Faculdade de Economia do Porto - FEP - Universidade do Porto
European Federation of Railways Trackworks Contractors June 24 th 2005 Metropolitan Porto Light Rail...
-
Upload
laura-watson -
Category
Documents
-
view
213 -
download
0
Transcript of European Federation of Railways Trackworks Contractors June 24 th 2005 Metropolitan Porto Light Rail...
European Federation of Railways Trackworks Contractors
June 24th 2005
Metropolitan Porto Light Rail SystemProject Presentation
2#
I.I. PROJECT DEVELOPMENTPROJECT DEVELOPMENT
II.II. ENGINEERINGENGINEERING
III.III. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. LINES IN OPERATIONLINES IN OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
3#
I.I. PROJECT DEVELOPMENTPROJECT DEVELOPMENT
II.II. ENGINEERINGENGINEERING
III.III. LINES IN OPERATIONLINES IN OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
4#
I. Project Development
GAIA LINE
TROFA LINE
MATOSINHOS LINEDragão
PÓVOA LINE
Campanhã
Initial Contract
876 M €
Project Changes 2001
193 M €
Red Line duplication
100 M €
Green Line duplication
106 M €
Campanhã –Dragão line 50 M€
Airport Line
42 M€
Airport Ismai
6#
I.I. PROJECT EVOLUTIONPROJECT EVOLUTION
II.II. ENGINEERINGENGINEERING
III.III. LINES IN OPERATIONLINES IN OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
7#
II. Engineering
• 3 Tunnels excavated with TBM-EPB (6,1 km)
• Underground stations • Heroísmo• Campo 24 de Agosto• Bolhão• Salgueiros• Faria Guimarães• Marquês• Combatentes• S. Bento• Aliados
UNDERGROUND WORKS
8#
II. Engineering
Tunnel – standard underground line
Surface –urban areas with crossroads and traffic lights
Surface – segregated channel with level crossings
PMO GUIFÕES
Airport
Pedras Rubras
Póvoa do Varzim
Trofa
Hosp. São João
Campanhã
Sr. Matosinhos
ISMAI
Fonte de Cuco
Sra. da Hora
Trindade
Casa da Música
Sto Ovideo
Estádio do
Dragão
FUNCTIONAL MAP OF THE NETWORK
9#
II. Engineering Tunnel works
• Close Mode: to control over-excavation risks
• Appropriate support pressure
• Integrated design team on site
• Independent design check procedure
TBM-EPB WORKS METHODOLOGY
10#
II. Engineering Tunnel works
• Automatic slurry injection in the working chamber to maintain the support pressure
• Double piston pump• TBM monitoring on a real
time basis
TBM-EPB WORKS METHODOLOGY
11#
II. Engineering
Tunnel• Extension 2,3 km • Diameter 7,8 m• Beginning of excavation 14/6/2000• End of excavation 21/10/2002• Volume of excavated material 138.000 m3
• Cost (without underground stations) 38 M €
Ring• Universal type 6+1• Length 1400 mm• Thickness 300 mm• Concrete C40/50
TUNNEL OF LINE A
12#
II. Engineering
Tunnel• Extension 3,8 km • Diameter 8 m• Beginning of excavation 11/6/2002• End of excavation 3/11/2003• Volume of excavated material 228.000 m3
• Cost (without underground stations) 53 M €
Ring• Universal type 6+1• Length 1400 mm• Thickness 300 mm• Concrete C40/50
TUNNEL OF LINE D
13#
II. Engineering Tunnel works
• Simplified station layouts• Unified solutions and
construction methods when possible
• Design team on site to adapt methods to real conditions
UNDERGROUND STATIONS METHODOLOGY
14#
II. Engineering Underground Stations
Faria Guimarães
Station
Cost: 23,5 M €
UNDERGROUND STATIONS
15#
II. Engineering
Marquês
Station
Cost: 22 M €
Salgueiros
Station
Cost: 23 M €
UNDERGROUND STATIONS
16#
II. Engineering
Heroísmo
Station
Cost: 25 M €
UNDERGROUND STATIONS
17#
II. Engineering
S. Bento
Station
Cost: 22 M €
UNDERGROUND STATIONS
18#
II. Engineering
BolhãoStationCost: 25 M €
UNDERGROUND STATIONS
19#
II. Engineering
AliadosStationCost: 23 M €
UNDERGROUND STATIONS
20#
II. EngineeringSURFACE
21#
II. EngineeringSURFACE
22#
II. EngineeringSURFACE
S. João Hospital
23#
II. EngineeringDIRECT COST PER QUILOMETER
(thousand nominal euros)Special Stations
Investment**
Km Invest / km
A Line 5 235 16 15Mat. – Trindade 1 168 12 14
Trind. – Antas 4 67 3 20
B Line 184 23 8
C Line (Ismai – Trofa)
71 9 8
C Line (S. Hora - Ismai)
159 10 15
Airport Line 27 2 18
D Line 6 184 8 22Average cost per Special Station 22 (000 euros)
Underground
Urban requalification costs on average 25% of the basic cost of the System
24#
II. Engineering LUIZ I BRIDGE
• Designed by Théophile Seyrig.
