    Introduction

    The Online Regional Project Monitoring and

    Evaluation System (eRPMES)

    The Online Project Monitoring is an internet-based solution tofacilitate the enrollment, submission and generation of monitoring

    reports patterned after the RPMES. It enables users to update peri-

    odic project accomplishment reports and access up-to-date infor-

    mation on project status. The system likewise generates and providesinformation on the performance of agencies taking into consideration

    the employment generation, physical accomplishment and funding

    utilization of their projects included in the Annual Project Monitoring

    Plan.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    4/55

    eRPMES Monitors Guide

    4

    Republic o f the Philippines

    REGIONAL DEVELOPMENT COUNCIL

    Region 1c/o NEDA Regional O ffice No. 1

    Heroes Hi ll, Guerrero Road, City of San Fernando, 2500 La Unio n

    Tel Nos. 888-5501 * 888-2679 * 888-2680 * 700-0856 Fax no. 888-2708 E-mail address: [email protected] Web Address: http//www .neda1.net

    RDC OFFICIALS

    GOV. DEOGRACIAS VICTOR SAVELLANO

    Chairman

    DR. SALVADOR T. DUQUE

    Co-Chairman

    DIR. LEONARDO N. QUITOS, JR.

    Vice-chairman

    ARD NESTOR G. RILLON

    Secretary

    RDC COUNCIL M EMBERS

    Local Government Units

    Gov. Michael Keon

    Gov. Deogracias Victor Savellano

    Gov. Manuel Ortega

    Gov. Amado Espino, Jr.

    Mayor Hernani Braganza

    Mayor AmadeoPerez

    Mayor Julier Resuello

    Mayor Alipio Fernandez, Jr.

    Mayor Pablo C. Ortega

    Mayor Allen Singson

    Mayor Eva Marie Medina

    Mayor Michael Farias

    Mayor Jeffrey Nalupta

    Mayor Ernesto Castaeda, Jr.

    Mayor EdgardoZaragoza

    Mayor George Pinzon

    Mayor Ramon Guico, Jr.

    Mayor Joseph de Lara

    Government Agencies

    USec. HermenegildoDumlao - NLGQA-PMODir. Florante Leal - DTI

    OIC Dir. Valeriano Lopez - DOH

    Dir. Mariano R. Alquiza - DPWH

    Dir. Manuel Biason- DILG

    Dir. Cipriano Santiago -DA

    Dir. Homer Tobias - DAR

    Dir. Samuel R. Peafiel - DENR

    Dir. Elsa Chan -DOST

    Dir. Leonardo Reynoso - DSWD

    Dir. Martin Valera -DOT

    Mgr. Silverio Mangaoang, Jr. - DOTC-RMC

    Dir. Peter Baluyan - DOF-BLGF

    Dir. Janet Abuel - DBM

    Dir. Ligaya Soledad Miguel -DepEd

    OIC Dir. Henry John Jalbuena - DOLE

    OIC Josephine Sanchez -PM S

    Dir. Evelyn Pascua - CHED

    Dir. Ramon Gatan - PNP

    Dir. PerlitaTabisaura NICA

    Dir. Washington Agustin TESDA

    Dir. Anita Chauhan CHR

    Dir. Primo Quetulio - BSP

    Private Sector

    Dr. Salvador Duque

    Mr. Vincent Adorna

    Dr. Roberto de los Reyes

    Mr. Ambrocio Valero

    Mr. Mario Zamoranos

    Mr. Marcelino dela Cruz

    Mr. Nelson Yuchiongtian

    Mr. Rodolfo Posadas

    Pastor Roland Santiago

    Mrs. Carmelita Duque

    Engr. Antonio de vera

    Col. SinforosoDumling (Ret)

    Mr. Glen Mark Dacasin

    ADVISORY COMMITTEE

    HON. ROQUE R. ABLAN, JR.

    1st District, Ilocos Norte

    HON. FERDINAND R. MARCOS

    2nd District, Ilocos NorteHON. RONALD SINGSON

    1st District, Ilocos Sur

    HON. ERIC D. SINGSON

    2nd District, Ilocos Sur

    HON. VICTOR FRANCISCO C. ORTEGA

    1st District, La Union

    HON. TOMAS L. DUMPIT, JR.

    2nd District, La Union

    HON. ARTHUR D. CELESTE

    1st District, Pangasinan

    HON. VICTOR AGUEDO E. AGBAYANI

    2nd District, Pangasinan

    HON. RACHEL J. ARENAS

    3rd District, Pangasinan

    HON. JOSE C. DE VENECIA, JR.

    4th District, Pangasinan

    HON. MARCOS O. COJUANGCO

    5th District, Pangasinan

    HON. CONRADO M. ESTRELLA III

    6th District, Pangasinan

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    5/55

    eRPMES Monitors Guide

    5

    T a b l e of C o n t e n t s

    Online Regional Project Monitoring and Evaluation System(e-RPMES) Monitors Guide

    Introduction........................................................................................................... i

    RDC ExCom Resolution No. 6, s. of 2010............................................................ ii

    A. Requirements............................................................................................. 1

    B. Getting Started......................................................................................... 2

    C. Enrolling Projects to the Monitoring Plan (PMC Form I-1)................ 3

    D. Submission of Quarterly Accomplishment Reports (PMC Form I-2)... 20

    E. Computing for the Agency Overall Performance............................. 25

    F. Viewing the Project Monitoring Reports............................................. 26

    1. Agency Accomplishment Report................................................... 26

    2. Agency Overall Performance......................................................... 273. Accomplishment Report by Sector................................................ 28

    G. Submission of Project Exception Report (PMC Form I-3A............... 30

    H. Submission of Updated Project Exception Report (PMC Form I-3B).. 32

    I. Printing the Project Monitoring Reports............................................... 33

    J. Changing Account Information................................................... 35

    K. Log-out Menu.......................................................................................... 36

    Addendum to the e-RPMES Monitors Guide (October 2011)...................... 37

    A. Quick Access to Summary Reports...........................................................37

    B. Data Integrity...................................................................................... 46

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    6/55

    eRPMES Monitors Guide

    6

    List of Tables

    Table 1. Overall Performance Rating................................................................... 26

    List of Figures

    Figure 1. System Diagram ......................................................................................... 1

    Figure 2. IRISNET Menu............................................................................................... 2

