ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC...

42
ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009

Transcript of ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC...

Page 1: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

ERCOTEmergency Interruptible Load Service

EILS Technical Workshop

Commissioners Hearing Room, PUC

July 17, 2009

Page 2: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

2EILS Technical WorkshopJuly 17, 2009 2

Antitrust Admonition

Page 3: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

3EILS Technical WorkshopJuly 17, 2009 3

Today’s Agenda (times are approximate)

9:00 AM Antitrust Admonition

9:05 AM EILS General Overview

9:30 AM Baseline discussion

10:30 AM Break

10:40 AMUpdates to procurement process & EILS Resource

Submission form

Noon Lunch

1:00 PMUpdates to procurement process & EILS Resource

Submission form

2:00 PM Scheduled Unavailability discussion

2:45 PM Non-TDSP meter data submission

3:15 PMReview procurement schedule for Oct. 2009- Jan. 2010

Contract Period

3:30 PM Adjourn

Page 4: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

4EILS Technical WorkshopJuly 17, 2009 4

Emergency Interruptible Load Service

What EILS is:• Service provided by loads (customers) willing to interrupt during

an electric grid emergency in exchange for a payment– “Controlled interruption of prepared customers vs.

uncontrolled interruption of unprepared customers”

• An additional tool for ERCOT Operations, deployed only in the late stages of a grid emergency– Last resort prior to firm load shedding (rotating outages)

‘Another tool for the operator toolbox’

Page 5: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

5EILS Technical WorkshopJuly 17, 2009 5

When EILS may be needed

• When emergencies can occur:– Cold weather months (due to natural gas curtailment & higher

forced outages)– Shoulder months (due to unforeseen weather events & large

amounts of scheduled maintenance)– Traditional summer peaks – Anytime, as may be caused by:

• generation outages (scheduled, forced or both)

• transmission outages beyond likely contingencies

• extreme weather events

• multiple simultaneous contingencies

• EILS may be more likely to be needed in off-peak hours or shoulder months than during traditional summer peaks

Page 6: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

6EILS Technical WorkshopJuly 17, 2009 6

Emergency Operations

Event/Action Trigger

ADVISORY: Notice to Market Participants Physical responsive below 3000 MW

WATCH: Start Reliability Must Run units, suspend unit testing, deploy Replacement & Non-spin Reserves

Physical responsive below 2500 MW

Energy Emergency Alert

Level 1: Dispatch all generation, issue public media appeal, acquire maximum power thru DC Ties

Physical responsive below 2300 MW

Level 2A: Deploy LaaRs Physical responsive below 1750 MW

Level 2B: Deploy EILS Resources Maintain frequency at 60 Hz

Level 3: Instruct transmission owners to shed firm load

Frequency below 59.8 hz

QSEs should have ample warning of tight conditions before EILS deployments.ERCOT Operators have flexibility to skip Level 2B if frequency is decaying rapidly. In these cases EILS

would be deployed immediately after Level 3 to enable faster recovery.

Page 7: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

7EILS Technical WorkshopJuly 17, 2009 7

Dispatch

• ERCOT Operations orders an EILS deployment via a phone call to the all-QSE hotline

• 10-minute deployment period begins when QSEs have received the instruction– QSEs’ responsibility to ensure their EILS Resources get the

message• EILS Resources must deploy within 10 minutes and must keep

their committed load off until released• ERCOT Operations will release EILS Resources after

Responsive Reserves have been restored• EILS Resources have 10 hours to return to service after release

Page 8: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

8EILS Technical WorkshopJuly 17, 2009 8

Eligibility: Who can participate?

• EILS Resources may be individual Loads or aggregations

• Must have:– 15-minute interval metering or statistically valid sample approved

by ERCOT– Capability of interrupting at least 1 MW of load on 10 minutes

notice at any time during the committed hours– Representation by a Qualified Scheduling Entity (QSE) with a

wide-area network agreement with ERCOT• Must have 24/7 operations that can receive the verbal dispatch

instruction

• QSE (not ERCOT) is responsible for notifying the customer

Page 9: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

9EILS Technical WorkshopJuly 17, 2009 9

How EILS Works

• QSEs representing selected EILS Resources are paid a capacity payment to be available for interruption

• EILS payments are made regardless of whether there is a deployment– If deployed, participants do not receive any additional payment

from ERCOT • ERCOT’s only financial relationship is with the QSE

– QSE submits bid– If bid is accepted, QSE is paid by ERCOT

• Payment to the EILS Resource (customer) is a private contractual issue between the customer and the QSE

