ESS Programme Plan and Schedule Update C. Darve, Deputy WP05 and WP04 leader Acknowledgement: N....
-
Upload
augusta-caren-jenkins -
Category
Documents
-
view
218 -
download
2
Transcript of ESS Programme Plan and Schedule Update C. Darve, Deputy WP05 and WP04 leader Acknowledgement: N....
ESS Programme Plan and Schedule Update
C. Darve, Deputy WP05 and WP04 leader
Acknowledgement: N. Elias, WP05 and WP04
P. Bosland, WP05 leader
https://ess-ics.atlassian.net/wiki/display/CRYOM/Cryomodules+Collaboration+space
2
Headline
ESS Programme Plan Scope
– Life-cycle flow for the cavities and cryomodules– Interface requirements between cavities and cryomodules see afternoon Workshop– Acceptance criteria and NC see afternoon Workshop– Use lessons-learned from ECCTD (and XFEL)
Schedule (time)
ESS Technical Annex (“schedule”)– PDR– CDR– Data packages– Tracking progress
Communication channels:– Follow-up– Collaboration Space web site– Video-conferences
3
Headline
ESS Programme Plan Scope
– Life-cycle flow for the cavities and cryomodules– Interface requirements between cavities and cryomodules see afternoon Workshop– Acceptance criteria and NC see afternoon Workshop– Use lessons-learned from ECCTD (and XFEL)
Schedule (time)
ESS Technical Annex (“schedule”)– PDR– CDR– Data packages– Tracking progress
Communication channels:– Follow-up– Collaboration Space web site– Video-conferences
Scope: Cavities and Cryomodules life-cycle
Cavity Cryomodule Technology Demonstrators:1 x Medium-beta, M-ECCTD <= FR-SW agreement1 x High-beta, H-ECCTD <= CEA/CNRS Early In-Kind
Production of cavities of the series with RF tests:36 x operating Medium-beta cavities <= LASA In-Kind84 x operating High-beta cavities <= STFC In-Kind
Production of all other cryomodule components (incl PC, CTS): <= CEA In-Kind
Cryomodule assembling: <= CEA In-Kind
Low-power tests of 3 first medium and high-beta cryomodules <= CEA FR In-KindRF and cryogenics for low power testing
Transport of cryomodules from assembly hall to ESS: 9 x Medium-beta cryomodules <= STFC In-Kind21 x High-beta cryomodules <= STFC In-Kind
4
5
Name Description ClarificationPlug-compatible cavity design
The cavities installed in the MBL cryomodules shall be designed such that they are plug-compatible with the cryomodule designed for the MB-ECCTD
"Plug compatible" means that no alterations to the design of the remainder of the cryomodule components are necessary, e.g. Anchoring system. Note that design alterations resulting from the results of the MB-ECCTD are not ruled out by this requirement.
R/Q The R/Q of the cavities designed for the MBL cryomodules shall not differ from that of the ECCTD cavity by more than +/-3.5%
R/Q should be calculated at a beam velocity of beta = 0.705. Note that no alteration of the geometric beta of the cavity is suggested by the use of this value for beta.
Epeak/Eacc The ratio of the peak surface electrical field (Epeak) to the accelerating gradient (Eacc) for the cavities installed in the MBL cryomodules shall not exceed that of the ECCTD cavities
Eacc should be calculated for a beam velocity of beta = 0.705. Note that no alteration of the geometric beta of the cavity is suggested by the use of this value for beta.
