    Mandal : Duggirala

    Estimate Cost Rs. #REF! Lakhs

    Grant :-

    Construction of side drains to internal roads in SC

    colony of Godavarru village of Duggirala Mandal.

    Estimate

    Name of the work

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    2/14

    Nominal mix 1:3:6 with 40mm HBG metal for Bed Concrete 0.10m depth is

    proposed.

    PCC M15 Concrete mix for Drain Wall is proposed to a length of 843.00 mts on

    both sides of the road is proposed.

    ,

    0.5%,PS Charges @ 0.3%, labour cess @ 1%, etc are shown in the detailed estimate.

    The above estimate is prepared with current S.S.R of 2012-2013. The work will be

    executed as per the APDSS.

    Earthwork in excavation for structures as per drawing and technical

    specifications Clause 305.1

    Sand filling 200mm th for shoe wall fondation is proposed.

    Specification report to accompany the detailed estimate for the work

    Construction of side drains to internal roads in SC colony of Godavarru village of

    Duggirala Mandal.

    Est.Rs. 23.00 Lakhs.

    The above work was proposed under indiramma Infrastructure funds.Hence detailed estimate is prepared with the following provisions.

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    3/14

    Est.Rs. 23.00 Lakhs.

    No

    s

    L

    (m)

    B

    (m)

    D

    (m)

    1 2 3 4 5 6 8 9 10

    1

    Main road 1 x 2 185.00 0.80 0.45 133.20 Cum

    Cross roads 7 x 2 40.00 0.80 0.45 201.60 Cum

    --- Do-- 7 x 2 54.00 0.80 0.45 272.16 Cum

    606.96 Cum 128.82 1Cum 78189

    2

    Main road 1 x 2 185.00 0.80 0.15 44.40 Cum

    Cross roads 7 x 2 40.00 0.80 0.15 67.20 Cum

    --- Do-- 7 x 2 54.00 0.80 0.15 90.72 Cum

    202.32 Cum 479.85 1Cum 97083

    3

    P.C.C grade M 10

    Main road 1 x 2 185.00 0.80 0.10 29.60 Cum

    Cross roads 7 x 2 40.00 0.80 0.10 44.80 Cum

    --- Do-- 7 x 2 54.00 0.80 0.10 60.48 Cum

    134.88 Cum 3465.68 1 Cum 467450

    Filling Sand in foundation trenches as per drawing and technical

    specification Clause 305.3.9 MORD & 304 MORTH

    Providing concrete for plain concrete in open foundations using 40 mm

    nominal size Graded hard stone aggregate, mechanically mixed, placed in

    foundation and compacted by vibration including curing for 14 days

    complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 MORD and 1500, 1700 & 2100 MORTH. for Bed Concrete

    Plain cement concrete in substructure complete as per drawings and

    Name of the work :Construction of side drains to internal roads in SC colony of Godavarru

    village of Duggirala Mandal.

    7

    Earthwork in excavation for structures as per drawing and technical

    specifications Clause 305.1 including setting out, construction of shoring

    and bracing, removal of stumps and other deleterious material and disposal

    upto a lead of 50 m, dressing of sides and bottom and backfilling in

    trenches with excavated suitable material as per Technical Specification

    305 MORD / 304 MORTH

    ESTIMATE DETAILED AND ABSTRACT

    SL

    No.Description of Item

    Measurements

    Quantity Rate PerAmount

    (Rs.)

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    4/14

    1 2 3 4 5 6 8 9 107

    6 Add Vat Tax @ 5% 100692.00

    7 10069.00

    8 Seignorage charges 50216.00

    9 PS Charges @ 3% 60415.00

    10 Labour Cess at 1% 20138.00

    11 44633

    Total Rs 2300000

    Provision for Q.C.Charges @0.50%

    Unforseen items if any

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    5/14

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    6/14

    0

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    7/14

    23.00 Lakhs

    Index-

    codeDescription Unit Quantity Rate Rs. Amount Rs.

