etep628

download etep628

of 11

Transcript of etep628

  • 7/29/2019 etep628

    1/11

    Overvoltages and insulation coordination of 1000-kV ACtransmission systems in China

    Gu Dingxie*,, Zhou Peihong, Dai Min, Xiu Muhong and He Huiwen

    High Voltage Research Division, State Grid Electric Power Research Institute of China, Wuhan, China

    SUMMARY

    Overvoltages and insulation coordination requirements of 1000-kV AC transmission systems in China areintroduced. On the basis of the single-circuit transmission project, which has been put into operation since2009, and the planned double-circuit transmission projects, the control of temporary overvoltage andswitching overvoltages and the determination of the rated voltage of metal oxide arrester are presented. The

    lightning protection measures for transmission lines and substations are given. Determination of insulationlevel of substation apparatus and clearance of external insulation for transmission lines and substations areprovided. Copyright# 2011 John Wiley & Sons, Ltd.

    key words: China; 1000-kV transmission system; overvoltage; insulation coordination

    1. 1000-kV AC TRANSMISSION SYSTEMS IN CHINA

    The schematic diagrams of two typical 1000-kV transmission systems are presented in Figures 1 and 2,

    respectively. The 1000-kV AC demonstration project in China shown in Figure 1, JindongnanNanyang

    Jingmen, has been put into operation since January 2009. It is a single-circuit transmission system. The

    planned HuainanShanghai 1000-kV double-circuit transmission system is shown in Figure 2.

    2. POWER FREQUENCY TEMPORARY OVERVOLTAGES AND METAL OXIDE ARRESTER

    PARAMETERS

    2.1. Amplitude and duration of temporary overvoltage

    For the single-circuit transmission lines, the elevated voltages as a result of load rejection with no fault

    and with single line-to-ground fault should be mainly taken into consideration during temporary

    overvoltage (TOV) calculation.

    For the double-circuit transmission lines, the situation with one of the circuits out of service also

    should be considered, besides the situation with two operation circuits. In addition, it is worth noting

    that six-phase load rejection should be considered [1,2].

    Most of the future 1000-kV lines in China will be relatively long, and generally, shunt reactors willbe installed for such transmission lines. It is the major measure to control the TOVs. The highest TOV

    may usually be caused by single-phase-to-ground fault with load rejection. The following two kinds of

    circumstances will lead to the situation described previously with the single-phase reclosing, which is

    adopted in China.

    (1) The three-phase circuit breakers (CBs) are opened by relay protection because of the unsuccessful

    single-phase reclosing.

    *Correspondence to: Gu Dingxie, High Voltage Research Division, State Grid Electric Power Research Institute,

    Wuhan, China.E-mail: [email protected]

    Copyright# 2011 John Wiley & Sons, Ltd.p

    EUROPEAN TRANSACTIONS ON ELECTRICAL POWEREuro. Trans. Electr. Power 2012; 22:8393Published online 6 September 2011 in Wiley Online Library (wileyonlinelibrary.com). DOI: 10.1002/etep.628

  • 7/29/2019 etep628

    2/11

    (2) In live working process, single-phase reclosing is usually required to be locked. The three-

    phase CBs will be opened when single-phase-to-ground fault occurs.The power frequency phase-to-ground TOVs are limited to 1.3 per unit at the bus-side terminal of

    the CB and 1.4 per unit at the line-side terminal in China.

    The TOV duration plays an important role in the determination of the metal oxide arrester (MOA)-

    rated voltage and the equipment insulation level. In China, a linkage method for opening CBs at the

    sending and the receiving end is adopted, which means that CBs at both ends will be opened

    synchronously if one of the CBs is opened for any reasons. This method is efficient to shorten the

    duration of TOV and reduce the energy absorbed by MOA. The maximum switching time difference

    between CBs at both ends can generally be controlled within 0.2s, and the TOV duration will not be over

    0.5s even if the CB at one of the ends failed to be opened and the backup protection is carried out [1,2].

