Estimating calculation

182
ELEMENT 1 – WORK BELOW LOWEST FLOOR LEVEL 1. Estimate Excavation Cost a. Excavation to Reduce Level Data: Size: 15.00m x 12.00m = 180.00m ² (Depth: 0.10m) Excavation Output: 1.75 – 2.00 hour/m³ Require 1 general construction worker at RM52.50/day Allow 15% profit including overhead b. Excavation in Pits for Pad Footing and Stump Data: Pit Size: 1.50m x 1.50m x 1.55m deep Excavation Output: 3.00 – 4.50 hour /m³ Require 2 general construction worker at RM52.50/day Allow 15% profit including overhead *Backfilling (30% of the excavation) c. Excavation in Trench for Ground Beam Data: Trench Size: 5.00m x 1.50m x 1.20m deep Excavation Output: 2.00 – 2.75 hour /m³ Require 2 general construction worker at RM52.50/day Allow 15% profit including overhead

Transcript of Estimating calculation

Page 1: Estimating calculation

ELEMENT 1 – WORK BELOW LOWEST FLOOR LEVEL1. Estimate Excavation Cost

a. Excavation to Reduce Level Data:

Size: 15.00m x 12.00m = 180.00m² (Depth: 0.10m) Excavation Output: 1.75 – 2.00 hour/m³ Require 1 general construction worker at RM52.50/day Allow 15% profit including overhead

b. Excavation in Pits for Pad Footing and StumpData:

Pit Size: 1.50m x 1.50m x 1.55m deep Excavation Output: 3.00 – 4.50 hour/m³ Require 2 general construction worker at RM52.50/day Allow 15% profit including overhead

*Backfilling (30% of the excavation)

c. Excavation in Trench for Ground BeamData:

Trench Size: 5.00m x 1.50m x 1.20m deep Excavation Output: 2.00 – 2.75 hour/m³ Require 2 general construction worker at RM52.50/day Allow 15% profit including overhead

Calculation:

Page 2: Estimating calculation

1.a. Cost for Excavation to Reduce Level

Excavation QuantitySize: 15.00m x 12.00m x 0.10m = 18.00m³Size < 1.50m deep = 18.00m³Excavation Time RequiredSize < 1.50m deep = 18.00m³ x 1.75 hour/m³ = 31.5 hoursExcavation CostGeneral construction worker at RM 52.50/day/person, 1day= 8hoursCost for 1 general construction worker = (31.5hours / 8.0hours) x RM 52.50 = RM206.72

Unit Rate for Excavation to Reduce LevelUnit rate for excavation to reduce level = RM 206.72 / 18.00 m³ = RM 11.48/m³100mm thick = RM 11.48/m³ x 0.10m = RM 1.15/m²Allow 15% profit including overhead = RM 1.15/m² x 1.15 = RM1.32/m²

Total Cost for Excavation to Reduce LevelRM1.32/m² x 180.00m² = RM237.60

Calculation:

Page 3: Estimating calculation

1.b. Cost for Excavation in Pits for Pad Footing and Stump Excavation QuantityPit Size: 1.50m x 1.50m x 1.55m = 3.49m³Pit Size < 1.50m deep = 1.50m x 1.50m x 1.50m = 3.38m³Pit Size 1.50m – 3.00m deep = 1.50m x 1.50m x (1.55 - 1.50m) = 0.11m³Excavation Time RequiredPit Size < 1.50m deep = 3.38m³ x 3.00hour/m³ = 10.14hoursPit Size 1.50m – 3.00m deep = 0.11m³ x 3.50hour/m³ = 0.39hoursTotal time required for excavation = 10.14hours + 0.39hours = 10.53hoursExcavation CostGeneral construction worker at RM 52.50/day/person, 1day= 8hoursCost for 2 general construction worker = [(10.53hours / 8.0hours) x RM 52.50] x 2 = RM138.21

Unit Rate in Pits for Pad Footing and Stump Unit rate for excavation in pits = RM138.21 / 4 m³ = RM 34.55/m³Allow 15% profit including overhead = RM 34.55 x 1.15 = RM39.73/m³

Total Cost in Pits for Pad Footing and Stump RM39.73/m³ x 4.00m³ = RM 158.92

Unit Rate for Backfilling (30%)RM39.73/m³ x 0.30 = RM 11.92/m³Total Cost for Backfilling (30%)RM 158.92 x 0.30 = RM47.68

Calculation:

Page 4: Estimating calculation

1.c. Cost for Excavation in Trench for Ground Beam

Excavation QuantityTrench Size: 5.00m X 1.50m X 1.20m = 9.00m³Trench Size < 1.50m deep = 9.00m³Excavation Time RequiredTrench Size < 1.50m deep = 9.00m³ x 2.00hour/m³ = 4.50hoursExcavation CostGeneral construction worker at RM 52.50/day/person, 1day= 8hoursCost for 2 general construction worker = [(4.50hours / 8.0hours) x RM 52.50] x 2 = RM59.06

Unit Rate for Excavation in Trench for Ground Beam Unit rate for excavation in trench = RM59.06 / 9.00 m³ = RM6.56/m³Allow 15% profit including overhead = RM6.56/m³ x 1.15 = RM 7.54/m³

Total Cost for Excavation in Trench for Ground Beam RM7.54/m³ x 9.00m³ = RM67.86

2. Estimate Lean Concrete and Hardcore Cost

Page 5: Estimating calculation

a. Lean Concrete (Grade 15) to:i. 50mm binding screed, spread and leveled under pad footingii. 50mm binding screed, spread and leveled under ground beamiii. 50mm binding screed, spread and leveled under ground floor slab

Data: Cost of Concrete

Use 1:2:4 concrete design (Grade 15) Ordinary Portland Cement at 1420kg/m³ at RM16.96/50kg Fine Aggregate at 1600kg/m³ at RM40.99/tonne Coarse Aggregate at 1400kg/m³ at RM41.69/tonne Shrinkage, consolidation and wastage 50%

Cost of Labour Labour gang consists of:

2 skilled concreter (foreign) at RM75.20/day/person, and; 1 semi-skilled concreter (foreign) at RM52.50/day/person

1 mixer output at 1.20m³/hour Cost of 1 mixer including fuel RM400.00/month Additional labour for placing of concrete at 0.60hour/m³, RM52.50/day Allow 15% profit including overhead

Calculation:

Page 6: Estimating calculation

Cost for Lean Concrete (Grade 15)

Material CostUse 1:2:4 concrete designOPC at 1420kg/m³ at RM16.96/50kg= (1420 x 16.96) / 50 = RM481.66/m³Fine Agg. at 1600kg/m³ at RM40.99/tonne= [(1600 x 40.99) / 1000] x 2= RM131.17/m³Coarse Agg. at 1400kg/m³ at RM41.69/tonne=[(1400 x 41.69) / 1000] x 4= RM233.46/m³

Gross cost/7m³ = RM846.29/7m³Add Shrinkage, consolidation & wastage 50%= RM846.29/7m³ x 1.50= RM1269.44/7m³Cost for 1m³ of concrete mix= RM1269.44 / 7m³ = RM181.35/m³

Plant Cost1 mixer at 1.2m³/hour, RM400.00/month 1 month= RM400.00, 1day= RM13.33, 1hour= RM1.67(1 hour / 1.2m³) x RM1.67 = RM1.39/m³

Labour Cost2 skilled concreter (foreign) = {[(1 / 1.2) x 75.20] / 8} x 2 = RM15.67/m³1 semi-skilled concretor (foreign) = [(1 / 1.2) x 52.50] / 8 = RM5.47/m³Additional labour for placing concrete (0.60 x 52.50) / 8 = RM3.94/m³

Total labour cost = RM25.08/m³

Summary of Unit Rate for Lean Concrete (Grade 15) to:

Page 7: Estimating calculation

i. 50mm binding screed, spread and leveled under pad footingii. 50mm binding screed, spread and leveled under ground beamiii. 50mm binding screed, spread and leveled under ground floor slab

Material cost + Plant cost + Labour cost = RM207.82/m³Allow 15% profit including overhead = RM207.82/m³ x 1.15 = RM238.99/m³50mm binding screed x 0.05m

= RM11.95/m²

Total Cost for Lean Concrete (Grade 15) to: i. 50mm binding screed, spread and leveled under pad footing

RM11.95/m² x 2m² = RM23.90

ii. 50mm binding screed, spread and leveled under ground beamRM11.95/m² x 17m² = RM203.15

iii. 50mm binding screed, spread and leveled under ground floor slabRM11.95/m² x 120m² = RM1434.00

2. Estimate Lean Concrete and Hardcore Cost

Page 8: Estimating calculation

b. 150mm thick Hardcore to:i. 50mm binding screed, spread and leveled under pad footingii. 50mm binding screed, spread and leveled under ground beamiii. 50mm binding screed, spread and leveled under ground floor slab

Data:Material Cost

Hardcore material RM65/m³ (6% GST excluded) Allow 10% compaction

Labour Cost 1 general construction worker at RM52.50/day

Allow 15% profit including overhead

Calculation:

Page 9: Estimating calculation

Cost for 150mm thick Hardcore to:i. 50mm binding screed, spread and leveled under pad footingii. 50mm binding screed, spread and leveled under ground beamiii. 50mm binding screed, spread and leveled under ground floor slab

Material CostHardcore material = RM65/m³ x 1.06 = RM68.90/m³10% Compaction = RM68.90/m³ x 1.10 = RM75.79/m³

Labour Cost1 general construction worker at RM52.50/day = [(1 / 1.2) x 52.50] / 8 = RM5.47/m³

Summary of Unit RateMaterial cost + Labour cost = RM81.26/m³Allow 15% profit including overhead = RM81.26/m³ x 1.15 = RM93.45/m³150mm thick hardcore = RM93.45/m³ x 0.15m = RM14.02/m²

Total Cost of 150mm thick Hardcore under Pad FootingRM14.02/m² x 2m² = RM28.04Total Cost of 150mm thick Hardcore under Ground BeamRM14.02/m² x 17m² = RM238.34Total Cost of 150mm thick Hardcore under Concrete SlabRM14.02/m² x 120m² = RM1682.40

3. Estimate Concrete Cost

Page 10: Estimating calculation

a. Vibrated reinforced concrete Grade 25 as described filled into formwork and well packed around reinforcement in:

i. Pad Footingii. Column Stumpiii. Ground Beam

b. Vibrated reinforced concrete Grade 30 as described filled into formwork and well packed around reinforcement in:

i. 125mm thick bed spread and levelled on binding screedii. 175mm thick bed spread and levelled on binding screed

Data:Cost of Concrete

Use 1:1:2 concrete design (Grade 25) Use 1:2:3 concrete design (Grade 30) Ordinary Portland Cement at 1420kg/m³ at RM16.96/50kg Fine Aggregate at 1600kg/m³ at RM40.99/tonne Coarse Aggregate at 1400kg/m³ at RM41.69/tonne Shrinkage, consolidation and wastage 50%

Cost of Labour Labour gang consists of:

3 skilled concreter (foreign) at RM75.20/day/person, and; 2 semi-skilled concreter (foreign) at RM52.50/day/person

1 mixer output at 1.20m³/hour Cost of 1 mixer including fuel RM400.00/month Additional labour for placing of concrete at 0.60hour/m³, RM52.50/day Additional labour for working around reinforcement at 0.55hour/m³, RM52.50/day Cost of vibrator, RM400.00/month Allow 15% profit including overhead

Calculation: Cost of Vibrated reinforced concrete Grade 25 as described filled into

Page 11: Estimating calculation

formwork and well packed around reinforcement in:i. Pad Footingii. Column Stumpiii. Ground Beam

Cost of Vibrated reinforced concrete Grade 30 as described filled into formwork and well packed around reinforcement in:

i. 125mm thick bed spread and levelled on binding screedii. 175mm thick bed spread and levelled on binding screed

Material Cost for Vibrated reinforced concrete Grade 25Use 1:1:2 concrete designOPC at 1420kg/m³ at RM16.96/50kg= (1420 x 16.96) / 50 = RM481.66/m³Fine Aggregate at 1600kg/m³ at RM40.99/tonne= (1600 x 40.99) / 1000 = RM65.58/m³Coarse Agg. at 1400kg/m³ at RM41.69/tonne=[(1400 x 41.69) / 1000] x 2= RM116.73/m³

Gross cost/4m³ = RM663.97/4m³Add Shrinkage, consolidation and wastage 50%= RM663.97/4m³ x 1.50= RM995.96/4m³Cost for 1m³ of concrete mix= RM995.96 / 4m³ = RM248.99/m³

Plant Cost1 mixer & vibrator at 1.2m³/hour, RM400.00/month 1 month= RM400.00, 1day= RM13.13, 1hour= RM1.67(1 hour / 1.2m³) x RM1.67 = RM1.39/m³

Total plant cost = RM1.39/m³ x 2 = RM2.78/m³

Labour Cost3 skilled concreter (foreign) = {[(1 / 1.2) x 75.20] / 8} x 3 = RM23.50/m³2 semi-skilled concretor (foreign) = {[(1 / 1.2) x 52.50] / 8} x 2 = RM10.94/m³Additional labour for placing concrete = (0.60 x 52.50) / 8 = RM3.94/m³Additional labour for working around reinforcement = (0.55 x 52.50) / 8 = RM3.61/m³

Total labour cost = RM41.99/m³

Summary of Unit Rate for Vibrated reinforced concrete Grade 25 Material cost + Plant cost + Labour cost = RM293.76/m³

Page 12: Estimating calculation

Allow 15% profit including overhead = RM293.76/m³ x 1.15 = RM337.82/m³

Total Cost for Vibrated reinforced concrete Grade 25 to Pad Footing RM337.82/m³ x 1m³ = RM337.82Total Cost for Vibrated reinforced concrete Grade 25 to Column Stump RM337.82/m³ x 1m³ = RM337.82Total Cost for Vibrated reinforced concrete Grade 25 to Ground Beam RM337.82/m³ x 4m³ = RM1351.28

Calculation:Cost of Vibrated reinforced concrete Grade 30 as described filled into

Page 13: Estimating calculation

formwork and well packed around reinforcement in:i. 125mm thick bed spread and levelled on binding screedii. 175mm thick bed spread and levelled on binding screed

Material Cost for Vibrated reinforced concrete Grade 25Use 1:2:3 concrete designOPC at 1420kg/m³ at RM16.96/50kg= (1420 x 16.96) / 50 = RM481.66/m³Fine Agg. at 1600kg/m³ at RM40.99/tonne= [(1600 x 40.99) / 1000] x 2 = RM131.17/m³Coarse Agg. at 1400kg/m³ at RM41.69/tonne=[(1400 x 41.69) / 1000] x 3= RM175.10/m³

Gross cost/6m³ = RM787.93/6m³Add Shrinkage, consolidation & wastage 50%= RM787.93/6m³ x 1.50= RM1181.90/4m³Cost for 1m³ of concrete mix= RM1181.90 / 4m³ = RM295.48/m³

Plant Cost1 mixer & vibrator at 1.2m³/hour, RM400.00/month 1 month= RM400.00, 1day= RM13.13, 1hour= RM1.67(1 hour / 1.2m³) x RM1.67 = RM1.39/m³Total plant cost = RM1.39/m³ x 2 = RM2.78/m³

Labour Cost3 skilled concreter (foreign) = {[(1 / 1.2) x 75.20] / 8} x 3 = RM23.50/m³2 semi-skilled concretor (foreign) = {[(1 / 1.2) x 52.50] / 8} x 2 = RM10.94/m³Additional labour for placing concrete = (0.60 x 52.50) / 8 = RM3.94/m³Additional labour for working around reinforcement = (0.55 x 52.50) / 8 = RM3.61/m³

Total labour cost = RM41.99/m³

Summary of Unit Rate for Vibrated reinforced concrete Grade 30 to 125mm thick bed

Page 14: Estimating calculation

Material cost + Plant cost + Labour cost = RM340.25/m³Allow 15% profit including overhead = RM340.25/m³ x 1.15 = RM391.29/m³125mm thick bed = RM391.29/m³ x 0.125m = RM48.91/m²

Summary of Unit Rate for Vibrated reinforced concrete Grade 30 to 175mm thick bedMaterial cost + Plant cost + Labour cost = RM340.25/m³Allow 15% profit including overhead = RM340.25/m³ x 1.15 = RM391.29/m³175mm thick bed = RM391.29/m³ x 0.175m = RM68.48/m²

Total Cost for Vibrated reinforced concrete Grade 30 to 125mm thick bed RM48.91/m² x 104m² = RM5086.64Total Cost for Vibrated reinforced concrete Grade 30 to 175mm thick bed RM68.48/m² X 14m² = RM958.72

4. Estimate Formwork CostSawn formwork as described to:

Page 15: Estimating calculation

i. sides of pad footingii. sides of column stumpiii. sides of ground beamiv. edge of concrete exceeding 100mm, not exceeding 200mm high

Data: 3m² of 12mm plywood at RM59.36 Cutting waste 15% Allow 4 uses of timber formwork Waste on each use 10% Nails, bolts at RM1.10/m² (6% GST excluded) Require 1 skilled formwork carpenter at RM89/10/day/person, and;

2 general construction worker (foreign) at RM52.50/day/person Require 8 hours to erect and fix all formwork Allow 15% profit including overhead

Calculation: Cost of formwork as described to:

Page 16: Estimating calculation

i. sides of pad footingii. sides of column stumpiii. sides of ground beam

Material Cost for Formwork to Sides of Pad Footing, Column Stump and Ground Beam3m² of 12mm plywood at RM59.36 = RM59.36 / 3m² = RM19.79m²Allow 15% cutting waste = RM19.79 x 0.15 = RM2.97/m²

Cost of Timber = RM22.76/m²

Allow 4 uses of timber formwork = RM22.76 / 4 = RM5.69/m²Waste on each use 10% = RM5.69 X 0.10 = RM0.57/m²Nails, bolts at RM1.10/m² x 1.06 = RM1.17/m²

Cost of reused formwork = RM7.43/m²

Labour Cost for Formwork to Sides of Pad Footing1 skilled formwork carpenter = RM89.10 = RM89.10/8hours2 general construction worker (foreign) = RM52.50 x 2 = RM105.00/8hours

RM194.10/8hoursRM194.10/8hours = RM194.10 / 5m² = RM38.82/m²

Labour Cost for Formwork to Sides of Column Stump1 skilled formwork carpenter = RM89.10 = RM89.10/8hours2 general construction worker (foreign) = RM52.50 x 2 = RM105.00/8hours

Page 17: Estimating calculation

RM194.10/8hoursRM194.10/8hours = RM194.10 / 14m² = RM13.86/m²

Labour Cost for Formwork to Sides of Ground Beam1 skilled formwork carpenter = RM89.10 = RM89.10/8hours2 general construction worker (foreign) = RM52.50 x 2 = RM105.00/8hours

RM194.10/8hoursRM194.10/8hours = RM194.10 / 7m² = RM27.73/m²

Summary of Unit Rate for Formwork to Sides of Pad FootingMaterial Cost + Labour Cost = RM7.43/m² + RM38.82/m² = RM46.25/m²Allow 15% profit including overhead = RM46.25/m² x 1.15 = RM53.19/m²Summary of Unit Rate for Formwork to Sides of Column StumpMaterial Cost + Labour Cost = RM7.43/m² + RM13.86/m² = RM21.29/m²Allow 15% profit including overhead = RM21.29/m² x 1.15 = RM24.48/m²Summary of Unit Rate for Formwork to Sides of Ground BeamMaterial Cost + Labour Cost = RM7.43/m² + RM27.73/m² = RM35.16/m²Allow 15% profit including overhead = RM35.16/m² x 1.15 = RM40.43/m²

Total Cost for Formwork to Sides of Pad FootingTotal Cost = RM53.19/m² x 5m² = RM265.95Total Cost for Formwork to Sides of Column StumpTotal Cost = RM24.48/m² x 14m² = RM342.72Total Cost for Formwork to Sides of Ground BeamTotal Cost = RM40.43/m² x 7m² = RM283.01

