Evidence Issues in Forensic Use of CPM Scheduling

35
Evidence Issues in Forensic Use of CPM Scheduling prepared by Fredric L. Plotnick, Ph.D., Esq., P.E. for the New Jersey State Bar Association Section on Construction Law

description

Evidence Issues in Forensic Use of CPM Scheduling. prepared by Fredric L. Plotnick, Ph.D., Esq., P.E. for the New Jersey State Bar Association Section on Construction Law. Fredric L. Plotnick Education 75-77-80-93-08 Teaching – Drexel – U of P Licensed PA-NJ-FL-MD - PowerPoint PPT Presentation

Transcript of Evidence Issues in Forensic Use of CPM Scheduling

Page 1: Evidence Issues in Forensic Use of CPM Scheduling

Evidence Issues inForensic Use of CPM Scheduling

prepared by

Fredric L. Plotnick, Ph.D., Esq., P.E.for the

New Jersey State Bar Association

Section on Construction Law

Page 2: Evidence Issues in Forensic Use of CPM Scheduling

Curriculum Vitae

• Fredric L. Plotnick• Education 75-77-80-93-08• Teaching – Drexel – U of P • Licensed PA-NJ-FL-MD• Bechtel – Hill – IUCS – Fuller

• EnProMaC 1983 – 2009 • USN Guideline Specification, 1986• CPM in Construction Management, 5th, 6th, 7th • Contract and the Legal Environment for

Engineers and Architects, 7th

• PSPE, ASCE, AACEi, PMI, …• ABA•FC, PBA, NJSBA, … • also enjoys fishing

Page 3: Evidence Issues in Forensic Use of CPM Scheduling

• How reliable is CPM to establish a claim of delay or disruption?

• Claims before CPM• Claims after CPM• Current State-of-the-Art• Frye v Daubert• Intrinsic Unreliability of CPM• Daubert II • Robinson Factor Analysis• Analytical Gap Test• Specific Flaws of this CPM• All leading to …

Page 4: Evidence Issues in Forensic Use of CPM Scheduling

RDM Relationship Diagramming Method

• Old Knowledge – New Software Technology

• New Knowledge – Software Implementation

• RDM – in a nutshell

RD CPM®

Compliance Certified

RD CPM®

Compliance Certified

Page 5: Evidence Issues in Forensic Use of CPM Scheduling

More Accurate Model / Calculations

• Events – Description – Coding – Maths • Durations – P/C/K – C/I/S – M/R/P – Calendar

• Restraints – FS/SS/PS/FF/FR/SF CT/CC/DD

• Reason/Why – Just-In-Time – Description • Relationship Coding – Automated Reason/Why

Page 6: Evidence Issues in Forensic Use of CPM Scheduling

Pre-CPM Claims of Delay

• Generally, if two parties claim concurrent delays, the court will not try to unravel the factors involved and will disallow the claims by both parties. In United States vs. Citizens and Southern National Bank, 367 F. 2d 473 (1966), a subcontractor was able to show delay damages caused by the general contractor. However, the general contractor, in turn, was able to demonstrate that portions of the damages were caused by factors for which he was not responsible. In the absence of clear evidence separating the two claims, the court rejected both claims, stating:

“As the evidence does not provide any reasonable basis for allocating the additional costs among those contributing factors, we conclude that the entire claim should have been rejected.” CPM in Construction Management, 6th Edition, page 547

Page 7: Evidence Issues in Forensic Use of CPM Scheduling

Post-CPM Claims of Delay• The courts gave early recognition to the validity of CPM. In 1972 (Appeal of

Minmar Builders, Inc. GSBCANo. 3430, 72-2 BOA), the court rejected a claim based on bar graph schedules, stating:

“The schedules were not prepared by the Critical Path Method (CPM) and, hence, are not probative as to whether any particular activity or group of activities was on the critical path or constituted the pacing element for the project.”

• Also in 1972, a Missouri Court (Natkin & Co. v. Fuller. 347 F Supp 17) stated that bar charts did not “afford an overall coordinated schedule of the total work covered by the contract.”

• An Illinois court (Pathman Construction Co. v. Hi-Way Electric Co. 65 Ill. App. ad 480, 382 N.E. 2d 453,460) in 1978 noted that

“technological advances and the use of computers to devise work schedules and chart progress on a particular project have facilitated the court’s ability to allocate damages.”

CPM in Construction Management, 6th Edition, page 26

Page 8: Evidence Issues in Forensic Use of CPM Scheduling

• Analysis of Delay• As-Planned• As-Built• As-Impacted• Zeroing-Out• Windows• Zeroing-Out Windows

State of the Art Analysis & Presentation

ACTIVITY IDACTIVITY

DESCRIPTIONORIGDUR

ActualDuration START FINISH

1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB

1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0

1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0

1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0

1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0

3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0

3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0

1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0

1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0

1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0

3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0

3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0

3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0

3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58

3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58

4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0

3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58

4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0

3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58

4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0

4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0

4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0

3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58

R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58

3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66

R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330

R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58

3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58

R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58

3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63

4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0

4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0

4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0

R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29

3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0

R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0

4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1

3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7

2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47

3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0

3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63

4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1

4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7

4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1

4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1

R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0

4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1

4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1

4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1

4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1

R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21

R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1

4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21

1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1

1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17

R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9

4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1

4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10

R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28

R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65

1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9

R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6

R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0

R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5

R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10

R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15

R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14

R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6

R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0

R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5

R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10

R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4

R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6

R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4

R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10

R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4

R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6

R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5

R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0

R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0

1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15

R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0

1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15

1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0

1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0

1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0

1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0

5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0

END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33

5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0

5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1

5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0

5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0

5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0

5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0

5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0

5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0

5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0

5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0

5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0

1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0

1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0

END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0

NOTICE TO PROCEED

MOBILIZATION

SED BASIN EXCAV to 236.15

SED BASIN SOG @ 236.40

SED BASIN SOG @ 240.40/242.75

SED BASIN (N,S,E) WALL to 264

FLOC BASIN FOOTING @ 240.25

FLOC BASIN FOOTING WALL to 247

FLOC BASIN CONC FILL to 247

FLOC BASIN SOG @~249 INCL GRADE BEAM

FLOC BASIN (N,S,W) WALL to 261.58/264

PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33

CHEM BLDG EAST SOG STEP FTGS @ 230//240.50

CHEM BLDG EAST WALL to 243//250

CHEM WEST SOG @ 246/246.67

CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250

CHEM WEST WALLS to 263

CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67

CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS

CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG

CHEM WEST BEAMS & SLABS to 264

CHEM BLDG EAST MASONRY TO 265

CHEM EAST GLAZED STRUCTURAL TILE

CHEM BLDG EAST MONORAIL SUPPORT STEEL

CHEM EAST CAST STONE/BRICK

CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266

CHEM BLDG EAST MASONRY TO 280

CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67

CHEM BLDG EAST MASONRY TO PARAPET

CHEM WEST STR STL COLS/BEAMS to 275.33/288.33

CHEM WEST ELEV SLAB @ 276

CHEM WEST MASONRY TO 280

CHEM WEST 3rd FLOOR C.M.U.

PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67

ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.

CHEM WEST MASONRY TO 288

PRE-OZONE CONTACT BASIN MASONRY to PARAPET

PIPE GALLERY/FILTER 12" DECK PANELS

CHEM BLDG EAST ROOFING

PRE-OZONE CONTACT BASIN ROOFING

CHEM WEST R/S LIME STO SILOS

CHEM WEST STR STL BEAMS @ 288.33

CHEM WEST R/S LIME FEEDER HOPPERS

CHEM WEST R/S LIME DUST COLLECTORS

ELECTRICAL ROOM MISCELLANEOUS WORK

CHEM WEST - LIME STO R/S LIME CONV BLOWERS

CHEM WEST - LIME STO R/S 6" 8" 10" PPG

CHEM WEST 8" DECK PANELS @ 289

CHEM WEST MASONRY TO PARAPET

ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR

CHEM WEST CAST STONE

CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT

2ND FL ARCH INTERNAL MASONRY

1ST FL ARCH INTERNAL MASONRY

2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING

CHEM WEST ROOFING @ 280.67/289

CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG

CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE

FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS

2ND FL ARCH ELEC R/I

1st FLOOR CHEM WEST PIPING & PANELS

2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS

S.B./FILTERS/FLOCC. PULL FEEDERS

CHEM EAST/PUMP STATION PULL FEEDERS

3rd FLOOR CHEM WEST PULL FEEDERS

CHEM WEST COMPUTER ROOM EQUIPMENT

1st FLOOR CHEM WEST PULL FEEDER WIRE

2nd FLOOR CHEM WEST/C.B. BRANCH WIRING

S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS

CHEM EAST/PUMP STATION PULL BRANCH WIRING

CHEM WEST LAB PIPING

1st FLOOR CHEM WEST PULL BRANCH WIRING

CHEM WEST LAB INSTRUMENTATION

CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT

CHEM WEST LAB EQUIPMENT/FURNITURE

1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT

S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT

2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE

ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS

OPERATIONAL PUNCHLIST

INSTALL SOFTWARE & DEBUG SYSTEM

PROCESS PAINTING

INITIAL MECH PERF TEST OPER TESTING & TRAINING

INITIAL MECH PERF TEST 48 HR PLANT OPERATION

INITIAL MECH PERF TEST PUNCHLIST

FINAL MECH PERF TEST 48 HR PLANT OPERATION

GARAGE EXCAV to 243

880 DAY PART A COMPLETION

GARAGE SOG @ 243.83

GARAGE FTG FDN @ 244

GARAGE FTG WALLS to 247.27 +/-

GARAGE BFILL

GARAGE SOG @ 248

GARAGE MASONRY

GARAGE STR STL @ 260 +/-

GARAGE 8" DECK PANELS @ 262.67

GARAGE ROOFING

GARAGE ARCH DETAILS

GARAGE BUILDING PUNCHLIST

ARCHITECTURAL & FINAL PUNCHLIST

OWNER ACCEPTANCE

1065 DAY PART B COMPLETION

Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95

(c) Primavera Systems, Inc.

inactive Sheet 1 of 1

As-BuiltAs-PlannedAs-Impacted

nProMaC, Inc

As-PlanSTART

As-PlanFINISH

EARLYSTART

EARLYFINISH

1991 1992 1993 1994M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J

24JUN91 29JUL91 25JUL91A 22FEB93A

10JUL91 2AUG91 13SEP91A 9DEC92A

4JUN91 24JUN91 12JUL91A 11JUN92A

6AUG91 19AUG91 22OCT91A 18JUN93A

7FEB92 14FEB92 18JUN92A 27JAN93A

4DEC91 17DEC91 27JAN92A 15JAN93A

9JUL91 10JUL91 8JUN92A 27AUG93A

23AUG91 6SEP91 14SEP92A 22DEC92A

12JUN92 12JUN92 2SEP92A 16AUG93A

16OCT91 19NOV91 25JUN92A 31AUG93A

12SEP91 20SEP91 26JUN92A 15JUL93A

24DEC91 15JAN92 18JUN93A 20DEC93A

9APR92 9APR92 24JUN92A 30SEP93A

4FEB92 6FEB92 16OCT92A 15NOV94A

21JAN93 27JAN93 1MAR94A 15SEP94A

P.S. CONCRETE

C.W./OZONE/GAC CONCRETE

S.B./FLOCC CONCRETE

FLUME/FILTER/P.G. CONCRETE

CHEM EAST CONCRETE

CONTACT BASIN CONCRETE

CHEM WEST CONCRETE

L/C CONCRETE

ROOF DECK

MASONRY

STRUCTURAL STEEL

ROOFING

MECH EQUIPMENT

OZONE SYSTEM

INSTRUMENTATION

Target Date 10MAY91Plot Date 20FEB95Data Date 1FEB95Project Start 10MAY91Project Finish 31JAN95

Primavera Systems, Inc.

Summary Bar/Early Dates

inactive

Critical DesignatorTarget Dates

R8U1 Page 1 of 1

A CT TI TLE O D E S- EC ON D AC T T ITL E OD ES -E CO ND

P CO 00 50 1 PC O00 5 NT P A DDL R OC K EX CA V & R EI NF C ONC 1 0 6/ 21 /9 1 PC O1 16 01 P CO1 16 N TP ADD L WA LL S LE EVE S CH EM W EST S LA B@ 27 6 1 05 /0 5/ 93

P CO 00 70 1 PC O00 7 NT P R EBA R RE VI SI ON S @ F LU ME S 1 0 7/ 26 /9 1 PC O1 17 01 P CO1 17 N TP WOO D BL OC KI NG @ RO OF O PE NIN GS 1 05 /2 1/ 93

P CO 00 80 1 PC O00 8 NT P G F L ET TE R 6/ 21 /91 1 0 7/ 26 /9 1 PC O1 20 01 P CO1 20 N TP ADD L NE LS ON S TUD S @ L/ C 1 05 /0 1/ 93

P CO 00 90 1 PC O00 9a NT P B RIC K LE DG ES & CL OU MN Q UA NTI TI ES 1 0 8/ 16 /9 1 PC O1 21 01 P CO1 21 N TP CHE M WE ST 3 RD SL AB /M AS ON RY IN TE RF AC E 1 04 /2 6/ 93

P CO 01 00 1 PC O01 0 NT P C ONS TR UC TI ON /C ONT RA CT IO N JOI NT S 1 0 9/ 06 /9 1 PC O1 24 01 P CO1 24 N TP ADD L RO OF H AT CHE S @ OZ ON E A IR P RE P 1 12 /2 1/ 92

P CO 01 20 1 PC O01 2 NT P R EVI SE D EL EC S UBS TA TI ON 1 0 9/ 26 /9 1 PC O1 26 01 P CO1 26 N TP MAS ON RY C HA NG ES CH LO R, L/ C B AT H, OZ ON E 1 03 /2 3/ 93

P CO 01 30 1 PC O01 3 NT P R EBA R CH AN GE S 1 1 0/ 10 /9 1 PC O1 28 01 P CO1 28 N TP ARC H MO DS F OR HV AC & P LU MBI NG 1 05 /2 0/ 93

P CO 01 40 1 PC O01 4 NT P W ATE RS TO P CH AN GES @ C LE AR WEL L & C. B 1 1 0/ 01 /9 1 PC O1 31 01 P CO1 31 N TP STR S TL B EA M REP AI RS @ C HLO R & GA C 1 02 /1 6/ 93

P CO 01 60 1 PC O01 6 NT P G F M EM O 10 /2 2/ 91 1 1 0/ 22 /9 1 PC O1 36 01 P CO1 36 N TP MOD IF Y 12 " S. S. AI R WA SH PI PE 1 06 /2 1/ 93

P CO 01 70 1 PC O01 7 NT P A DDL R EB AR @ C .W. S UM PS 1 0 9/ 25 /9 1 PC O1 41 01 P CO1 41 N TP MAS ON RY C HA NG E @ C HI MN EY AR EA 1 09 /0 3/ 93

P CO 01 80 1 PC O01 8 NT P G F M EM O 10 -2 9- 91 1 1 0/ 29 /9 1 PC O1 45 01 P CO1 45 N TP MOD S @ EL EV AT OR MA CH IN E ROO M 1 07 /2 6/ 93

P CO 02 00 1 PC O02 0 NT P G F L ET TE R 11 /1 1/9 1 1 1 1/ 11 /9 1 PC O1 48 01 P CO1 48 N TP CHA NG E DO OR S IZE @ C OR R 122 & L IN TE L 1 08 /2 7/ 93

P CO 02 10 1 PC O02 1 NT P F LOC C WL AK WA Y CHA NG ES 1 1 1/ 18 /9 1 PC O1 49 01 P CO1 49 N TP STR F RA MI NG C HAN GE S @ P. S. LO UV ER 1 10 /2 5/ 93

P CO 02 20 1 PC O02 2 NT P F LOC C DR AI N SL OT RE LO CA TI ON 1 1 1/ 21 /9 1 PC O1 50 01 P CO1 50 N TP A DDL N EL SO N ST UDS C HE M WE ST 3R D FL 1 07 /0 2/ 93

P CO 02 60 1 PC O02 6 NT P F LOC C IN TE RM ED BA FF LE W AL L D RA IN 1 1 1/ 25 /9 1 PC O1 51 01 P CO1 51 N TP L &N CH LO RI NE S YST EM M OD IF ICA TI ON S 1 03 /1 5/ 94

P CO 02 70 1 PC O02 7 NT P S .S. W AL KW AY C HAN GE S 1 1 2/ 03 /9 1 PC O1 52 01 P CO1 52 N TP A DDL M ET AL S TU D F RA MI NG @ L/ C 1 10 /1 3/ 93

P CO 02 80 1 PC O02 8 NT P R ELO CA TE S .B . DOO RS 1 1 2/ 05 /9 1 PC O1 54 01 P CO1 54 N TP N EW CA RP ET S TY LE 1 09 /0 2/ 93

P CO 02 90 1 PC O02 9 NT P C HEM E AS T RE BA R M OD IF IC AT ION 1 1 2/ 12 /9 1 PC O1 55 01 P CO1 55 N TP A DDL S UB CO NT RA CT WO RK @ L /C RO OF 1 08 /1 4/ 93

P CO 03 00 1 PC O03 0 NT P H ATC H & AN CH OR BO LT C HA NG ES 1 0 1/ 01 /9 2 PC O1 55 03 P CO1 55 S UBC ON TR AC T WO RK @ L/ C RO OF OP EN IN GS 1 no ne

P CO 03 10 1 PC O03 1 NT P A DDS W AL L PI PE S & B LI ND F LAN GE S 1 1 0/ 11 /9 1 PC O1 56 01 P CO1 56 N TP I NST AL L 30 " NJ BF V @ NO RT H B RA NC H 1 05 /0 6/ 94

P CO 03 20 1 PC O03 2 NT P E NVI RE X S. B. S LUD GE C OL L FIL L CO NC 1 0 1/ 02 /9 2 PC O1 56 03 P CO1 56 I NST L 30 " NJ B FV @ NO RT H BRA NC H RW PS 3 no ne

P CO 03 30 1 PC O03 3 NT P G F L ET TE R 12 /1 9/9 1 1 1 2/ 12 /9 1 PC O1 57 01 P CO1 57 N TP R EPL AC EM EN T LO UVE R @ L/ C 1 12 /1 0/ 93

P CO 03 40 1 PC O03 4 NT P G F M EM O 12 /2 0/ 91 DI ME NS IO NAL C HA NG ES 1 1 2/ 20 /9 1 PC O1 57 03 P CO1 57 I NST AL L RE PL AC EME NT L OU VE R @ L /C 1 no ne

P CO 03 50 1 PC O03 5 NT P G F L ET TE R 12 /1 9/9 5 DR WG C LAR IF IC AT N 1 1 2/ 19 /9 1 PC O1 60 01 P CO1 60 N TP A DD 2 TU RB ID IM ETE R IN DI CA TOR S TO G AC 1 01 /2 0/ 94

P CO 03 90 1 PC O03 9 NT P C HAN GE S P. S. D RAI N PI PI NG 1 0 1/ 29 /9 2 PC O1 61 01 P CO1 61 N TP A DD PR ES SU RE S WIT CH & A LA RM CO NT AC TS 1 03 /0 2/ 94

P CO 04 10 1 PC O04 1 NT P S PIL L CO NT AI NM ENT T AN K RE VIS IO NS 1 0 1/ 28 /9 2 PC O1 61 03 P CO1 61 P RES SU RE S WI TC H & A LA RM C ONT AC T HS PS 1 no ne

P CO 04 20 1 PC O04 2 NT P A DDL D RA IN C HA NNE L 1 0 1/ 28 /9 2 PC O1 62 01 P CO1 62 N TP A DD 4 SL OT D IF FUS ER S IN L /C 1 01 /1 0/ 94

P CO 04 50 1 PC O04 5 NT P G F M EM O 1/ 28 /9 2 R EF R FI #3 0 1 0 1/ 28 /9 2 PC O1 62 03 P CO1 62 A DD 4 SL OT D IF FUS ER S IN L /C 10 no ne

P CO 04 60 1 PC O04 6 NT P G F M EM O 2/ 18 /9 2 R EF R FI #4 7 1 0 2/ 18 /9 2 PC O1 63 01 P CO1 63 N TP A DD FI RE WA LL I N L /C 1 01 /1 4/ 94

P CO 04 70 1 PC O04 7 NT P C HEM B LD G CO L & J OI NT C HA NGE S 1 0 2/ 26 /9 2 PC O1 63 03 P CO1 63 A DD FI RE WA LL I N L /C T &M 13 no ne

P CO 04 90 1 PC O04 9 NT P F LUM E OV ER FL OW BO X EL EV R EV& R EL AT ED 1 0 7/ 09 /9 2 PC O1 65 01 P CO1 65 N TP C ONT RO L MO NI TO R F RA ME WO RK RE VI SI ON S 1 02 /2 4/ 94

P CO 05 10 1 PC O05 1 NT P P .S. T &M W OR K PER A AM #2 09 1 0 4/ 23 /9 2 PC O1 68 01 P CO1 68 N TP 8 " B YP AS S AR OU ND 10 " PL AN T S ER VI CE 1 04 /2 8/ 94

P CO 05 20 1 PC O05 2 NT P P .S. E LE CT RI C OPE NI NG S RE VIS IO N 1 0 4/ 23 /9 2 PC O1 68 03 P CO1 68 8 " B YP AS S AR OU ND 10 " PL AN T S ER VI CE 30 no ne

P CO 05 30 1 PC O05 3 NT P C .B. W AL L PO UR DE LA Y 1 0 5/ 06 /9 2 PC O1 71 01 P CO1 71 N TP M ODI FY L /C T OI LET P AR TI TI ONS 1 03 /2 5/ 94

P CO 05 40 1 PC O05 4 NT P H AND RA IL C HA NG ES 1 0 4/ 16 /9 2 PC O1 71 03 P CO1 71 P ROC UR EM EN T RE L/ C TO IL ET PA RT IT IO NS 52 no ne

P CO 05 70 1 PC O05 7 NT P C HEM B LD G SL AB TH IC KN ES S 1 0 5/ 22 /9 2 PC O1 77 01 P CO1 77 N TP C HLO RI NA TI ON S YST EM M OD IF ICA TI ON S 1 04 /0 7/ 94

P CO 05 80 1 PC O05 8 NT P A DDI TI ON AL W AT ERS TO P 1 0 5/ 29 /9 2 PC O1 77 03 P CO1 77 C HLO RI NA TI ON S YST EM M OD IF ICA TI ON S 20 no ne

P CO 05 90 1 PC O05 9 NT P C ERA MI C TI LE C HAN GE S 1 0 6/ 01 /9 2 PC O1 80 01 P CO1 80 N TP ADD L PR OJ EC T MIL LW OR K 1 01 /0 7/ 94

P CO 06 20 1 PC O06 2 NT P P .S. R AI N PI PI NG RE VI SI ON S 1 0 6/ 12 /9 2 PC O1 81 01 P CO1 81 N TP CEI LI NG C HA NG ES 1 02 /2 1/ 94

P CO 06 30 1 PC O06 3 NT P C HEM W ES T SU MP CH AN GE S 1 0 6/ 15 /9 2 PC O1 81 03 P CO1 81 ADD L ME TA L SO FFI T EN VI R LAB 2 no ne

P CO 06 40 1 PC O06 4 NT P D ELE TE C OM PU TE R A CC ES S FL OOR 1 0 4/ 16 /9 2 PC O1 81 04 P CO1 81 REM OV E IN SU L FRO M ME TA L CEI LI NG 3 no ne

P CO 06 50 1 PC O06 5 NT P D ELE TE F LO CC T ERR AZ ZO 1 0 4/ 10 /9 2 PC O1 82 01 P CO1 82 N TP E XPA NS IO N JO IN T B OO T RE TR OFI T 1 03 /1 7/ 94