Page 10: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

10EILS Technical WorkshopJuly 17, 2009 10

Contract Periods & Time Periods

• EILS is procured for 4-month Contract Periods– February thru May– June thru September– October thru January

• Participants may bid to provide the service for one or more Time Periods:

1. Business Hours 1: 8AM to 1PM Monday-Friday*

2. Business Hours 2: 1PM to 4PM Monday-Friday*

3. Business Hours 3: 4PM to 8PM Monday-Friday* * Except ERCOT Holidays

4. Non-Business Hours: All other hours• Time Periods are designed to allow flexibility in for customers

during traditional business hours

Page 11: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

11EILS Technical WorkshopJuly 17, 2009 11

Procurement

Step 1: Resource Identification Submission• QSEs identify and submit potential EILS Resources to ERCOT• ERCOT staff reviews the prospective EILS Resource’s

historical load data (ideally 12 months or more)• ERCOT returns the results of its data evaluation back to the

QSE as a service to help avoid over- or under-bidding of capacity

• ERCOT makes baseline assignmentsStep 2: Bid Submission• QSEs submit Bids on behalf of EILS Resources

– $ per MW per Hour– Fractional bids above the 1 MW minimum are accepted to

tenths of a MW• Bidders also must declare Minimum Base Load

– Minimum Base Load is the “drop-to” target for EILS Resources on the Alternate Baseline

Page 12: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

12EILS Technical WorkshopJuly 17, 2009 12

Procurement & payment

• ERCOT management selects EILS providers based on submitted QSE bids

• ‘Reasonableness’ criteria and limits may be applied to stay under the PUC’s cost cap of $50 million per year– See document posted at the EILS web page

• Participants are paid as bid if ERCOT accepts their offer– No clearing price mechanism

• Payments are made to QSEs ≤70 days after the end of the Contract Period

• Payments will be adjusted if the EILS Resource fails to perform in either of two ways:1. Availability: Load must be online and available for interruption

during the contracted hours2. Performance: Load must meet its curtailment obligations if

ERCOT dispatches EILS in an emergency

Page 13: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

Baselines

Page 14: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

14EILS Technical WorkshopJuly 17, 2009 14

Baselines

• EILS Baselines are assigned by ERCOT based on interval meter data evaluation

• Default Baseline:– ‘Drop-by’ requirement– Three default baseline types:

• Statistical Regression Model

• Middle-8-of-10 Preceding Like Days

• Matching Day Pair

• Alternate Baseline– ‘Drop-to’ requirement (not really a baseline per se)– Designed for highly variable loads; allows participation by loads

that cannot be modeled accurately– Open to all participants if they so choose

Page 15: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

15EILS Technical WorkshopJuly 17, 2009 15

Default Baselines

• Default baseline is a statistical estimation of what a load would have done in the absence of a deployment

• For each ESI ID (individual load or part of an aggregation), ERCOT determines whether one or more of the 3 default baseline types are applicable

• If ERCOT deems the adjusted load estimates produced by a default baseline model are sufficiently accurate and reliable, the estimates generated for an EILS event day will comprise the baseline

• Baseline loads (individually or in aggregate) are compared to actual loads on the event day to assess performance by the EILS Resource– Interval performance factors are calculated by comparing actual

load to the baseline for each 15-minute interval– Event Performance Factor is the average of all interval

performance factors

Page 16: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

16EILS Technical WorkshopJuly 17, 2009 16

Default Baseline concept

Metered Load

TIME

MW

Baseline

1 MW Contracted Load Reduction

10-minute reduction deadline

ReleaseDeployment instruction

Normal operations

(max 10 hours)

9

8

7

6

5

4

3

2

1

0

Page 17: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

17EILS Technical WorkshopJuly 17, 2009 17

Default Baseline types: Regression Model

• Rationale: Load can be predicted using weather and calendar variables

• Creates a baseline through regression analysis using numerous inputs:– Historical interval meter data – going back at least 12 months,

longer if necessary and available– Interval meter data collected during the Contract Period– Weather data– Calendar data– Sunrise/sunset times

• Same methodology used to create ERCOT’s daily Load Profiles• Detailed description of the regression methodology is available

under the ‘Forms & Supporting Documents’ tab at:http://www.ercot.com/services/programs/load/eils/

Page 18: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

18EILS Technical WorkshopJuly 17, 2009 18

Default Baseline types: Middle 8-of-10 Preceding Like Days

• Rationale: Load on recent days of the same day-type prior to an EILS event is likely to be similar to business-as-usual load for the event day

• Step 1: Identify the 10 most recent days having the same day-type as the event day.

