Ever-tite v Green
Transcript of Ever-tite v Green
-
8/10/2019 Ever-tite v Green
1/2
Citation.22 Ill.83 So. 2d 449 (La. Ct. App. 1955)
Brief Fact Summary.The Plaintiff-Appellant, Ever-Tite Roofing Corp. (Plaintiff), contracted with
Defendant-Appellee, Green (Defendant), to renovate his home. When Plaintiff arrived at the job
there was another company doing the work.
Synopsis of Rule of Law.An offer proposed may be withdrawn before its acceptance and no
obligation is incurred thereby. The power to accept is limited by the terms of the contract or at the
end of a reasonable time.
Facts.The Defendant signed a document for the purpose of re-roofing their residence. The
document included the work to be done and the price to be paid in monthly installments. The
document was also signed by Plaintiffs sales agent who was unauthorized to accept the contract on
behalf of the Plaintiff. The document contained a provision that read this agreement shall become
binding only upon written acceptance hereof, by the principal or authorized officer of the Contractor
or upon commencing performance of the work. This contract is not subject to cancellation. Plaintiff
performed a timely credit report and immediately following approval, the Plaintiff engaged workmen
and loaded trucks and materials and proceeded to Defendants house to do the work. When Plaintiff
arrived he found another company in the performance of the work Plaintiff had already contracted to
do. Defendant told Plaintiff the other company signed a contract to do the work two days before.
Defendant forbade the
Plaintiff from doing the work. Defendant made no attempt to contact Plaintiff before this date.
Defendant knew it would take several days because of the necessity to acquire financing. The
Plaintiff proceeded with due diligence to this end.
Issue.Was letting the contractor know when he showed up to do the job adequate notice of
withdrawal?
Had the offer expired
Held. No. Reversed.
No. Because no time was specified within which the offer had to be accepted, then reasonable time
must be allowed.
No. Because the offer was accepted when Plaintiff began loading of the trucks and transporting men and
materials to the Defendants residence.
An offer proposed may be withdrawn before its acceptance and no obligation is incurred thereby.
The power to create a contact by acceptance of an offer terminates at the time specified in the offer, or,
if not time is specified, at the end of reasonable time.
What constitutes a reasonable time is a question of fact. It depends on the nature of the contract
proposed, the usages of business and other circumstances of the case which the offeree at the time of
his acceptance either knows or has reason to know.
http://www.bloomberglaw.com/document/XLU8JQ003?jcsearch=83%2520So.%25202d%2520449#jcite%22&ORIGINATION_CODE=00344http://www.bloomberglaw.com/document/XLU8JQ003?jcsearch=83%2520So.%25202d%2520449#jcite%22&ORIGINATION_CODE=00344http://www.bloomberglaw.com/document/XLU8JQ003?jcsearch=83%2520So.%25202d%2520449#jcite%22&ORIGINATION_CODE=00344http://www.bloomberglaw.com/document/XLU8JQ003?jcsearch=83%2520So.%25202d%2520449#jcite%22&ORIGINATION_CODE=00344 -
8/10/2019 Ever-tite v Green
2/2
Discussion. Here, the court is being generous in allowing the work to commence upon the loading of the
truck. The court is not clear about what type of work will be deemed acceptance and in what situations.