P CO 06 60 1 PC O06 6 NT P A DD 1 LO UV ER 1 0 5/ 29 /9 2 PC O1 82 03 P CO1 82 P ROC UR EM T F/ E XPA NS N JO IN T B OO T RE TR O 20 no ne

P CO 06 70 1 PC O06 7 NT P S UBS TI TU TE G AT E F OR B FV 'S & BA CK FL OW 1 0 2/ 28 /9 2 PC O1 82 05 P CO1 82 T &M IN ST L EX PA NSN J OI NT B OOT R ET RO FI T 5 no ne

P CO 06 80 1 PC O06 8 NT P S .B. R OO F BE AM CO NS TR UC TI ON JO IN T 1 0 2/ 25 /9 2 PC O1 83 01 P CO1 83 N TP R AW WA TE R SA MP LE LI NE E XT ENS IO N 1 03 /3 0/ 94

P CO 07 00 1 PC O07 0 NT P C HAN GE P VC M AS ONR Y FL AS HI NG 1 0 6/ 25 /9 2 PC O1 84 01 P CO1 84 N TP O ZON E PI PI NG M ODI FI CA TI ON S 1 04 /1 8/ 94

P CO 07 10 1 PC O07 1 NT P M ODI FY P IP E SU PPO RT S 1 0 7/ 30 /9 2 PC O1 84 03 P CO1 84 P ROC UR ME NT F / OZO NE P IP IN G M OD S 15 no ne

P CO 07 20 1 PC O07 2 NT P A DD CA RP ET T O COM PU TE R RO OM 1 0 4/ 16 /9 2 PC O1 85 01 P CO1 85 N TP I NST AL L LA RG ER AN GL E CL IP S @ R OO F 1 07 /0 2/ 93

P CO 07 30 1 PC O07 3 NT P 7 /1/ 92 M OD IF IC ATI ON S PE R RFI #8 2 1 0 7/ 13 /9 2 PC O1 86 01 P CO1 86 N TP INC OR RE CT P IP E P AI NT IN G 1 11 /0 1/ 93

P CO 07 50 1 PC O07 5 NT P A DDL C AS T ST ON E 1 0 7/ 23 /9 3 PC O1 86 03 P CO1 86 F IX IN CO RR EC T PIP E PA IN TI NG 3 no ne

P CO 07 60 1 PC O07 6 NT P A AM FW O# 08 69 W ALL P OU R DE LAY 1 0 7/ 16 /9 2 PC O1 87 01 P CO1 87 N TP VAR IO US C ON TR ACT D WG C HA NGE S 1 03 /0 2/ 93

P CO 07 90 1 PC O07 9 NT P P .S. T AP ER ED R OOF M OD IF IC ATI ON S 1 0 6/ 16 /9 3 PC O1 88 01 P CO1 88 N TP LEV EL P RO BE S UPP OR T BR AC KET 1 03 /2 5/ 94

P CO 08 10 1 PC O08 1 NT P C ORE D RI LL O PE NIN GS @ C .B . 1 0 7/ 22 /9 2 PC O1 90 01 P CO1 90 N TP APP LY S EA LE R TO EX PO SE D INT B RI CK 1 05 /2 0/ 94

P CO 08 20 1 PC O08 2 NT P A DDL F LO OR O PE NIN GS @ P IL OT TE ST E Q 1 0 9/ 15 /9 2 PC O1 90 03 P CO1 90 INT M AS ON RY C LEA NI NG & S EAL ER 10 no ne

P CO 08 40 1 PC O08 4 NT P C HEM B LD G 2N D FL CO NS TR J OIN T DE LA Y 1 0 9/ 16 /9 2 PC O1 91 01 P C01 91 N TP L&N C ON TR AC T EXT EN SI ON R EQU ES T 1 02 /0 1/ 94

P CO 08 50 1 PC O08 5 NT P P .S. R OO F PL AN K C HA NG ES 1 0 6/ 24 /9 2 PC O1 92 01 P CO1 92 N TP POS T CL 2/ GA C EFF L SA MP LE PT C HA NG ES 1 05 /2 0/ 94

P CO 08 90 1 PC O08 9 NT P P IPE B LA NK -O FF PL AT E @ 42 " F UT P PG 1 0 3/ 24 /9 2 PC O1 92 03 P CO1 92 A DDL W OR K 1 no ne

P CO 09 00 1 PC O09 0 NT P A LUM IN UM S UP PO RT FR AM IN G & C UR B @ PS 1 0 9/ 04 /9 2 PC O1 94 01 P CO1 94 N TP HAN DI CA PP ED P ARK IN G RE VI SIO NS 1 06 /0 8/ 94

P CO 09 00 3 PC O09 0 F ABR & I NS TA LL MC C SU PP OR T 3 3 n on e PC O1 94 03 P CO1 94 HAN DI CA PP ED P ARK IN G RE VI SIO NS 10 no ne

P CO 09 10 1 PC O09 1 NT P R E M AS ON RY , RO OFI NG , TE RR AZZ O 1 0 9/ 04 /9 2 PC O1 95 01 P CO1 95 N TP ADD R EG UL AT OR S - A IR P UR GE ME TE R CO N 1 06 /0 8/ 94

P CO 09 3B 1 PC O09 3b NT P S TRU CT UR AL S TE EL CH AN GE S 1 0 5/ 20 /9 2 PC O1 95 03 P CO1 95 ADD R EG UL AT OR S 1 no ne

P CO 09 3C 1 PC O09 3c NT P S TRU CT UR AL S TE EL CH AN GE S 1 0 6/ 16 /9 2 PC O1 96 01 P CO1 96 N TP INS TA LL V AL VE @ 48 " RA W WAT ER L IN E 1 06 /1 4/ 94

P CO 09 3F 1 PC O09 3f NT P S TRU CT UR AL S TE EL CH AN GE S 1 0 9/ 25 /9 2 PC O1 96 03 P CO1 96 A DDL W OR K 2 no ne

P CO 09 3H 1 PC O09 3h NT P S TRU CT UR AL S TE EL CH AN GE S 1 1 2/ 16 /9 2 PC O1 97 01 P CO1 97 N TP COR E DR IL L VE NT HO LE S IN P. S. S UM P 1 06 /0 1/ 94

P CO 09 40 1 PC O09 4 NT P M ASO NR Y CH AN GE S 1 0 1/ 04 /9 3 PC O1 97 03 P CO1 97 A DDL W OR K 3 no ne

P CO 09 7A 1 PC O09 7a NT P M ASO NR Y CH AN GE S C HL OR ,L /C BA TH ,O ZO NE 1 1 1/ 10 /9 2 PC O1 98 01 P CO1 98 N TP CHA NG E HD WE D OOR S 20 2 & 203 1 06 /1 6/ 94

P CO 09 7C 1 PC O09 7c NT P M ASO NR Y CH AN GE S C HL OR ,L /C BA TH ,O ZO NE 1 0 2/ 10 /9 3 PC O1 99 01 P CO1 99 N TP LOW ER G AC S AM PLE L IN E FO OT VA LV E 1 06 /1 6/ 94

P CO 10 00 1 PC O10 0 NT P B EAM 3 0A 1 1 0/ 13 /9 2 PC O2 01 01 P CO2 01 N TP FUT F LO RI DE C HEM F D CA RR IER C ON DU IT 1 06 /1 6/ 94

P CO 10 10 1 PC O10 1 NT P A DD PI PE S UP PO RT CH AN NE LS @ GA C P. G. 1 1 1/ 16 /9 2 PC O2 01 03 P CO2 01 A DDL W OR K 2 no ne

P CO 10 20 1 PC O10 2 NT P L ATE RA L BR AC IN G R EQ MT S 1 1 2/ 01 /9 2 PC O2 03 01 P CO2 03 N TP PIT OT T UB E FL OW ME TE R XM TR RE LO C 1 06 /1 6/ 94

P CO 10 5B 1 PC O10 5b NT P M ODI FI ED R OO F PLA NK 1 0 3/ 20 /9 3 PC O2 03 03 P CO2 03 ADD L WO RK 2 no ne

P CO 10 5C 1 PC O10 5c NT P M ODI FI ED R OO F PLA NK 1 0 3/ 25 /9 3 PC O2 04 01 P CO2 04 N TP GAR AG E RE VI SI ONS 1 07 /1 2/ 94

P CO 10 5C 3 PC O10 5 F ABR M OD IF IE D ROO F PL AN K 2 0 n on e PC O2 04 03 P CO2 04 A DDL P RO CU RE ME NT 25 no ne

P CO 10 70 1 PC O10 7 NT P E XTR A NE LS ON S TUD S @ L/ C 1 0 2/ 04 /9 3 PC O2 04 05 P CO2 04 A DDL W OR K U /S PP G 2 no ne

P CO 10 80 1 PC O10 8 NT P S OFF IT & L IN TE L T O CO NC EA L D UC TW OR K 1 0 1/ 20 /9 3 PC O2 11 01 P CO2 11 N TP 48" R AW W AT ER MA IN T IE -I N T O IN TE RI M 1 08 /2 9/ 94

P CO 10 90 1 PC O10 9 NT P R EV BA SE P LA TE , L IN TE L, M ASO NR Y 1 0 3/ 25 /9 3 PC O2 11 03 P CO2 11 PRO CU RE A DD L 48" P IP E 55 no ne

P CO 11 00 1 PC O11 0 NT P S TRU CT UR AL S TE EL MO DI FI CA TIO NS 1 0 4/ 19 /9 3 PC O2 11 05 P CO2 11 INS TA LL T IE -I N P IP E 14 no ne

P CO 11 00 3 PC O11 0a R EPA IR S TO L IM E S IL O ST R STL 6 n on e PC O2 12 01 P CO2 12 N TP ADD L FI LT ER B ACK WA SH T UR BID OM ET ER S 1 06 /1 4/ 94

P CO 11 00 4 PC O11 0b R EPA IR S TO E LE VAT OR S HA FT ST R ST L 5 n on e PC O2 14 01 P CO2 14 N TP GAR AG E RO OF P LAN K CH AN GE S 1 08 /1 7/ 94

P CO 11 10 1 PC O11 1 NT P P IPE M OD S @ WA TER M ET ER C HAM BE R 1 0 4/ 12 /9 3

P CO 11 20 1 PC O11 2 NT P A DDL L IN TE L @ COR RI DO R 11 6 1 0 2/ 03 /9 3

ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD

DUR DAYS DUR DAYS DUR DAYS

PCO00501 1020 0 FS 2 0 PCO097A1 3370 0 FS 3 0 PCO18403 2250 0 FS 15 0

PCO00501 1070 0 FS 2 0 PCO097C1 R3115 0 FS 1 0 PCO18501 3065 0 FS 10 0

PCO00701 2315 0 FS 3 0 PCO10001 2065 0 FS 2 0 PCO18601 PCO18603 0 FS 0 0

PCO00801 3310 0 FS 3 0 PCO10101 2060 1 FF 1 0 PCO18603 3031 0 FS 0 0

PCO00901 3015 0 FS 2 0 PCO10201 2160 0 FS 2 0 PCO18603 R2799 0 FS 0 0

PCO00901 3025 0 FS 9 0 PCO10201 2455 0 FS 2 0 PCO18701 3360 0 FS 1 0

PCO01001 1100 0 FS 6 0 PCO10201 4120 0 FS 2 0 PCO18701 4125 0 FS 2 0

PCO01001 1105 0 FS 12 0 PCO105B1 2225 5 FF 2 0 PCO18801 6015 0 FS 1 0

PCO01201 2335 0 FS 0 10 PCO105C1 PCO105C3 0 FS 0 0 PCO19001 PCO19003 0 FS 0 0

PCO01301 1110 0 FS 1 0 PCO105C3 2185 0 FS 0 0 PCO19003 1390 0 FS 0 0

PCO01401 1055 0 FS 0 0 PCO10701 5030 0 FS 2 0 PCO19101 R1321 0 FS 0 0

PCO01401 1100 0 FS 4 0 PCO10801 4129 2 FF 2 0 PCO19101 R6165 20 FF 0 0

PCO01601 2325 0 FS 0 0 PCO10901 5030 0 FF 0 15 PCO19101 136106 15 FF 0 0

PCO01701 1100 0 FS 2 2 PCO11001 PCO11003 0 FS 0 0 PCO19201 PCO19203 0 FS 0 0

PCO01801 2425 0 FS 0 0 PCO11001 PCO11004 0 FS 0 0 PCO19203 1515 0 FS 0 0

PCO02001 2455 0 FS 1 0 PCO11003 4120 0 FS 0 0 PCO19401 PCO19403 0 FS 0 0

PCO02101 3185 0 FS 0 0 PCO11004 4120 0 FS 0 0 PCO19403 R4515 0 FS 0 0

PCO02201 3150 0 FS 0 0 PCO11101 6335 4 FF 0 0 PCO19501 PCO19503 0 FS 0 0

PCO02201 3155 0 FS 0 0 PCO11201 2450 3 FF 3 0 PCO19503 1500 5 FF 0 0

PCO02601 3155 0 FS 0 0 PCO11601 4120 1 FF 2 0 PCO19601 PCO19603 0 FS 0 0

PCO02701 3030 0 FS 1 0 PCO11701 R4800 0 FS 10 0 PCO19603 1515 0 FS 0 0

PCO02801 3060 0 FS 0 0 PCO11701 R4801 0 FS 2 0 PCO19701 PCO19703 0 FS 0 0

PCO02901 3305 0 FS 0 0 PCO11701 R4802 0 FS 5 0 PCO19703 1515 0 FS 0 0

PCO03001 1140 0 FS 2 0 PCO11701 R4803 0 FS 2 0 PCO19801 1390 5 FF 0 0

PCO03001 2425 0 FS 1 0 PCO11701 R4804 0 FS 2 0 PCO19901 1515 0 FS 0 0

PCO03101 2020 0 FS 3 0 PCO11701 R4805 0 FS 3 0 PCO20101 PCO20103 0 FS 0 0

PCO03201 3030 0 FS 12 0 PCO12001 5050 2 FF 2 0 PCO20103 1515 0 FS 0 0

PCO03301 3085 0 FS 0 0 PCO12101 4120 10 FF 1 0 PCO20301 PCO20303 0 FS 0 0

PCO03401 2330 0 FS 0 0 PCO12401 2230 0 FS 3 0 PCO20303 1515 0 FS 0 0

PCO03501 3410 0 FS 0 0 PCO12401 R4800 0 FS 2 0 PCO20401 PCO20403 0 FS 0 0

PCO03901 2415 0 FS 0 0 PCO12601 5030 0 FS 1 0 PCO20403 PCO20405 0 FS 0 0

PCO03901 2425 0 FS 5 0 PCO12801 1300 1 FF 1 0 PCO20405 5205 0 FS 0 0

PCO04101 5315 0 FS 1 0 PCO12801 4540 0 FS 1 0 PCO20405 5260 30 FS 0 0

PCO04201 1140 0 FS 1 0 PCO13101 2170 1 FF 0 0 PCO21101 PCO21103 0 FS 0 0

PCO04201 3080 0 FS 0 0 PCO13101 3371 1 FF 0 0 PCO21103 PCO21105 3 FS 0 0

PCO04501 4055 0 FS 0 0 PCO13601 R1140 0 FS 2 0 PCO21105 1390 0 FS 0 0

PCO04601 1140 0 FS 0 0 PCO14101 R1495 0 FS 1 0 PCO21105 R4515 0 FS 0 0

PCO04701 4040 0 FS 0 0 PCO14501 1200 0 FS 2 0 PCO21201 R2627 3 FF 3 0

PCO04701 4045 0 FS 1 0 PCO14501 4405 0 FS 1 0

PCO04901 3085 0 FS 4 20 PCO14801 1300 0 FS 2 0

PCO05101 2425 0 FS 6 12 PCO14901 R3665 0 FS 2 0

PCO05201 2425 0 FS 0 0 PCO15001 4135 0 FS 1 0

PCO05301 3415 0 FS 1 0 PCO15101 R1321 1 FF 1 0

PCO05401 2615 0 FS 0 0 PCO15201 R4030 0 FS 2 0

PCO05701 4030 0 FS 0 0 PCO15401 1225 0 FS 0 0

PCO05801 3315 0 FS 1 0 PCO15401 1325 0 FS 0 0

PCO05901 1260 0 FS 0 0 PCO15401 5190 0 FS 0 0

PCO05901 1360 0 FS 0 0 PCO15501 PCO15503 0 FS 0 0

PCO05901 5155 0 FS 0 0 PCO15503 5090 0 FS 0 0

PCO06201 2450 0 FS 1 0 PCO15601 PCO15603 0 FS 0 0

PCO06301 4060 0 FS 2 0 PCO15603 1505 0 FS 0 0

PCO06401 1325 0 FS 0 0 PCO15701 PCO15703 0 FS 0 0

PCO06501 1325 0 FS 0 0 PCO15703 R4115 0 FS 0 0

PCO06601 1260 0 FS 0 0 PCO16001 R1321 1 FF 1 0

PCO06701 2000 0 FS 0 0 PCO16001 136106 15 FF 1 0

PCO06801 3040 0 FS 12 0 PCO16101 PCO16103 0 FS 0 0

PCO07001 3060 0 FS 0 0 PCO16103 1500 0 FS 0 0

PCO07101 2050 0 FS 1 0 PCO16201 PCO16203 0 FS 0 0

PCO07201 1325 0 FS 0 0 PCO16203 R4115 0 FS 0 0

PCO07301 4615 0 FS 2 5 PCO16301 PCO16303 0 FS 0 0

PCO07501 R1495 0 FS 2 0 PCO16303 R4115 0 FS 0 0

PCO07601 4615 2 FS 2 0 PCO16501 R1321 5 FF 0 0

PCO07901 3390 0 FS 2 0 PCO16801 PCO16803 0 FS 0 0

PCO08101 3505 0 FS 2 0 PCO16803 1515 0 FS 0 0

PCO08201 4060 0 FS 2 0 PCO17101 PCO17103 0 FS 0 0

PCO08401 4060 0 FS 2 0 PCO17103 5155 0 FS 3 0

PCO08501 2465 0 FS 1 22 PCO17701 PCO17703 0 FS 0 0

PCO08901 4005 0 FS 1 0 PCO17703 1505 0 FS 0 0

PCO09001 PCO09003 0 FS 0 0 PCO18001 5155 1 FF 0 0

PCO09003 2610 0 FS 0 0 PCO18101 PCO18103 0 FS 0 0

PCO09101 2180 0 FS 1 0 PCO18101 PCO18104 0 FS 0 0

PCO09101 3390 0 FS 1 0 PCO18103 5155 1 FF 0 0

PCO09101 R3395 0 FS 2 0 PCO18104 5155 1 FF 0 0

PCO093B1 2435 0 FS 1 0 PCO18201 PCO18203 0 FS 0 0

PCO093C1 5045 0 FS 2 0 PCO18203 PCO18205 0 FS 0 0

PCO093F1 5045 0 FS 1 0 PCO18205 2041 0 FS 2 0

PCO093H1 3360 0 FS 0 0 PCO18205 3031 0 FS 0 0

PCO093H1 3371 0 FS 1 0 PCO18301 1505 0 FS 1 0

PCO09401 1200 2 FF 2 0 PCO18301 5320 0 FF 2 0

PCO09401 3370 0 FS 1 0 PCO18401 PCO18403 0 FS 0 0

1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N

1 0 0 5

M O B I L I Z A T I O N

3 0 0 0

S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5

3 0 1 5

S E D B A S I N ( N , S , E ) W A L L t o 2 6 4

3 4 0 0

P R E - O Z O N E C O N T A C TB A S I N E X C A V t o 2 4 0 . 2 5

4 0 8 0

C H E M W E S T I N S T LC O N T A I N M E N T L I N E R

4 1 9 0

C H E M W E S T R / SS P A R E B A T C H T A N K

4 1 7 2

C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S

1 3 0 0

2 N D F L A R C HI N T E R N A L M A S O N R Y

R 1 3 5 5

C H E M W E S T 2 n dF L O O R C A R P E T

1 3 0 5

2 N D F L A R C HC A R P E N T R Y / D R Y W A L L

2 2 3 0

O Z O N E / T R A N S F O R M E R R O O F I N G

4 1 2 5

C H E M W E S TM A S O N R Y T O 2 8 0

3 0 9 0

P I P E G A L L E R Y I N S T L L G P P G

3 3 2 0

C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9

3 4 0 5

C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G

1 0 2 0

S E D B A S I NE X C A V t o 2 3 6 . 1 5

1 0 7 0

S E D B A S I NS O G @ 2 3 6 . 4 0

2 3 2 5

F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

3 4 1 0

P R E - O Z O N E C O N T A C TB A S I N S O G @ 2 4 2 . 5 0

3 3 1 0

C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0

2 3 9 0

F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3

3 1 0 0

P I P E G A L L E R YE L E V S L A B @ 2 5 6

3 1 0 5

P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4

2 5 1 0

F I L T E R # 1 - 6 W A L K W A Y @2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]

2 2 5 0

O Z O N E R / S 6 "8 " O Z O N E P P G

R 1 3 2 0

C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T

R 1 3 4 5

C H E M W E S T 2 n d F L O O RR U B B E R T I L E F L O O R

R 3 3 1 0

G A C C O N T A C T O R -P . G . S A M P L E P U M P S

2 5 2 0

P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7

3 1 1 5

P I P E G A L L E R Y A R E AE L E V S L A B @ 2 6 4 . 6 7

2 3 5 5

F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7

2 4 2 5

P U M P S T A E L E VS L A B @ 2 5 0

2 3 7 0

F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

3 0 8 0

P I P E G A L L E R Y S O G @ 2 4 2 . 5 0

1 0 1 0

C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5

2 3 0 0

F L U M E S E X C A Vt o 2 2 4 . 7 5

3 0 7 5

P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G

2 3 4 0

F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

2 3 5 0

F L U M E F I L T 1 - 2 W A L Lt o H A U N C H t o 2 4 8 . 6 7

4 3 2 0

C H E M W E S T / S E T T L E D / M I X E DB Y P A S S 4 8 " 5 4 " 6 6 " P P G

2 5 0 0

F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N

2 5 2 5

P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S

R 3 3 2 0

G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S

R 1 0 6 0

C H E M W E S T 2 n d F L O O RI N S T R U M E N T A T I O N R E V I E W

R 5 0 6 0

G A R A G E -P A I N T I N G

R 5 0 5 0

G A R A G E - H O L L O WM E T A L D O O R S

4 4 6 0

C H E M W E S T R / SC H E M F E E D L I N E S

4 1 4 5

C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T

R 4 8 0 0

A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E

4 1 7 5

C H E M W E S T R / SK M n O 4 F E E D E R

2 3 9 5

F L U M E W A L Lt o 2 6 3 . 8 3

4 3 1 0

C H E M W E S T / R A W W A T E R 4 8 "P P G w / P R E C O N T A C T B Y P A S S

4 0 5 5

C H E M W E S TW A L L S t o 2 6 3

2 3 8 0

F L U M E W A L L &S L A B t o 2 5 0 . 1 6

2 3 7 5

F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2

1 1 5 0

F L O C B A S I NC O N C F I L L t o 2 4 7

3 0 2 0

P I P E G A L L E R Y S T R U C B F I L L

1 0 1 5

P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0

2 3 1 5

F L U M E S / P U M PS T A S O G @ 2 2 7

2 3 3 0

F L U M E F I L T 3 - 6 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

1 0 8 0

F L O C B A S I N F O O T I N GW A L L t o 2 4 7

2 3 4 5

F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2

3 3 1 5

C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0

4 0 6 0

C H E M W E S T B E A M S& S L A B S t o 2 6 4

4 1 0 0

C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3

2 5 3 0

P I P E G A L L E R Y / F I L T E R R O O F I N G

R 1 2 7 0

C H E M W E S TP O L Y M E R L I N E S

R 1 3 4 0

C H E M W E S T 2 n dF L O O R V C T F L O O R

R 5 0 3 5

G A R A G E -M I S C . M E T A L S

R 4 5 3 5

S I T E W O R K - C H A I NL I N K F E N C E

R 1 3 5 0

C H E M W E S T 2 n d F L O O RQ U A R R Y T I L E F L O O R

6 1 8 0

C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P

3 5 2 5

P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7

4 1 2 0

C H E M W E S TE L E V S L A B @ 2 7 6

3 3 2 5

C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7

3 3 0 0

C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5

1 0 7 5

F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5

1 0 5 0

C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S

1 0 6 0

P U M P S T A I N S T LR O C K A N C H O R S

3 1 5 0

F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M

3 3 0 5

C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0

3 3 6 0

C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7

3 3 7 5

C H E M B L D G E A S T M A S O N R Y T O 2 8 0

R 1 2 1 5

C H E M W E S TL I M E F E E D E R S

3 3 9 0

C H E M B L D GE A S T R O O F I N G

R 1 2 4 5

C H E M W E S TF I L T E R A I D L I N E S

R 1 3 0 5

C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E

R 4 6 6 5

Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( W E S T )

R 4 6 6 0

Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )

R 1 3 1 0

C H E M W E S T L A BI N S T R U M E N T A T I O N

R 1 2 6 5

C H E M W E S T P O L Y M E RM I X I N G S Y S T E M

R 4 8 0 4

A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .

R 1 7 4 1

C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7

2 4 5 5

P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7

1 1 2 0

O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K

1 0 6 5

P U M P S T AS O G @ 2 2 2

3 0 0 5

S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7

1 1 2 5

O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5

1 1 3 5

C L E A R W E L L / O Z O N E I N S T L7 2 x 4 8 S L U I C E G A T E S

2 4 5 0

P U M P S T AM A S O N R Y t o 2 8 3

R 1 7 4 0

C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6

R 1 0 3 5

C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R

6 1 3 5

C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S

R 1 3 1 5

C H E M W E S TL A B P I P I N G

R 4 5 9 0

Y A R D P I P E - 6 " T I E - I NT O H Y D R A N T ( N O R T H W E S T )

5 3 6 0

S I T E S E E D I N G& L A N D S C A P I N G

4 4 1 0

C H E M W E S T A L U M S T O R / SM I S C P P G & E Q : S E A L W A T E R

6 1 3 0

C H E M W E S T 3 R D F L R / SF E E D P U M P S & T A N K S

3 5 3 0

P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T

3 5 2 0

P R E - O Z O N E C O N T A C TB A S I N M A S O N R Y t o 2 8 0

3 3 7 0

C H E M B L D G E A S T M A S O N R Y T O 2 6 5

4 0 5 0

C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7

1 1 4 0

C L E A R W E L L / O Z O N EE L E V S L A B @ 2 5 0 + / -

1 1 1 5

O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0

1 1 1 0

O Z O N E W A L L S t o 2 4 8 . 5 0

1 1 0 0

C L E A R W E L L / O Z O N E S O G @ 2 2 7

3 1 5 5

F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4

3 4 1 5

P R E - O Z O N E C . B . E X T W A L Lt o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3

3 3 4 5

C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0

R 1 7 6 0

C H E M E A S T G L A Z E DS T R U C T U R A L T I L E

2 5 0 5

F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]

6 3 1 0

S E D B A S I N M I S CP P G & E Q U I P

R 2 6 2 7

F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N

4 4 5 5

C H E M W E S T R / S 1 5 "P V C & S A M P L E L I N E S

5 3 5 0

S I T E F I N EG R A D I N G

R 4 5 1 0

S I T E W O R K - D E M O@ P R O P A N E T A N K S

4 4 2 0

C H E M W E S T A L U M S T OR / S I N S T R U M E N T A T I O N

R 2 6 3 5

F I L T E R S - P . G .S A M P L E P U M P S

2 6 0 0

P U M P S T A M I S CP P G & E Q U I P

4 1 8 0

C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K

4 3 0 0

C H E M W E S T R / SP O L Y P H O S P H A T E T A N K

4 3 0 5

C H E M W E S T I N S T LA L U M S T O T A N K S

4 1 8 5

C H E M W E S T R / SF I L T E R A I D B A T C H T A N K

2 2 0 0

G A C A R E A M I S CP P G & E Q U I P

4 5 0 5

C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G

R 5 4 2 5

N O R T H B R A N C HI N T A K E - P A I N T I N G

R 5 4 2 0

N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N

4 5 1 5

C H E M W E S T B L O W E R R O O M R / S M I S C P P G & E Q U I P

6 3 0 5

S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P

R 1 4 1 5

C H E M W E S T 3 r dF L O O R C . M . U .

3 0 6 5

S E D B A S I N / F L O CB A S I N R O O F I N G

3 1 1 0

P I P E G A L L E R Y I N S T LS M P P G & V A L V E S

R 1 4 5 0

C H E M W E S T 2 n d F L O O RD O O R S & W I N D O W S

6 4 2 5

N O R T H B R A N C H R E P L A C EP U M P S # 1 & # 2 & P P G

5 2 1 0

G A R A G E F T GF D N @ 2 4 4

1 5 0 0

O P E R A T I O N A LP U N C H L I S T

R 1 3 3 0

C H E M W E S T 2 n d F L O O RE P O X Y T E R R A Z Z O

R 2 6 2 5

F I L T E R S - P . G .I N S T R U M E N T A T I O N R E V I E W

6 3 0 0

S E D B A S I NR / S 6 " 8 " P P G

4 1 2 6

C H E M W E S TM A S O N R Y T O 2 8 8

4 2 0 0

C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9

1 2 0 0

1 S T F L A R C HI N T E R N A L M A S O N R Y

1 3 3 5

2 N D F L A R C H M I L L W O R K

R 1 1 2 5

C H E M W E S T D I PP L A N T S E R V I C E

1 5 1 0

P R O C E S SP A I N T I N G

5 2 0 5

G A R A G EE X C A V t o 2 4 3

1 5 1 5

I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N

R 1 3 2 1

I N S T A L L S O F T W A R E& D E B U G S Y S T E M

4 4 6 5

C H E M W E S T R / SM I S C P P G & E Q U I P

R 1 4 4 5

C H E M W E S T 1 s tF L O O R D O O R S

4 1 2 7

C H E M W E S T M A S O N R YT O P A R A P E T

4 1 6 0

C H E M W E S T R / SL I M E S T O S I L O S

4 1 6 5

C H E M W E S T R / SL I M E F E E D E R H O P P E R S

R 1 4 9 5

C H E M W E S TC A S T S T O N E

4 2 0 5

C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9

R 1 1 1 5

C H E M W E S T C O P P E RW A T E R L I N E S

1 5 2 0

I N I T I A L M E C H P E R FT E S T P U N C H L I S T

1 5 2 5

F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N

6 1 9 0

C H E M W E S T 3 R D F I L T E RA I D M I S C P P G & E Q U I P

4 1 7 0

C H E M W E S T R / S L I M ED U S T C O L L E C T O R S

4 1 9 5

C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G

R 2 6 0 5

F I L T E R S - P . G .M I S C . P I P E

R 1 3 2 2

C H E M W E S T 3 r d F L O O RI N S T R U M E N T A T I O N R E V I E W

5 2 0 0

G A R A G E D E M O E X G1 6 " W A T E R M A I N

5 2 1 5

G A R A G E S O G@ 2 4 3 . 8 3

R 1 3 3 5

C H E M W E S T 2 n d F L O O RC E R A M I C T I L E F L O O R S / W A L L S

R 3 3 0 5

G A C C O N T A C T O R -I N S T R U M E N T A T I O N R E V I E W

4 1 3 5

C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3

R 4 8 0 5

A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R

R 1 3 2 5

C H E M W E S T 1 s t F L O O RR U B B E R T I L E F L O O R

5 2 2 0

G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -

5 2 2 5

G A R A G E B F I L L

R 1 3 7 5

C H E M W E S T 2 n d F L O O RA C O U S T I C A L W A L L T R E A T M E N T

1 2 0 5

1 S T F L A R C HC A R P E N T R Y / D R Y W A L L

4 2 1 0

C H E M W E S TR / S E L E V A T O R

1 3 5 5

2 N D F L A R C H P A I N T I N G

5 2 3 0

G A R A G ES O G @ 2 4 8

5 2 3 5

G A R A G EM A S O N R Y

4 3 4 5

C H E M W E S T R E C I R C M I S CP P G & E Q : S E A L W A T E R S Y S

4 4 0 0

C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P

5 2 4 0

G A R A G E S T RS T L @ 2 6 0 + / -

5 2 5 0

G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7

4 4 0 5

C H E M W E S T R / SA i r , A . F . , A . V . P P G

4 4 3 0

C H E M W E S T R / S R A WW A T E R S A M P L E P U M P

5 2 5 5

G A R A G ER O O F I N G

5 2 6 0

G A R A G EA R C H D E T A I L S

4 5 4 0

C H E M W E S T L I M E S T O M I S C P P G & E Q U I P

6 1 1 5

C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P

R 5 0 2 5

G A R A G E - F / R / PS E T T L I N G B A S I N S

5 2 9 0

G A R A G E B U I L D I N GP U N C H L I S T

1 3 9 0

A R C H I T E C T U R A L &F I N A L P U N C H L I S T

R 5 0 2 0

G A R A G E - F / R / PC O N C R E T E P A D S

R 1 4 1 0

C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E

R 1 3 8 5

C H E M W E S T 2 n d F L O O RA C O U S T I C A L T I L E C E I L I N G

R 5 0 5 5

G A R A G E -C O I L I N G D O O R S

R 1 3 9 5

C H E M W E S T 2 n d F L O O RG Y P S U M B O A R D C E I L I N G

R 1 3 9 0

C H E M W E S T 2 n d F L O O RM E T A L C E I L I N G

R 1 0 5 5

C H E M W E S T 1 s t F L O O RI N S T R U M E N T A T I O N R E V I E W

1 3 2 5

2 N D F L A R C H F L O O R I N G

Pl ot D at e 15 FE B9 5Da ta D at e 10 MA Y9 1Pr oj ec t St ar t10 MA Y9 1Pr oj ec t Fi ni sh26 NO V9 3

(c ) Pr im av er a S ys te ms , Inc .

A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P

P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T

W 0 0 X P a g e 1 o f 1

1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N

1 0 1 0

C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5

1 1 0 5

C L E A R W E L L W A L L S t o 2 5 0

1 1 3 5

C L E A R W E L L / O Z O N E I N S T L 7 2 x 4 8 S L U I C E G A T E S

2 0 6 5

G A C P P G G A L L E R YE L E V S L A B @ 2 6 9 . 6 7

R 3 3 9 5

G A C C O N T A C T O RP A R A P E T M A S O N R Y

4 1 3 5

C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3

4 1 2 5

C H E M W E S T M A S O N R Y T O 2 8 0

3 4 0 0

P R E - O Z O N E C O N T A C T B A S I N E X C A V t o 2 4 0 . 2 5

1 0 7 5

F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5

1 0 5 5

C L E A R W E L L / O Z O N E 2 S O G @ 2 2 1

1 0 5 0

C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S

1 0 1 5

P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0

1 0 6 5

P U M P S T AS O G @ 2 2 2

2 3 3 5

P U M P S T A T I O N W A L L S t o 2 4 8 . 6 7

1 1 2 5

O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5

3 3 1 5

C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0

4 0 3 0

C H E M W E S T W A S T E W A T E RS U M P G R A D E B E A M # 1 7 & 1 8

2 1 8 5

G A C A R E A 8 "D E C K P A N E L @ 2 8 4

R 4 8 0 3

A S S O R T E D R O O F T O PW O R K C H L O R I N E B U I L D I N G

6 0 4 5

C H E M E A S T C L 2 S T O R / S M O N O R A I L

3 3 7 1

C H E M B L D G E A S TM O N O R A I L S U P P O R T S T E E L

2 1 6 0

O Z O N E / T R A N S F O R M E RE L E V S L A B # 1 @ 2 6 4 . 6 7

3 3 4 5

C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0

3 4 1 0

P R E - O Z O N E C O N T A C T B A S I N S O G @ 2 4 2 . 5 0

3 0 1 5

S E D B A S I N ( N , S , E ) W A L L t o 2 6 4

1 0 6 0

P U M P S T A I N S T LR O C K A N C H O R S

1 0 2 0

S E D B A S I NE X C A V t o 2 3 6 . 1 5

1 0 7 0

S E D B A S I NS O G @ 2 3 6 . 4 0

1 1 0 0

C L E A R W E L L / O Z O N E S O G @ 2 2 7

1 1 1 0

O Z O N E W A L L S t o 2 4 8 . 5 0

3 1 8 5

F L O C B A S I NW A L K W A Y S @ 2 6 4 . 6 7

2 5 0 0

F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N

2 5 0 5

F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]

4 5 0 5

C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G

2 4 5 0

P U M P S T A M A S O N R Y t o 2 8 3

3 0 8 0

P I P E G A L L E R Y S O G @ 2 4 2 . 5 0

2 3 2 5

F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

2 3 1 5

F L U M E S / P U M PS T A S O G @ 2 2 7

2 3 0 0

F L U M E S E X C A Vt o 2 2 4 . 7 5

3 0 0 0

S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5

2 3 5 0

F L U M E F I L T 1 - 2 W A L L t o H A U N C H t o 2 4 8 . 6 7

2 4 2 5

P U M P S T A E L E V S L A B @ 2 5 0

4 3 2 0

C H E M W E S T / S E T T L E D / M I X E D B Y P A S S 4 8 " 5 4 " 6 6 " P P G

5 0 5 0

L O B B Y / C O N F E R E N C EC A S T S T O N E & G R A N I T E

R 1 1 2 5

C H E M W E S T D I PP L A N T S E R V I C E

5 0 9 0

L O B B Y / C O N F R O O F I N G

R 4 1 1 5

L O B B Y / C O N F E R E N C EM E T A L C E I L I N G S Y S T E M

6 1 1 5

C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P

R 1 2 1 5

C H E M W E S TL I M E F E E D E R S

R 3 1 1 5

O Z O N E E Q U I P M E N T B L D G .C A S T S T O N E / B R I C K

2 4 5 5

P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7

3 3 2 0

C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9

2 4 3 5

P U M P S T A M E Z Z E R E C TS T R U C S T E E L t o 2 8 3

1 1 2 0

O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K

3 0 2 0

P I P E G A L L E R Y S T R U C B F I L L

1 0 8 0

F L O C B A S I N F O O T I N GW A L L t o 2 4 7

3 0 0 5

S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7

2 0 0 0

C L E A R W E L L @ G A C P P G G A L L E R Y W A L L & S L A B @ 2 3 9 . 9 2

3 0 8 5

P I P E G A L L E R Y W A L L t o 2 5 4 . 8 3

4 0 4 5

C H E M W E S T F T GW A L L b e l o w 2 4 6

1 2 0 0

1 S T F L A R C H I N T E R N A L M A S O N R Y

R 1 4 4 5

C H E M W E S T 1 s tF L O O R D O O R S

3 0 3 1

S E D B A S I N W A T E R T E S T

2 1 8 0

G A C A R E A M A S O N R Y

3 1 0 5

P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4

2 0 5 0

G A C A R E A W A L L S & E L E V S L A B t o 2 6 8 . 6 7

3 0 3 0

S E D B A S I N E L E VS L A B @ 2 6 4 . 6 7

3 0 2 5

S E D B A S I N L A U N D E R C O L S W A L L S B E A M S

1 1 5 0

F L O C B A S I NC O N C F I L L t o 2 4 7

2 4 1 5

P U M P S T A P I P E A R E AW A L L S 2 3 6 t o 2 4 8 . 6 7

2 3 5 5

F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7

4 0 0 5

C H E M W E S T R / S4 2 " U / S F U T P P G

2 3 9 5

F L U M E W A L Lt o 2 6 3 . 8 3

3 1 1 5

P I P E G A L L E R Y A R E A E L E V S L A B @ 2 6 4 . 6 7

4 1 7 2

C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S

4 4 3 0

C H E M W E S T R / S R A WW A T E R S A M P L E P U M P

4 2 0 5

C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9

4 1 9 5

C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G

4 1 2 0

C H E M W E S TE L E V S L A B @ 2 7 6

2 0 6 0

G A C P P G G A L L E R Y I N S T L P P G & S U P P @ 2 5 0

2 0 2 0

C L E A R W E L L @ G A C P P GG A L L E R Y W A L L S t o 2 4 8 . 5 0

3 1 5 0

F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M

2 3 3 0

F L U M E F I L T 3 - 6 W A L L S t o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

6 3 0 5

S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P

3 1 0 0

P I P E G A L L E R YE L E V S L A B @ 2 5 6

6 3 1 0

S E D B A S I N M I S CP P G & E Q U I P

4 1 0 0

C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3

R 1 4 1 5

C H E M W E S T 3 r dF L O O R C . M . U .

4 1 2 7

C H E M W E S T M A S O N R YT O P A R A P E T

5 2 0 5

G A R A G EE X C A V t o 2 4 3

4 2 0 0

C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9

4 1 6 5

C H E M W E S T R / SL I M E F E E D E R H O P P E R S

2 2 2 5

O Z O N E / T R A N S F O R M E R8 " D E C K P A N E L S @ 2 7 8

4 1 6 0

C H E M W E S T R / SL I M E S T O S I L O S

4 0 5 0

C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7

3 4 1 5

P R E - O Z O N E C . B . E X T W A L L t o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3

3 1 5 5

F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4

1 1 4 0

C L E A R W E L L / O Z O N E E L E V S L A B @ 2 5 0 + / -

4 3 1 0

C H E M W E S T / R A W W A T E R 4 8 " P P G w / P R E C O N T A C T B Y P A S S

6 3 3 5

Y A R D P P G T R E A T E D W A T E RM E T E R P I T I N T P P G

R 1 1 4 0

C H E M W E S TS . S . A I R L I N E S

4 1 9 0

C H E M W E S T R / SS P A R E B A T C H T A N K

1 5 2 5

F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N

5 2 1 0

G A R A G E F T GF D N @ 2 4 4

5 2 2 0

G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -

1 5 1 5

I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N

1 5 1 0

P R O C E S SP A I N T I N G

4 1 8 5

C H E M W E S T R / SF I L T E R A I D B A T C H T A N K

1 3 0 0

2 N D F L A R C H I N T E R N A L M A S O N R Y

3 4 0 5

C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G

2 3 8 0

F L U M E W A L L &S L A B t o 2 5 0 . 1 6

3 0 7 5

P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G

3 0 4 0

S E D B A S I N C O L S & B E A M S t o 2 7 7 . 3 3

3 0 6 0

S E D B A S I N M A S O N R Y t o 2 8 0 . 5 0

4 1 7 5

C H E M W E S T R / SK M n O 4 F E E D E R

6 1 3 5

C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S

5 1 5 5

L O B B Y / C O N F F I N I S H E S ,F U R N I S H I N G S & S P E C I A L T I E S

R 1 3 2 0

C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T

R 1 3 1 0

C H E M W E S T L A BI N S T R U M E N T A T I O N

R 4 6 6 0

Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )

R 4 6 6 5

5 2 9 0R 4 5 1 5

S I T E W O R K -D R I V E " A "

5 2 4 0

G A R A G E S T RS T L @ 2 6 0 + / -

5 2 1 5

G A R A G E S O G@ 2 4 3 . 8 3

R 1 3 2 1

I N S T A L L S O F T W A R E& D E B U G S Y S T E M

R 1 3 0 5

C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E

5 3 1 5

Y A R D P P G I N S T A L LC O N T A I N M E N T T A N K & P P G

2 2 3 0

O Z O N E / T R A N S F O R M E R R O O F I N G

2 5 3 0

P I P E G A L L E R Y / F I L T E R R O O F I N G

2 5 2 5

P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S

2 5 2 0

P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7

2 5 1 0

F I L T E R # 1 - 6 W A L K W A Y @ 2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]

3 3 1 0

C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0

1 1 1 5

O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0

3 3 0 0

C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5

3 3 0 5

C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0

3 3 2 5

C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7

3 3 6 0

C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7

3 3 7 0

C H E M B L D G E A S T M A S O N R Y T O 2 6 5

R 3 3 2 0

G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S

R 3 3 1 0

G A C C O N T A C T O R -P . G . S A M P L E P U M P S

R 2 6 2 7

F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N

R 1 3 1 5

C H E M W E S TL A B P I P I N G

R 5 4 2 0

N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N

5 2 5 0

G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7

5 2 2 5

G A R A G E B F I L L

1 5 2 0

I N I T I A L M E C H P E R FT E S T P U N C H L I S T

R 1 0 3 5

C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R

R 1 7 4 0

C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6

5 0 3 0

L O B B Y / C O N F M A S O N R Y

2 6 0 0

P U M P S T A M I S C P P G & E Q U I P

2 3 9 0

F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3

2 3 4 0

F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

2 3 4 5

F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2

4 0 4 0

C H E M W E S T C O L S

4 0 6 0

C H E M W E S T B E A M S & S L A B S t o 2 6 4

3 3 7 5

C H E M B L D G E A S T M A S O N R Y T O 2 8 0

6 1 8 0

C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P

5 2 3 0

G A R A G ES O G @ 2 4 8

5 2 5 5

G A R A G E R O O F I N G

5 2 6 0

G A R A G EA R C H D E T A I L S

5 2 3 5

G A R A G EM A S O N R Y

R 4 8 0 5

A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R

R 1 7 4 1

C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7

3 0 9 0

P I P E G A L L E R Y I N S T L L G P P G

2 3 7 0

F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

2 3 7 5

F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2

4 0 5 5

C H E M W E S T W A L L S t o 2 6 3

4 0 8 0

C H E M W E S T I N S T LC O N T A I N M E N T L I N E R

4 1 4 5

C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T

4 1 2 9

C H E M W E S T M A S O N R Y T O 2 7 7

4 6 1 5

C H E M W E S T W E S T O FC L # 3 W A L L S T O 2 6 3

6 3 0 0

S E D B A S I N R / S 6 " 8 " P P G

R 1 4 9 5

C H E M W E S T C A S T S T O N E

1 5 0 0

O P E R A T I O N A LP U N C H L I S T

R 1 2 4 5

C H E M W E S TF I L T E R A I D L I N E S

3 0 6 5

S E D B A S I N / F L O CB A S I N R O O F I N G

R 1 7 6 0

C H E M E A S T G L A Z E DS T R U C T U R A L T I L E

3 5 0 5

P R E - O Z O N E C O N T A C T B A S I N E L E V S L A B @ 2 6 9 . 3 3

4 3 0 5

C H E M W E S T I N S T LA L U M S T O T A N K S

2 1 7 0

G A C A R E A R O O FF R A M I N G S T E E L

4 1 2 6

C H E M W E S TM A S O N R Y T O 2 8 8

4 4 0 0

C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P

R 2 6 3 5

F I L T E R S - P . G .S A M P L E P U M P S

3 5 2 5

P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7

3 5 2 0

P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o 2 8 0

5 0 4 5

L O B B Y / C O N F S T R S T Lt o 2 8 6 . 6 5 - P A R T I A L

R 4 8 0 0

A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E

4 1 8 0

C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K

4 1 7 0

C H E M W E S T R / S L I M ED U S T C O L L E C T O R S

4 3 0 0

C H E M W E S T R / SP O L Y P H O S P H A T E T A N K

2 4 6 5

P U M P S T A 8 "D E C K P A N E L S @ 2 8 4

R 4 8 0 1

A S S O R T E D R O O F T O PW O R K H . S . P . S .