– Day-types are defined as:• Weekdays (Monday – Friday excluding holidays)• Weekend / Holidays (Saturday, Sunday and ERCOT Holidays)

– Discard any day with:• Energy Emergency Alert (EEA) events• Scheduled unavailability • Other apparent outlier load values

– After discarding, go back in time until 10 acceptable days are found

• Step 2: Calculate overall kWh consumption for each of the 10 days and eliminate the days with the highest and lowest usage

• Step 3: Average the interval loads for the 8 remaining days -- result is the unadjusted baseline

Page 19: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

19EILS Technical WorkshopJuly 17, 2009 19

Default Baseline types: Matching Day Pair

• Rationale: Historical matching day-pairs can be found that are similar to load on the day-of and day preceding the event

• Step 1: Match intervals for the entire day before and the day of the event (up to one hour before the start of the event) with corresponding intervals for all day-pairs of the same type for the preceding year

– Day-pair types are classified by event day and are defined as follows:• Weekdays (Monday – Friday excluding holidays)• Weekend / Holidays (Saturday, Sunday and ERCOT Holidays)

– Discard any days with:• Energy Emergency Alert (EEA) events• Scheduled unavailability • Other apparent outlier load values

• Step 2: Calculate the sum of squared differences across the matching intervals between a matching day-pair and the event day-pair

• Step 3: Unadjusted baseline = interval-by-interval average of the 10 matching day-pairs with the lowest sum of squared differences

Page 20: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

20EILS Technical WorkshopJuly 17, 2009 20

Default Baselines: Event-day Adjustment

• An event-day adjustment is applied to all 3 default baseline types to improve accuracy

• Adjustment is based on the 8 intervals beginning three hours before the event start time– Load changes occurring in the hour before the event will not affect

the adjusted baseline• Actual kWh for the adjustment period = the sum of the Load’s

actual kWh across the 8 adjustment intervals • Baseline kWh = the sum of the baseline estimates across the

same 8 intervals • Adjustment factor = actual kWh divided by the baseline kWh • Adjusted baseline kWh = unadjusted baseline kWh for each event

interval x the adjustment factor

Page 21: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

21EILS Technical WorkshopJuly 17, 2009 21

Alternate Baseline

• Some loads do not have enough predictability to allow ERCOT to create a default baseline model; for example:– Fluctuating or batch-process loads– Loads with unpredictable downtimes or irregular schedules

• ERCOT will assign such loads to the Alternate Baseline– A.K.A. “drop to” baseline

• EILS Resources may choose the Alternate Baseline if they desire– Some Loads prefer the Alternate Baseline (e.g., industrials with

high load factors)• MW Bids should be ≤ projected average hourly load minus

declared Minimum Base Load• During an EILS deployment, load must not exceed its declared

Minimum Base Load throughout the event

Page 22: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

22EILS Technical WorkshopJuly 17, 2009 22

Availability Factor

• Using interval meter data after the fact, ERCOT calculates an Availability Factor for each EILS Resource

• Availability Factors are specific to baseline assignments:– Default Baseline: Percentage of committed hours that Load was

greater than than 95% of committed MW capacity– Alternate Baseline: Average hourly load (minus declared

Minimum Base Load) divided by committed MW capacity– Exempted:

• Any hours an EEA is in effect

• Scheduled Periods of Unavailability (up to 2% of hours in a Contract Period if noticed 5 Business Days in advance)

• Any hours an EILS test was being conducted

• If availability factor drops below 0.95, payment will be reduced• If it’s 0.95 or greater, it will be reset to 1.0• Capped at 1.0

Page 23: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

23EILS Technical WorkshopJuly 17, 2009 23

Performance Factor

• In a deployment event, EILS Resource must shed its committed load within 10 minutes and keep it off until released

• Performance will be evaluated by ERCOT using 15-minute interval data via the following calculations:– Interval Performance Factor (number between 0 and 1) = ratio

of actual to committed load reduction during each 15-minute interval covered by the event, specific to baseline assignment:• Default = baseline minus actual Load, divided by MW bid value,

weighted to the fraction of the interval that the curtailment period is in effect

• Alternate = declared Minimum Base Load divided by actual Load, with separate calculations for partial intervals at the beginning and end of the deployment period

– Event Performance Factor = average of the interval performance factors for all intervals of the deployment