Calculation: Cost of formwork as described to:

iv. edge of concrete exceeding 100mm, not exceeding 200mm high

Material Cost for Formwork

Page 18: Estimating calculation

3m² of 12mm plywood at RM59.36 = RM59.36 / 3m² = RM19.79m²Allow 15% cutting waste = RM19.79 x 0.15 = RM2.97/m²

Cost of Timber = RM22.76/m²Allow 4 uses of timber formwork = RM22.76 / 4 = RM5.69/m²Waste on each use 10% = RM5.69 X 0.10 = RM0.57/m²Nails, bolts at RM1.10/m² x 1.06 = RM1.17/m²

Cost of reused formwork = RM7.43/m²150mm thick concrete slab = RM7.43/m² x 0.15 = RM1.11/mLabour Cost for Formwork 1 skilled formwork carpenter = RM89.10 = RM89.10/8hours2 general construction worker (foreign) = RM52.50 x 2 = RM105.00/8hours

RM194.10/8hoursRM194.10/8hours = RM194.10 / 44m = RM4.41/m

Summary of Unit Rate for FormworkMaterial Cost + Labour Cost = RM1.11/m + RM4.41/m = RM5.52/mAllow 15% profit including overhead = RM5.52/m x 1.15 = RM6.35/m

Total Cost for FormworkTotal Cost = RM6.35/m x 44m = RM279.40

5. Estimate Mild Steel Reinforcement Bar Costa. 8mm Diameter in:

i. Column Stump as Linksii. Ground Beam as Stirrups

Data:

Page 19: Estimating calculation

Material Cost 8mm diameter bar delivered to site at RM1000.00/tonne Allow for labour stacking and loading at RM5/tonne Tie wire at 0.66kg/100kg of reinforcement bar at RM4/kg (6% GST excluded) Allow spacers at RM4/tonne of rebar Allow 7% waste Rolling margin RM22/tonne Allow 15% profit including overhead

Labour Cost Require 1 skilled barbender (foreign) at RM83.60/day, and;

1 general construction worker (foreign) at RM52.50/day Allow 10% idling time Allow 15% profit including overheads Time analysis for 100kg of reinforcement bar

Select 28 minutesCut 32 minutesBend 35 minutesFix 23 minutesHoist Twice 7 minutes

Calculation:Cost for Mild Steel Reinforcement Bar

a. 8mm Diameter in:i. Column Stump as Linksii. Ground Beam as Stirrups

Material Cost

Page 20: Estimating calculation

8mm diameter mild steel bar delivered to site = RM1000.00/tonneAllow labour unloading and stacking = RM5.00/tonneTie wire = (0.66kg / 100kg) x 1000 x (RM4.00 x 1.06) = RM27.98/tonneSpacer for rebar = RM4.00/tonne7% wastage = RM1000.00 x 0.70 = RM700.00/tonneRolling margin = RM22.00/tonne

Cost of Meterial = RM1758.98/tonne

Labour Cost1 skilled barbender (foreign) = RM83.60 / 8 hours = RM10.45/hour1 general construction worker (foreign) = RM52.50 / 8hours = RM6.56/hour

Gross total = RM17.01/hour10% idling time = RM17.01 x 1.10 = RM18.71/hour

Time Analysis per 100kg of rebarSelect + Cut + Bend + Fix + Hoist twice = (28+32+35+23+7)minutes = 125minutesCost of labour = (125minutes / 60) x RM18.71 = RM38.98/100kg

Cost of Labour = RM389.80/tonne

SummaryMaterial cosf + Labour cost = RM1758.98 + RM389.80 = RM2148.78/tonne15% profit including overhead = RM2148.78 x 0.15 = RM322.32/tonne

Unit Rate = RM2471.10/tonne

Total Cost for Links in Column StumpQuantity = 34kgRate = RM2471.10 / 1000 = RM2.47/kgRebar Cost = Quantity x Rate = RM83.98

Total Cost for Stirrups in Ground BeamQuantity = 116kgRate = RM2471.10 / 1000 = RM2.47/kgRebar Cost = Quantity x Rate = RM286.52

5. Estimate Mild Steel Reinforcement Bar Costb. 10mm Diameter in:

i. Pad Footing as Loopsii. Ground Beam as Stirrups

Page 21: Estimating calculation

Data:Material Cost

10mm diameter bar delivered to site at RM2102.33/tonne Allow for labour stacking and loading at RM5/tonne Tie wire at 0.66kh/100kg of reinforcement bar at RM4/kg (6% GST excluded) Allow spacers at RM4/tonne of rebar Allow 7% waste Rolling margin RM22/tonne Allow 15% profit including overhead

Labour Cost Require 1 skilled barbender (foreign) at RM83.60/day, and;

1 general construction worker (foreign) at RM52.50/day Allow 10% idling time Allow 15% profit including overheads Time analysis for 100kg of reinforcement bar

Select 28 minutesCut 32 minutesBend 35 minutesFix 23 minutesHoist Twice 7 minutes

Calculation:Cost for Mild Steel Reinforcement Bar

b. 10mm Diameter in:i. Pad Footing as Loopsii. Ground Beam as Stirrups

Page 22: Estimating calculation

Material Cost10mm diameter mild steel bar delivered to site = RM2102.33/tonneAllow labour unloading and stacking = RM5.00/tonneTie wire = (0.66kg / 100kg) x 1000 x (RM4.00 x 1.06) = RM27.98/tonneSpacer for rebar = RM4.00/tonne7% wastage = RM2102.33 x 0.70 = RM1471.63/tonneRolling margin = RM22.00/tonne

Cost of Meterial = RM3632.94/tonne

Labour Cost1 skilled barbender (foreign) = RM83.60 / 8 hours = RM10.45/hour1 general construction worker (foreign) = RM52.50 / 8hours = RM6.56/hour

Gross total = RM17.01/hour10% idling time = RM17.01 x 1.10 = RM18.71/hour

Time Analysis per 100kg of rebarSelect + Cut + Bend + Fix + Hoist twice = (28+32+35+23+7)minutes = 125minutesCost of labour = (125minutes / 60) x RM18.71 = RM38.98/100kg

Cost of Labour = RM389.80/tonne

SummaryMaterial cosf + Labour cost = RM3632.94 + RM389.80 = RM4022.74/tonne15% profit including overhead = RM4022.74 x 0.15 = RM603.41/tonne

Unit Rate = RM4626.15/tonne

Total Cost for Loops in Pad FootingQuantity = 7kgRate = RM4626.15 / 1000 = RM4.63/kgRebar Cost = Quantity x Rate = RM32.41

Total Cost for Stirrups in Ground BeamQuantity = 101kgRate = RM4626.15 / 1000 = RM4.63/kgRebar Cost = Quantity x Rate = RM467.63

6. Estimate High Tensile Reinforcement Bar Costa. 10mm Diameter in:

i. Ground Beamb. 12mm Diameter in:

i. Pad Footing ii. Column Stump iii. Ground Beam

Page 23: Estimating calculation

c. 16mm Diameter in:i. Pad Footing ii. Colump Stump

Data:Material Cost

10mm diameter bar delivered to site at RM1996.33/tonne 12mm diameter bar delivered to site at RM1996.33/tonne 16mm diameter bar delivered to site at RM1925.67/tonne Allow for labour stacking and loading at RM5/tonne Tie wire at 0.66kh/100kg of reinforcement bar at RM4.00/kg (6% GST excluded) Allow spacers at RM4/tonne of rebar Allow 7% waste Rolling margin RM22/tonne Allow 15% profit including overhead

Labour Cost Require 1 skilled barbender (foreign) at RM83.60/day, and;

1 general construction worker (foreign) at RM52.50/day Allow 10% idling time Allow 15% profit including overheads Time analysis for 100kg of reinforcement bar

Select 28 minutesCut 32 minutesBend 35 minutesFix 23 minutesHoist Twice 7 minutes

Calculation:Cost for High Tensile Reinforcement Bar

a. 10mm Diameter in:i. Ground Beam

Page 24: Estimating calculation

Material Cost10mm diameter high tensile bar delivered to site = RM1996.33/tonneAllow labour unloading and stacking = RM5.00/tonneTie wire = (0.66kg / 100kg) x 1000 x (RM4.00 x 1.06) = RM27.98/tonneSpacer for rebar = RM4.00/tonne7% wastage = RM1996.33 x 0.70 = RM1397.43/tonneRolling margin = RM22.00/tonne

Cost of Meterial = RM3452.74/tonne

Labour Cost1 skilled barbender (foreign) = RM83.60 / 8 hours = RM10.45/hour1 general construction worker (foreign) = RM52.50 / 8hours = RM6.56/hour

Gross total = RM17.01/hour10% idling time = RM17.01 x 1.10 = RM18.71/hour

Time Analysis per 100kg of rebarSelect + Cut + Bend + Fix + Hoist twice = (28+32+35+23+7)minutes = 125minutesCost of labour = (125minutes / 60) x RM18.71 = RM38.98/100kg

Cost of Labour = RM389.80/tonne

SummaryMaterial cosf + Labour cost = RM3452.74 + RM389.80 = RM3842.54/tonne15% profit including overhead = RM3842.54 x 0.15 = RM576.38/tonne

Unit Rate = RM4418.92/tonne

Total Cost for 10mm Diameter High Tensile Bar in Ground BeamQuantity = 300kgRate = RM4418.92 / 1000 = RM4.42/kgRebar Cost = Quantity x Rate = RM1326.00

Calculation:Cost for High Tensile Reinforcement Bar

b. 12mm Diameter in:i. Pad Footing

Page 25: Estimating calculation

ii. Column Stumpsiii. Ground Beam

Material Cost12mm diameter high tensile bar delivered to site = RM1996.33/tonneAllow labour unloading and stacking = RM5.00/tonneTie wire = (0.66kg / 100kg) x 1000 x (RM4.00 x 1.06) = RM27.98/tonneSpacer for rebar = RM4.00/tonne7% wastage = RM1996.33 x 0.70 = RM1397.43/tonneRolling margin = RM22.00/tonne

Cost of Meterial = RM3452.66/tonne

Labour Cost1 skilled barbender (foreign) = RM83.60 / 8 hours = RM10.45/hour1 general construction worker (foreign) = RM52.50 / 8hours = RM6.56/hour

Gross total = RM17.01/hour10% idling time = RM17.01 x 1.10 = RM18.71/hour

Time Analysis per 100kg of rebarSelect + Cut + Bend + Fix + Hoist twice = (28+32+35+23+7)minutes = 125minutesCost of labour = (125minutes / 60) x RM18.71 = RM38.98/100kg

Cost of Labour = RM389.80/tonneSummaryMaterial cosf + Labour cost = RM3452.66 + RM389.80 = RM3842.46/tonne15% profit including overhead = RM3842.46 x 0.15 = RM576.37/tonne

Unit Rate = RM4418.83/tonne

Total Cost for 12mm Diameter High Tensile Bar in Pad FootingQuantity = 17kgRate = RM4418.83 / 1000 = RM4.42/kgRebar Cost = Quantity x Rate = RM75.14

Total Cost for 12mm Diameter High Tensile Bar in Column StumpsQuantity = 90kgRate = RM4418.83 / 1000 = RM4.42/kgRebar Cost = Quantity x Rate = RM397.80

Total Cost for 12mm Diameter High Tensile Bar in Ground BeamQuantity = 349kgRate = RM4418.83 / 1000 = RM4.42/kgRebar Cost = Quantity x Rate = RM1542.58

Calculation:Cost for High Tensile Reinforcement Bar

c. 16mm Diameter in:

Page 26: Estimating calculation

i. Pad Footingii. Column Stumps

Material Cost16mm diameter high tensile bar delivered to site = RM1925.67/tonneAllow labour unloading and stacking = RM5.00/tonneTie wire = (0.66kg / 100kg) x 1000 x (RM4.00 x 1.06) = RM27.98/tonneSpacer for rebar = RM4.00/tonne7% wastage = RM1925.67 x 0.70 = RM1347.97/tonneRolling margin = RM22.00/tonne

Cost of Meterial = RM3332.62/tonne

Labour Cost1 skilled barbender (foreign) = RM83.60 / 8 hours = RM10.45/hour1 general construction worker (foreign) = RM52.50 / 8hours = RM6.56/hour

Gross total = RM17.01/hour10% idling time = RM17.01 x 1.10 = RM18.71/hour

Time Analysis per 100kg of rebarSelect + Cut + Bend + Fix + Hoist twice = (28+32+35+23+7)minutes = 125minutesCost of labour = (125minutes / 60) x RM18.71 = RM38.98/100kg

Cost of Labour = RM389.80/tonne

SummaryMaterial cosf + Labour cost = RM3332.62 + RM389.80 = RM3722.42/tonne15% profit including overhead = RM3722.42 x 0.15 = RM558.36/tonne

Unit Rate = RM4280.78/tonne

Total Cost for 16mm Diameter High Tensile Bar in Pad FootingQuantity = 20kgRate = RM4280.78 / 1000 = RM4.28/kgRebar Cost = Quantity x Rate = RM85.60

Total Cost for 16mm Diameter High Tensile Bar in Column StumpsQuantity = 100kgRate = RM4280.78 / 1000 = RM4.28/kgRebar Cost = Quantity x Rate = RM428.00

7. Estimate Layer of Steel Fabric Reinforcement Costa. A6: 2.61kg/m² to 125mm slab

Page 27: Estimating calculation

b. A8: 3.01kg/m² to 175mm slab

Data:Material Cost

A6: 2.61kg/m² at RM6.36/m² A8: 3.01kg/m² at RM10.60/m² Allow 5% wastage

Labour Cost Require 2 general construction workers at RM52.50/day/person Allow 10% idling time Allow 15% profit including overhead

Calculation:Cost for Layer of Steel Fabric Reinforcement Cost

a. A6: 2.61kg/m² to 125mm slab

Page 28: Estimating calculation

Material CostA6: 2.61kg/m² material cost = RM6.36/m²Add 5% wastage = RM6.36/m² x 1.05 = RM6.68/m²

Labour Cost per hour2 general construction worker (foreign) = (RM52.50 / 8hours) x 2 =

RM13.13/hour10% idling time = RM13.13 x 1.10 = RM14.44/hour

Summary of Unit RateMaterial cost + Labour cost = RM6.68 + RM14.44 = RM20.99/m²Allow 15% profit including overhead = RM20.99/m² x 1.15 = RM24.14/m²

Total CostQuantity = 178m²Rate = RM24.14/m²BRC Cost = Quantity x Rate = RM4296.92

Calculation:Cost for Layer of Steel Fabric Reinforcement Cost

b. A8: 3.01kg/m² to 175mm slab

Page 29: Estimating calculation

Material CostA6: 3.01kg/m² material cost = RM10.60/m²Add 5% wastage = RM10.60/m² x 1.05 = RM11.13/m²

Labour Cost per hour2 general construction worker (foreign) = (RM52.50 / 8hours) x 2 =

RM13.13/hour10% idling time = RM13.13 x 1.10 = RM14.44/hour

Summary of Unit RateMaterial cost + Labour cost = RM11.13 + RM14.44 = RM25.57/m²Allow 15% profit including overhead = RM25.57/m² x 1.15 = RM29.41/m²

Total CostQuantity = 28m²Rate = RM29.41/m²BRC Cost = Quantity x Rate = RM823.48

Element No. 2 Frame

Estimate Concrete Cost for Beam

Page 30: Estimating calculation

A) Reinforced concrete Grade 25 as described filled into formwork and well packed around beam.

Concrete Data

Cost of concrete:

Use 1:1:2 concrete design (Grade 25)

1. Ordinary Portland Cement at 1420kg/m3 at RM16.96/50kg.2. Fine aggregate at 1600kg/m3 at RM 40.99/tonne. 3. Coarse aggregate at 1400kg/m3 at RM 41.69/tonne. 4. Shrinkage, consolidation and wastage 50%.

Cost of Labour:

1. Labour gang 5 numbers, 3 skilled concretor and 2 semiskilled concretor, 8 hours/day. 2. Skilled concretor RM75.20/day, semiskilled concretor RM 61.80/day. 3. Additional labour placing concrete into beams 0.60hr/m3, RM 52.50/day.4. Additional labour for working around reinforcement, 0.55hr/m3, RM52.50/day. 5. One mixer output at 1.2 m3 per hour, RM400.00/month including fuel. 6. One concrete vibrator output at 1.2 m3 per hour, RM400.00/month including fuel.

Allow 15% of profit including overhead.

Estimate Grade 25 Concrete Cost for Beam

Step 1 Material Cost

Page 31: Estimating calculation

Use 1:1:2 Concrete Design (RM)

Ordinary Portland Cement at 1420kg/m3 at RM 16.96/50kg :(1420/50)xRM16.96 481.66/m3

Fine Aggregate at 1600kg/m3 at RM40.99/tonne: (1600/1000)xRM40.99 65.58/m3

Course Aggregate at 1400kg/m3 at RM41.69/tonne: (1400/1000)xRM41.69x2m3 116.73/2m 3 Gross Cost per 4m3 663.97/4m3 Add 50% Shrinkage, consolidation and wastage 663.97x50% 331.99/4m 3

995.96/4m 3 1m3 of concrete mix: (995.96/4) 248.99/m 3 Step 2 Mix-Plant

One mixer at 1.2m3 per hour: 1/1.2x[400/(30x8)] 1.39/m 3 Step 2 Mix-Labour

3 Skilled Concretor: (75.20/8)x3x0.84 23.69/m3

2 Semi-skilled Concretor: (61.80/8)x2x0.84 12.99/m 3 Total Labour Cost 36.68/m 3

Step 3 Place- Labour and Vibrator

Additional labour for placing concrete into beams:(52.50/8)x0.60 3.94/m3

Additional labour for working around reinforcement: (52.50/8)x0.55 3.61/m3

Cost of concrete vibrator: 1/1.2x[400/(30x8)] 1.39/m 3 Total Labour and Vibrator Cost 8.94/m 3 Step 4 Summary for Unit Rate

RM248.99(Material) +RM1.36(Plant)+RM36.68(Labour) +RM8.94(Labour and Vibrator)+RM44.40( 15%profit&overhead) ________ RM340.37/m 3 Step 5 Total Cost6.00m3xRM340.37/m3 = RM2042.22

Element No. 2 Frame

Estimate Concrete Cost for Column

B) Reinforced concrete Grade 30 as described filled into formwork and well packed around columns.

Concrete Data

Page 32: Estimating calculation

Cost of concrete:

Use 1:2:3concrete design (Grade 30)

1. Ordinary Portland Cement at 1420kg/m3 at RM16.96/50kg.2. Fine aggregate at 1600kg/m3 at RM 40.99/tonne. 3. Coarse aggregate at 1400kg/m3 at RM 41.69/tonne. 4. Shrinkage, consolidation and wastage 50%.

Cost of Labour:

1. Labour gang 5 numbers, 3 skilled concretor and 2 semiskilled concretor, 8 hours/day. 2.Skilled concretor RM75.20/day, semiskilled concretor RM 61.80/day. 3. Additional labour placing concrete into beams 0.60hr/m3, RM 52.50/day.4.Additional labour for working around reinforcement, 0.55hr/m3, RM52.50/day. 5.One mixer output at 1.2 m3 per hour, RM400.00/month including fuel. 6.One concrete vibrator output at 1.2 m3 per hour, RM400.00/month including fuel.

Allow 15% of profit including overhead.

