eRPMES Monitors Guide
2
-
8/2/2019 eRPMES Monitor's Guide Version 2
3/55
eRPMES Monitors Guide
3
Introduction
The Online Regional Project Monitoring and
Evaluation System (eRPMES)
The Online Project Monitoring is an internet-based solution tofacilitate the enrollment, submission and generation of monitoring
reports patterned after the RPMES. It enables users to update peri-
odic project accomplishment reports and access up-to-date infor-
mation on project status. The system likewise generates and providesinformation on the performance of agencies taking into consideration
the employment generation, physical accomplishment and funding
utilization of their projects included in the Annual Project Monitoring
Plan.
-
8/2/2019 eRPMES Monitor's Guide Version 2
4/55
eRPMES Monitors Guide
4
Republic o f the Philippines
REGIONAL DEVELOPMENT COUNCIL
Region 1c/o NEDA Regional O ffice No. 1
Heroes Hi ll, Guerrero Road, City of San Fernando, 2500 La Unio n
Tel Nos. 888-5501 * 888-2679 * 888-2680 * 700-0856 Fax no. 888-2708 E-mail address: [email protected] Web Address: http//www .neda1.net
RDC OFFICIALS
GOV. DEOGRACIAS VICTOR SAVELLANO
Chairman
DR. SALVADOR T. DUQUE
Co-Chairman
DIR. LEONARDO N. QUITOS, JR.
Vice-chairman
ARD NESTOR G. RILLON
Secretary
RDC COUNCIL M EMBERS
Local Government Units
Gov. Michael Keon
Gov. Deogracias Victor Savellano
Gov. Manuel Ortega
Gov. Amado Espino, Jr.
Mayor Hernani Braganza
Mayor AmadeoPerez
Mayor Julier Resuello
Mayor Alipio Fernandez, Jr.
Mayor Pablo C. Ortega
Mayor Allen Singson
Mayor Eva Marie Medina
Mayor Michael Farias
Mayor Jeffrey Nalupta
Mayor Ernesto Castaeda, Jr.
Mayor EdgardoZaragoza
Mayor George Pinzon
Mayor Ramon Guico, Jr.
Mayor Joseph de Lara
Government Agencies
USec. HermenegildoDumlao - NLGQA-PMODir. Florante Leal - DTI
OIC Dir. Valeriano Lopez - DOH
Dir. Mariano R. Alquiza - DPWH
Dir. Manuel Biason- DILG
Dir. Cipriano Santiago -DA
Dir. Homer Tobias - DAR
Dir. Samuel R. Peafiel - DENR
Dir. Elsa Chan -DOST
Dir. Leonardo Reynoso - DSWD
Dir. Martin Valera -DOT
Mgr. Silverio Mangaoang, Jr. - DOTC-RMC
Dir. Peter Baluyan - DOF-BLGF
Dir. Janet Abuel - DBM
Dir. Ligaya Soledad Miguel -DepEd
OIC Dir. Henry John Jalbuena - DOLE
OIC Josephine Sanchez -PM S
Dir. Evelyn Pascua - CHED
Dir. Ramon Gatan - PNP
Dir. PerlitaTabisaura NICA
Dir. Washington Agustin TESDA
Dir. Anita Chauhan CHR
Dir. Primo Quetulio - BSP
Private Sector
Dr. Salvador Duque
Mr. Vincent Adorna
Dr. Roberto de los Reyes
Mr. Ambrocio Valero
Mr. Mario Zamoranos
Mr. Marcelino dela Cruz
Mr. Nelson Yuchiongtian
Mr. Rodolfo Posadas
Pastor Roland Santiago
Mrs. Carmelita Duque
Engr. Antonio de vera
Col. SinforosoDumling (Ret)
Mr. Glen Mark Dacasin
ADVISORY COMMITTEE
HON. ROQUE R. ABLAN, JR.
1st District, Ilocos Norte
HON. FERDINAND R. MARCOS
2nd District, Ilocos NorteHON. RONALD SINGSON
1st District, Ilocos Sur
HON. ERIC D. SINGSON
2nd District, Ilocos Sur
HON. VICTOR FRANCISCO C. ORTEGA
1st District, La Union
HON. TOMAS L. DUMPIT, JR.
2nd District, La Union
HON. ARTHUR D. CELESTE
1st District, Pangasinan
HON. VICTOR AGUEDO E. AGBAYANI
2nd District, Pangasinan
HON. RACHEL J. ARENAS
3rd District, Pangasinan
HON. JOSE C. DE VENECIA, JR.
4th District, Pangasinan
HON. MARCOS O. COJUANGCO
5th District, Pangasinan
HON. CONRADO M. ESTRELLA III
6th District, Pangasinan
-
8/2/2019 eRPMES Monitor's Guide Version 2
5/55
eRPMES Monitors Guide
5
T a b l e of C o n t e n t s
Online Regional Project Monitoring and Evaluation System(e-RPMES) Monitors Guide
Introduction........................................................................................................... i
RDC ExCom Resolution No. 6, s. of 2010............................................................ ii
A. Requirements............................................................................................. 1
B. Getting Started......................................................................................... 2
C. Enrolling Projects to the Monitoring Plan (PMC Form I-1)................ 3
D. Submission of Quarterly Accomplishment Reports (PMC Form I-2)... 20
E. Computing for the Agency Overall Performance............................. 25
F. Viewing the Project Monitoring Reports............................................. 26
1. Agency Accomplishment Report................................................... 26
2. Agency Overall Performance......................................................... 273. Accomplishment Report by Sector................................................ 28
G. Submission of Project Exception Report (PMC Form I-3A............... 30
H. Submission of Updated Project Exception Report (PMC Form I-3B).. 32
I. Printing the Project Monitoring Reports............................................... 33
J. Changing Account Information................................................... 35
K. Log-out Menu.......................................................................................... 36
Addendum to the e-RPMES Monitors Guide (October 2011)...................... 37
A. Quick Access to Summary Reports...........................................................37
B. Data Integrity...................................................................................... 46
-
8/2/2019 eRPMES Monitor's Guide Version 2
6/55
eRPMES Monitors Guide
6
List of Tables
Table 1. Overall Performance Rating................................................................... 26
List of Figures
Figure 1. System Diagram ......................................................................................... 1
Figure 2. IRISNET Menu............................................................................................... 2
Figure 3. e-RPMES Log-in Window............................................................................. 2
Figure 4. Online Project Monitoring Home Page................... ................. ................. 3
Figure 5. Agency Project Page................................................................................ 3
Figure 6. Project Enrollment Window....................................................................... 3
Figure 7. Project Period............................................................................................ 4
Figure 8. Project Type................................................................................................ 4
Figure 9. a. MDG and PDAF Project Sector............................................................... 5
Figure 9.b. RAACC Project Sector............................................................................. 5
Figure 9.c. RDA and Typhoon Rehab Project Sector................................................. 5
Figure 10. Indicator Set Menu.................................................................................. 6
Figure 11. Project Enrollment for Single-indicator Projects........................................ 6
Figure 12. Man-days Target....................................................................................... 7
Figure 13. Physical Targets ........................................................................................ 8
Figure 14. Financial Targets....................................................................................... 8Figure 15. Enrolling the Project................................................................................. 8
Figure 16. Project Enrollment for Multi-indicator A Project....................................... 9
Figure 16.a. Multi-indicator A: Setting up the Physical Targets................................. 10
Figure 17. Project Enrollment for Multi-indicator B Projects..................................... 10
Figure 17. a. Multi-indicator B: Setting up the Man-days Targets.............................. 11
Figure 17. b. Multi-indicator B: Adding Another Indicator........................................ 11