• Event performance factor of ≥0.95 constitutes successful performance for the event

Page 24: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

24EILS Technical WorkshopJuly 17, 2009 24

Aggregated EILS Resources

• Aggregations receive baseline assignments (default or alternate) just as individual EILS Resources

• Aggregations are more likely to qualify for a default baseline than individual loads– Aggregations with larger numbers of loads are more likely to

qualify than small aggregations• Performance & availability of aggregations are:

– Calculated the same as for individual EILS Resources -- according to baseline assignment

– Determined at the aggregation level using summed load totals

Page 25: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

25EILS Technical WorkshopJuly 17, 2009 25

Payment Formula

• Within 70 days after the end of a Contract Period, QSEs representing EILS Resources are paid as follows, by Time Period:

(Bid amount X MW X Hours)

X

(Availability Factor) Number between 0 and 1

X

(Performance Factor) Number between 0 and 1

Page 26: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

26EILS Technical WorkshopJuly 17, 2009 26

Compliance & Testing

• Failure to meet availability or performance obligations is a violation of ERCOT Protocols– In addition to payment reduction, EILS Resource and/or its QSE

are subject to 6-month suspension from program• For aggregated EILS Resources, the entire aggregation is subject to

suspension

– Also subject to administrative penalties by the Public Utility Commission of Texas

• EILS Resources are subject to annual unannounced testing– Must deploy in 10 minutes just as in an actual event– Failure will result in re-testing– Two failures in a row subjects the EILS Resource to a 6-month

suspension– Substantial change to an EILS Resource during a year may

result in an additional test

Page 27: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

Updates to Procurement Process

Page 28: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

28EILS Technical WorkshopJuly 17, 2009 28

Updates to Procurement Process

• Goal s– Streamline and automate process to accommodate program

growth– Reduce data entry and manipulation errors– Create an interactive process which allows QSEs to reconfigure

Resources during the Resource ID phase to achieve a desired baseline

– Provide baseline certainty at the Resource ID phase– Avoid redundant baseline analysis during both the Resource ID

and Bid Analysis phases– Improve scheduled unavailability process

Page 29: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

29EILS Technical WorkshopJuly 17, 2009 29

Procurement Updates: Preliminary Baseline Review

• Purpose : Enable QSEs to obtain unofficial baseline assignments outside the procurement process

• New form (EILS Resource Submission Form – same for all phases of EILS)– QSE may submit EILS Resources multiple resources in one

workbook (one tab per resource)– May submit multiple configurations of ESIIDs and/or Time

Periods (baseline assignment options are likely to be influenced by the specific configuration)

– ERCOT will provide baseline results in separate workbooks for each submitted Resource

– Preliminary Baseline Review phase will be closed during the EILS Resource ID phase

Page 30: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

30EILS Technical WorkshopJuly 17, 2009 30

Procurement Updates: Resource ID Phase

• Purpose : Enable QSEs to officially identify and submit potential EILS Resources to ERCOT

• ERCOT staff reviews prospective EILS Resources and determines baseline assignment eligibility and historical Load availability

• EILS Resource ID phase extended to approximately four weeks• New form (EILS Resource Submission Form – same for all phases of EILS)• Interactive process between ERCOT and the QSE

– QSE submits form with prospective EILS Resources• Multiple Resources per workbook allowed

– ERCOT validates inputs for each Resource, exceptions reported back to QSE for potential correction and resubmission

– For validated Resources, ERCOT produces one workbook per resource showing:• Identification tab and Resource tab as submitted by QSE• Baseline eligibility and Load availability • ERCOT Assigned unique Resource ID number

– Resources may be reconfigured (ESIIDs and/or Time Periods) and resubmitted– Only validated resources with an assigned Resource ID number are allowed to bid

• Resources submitted on or before 8-20-09 will be eligible for Default baselines • Resources submitted from 8-21-09 through 8-26-09 will only be eligible for

Alternate baseline

Page 31: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

31EILS Technical WorkshopJuly 17, 2009 31

Procurement Updates: Bid Phase

• Purpose: Enable QSEs to officially offer EILS Resources to ERCOT• QSE may submit bids only for Resources validated during the

Resource ID phase with an assigned number– Uses the new EILS Resource Submission Form (same for all phases of

EILS)– Identification fields will be pre-populated by ERCOT– QSEs will enter bid-related inputs to the workbook:

• MW capacity offer• Price• Minimum Base Load• Baseline selection (if multiple options available)• Proration selection