Estimate Grade 30 Concrete Cost for Column

Step 1 Material Cost

Use 1:2:3 Concrete Design (RM)

Ordinary Portland Cement at 1420kg/m3 at RM 16.96/50kg :(1420/50)xRM16.96 481.66/m3

Fine Aggregate at 1600kg/m3 at RM40.99/tonne: (1600/1000)xRM40.99x2m 131.17/2m3

Course Aggregate at 1400kg/m3 at RM41.69/tonne: (1400/1000)xRM41.69x3m3 175.10/3m 3 Gross Cost per 6m3 787.93/6m 3

Page 33: Estimating calculation

Add 50% Shrinkage, consolidation and wastage 787.93x50% 393.97/6m 3 1181.9/6m 3

1m3 of concrete mix: (1181.9/6) 196.98/m 3

Step 2 Mix-Plant

One mixer at 1.2m3 per hour: 1/1.2x[400/(30x8)] 1.39/m 3

Step 2 Mix-Labour

3 Skilled Concretor: (75.20/8)x3x0.84 23.69/m3

2 Semi-skilled Concretor: (61.80/8)x2x0.84 12.99/m 3 Total Labour Cost 36.68/m 3

Step 3 Place- Labour and Vibrator

Additional labour for placing concrete into columns:(52.50/8)x0.60 3.94/m3

Additional labour for working around reinforcement: (52.50/8)x0.55 3.61/m3

Cost of concrete vibrator: One mixer at 1.2m3 per hour: 1/1.2x[400/(30x8) 1.39/m 3 Total Labour and Vibrator Cost 8.94/m 3

Step 4 Summary for Unit Rate

RM196.98(Material) +RM1.36(Plant)+RM36.68(Labour) __________ +RM8.94(Labour and Vibrator)+ RM36.59 (15% profit &overhead) RM280.55/m 3

Step 5 Total Cost

3.00m3xRM280.55/m3 = RM841.65

Estimate Formwork Cost for Beams and Columns

Formwork Data

1. 1219mmx2438mmx12mm plywood at RM59.36/piece, allowance for cutting 15%.2. Allow 4 use for timber formwork. 3. Waste on each use 10%.4. Nails, bolts RM1.10/m2

Page 34: Estimating calculation

5. 1 skilled formwork carpenter at RM 89.10/day6. 1 general labour at RM52.50/day 7. The workers take 24 hours to erect and fixing all beam formwork and 9 hours for all column formwork. 8. Allow 15% profit including overhead.

Estimate Formwork Cost for Beams

Step 1 Material Cost

(RM)3m2 of 12mm plywood at RM59.36 59.36/3 9.79/m2

Allowance for cutting waste 15% 19.79x15% 2.97/m 2 Cost of timber 12.76/m 2

Page 35: Estimating calculation

Allow 4 uses of timber formwork 12.76/4 3.19/m2

Waste on each use, 10% 5.69x10% 0.57/m2

Nails,bolts and mould oil 1.10x.1.06(GST) 1.17/m 2 4.93/m 2

Step 2 Labour Cost

24 hours are required to fix and dismantle 63m2 formwork:24/63=0.38hr/m2

(RM)Skilled Formwork Carpenter: (89.10/8)x0.38 4.23/m2

General Labour: (52.50/8)x0.38 2.49/m 2 Total Labour Cost 6.72/m 2

Step 3 Summary for Unit Rate (Labour+Material) RM4.93/m2(Material)+RM6.72/m2(Labour)+ ___________RM1.75(15%Profit&Overhead) RM13.40/m 2

Step 4 Total Cost _________63m2 xRM13.40/m2 RM844.20

Estimate Formwork Cost for Columns

Step 1 Material Cost

(RM)3m2 of 12mm plywood at RM59.36 59.36/3 9.79/m2

Allowance for cutting waste 15% 19.79x15% 2.97/m 2 Cost of timber 12.76/m 2 Allow 4 uses of timber formwork 12.76/4 3.19/m2

Waste on each use, 10% 5.69x10% 0.57/m2

Nails,bolts and mould oil 1.10x.1.06(GST) 1.17/m 2

Page 36: Estimating calculation

4.93/m 2 Step 2 Labour Cost

24 hours are required to fix and dismantle 63m2 formwork:24/63=0.38hr/m2

(RM)Skilled Formwork Carpenter: (89.10/8)x0.38 4.23/m2

General Labour: (52.50/8)x0.38 2.49/m 2 Total Labour Cost 6.72/m 2

Step 3 Summary for Unit Rate (Labour+Material) RM4.93/m2(Material)+RM6.72/m2(Labour)+ ___________RM1.75(15%Profit&Overhead) RM13.40/m 2

Step 4 Total Cost 27m2 xRM13.40/m2 = RM361.80

Estimate cost for Mild Steel Reinforcement Bar

A) 8mm diameter in column as links B) 8mm diameter in beam as stirrups C) 10mm diameter in beam as stirrups

Material Cost

1. 8mm diameter and 10mm diameter reinforcement bar delivered to site is RM1000.00/tonne and RM2102.33/tonne respectively. 2. Allow for labour unloading and stacking RM5.00/tonne. 3. Allow 0.66kg tie wire for each 100kg of reinforcement at RM4/kg (Excluding GST)4. Allow spacer of RM4.00 per tonne of rebar.

Page 37: Estimating calculation

5. Allow waste 7%. 6. Allow for rolling margin RM22/tonne.

Labour Cost

1. 1 skilled barbender at RM83.60/day, 1 semiskilled barbender at RM62.50/day, 8 hour/day. 2. Allow 10% idling time. 3. Time analysis at 100kg of reinforcement bar

Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutes

Allow 15% profit including overhead.

Estimate cost for High Tensile Steel Reinforcement Bar

A) 12mm diameter in column.B) 16mm diameter in column.C) 10mm diameter in beam.D) 12mm diameter in beam.

Material Cost

1. 12mm and 10mm diameter at RM1996.33/tonne, 16mm diameter at RM1925.67/tonne. 7. Allow for labour unloading and stacking RM5.00/tonne. 8. Allow 0.66kg tie wire for each 100kg of reinforcement at RM4/kg (Excluding GST). 9. Allow spacer of RM4.00 per tonne of rebar.

Page 38: Estimating calculation

10. Allow waste 7%. 11. Allow for rolling margin RM22/tonne.

Labour Cost

1. 1 skilled barbender at RM83.60/day, 1 semiskilled barbender at RM62.50/day, 8 hour/day. 4. Allow 10% idling time. 5. Time analysis at 100kg of reinforcement bar

Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutes

Allow 15% profit including overhead.

Estimate Cost of 8mm Diameter Mild Steel Reinforcement in Column as Links

Step 1 Material Cost

8mm diameter mild steel reinforcement bar delivered to site: RM1000.00/tonneAdd: Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM985.40/tonne =RM68.98/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 39: Estimating calculation

Cost of Material=RM1000.00/tonne+RM5.00tonne+RM68.98/tonne+RM26.40/tonne+RM22.00/tonne+RM27.98/tonne=RM1150.36/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate Summary

RM1150.36/tonne(Material)+ RM418.50/tonne (Labour)+RM235.33/tonne(15% Profit and Overhead)=RM1804.19/tonne

Step 5 Total Cost

(76/1000)xRM1804.19/tonne= RM137.12

Estimate Cost of 8mm Diameter Mild Steel Reinforcement in Beam as Stirrups

Step 1 Material Cost

8mm diameter mild steel reinforcement bar delivered to site: RM1000.00/tonneAdd: Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM985.40/tonne =RM68.98/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 40: Estimating calculation

Cost of Material=RM1000.00/tonne+RM5.00tonne+RM68.98/tonne+RM26.40/tonne+RM22.00/tonne+RM27.98/tonne=RM1150.36/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate SummaryRM1150.36/tonne(Material)+ RM418.50/tonne (Labour)+RM235.33/tonne(15% Profit and Overhead)=RM1804.19/tonne

Step 5 Total Cost

(73/1000)xRM1804.19/tonne=RM131.71

Estimate Cost of 10mm Diameter Mild Steel Reinforcement in Beam as Stirrups

Step 1 Material Cost

10mm diameter mild steel reinforcement bar delivered to site: RM2102.33/tonneAdd: :Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM2102.33/tonne =RM147.16/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 41: Estimating calculation

Cost of Material=RM2102.33/tonne+RM5.00/tonne+RM147.16/tonne+RM26.40/tonne+RM22.00/tonne+RM27.98/tonne= RM2330.87/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate SummaryRM2330.87/tonne (Material)+ RM418.50/tonne (Labour)+RM412.41(15%Profit&Overhead)= RM3161.78/tonne

Step 5 Total Cost(100/1000)xRM3161.78/tonne= RM316.18

Estimate Cost of 12mm Diameter High Tensile Steel Reinforcement in Column

Step 1 Material Cost

12mm diameter mild steel reinforcement bar delivered to site: RM1996.33/tonneAdd: Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM1996.33/tonne =RM139.74/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 42: Estimating calculation

Cost of Material=RM1996.33/tonne+RM5/tonne+RM139.74/tonne+RM26.40/tonne+RM22/tonne+RM27.98/tonne= RM2217.45/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate SummaryRM2217.45/tonne (Material)+ RM418.50/tonne (Labour)+RM395.39(15%Profit&Overhead)=RM3031.34/tonne

Step 5 Total Cost(208/1000)xRM3031.34/tonne=RM630.52

Estimate Cost of 16mm Diameter High Tensile Steel Reinforcement in Column

Step 1 Material Cost

16mm diameter mild steel reinforcement bar delivered to site: RM1925.67/tonneAdd: :Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM1925.67/tonne =RM134.80/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 43: Estimating calculation

Cost of Material=RM1925.67/tonne+RM5/tonne+RM134.80/tonne+RM26.40/tonne+RM22/tonne+RM27.98/tonne=RM2141.85/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate SummaryRM2141.85/tonne (Material)+ RM418.50/tonne (Labour)+RM384.00/tonne(15%Profit&Overhead)=RM2944.35/tonne

Step 5 Total Cost(222/1000)xRM2944.35/tonne=RM653.65

Estimate Cost of 10mm Diameter High Tensile Steel Reinforcement in Beam

Step 1 Material Cost

12mm diameter mild steel reinforcement bar delivered to site: RM1996.33/tonneAdd: Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM1996.33/tonne =RM139.74/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 44: Estimating calculation

Cost of Material=RM1996.33/tonne+RM5/tonne+RM139.74/tonne+RM26.40/tonne+RM22/tonne+RM27.98/tonne= RM2217.45/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate SummaryRM2217.45/tonne (Material)+ RM418.50/tonne (Labour)+RM395.39(51%Profit&Overhead)=RM3031.34/tonne

Step 5 Total Cost(250/1000)xRM3031.34/tonne =RM757.84

Estimate Cost of 12mm Diameter High Tensile Steel Reinforcement in Beam

Step 1 Material Cost

12mm diameter mild steel reinforcement bar delivered to site: RM1996.33/tonneAdd: Labour unloading and stacking RM5/tonneAdd: 7% wastage on rebar: 7%x RM1996.33/tonne =RM139.74/tonne Add: Tie wire (0.66/100)x1000x[4x1.06(GST)] = RM27.98/tonne Add: Rolling Margin: RM22/tonneAdd: Concrete Spacer: RM4/tonne

Page 45: Estimating calculation

Cost of Material=RM1996.33/tonne+RM5/tonne+RM139.74/tonne+RM26.40/tonne+RM22/tonne+RM27.98/tonne= RM2217.45/tonne

Step 2 Labour Cost

Skilled Barbender Hourly Rate: 83.60/8=RM10.45/hourSemiskilled Barbender Hourly Rate: 62.50/8=RM7.81/hour Gross total of Labour Rate: RM10.45/hour+RM7.81/hour=RM18.26/hour10% of Idling time: RM1.83/hour Cost of Labour RM18.26/hour+RM1.83/hour=RM20.09/hour

Step 3 Time Analysis per 100kg Select 28 minutesCut 32 minutes

Bend 35 minutesFix 23 minutes

Hoist Twice 7 minutesTotal Time 125 minutes

Cost of labour: 125/60xRM20.09=RM41.85/100kg 41.85/100x1000=RM418.50/tonne

Step 4 Unit Rate SummaryRM2217.45/tonne (Material)+ RM418.50/tonne (Labour)+RM395.39(51%Profit&Overhead)=RM3031.34/tonne

Step 5 Total Cost(270/1000)xRM3031.34/tonne =RM818.46

ELEMENT NO. 3 – ROOF CONSTRUCTION AND FINISHESROOF FRAMEB4 (3)/1/A Roof Beam & B4 (3)/1/B Roof Trusses and Frame & B4 (3)/1/C Purlin

To supply, fix and connect sawn Group A treated merbau hardwood kiln dried for

- 125mm x 250mm roof beam with total quantity 161m,

- 100mm x 200mm roof trusses and frame with total quantity 238m, and

- 90mm x 75mm purlin with total quantity 225m.

Estimating Data:

Page 46: Estimating calculation

Material Data

- 1m3 of timber including GST (6%), load and stacked on site = RM3778.00/m3.- Allow 10% cutting wastage.- Nails required for general construction work excluding GST (6%) = 1.5kg/m3 at

RM5.00/kg

Labour Data- 1 gang of carpenter consists of 2 carpenters (joinery) and 2 unskilled labourers.- Carpenter (joinery) and unskilled labour rates are RM96.50/day and RM68.90 /day

respectively. (8 hours per day)

Output Data- Time required for 1 gang of carpenter to cut to length, set out and fix 1m3 of timber in

roof = average time of 18 hours.

Other Cost- Allow 3% of material cost and labour cost for small tools.

*Scaffolding - unnecessary (2.5m high can easily reach using stool or ladder)

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.

Estimate cost for B4 (3)/1/A Roof BeamCalculation:

No Description / Subdescription Formula = Total Unit

1 Material CostCost / m3

Timber per m3 =RM3778 = 3778.00 RM/m310% Cutting wastage =RM3778 X 0.10 = 377.80 RM/m3Allow nails at 1.5kg/m3 at RM5.00/kg

=1.5 x 5.00 x 1.06 = 7.95 RM/m3

Total material cost = 4163.75 RM/m3

Page 47: Estimating calculation

2 Labour Costa Hourly rate

2 x Carpenter (Joinery) at RM96.50/day

=2 x 96.50 /8 = 24.13 RM/hour

2 x Labourer at RM68.90/day =2 x 68.90 /8 = 17.23 RM/hourTotal hourly rate = 41.36 RM/hour

b Time required 1m3 requires 18 hours to cut, set and fix

c Labour costTime required to set 1m3 x hourly rate

=18 x 41.36 = 744.48 RM/m3

3 Total Cost including profit and overheada Total cost /m3

Material cost /m3 + labour cost /m3

=4163.75 + 744.48 = 4908.23 RM/m3

b Total quantity125mm x 250mm x 161m =(0.125 x 0.25 x 161) = 5.03 m3

c Total costtotal cost = qty (m3) x rate (RM/m3)

=5.03 x 4908.23 = 24688.40 RM

add small tools cost =24688.40 x 0.03 = 740.65 RMadd profit & overhead =24688.40 x 0.15 = 3703.26 RM

TOTAL = 29132.31 RM

4 Unit CostTotal cost (RM) / total qty (m) =29132.31/161 = 180.94 RM/m

Estimate cost for B4 (3)/1/B Roof Trusses and FrameCalculation:

No Description / Subdescription Formula = Total Unit

1 Material CostCost / m3

Timber per m3 =RM3778 = 3778.00 RM/m310% Cutting wastage =RM3778 X 0.10 = 377.80 RM/m3Allow nails at 1.5kg/m3 at RM5.00/kg

=1.5 x 5.00 x 1.06 = 7.95 RM/m3

Total material cost = 4163.75 RM/m3

Page 48: Estimating calculation

2 Labour Costa Hourly rate

2 x Carpenter (Joinery) at RM96.50/day

=2 x 96.50 /8 = 24.13 RM/hour

2 x Labourer at RM68.90/day =2 x 68.90 /8 = 17.23 RM/hourTotal hourly rate = 41.36 RM/hour

b Time required 1m3 requires 18 hours to cut, set and fix

c Labour costTime required to set 1m3 x hourly rate

=18 x 41.36 = 744.48 RM/m3

3 Total Cost including profit and overheada Total cost /m3

Material cost /m3 + labour cost /m3

=4163.75 + 744.48 = 4908.23 RM/m3

b Total quantity100mm x 200mm x 238m =(0.10 x 0.20 x 238) = 4.76 m3

c Total costtotal cost = qty (m3) x rate (RM/m3)

=4.76 x 4908.23 = 23363.17 RM

add small tools cost =23363.17 x 0.03 = 700.90 RMadd profit & overhead =23363.17 x 0.15 = 3504.48 RM

TOTAL = 27568.55 RM

4 Unit CostTotal cost (RM) / total qty (m) =27568.55/238 = 115.83 RM/m

Estimate cost for B4 (3)/1/C Purlin Calculation:

No Description / Subdescription Formula = Total Unit

1 Material CostCost / m3

Timber per m3 =RM3778 = 3778.00 RM/m310% Cutting wastage =RM3778 X 0.10 = 377.80 RM/m3Allow nails at 1.5kg/m3 at RM5.00/kg

=1.5 x 5.00 x 1.06 = 7.95 RM/m3

Total material cost = 4163.75 RM/m3

Page 49: Estimating calculation

2 Labour Costa Hourly rate

2 x Carpenter (Joinery) at RM96.50/day

=2 x 96.50 /8 = 24.13 RM/hour

2 x Labourer at RM68.90/day =2 x 68.90 /8 = 17.23 RM/hourTotal hourly rate = 41.36 RM/hour

b Time required 1m3 requires 18 hours to cut, set and fix

c Labour costTime required to set 1m3 x hourly rate

=18 x 41.36 = 744.48 RM/m3

3 Total Cost including profit and overheada Total cost /m3

Material cost /m3 + labour cost /m3

=4163.75 + 744.48 = 4908.23 RM/m3

b Total quantity90mm x 75mm x 225m =(0.090 x 0.075 x 225) = 1.52 m3

c Total costtotal cost = qty (m3) x rate (RM/m3)

=1.52 x 4908.23 = 7460.51 RM

add small tools cost =7460.51 x 0.03 = 223.82 RMadd profit & overhead =7460.51 x 0.15 = 1119.08 RM

TOTAL = 8803.41 RM

4 Unit CostTotal cost (RM) / total qty (m) =8803.41/225 = 39.13 RM/m

B4 (3)/1/D Fascia Board & B4 (3)/1/E Battens

To supply, fix and connect

- wrot pressure treated merbau for 150mm x 25mm fascia board with total quantity

46m.

- sawn Group B treated merbau for 38mm x 75mm battens with total quantity 672m.

Estimating Data:

Material Data

Page 50: Estimating calculation

- 1m3 of timber - in wrot pressure including GST (6%), load and stacked on site = RM3143.00/m3.- in sawn pressure including GST (6%), load and stacked on site =

RM3778.00/m3.- Allow 5% cutting wastage.- Nails required for general construction work excluding GST (6%) = 1.5kg/m3 at

RM5.00/kg

Labour Data- 1 gang of carpenter consists of 2 carpenters (joinery) and 2 unskilled labourers.- Carpenter (joinery) and unskilled labour rates are RM96.50/day and RM68.90 /day

respectively. (8 hours per day)

Output Data- Time required for 1 gang of carpenter to cut to length, set out and fix 1m3 of timber in

roof = average time of 18 hours

Other Cost- Allow 3% of material cost and labour cost for small tools.

*Scaffolding - unnecessary (2.5m high can easily reach using stool or ladder)

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.

