1

    Total (Variables can be calculated by specifying any one of them) 1

    From the degree of freedom, one variable, any of F FP, F FB, or PPDIPB , must first be specified

    before the others can be calculated. In chemical reaction engineering, they can be expressed

    in conversion of the limiting reactant, which is the reactor design variable and thus will be

    the variable to calculate the mole balance.

    2.1.1.  Reaction Selectivity, Yield and Stoichiometry

    The extent of reaction will be calculated in the stoichiometric manner employing theconversion and flow of limiting reactant. The limiting reactant can first be identified from the

    scheme of reactor through selectivity analysis. Thus,

    / =    = 

      = 

      =   − 1  ( 2.2)

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    7/31

    where for cumene: C1 = 102.81, C2 = -8674.6, C3 = -11.922, C4 = 7.0048 x 10-6 and C5 = 2

    thus, PP = 571,318 Pa or 5.71 bar. This means cumene exist in liquid phase at 30 bar, the

    minimum pressure of the reaction. Benzene, however, by using the same method, its vapour

    pressure at 300oC is 54.76 bar, reveals that its phase is gas. Hence, due to this pressure and

    temperature conditions the concentration of benzene is always high at reactive gas phase to

    have effective contact with propylene thus securing the maximum selectivity.

    The selectivity equations (Equation 2.2) cannot simply quantify the difference between both

    reactant feed flows required as taught in the BKF2453 subject. Hence, some detail analyses

    by using the batch reactor algorithm is necessary to delineate the effects of feed ratios of

    propylene:benzene. From calculations using Ordinary Differential Equation (ODE) in

    Polymath (Appendix A) the results for various ratios can be summarised and plotted as

    depicted in Figure 2.2. All selectivities clearly decrease as the conversion of propylene

    increase. The graph also shows that propylene cannot be excess as it will render the

    selectivity to be almost zero at nearly half of the limiting reactant mole and thus high

    selectivity is attributed to excess benzene whereby the ratio of 1:4 shows the maximum. It

    also implies that the limiting reactant of the process will be propylene.

    Figure 2.2 selectivity as functions of propylene conversion at various molar feed ratio,

    propylene:benzene

    0.00E+00

    1.00E+02

    2.00E+02

    3.00E+02

    4.00E+02

    5.00E+02

    6.00E+02

    7.00E+02

    8.00E+02

    9.00E+02

    1.00E+03

    0 0.2 0.4 0.6 0.8 1 1.2

           S     e       l     e     c

          t       i     v       i      t     y

    Xp

    1:1

    1:2

    2:1

    1:4

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    8/31

    The yield is the fraction of propylene converted in the reactor that corresponds to the

    cumene flow at the reactor outlet. Also, this cumene is all recovered and taken (assuming

    100% separation efficiency for the second level of decision) from the process. Using the

    same algorithm for the selectivity (Appendix A), the resulting yield of the reaction can be

    plotted as shown in Figure 2.3. The results of yield from various feed ratios show a good

    agreement with the selectivity’s whereby the excess propylene clearly declines the yield to

    zero before XP = 0.6. The feed with equal molar ratio exhibits significant drop up to 0.85 of

    yield. The molar ratios of 1:2 and 1:4 do not have much difference, implies that further

    excess of benzene is no longer sensitive to yield enhancement. Therefore the feed ratio,

    propylene:benzene, of 1:2 is probably preferable for this process.

    Figure 2.3 Reaction yields against the conversion of propylene for various feed ratio,

    propylene:benzene

    The equation of the yield against the conversion of propylene for the P:B feed ratio of 1:2 (as

    exhibited in Figure 2.3) can be derived by using the Regression function in Polymath on thedata of the results from the batch reactor algorithm (Appendix B). The equation of power

    with 0.99 R-square fits the correlation as follows

    Y  = 1 – 0.0193 X P1.6321  ( 2.5)

    For a production of P mol/hr (52 08 kmol/hr) the propylene fed to the process F must be

    0.6

    0.65

    0.7

    0.75

    0.8

    0.85

    0.9

    0.95

    1

    1.05

    1.1

    0 0.2 0.4 0.6 0.8 1 1.2

           Y       i     e       l       d

    Xp

    1:11:2

    2:1

    1:4

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    9/31

    ∴  =  ..   ( 2.7)If a fraction Y   of propylene is converted to cumene, a faction 1-Y   must be lost to p-

    diisopropyl benzene. From the stoichiometry of the reactions (Equation 2.1), the amount of

    PDIPB , PPDIPB , must be

     = 1 −  =    1 −   ( 2.8)The benzene input is identical to propylene input because benzene also involves indirectly

    with the second reaction. Hence,

     =   ( 2.9)In summary, the above variables can be calculated for respective streams as tabulated in

    Table 2.3.

