ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by...

17
ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM Damped Cavity Collaboration BESSY, Daresbury Lab, DELTA, MaxLab, NTHU Cavity concept and design goals Simulations and impedance measurement results Prototype cavity conditioning and first beam tests What lessons have we learned so far? Further developments Summary and outlook

Transcript of ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by...

Page 1: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Status of the HOM Damped Cavity Project

E. Weihreter / BESSY

Project funded by the EC under contract HPRI-CT-1999-50011

for the HOM Damped Cavity CollaborationBESSY, Daresbury Lab, DELTA, MaxLab, NTHU

♦ Cavity concept and design goals

♦ Simulations and impedance measurement results

♦ Prototype cavity conditioning and first beam tests

♦ What lessons have we learned so far?

♦ Further developments

♦ Summary and outlook

Page 2: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Fundamental mode frequency f = 500 MHz

Insertion length L 0.7 m

Shunt impedance R 4 M

Max. thermal power P = 100 kW

Compact design to fit into existing SR source tunnels

Cavity ConceptDesign Goals

Page 3: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Simulation Models

S11=1

~ 106 mesh points 2-3 days cpu time

~18* 106 mesh points 6-7 weeks cpu time

Page 4: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Simulations and Impedance Measurement Results

Tapered CWCT

Homogenious waveguidewith S11 = 1 boundary

Page 5: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Threshold impedances for different rings

sb

s

HOMC

thresh

I

QE

fNZ

0

||,

.||

211

yxyxbrevC

threshyx If

E

NZ

,,

0.,

21

Page 6: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Tuning and Cavity Test at ZANON S.p.A. / Italy

Page 7: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Measured Impedance Spectra of

Page 8: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Measured Cavity Parameters

Parameter

3D MWS Simulation

Standard/New Method

Measurement

f0 (MHz) 500.98 499.65

Q0 32557 / 28410 26692

Reff/Q0 (Ω)

114.5 115.4

Reff (MΩ) 3.73 / 3.25 3.1

Nominal Frequency 499.65 MHz

Tuning Range 2 MHz

Shunt Impedance 3.1 MΩ

Unloaded Q 26692

Thermal Power Capability 100 kW

Longitudinal HOM Impedance

≤ 4.8 kΩ

Transverse HOM Impedance

≤ 180 kΩ/m

Waveguide cut-off 615 MHz

Coupling Range 0-8

Insertion Length 50 cm

Beam Hole DiameterTE11 cut-offTM01 cut-off

743.742.31

mmGHzGHz

Resonant frequency vs. plunger positionas measured and calculated.

Page 9: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Prototype Cavity Conditioning

Peak and average cavity input power during

RF conditioning (pvac< 5*10-7 mb) Vacuum conditioning procedure

Increase in vacuum pressure around 200W and 600 W,however no serious multipacting thresholds observed

Page 10: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Cavity installed in the DELTA Ring

Page 11: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

First Beam Observations at 1480 MeV

DORIS Cavity

HOM Damped Cavity

CBM 55 is not driven by the cavity !!

Page 12: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

DORIS Cavity beam spectrum at low energy

Final beam tests: measurement of coupled bunch instability thresholds at 540 MeV

Page 13: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

What lessons have we learned so far ?

♦ The tapered waveguides are the most critical components of the cavity

∙ about 60% of total manufacturing costs

∙ small tolerances

∙ vacuum brazing is a subtle technique, to be avoided where possible

♦ Engineering layout of e-beam welds and quality control during manufacturing must be improved

♦ Gaps between the ridges and the waveguide port wall should not be longer than 80 mm to avoid resonances coupling to the fundamental mode

♦ A CF 63 flange should be added at the end of the tapered waveguide

♦ Homogenous damping waveguides allow further reduction of HOM impedances

Page 14: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Avoid long gaps coupling to fundamental mode

gap

Page 15: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Further Development: Homogenious ferrite loaded waveguide

0.6 0.8 1 1.2 1.4

F req u en cy (G H z)

0

0.2

0.4

0.6

0.8

1

S11

---L = 1 5 0 m m (m esh 5 8 6 1 )---L = 2 0 0 m m (m esh 8 4 9 3 )---L = 2 5 0 m m (m esh 1 0 3 2 2 )---L = 3 0 0 m m (m esh 1 1 6 4 3 )---L = 3 5 0 m m (m esh 1 7 0 5 8 )N ew ferrite p a ra m eter ,T = 3 .2 m m ,C o v er-M o d el

D ifferen t L en g th o f F err ite(C -4 8 ,N i-Z n ) w ith Q u a rter C over-M odel (d iscrete)

0.5 1 1.5 2 2.5 3

F req u en cy (G H z)

0

0.2

0.4

0.6

0.8

1

S11

E x p erim en t m ea su rem en t(co v ered m o d el,g a te1 1 n s~3 0 n s)E x p erim en t m ea su rem en t(co v ered m o d el,w ith o u t set g a te)E x p erim en t m ea su rem en t(N O -co v ered m o d el,g a te1 0 .1 3 2 n s~1 0 0 n s)H F S S S im u la tio n resu lt(co v ered m o d el)

T o C o m p a re W ith E x p erim en t a n d S im u la tio n R esu lt

Page 16: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

TDR measurement set-up

CWCT used as adapter

Ferrite load

Circular ridged waveguide

Low power model of a homogenous ridged waveguide load

Page 17: ESLS-RF Meeting 2004 Status of the HOM Damped Cavity Project E. Weihreter / BESSY Project funded by the EC under contract HPRI-CT-1999-50011 for the HOM.

ESLS-RF Meeting 2004

Summary

♦ A HOM damped prototype cavity has been built and tested under low and high power conditions

♦ Impedance measurements show that longitudinal HOM impedances < 4.8 kΩ transverse HOM impedances < 180 kΩ/m fundamental mode impedance 3.1 MΩ

♦ Measurements are in good agreement with calculations: Simulation tools are reliable

♦ Successful high power operation up to 30 kW thermal power, no serious multipacting thresholds found

♦ Technical improvements modifications e-beam welds, avoid vacuum brazing where possible reduced gaps between ridges and CWCT port CF 63 flange at the end of the CWCT ♦ Conceptual and technical layout has been verified. Cavity design is ready for use.

Outlook

♦ Final beam test of the cavity in DELTA at 540 MeV early in 2005 ♦ Development of a high power prototype for a homogenious wavegude load is under way to reduce manufacturing cost and further reduce HOM impedances by a factor 3-4