Estimate cost for B4 (3)/1/D Fascia BoardCalculation:

No Description / Subdescription Formula = Total Unit

1 Material CostCost / m3

Timber per m3 =RM3143 = 3143.00 RM/m35% Cutting wastage =RM3143 x 0.05 = 157.15 RM/m3

- Allow nails at 1.5kg/m3 at RM5.00/kg

=1.5 x 5.00 x 1.06 = 7.95 RM/m3

Page 51: Estimating calculation

Total material cost = 3308.10 RM/m3

2 Labour Costa Hourly rate

2 x Carpenter (Joinery) at RM96.50/day

=2 x 96.50 /8 = 24.13 RM/hour

2 x Labourer at RM68.90/day =2 x 68.90 /8 = 17.23 RM/hourTotal hourly rate = 41.36 RM/hour

b Time required 1m3 requires 18 hours to cut, set and fix

c Labour costTime required to set 1m3 x hourly rate

=18 x 41.36 = 744.48 RM/m3

3 Total Cost including profit and overheada Total cost /m3

Material cost /m3 + labour cost /m3

=3308.10 + 744.48 = 4052.58 RM/m3

b Total quantity150mm x 25mm x 46m =(0.15 x 0.025 x 46) = 0.17 m3

c Total costtotal cost = qty (m3) x rate (RM/m3)

=0.17 x 4052.58 = 688.94 RM

add small tools cost =688.94 x 0.03 = 20.67 RMadd profit & overhead =688.94 x 0.15 = 103.34 RM

TOTAL = 812.95 RM

4 Unit CostTotal cost (RM) / total qty (m) =812.95/46 = 17.67 RM/m

Estimate cost for B4 (3)/1/E BattensCalculation:

No Description / Subdescription Formula = Total Unit

1 Material CostCost / m3

Timber per m3 =RM3778 = 3778.00 RM/m35% Cutting wastage =RM3778 x 0.05 = 188.90 RM/m3Allow nails at 1.5kg/m3 at RM5.00/kg

=1.5 x 5.00 x 1.06 = 7.95 RM/m3

Total material cost = 3974.85 RM/m3

Page 52: Estimating calculation

2 Labour Costa Hourly rate

2 x Carpenter (Joinery) at RM96.50/day

=2 x 96.50 /8 = 24.13 RM/hour

2 x Labourer at RM68.90/day =2 x 68.90 /8 = 17.23 RM/hourTotal hourly rate = 41.36 RM/hour

b Time required 1m3 requires 18 hours to cut, set and fix

c Labour costTime required to set 1m3 x hourly rate

=18 x 41.36 = 744.48 RM/m3

3 Total Cost including profit and overheada Total cost /m3

Material cost /m3 + labour cost /m3

=3974.85 + 744.48 = 4719.33 RM/m3

b Total quantity38mm x 75mm x 672m =(0.038 x 0.075 x 672) = 1.92 m3

c Total costtotal cost = qty (m3) x rate (RM/m3)

=1.92 x 4719.33 = 9061.11 RM

add small tools cost =9061.11 x 0.03 = 271.83 RMadd profit & overhead =9061.11 x 0.15 = 1359.17 RM

TOTAL = 10692.11 RM

4 Unit CostTotal cost (RM) / total qty (m) =10692.11/672 = 15.91 RM/m

RAINWATER GOODSB4 (3)/1/F Coloured Interlocking Concrete Roof Tiles & B4 (3)/1/G Coloured Ridge Tiles & B4 (3)/1/H Eaves Caps

To supply and lay - 380mm x 230mm single lap interlocking concrete roof tiles fixed with galvanized steel

nails to every tiles at every alternative course to 185m2 roofing surface.- 200mm x 200mm coloured ridge tiles fixed with galvanized steel nails to every tiles at

every alternative course to 14m roofing.

Page 53: Estimating calculation

- Eaves cap fixed with galvanized steel nails to every tiles at every alternative course to 30m roofing.

Tiles or caps are to be over lapped at least 70mm for bottom and top. Moreover, for interlocking roof tiles are also required to be over lapped at least 25mm for sides. No underlay or insulation required.

Estimating Data:

Material Data

- We proposed to use 420mm x 330mm interlocking roof tiles including delivery and GST (6%) = RM2.24/piece to replace 380mm x 230mm roof tiles

- We proposed to use 330mm x 250mm coloured ridge tiles including delivery but excluding GST (6%) = RM12.74/piece to replace 200mm x 200mm ridge tiles

- RM15.80 for 1 No. of eaves cap including delivery and GST (6%).- Wastage for broken tiles = 3%- Nails excluding GST (6%) = RM4.00/100 Nos - Wastage for nails = 20%

Labour Data- 1 gang of roofer consists of 2 roofers and 2 unskilled labourers.- Roofer and unskilled labour rates are RM88.20/day and RM 67.00/day respectively.

(8 hours per day)

Output Data- Time required to unload 1000 pieces of tiles = 15 minutes- Time required to lay 1000 pieces of tiles = 6 hours- Time required to fix every 10m of eaves cap = 1 hour

Tools Cost- Allow 3% of the material cost for small tools (material cost includes such element,

nails and wastages).*Scaffolding - unnecessary (2.5m high can easily reach using stool or ladder)

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.Estimate cost for B4 (3)/1/F Coloured Interlocking Concrete Roof TilesCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m2

Cost per tile =2.24 = 2.24 RM/NoCost per nail =4.00/100 x 1.06 = 0.04 RM/No

Page 54: Estimating calculation

No. of tiles/m2 =1 /[(0.42-0.07) x (0.33-0.025)] = 10 No/m2No. of nails/m2 = half of tiles required

=10/2 = 5 No/m2

Cost of tiles/m2 incl. wastage

=RM2.24 x 10 x 1.03 = 23.07 RM/m2

Cost of nails/m2 incl. wastage

=RM0.04 x 5 x 1.20 = 0.24 RM/m2

23.31 RM/m2b Total material cost

Material cost/m2 x Qty required=23.31 x 185m2 = 4312.35 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysisUnload 1000 pieces of tiles 15 / 60 (minutes) = 0.25 hourLay 1000 pieces of tiles = 6 hours

Total time required to fix 1000 tiles = 6.25 hours

Time required to lay 185m2 of tiles

=6.25/1000 x 10 x185 = 11.56 hours

Labour cost to lay 185m2 =11.56 x 38.80 = 448.53 RM

No Description / Subdescription Formula = Total Unit

3 Tools CostAllow 3% of material cost for small tools

=4312.35 x 0.03 = 129.37 RM

Total tools cost = 129.37 RM

4 Total cost including profit and overhead

Page 55: Estimating calculation

material + labour + tools =4312.35 + 448.53 + 129.37 = 4890.25 RMadd profit & overhead =4890.25 x 0.15 = 733.54 RM

TOTAL = 5623.79 RM

5 Unit costTotal cost(RM)/total quantity(m2)

=5623.79/185 = 30.40 RM/m2

Estimate cost for B4 (3)/1/G Coloured Ridge TilesCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Cost per tile =12.74 x 1.06 = 13.50 RM/NoCost per nail =4.00/100 x 1.06 = 0.04 RM/No

Page 56: Estimating calculation

No. of tiles/m =1/(0.33-0.07) = 4 No/mNo. of nails/m = half of tiles required

=4/2 = 2 No/m

Cost of tiles/m incl. wastage =RM13.50 x 4 x 1.03 = 55.62 RM/mCost of nails/m incl. wastage =RM0.04 x 2 x 1.20 = 0.10 RM/m

55.72 RM/mb TOTAL MATERIAL COST

Material cost/m x Qty required= 55.72 x 14m = 780.08 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysisUnload 1000 pieces of tiles 15 / 60 (minutes) = 0.25 hourLay 1000 pieces of tiles = 6 hours

Total time required to fix 1000 tiles = 6.25 hours

Time required to lay 14m of tiles

=6.25/1000 x 4 x 14 = 0.35 hour

Labour cost to lay 14m =0.35 x 38.80 = 13.58 RM

3 Tools CostAllow 3% of material cost for small tools

=780.08 x 0.03 = 23.40 RM

Total tools cost = 23.40 RM

No Description / Subdescription Formula = Total Unit

4 Total cost including profit and overheadmaterial + labour + tools =780.08 + 13.58 + 23.40 = 817.06 RMadd profit & overhead =817.06 x 0.15 = 122.56 RM

TOTAL = 939.62 RM

5 Unit cost

Page 57: Estimating calculation

Total cost(RM)/total quantity(m)= 939.62/14 = 67.12 RM/m

Estimate cost for B4 (3)/1/H Eaves CapsCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Cost per cap =15.80 = 15.80 RM/No

Page 58: Estimating calculation

Cost per nail =4.00/100 x 1.06 = 0.04 RM/No

No. of caps/m =1/(0.33-0.07) = 4 No/mNo. of nails/m = half of tiles required

=4/2 = 2 No/m

Cost of caps/m incl. wastage =RM15.80 x 4 x 1.03 = 65.10 RM/mCost of nails/m incl. wastage =RM0.04 x 2 x 1.20 = 0.10 RM/m

65.20 RM/mb TOTAL MATERIAL COST

Material cost/m x Qty required=65.20 x 30m = 1956.00 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 / 8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysisEvery 10m of eaves cap required 1 hour to fix

Time required to fix 30m eaves cap

=30/10 = 3.00 RM/m

Labour cost to fix 30m =3.00 x 38.80 = 116.40 RM

3 Tools CostAllow 3% of material cost for small tools

=1956.00 x 0.03 = 58.68 RM

Total tools cost = 58.68 RM

No Description / Subdescription Formula = Total Unit

4 Total cost including profit and overheadmaterial + labour + tools =1956.00 + 116.40 + 58.68 = 2131.08 RMadd profit & overhead =2131.08 x 0.15 = 319.66 RM

TOTAL = 2450.74 RM

Page 59: Estimating calculation

5 Unit costTotal cost(RM)/total quantity(m)

=2450.74/30 = 81.69 RM/m

B4 (3)/1/I Hip Capping Tiles

To supply and fix matching hip capping tiles bedded and jointed in cement and sand (1:3) mortar as described including cut and splayed ends, mitres and intersections with total quantity 40m. Tiles or caps are to be over lapped at least 70mm for bottom and top.

Estimating Data:

Page 60: Estimating calculation

Material Data

- 330mm x 250mm Hip capping tiles at RM12.74/piece including delivery but excluding GST (6%)

- Ordinary Portland Cement at 1420kg/m3 at RM16.96/50kg including delivery and GST (6%)

- Fine mining sand at 1600kg/m3 at RM40.99/tonne including delivery and GST (6%) - Allow 10% of cutting and mitering wastage - Wastage for broken tiles = 3%- Wastage and shrinkage for mortar = 40%- Assumed 19mm thick for cement mortar

Labour Data- 1 gang of roofer consists of 2 roofers and 2 unskilled labourers.- Roofer and unskilled labour rates are RM88.20/day and RM 67.00/day respectively.

(8 hours per day)

Output Data- Time required to unload 1000 pieces of tiles = 15 minutes- Time required to lay 1000 pieces of tiles = 6 hours

Tools Cost- Allow 3% of the material cost for small tools (material cost includes hip cap tiles,

mortar and wastages).

*Scaffolding - unnecessary (2.5m high can easily reach using stool or ladder)

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.

Estimate cost for B4 (3)/1/I Hip Capping TilesCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost of tiles / m

Page 61: Estimating calculation

Cost per tile =12.74 x 1.06 = 13.50 RM/NoNo. of tiles/m =1/(0.33-0.07) = 4 No/mCost of tiles/m incl. wastage =13.50 x 4 x 1.03 = 55.62 RM/m

b Cement mortar mix (1:3) per mOPC at 1420kg/m3 at RM16.96/50kg

=(1420/50) x 16.96 = 491.66 RM/m3

Fine mining sand at 1600kg/m3 at RM40.99/tonne

=(1600/1000) x 40.99 x 3 = 196.75 RM/3m3

Gross Total = 688.41 RM/4m3

Add 40% shrinkage and wastage

=688.41 x 0.40 = 275.36 RM/4m3

Net total for 4m3 = 963.77 RM/4m3

Divide by parts of mix (1:3) =963.77 / 4 = 240.94 RM/m3

Cost per m =240.94 x 0.25 x 0.019 = 1.14 RM/m

c Total material cost per m =55.62 + 1.14 = 56.76 RM/m

d TOTAL MATERIAL COSTMaterial cost/m x Qty required =56.76 x 40m = 2270.40 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysisUnload 1000 pieces of tiles 15 / 60 (minutes) = 0.25 hourLay 1000 pieces of tiles = 6 hours

Total time required to fix 1000 tiles = 6.25 hours

Time required to lay 40m of tiles

=6.25/1000 x 4 x 40 = 1.00 hour

Labour cost to lay 40m =1.00 x 38.80 = 38.80 RM

3 Tools CostAllow 3% of material cost for small tools

=2270.40 x 0.03 = 68.11 RM

Total tools cost = 68.11 RM

Page 62: Estimating calculation

4 Total cost including profit and overheadmaterial + labour + tools =2270.40 + 38.80 + 68.11 = 2377.31 RMadd profit & overhead =2377.31 x 0.15 = 356.60 RM

TOTAL = 2733.91 RM

5 Unit costTotal cost(RM)/total quantity(m)

=2733.91/40 = 68.35 RM/m

B4 (3)/1/J Half Round Gutter & B4 (3)/1/K Flashing & B4 (3)/1/L Flashing as Valley

To supply and fix - 125mm diameter Colourbond “Blue scope” half round gutter with total quantity 28m.- Approved Colourbond flashing with total quantity 56m.- Approved Colourbond flashing as valley with total quantity 25m.

Page 63: Estimating calculation

Estimating Data:

Material Data

- We proposed to use 125mm diameter Arensi-Marley F370 half round gutter including delivery but excluding GST (6%) = RM62.10/4m to replace Colourbond “Blue scope” half round gutter.

- 1 piece of 180mm girth flashing including delivery and GST (6%) = RM14.00/8ft- 1 piece of 450mm girth flashing including delivery and GST (6%) = RM30.00/8ft- Wastage for each element = 3%

Labour Data- 1 gang of roofer consists of 2 roofers and 2 unskilled labourers.- Roofer and unskilled labour rates are RM88.20/day and RM 67.00/day respectively.

(8 hours per day)

Output Data- Time required to fix every 8 meters of half round gutter = 1 hour- Time required to fix every 8 meters of flashing = 1 hour

Tools Cost- Allow 3% of the material cost for small tools and nails (material cost includes such

element and wastage).

*Scaffolding - unnecessary (2.5m high can easily reach using stool or ladder)

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.

Estimate cost for B4 (3)/1/J Half Round GutterCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Cost of gutter at RM62.10 per 4m

Page 64: Estimating calculation

Cost of gutter per m =(62.10/4) x 1.06 = 16.46 RM/m

Cost of 3% wastage =RM16.46 x 0.03 = 0.49 RM/m16.95 RM/m

b TOTAL MATERIAL COSTMaterial cost/m x Qty required

= 16.95 x 28m = 474.60 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysis1 hour for every 8m of half round gutterTime required to fix 28m gutter

=28/8 = 3.50 hours

Labour cost to fix 28m =3.50 x 38.80 = 135.80 RM

3 Tools CostAllow 3% of material cost for small tools and nails

=474.60 x 0.03 = 14.24 RM

Total tools cost = 14.24 RM

4 Total cost including profit and overheadmaterial + labour + tools =474.60 + 135.80 + 14.24 = 624.64 RMadd profit & overhead =624.64 x 0.15 = 93.70 RM

TOTAL = 718.34 RM

5 Unit costTotal cost(RM)/total quantity(m)

=718.34/28 = 25.66 RM/m

Estimate cost for B4 (3)/1/K FlashingCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Page 65: Estimating calculation

Cost of flashing at RM14.00 per ft 1 ft = 0.3048m

Cost of flashing per m =14.00/0.3048 = 45.93 RM/m

Cost of 3% wastage =RM45.93 x 0.03 = 1.38 RM/m47.31 RM/m

b TOTAL MATERIAL COSTMaterial cost/m x Qty required

= 47.31 x 56m = 2649.36 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysis1 hour for every 8m of flashingTime required to fix 56m of flashing

=56/8 = 7.00 hours

Labour cost to fix 56m =7.00 x 38.80 = 271.60 RM

3 Tools CostAllow 3% of material cost for small tools and nails

=2649.36 x 0.03 = 79.48 RM

Total tools cost = 79.48 RM

4 Total cost including profit and overheadmaterial + labour + tools =2649.36 + 271.60 + 79.48 = 3000.44 RMadd profit & overhead =3000.44 x 0.15 = 450.07 RM

TOTAL = 3450.51 RM

5 Unit costTotal cost(RM)/total quantity(m)

=3450.51/56 = 61.62 RM/m

Estimate cost for B4 (3)/1/L Flashing as ValleyCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Cost

Page 66: Estimating calculation

a Cost / mCost of flashing at RM30.00 per ft

1 ft = 0.3048mCost of flashing per m =30.00/0.3048 = 98.43 RM/m

Cost of 3% wastage =RM98.43 x 0.03 = 2.95 RM/m101.38 RM/m

b TOTAL MATERIAL COSTMaterial cost/m x Qty required

= 101.38 x 25m = 2534.50 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysis1 hour for every 8m of flashingTime required to fix 25m of flashing

=25/8 = 3.13 hours

Labour cost to fix 25m =3.13 x 38.80 = 121.44 RM

3 Tools CostAllow 3% of material cost for small tools and nails

=2534.50 x 0.03 = 76.04 RM

Total tools cost = 76.04 RM

4 Total cost including profit and overheadmaterial + labour + tools =2534.50 + 121.44 + 76.04 = 2731.98 RMadd profit & overhead =2731.98 x 0.15 = 409.80 RM

TOTAL = 3141.78 RM

5 Unit costTotal cost(RM)/total quantity(m)

=3141.78/25 = 125.67 RM/m

B4 (3)/2/A Rectangular Pipe to Walls and Columns & B4 (3)/2/B Rectangular Pipe embedded in Concrete

To supply and fix approved solvent welded - 150mm x 75mm unplasticised UPVC rectangular pipe to walls and columns with total

quantity 25m

Page 67: Estimating calculation

- 150mm x 75mm unplasticised UPVC rectangular pipe embedded in concrete with total quantity 40m

from Arensi-Marly to B.S. 4576: PT 1989 including jointing in accordance with the manufacturer’s recommendation including all bends, tees, connectors, sockets, collars, cleaning eyes, brackets, holder bats, hangers, pipe clips at every 1500mm intervals.

Estimating Data:

Material Data

- RM61.90/4m for unplasticised UPVC rectangular pipe excluding GST (6%)- Wastage for pipes = 3%- Allow 10% for all necessary jointing elements in accordance with the manufacturer’s

recommendation.

Labour Data- 1 gang of roofer consists of 2 roofers and 2 unskilled labourers.- Roofer and unskilled labour rates are RM88.20/day and RM 67.00/day respectively.

(8 hours per day)

Output Data- Time required to fix and joint every 8m of pipes = 1hour

Tools Cost- Allow 3% of the material cost for small tools (material cost includes such element,

jointing elements and wastage).

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.