    Table 2.3 Stream Table of Mole Balance of Benzene Alkylation Process

    Component 1 2 3 4 5

    Propylene PC  /Y 0 0 0 0

    Propane  0.0480.952   0 0 0 0.048

    0.952  Benzene 0 PC  /Y   0  0 0

    Cume 0 0 PC 0 0

    P-diisopropyl benzene 0 0 0 1 −   0

    Temperature (oC) 28 28 28 28 28

    Pressure (bar) 12 1 1 1 1

    Where Y = 1 – 0.0193 X P1.6321

      ; 

    2.2.  Economic Potential

    Since the practical values of the design variables depend on the process economics, the

    stream costs are calculated where all of the costs of all raw materials and product streams

    equated in term of design variables. The potential of economics (EP) at the second level is

    therefore

    EP ($/yr) = Cumene Value + Fuel Value of PDIPB + Fuel Value of Propane –

    Propylene Cost – Benzene Cost. ( 2.10)

    The prices of materials and fuel value for cost estimation are as tabulated in Table 3.4

    Table 2.4 Price Data for Benzene Alkylation

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    10/31

    Power of fuel can be calculated from the enthalpies of combustion of PDIPB and propane: -

    ∆HC-PDIPBo  = 6.82 kJ/kmol (Turton, Bailie, Whiting, & Shaeiwitz, 2008) and - ∆HC-PA

    o  = 2.2

    kJ/kmol (Poling et al., 2008).

    The economic potential in Eq 3.12 would finally be

     = $1200 + $0.1 −∆     + −∆   .. −$267

     −

    $167   ( 2.11)where Y  can be calculated from Equation 2.5.

    Figure 2.4 shows the result of economic potential for the benzene alkylation process. All

    range of conversion yields positive potential and the minimum is $902 mil per year at  X P = 1.

    The highest profit is indicated by the X P = 0.

    As this economic potential is the annual profit that does not have to pay anything for capital

    costs and utilities costs, all the analyses are just catering the sale of products (including

    byproducts) and the purchasing of raw materials. The next level of decisions would use the

    positive range obtained from this level.

    Figure 2.4 Economic Potential – Level 2

    3.  Level 3 Decision: Recycle Structure of the Flowsheet

    At the third level, the recycle stream is focused including the reactor. A compressor, as the

    9.00E+08

    9.02E+08

    9.04E+08

    9.06E+08

    9.08E+08

    9.10E+08

    9.12E+08

    9.14E+08

    0 0.2 0.4 0.6 0.8 1 1.2

            $        /     y     r

    Xp

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    11/31

    Figure 3.1 Benzene Alkylation Process with Liquid and Gas Recycle Streams

    3.1.  Mole Balances for the Reactor

    Before solving the mole balance, the unknown variables must be ensured that they can be

    solved by using specifications and equations available from the process. The degrees of

    freedom of 2 recycle junctions and a reactor based on Figure 3.1 can be tabulated as in

    Table 3.1.

    Table 3.1 Degree of freedom analyses for unit and junctions appeared at level 2 decision

    Unit or junction 1 2 Reactor

    Unknown variables F FP  F PA , F PO and F P: 4 F FB  F B and F B0: 3 F P0 , F PA , F P , F B0 , F B  and

    PPDIPB: 6

    Independent reactions - - 2Balance F FP +F P = F P0: -1 F FB + F B = F B0: -1 Independent extent of

    reactions: -4

    Feed condition Purity percentage: -1 - Molar feed ratio, ΘB: -1Information from the

    2nd level of decision

    F FP = PC /Y: -1 F FB = PC /Y: -1 F PA: -1

    Variables to be

    specified

    1 ( variable X P) 1 ( variable X P) 2 ( variable X P and F P0)

