Evaluation of Overall Risk Management in Decommissioning … · Decommissioning should be...

31
Evaluation of Overall Risk Management in Decommissioning Sep. 11, 2018 2018 Sino-Japanese Workshop on NPP Decommissioning Technology 1 Satoshi Yanagihara University of Fukui ANDES executive director

Transcript of Evaluation of Overall Risk Management in Decommissioning … · Decommissioning should be...

  • Evaluation of Overall Risk Management in

    Decommissioning

    Sep. 11, 2018 2018 Sino-Japanese Workshop on NPP Decommissioning Technology

    1

    Satoshi Yanagihara University of Fukui

    ANDES executive director

  • Contents

    Principle of nuclear decommissioning

    Dose evaluation in decommissioning project

    Basis of risk assessment

    Evaluation of project risk(1) – cost over-run

    Evaluation of project risk(2) – schedule slip

    2

  • Technology Deployment: Decommissioning is an aggregation of wide variety of technology. Basic knowledge is crucial including application of other areas.

    Radiation Risk: Various types of radioactive materials or radioactive waste in various physical and chemical forms arise from any nuclear decommissioning activity and they pose different levels of risk.

    Waste Management: Proper waste management is a key for successfully implementing a decommissioning project. Knowledge on waste management should be equipped together with nuclear decommissioning.

    Project Management: Planning and evaluation of a decommission project are indispensable. The relevant methodology and tools are applicable for those in such areas of cost engineering, risk management and decision analysis.

    Principle of Nuclear Decommissioning

    3

  • Decontamination of building surfaces

    Radioactive waste treatment and storage

    Final surval of ratioactivity

    Dismantling of components

    Removal of spent fules

    Remote dismantling of core part

    Dismantling of compnents around core part

    4

    Typical Decommissioning Process in Reactor and Rad-waste Buildings

    Time (10 -60 years)

    Different kinds of risks exist in the

    decommissioning process

  • 5

    Risks in Decommissioning Process

    IAEA, Safety Assessment for Decommissioning, Safety Reports Series No.77, 2013

  • Criteria for Radiation Safety

    Dose limit for public around nuclear facilities Criteria for the dose limit of public in the outer area of environmental monitoring

    Effective dose limit : 1mSv/year Equivalent dose for the skin : 50mSv/year Equivalent of crystalline lens : 15mSv/year

    Dose limit for workers Criteria of effective dose received by radiation workers in controlled areas

    One year : 50mSv Five years :100mSv Emergency :100mSv

    6

  • Dose Evaluation in Dismantling Activities

    Evaluation of Public Dose

    Public dose is evaluated under normal situation and accidents by applying the amount of each nuclide released into atmosphere and ocean.

    External exposure Internal exposure

    Evaluation of Worker Dose

    Worker dose is evaluated under normal situation by applying dose rate in working area considering area characteristics, work schedule, occupational type, etc.

    7

  • Characterization of Dismantling

    Work Activities (JPDR)

    Work Area Dose rate differs from position to position in the area

    ex. Max. 8.0mSv/h, Min. 0.2mSv/h (at service floor)

    Dose rate decreases with removal of component Lower dose rate - during dismantling, post-dismantling

    Work Activity Working location depends on occupational types

    • Near radioactive component for cutting activity • Observation of laborer’s activities away from them etc.

    Workers are exposed in limited time and activity

    D&D work consists of various kinds of work activities. • Preparation, Cleaning up, Assistant Work, Entering and exiting of

    controlled area etc.

    8

  • Atmosphere

    Contamination Control Enclosure

    Ventilation System (Building)

    Leakage (Enclosure)

    Inside Building

    Filtering Collection

    Dismantling of Equipment and Structures

    Stack

    Leakage (Building)

    Release of Radioactive Materials to Atmosphere in Normal Situation

    Release at Higher

    Position

    Release at Ground

    Atmosphere

    Filtering Collection

    Ventilation System (Enclosure)

    Radioactivity Particulate, Tritium, C-14

    9

  • Calculation Flow for Public Dose

    Amount of radioactivity produced

    Amount of radioactivity released into working area

    Radioactive plume

    Radioactivity in dismantling activities -Particulate radioactivity (Co-60, Eu-152 etc. ) -Gaseous radioactivity (H-3, C-14)

    Deposition on the ground

    Ingestion of vegetable,

    milk, meet etc.