Estimate cost for B4 (3)/2/A Rectangular Pipe to Walls and ColumnsCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Page 68: Estimating calculation

Cost of pipe at RM61.90 per 4m Cost of pipe per m =(61.90/4) x 1.06 = 16.40 RM/m

Cost of 3% wastage =RM16.40 x 0.03 = 0.49 RM/m

Allow 10% for joint elements =RM16.40 x 0.10 = 1.64 RM/m18.53 RM/m

b TOTAL MATERIAL COSTMaterial cost/m x Qty required

= 18.53 x 25m = 463.25 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysis1 hour for every 8m of pipesTime required to fix 25m of pipes

=25/8 = 3.13 hours

Labour cost to fix 25m =3.13 x 38.80 = 121.44 RM

3 Tools CostAllow 3% of material cost for small tools

=463.25 x 0.03 = 13.90 RM

Total tools cost = 13.90 RM

4 Total cost including profit and overheadmaterial + labour + tools =463.25 + 121.44 + 13.90 = 598.59 RMadd profit & overhead =598.59 x 0.15 = 89.79 RM

TOTAL = 688.38 RM

5 Unit costTotal cost(RM)/total quantity(m)

= 688.38/25 = 27.54 RM/mEstimate cost for B4 (3)/2/A Rectangular Pipe embedded in ConcreteCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Page 69: Estimating calculation

Cost of pipe at RM61.90 per 4m Cost of pipe per m =(61.90/4) x 1.06 = 16.40 RM/m

Cost of 3% wastage =RM16.40 x 0.03 = 0.49 RM/m

Allow 10% for joint elements =RM16.40 x 0.10 = 1.64 RM/m18.53 RM/m

b TOTAL MATERIAL COSTMaterial cost/m x Qty required

= 18.53 x 40m = 741.20 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysis1 hour for every 8m of pipesTime required to fix 40m of pipes

=40/8 = 5.00 hours

Labour cost to fix 40m =5.00 x 38.80 = 194.00 RM

3 Tools CostAllow 3% of material cost for small tools

=741.20 x 0.03 = 22.24 RM

Total tools cost = 22.24 RM

4 Total cost including profit and overheadmaterial + labour + tools =741.20 + 194.00 + 22.24 = 957.44 RMadd profit & overhead =957.44 x 0.15 = 143.62 RM

TOTAL = 1101.06 RM

5 Unit costTotal cost(RM)/total quantity(m)

=1101.06/40 = 27.53 RM/mRAINWATER OUTLETB4 (3)/2/C Rainwater Outlet

To supply and fix approved 4 Nos. of 150mm diameter rainwater outlet with dome shape grating setting in upvc gutter including jointing on 159mm x 75mm rectangular UPVC outletpipe complete with and including all necessary floor flange, solvent socket and connectors all to Architect’s approval.

Page 70: Estimating calculation

Estimating Data:

Material Data

- RM39.50 for 1 No. of rainwater outlet with dome shape grating including delivery and GST (6%).

- Allow 10% for all necessary elements in accordance with the Architect’s approval.

Labour Data- 1 gang of roofer consists of 2 roofers and 2 unskilled labourers.- Roofer and unskilled labour rates are RM88.20/day and RM 67.00/day respectively.

(8 hours per day)

Output Data- Time required to fix every 20 Nos. of rainwater outlets = 1hour

Tools Cost- Allow 3% of the material cost for small tools (material cost includes such element,

necessary elements and wastage).

Tendering Factor- Allow 15% of the total cost incurs for profit and overhead.

Estimate cost for B4 (3)/2/C Rainwater OutletCalculation:

No Description / Subdescription Formula = Total Unit

1 Material Costa Cost / m

Page 71: Estimating calculation

Cost of rainwater outlet at RM39.50 per No. Cost of 4 Nos. of rainwater outlet

=39.50 x 4 = 158.00 RM

Allow 10% for necessary elements=RM158.00 x 0.10 = 15.80 RM

Total material cost = 173.80 RM

2 Labour Costa Hourly rate

2 x Roofer at RM88.20/day =2 x 88.20 /8 = 22.05 RM/hour2 x Labourer at RM67.00/day =2 x 67.00 /8 = 16.75 RM/hour

Roofer gang hourly rate = 38.80 RM/hour

b Time analysis1 hour for every 20 Nos. of rainwater outletsTime required to fix 4 Nos. =4/20 = 0.20 hours

Labour cost to fix 4 Nos. =0.20 x 38.80 = 7.76 RM

3 Tools CostAllow 3% of material cost for small tools

=173.80 x 0.03 = 5.21 RM

Total tools cost = 5.21 RM

4 Total cost including profit and overheadmaterial + labour + tools =173.80 + 7.76 + 5.21 = 186.77 RMadd profit & overhead =186.77 x 0.15 = 28.02 RM

TOTAL = 214.79 RM

5 Unit costTotal cost(RM)/total quantity(No.)

=214.79/4 = 53.70 RM/No.

Remarks

Prices obtained from timber merbau

http://www.mtib.gov.my/index.php?option=com_content&view=article&id=87&Itemid=88&lang=en

nails for timber

Page 72: Estimating calculation

http://www.ewarehouse.atkc.com.my/concrete-nail?search=concrete steel nail nails for roof tiles

http://www.ewarehouse.atkc.com.my/acebrandgalvanizedflatheadconcretesteelnail60mmx3mm(100pcs-box)?search=concrete steel nail

gang of carpenterhttp://myn3c.cidb.gov.my/cidb_n3c/output/PDF_FILE/view_yearly_labour_pdf.php?state=SELANGOR&&year=2015&&lab=18

gang of rooferhttp://myn3c.cidb.gov.my/cidb_n3c/output/PDF_FILE/view_yearly_labour_pdf.php?state=SELANGOR&&year=2015&&lab=19

interlocking roof tileshttp://myn3c.cidb.gov.my/cidb_n3c/output/PDF_FILE/view_yearly_material_pdf.php?state=SELANGOR&&year=2015&&mat=7

ridge tile & hip cap tileshttp://www.ewarehouse.atkc.com.my/building_material/monier-roofing-system/monier-elabana-tropical-roof-system-ridge-hip-tile

half round gutterhttp://www.ewarehouse.atkc.com.my/arensi-marleyf370spheragutter4-0m-brown?search=gutter

upvc rectangular pipehttp://www.arensimarley.com/pro-roof-drainage-pipe.htm

Seng Bee Hardware & Timber Sdn Bhd- RM15.80 for 1 No. of eaves cap including delivery and GST (6%).- 1 piece of 180mm girth flashing including delivery and GST (6%) = RM14.00/8ft- 1 piece of 450mm girth flashing including delivery and GST (6%) = RM30.00/8ft- RM39.50 for 1 No. of rainwater outlet with dome shape grating including delivery and

GST (6%).

ELEMENT NO.4 – External WallEstimate the tender lump sum to construct half brick thick wall of the size 2.3m high x 24m long (assumed) and one brick thick wall of the size 2.3m high x 20m long (assumed). Half brickwall shall be laid in Stretcher Bond and one brickwall shall be laid in English Bond, using common clay brick in cement mortar (1:3). Exmet and DPC shall be laid. Each end of the wall shall be tied to column 6mm diameter rod at 450mm girth at 400mm ctc.

Page 73: Estimating calculation

Data:Material Cost:

1. Brickwork Common clay brick RM0.42*(1) per piece 1m2 of half brick required 59 pieces of brick 1m2 of one brick required 118 pieces of brick Allow 5% waste on brick Mortar required for 1m2 of half brickwall is 0.07m3 Mortar required for 1m2 of one brickwall is 0.15m3 Ordinary Portland Cement including unloading is RM16.96/50kg*(2) Sand including unloading is RM40.99/tonne*(3) 1m3 of Ordinary Portland Cement = 1420kg 1m3 of sand = 1600kg Allow 30% shrinkage for mortar Cost of exmet at RM10.60/20m*(4) roll (allow 5% for wastage and

overlapped)

2. DPC RM37.10/5kg*(5) 1m2 required 0.5kg DPC Allow 5% wastage and 15% overlapped

3. Bonding Ties 6mm diameter mild steel, RM9/11m*(6) Each bonding tie required 0.3m

Labour Cost: 1 gang of brick layer consists of 1 skilled foreign bricklayer and 1 semi-skilled

foreign bricklayer 1 skilled foreign bricklayer @ RM78/day*(7) 1 semi-skilled foreign bricklayer @ RM61.80/day*(7) Operating hour is 8 hours/day

Labourer Output: 1 gang of brick layer = 120 bricks/hour including fixing bonding ties, exmet and

DPC

Tendering Factor: Allow 15% of the total cost incurs for profit and overhead

Page 74: Estimating calculation

* (1) Price for Common clay brick is obtained from CIDB* (2) Price for Ordinary Portland Cement is obtained from CIDB* (3) Price for Sand is obtained from CIDB* (4) Cost of exmet is obtained from SENG BEE HARDWARE & TIMBER SDN

BHD* (5) Cost of DPC is obtained from SENG BEE HARDWARE & TIMBER SDN BHD* (6) Cost of 6mm diameter mild steel is obtained from JAYAMAS HARDWARE & TIMBER* (7) Daily rate for bricklayer is obtained from CIDB

Page 75: Estimating calculation

Calculation:Material Cost

STEP 1 : Brickwall Cement Mortar Mix (1:3)Ordinary Portland Cement including unloading1m3 of at 1420kg/m3 at RM16.96/50kg = 1420/50 x RM16.96 RM 481.66

Sand at 3m3 at 1600kg/m3 at RM40.99/tonne = 3x(1600/1000xRM40.99) RM 196.75Gross Total RM 678.41

Add 30% shrinkage = RM678.41 x 0.30 RM 203.52Net Total for 4m3 RM 881.93

Divide by parts of mix (1:3) = RM881.93 /4m3 RM 220.48/m3

Half brick required 0.07m3 of mortar /m2 = 0.07 x RM220.48 RM 15.43/m2One brick required 0.15m3 of mortar /m2 = 0.15 x RM220.48 RM 33.07/m2

Half Brick ThickAssume 59 bricks required for 1m2 of half brickMaterial cost /m2 = RM0.42 x 59/m2 RM 24.78/m2Add 5% waste on brick = RM24.78 x 0.05 RM 1.24

Total for half brick RM 26.02/m2

One Brick ThickAssume 118 bricks required for 1m2 of one brickMaterial cost /m2 = RM0.42 x 118/m2 RM 49.56/m2Add 5% waste on brick = RM49.56 x 0.05 RM 2.48

Total for one brick RM 52.04/m2

Exmet20m long, RM10.60/rollCost of 1m length = RM10.60/20m RM 0.53/mNos. of interval exmet laid in 2.3m = 2.3 / [(0.065+0.010)*4] 8 Nos

Half brick 24m long = 24 x 8 x RM0.53 RM 101.76Allow 5% for wastage and overlapped = RM101.76 x 0.05 RM 5.09

Total for half brick RM 106.85Convert to m2 = RM106.85 / (2.3m x 24m) RM 1.94/m2

One brick 20m long = 20 x 8 x RM0.53 RM 84.80Allow 5% for wastage and overlapped = RM84.80 x 0.05 RM 4.24

Total for one brick RM 89.04Convert to m2 = RM89.04/ (2.3m x 20m) RM 1.94/m2

STEP 2 : DPCRM37.10/5kg, 1m2 required 0.5kg DPCCost of 1m2 = RM37.10/5kg x 0.5kg/m2 RM 3.71/m2Half brick thick1m of 115mm DPC = RM3.71/m2 x 0.115m RM 0.43/m

Page 76: Estimating calculation

Add 5% wastage = RM0.43 x 0.05 RM 0.02Add 15% overlapped = RM0.43 x 0.15 RM 0.06

Total for half brick RM 0.51/mOne brick thick1m2 of 225mm DPC RM 3.71/m2Add 5% wastage = RM3.71 x 0.05 RM 0.19Add 15% overlapped = RM3.71 x 0.15 RM 0.56

Total for one brick RM 4.46/m2

STEP 3 : Bonding Ties6mm diameter rod at 450mm girth, RM9/11mCost of each bonding tie required 0.3m = RM9/11m x 0.3m/no. RM 0.25/no. Total cost = no. x rate = 162 x RM0.25 RM 40.50

Labour CostCost of gang per hour1 skilled foreign bricklayer RM78/day = RM78/8hrs RM 9.75/hr1 semi-skilled foreign bricklayer RM61.80/day = RM61.80/8hrs RM 7.73/hr

Cost per hour RM 17.48/hr

1 hour the brick layer gang can lay 120bricks1m2 Half brick required 59 bricks = RM17.48/120 x 59/m2 RM 8.59/m21m2 One brick required 118 bricks = RM17.48/120 x 118/m2 RM 17.19/m2

Summary (Unit Rate)Half Brickwall Material Cost

Cement Mortar M2 RM 15.43/m2 Brick M2 RM 26.02/m2 Exmet M2 RM 1.94/m2

RM 43.39/m2

115mm wide DPC Material Cost M RM 0.51/m

Half Brickwall Labour Cost Labour to lay 1m2 RM 8.59/m2

One Brickwall Material Cost Cement Mortar M2 RM 33.07/m2 Brick M2 RM 52.04/m2 Exmet M2 RM 1.94/m2

RM 87.05/m2

225mm wide DPC Material Cost M2 RM 4.46/m2

One Brickwall Labour Cost Labour to lay 1m2 RM 17.19/m2

Bonding Ties Material Cost No. RM 0.25/no.

Lump Sump Tender

Page 77: Estimating calculation

Material Cost Rate Quantities Total Half Brickwall M2 43.39 55 RM 2386.45 115mm wide DPC M 0.51 24 RM 12.24 One Brickwall M2 87.05 46 RM 4004.30 225mm wide DPC M2 4.46 5 RM 22.30 Bonding Ties No. 0.25 162 RM 40.50

Labour Cost Half Brickwall M2 8.59 55 RM 472.45 One Brickwall M2 17.19 46 RM 790.74

Total Cost = (Material + Labour) x Quantity RM 7728.98Add profit and overhead 15% RM 1159.35

TOTAL TENDER SUM RM 8888.33

ELEMENT NO.5 – Internal Wall

Page 78: Estimating calculation

Estimate the tender lump sum to construct half brick thick wall of the size 3m high x 26m long (assumed). The brick shall be laid in Stretcher, using common clay brick in cement mortar (1:3). Exmet and DPC shall be laid. Each end of the wall shall be tied to column 6mm diameter rod at 450mm girth at 400mm ctc.Data:Material Cost:

4. Brickwork Common clay brick RM0.42*(1) per piece 1m2 of half brick required 59 pieces of brick Allow 5% waste on brick Mortar required for 1m2 of half brickwall is 0.07m3 Ordinary Portland Cement including unloading is RM16.96/50kg*(2) Sand including unloading is RM40.99/tonne*(3) 1m3 of Ordinary Portland Cement = 1420kg 1m3 of sand = 1600kg Allow 30% shrinkage for mortar Cost of exmet at RM10.60/20m*(4) roll (allow 5% for wastage and

overlapped)5. DPC

RM37.10/5kg*(5) 1m2 required 0.5kg DPC Allow 5% wastage and 15% overlapped

6. Bonding Ties 6mm diameter mild steel, RM9/11m*(6) Each bonding tie required 0.3m

Labour Cost: 1 gang of brick layer consists of 1 skilled foreign bricklayer and 1 semi-skilled

foreign bricklayer 1 skilled foreign bricklayer @ RM78/day*(7) 1 semi-skilled foreign bricklayer @ RM61.80/day*(7) Operating hour is 8 hours/day

Labourer Output: 1 gang of brick layer = 120 bricks/hour including fixing bonding ties, exmet and

DPC

Tendering Factor: Allow 15% of the total cost incurs for profit and overhead

* (1) Price for Common clay brick is obtained from CIDB* (2) Price for Ordinary Portland Cement is obtained from CIDB

Page 79: Estimating calculation

* (3) Price for Sand is obtained from CIDB* (4) Cost of exmet is obtained from SENG BEE HARDWARE & TIMBER SDN

BHD* (5) Cost of DPC is obtained from SENG BEE HARDWARE & TIMBER SDN BHD* (6) Cost of 6mm diameter mild steel is obtained from JAYAMAS HARDWARE & TIMBER* (7) Daily rate for bricklayer is obtained from CIDB

Page 80: Estimating calculation

Calculation:Material Cost

STEP 1 : Brickwall Cement Mortar Mix (1:3)Ordinary Portland Cement including unloading1m3 of at 1420kg/m3 at RM16.96/50kg = 1420/50 x RM16.96 RM 481.66

Sand at 3m3 at 1600kg/m3 at RM40.99/tonne = 3x(1600/1000xRM40.99) RM 196.75Gross Total RM 678.41

Add 30% shrinkage = RM678.41 x 0.30 RM 203.52Net Total for 4m3 RM 881.93

Divide by parts of mix (1:3) = RM881.93 /4m3 RM 220.48/m3

Half brick required 0.07m3 of mortar /m2 = 0.07 x RM220.48 RM 15.43/m2

Half Brick ThickAssume 59 bricks required for 1m2 of half brickMaterial cost /m2 = RM0.42 x 59/m2 RM 24.78/m2Add 5% waste on brick = RM24.78 x 0.05 RM 1.24

Total for half brick RM 26.02/m2

Exmet20m long, RM10.60/rollCost of 1m length = RM10.60/20m RM 0.53/mNos. of interval exmet laid in 3m = 3 / [(0.065+0.010)*4] 10 Nos

Half brick 26m long = 26 x 10 x RM0.53 RM 137.80Allow 5% for wastage and overlapped = RM137.80 x 0.05 RM 6.89

Total for half brick RM 144.69Convert to m2 = RM144.69 / (3m x 26m) RM 1.86/m2

STEP 2 : DPCRM37.10/5kg, 1m2 required 0.5kg DPCCost of 1m2 = RM37.10/5kg x 0.5kg/m2 RM 3.71/m2Half brick thick1m of 115mm DPC = RM3.71/m2 x 0.115m RM 0.43/mAdd 5% wastage = RM0.43 x 0.05 RM 0.02Add 15% overlapped = RM0.43 x 0.15 RM 0.06

Total for half brick RM 0.51/m

STEP 3 : Bonding Ties6mm diameter rod at 450mm girth, RM9/11mCost of each bonding tie required 0.3m = RM9/11m x 0.3m/no. RM 0.25/no.Total cost = no. x rate = 36 x RM0.25 RM 9.00

Labour CostCost of gang per hour1 skilled foreign bricklayer RM78/day = RM78/8hrs RM 9.75/hr

Page 81: Estimating calculation

1 semi-skilled foreign bricklayer RM61.80/day = RM61.80/8hrs RM 7.73/hrCost per hour RM 17.48/hr

1 hour the brick layer gang can lay 120 bricks1m2 Half brick required 59 bricks = RM17.48/120 x 59/m2 RM 8.59/m2

Summary (Unit Rate)Half Brickwall Material Cost

Cement Mortar M2 RM 15.43/m2 Brick M2 RM 26.02/m2 Exmet M2 RM 1.86/m2

RM 43.31/m2

115mm wide DPC Material Cost M RM 0.51/m

Half Brickwall Labour Cost Labour to lay 1m2 RM 8.59/m2

Bonding Ties Material Cost No. RM 0.25/no.

Lump Sump TenderMaterial Cost Rate Quantities Total

Brickwall M2 43.31 78 RM 3378.18 115mm wide DPC M 0.51 26 RM 13.26 Bonding Ties No. 0.25 36 RM 9.00

Labour Cost M2 8.59 78 RM 670.02Total Cost = (Material + Labour) x Quantity RM 4070.46

Add profit and overhead 15% RM 610.57TOTAL TENDER SUM RM 4681.03

Page 82: Estimating calculation

Element No. 6 DOORS AND IRONMONGERIESMaterial DataPrecast Concrete Lintels

Calculate 150mm x 150mm high precast reinforced concrete (Grade 30) lintels as per Engineer’s details.

Material Cost 150mm x 150mm high precast concrete (Grade 30) lintels RM 29.00Allow waste 5% on lintels

Labour CostJoiner rate at RM68.90/day (8 hours day)Marking out lintels 15mins/mCutting lintels 30mins/mErect lintels 30mins/mFixing lintels 30mins/m

Tendering factorsProfit + Overheads 15%

*Price obtain from Seng Bee

Page 83: Estimating calculation

Calculation of Precast Concrete Lintels

Calculate 150mm x 150mm high precast reinforced concrete (Grade 30) lintels as per Engineer’s details.

Step 1: Material CostNo Item Unit Quantity Rate (RM)/m

1 150mm x 150mm high precast reinforced concrete (Grade 30) lintels

m 9 29.00

Total material cost RM 261.00

Step 2: Labour CostNo Item Unit Quantity Hour/unit Time required

1 Marking out lintels 15mins/m

m 9 0.25 2.25

2 Cutting lintels30mins/m

m 9 0.50 4.50

3 Erect lintels30mins/m

m 9 0.50 4.50

4 Fixing lintels30mins/m

m 9 0.50 4.50

Total time required

15.75

Total labour cost RM 68.90/8 x 15.75 = RM135.65

Step 3: Allow estimation factorTotal material cost x 5% wastage = RM261.00 x 5% = RM13.05

Page 84: Estimating calculation

Step 4: Total costMaterial RM261.00

Labour RM135.65

Estimation factor RM13.05

Total RM364.70

Prodit + overhead RM364.70 x 15% =  RM54.71

Total cost RM419.41

Step 5: Unit rateTotal cost/quantity: RM419.41/9 = RM46.60/m

Page 85: Estimating calculation

Material DataDoor Frames

38mm thick skeleton frame flush door including packing, grounds, fixing cramps, dowels and all other fixing as per drawing.