    2.2. Metal oxide arrester parameters

    The traditional principle for determining Un of MOA is that Un should be not less than TOV, where

    Un is the rated voltage. However, because of good performance of MOA for withstanding overvoltage

    in short time, the 1000-kV projects of China do not follow the principle, and Un is allowed to be lower

    than TOV for a short time. Un of MOA for 1000-kV system in China has been selected as 828kV,

    which is equivalent to 1.3 per unit and less than 1.4 per unit. According to the test data from MOA

    manufacturers in China, MOA is able to withstand 1.4 per unit TOV with the duration up to 10s [2].

    Main electrical parameters for MOA (Un is equal to 828kV) installed at the bus-side and line-side

    terminals of CB or at the transformer side are listed in Table I.

    The energy absorption capability is 40MJ [3]. The calculation results show that the actual maximum

    absorption energy of MOA will be less than 10MJ afterit withstands TOV, which lasts 0.5s, and absorbs

    2 +600MW

    2 +600MW

    2 +600MW

    30km

    12km

    3km

    Bengbu

    2+720MVA

    2+210Mvar

    1+210Mvar 1+210Mvar

    1+210Mvar

    2+720MVA

    2+720MVA

    Tianji

    Pingwei

    500kV

    UHV-T1

    Huainan

    720Mvar

    720Mvar 720Mvar

    720Mvar

    Double circuit line322km 146km

    Double circuit line

    720Mvar720Mvar

    Wannan Zhebei Huxi

    Double circuit line164km

    720Mvar 720Mvar

    UHV-T2 UHV-T3

    500kV

    UHV-T4

    500kV

    500kV

    Figure 2. Schematic diagram of the planned 1000-kV AC double-circuit transmission system in China.

    JingdongnanPower Plant

    North China

    500kV Power Grid

    358km 283km

    Jindongnan Nanyang Jingmen

    500kV Power Grid

    Central China

    Figure 1. Schematic diagram of the 1000-kV AC demonstration project (single circuit) in China.

    G. DINGXIE ET AL.84

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    3/11

    injected energy produced by twice closing switching overvoltages (SOVs) before TOV. Therefore, there

    is still sufficient margin of MOA absorption capability with 828-kV Un. At the same time, the reduction

    of MOA Un will be beneficial to lowering the lightning and switching impulse protection levels as well

    as the requirements of the equipment insulation level. The overvoltages on the lines can also be limited to

    a certain extent.

    3. SWITCHING OVERVOLTAGE

    The important sources of SOVs are associated with the following events [4,5]:

    (1) Line energization and re-energization(2) Ground-fault occurrence

    (3) Ground-fault clearing

    (4) Transformer switching at no load

    3.1. Line energization and re-energization

    Switching overvoltages because of line energization and re-energization are control factors for the

    insulation design of 1000-kV lines in China. The main measure to control the overvoltages is the use

    of CBs with pre-insertion resistors. In China, the 600- pre-insertion resistors are used, and the pre-

    insertion time is 9.51.5ms.The maximum phase-to-ground statistical SOVs along a 1000-kV line shall be not more than 1.7 per

    unit in China. The maximum phase-to-ground statistical SOVs in a 1000-kV substation shall be not more

    than 1.6 per unit and the maximum phase-to-phase statistical SOVs shall be not more than 2.9 per unit [6].The times-to-crests of SOVs as a result line energization and re-energization are generally 1000~

    3000ms, which may greatly influence the clearance design of transmission line [6].

    3.2. Ground-fault occurrence

    For single-circuit 1000-kV transmission lines in China, only the SOVs as a result of single-line-to-

    ground fault occurrence are taken into account. The double-line-to-ground fault event can be ignored.

    For double-circuit 1000-kV transmission lines, it is sufficient to consider only the SOVs as a result of

    single-line-to-ground fault occurrence on one of the circuits. The event of single-line-to-ground faults on

    both circuits can be ignored, or the SOVs on health phases are allowed to exceed 1.7 per unit.

    However, the probability of simultaneous single-line-to-ground faults on both circuits is close to 0

    according to the calculation results of lightning protection for 1000-kV transmission lines and theoperating experience of 500-kV double-circuit lines for over 10years. Thus, this kind of events can be

    neglected during insulation coordination [7].