• Constructed between 1881 and 1886.
• Opened on the 31st of October 1886.
• Upper deck of 400m long.
• Seven columns.• Arch with 172 m span
and 45 m rise.
25#
II. Engineering LUIZ I BRIDGE
Main anomalies detected:•Paint detachment and corrosion points;•Loss of rivets;•Structure’s coating deterioration;•Moisture and water infiltration;•Corrosion at connection nodes;•“Trellis” plates buckling;•Lower flange plate buckling;• Very intense corrosion in some connection
plates of the transversal bracing.
26#
II. Engineering LUIZ I BRIDGE
Rebuilding work:• Total replacement of the upper deck.
• Reinforcement of main beam diagonals.
• Reinforcement of column diagonals.
• Reinforcement of suspension elements.
• Reinforcement of diagonals on the arch plane.
• Reinforcement of the vertical transversal bracing diagonals.
• Replacement of all corroded elements.
• Repair and replacement of the bearings.
• Total painting.
27#
II. Engineering LUIZ I BRIDGE
- Road width……………………………….…..……..5,520 m *- Sidewalks.………………..…………………..……..1,355 m *- Total width……………………………………..…….8,230 m *
- Railway width……………………………....……..6,400 m - Sidewalks..…………………………………..……..1,700 m - Total width..…………………………………..…….9,800 m
-General data before intervention
-General data after intervention
-Cost: 7,4 M €
28#
-Bridge‘s scaffolding
-Sidewalk and rail sleepers
II. Engineering LUIZ I BRIDGE
29#
Total length: 497,2 m
Spans: 24.80m + 5 x 30.60m + 40.50m + 5 x 30.60m + 40.50m + 48.80m + 36.60m = 497.20 m
Structure: Continuous beam, in a steel-concrete composite structure, supported by 14 reinforced concrete columns and 2 abutments, through neoprene pot-bearings.
Located on the Green Line (Fonte do Cuco / Trofa) between the stations of Custió and Parque in the city of Maia.
II. EngineeringPARQUE DA MAIA VIADUCT
Parque da Maia Viaduct longitudinal section
-Cost: 6,8 M €
30#
Parque station:
The deck’s cross-section width enlarges from10,10 meters to 13,75 meters.
II. EngineeringPARQUE DA MAIA VIADUCT
Parque da Maia Station
Construction methodThe construction phasing together with the metallic beams slenderness and the fact that the beams are used for the slab’s concreting led to use an opposite deformation at manufacturing.The slab’s concreting was done:
• in a first phase on the spans
• in a second phase over the columns, in order to reduce the concrete shrinking stresses.
31#
Viaduto Maia Norte
Located on the Green Line (Fonte do Cuco / Trofa) between the stations of Forum and Zona Industrial in the city of Maia.
Connects Travessa dos Brandinhais and the Industrial District.
Total length: 524,40 meters.
II. EngineeringMAIA NORTE’S VIADUCT
Maia Norte Viaduct – Side view
-Cost: 6,0 M €
32#
Technical Specification:
• Continuous beam, in a steel-concrete composite structure, supported by 14 reinforced concrete columns and 2 abutments.
• Total length: 524,40m
• Spans: 22.80m + 7x34.20m + 2x39.90m + 45.60m + 2x39.90m + 34.20m + 22.80m.
• Deck’s total width: 12.00m.
• 2 steel beams and a reinforced concrete slab.
• Total height: 2,50m, as the steel beam is 2,00m high and the concrete slab’s maximum thickness is 0,50m.
• Y-shaped concrete columns with a variable height ranging from 4.20m to 16.70m.
• Pile foundations with groups of 5 or 6 1,00m diameter piles by column.
II. EngineeringMAIA NORTE’S VIADUCT
33#
B rak in g cu rv e
A d v an ced s ign a lin fo
A d v an ced s ign a lin fo
S ign a lin fo
P erm itted sp eedU p d a te o f sp eed
p ro file
A rea w ith m ixed tra ffic
"D riv er s igh t" O p era tio n L IN E O p era tio nL IN E O p era tio n
• Automatic Vehicle Regulation• ATP – Automatic Train Protection (Ebicab 900)
• TMS (Traffic Management System) with powerful control and regulation tools
II. EngineeringSIGNALING SYSTEMS
34#
II. EngineeringSIGNALING SYSTEMS
Initial SystemInitial System UpgradingUpgradingOld System New System. MCDS Interlocking . Ebilock 950 Electronic Interlocking
.SIL 2 .SIL 4
.MTBF = 72.000 hours .MTBF > 2 Millions hours
.Standard CENELEC EN 50126, EN 50128, EN 50129 . Level Crossings Stand Alone, not integrated in the signalling system . Level Crossings integrated in the Signalling System
. Train detection based in Axle Counters . Train detection based in track circuits
. Route setting from the train via Radio. . ATP – Automatic Train Protection in all the network
. ATS – Automatic Train Stop only in the tunnel signals . Automatic route setting from the CTC
. Reversal way Signalling
.16 t/h/s in the common trunk . 24 t/h/s in the common trunk
. CTC with the basic tools . CTC with powerful tools to control and regulation.