Material costDoorframe sets; including packing, grounds, fixing cramps, dowels and all other fixing as per architect detail’s drawing

Proposed:Size: 0.914mx2.134m RM126.14

Labour costJoiner rate at RM68.90/day (8 hours/day)Framing a door 6mins/mHanging a door 6mins/mScrewing bolts and nuts 3mins/mFixing door frame 3mins/m

Allow profit + overhead 15%Allow 5% of material cost

*Price obtained from ATKChttp://www.ewarehouse.atkc.com.my/kempas-door-frame-3-w-x7-h

Page 86: Estimating calculation

Calculation of door frame

38mm thick skeleton frame flush door including packings, grounds, fixing cramps, dowels and all other fixing as per drawings.

Girth of door frame: 2/2.134+0.914 = 5.182m Price of door frame: RM126.14/5.182 = RM24.34/m

Step 1: Material CostNo Item Unit Quantity Rate (RM)/m

1 Door frame sets m 39 24.34

Total material cost 949.26

Step 2: Labour CostNo Item Unit Quantity Hour/unit Time required

1 Framing a door6mins/m

m 39 0.10 3.90

2 Hanging a door6mins/m

m 39 0.10 3.90

3 Screwing a door3mins/m

m 39 0.05 1.95

4 Fixing door frame3mins/m

m 39 0.05 1.95

Total time required

11.70

Total labour costRM68.90/8x11.70 = RM100.77

Step 3: Allow estimation factorRM949.26x5% = RM47.46

Page 87: Estimating calculation

Step 4: Total costMaterial RM949.26

Labour RM100.77

Estimation factor RM47.46

Total RM1097.49

Profit + overhead RM1097.49 x 15% =  RM164.62

Total cost RM1262.11

Step 5: Unit rateTotal cost/quantity: RM1262.11/39 = RM32.36/m

*Quantity of door frame:New proposed door size 685.8mm x 2057.4mm (2 nos)New proposed door size 762mm x 2057.4mm (6 nos)

*Doorframe girth: 2 x [ 0.686+(2x2.057) ]= 9.6Doorframe girth: 6 x [ 0.762+(2x2.057) ]= 29.26

9.6+29.26= 38.86 (39m)

Page 88: Estimating calculation

Material DataDoor Frames

38mm thick skeleton frame flush door including packings, grounds, fixing cramps, dowels and all other fixing as per drawing.

Material costArchitrave; including packings, grounds, fixing cramps, dowels and all other fixing as per architect detail’s drawing

Size: 19x57x2100mm RM5.75/m

Labour costJoiner rate at RM68.90/day (8 hours/day)Framing a door 6mins/mHanging a door 6mins/mScrewing bolts and nuts 3mins/mFixing door frame 3mins/m

Allow profit + overhead 15%Allow 5% of material cost

*Price obtained from Seng Bee

Page 89: Estimating calculation

Calculation of door frame

38mm thick skeleton frame flush door including packings, grounds, fixing cramps, dowels and all other fixing as per drawings.

Price per m:RM5.75/2.10m = RM2.74/m

Step 1: Material Cost No Item Unit Quantity Rate (RM)

1 Architrave m 78 2.74

Total material cost 213.72

Step 2: Labour Cost No Item Unit Quantity Hour/unit Time required

1 Framing a door6mins/m

m 78 0.10 7.80

2 Hanging a door6mins/m

m 78 0.10 7.80

3 Screwing a door3mins/m

m 78 0.05 3.90

4 Fixing door frame3mins/m

m 78 0.05 3.90

Total time required

23.40

Total labour costRM68.90/8x23.40 = RM201.53

Step 3: Allow estimation factorRM213.72x5% = RM10.69

Page 90: Estimating calculation

Step 4: Total costMaterial RM213.72

Labour RM201.53

Estimation factor RM10.69

Total RM425.94

Profit + overhead RM425.94 x 15% =  RM63.89

Total cost RM489.83

Step 5: Unit rateTotal cost/quantity = RM489.83/78 = RM6.28/m

*Quantity of door frame:New proposed door size 0.686m x 2.057m (2 nos)New proposed door size 0.762m x 2.057m (6 nos)

Door frame girth: 2 x [ 0.686+(2x2.057) ]= 9.6Door frame girth: 6 x [ 0.762+(2x2.057) ]= 29.26

9.6+29.26= 38.86 (39m) 2 sides architrave: 2x39= 78m

Page 91: Estimating calculation

Material DataDoor Leaf

Supply and fix 38mm thick skeleton frame flush door in Nyatoh finish plywood constructed of stiles, top, intermediate and bottom rail and covered on both side with 6mm thick plywood.

Material costProposedSingle leaf plywood flush door 0.686m(w) x 2.057m(h) (ED1) RM79.50/noSingle leaf plywood flush door 0.762m(w) x 2.057m(h) (ND1) RM79.50/noAllow 5% of material cost for other small tools and ladders

Labour costJoiner rate at RM68.90/day (8 hours day)Framing a door 15mins/noHanging a door 15mins/noMortising the door for hinges 30mins/noInstall cylinder lock 20mins/no

Tendering factorProfit + overhead 15%

*Price obtained from ATKChttp://www.ewarehouse.atkc.com.my/index.php?route=product/category&path=72_102&page=1

Page 92: Estimating calculation

Calculation of door leaf

Supply and fix 38mm thick skeleton frame flush door in Nyatoh finish plywood constructed of stiles, top, intermediate and bottom rail and covered on both side with 6mm thick plywood.

Step 1: Material costNo Item Unit Quantity Rate (RM)

1 Single leaf plywood flush door 685.8mm(w)x2057.4mm(h)  (ED1)

No 2 79.50

Total material cost

159.00

Step 2: Labour cost No Item Unit Quantity Hour/unit Time

required

1 Framing a door 15mins/no

No 2 0.25 0.50

2 Hanging a door 15mins/no

No 2 0.25 0.50

3 Mortising the door for hinges 30mins/no

No 2 0.50 1.00

4 Install cylinder lock 20mins/no

No 2 0.33 0.66

Total time required

2.66

Total labour costRM68.9/8x2.66 = RM22.91

Step 3:Tendering/tools costAllow 5% for tools: RM159.00x0.05 = RM7.95

Step 4: Total cost

Page 93: Estimating calculation

Material RM159.00

Labour RM22.91

Tendering RM7.95

Total RM189.86

Profit + overhead RM189.86x15% RM28.48

Total cost RM218.34

Step 5: Unit rateTotal cost/quantity: RM218.34/2 = RM109.17/no

Calculation of door leaf

Page 94: Estimating calculation

Supply and fix 38mm thick skeleton frame flush door in Nyatoh finish plywood constructed of stiles, top, intermediate and bottom rail and covered on both side with 6mm thick plywood.

Step 1: Material costNo Item Unit Quantity Rate (RM)

1 Single leaf plywood flush door 762mm(w)x2057.4mm(h) (ND1)

No 6 79.50

Total material cost

477.00

Step 2: Labour costNo Item Unit Quantity Hour/unit Time

required

1 Framing a door 15mins/no No 6 0.25 1.50

2 Hanging a door 15mins/no No 6 0.25 1.50

3 Mortising the door for hinges 30mins/no

No 6 0.50 3.00

4 Install cylinder lock 20mins/no No 6 0.33 1.98

Total time required

7.98

Total labour costRM68.9/8x7.98 = RM68.73

Step 3:Tendering/tools costAllow 5% for tools: RM477.00x0.05 = RM23.85

Step 4: Total costMaterial RM477.00

Page 95: Estimating calculation

Labour RM68.73

Tendering RM23.85

Total RM569.58

Profit + overhead RM569.58x15% RM85.44

Total cost RM655.02

Step 5: Unit rateTotal cost/quantity: RM655.02/6 = RM109.17/no

Material DataDoor Ironmongeries

Page 96: Estimating calculation

Supply and fix ironmongeries to timber; including provision of matching screw.

Material CostCylindric entrance lock (Model: LOCKWOOD-7120) RM57.24/setSurface pill handle on rose (Model: LOCKWOOD-TW250) RM50.00/setHinge 4” in stainless steel finish (Model: LOCKWOOD HG1) RM29.68/set

Labour CostJoiner rate at RM68.90/day (8 hours day)Handling for steel butt hinges 15mins/noFastening bolts and nuts for hinges 10mins/noHandling all ironmongeries 15mins/noFixing the ironmongeries 15mins/no

Tendering factorProfit + overhead 15%

Tendering/tools costAllow 5% of the material cost for other small tools

*Price obtained from CIDB and Seng Bee

Calculation of door ironmongeries

Supply and fix stainless steel butt hinges 102mmx76mmx2mm (Model: LOCKWOOD HG1)

Page 97: Estimating calculation

Step 1: Material costNo Item Unit Quantity Rate (RM)

1 Supply and fix stainless steel butt hinges 102mmx76mmx2mm (Model: LOCKWOOD HG1)

No 18 29.68

Total material cost

534.24

Step 2: Labour costNo Item Unit Quantity Hour/unit Time

required

1 Handling for steel butt hinges        15mins/no

no 18 0.25 4.50

2 Fastening bolts and nuts for hinges       10mins/no

no 18 0.17 3.06

Total time required

7.56

Total labour costRM68.90/8x7.56 = RM65.11

Step 3: Tendering /tools costAllow 5% for tools: RM534.24x0.05=RM26.71

Step 4: Total cost Material RM534.24

Labour RM65.11

Tendering RM26.71

Page 98: Estimating calculation

Total RM626.06

Profit + overhead RM626.06x15% RM93.91

Total cost RM719.97

Step 5: Unit rateTotal cost/quantity: RM719.97/18 = RM40.00/no

Calculation of door ironmongeries

Supply and fix ironmongeries to timber, including provision of matching screw.

Step 1: Material cost

Page 99: Estimating calculation

No Item Unit Quantity Rate (RM)

1 Cylindric entrance lock (Model: LOCKWOOD-7120)

No 2 57.24

Total material cost

114.48

Step 2: Labour cost No Item Unit Quantity Hour/unit Time

required

1 Handling all ironmongeries15mins/no

no 2 0.25 0.50

2 Fixing the ironmongeries15mins/no

no 2 0.25 0.50

Total time required

1.00

Total labour costRM68.90/8x1.00 = RM8.61

Step 3: Tendering /tools costAllow 5% for tools: RM114.48x0.05=RM5.72

Step 4: Total costMaterial RM114.48

Labour RM8.61

Tendering RM5.72

Total RM128.81

Profit + overhead RM128.81x15% RM19.32

Total cost RM148.13

Step 5: Unit rateTotal cost/quantity: RM148.13/2 = RM74.07noCalculation of door ironmongeries

Supply and fix ironmongeries to timber, including provision of matching screw.

Step 1: Material cost

Page 100: Estimating calculation

No Item Unit Quantity Rate (RM)

1 Surface pill handle on rose

No 6 50.00

Total material cost

300.00

Step 2: Labour cost No Item Unit Quantity Hour/unit Time

required

1 Handling all ironmongeries15mins/no

no 6 0.25 1.50

2 Fixing the ironmongeries15mins/no

no 6 0.25 1.50

Total time required

3,00

Total labour costRM68.90/8x3.00 = RM25.84

Step 3: Tendering /tools costAllow 5% for tools: RM300.00x0.05=RM15.00

Step 4: Total costMaterial RM300.00

Labour RM25.84

Tendering RM15.00

Total RM340.84

Profit + overhead RM340.84x15% RM51.13

Total cost RM391.97

Step 5: Unit rateTotal cost/quantity: RM391.97/6 = RM65.34/no

Material DataPainting

Estimate the total cost and the unit rate per m2 in preparing and applying two coats of clear vanish on woodwork to general surface of timber panel, door frame and architrave.

Page 101: Estimating calculation

Painting dataPaint material Cost bucket (5litre) Surface Litres per 100m2

2 final coats  RM98.23 wood 8.30Allow 10% of wastage for all works

Painter dataDaily rate for painter is RM67.30/day for 8 hours day

Painter output data are as follow: Paint materials Surface Hours per 100m2

2 Final coats wood 4.5

Tendering/tools costAllow 20% material costs for paint brush, accessories and other small tools.

Tendering factorAllow 15% profit + overhead

*Price obtained from CIDB

Calculation of painting

Estimate the total cost and the unit rate per m2 in preparing and applying two coats of clear vanish on woodwork to general surface of timber panel.

Page 102: Estimating calculation

Step 1: Material costa. Cost/100m2Description Formula Total Unit

2 final coats 98.23/5x8.3x2 326.12 100m2

+ wastage 10% 326.12x0.10 32.60 100m2

Total material cost 358.73 100m2

Step 2: Labour costa. Hourly ratePainter at RM67.30/day

67.30/8 8.41 100m2

b.Time required to paint 100m22 final coats 4.5x2 9 100m2

Total time required to paint 100m2

9 100m2

c. Total labour costHourly rate x time required: 8.41x9 = 75.69/100m2

Step 3: Total cost per 100m2 including profit and overhead Material cost + labour cost: 358.73+75.69

434.42

Allow 20% for tools: 434.42x0.20 86.88 100m2

Total 521.30 100m2

+ Profit and overhead 521.30x15% 78.20

Total time required to paint 100m2 599.50 100m2

Step 4: Unit costTotal cost (RM)/total quantity (m2): RM599.59/100 = RM6.00/m2

Step 5: Total costQuantity required x unit rate: 32m2 x 6.00 = RM191.84/m2

Calculation of painting

Estimate the total cost and the unit rate per m in preparing and applying two coats of clear vanish on woodwork to general surface of door frame.

Page 103: Estimating calculation

Step 1: Material costa. Cost/100mDescription Formula Total Unit

2 final coats 98.23/5x(8.3/100)x2 3.26 1m2

+ wastage 10% 3.26x0.10 0.33 1m2

Total material cost 3.59 1m2

250mm girth 3.59 x 0.25 0.90 1m Step 2: Labour costa. Hourly ratePainter at RM67.30/day

67.30/8 8.41 100m

b. Time required to paint 100m2 final coats (4.5/100)x2 0.09 1m2

Total time required to paint 1m2

0.09 1m2

250mm girth 0.09 x 0.25 0.02 1m

c. Total labour costHourly rate x time required: 8.41x0.02 = 0.17/m

Step 3: Total cost per 100m including profit and overheadMaterial cost+labour cost: 0.90+0.17 1.07 1m

Allow 20% for tools: 1.07x0.20 0.21 1m

Total 1.28 1m

+Profit and overhead 1.28x15% 0.19 1m

Total Unit Rate 1.47 1m

Step 4: Total costQuantity required x unit rate: 39m x RM1.47/m = RM57.33/m

Calculation of painting

Estimate the total cost and the unit rate per m in preparing and applying two coats of clear vanish on woodwork to general surface of architrave.

Page 104: Estimating calculation

Step 1: Material costa. Cost/100mDescription Formula Total Unit

2 final coats 98.23/5x(8.3/100)x2 3.26 1m2

+ wastage 10% 3.26x0.10 0.33 1m2

Total material cost 3.59 1m2

100mm girth 3.59x0.10 0.36 1m

Step 2: Labour costa.Hourly ratePainter at RM67.30/day

67.30/8 8.41 100m

b.Time required to paint 100m2 final coats (4.5/100)x2 0.09 1m2

Total time required to paint 1m2

0.09 1m2

100mm girth 0.09 x 0.10 0.09 1m

c. Total labour costHourly rate x time required: 8.41x 0.09hour = 0.76/1m

Step 3: Total cost per 100m including profit and overhead Material cost+labour cost: 0.36+0.76 1.12 1m

Allow 20% for tools: 1.12x0.20 0.22 1m

Total 1.34 1m

+Profit and overhead 1.34x15% 0.20 1m

Total Unit Rate 1.54 1m

Step 4: Total costQuantity required x unit rate: 78m x RM1.54/m = RM120.12/m

Material DataRoller door

Colour bond roller door as architect’s approval; as per drawing overall size 3500mm x 2000mm

Page 105: Estimating calculation

Material costColour bond roller door RM153.01

Labour costJoiner rate at RM68.90/day (8 hours day)Handling the roller door 15mins/noConnector roller door 30mins/noFastened the bolts and nuts 20mins/noFixing roller door 15mins/no

Tendering factorAllow 15% profit + overhead

Tendering/tools costAllow 5% of the material cost for other small tools and ladder

Calculation of roller door

Colourbond roller door as architect’s approval; as per drawing overall size 3500mm x 2000mm

Page 106: Estimating calculation

Data:-Rate for roller door:1m2= 10.76 square feet1 square feet= RM18.00 (Price from Sabah)1m2= RM18x10.76RM193.68x0.21% (Price difference between Sabah and Selangor)= RM40.67RM193.68-RM40.67= RM153.01/m2

Step 1: Material costNo Item Unit Quantity Rate (RM)/m2

1 3500mm x 2000mm colour bond roller door to architect’s approval

no 1 153.01

Total material cost

153.01

Step 2: Labour costNo Item Unit Quantity Hour/unit Time

required

1 Handling the roller door 15mins/no

no 1 0.25 0.25

2 Connectors roller door 30mins/no

no 1 0.50 0.50

3 Fastened the bolts and nuts 20mins/no

no 1 0.33 0.33

4 Fixing roller door 15mins/no

no 1 0.25 0.25

Total time required

1.33

Total labour costRM68.90/8x1.33 = RM11.45

Step 3: Tendering/tool costAllow 5% for tools = RM153.01x0.05% = RM7.65

Step 4: Total costMaterial RM153.01

Page 107: Estimating calculation

Labour RM11.45

Tendering RM7.65

Total RM172.11

Profit + overhead RM172.11x15% RM25.82

Total cost/no RM197.93

ELEMENT NO. 7 – INTERNAL WALL FINISHESEstimate Cost of InsituFinishings20mm thick cement and sand (1:3) plastering with approved plasticizer.Estimating Data:Materials:

ITEM COST

Page 108: Estimating calculation

OP Cement (50kg/bag)* RM16.96/bagFineMining Sand* RM40.99/tonneShrinkage factor for (1:3) mix 30%Wastage factor for mixing mortar 10%

Labour rate:Skilled labour* RM85/daySemi-skilled labour* RM63/day

Output data: Plasticizer used is 6L/tone of cement at a cost of RM5.00 per litre. Coverage for 20mm thick plaster is 75mm per 1000kg. 2 skilled and 1 semi-skilled labour. Output for mix and apply is 100m2 in 18

hours. Taking delivery and staking cement at 20 nos. of 50kg bag per hour.

Material weight: Density of cement – 1420kg/m3 Density of sand – 1600kg/m3

Tendering factor: Allow 15% of profit including overhead

*Price for OP Cement is obtained from CIDB.*Price for Fine Mining Sand is obtained from CIDB.*Labour rates are obtained from CIDB.