    Switching overvoltages as a result single-line-to-ground fault occurrence are low, with the

    maximum 2% overvoltage below 1.51 per unit [6]. It is not the control factor that determines the line

    insulation level.

    3.3. Ground-fault clearing

    Switching overvoltages on a transmission line can be caused by ground-fault clearing on the adjacent

    lines. The number of grounded phases may significantly influence the crest of such overvoltage. The

    Table I. Main electrical parameters of the 1000-kV substation metal oxide arrester (unit, kV).

    Systemvoltage

    Ratedvoltage Un

    (RMS)

    Continuousoperation voltage

    (RMS)

    30/60s and 2kAswitching impulse residual

    voltage

    8/20s and 20kAlightning impulse residual

    voltage

    1000 828 638 1460 1620

    RMS, root mean square.

    1000-KV AC TRANSMISSION SYSTEMS IN CHINA 85

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    4/11

    SOVs can be within the allowable range while clearing a single-phase ground fault and may exceed

    the allowable values while clearing a two-phase or three-phase ground fault. Opening resistor can be

    used to control this kind of SOVs.

    For JindongnanNanyangJingmen 1000-kV transmission line in China, the following points

    should be taken into consideration:

    (1) The installation of opening resistors will increase the cost and CB fault probability because of

    the mechanical complexities of the breaker mechanisms.

    (2) The probability of two-phase or three-phase ground faults on 1000-kV transmission lines is very low.

    (3) The maximum overvoltage occurs on transmission lines rather than in substations. Probably,

    the SOVs may result in line insulation flashover. However, it will not threaten the equipment in

    substations.

    So, it is not necessary to install opening resistors for JindongnanNanyangJingmen 1000-kV

    transmission lines.

    3.4. Transformer switching at no load

    Both calculation research and field tests made in China indicate that the pre-insertion resistors are not

    necessary for the 500-kV CBs during transformer switching at no load at the 500-kV side. In such

    case, no excessively high resonance overvoltage will be caused, and both amplitudes of inrush currentand overvoltage are within the allowable range.

    The possibility of relatively high resonance overvoltage and the inrush current caused by transformer

    switching at no load at the 1000-kV side is greater than that at the 500-kV side. The adoption of pre-

    insertion resistors is beneficial for reducing resonance overvoltage and inrush current. However, it is not

    effective for all system wiring configurations and may lead to higher cost and lower reliability. It is

    recommended to install the pre-insertion resistors in CBs, which are used for energizing both 1000-kV

    unloaded transformer and 1000-kV unloaded transmission line. And for the CBs, which are used only for

    energizing 1000-kV unloaded transformer, the pre-insertion resistors are not necessary.

    To effectively restrict the harmonic resonance overvoltage and make it possible to use CB with no pre-

    insertion resistors at B13 for switching 1000-kV transformer, the following measures can be adopted:

    (1) Energizing the transformer at the 500-kV side.(2) If measure 1 cannot be achieved, switch the unloaded transformer by line CB B12 with pre-

    insertion resistors, which are in the middle position of the CB branch, as shown in Figure 3 and

    pointed by the arrow.

    4. VERY FAST TRANSIENT OVERVOLTAGE

    The operation of disconnect switch (DS) within a gas-insulated-switchgear (GIS) system generates

    very fast transient overvoltage (VFTO) with very steep wave front and very high amplitude. Such

    VFTO will probably damage insulation of the following equipment:

    1000kV 500kV

    B11

    B12

    B12

    B51

    B52

    B53

    Figure 3. Schematic diagram of the transformer switching at no load.

    G. DINGXIE ET AL.86

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    5/11

    (1) GIS bodies;

    (2) Equipment with windings, such as transformers;

    (3) Secondary equipment.