    Radiation Source in Dismantling Nuclear Facilities:

    Radiation from radioactive waste -Direct g-ray -Skyshine radiation

    Radiation

    Accumulation in seafood

    External Internal

    Internal

    Internal External

    Amount of waste arising from activities

    Storage of waste

    Amount of radioactivity released into environment

    g-ray radiation

    Skyshine radiation

    External External

    in Atmosphere in Ocean

    Inhalation Radiation

    External

    Radiation

    Radioactive Sea Water

    swimming, Fishing

    Ingestion of seafood

    Emission of g-rays out of building

    10

  • Evaluation of Accident Conditions

    Event Object to be Considered

    Fire Filter, Solid Waste

    Explosion Flammable Gas, Dynamites for Controlled Blasting

    Drop Interaction of Equipment or Container and Floor or Enclosure

    Clash Interaction of Dismantling Equipment and Container

    Operation Mistake by Worker False Open or Close of Valve

    Malfunction of Equipment

    Leak of Liquid Waste, Halt of Active Equipment (Stop of Ventilation etc.), Runaway of Cutting Machine,

    Loss of Electric Power etc.

    Scenario of Accidents Cause of Releasing Radioactive Materials Radioactive Inventory at Accident (Transferred to Filter) Cause of Releasing Radioactive Materials

    11

  • 12

    Example of Safety Evaluation

    Decommissioning plan Phase 1: Preparation for dismantling (10 years) Phase 2: Dismantling of components around core part (15 years) Phase 3: Dismantling of core part (8years) Phase 4: Demolishing of buildings (7years) Public and worker dose in Phase 1 Normal Situation • Worker Dose : 1.4 person-Sv • Public Dose : max. 6.6 μSv (individual)

    Accident Condition • Public Dose : max. 0.25 μSv (individual) • Radiation release : max. 2.8 E11 Bq

    Ikata NPP Unit1 (PWR: 566 MWe)

    Source: SHIKOKU ELECTRIC POWER CO, INC

  • Risk Assessment

    Risk Assessment

    Identify Risk Items Quantify Risk Items Prioritize Risk Items

    13

    Selection of possible events of unexpected occurrences or accidents

    Risk for each event is defined as a function of probability and consequence

    Each event is prioritize into acceptable, or unacceptable by uing risk matrix

  • A few examples of possible accidents or unexpected occurrences which could occur during the execution of particular tasks and which might lead to significant doses to site personnel or the public.

    Identify Risk Items 1/2

    Possible Unexpected Occurrence or Accidents

    Fuel element dropped during handling Loss of cooling during irradiated fuel transfer Criticality of fuel storage Unexpectedly high radiation field Malfunctioning of protective equipment Malfunctioning of monitoring instruments Fire in contaminated chemical solvent Vacuum filter bag rupture

    14

  • Possible Unexpected Occurrence or Accidents (continued) Spillage of contaminated liquids Loss of essential services Local loss of contamination control Cutting equipment failure Accidental cutting of activated material Inadequate mechanical support for component being cut Oxyacetylene explosion Excessive amount of explosive charge HEPA filter failure Combustible waste fire

    15

    Identify Risk Items 2/2

  • Reactor pressure vessel

    Dismantling Project

    Machinery around reactor

    Hands-on Dismantling

    Decontamination

    Piping connected to RPV

    Reactor internals

    Post-cleanup activities

    Measure for shredding contamination by vinyl sheet

    Facility characterization

    Setting of Local ventilation

    Setting of remote systems

    Remote dismantling

    Radiation survey Dismantling

    Measure for shredding contamination by vinyl sheet

    Dismantling Setting of Local

    ventilation Setting of scaffolding

    Transfer of wastes

    A

    A

    Example of Work Breakdown Structure

    16

    Risk Identification

    risk of schedule slip risk of radiation and industrial hazards

    risk of industrial hazards

  • 17

    Risk Matrix

    Lik

    eli

    ho

    od

    Risk = f(probability, consequence)

    HIGH RISK: not acceptable MODERATE RISK

    Quantify Risk Items

    Consequence

    Certain Medium High Extreme Extreme Extreme

    Likely Medium Medium High Extreme Extreme

    Possible Low Medium Medium High Extreme

    Unlikely Low Low Medium Medium High

    Rare Low Low Low Medium Medium

    Very Low Low Medium High Very HighLOW RISK: Acceptable

  • Definition Process of balancing risk with cost, schedule, and other programmatic consideration.

    risk identification, risk assessment, decision-making on the disposition of risk, tracing the effectiveness of the results of the actions.

    Objective

    Maximizing the results of positive events and minimizing the consequences of adverse events.

    Project Risk Management

    Risk Management is an essential for project management.

    18

  • Risk Triangle

    Technical problem

    Cost over-run Schedule slip

    Project management always involves risk.

    Decommissioning should be accomplished on schedule, and is accomplished within budgeted cost as any engineering project do the same.

    At the start of decommissioning project, there are uncertainties in each of these factors and it is important to manage the associated risk.