    Figure 3. e-RPMES Log-in Window............................................................................. 2

    Figure 4. Online Project Monitoring Home Page................... ................. ................. 3

    Figure 5. Agency Project Page................................................................................ 3

    Figure 6. Project Enrollment Window....................................................................... 3

    Figure 7. Project Period............................................................................................ 4

    Figure 8. Project Type................................................................................................ 4

    Figure 9. a. MDG and PDAF Project Sector............................................................... 5

    Figure 9.b. RAACC Project Sector............................................................................. 5

    Figure 9.c. RDA and Typhoon Rehab Project Sector................................................. 5

    Figure 10. Indicator Set Menu.................................................................................. 6

    Figure 11. Project Enrollment for Single-indicator Projects........................................ 6

    Figure 12. Man-days Target....................................................................................... 7

    Figure 13. Physical Targets ........................................................................................ 8

    Figure 14. Financial Targets....................................................................................... 8Figure 15. Enrolling the Project................................................................................. 8

    Figure 16. Project Enrollment for Multi-indicator A Project....................................... 9

    Figure 16.a. Multi-indicator A: Setting up the Physical Targets................................. 10

    Figure 17. Project Enrollment for Multi-indicator B Projects..................................... 10

    Figure 17. a. Multi-indicator B: Setting up the Man-days Targets.............................. 11

    Figure 17. b. Multi-indicator B: Adding Another Indicator........................................ 11

    Figure 17. c. Multi-indicator B: Setting up Physical Targets........................................ 12

    Figure 17. d. Multi-indicator B: Setting up Financial Targets..................................... 12

    Figure 18. Project Enrollment for With-Subcomponent A Projects.......................... 13

    Figure 18. a. With-Subcomponent A : Setting up Man-days Targets....................... 13

    Figure 18. b. With-Subcomponent A : Setting up Financial Targets........................ 14

    Figure 18. c. With-Subcomponent A : Adding another Component...................... 14

    Figure 18. d. With-Subcomponent A : Setting up Physical Targets............................ 15

    Figure 19. Project Enrollment for With-Subcomponent B Projects............................15

    Figure 19.a With-Subcomponent B: Adding another Component......................... 16

    Figure 19.b With-Subcomponent B: Setting up Physical Targets............................. 16

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    7/55

    eRPMES Monitors Guide

    7

    Figure 19.c With-Subcomponent B: Setting Up Financial Targets............................ 17

    Figure 20. Saving the Enrolled Project..................................................................... 17

    Figure 21. Expanded Agency Project Page............................................................. 18

    Figure 22. Project Information................................................................................. 18

    Figure 23. Editing Project Information and Targets................................................. 18

    Figure 24. Deleting Projects..................................................................................... 19

    Figure 25. Agency Action Plan................................................................................ 19

    Figure 26. Agency Plan: Generating Spreadsheet File............................................. 19

    Figure 27. Downloading Spreadsheet File............................................................... 19

    Figure 28. Reporting Quarterly Accomplishments................................................... 20

    Figure 29. Reporting Physical, Financial, and Man-days Accomplishments............. 21

    Figure 30. Agency Monitoring Plan........................................................................... 21

    Figure 31. Physical, Financial, and Man-days Accomplishment Report.................. 22

    Figure 32. Inputting Actual Accomplishments........................................................ 22

    Figure 33. Saving the Report................................................................................... 23

    Figure 34. Prompt for Missing /Invalid Entries.......................................................... 23

    Figure 35. Submitting the Report............................................................................. 23

    Figure 36. PMC Form O-1: Physical and Financial Status Report............................. 24

    Figure 37. Agency Accomplishment: Generating Spreadsheet File......................... 24

    Figure 38. Agency Project Page.............................................................................. 26

    Figure 39. Viewing the Accomplishment Report (Form O-1)................................... 27

    Figure 40. Physical and Financial Status Report (PMC Form O-1)............................ 27Figure 41. Viewing the Agency Overall Performance............................................. 28

    Figure 42. Summary of Agency Overall Performance.............................................. 28

    Figure 43. Agency Project Page.............................................................................. 29

    Figure 44. Viewing the Accomplishment Report by Sector..................................... 29

    Figure 45. Agency Project Page.............................................................................. 30

    Figure 46. Submission Status for the Project Exception Report................................ 30

    Figure 47. The PMC Form I-3A: Project Exception Report.......................................... 31

    Figure 48. Filling out the PMC Form I-3A................................................................... 31

    Figure 49. Agency Project Page.............................................................................. 32

    Figure 50. The PMC Form I-3B: Updated Project Exception Report......................... 32

    Figure 51. Filling out the PMC Form I-3B................................................................... 33

    Figure 52. Printing Multiple Pages of the Report..................................................... 34

    Figure 53. Page Setup Menu............ ............ ........... ............ ............ ........... ............ . 34

    Figure 54. Changing Account Information............................................................. 35

    Figure 55. Account Information Page...................................................................... 35

    Figure 56. Logging out of e-RPMES........................................................................... 36

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    8/55

    eRPMES Monitors Guide

    8

    Figure 57.a. Summary Report Links ......................................................................... 37

    Figure 57.b. Summary Report Links (Agency Project page)..................................................38

    Figure 58. Monitoring Plan Summary.............................................................................. 38

    Figure 59. Monitoring Plan Drop-Down Menus)............................................................... 39

    Figure 60. MDG Sector Drop-Down Menu.......................................................................... 39

    Figure 61. PDAF Sector Drop-Down Menu..................................................................... 39

    Figure 62. RAACC Sector Drop-Down Menu................................................................ 40

    Figure 63. RDA Sector Drop-Down Menu......................................................................... 40

    Figure 64. Typhoon Rehab Sector Drop-Down Menu..................................................... 40

    Figure 65. Example of a Monitoring Plan Summary Table............................................ 41

    Figure 66. Example of Changes in a Monitoring Plan Summary Table.............................. 42

    Figure 67. Overall Performance Summary Table......................................................... 42

    Figure 68. Example of Overall Performance Summary Table........................................ 43Figure 69. Montoring Report Summary Table...................................................................... 44

    Figure 70. Example of Montoring Report Summary Table............................................... 44

    Figure 71. Job Generation Summary Table............................................................... 45

    Figure 72. Job Generation Summary Table...................................................................... 45

    Figure 73. Data Integrity Feature Location......................................................................... 46

    Figure 74. Agency Head Approval................................................................................ 47

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    9/55

    eRPMES Monitors Guide

    9

    Online Regional Project Monitoring and Evaluation System(e-RPMES) Monitors Manual

    A. Requirements

    The e-RPMES is an internet-based solution Regional Line Agencies, LocalGovernment Units and State Universities and Colleges can use to facilitatethe periodic update of their project accomplishments. It also providesdevelopment stakeholders, i.e., the Regional Development Council, quickand convenient access to the latest information on the status of programs

    and projects implemented in Region 1 as well as the performance ofgovernment agencies and institutions enrolled in the Regional ProjectMonitoring and Evaluation System (RPMES).

