UIC ERTMS World Conference ERTMS Baselines Pio GUIDO, Head of ERTMS Unit Istanbul, 2 April 2014.
ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS...
Transcript of ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS...
![Page 1: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/1.jpg)
ERTMS – Baseline 3 Implementation and experience from first
commissioned line at Nordjyske Jernbaner. First mover in Denmark
or guinea pig?
Johannes Flyvbjerg Jakobsen – NJ Safety Manager
Peter Boll – BDK SP West Safety Manager
Joanna Wisniewska – BDK SP Onboard Safety Manager
![Page 2: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/2.jpg)
Before Implementation.
![Page 3: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/3.jpg)
The road to the digital signal system in North Jutland
• Project launch in 2012.• Official roll-out date in week 43
2018
Consequences afterimplementation
• No other rail operators in the ERTMS equipped area.
Early deployment line
![Page 4: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/4.jpg)
Preparing the company for ERTMS L2
• SLS - Obtain new NSA Approval as the First RU in Denmark
• Rolling stock - Obtain new NSA Approval as the first RU in Denmark
• Trusted cooperation with the NSA
![Page 5: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/5.jpg)
Level 2 Baseline 3, new Interlocking, and new TMS
Replace the wheels while driving
▪ The Signalling programme is a brownfield project
▪ Commissioning of the system should minimise impact on the line in operation
Interlocking elements were the biggest challenge for EDL
▪ ‘Change over system’ area allows for full functional test of generic system
▪ Point Machines and Level Crossings were not installed outside the COS area
▪ Virtual Balise Covers were used to allow for the ETCS tests
![Page 6: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/6.jpg)
Joint Test Lab, SIT
Joint Test Lab
▪ Development and external interfaces, more than 2 years of test
Site Integration Tests
▪ installation of components and connectivity test
![Page 7: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/7.jpg)
Onboard approval
• Few approval received for level NTC/level 0
• Work on the delta to obtain first approval for level 2
• ESC test report
• ESC statement
• Key aspects:
➢Collaboration with the NSA
➢ Transparency with the RU´s during entire safety process
➢ Assessor, DeBo involvement
new process
Test & Transport
Fitment and Commissioning
HandoverFrom RU
STM and ETCS Dynamic Tests on
closed trackL0/LNTC
Test Train(Litra MR/MRD)
Test & Transport
Fitment and Commissioning
HandoverFrom RU
STM and ETCS Dynamic Tests on
closed trackL0/LNTC
FoC(Litra xx)
Fitment and Commissioning
HandoverFrom RU
Series N.1(Litra xx)
Covering thewhole train series
Handback to RU
Handback to RU
L2Test &
TransportSoftware Upgrade
and CommissioningHandoverFrom RU
Train Track Validation Tests
(On specific TS CCS) on closed tracks
Test Train(Litra MR/MRD)
Software Upgrade and Commissioning
HandoverFrom RU
Handback to RU
FoC(Litra xx)
Software Upgrade and Commissioning
HandoverFrom RU
Handback to RU
Series N.1(Litra xx)
Covering thewhole train series
L2
Handback to RU
Approval Level 2 (additional to Level 0 and Level NTC)
Handback to RU
Poss ible site tests based ondelta approach
depending on FoC
Approval Level 0 and Level NTC
![Page 8: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/8.jpg)
During implementation.
![Page 9: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/9.jpg)
During implementation.
• Line closed for 2 weeks
• 52 drivers to be trained.
• Onboard and supplier team present – key part to handle any findings
• Consequences
• 100% production are affected of the change to ERTMS.
![Page 10: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/10.jpg)
SAT, Trial Run, and Commissioning
Site Acceptance Test
▪ all external interfaces tested, final evidence to the safety documentation
Trial Run
▪ Evidence of operational readiness
Commissioning period
▪ Majority of Point Machines and Level Crossings installed and final day of training of the drivers
![Page 11: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/11.jpg)
After implementation.
![Page 12: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/12.jpg)
Surprice and breaking news! - the press wrote:
Finally, good news from the trains.
The trains in North Jutland have increasing punctuality.
![Page 13: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/13.jpg)
NJ – train punctuality after implementation in 2018NJ – Train punctuality August 2019Tr
ain
pu
nct
ual
ity
ERTMS overall impact punctuality Punctuality 2018
tota
l im
pac
t
![Page 14: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/14.jpg)
Future Challenges
Infrastructure
How to test and commissioning without impacting the already commissioned lines ?
How to implement track layout changes in the roll out plan ?
Onboard
Handling configuration changes correctly according to 2018/545 and IO
One stop shop
Update to MR1 3.4.0
Compatibility with two types of line – not done yet
![Page 15: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/15.jpg)
Sharing of knowledge as first mover.
![Page 16: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/16.jpg)
Lessons learned
• Share knowledge from NJ til other RU in Denmark. Do not built fence around knowledge that are accumulatet in the company.
• Retraining has to be taken into considertion while the system har a high performance.
• Share knowledge and best practice across railways
![Page 17: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner.](https://reader035.fdocuments.in/reader035/viewer/2022071114/5feb0dbcb36ed41abf4f3e35/html5/thumbnails/17.jpg)
Thanks for the interest