Evaluation of Overall Risk Management in Decommissioning … · Decommissioning should be...
Transcript of Evaluation of Overall Risk Management in Decommissioning … · Decommissioning should be...
-
Evaluation of Overall Risk Management in
Decommissioning
Sep. 11, 2018 2018 Sino-Japanese Workshop on NPP Decommissioning Technology
1
Satoshi Yanagihara University of Fukui
ANDES executive director
-
Contents
Principle of nuclear decommissioning
Dose evaluation in decommissioning project
Basis of risk assessment
Evaluation of project risk(1) – cost over-run
Evaluation of project risk(2) – schedule slip
2
-
Technology Deployment: Decommissioning is an aggregation of wide variety of technology. Basic knowledge is crucial including application of other areas.
Radiation Risk: Various types of radioactive materials or radioactive waste in various physical and chemical forms arise from any nuclear decommissioning activity and they pose different levels of risk.
Waste Management: Proper waste management is a key for successfully implementing a decommissioning project. Knowledge on waste management should be equipped together with nuclear decommissioning.
Project Management: Planning and evaluation of a decommission project are indispensable. The relevant methodology and tools are applicable for those in such areas of cost engineering, risk management and decision analysis.
Principle of Nuclear Decommissioning
3
-
Decontamination of building surfaces
Radioactive waste treatment and storage
Final surval of ratioactivity
Dismantling of components
Removal of spent fules
Remote dismantling of core part
Dismantling of compnents around core part
4
Typical Decommissioning Process in Reactor and Rad-waste Buildings
Time (10 -60 years)
Different kinds of risks exist in the
decommissioning process
-
5
Risks in Decommissioning Process
IAEA, Safety Assessment for Decommissioning, Safety Reports Series No.77, 2013
-
Criteria for Radiation Safety
Dose limit for public around nuclear facilities Criteria for the dose limit of public in the outer area of environmental monitoring
Effective dose limit : 1mSv/year Equivalent dose for the skin : 50mSv/year Equivalent of crystalline lens : 15mSv/year
Dose limit for workers Criteria of effective dose received by radiation workers in controlled areas
One year : 50mSv Five years :100mSv Emergency :100mSv
6
-
Dose Evaluation in Dismantling Activities
Evaluation of Public Dose
Public dose is evaluated under normal situation and accidents by applying the amount of each nuclide released into atmosphere and ocean.
External exposure Internal exposure
Evaluation of Worker Dose
Worker dose is evaluated under normal situation by applying dose rate in working area considering area characteristics, work schedule, occupational type, etc.
7
-
Characterization of Dismantling
Work Activities (JPDR)
Work Area Dose rate differs from position to position in the area
ex. Max. 8.0mSv/h, Min. 0.2mSv/h (at service floor)
Dose rate decreases with removal of component Lower dose rate - during dismantling, post-dismantling
Work Activity Working location depends on occupational types
• Near radioactive component for cutting activity • Observation of laborer’s activities away from them etc.
Workers are exposed in limited time and activity
D&D work consists of various kinds of work activities. • Preparation, Cleaning up, Assistant Work, Entering and exiting of
controlled area etc.
8
-
Atmosphere
Contamination Control Enclosure
Ventilation System (Building)
Leakage (Enclosure)
Inside Building
Filtering Collection
Dismantling of Equipment and Structures
Stack
Leakage (Building)
Release of Radioactive Materials to Atmosphere in Normal Situation
Release at Higher
Position
Release at Ground
Atmosphere
Filtering Collection
Ventilation System (Enclosure)
Radioactivity Particulate, Tritium, C-14
9
-
Calculation Flow for Public Dose
Amount of radioactivity produced
Amount of radioactivity released into working area
Radioactive plume
Radioactivity in dismantling activities -Particulate radioactivity (Co-60, Eu-152 etc. ) -Gaseous radioactivity (H-3, C-14)
Deposition on the ground
Ingestion of vegetable,
milk, meet etc.