    The following are the basic requirements in accessing the e-RPMES:

    1. Internet connection. Make sure that your computer has access to theInternet.

    2. Mozilla Firefox Internet browser. The system works best with a Mozilla Firefox

    Internet browser. It is highly recommended that you install a Mozilla FirefoxInternet browser on your PC. The software is available for free at: http://www.mozilla.com.

    Figure 1. System Diagram

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    10/55

    eRPMES Monitors Guide

    10

    B. Getting Started

    1. To get to the e-RPMES, go to the IRISnet websiteat http://ilocos.net.ph/.

    On the IRISnet menu (left column), find and click

    the link Project Monitoring. A new tab will openon your browser containing the e- RPMES home

    page entitled: ONLINE PROJECT MONITORING.

    2. Click Login. Supply the needed information.

    The acronym (in small letters)of your agencyserves as its Username. By default, the Password

    is the same as the Username.

    Example: NEDA will have neda as Username;neda will also be the Password.

    Users are advised to change default Username

    and Password for security purposes. (Please seeI. Changing your Acccount Info). If you do not

    know your username and password, forget your login information, or

    if the system does not accept your Username and Password, please

    contact the Regional Project Monitoring Committee (RPMC) Secre-

    tariat at 072-888-2679 or 888-5501.

    1

    2

    Figure 3. The e-RPMES Login Window

    Figure 2. IRISNET Menu

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    11/55

    eRPMES Monitors Guide

    11

    C. Enrolling Projects to the Monitoring Plan (PMC Form I-1)

    1. Once you were able to successfully login, click Agency Project.

    2. To add projects individually, click ADD. The Project Enrollmentwindow will appear asking for information you are providing inthe RPMES Form I-1.

    1

    Figure 4. Online Project Monitoring Home Page

    Figure 5. Agency Project Page

    2

    INITIAL PROJECT REPORT

    (PMC Form I-1)

    This is used to record the basic information on programs and projects

    enrolled by RLA, SUC, or LGU in the RPMES. It contains such information as

    name, period, type, sector, fund source, location, indicator, and unit of

    measure of the project being enrolled.

    It also provides information on the physical and financial target as well as

    the employment generated (in man-days) by the project.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    12/55

    eRPMES Monitors Guide

    12

    Figure 6. Project Enrollment Window

    3. In Period, click -SELECT- and a drop-down menu containing the two classificationscarry over and current year will appear.These two refer to the period ofimplementation of the project.

    3

    4

    Figure 8. Project Type

    4. In Project Type, click -SELECT- and a drop-down menu will appear.From this list, click the type of projects you wish to enroll. There are five typesto choose from:

    a. (MDG) Millennium Development Goalsb. (PDAF) Priority Development Assistance Fund

    c. (RAACC) Regional Action Agenda onClimate Changed. (RDA)Regional Development Agendae. (Typhoon Rehab) Typhoon Damages

    Rehabilitation ProgramIn selecting the project type for the project thatyou are enrolling, kindly refer to the list ofprojects provided by the RPMC Secretariat.

    5. In Sector, click -SELECT- and a dropdown menu will appear showing the sectors

    Carry-Over

    A project is classified as carry-over if it was funded during the

    previousyear but still being implemented until the current year.

    Current Year

    A project is considered current year if it has been funded and is

    being implementedduring the present year.

    of the project type you selected. Click thesector to which the project belongs.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    13/55

    eRPMES Monitors Guide

    13

    a. For MDG and PDAF projects, thefollowing are the choices, which

    correspond to the eight developmentgoals:

    1. Goal 12. Goal 23. Goal 3

    4. Goal 45. Goal 56. Goal 67. Goal 78. Goal 8

    b. For RAACC projects, the choices are:1. Mitigation2. Adaptation

    c. For RDA and Typhoon Rehab projects,these are the choices:

    1. Economic Development Sector2. Social Development Sector

    3. Infra Development Sector

    4. Governance Sector

    The list provided by the RPMC Secretariatlikewise classifies the projects by sector and/

    or sub-theme. Please follow it accordingly.

    6. In Indicator Set, the system asks whetheror not the project has more than oneindicator or has sub-components. Click -

    SELECT- and a drop down menu willappear. The following are your choices:

    a. single-indicator. The project has asingle indicator.

    b. multi-indicator: A. The project hasmultiple Units of Measure with singlefunding support.

    5.a

    Figure 9.a. MDG and PDAFProject Sector

    5.b

    5.c

    Figure 9.b. RAACC Project Sector

    Figure 9.c. RDA and TyphoonRehab Project Sector

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    14/55

    eRPMES Monitors Guide

    14

    c. multi-indicator: B. The project hasmultiple Units of Measure; each Unit ofMeasure has assigned funding support.

    d. with-subcomponent: A. The projecthas subcomponents with single funding

    support.e. with-subcomponent: B. The projecthas subcomponents; each

    subcomponent has assigned fundingsupport.

    7. If the project falls undersingle-indicator,follow the steps mentioned below:

    a. In Project, provide the short name or the acronym of the projectyou wish to enrol.b. In Full Name, provide the complete title of the project as found inthe approved program of work, loan and grant agreement.

    c. In Fund, click -SELECT-. Choose by clicking whether the project isForeign or Local-funded.

    6

    Figure 10. Indicator Menu

    Figure 10. Indicator Menu

    Figure 11. Project Funding Figure 12. Project Location

    7

    7.c 7.d

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    15/55

    eRPMES Monitors Guide

    15

    d. In Location, click the specific province and district wherein the

    project will be implemented. If the project cannot be disaggregatedby province, click Regionwide.e. In Unit of Measure, provide the unit for measuring the outputs of theproject on the space provided for.

    f. To set the employment targets of your project, click the red Man-days button. The employment or jobs generated by the projects willbe measured in terms of man-days.

    i. On the Man-days Targets dialog box, set the physical targetsper quarter. For quarters which have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when the project

    will start and put 0 on the succeeding quarters.ii. Click Set Targets to save the man-days targets.

