Evaluation and Solution of energy Crisis in Nepal
-
Upload
ramhari-poudyalbeng-msc-miet -
Category
Engineering
-
view
54 -
download
2
Transcript of Evaluation and Solution of energy Crisis in Nepal
SONEUK Conference on Infrastructure Development in Nepal, London, 18th Feb 2017
Evaluation and Solution of Energy Crisis in Nepal
Ramhari Poudyal, B.Eng,M.Sc.; MIETPhD candidate, Swansea University,UK
The world is facing an enormous challenge to provide sufficient quantity of clean energy for its burgeoning population.
Energy is a fundamental asset for socio–economic development and poverty eradication of any country.
Over 1.2 billion people 20 % of the world population have no access to electricity
768 million people lack access to clean drinking water and 2.5 billion do not have adequate sanitation
2.8 billion people still cook with solid fuel like wood, agricultural residue, animal dung
1 billion people live more than 2 km from an all-weather road.
Introduction
Nepal has been suffering from the chaotic energy crisis for about a decade.
A normal life of citizens is being crippled with long hours of load shedding and never ending queues in front of the gas stations.
About 6.6 million people of Nepal have no electricity
However Nepal has huge potential for generating
• 43,000 MW of hydro-electricity• 2,100 MW of solar power and• 3,000 MW of wind power
Introduction
Types of energy crisis :• Oil Crisis• Petroleum Crisis• Energy Shortage• Electricity Shortage
Energy Crisis - Nepal
Political Events
Aging Infrastruc
ture
Attacks by
Terrorists or
MilitaryInfrastructure
damage from
severe weather
Over Consum
ption
Industrial Actions
Factors of Energy Crisis
Energy overview & Electricity Consumption
78%
12%
4%3% 3%
Energy Overview 2015Biomass Petro -Product Coal Grid Electric
Modern RenewableThe electricity consumption in
different sectors
Electricity Consumption Per Capita (MWh /Capita) in 2014
Icelan
d
Norway
Canada
USASau
di UKChina
India
Bangla
desh
Mynmar
Nepal
0
10
20
30
40
50
60
53.9
23
15.5412.96
9.14
5.13 3.930.80.3100000000000010.21 0.14
Total Energy Consumption Per Capita KWh/Year 2013
Total Electricity of Nepal
S.No. Organisation Capacity
1 NEA 350MW
2 PPI 180MW
3 Imported from India 355MW
Total 885MW
Total Demand 1325MW
Total Supply 885MW
Total Deficit 440MW
Total loss 25.78% (228MW)
13 Billion
Time overruns Hydropower and Transmission line projects in Nepal
Project Time OverrunKulekhani I 21 MonthsMarsyandi 7 MonthsKali Gandaki – A 18 months
Chilime 60 monthsKulekhani III 54 monthsRaughat 72 monthsUpper Trisuli 38 monthsUpper Tamakoshi 12 months
220 KV Khimti – Dhalkebar More than 10 Years not yet completed
400 KV Dhalkebar – Muzzaffarpur 6 months
Trisuli 3 A 26 monthsChameliya 60 monthsMiddle Marsyangdi 48 Months
The main reason behind this time and cost overruns is mostly due to NEA’s centralised and prolonged procurement processes
ghost contractors leaving work to be executed by inexperienced and technically and financially weak local contractors.
low project readiness at project approval, weak project management capacity of NEA .
The total losses of NEA at present have reached NPR 27 billion despite the government written off NPR 27 billion in 2011.
Resource
Value Units Rank Period Source
Hydro Power
45,000 MW WECS
Wind Potential
7,606
Area(Km2)
Class 3 – 7 Wind
at 50 m
36 1990 NREL
Solar Potential
466,643,167 MW h/Year 89 2008 NREL
Coal Reserves
1.10Million Short
Tons77 2008 EIA
Natural Gas Reserves
0Cubic
Meters(Cum)152 2010
CIA World
Fact Book
Oil Reserves 0 Barrels (BBL) 151 2010CIA World
Fact Book
Bio Gas reserves
About 200,000 Plants of 10 Cu m size
at excising livestock populationCu m APEC
Fuel wood 7 metric Ton Metric Ton APEC
Potential Energy source of Nepal
National GDPAs usual reference scenario
Sector wise Energy DemandAs usual reference scenario
“To make an energy fix, We need an energy mix.”
- BP Slogan
Energy Matrix
“Sustainable Transport system a must to minimise air pollution in Kathmandu valley” – Dr. Carlos (WHO)
Kathmandu becoming mask town Air pollution killing double of what tobacco kills in
Kathmandu Lung cancer is the No. 1 in Nepal. Over 4 million people die prematurely from illness
attributable to the household air pollution from cooking with solid fuels.”