    From the analysis, the solution must start at Junction 1 as it has the lowest degree and it

    deals with the limiting reactant. Thus,

    F FP +F P = F P0 

    SeparatorsReactor

    Benzene recycle

    Benzene

    Feed

    Propylene feed

    Propylene

    Recycle

    Cumene

    PDIPB

    PC

    PPDIPB

    F P, PC , F PA

    F B 

    F FB 

    F FP and F PA 

    F B0 

    F P0 , F PA 

    RG and y PH

    1

    2

    Propane

    F P 

    F B , PPDIPB 

    F PA

    Compressor  

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    12/31

    3.2 Block flow diagram of the benzene alkylation at the 2nd

      level of decision: recycle

    structure.

    3.2.  Reactor Design

    Since both rate laws are the power law models and the reaction occurs irreversibly in

    gaseous phase (assuming the mass transfer limitation is deemed negligible), the right and

    economical reactor is thus the pack bed reactor as can be clearly seen from the plot of the

    Levenspiel.

    Based on the selectivity analysis, propylene feed must be limited at any cost. High selectivity

    can be sustained if the concentration of cumene is low. This probably can be attained by

    having continuous exit flow of cumene along the reactor length. In fact, it is critical as the

    reactor has potential of distribution problem in the catalyst packing due to the multiplicity ofphases. The reactor scheme suggestion can be illustrated in 3.3 where the liquid phase will

    flow downward of the catalyst packing.

    P, B and PA 

    Separator

    sReactor

    Compressor

    Benzene recycle

    Benzene Feed

    Propylene feed

    Propylene

    Recycle

    Cumene

    PDIPB

    PC

    PPDIPB

    F P0 (1-X)

    F P (Θ B -X)

    F FB 

    F FP and F PA 

    Θ BF P 

    F P0 

    RG and y PH

    1

    2

    Propane

    F P0 (1-X)

    F P (Θ B -X)

    F PA

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    13/31

    3.2.1.  Thermal Effect: Adiabatic or not

    The thermal effect of the reactor can be observed from the energy balance calculation via

    the plot of reaction temperature versus propylene conversion. From various references,

    heat capacities of the involving components are not unique and changed with respect to

    absolute temperature as tabulated in Table 3.2.

    Table 3.2 Heat capacities of components:

    Components C1 x 1e-5 C2 x 1e-5 C3 x 1e-3 C4 x 1e-5 C5

    Benzene* 0.44767 2.3085 1.4792 1.6836 677.66

    Propylene* 0.43852 1.506 1.3988 0.74754 616.46

    Propane* 0.5192 1.9245 1.6265 1.168 723.6

    Cumene* 1.081 3.7932 1.7505 3.0027 794.8

    C1 C2 C3 C4 C5

    PDIB** -30.99e-5 1.01728 -6.0 e-4 

    1.312e-7

    *  = +   // +   //

     the unit is J/kmol – from Perry Handbook 8

    th 

    ed.

    **

     = 1 + 2 + 3

     + 4, the unit is J/mol – from chemical property website

    http://chemeo.com/cid/56-152-1 

    In using ODE of Polymath, only one dependant variable is allowed for one program. In

    particular, for the batch reactor design algorithm, the variable is time. If differential

    equation of enthalpy against absolute temperature is inputted, the program will then not

    allow running. Normally, Matlab software is used to solve it. Since this BKF2453 project

    encourages students to use Polymath and the range of reaction temperature is just 50oC, the

    average heat capacities are used.

    The previous algorithm is again employed here with the addition of heat effect, (Appendix

    C), the differential equation, dT/dt (for the batch reactor – Equation T8-1.H page 477, Fogler

    Textbook 4th

     Ed with exclusion of the heat exchange term) using the average heat capacities.

    The result of the propylene conversion against the reaction temperature can be seen in

    Figure 3.4. The batch reactor algorithm is used here because the temperature is plotted

    against conversion and not against the reactor size variable such as retention time or volume

    or weight of catalyst. The temperature increase is only 0.3

    o

    C.

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    14/31

    Figure 3.4 The conversion versus reaction temperature for adiabatic reactor

    The X-T plot in Figure 3.4 shows temperature increase due to the exothermic of the reaction

    and the final temperature is not too high. There is no run away reaction occurs at anytemperature. Thus, adiabatic condition is preferable for the reactor of choice, the pack bed

    reactor because of simpler design and cost incurred.