    Figure 12. Man-days Targets

    7.f

    g. To set the physical targets of your project, click the red Physicalbutton. A dialog box will appear.

    i. On the Physical Targets dialog box, set the physical targets perquarter. For quarters which have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when the projectwill start and put 0 on the succeeding quarters.

    ii. Click Set Targets to save your physical targets.

    EMPLOYMENTGENERATED

    (inman-days)

    This refers to the jobs targeted to be created by the project, expressed in

    man-days for the quarter.

    Formula:

    Man-days = no. of persons employed X no. of days worked during the quarter

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    16/55

    eRPMES Monitors Guide

    16

    7.g

    Figure 13. Physical Targets

    h. To set the financial targets of your project, click on the red Financialbutton. A dialog box will appear.

    i. On the Financial Targets dialog box, set the financial targets perquarter. For quarters which have no target, put 0.ii. Click Set Targets to save your financial targets.

    i. Click Enroll Project to save theproject and its correspondingtargets.

    7.h

    Figure 14. Financial Targets

    Figure 15. Enrolling the Project

    7.i

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    17/55

    eRPMES Monitors Guide

    17

    8. If the project falls under multi-indicator: A, follow these steps:a. In Period, click -SELECT- then classify whether the project is carryover or current year project.b. In Project, provide the short name or the acronym of the project.

    c. In Full Name, provide the complete title of the project as found in

    the approved program of work, loan and grant agreement.d. In Fund, click -SELECT-. Choose by clicking whether the project isForeign or Local-funded.

    e. In Location, click the province anddistrict wherein the project will be

    implemented. If the project cannot bedisaggregated by province, clickRegionwidef. Click the red financial button. On the

    dialogue box, set the financial targets perquarter. For quarters which have notarget, put 0.g. Click Set Targets to save the financialtargets.

    Figure 15. Project Enrollment for Multi-indicator:A Projects

    8

    8.g

    8.f

    h. To add the units of measure of the project, click the icon. Anotherrow will appear below a yellow bar.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    18/55

    eRPMES Monitors Guide

    18

    i. In Unit of Measure, provide the unit of measure of the project onthe space provided for.ii. To set the physical targets of your project, click the red Physicalbutton. A dialog box will appear.

    1. On the Physical Targets dialog box, set the physical targets

    per quarter. For quarters that have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when theproject will start and put 0 on the succeeding quarters.2. Click Set Targets to save your physical targets.

    h. To add another unit of measure, simply click the icon and repeat

    steps 9.g.i. through iv.i. To remove a unit of measure, click the icon.j. Click Enroll Project to save the project and its corresponding targets.

    9. If the project falls under multi-indicator: B, follow these steps:

    8.g.

    ii

    9

    Figure 16.a. Multi-indicator A: Setting up the Physical Targets

    Figure 17. Project Enrollment for Multi-indicator: B Projects

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    19/55

    eRPMES Monitors Guide

    19

    a. In Period, click -SELECT- then classify whether the project is carryover or current year project.b. In Project, provide the short name or the acronym of the project.c. In Full Name, provide the complete title of the project.

    d. In Fund, click -SELECT-. Choose by clicking whether the project is

    Foreign or Local-funded.e. In Location, provide the site or location of the project.

    f. To set the employment targets of your project, click the Man-daysbutton.

    i. On the Man-days Targets dialog box, set the physical targets perquarter. For quarters which have no targets, put 0. For retained

    targets, indicate the number of units on the quarter when the projectwill start and put 0 on the succeeding quarters.ii. Click Set Targets to save the man-days targets.

    g. To add another indicator, click the icon. Another row will appearbelow a yellow bar.

    i. In Fund, click -SELECT-. Choose by clicking whether the projectis Foreign or Local-funded.ii. Indicate the project location by choosing the district andprovince from the set of choices.

    9.f

    9.g

    Figure 17.a. Multi-indicator B: Setting up the Man-days Target

    Figure 17.b. Multi-indicator B: Adding another Indicator

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    20/55

    eRPMES Monitors Guide

    20

    iii. In Unit of Measure, provide the unit of measure of the project onthe space provided for.

    iv. To set the physical targets of your project, click the red Physicalbutton. A dialog box will appear.

    1. Set the physical targets per quarter. For quarters that have notargets, put 0. For retained targets, indicate the number of units

    on the quarter when the project will start and put 0 on thesucceeding quarters.2. Click Set Targets to save your physical targets.

    v.To set the financial targets of your project, click the red Financialbutton. A dialog box will appear.

    1. Set the financial targets per quarter. For quarters that have notarget, put 0 in the space provided for.

    ii.Click on Set Targets to save your financial targets.

    h. Click Enroll Project to save the project and its corresponding targets.

    9.g.

    v

    9.g.

    iv

    Figure 17.c. Multi-indicator B: Setting up Physical Targets

    Figure 17.d. Multi-indicator B: Setting up Financial Targets

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    21/55

    eRPMES Monitors Guide

    21

    10. If the project falls under with-subcomponent: A, follow these steps:

    a. In Period, click -SELECT- then classify whether the project is carry

    over or current year project.b. In Project, provide the short name or the acronym of the project.

    c. In Full Name, provide the complete title of the project.d. In Fund, click -SELECT-. Choose whether the project is Foreignor Local-funded.

    e. In Location, click the province and district wherein the project willbe implemented. If the project cannot be disaggregated by province,

    click Regionwide.

    f. Provide the Unit of Measure in the space provided for.

    g. To set the employment targets of your project, click the Man-daysbutton.

    i. On the Man-days Targets dialog box, set the physical targets perquarter. For quarters which have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when the project

    will start and put 0 on the succeeding quarters.ii. Click Set Targets to save the man-days targets.