Interface requirements between cavities and cryomodules
Cavity design shall be compatible with :• Cold tuning system• Power coupler• Cryomodules component, e.g. thermal and magnetic
shield, tie-rod system• Assembly procedures• Tooling handeling• Use the technologies demonstrated via the ECCTD
Preliminary
6
Cryomodule & main components
Similar to CEBAF/SNS cryomodule concept with 4 cavities per cryomodule
Common cryomodule design for medium and high beta cavities
Medium High
Geometrical beta 0.67 0.86Frequency (MHz) 704.42Maximum surface field in operation (MV/m) 45 45
Nominal Accelerating gradient (MV/m) 16.7 19.9
Nominal Accelerating Voltage (MV) 14,3 18,2
Q0 at nominal gradient > 5e9Cavity dynamic heat load (W) 4,9 6,5
Power Coupler(HIPPI type coupler)
• Diameter 100 mm • 1.1 MW peak power• Antenna & window water cooling• Outer conductor cooled with SHe• Doorknob transition equipped with a bias system
Cold Tuning System(Saclay V5 type modified for ESS cavities)
• stepper motor + gear box at cold• Max tuner stroke: ± 3 mm• Max tuning range: ~ 600 kHz• Tuning resolution: ~1 Hz• 2 piezo staks
Cavities without HOM coupler
5 cells high beta (0,86) cavity6-cells medium beta
(0,67) cavity
7
Cavity Production
Transport to CEA
Assembly in Cryomodule
Acceptance Test in VC
Acceptance Test @ CEA-
in* Possible “partner’s transfer flagpoint”
*
Transport to ESS
Acceptance Test @ CEA-
out
*Acceptance
Test @ ESS-in High Power Test @ ESS
Acceptance Test Tunnel
Ready For InstallationIn tunnel
INFN/STFC
ESS/STFC
CEA
Scope: Cavities and Cryomodules Life-cycle
Ready For Assembly in CM
8
Cavity Production
Transport to CEA
Assembly in Cryomodule
Acceptance Test
Acceptance Test
NC
Report
NCMinor
NCRepairable
at CEA
NC
Report
NCNot
Repairable at CEA
Repair
Out of Work
Data management and dealing with non-conformance
* “partner’s transfer flagpoint”
*
*
NCMinor
NCRepairable at
STFC/LASA
NCNot Repairable at STFC/LASA
9
Data management
Action items:- Define a general Data management system, based on a simplified version of the XFEL DB, to
be implemented at the ESS. Study: system functionality and select data to store.
- Define simplified Data management system at ESS, CEA, LASA, STFC, Desy, Zanon, RI, etc..
10
M&H Technology Demonstrators
Engineering studies completed
Fabrication of the components in progress
Assembly infrastructure and procedures
Preparation of the test stands (coupler processing & cryomodule tests)
11
Technology Demonstrators: ECCTD
The goals of the ECCTD are to verify/validate the design to initiate the series production.
It shall verify (but not necessarily be limited to):
• Fabrication process and industrialization of ALL cryomodule components: e.g. Fabricate successfully the SRF 704 MHz cavities, chemical and heat treatments, power couplers, CTS, cryomodule equipment, assembly procedures, etc
• Validate RF design: e.g. performance of cavities in vertical cryostat and on the test stand; power coupler performance, test slow tuning system, fast tuning System, LLRF
• Validate thermal and vacuum cryomodule design: eg. cool-down rate, operating conditions; heat loads; cooling scheme efficiency, leak tightness;
• Validate the alignment techniques.
• Validate the toolings design: e.g. handling and transportation
• Validate the verification procedure and threshold: e.g. Acceptance criteria process, SAT, FAT
• Verify the non-conformity tracking process.
• Control command: e.g. Validate the PLC sequences and the fast acting system, verify the operating algorithms
• ES&H e.g. Complete risk analysis, Cavities and CM mechanical relief sizing.
• Training: e.g. fabrication follow-up, testing procedure, assembly, operation,
12
Ex: “HoA - ANNEX C: H-ECCTD Test Plan”
Before installation:vacuum tightness checks
alignment measurements
After installation / RF power OFF: Cryogenics and vacuum connections leak checks
Temperatures measurement during cool down
Static losses measurement
RF resonant frequencies measurement (fundamental and HOMs)
Alignment measurement at room temperature and at cold temperature
At cold temperature with RF power (limited to 3 months)Measurement of every cavity from 1 to 4 at low power:
external coupling factors measurements: Q i, Qt
Tuning operations study
Test of every cavity from 1 to 4 at high power in pulsed modeMaximum accelerating gradient measurement
