Eskom-selective-reopener-presentation1.pdf

21
Eskom MYPD 3 Selective Reopener Stakeholder Consultation June 2015

Transcript of Eskom-selective-reopener-presentation1.pdf

  • Eskom MYPD 3Selective Reopener

    Stakeholder Consultation

    June 2015

  • Electricity Regulation Act (ERA)

    Allows for recovery of efficient cost and reasonable return Ensures that Eskom does not discriminate between customer groupings

    2

    Nersa processes in terms of ERA and MYPD methodology

    Allows for reopener of MYPD decision if significant changes in assumptions (forward looking)

    Requires submission of Regulatory Clearing Account (RCA) to address variances between actuals and MYPD decision (backward looking)

    Requires reasonable consultation with public

    Balance impact of tariff increases on consumers and sustainability of Eskom Ensures protection of poor

    Municipal Finance Management Act (MFMA)

    Requires Eskom to consult with NT and SALGA prior to submission to Nersa for tariff applications

    Requires Eskom to table tariff increases applicable to Municipalities in Parliament

  • MYPD 2 and MYPD 3 RCA

    3

    31

    March

    Yn+1

    1 April

    Yn31

    March

    Yn+x

    MYPD RCA

    applies to history

    (adjustment

    occurs after

    event)

    MYPD

    applies to future

    Both mechanisms

    require adjustments

    to tariffs

    Process time lines - using current rules implies at least 2 year time lag to

    liquidate variances as its based on audited financials

  • Context of Selective Reopener of MYPD 3 Application

    4

    Key Operational Challenges

    Availability of coal-fired power stations has been further deteriorating in comparison to assumptions in MYPD 3 application where assumed

    average EAF of 82%

    Availability further impacted with Duvha boiler and Majuba silo incidents which were not assumed in application

    Delay in generation new build in comparison to assumptions in MYPD 3

    Requirement for space to maintain Generation units

    Require increase in tariffs to costs of further supply options (high OCGTs and STPPP)

    to assist in minimising the impact of further load shedding

  • Context of Selective Reopener of MYPD 3 Application

    5

    Key Financial Challenges

    Funding of OCGT and STPPP Had to borrow to run OCGTs in 2014 and 2015. This amount will be requested for recovery through the RCA

    process.

    Eskoms cash-flow and liquidity situation cannot allow this to continue

    Equity - Unlikely that further equity injection is forthcoming from Government in the short term

    Debt - Limits to further significant borrowings are being reached with current credit ratings and negative outlook. Access and costs to

    borrowings becoming more challenging

    Financial and liquidity challenges where ROA less than cost of capital results in deterioration of balance sheet

    Expansion programme funded from debt substantially on a weakened balance sheet

    Require increase in tariffs to costs of further supply options (high OCGTs & STPPP)

    to assist in minimising the impact of further load shedding

  • Eskom applying for in selective reopener which will add 10% to the already approved 12,69% for 2015/16

    6

    Price decision

    MYPD3 original decision of 8% price increase

    RCA for MYPD2

    Price adjusted for prudent costs and revenue variances through the RCA for MYPD2 which resulted in the awarding of another 4,69%price increase on top of the 8%, equating to 12,69% which has already been approved by Nersa

    Selective reopener

    Eskom is applying for the recovery of efficient costs relating to OCGTs and STPPP for the next 3 years. Eskom cannot wait for an RCA process to recover these costs due to the financial challenges facing the organisation.

    This expenditure will contribute towards Eskom creating space to do necessary maintenance whilst mitigating the impacts of future load shedding.

    Requires an adjustment 10% linked to the extraordinary costs to limit load shedding.

    If National Treasury gazettes increase in environmental levy by 2c/kWh,

    would need to be recovered by Eskom through a further price increase of 2,5%

    5 year period

    2014 2018 1 year period

    2016 3 year period

    2016 2018

  • Unpacking the price drivers in 2015/16

    2015/16 Comments

    Rest of normal costs and returns 6.8%

    OCGTs 0.1% Allowed R1,5bn

    Other IPPs (Renewables and DOE Peaker) 0.7% Allowed R14.4bn

    STPPP 0% Allowed R0bn

    Environmental levy 0.4% Allowed R9.3bn

    MYPD3 Original price decision 8.0%

    MYPD2 RCA clawback decision by Nersa 4.7%

    Revised price already granted by Nersa 12.7% Nersa decision awarded after

    RCA

    Selective Reopener 9.5% Required to reduce load

    shedding

    - OCGTs 6.4% Applied for R10.9bn

    - STPPP 3.1% Applied for R5.3bn

    Environmental levy increase if gazetted 2.5% Pass through of levy costs

    Overall price to consumer (1+2+ 3) 24.7%

    7

    1

    2

    3

  • Challenge with sufficient capacity : Eskoms Gx New Build Assumptions in MYPD application did not materialise