    Very fast transient overvoltage should be more worthy of attention for 1000-kV GIS. Generally,

    the higher the system-rated voltage is, the lower the ratio of the lightning impulse withstand

    voltage (LIWV) of equipment and the system-rated voltage is. For example, the rated voltage of

    1000-kV GIS and the crest VFTO are two times higher than that of 500-kV GIS; however, the

    LIWV of the 1000-kV GIS equipment is only 1.55 times higher than that of 500-kV GIS

    equipment. Therefore, VFTO may be more harmful to 1000-kV GIS equipment than to 500-kV

    GIS equipment.

    The calculation research on VFTO has been carried out for 1000-kV GIS. The results show the

    following [8,9]:

    (1) Shunt resistors are necessary for DSs in GIS to effectively limit VFTO. The resistance is 500, and

    the crest VFTO can be limited to 1.13 per unit from 3.11 per unit (1 per unit is equal to 898kV).

    (2) The crest VFTO caused by the DS operation can be up to 2.15 per unit in the hybrid GIS, which

    is within allowable range. Therefore, shunt resistors are not necessary for the DSs of the hybrid

    GIS from a safe and economic point of view.

    (3) The wiring configurations of GIS, such as bus length, will affect the crest VFTO, and both the

    initial wiring configuration and the future wiring configuration should be considered.

    Because the transformers of GIS in China are usually connected via overhead lines with a distance

    from several 10 to 100m, the amplitude of VFTO will attenuate fast and the wave front will be less

    steep. The crest VFTO at the transformers is low (the calculated crest value is 925kV) with slow rising

    speed (the calculated time-to-crest is longer than 1.5ms). There should be no any harm to the

    transformer insulation.

    5. INCOMING LIGHTNING OVERVOLTAGE TO SUBSTATION AND THE ARRESTERS

    LAYOUT

    The incoming lightning overvoltage to 1000-kV substation is the control factor for the equipmentinsulation design.

    While calculating the incoming lightning overvoltages to 1000-kV substations of China, two wiring

    configurations with rigorous conditions should be taken into consideration (as shown in Figure 4).

    (1) Single line with CBs opened

    (2) Single line single transformer wiring configuration

    The maximum incoming lightning overvoltage to substations is caused by the shielding failure in

    the entrance section of the transmission line. Two kinds of measures for limiting incoming lightning

    overvoltage have been adopted in China.

    (1) Limiting the maximum lightning shielding failure current in the entrance section of the

    transmission line

    Ground wire protection angle less than 4 and three ground wires (as shown in Figure 5) in theentrance section of the transmission line are effective methods to limit the current.

    (2) Optimizing the layout of MOAs

    The layout with less MOAs has been adopted. One group of three-phase MOA is installed at the

    entrance of each circuit. One group is installed for each busbar. One group is installed beside the

    transformer. The amplitudes of overvoltages in different substations are different. The calculated typical

    maximum lightning overvoltages are 2040kV for GIS, 1854kV for shunt reactors, and 1796kV for

    transformers. The LIWVs of the transformers and the shunt reactors are 2250kV and that of other

    equipment are 2400kV in China. The allowed LIWVs of equipment are higher than the maximum

    1000-KV AC TRANSMISSION SYSTEMS IN CHINA 87

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    6/11

    incoming lightning overvoltage and can meet the requirements of safety margin of internal (15%) andexternal (5%) insulation. Because of the small probability of single-line wiring configuration, the safety

    margin of internal insulation can be reduced to 10% for this kind of wiring configuration.

    Probabilistic or statistical method is also used to calculate the incoming lightning overvoltage to

    substation in addition to deterministic method. The mean time between failures of substation as a

    result of lightning is required to be more than 1500years while using statistical method.

    6. LIGHTNING PROTECTION OF LINES

    Because of the importance and the higher insulation level of the 1000-kV transmission lines, their

    expected lightning trip-out rate should be lower than that of the 500-kV lines by adopting control

    measures. According to the operating experience of 500-kV transmission lines in China, the average

    lightning trip-out rate is 0.14 times per 100km/year. So, the expected lightning trip-out rate of 1000-kVtransmission lines can be set as 0.1 times per 100km/year, which is equal to 70% of the trip-out rate of

    500-kV transmission lines. The schematic diagrams of towers of 1000-kV single-circuit and double-

    circuit transmission lines are shown in Figure 6.