Radiation Source in Dismantling Nuclear Facilities:
Radiation from radioactive waste -Direct g-ray -Skyshine radiation
Radiation
Accumulation in seafood
External Internal
Internal
Internal External
Amount of waste arising from activities
Storage of waste
Amount of radioactivity released into environment
g-ray radiation
Skyshine radiation
External External
in Atmosphere in Ocean
Inhalation Radiation
External
Radiation
Radioactive Sea Water
swimming, Fishing
Ingestion of seafood
Emission of g-rays out of building
10
-
Evaluation of Accident Conditions
Event Object to be Considered
Fire Filter, Solid Waste
Explosion Flammable Gas, Dynamites for Controlled Blasting
Drop Interaction of Equipment or Container and Floor or Enclosure
Clash Interaction of Dismantling Equipment and Container
Operation Mistake by Worker False Open or Close of Valve
Malfunction of Equipment
Leak of Liquid Waste, Halt of Active Equipment (Stop of Ventilation etc.), Runaway of Cutting Machine,
Loss of Electric Power etc.
Scenario of Accidents Cause of Releasing Radioactive Materials Radioactive Inventory at Accident (Transferred to Filter) Cause of Releasing Radioactive Materials
11
-
12
Example of Safety Evaluation
Decommissioning plan Phase 1: Preparation for dismantling (10 years) Phase 2: Dismantling of components around core part (15 years) Phase 3: Dismantling of core part (8years) Phase 4: Demolishing of buildings (7years) Public and worker dose in Phase 1 Normal Situation • Worker Dose : 1.4 person-Sv • Public Dose : max. 6.6 μSv (individual)
Accident Condition • Public Dose : max. 0.25 μSv (individual) • Radiation release : max. 2.8 E11 Bq
Ikata NPP Unit1 (PWR: 566 MWe)
Source: SHIKOKU ELECTRIC POWER CO, INC
-
Risk Assessment
Risk Assessment
Identify Risk Items Quantify Risk Items Prioritize Risk Items
13
Selection of possible events of unexpected occurrences or accidents
Risk for each event is defined as a function of probability and consequence
Each event is prioritize into acceptable, or unacceptable by uing risk matrix
-
A few examples of possible accidents or unexpected occurrences which could occur during the execution of particular tasks and which might lead to significant doses to site personnel or the public.
Identify Risk Items 1/2
Possible Unexpected Occurrence or Accidents
Fuel element dropped during handling Loss of cooling during irradiated fuel transfer Criticality of fuel storage Unexpectedly high radiation field Malfunctioning of protective equipment Malfunctioning of monitoring instruments Fire in contaminated chemical solvent Vacuum filter bag rupture
14
-
Possible Unexpected Occurrence or Accidents (continued) Spillage of contaminated liquids Loss of essential services Local loss of contamination control Cutting equipment failure Accidental cutting of activated material Inadequate mechanical support for component being cut Oxyacetylene explosion Excessive amount of explosive charge HEPA filter failure Combustible waste fire
15
Identify Risk Items 2/2
-
~
~
Reactor pressure vessel
Dismantling Project
Machinery around reactor
Hands-on Dismantling
Decontamination
Piping connected to RPV
Reactor internals
Post-cleanup activities
Measure for shredding contamination by vinyl sheet
Facility characterization
Setting of Local ventilation
Setting of remote systems
Remote dismantling
Radiation survey Dismantling
Measure for shredding contamination by vinyl sheet
Dismantling Setting of Local
ventilation Setting of scaffolding
Transfer of wastes
~
A
A
Example of Work Breakdown Structure
16
Risk Identification
risk of schedule slip risk of radiation and industrial hazards
risk of industrial hazards
-
17
Risk Matrix
Lik
eli
ho
od
Risk = f(probability, consequence)
HIGH RISK: not acceptable MODERATE RISK
Quantify Risk Items
Consequence
Certain Medium High Extreme Extreme Extreme
Likely Medium Medium High Extreme Extreme
Possible Low Medium Medium High Extreme
Unlikely Low Low Medium Medium High
Rare Low Low Low Medium Medium
Very Low Low Medium High Very HighLOW RISK: Acceptable
-
Definition Process of balancing risk with cost, schedule, and other programmatic consideration.
risk identification, risk assessment, decision-making on the disposition of risk, tracing the effectiveness of the results of the actions.
Objective
Maximizing the results of positive events and minimizing the consequences of adverse events.
Project Risk Management
Risk Management is an essential for project management.
18
-
Risk Triangle
Technical problem
Cost over-run Schedule slip
Project management always involves risk.
Decommissioning should be accomplished on schedule, and is accomplished within budgeted cost as any engineering project do the same.
At the start of decommissioning project, there are uncertainties in each of these factors and it is important to manage the associated risk.
Risk management can help limit the potential for negative consequences arising from uncertainties and maximize the positive aspects.