Figure 17. c. Multi-indicator B: Setting up Physical Targets........................................ 12
Figure 17. d. Multi-indicator B: Setting up Financial Targets..................................... 12
Figure 18. Project Enrollment for With-Subcomponent A Projects.......................... 13
Figure 18. a. With-Subcomponent A : Setting up Man-days Targets....................... 13
Figure 18. b. With-Subcomponent A : Setting up Financial Targets........................ 14
Figure 18. c. With-Subcomponent A : Adding another Component...................... 14
Figure 18. d. With-Subcomponent A : Setting up Physical Targets............................ 15
Figure 19. Project Enrollment for With-Subcomponent B Projects............................15
Figure 19.a With-Subcomponent B: Adding another Component......................... 16
Figure 19.b With-Subcomponent B: Setting up Physical Targets............................. 16
-
8/2/2019 eRPMES Monitor's Guide Version 2
7/55
eRPMES Monitors Guide
7
Figure 19.c With-Subcomponent B: Setting Up Financial Targets............................ 17
Figure 20. Saving the Enrolled Project..................................................................... 17
Figure 21. Expanded Agency Project Page............................................................. 18
Figure 22. Project Information................................................................................. 18
Figure 23. Editing Project Information and Targets................................................. 18
Figure 24. Deleting Projects..................................................................................... 19
Figure 25. Agency Action Plan................................................................................ 19
Figure 26. Agency Plan: Generating Spreadsheet File............................................. 19
Figure 27. Downloading Spreadsheet File............................................................... 19
Figure 28. Reporting Quarterly Accomplishments................................................... 20
Figure 29. Reporting Physical, Financial, and Man-days Accomplishments............. 21
Figure 30. Agency Monitoring Plan........................................................................... 21
Figure 31. Physical, Financial, and Man-days Accomplishment Report.................. 22
Figure 32. Inputting Actual Accomplishments........................................................ 22
Figure 33. Saving the Report................................................................................... 23
Figure 34. Prompt for Missing /Invalid Entries.......................................................... 23
Figure 35. Submitting the Report............................................................................. 23
Figure 36. PMC Form O-1: Physical and Financial Status Report............................. 24
Figure 37. Agency Accomplishment: Generating Spreadsheet File......................... 24
Figure 38. Agency Project Page.............................................................................. 26
Figure 39. Viewing the Accomplishment Report (Form O-1)................................... 27
Figure 40. Physical and Financial Status Report (PMC Form O-1)............................ 27Figure 41. Viewing the Agency Overall Performance............................................. 28
Figure 42. Summary of Agency Overall Performance.............................................. 28
Figure 43. Agency Project Page.............................................................................. 29
Figure 44. Viewing the Accomplishment Report by Sector..................................... 29
Figure 45. Agency Project Page.............................................................................. 30
Figure 46. Submission Status for the Project Exception Report................................ 30
Figure 47. The PMC Form I-3A: Project Exception Report.......................................... 31
Figure 48. Filling out the PMC Form I-3A................................................................... 31
Figure 49. Agency Project Page.............................................................................. 32
Figure 50. The PMC Form I-3B: Updated Project Exception Report......................... 32
Figure 51. Filling out the PMC Form I-3B................................................................... 33
Figure 52. Printing Multiple Pages of the Report..................................................... 34
Figure 53. Page Setup Menu............ ............ ........... ............ ............ ........... ............ . 34
Figure 54. Changing Account Information............................................................. 35
Figure 55. Account Information Page...................................................................... 35
Figure 56. Logging out of e-RPMES........................................................................... 36
-
8/2/2019 eRPMES Monitor's Guide Version 2
8/55
eRPMES Monitors Guide
8
Figure 57.a. Summary Report Links ......................................................................... 37
Figure 57.b. Summary Report Links (Agency Project page)..................................................38
Figure 58. Monitoring Plan Summary.............................................................................. 38
Figure 59. Monitoring Plan Drop-Down Menus)............................................................... 39
Figure 60. MDG Sector Drop-Down Menu.......................................................................... 39
Figure 61. PDAF Sector Drop-Down Menu..................................................................... 39
Figure 62. RAACC Sector Drop-Down Menu................................................................ 40
Figure 63. RDA Sector Drop-Down Menu......................................................................... 40
Figure 64. Typhoon Rehab Sector Drop-Down Menu..................................................... 40
Figure 65. Example of a Monitoring Plan Summary Table............................................ 41
Figure 66. Example of Changes in a Monitoring Plan Summary Table.............................. 42
Figure 67. Overall Performance Summary Table......................................................... 42
Figure 68. Example of Overall Performance Summary Table........................................ 43Figure 69. Montoring Report Summary Table...................................................................... 44
Figure 70. Example of Montoring Report Summary Table............................................... 44
Figure 71. Job Generation Summary Table............................................................... 45
Figure 72. Job Generation Summary Table...................................................................... 45
Figure 73. Data Integrity Feature Location......................................................................... 46
Figure 74. Agency Head Approval................................................................................ 47
-
8/2/2019 eRPMES Monitor's Guide Version 2
9/55
eRPMES Monitors Guide
9
Online Regional Project Monitoring and Evaluation System(e-RPMES) Monitors Manual
A. Requirements
The e-RPMES is an internet-based solution Regional Line Agencies, LocalGovernment Units and State Universities and Colleges can use to facilitatethe periodic update of their project accomplishments. It also providesdevelopment stakeholders, i.e., the Regional Development Council, quickand convenient access to the latest information on the status of programs
and projects implemented in Region 1 as well as the performance ofgovernment agencies and institutions enrolled in the Regional ProjectMonitoring and Evaluation System (RPMES).