    MOA

    Single transmission line

    Bushing

    CB whichis openedis openedCB which

    Transformer

    Incoming lightningwave u(t) wave u(t)

    Incoming lightning

    Transformer

    CB whichis closed

    is closedCB which

    Bushing

    Single transmission line

    MOA

    MOAMOA

    Figure 4. Substation wiring configurations considered during the incoming lightning overvoltagecalculation, (a) single line with CBs opened, (b) single line single transformer wiring configuration.

    Figure 5. Three ground wires adopted in the entrance section of the transmission line.

    G. DINGXIE ET AL.88

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    7/11

    Operating experience shows that the proportion of the lightning backflashover rate is becoming less

    and less to the total lightning trip-out rate as the line insulation level improved. The proportion is less

    than 10% for 500-kV transmission lines in China. The calculation results show that the lightning back

    flashover at 1000-kV line will not occur. Lightning shielding failure is the main cause of lightning trip

    out. Therefore, to prevent lightning shielding failure is the key point of lightning protection of 1000-kV

    lines.

    The main method for calculating the shielding failure rate is the improved electrical geometric

    model (EGM). The influence of terrain along the transmission line, correction coefficient of the

    lightning striking distance to the earth, and the probability distribution of the intruding lightning

    angle of lightning leader have been considered to improve the EGM model. At the same time, the

    study on the leader propagation model has been carried out in China. However, the calculation

    results are quite different with different parameters and criterions, and the determination of these

    parameters and criterions is difficult so far. Therefore, the calculation results from EGM are the main

    design basis for the lightning protection, and the results from leader propagation model are taken as

    reference.

    Reducing the ground wire protection angle a can reduce the shielding failure trip-out rate, and the

    trip-out rate is affected by terrain along the lines significantly too. The following principles for ground

    wire protection angle a of 1000kV lines should be used.

    (1) For single-circuit transmission lines, a used in plain area is less than 6 and less than 4 in themountain area.

    (2) For double-circuit transmission lines, a used in plain area is less than 3 and less than 5 inthe mountain area.

    (3) For jumper line at the strained angled towers, a of single-circuit transmission lines in plain areais less than 6 and not more than 0 for the single-circuit or the double-circuit transmission linesin the mountain area.

    The protection angle mentioned previously refers to the angle between the connecting line from

    the ground wire to the outermost sub-conductor and the perpendicular line of the horizontal

    surface.

    With long air gap clearances, higher insulation level and no arcing horn installed on China 1000-kV

    transmission lines, it is possible to limit the lightning trip-out rate to the expected value.

    Because the 1000-kV AC demonstration project (JindongnanNanyangJingmen) in China was put

    into operation in January 2009, no lightning trip-out fault has occurred until now.

    a)Typical towers of single-circuittransmission lines

    (b)Typical tower of double-circuittransmission lines

    Figure 6. Schematic diagrams of towers of 1000kV single-circuitand double-circuit transmissionlines (unit, m),(a) typical towers of single-circuit transmission lines, (b) typical tower of double-circuit transmission lines.

    1000-KV AC TRANSMISSION SYSTEMS IN CHINA 89

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    8/11

    7. INSULATION COORDINATION

    7.1. Principles of insulation coordination

    In the insulation coordination process, safety margin of internal insulation (15%) and external

    insulation (5%) are required in China [2,10].

    To determine the air gap clearance of 1000-kV AC lines and substations, lightning and switching

    surge impulse and power frequency voltage testing using a full-scale model are conducted, and a serial

    of critical 50% flashover voltage curves was obtained, which is important for insulation coordination

    process [2].

    7.2. Insulation levels of substation equipment

    The insulation levels of the major equipment in 1000-kV substations of China are shown in Table II.

    In general, the equipment insulation levels of China are lower than those of Russia and higher than

    those of Japan [11]. They are determined by the overvoltage levels to which 1000-kV transmission

    systems are exposed and the equipment manufacturing experience of China.