Lorentz force detuning compensation study
Dynamic losses at 2 K measurement
Field emission thresholds and quench limits determination
Cryogenic behaviors study
Temperature measurements
Couplers: variation of He mass flow and CM consumption as a function of RF power (to optimize coupler static losses)
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
PROTOTYPES ECCTD 34 ms Jeu 01/01/15 Lun 13/11/17
M-ECCTD 27 ms Jeu 01/01/15 Mar 11/04/17
Tests 4 ms Lun 10/10/16 Mer 08/02/17
Mid-test flag 0 ms Ven 09/12/16 Ven 09/12/16
PRR review decision 0 ms Ven 23/12/16 Ven 23/12/16
End of the tests - Disassembly 2 ms Jeu 09/02/17 Mar 11/04/17
H-ECCTD 28 ms Lun 06/07/15 Lun 13/11/17
Tests 2 ms Mer 13/09/17 Lun 13/11/17
Mid-test flag 0 ms Ven 13/10/17 Ven 13/10/17
PRR review decision 0 ms Ven 13/10/17 Ven 13/10/17
CAVITIES 49 ms Ven 23/12/16 Mer 10/02/21
Medium beta production (INFN) (36) 21 ms Ven 23/12/16 Mar 02/10/18
Cavity delivery (3 cav/m.) 12 ms Jeu 28/09/17 Mar 02/10/18
High beta production (STFC) (84) 39 ms Ven 27/10/17 Mer 10/02/21
Cavity delivery (3 cav/m.) 30 ms Jeu 02/08/18 Mer 10/02/21
COUPLERS 64 ms Lun 01/06/15 Mer 21/10/20
Conditioning stand 24 ms Lun 01/06/15 Mer 07/06/17
Manufacturing & RF processing (36+84) 51 ms Lun 01/06/15 Mar 17/09/19
Pre-serial manufacturing (4) 13 ms Ven 09/12/16 Ven 12/01/18
RF conditionning Pre-serial (2 pairs) 6 ms Jeu 08/06/17 Ven 08/12/17
Restart serial prod delay 4 ms Ven 08/09/17 Mar 09/01/18
manufacturing MBC 1-36 (6cpl./m.) 6 ms Mer 10/01/18 Jeu 12/07/18
RF conditionning MBC (4 cpl./m.) 10 ms Mar 13/03/18 Lun 14/01/19 Mb couplers processing manufacturing HPC 1-84 (6cpl./m.) 14 ms Ven 13/07/18 Mar 17/09/19
RF conditionning HBC 1-44 (4 cpl./m.) 11 ms Mar 15/01/19 Mer 18/12/19 Hb couplers processing RF conditionning HBC 45-84 (4 cpl./m.) 10 ms Jeu 19/12/19 Mer 21/10/20 Hb couplers processing
CRYOMODULES 75,64 ms Mar 01/09/15 Ven 14/01/22
Components manufacturing 54 ms Mar 01/09/15 Jeu 19/03/20
MBL Modules assembly 16 ms Ven 29/12/17 Lun 06/05/19
Assembly 14 ms Ven 29/12/17 Mar 05/03/19
n°1 4 ms Ven 29/12/17 Mar 01/05/18
n°2-3 4 ms Mer 02/05/18 Ven 31/08/18
n°4-9 6 ms Lun 03/09/18 Mar 05/03/19
RF power tests at Lund 11 ms Ven 01/06/18 Lun 06/05/19
n°1 2 ms Ven 01/06/18 Mer 01/08/18
n°2-3 3 ms Jeu 02/08/18 Jeu 01/11/18
n°4-9 6 ms Ven 02/11/18 Lun 06/05/19
HBL Modules 33 ms Ven 05/04/19 Ven 14/01/22
Assembly 31 ms Ven 05/04/19 Lun 15/11/21
n°1-11 16 ms Ven 05/04/19 Lun 10/08/20
n°12-21 15 ms Mar 11/08/20 Lun 15/11/21
RF power tests at Lund 31 ms Jeu 06/06/19 Ven 14/01/22
n°1-11 16 ms Jeu 06/06/19 Ven 09/10/20
n°12-21 15 ms Lun 12/10/20 Ven 14/01/22
2021 20222015 2016 2017 2018 2019 2020
HBL cryomodules
MBL cryomodulesMBL assembly
CM manufacturingCryomodules procurement assembly and tests
Couplers procurement assembly and testsConditionning stand
Manufacturing & RF processing
Cavities production Mb & HbMb cavities prod
Mb delivery
Hb cavities deliveryHb cavities production
Task name duration start date end date
1
2
6
MBL tests
1
2
6
11 HBL
10 HBL
tests 21 HBL
11 HBL
11 HBL
Assembly 21 HBL
1st April 2015 TAC11 13
M-ECCTD CDR review decision
H-ECCTD CDR review decision
2) Power couplers contract awarded
RF power source ready for coupler processing
Cryomodule components contract awarded
Planning Ready For Installation OK with ESS schedule:03/09/18 => 02/05/19 1CM/month
Planning Ready For Installation OK with ESS schedule:Q1 + Q2 2021: installation of HBL n° 1 to 11Q1 + Q2 2022: Installation of HBL n° 12 to 21
Overall WP5 planning
1) Mb cavities contract awarded
1) Hb cavities contract awarded
Mb – CDR – 15/09/16
Hb – CDR – 15/09/17
CDR – 23/12/16
CDR – 13/10/17
14
Proposed Milestones for LASAIKC “Technical Annex”
15
Proposed Milestones for LASA IKC “Technical Annex”
16
Proposed Milestones for STFC IKC “Technical Annex”
17
Proposed Milestones for STFC IKC “Technical Annex”
18
Headline
ESS Programme Plan Scope
– Life-cycle flow for the cavities and cryomodules– Interface requirements between cavities and cryomodules see afternoon Workshop– Acceptance criteria and NC see afternoon Workshop– Use lessons-learned from ECCTD (and XFEL)
Schedule (time)
ESS Technical Annex (“schedule”)– PDR– CDR– Data packages– Tracking progress
Communication channels:– Follow-up– Collaboration Space web site– Video-conferences
19
Technical Annex - TOC