    10

    10.g

    Figure 18. Project Enrollment for With-Subcomponent A Projects

    Figure 18.a. With-Subcomponent A: Setting up Man-days Targets

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    22/55

    eRPMES Monitors Guide

    22

    h. To set the financial targets of your project, click on the red Financial

    button. A dialog box will appear.i. Set the financial targets per quarter. For quarters that have no target,

    put 0.ii. Click Set Targets to save your financial targets.

    i. To add subcomponents of the project, click the icon. Another rowwill appear below an orange bar.

    i. In Component, provide the short name or acronym of theprojects subcomponent.

    ii. In Full Name, provide the complete title of the projectssubcomponent.

    iii. In Location, click the specific province and the district whereinthe project will be located. If the project cannot be disaggregatedby province, click Regionwide.iv. In Unit of Measure, provide the unit of measure of thesubcomponent on the space provided for.

    10.g

    Figure 18.c. With-Subcomponent A: Adding another Component

    Figure 18.b. With-Subcomponent A: Setting up Financial Targets

    10.i

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    23/55

    eRPMES Monitors Guide

    23

    v. To set the physical targets of the subcomponent, click the redPhysical button. A dialog box will appear.

    1. Set the physical targets per quarter. For quarters that have notargets, put 0. For retained targets, indicate the number of units

    on the quarter when the project will start and put 0 on the

    succeeding quarters.2. Click Set Targets to save your physical targets.

    j. To add another subcomponent, simply click the the icon and repeatsteps 10.h.i through v.2.k. To remove a subcomponent, click icon.l. Click Enroll Project to save the project and its corresponding

    subcomponents.

    11. If the project falls under with-subcomponent: B, follow the steps below:a. In Period, click -SELECT- then classify whether the project is carryover or current year project.

    b. In Project, provide the short name or the acronym of the project.

    10.h.

    v

    11

    Figure 18.d. With-Subcomponent A: Setting Up Physical Targets

    Figure 19. Project Enrollment for With-Subcomponent B Projects

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    24/55

    eRPMES Monitors Guide

    24

    c. In Full Name, provide the complete title of the project.d. In Fund, click -SELECT-. Choose by clicking whether the project isForeign-funded or Local-funded.

    e. In Location, provide the site or location of the project.

    f. To add subcomponents of the project, click the icon. Another rowwill appear below an orange bar.

    i. In Component, provide the short name or acronym of theprojects subcomponent.

    ii. In Full Name, provide the complete title of the projectssubcomponent.iii. In Fund, indicate whether the project is foreign or local-funded.iv. In Location, select the specific location by choosing the province

    and district of project sub-component implementation.v. In Unit of Measure, provide the unit of measure of thesubcomponent on the space provided for.v. To set the physical targets of the subcomponent, click the red

    Physical button. A dialog box will appear.

    11.f

    11.f.

    v

    Figure 19.a. With-Subcomponent B: Adding another Component

    Figure 19.b. With-Subcomponent B: Setting up Physical Targets

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    25/55

    eRPMES Monitors Guide

    25

    1. On the Physical Targets dialog box, set the physical targetsper quarter. For quarters which have no targets, put 0. Forretained targets, indicate the number of units on the quarter whenthe project will start and put 0 on the succeeding quarters.

    2. Click Set Targets to save your physical targets.vi. To set the financial targets of your projects subcomponent, clickthe red Financial button. A dialog box will appear.

    1. On the Financial Targets dialog box, set the financial targets

    per quarter. For quarters which have no target, put 0.2. Click on Set Targets to save your financial targets.

    g. To add another subcomponent, simply click the icon and repeatsteps 10.f.i through to vi.2.h. To remove a subcomponent, click the icon.i. Click Enroll Project to save the project and its correspondingsubcomponents.

    12. Once you click Enroll Project, the windowwill close and you will be redirected to the

    Agency Project page. To view your enrolled

    projects, choose the Project Type and clickthe expand icon .

    The system will show the information regardingthe projects location, unit of measure, as wellas the targeted physical accomplishment,

    financial resources, and man-days.

    11. f.

    vi

    11.i

    Figure 19.c. With-Subcomponent B: Setting Up Financial Targets

    Figure 20. Saving the EnrolledProject

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    26/55

    eRPMES Monitors Guide

    26

    a. Other information regarding the project

    such as the period of implementation,project type, and fund source can beobtained by simply pointing the cursor overthe project name (in blue).

    13. To edit the information and quarterlytargets entered in the project enrollment,

    click the icon. A new window will appear.

    14. Input the necessarycorrections then click theSave Changes button atthe lower right hand cornerof the window.

    15. To remove projects,indicators and sub-

    components, simply tick theprojects you wish to removeon the box on the far rightside of the monitoring plan.Click DELETE SELECTED.

    12

    12.a

    13

    Figure 21. Expanded Agency Project Page

    Figure 22. Project Information

    Figure 23. Editing Project Information and Targets

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    27/55

    eRPMES Monitors Guide

    27

    16. To view the Agency Action Plan (PMC

    Form I-1, click the icon underneath

    the Action Plan / I-1 column. A newwindow will open to show the AgencyAction Plan.

    a. To generate a spreadsheet file of the

    Agency Action Plan, click the icon

    beside the Project Type drop-down

    selection menu. A dialogue box will

    appear indicating wherethe download link for thespreadsheet can befound. Click OK.

    b. Click the link (here)below the Agency ActionPlan matrix to download

    the spreadsheet file.

    17. To enroll another project,follow steps C.1 through 11.

    15

    Figure 24. Deleting Projects

    Figure 25. Agency Action Plan

    Figure 26. Agency Plan: Generating Spreadsheet File

    Figure 27. Downloading Spreadsheet File

    16

    16.a

    16.b

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    28/55

    eRPMES Monitors Guide

    28

    2. Notice too that under the column, Physical, Financial and Man-daysReport, the status of your submission of quarterly accomplishment reportor PMC Form I-2 is indicated under the sub-column, Submission Status. If

    the color of the quarter (Q1, Q2, Q3 and Q4), is red, it means that you

    D. Submission of Quarterly Accomplishment Reports (PMC Form I-2)

    Figure 28. Reporting Quarterly Accomplishments

    1

    Physical and Financial AccomplishmentReport

    (PMC Form I-2)

    This report provides information on the status of implementation of

    projects on a quarterly basis. It facilitates the quarterly reporting on the

    status of physical and financial accomplishment of the enrolled projects.

    The accomplishment on man-days generated as of the reporting period is

    also integrated in the form. Information agencies deem necessary in

    interpreting or justifying the status of implementation of their respective

    projectsmay also be stipulated in the report .