The following are the basic requirements in accessing the e-RPMES:
1. Internet connection. Make sure that your computer has access to theInternet.
2. Mozilla Firefox Internet browser. The system works best with a Mozilla Firefox
Internet browser. It is highly recommended that you install a Mozilla FirefoxInternet browser on your PC. The software is available for free at: http://www.mozilla.com.
Figure 1. System Diagram
-
8/2/2019 eRPMES Monitor's Guide Version 2
10/55
eRPMES Monitors Guide
10
B. Getting Started
1. To get to the e-RPMES, go to the IRISnet websiteat http://ilocos.net.ph/.
On the IRISnet menu (left column), find and click
the link Project Monitoring. A new tab will openon your browser containing the e- RPMES home
page entitled: ONLINE PROJECT MONITORING.
2. Click Login. Supply the needed information.
The acronym (in small letters)of your agencyserves as its Username. By default, the Password
is the same as the Username.
Example: NEDA will have neda as Username;neda will also be the Password.
Users are advised to change default Username
and Password for security purposes. (Please seeI. Changing your Acccount Info). If you do not
know your username and password, forget your login information, or
if the system does not accept your Username and Password, please
contact the Regional Project Monitoring Committee (RPMC) Secre-
tariat at 072-888-2679 or 888-5501.
1
2
Figure 3. The e-RPMES Login Window
Figure 2. IRISNET Menu
-
8/2/2019 eRPMES Monitor's Guide Version 2
11/55
eRPMES Monitors Guide
11
C. Enrolling Projects to the Monitoring Plan (PMC Form I-1)
1. Once you were able to successfully login, click Agency Project.
2. To add projects individually, click ADD. The Project Enrollmentwindow will appear asking for information you are providing inthe RPMES Form I-1.
1
Figure 4. Online Project Monitoring Home Page
Figure 5. Agency Project Page
2
INITIAL PROJECT REPORT
(PMC Form I-1)
This is used to record the basic information on programs and projects
enrolled by RLA, SUC, or LGU in the RPMES. It contains such information as
name, period, type, sector, fund source, location, indicator, and unit of
measure of the project being enrolled.
It also provides information on the physical and financial target as well as
the employment generated (in man-days) by the project.
-
8/2/2019 eRPMES Monitor's Guide Version 2
12/55
eRPMES Monitors Guide
12
Figure 6. Project Enrollment Window
3. In Period, click -SELECT- and a drop-down menu containing the two classificationscarry over and current year will appear.These two refer to the period ofimplementation of the project.
3
4
Figure 8. Project Type
4. In Project Type, click -SELECT- and a drop-down menu will appear.From this list, click the type of projects you wish to enroll. There are five typesto choose from:
a. (MDG) Millennium Development Goalsb. (PDAF) Priority Development Assistance Fund
c. (RAACC) Regional Action Agenda onClimate Changed. (RDA)Regional Development Agendae. (Typhoon Rehab) Typhoon Damages
Rehabilitation ProgramIn selecting the project type for the project thatyou are enrolling, kindly refer to the list ofprojects provided by the RPMC Secretariat.
5. In Sector, click -SELECT- and a dropdown menu will appear showing the sectors
Carry-Over
A project is classified as carry-over if it was funded during the
previousyear but still being implemented until the current year.
Current Year
A project is considered current year if it has been funded and is
being implementedduring the present year.
of the project type you selected. Click thesector to which the project belongs.
-
8/2/2019 eRPMES Monitor's Guide Version 2
13/55
eRPMES Monitors Guide
13
a. For MDG and PDAF projects, thefollowing are the choices, which
correspond to the eight developmentgoals:
1. Goal 12. Goal 23. Goal 3
4. Goal 45. Goal 56. Goal 67. Goal 78. Goal 8
b. For RAACC projects, the choices are:1. Mitigation2. Adaptation
c. For RDA and Typhoon Rehab projects,these are the choices:
1. Economic Development Sector2. Social Development Sector
3. Infra Development Sector
4. Governance Sector
The list provided by the RPMC Secretariatlikewise classifies the projects by sector and/
or sub-theme. Please follow it accordingly.
6. In Indicator Set, the system asks whetheror not the project has more than oneindicator or has sub-components. Click -
SELECT- and a drop down menu willappear. The following are your choices:
a. single-indicator. The project has asingle indicator.
b. multi-indicator: A. The project hasmultiple Units of Measure with singlefunding support.
5.a
Figure 9.a. MDG and PDAFProject Sector
5.b
5.c
Figure 9.b. RAACC Project Sector
Figure 9.c. RDA and TyphoonRehab Project Sector
-
8/2/2019 eRPMES Monitor's Guide Version 2
14/55
eRPMES Monitors Guide
14
c. multi-indicator: B. The project hasmultiple Units of Measure; each Unit ofMeasure has assigned funding support.
d. with-subcomponent: A. The projecthas subcomponents with single funding
support.e. with-subcomponent: B. The projecthas subcomponents; each
subcomponent has assigned fundingsupport.
7. If the project falls undersingle-indicator,follow the steps mentioned below:
a. In Project, provide the short name or the acronym of the projectyou wish to enrol.b. In Full Name, provide the complete title of the project as found inthe approved program of work, loan and grant agreement.
c. In Fund, click -SELECT-. Choose by clicking whether the project isForeign or Local-funded.
6
Figure 10. Indicator Menu
Figure 10. Indicator Menu
Figure 11. Project Funding Figure 12. Project Location
7
7.c 7.d
-
8/2/2019 eRPMES Monitor's Guide Version 2
15/55
eRPMES Monitors Guide
15
d. In Location, click the specific province and district wherein the
project will be implemented. If the project cannot be disaggregatedby province, click Regionwide.e. In Unit of Measure, provide the unit for measuring the outputs of theproject on the space provided for.
f. To set the employment targets of your project, click the red Man-days button. The employment or jobs generated by the projects willbe measured in terms of man-days.
i. On the Man-days Targets dialog box, set the physical targetsper quarter. For quarters which have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when the project
will start and put 0 on the succeeding quarters.ii. Click Set Targets to save the man-days targets.