Calculation: Cost of InsituFinishingsMATERIAL COSTCement and sand (1:3) + plasticizer – m2OP Cement including unloading:1m3 at 1420kg/m3 at RM16.96/50kg =1420/50 x 16.96 481.66

Page 109: Estimating calculation

Sand at 3m3 at 1600kg/m3 at RM40.99/tonne =1600/1000 x 40.99 x 3196.75

Gross Total 678.41/4m3Divide by parts of mix (1:3) =678.41/4 169.60/m3Plasticizer 6L/1000kg by cement @RM5/L =6/1000x(1420/4)x5 10.65

180.25Add shrinkage, waste (30%+10%) =180.25 x (30%+10%) 281.19Cost per m2 =281.19 x 0.020 RM 5.62/m2

LABOUR COST (M2)Labour gang

2 skilled @RM85/person/day =RM85/8 x 2 21.25/hour1 semi-skilled @RM63/person/day =RM63/8 7.88/hour

Labour gang hourly rate RM 29.13/hour

Coverage of plasteris 75m2/1000kgAssumed 1000kg refers to cement onlyTherefore 1m2 requires how many kg of cement =1000/75 13.33kg

Time required by labourDelivery and staking of 13.33kg cement =[13.33/ (20x50)] x 1 0.013 hourMix and apply 1m2 =18 hours/100m2 0.180 hourTotal time required 0.193 hourTotal labour cost per m2 =0.193 x 29.13 RM 5.62/m2

Total cost (m2)Total cost = material + labour =5.62 + 5.62 11.24 ringgit15% (overhead + profit) 1.69

Total 12.93 ringgit

Estimate Cost of Backings and Tiles FinishingsI. 15mm thick cement and sand (1:3) backings; cement screeded finish; with

approved adhesive mix with clean water; to receive wall tilesII. 300mmx300mmx5mm thick ceramic tiles in glazed finish; pointing and grouting

with approved admix in white cement

Page 110: Estimating calculation

Allow 15% profit including overhead

Material cost: 300mmx300mmx5mm glazed ceramic tiles @RM1.25/piece* OP Cement 1m3 at 1420kg/m3 at RM16.96/50kg Sand 1600kg/m3 at RM 40.99/tonne Allow 33.33% waste and shrinkage for cement mortar Allow 10% waste for ceramic tiles Allow RM2.00 for white cement mortar/m2

Labour cost*: Semi-skilled labour for cement mortar mix RM61.80/day (8 hours) Tiler (skilled labour) RM87.20/day (8 hours)

Output data:To mix 1m3 of cement mortar requires 1hourTo lay 1m2 of ceramic tiles requires 2.5hoursTo do 1m2 of pointing requires 1hour

*Price for OP Cement is obtained from CIDB.*Price for Fine Mining Sand is obtained from CIDB.*Price for Ceramic Wall Tiles are obtained from CIDB.*Labour rates are obtained from CIDB.

Calculation: Cost of Backings and Tiles FinishingsMATERIAL COSTCement and sand mix (1:3) – m2OP Cement including unloading:1m3 at 1420kg/m3 at RM16.96/50kg =1420/50 x 16.96 481.66Sand at 3m3 at 1600kg/m3 at RM40.99/tonne =1600/1000 x 40.99 x 3

196.75

Page 111: Estimating calculation

Gross Total 678.41Add waste, shrinkage 33.33% =678.41 x 33.33% 226.11

Net total for 4m3 904.52Divide by parts of mix (1:3) =904.52/4 226.13/m3Cost per m2 =226.13 x 0.015 3.39/m2

Ceramic tiles (m2)No. of tiles per m2 =1/(0.3x0.3) 11.11 piecesGross cost per m2 @RM1.25/piece =11.11 x 1.25 13.89Add 10% wastage =13.89 x 0.10 1.39Net cost per m2 =13.89 + 1.39 15.28/m2White Cement Mortar (m2) 2.00Total Material Cost =15.28 + 3.39 + 2.00 20.67

LABOUR COST (M2)To mix cement and sand

Semi-skilled labour @RM61.80/day =61.80/8 7.73/hourCost to mix 1m2 =7.73 x 1 x 0.015 0.12/m2

To lay ceramic tiles and pointingTiler @RM87.20/day =87.20/8 10.90/hourCost to lay 1m2 and point 1m2 =(2.5+1) x 10.90 38.15/m2

Total labour cost /m2 =0.12 + 38.15 38.27/m2

TOTAL COST (M2)Quantity = 95 95 m2Total cost = Qty x rate = 95 x (20.67+38.27) 5599.30 ringgitAdd 15% (profit+overhead) 839.90

Total 6439.20ringgit

Estimate Cost of PaintingPrepare one coat of primer; 2 undercoats and 1 final coat on plastered surface.

Paint Data*:Paint materials Cost/bucket (5litres) Surface Litres per 100m2

Primer RM120.00 Plaster 8.3

Page 112: Estimating calculation

Undercoat RM120.00 Plaster 7.2Final coat RM38.00 (1 litre) Plaster 8.3

Allow 10% wastage for all works.

Painter Data*: Skilled labour rate is RM88/day for 8 hours day.

Paint materials Surface Hour per 100m2Primer Plaster 6.6

Undercoat Plaster 5.8Final coat Plaster 4.5

Tendering/Tools Cost: 20% material cost for paint brush, accessories and other small tools. 3% for scaffolding

Tendering Factor: 15% profit including overhead.

*Price for primer, undercoat, and final paint are obtained from Seng Bee Hardware & Timber SdnBhd Mr. Lee.*Labour rates are obtained from CIDB.

Calculation: Cost of PaintingMATERIAL COSTCost/100m2

1 coat primer =120/5 x 8.3 199.20/100m22 undercoat =120/5 x 7.2 x 2 345.60/100m21 final coat =38 x 8.3 315.40/100m2

860.20/100m2

Page 113: Estimating calculation

Add wastage 10% =860.20x 0.10 86.02/100m2946.22/100m2

LABOUR COSTHourly rate

Painter at RM88/day =88/8 11.00Time required to paint 100m2

1 coat primer =6.6 6.6 hr/100m22 undercoat =5.8 x 2 11.60hr/100m2I final coat =4.5 4.5hr/100m2

Total time required to paint 100m2 22.70hr/100m2Total labour cost

Hourly rate x time required =11.00 x 22.70 249.70/100m2

Total cost per 100m2 including profit and overheadMaterial cost + labour cost =946.22+249.70

1195.92ringgit/100m2Allow 20% for tools =946.22 x 0.20 189.24ringgit/100m2

Total cost/100m21385.16 ringgit/100m2

Add scaffolding =1385.16 x 0.03 41.55ringgit/100m2 1426.71 ringgit/100m2

Add 15% (profit+overhead) =1426.71 x 0.15214.01ringgit/100m2

Total 1640.72 ringgit/100m2

Unit CostTotal cost (RM)/total qty (m2) =1640.72/100 16.41m2

Total costQuantity required x unit rate =132 x 16.41 2166.12 ringgitQuantity =132m2

CADANGAN MEMBINA SATU RUMAH CONTOH DI ATAS LOT 123, MUKIMPETALING JAYA, NEGERI SELANGOR DARUL EHSAN

BILLS OF QUANTITIESBILL NO. 4 – MAIN BUILDING WORKSELEMENT NO. 8 – INTERNAL FLOOR FINISHES

BQ ref ITEM DESCRIPTION Unit Qty Rate (RM) TOTAL (RM)

BEDS ANDD BACKINGSCement and sand (1:3) screed as described:

Page 114: Estimating calculation

20mm thick, smooth steel trowelled:

B4(8)/1/A To floor

20mm thick as backings screed with approved adhesive mix with clean water; to receive floor tiles

m2 18

B4(8)/1/B

B4(8)/1/C

B4(8)/1/D

B4(8)/1/E

To floor

To floor: laid to fall not exceeding 15⁰ from horizontal

To drop: 100mm high

To skirting: 150mm high

m2

m2

m

m

86

4

7

70

TILES FINISHING300mm x 300mm x 8mm thick ceramic tiles in glazed finish; “SIXNY 3-23001 WHITE” including; pointing and grouting with approved admix in white cement

B4(8)/1/F

B4(8)/1/G

B4(8)/1/H

B4(8)/1/I

To floor

To floor: laid to fall not exceeding 15⁰ from horizontal

To drop: 100mm high

To skirting: 150mm high

m2

m2

m

m

86

4

7

70

Total Carry To Summary Page of Bill No.4 – Page B4 (Summary)/1B4(8)/1

ELEMENT NO.8 – INTERNAL FLOOR FINISHES

ELEMENT NO. 8 DATA:

Material Cost

300mm x 300mm x 8mm thick glazed ceramic floor tile RM2.90/piece

OPC 1m3 at 1420kg/m3 RM16.96/50kg

Normal mining sand at 1600kg/m3 RM37.81/tonne

Page 115: Estimating calculation

Wastage & Shrinkage for cement mortar 15%

Waste for ceramic tiles 10%

Labour Cost (8hours/day)

Unskilled Labour, Foreign RM52.50/day

Tiler, Skilled, Foreign RM87.20/day

Output Data

To mix 1m3 of cement mortar requires 1hour

To lay 1m2 of ceramic tiles requires 2hours

To do 1m2 pointing requires 0.5hour

Tendering factor:

Allow 15% for profit & overhead.

* Price for Plain 300mm x 300mm x 8mm thick glazed ceramic floor tile, Ordinary Portland Cement, normal mining sand, tiler skilled and unskilled labour rates are obtained from CIDB.

ELEMENT NO.8 – INTERNAL FLOOR FINISHES

Estimate the cost to finish 18m2 floor with 20mm thick cement and sand (1:3), smooth steel

trowelled.

CALCULATION

STEP 1: MATERIAL COST

Cement Mortar Mix (1:3) – m2

Ordinary Portland Cement including unloading:

1m3 at 1420kg/m3 at RM16.96/50kg = 1420kg/m3 x RM16.96/50kg =

Page 116: Estimating calculation

481.66

Sand at 3m3 at 1600kg/m3 at RM37.81/tonne = 1600kg/m3 x RM37.81/1000kg x 3 =

181.49

Gross Total 663.15

add 15% wastage & shrinkage = 663.15 x 15% = 99.47

Net total for 4m3

762.62

Divide by parts of mix (1:3) = 762.62 / 4 = 190.66/m3

Cost per m2 = 190.66 x 0.020 = 3.81/m2

STEP 2: LABOUR COST(m2)

To mix cement mortar

Unskilled labour @RM52.50/day = RM52.50 / 8hour = RM6.56/hour

Cost to mix 1m2 = RM6.56/hour x 1hour/m3 x 0.020m = RM0.13/m2

STEP 3: TOTAL COST (m2)

Total cost = Qty x rate = 18m2 x RM(3.81+0.13)/m2 = RM70.92

Add 15% profit & overhead = RM10.64

TOTAL RM 81.56

Estimate the cost to finish 86m2 floor with 20mm thick cement and sand (1:3) as backings

screed with approved adhesive mix with clean water; to receive floor tiles.

CALCULATION

STEP 1: MATERIAL COST

Cement Mortar Mix (1:3) – m2

Ordinary Portland Cement including unloading:

1m3 at 1420kg/m3 at RM16.96/50kg = 1420kg/m3 x RM16.96/50kg =

Page 117: Estimating calculation

481.66

Sand at 3m3 at 1600kg/m3 at RM37.81/tonne = 1600kg/m3 x RM37.81/1000kg x 3 =

181.49

Gross Total 663.15

add 15% wastage & shrinkage = 663.15 x 15% = 99.47

Net total for 4m3

762.62

Divide by parts of mix (1:3) = 762.62 / 4 = 190.66/m3

Cost per m2 = 190.66 x 0.020 = 3.81/m2

STEP 2: LABOUR COST(m2)

To mix cement mortar

Unskilled labour @RM52.50/day = RM52.50 / 8hour = RM6.56/hour

Cost to mix 1m2 = RM6.56/hour x 1hour/m3 x 0.020m = RM0.13/m2

STEP 3: TOTAL COST (m2)

Total cost = Qty x rate = 86m2 x RM(3.81+0.13)/m2 = RM338.84

Add 15% profit & overhead = RM 50.83

TOTAL RM 389.67

Estimate the cost to finish 4m2 floor: laid to fall not exceeding 15⁰ from horizontal with 20mm

thick cement and sand (1:3) as backings screed with approved adhesive mix with clean water;

to receive floor tiles.

CALCULATION

STEP 1: MATERIAL COST

Cement Mortar Mix (1:3) – m2

Ordinary Portland Cement including unloading:

1m3 at 1420kg/m3 at RM16.96/50kg = 1420kg/m3 x RM16.96/50kg =

481.66

Sand at 3m3 at 1600kg/m3 at RM37.81/tonne = 1600kg/m3 x RM37.81/1000kg x 3 =

181.49

Page 118: Estimating calculation

Gross Total 663.15

add 15% wastage & shrinkage = 663.15 x 15% = 99.47

Net total for 4m3

762.62

Divide by parts of mix (1:3) = 762.62 / 4 = 190.66/m3

Cost per m2 = 190.66 x 0.020 = 3.81/m2

STEP 2: LABOUR COST(m2)

To mix cement mortar

Unskilled labour @RM52.50/day = RM52.50 / 8hour = RM6.56/hour

Cost to mix 1m2 = RM6.56/hour x 1hour/m3 x 0.020m = RM0.13/m2

STEP 3: TOTAL COST (m2)

Total cost = Qty x rate = 4m2 x RM(3.81+0.13)/m2 = RM15.76

Add 15% profit & overhead = RM 2.36

TOTAL RM 18.12

Estimate the cost to finish 7m long, 100mm high drop with 20mm thick cement and sand (1:3)

as backings screed with approved adhesive mix with clean water; to receive floor tiles.

CALCULATION

STEP 1: MATERIAL COST

Cement Mortar Mix (1:3) – m

Ordinary Portland Cement including unloading:

1m3 at 1420kg/m3 at RM16.96/50kg = 1420kg/m3 x RM16.96/50kg =

481.66

Sand at 3m3 at 1600kg/m3 at RM37.81/tonne = 1600kg/m3 x RM37.81/1000kg x 3 =

181.49

Gross Total 663.15

add 15% wastage & shrinkage = 663.15 x 15% = 99.47

Net total for 4m3

762.62

Divide by parts of mix (1:3) = 762.62 / 4 = 190.66/m3

Page 119: Estimating calculation

Cost per m = RM190.66/m3 x 0.020m x 0.100m =

0.38/m

STEP 2: LABOUR COST(m)

To mix cement mortar

Unskilled labour @RM52.50/day = RM52.50 / 8hour = RM6.56/hour

Cost to mix 1m = RM6.56/hour x 1hour/m3 x 0.020m x 0.100m =

RM0.01/m

STEP 3: TOTAL COST (m)

Total cost = Qty x rate = 7m x RM(0.38+0.01)/m = RM 2.73

Add 15% profit & overhead = RM 0.41

TOTAL RM 3.14

Estimate the cost to finish 70m long, 150mm high skirting with 20mm thick cement and sand

(1:3) as backings screed with approved adhesive mix with clean water; to receive floor tiles.

CALCULATION

STEP 1: MATERIAL COST

Cement Mortar Mix (1:3) – m

Ordinary Portland Cement including unloading:

1m3 at 1420kg/m3 at RM16.96/50kg = 1420kg/m3 x RM16.96/50kg =

481.66

Sand at 3m3 at 1600kg/m3 at RM37.81/tonne = 1600kg/m3 x RM37.81/1000kg x 3 =

181.49

Gross Total 663.15

add 15% wastage & shrinkage = 663.15 x 15% = 99.47

Net total for 4m3

762.62

Divide by parts of mix (1:3) = 762.62 / 4 = 190.66/m3

Cost per m = RM190.66/m3 x 0.020m x 0.150m =

0.57/m

Page 120: Estimating calculation

STEP 2: LABOUR COST(m)

To mix cement mortar

Unskilled labour @RM52.50/day = RM52.50 / 8hour = RM6.56/hour

Cost to mix 1m = RM6.56/hour x 1hour/m3 x 0.020m x 0.150m =

RM0.02/m

STEP 3: TOTAL COST (m)

Total cost = Qty x rate = 70m x RM(0.57+0.02)/m = RM 41.30

Add 15% profit & overhead = RM 6.20

TOTAL RM 47.50

Estimate the cost to finish 86m2 floor with 300mm x 300mm x 5mm thick ceramic tiles in

glazed finish; “SIXNY 3-23001 WHITE” including; pointing and grouting with approved admix in

white cement.

CALCULATION

STEP 1: MATERIAL COST

Ceramic tiles – m2

No. of tiles per m2 = 1m2/(0.3mx0.3m) = 11.11 pieces

Gross cost per m2 @RM2.90/piece =11.11 x RM 2.90 = RM32.22

Add 10% wastage =RM32.22 x 10% =RM 3.22

Net cost per m2 =RM32.22 + RM3.22

=RM35.44/m2

STEP 2: LABOUR COST(m2)

To lay ceramic tiles and pointing

Tiler @RM87.20/day = RM87.20 / 8hour = RM10.90/hour

Cost to lay and point 1m2 = RM10.90/hour x (2+0.5)hour/m2 = RM27.25/m2

STEP 3: TOTAL COST (m2)

Total cost = Qty x rate =86m2 x RM(35.44+27.25)/m2 = RM5,391.34

Add 15% profit & overhead = RM 808.70

TOTAL RM 6,200.04

Page 121: Estimating calculation

Estimate the cost to finish 4m2 floor: laid to fall not exceeding 15⁰ from horizontal; with

300mm x 300mm x 5mm thick ceramic tiles in glazed finish; “SIXNY 3-23001 WHITE” including;

pointing and grouting with approved admix in white cement.

CALCULATION

STEP 1: MATERIAL COST

Ceramic tiles – m2

No. of tiles per m2 = 1m2/(0.3mx0.3m) = 11.11 pieces

Gross cost per m2 @RM2.90/piece =11.11 x RM 2.90 = RM32.22

Add 10% wastage =RM32.22 x 10% =RM 3.22

Net cost per m2 =RM32.22 + RM3.22

=RM35.44/m2

STEP 2: LABOUR COST(m2)

To lay ceramic tiles and pointing

Tiler @RM87.20/day = RM87.20 / 8hour = RM10.90/hour

Cost to lay and point 1m2 = RM10.90/hour x (2+0.5)hour/m2 = RM27.25/m2

STEP 3: TOTAL COST (m2)

Total cost = Qty x rate =4m2 x RM(35.44+27.25)/m2= RM 250.76

Add 15% profit & overhead = RM 37.61

TOTAL RM 288.37

Page 122: Estimating calculation

Estimate the cost to finish 7m long, 100mm high drop with 300mm x 300mm x 5mm thick

ceramic tiles in glazed finish; “SIXNY 3-23001 WHITE” including; pointing and grouting with

approved admix in white cement.

CALCULATION

STEP 1: MATERIAL COST

Ceramic tiles – m

No. of tiles per m = 1m2/0.3m = 3.33 pieces

Gross cost per m @RM2.90/piece =3.33 x RM 2.90 = RM9.66

Add 10% wastage =RM9.66 x 10% =RM0.97

Net cost per m =RM9.66 + RM0.97

=RM10.63/m

STEP 2: LABOUR COST(m)

To lay ceramic tiles and pointing

Tiler @RM87.20/day = RM87.20 / 8hour = RM10.90/hour

Cost to lay and point 1m = RM10.90/hour x (2+0.5)hour/m2 x 0.3m = RM 8.18/m

STEP 3: TOTAL COST (m)

Total cost = Qty x rate =7m x RM(10.63+8.18)/m = RM 131.67

Add 15% profit & overhead = RM 19.75

TOTAL RM 151.42

Page 123: Estimating calculation

Estimate the cost to finish 70m long, 150mm high skirting with 300mm x 300mm x 5mm thick

ceramic tiles in glazed finish; “SIXNY 3-23001 WHITE” including; pointing and grouting with

approved admix in white cement.