    3.2.2.  Reactor Design

    The pack bed reactor is designed by using the desired production rate where the feed is

    changed by the conversion of propylene following Equation 3.1. The algorithm of reactor for

    multiple reactions is thus employed here with several molar flow rates calculated from theconversion specified in the range of 0 1.

    The mole balance of a pack bed reactor is

     = ′   where i = P, B, C and PDIPB

    The net rate laws are calculated as following

     =   for Reaction 1 =   for Reaction 2where

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    15/31

     =

     ∑   where -∆HRxn(T) = Y [-∆HRxn1(T)] + (1-Y)[ -∆HRxn2(T)] which Y  is reaction

    yield as Y  = 1 – 0.0193 X P1.6321 and X P = (F P0 – F P)/F P0

      is heat capacity for respective components of which all change with temperature.However, in this project average heat capacities between 300 – 350 oC are used in

    Polymath Educational Edition.

    Stoichiometry:-

    From the selectivity analysis, propylene was identified as the limiting reactant

     =     where C T0 = P0/(RT ); F T  = ∑ F i  and y  = P/P0Pressure drop:-

     =

     

     

    where F T0 = 3F P0 as for F B0 = 2F P0 

    and =     whilst = 

      +1.75 

    with ρ0  = 19.1 kg m-3, gC  = 1, DP  =0.01 m, µ  = 2.914 x 10

    -5  Pa.s, φ  = 0.5 and G  =FP0*MWP/Ac. Ac  is the cross sectional area for 1.5” schedule 40 pipe, which is

    approximately 0.0013 m2.

    From various conversions, the weight of catalyst obtained from the algorithm (can refer

    Appendix D) is plotted as can be seen in Figure 3.5. Besides, the volume of the reactor canbe obtained from the weight of the catalyst by using its bulk density.

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    16/31

    Figure 3.5 the weight of catalyst and volume for PBR against the propylene conversion.

    Two trends of weight and volume plotted at the same line but their values are referred at

    left and right axes, respectively.

    3.2.3.  Reactor Cost

    The plug flow reactor cost estimation follows the shell and tube method. From the graph of

    purchased cost versus tube surface area ¼” schedule 40 pipes in Figure 15-13 (Peters &

    Timmberhaus, 1991), the following correlation (readily included inflation for 2014) was

    obtained.

    Purchased Cost,

    C  A0 = 125933V + 651508 ( 3.2)

    3.3.  Compressor Design and Costs

    A compressor is required as the process has a gas recycle stream. Compressors are so

    expensive that spares are seldom provided for centrifugal units (although reciprocating

    compressors may have spares because of a lower service factor). In practice, one standby

    compressor would also be purchased to accommodate for any failure and breakdown.

    The design equation for the theoretical horsepower (hp) for the centrifugal gas compressor

    (for various pressure loads) is as follows

    53.03 101out 

    in in

    in

     P hp P Q

     P 

    γ 

    γ 

    −   × = −  

      ( 

    3.3)

    where Pin = lbf /ft3, Qin = ft

    3/min (calculate from gas real law equation for RG) and γ = (C  p /C v   –

    1)/(C  p /C v ). The exit temperature from a compressor stage is

    out out  

    in in

    T P 

    T P 

    γ 

    =

      ( 

    3.4)

    where the temperatures and pressure must be in the Rankine absolute units. Values of γ that can be used for first estimates are given in Table

    T bl 3 3 V l f f i f

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    17/31

    The compressor will be designed pressures Pin = 1 bar to Pout  = 15 bar which is identical to

    the feed of fresh propylene. The pressure is enough to liquefy the propylene flow. The flow

    of both propylene and benzene liquids will be dosed by pumps equipped with non-return

    valves.

    3.3.1.  Efficiency

    At this level, the compressor has 90% of efficiency to account for fluid friction in suction and

    discharge valves, ports, friction or moving metal surfaces, fluid turbulence, etc. The driver is

    also assumed to have 90% of efficiency to account for the conversion of the input energy to

    shaft work.

    3.3.2.  Annualized Installed Cost

    The brake horsepower, bph, is obtained by introducing the compressor efficiency into Eq.