    1. On the Agency Project page, choose the project type you wish to reporton by clicking -SELECT- on the Project Type. Notice that a row appearsbetween ADD and DELETE SELECTED buttons.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    29/55

    eRPMES Monitors Guide

    29

    Figure 29. Reporting Physical, Financial, and Man-days Accomplishments

    2

    have not submitted a report for that quarter; green means that you havealready submitted a report for the specific quarter. If the color of the quarter

    isbrown, it means that you are not yet required to submit a report for thatquarter.

    3. Click on the expand icon . Your agency monitoring plan will appear.

    4. On the Physical, Financial, and Man-days Report column and I-2 sub-

    column, click on the submit report icon . A new window will open

    containing the PMC Form I-2: Physical, Financial, and Man-daysAccomplishment Report on the Agency Action Plan.

    5. In Quarter, select by clicking the period you wish to report. Yourmonitoring plan will appear.

    Figure 30. Agency Monitoring Plan

    4

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    30/55

    eRPMES Monitors Guide

    30

    Figure 31. Physical, Financial, and Man-days Accomplishment Report

    6. In Actual Accomplishment to Date (Column 10), provide theaccomplishment in each of the projects. For quarters which do not have

    targets, put 0.

    7. In Actual Releases to Date (Column 16), provide the amount of the

    funds released for the project. For quarters which do not have financialtargets, put 0.

    8. In Actual Expenditure to Date (Column 17), provide the amount of thefunds released which may have been either Disbursed or AccountsPayable.

    9. In Remarks (Column 26), provide information that are useful in

    interpreting or justifying your report.

    Figure 32. Inputting Actual Accomplishments

    5

    6

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    31/55

    eRPMES Monitors Guide

    31

    10. You may save yourreport in case you cannotfinish encoding youragency accomplishments

    for the quarter. Find and

    click Save Report buttonat the bottom-right cornerof the window. A dialoguebox will open to confirm

    that the records that wereinputted have beensaved. Click OK.

    Figure 33. Saving the Report

    10

    Take note that by clicking Save Report, the report has not yet been

    submitted to the Secretariat; it is merely saved. Computations for the projecttarget accomplishments will only be done once the report has beencompleted and

    submitted.

    11. Make sure that therequired fields in columns10, 16, 17 and 26 are all

    complete before you

    submit your report. Findand click Submit Report

    button at the bottom-right corner ofthe window to submit the report.

    The system will prompt you for fieldswith missing or invalid entries.

    12. If your report is complete, aprintable version of your report willopen once you click Submit Report.

    Figure 34. Prompt for Missing /Invalid Entries

    11

    Figure 35. Submitting the Report

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    32/55

    eRPMES Monitors Guide

    32

    Figure 36. PMC Form O-1: Physical andFinancial Status Report

    a. To generate a spreadsheet fileof the Physical and Financial Status

    report, click the icon beside the

    Quarter drop-down menu. Adialogue box will appear indicatingwhere the download link for thespreadsheet can be found. Click

    OK.i. Click the link (here) belowthe Agency Action Plan matrixto download the spreadsheetfile.

    12.a

    Figure 37. Agency Accomplishment:

    Generating Spreadsheet File

    12

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    33/55

    eRPMES Monitors Guide

    33

    6

    The e-RPMES automatically computes for the physical accomplishment, ex-

    penditure rate and overall performance. The online system also generatescorresponding interpretation for the level of overall performance of theagency.

    Physical Accomplishment

    This refers to the ratio of the actual accomplishment to the physical targets

    during the quarter, multiplied by 100.

    Formula:Standard of Physical Actual Accomplishment

    Accomplishment Target Accomplishment 100

    FundsUtilization

    This refers to the ratio of the total expenditure to the total releases during

    the quarter, multiplied by 100.

    Formula:

    Standard of Funds Total Expenditures

    Utilization Total Releases 100

    Overall Performance

    Otherwise referred to as financially-correlated performance, this is the ratio

    of the agencys physical accomplishment to its funds utilization during the

    quarter, multipliedby 100.

    Formula: Standard of Physical

    Standard of Overall Accomplishment

    Performance Standard of Funds

    Utilization

    100

    E. Computing for the Agency Overall Performance

    (Financially- Correlated Performance)

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    34/55

    eRPMES Monitors Guide

    34

    The following table shows the overall performance rating as well as theinterpretation of the agencys performance.

    Table 1. Overall Performance Rating

    F. Viewing the Project Monitoring Reports

    1. Agency Accomplishment Report (PMC Form I-2)

    Figure 38. Agency Project Page

    1.a

    Deviation from

    Target

    Recommended

    Interpretation Qualitative Rating

    105.1 - above Less Accurate Planning Fair

    100.0-105.0 Very Efficient and Effective Outstanding

    Program Management

    95.0-99.9 Efficient and Effective Excellent

    Program Management

    85.0-94.5 Very Efficient and Effective Very Satisfactory

    Program Implementation

    75.0-84.9 Efficient and Effective Satisfactory

    Program Implementation

    50.0-74.9 Less Efficicent Program Fair

    Implementation

    0.0-49.9 Inefficicent Program Unsatisfactory

    Implementation/

    Defective Planning

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    35/55

    eRPMES Monitors Guide

    35

    a. To view the agency accomplishment report, proceed to the AgencyProject Page first.

    b. Find the O-1

    subcolumn underPhysical, Financialand Man-daysReport and click the

    icon. A new

    window containing

    the PMC Form O-1 willappear.

    Figure 40. Physical and Financial Status Report (PMC Form O-1)

    Figure 39. Viewing the Accomplishment Report (Form O-1)

    1.b

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    36/55

    eRPMES Monitors Guide

    36

    2. Agency Overall Performance

    a. In the agency project page, click the icon underneath the column

    of Project Exception Report to view the overall performance ofagencies participating in the e-RPMES.

    b. A new window will appear containing the Summary of Agency OverallPerformance.

    Figure 41. Viewing the Agency Overall Performance

    Figure 42. Summary of Agency Overall Performance

    2.a

    2.b

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    37/55

    eRPMES Monitors Guide

    37

    3. Accomplishment Report by Sector

    a. In the agency project page, select the type of project from the drop-

    down Project Type menu, then click the icon underneath the

    column of Updated Project Exception Report to view theaccomplishment report on projects enrolled in the different sectors.

    b. In the new window, select the particular Quarter and Sector youwish to view. The system will automatically load the the Summary ofAgency Overall Performance by Sector.