In some case, technical problem may be replaced by Casualty.
19
-
Decommissioning Cost
When planning decommissioning scenarios, all activities described in the decommissioning plan should be included in the estimation of the cost for decommissioning project.
20
Level 1
Pre-decommissioning actions
Facility shutdown activities
Procurement of general equipment and material
Dismantling activities
Waste processing, storage and disposal
Site security, surveillance and maintenance
Site restoration, cleanup and landscaping
Project management, engineering and site support
Research and development
Fuel and nuclear material
Other costs
The working grout of OECD/NEA studied first the decommissioning cost. Cost items(213) are identified in hierarchy form.
Cost Groups include the followings:
Labor costs
Capital, equipment and material costs
Expenses
Contingency
OECD/NEA, International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, 2012
A.L.Taboas, A.A.Moghissi and T.S.LaGuardia: The Decommissioning Handbook, ASME Press, 2004
-
Cost Estimation(Case Study) (1100MWe NPP)
21
No Discription Likely cost ($) %
1 Spent fuel 64,312,000 15.26
2 Project management 132,812,000 31.50
3 General plant operation and maintenance 13,723,000 3.26
4 Site preparation 10,173,000 2.41
5 Asbestos removal and disposal 8,632,000 2.05
6 large component removal 6,001,000 1.42
7 Segmentation and removal of reactor vessel internals and reactor 21,877,000 5.19
8 Component and piping disposition 20,838,000 4.94
9 Contaminated building demolition 13,987,000 3.32
10 Other building building demolition 16,042,000 3.81
11 Final status survey and licence termination 2,607,000 0.62
12 Waste management 93,266,000 22.12
13 Soil remediation 742,000 0.18
14 Clean material disposition 1,087,000 0.26
15 Site restoration 15,466,000 3.67
Totals 421,565,000 100.00
OECD/NEA, ,Addressing Uncertainties in Cost Estimates for Decommissioning nuclear Facilities, NEA No.7344, 2017
-
Estimating Uncertainty
Triangle distribution
22
OECD/NEA, ,Addressing Uncertainties in Cost Estimates for Decommissioning nuclear Facilities, NEA No.7344, 2017
No Discription Likely cost ($) % below % above Exp cost ($)
1 Spent fuel 64,312,000 5.0 25.0 68,599,467
2 Project management 132,812,000 5.0 15.0 137,239,067
3 General plant operation and maintenance 13,723,000 5.0 15.0 14,180,433
4 Site preparation 10,173,000 5.0 25.0 10,851,200
5 Asbestos removal and disposal 8,632,000 5.0 25.0 9,207,467
6 large component removal 6,001,000 5.0 25.0 6,401,067
7 Segmentation and removal of reactor vessel internals & reactor 21,877,000 5.0 75.0 26,981,633
8 Component and piping disposition 20,838,000 10.0 20.0 21,532,600
9 Contaminated building demolition 13,987,000 5.0 30.0 15,152,583
10 Other building building demolition 16,042,000 5.0 25.0 17,111,467
11 Final status survey and licence termination 2,607,000 5.0 25.0 2,780,800
12 Waste management 93,266,000 5.0 25.0 99,483,733
13 Soil remediation 742,000 10.0 35.0 803,833
14 Clean material disposition 1,087,000 5.0 15.0 1,123,233
15 Site restoration 15,466,000 5.0 20.0 16,239,300
Totals 421,565,000 5.7 26.7 451,074,550
-
23
Description Likely costs %below %above Exp costs
Dry casks do not meet regulations 39,926,000 5.0 40.0 44,584,033
Additional ACM found post characterisation 2,158,000 5.0 20.0 2,265,900
Large component transport needs supports 2,100,000 2.0 25.0 2,261,000
Reactor vessel segments cannot be "blended" 3,282,000 5.0 30.0 3,555,500
Containment concrete shorter than expected 2,098,000 10.0 20.0 2,167,933
disposal site close/store on -site 23,317,000 5.0 25.0 24,871,467
Soil contamination deeper than mearured 742,000 10.0 25.0 779,100
Total 73,623,000 6.0 26.43 80,484,933
Risk Evaluation Results Triangle distribution
OECD/NEA, ,Addressing Uncertainties in Cost Estimates for
Decommissioning nuclear Facilities, NEA No.7344, 2017
(US $)
-
24
Out-of-scope uncertainties
In-scope
Pro
ject