3 5 3 0

P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T

4 5 4 0

C H E M W E S T L I M E S T O M I S C P P G & E Q U I P

3 3 9 0

C H E M B L D GE A S T R O O F I N G

R 4 8 0 4

A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .

R 4 8 0 2

A S S O R T E D R O O F T O PW O R K G A C C O N T A C T O R

R 1 4 1 0

C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E

Pl ot D at e 15 FE B9 5Da ta D at e 1 FE B9 5Pr oj ec t St ar t10 MA Y9 1Pr oj ec t Fi ni sh31 JA N9 5

(c ) Pr im av er a S ys te ms , Inc .

A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P

P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T

R 8 U 1 P a g e 1 o f 1

As-Planned v. As-Built Summary

As-Planned v As-Impacted v As-Built

As-Plan of Significant Acitivities

As-Built of Significant Activities

CHANGE ORDERS IMPACTING CRITICAL WORK & IMPACT TO WORK DURATIONS

Actual Actual Crit. # of BasePCO'sPCO TF

Relief From L/D’sExtended Overhead

Page 9: Evidence Issues in Forensic Use of CPM Scheduling

Add Probability and Risk

• Pertmaster – Monte Carlo -15%/+20%

• Calculate probability of finish by set date

• Track alternate critical paths by frequency

• What was natural risk of project delay?

Page 10: Evidence Issues in Forensic Use of CPM Scheduling

State of the Art Analysis & PresentationACTIVITY ID

ACTIVITYDESCRIPTION

ORIGDUR

ActualDuration START FINISH

1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB

1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0

1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0

1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0

1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0

3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0

3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0

1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0

1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0

1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0

3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0

3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0

3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0

3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58

3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58

4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0

3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58

4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0

3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58

4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0

4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0

4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0

3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58

R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58

3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66

R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330

R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58

3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58

R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58

3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63

4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0

4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0

4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0

R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29

3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0

R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0

4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1

3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7

2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47

3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0

3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63

4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1

4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7

4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1

4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1

R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0

4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1

4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1

4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1

4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1

R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21

R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1

4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21

1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1

1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17

R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9

4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1

4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10

R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28

R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65

1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9

R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6

R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0

R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5

R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10

R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15

R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14

R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6

R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0

R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5

R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10

R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4

R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6

R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4

R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10

R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4

R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6

R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5

R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0

R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0

1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15

R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0

1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15

1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0

1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0

1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0

1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0

5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0

END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33

5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0

5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1

5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0

5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0

5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0

5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0

5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0

5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0

5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0

5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0

5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0

1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0

1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0

END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0

NOTICE TO PROCEED

MOBILIZATION

SED BASIN EXCAV to 236.15

SED BASIN SOG @ 236.40

SED BASIN SOG @ 240.40/242.75

SED BASIN (N,S,E) WALL to 264

FLOC BASIN FOOTING @ 240.25

FLOC BASIN FOOTING WALL to 247

FLOC BASIN CONC FILL to 247

FLOC BASIN SOG @~249 INCL GRADE BEAM

FLOC BASIN (N,S,W) WALL to 261.58/264

PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33

CHEM BLDG EAST SOG STEP FTGS @ 230//240.50

CHEM BLDG EAST WALL to 243//250

CHEM WEST SOG @ 246/246.67

CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250

CHEM WEST WALLS to 263

CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67

CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS

CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG

CHEM WEST BEAMS & SLABS to 264

CHEM BLDG EAST MASONRY TO 265

CHEM EAST GLAZED STRUCTURAL TILE

CHEM BLDG EAST MONORAIL SUPPORT STEEL

CHEM EAST CAST STONE/BRICK

CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266

CHEM BLDG EAST MASONRY TO 280

CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67

CHEM BLDG EAST MASONRY TO PARAPET

CHEM WEST STR STL COLS/BEAMS to 275.33/288.33

CHEM WEST ELEV SLAB @ 276

CHEM WEST MASONRY TO 280

CHEM WEST 3rd FLOOR C.M.U.

PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67

ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.

CHEM WEST MASONRY TO 288

PRE-OZONE CONTACT BASIN MASONRY to PARAPET

PIPE GALLERY/FILTER 12" DECK PANELS

CHEM BLDG EAST ROOFING

PRE-OZONE CONTACT BASIN ROOFING

CHEM WEST R/S LIME STO SILOS

CHEM WEST STR STL BEAMS @ 288.33

CHEM WEST R/S LIME FEEDER HOPPERS

CHEM WEST R/S LIME DUST COLLECTORS

ELECTRICAL ROOM MISCELLANEOUS WORK

CHEM WEST - LIME STO R/S LIME CONV BLOWERS

CHEM WEST - LIME STO R/S 6" 8" 10" PPG

CHEM WEST 8" DECK PANELS @ 289

CHEM WEST MASONRY TO PARAPET

ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR

CHEM WEST CAST STONE

CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT

2ND FL ARCH INTERNAL MASONRY

1ST FL ARCH INTERNAL MASONRY

2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING

CHEM WEST ROOFING @ 280.67/289

CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG

CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE

FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS

2ND FL ARCH ELEC R/I

1st FLOOR CHEM WEST PIPING & PANELS

2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS

S.B./FILTERS/FLOCC. PULL FEEDERS

CHEM EAST/PUMP STATION PULL FEEDERS

3rd FLOOR CHEM WEST PULL FEEDERS

CHEM WEST COMPUTER ROOM EQUIPMENT

1st FLOOR CHEM WEST PULL FEEDER WIRE

2nd FLOOR CHEM WEST/C.B. BRANCH WIRING

S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS

CHEM EAST/PUMP STATION PULL BRANCH WIRING

CHEM WEST LAB PIPING

1st FLOOR CHEM WEST PULL BRANCH WIRING

CHEM WEST LAB INSTRUMENTATION

CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT

CHEM WEST LAB EQUIPMENT/FURNITURE

1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT

S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT

2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE

ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS

OPERATIONAL PUNCHLIST

INSTALL SOFTWARE & DEBUG SYSTEM

PROCESS PAINTING

INITIAL MECH PERF TEST OPER TESTING & TRAINING

INITIAL MECH PERF TEST 48 HR PLANT OPERATION

INITIAL MECH PERF TEST PUNCHLIST

FINAL MECH PERF TEST 48 HR PLANT OPERATION

GARAGE EXCAV to 243

880 DAY PART A COMPLETION

GARAGE SOG @ 243.83

GARAGE FTG FDN @ 244

GARAGE FTG WALLS to 247.27 +/-

GARAGE BFILL

GARAGE SOG @ 248

GARAGE MASONRY

GARAGE STR STL @ 260 +/-

GARAGE 8" DECK PANELS @ 262.67

GARAGE ROOFING

GARAGE ARCH DETAILS

GARAGE BUILDING PUNCHLIST

ARCHITECTURAL & FINAL PUNCHLIST

OWNER ACCEPTANCE

1065 DAY PART B COMPLETION

Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95

(c) Primavera Systems, Inc.

inactive Sheet 1 of 1

As-BuiltAs-PlannedAs-Impacted

nProMaC, Inc

As-PlanSTART

As-PlanFINISH

EARLYSTART

EARLYFINISH

1991 1992 1993 1994M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J

24JUN91 29JUL91 25JUL91A 22FEB93A

10JUL91 2AUG91 13SEP91A 9DEC92A

4JUN91 24JUN91 12JUL91A 11JUN92A

6AUG91 19AUG91 22OCT91A 18JUN93A

7FEB92 14FEB92 18JUN92A 27JAN93A

4DEC91 17DEC91 27JAN92A 15JAN93A

9JUL91 10JUL91 8JUN92A 27AUG93A

23AUG91 6SEP91 14SEP92A 22DEC92A

12JUN92 12JUN92 2SEP92A 16AUG93A

16OCT91 19NOV91 25JUN92A 31AUG93A

12SEP91 20SEP91 26JUN92A 15JUL93A

24DEC91 15JAN92 18JUN93A 20DEC93A

9APR92 9APR92 24JUN92A 30SEP93A

4FEB92 6FEB92 16OCT92A 15NOV94A

21JAN93 27JAN93 1MAR94A 15SEP94A

P.S. CONCRETE

C.W./OZONE/GAC CONCRETE

S.B./FLOCC CONCRETE

FLUME/FILTER/P.G. CONCRETE

CHEM EAST CONCRETE

CONTACT BASIN CONCRETE

CHEM WEST CONCRETE

L/C CONCRETE

ROOF DECK

MASONRY

STRUCTURAL STEEL

ROOFING

MECH EQUIPMENT

OZONE SYSTEM

INSTRUMENTATION

Target Date 10MAY91Plot Date 20FEB95Data Date 1FEB95Project Start 10MAY91Project Finish 31JAN95

Primavera Systems, Inc.

Summary Bar/Early Dates

inactive

Critical DesignatorTarget Dates

R8U1 Page 1 of 1

A C T T I T L E O D E S - E C O N D A C T T I T L E O D E S - E C O N D

P C O 0 0 5 0 1 P C O 0 0 5 N T P A D D L R O C K E X C A V & R E I N F C O N C 1 0 6 / 2 1 / 9 1 P C O 1 1 6 0 1 P C O 1 1 6 N T P A D D L W A L L S L E E V E S C H E M W E S T S L A B @ 2 7 6 1 0 5 / 0 5 / 9 3

P C O 0 0 7 0 1 P C O 0 0 7 N T P R E B A R R E V I S I O N S @ F L U M E S 1 0 7 / 2 6 / 9 1 P C O 1 1 7 0 1 P C O 1 1 7 N T P W O O D B L O C K I N G @ R O O F O P E N I N G S 1 0 5 / 2 1 / 9 3

P C O 0 0 8 0 1 P C O 0 0 8 N T P G F L E T T E R 6 / 2 1 / 9 1 1 0 7 / 2 6 / 9 1 P C O 1 2 0 0 1 P C O 1 2 0 N T P A D D L N E L S O N S T U D S @ L / C 1 0 5 / 0 1 / 9 3

P C O 0 0 9 0 1 P C O 0 0 9 a N T P B R I C K L E D G E S & C L O U M N Q U A N T I T I E S 1 0 8 / 1 6 / 9 1 P C O 1 2 1 0 1 P C O 1 2 1 N T P C H E M W E S T 3 R D S L A B / M A S O N R Y I N T E R F A C E 1 0 4 / 2 6 / 9 3

P C O 0 1 0 0 1 P C O 0 1 0 N T P C O N S T R U C T I O N / C O N T R A C T I O N J O I N T S 1 0 9 / 0 6 / 9 1 P C O 1 2 4 0 1 P C O 1 2 4 N T P A D D L R O O F H A T C H E S @ O Z O N E A I R P R E P 1 1 2 / 2 1 / 9 2

P C O 0 1 2 0 1 P C O 0 1 2 N T P R E V I S E D E L E C S U B S T A T I O N 1 0 9 / 2 6 / 9 1 P C O 1 2 6 0 1 P C O 1 2 6 N T P M A S O N R Y C H A N G E S C H L O R , L / C B A T H , O Z O N E 1 0 3 / 2 3 / 9 3

P C O 0 1 3 0 1 P C O 0 1 3 N T P R E B A R C H A N G E S 1 1 0 / 1 0 / 9 1 P C O 1 2 8 0 1 P C O 1 2 8 N T P A R C H M O D S F O R H V A C & P L U M B I N G 1 0 5 / 2 0 / 9 3

P C O 0 1 4 0 1 P C O 0 1 4 N T P W A T E R S T O P C H A N G E S @ C L E A R W E L L & C . B 1 1 0 / 0 1 / 9 1 P C O 1 3 1 0 1 P C O 1 3 1 N T P S T R S T L B E A M R E P A I R S @ C H L O R & G A C 1 0 2 / 1 6 / 9 3

P C O 0 1 6 0 1 P C O 0 1 6 N T P G F M E M O 1 0 / 2 2 / 9 1 1 1 0 / 2 2 / 9 1 P C O 1 3 6 0 1 P C O 1 3 6 N T P M O D I F Y 1 2 " S . S . A I R W A S H P I P E 1 0 6 / 2 1 / 9 3

P C O 0 1 7 0 1 P C O 0 1 7 N T P A D D L R E B A R @ C . W . S U M P S 1 0 9 / 2 5 / 9 1 P C O 1 4 1 0 1 P C O 1 4 1 N T P M A S O N R Y C H A N G E @ C H I M N E Y A R E A 1 0 9 / 0 3 / 9 3

P C O 0 1 8 0 1 P C O 0 1 8 N T P G F M E M O 1 0 - 2 9 - 9 1 1 1 0 / 2 9 / 9 1 P C O 1 4 5 0 1 P C O 1 4 5 N T P M O D S @ E L E V A T O R M A C H I N E R O O M 1 0 7 / 2 6 / 9 3

P C O 0 2 0 0 1 P C O 0 2 0 N T P G F L E T T E R 1 1 / 1 1 / 9 1 1 1 1 / 1 1 / 9 1 P C O 1 4 8 0 1 P C O 1 4 8 N T P C H A N G E D O O R S I Z E @ C O R R 1 2 2 & L I N T E L 1 0 8 / 2 7 / 9 3

P C O 0 2 1 0 1 P C O 0 2 1 N T P F L O C C W L A K W A Y C H A N G E S 1 1 1 / 1 8 / 9 1 P C O 1 4 9 0 1 P C O 1 4 9 N T P S T R F R A M I N G C H A N G E S @ P . S . L O U V E R 1 1 0 / 2 5 / 9 3

P C O 0 2 2 0 1 P C O 0 2 2 N T P F L O C C D R A I N S L O T R E L O C A T I O N 1 1 1 / 2 1 / 9 1 P C O 1 5 0 0 1 P C O 1 5 0 N T P A D D L N E L S O N S T U D S C H E M W E S T 3 R D F L 1 0 7 / 0 2 / 9 3

P C O 0 2 6 0 1 P C O 0 2 6 N T P F L O C C I N T E R M E D B A F F L E W A L L D R A I N 1 1 1 / 2 5 / 9 1 P C O 1 5 1 0 1 P C O 1 5 1 N T P L & N C H L O R I N E S Y S T E M M O D I F I C A T I O N S 1 0 3 / 1 5 / 9 4

P C O 0 2 7 0 1 P C O 0 2 7 N T P S . S . W A L K W A Y C H A N G E S 1 1 2 / 0 3 / 9 1 P C O 1 5 2 0 1 P C O 1 5 2 N T P A D D L M E T A L S T U D F R A M I N G @ L / C 1 1 0 / 1 3 / 9 3

P C O 0 2 8 0 1 P C O 0 2 8 N T P R E L O C A T E S . B . D O O R S 1 1 2 / 0 5 / 9 1 P C O 1 5 4 0 1 P C O 1 5 4 N T P N E W C A R P E T S T Y L E 1 0 9 / 0 2 / 9 3

P C O 0 2 9 0 1 P C O 0 2 9 N T P C H E M E A S T R E B A R M O D I F I C A T I O N 1 1 2 / 1 2 / 9 1 P C O 1 5 5 0 1 P C O 1 5 5 N T P A D D L S U B C O N T R A C T W O R K @ L / C R O O F 1 0 8 / 1 4 / 9 3

P C O 0 3 0 0 1 P C O 0 3 0 N T P H A T C H & A N C H O R B O L T C H A N G E S 1 0 1 / 0 1 / 9 2 P C O 1 5 5 0 3 P C O 1 5 5 S U B C O N T R A C T W O R K @ L / C R O O F O P E N I N G S 1 n o n e

P C O 0 3 1 0 1 P C O 0 3 1 N T P A D D S W A L L P I P E S & B L I N D F L A N G E S 1 1 0 / 1 1 / 9 1 P C O 1 5 6 0 1 P C O 1 5 6 N T P I N S T A L L 3 0 " N J B F V @ N O R T H B R A N C H 1 0 5 / 0 6 / 9 4

P C O 0 3 2 0 1 P C O 0 3 2 N T P E N V I R E X S . B . S L U D G E C O L L F I L L C O N C 1 0 1 / 0 2 / 9 2 P C O 1 5 6 0 3 P C O 1 5 6 I N S T L 3 0 " N J B F V @ N O R T H B R A N C H R W P S 3 n o n e

P C O 0 3 3 0 1 P C O 0 3 3 N T P G F L E T T E R 1 2 / 1 9 / 9 1 1 1 2 / 1 2 / 9 1 P C O 1 5 7 0 1 P C O 1 5 7 N T P R E P L A C E M E N T L O U V E R @ L / C 1 1 2 / 1 0 / 9 3

P C O 0 3 4 0 1 P C O 0 3 4 N T P G F M E M O 1 2 / 2 0 / 9 1 D I M E N S I O N A L C H A N G E S 1 1 2 / 2 0 / 9 1 P C O 1 5 7 0 3 P C O 1 5 7 I N S T A L L R E P L A C E M E N T L O U V E R @ L / C 1 n o n e

P C O 0 3 5 0 1 P C O 0 3 5 N T P G F L E T T E R 1 2 / 1 9 / 9 5 D R W G C L A R I F I C A T N 1 1 2 / 1 9 / 9 1 P C O 1 6 0 0 1 P C O 1 6 0 N T P A D D 2 T U R B I D I M E T E R I N D I C A T O R S T O G A C 1 0 1 / 2 0 / 9 4

P C O 0 3 9 0 1 P C O 0 3 9 N T P C H A N G E S P . S . D R A I N P I P I N G 1 0 1 / 2 9 / 9 2 P C O 1 6 1 0 1 P C O 1 6 1 N T P A D D P R E S S U R E S W I T C H & A L A R M C O N T A C T S 1 0 3 / 0 2 / 9 4

P C O 0 4 1 0 1 P C O 0 4 1 N T P S P I L L C O N T A I N M E N T T A N K R E V I S I O N S 1 0 1 / 2 8 / 9 2 P C O 1 6 1 0 3 P C O 1 6 1 P R E S S U R E S W I T C H & A L A R M C O N T A C T H S P S 1 n o n e

P C O 0 4 2 0 1 P C O 0 4 2 N T P A D D L D R A I N C H A N N E L 1 0 1 / 2 8 / 9 2 P C O 1 6 2 0 1 P C O 1 6 2 N T P A D D 4 S L O T D I F F U S E R S I N L / C 1 0 1 / 1 0 / 9 4

P C O 0 4 5 0 1 P C O 0 4 5 N T P G F M E M O 1 / 2 8 / 9 2 R E F R F I # 3 0 1 0 1 / 2 8 / 9 2 P C O 1 6 2 0 3 P C O 1 6 2 A D D 4 S L O T D I F F U S E R S I N L / C 1 0 n o n e

P C O 0 4 6 0 1 P C O 0 4 6 N T P G F M E M O 2 / 1 8 / 9 2 R E F R F I # 4 7 1 0 2 / 1 8 / 9 2 P C O 1 6 3 0 1 P C O 1 6 3 N T P A D D F I R E W A L L I N L / C 1 0 1 / 1 4 / 9 4

P C O 0 4 7 0 1 P C O 0 4 7 N T P C H E M B L D G C O L & J O I N T C H A N G E S 1 0 2 / 2 6 / 9 2 P C O 1 6 3 0 3 P C O 1 6 3 A D D F I R E W A L L I N L / C T & M 1 3 n o n e

P C O 0 4 9 0 1 P C O 0 4 9 N T P F L U M E O V E R F L O W B O X E L E V R E V & R E L A T E D 1 0 7 / 0 9 / 9 2 P C O 1 6 5 0 1 P C O 1 6 5 N T P C O N T R O L M O N I T O R F R A M E W O R K R E V I S I O N S 1 0 2 / 2 4 / 9 4

P C O 0 5 1 0 1 P C O 0 5 1 N T P P . S . T & M W O R K P E R A A M # 2 0 9 1 0 4 / 2 3 / 9 2 P C O 1 6 8 0 1 P C O 1 6 8 N T P 8 " B Y P A S S A R O U N D 1 0 " P L A N T S E R V I C E 1 0 4 / 2 8 / 9 4

P C O 0 5 2 0 1 P C O 0 5 2 N T P P . S . E L E C T R I C O P E N I N G S R E V I S I O N 1 0 4 / 2 3 / 9 2 P C O 1 6 8 0 3 P C O 1 6 8 8 " B Y P A S S A R O U N D 1 0 " P L A N T S E R V I C E 3 0 n o n e

P C O 0 5 3 0 1 P C O 0 5 3 N T P C . B . W A L L P O U R D E L A Y 1 0 5 / 0 6 / 9 2 P C O 1 7 1 0 1 P C O 1 7 1 N T P M O D I F Y L / C T O I L E T P A R T I T I O N S 1 0 3 / 2 5 / 9 4

P C O 0 5 4 0 1 P C O 0 5 4 N T P H A N D R A I L C H A N G E S 1 0 4 / 1 6 / 9 2 P C O 1 7 1 0 3 P C O 1 7 1 P R O C U R E M E N T R E L / C T O I L E T P A R T I T I O N S 5 2 n o n e

P C O 0 5 7 0 1 P C O 0 5 7 N T P C H E M B L D G S L A B T H I C K N E S S 1 0 5 / 2 2 / 9 2 P C O 1 7 7 0 1 P C O 1 7 7 N T P C H L O R I N A T I O N S Y S T E M M O D I F I C A T I O N S 1 0 4 / 0 7 / 9 4

P C O 0 5 8 0 1 P C O 0 5 8 N T P A D D I T I O N A L W A T E R S T O P 1 0 5 / 2 9 / 9 2 P C O 1 7 7 0 3 P C O 1 7 7 C H L O R I N A T I O N S Y S T E M M O D I F I C A T I O N S 2 0 n o n e

P C O 0 5 9 0 1 P C O 0 5 9 N T P C E R A M I C T I L E C H A N G E S 1 0 6 / 0 1 / 9 2 P C O 1 8 0 0 1 P C O 1 8 0 N T P A D D L P R O J E C T M I L L W O R K 1 0 1 / 0 7 / 9 4

P C O 0 6 2 0 1 P C O 0 6 2 N T P P . S . R A I N P I P I N G R E V I S I O N S 1 0 6 / 1 2 / 9 2 P C O 1 8 1 0 1 P C O 1 8 1 N T P C E I L I N G C H A N G E S 1 0 2 / 2 1 / 9 4

P C O 0 6 3 0 1 P C O 0 6 3 N T P C H E M W E S T S U M P C H A N G E S 1 0 6 / 1 5 / 9 2 P C O 1 8 1 0 3 P C O 1 8 1 A D D L M E T A L S O F F I T E N V I R L A B 2 n o n e

P C O 0 6 4 0 1 P C O 0 6 4 N T P D E L E T E C O M P U T E R A C C E S S F L O O R 1 0 4 / 1 6 / 9 2 P C O 1 8 1 0 4 P C O 1 8 1 R E M O V E I N S U L F R O M M E T A L C E I L I N G 3 n o n e

P C O 0 6 5 0 1 P C O 0 6 5 N T P D E L E T E F L O C C T E R R A Z Z O 1 0 4 / 1 0 / 9 2 P C O 1 8 2 0 1 P C O 1 8 2 N T P E X P A N S I O N J O I N T B O O T R E T R O F I T 1 0 3 / 1 7 / 9 4

P C O 0 6 6 0 1 P C O 0 6 6 N T P A D D 1 L O U V E R 1 0 5 / 2 9 / 9 2 P C O 1 8 2 0 3 P C O 1 8 2 P R O C U R E M T F / E X P A N S N J O I N T B O O T R E T R O 2 0 n o n e

P C O 0 6 7 0 1 P C O 0 6 7 N T P S U B S T I T U T E G A T E F O R B F V ' S & B A C K F L O W 1 0 2 / 2 8 / 9 2 P C O 1 8 2 0 5 P C O 1 8 2 T & M I N S T L E X P A N S N J O I N T B O O T R E T R O F I T 5 n o n e

