Estimating Task Durations

Methodologies and Psychologyof Estimating

Page 2: Estimating Task Durations Methodologies and Psychology of Estimating.

Project Schedules and Estimates

Accuracy at the task level translates up to the accuracy at the project level

Consistency is key

Page 3: Estimating Task Durations Methodologies and Psychology of Estimating.

Estimating the unknownHow long does it take to catch a fish?

Might be right away

Might be never

Might be anything in between

Page 4: Estimating Task Durations Methodologies and Psychology of Estimating.

Estimating the unknownApply metrics to the madness

What is ‘most likely’ to happen?

Page 5: Estimating Task Durations Methodologies and Psychology of Estimating.

Estimating the unknownWhat are the required ‘tools’ to complete the task?

Do we need to acquire the tools before attempting the task?

Page 6: Estimating Task Durations Methodologies and Psychology of Estimating.

Estimating the unknownMultiple tasks create an accumulation of guesses

‘Buffers’ 5+5=13

Page 7: Estimating Task Durations Methodologies and Psychology of Estimating.

So what do we do? Buffers are not secrets

Everyone knows durations are buffered

Page 8: Estimating Task Durations Methodologies and Psychology of Estimating.

What Does the Task Duration Really

Represent?Discussion

Page 9: Estimating Task Durations Methodologies and Psychology of Estimating.

Here are several approaches to estimating

task durations: Elapsed Time vs. Working Time

Task Time vs. Resource Time

Interface Losses & Delays

Theoretical Duration vs. Experience

Page 10: Estimating Task Durations Methodologies and Psychology of Estimating.

Elapsed Time vs. Working Time

We don’t work ALL the time

Page 11: Estimating Task Durations Methodologies and Psychology of Estimating.

Task Time vs. Resource Time

The number of people involved affects the elapsed time

Page 12: Estimating Task Durations Methodologies and Psychology of Estimating.

Interface Losses & Delays

How do we represent these spans of time to accommodate ‘buffers’ / ‘losses’?

Page 13: Estimating Task Durations Methodologies and Psychology of Estimating.

Theoretical Duration vs. Experience

What I know SHOULD happenvs.What I know Will happen

Page 14: Estimating Task Durations Methodologies and Psychology of Estimating.

Here are a few traps to note:

Page 15: Estimating Task Durations Methodologies and Psychology of Estimating.

Traps: MathImproper use of averaging

Page 16: Estimating Task Durations Methodologies and Psychology of Estimating.

Trap: Skill Levels, Learning Curves &

PrioritiesKnow your people

Know your priorities

Page 17: Estimating Task Durations Methodologies and Psychology of Estimating.

Task Duration EstimationPERT Method

(a + 4b + c) / 6

Page 18: Estimating Task Durations Methodologies and Psychology of Estimating.

PERT MethodDocument the estimation process

Page 19: Estimating Task Durations Methodologies and Psychology of Estimating.

Delphi MethodWAG and SWAG

Page 20: Estimating Task Durations Methodologies and Psychology of Estimating.

The Psychology of Task Durations

10 days to do 5 days of work. Why?

Page 21: Estimating Task Durations Methodologies and Psychology of Estimating.

The Psychology of Task Durations

Work seems to expand if we have time for it

Page 22: Estimating Task Durations Methodologies and Psychology of Estimating.

The Psychology of Task Durations

Do it tomorrow

Page 23: Estimating Task Durations Methodologies and Psychology of Estimating.

The Psychology of Task Durations

Padding – we can’t seem to win either way

Page 24: Estimating Task Durations Methodologies and Psychology of Estimating.

The Psychology of Task Durations

It seems for many it is natural to keep working until we are out of time or late

Page 25: Estimating Task Durations Methodologies and Psychology of Estimating.

Practical Time Estimating

We must pad or buffer

We must be realistic

Where’s the balance?

Page 26: Estimating Task Durations Methodologies and Psychology of Estimating.

Practical Time Estimating

There are methods that are tried and true

Page 27: Estimating Task Durations Methodologies and Psychology of Estimating.

Practical Time Estimating

Technique Example 1

Page 28: Estimating Task Durations Methodologies and Psychology of Estimating.

Practical Time Estimating

Technique Example 2

Page 29: Estimating Task Durations Methodologies and Psychology of Estimating.

Practical Time Estimating

Technique Example 3

Page 30: Estimating Task Durations Methodologies and Psychology of Estimating.

Practical Time Estimating

Technique Example 4

Page 31: Estimating Task Durations Methodologies and Psychology of Estimating.

Develop consistency in estimating

Follow standards

Page 32: Estimating Task Durations Methodologies and Psychology of Estimating.

Key factors in achieving project success

Know your objectives and these will drive your approach to Task Duration Estimations

Page 33: Estimating Task Durations Methodologies and Psychology of Estimating.

Estimating Task Durations

Standards

Documentation

Communication