CALCULATION

STEP 1: MATERIAL COST

Ceramic tiles – m

No. of tiles per m = 1m2/0.3m = 3.33 pieces

Gross cost per m @RM2.90/piece =3.33 x RM 2.90 = RM9.66

Add 10% wastage =RM9.66 x 10% =RM0.97

Net cost per m =RM9.66 + RM0.97

=RM10.63/m

STEP 2: LABOUR COST(m)

To lay ceramic tiles and pointing

Tiler @RM87.20/day = RM87.20 / 8hour = RM10.90/hour

Cost to lay and point 1m = RM10.90/hour x (2+0.5)hour/m2 x 0.3m = RM 8.18/m

STEP 3: TOTAL COST (m)

Total cost = Qty x rate =70m x RM(10.63+8.18)/m = RM 1,316.70

Add 15% profit & overhead = RM 197.51

TOTAL RM 1,514.21

Page 124: Estimating calculation

ELEMENT NO. 9 – INTERNAL CEILING FINISHES1. Plasterboard Ceiling- We proposed to use Plain Gysum Board, ‘BORAL’, 610mm x 1220mm x 9.5mm to

replace 10mm thick ‘BORAL’ plasterboard. - We proposed to use Astino Aluzinc Batten 121 63.0mm x 26.0mm x 0.48mm (T) x 6.0m

(L) to replace 12mm x 32mm 0.4mm ceiling batten.

Data:Material Cost:

Plain Gysum Board, ‘BORAL’, 610mm x 1220mm x 9.5mm – RM 6.36/sheet* Allow 10% cutting wastage Screws required for general construction work 50 pcs/m2 at RM2.00/50pcs* Astino Aluzinc Batten 121 63.0mm x 26.0mm x 32.0mm 0.48mm (T) x 6.0m (L) –

RM 12.96 per unit*.

Labour Cost: 1 gang of carpenter consists of 2 carpenters and 1 unskilled labourer 1 gang of installer consists of one skilled labour and one unskilled labour. The daily rate for carpenter is RM96.50* for an 8 hours day The daily rate for skilled labourer is RM 61.90* for an 8 hours day The daily rate for unskilled labourer is RM52.50* for an 8 hours day

Labourer Output: The workers need 24 hours to install total area of 104m2 of plasterboard ceiling

with ceiling batten ( 24/104 = 0.23 h/m2 ) The workers need 0.23 hours to install 1 m2 plasterboard ceiling with ceiling

batten

Tendering Factor: Allow 15% of the total cost incurs for profit and overhead

* Price for Plain Gysum Board, ‘BORAL’, 610mm x 1220mm x 9.5mm, carpenter skilled and unskilled labour rates are obtained from CIDB.

* Price for screws is obtained from http://www.ewarehouse.atkc.com.my/combinedpanheadtappingscrew4x1(50pcs-pkt)?search=Screw&sort=p.price&order=ASC. The price is exclusive 6% GST.

* Price for Astino Aluzinc Batten 121 63.0mm x 26.0mm x 32.0mm 0.48mm (T) x 6.0m (L) is obtained from http://www.ewarehouse.atkc.com.my/astino-batten-121-63-0mm-x-26-0mm-x-32-0mm-0-48mm-t-x-6-0m-l?search=%20batten. The price is exclusive 6% GST.

Page 125: Estimating calculation

Calculation:Material Cost Plain Gysum Board, 610mm x 1220mm x 9.5mm = RM 6.36/sheet

= RM6.36 / (0.61 x 1.22) = RM 8.55/m2

Allow 10% cutting wastage = RM8.55 x 10% = RM 0.86/m2Screw = RM 2.00/m2

Add 6% GST = RM2.00 x 6% = RM 0.12/m2 Total Plasterboard Ceiling Cost

per m2 = RM11.53/m2

Astino Aluzinc Batten 121 63.0mm x 26.0mm x 0.48mm (T) x 6.0m (L) = RM12.96/unit

Average width = (63 + 26) / 2 = 44.5mm Batten in m2 = length x width = 6 m x 0.445m = 2.67m2

Ceiling Batten Cost per m2 = RM12.96 / 2.67m2 = RM 4.85/m2Add 6% GST = RM 4.85 x 6% = RM 0.49/m2

Total Ceiling Batten Cost per m2 = RM 5.34/m2

Total Material Cost per m2 = RM11.53/m2 + RM5.34/m2 = RM16.87/m2

Labour CostHourly rate: 2 carpenter at RM96.50/day = 2 x RM96.50/8 = RM24.13/hour

1 skilled labourer at RM61.90/day = RM61.90/8 = RM 7.74/hour 2 unskilled labourer at RM52.50/day = 2 x

RM52.50/8 = RM13.13/hour

Total hourly rate = RM 45.00/hour

Time required: 0.23h/m2 Total labour cost per m2 = RM 45/h x 0.23h/m2 = RM10.35/m2

Total CostTotal gross cost per m2 = Material cost/m2 + labour cost/m2

= RM16.87/m2 + RM 10.35/m2 = RM27.22Profit and Overhead = RM 27.22 x 15% = RM 4.08

Unit cost (m2) = RM31.30

Total Cost (m2)Unit cost (RM/m2) x total quantity (m2) = RM31.30 x 104m2 = RM 3255.20

2. Painting - one coat primer, two undercoats and one final emulsion paint

Page 126: Estimating calculation

Paint Data:Paint Materials Cost* Litres per 100m2

Primer RM120/5 litres 8.3Undercoat RM120/5 litres 7.2Final coat RM 38/litre 8.3

Allow 10% wastage for all works

Painter Data: 1 gang of painter consists of 1 painter and 1 unskilled labourer Daily rate for painter is RM88.00* for an 8 hours day. The daily rate for unskilled labourer is RM52.50* for an 8 hours day.

Painter output data:Paint Materials Hour per 100m2

Primer 5.0Undercoat 4.4Final coat 3.4

Tendering / Tools Cost: Allow 20% of the material cost for paint brush, accessories and other small tools

Tendering Factor: Allow 15% of the total cost incurs for the profit and overhead

*Cost of paint is obtained from Seng Bee Hardware & Timber Sdn Bhd, Mr. Lee*Daily rate for painter is obtained from CIDB

Calculation:Material cost:

Page 127: Estimating calculation

Cost / 100m21 coat primer = RM120 / 5 x 8.3 = RM199.20/100m22 undercoat = RM120 / 5 x 7.2 x 2 = RM345.60/100m21 final coat = RM 38 x 8.3 = RM315.40/100m2

RM860.20/100m2Allow 10% wastage = RM860.20 x 10 % = RM 86.02/100m2

RM946.22/100m2

Labour cost:Hourly rate

Painter at RM88.00/day = RM88/8 = RM11.00 Unskilled labourer at RM52.50/day = RM52.50/8 = RM 6.56

RM17.56

Time required to paint 100m21 coat primer = 5.00 hr/100m22 undercoat = 4.4 x 2 = 8.80 hr/100m21 final coat = 3.40 hr/100m2

Total time required to paint 100m2 = 17.20 hr/100m2

Total labour cost = hourly rate x time required= RM 17.56 x 17.20 hr/100m2 = RM302.30/100m2

Total cost per 100m2 including profit and overhead:Material cost + Labour cost = RM946.22 + RM302.30 = RM1248.52/100m2Allow 20% for tools = RM1248.52 x 20% = RM 249.70/100m2

Gross total cost per 100m2 = RM1498.22/100m2

Add profit and overhead = RM1498.22 x 15% = RM 224.73/100m2Total cost per

100 m2 = RM1722.95/100m2

Unit cost:Total cost per 100m2 / 100m2 = RM1722.95 / 100m2 = RM17.23/m2

Total cost:Unit cost x total quantity = RM17.23/m2 x 104m2 = RM1791.92

CADANGAN MEMBINA SATU RUMAH CONTOH DI ATAS LOT 123, MUKIMPETALING JAYA, NEGERI SELANGOR DARUL EHSAN

BILLS OF QUANTITIESBILL NO.4 - MAIN BUILDING WORKSELEMENT NO. 10 - EXTERNAL FINISHES

BQ REF ITEM DESCRIPTION UNIT QTY RATE (RM) TOTAL (RM)

Page 128: Estimating calculation

B4(10)/1/A

B4(10)/1/B

B4(10)/1/C

B4(10)/1/D

B4(10)/1/E

INSITU FINISHINGS20mm thick cement and sand (1:3) plastering with approved plasticizer as described:-Wall and column

20mm thick cement and sand (1:3) screed including smooth trowelled as described:-

To floor

3mm thick cement skim coat to soffit and sides of soffit as described:-

Not exceeding 3.00m above floor

PAINTINGPreparing; applying one coat of solvent based alkaline resisting primer; 2 undercoat and 1 final emulsion paint; “ ICI ” or approved equivalent:-

Plastered surface, wall and column

To soffit and sides of soffit not exceeding 3.00m above ground

M2

M2

M2

M2

M2

91

18

36

91

36

12

85

7

13

13

1092

1530

252

1169

463

Total Carry To Summary Page of Bill No.4 - Page B4(Summary)/

ELEMENT NO.10 - EXTERNAL FINISHES

Calculate the cost per m2 for the 20mm thick cement and sand (1:3) plastering with approved plasticizer as described to wall and column.

DATA:

Page 129: Estimating calculation

Materials:ITEM COST

Ordinary Portland Cement (50kg/bag) RM16.96/bagSand (Normal Mining Sand) RM37.81/m3

Shrinkage factor for (1:3) mix 30%Wastage factor for mixing mortar 10%

Labour rate:Skilled Labour RM85/day

Unskilled Labour RM63/day

Output data:- Plasticizer used is 6 litre/ton of cement at a cost of RM5.00/litre.- Coverage for 20mm thick plaster is 75m2 / 1000kg- Gang compromises 2 skilled & 1 unskilled labourers. Gang output for mix and apply is 100m2 in 18 hours.- Taking delivery & stacking cement at 20 nos of 50 kg bag per hour.

Material weight:- Density of cement is 1420 kg/m3- Density of sand is 1600 kg/m3

Tendering factor:- Allow 15% for profit and overhead.

* Cost of paint is obtained from Seng Bee Hardware & Timber Sdn Bhd, Mr. Lee

* Daily rate for plasterer is obtain from CIDB

Calculation :

Step 1: Material cost

Ordinary Portland Cement including unloading:1m3 at 1420kg/m3 at RM 16.96 / 50kg = 1420/50 x RM16.96 = 481.66

Page 130: Estimating calculation

Sand at 3m3 at 1600kg/m3 at RM37.81/m3 = 37.81 x 3 = 113.43 Gross Total 595.09 /4m3

Divide by parts of mix (1:3) = 595.09 / 4 = 148.77Plasticizer 6L/1000kg cement @ RM5/litre = 6/1000x(1420/4)xRM5.00 = 10.65 159.42

Add shrinkage, waste (30% + 10%) = 159.42 x (30% + 10%) = 223.19

Cost per m2 = 223.19 x 0.020 = RM 4.46/m2

STEP 2: Labour costLabour Gang:- 2 skilled labour @ RM85/person/day =RM85/8 x 2 = 21.25/hour- 1 unskilled labour @ RM63/person/day =RM63/8 x 1 = 7.88/hour Labour gang hourly rate (RM) = 29.13/hr

Coverage of plaster is 75m2/1000kg =1000/75 =13.33kgAssumed 1000kg is refers to cement only

Time required by labour:Delivery and Staking of 13.33 kg cement = [13.33/(20 x 50)]x1 = 0.013 hrMix and apply 1m2 = 18 hr / 100m2 =0.180hr Total time required 0.193 hr

Total labour cost per m2 = 0.193 x 29.13 = 5.62/m2

Step 3: Total cost (m2)

Total cost : Material + Labour = 4.46 + 5.62 = RM10.08Add 15 % profit & overhead = RM 1.51 TOTAL RM 11.59

Calculate the cost to finish 20 mm thick cement and sand (1:3) screed including smooth steel trowelled as described to floor.

DATA

Material cost:- Ordinary Portland Cement 1m3 at 1420kg/m3 at RM16.96/50kg

Page 131: Estimating calculation

- Sand 1600kg/m3 at RM37.81/tonne- Allow 33.33% waste and shrinkage for cement mortar

Labour cost:- Unskilled labour for cement mortar mix RM52.50/day(8 hrs)

Output data:- To mix 1m3 of cement mortar require 1 hour

* Dairy rate for general builder is obtain from CIDB

Calculation

Step 1: Material costCement mortar mix (1:3) - m2

Ordinary Portland Cement including unloading:1m3 at 1420kg/m3 at RM 16.96 / 50kg = 1420/50 x RM16.96 = 481.66

Page 132: Estimating calculation

Sand at 3m3 at 1600kg/m3 at RM37.81/m3 = 37.81 x 3 = 113.43 Gross Total 595.09

Add shrinkage, waste etc 33.33% = 595.09 x 33% = 198.34 Net total for 4m3 793.43

Divide by parts of mix (1:3) =793.43/4 =198.36/m3

Total Material Cost/m2 =198.36 x 0.020 = 3.97

Step 2: Labour cost

To mix cement mortar @unskilled labour rm52.50/day = RM52.50/8 = 6.56/ hr @cost to mix 1m2 =RM6.25x1x0.020 = 0.13 / m2 Total labour cost / m2 0.13

Step 3: Total Cost (m2)Total cost = 18 (3.97 + 0.13) =73.80Add 15% for profit and overhead =11.07 84.87

Calculate the cost to finish 3mm thick cement skim coat to soffit and sides of soffit as described to not exceeding 3.00m above floor.

DATA:

Materials rate:ITEM COST

Ordinary Portland Cement (50 kg/bag) RM16.96/bag

Page 133: Estimating calculation

SIKA Skim coat (25kg/bag) RM18.20/bagShrinkage factor 30%Wastage factor 10%

Labour rate:Skilled labour (foreign) RM85.00/dayUnskilled labour (foreign) RM63.00/day

Output data:- Plasticizer used is 6 litre/ton of cement at a cost of RM5.00/litre.- Coverage for 3mm thick plaster is 75m2 / 1000kg- Gang compromises 2 skilled & 1 unskilled labourers. Gang output for mix and apply is 100m2 in 18 hours.- Taking delivery & stacking cement at 20 nos of 50 kg bag per hour.

Material weight:- Density of cement is 1420kg/m3- Density of skim coat is 1.2kg/m

Tendering factor:- Allow 15% for profit and overhead

* Cost of paint is obtained from Seng Bee Hardware & Timber Sdn Bhd, Mr. Lee

* Daily rate for plasterer is obtain from CIDB

* SIKA Skim coat price is obtain from http://www.ewarehouse.atkc.com.my/sika-brefill-mortar-white-high-performance-base-finish-skimcoats-25kg?search=skim coat

Calculation:

Step 1: Material costOrdinary Portland Cement including unloading:1m3 at 1420kg/m3 at RM16.96/50kg =1420/50xRM16.96 =481.66

Skim coat at 3m3 at 1600kg/m3 at RM18.20/25kg =18.20 x 3 = 54.60 Gross Total 536.26

Page 134: Estimating calculation

Divide by parts of mix (1:3) =536.26/4 =134.07Plasticizer 6L/1000kg cement @RM5/litre =6/1000x(1420/4)xRM5.00 = 10.65 144.72

Add shrinkage, waste (30%+10%) = 144.72 x (30% + 10%) = 202.61

Cost per m2 = 202.61 x 0.003 = 0.61/m2

Step 2 : Labour cost

Labour gang 2 skilled @ RM85/person/day =RM85/8x2 =21.25/hr 1 unskilled @ RM63/person/day =RM63/8x1 = 7.88/ hr Labour gang hourly rate 29.13/hr

Coverage of plaster is 75m2/1000kgAssumed 1000kg refers to cement only =1000/75 =13.33kg

Time required by labourDelivery & staking of 13.33kg cement =[13.33/(20x50)]x1 =0.013hrMix & apply 1m2 =18hrs/100m2 =0.180hr

Total time required 0.193hr

Total labour cost per m2 =0.193x29.13 =5.62/m2

Step 3: Total costTotal cost = 0.61 + 5.62 = 6.23 Add 15% for profit and overhead = 0.93 RM 7.16 PAINTING

Preparing; applying one coat of solvent based alkaline resisting primer; 2 undercoat and 1 final emulsion paint; “ICI” or approved equivalent to plastered surface ; wall and column

DATA : Paint Data:

Material Cost Surface Litre/ 100m2Primer (Solvent based

alkaline resisiting) 120.00/5 litre Plastered 8.3Undercoat

120.00/5 litre Plastered 7.2Final coat( emulsion

paint) 38.00/1 litre Plastered 8.3

Page 135: Estimating calculation

*Allow 5% wastage for all works.Painter Data:- Daily rate for skilled labour (foreign) RM88/day (8 hrs)

Time required:Materials Surface Hr/100m2

Primer (Solvent based alkaline resisting) Plastered 6.6Undercoat

Plastered 5.8Final Coat ( emulsion

paint) Plastered 4.5

Tendering/ tool cost:- Allow 10% of material costTendering factor:- Allow 15% for profit and overhead.

* Cost of paint is obtained from Seng Bee Hardware & Timber Sdn Bhd, Mr. Lee

* Daily rate for painter is obtain from CIDB

Calculation:

Step 1: Material cost

1 coat primer = 120/5x8.3x1 =199.202 undercoat = 120/5x7.2x2 = 345.601 final coat =38/1x8.3x1 = 315.40

Page 136: Estimating calculation

860.20Add 5% wastage = 860.2x 0.05 = 43.01 903.21

Step 2: Labour costHourly rate Painter at RM88/8 =11.00

Time required to paint 100m21 coat primer =6.6 =6.62 undercoat =5.8x2 =11.61 final coat =4.5 = 4.5 Total time required to paint 100m2 = 22.70

Total labour cost =11.00 x 22.70 =249.70

Step 3: Total cost per 100m2 including profit and overhead

Material cost + labour cost =903.21 +249.70 = 1152.91Allow 10% for tool cost =1152.91 x 0.1 = 115.29Allow 15% for profit & overhead =115.29x0.15 = 17.29 1285.49Step 4: Unit cost1285.49/100 =12.85/m2

Step 5: Total CostQty req x unit rate = 91 x 12.85 = RM 1169.35

Preparing; applying one coat of solvent based alkaline resisting primer; 2 undercoat and 1 final emulsion paint; “ICI” or approved equivalent ; to soffit and sides of soffit not exceeding 3.00m above ground.

DATA:

Paint data:Material Cost Surface Litre/ 100m2

Primer (Solvent based alkaline resisiting) 120.00/5 litre Plastered 8.3

Undercoat120.00/5 litre Plastered 7.2

Final coat( emulsion paint) 38.00/1 litre Plastered 8.3

*Allow 5% wastage for all works.

Painter Data:

Page 137: Estimating calculation

- Daily rate for skilled labour (foreign) RM88/day (8 hrs)

Time required:Materials Surface Hr/100m2

Primer (Solvent based alkaline resisting) Plastered 6.6Undercoat

Plastered 5.8Final Coat ( emulsion

paint) Plastered 4.5

Tendering/ tool cost:- Allow 10% of material cost

Tendering factor:- Allow 5% for profit and overhead.

* Cost of paint is obtained from Seng Bee Hardware & Timber Sdn Bhd, Mr. Lee

* Daily rate for painter is obtain from CIDB

Calculation:Step 1: Material cost

1 coat primer = 120/5x8.3x1 =199.202 undercoat = 120/5x7.2x2 = 345.601 final coat =38/1x8.3x1 = 315.40 860.20Add 5% wastage = 860.2x 0.05 = 43.01

Page 138: Estimating calculation

903.21

Step 2: Labour costHourly rate Painter at RM88/8 =11.00

Time required to paint 100m21 coat primer =6.6 =6.62 undercoat =5.8x2 =11.61 final coat =4.5 = 4.5 Total time required to paint 100m2 = 22.70

Total labour cost =11.00 x 22.70 =249.70

Step 3: Total cost per 100m2 including profit and overhead

Material cost + labour cost =903.21 +249.70 = 1152.91Allow 10% for tool cost =1152.91 x 0.1 = 115.29Allow 15% for profit & overhead =115.29x0.15 = 17.29 1285.49Step 4: Unit cost1285.49/100 =12.85/m2

Step 5: Total CostQty req x unit rate = 36 x 12.85 = RM 462.60