    2 3 4 5 6

    1 Excavation for Structures

    (I) Ordinary soil

    (A) Manual Means

    (i) Upto 3 m depth

    Unit = cumTaking output = 10 cum

    a) Labour

    Mazdoor (Unskilled) day 3.64 250.00 910.00

    Add 20% MAA on Labour

    . Add seignorage charges cum 10.00 22.00 220.00

    Cost for 10 cum = a+b+c 1130.00

    158.20

    Rate per cum = (a+b+c)/10 1288.20

    128.82 1Cum

    2

    Sand filling Sand

    Unit = cum

    Add contractor profit and over head charges at 14%

    Earthwork excavation in B.C soils for structures as per

    drawing and technical specifications Clause 305.1 including

    setting out, construction of shoring and bracing, removal of

    stumps and other deleterious material and disposal upto a lead

    of 50 m, dressing of sides and bottom and backfilling in

    trenches with excavated suitable material as per Technical

    Specification 305 MORD / 304 MORTH

    Note : Classifications of Earth Work Specification are as

    per 302.2.1(a) of MORD and 301.2.1 of MORT&H

    R-FNDN-2

    Filling in foundation trenches with sand as per drawing and

    technical specification Clause 305.3.9 MORD & 304 MORTH

    DETAILED DATAS

    Grant: Est.Cost:Rs

    S. No

    1

    Construction of side drains to internal roads in SC colony of Godavarru

    village of Duggirala Mandal.Name of the work :

    RBR-FNDN-1

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    8/14

    (a) Material

    Cement t 0.22 4500.00 990.00

    Coarse sand cum 0.45 434.12 195.35

    40mm HBG Metal cum 0.90 1313.78 1182.40

    Water kl 1.20 0.00 0.00

    (b) LabourMason (1st Class) day 0.10 350.00 35.00

    Mazdoor (Unskilled) day 1.39 280.00 389.20

    Add 20% MAA on Labour

    (c) Machinery

    Mechanical concrete mixer

    0.4/0.28 cum capacity f itted with

    water measuring device and

    preferably also with load cell.

    hour 0.40 417.40 166.96

    Water tanker 6 kl capacity hour 0.13 624.00 81.12

    Rate per cum = a+b+c+d+e+f 3040.04

    425.61

    Sundries 0.03

    3465.68 1Cum

    4 5) I) i

    For height upto 5 m

    Unit = cum

    P.C.C grade M 15

    Nominal mix (1:2.5:5) using CC

    Mixer (MORD)

    Unit = cum

    (a) Material

    Cement t 0.275 4500.00 1237.50

    Add contractor profit and over head charges at 14%

    Plain cement concrete in substructure complete as per drawings and

    technical specification Clauses 802, 804, 805, 806, 807, 1202 and

    1204 MORD and 1500, 1700 & 2200 MORTH

    Note : Water for concrete :A provision for cost of water may be

    added at 1.2 kl / 1 cum (including curing purpose) keeping the site

    Coarse Aggregate : Single grade nominal size can also be used

    instead of graded metal, keeping the site conditions in view

    RBR-SBST-5

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    9/14

    Rate per cum = a+b+c+d+e+f 3637.90

    509.31

    Sundries 0.06

    4147.27 1Cum

    5 5 Sub Analysis:

    Cement Mortar (1 : 5)

    Unit : 1cum

    A. MATERIALS:

    Cement kg. 288.0 4.50 1296.00

    Sand (including 5% wastage) cum 1.05 434.12 455.83

    B. MACHINERY

    - Nil - -

    C. LABOUR:

    Man mazdoor for mixing mortar day 0.20 280.00 56.00

    Grand Total 1807.83

    6 3)c)