    4.9:

    bph = hp/0.9 ( 

    3.5)

    Then, Guthrie’s correlation can be used to calculate the installed cost for various types of

    compressors:

    Installed Cost = ( )0.82&

    517.5 2.11280

      c

     M S bhp F  

    +

      ( 3.6)

    where F c  is the correction factor (F c = 1 in this case) and M&S (Marshall and Swift inflation

    index) those are obtainable from the Peters’ textbook (Peters & Timmberhaus, 1991).

    3.3.3. 

    Operating Cost

    By dividing the brake horsepower by the driver efficiency (80%) , the utility requirement can

    be calculated. Then from the utility cost ($0.1/kW for 2014) and using 8000 hr/yr, the

    operating cost can be obtained.

    3.4.  Economical Potential

    The previous economic analysis for the input-output structure considered only the streamcosts, i.e., products plus by-products minus raw material costs. At the second level decision

    where the reactor system complete with the recycle streams, the previous economic

    potential will be minus to the cost of reactor and catalysts, and the cost of multistage

    compressor elevating pressure from 1 bar to 15 bar of propylene recycle. The result of the

    l l ti

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    18/31

    ( ) ( ) ( )0.823 2&

    EP ($/yr) EP ($/yr) Catalyst cost installation cost 517.5 2.11280

    Compressor Operating Cost

    c

     M S W V bhp F  

    = − − − +

    − 

    as shown from the graph in Figure 3.6, indicates that the optimum conversion of propylene,

    at the stage where no separators are considered yet, is 0.6.

    Figure 3.6 The Profitability of the Process at Level 3 Decision versus Propylene

    Conversion.

    4.  References

    Biegler, L. T., Grossmann, I. E., & Westberg, A. W. (1997). Systematic Methods of Chemical

    Process Design: Prentice-Hall.

    Douglas, J. M. (1988). Conceptual Design of Chemical Processes. New York: McGraw Hill.

    Felder, R. M., & Rousseau, R. W. (2005). Elementary Principles of Chemical Processes (3 ed.).

    New York: John Wiley & Sons.

    Peters, M. S., & Timmberhaus, K. D. (1991). Mass Transfer and Reactor Equipment - Designand Costs. In J. J. Carberry, J. R. Fair, W. P. Schowalter, M. Tirrell & J. Wei (Eds.),

    Plant Design and Economics for Chemical Engineers  (4th ed.). New York: McGraw

    Hill.

    Poling, B. E., THompson, G. H., Friend, D. G., Rowley, R. L., & Wilding, W. V. (2008). Physical

    and Chemical Data. In D. W. Green & R. H. Perry (Eds.), Perry's Chemical Engineers'

    $800,000,000

    $820,000,000

    $840,000,000

    $860,000,000

    $880,000,000

    $900,000,000

    $920,000,000

    0 0.2 0.4 0.6 0.8 1 1.2

            $        /     y     r

    Xp

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    19/31

    APPENDIX A 

    ALGORITHM USING BATCH REACTOR DESIGN TO ANALYSE SELECTIVITY OF REACTIONS 

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    20/31

    Appendix A.txtAPPENDIX A# mole balance

    d(Cp)/d(t) = rpCp(0) = 209.911 # propylened(Cb)/d(t) = rb # benzeneCb(0) = 419.822d(Cc)/d(t) = rc # cumeneCc(0) = 0d(Cpdib)/d(t) = rpdib # p-diisopropyl benzeneCpdib(0) = 0

    # rate lawr1prime = k1prime * Cp * Cb

    r2prime = k2prime * Cp * Ccrp = -r1prime - r2primerb = -r1primerc = r1prime - r2primerpdib = r2primek1prime = 3.5e4 * exp(-1.04e5 / R / T)k2prime = 2.9e6 * exp(-1.47e5 / R / T)R = 8.314T = 300 + 273

    # Selectivity, Yield and ConversionS = (r1prime - r2prime + 0.00001) / (r2prime + 0.00001)Y = (r1prime - r2prime + 0.00001) / (r1prime + r2prime + 0.00001)Xp = 1 - Cp * Nt * P0 / (Cp0 * Nt0 * P)Xb = theta - Cb * Nt * P0 / (Cp0 * Nt0 * P)Nt = (Cp + Cb + Cc + Cpdib) * VV = 1Nt0 = (Cp0 + Cb0) * VP0 = (Cp0 + Cb0) * R * TP = (Cp + Cb + Cc + Cpdib) * R * TCp0 = 209.911