Figure 12. Man-days Targets
7.f
g. To set the physical targets of your project, click the red Physicalbutton. A dialog box will appear.
i. On the Physical Targets dialog box, set the physical targets perquarter. For quarters which have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when the projectwill start and put 0 on the succeeding quarters.
ii. Click Set Targets to save your physical targets.
EMPLOYMENTGENERATED
(inman-days)
This refers to the jobs targeted to be created by the project, expressed in
man-days for the quarter.
Formula:
Man-days = no. of persons employed X no. of days worked during the quarter
-
8/2/2019 eRPMES Monitor's Guide Version 2
16/55
eRPMES Monitors Guide
16
7.g
Figure 13. Physical Targets
h. To set the financial targets of your project, click on the red Financialbutton. A dialog box will appear.
i. On the Financial Targets dialog box, set the financial targets perquarter. For quarters which have no target, put 0.ii. Click Set Targets to save your financial targets.
i. Click Enroll Project to save theproject and its correspondingtargets.
7.h
Figure 14. Financial Targets
Figure 15. Enrolling the Project
7.i
-
8/2/2019 eRPMES Monitor's Guide Version 2
17/55
eRPMES Monitors Guide
17
8. If the project falls under multi-indicator: A, follow these steps:a. In Period, click -SELECT- then classify whether the project is carryover or current year project.b. In Project, provide the short name or the acronym of the project.
c. In Full Name, provide the complete title of the project as found in
the approved program of work, loan and grant agreement.d. In Fund, click -SELECT-. Choose by clicking whether the project isForeign or Local-funded.
e. In Location, click the province anddistrict wherein the project will be
implemented. If the project cannot bedisaggregated by province, clickRegionwidef. Click the red financial button. On the
dialogue box, set the financial targets perquarter. For quarters which have notarget, put 0.g. Click Set Targets to save the financialtargets.
Figure 15. Project Enrollment for Multi-indicator:A Projects
8
8.g
8.f
h. To add the units of measure of the project, click the icon. Anotherrow will appear below a yellow bar.
-
8/2/2019 eRPMES Monitor's Guide Version 2
18/55
eRPMES Monitors Guide
18
i. In Unit of Measure, provide the unit of measure of the project onthe space provided for.ii. To set the physical targets of your project, click the red Physicalbutton. A dialog box will appear.
1. On the Physical Targets dialog box, set the physical targets
per quarter. For quarters that have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when theproject will start and put 0 on the succeeding quarters.2. Click Set Targets to save your physical targets.
h. To add another unit of measure, simply click the icon and repeat
steps 9.g.i. through iv.i. To remove a unit of measure, click the icon.j. Click Enroll Project to save the project and its corresponding targets.
9. If the project falls under multi-indicator: B, follow these steps:
8.g.
ii
9
Figure 16.a. Multi-indicator A: Setting up the Physical Targets
Figure 17. Project Enrollment for Multi-indicator: B Projects
-
8/2/2019 eRPMES Monitor's Guide Version 2
19/55
eRPMES Monitors Guide
19
a. In Period, click -SELECT- then classify whether the project is carryover or current year project.b. In Project, provide the short name or the acronym of the project.c. In Full Name, provide the complete title of the project.
d. In Fund, click -SELECT-. Choose by clicking whether the project is
Foreign or Local-funded.e. In Location, provide the site or location of the project.
f. To set the employment targets of your project, click the Man-daysbutton.
i. On the Man-days Targets dialog box, set the physical targets perquarter. For quarters which have no targets, put 0. For retained
targets, indicate the number of units on the quarter when the projectwill start and put 0 on the succeeding quarters.ii. Click Set Targets to save the man-days targets.
g. To add another indicator, click the icon. Another row will appearbelow a yellow bar.
i. In Fund, click -SELECT-. Choose by clicking whether the projectis Foreign or Local-funded.ii. Indicate the project location by choosing the district andprovince from the set of choices.
9.f
9.g
Figure 17.a. Multi-indicator B: Setting up the Man-days Target
Figure 17.b. Multi-indicator B: Adding another Indicator
-
8/2/2019 eRPMES Monitor's Guide Version 2
20/55
eRPMES Monitors Guide
20
iii. In Unit of Measure, provide the unit of measure of the project onthe space provided for.
iv. To set the physical targets of your project, click the red Physicalbutton. A dialog box will appear.
1. Set the physical targets per quarter. For quarters that have notargets, put 0. For retained targets, indicate the number of units
on the quarter when the project will start and put 0 on thesucceeding quarters.2. Click Set Targets to save your physical targets.
v.To set the financial targets of your project, click the red Financialbutton. A dialog box will appear.
1. Set the financial targets per quarter. For quarters that have notarget, put 0 in the space provided for.
ii.Click on Set Targets to save your financial targets.
h. Click Enroll Project to save the project and its corresponding targets.
9.g.
v
9.g.
iv
Figure 17.c. Multi-indicator B: Setting up Physical Targets
Figure 17.d. Multi-indicator B: Setting up Financial Targets
-
8/2/2019 eRPMES Monitor's Guide Version 2
21/55
eRPMES Monitors Guide
21
10. If the project falls under with-subcomponent: A, follow these steps:
a. In Period, click -SELECT- then classify whether the project is carry
over or current year project.b. In Project, provide the short name or the acronym of the project.
c. In Full Name, provide the complete title of the project.d. In Fund, click -SELECT-. Choose whether the project is Foreignor Local-funded.
e. In Location, click the province and district wherein the project willbe implemented. If the project cannot be disaggregated by province,
click Regionwide.
f. Provide the Unit of Measure in the space provided for.
g. To set the employment targets of your project, click the Man-daysbutton.
i. On the Man-days Targets dialog box, set the physical targets perquarter. For quarters which have no targets, put 0. For retainedtargets, indicate the number of units on the quarter when the project
will start and put 0 on the succeeding quarters.ii. Click Set Targets to save the man-days targets.
10
10.g
Figure 18. Project Enrollment for With-Subcomponent A Projects
Figure 18.a. With-Subcomponent A: Setting up Man-days Targets
-
8/2/2019 eRPMES Monitor's Guide Version 2
22/55
eRPMES Monitors Guide
22
h. To set the financial targets of your project, click on the red Financial
button. A dialog box will appear.i. Set the financial targets per quarter. For quarters that have no target,
put 0.ii. Click Set Targets to save your financial targets.
i. To add subcomponents of the project, click the icon. Another rowwill appear below an orange bar.
i. In Component, provide the short name or acronym of theprojects subcomponent.
ii. In Full Name, provide the complete title of the projectssubcomponent.
iii. In Location, click the specific province and the district whereinthe project will be located. If the project cannot be disaggregatedby province, click Regionwide.iv. In Unit of Measure, provide the unit of measure of thesubcomponent on the space provided for.