    Medupi Kusile Ingula Sere

    2012/13 0 0 0 0

    2013/14 722 0 333 100

    2014/15 1 444 723 999 0

    2015/16 722 723 0 0

    2016/17 722 723 0 0

    2017/18 722 1 446 0 0

    2018/19 0 723 0 0

    8

    Energy assumed to be delivered by each coal unit (assume at 75% EAF)

    is approximately 4500GWhr per unit per year

    This energy had to be replaced by other supply sources

  • Challenge with sufficient capacity : Status of Eskoms existing generation fleet

    The underlying cause of the deterioration in the fleets performance is the lack of sufficient capacity,

    aggravated by the onset of age and usage related equipment failures.

    About 80% of the existing fleets capacity is now in that period where they require major

    equipment replacements in order to restore the plants economic life.

    Deferring this work in the recent past is a major cause of the escalation in plant breakdowns.

    The first contributor to the capacity shortage is the delay of new capacity.

    Decision to build Medupi (and other stations) was needed by, not later than, 1999 to meet

    increasing demand by 2007.

    Decision only made in late 2004; approval for 1st new base load station made in December 2005

    (revised in December 2006 to become Medupi) => needed capacity not available in time.

    This was exacerbated by delays in the commissioning of both Medupi and Kusile.

    The second contributor is the deteriorating plant performance of existing plant.

    Over the past 10 years, but particularly since the 2010 World Cup, necessary philosophy

    maintenance was delayed in the interests of keeping the lights on.

    The above led to the very high load factors and limited the time available for maintenance outages.

    This high utilisation of deteriorated plant created the cycle of deteriorating availability.

    Despite some improvements due to efficiency and effectiveness of operations and maintenance,

    this cycle can only be broken once there are adequate funds and space in which to perform the

    required maintenance

  • Challenge with sufficient capacity : Creating space for maintenance for sustainability

    High and increasing reactive maintenance, and the resultant decreasing amount of proactive

    maintenance, are the direct result of the constrained system, aggravated by the reduced plant

    reliability and also by capital expenditure constraints.

    Eskom is convinced that the only way to restore plant reliability is to put emphasis on proactive

    maintenance, which includes refurbishment. If this is done, availability should improve, but if outages

    continue to be deferred in order to keep the lights on, availability can be expected to deteriorate

    further.

    It is thus prudent that the OCGTs were, as was expected when they were commissioned, utilised

    beyond their normal peaking function, during the 2015 financial year, to improve the supply / demand

    balance during the period of plant shortage as NERSA said in December 2007. This contributed to

    creating space for maintenance and limiting load shedding, once all other demand and supply side

    options had been fully utilised.

  • Benefits derived from use of OCGT and STPPP during April 2015 Illustration at daily peak for April 2015

    11

  • KM03 RTS 06/06

    HD04 RTS 24/06

    AN05 RTS 22/06

    HD10 RTS 18/06

    12

    Maintenance Schedule & Capacity Outlookfor June 2015 (illustrates benefit of OCGTs)

    KD03 RTS 27/06

    MJ01 RTS 12/06

    MJ05 Turbine 4 Cylinder

    Overhaul for 71 days 13/06

    AN06 MGO for 66d 23/06

    GA02 RTS 28/06

    KM02 RTS 19/06

    KD05 Gen H2 Cooler repairs

    for 7 days 12/06

    KD05 RTS 19/06

    DV04 RTS 08/06

    AL42 RTS 09/06

    AL42 Minor Inspection for

    6.75 days 02/06

    CD06 RTS 21/06

    HD05 RTS 04/06

  • Increase in Environmental levy

    In Minister Nenes Budget speech(Feb 2015) increased electricity levy from 3.5c/kWh to 5.5c/kWh, to assist in demand management

    When the selective reopener application was made, it was assumed that required legislation will be effective in 2015/16 year however did not occur

    Eskom can recover the environmental levy costs from its customers to remain revenue neutral and is treated as pass through item

    If tariffs are not adjusted then Eskom can include as variance in RCA will be a time lag in recovery. This would further impact liquidity- thus included in

    selective reopener.