    Figure 42. Viewing the Agency Accomplishment Report by Sector

    Figure 43. Agency Project Page

    Figure 44. Viewing the Accomplishment Report by Sector

    3.a

    3.b

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    38/55

    eRPMES Monitors Guide

    38

    G. Submission of Project Exception Report (PMC Form I-3A)

    1. In filling out the Project Exception Report, go to the Agency Projectpage, choose the project type by clicking -SELECT- on the Project Type.

    2. On the Project Exception Report column, under the Submission Statussub-column, see if the period (Q1, Q2, Q3 or Q4) you have reported ishighlighted in red. This means that some of your projects are behind scheduleand have registered negative slippages of 15% or higher. You are required

    to accomplish the Project Exception Report or PMC Form I-3A. If the periods(Q1, Q2, Q3 and Q4) remain colored brown, your projects do not require

    submission of the Project Exception Report.

    Figure 45. Agency Project Page

    Figure 46. Submission Status for the Project Exception Report

    PROJECT EXCEPTION REPORT

    (PMC Form I-3A)

    This is used to record critical problems resulting in the delay of project

    implementation that need immediate action by the RPMC or the RDC. It is

    also used to document the reasons or factors that have contributed to theoutstanding performance in the implementation of a specific project.

    1

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    39/55

    eRPMES Monitors Guide

    39

    The system will prompt the implementing agencies regarding the due datefor submission of the PER as scheduled by the RPMC Secretariat.

    3. On the same column, find and click on the submit report icon. A newwindow will open containing the PMC Form I-3A: Project Exception Report.

    4. In Quarter, select which period you want to report. Projects in differentsectors, which are behind schedule, are listed on the first column of the

    Name of Project/location column.The slippages of the projects are indicated under the Findings column.

    5. On the Possible Reasons/Causes column, indicate the reasons for thedelay in the project implementation.

    6. On the Recommendations column, indicate suggestions to improvethe work progress or remedial measures to address the problemsencountered.

    Figure 47. The PMC Form I-3A: Project Exception Report

    Figure 48. Filling out the PMC Form I-3A

    3

    4

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    40/55

    eRPMES Monitors Guide

    40

    7. Make sure that all required fields are filled-out. Click Save Report tosave and submit your report.

    H. Submission of Updated Project Exception Report (PMC Form I-3B)

    1. Submission of the Updated Project Exception Report or PMC Form I-3B is

    required only for projects that have negative 15% slippage seven days priorto a scheduled meeting of the RPMC. The RPMC Secretariat will notifyconcerned agencies to accomplish the Updated Project Exception Reportprior to the meeting.

    2. After receiving notification from the RPMC Secretariat, go to the Agency

    Project page. Choose the project type by clicking -SELECT- on theProject Type box.

    3. On the Updated Project Exception Report column, click the submit report

    icon . A new window will open containing the PMC Form I-3B:

    Figure 49. Agency Project Page

    Figure 50. The PMC Form I-3B: Updated Project Exception Report

    3

    2

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    41/55

    eRPMES Monitors Guide

    41

    Updated Project Exception Report. Note that the entries made in the ProjectException Report of PMC Form I-3A were automatically replicated in this

    form.

    4.On the Actions Taken column, indicate the steps undertaken to addressthe problems encountered or measures that have improved the workprogress.

    5. On the Updates column, provide the latest status of the project.

    6. Make sure that all required fields are filled-out. Click Save Report tosave and submit your report.

    Figure 51. Filling out the PMC Form I-3B

    4

    I.Printing the Reports

    1. To print the Physical and Financial Status Report, you must view the report

    first. Kindly refer to F. Viewing the Project Monitoring Reports for theprocedures.

    a. In printing multiple pages of the report, click the appropriate icon

    at the left side of the status report matrix to create separate tables foreach project indicator or sub-component.

    b. Click the icons to create and adjust page breaks for printing

    the status report.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    42/55

    eRPMES Monitors Guide

    42

    Figure 52. Printing Multiple Pages of the Report

    Figure 53. Page Setup Menu

    c. In the window containing the report you wish to print, click File on theMenu Bar then click Page Setup to customize the documentaccording to your printing preferences before hitting the Print menu

    and creating a hardcopy of the report.

    1.c

    1.a

    It is also advised to preview the document first before printing to makesure that the desired setups have been followed.

    d. In printing summary reports of agency performance, proceedimmediately to step I.1.c.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    43/55

    eRPMES Monitors Guide

    43

    Figure 47. Logging out of thee-RPMES

    J. Changing Account Information

    For the purpose of securing the

    integrity of the information beinginputted into the online RPMES,

    among others, it is highly advisedthat agencies change their e-RPMES account information. Please

    consider the following steps:

    Figure 54. Changing Account Information

    1

    2

    1. Once you login, click MyAccount.

    Figure 55. Account Information Page

    2

    2. In Old Username, provide your present username.

    3. In New Username, provide the new username you wish to use.4. In Old Password, type your present password.

    5. In New Password, type your desired password.

    6. In Re-Type Password, simply re-type your desired password.

    7. Click Save and Exit. Your new username and password is saved. Pleaseremember your username and password.

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    44/55

    eRPMES Monitors Guide

    44

    1

    K. Log-Out Menu

    1. Click Log-out menu to exit from

    the Online Project Monitoring.

    Figure 56. Logging out of e-RPMES

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    45/55

    eRPMES Monitors Guide

    45

    Addendum to the ERPMES Monitors Guide

    (October 2011)

    In the 2nd Quarter of 2011, the following additional features were included

    in the eRPMES.

    A. Quick Access to Summary Reports

    In the home page of the eRPMES, summary tables for Monitoring Plan,

    Overall Performance, Accomplishment Report and Job Generation Reportcan be readily accessed not only by the project monitors and RPMC

    Secretariat, but also by the general public.

    1. To access the summary reports of each project type, click the drop-

    down buttons to indicate the Year and the Project type you wish toview. These are found at the lower left side of the window just below theeRPMES logo and description.

    For agency users, these links are also located below the list of agencies

    in the Agency Project page of the eRPMES.