SCHEDULE AIK [ACCSYS WP NUMBER . ACCSYS IKC REGISTER NUMBER] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS and [name of partner] on DATE
1. Scope
2. Related documents
2.1 Applicable Documents
2.2 Reference documents
3. Terms and Definitions
4. Project definition
4.1 Deliverable Item definition
4.2 Project Stages Definition
4.2.1 Stage 1: Design Stage
4.2.2 Stage 2: Realization and Verification
4.2.3 Stage 3: Installation, Commissioning and Initial Operations
20
PDR - Definition
“Preliminary Design Review(s) reviews preliminary design, sometimes referred to as conceptual design. A PDR assesses preliminary design options and decisions in comparison with ESS input baseline reference design including requirements.
A successful PDR demonstrates that design is sufficiently developed, clear and agreed between ESS and the Partner.
Preliminary design updates the baseline reference design which was agreed at Kick-off, and a successful PDR establishes a new baseline, described in [CMP] The ‘Allocated Baseline’ from which the Partner may proceed to detailed design, including any agreed pre-series prototyping.
For planning purposes, a PDR should be limited to no more than one working day.”
21
PDR - DeliverablesThe contents of the technical data package for PDR(s) shall include but not be limited to:• Requirements, agreed or proposed updates to documents comprising the baseline reference
design.
• Design Reports, including reports of prototyping and other preliminary design-related analyses, tests, simulations.
• Design Data, (preliminary design level of detail) including 3D CAD models and CAD drawings, general arrangement drawings, P&ID, FE models, etc., and interface descriptions including at least interface identification and any preliminary design definition.
• RAMI Report, an initial version of a report of the estimation of the probability and consequences of failures in equipment as well as main maintenance tasks and proposed spare parts.
• Safety Report, an initial version of the safety risk assessment report (including identifying hazards and evaluating likelihood of incidents occurring and severity of potential consequences, also list of existing control measures).
• [PQP], any outline draft for the Project Quality Plan including initial identification of Standards to be applied, initial planning for compliance testing and inspection, and initial planning for verification.
22
CDR - Definition
“Critical Design Review(s) conclude Stage 1. The CDR assesses if the design meets all facility element requirements with acceptable risk and within the cost and schedule constraints.
The CDR demonstrates that the maturity of the design is appropriate to support proceeding with full-scale fabrication, assembly, integration, test, and future operation and decommissioning.
The CDR should also review initial planning for verification.
Detailed design updates the baseline reference design which was agreed at
Kick-off, and any ‘Allocated Baseline’ of preliminary design established by PDR. A successful CDR establishes a new baseline, described in [CMP] as the ‘Design Baseline’ from which the Partner may proceed to Stage 2 Realisation and Verification. “
23
CDR
“The contents of the technical data package for CDR(s) shall include but not be limited to:
Requirements, agreed or proposed updates to documents comprising the baseline reference design.
• Design Reports, including reports of prototyping and other design-related analyses, tests, simulations.
• Design Data, (detailed design level) including 3D CAD models and CAD drawings, general arrangement drawings, P&ID, FE models, etc., and detailed interface descriptions including interface identification and definition for controlling interface design.
• RAMI Report, a report of the estimation of the probability and consequences of failures in equipment as well as main maintenance tasks and proposed spare parts.
• Safety Report, safety risk assessment report (including identifying hazards and evaluating likelihood of incidents occurring and severity of potential consequences, also list of existing control measures).
• Verification Plan, (including planned FAT and SAT activities)
• [PQP], a full draft for the Project Quality Plan including identification of Standards applied in design, procurement, manufacture and assembly, and planning for compliance testing and inspection.”