P C O 0 6 8 0 1 P C O 0 6 8 N T P S . B . R O O F B E A M C O N S T R U C T I O N J O I N T 1 0 2 / 2 5 / 9 2 P C O 1 8 3 0 1 P C O 1 8 3 N T P R A W W A T E R S A M P L E L I N E E X T E N S I O N 1 0 3 / 3 0 / 9 4

P C O 0 7 0 0 1 P C O 0 7 0 N T P C H A N G E P V C M A S O N R Y F L A S H I N G 1 0 6 / 2 5 / 9 2 P C O 1 8 4 0 1 P C O 1 8 4 N T P O Z O N E P I P I N G M O D I F I C A T I O N S 1 0 4 / 1 8 / 9 4

P C O 0 7 1 0 1 P C O 0 7 1 N T P M O D I F Y P I P E S U P P O R T S 1 0 7 / 3 0 / 9 2 P C O 1 8 4 0 3 P C O 1 8 4 P R O C U R M E N T F / O Z O N E P I P I N G M O D S 1 5 n o n e

P C O 0 7 2 0 1 P C O 0 7 2 N T P A D D C A R P E T T O C O M P U T E R R O O M 1 0 4 / 1 6 / 9 2 P C O 1 8 5 0 1 P C O 1 8 5 N T P I N S T A L L L A R G E R A N G L E C L I P S @ R O O F 1 0 7 / 0 2 / 9 3

P C O 0 7 3 0 1 P C O 0 7 3 N T P 7 / 1 / 9 2 M O D I F I C A T I O N S P E R R F I # 8 2 1 0 7 / 1 3 / 9 2 P C O 1 8 6 0 1 P C O 1 8 6 N T P I N C O R R E C T P I P E P A I N T I N G 1 1 1 / 0 1 / 9 3

P C O 0 7 5 0 1 P C O 0 7 5 N T P A D D L C A S T S T O N E 1 0 7 / 2 3 / 9 3 P C O 1 8 6 0 3 P C O 1 8 6 F I X I N C O R R E C T P I P E P A I N T I N G 3 n o n e

P C O 0 7 6 0 1 P C O 0 7 6 N T P A A M F W O # 0 8 6 9 W A L L P O U R D E L A Y 1 0 7 / 1 6 / 9 2 P C O 1 8 7 0 1 P C O 1 8 7 N T P V A R I O U S C O N T R A C T D W G C H A N G E S 1 0 3 / 0 2 / 9 3

P C O 0 7 9 0 1 P C O 0 7 9 N T P P . S . T A P E R E D R O O F M O D I F I C A T I O N S 1 0 6 / 1 6 / 9 3 P C O 1 8 8 0 1 P C O 1 8 8 N T P L E V E L P R O B E S U P P O R T B R A C K E T 1 0 3 / 2 5 / 9 4

P C O 0 8 1 0 1 P C O 0 8 1 N T P C O R E D R I L L O P E N I N G S @ C . B . 1 0 7 / 2 2 / 9 2 P C O 1 9 0 0 1 P C O 1 9 0 N T P A P P L Y S E A L E R T O E X P O S E D I N T B R I C K 1 0 5 / 2 0 / 9 4

P C O 0 8 2 0 1 P C O 0 8 2 N T P A D D L F L O O R O P E N I N G S @ P I L O T T E S T E Q 1 0 9 / 1 5 / 9 2 P C O 1 9 0 0 3 P C O 1 9 0 I N T M A S O N R Y C L E A N I N G & S E A L E R 1 0 n o n e

P C O 0 8 4 0 1 P C O 0 8 4 N T P C H E M B L D G 2 N D F L C O N S T R J O I N T D E L A Y 1 0 9 / 1 6 / 9 2 P C O 1 9 1 0 1 P C 0 1 9 1 N T P L & N C O N T R A C T E X T E N S I O N R E Q U E S T 1 0 2 / 0 1 / 9 4

P C O 0 8 5 0 1 P C O 0 8 5 N T P P . S . R O O F P L A N K C H A N G E S 1 0 6 / 2 4 / 9 2 P C O 1 9 2 0 1 P C O 1 9 2 N T P P O S T C L 2 / G A C E F F L S A M P L E P T C H A N G E S 1 0 5 / 2 0 / 9 4

P C O 0 8 9 0 1 P C O 0 8 9 N T P P I P E B L A N K - O F F P L A T E @ 4 2 " F U T P P G 1 0 3 / 2 4 / 9 2 P C O 1 9 2 0 3 P C O 1 9 2 A D D L W O R K 1 n o n e

P C O 0 9 0 0 1 P C O 0 9 0 N T P A L U M I N U M S U P P O R T F R A M I N G & C U R B @ P S 1 0 9 / 0 4 / 9 2 P C O 1 9 4 0 1 P C O 1 9 4 N T P H A N D I C A P P E D P A R K I N G R E V I S I O N S 1 0 6 / 0 8 / 9 4

P C O 0 9 0 0 3 P C O 0 9 0 F A B R & I N S T A L L M C C S U P P O R T 3 3 n o n e P C O 1 9 4 0 3 P C O 1 9 4 H A N D I C A P P E D P A R K I N G R E V I S I O N S 1 0 n o n e

P C O 0 9 1 0 1 P C O 0 9 1 N T P R E M A S O N R Y , R O O F I N G , T E R R A Z Z O 1 0 9 / 0 4 / 9 2 P C O 1 9 5 0 1 P C O 1 9 5 N T P A D D R E G U L A T O R S - A I R P U R G E M E T E R C O N 1 0 6 / 0 8 / 9 4

P C O 0 9 3 B 1 P C O 0 9 3 b N T P S T R U C T U R A L S T E E L C H A N G E S 1 0 5 / 2 0 / 9 2 P C O 1 9 5 0 3 P C O 1 9 5 A D D R E G U L A T O R S 1 n o n e

P C O 0 9 3 C 1 P C O 0 9 3 c N T P S T R U C T U R A L S T E E L C H A N G E S 1 0 6 / 1 6 / 9 2 P C O 1 9 6 0 1 P C O 1 9 6 N T P I N S T A L L V A L V E @ 4 8 " R A W W A T E R L I N E 1 0 6 / 1 4 / 9 4

P C O 0 9 3 F 1 P C O 0 9 3 f N T P S T R U C T U R A L S T E E L C H A N G E S 1 0 9 / 2 5 / 9 2 P C O 1 9 6 0 3 P C O 1 9 6 A D D L W O R K 2 n o n e

P C O 0 9 3 H 1 P C O 0 9 3 h N T P S T R U C T U R A L S T E E L C H A N G E S 1 1 2 / 1 6 / 9 2 P C O 1 9 7 0 1 P C O 1 9 7 N T P C O R E D R I L L V E N T H O L E S I N P . S . S U M P 1 0 6 / 0 1 / 9 4

P C O 0 9 4 0 1 P C O 0 9 4 N T P M A S O N R Y C H A N G E S 1 0 1 / 0 4 / 9 3 P C O 1 9 7 0 3 P C O 1 9 7 A D D L W O R K 3 n o n e

P C O 0 9 7 A 1 P C O 0 9 7 a N T P M A S O N R Y C H A N G E S C H L O R , L / C B A T H , O Z O N E 1 1 1 / 1 0 / 9 2 P C O 1 9 8 0 1 P C O 1 9 8 N T P C H A N G E H D W E D O O R S 2 0 2 & 2 0 3 1 0 6 / 1 6 / 9 4

P C O 0 9 7 C 1 P C O 0 9 7 c N T P M A S O N R Y C H A N G E S C H L O R , L / C B A T H , O Z O N E 1 0 2 / 1 0 / 9 3 P C O 1 9 9 0 1 P C O 1 9 9 N T P L O W E R G A C S A M P L E L I N E F O O T V A L V E 1 0 6 / 1 6 / 9 4

P C O 1 0 0 0 1 P C O 1 0 0 N T P B E A M 3 0 A 1 1 0 / 1 3 / 9 2 P C O 2 0 1 0 1 P C O 2 0 1 N T P F U T F L O R I D E C H E M F D C A R R I E R C O N D U I T 1 0 6 / 1 6 / 9 4

P C O 1 0 1 0 1 P C O 1 0 1 N T P A D D P I P E S U P P O R T C H A N N E L S @ G A C P . G . 1 1 1 / 1 6 / 9 2 P C O 2 0 1 0 3 P C O 2 0 1 A D D L W O R K 2 n o n e

P C O 1 0 2 0 1 P C O 1 0 2 N T P L A T E R A L B R A C I N G R E Q M T S 1 1 2 / 0 1 / 9 2 P C O 2 0 3 0 1 P C O 2 0 3 N T P P I T O T T U B E F L O W M E T E R X M T R R E L O C 1 0 6 / 1 6 / 9 4

P C O 1 0 5 B 1 P C O 1 0 5 b N T P M O D I F I E D R O O F P L A N K 1 0 3 / 2 0 / 9 3 P C O 2 0 3 0 3 P C O 2 0 3 A D D L W O R K 2 n o n e

P C O 1 0 5 C 1 P C O 1 0 5 c N T P M O D I F I E D R O O F P L A N K 1 0 3 / 2 5 / 9 3 P C O 2 0 4 0 1 P C O 2 0 4 N T P G A R A G E R E V I S I O N S 1 0 7 / 1 2 / 9 4

P C O 1 0 5 C 3 P C O 1 0 5 F A B R M O D I F I E D R O O F P L A N K 2 0 n o n e P C O 2 0 4 0 3 P C O 2 0 4 A D D L P R O C U R E M E N T 2 5 n o n e

P C O 1 0 7 0 1 P C O 1 0 7 N T P E X T R A N E L S O N S T U D S @ L / C 1 0 2 / 0 4 / 9 3 P C O 2 0 4 0 5 P C O 2 0 4 A D D L W O R K U / S P P G 2 n o n e

P C O 1 0 8 0 1 P C O 1 0 8 N T P S O F F I T & L I N T E L T O C O N C E A L D U C T W O R K 1 0 1 / 2 0 / 9 3 P C O 2 1 1 0 1 P C O 2 1 1 N T P 4 8 " R A W W A T E R M A I N T I E - I N T O I N T E R I M 1 0 8 / 2 9 / 9 4

P C O 1 0 9 0 1 P C O 1 0 9 N T P R E V B A S E P L A T E , L I N T E L , M A S O N R Y 1 0 3 / 2 5 / 9 3 P C O 2 1 1 0 3 P C O 2 1 1 P R O C U R E A D D L 4 8 " P I P E 5 5 n o n e

P C O 1 1 0 0 1 P C O 1 1 0 N T P S T R U C T U R A L S T E E L M O D I F I C A T I O N S 1 0 4 / 1 9 / 9 3 P C O 2 1 1 0 5 P C O 2 1 1 I N S T A L L T I E - I N P I P E 1 4 n o n e

P C O 1 1 0 0 3 P C O 1 1 0 a R E P A I R S T O L I M E S I L O S T R S T L 6 n o n e P C O 2 1 2 0 1 P C O 2 1 2 N T P A D D L F I L T E R B A C K W A S H T U R B I D O M E T E R S 1 0 6 / 1 4 / 9 4

P C O 1 1 0 0 4 P C O 1 1 0 b R E P A I R S T O E L E V A T O R S H A F T S T R S T L 5 n o n e P C O 2 1 4 0 1 P C O 2 1 4 N T P G A R A G E R O O F P L A N K C H A N G E S 1 0 8 / 1 7 / 9 4

P C O 1 1 1 0 1 P C O 1 1 1 N T P P I P E M O D S @ W A T E R M E T E R C H A M B E R 1 0 4 / 1 2 / 9 3

P C O 1 1 2 0 1 P C O 1 1 2 N T P A D D L L I N T E L @ C O R R I D O R 1 1 6 1 0 2 / 0 3 / 9 3

ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD ACT SUC LAG REL ADD ADD

DUR DAYS DUR DAYS DUR DAYS

PCO00501 1020 0 FS 2 0 PCO097A1 3370 0 FS 3 0 PCO18403 2250 0 FS 15 0

PCO00501 1070 0 FS 2 0 PCO097C1 R3115 0 FS 1 0 PCO18501 3065 0 FS 10 0

PCO00701 2315 0 FS 3 0 PCO10001 2065 0 FS 2 0 PCO18601 PCO18603 0 FS 0 0

PCO00801 3310 0 FS 3 0 PCO10101 2060 1 FF 1 0 PCO18603 3031 0 FS 0 0

PCO00901 3015 0 FS 2 0 PCO10201 2160 0 FS 2 0 PCO18603 R2799 0 FS 0 0

PCO00901 3025 0 FS 9 0 PCO10201 2455 0 FS 2 0 PCO18701 3360 0 FS 1 0

PCO01001 1100 0 FS 6 0 PCO10201 4120 0 FS 2 0 PCO18701 4125 0 FS 2 0

PCO01001 1105 0 FS 12 0 PCO105B1 2225 5 FF 2 0 PCO18801 6015 0 FS 1 0

PCO01201 2335 0 FS 0 10 PCO105C1 PCO105C3 0 FS 0 0 PCO19001 PCO19003 0 FS 0 0

PCO01301 1110 0 FS 1 0 PCO105C3 2185 0 FS 0 0 PCO19003 1390 0 FS 0 0

PCO01401 1055 0 FS 0 0 PCO10701 5030 0 FS 2 0 PCO19101 R1321 0 FS 0 0

PCO01401 1100 0 FS 4 0 PCO10801 4129 2 FF 2 0 PCO19101 R6165 20 FF 0 0

PCO01601 2325 0 FS 0 0 PCO10901 5030 0 FF 0 15 PCO19101 136106 15 FF 0 0

PCO01701 1100 0 FS 2 2 PCO11001 PCO11003 0 FS 0 0 PCO19201 PCO19203 0 FS 0 0

PCO01801 2425 0 FS 0 0 PCO11001 PCO11004 0 FS 0 0 PCO19203 1515 0 FS 0 0

PCO02001 2455 0 FS 1 0 PCO11003 4120 0 FS 0 0 PCO19401 PCO19403 0 FS 0 0

PCO02101 3185 0 FS 0 0 PCO11004 4120 0 FS 0 0 PCO19403 R4515 0 FS 0 0

PCO02201 3150 0 FS 0 0 PCO11101 6335 4 FF 0 0 PCO19501 PCO19503 0 FS 0 0

PCO02201 3155 0 FS 0 0 PCO11201 2450 3 FF 3 0 PCO19503 1500 5 FF 0 0

PCO02601 3155 0 FS 0 0 PCO11601 4120 1 FF 2 0 PCO19601 PCO19603 0 FS 0 0

PCO02701 3030 0 FS 1 0 PCO11701 R4800 0 FS 10 0 PCO19603 1515 0 FS 0 0

PCO02801 3060 0 FS 0 0 PCO11701 R4801 0 FS 2 0 PCO19701 PCO19703 0 FS 0 0

PCO02901 3305 0 FS 0 0 PCO11701 R4802 0 FS 5 0 PCO19703 1515 0 FS 0 0

PCO03001 1140 0 FS 2 0 PCO11701 R4803 0 FS 2 0 PCO19801 1390 5 FF 0 0

PCO03001 2425 0 FS 1 0 PCO11701 R4804 0 FS 2 0 PCO19901 1515 0 FS 0 0

PCO03101 2020 0 FS 3 0 PCO11701 R4805 0 FS 3 0 PCO20101 PCO20103 0 FS 0 0

PCO03201 3030 0 FS 12 0 PCO12001 5050 2 FF 2 0 PCO20103 1515 0 FS 0 0

PCO03301 3085 0 FS 0 0 PCO12101 4120 10 FF 1 0 PCO20301 PCO20303 0 FS 0 0

PCO03401 2330 0 FS 0 0 PCO12401 2230 0 FS 3 0 PCO20303 1515 0 FS 0 0

PCO03501 3410 0 FS 0 0 PCO12401 R4800 0 FS 2 0 PCO20401 PCO20403 0 FS 0 0

PCO03901 2415 0 FS 0 0 PCO12601 5030 0 FS 1 0 PCO20403 PCO20405 0 FS 0 0

PCO03901 2425 0 FS 5 0 PCO12801 1300 1 FF 1 0 PCO20405 5205 0 FS 0 0

PCO04101 5315 0 FS 1 0 PCO12801 4540 0 FS 1 0 PCO20405 5260 30 FS 0 0

PCO04201 1140 0 FS 1 0 PCO13101 2170 1 FF 0 0 PCO21101 PCO21103 0 FS 0 0

PCO04201 3080 0 FS 0 0 PCO13101 3371 1 FF 0 0 PCO21103 PCO21105 3 FS 0 0

PCO04501 4055 0 FS 0 0 PCO13601 R1140 0 FS 2 0 PCO21105 1390 0 FS 0 0

PCO04601 1140 0 FS 0 0 PCO14101 R1495 0 FS 1 0 PCO21105 R4515 0 FS 0 0

PCO04701 4040 0 FS 0 0 PCO14501 1200 0 FS 2 0 PCO21201 R2627 3 FF 3 0

PCO04701 4045 0 FS 1 0 PCO14501 4405 0 FS 1 0

PCO04901 3085 0 FS 4 20 PCO14801 1300 0 FS 2 0

PCO05101 2425 0 FS 6 12 PCO14901 R3665 0 FS 2 0

PCO05201 2425 0 FS 0 0 PCO15001 4135 0 FS 1 0

PCO05301 3415 0 FS 1 0 PCO15101 R1321 1 FF 1 0

PCO05401 2615 0 FS 0 0 PCO15201 R4030 0 FS 2 0

PCO05701 4030 0 FS 0 0 PCO15401 1225 0 FS 0 0

PCO05801 3315 0 FS 1 0 PCO15401 1325 0 FS 0 0

PCO05901 1260 0 FS 0 0 PCO15401 5190 0 FS 0 0

PCO05901 1360 0 FS 0 0 PCO15501 PCO15503 0 FS 0 0

PCO05901 5155 0 FS 0 0 PCO15503 5090 0 FS 0 0

PCO06201 2450 0 FS 1 0 PCO15601 PCO15603 0 FS 0 0

PCO06301 4060 0 FS 2 0 PCO15603 1505 0 FS 0 0

PCO06401 1325 0 FS 0 0 PCO15701 PCO15703 0 FS 0 0

PCO06501 1325 0 FS 0 0 PCO15703 R4115 0 FS 0 0

PCO06601 1260 0 FS 0 0 PCO16001 R1321 1 FF 1 0

PCO06701 2000 0 FS 0 0 PCO16001 136106 15 FF 1 0

PCO06801 3040 0 FS 12 0 PCO16101 PCO16103 0 FS 0 0

PCO07001 3060 0 FS 0 0 PCO16103 1500 0 FS 0 0

PCO07101 2050 0 FS 1 0 PCO16201 PCO16203 0 FS 0 0

PCO07201 1325 0 FS 0 0 PCO16203 R4115 0 FS 0 0

PCO07301 4615 0 FS 2 5 PCO16301 PCO16303 0 FS 0 0

PCO07501 R1495 0 FS 2 0 PCO16303 R4115 0 FS 0 0

PCO07601 4615 2 FS 2 0 PCO16501 R1321 5 FF 0 0

PCO07901 3390 0 FS 2 0 PCO16801 PCO16803 0 FS 0 0

PCO08101 3505 0 FS 2 0 PCO16803 1515 0 FS 0 0

PCO08201 4060 0 FS 2 0 PCO17101 PCO17103 0 FS 0 0

PCO08401 4060 0 FS 2 0 PCO17103 5155 0 FS 3 0

PCO08501 2465 0 FS 1 22 PCO17701 PCO17703 0 FS 0 0

PCO08901 4005 0 FS 1 0 PCO17703 1505 0 FS 0 0

PCO09001 PCO09003 0 FS 0 0 PCO18001 5155 1 FF 0 0

PCO09003 2610 0 FS 0 0 PCO18101 PCO18103 0 FS 0 0

PCO09101 2180 0 FS 1 0 PCO18101 PCO18104 0 FS 0 0

PCO09101 3390 0 FS 1 0 PCO18103 5155 1 FF 0 0

PCO09101 R3395 0 FS 2 0 PCO18104 5155 1 FF 0 0

PCO093B1 2435 0 FS 1 0 PCO18201 PCO18203 0 FS 0 0

PCO093C1 5045 0 FS 2 0 PCO18203 PCO18205 0 FS 0 0

PCO093F1 5045 0 FS 1 0 PCO18205 2041 0 FS 2 0

PCO093H1 3360 0 FS 0 0 PCO18205 3031 0 FS 0 0

PCO093H1 3371 0 FS 1 0 PCO18301 1505 0 FS 1 0

PCO09401 1200 2 FF 2 0 PCO18301 5320 0 FF 2 0

PCO09401 3370 0 FS 1 0 PCO18401 PCO18403 0 FS 0 0

1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N

1 0 0 5

M O B I L I Z A T I O N

3 0 0 0

S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5

3 0 1 5

S E D B A S I N ( N , S , E ) W A L L t o 2 6 4

3 4 0 0

P R E - O Z O N E C O N T A C TB A S I N E X C A V t o 2 4 0 . 2 5

4 0 8 0

C H E M W E S T I N S T LC O N T A I N M E N T L I N E R

4 1 9 0

C H E M W E S T R / SS P A R E B A T C H T A N K

4 1 7 2

C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S

1 3 0 0

2 N D F L A R C HI N T E R N A L M A S O N R Y

R 1 3 5 5

C H E M W E S T 2 n dF L O O R C A R P E T

1 3 0 5

2 N D F L A R C HC A R P E N T R Y / D R Y W A L L

2 2 3 0

O Z O N E / T R A N S F O R M E R R O O F I N G

4 1 2 5

C H E M W E S TM A S O N R Y T O 2 8 0

3 0 9 0

P I P E G A L L E R Y I N S T L L G P P G

3 3 2 0

C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9

3 4 0 5

C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G

1 0 2 0

S E D B A S I NE X C A V t o 2 3 6 . 1 5

1 0 7 0

S E D B A S I NS O G @ 2 3 6 . 4 0

2 3 2 5

F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

3 4 1 0

P R E - O Z O N E C O N T A C TB A S I N S O G @ 2 4 2 . 5 0

3 3 1 0

C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0

2 3 9 0

F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3

3 1 0 0

P I P E G A L L E R YE L E V S L A B @ 2 5 6

3 1 0 5

P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4

2 5 1 0

F I L T E R # 1 - 6 W A L K W A Y @2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]

2 2 5 0

O Z O N E R / S 6 "8 " O Z O N E P P G

R 1 3 2 0

C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T

R 1 3 4 5

C H E M W E S T 2 n d F L O O RR U B B E R T I L E F L O O R

R 3 3 1 0

G A C C O N T A C T O R -P . G . S A M P L E P U M P S

2 5 2 0

P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7

3 1 1 5

P I P E G A L L E R Y A R E AE L E V S L A B @ 2 6 4 . 6 7

2 3 5 5

F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7

2 4 2 5

P U M P S T A E L E VS L A B @ 2 5 0

2 3 7 0

F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

3 0 8 0

P I P E G A L L E R Y S O G @ 2 4 2 . 5 0

1 0 1 0

C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5

2 3 0 0

F L U M E S E X C A Vt o 2 2 4 . 7 5

3 0 7 5

P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G

2 3 4 0

F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

2 3 5 0

F L U M E F I L T 1 - 2 W A L Lt o H A U N C H t o 2 4 8 . 6 7

4 3 2 0

C H E M W E S T / S E T T L E D / M I X E DB Y P A S S 4 8 " 5 4 " 6 6 " P P G

2 5 0 0

F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N

2 5 2 5

P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S

R 3 3 2 0

G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S

R 1 0 6 0

C H E M W E S T 2 n d F L O O RI N S T R U M E N T A T I O N R E V I E W

R 5 0 6 0

G A R A G E -P A I N T I N G

R 5 0 5 0

G A R A G E - H O L L O WM E T A L D O O R S

4 4 6 0

C H E M W E S T R / SC H E M F E E D L I N E S

4 1 4 5

C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T

R 4 8 0 0

A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E

4 1 7 5

C H E M W E S T R / SK M n O 4 F E E D E R

2 3 9 5

F L U M E W A L Lt o 2 6 3 . 8 3

4 3 1 0

C H E M W E S T / R A W W A T E R 4 8 "P P G w / P R E C O N T A C T B Y P A S S

4 0 5 5

C H E M W E S TW A L L S t o 2 6 3

2 3 8 0

F L U M E W A L L &S L A B t o 2 5 0 . 1 6

2 3 7 5

F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2

1 1 5 0

F L O C B A S I NC O N C F I L L t o 2 4 7

3 0 2 0

P I P E G A L L E R Y S T R U C B F I L L

1 0 1 5

P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0

2 3 1 5

F L U M E S / P U M PS T A S O G @ 2 2 7

2 3 3 0

F L U M E F I L T 3 - 6 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

1 0 8 0

F L O C B A S I N F O O T I N GW A L L t o 2 4 7

2 3 4 5

F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2

3 3 1 5

C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0

4 0 6 0

C H E M W E S T B E A M S& S L A B S t o 2 6 4

4 1 0 0

C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3

2 5 3 0

P I P E G A L L E R Y / F I L T E R R O O F I N G

R 1 2 7 0

C H E M W E S TP O L Y M E R L I N E S

R 1 3 4 0

C H E M W E S T 2 n dF L O O R V C T F L O O R

R 5 0 3 5

G A R A G E -M I S C . M E T A L S

R 4 5 3 5

S I T E W O R K - C H A I NL I N K F E N C E

R 1 3 5 0

C H E M W E S T 2 n d F L O O RQ U A R R Y T I L E F L O O R

6 1 8 0

C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P

3 5 2 5

P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7

4 1 2 0

C H E M W E S TE L E V S L A B @ 2 7 6

3 3 2 5

C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7

3 3 0 0

C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5

1 0 7 5

F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5

1 0 5 0

C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S

1 0 6 0

P U M P S T A I N S T LR O C K A N C H O R S

3 1 5 0

F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M

3 3 0 5

C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0

3 3 6 0

C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7

3 3 7 5

C H E M B L D G E A S T M A S O N R Y T O 2 8 0

R 1 2 1 5

C H E M W E S TL I M E F E E D E R S

3 3 9 0

C H E M B L D GE A S T R O O F I N G

R 1 2 4 5

C H E M W E S TF I L T E R A I D L I N E S

R 1 3 0 5

C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E

R 4 6 6 5

Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( W E S T )

R 4 6 6 0

Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )

R 1 3 1 0

C H E M W E S T L A BI N S T R U M E N T A T I O N

R 1 2 6 5

C H E M W E S T P O L Y M E RM I X I N G S Y S T E M

R 4 8 0 4

A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .

R 1 7 4 1

C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7

2 4 5 5

P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7

1 1 2 0

O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K

1 0 6 5

P U M P S T AS O G @ 2 2 2

3 0 0 5

S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7

1 1 2 5

O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5

1 1 3 5

C L E A R W E L L / O Z O N E I N S T L7 2 x 4 8 S L U I C E G A T E S

2 4 5 0

P U M P S T AM A S O N R Y t o 2 8 3

R 1 7 4 0

C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6

R 1 0 3 5

C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R

6 1 3 5

C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S

R 1 3 1 5

C H E M W E S TL A B P I P I N G

R 4 5 9 0

Y A R D P I P E - 6 " T I E - I NT O H Y D R A N T ( N O R T H W E S T )

5 3 6 0

S I T E S E E D I N G& L A N D S C A P I N G

4 4 1 0

C H E M W E S T A L U M S T O R / SM I S C P P G & E Q : S E A L W A T E R

6 1 3 0

C H E M W E S T 3 R D F L R / SF E E D P U M P S & T A N K S

3 5 3 0

P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T

3 5 2 0

P R E - O Z O N E C O N T A C TB A S I N M A S O N R Y t o 2 8 0

3 3 7 0

C H E M B L D G E A S T M A S O N R Y T O 2 6 5

4 0 5 0

C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7

1 1 4 0

C L E A R W E L L / O Z O N EE L E V S L A B @ 2 5 0 + / -

1 1 1 5

O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0

1 1 1 0

O Z O N E W A L L S t o 2 4 8 . 5 0

1 1 0 0

C L E A R W E L L / O Z O N E S O G @ 2 2 7

3 1 5 5

F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4

3 4 1 5

P R E - O Z O N E C . B . E X T W A L Lt o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3

3 3 4 5

C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0

R 1 7 6 0

C H E M E A S T G L A Z E DS T R U C T U R A L T I L E

2 5 0 5

F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]

6 3 1 0

S E D B A S I N M I S CP P G & E Q U I P

R 2 6 2 7

F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N

4 4 5 5

C H E M W E S T R / S 1 5 "P V C & S A M P L E L I N E S

5 3 5 0

S I T E F I N EG R A D I N G

R 4 5 1 0

S I T E W O R K - D E M O@ P R O P A N E T A N K S

4 4 2 0

C H E M W E S T A L U M S T OR / S I N S T R U M E N T A T I O N

R 2 6 3 5

F I L T E R S - P . G .S A M P L E P U M P S

2 6 0 0

P U M P S T A M I S CP P G & E Q U I P

4 1 8 0

C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K

4 3 0 0

C H E M W E S T R / SP O L Y P H O S P H A T E T A N K

4 3 0 5

C H E M W E S T I N S T LA L U M S T O T A N K S

4 1 8 5

C H E M W E S T R / SF I L T E R A I D B A T C H T A N K

2 2 0 0

G A C A R E A M I S CP P G & E Q U I P

4 5 0 5

C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G

R 5 4 2 5

N O R T H B R A N C HI N T A K E - P A I N T I N G

R 5 4 2 0

N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N

4 5 1 5

C H E M W E S T B L O W E R R O O M R / S M I S C P P G & E Q U I P

6 3 0 5

S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P

R 1 4 1 5

C H E M W E S T 3 r dF L O O R C . M . U .

3 0 6 5

S E D B A S I N / F L O CB A S I N R O O F I N G

3 1 1 0

P I P E G A L L E R Y I N S T LS M P P G & V A L V E S

R 1 4 5 0

C H E M W E S T 2 n d F L O O RD O O R S & W I N D O W S

6 4 2 5

N O R T H B R A N C H R E P L A C EP U M P S # 1 & # 2 & P P G

5 2 1 0

G A R A G E F T GF D N @ 2 4 4

1 5 0 0

O P E R A T I O N A LP U N C H L I S T

R 1 3 3 0

C H E M W E S T 2 n d F L O O RE P O X Y T E R R A Z Z O

R 2 6 2 5

F I L T E R S - P . G .I N S T R U M E N T A T I O N R E V I E W

6 3 0 0

S E D B A S I NR / S 6 " 8 " P P G

4 1 2 6

C H E M W E S TM A S O N R Y T O 2 8 8

4 2 0 0

C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9

1 2 0 0

1 S T F L A R C HI N T E R N A L M A S O N R Y

1 3 3 5

2 N D F L A R C H M I L L W O R K

R 1 1 2 5

C H E M W E S T D I PP L A N T S E R V I C E

1 5 1 0

P R O C E S SP A I N T I N G

5 2 0 5

G A R A G EE X C A V t o 2 4 3

1 5 1 5

I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N

R 1 3 2 1

I N S T A L L S O F T W A R E& D E B U G S Y S T E M

4 4 6 5

C H E M W E S T R / SM I S C P P G & E Q U I P

R 1 4 4 5

C H E M W E S T 1 s tF L O O R D O O R S

4 1 2 7

C H E M W E S T M A S O N R YT O P A R A P E T

4 1 6 0

C H E M W E S T R / SL I M E S T O S I L O S

4 1 6 5

C H E M W E S T R / SL I M E F E E D E R H O P P E R S

R 1 4 9 5

C H E M W E S TC A S T S T O N E

4 2 0 5

C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9

R 1 1 1 5

C H E M W E S T C O P P E RW A T E R L I N E S

1 5 2 0

I N I T I A L M E C H P E R FT E S T P U N C H L I S T

1 5 2 5

F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N

6 1 9 0

C H E M W E S T 3 R D F I L T E RA I D M I S C P P G & E Q U I P

4 1 7 0

C H E M W E S T R / S L I M ED U S T C O L L E C T O R S

4 1 9 5

C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G

R 2 6 0 5

F I L T E R S - P . G .M I S C . P I P E

R 1 3 2 2

C H E M W E S T 3 r d F L O O RI N S T R U M E N T A T I O N R E V I E W

5 2 0 0

G A R A G E D E M O E X G1 6 " W A T E R M A I N

5 2 1 5

G A R A G E S O G@ 2 4 3 . 8 3

R 1 3 3 5

C H E M W E S T 2 n d F L O O RC E R A M I C T I L E F L O O R S / W A L L S

R 3 3 0 5

G A C C O N T A C T O R -I N S T R U M E N T A T I O N R E V I E W

4 1 3 5

C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3

R 4 8 0 5

A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R

R 1 3 2 5

C H E M W E S T 1 s t F L O O RR U B B E R T I L E F L O O R

5 2 2 0

G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -

5 2 2 5

G A R A G E B F I L L

R 1 3 7 5

C H E M W E S T 2 n d F L O O RA C O U S T I C A L W A L L T R E A T M E N T

1 2 0 5

1 S T F L A R C HC A R P E N T R Y / D R Y W A L L

4 2 1 0

C H E M W E S TR / S E L E V A T O R

1 3 5 5

2 N D F L A R C H P A I N T I N G

5 2 3 0

G A R A G ES O G @ 2 4 8

5 2 3 5

G A R A G EM A S O N R Y

4 3 4 5

C H E M W E S T R E C I R C M I S CP P G & E Q : S E A L W A T E R S Y S

4 4 0 0

C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P

5 2 4 0

G A R A G E S T RS T L @ 2 6 0 + / -

5 2 5 0

G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7

4 4 0 5

C H E M W E S T R / SA i r , A . F . , A . V . P P G

4 4 3 0

C H E M W E S T R / S R A WW A T E R S A M P L E P U M P

5 2 5 5

G A R A G ER O O F I N G

5 2 6 0

G A R A G EA R C H D E T A I L S

4 5 4 0

C H E M W E S T L I M E S T O M I S C P P G & E Q U I P

6 1 1 5

C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P

R 5 0 2 5

G A R A G E - F / R / PS E T T L I N G B A S I N S

5 2 9 0

G A R A G E B U I L D I N GP U N C H L I S T

1 3 9 0

A R C H I T E C T U R A L &F I N A L P U N C H L I S T

R 5 0 2 0

G A R A G E - F / R / PC O N C R E T E P A D S

R 1 4 1 0

C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E

R 1 3 8 5

C H E M W E S T 2 n d F L O O RA C O U S T I C A L T I L E C E I L I N G

R 5 0 5 5

G A R A G E -C O I L I N G D O O R S

R 1 3 9 5

C H E M W E S T 2 n d F L O O RG Y P S U M B O A R D C E I L I N G

R 1 3 9 0

C H E M W E S T 2 n d F L O O RM E T A L C E I L I N G

R 1 0 5 5

C H E M W E S T 1 s t F L O O RI N S T R U M E N T A T I O N R E V I E W

1 3 2 5

2 N D F L A R C H F L O O R I N G

P l o t D a t e 1 5 F E B 9 5D a t a D a t e 1 0 M A Y 9 1P r o j e c t S t a r t1 0 M A Y 9 1P r o j e c t F i n i s h2 6 N O V 9 3

( c ) P r i m a v e r a S y s t e m s , I n c .

A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P

P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T

W 0 0 X P a g e 1 o f 1

1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5

M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E C J A N

1 0 1 0

C L E A R W E L L / O Z O N E E X C A Vt o 2 2 4 . 7 5 / 2 1 8 . 7 5

1 1 0 5

C L E A R W E L L W A L L S t o 2 5 0

1 1 3 5

C L E A R W E L L / O Z O N E I N S T L 7 2 x 4 8 S L U I C E G A T E S

2 0 6 5

G A C P P G G A L L E R YE L E V S L A B @ 2 6 9 . 6 7

R 3 3 9 5

G A C C O N T A C T O RP A R A P E T M A S O N R Y

4 1 3 5

C H E M W E S T S T R S T LB E A M S @ 2 8 8 . 3 3

4 1 2 5

C H E M W E S T M A S O N R Y T O 2 8 0

3 4 0 0

P R E - O Z O N E C O N T A C T B A S I N E X C A V t o 2 4 0 . 2 5

1 0 7 5

F L O C B A S I NF O O T I N G @ 2 4 0 . 2 5

1 0 5 5

C L E A R W E L L / O Z O N E 2 S O G @ 2 2 1

1 0 5 0

C L E A R W E L L / O Z O N EI N S T L R O C K A N C H O R S

1 0 1 5

P U M P S T A T I O NE X C A V t o 2 1 9 . 5 0

1 0 6 5

P U M P S T AS O G @ 2 2 2

2 3 3 5

P U M P S T A T I O N W A L L S t o 2 4 8 . 6 7

1 1 2 5

O Z O N E W A L L S &C A S C A D E t o 2 4 3 . 2 5

3 3 1 5

C H E M B L D G E A S T B E A M4 4 , 4 5 , S L A B @ 2 4 7 . 5 0 , P I L A S @ 2 5 0

4 0 3 0

C H E M W E S T W A S T E W A T E RS U M P G R A D E B E A M # 1 7 & 1 8

2 1 8 5

G A C A R E A 8 "D E C K P A N E L @ 2 8 4

R 4 8 0 3

A S S O R T E D R O O F T O PW O R K C H L O R I N E B U I L D I N G

6 0 4 5

C H E M E A S T C L 2 S T O R / S M O N O R A I L

3 3 7 1

C H E M B L D G E A S TM O N O R A I L S U P P O R T S T E E L

2 1 6 0

O Z O N E / T R A N S F O R M E RE L E V S L A B # 1 @ 2 6 4 . 6 7

3 3 4 5

C H E M B L D G E A S T S T OA R E A E L E V S L A B @ 2 5 0

3 4 1 0

P R E - O Z O N E C O N T A C T B A S I N S O G @ 2 4 2 . 5 0

3 0 1 5

S E D B A S I N ( N , S , E ) W A L L t o 2 6 4

1 0 6 0

P U M P S T A I N S T LR O C K A N C H O R S

1 0 2 0

S E D B A S I NE X C A V t o 2 3 6 . 1 5

1 0 7 0

S E D B A S I NS O G @ 2 3 6 . 4 0

1 1 0 0

C L E A R W E L L / O Z O N E S O G @ 2 2 7

1 1 1 0

O Z O N E W A L L S t o 2 4 8 . 5 0

3 1 8 5

F L O C B A S I NW A L K W A Y S @ 2 6 4 . 6 7

2 5 0 0

F I L T E R # 1 - 6 I N S T LF I L T E R U / D R A I N

2 5 0 5

F I L T E R # 1 - 6 B E A M S @2 6 4 . 6 7 [ P R E C A S T = 1 5 d a y s ]

4 5 0 5

C H E M W E S T B L O W E R R O O M R / S 6 " 8 " 1 2 " A I R P P G

2 4 5 0

P U M P S T A M A S O N R Y t o 2 8 3

3 0 8 0

P I P E G A L L E R Y S O G @ 2 4 2 . 5 0

2 3 2 5

F L U M E F I L T 1 - 2 W A L L St o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

2 3 1 5

F L U M E S / P U M PS T A S O G @ 2 2 7

2 3 0 0

F L U M E S E X C A Vt o 2 2 4 . 7 5

3 0 0 0

S E D B A S I N S O G@ 2 4 0 . 4 0 / 2 4 2 . 7 5

2 3 5 0

F L U M E F I L T 1 - 2 W A L L t o H A U N C H t o 2 4 8 . 6 7

2 4 2 5

P U M P S T A E L E V S L A B @ 2 5 0

4 3 2 0

C H E M W E S T / S E T T L E D / M I X E D B Y P A S S 4 8 " 5 4 " 6 6 " P P G

5 0 5 0

L O B B Y / C O N F E R E N C EC A S T S T O N E & G R A N I T E

R 1 1 2 5

C H E M W E S T D I PP L A N T S E R V I C E

5 0 9 0

L O B B Y / C O N F R O O F I N G

R 4 1 1 5

L O B B Y / C O N F E R E N C EM E T A L C E I L I N G S Y S T E M

6 1 1 5

C H E M W E S T F E E D ( L I M E ) M I S C P P G & E Q U I P

R 1 2 1 5

C H E M W E S TL I M E F E E D E R S

R 3 1 1 5

O Z O N E E Q U I P M E N T B L D G .C A S T S T O N E / B R I C K

2 4 5 5

P U M P S T A M E Z Z P O U RW A L K W A Y @ 2 6 4 . 6 7

3 3 2 0

C H E M B L D G E A S T S T OA R E A W A L L S t o 2 4 9

2 4 3 5

P U M P S T A M E Z Z E R E C TS T R U C S T E E L t o 2 8 3

1 1 2 0

O Z O N E I N L E T O R I F I C ET R O U G H W A L L S & S U P P W O R K

3 0 2 0

P I P E G A L L E R Y S T R U C B F I L L

1 0 8 0

F L O C B A S I N F O O T I N GW A L L t o 2 4 7

3 0 0 5

S E D B A S I N S U M P S W A L L t o 2 4 1 . 1 7

2 0 0 0

C L E A R W E L L @ G A C P P G G A L L E R Y W A L L & S L A B @ 2 3 9 . 9 2

3 0 8 5

P I P E G A L L E R Y W A L L t o 2 5 4 . 8 3

4 0 4 5

C H E M W E S T F T GW A L L b e l o w 2 4 6

1 2 0 0

1 S T F L A R C H I N T E R N A L M A S O N R Y

R 1 4 4 5

C H E M W E S T 1 s tF L O O R D O O R S

3 0 3 1

S E D B A S I N W A T E R T E S T

2 1 8 0

G A C A R E A M A S O N R Y

3 1 0 5

P I P E G A L L E R Y A R E A W A L L S t o 2 6 3 . 8 4

2 0 5 0

G A C A R E A W A L L S & E L E V S L A B t o 2 6 8 . 6 7

3 0 3 0

S E D B A S I N E L E VS L A B @ 2 6 4 . 6 7

3 0 2 5

S E D B A S I N L A U N D E R C O L S W A L L S B E A M S

1 1 5 0

F L O C B A S I NC O N C F I L L t o 2 4 7

2 4 1 5

P U M P S T A P I P E A R E AW A L L S 2 3 6 t o 2 4 8 . 6 7

2 3 5 5

F L U M E F I L T 1 - 2 W A L L t o 2 6 4 . 6 7

4 0 0 5

C H E M W E S T R / S4 2 " U / S F U T P P G

2 3 9 5

F L U M E W A L Lt o 2 6 3 . 8 3

3 1 1 5

P I P E G A L L E R Y A R E A E L E V S L A B @ 2 6 4 . 6 7

4 1 7 2

C H E M W E S T - L I M E S T OR / S L I M E C O N V B L O W E R S

4 4 3 0

C H E M W E S T R / S R A WW A T E R S A M P L E P U M P

4 2 0 5

C H E M W E S T R O O F I N G@ 2 8 0 . 6 7 / 2 8 9

4 1 9 5

C H E M W E S T - L I M E S T O R / S 6 " 8 " 1 0 " P P G

4 1 2 0

C H E M W E S TE L E V S L A B @ 2 7 6

2 0 6 0

G A C P P G G A L L E R Y I N S T L P P G & S U P P @ 2 5 0

2 0 2 0

C L E A R W E L L @ G A C P P GG A L L E R Y W A L L S t o 2 4 8 . 5 0

3 1 5 0

F L O C B A S I N S O G @ ~ 2 4 9I N C L G R A D E B E A M

2 3 3 0

F L U M E F I L T 3 - 6 W A L L S t o 2 4 1 . 1 6 / 2 4 3 . 1 6 / 2 4 4 . 7 5

6 3 0 5

S E D B A S I N R / S S E D I M E N T A T I O NC O L L E C T O R E Q U I P

3 1 0 0

P I P E G A L L E R YE L E V S L A B @ 2 5 6

6 3 1 0

S E D B A S I N M I S CP P G & E Q U I P

4 1 0 0

C H E M W E S T S T R S T LC O L S / B E A M S t o 2 7 5 . 3 3 / 2 8 8 . 3 3

R 1 4 1 5

C H E M W E S T 3 r dF L O O R C . M . U .

