ERCOT Planning Go-Live Introduction and Background
description
Transcript of ERCOT Planning Go-Live Introduction and Background
December 15 2010
Nodal Planning Go-Live Workshop
ERCOT Planning Go-Live Introduction and Background
Jay TeixeiraManager, Model Administration
2 Nodal Planning Go-Live Workshop
December 15 2010
ERCOT Concerns regarding Planning Go-Live
• Topology Processor is in production for CRR– Data, such as connectivity node groups (CNG) must be
maintained by ERCOT and TSPs– Equipment IDs and Circuit IDs for all equipment must be
populated and unique and are dependent on correct CNG definition
• Easier to maintain one model than two
3 Nodal Planning Go-Live Workshop
December 15 2010
Reasons to Go Live in April 2010
• Date to start building Data Set A cases which are heavily used by ERCOT– Near Term congestion analysis and studies to support ERCOT
Operations (SPS, RMR, etc)– Studies simulate planned outages, manual process to map to
SSWG cases• Protocols require consistency in all operational models• Value to both ERCOT and Market Participants in moving to a
process that satisfies the consistency requirements
4 Nodal Planning Go-Live Workshop
December 15 2010
Data Set A Uses from June PLWG meeting
ERCOT Use DS A Case Used
Determining Flat load for Near Term congestion and 5 year plan cases
Uses all 8 cases for range of load level.
SPS Reviews Can use any of all 8 cases depending on SPS under study and time frame
RMR Analysis Can use any of all 8 cases depending on RMR unit under study and time frame
Transmission Loss Factor Calculations Uses generation, load, losses from all 8 cases
Near term congestion analysis Uses summer peak topology
ERCOT Operations requested studies Can use any of all 8 cases
Dynamic Data Set (wind and no wind) Currently use summer peak, DWG proposal to use peak and off-peak case
Stability Screening Studies (Dynamic and Voltage)
PV and TS for summer, PV for winter peak and TS for winter off-peak
NERC Compliance Studies Summer peak and one off-peak
Voltage Profile Studies Peak(Sum, Win) and Off peak (Spg, Fal) cases
5
Current Process – Separate System for Planning
Nodal Planning Go-Live Workshop
December 15 2010
ERCOTManual Process
TSP Review
Case complete
?
Case Posted
Yes
NoTSPs submitChanges via IDEV, other
NMMS db
ERCOT Topology
Processor for ODMS
ERCOT/TSP Network Model
update via NOMCR
CRR Top Output
Planning Case
Creation
ERCOT Dispatch
TSPs submit RAWD files for their area
containingTopology,
Load, Voltage Control
6
Topology Processor/Model on Demand Integrated System
Nodal Planning Go-Live Workshop
December 15 2010
TSPProfiles
Planning Topology
Output
TSP Review
Case complete
?
Case Posted
Yes
NoTSPs submitChange via MOD
NMMS db
ERCOT Topology
Processor for ODMS
ERCOT/TSP Network Model
update via NOMCR
CRR Topology Output
Planning Case Output
ERCOTModel on Demand
TSP Standard PMCR
TSP Future PMCR
ERCOT DispatchProfile
7 Nodal Planning Go-Live Workshop
December 15 2010
Bus Branch Load GenSwiched Shunt XF FACT
Mult-Section Lines Area Owner Totals
Total of DSB Submission
%Size of DSB submission
AEN Add 1 14 1 7 1 24add 1Delete 2 23 3 1 1 30Modify 2 14 16
3 37 6 1 0 22 2 0 0 0 70 263 26.62%AEP Add 8 1 133 8 1 9 1 3 164
Delete 3 5 7 1 1 17Modify 7 2 5 2 16
18 6 133 17 2 10 0 0 6 5 197 2638 7.47%CNP Add 38 165 97 9 26 7 151 493
Delete 93 251 125 9 21 5 504Modify 10 7 6 86 109
141 423 228 18 47 98 0 151 0 0 1106 1833 60.34%CPS Add 13 13
Delete 13 6 19Modify 22 22
0 26 6 0 22 0 0 0 0 0 54 349 15.47%GPL Add 6
Delete 6Modify 2 1 3
0 2 0 13 0 0 0 0 0 0 3 273 1.10%LCRA Add 383 383
Delete 324 324Modify 1 1
0 0 708 0 0 0 0 0 0 0 708 1043 67.88%Oncor Add 253 253
Delete 2 2Modify 0
0 0 0 0 255 0 0 0 0 0 255 5087 5.01%STEC Add 6 3 3 12
Delete 6 16 3 25Modify 4 4
0 12 23 0 0 6 0 0 0 0 41 540 7.59%2434
Topology Processor Results from the 2010 Test case as of 11-23-2010This includes all the PMCRs from pass1, pass2 and pass3.