    Figure 57.a. Summary Report Links

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    46/55

    eRPMES Monitors Guide

    46

    Figure 57.b. Summary Report Links (Agency Project page)

    1.a. To view the Monitoring Plan summary table, click the link for

    Monitoring Plan (in violet colored text). A new window showingthe title PMC Form I-1 Agency Action Plan will appear. This table

    lists down the enrolled projects of the different implementing

    agencies as well as the quarterly physical, financial, and man-

    days targets of the project. The location and unit for measuring

    the project deliverables can be seen in the summary.

    Figure 58. Monitoring Plan Summary

    1.a.i. Use the drop-down buttons to indicate the specific Quarter to

    be viewed. The default setting for viewing the summary tables is the

    overall report. Users can delimit the information they want to view

    based on the Sector, Location, Implementation Period, and Fund

    Source of the Projects. The drop-down button for each of these fields

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    47/55

    eRPMES Monitors Guide

    47

    can help the users delimit or extend the project information

    according to their desired specifications.

    1.a.ii. The Sector options in the drop-down menu vary depending on

    the Project Type. The following figures show the aforementioned

    variations:

    Figure 59. Monitoring Plan Drop-Down Menus

    Figure 60. MDG Sector Drop-Down Menu

    Figure 61. PDAF Sector Drop-Down Menu

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    48/55

    eRPMES Monitors Guide

    48

    Figure 62. RAACC Sector Drop-Down Menu

    Figure 63. RDA Sector Drop-Down Menu

    Figure 64. Typhoon Rehab Sector Drop-Down Menu

    1.a.iii. The following shows an example of the Monitoring Plan

    Summary Table. The specified fields in this example are:

    Project Type: RDA Quarter: SecondSector: Agribusiness Sector Location: Select All

    Implementation Period: Select All Fund Source: Select All

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    49/55

    eRPMES Monitors Guide

    49

    Figure 65. Example of a Monitoring Plan Summary Table

    The specific projects or implementing agencies are listed on the first

    column. The specific implementation period, sector, and fund source

    are also properly indicated on the same column prior to the agencys

    list of projects.

    1. a.iv. The table automatically adjusts as the fields are changed to

    indicate the specific viewing options of the user. For example,

    delimiting the field for Location of project, which classifies the projects

    according to the scope of implementation (Region-wide, Province-

    wide, and Congressional District and City-wide) will result to the

    changes in the Summary Table. In the following example, the

    Location field has been specified to Ilocos Norte. The rows

    containing information on projects that are implemented by

    agencies in Ilocos Norte are highlighted (in yellow).

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    50/55

    eRPMES Monitors Guide

    50

    Figure 66. Example of Changes in a Monitoring Plan Summary Table

    1.b. To view the Overall Performance of agencies, click the link for

    Overall Performance (in violet colored text) found in the eRPMEShome page. Prior to this, the Year and Project Type should already

    be indicated. A new window will open, showing the summary table

    for over all performance.

    Figure 67. Overall Performance Summary Table

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    51/55

    eRPMES Monitors Guide

    51

    1.b.1. Notice that the column on Project Caterogy also includes

    the information on the implementation period of projects, particularly

    carry overand current yearprojects. Fund source, which is either

    foreign or local, is also indicated. Notice too that there are still no

    pertinent values indicated in the specific columns for Physical Status,

    Financial Status, Overall Performance, Interpretation and Man-days

    Status.

    Use the drop-down button to choose the Quarter to be viewed.

    Upon choosing the quarter, information on the performance of

    agency implementers will immediately be populated.

    The following example shows the 2nd quarter 2011 overall

    accomplishment of agencies under the theme MillenniumDevelopment Goals.

    Figure 68. Example of Overall Performance Summary Table

    1.c. To view the Accomplishment Report of agencies, click the link

    for Accomplishment Report (in violet colored text) found in the

    eRPMES home page. Select the year and project type you wish to

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    52/55

    eRPMES Monitors Guide

    52

    view. Another window will immediately open to show the

    Accomplishment Report on the Agency Action Plan.

    Figure 69. Montoring Report Summary Table

    1. c.i. Use the drop-down buttons to indicate the specific Quarter to

    be viewed. The default setting for viewing the summary tables is the

    overall report. Users can delimit the information they want to view

    based on the Sector, Location, Implementation Period, and FundSource of the Projects. The drop-down button for each of these fields

    can help the users delimit or extend the project information

    according to their desired specifications.

    The following example shows the RDA accomplishment report of

    agencies in the second quarter 2011.

    Figure 70. Example of Montoring Report Summary Table

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    53/55

    eRPMES Monitors Guide

    53

    1.d. To view the Job Generation Report of agencies, click the link for

    Job Generation Report (in violet colored text) found in the eRPMES

    home page. The year and project type you wish to view should

    already be indicated. Another window will direct you immediately

    to the Job Generation Report summary table.

    Figure 71. Job Generation Summary Table

    1.d.i. Use the drop-down buttons to indicate the specific Quarter to

    be viewed. The default setting for viewing the summary tables is the

    overall report. Users can delimit the information they want to view

    based on the Sector, Location, Implementation Period, and Fund

    Source of the Projects. The drop-down button for each of these fields

    can help the users delimit or extend the project information

    according to their desired specifications.

    Figure 72. Job Generation Summary Table

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    54/55

    eRPMES Monitors Guide

    54

    The preceding example shows the RAACC Man-days

    Accomplishment agencies in the second quarter 2011. The quarterly

    targets of the project as well as the actual accomplishment and

    Job Generation Performance can be seen in the report.

    B. Data Integrity

    Another feature was included to ensure that the data submitted through

    the eRPMES are reliable. This involves indicating that the data was duly

    approved by the agency head prior to encoding and submission to the

    RPMC Secretariat.

    1. Provisions for this can be found at the lowest portion of the PMC FormI-2: Physical, Financial and Man-Days Accomplishment Report on the

    Agency Action Plan before the Save Report and Submit Report

    buttons.

    Figure 73. Data Integrity Feature Location

  • 8/2/2019 eRPMES Monitor's Guide Version 2

    55/55

    eRPMES Monitors Guide

    b.1. To signify that the encoded data has been durly approved by

    the Head of the Agency, click on the box beside Agency Head

    Approval (in red color).

    b.2. Supply your name and designation on the space provided for

    before clicking the Submit Report Button.

    Figure 74. Agency Head Approval