4 1 2 7

C H E M W E S T M A S O N R YT O P A R A P E T

5 2 0 5

G A R A G EE X C A V t o 2 4 3

4 2 0 0

C H E M W E S T 8 "D E C K P A N E L S @ 2 8 9

4 1 6 5

C H E M W E S T R / SL I M E F E E D E R H O P P E R S

2 2 2 5

O Z O N E / T R A N S F O R M E R8 " D E C K P A N E L S @ 2 7 8

4 1 6 0

C H E M W E S T R / SL I M E S T O S I L O S

4 0 5 0

C H E M W E S T S O G@ 2 4 6 / 2 4 6 . 6 7

3 4 1 5

P R E - O Z O N E C . B . E X T W A L L t o 2 6 1 . 8 3 / 2 6 8 . 3 3 / 2 6 9 . 3 3

3 1 5 5

F L O C B A S I N ( N , S , W ) W A L L t o 2 6 1 . 5 8 / 2 6 4

1 1 4 0

C L E A R W E L L / O Z O N E E L E V S L A B @ 2 5 0 + / -

4 3 1 0

C H E M W E S T / R A W W A T E R 4 8 " P P G w / P R E C O N T A C T B Y P A S S

6 3 3 5

Y A R D P P G T R E A T E D W A T E RM E T E R P I T I N T P P G

R 1 1 4 0

C H E M W E S TS . S . A I R L I N E S

4 1 9 0

C H E M W E S T R / SS P A R E B A T C H T A N K

1 5 2 5

F I N A L M E C H P E R F T E S T4 8 H R P L A N T O P E R A T I O N

5 2 1 0

G A R A G E F T GF D N @ 2 4 4

5 2 2 0

G A R A G E F T G W A L L St o 2 4 7 . 2 7 + / -

1 5 1 5

I N I T I A L M E C H P E R F T E S T 4 8 H R P L A N T O P E R A T I O N

1 5 1 0

P R O C E S SP A I N T I N G

4 1 8 5

C H E M W E S T R / SF I L T E R A I D B A T C H T A N K

1 3 0 0

2 N D F L A R C H I N T E R N A L M A S O N R Y

3 4 0 5

C H E M B L D G W E S T ( N O R T H ) 2 4 " 3 6 " 4 2 " 6 " U / S P P G

2 3 8 0

F L U M E W A L L &S L A B t o 2 5 0 . 1 6

3 0 7 5

P I P E G A L L E R Y 2 4 "3 6 " 6 " 8 " U / S P P G

3 0 4 0

S E D B A S I N C O L S & B E A M S t o 2 7 7 . 3 3

3 0 6 0

S E D B A S I N M A S O N R Y t o 2 8 0 . 5 0

4 1 7 5

C H E M W E S T R / SK M n O 4 F E E D E R

6 1 3 5

C H E M W E S T 3 R D F L I N S T A L LB A T C H T A N K M I X E R S

5 1 5 5

L O B B Y / C O N F F I N I S H E S ,F U R N I S H I N G S & S P E C I A L T I E S

R 1 3 2 0

C H E M W E S T C O M P U T E RR O O M E Q U I P M E N T

R 1 3 1 0

C H E M W E S T L A BI N S T R U M E N T A T I O N

R 4 6 6 0

Y A R D P I P E - 6 " D I P H Y D R A N TM O D I F I C A T I O N ( S . E . )

R 4 6 6 5

5 2 9 0R 4 5 1 5

S I T E W O R K -D R I V E " A "

5 2 4 0

G A R A G E S T RS T L @ 2 6 0 + / -

5 2 1 5

G A R A G E S O G@ 2 4 3 . 8 3

R 1 3 2 1

I N S T A L L S O F T W A R E& D E B U G S Y S T E M

R 1 3 0 5

C H E M W E S T L A BE Q U I P M E N T / F U R N I T U R E

5 3 1 5

Y A R D P P G I N S T A L LC O N T A I N M E N T T A N K & P P G

2 2 3 0

O Z O N E / T R A N S F O R M E R R O O F I N G

2 5 3 0

P I P E G A L L E R Y / F I L T E R R O O F I N G

2 5 2 5

P I P E G A L L E R Y / F I L T E R 1 2 " D E C K P A N E L S

2 5 2 0

P I P E G A L L E R Y / F I L T E R S T R S T L t o 2 7 7

2 5 1 0

F I L T E R # 1 - 6 W A L K W A Y @ 2 6 5 . 3 3 [ P R E C A S T = 1 5 d a y s ]

3 3 1 0

C H E M B L D G E A S TW A L L t o 2 4 3 / / 2 5 0

1 1 1 5

O Z O N E B A F F L E W A L L St o 2 4 2 . 2 5 / 2 4 7 . 5 0

3 3 0 0

C H E M B L D G E A S T I N T L5 4 " U / S P P G @ 2 2 5 . 2 5

3 3 0 5

C H E M B L D G E A S T S O GS T E P F T G S @ 2 3 0 / / 2 4 0 . 5 0

3 3 2 5

C H E M B L D G E A S T C O L S t o 2 6 4 . 6 7

3 3 6 0

C H E M B L D G E A S T B E A M S4 3 , 4 6 , 4 7 & S L A B @ 2 6 4 . 6 7

3 3 7 0

C H E M B L D G E A S T M A S O N R Y T O 2 6 5

R 3 3 2 0

G A C C O N T A C T O R -P L A N T S E R V I C E L I N E S

R 3 3 1 0

G A C C O N T A C T O R -P . G . S A M P L E P U M P S

R 2 6 2 7

F I L T E R O P E R A T I N GR O O M I N S T R U M E N T A T I O N

R 1 3 1 5

C H E M W E S TL A B P I P I N G

R 5 4 2 0

N O R T H B R A N C H I N T A K E- I N S T R U M E N T A T I O N

5 2 5 0

G A R A G E 8 " D E C KP A N E L S @ 2 6 2 . 6 7

5 2 2 5

G A R A G E B F I L L

1 5 2 0

I N I T I A L M E C H P E R FT E S T P U N C H L I S T

R 1 0 3 5

C H E M W E S T C O N C R E T E P A D S& C U R B S - 3 R D F L O O R

R 1 7 4 0

C H E M B L D G E A S T C L 2 A R E A 8 " D E C K P A N E L S @ 2 6 6

5 0 3 0

L O B B Y / C O N F M A S O N R Y

2 6 0 0

P U M P S T A M I S C P P G & E Q U I P

2 3 9 0

F L U M E U - S H A P Et o 2 5 4 . 8 3 / 2 5 8 . 3 3

2 3 4 0

F L U M E F I L T 1 - 2 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

2 3 4 5

F L U M E F I L T 1 - 2E L E V S L A B @ 2 4 6 . 4 2

4 0 4 0

C H E M W E S T C O L S

4 0 6 0

C H E M W E S T B E A M S & S L A B S t o 2 6 4

3 3 7 5

C H E M B L D G E A S T M A S O N R Y T O 2 8 0

6 1 8 0

C H E M W E S T F I L T E R A I D M I S C P P G & E Q U I P

5 2 3 0

G A R A G ES O G @ 2 4 8

5 2 5 5

G A R A G E R O O F I N G

5 2 6 0

G A R A G EA R C H D E T A I L S

5 2 3 5

G A R A G EM A S O N R Y

R 4 8 0 5

A S S O R T E D R O O F T O P W O R KC H E M W E S T 3 r d F L O O R

R 1 7 4 1

C H E M B L D G E A S T E L E C A R E A 8 " D E C K P A N E L S @ 2 8 0 . 6 7

3 0 9 0

P I P E G A L L E R Y I N S T L L G P P G

2 3 7 0

F L U M E F I L T 3 - 6 E L E VS L A B @ 2 4 4 / 2 4 4 . 7 5

2 3 7 5

F L U M E F I L T 3 - 6E L E V S L A B @ 2 4 6 . 4 2

4 0 5 5

C H E M W E S T W A L L S t o 2 6 3

4 0 8 0

C H E M W E S T I N S T LC O N T A I N M E N T L I N E R

4 1 4 5

C H E M W E S T / S K Y L I G H T F R A M I N G R O O F I N G i n c S K Y L I G H T

4 1 2 9

C H E M W E S T M A S O N R Y T O 2 7 7

4 6 1 5

C H E M W E S T W E S T O FC L # 3 W A L L S T O 2 6 3

6 3 0 0

S E D B A S I N R / S 6 " 8 " P P G

R 1 4 9 5

C H E M W E S T C A S T S T O N E

1 5 0 0

O P E R A T I O N A LP U N C H L I S T

R 1 2 4 5

C H E M W E S TF I L T E R A I D L I N E S

3 0 6 5

S E D B A S I N / F L O CB A S I N R O O F I N G

R 1 7 6 0

C H E M E A S T G L A Z E DS T R U C T U R A L T I L E

3 5 0 5

P R E - O Z O N E C O N T A C T B A S I N E L E V S L A B @ 2 6 9 . 3 3

4 3 0 5

C H E M W E S T I N S T LA L U M S T O T A N K S

2 1 7 0

G A C A R E A R O O FF R A M I N G S T E E L

4 1 2 6

C H E M W E S TM A S O N R Y T O 2 8 8

4 4 0 0

C H E M W E S T A L U M S T O R / SA L U M T R A N S F E R P U M P

R 2 6 3 5

F I L T E R S - P . G .S A M P L E P U M P S

3 5 2 5

P R E - O Z O N E C O N T A C T B A S I N 8 " D E C K P A N E L S @ 2 8 0 . 6 7

3 5 2 0

P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o 2 8 0

5 0 4 5

L O B B Y / C O N F S T R S T Lt o 2 8 6 . 6 5 - P A R T I A L

R 4 8 0 0

A S S O R T E D R O O F T O P W O R KF L O C C . / S . B . / F I L T E R / O Z O N E

4 1 8 0

C H E M W E S T R / SP O L Y P H O S P H A T E B A T C H T A N K

4 1 7 0

C H E M W E S T R / S L I M ED U S T C O L L E C T O R S

4 3 0 0

C H E M W E S T R / SP O L Y P H O S P H A T E T A N K

2 4 6 5

P U M P S T A 8 "D E C K P A N E L S @ 2 8 4

R 4 8 0 1

A S S O R T E D R O O F T O PW O R K H . S . P . S .

3 5 3 0

P R E - O Z O N E C O N T A C T B A S I N M A S O N R Y t o P A R A P E T

4 5 4 0

C H E M W E S T L I M E S T O M I S C P P G & E Q U I P

3 3 9 0

C H E M B L D GE A S T R O O F I N G

R 4 8 0 4

A S S O R T E D R O O F T O P W O R KE L E C T R I C A L R O O M / C . B .

R 4 8 0 2

A S S O R T E D R O O F T O PW O R K G A C C O N T A C T O R

R 1 4 1 0

C H E M W E S T 3 r d F L O O RG L A Z E D S T R U C T U R A L T I L E

P l o t D a t e 1 5 F E B 9 5D a t a D a t e 1 F E B 9 5P r o j e c t S t a r t1 0 M A Y 9 1P r o j e c t F i n i s h3 1 J A N 9 5

( c ) P r i m a v e r a S y s t e m s , I n c .

A c t i v i t y B a r / E a r l y D a t e sa c t i d S U M M A R Y R O L L - U P

P . S . C O N C R E T E C . W . / O Z O N E / G A C C O N C R E T ES . B . / F L O C C C O N C R E T E F L U M E / F I L T E R / P . G . C O N C R E T EC H E M E A S T C O N C R E T E C O N T A C T B A S I N C O N C R E T EC H E M W E S T C O N C R E T E L / C C O N C R E T ES T R U C T U R A L S T E E L M A S O N R YR O O F D E C K M E C H E Q U I P M E N T

R 8 U 1 P a g e 1 o f 1

As-Planned v. As-Built Summary

As-Planned v As-Impacted v As-Built

As-Plan of Significant Acitivities

As-Built of Significant Activities

CHANGE ORDERS IMPACTING CRITICAL WORK & IMPACT TO WORK DURATIONS

Actual Actual Crit. # of BasePCO'sPCO TF

But the duration of each activityin the CPM is only an estimateExpected Duration is -15%/+20%

Page 11: Evidence Issues in Forensic Use of CPM Scheduling

Intrinsic Unreliability of CPM

• 10 + 10 + 10 ≠ 30

• Leveled Schedule ≤ 2 x Optimal Schedule

Page 12: Evidence Issues in Forensic Use of CPM Scheduling

Risk and Monte Carlo Simulation

Project Duration ≈ 31⅔

LATEST DATE 5 JUN 6 EXPECTED DATE 31 MAY 6 EARLIEST DATE 26 MAY 6 TARGET DATE 30 MAY 06

Plot Date 10FEB06 (c) Primavera Systems, Inc.

MONTE CARLO TEST #2Title

Finish Date of Project

MC02MPRJ.MC Sheet 1 of 1

Date Revision Checked Approved

0

10

20

30

40

50

60

70

80

90

100

%

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

%

26 27 28 29 30 31 32 33 34 35 36DAY

A 10±2B 10±2C 10±2D 10±2 ≈ 40

Estimating

A 10±2

B 10±2

C 10±2

D 10±2

Scheduling

Excerpt from page 142 of CPM in Construction Management

Page 13: Evidence Issues in Forensic Use of CPM Scheduling

Excerpt from page 142 of CPM in Construction Management

A 10±2

B 10±2

C 10±2

D 10±2

Page 14: Evidence Issues in Forensic Use of CPM Scheduling

State of the Art Analysis?

LATEST DATE 23 SEP 93 EXPECTED DATE 5 AUG 93 EARLIEST DATE 16 JUN 93 TARGET DATE 14 JUN 93

Plot Date 24NOV08 (c) Primavera Systems, Inc.

N PENN and N WALES WATER AUTHORITYFOREST PARK WATER TREATMENT PLANT

TitleFinish Date of Project

W00VMPRJ.MC Sheet 1 of 1ALLAN A. MYERS, INC. -- ENPROMAC, INC.

Date Revision Checked Approved

0

10

20

30

40

50

60

70

80

90

100

%

0

1

2

3

4

%

14

JUN

93

21

JUN

93

28

JUN

93

5

JUL

93

12

JUL

93

19

JUL

93

26

JUL

93

2

AUG

93

9

AUG

93

16

AUG

93

23

AUG

93

30

AUG

93

6

SEP

93

13

SEP

93

20

SEP

93

LATEST DATE 23 SEP 93 EXPECTED DATE 5 AUG 93 EARLIEST DATE 16 JUN 93 TARGET DATE 14 JUN 93

Plot Date 24NOV08 (c) Primavera Systems, Inc.

Not Named WATER AUTHORITYNot Named WATER TREATMENT PLANT

Initial Schedule Submittal (As-Planned)Finish Date of Project

W00VMPRJ.MC Sheet 1 of 1ALLAN A. MYERS, INC. -- ENPROMAC, INC.

Date Revision Checked Approved

0

10

20

30

40

50

60

70

80

90

100

%

0

1

2

3

4

%

14

JUN

93

21

JUN

93

28

JUN

93

5

JUL

93

12

JUL

93

19

JUL

93

26

JUL

93

2

AUG

93

9

AUG

93

16

AUG

93

23

AUG

93

30

AUG

93

6

SEP

93

13

SEP

93

20

SEP

93

ACTIVITY IDACTIVITY

DESCRIPTIONORIGDUR

ActualDuration

EARLYSTART

EARLYFINISH PCO1 PCO2 Z1TF

1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB

1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0

1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0

1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0

1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0

3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0

3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0

1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0

1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0

1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0

3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0

3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0

3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0

3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58

3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58

4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0

3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58

4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0

3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58

4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0

4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0

4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0

3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58

R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58

3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66

R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330

R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58

3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58

R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58

3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63

4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0

4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0

4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0

R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29

3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0

R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0

4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1

3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7

2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47

3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0

3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63

4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1

4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7

4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1

4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1

R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0

4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1

4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1

4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1

4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1

R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21

R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1

4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21

1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1

1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17

R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9

4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1

4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10

R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28

R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65

1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9

R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6

R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0

R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5

R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10

R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15

R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14

R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6

R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0

R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5

R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10

R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4

R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6

R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4

R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10

R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4

R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6

R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5

R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0

R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0

1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15

R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0

1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15

1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0

1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0

1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0

1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0

5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0

END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33

5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0

5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1

5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0

5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0

5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0

5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0

5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0

5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0

5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0

5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0

5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0

1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0

1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0

END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0

NOTICE TO PROCEED

MOBILIZATION

SED BASIN EXCAV to 236.15

SED BASIN SOG @ 236.40

SED BASIN SOG @ 240.40/242.75

SED BASIN (N,S,E) WALL to 264

FLOC BASIN FOOTING @ 240.25

FLOC BASIN FOOTING WALL to 247

FLOC BASIN CONC FILL to 247

FLOC BASIN SOG @~249 INCL GRADE BEAM

FLOC BASIN (N,S,W) WALL to 261.58/264

PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33

CHEM BLDG EAST SOG STEP FTGS @ 230//240.50

CHEM BLDG EAST WALL to 243//250

CHEM WEST SOG @ 246/246.67

CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250

CHEM WEST WALLS to 263

CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67

CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS

CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG

CHEM WEST BEAMS & SLABS to 264

CHEM BLDG EAST MASONRY TO 265

CHEM EAST GLAZED STRUCTURAL TILE

CHEM BLDG EAST MONORAIL SUPPORT STEEL

CHEM EAST CAST STONE/BRICK

CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266

CHEM BLDG EAST MASONRY TO 280

CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67

CHEM BLDG EAST MASONRY TO PARAPET

CHEM WEST STR STL COLS/BEAMS to 275.33/288.33

CHEM WEST ELEV SLAB @ 276

CHEM WEST MASONRY TO 280

CHEM WEST 3rd FLOOR C.M.U.

PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67

ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.

CHEM WEST MASONRY TO 288

PRE-OZONE CONTACT BASIN MASONRY to PARAPET

PIPE GALLERY/FILTER 12" DECK PANELS

CHEM BLDG EAST ROOFING

PRE-OZONE CONTACT BASIN ROOFING

CHEM WEST R/S LIME STO SILOS

CHEM WEST STR STL BEAMS @ 288.33

CHEM WEST R/S LIME FEEDER HOPPERS

CHEM WEST R/S LIME DUST COLLECTORS

ELECTRICAL ROOM MISCELLANEOUS WORK

CHEM WEST - LIME STO R/S LIME CONV BLOWERS

CHEM WEST - LIME STO R/S 6" 8" 10" PPG

CHEM WEST 8" DECK PANELS @ 289

CHEM WEST MASONRY TO PARAPET

ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR

CHEM WEST CAST STONE

CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT

2ND FL ARCH INTERNAL MASONRY

1ST FL ARCH INTERNAL MASONRY

2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING

CHEM WEST ROOFING @ 280.67/289

CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG

CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE

FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS

2ND FL ARCH ELEC R/I

1st FLOOR CHEM WEST PIPING & PANELS

2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS

S.B./FILTERS/FLOCC. PULL FEEDERS

CHEM EAST/PUMP STATION PULL FEEDERS

3rd FLOOR CHEM WEST PULL FEEDERS

CHEM WEST COMPUTER ROOM EQUIPMENT

1st FLOOR CHEM WEST PULL FEEDER WIRE

2nd FLOOR CHEM WEST/C.B. BRANCH WIRING

S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS

CHEM EAST/PUMP STATION PULL BRANCH WIRING

CHEM WEST LAB PIPING

1st FLOOR CHEM WEST PULL BRANCH WIRING

CHEM WEST LAB INSTRUMENTATION

CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT

CHEM WEST LAB EQUIPMENT/FURNITURE

1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT

S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT

2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE

ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS

OPERATIONAL PUNCHLIST

INSTALL SOFTWARE & DEBUG SYSTEM

PROCESS PAINTING

INITIAL MECH PERF TEST OPER TESTING & TRAINING

INITIAL MECH PERF TEST 48 HR PLANT OPERATION

INITIAL MECH PERF TEST PUNCHLIST

FINAL MECH PERF TEST 48 HR PLANT OPERATION

GARAGE EXCAV to 243

880 DAY PART A COMPLETION

GARAGE SOG @ 243.83

GARAGE FTG FDN @ 244

GARAGE FTG WALLS to 247.27 +/-

GARAGE BFILL

GARAGE SOG @ 248

GARAGE MASONRY

GARAGE STR STL @ 260 +/-

GARAGE 8" DECK PANELS @ 262.67

GARAGE ROOFING

GARAGE ARCH DETAILS

GARAGE BUILDING PUNCHLIST

ARCHITECTURAL & FINAL PUNCHLIST

OWNER ACCEPTANCE

1065 DAY PART B COMPLETION

Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95

(c) Primavera Systems, Inc.

inactiveALLAN A. MYERS, INC. - COMBINED WORKING SCHEDULE

Date ApprovedCheckedRevision

As-Built v As-Impacted v As-Planned

FOREST PARK WATER TREATMENT PLANT

N PENN and N WALES WATER AUTHORITYSheet 1 of 1

As-BuiltAs-PlannedAs-Impacted

nProMaC, Inc

Probability of completion on timeis less than one percent

Why?

Completion by 05AUG93has only 50% chance

Completion by 27AUG93has only 90% chance

Page 15: Evidence Issues in Forensic Use of CPM Scheduling

59%-15%/+20%

A 10±2

B 10±2

C 10±2

D 10±2

Why is the probability for 14JUN93 so low?

41%

PCT PREDECESSOR REL PCT FREE ACTIVITY DESCRIPTION CRIT ACTIVITIES DESCRIPTION TYPE CRIT FLOAT ----------- ---------------------------------------- ---- ----------- ---------------------------------------- ------- ---- ------ 2230 OZONE/TRANSFORMER ROOFING 59 2225 OZONE/TRANSFORMER 8" DECK PANELS @ 278 FS 0.0 59 0.0 75307 ROOFING- FAB AND DELIVER FS 0.0 0 215.8 1300 2ND FL ARCH INTERNAL MASONRY 100 2190 GAC AREA ROOFING FS 0.0 0 17.6 2230 OZONE/TRANSFORMER ROOFING FS 0.0 59 3.8 2470 PUMP STA ROOFING FS 0.0 0 124.3 2530 PIPE GALLERY/FILTER ROOFING FS 0.0 0 92.7 3065 SED BASIN/FLOC BASIN ROOFING FS 0.0 0 40.1 3390 CHEM BLDG EAST ROOFING FS 0.0 0 127.5 3535 PRE-OZONE CONTACT BASIN ROOFING FS 0.0 0 31.6 4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc FS 0.0 0 20.0 4205 CHEM WEST ROOFING @ 280.67/289 FS 0.0 41 7.4 1305 2ND FL ARCH CARPENTRY/DRYWALL 100 1300 2ND FL ARCH INTERNAL MASONRY FS 0.0 100 0.0 79007 CAULKING - FAB AND DELIVER FS 0.0 0 286.1 81107 HOLLOW METAL DOORS - FAB AND DELIVER FS 0.0 0 254.5 81207 ALUMINIUM DOORS - FAB AND DELIVER FS 0.0 0 254.5 85207 ALUMINIUM WINDOWS - FAB AND DELIVER FS 0.0 0 254.5

100%

Alternate Probable Critical Paths

Page 16: Evidence Issues in Forensic Use of CPM Scheduling

Evidence Issues for any CPM• CPM may be less certain than generally believed

• Certainty of the proffered CPM should be questioned

• Understanding of the “expert” relating to Risk is fair game

59%

41%

100%

PCT PREDECESSOR REL PCT FREE ACTIVITY DESCRIPTION CRIT ACTIVITIES DESCRIPTION TYPE CRIT FLOAT ----------- ---------------------------------------- ---- ----------- ---------------------------------------- ------- ---- ------ 2230 OZONE/TRANSFORMER ROOFING 59 2225 OZONE/TRANSFORMER 8" DECK PANELS @ 278 FS 0.0 59 0.0 75307 ROOFING- FAB AND DELIVER FS 0.0 0 215.8 1300 2ND FL ARCH INTERNAL MASONRY 100 2190 GAC AREA ROOFING FS 0.0 0 17.6 2230 OZONE/TRANSFORMER ROOFING FS 0.0 59 3.8 2470 PUMP STA ROOFING FS 0.0 0 124.3 2530 PIPE GALLERY/FILTER ROOFING FS 0.0 0 92.7 3065 SED BASIN/FLOC BASIN ROOFING FS 0.0 0 40.1 3390 CHEM BLDG EAST ROOFING FS 0.0 0 127.5 3535 PRE-OZONE CONTACT BASIN ROOFING FS 0.0 0 31.6 4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc FS 0.0 0 20.0 4205 CHEM WEST ROOFING @ 280.67/289 FS 0.0 41 7.4 1305 2ND FL ARCH CARPENTRY/DRYWALL 100 1300 2ND FL ARCH INTERNAL MASONRY FS 0.0 100 0.0 79007 CAULKING - FAB AND DELIVER FS 0.0 0 286.1 81107 HOLLOW METAL DOORS - FAB AND DELIVER FS 0.0 0 254.5 81207 ALUMINIUM DOORS - FAB AND DELIVER FS 0.0 0 254.5 85207 ALUMINIUM WINDOWS - FAB AND DELIVER FS 0.0 0 254.5

-15%/+20%

A 10±2

B 10±2

C 10±2

D 10±2

59%

41%

100%

PCT PREDECESSOR REL PCT FREE ACTIVITY DESCRIPTION CRIT ACTIVITIES DESCRIPTION TYPE CRIT FLOAT ----------- ---------------------------------------- ---- ----------- ---------------------------------------- ------- ---- ------ 2230 OZONE/TRANSFORMER ROOFING 59 2225 OZONE/TRANSFORMER 8" DECK PANELS @ 278 FS 0.0 59 0.0 75307 ROOFING- FAB AND DELIVER FS 0.0 0 215.8 1300 2ND FL ARCH INTERNAL MASONRY 100 2190 GAC AREA ROOFING FS 0.0 0 17.6 2230 OZONE/TRANSFORMER ROOFING FS 0.0 59 3.8 2470 PUMP STA ROOFING FS 0.0 0 124.3 2530 PIPE GALLERY/FILTER ROOFING FS 0.0 0 92.7 3065 SED BASIN/FLOC BASIN ROOFING FS 0.0 0 40.1 3390 CHEM BLDG EAST ROOFING FS 0.0 0 127.5 3535 PRE-OZONE CONTACT BASIN ROOFING FS 0.0 0 31.6 4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc FS 0.0 0 20.0 4205 CHEM WEST ROOFING @ 280.67/289 FS 0.0 41 7.4 1305 2ND FL ARCH CARPENTRY/DRYWALL 100 1300 2ND FL ARCH INTERNAL MASONRY FS 0.0 100 0.0 79007 CAULKING - FAB AND DELIVER FS 0.0 0 286.1 81107 HOLLOW METAL DOORS - FAB AND DELIVER FS 0.0 0 254.5 81207 ALUMINIUM DOORS - FAB AND DELIVER FS 0.0 0 254.5 85207 ALUMINIUM WINDOWS - FAB AND DELIVER FS 0.0 0 254.5

-15%/+20%

A 10±2

B 10±2

C 10±2

D 10±2A 10±2

B 10±2

C 10±2

D 10±2

Page 17: Evidence Issues in Forensic Use of CPM Scheduling

Specific Flaws of this CPM

• Frye Credential Test• Daubert Theory Test• Testimony by Expert• Ultimate Conclusion

Analytical Gap Test

Page 18: Evidence Issues in Forensic Use of CPM Scheduling

Specific Flaws of this CPM

• Is the As-Planned a CPM or only a bar-chart?• Logic network from one start end to one finish end – no other open ends!