10.g
Figure 18.c. With-Subcomponent A: Adding another Component
Figure 18.b. With-Subcomponent A: Setting up Financial Targets
10.i
-
8/2/2019 eRPMES Monitor's Guide Version 2
23/55
eRPMES Monitors Guide
23
v. To set the physical targets of the subcomponent, click the redPhysical button. A dialog box will appear.
1. Set the physical targets per quarter. For quarters that have notargets, put 0. For retained targets, indicate the number of units
on the quarter when the project will start and put 0 on the
succeeding quarters.2. Click Set Targets to save your physical targets.
j. To add another subcomponent, simply click the the icon and repeatsteps 10.h.i through v.2.k. To remove a subcomponent, click icon.l. Click Enroll Project to save the project and its corresponding
subcomponents.
11. If the project falls under with-subcomponent: B, follow the steps below:a. In Period, click -SELECT- then classify whether the project is carryover or current year project.
b. In Project, provide the short name or the acronym of the project.
10.h.
v
11
Figure 18.d. With-Subcomponent A: Setting Up Physical Targets
Figure 19. Project Enrollment for With-Subcomponent B Projects
-
8/2/2019 eRPMES Monitor's Guide Version 2
24/55
eRPMES Monitors Guide
24
c. In Full Name, provide the complete title of the project.d. In Fund, click -SELECT-. Choose by clicking whether the project isForeign-funded or Local-funded.
e. In Location, provide the site or location of the project.
f. To add subcomponents of the project, click the icon. Another rowwill appear below an orange bar.
i. In Component, provide the short name or acronym of theprojects subcomponent.
ii. In Full Name, provide the complete title of the projectssubcomponent.iii. In Fund, indicate whether the project is foreign or local-funded.iv. In Location, select the specific location by choosing the province
and district of project sub-component implementation.v. In Unit of Measure, provide the unit of measure of thesubcomponent on the space provided for.v. To set the physical targets of the subcomponent, click the red
Physical button. A dialog box will appear.
11.f
11.f.
v
Figure 19.a. With-Subcomponent B: Adding another Component
Figure 19.b. With-Subcomponent B: Setting up Physical Targets
-
8/2/2019 eRPMES Monitor's Guide Version 2
25/55
eRPMES Monitors Guide
25
1. On the Physical Targets dialog box, set the physical targetsper quarter. For quarters which have no targets, put 0. Forretained targets, indicate the number of units on the quarter whenthe project will start and put 0 on the succeeding quarters.
2. Click Set Targets to save your physical targets.vi. To set the financial targets of your projects subcomponent, clickthe red Financial button. A dialog box will appear.
1. On the Financial Targets dialog box, set the financial targets
per quarter. For quarters which have no target, put 0.2. Click on Set Targets to save your financial targets.
g. To add another subcomponent, simply click the icon and repeatsteps 10.f.i through to vi.2.h. To remove a subcomponent, click the icon.i. Click Enroll Project to save the project and its correspondingsubcomponents.
12. Once you click Enroll Project, the windowwill close and you will be redirected to the
Agency Project page. To view your enrolled
projects, choose the Project Type and clickthe expand icon .
The system will show the information regardingthe projects location, unit of measure, as wellas the targeted physical accomplishment,
financial resources, and man-days.
11. f.
vi
11.i
Figure 19.c. With-Subcomponent B: Setting Up Financial Targets
Figure 20. Saving the EnrolledProject
-
8/2/2019 eRPMES Monitor's Guide Version 2
26/55
eRPMES Monitors Guide
26
a. Other information regarding the project
such as the period of implementation,project type, and fund source can beobtained by simply pointing the cursor overthe project name (in blue).
13. To edit the information and quarterlytargets entered in the project enrollment,
click the icon. A new window will appear.
14. Input the necessarycorrections then click theSave Changes button atthe lower right hand cornerof the window.
15. To remove projects,indicators and sub-
components, simply tick theprojects you wish to removeon the box on the far rightside of the monitoring plan.Click DELETE SELECTED.
12
12.a
13
Figure 21. Expanded Agency Project Page
Figure 22. Project Information
Figure 23. Editing Project Information and Targets
-
8/2/2019 eRPMES Monitor's Guide Version 2
27/55
eRPMES Monitors Guide
27
16. To view the Agency Action Plan (PMC
Form I-1, click the icon underneath
the Action Plan / I-1 column. A newwindow will open to show the AgencyAction Plan.
a. To generate a spreadsheet file of the
Agency Action Plan, click the icon
beside the Project Type drop-down
selection menu. A dialogue box will
appear indicating wherethe download link for thespreadsheet can befound. Click OK.
b. Click the link (here)below the Agency ActionPlan matrix to download
the spreadsheet file.
17. To enroll another project,follow steps C.1 through 11.
15
Figure 24. Deleting Projects
Figure 25. Agency Action Plan
Figure 26. Agency Plan: Generating Spreadsheet File
Figure 27. Downloading Spreadsheet File
16
16.a
16.b
-
8/2/2019 eRPMES Monitor's Guide Version 2
28/55
eRPMES Monitors Guide
28
2. Notice too that under the column, Physical, Financial and Man-daysReport, the status of your submission of quarterly accomplishment reportor PMC Form I-2 is indicated under the sub-column, Submission Status. If
the color of the quarter (Q1, Q2, Q3 and Q4), is red, it means that you
D. Submission of Quarterly Accomplishment Reports (PMC Form I-2)
Figure 28. Reporting Quarterly Accomplishments
1
Physical and Financial AccomplishmentReport
(PMC Form I-2)
This report provides information on the status of implementation of
projects on a quarterly basis. It facilitates the quarterly reporting on the
status of physical and financial accomplishment of the enrolled projects.
The accomplishment on man-days generated as of the reporting period is
also integrated in the form. Information agencies deem necessary in
interpreting or justifying the status of implementation of their respective
projectsmay also be stipulated in the report .
1. On the Agency Project page, choose the project type you wish to reporton by clicking -SELECT- on the Project Type. Notice that a row appearsbetween ADD and DELETE SELECTED buttons.