    NT in its comments still considering implementation Impact is as follows, if were implemented from 1 July 2015

    13

    Price element Price impact in 2015/16

    Standard tariff after MYPD2 RCA decision 79,73 c/kWh

    Impact of change in environmental levy by 2c/kWh 2c/kWh / 79.73c/kWh = 2,51%

  • Summary of selective reopener revenue application and price impact

    14

    Selective Reopener for OCGTs and STPPP (R'm) 2015/16 2016/17 2017/18 Total

    OCGTs total costs 12 458 12 458 12 458 37 375

    Less OCGTs included MYPD3 decision -1 508 -1 599 -1 724 -4 831

    OCGTs - costs to be recovered 10 950 10 859 10 734 32 544

    STPPP - IPPs costs to be recovered 5 357 5 879 6 279 17 515

    Less STPPP costs included in MYPD3 decision - - - -

    STPPP - IPPs costs to be recovered 5 357 5 879 6 279 17 515

    Total Revenue requirement adjustment (R'm) 16 307 16 739 17 013 50 059

    Price increase required (%) 9.58% 3.24% 7.26%

    NOTE

    * The price increase in 2015/16 is above the 12,69% already announced, thus the absolute increase is 22,27% excluding change in enironmental levy

    ** The price increases of 3,24% in 2016/17 and 7,26% in 2017/18 are absolute increases in those years

    ***The price drop to 3,24% in 2016/17 is due to the adjustment in 2015/16 which increases the base and thus to achieve the original

    allowed revenue in 2016/17 requires a lower price increase. The 3,24% and 7.26% assumes a no RCA adjustment which would need to be

    included following regulatory processes. `

  • Summary of price impact of selective reopener based on Nersa methodology

    15

    Revenue Requirement and Price Increases 2015/16 2016/17 2017/18

    Revenue standard tariffs allowed - R862bn (R'm) 163 179 180 070 198 954

    Sales per MYPD3 (GWh) 213 545 218 194 223 219

    Price c/kWh 76.41 82.53 89.13

    Plus MYPD2 RCA (R'm) 7 085

    Adjusted revenue after RCA decision (R'm) 170 264 180 070 198 954

    Price c/kWh after MYPD2 RCA (c/kWh) 79.73

    Selective Re-opener for OCGTs and STPPP (2015/16~2017/18) (R'm) 16 307 16 739 17 013

    Adjusted revenue requirements after MYPD2 RCA and Re-opener (R'm) 186 571 196 809 215 967

    Price c/kWh after MYPD2 RCA and Re-opener 87.37 90.20 96.75

    Price increase required (%) 9.58% 3.24% 7.26%

    Price increase required (%) - OCGTs 6.43% 3.12% 7.35%

    Price increase required (%) - STPPP 3.15% 0.12% -0.09%

    * The price increase in 2015/16 is above the 12,69% already announced, thus the absolute increase is 22,27% excluding change in enironmental levy

    ** The price increases of 3,24% in 2016/17 and 7,26% in 2017/18 are absolute increases in those years

  • Key comments from SALGA and NT

    SALGA

    Will result in further increasing non-payment and electricity theft thus less steep path of price increases

    Committed to financial viability and long term sustainability of Eskom

    Require time to rework budget and ensure approval process

    Unclear of what cost of unserved energy required to assess impact

    Further equity should be provided by National Treasury though constraints in national funding

    National Treasury

    Eskoms weak financial position and resulting downgrade of Eskoms credit rating is recognised

    Only option for healthy financial position and minimise load shedding is increasing tariffs

    Need immediate adjustments to assist with current liquidity challenges, and begin strengthening towards a

    financial sustainability.

    Cost of load-shedding is R9 to 15 per kWh.

    Only increases for 2015/16 year supported. Further tariff increases once substantial information towards

    cost-reflective or long-run marginal cost tariff level is.