    Risk management can help limit the potential for negative consequences arising from uncertainties and maximize the positive aspects.

    In some case, technical problem may be replaced by Casualty.

    19

  • Decommissioning Cost

    When planning decommissioning scenarios, all activities described in the decommissioning plan should be included in the estimation of the cost for decommissioning project.

    20

    Level 1

    Pre-decommissioning actions

    Facility shutdown activities

    Procurement of general equipment and material

    Dismantling activities

    Waste processing, storage and disposal

    Site security, surveillance and maintenance

    Site restoration, cleanup and landscaping

    Project management, engineering and site support

    Research and development

    Fuel and nuclear material

    Other costs

    The working grout of OECD/NEA studied first the decommissioning cost. Cost items(213) are identified in hierarchy form.

    Cost Groups include the followings:

    Labor costs

    Capital, equipment and material costs

    Expenses

    Contingency

    OECD/NEA, International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, 2012

    A.L.Taboas, A.A.Moghissi and T.S.LaGuardia: The Decommissioning Handbook, ASME Press, 2004

  • Cost Estimation(Case Study) (1100MWe NPP)

    21

    No Discription Likely cost ($) %

    1 Spent fuel 64,312,000 15.26

    2 Project management 132,812,000 31.50

    3 General plant operation and maintenance 13,723,000 3.26

    4 Site preparation 10,173,000 2.41

    5 Asbestos removal and disposal 8,632,000 2.05

    6 large component removal 6,001,000 1.42

    7 Segmentation and removal of reactor vessel internals and reactor 21,877,000 5.19

    8 Component and piping disposition 20,838,000 4.94

    9 Contaminated building demolition 13,987,000 3.32

    10 Other building building demolition 16,042,000 3.81

    11 Final status survey and licence termination 2,607,000 0.62

    12 Waste management 93,266,000 22.12

    13 Soil remediation 742,000 0.18

    14 Clean material disposition 1,087,000 0.26

    15 Site restoration 15,466,000 3.67

    Totals 421,565,000 100.00

    OECD/NEA, ,Addressing Uncertainties in Cost Estimates for Decommissioning nuclear Facilities, NEA No.7344, 2017

  • Estimating Uncertainty

    Triangle distribution

    22

    OECD/NEA, ,Addressing Uncertainties in Cost Estimates for Decommissioning nuclear Facilities, NEA No.7344, 2017

    No Discription Likely cost ($) % below % above Exp cost ($)

    1 Spent fuel 64,312,000 5.0 25.0 68,599,467

    2 Project management 132,812,000 5.0 15.0 137,239,067

    3 General plant operation and maintenance 13,723,000 5.0 15.0 14,180,433

    4 Site preparation 10,173,000 5.0 25.0 10,851,200

    5 Asbestos removal and disposal 8,632,000 5.0 25.0 9,207,467

    6 large component removal 6,001,000 5.0 25.0 6,401,067

    7 Segmentation and removal of reactor vessel internals & reactor 21,877,000 5.0 75.0 26,981,633

    8 Component and piping disposition 20,838,000 10.0 20.0 21,532,600

    9 Contaminated building demolition 13,987,000 5.0 30.0 15,152,583

    10 Other building building demolition 16,042,000 5.0 25.0 17,111,467

    11 Final status survey and licence termination 2,607,000 5.0 25.0 2,780,800

    12 Waste management 93,266,000 5.0 25.0 99,483,733

    13 Soil remediation 742,000 10.0 35.0 803,833

    14 Clean material disposition 1,087,000 5.0 15.0 1,123,233

    15 Site restoration 15,466,000 5.0 20.0 16,239,300

    Totals 421,565,000 5.7 26.7 451,074,550

  • 23

    Description Likely costs %below %above Exp costs

    Dry casks do not meet regulations 39,926,000 5.0 40.0 44,584,033

    Additional ACM found post characterisation 2,158,000 5.0 20.0 2,265,900

    Large component transport needs supports 2,100,000 2.0 25.0 2,261,000

    Reactor vessel segments cannot be "blended" 3,282,000 5.0 30.0 3,555,500

    Containment concrete shorter than expected 2,098,000 10.0 20.0 2,167,933

    disposal site close/store on -site 23,317,000 5.0 25.0 24,871,467

    Soil contamination deeper than mearured 742,000 10.0 25.0 779,100

    Total 73,623,000 6.0 26.43 80,484,933

    Risk Evaluation Results Triangle distribution

    OECD/NEA, ,Addressing Uncertainties in Cost Estimates for

    Decommissioning nuclear Facilities, NEA No.7344, 2017

    (US $)