-
8/2/2019 eRPMES Monitor's Guide Version 2
29/55
eRPMES Monitors Guide
29
Figure 29. Reporting Physical, Financial, and Man-days Accomplishments
2
have not submitted a report for that quarter; green means that you havealready submitted a report for the specific quarter. If the color of the quarter
isbrown, it means that you are not yet required to submit a report for thatquarter.
3. Click on the expand icon . Your agency monitoring plan will appear.
4. On the Physical, Financial, and Man-days Report column and I-2 sub-
column, click on the submit report icon . A new window will open
containing the PMC Form I-2: Physical, Financial, and Man-daysAccomplishment Report on the Agency Action Plan.
5. In Quarter, select by clicking the period you wish to report. Yourmonitoring plan will appear.
Figure 30. Agency Monitoring Plan
4
-
8/2/2019 eRPMES Monitor's Guide Version 2
30/55
eRPMES Monitors Guide
30
Figure 31. Physical, Financial, and Man-days Accomplishment Report
6. In Actual Accomplishment to Date (Column 10), provide theaccomplishment in each of the projects. For quarters which do not have
targets, put 0.
7. In Actual Releases to Date (Column 16), provide the amount of the
funds released for the project. For quarters which do not have financialtargets, put 0.
8. In Actual Expenditure to Date (Column 17), provide the amount of thefunds released which may have been either Disbursed or AccountsPayable.
9. In Remarks (Column 26), provide information that are useful in
interpreting or justifying your report.
Figure 32. Inputting Actual Accomplishments
5
6
-
8/2/2019 eRPMES Monitor's Guide Version 2
31/55
eRPMES Monitors Guide
31
10. You may save yourreport in case you cannotfinish encoding youragency accomplishments
for the quarter. Find and
click Save Report buttonat the bottom-right cornerof the window. A dialoguebox will open to confirm
that the records that wereinputted have beensaved. Click OK.
Figure 33. Saving the Report
10
Take note that by clicking Save Report, the report has not yet been
submitted to the Secretariat; it is merely saved. Computations for the projecttarget accomplishments will only be done once the report has beencompleted and
submitted.
11. Make sure that therequired fields in columns10, 16, 17 and 26 are all
complete before you
submit your report. Findand click Submit Report
button at the bottom-right corner ofthe window to submit the report.
The system will prompt you for fieldswith missing or invalid entries.
12. If your report is complete, aprintable version of your report willopen once you click Submit Report.
Figure 34. Prompt for Missing /Invalid Entries
11
Figure 35. Submitting the Report
-
8/2/2019 eRPMES Monitor's Guide Version 2
32/55
eRPMES Monitors Guide
32
Figure 36. PMC Form O-1: Physical andFinancial Status Report
a. To generate a spreadsheet fileof the Physical and Financial Status
report, click the icon beside the
Quarter drop-down menu. Adialogue box will appear indicatingwhere the download link for thespreadsheet can be found. Click
OK.i. Click the link (here) belowthe Agency Action Plan matrixto download the spreadsheetfile.
12.a
Figure 37. Agency Accomplishment:
Generating Spreadsheet File
12
-
8/2/2019 eRPMES Monitor's Guide Version 2
33/55
eRPMES Monitors Guide
33
6
The e-RPMES automatically computes for the physical accomplishment, ex-
penditure rate and overall performance. The online system also generatescorresponding interpretation for the level of overall performance of theagency.
Physical Accomplishment
This refers to the ratio of the actual accomplishment to the physical targets
during the quarter, multiplied by 100.
Formula:Standard of Physical Actual Accomplishment
Accomplishment Target Accomplishment 100
FundsUtilization
This refers to the ratio of the total expenditure to the total releases during
the quarter, multiplied by 100.
Formula:
Standard of Funds Total Expenditures
Utilization Total Releases 100
Overall Performance
Otherwise referred to as financially-correlated performance, this is the ratio
of the agencys physical accomplishment to its funds utilization during the
quarter, multipliedby 100.
Formula: Standard of Physical
Standard of Overall Accomplishment
Performance Standard of Funds
Utilization
100
E. Computing for the Agency Overall Performance
(Financially- Correlated Performance)
-
8/2/2019 eRPMES Monitor's Guide Version 2
34/55
eRPMES Monitors Guide
34
The following table shows the overall performance rating as well as theinterpretation of the agencys performance.
Table 1. Overall Performance Rating
F. Viewing the Project Monitoring Reports
1. Agency Accomplishment Report (PMC Form I-2)
Figure 38. Agency Project Page
1.a
Deviation from
Target
Recommended
Interpretation Qualitative Rating
105.1 - above Less Accurate Planning Fair
100.0-105.0 Very Efficient and Effective Outstanding
Program Management
95.0-99.9 Efficient and Effective Excellent
Program Management
85.0-94.5 Very Efficient and Effective Very Satisfactory
Program Implementation
75.0-84.9 Efficient and Effective Satisfactory
Program Implementation
50.0-74.9 Less Efficicent Program Fair
Implementation
0.0-49.9 Inefficicent Program Unsatisfactory
Implementation/
Defective Planning
-
8/2/2019 eRPMES Monitor's Guide Version 2
35/55
eRPMES Monitors Guide
35
a. To view the agency accomplishment report, proceed to the AgencyProject Page first.
b. Find the O-1
subcolumn underPhysical, Financialand Man-daysReport and click the
icon. A new
window containing
the PMC Form O-1 willappear.
Figure 40. Physical and Financial Status Report (PMC Form O-1)
Figure 39. Viewing the Accomplishment Report (Form O-1)
1.b
-
8/2/2019 eRPMES Monitor's Guide Version 2
36/55
eRPMES Monitors Guide
36
2. Agency Overall Performance
a. In the agency project page, click the icon underneath the column
of Project Exception Report to view the overall performance ofagencies participating in the e-RPMES.
b. A new window will appear containing the Summary of Agency OverallPerformance.
Figure 41. Viewing the Agency Overall Performance
Figure 42. Summary of Agency Overall Performance
2.a
2.b
-
8/2/2019 eRPMES Monitor's Guide Version 2
37/55
eRPMES Monitors Guide
37
3. Accomplishment Report by Sector
a. In the agency project page, select the type of project from the drop-
down Project Type menu, then click the icon underneath the
column of Updated Project Exception Report to view theaccomplishment report on projects enrolled in the different sectors.
b. In the new window, select the particular Quarter and Sector youwish to view. The system will automatically load the the Summary ofAgency Overall Performance by Sector.