8
Notes for Previous Slide
• AEP 133 added load records appears to separate load into Residential, Wholesale, etc to match SSWG case. Do not get removed by SCR.
• LCRA 383 load adds and 324 load deletes appears to be to realign Load ID field to new modeling philosophy. Will be changed in IMM and not necessary to submit as future PMCR
• ERCOT is reviewing all “Standard PMCR’s” – Some may be reduced by making changes in IMM
• Up to 230 have been found
– Some may be just for comparison purposes• May be why changes to IMM were not made
December 15 2010 Nodal Planning Go-Live Workshop
9 Nodal Planning Go-Live Workshop
December 15 2010
• PMCR’s are not the same as NOMCR’s• NOMCR’s are very detailed xml files• PMCR’s vary from 1 line of data to up to 4 lines of
data
What are PMCR’s?
10
Example of PMCR File
• <PROJECT>, 30• AEN_TEST_CASE_10SUM_PMCR_FILE,Standard_PMCR,Active,Make sure Autos are 3-winding• <PHASE>,TEST_PMCR,10/8/2010,10/8/2010,• BUS, DELETE,9281,'TRADPOST1',138,1,0,0,9,709,1,0,190• BUS, ADD,9025,'HP_STATC',32,1,0,0,9,709,0.9986,-3.2377,100• LOAD, DELETE,9187,'1',1,9,709,2,0,0,0,0,0,190• LOAD, ADD,9184,'DG',1,9,709,-2.12,0.597,0,0,0,0,400• LOAD, MODIFY,9282,'1',1,9,709,20.324,14.287,0,0,0,0,190• GENERATOR, DELETE,9118,'VC',0,0,110,-80,1.018,0,110,0,9999,0,0,0,1,100,0,0,1,1• BRANCH, DELETE,7288,-9288,'BC',0,0.0001,0,9999,9999,9999,0,0,0,0,1,0,1,1• FACTS, ADD,1,9025,0,1,0,0,0.9986,100,9999,0.9,1.1,1.2,100,0.05,100,100,0,0,0• TRANSFORMER, ADD,9025,9118,0,'1',1,1,1,0,0,1,'STATC1',1,190,1,,,,,,• 0.0025,0.08,100,,,,,,,,• 1,0,-30,120,120,120,0,0,1.5,0.51,1.5,0.51,33,0,0,0• 1,0,,,,,,,,,,,,,,• TRANSFORMER, MODIFY,9002,9188,0,'1',1,1,1,0,0,2,,1,189,1,,,,,,• 0.00521,0.18106,100,,,,,,,,• 1,13.8,0,139,139,139,0,0,1,1,1.1,0.9,33,0,0,0• 1,0,,,,,,,,,,,,,,• Q
This file contains 10 PMCRS
December 15 2010 Nodal Planning Go-Live Workshop
11
The effect of SCRs on the number of PMCR’s submitted
SCR # SCR Description
PMCR Reduction Achieved by
SCR1 Comment
Possible PMCR Reduction
by SCR2
Additional PMCR's considered as reduced by SCR
1 UpgradeTP to PSS/E version32 - Unable to Determine -
2 Distribution Capacitor Banks 231Unable to Determine all 557
PMCR's CNP add Caps + AEP estimate (200)+Add'l Oncor estimate (100)
3 Zero Impedance Line Ratings 118 118
4Associate Loads and Capacitor banks with the correct CNG 17
Unable to Determine all 114 PMCR's CNP add Loads
5 Additional Transformer Data for Planning - Unable to Determine 86 PMCR's CNP Modify XF6 FACTS Devices 7 21 Only 21 in case
7Assign valid PSSE IDs to Breakers/Switches/Series Devices 245 245
8 Phase Shift of Autos For Short Circuit Studies 46 46
SCR 760 Total Number and as percent of 2434 664 27.3% 1187 43.4%
SCR759 - Increase ACLineSegment Length 151 6.2%
Should Not Be Modeled as a Standard PMCR3 44
3PMCR's that were submitted that either should have included in profile or reflect change that needs to also be made in IMM
1Using values that ERCOT was able to determine from submitted PMCR's2Using values as in footnote 1 but including additional PMCR's and estimated non-submitted PMCR's that might be reduced by SCR
December 15 2010 Nodal Planning Go-Live Workshop
12 Nodal Planning Go-Live Workshop
December 15 2010
TAC Approved Principles of Consistency
• Consensus version developed by Joint ROS/TPTF on August 4, 2006
• Approved by TPTF on August 7, 2006• Approved by ROS on August 11, 2006