  • 24

    Out-of-scope uncertainties

    In-scope

    Pro

    ject

    baseline e

    stim

    ate

    Funded risk 10.6 million

    Estimating

    uncertainty

    68.2 million

    Allowances 421.6 million

    Base cost

    -Assumptions

    -Exclusions

    -Boundary

    conditions

    As per basis of

    estimates

    Risk Evaluation for Cost Over-run

    OECD/NEA, ,Addressing Uncertainties in Cost Estimates for

    Decommissioning nuclear Facilities, NEA No.7344, 2017

    (US $)

  • Duration of Decommissioning Projects in Japan

    25

    Plant Name Type Power(MWe) Cost(Oku-yen)Duration

    (year)

    JPDR BWR 1.5 230* 10

    Tokai GCR 166 885 25

    Fugen ATR** 166 750 25

    Hamaoka-1 BWR 540 379 27

    Hamaoka-2 BWR 840 462 27

    Mihama-1 PWR 340 324 30

    Mihama-2 PWR 500 359 30

    Tsuruga-1 BWR 357 363 24

    Shimane-1 BWR 460 382 30

    Genkai-1 PWR 559 364 28

    Ikata-1 PWR 566 407 40

    Monju FBR 28 3,750 30

    Fukushima Daiichi BWR *** 80,000 40

    *: including R&D, **:Advanced Thermal Reactor, ***:Unit 1:460MWe, Unit 2-5:784MWe, Unit 6:1100MWe

  • 26

    Radiological

    characterization Safe enclosure

    Dismantling

    core part Demolition of

    building structures

    2016 2022 2035

    Dismantling core part Dismantling core components Dismantling reactor pressure vessel Dismantling steam generator Dismantling primary system Demolishing biological shield Conditioning of dismantled waste

    Building demolition

    decontamination

    Radiation measurement

    Cancelation of controlled area

    2040

    Major Activities in 5 Years

    Displacement of spent fuels

    Rad-waste management

    Decommissioning Process (Example)

  • 27

    Schedule Risks on Waste Management

    Radioactive waste disposal facilities should be prepared before starting dismantling of core components.

    Radioactive waste will be disposed of three different disposal facilities depending of the radioactivity level.

    L1: Intermediate level waste disposal L2: Low level rad-waste disposal L3: Extremely low level rad-waste disposal

    Disposal depends on possibility of rad-waste disposal facilities

    no L1 facility:storage(shortage of storage space) no L2 facility : storage(shortage of storage space) no L3 facility : work-stoppage (schedule delay)

  • 28

    Necessary Process for Rad-waste Disposal

    L1 facility

    L2 facility

    (quite difficult)

    (experienced) (experienced)

    L3 facility

    (Experienced) (easy) (easy)

    28

    Siting Licensing Construction Operation

    Siting Licensing Construction Operation

    Siting Licensing Construction Operation

  • 29

    Risk Evaluation of Waste Disposal

    Disposal facilities L1 L2 L3 L1 L2 L3

    Siting 10 0 10 40 100 50

    Licensing 3 3 3 90 97 97

    Constraction 3 2 1 95 99 99

    Transportation 3 3 2 98 95 99

    34 91 48

    66 9 52Possibility of disposal

    Expected Year Possibility (%)*

    succeed

    not succeed

    Evaluation of work years and possibility to complete the tasks

    * Possibility is assumed by the expert judgement.

  • 30

    1. Requirement of all rad-waste disposal (L1, L2, L3)

    P(E) =P(E1∪E2∪E3)

    =P(E1)+P(E2)+P(E3) -

    (P(E1∩E2)+P(E1∩E3)+P(E2∩E3)) + 2 ⋇ P(E1∩E2∩E3)

    = 0.89

    P(E) :Fault of rad-waste disposal E1: L1 waste, E2: L2 waste, E3: L3 waste

    2. Requirement of rad- waste disposal for L2 and L3

    P(E) =P(E2∪E3)

    =P(E2)+P(E3) - P(E2∩E3)

    = 0.52

    P(E) :Fault of rad-waste disposal E2: L2 waste, E3: L3 waste

    Probability of Project Completion until Defined Date –case study

  • Summary

    A safety evaluation will be made for each task associated with the reactor

    or reactor systems and any other decommissioning activities which could

    give rise to a significant radiological hazard.

    After displacing spent fuels, radiation risk will decrease; risks of industrial

    hazards will be analyzed for safety of workers.

    Planning and evaluation of a decommission project are indispensable;

    risk management in decommissioning project plays an important role for

    completion of the planed cost and schedule.

    Project risk analysis always deal with the uncertainty; cost estimation should be made with analysis of risks and uncertainty.

    Proper waste management is a key for successfully implementing the

    decommissioning project. The risk analysis include the process of waste

    management from arising to final disposal.

    31