Figure 42. Viewing the Agency Accomplishment Report by Sector
Figure 43. Agency Project Page
Figure 44. Viewing the Accomplishment Report by Sector
3.a
3.b
-
8/2/2019 eRPMES Monitor's Guide Version 2
38/55
eRPMES Monitors Guide
38
G. Submission of Project Exception Report (PMC Form I-3A)
1. In filling out the Project Exception Report, go to the Agency Projectpage, choose the project type by clicking -SELECT- on the Project Type.
2. On the Project Exception Report column, under the Submission Statussub-column, see if the period (Q1, Q2, Q3 or Q4) you have reported ishighlighted in red. This means that some of your projects are behind scheduleand have registered negative slippages of 15% or higher. You are required
to accomplish the Project Exception Report or PMC Form I-3A. If the periods(Q1, Q2, Q3 and Q4) remain colored brown, your projects do not require
submission of the Project Exception Report.
Figure 45. Agency Project Page
Figure 46. Submission Status for the Project Exception Report
PROJECT EXCEPTION REPORT
(PMC Form I-3A)
This is used to record critical problems resulting in the delay of project
implementation that need immediate action by the RPMC or the RDC. It is
also used to document the reasons or factors that have contributed to theoutstanding performance in the implementation of a specific project.
1
-
8/2/2019 eRPMES Monitor's Guide Version 2
39/55
eRPMES Monitors Guide
39
The system will prompt the implementing agencies regarding the due datefor submission of the PER as scheduled by the RPMC Secretariat.
3. On the same column, find and click on the submit report icon. A newwindow will open containing the PMC Form I-3A: Project Exception Report.
4. In Quarter, select which period you want to report. Projects in differentsectors, which are behind schedule, are listed on the first column of the
Name of Project/location column.The slippages of the projects are indicated under the Findings column.
5. On the Possible Reasons/Causes column, indicate the reasons for thedelay in the project implementation.
6. On the Recommendations column, indicate suggestions to improvethe work progress or remedial measures to address the problemsencountered.
Figure 47. The PMC Form I-3A: Project Exception Report
Figure 48. Filling out the PMC Form I-3A
3
4
-
8/2/2019 eRPMES Monitor's Guide Version 2
40/55
eRPMES Monitors Guide
40
7. Make sure that all required fields are filled-out. Click Save Report tosave and submit your report.
H. Submission of Updated Project Exception Report (PMC Form I-3B)
1. Submission of the Updated Project Exception Report or PMC Form I-3B is
required only for projects that have negative 15% slippage seven days priorto a scheduled meeting of the RPMC. The RPMC Secretariat will notifyconcerned agencies to accomplish the Updated Project Exception Reportprior to the meeting.
2. After receiving notification from the RPMC Secretariat, go to the Agency
Project page. Choose the project type by clicking -SELECT- on theProject Type box.
3. On the Updated Project Exception Report column, click the submit report
icon . A new window will open containing the PMC Form I-3B:
Figure 49. Agency Project Page
Figure 50. The PMC Form I-3B: Updated Project Exception Report
3
2
-
8/2/2019 eRPMES Monitor's Guide Version 2
41/55
eRPMES Monitors Guide
41
Updated Project Exception Report. Note that the entries made in the ProjectException Report of PMC Form I-3A were automatically replicated in this
form.
4.On the Actions Taken column, indicate the steps undertaken to addressthe problems encountered or measures that have improved the workprogress.
5. On the Updates column, provide the latest status of the project.
6. Make sure that all required fields are filled-out. Click Save Report tosave and submit your report.
Figure 51. Filling out the PMC Form I-3B
4
I.Printing the Reports
1. To print the Physical and Financial Status Report, you must view the report
first. Kindly refer to F. Viewing the Project Monitoring Reports for theprocedures.
a. In printing multiple pages of the report, click the appropriate icon
at the left side of the status report matrix to create separate tables foreach project indicator or sub-component.
b. Click the icons to create and adjust page breaks for printing
the status report.
-
8/2/2019 eRPMES Monitor's Guide Version 2
42/55
eRPMES Monitors Guide
42
Figure 52. Printing Multiple Pages of the Report
Figure 53. Page Setup Menu
c. In the window containing the report you wish to print, click File on theMenu Bar then click Page Setup to customize the documentaccording to your printing preferences before hitting the Print menu
and creating a hardcopy of the report.
1.c
1.a
It is also advised to preview the document first before printing to makesure that the desired setups have been followed.
d. In printing summary reports of agency performance, proceedimmediately to step I.1.c.
-
8/2/2019 eRPMES Monitor's Guide Version 2
43/55
eRPMES Monitors Guide
43
Figure 47. Logging out of thee-RPMES
J. Changing Account Information
For the purpose of securing the
integrity of the information beinginputted into the online RPMES,
among others, it is highly advisedthat agencies change their e-RPMES account information. Please
consider the following steps:
Figure 54. Changing Account Information
1
2
1. Once you login, click MyAccount.
Figure 55. Account Information Page
2
2. In Old Username, provide your present username.
3. In New Username, provide the new username you wish to use.4. In Old Password, type your present password.
5. In New Password, type your desired password.
6. In Re-Type Password, simply re-type your desired password.
7. Click Save and Exit. Your new username and password is saved. Pleaseremember your username and password.
-
8/2/2019 eRPMES Monitor's Guide Version 2
44/55
eRPMES Monitors Guide
44
1
K. Log-Out Menu
1. Click Log-out menu to exit from
the Online Project Monitoring.
Figure 56. Logging out of e-RPMES
-
8/2/2019 eRPMES Monitor's Guide Version 2
45/55
eRPMES Monitors Guide
45
Addendum to the ERPMES Monitors Guide
(October 2011)
In the 2nd Quarter of 2011, the following additional features were included
in the eRPMES.
A. Quick Access to Summary Reports
In the home page of the eRPMES, summary tables for Monitoring Plan,
Overall Performance, Accomplishment Report and Job Generation Reportcan be readily accessed not only by the project monitors and RPMC
Secretariat, but also by the general public.
1. To access the summary reports of each project type, click the drop-
down buttons to indicate the Year and the Project type you wish toview. These are found at the lower left side of the window just below theeRPMES logo and description.
For agency users, these links are also located below the list of agencies
in the Agency Project page of the eRPMES.