    Cb0 = 419.822theta = Cb0 / Cp0

    t(0) = 0t(f) = 3600

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    21/31

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    22/31

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    23/31

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    24/31

    APPENDIX B 

    REGRESSION RESULT OF CORRELATION BETWEEN YIELD AND CONVERSION OF PROPYLENE 

    Page 1 of 2

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    25/31

    Model: Y = 1-A*Xp^B

    Nonlinear regression settingsMax # iterations = 300

    Precision

    General

    Source data points and calculated data points

    POLYMATH ReportNonlinear Regression (L-M) 03-May-2014

     Variable Initial guess Value 95% confidence

     A 0.008 0.0192825 7.782E-05

    B 1.74 1.63208 0.0341333

    R^2 0.9978368

    R^2adj 0.9977975

    Rmsd 2.869E-05

     Variance 4.861E-08

    Sample size 57

    Model vars 2

    Indep vars 1

    Iterations 6

     Xp Y Y calc Delta Y1 0 1 1. 0

    2 0.2563921 0.9970792 0.9979085 -0.0008293

    3 0.3868124 0.9952462 0.995908 -0.0006618

    4 0.4707557 0.9939056 0.9943618 -0.0004562

    5 0.5109773 0.9932113 0.9935546 -0.0003433

    6 0.5870242 0.9917937 0.9919166 -0.0001229

    7 0.6226019 0.9910784 0.9911019 -2.347E-05

    8 0.6561975 0.9903694 0.990305 6.444E-05

    9 0.7142212 0.9890606 0.9888671 0.0001935

    10 0.7387246 0.988473 0.988237 0.000236

    Page 2 of 2

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    26/31

    22 0.9225748 0.9832496 0.9830939 0.0001557

    23 0.9282395 0.9830617 0.9829242 0.0001375

    24 0.9334649 0.9828867 0.982767 0.0001197

    25 0.9427443 0.9825721 0.9824865 8.558E-05

    26 0.9468626 0.9824308 0.9823615 6.932E-05

    27 0.9506714 0.9822993 0.9822455 5.376E-05

    28 0.9541956 0.9821769 0.982138 3.891E-05

    29 0.9604798 0.9819569 0.9819456 1.13E-05

    30 0.9632795 0.9818582 0.9818596 -1.431E-06

    31 0.9658745 0.9817664 0.9817798 -1.341E-0532 0.9682808 0.981681 0.9817057 -2.466E-05

    33 0.9725834 0.9815276 0.9815728 -4.52E-05

    34 0.9745053 0.9814589 0.9815133 -5.444E-05

    35 0.9762894 0.9813951 0.9814581 -6.297E-05

    36 0.9779461 0.9813358 0.9814067 -7.089E-05

    37 0.9809142 0.9812295 0.9813145 -8.5E-05

    38 0.9822423 0.9811821 0.9812732 -9.109E-05

    39 0.9834765 0.9811381 0.9812348 -9.667E-05

    40 0.9846237 0.9810974 0.981199 -0.0001016

    41 0.9866818 0.9810248 0.9811349 -0.0001101

    42 0.9876038 0.9809926 0.9811061 -0.0001135

    43 0.9884613 0.9809628 0.9810793 -0.0001165

    44 0.9892589 0.9809355 0.9810544 -0.0001189

    45 0.990691 0.9808873 0.9810096 -0.0001223

    46 0.9913332 0.9808662 0.9809895 -0.0001233

    47 0.9919307 0.980847 0.9809708 -0.0001238

    48 0.9924868 0.9808295 0.9809534 -0.0001239

    49 0.9934859 0.9807996 0.9809221 -0.0001225

    50 0.9939341 0.980787 0.980908 -0.00012151 0.9943514 0.9807758 0.9808949 -0.0001191

    52 0.9947397 0.980766 0.9808828 -0.0001168

    53 0.9954379 0.9807506 0.9808609 -0.0001103

    54 0 9957513 0 9807448 0 980851 -0 0001062

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    27/31

    APPENDIX C 

    ALGORITHM USING BATCH REACTOR DESIGN TO ANALYSE HEAT EFFECT OF REACTIONS 

    Polymath DEQ Program

    No TitleFile: D:\My Tasks\Courseworks\Sem 2 2013-2014\BKF2453 Chem Rxn Eng 1\Assessments\Mini Project\Appendix C pol