    7.2.1. Transformer insulation level. The transformer insulation levels are shown in Table III.

    The insulation level of 1000-kV transformer is determined by its LIWV and the power frequencyvoltage withstand. LIWV 2250kV of China can meet the requirement of safety margin, for the

    lightning overvoltage incoming to the transformer terminal will be not so high with low lightning

    impulse protection level of MOA and reduced maximum shielding failure lightning current.

    Operating experience indicates that most transformer faults occurred under the normal operating

    voltage. The power frequency voltage withstand testing is conducted to check the existence of partial

    discharges in transformer, and it is strictly considered in China. In China, the testing power frequency

    voltage is 1100kV, and the duration of its application is 5 min, which is more strict than 1 min

    recommended by the International Electrotechnical Commission [12].

    7.2.2. Testing voltage on longitudinal insulation of CB and DS. The lightning impulse testing voltage

    on longitudinal insulation of 1000-kV CBs and DSs of China is 2250+900 (kV), in which 900kV is

    the amplitude of the power frequency component of opposite polarity.However, the amplitude of the power frequency component of opposite polarity recommended by

    the IEC 60071-1 is 0:7 Um ffiffiffi

    2p

    =ffiffiffi

    3p

    , which refers to the peak value of the operating voltage

    multiplied with the coefficient 0.7, and with this coefficient, about one-fourth cycle of the operating

    voltage cannot be covered and the guaranteed coverage probability is 0.75.

    Table II. Rated insulation withstand voltages for 1000-kV equipment (unit, kV).

    Equipment Lightning impulsewithstand voltage

    Switching impulsewithstand voltage

    Power-frequency short-duration withstand voltage

    Transformer and reactor 2250 (choppedlightning impulse:

    2400)

    1800 1100 (5min)

    GIS (CB, DS, pipe) 2400 1800 1100 (1min)Post insulator and DS

    (open type)2550 1800 1100 (1min)

    Capacitive voltagetransformers

    2400 1800 1300 (5min)

    Bushing of transformerand reactor

    2400 (choppedlightning impulse:

    2760)

    1950 1200 (5min)

    Bushing of GIS 2400 1800 1100 (1min)Longitudinal insulation

    of switching device2400+900 1675+900 1100+635 (1min)

    GIS, gas-insulated-switchgear; DS, disconnect switch.

    G. DINGXIE ET AL.90

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    9/11

    In China, the coefficient is specified as 0.7 ~1.0 in the National Standard Insulation Coordination

    Part 2: Application Guide for Insulation Coordination for High Voltage Transmission and Distribution

    Equipment (GB311.1-1997), and the coefficient is set as 1 for 1000-kV CBs and DSs. For the

    importance of the 1000-kV equipment, the coefficient is set as 1 and the amplitude of the power

    frequency component of opposite polarity is the peak value of the operating voltage.

    7.3. Minimum air clearances of substation

    The minimum air clearances of 1000-kV substations of China with altitude above sea level below

    1000m are listed in Table IV. In Table IV, A1 is the minimum clearance between conductor and

    framework, A100 is the minimum clearance between equipment and the framework, and A2 is the

    minimum clearance between two phases.

    7.4. Line insulation levels

    To determine the minimum number of insulators, contamination withstand voltage method and

    specific creepage distance method can be used. The insulator selection of 1000-kV AC demonstration

    project in China is regulated as follows:

    (1) Suspension string. For area with pollution level II medium, where equivalent salt deposit

    density (ESDD) is 0.06~ 0.10mg/cm2, 54 units of double-shed disk-type insulators (for 300 kN)

    are required. For areas with pollution level III heavy (ESDD=0.10~0.25mg/cm2) and IV very

    heavy (ESDD=0.25~0.35mg/cm2), the composite insulator with total length of 9750mm and

    creepage distance of 30300mm is required [10].

    (2) Tension string. For area with pollution levels II, III, and IV, 44, 54, and 60 units of disk-typeinsulators with creepage distance of 700mm (for 550kN) is required, respectively.

    The minimum air clearances for 1000-kV transmission lines in China are listed in Table V.