24
CDR
“The CDR data package shall also contain documentation to initiate a competitive tender for the procurement of the facility element and to support the project activities. The CDR data package should additionally include but not necessarily be limited to:
Procurement Package, a complete documentation package for the procurement of the facility element including as a minimum a statement of work, manufacturing follow-up description, applicable and reference documentation
Project Plan , updated plan in Gant chart form, describing in detail remaining Stage 1 activities, describing in detail Stage 2 Realisation & Verification activities, and an outline of any Stage 3 Installation, Commissioning and Initial Operations activities for the Partner.
Risks, Risk Register, showing identified project management risks and/or technical risks.”
25
Example of status/doc at CDR-phaseTo start stage 2 the necessary prerequisite are the following:• The interface document of the cryomodules with the tests stations at CEA Saclay, with the
transport to ESS-Lund, with the test stand at ESS-Lund and with the LINAC infrastructure is settled by the end of stage 1.
• The acceptance criteria for the cryomodule assembly are settled by the end of stage 1. The ESS acceptance management process is operational.
• The verification plan followed up all along the cryomodule assembly, at the test stand at Saclay until the shipment to ESS-Lund is settled by the end of stage 1.
• The configuration items for cryomodule is clearly defined. • The cavity string configuration with individual cavity performance for each cryomodule is known 3
weeks before the assembly.• The last version of all assembly drawings and P&ID is released at the end of stage 1. Each
design change needs an acceptance from CEA and the assembly drawing has to be updated and released to CEA.
• The ESS change management process is operational. • The ESS-“CHESS” interface is operational to upload the cryomodule assembly documentation.• The ESS non-conformity management process is operational.• Transport test is successfully performed.• Could this sentence be more specific?• Should we clearly refer to a “document management database”?
26
Headline
ESS Programme Plan Scope
– Life-cycle flow for the cavities and cryomodules– Interface requirements between cavities and cryomodules see afternoon Workshop– Acceptance criteria and NC see afternoon Workshop– Use lessons-learned from ECCTD (and XFEL)
Schedule (time)
ESS Technical Annex (“schedule”)– PDR– CDR– Data packages– Tracking progress
Communication channels:– Follow-up– Collaboration Space web site– Video-conferences
27
Communication channels
• SRF collaboration Kick-off meeting at Saclay: 23 June 2015
• SRF collaboration at STFC: 15 December 2015
• Medium-beta cavity design: 2-3 November 2015
• Weekly Vidyo meeting: Fridays mornings
• Monthly Project reports
Collaborative Project Objectives: • Freeze the cavities design • List interfaces requirements• CEA needs to analyse the impact on the cryomodule design and on the
toolings before approval• Track actions items • Etc
Cryomodules Collaboration space
Interface between Cryomodule and Cavities- Within EMR
2015-11-02 Interfaces Meeting @ LASA - Medium-beta cavity/cryomodules
2015-12-15 Interface Meeting @ STFC - Collaboration for SRF Elliptical Cavities Collaboration
Interface with Radio-Frequences - RFS - WP08
Interface with RF sources
Interface with RFS/LLRF2015-06-10 - Interface Meeting between EMR and LLRF - Meeting notes (LLRF Interface)
2015-10-21 - Interface Meeting between EMR and RF systems - Meeting notes
Interface with RFS/RFDS
Interface with RFS/Interlocks
Interface with Cryogenics (Cryoplant, Distribution System) - CRYO - WP11
2015-02-16: Interface Meeting - Cryogenic InstrumentationMinutes of meeting 16-Feb-2015 (Cryogenic Instrumentation)
2015-03-04: PED Meetings - Pressure Equipment Directive
2015-03-09: Interface Meeting - Cryomodule instrumentationMinutes of 2015-03-09 (Cryomodule instrumentation)
2015-08-31: Interface Meeting - Pressure Configuration
Cryomodules Collaboration space
Interface with Vacuum - VAC - WP122015-07-21: Interface Meeting - Cryomodules vacuum2015-10-12 Interface meeting - Cryomodules VacuumBeam Vacuum Interface RequirementsInsulation Vacuum Interface Requirements
Interface with Cabling and Conventional Power - CNPW - WP15
Interface with Cooling support - WTRC - WP16
Interface with Power Supplies, HV Power Converters - PWRC - WP17
Interface with Proton Beam Instrumentation - PBI - WP07
Interface with Test Stands - WP10Interface with Control and Command - Integrated Control System (ICS)Interface with Survey and Alignment
30
Thanks for your attention
31
Compliance with European Pressure Equipment Directive (PED)
• Volumes of the helium circuits and vessels < 48 l• 1.431 bara < Working pressure• Ps = 1.04 barg
TUV Nord analysis report:The elliptical and Spoke cryomodules are
classified according to PED article 3.3
Cryo pipes designed to reduce the overpressure in case of beam vacuum
failure
continuous diphasic pipe Ø=100 with large
curvatures
2 Ø=100 bursting disks at each extremity
- 32 -S. Bousson, Workshop on Requirements Conformance for SRF Cryomodules, Lund, 15th Oct. 2014
Spoke cryomodule overall life cycle
Appro Niobium
FabricationCavité
Traitement surfaceCavité
Assemblagecavité
Salle blanche
Test en CV
COMPONENT
PHAS
EEx
port
/de
liver
yTe
st /
valid
ation
Prép
arati
on/
asse
mbl
ySU
pply
/Pr
oduc
tion
Niobium Cavities Couplers vesselVacuum
Cryomod.Full.