• Entitled “Principles of Consistency” applies to:• Annual Planning Models• CRR Network Models• Network Operations Models
13 Nodal Planning Go-Live Workshop
December 15 2010
TAC Approved Principles of Consistency
• Purpose to provide principles to define the term “consistent” as used in sections 3.10 and 3.11 of ERCOT Protocols to describe relationships between the models to which it applies• “The name of existing Transmission Elements
including Electrical Buses, lines, transformers, generators, loads, breakers, switches, capacitors, reactors, phase shifters, or other similar devices, if modeled as part of the ERCOT Transmission Grid, must be identical (Protocols Section 3.10 Network Operations Modeling and Telemetry)”
14
CRR Names use Topology Process Bus Numbers and Names
Nodal Planning Go-Live Workshop
December 15 2010
Name Limit DeviceName DeviceType FlowDirectionW_TO_N 6444 SARC7A 1440 COMCHESS1_5 1 LINE From-To
Non-Thermal Constraints
Contingency DeviceName DeviceType ActionSRSFB9 44290 FTBEND_ 69 700151 700151_ 1 A1 XFMR OUT
Contingencies
DeviceName DeviceType BaseCaseRating EmergencyRating1 ROANSPRARE 4 IOLA 1 LINE 269 269
Monitored Lines and Transformers
15 Nodal Planning Go-Live Workshop
December 15 2010
TAC Approved Principles of Consistency
• “All existing transmission line’s and transformer’s impedances (or equivalent branch circuit impedance) and ratings (Normal, Emergency and 15-Minute, if modeled) shall be identical for equipment without Dynamic Ratings and for equipment with Dynamic Ratings having the same assumed ambient weather conditions, and shall use Dynamic Ratings where implemented according to the nodal protocols ("Identical" as used herein permits only those differences due to the use of different numerical precision)”
16 Nodal Planning Go-Live Workshop
December 15 2010
TAC Approved Principles of Consistency
• “If all normally closed breakers and switches are closed and normally open breakers and switches are open in the CRR Network and Network Operations Model, the calculated line flows between substations in the Annual Planning Model shall be consistent (very close), when all models use the same load magnitude and distribution, generation commitment and dispatch, and voltage profile”
17
SCR760 Preliminary Impact Analysis
SCR TSP Requirement Cost Delivery
760-1
Keep TP current for all new PSS/E releases
$610K - $760K Dec 2012
760-2 Represent Distribution Capacitor Banks on the proper bus in Topology Processor PSS/E case $210K - $260K May 2012
760-3Represent the proper ratings on zero impedance lines in Topology Processor cases $560K – 720K Mar 2013
760-4Planning should be able to model loads and capacitor banks on the correct PSS/E busses $165K – 205K
May 2012
760-5Represent the actual transformer models in the PSS/E cases
$145K - $185KMay 2012
760-6 Update IMM and TP to incorporate FACTS devices $230K - $295K Dec 2012
760-7Modify TP to assign valid PSS/E IDs to Breakers/Switches/Series Devices
$105K-$140K Sep 2011
760-8Allow representation of a phase shift for an autotransformer winding in the Topology Processor PSS/E cases $95K - $130K Sep 2011
TOTAL $2.1M - $2.7M
Annual Recurring Cost$535K – $715K
December 15 2010 Nodal Planning Go-Live Workshop
18
Delivery Plan
December 15 2010 Nodal Planning Go-Live Workshop
Questions?
December 15 2010 Nodal Planning Go-Live Workshop