    Support NERSA in-principle approval of STPPP costs for 2015/16

    In-principle support by Government for OCGTs to prevent load-shedding. Must motivate for exact levels

    16

  • Conclusion

    Due to operational and financial challenges facing Eskom, allowance by Nersa

    for recovery of higher OCGT and STPPP costs is essential to allow Eskom to

    continue to utilise these supply options to help mitigate the impact of load

    shedding and contributes to space for Generation maintenance

    Under the circumstances, still viable to use expensive OCGT (approximately

    R2.75 to R3.00/kWhr depending on fuel price) when compared to cost of

    unserved energy estimated by National Treasury to be between R9 to

    R15/kWhr

    Contributes to improvement of industry towards sustainability

    17

  • 18

    Tariff category increases

    There are four types of tariff categories:

    1. Municipal tariffs

    These are all the tariffs in the tariff book available to Municipal customers bulkand other small supply points.

    2. Urban tariffs (directly supplied by Eskom)

    These tariffs are Businessrate, Megaflex, Miniflex, Nightsave Urban (Large andSmall), Transflex and Public lighting tariffs. The sales on these tariffs are mainlyfor Mining, Industrial, Traction and Commercial customers.

    3. Rural tariffs (directly supplied by Eskom)

    These tariffs are Ruraflex, Nightsave rural and Landrate. The sales on thesetariffs are mainly for customers taking supplies in rural areas and are mainly foragricultural customers.

    4. Residential IBT tariffs (directly supplied by Eskom)

    These tariffs are Homelight and Homepower on the NERSA IBT rates. Thesales on these tariffs are for residential customers.

  • Detailed 2015/16 price impact of selective reopener based on Nersa methodology

    19

    NERSA

    existing

    decision

    Reopen

    er

    increas

    Total

    9 months

    NERSA

    existing

    decision

    Reopener

    increases

    Total

    12

    months

    Municipal 14.24% 1 Jul n/a 14.24% plus 12.80% =27.04% 12.69% plus 9.74% =22.43%

    Key industrial and urban 12.69% 1 Apr 12.69% 12.69% plus 12.80% =25.49% 12.69% plus 9.50% =22.19%

    Rural 12.69% 1 Apr 12.69% 12.69% plus 12.80% =25.49% 12.69% plus 9.68% =22.37%

    Homelight 20A Block 1 0-350kWh 10.29% 1 Apr 10.29% 10.29% plus 10.40% =20.69% 10.29% plus 8.04% =18.33%

    Homelight 20A Block 2 >350kWh 12.29% 1 Apr 12.29% 12.29% plus 12.40% =24.69% 12.29% plus 9.68% =21.97%

    Homelight 60A 12.69% 1 Apr 12.69% 12.69% plus 12.80% =25.49% 12.69% plus 9.68% =22.37%

    Homepower 12.69% 1 Apr 12.69% 12.69% plus 12.80% =25.49% 12.69% plus 9.77% =22.46%

    NERSA

    decision

    27 November

    2014

    Effective

    on 1 April

    2015

    To be implemented

    1 July 2015

    Annual average

    increase

    9-month increase 12-month increase

    Note: Excluding the increase in the environmental levy

    Assume the application is approved in entirety

  • 2015/16 Retail tariff structural adjustments

    Eskom proposed retail structural adjustments plan 2015/16 and beyond

    1. TOU morning and evening winter peak

    shift

    2. Some name changes to rate

    components

    3. New tariffs

    Net-metering tariffs tariff for customers with own generation)

    Prepaid tariff for small agriculture (Landlight 60A)

    Review of the Transmission use of system charges for generators

    based on NERSA approved revenue

    Updating NMD Rules- rules for notification of demand and export

    capacity

    20

    1. Update tariffs structures based on cost drivers

    2. TOU structure review

    Understand the country profile to determine the alternative TOU tariff design required

    based on the load profiles

    Determine whether TOU periods can be allocated regionally

    Determine whether the peak, standard. off-peak and seasonal tariff signals are still

    appropriate

    3. New tariffs

    Simplification of the Municipality tariffs through rationalising and redesigning the

    Municipality tariffs

    Voluntary critical peak day tariff TOU for residential and small commercial

    2015/16 2016/17 2017/18

    1. Update tariffs structures based on

    cost drivers

    2. Combine Nightsave large and small

    3. Revising the voltage categories

    4. Revising the low voltage subsidies

    5. Review of Homepower bulk structure

    6. New tariffs

    Green tariff Homepower bulk tariff structure New public lighting tariff

    For Approval

    To be submitted separately

  • Thank you

    Questions