compon..Cryomod.
stringCavityCTS …
Transport -> site
assemblage
Transport -> Fabriquant
cavités
…
…
…
…
FabricationEnceinte
Cryomodule
Transport -> site
assemblage
Appro Compos.
cryomodule
Transport -> site
assemblage
Assemblagetrain
cavités
Transport -> site
assemblage
FabricationSAF
AssemblageSAF
Test à chaud SAF
Transport -> site
assemblage
Assemblagecryomodule
Test àchaud
Transport -> Uppsala
FabricationCoupleur
Préparation salle blanche
coupleurs
Conditionn-ement
coupleurs
Transport -> site
assemblage
33
Charge to the Committee
This review constitutes the principal technical and project review of the Work Package for this year. Additional specific design reviews may also be held. Keeping in mind the current status of the Accelerator Project, the committee is asked to review the information presented, answer to the extent possible the questions below and make specific recommendations to increase the likelihood of success of the Work Package.
The result of the review will be a short report that includes recommendations. The committee serves in an advisory capacity to the Work Package Leader and the ACCSYS management team.
• Has the work package reached a level of technical maturity consistent with its current status on the schedule?• Are there any technical concerns regarding the work package?• Is any additional development or testing required for the work package to meet its goals?• Are the requirements for the work package well understood and documented?• Are all the interfaces between the work packages and other work packages and products properly defined,
understood and agreed upon?• Have all safety issues in the work package been properly identified and dealt with?• Are there sufficient resources (funding, staff) assigned to the work package to allow the goals of the work
package to be met?• Are there decisions that need to be made in order to allow the work package to meet scope, cost and schedule?• Are there any outstanding procurements or personnel actions that are limiting the progress on the Work
Package?• Is the Work Package on track to meeting its milestones?• Are there any adjustments to the schedule and milestones that should be made?• Are there any changes to the work package scope that should be made?• Are additional reviews warranted before the next annual audit?
34
Technical Annex - TOC
4.3 Project Schedule and Key Milestones
4.3.1 Kick-off meeting
4.3.2 Status meetings
4.3.3 Design Review(s) in Stage 1
4.3.4 Readiness / Acceptance Review(s) in Stage 2
4.3.5 Review(s) in Stage 3
4.4 Deliverables
4.4.1 Status reports
4.4.2 Technical Data Package(s) for Design Review(s), Stage 1.
4.4.3 Technical Data Package(s) for Review(s), Stage 2
4.4.4 Final report
4.4.5 Documentation package for supply
35
Technical Annex - TOC
5. Tasks applicable to all project stages
5.1 Project management and control
5.1.1 Use of a Planning Tool
5.1.2 Delivery Milestones
5.1.3 Milestone Definition List
5.1.4 Interim Milestones
5.1.5 EV – Weighted MS value
5.1.6 Monthly Forecasting
5.2 Risk Management
5.2.1 ESS Risk Management Process
5.2.2 ESS risk criteria
5.2.3 Risk register
5.2.4 Risk status report
36
Technical Annex - TOC
5.3 Configuration management
5.4 Organization
5.5 Product & Quality assurance and safety
5.5.1 Applicable law, legislation and standards
5.5.2 Safety
5.5.3 Quality
5.5.4 Licensing
6. Documentation format
7. Transportation and DELIVERY
8. Warranty
9. Excluded Background