baseline e
stim
ate
Funded risk 10.6 million
Estimating
uncertainty
68.2 million
Allowances 421.6 million
Base cost
-Assumptions
-Exclusions
-Boundary
conditions
As per basis of
estimates
Risk Evaluation for Cost Over-run
OECD/NEA, ,Addressing Uncertainties in Cost Estimates for
Decommissioning nuclear Facilities, NEA No.7344, 2017
(US $)
-
Duration of Decommissioning Projects in Japan
25
Plant Name Type Power(MWe) Cost(Oku-yen)Duration
(year)
JPDR BWR 1.5 230* 10
Tokai GCR 166 885 25
Fugen ATR** 166 750 25
Hamaoka-1 BWR 540 379 27
Hamaoka-2 BWR 840 462 27
Mihama-1 PWR 340 324 30
Mihama-2 PWR 500 359 30
Tsuruga-1 BWR 357 363 24
Shimane-1 BWR 460 382 30
Genkai-1 PWR 559 364 28
Ikata-1 PWR 566 407 40
Monju FBR 28 3,750 30
Fukushima Daiichi BWR *** 80,000 40
*: including R&D, **:Advanced Thermal Reactor, ***:Unit 1:460MWe, Unit 2-5:784MWe, Unit 6:1100MWe
-
26
Radiological
characterization Safe enclosure
Dismantling
core part Demolition of
building structures
2016 2022 2035
Dismantling core part Dismantling core components Dismantling reactor pressure vessel Dismantling steam generator Dismantling primary system Demolishing biological shield Conditioning of dismantled waste
Building demolition
decontamination
Radiation measurement
Cancelation of controlled area
2040
Major Activities in 5 Years
Displacement of spent fuels
Rad-waste management
Decommissioning Process (Example)
-
27
Schedule Risks on Waste Management
Radioactive waste disposal facilities should be prepared before starting dismantling of core components.
Radioactive waste will be disposed of three different disposal facilities depending of the radioactivity level.
L1: Intermediate level waste disposal L2: Low level rad-waste disposal L3: Extremely low level rad-waste disposal
Disposal depends on possibility of rad-waste disposal facilities
no L1 facility:storage(shortage of storage space) no L2 facility : storage(shortage of storage space) no L3 facility : work-stoppage (schedule delay)
-
28
Necessary Process for Rad-waste Disposal
L1 facility
L2 facility
(quite difficult)
(experienced) (experienced)
L3 facility
(Experienced) (easy) (easy)
28
Siting Licensing Construction Operation
Siting Licensing Construction Operation
Siting Licensing Construction Operation
-
29
Risk Evaluation of Waste Disposal
Disposal facilities L1 L2 L3 L1 L2 L3
Siting 10 0 10 40 100 50
Licensing 3 3 3 90 97 97
Constraction 3 2 1 95 99 99
Transportation 3 3 2 98 95 99
34 91 48
66 9 52Possibility of disposal
Expected Year Possibility (%)*
succeed
not succeed
Evaluation of work years and possibility to complete the tasks
* Possibility is assumed by the expert judgement.
-
30
1. Requirement of all rad-waste disposal (L1, L2, L3)
P(E) =P(E1∪E2∪E3)
=P(E1)+P(E2)+P(E3) -
(P(E1∩E2)+P(E1∩E3)+P(E2∩E3)) + 2 ⋇ P(E1∩E2∩E3)
= 0.89
P(E) :Fault of rad-waste disposal E1: L1 waste, E2: L2 waste, E3: L3 waste
2. Requirement of rad- waste disposal for L2 and L3
P(E) =P(E2∪E3)
=P(E2)+P(E3) - P(E2∩E3)
= 0.52
P(E) :Fault of rad-waste disposal E2: L2 waste, E3: L3 waste
Probability of Project Completion until Defined Date –case study
-
Summary
A safety evaluation will be made for each task associated with the reactor
or reactor systems and any other decommissioning activities which could
give rise to a significant radiological hazard.
After displacing spent fuels, radiation risk will decrease; risks of industrial
hazards will be analyzed for safety of workers.
Planning and evaluation of a decommission project are indispensable;
risk management in decommissioning project plays an important role for
completion of the planed cost and schedule.
Project risk analysis always deal with the uncertainty; cost estimation should be made with analysis of risks and uncertainty.
Proper waste management is a key for successfully implementing the
decommissioning project. The risk analysis include the process of waste
management from arising to final disposal.
31