Figure 57.a. Summary Report Links
-
8/2/2019 eRPMES Monitor's Guide Version 2
46/55
eRPMES Monitors Guide
46
Figure 57.b. Summary Report Links (Agency Project page)
1.a. To view the Monitoring Plan summary table, click the link for
Monitoring Plan (in violet colored text). A new window showingthe title PMC Form I-1 Agency Action Plan will appear. This table
lists down the enrolled projects of the different implementing
agencies as well as the quarterly physical, financial, and man-
days targets of the project. The location and unit for measuring
the project deliverables can be seen in the summary.
Figure 58. Monitoring Plan Summary
1.a.i. Use the drop-down buttons to indicate the specific Quarter to
be viewed. The default setting for viewing the summary tables is the
overall report. Users can delimit the information they want to view
based on the Sector, Location, Implementation Period, and Fund
Source of the Projects. The drop-down button for each of these fields
-
8/2/2019 eRPMES Monitor's Guide Version 2
47/55
eRPMES Monitors Guide
47
can help the users delimit or extend the project information
according to their desired specifications.
1.a.ii. The Sector options in the drop-down menu vary depending on
the Project Type. The following figures show the aforementioned
variations:
Figure 59. Monitoring Plan Drop-Down Menus
Figure 60. MDG Sector Drop-Down Menu
Figure 61. PDAF Sector Drop-Down Menu
-
8/2/2019 eRPMES Monitor's Guide Version 2
48/55
eRPMES Monitors Guide
48
Figure 62. RAACC Sector Drop-Down Menu
Figure 63. RDA Sector Drop-Down Menu
Figure 64. Typhoon Rehab Sector Drop-Down Menu
1.a.iii. The following shows an example of the Monitoring Plan
Summary Table. The specified fields in this example are:
Project Type: RDA Quarter: SecondSector: Agribusiness Sector Location: Select All
Implementation Period: Select All Fund Source: Select All
-
8/2/2019 eRPMES Monitor's Guide Version 2
49/55
eRPMES Monitors Guide
49
Figure 65. Example of a Monitoring Plan Summary Table
The specific projects or implementing agencies are listed on the first
column. The specific implementation period, sector, and fund source
are also properly indicated on the same column prior to the agencys
list of projects.
1. a.iv. The table automatically adjusts as the fields are changed to
indicate the specific viewing options of the user. For example,
delimiting the field for Location of project, which classifies the projects
according to the scope of implementation (Region-wide, Province-
wide, and Congressional District and City-wide) will result to the
changes in the Summary Table. In the following example, the
Location field has been specified to Ilocos Norte. The rows
containing information on projects that are implemented by
agencies in Ilocos Norte are highlighted (in yellow).
-
8/2/2019 eRPMES Monitor's Guide Version 2
50/55
eRPMES Monitors Guide
50
Figure 66. Example of Changes in a Monitoring Plan Summary Table
1.b. To view the Overall Performance of agencies, click the link for
Overall Performance (in violet colored text) found in the eRPMEShome page. Prior to this, the Year and Project Type should already
be indicated. A new window will open, showing the summary table
for over all performance.
Figure 67. Overall Performance Summary Table
-
8/2/2019 eRPMES Monitor's Guide Version 2
51/55
eRPMES Monitors Guide
51
1.b.1. Notice that the column on Project Caterogy also includes
the information on the implementation period of projects, particularly
carry overand current yearprojects. Fund source, which is either
foreign or local, is also indicated. Notice too that there are still no
pertinent values indicated in the specific columns for Physical Status,
Financial Status, Overall Performance, Interpretation and Man-days
Status.
Use the drop-down button to choose the Quarter to be viewed.
Upon choosing the quarter, information on the performance of
agency implementers will immediately be populated.
The following example shows the 2nd quarter 2011 overall
accomplishment of agencies under the theme MillenniumDevelopment Goals.
Figure 68. Example of Overall Performance Summary Table
1.c. To view the Accomplishment Report of agencies, click the link
for Accomplishment Report (in violet colored text) found in the
eRPMES home page. Select the year and project type you wish to
-
8/2/2019 eRPMES Monitor's Guide Version 2
52/55
eRPMES Monitors Guide
52
view. Another window will immediately open to show the
Accomplishment Report on the Agency Action Plan.
Figure 69. Montoring Report Summary Table
1. c.i. Use the drop-down buttons to indicate the specific Quarter to
be viewed. The default setting for viewing the summary tables is the
overall report. Users can delimit the information they want to view
based on the Sector, Location, Implementation Period, and FundSource of the Projects. The drop-down button for each of these fields
can help the users delimit or extend the project information
according to their desired specifications.
The following example shows the RDA accomplishment report of
agencies in the second quarter 2011.
Figure 70. Example of Montoring Report Summary Table
-
8/2/2019 eRPMES Monitor's Guide Version 2
53/55
eRPMES Monitors Guide
53
1.d. To view the Job Generation Report of agencies, click the link for
Job Generation Report (in violet colored text) found in the eRPMES
home page. The year and project type you wish to view should
already be indicated. Another window will direct you immediately
to the Job Generation Report summary table.
Figure 71. Job Generation Summary Table
1.d.i. Use the drop-down buttons to indicate the specific Quarter to
be viewed. The default setting for viewing the summary tables is the
overall report. Users can delimit the information they want to view
based on the Sector, Location, Implementation Period, and Fund
Source of the Projects. The drop-down button for each of these fields
can help the users delimit or extend the project information
according to their desired specifications.
Figure 72. Job Generation Summary Table
-
8/2/2019 eRPMES Monitor's Guide Version 2
54/55
eRPMES Monitors Guide
54
The preceding example shows the RAACC Man-days
Accomplishment agencies in the second quarter 2011. The quarterly
targets of the project as well as the actual accomplishment and
Job Generation Performance can be seen in the report.
B. Data Integrity
Another feature was included to ensure that the data submitted through
the eRPMES are reliable. This involves indicating that the data was duly
approved by the agency head prior to encoding and submission to the
RPMC Secretariat.
1. Provisions for this can be found at the lowest portion of the PMC FormI-2: Physical, Financial and Man-Days Accomplishment Report on the
Agency Action Plan before the Save Report and Submit Report
buttons.
Figure 73. Data Integrity Feature Location
-
8/2/2019 eRPMES Monitor's Guide Version 2
55/55
eRPMES Monitors Guide
b.1. To signify that the encoded data has been durly approved by
the Head of the Agency, click on the box beside Agency Head
Approval (in red color).
b.2. Supply your name and designation on the space provided for
before clicking the Submit Report Button.
Figure 74. Agency Head Approval