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    28/31

    File: D:\My Tasks\Courseworks\Sem 2 2013-2014\BKF2453 Chem Rxn Eng 1\Assessments\Mini Project\Appendix C.pol

    # APPENDIX C# mole balanced(Cp)/d(t) = rpCp(0) = 209.911 # propylened(Cb)/d(t) = rb # benzene

    Cb(0) = 419.822d(Cc)/d(t) = rc # cumeneCc(0) = 0d(Cpdipb)/d(t) = rpdipb # p-diisopropyl benzeneCpdipb(0) = 0

    # rate lawr1prime = k1prime * Cp * Cbr2prime = k2prime * Cp * Cc

    rp = -r1prime - r2primerb = -r1primerc = r1prime - r2primerpdipb = r2primek1prime = 3.5e4 * exp(-1.04e5 / R / T0) * exp(-1.04e5 / R * (1 / T0 - 1 / T))k2prime = 2.9e6 * exp(-1.47e5 / R / T0) * exp(-1.47e5 / R * (1 / T0 - 1 / T))R = 8.314T0 = 300 + 273

    # Energy balance

    d(T)/d(t) = (-rp * V) * (-delHrxn) / (Np * Cpp + Nb * Cpb + Nc * Cpc + Npdipb * Cppdipb + Npa * Cppa) # Energy balanceT(0) = 573.15Np = Cp * VNb = Cb * VNc = Cc * VNpdipb = Cpdipb * VNpa = 0.048 * Np / 0.942delHrxn = -99000 - (Y * Cpc + (1 - Y) * Cppdipb - Cpb - Cpp) * (T - T0)Cpb = 118301.05Cpp = 75645.53Cppa = 103155.16Cpc = 237763.42Cppdipb = 421721.13

    # Selectivity, Yield and ConversionS = (r1prime - r2prime + 0.00001) / (r2prime + 0.00001)Y = (r1prime - r2prime + 0.00001) / (r1prime + r2prime + 0.00001)Xp = 1 - Cp * Nt * P0 / (Cp0 * Nt0 * P)Xb = theta - Cb * Nt * P0 / (Cp0 * Nt0 * P)

    Nt = (Cp + Cb + Cc + Cpdipb) * VV = 1Nt0 = (Cp0 + Cb0) * VP0 = (Cp0 + Cb0) * R * TP = (Cp + Cb + Cc + Cpdipb) * R * TCp0 = 209.911Cb0 = 419.822

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    29/31

    APPENDIX D 

    ALGORITHM USING PACKED BED REACTOR DESIGN TO ESTIMATE THE WEIGHT OF CATALYST AND 

    VOLUME OF THE REACTOR 

    ECONOMIC 

    POTENTIAL 

    CALCULATIONS 

    AT 

    LEVEL 

    DECISIONS 

    Polymath DEQ Program

    No TitleFile: D:\My Tasks\Courseworks\Sem 2 2013-2014\BKF2453 Chem Rxn Eng 1\Assessments\Mini Project\Appendix D#2 - PBR design.pol

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    30/31

    y g j pp g p

     APPENDIX D-1 Mole Balance of PBR

    d(Fp)/d(W) = rp # Propylene balanceFp(0) = 1.446681718d(Fb)/d(W) = rb # benzene

    Fb(0) = 2.893363436d(Fc)/d(W) = rc # cumeneFc(0) = 0d(Fpdipb)/d(W) = rpdib # p-diisopropyl benzeneFpdipb(0) = 0Ft0 = Fp0 * 3

     = 1 - 0.0193 * Xp ^ 1.6321p = (Fp0 - Fp) / Fp0

    Fp0 = 1.446681718

     Rate Lawr1prime = k1prime * Cp * Cbr2prime = k2prime * Cp * Ccrp = -r1prime - r2primerb = -r1primerc = r1prime - r2primerpdib = r2primek1prime = 3.5e4 * exp(-1.04e5 / R / T0) * exp(1.04e5 / R * (1 / T0 - 1 / T))k2prime = 2.9e6 * exp(-1.47e5 / R / T0) * exp(1.47e5 / R * (1 / T0 - 1 / T))