    For single-circuit transmission lines, the minimum conductor-to-tower clearances of the middle

    phase are determined to withstand the expected maximum switching overvoltages, and the clearances

    of the two outer phases are determined to withstand the operating voltage at high wind speed. So, the

    minimum air gap clearances for lightning impulse withstand have not been regulated.

    However, towers of double-circuit transmission lines are higher. They are more likely to be struck

    by lightning because of the larger lightning attraction area and weakened shielding effect of earth.

    Table III. Insulation levels of ultra-high voltage transformers of China and Japan (unit, kV).

    Country Lightning impulse withstandvoltage

    Switching impulse withstandvoltage

    Power frequency voltagewithstand

    China 2250 1800 1100(5min)Japan 1950 1425 1100(5min)

    Table IV. Minimum air clearance for the 1000-kV substation with altitude above sea level below 1000 m

    (unit, m).

    Type of voltage applied A1 A2

    A1 A100

    Power frequency 4.2 6.8Switching impulse 6.8 7.5 10.1 (corona ringcorona

    ring) 9.2 (four-bundledconductorsfour-bundledconductors) 11.3 (tubularbustubular bus)

    Lightning impulse 5.0 5.5

    1000-KV AC TRANSMISSION SYSTEMS IN CHINA 91

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    10/11

    Because shielding failure will not be caused by heavy current, appropriate improved insulation can

    effectively reduce the number of lightning shielding failures. One of the main measures for insulation

    improvement is to increase the air gap clearances between the phase conductors and the towers,

    especially the clearances between the conductors and the tower trusses under them. Thus, the

    minimum air gap clearances for lightning impulse withstand have been regulated.

    To determine the air gap clearance of 1000-kV AC lines considering the influence of tower

    width, full-scale switching surge impulse testing was conducted. The times-to-crest of switching

    impulse is 1000ms. The influence of the number of parallel gaps on the discharge voltage has been

    considered in the insulation coordination process, and the flashover rate of the entire line insulation

    under SOV has been calculated. During the calculation, the variation of SOVs amplitude at differentpositions along the line and the probability distribution of SOVs at each position are taken into

    account. It is regulated that the flashover rate of the entire line insulation under SOV must be not

    higher than 0.01 times per year.

    8. CONCLUSIONS

    (1) The power frequency phase to ground TOVs are limited to 1.3 per unit at the bus-side-terminal

    of the CB and 1.4 per unit at the line side terminal in China, and generally, the TOV duration

    can be controlled within 0.2s and will not be more than 0.5s.

    (2) Rated voltage Un of MOA for 1000-kV system in China has been selected as 828 kV.

    (3) The maximum phase-to-ground statistical SOVs along a 1000-kV line shall be not more than1.7 per unit in China. The maximum phase-to-ground statistical SOVs in a 1000-kV

    substation shall be not more than 1.6 per unit, and the maximum phase-to-phase statistical

    SOVs shall be not more than 2.9 per unit.

    (4) Shunt resistors of 500 are necessary for DSs in GIS to effectively limit VFTO.

    (5) The maximum incoming lightning overvoltage to substations is caused by the shielding failure

    in the entrance section of the transmission line. Limiting the maximum lightning shielding

    failure current in the entrance section of the transmission line and optimizing the layout of

    MOAs can limit the overvoltage. Ground wire protection angle less than 4 and three groundwires in the entrance section of the transmission line are measures adopted in China to limit the

    maximum lightning shielding failure current.

    Table V. Minimum clearances for 1000-kV transmission lines in China (unit, m).