According to Environment Performance Index, 2016, Nepal falls in the 149th place among 180 countries in terms of air quality.
The no. of deaths caused by air pollution indoor and outdoor is 30,000 a year. This is twice as much as the no. of deaths caused by tobacco
Sustainable Transport System
Kathmandu Valley Pollution Index(PM2.5) on 2nd Feb, 2017
A world Bank estimate of Nepal’s infrastructure gap pegs investment needs at between 8 – 12 % of national income
Nepal’s medium term ambition is to become a middle – income nation by 2030, while graduating out of the least developed country (LDC) status by 2022.
Source: WDI 2012
Energy Investment of selected countries
Distributed Renewable energy in Developing CountriesTechnology Typical Characteristics Installed Costs or LCOE
US$ / KW or US Cents /KWh
Biogas digester Digester size: 6 – 8 m3 Unit cost: US$ 612/Unit (Asia); US$ 886/Unit (Africa)
Biomass gasifier Size: 20 – 5,000 KW LCOE: 8 – 12 (Global)LCOE: 5 – 6 (China)
Solar home system System size: 20 – 100 W LCOE: 160 – 200 (Global)LCOE: 4 (Bangladesh)
Household wind turbine Turbine size: 0.1 – 3 KW(Off – grid, residential)
1. – 2.5 MW(Industrial, institutional)
Capitol cost: 10,000 / KW (1 KW turbine)5,000 / KW (5KW)2,500 – 3,500 / KW (250 KW)LCOE: 15 – 35+
Hydropower:Off – grid /rural
Plant size: 0.1 – 1,000 KWPlant / Storage type:Run – off – river, diurnal storage, hydrokinetic
Capital costs: 1,175 – 6,000LCOE: 5 – 40
Village – scale mini – grid System size: 10 – 1,000 KW LCOE 25 – 100
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 240
200
400
600
800
1000
1200
1400
The electric utility managed to post healthy growth in revenue, thanks to uninterrupted power supply to many parts of the country mainly due to effective demand side management and 18 percent rise(18.28 billion NRs) in electricity tariff in July last year.
Load Profile of NEA
Electric power transmission and distribution losses (% of output)
1971 1973 1975 1977 1979 1981 1983 1985 1987 1989 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 20130
5
10
15
20
25
30
35
40
15.11
28.84
37.5
26.75
30.05
21.34 20.89 21.62 21.8 21.0819.31
21.1119.73
22.41 21.8520.99
19.49
28.3430.26
34.44
31.55 31.48
Electric power transmission and distribution losses (% of Output) in Nepal 1971 - 2013
Comparison of Transmission line
Comparison of Transmission line
The costs of new electricity transmission infrastructureCase Study
75 KM Route
Build (Capital) Lifetime
Report per KM
National Grid
Per KM
Report per KM
National Grid per KM
Overhead £ 1.6 m £ 1.6 m £ 4.0 m £ 4.8 m
Underground £ 16.7 m £ 18.8 m £ 18.9 m 20.8m
Cost Difference
£ 15.1 m £ 17.2 m £ 14.9 m 16.0 m
Case Study
15 KM Route
£1.7 m £1.6 m £4.1 m £4.8 m
Underground £ 17.4 m £ 18.0 m £ 19.3 m £ 19.2 m
Cost Difference
£ 15.7 m £ 16.4 m £ 15.2 m £ 14.4 m
(Investment Requirements 2011–2020 (total, in billions of dollars 2010)
Source: Andres et al. (2013), World Bank
Access to infrastructure Services in South Asian Region Countries
Source: World Development Indicators 2013
Solar and Wind maps of Nepal“our goal here is to fundamentally change the way the world uses energy. The goal is a complete transformation of the entire energy infrastructure of the world.”Elon Musk, CEO of Tesla & Chairman of Solar City, May 2015Solar radiation 3.6 – 6.2 KWh/m2/day, 300 days sunny, Average sunshine day 6.8Hours/day
Wind projects are relatively quick to install, and takes much less space than large solar arrays. If there is road access, equipment and no political obstructions, a 100MW wind farm can be built within six months. Our primary concern would be road access to wind sites since bigger turbines mean cheaper cost of electricity generation.