. Cost – 32 Millions Euros . Cost – 62 Millions Euros
Supplier:Supplier: Bombardier TransportationBombardier Transportation
35#
I.I. PROJECT EVOLUTIONPROJECT EVOLUTION
II.II. ENGINEERINGENGINEERING
III.III. LINES IN OPERATIONLINES IN OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
36#
III. Lines in Operation
Matosinhos – Trindade 18 12,3
Trindade – Dragão 6 3,4
Sra. Hora – Pedras Rubras 5 6,7
29 22,4
Line / Branch Stations kms
Dec 2002
Jun 2004
Mar 2005
Póvoa do Varzim
Sra. da Hora
Trindade
Dragão
Sto Ovídeo
Hospital S João
Trofa
Matosinhos
Ismai
Pedras Rubras
Gondomar
Aeroporto
Conclusion of entire approved network in the next 8 months (except Ismai-Trofa)
Demand forecast 1.8 Million P*Kms/year
37#
I.I. PROJECT EVOLUTIONPROJECT EVOLUTION
II.II. ENGINEERINGENGINEERING
III.III. LINES IN OPERATIONLINES IN OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
38#
IV. Intermodality in AMP
Created in December 2002:– Metro do Porto– STCP– USGP/CP
• Main Goals:– Create a common zoning in
AMP and Trofa– Create and manage an
integrated ticketing system– Implement a revenue sharing
model between operators
TIP, ACE
39#
IV. Intermodality in AMP
• Contact-less technology• Andante cards
• CTS• GTML2 – Andante Gold
COMMON TICKETING SYSTEM
40#
Andante Products– 0ccasional Tickets
• Voyage Ticket• Andante 24
– Valid 24 hours after the first validation
– Season Tickets• Monthly Ticket• Andante 10-16
– Valid in the 10h-16h period in the working days and without any restrictions in the weekends and holidays
IV. Intermodality in AMPCOMMON PRICING
41#
I.I. PROJECT EVOLUTIONPROJECT EVOLUTION
II.II. ENGINEERINGENGINEERING
III.III. LINES IN OPERATIONLINES IN OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
42#
V. Commercial OperationNUMBER OF VALIDATIONS
• 82% increase on weekday average in (May 2004 vs May 2005)
• Average covered distance of 4,7 kms (2004) Average commercial speed of 24,7 kms/h (2004)
• Occupation rate of 11,1% (2004)
0
10.000
20.000
30.000
40.000
50.000
60.000
Jan Fev Mar Abr Mai Jun Jul Ago Set Out Nov Dez
2003 D útil 2004 D útil 2005 D util
43#
V. Commercial Operation
• More than 1 M monthly validations
• 83% increase from 2003 to 2004
• Occupation rate of 11,1% (2004)
• Income: 11.26 cents per Pkm (2004)
• Operational cost: 2.85 cents per Seat km (2004)
• Dec 04: 49% of 2008 Blue Line forecast demand reached, Forecast considering entire network in operation for 3 years and bus network restructured to feed metro
• Since Sep 04: more than 100% of this demand achieved, in morning peak hour on urban stretches in Porto
44#
I.I. PROJECT EVOLUTIONPROJECT EVOLUTION
II.II. ENGINEERINGENGINEERING
III.III. LINES IN OPERATIONLINES IN OPERATION
IV.IV. INTERMODALITY IN AMPINTERMODALITY IN AMP
V.V. COMMERCIAL OPERATIONCOMMERCIAL OPERATION
VI.VI. NEW PROJECTSNEW PROJECTS
45#
VI. New ProjectsNETWORK
1. Duplication of Green Line2. Yellow Line Extension 3. Gondomar Line4. Boavista Line
and…
5. Gaia Line II6. Maia Line II
46#
VI. New Projects
GAIA
TROFA
MATOSINHOS
Airport
PÓVOA
1. DUPLICATION OF GREEN LINE
Ismai
Pateiras
PORTO
• Length
8,7 kms
• Number of Stations
5
• Additional Budget
46 M €
47#
VI. New Projects2. YELLOW LINE EXTENSION
• Length 1,4 kms
• Number of Stations 3 – Sto. Ovídeo– Cravel– Quinta do Cedro
• Demand 78 Thousand P*Kms/Y
• Budget 76,7 M €
Laborim Depot 36 M € GAIA LINE
TROFA LINE
MATOSINHOS LINEDragão
PÓVOA LINE
Sto. Ovídeo
Laborim
Airport
48#
VI. New Projects
GONDOMAR
LINE
11 kms80 M Pass.kms
3. GONDOMAR LINE
• Length
11 kms
• Number of Stations
17
• Demand
295 Thousand P*Kms/Y
• Budget
201 M €
49#
VI. New Projects4. BOAVISTA LINE
BOAVISTA LINE
• Length
7 kms
• Number of Stations
17
• Demand
88 Thousand P*Kms/Y
• Budget
139 M €
European Federation of Railways Trackworks Contractors
June 24th 2005
Metropolitan Porto Light Rail SystemProject Presentation