    Type of voltage applied Type of lines Minimum clearances

    Power frequencyvoltage

    Single circuit anddouble circuit

    2.7 at elevations 500m above sea level2.9 at elevations 1000m above sea level3.1 at elevations 1500m above sea level

    Switching

    impulse

    Single circuit outer phase: 5.9, middle phase: 6.7* or 7.9** at

    elevations 500m above sea levelouter phase: 6.2, middle phase: 7.2* or 8.0** atelevations 1000m above sea level

    outer phase: 6.4, middle phase: 7.9* or 8.1** atelevations 1500m above sea level

    Double circuit 6.0 at elevations 500m above sea level6.2 at elevations 1000m above sea level6.4 at elevations 1500m above sea level

    Lightningimpulse

    Single circuit Not to be specifiedDouble circuit Plain area: 6.7; mountain area: 7.0 at elevations 500m

    above sea levelPlain area: 7.1; mountain area: 7.4 at elevations 1000m

    above sea levelPlain area: 7.6; mountain area: 7.9 at elevations 1500m

    above sea level

    *These values are air gap clearances between the middle phases and the tower trusses above them.**These values are air gap clearances between the middle phases and the tower trusses below them.

    G. DINGXIE ET AL.92

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep

  • 7/29/2019 etep628

    11/11

    (6) To prevent lightning shielding failure is the key point of lightning protection of 1000-kV lines.

    Reducing the ground wire protection angle a can reduce the shielding failure trip-out rate

    effectively.

    (7) The equipment insulation levels of China are lower than those of Russia and higher than those

    of Japan.

    9. LIST OF ABBREVIATIONS AND SYMBOLS

    TOV temporary overvoltageCB circuit breakerMOA metal oxide arresterSOV switching overvoltagesDS disconnect switchGIS gas-insulated-switchgearVFTO very fast transient overvoltageLIWV lightning impulse withstand voltageEGM electrical geometric model ground wire protection angleESDD equivalent salt deposit density

    REFERENCES

    1. Liu Zhengya. Overvoltage and insulation coordination of UHV AC transmission system. Electric Power Press,

    Beijing: China, 2008; 1017. (in Chinese)

    2. National standard of P.R.C. GB/Z 248422009. Overvoltage and insulation corordination of 1000kV UHV AC

    transmission project, 2009; 3. (in Chinese)

    3. National standard of P.R.C. GB/Z 248452009. Specification of metaloxide surge arresters without gaps for

    1000kVac system, 2009; 6. (in Chinese)

    4. Gu Dingxie, Dai Min, et al. Study on overvoltage and insulation of 1000kV UHV AC double-circuit line

    transmission system. State Grid Electric Power Reseach Instituite 2008; 2340. (in Chinese)

    5. Gu Dingxie, Zhou Peihong, Dai Min. Comparison and analysis on overvoltage and insulation coordination of UHV

    AC transmission systems in China and Japan. High Voltage Engineering 2009; 35(6): 12481253. (in Chinese)

    6. Gu Dingxie, Zhou Peihong, Xiu Muhong, et al. Study on overvoltage and insulation coordination for 1000kV AC

    transmission system. High Voltage Engineering 2006; 32(12): 16. (in Chinese)

    7. Gu Dingxie, Dai Min, et al. Analysis of failure trip rate of 1000kV double circuits on the same tower. High VoltageEngineering 2009; 35(3): 441444. (in Chinese)

    8. Gu Dingxie, Xiu Muhong, Dai Min, et al. Study on VFTO of 1000kV GIS substation. High Voltage Engineering

    2007; 33(11): 2732. (in Chinese)

    9. Yamagata Y, Tanaka K, Nishiwaki S, et al. Suppression of VFT in 1100kV GIS by adopting resistor-fitted

    disconnector. IEEE Transactions on Power Delivery 1996; 11(2): 872880.

    10. IEC60071-2 1996 International standard Insulation Co-ordination-Part 2: Application guide, 1996; 6971.

    11. Watanabe T, Yamagata Y, Zaima E. Insulation Coordination for UHV System. CIGRE 1998. Session 33101.

    Paris, 1998, 110.

    12. Yamagata Y, Tamaki E, Ikeda M, et al. Development andfield test of 1000kV 3000 mva transformer, CIGRE 1998;

    Session 12303, Paris, 1998, 16.

    1000-KV AC TRANSMISSION SYSTEMS IN CHINA 93

    Copyright# 2011 John Wiley & Sons, Ltd. Euro. Trans. Electr. Power2012; 22:8393

    DOI: 10.1002/etep