Solar and Wind Price in $ Million/Megawatts 2010 - 2016
2010 2011 2012 2013 2014 2015 Q - 3 20160
1
2
3
4
5
6
5.5
4.24.5
2.7 2.8
2
1.651.8 1.9 2
2.42.2
1.81.66
Solar
Wind
Source: Bloomberg Energy Finance
“Bangladesh is the world’s largest market for solar home systems, and other developing countries are seeing rapid expansion of small-scale renewable systems, including renewables-based mini-grids, to provide electricity for people living far from the grid.” – REN 21
IEA estimates that to achieve that Universal electrification objective by 2030, grid extension will be 30% and 70 % will be mini grids or off grid system.
Bangladesh
India China Nepal Kenya0
500,0001,000,0001,500,0002,000,0002,500,0003,000,0003,500,0004,000,000
Number of Solar Home Systems in top five Countries, End - 2014
Monthly Lifecycle costs of cooking in urban householdsSource: NOC 2013, NEA 2012Economic Cost of cooking kerosene NRS1500Economic Cost of cooking LPG NRS13751 INR = 1.60 NRS
Monthly Lifecycle costs of cooking in urban households(Based on D’sa, A. and Narsimha Murthy, K.V. 2004)
Year Kerosene LPG Electricity
1997 180 350 605
2000 270 410 680
2003 340 510 790
2012 1640 1030 940
Traditional bulb CFL LED Light Output
Watts
EnergyBillsNRs/Month(@5hr/day)
Watts EnergyBillsNRs/Month(@5hr/day)
Watts EnergyBillsNRs/Month(@5hr/day)
Lumens
40 Rs 45 8-12 Rs 11 4-5 Rs 5 450
60 Rs 68 13 -18
Rs 18 6 – 8 Rs 8 300 -900
100 Rs 113 23-30 Rs 30 16-20 Rs 20 1600 -1800
150 Rs 169 30-55 Rs 48 25-28 Rs 30 2600-2800 Source:
[NEEP]
Equivalent Wattages and Light output of Traditional, CFL and LED light
Energy Cost on product value in % for different industrial Sectors in Nepal
The UN Secretary – General’s initiative Sustainable Energy for all mobilizes global action to achieve universal access to modern energy services, double the global rate of improvement in energy efficiency, and double the share of renewable energy in energy in the global energy mix by 2030.
ChinaIndia
Pakist
an
Sri Lank
a
Bangla
desh
Nepal
Asian A
vg.
0
200
400
600
800
1000
1200
630560
630
300380
1020
470
Energy efficiency in Kgoe/US$ 1,000GDP (IEA,2012)
Series 1
Lime S
tone B
ased
Cem
ent
Cold S
torag
e
Fixed C
himne
y Bric
k
Pulp &
Pap
er
VSBKHote
l
Soap &
Che
mical
Clinke
r bas
ed C
emen
t
Biscuit
DairyMeta
l
Noodle
Vegeta
ble O
il & G
hee
Bevera
geSug
ar05
101520253035404550 47.6
37.91
31.91
19.8314.41
7.545.344.914.794.593.242.682.261.391.21
Energy Cost on product value in % for different industrial Sectors in Nepal
Source: Nepal Energy Efficiency Program
Sectors % for Electrical
% for Thermal
The Electrical Saving Potential
The Thermal Saving Potential
Beverage
9.09% 19.25% 1390.804 MWh
10707.587 GJ
Biscuit Sub Sector
29.47% 15.38% 1052.435MWh
8702.705GJ
Dairy Sub Sector
6.31% 13.91% 504.602MWh
12785.202GJ
Instant Noodle Sub Sector
6.15% 11.38% 243.34MWh
26786.582GJ
Sugar Sub Sector
14.55% 20.73% 783.678MWh
2095.16GJ
Vegetable Oil & Ghee Sub Sector
5.49% 11.07% 1200.312MWh
78084.573GJ
Residential Commercial Industrial Aggregate Avg.
0.065$/KWh0.035$/KWh
0.032$/KWh
0.042$/KWh
Average Costs of Energy Efficiency Programs by Sector(2012)
Energy Saving Potential Sectors (ESPS) conducted by NEEP
Conclusion
Government of Nepal needs a new strategy to come out of the power crisis along with adding new power generation. The major reason of current power crisis is the inefficient use of available resources. Development and deployment of renewable energy resources; solar, wind, micro
hydro, biomass etc. Optimum and Efficient use of resources and conservation of energy More researches on electrical power and potential renewable energy solutions must be
applied to improve of life of Nepalese people. NEA should take this power outage as an opportunity to brainstorm how to create
innovative policies and encourage private sector investment. Nepal needs significant investments into modern infrastructure to avoid the transmission
and distribution losses. In order to improve the industrial energy efficiency, the government can greatly influence
and develop the relevant policy including collection of appropriate data.