• Every activity must have a physical methodology predecessor & successor

• Activities Placed by Logic Restraints – NOT Date Constraints

• Proper Logic May Be Restated in “ADM” Finish-to-Start-no-Lag Format

• Resource (preferential) Logic Not Probative for Delay Analyses• But how do we distinguish Physical from Resource Logic?

• How reliable is this CPM to establish a claim of delay or disruption?

Page 19: Evidence Issues in Forensic Use of CPM Scheduling

Primavera Scheduling and Leveling Calculations -- Scheduling Report Page: 1 This Primavera software is registered to EnProMaC. Start of schedule for project 367B. Serial number...19123456 User name FRED .

Open end listing -- Scheduling Report Page: 11 ---------------- Activity 100.000000 has no predecessors Activity 100.000100 has no predecessors Activity 100.000200 has no predecessors Activity 100.000210 has no predecessors Activity 100.000300 has no predecessors Activity 100.000400 has no predecessors Activity 100.000520 has no predecessors Activity 100.000530 has no predecessors Activity 100.000572 has no predecessors Activity 100.000573 has no predecessors Activity 100.000574 has no predecessors Activity 100.000575 has no predecessors Activity 100.000577 has no predecessors Activity 100.000600 has no predecessors Activity 100.000690 has no predecessors Activity 100.009999 has no successors Activity 121.130007 has no successors Activity 121.130010 has no predecessors Activity 121.130010 has no successors Activity 121.130013 has no successors Activity 121.130014 has no successors Activity 121.130015 has no successors Activity 121.130031 has no successors Activity 121.130032 has no successors Activity 121.130046 has no successors Activity 121.130057 has no successors Activity 121.130060 has no successors Activity 121.130095 has no successors

Scheduling Statistics for Project 367B: Schedule calculation mode - Progress override Schedule calculation mode - Contiguous activities Float calculation mode - Use finish dates Schedule run on Thu Dec 25 14:07:26 2008 Run Number 485.

Number of activities.................. 2161 Number of activities in longest path.. 30 Started activities.................... 0 Completed activities.................. 0 Number of relationships............... 4024 Percent complete...................... 0.0 Number of hammocks ................... 41 Number of expected finish activities.. 3 Number of early constraints........... 44 Number of late constraints........... 2

Data date............................. 01MAR96 Start date............................ 01MAR96 Imposed finish date................... Latest calculated early finish........ 02JUL97

As-Planned Logic?

Contractor v U.S. NavyReview using P3 diagnosticCheck for Open EndsCheck for ConstraintsCheck for Critical Path

Page 20: Evidence Issues in Forensic Use of CPM Scheduling

As-Planned Logic?

Contractor v U.S. NavyReviewing detail of each activity

Why do all predecessors of a critical activity have float?

How does critical path startten months into project?

Checking Logic of Critical & Near Critical Paths

Page 21: Evidence Issues in Forensic Use of CPM Scheduling

RDM Analysis of the As-Planned Logic

• check for hidden open ends• check for misunderstood logic SS 5

FF 5

A

B 10

C

A 10

C 10

need never finish

may start anytime

Day 10

A 20

B 10

FF5

SS5

SS5 C 10

interruptible duration

Page 22: Evidence Issues in Forensic Use of CPM Scheduling

RDM Analysis of the As-Planned Logic

• check for hidden open ends• check for misunderstood logic• check for physical v resource logic

Day 10

A 20

B 10

FF5

SS5

SS5 C 10

interruptible duration continuous duration

A 20

B 10

FF5

SS5

SS5 C 10

Day 20ES = EF – Dur ?

R eason/W hy Codes

Steel required before elev floor slabs

SubcHandoff CraftChange TowerSame FloorSame

Steel required before eForm crew moves to floSlab required before ro

R eason/W hy Codes

Steel required before elev floor slabs

SubcHandoff CraftChange TowerSame FloorSame

Steel required before eForm crew moves to floSlab required before ro

Page 23: Evidence Issues in Forensic Use of CPM Scheduling

RDM Analysis of the As-Planned Logic

• check for hidden open ends• check for misunderstood logic• check for physical v resource logic• check for physical-logic-only open ends• check if the as-planned is a CPM or merely a bar-chart

R eason/Why Codes

Steel required before elev floor slabs

SubcHandoff CraftChange TowerSame FloorSame

Steel required before eForm crew moves to floSlab required before ro

R eason/Why Codes

Steel required before elev floor slabs

SubcHandoff CraftChange TowerSame FloorSame

Steel required before eForm crew moves to floSlab required before ro

Page 24: Evidence Issues in Forensic Use of CPM Scheduling

Our Example Today

The CPM Schedule

The Bridge Hotels and Casino

Page 25: Evidence Issues in Forensic Use of CPM Scheduling

Entitlement to Total Delay

_____ 226

Direct ExaminationTestimony for the Contractor

Page 26: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

• set the predicate for a proper CPM• every activity (other than first) must have a predecessor• every activity (other than last) must have a successor• if these rules not followed the logic network will have open ends• what is wrong with open ends?• this required logic must be methodology (physical), not just resource • non-physical resource restraint example – crew from tower to tower• if non-physical resource restraints are removed – more open ends?

• does CPM used for this analysis meet these criteria?

Cross-Examination

Page 27: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

Page 28: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

Page 29: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

Page 30: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

bars look good!

Page 31: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

logic not so good!

Page 32: Evidence Issues in Forensic Use of CPM Scheduling

attacking the report

with Pertmaster RDCPMignored resource logicmakes logic looks bad!

Page 33: Evidence Issues in Forensic Use of CPM Scheduling

Decision Time

_____ 226

Page 34: Evidence Issues in Forensic Use of CPM Scheduling

Evidence Issues for this CPM

• The As-Planned Schedule Logic may be flawed

• Distinguishing Methodology from Resource Logic is key

• Understanding of the “expert” relating to Logic is fair gameACTIVITY ID

ACTIVITYDESCRIPTION

ORIGDUR

ActualDuration

EARLYSTART

EARLYFINISH PCO1 PCO2 Z1TF

1991 1992 1993 1994 1995MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB

1000 NOTICE TO PROCEED 1 1 10MAY91A 10MAY91A 0

1005 MOBILIZATION 10 10 10MAY91A 23MAY91A 0

1020 SED BASIN EXCAV to 236.15 5 24 24MAY91A 27JUN91A 005 1 0

1070 SED BASIN SOG @ 236.40 15 38 12JUL91A 4SEP91A 005 1 0

3000 SED BASIN SOG @ 240.40/242.75 44 50 15JUL91A 23SEP91A 0

3015 SED BASIN (N,S,E) WALL to 264 64 84 5SEP91A 3JAN92A 009 1 0

1075 FLOC BASIN FOOTING @ 240.25 5 5 14NOV91A 20NOV91A 0

1080 FLOC BASIN FOOTING WALL to 247 5 5 21NOV91A 27NOV91A 0

1150 FLOC BASIN CONC FILL to 247 1 1 29NOV91A 29NOV91A 0

3150 FLOC BASIN SOG @~249 INCL GRADE BEAM 40 25 2DEC91A 7JAN92A 022 1 0

3155 FLOC BASIN (N,S,W) WALL to 261.58/264 50 48 2JAN92A 9MAR92A 022 2 0

3415 PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33 40 73 21APR92A 2OCT92A 053 1 0

3305 CHEM BLDG EAST SOG STEP FTGS @ 230//240.50 6 8 18JUN92A 29JUN92A 029 1 58

3310 CHEM BLDG EAST WALL to 243//250 22 22 1JUL92A 31JUL92A 008 1 58

4050 CHEM WEST SOG @ 246/246.67 30 16 26OCT92A 16NOV92A 0

3315 CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250 16 22 5AUG92A 3SEP92A 058 1 58

4055 CHEM WEST WALLS to 263 30 230 13JUL92A 27AUG93A 045 1 0

3360 CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67 25 28 17DEC92A 27JAN93A 093 2 58

4310 CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS 4 120 10AUG92A 28JAN93A 0

4320 CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG 10 158 27AUG92A 9APR93A 0

4060 CHEM WEST BEAMS & SLABS to 264 50 52 16SEP92A 8MAR93A 084 3 0

3370 CHEM BLDG EAST MASONRY TO 265 10 26 22MAR93A 26APR93A 097 2 58

R1760 CHEM EAST GLAZED STRUCTURAL TILE 10 6 19APR93A 26APR93A 58

3371 CHEM BLDG EAST MONORAIL SUPPORT STEEL 2 4 21APR93A 27APR93A 131 2 66

R1795 CHEM EAST CAST STONE/BRICK 10 67 20APR93A 25JUL93A 330

R1740 CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266 2 8 28APR93A 7MAY93A 58

3375 CHEM BLDG EAST MASONRY TO 280 10 16 8MAY93A 1JUN93A 58

R1741 CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67 2 3 2JUN93A 4JUN93A 58

3385 CHEM BLDG EAST MASONRY TO PARAPET 5 36 5JUN93A 27JUL93A 63

4100 CHEM WEST STR STL COLS/BEAMS to 275.33/288.33 6 12 19MAR93A 5APR93A 0

4120 CHEM WEST ELEV SLAB @ 276 24 30 29MAR93A 7MAY93A 121 5 0

4125 CHEM WEST MASONRY TO 280 10 176 19OCT92A 27JUN93A 187 1 0

R1415 CHEM WEST 3rd FLOOR C.M.U. 8 36 16JUN93A 5AUG93A 29

3525 PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67 5 3 2JUN93A 4JUN93A 0

R4804 ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B. 10 30 4JUN93A 16JUL93A 117 1 0

4126 CHEM WEST MASONRY TO 288 15 15 5JUN93A 27JUN93A 1

3530 PRE-OZONE CONTACT BASIN MASONRY to PARAPET 3 10 17MAY93A 28MAY93A 7

2525 PIPE GALLERY/FILTER 12" DECK PANELS 5 20 21APR93A 18MAY93A 47

3390 CHEM BLDG EAST ROOFING 8 25 28JUL93A 31AUG93A 079 2 0

3535 PRE-OZONE CONTACT BASIN ROOFING 8 9 19AUG93A 31AUG93A 63

4160 CHEM WEST R/S LIME STO SILOS 1 1 23DEC92A 23DEC92A 1

4135 CHEM WEST STR STL BEAMS @ 288.33 10 13 28JUN93A 15JUL93A 150 1 7

4165 CHEM WEST R/S LIME FEEDER HOPPERS 1 4 17MAY93A 20MAY93A 1

4170 CHEM WEST R/S LIME DUST COLLECTORS 2 2 13MAY93A 14MAY93A 1

R6155 ELECTRICAL ROOM MISCELLANEOUS WORK 88 84 16APR93A 13AUG93A 0

4172 CHEM WEST - LIME STO R/S LIME CONV BLOWERS 2 3 10MAY93A 12MAY93A 1

4195 CHEM WEST - LIME STO R/S 6" 8" 10" PPG 10 36 20MAY93A 12JUL93A 1

4200 CHEM WEST 8" DECK PANELS @ 289 20 19 21JUL93A 16AUG93A 1

4127 CHEM WEST MASONRY TO PARAPET 10 11 17AUG93A 31AUG93A 1

R4805 ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR 10 6 24AUG93A 31AUG93A 117 1 21

R1495 CHEM WEST CAST STONE 20 98 1MAR93A 8SEP93A 141 2 1

4145 CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT 8 7 31AUG93A 9SEP93A 21

1300 2ND FL ARCH INTERNAL MASONRY 25 200 19OCT92A 30JUL93A 148 2 1

1200 1ST FL ARCH INTERNAL MASONRY 20 195 26OCT92A 30JUL93A 145 2 17

R6090 2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING 30 33 15JUL93A 30AUG93A 9

4205 CHEM WEST ROOFING @ 280.67/289 8 9 2SEP93A 15SEP93A 1

4505 CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG 5 123 28DEC92A 18JUN93A 10

R1410 CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE 7 42 16JUN93A 13AUG93A 28

R2675 FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS 1 1 30APR93A 30APR93A 65

1320 2ND FL ARCH ELEC R/I 10 214 16NOV92A 17SEP93A 9

R6000 1st FLOOR CHEM WEST PIPING & PANELS 15 15 1AUG93A 21AUG93A 6

R6095 2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS 10 10 1SEP93A 15SEP93A 0

R6115 S.B./FILTERS/FLOCC. PULL FEEDERS 15 17 22AUG93A 15SEP93A 5

R6040 CHEM EAST/PUMP STATION PULL FEEDERS 15 15 1OCT93A 21OCT93A 10

R6140 3rd FLOOR CHEM WEST PULL FEEDERS 10 11 22OCT93A 5NOV93A 15

R1320 CHEM WEST COMPUTER ROOM EQUIPMENT 5 6 25MAR94A 1APR94A 14

R6005 1st FLOOR CHEM WEST PULL FEEDER WIRE 10 10 21AUG93A 5SEP93A 6

R6100 2nd FLOOR CHEM WEST/C.B. BRANCH WIRING 30 54 15SEP93A 30NOV93A 0

R6120 S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS 25 25 16SEP93A 20OCT93A 5

R6045 CHEM EAST/PUMP STATION PULL BRANCH WIRING 20 22 22OCT93A 22NOV93A 10

R1315 CHEM WEST LAB PIPING 2 5 23MAY94A 30MAY94A 4

R6010 1st FLOOR CHEM WEST PULL BRANCH WIRING 15 18 6SEP93A 30SEP93A 6

R1310 CHEM WEST LAB INSTRUMENTATION 5 5 23MAY94A 30MAY94A 4

R6050 CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT 20 21 1APR94A 30APR94A 10

R1305 CHEM WEST LAB EQUIPMENT/FURNITURE 5 6 15FEB94A 22FEB94A 4

R6015 1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT 10 11 1OCT93A 15OCT93A 6

R6125 S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT 15 19 5APR94A 30APR94A 5

R6105 2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE 20 21 1DEC93A 30DEC93A 0

R6165 ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS 30 35 1MAR94A 18APR94A 191 1 0

1500 OPERATIONAL PUNCHLIST 25 36 1MAY94A 21JUN94A 161 2 15

R1321 INSTALL SOFTWARE & DEBUG SYSTEM 20 42 18APR94A 15JUN94A 165 4 0

1510 PROCESS PAINTING 20 21 15APR94A 15MAY94A 15

1505 INITIAL MECH PERF TEST OPER TESTING & TRAINING 20 65 1MAR94A 31MAY94A 156 3 0

1515 INITIAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 201 7 0

1520 INITIAL MECH PERF TEST PUNCHLIST 5 5 20JUN94A 24JUN94A 0

1525 FINAL MECH PERF TEST 48 HR PLANT OPERATION 2 5 20JUN94A 24JUN94A 0

5205 GARAGE EXCAV to 243 2 0 17AUG94A 22AUG94A 204 1 0

END1 880 DAY PART A COMPLETION 1 0 24JUN94A 24JUN94A END 33

5215 GARAGE SOG @ 243.83 4 0 1SEP94A 8SEP94A 0

5210 GARAGE FTG FDN @ 244 3 108 29AUG94A 31AUG94A 1

5220 GARAGE FTG WALLS to 247.27 +/- 4 0 9SEP94A 16SEP94A 0

5225 GARAGE BFILL 1 0 16SEP94A 19SEP94A 0

5230 GARAGE SOG @ 248 5 0 21SEP94A 29SEP94A 0

5235 GARAGE MASONRY 5 20 3OCT94A 28OCT94A 214 1 0

5240 GARAGE STR STL @ 260 +/- 2 0 18OCT94A 20OCT94A 0

5250 GARAGE 8" DECK PANELS @ 262.67 5 6 21OCT94A 28OCT94A 214 1 0

5255 GARAGE ROOFING 8 31 31OCT94A 13DEC94A 0

5260 GARAGE ARCH DETAILS 2 14 3JAN95A 20JAN95A 204 1 0

5290 GARAGE BUILDING PUNCHLIST 10 5 15JAN95A 20JAN95A 0

1390 ARCHITECTURAL & FINAL PUNCHLIST 20 63 1NOV94A 31JAN95A 190 3 0

1395 OWNER ACCEPTANCE 1 63 1NOV94A 31JAN95A 0

END2 1065 DAY PART B COMPLETION 1 0 31JAN95A 31JAN95A 0

NOTICE TO PROCEED

MOBILIZATION

SED BASIN EXCAV to 236.15

SED BASIN SOG @ 236.40

SED BASIN SOG @ 240.40/242.75

SED BASIN (N,S,E) WALL to 264

FLOC BASIN FOOTING @ 240.25

FLOC BASIN FOOTING WALL to 247

FLOC BASIN CONC FILL to 247

FLOC BASIN SOG @~249 INCL GRADE BEAM

FLOC BASIN (N,S,W) WALL to 261.58/264

PRE-OZONE C.B. EXT WALL to 261.83/268.33/269.33

CHEM BLDG EAST SOG STEP FTGS @ 230//240.50

CHEM BLDG EAST WALL to 243//250

CHEM WEST SOG @ 246/246.67

CHEM BLDG EAST BEAM 44,45,[email protected],PILAS@250

CHEM WEST WALLS to 263

CHEM BLDG EAST BEAMS 43,46,47 & SLAB @ 264.67

CHEM WEST/RAW WATER 48" PPG w/PRECONTACT BYPASS

CHEM WEST/SETTLED/MIXED BYPASS 48" 54" 66" PPG

CHEM WEST BEAMS & SLABS to 264

CHEM BLDG EAST MASONRY TO 265

CHEM EAST GLAZED STRUCTURAL TILE

CHEM BLDG EAST MONORAIL SUPPORT STEEL

CHEM EAST CAST STONE/BRICK

CHEM BLDG EAST CL2 AREA 8" DECK PANELS @ 266

CHEM BLDG EAST MASONRY TO 280

CHEM BLDG EAST ELEC AREA 8" DECK PANELS @280.67

CHEM BLDG EAST MASONRY TO PARAPET

CHEM WEST STR STL COLS/BEAMS to 275.33/288.33

CHEM WEST ELEV SLAB @ 276

CHEM WEST MASONRY TO 280

CHEM WEST 3rd FLOOR C.M.U.

PRE-OZONE CONTACT BASIN 8" DECK PANELS @ 280.67

ASSORTED ROOF TOP WORK ELECTRICAL ROOM/C.B.

CHEM WEST MASONRY TO 288

PRE-OZONE CONTACT BASIN MASONRY to PARAPET

PIPE GALLERY/FILTER 12" DECK PANELS

CHEM BLDG EAST ROOFING

PRE-OZONE CONTACT BASIN ROOFING

CHEM WEST R/S LIME STO SILOS

CHEM WEST STR STL BEAMS @ 288.33

CHEM WEST R/S LIME FEEDER HOPPERS

CHEM WEST R/S LIME DUST COLLECTORS

ELECTRICAL ROOM MISCELLANEOUS WORK

CHEM WEST - LIME STO R/S LIME CONV BLOWERS

CHEM WEST - LIME STO R/S 6" 8" 10" PPG

CHEM WEST 8" DECK PANELS @ 289

CHEM WEST MASONRY TO PARAPET

ASSORTED ROOF TOP WORK CHEM WEST 3rd FLOOR

CHEM WEST CAST STONE

CHEM WEST/SKYLIGHT FRAMING ROOFING inc SKYLIGHT

2ND FL ARCH INTERNAL MASONRY

1ST FL ARCH INTERNAL MASONRY

2nd FLOOR CHEM WEST/C.B. ELECTRICAL PIPING

CHEM WEST ROOFING @ 280.67/289

CHEM WEST BLOWER ROOM R/S 6" 8" 12" AIR PPG

CHEM WEST 3rd FLOOR GLAZED STRUCTURAL TILE

FILTERS 2nd FLOOR GLAZED STRUCTURAL TILE WALLS

2ND FL ARCH ELEC R/I

1st FLOOR CHEM WEST PIPING & PANELS

2nd FLOOR CHEM WEST/CONTACT BASIN PULL FEEDERS

S.B./FILTERS/FLOCC. PULL FEEDERS

CHEM EAST/PUMP STATION PULL FEEDERS

3rd FLOOR CHEM WEST PULL FEEDERS

CHEM WEST COMPUTER ROOM EQUIPMENT

1st FLOOR CHEM WEST PULL FEEDER WIRE

2nd FLOOR CHEM WEST/C.B. BRANCH WIRING

S.B./FILTERS/FLOCC. PULL BRANCH CIRCUITS

CHEM EAST/PUMP STATION PULL BRANCH WIRING

CHEM WEST LAB PIPING

1st FLOOR CHEM WEST PULL BRANCH WIRING

CHEM WEST LAB INSTRUMENTATION

CHEM EAST/PUMP STATION FLEX & CONNECT EQUIPMENT

CHEM WEST LAB EQUIPMENT/FURNITURE

1st FLOOR CHEM WEST FLEX & CONNECT EQUIPMENT

S.B./FILTERS/FLOCC. FLEX & CONNECT EQUIPMENT

2nd FLOOR CHEM WEST/C.B. FLEX/CONNECT/DEVICE

ELECTRICAL ROOM TERMINATE WIRE FROM OTHER AREAS

OPERATIONAL PUNCHLIST

INSTALL SOFTWARE & DEBUG SYSTEM

PROCESS PAINTING

INITIAL MECH PERF TEST OPER TESTING & TRAINING

INITIAL MECH PERF TEST 48 HR PLANT OPERATION

INITIAL MECH PERF TEST PUNCHLIST

FINAL MECH PERF TEST 48 HR PLANT OPERATION

GARAGE EXCAV to 243

880 DAY PART A COMPLETION

GARAGE SOG @ 243.83

GARAGE FTG FDN @ 244

GARAGE FTG WALLS to 247.27 +/-

GARAGE BFILL

GARAGE SOG @ 248

GARAGE MASONRY

GARAGE STR STL @ 260 +/-

GARAGE 8" DECK PANELS @ 262.67

GARAGE ROOFING

GARAGE ARCH DETAILS

GARAGE BUILDING PUNCHLIST

ARCHITECTURAL & FINAL PUNCHLIST

OWNER ACCEPTANCE

1065 DAY PART B COMPLETION

Target Date 10MAY91Plot Date 15FEB95Data Date 1FEB95Project Start10MAY91Project Finish31JAN95

(c) Primavera Systems, Inc.

inactiveALLAN A. MYERS, INC. - COMBINED WORKING SCHEDULE

Date ApprovedCheckedRevision

As-Built v As-Impacted v As-PlannedFOREST PARK WATER TREATMENT PLANTN PENN and N WALES WATER AUTHORITY

Sheet 1 of 1

As-BuiltAs-PlannedAs-Impacted

nProMaC, Inc

Page 35: Evidence Issues in Forensic Use of CPM Scheduling