    Unit = 10 sqm

    Taking output = 10 sqm(a) Material

    Cement mortar 1:5 (Rate as in

    item 11.5 II )

    cum 0.144 1807.83 260.33

    (b) Labour

    Mate day -

    Mason 1st Class day 0.500 350.00 175.00

    Mazdoor (Unskilled) day 0.540 280.00 151.20

    Rate per 10 sqm = (a+b+c+d) 586.53

    82.11

    668.64

    66.86 1Sqm

    Add contractor profit and over head charges at 14%

    Add contractor profit and over head charges at 14%

    RBR-SBST-3

    Plastering with cement mortar (1:5), 12 mm thickness as

    per technical specification 1300 & 2200 MORTH

    RBR-FNDN-5

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    10/14

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    11/14

    0

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    12/14

    Name of the work : Construction of side drains to internal roads in SC colony of Godavarru village of Duggirala Mandal.

    23.00 Lakhs.

    1 2 3 4 5 6 7 8 9 12 13 14 15 16 17

    1 Sand for Concrete krishnariver 3 385.00 0.00 0.00 385.00 56.00 0.00 -6.88 49.12 434.12 ./cum

    2 Coarse Sand for filling krishnariver 3 285.00 0.00 0.00 285.00 56.00 0.00 -6.88 49.12 334.12 ./cum

    3 Gravel Vejendala 37 98.00 0.00 0.00 98.00 450.00 0.00 -55.26 394.74 492.74 ./cum

    4Aggregates 40 mm

    nominal size SS5Lam 50 588.00 70.00 147.00 805.00 580.00 0.00 -71.22 508.78 1313.78 ./cum

    5Aggregates 20 mm

    nominal size SS5Lam 50 984.00 70.00 246.00 1300.00 580.00 0.00 -71.22 508.78 1808.78 ./cum

    6Aggregates 12 mm

    nominal size SS5Lam 50 780.00 70.00 195.00 1045.00 580.00 0.00 -71.22 508.78 1553.78 ./cum

    7 Cement Tenali 25 4600.00 0.00 0.00 5700.00 0.00 0.00 0.00 0.00 5700.00 ./Mt

    8300 dia. RCC NP2 class

    Plain ended pipesTenali 25 348.00 0.00 0.00 348.00 2 2.60 0.00 0.00 22.60 370.60 ./1Rm

    Initial

    Charges

    AddBlasting

    charges

    Machine

    crushing

    charges@

    25%

    Netbasiccost

    Units

    Est.Cost:

    Conveyance Cost

    Add

    Conveyance

    ChargesName of

    Quarry

    Lead in

    KM

    DeductCP&

    OH(12.28%)

    Material Basic Cost

    Est.Cost Rs..

    LEAD STATEMENT

    2. Certified that the metal is obtained by blasting.

    loading

    chargesSl.

    No

    Certificates :

    1. Certified that the above leads are shortest and correct to the best of my knowledge and belief.

    Discription of Item

    NetConveyanc

    e

    Charges

    AddSeigniorag

    e

    Charges

    Total Cost

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    13/14

  • 8/13/2019 Est Drain SC-Colony Godavarru 1

    14/14

    Sl No Unit Qty Metal Sand Earth Work

    1 1Cum 606.96 0.00 0.00 606.96

    2 PCC M10 mix(1:3:6) for Bed Concrete 1Cum 134.88 121.39 60.70 0.00

    3 1Cum 202.32 0.00 202.32 0.00

    PCC M15 mix For Drain Wall 1Cum 310.22 279.20 139.60 0.00

    4 10Sqm 1264.50 0.00 18.21 0.00

    400.59 420.82 606.96

    50.00 40.00 22.00

    20029.50 16832.95 13353.12

    50215.57 or 50216.00

    SEIGNORAGE CHARGES

    Name of Work : - Construction of CC Drains at Karrevari Bazar,SC Colony,Gudiwada(V) of Tenali(M)

    Description of Item

    Eart Work

    Filling with Sand

    Plastering CM (1:5) 12mm thick