    R = 8.314 # kJ/kmol/K0 = 300 + 273

     StoichiometryCp = Ct0 * Fp / Ft * y * T0 / TCb = Ct0 * Fb / Ft * y * T0 / TCc = Ct0 * Fc / Ft * y * T0 / TCpdipb = Ct0 * Fpdipb / Ft * y * T0 / TFt = Fp + Fb + Fc + FpdipbCt0 = P0 / (1000 * R * T0) # kmol/m^3P0 = 30e5 # Pa

     Energy balancedelHrxn = -99000 - (Y * Cpc + (1 - Y) * Cppdipb - Cpb - Cpp) * (T - T0)Cpb = 118301.05 # J/kmol mean heat capacity between 300-350CCpp = 75645.53 # J/kmol mean heat capacity between 300-350CCppa = 103155.16 # J/kmol mean heat capacity between 300-350CCpc = 237763.42 # J/kmol mean heat capacity between 300-350CCppdipb = 421721.13 # J/kmol mean heat capacity between 300-350C

    d(T)/d(W) = rp * delHrxn / (Fb * Cpb + Fp * Cpp + Fc * Cpc + Fpdipb * Cppdipb + 0.0001) # Energy Balance for PBR(0) = 573 # K

     Pressure drop using air propertiesd(y)/d(W) = -alfa / (2 * y) * Ft / Ft0 * T / T0(0) = 1

    alfa = 2 * beta / (Ac * rhoB * P0)

  • 8/17/2019 Example of CRE1 Miniproject Ver.2 Student Edition (1)

    31/31

    Appendix D‐2 

    Xp  Y  EP2  Ffp  Fp0  Fb0  G  alfa  W (kg)  V (m3) 

    0.000000001 1  911917967 0.014467 14466667 28933333 264957265 5.88798E+14 1.85E+04 7.4

    0.00085 1  911917870 0.014467 17.01961 34.03922 311.714488 815.7470646 1.83E+04 7.3

    0.001000001 1  911917841 0.014467 14.46666 28.93331 264.9570649 589.4782606 1.60E+04 6.404

    0.010000001 0.999989  911912549 0.014467 1.446682 2.893363 26.49600216 5.956185192 1.44E+04 5.764

    0.020000001 0.999967  911901171 0.014467 0.723357 1.446714 13.24829393 1.506131881 1.51E+04 6.02

    0.100000001 0.99955 

    911685603 0.014473 0.144732 0.289464 2.65076614 0.065743789 1.51E+04 6.02

    0.200000001 0.998604  911197040 0.014487 0.072434 0.144869 1.326637805 0.018169804 1.57E+04 6.276

    0.300000001 0.997295  910518832 0.014506 0.048353 0.096706 0.885586389 0.008853173 1.66E+04 6.628

    0.400000001 0.995674  909676778 0.01453 0.036324 0.072648 0.665271076 0.005421388 1.76E+04 7.044

    0.500000001 0.993773  908685939 0.014557 0.029115 0.058229 0.533234732 0.003754896 1.89E+04 7.564

    0.600000001 0.991615  907556315 0.014589 0.024315 0.04863 0.445329311 0.002807558 2.06E+04 8.24

    0.700000001 0.989217  906294986 0.014624 0.020892 0.041784 0.382636367 0.002211117 2.31E+04 9.244

    0.800000001 0.986591  904907135 0.014663 0.018329 0.036658 0.335697893 0.001807719 2.68E+04 10.7

    0.900000001 0.983749  903396616 0.014706 0.01634 0.032679 0.299260198 0.001520047 3.46E+04 13.828

    0.950000001 0.98225  902596284 0.014728 0.015503 0.031007 0.28394238 0.001405764 4.20E+04 16.78949

    0.970000001 0.981636  902267834 0.014737 0.015193 0.030386 0.278261821 0.001364383 4.80E+04 19.216

    0.980000001 0.981326  902101835 0.014742 0.015043 0.030086 0.275509419 0.001344527 5.25E+04 20.988

    0.990000001 0.981014  901934655 0.014747 0.014896 0.029791 0.272813233 0.0013252 6.11E+04 24.44

    1.000000001 0.9807 

    901766298 0.014751 0.014751 0.029503 0.270171576 0.001306382 2.15E+05 85.92