– No other changes allowed (e.g. ESIIDs, Time Periods etc.)• QSE will submit one form per EILS Resource

– Large numbers of files may be Zipped• QSEs must ensure that no ESI ID is submitted more than once

– Bids with duplicate ESI IDs are subject to rejection by ERCOT

Page 32: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

32EILS Technical WorkshopJuly 17, 2009 32

EILS Resource Submission Form Review

– Open EILS Resource Submission Form examples

Page 33: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

33EILS Technical WorkshopJuly 17, 2009 33

EILS Resource Submission Form Review

• Exceptions Tab:

– Any errors or warning messages related to data submitted by the QSE will appear on this tab

– Errors result in no Resource ID number being assigned – resource will not be eligible for bid submission

– Example errors:• “ESIID not in Lodestar”• “Current Svc history status: I”• “Current Svc history status: D”• “Sub-meter Data Failed Validation”

– Warnings are produced for information purposes, resource will be eligible for bid submission but some QSE action may be required

– Example warnings:• “Currently NIDR meterdata type”• “NonLS Intervaldata with no matching Input Unique_Meter_Id”• “Missing NonLS Intervaldata”• “IDR servhist starts 29JAN2009 which is 394 days after begin of review period”

Page 34: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

34EILS Technical WorkshopJuly 17, 2009 34

EILS Resource Submission Form Review

• Availability Results Tab:– Tab is the same as in previous contract periods

• Exception: Minimum base Load will no longer be input for the Resource ID Phase

• Minimum base Load has no impact on eligible baseline assignments

– Results based on most recent 12 months of historical load data– Available Capacity in MW is reported for Resources eligible for

Default Baseline – value reported is 95th percentile Load level– Average Load in MW is reported for all Resources

• Resources ineligible for a Default Baseline only receive this value

• Resources eligible for a Default Baseline also receive this value (they may opt for an alternate baseline)

– QSEs should carefully consider baseline assignment for a resource when determining bid and minimum base Load amounts

Page 35: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

35EILS Technical WorkshopJuly 17, 2009 35

EILS Resource Submission Form Review

• Baseline Information Tab:– This tab contains diagnostic statistics to assist QSE with default

baseline assignment selection and MW bid determination• Results for all acceptable default baseline options are shown

• Results for any other default baselines are omitted

• If only the Alternate Baseline is available for a Resource, no results are shown

– Statistics provided:• RSquare: The percent of variation in actual load that is explained by

variation in the baseline load. (100% indicates a perfect baseline)

• MAPE: Mean Absolute Percent Error—Average absolute difference between the actual load and the baseline estimate

• PXX_kW_Confidence: (XX = 90, 95, 99) Based on historical data, the kW amount by which a QSE may consider de-rating an offer to achieve a XX% probability of meeting event performance requirements

Page 36: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

36EILS Technical WorkshopJuly 17, 2009 36

Scheduled Unavailability

• Open Scheduled Unavailability form

Page 37: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

37EILS Technical WorkshopJuly 17, 2009 37

Scheduled Unavailability

• Reports will be provided to QSE for all unavailability notices received by ERCOT

– Status of 2% exclusion– Exceptions

• Possible exceptions:– Not all ESIIDs in Resource entered on form– ESIID/Unique Meter ID not participating in current contract period– Invalid dates and times, for example:

• Stop date before start date• Invalid date or time• New submissions or cancellations with missing start or stop dates and times• Revisions with missing start, stop ,revised start or revised stop dates and times

– Revisions or Cancellations without matching New Submissions– Overlapping New Submissions without an intervening revision or cancellation– Insufficient notice for unavailability

• 5 Business days required for New Submission, and Revisions (adding periods of unavailability)

– Otherwise, not eligible for the 2% exclusion but will not be used for default baseline calculations

• 1 Business day required for Cancellations & Revisions (deleting periods of unavailability)– Otherwise, period will be treated as unavailable and will be counted towards 2%

exclusion allowance for the Resource

Page 38: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

38EILS Technical WorkshopJuly 17, 2009 38

38

Non-ERCOT Interval Data

• QSEs have the option to arrange for 15-minute interval kWh data to be collected and provided to ERCOT – Sub-metering a specific Load within a facility – Premise level metering for NIDR customers– Premise level metering for participants in Non Opt-in Entity areas

• Interval Data File Format Description

http://www.ercot.com/content/services/programs/load/eils/keydocs/Interval%20Data%20File%20Format%20Description.doc

• IDR Data Format Example

http://www.ercot.com/content/services/programs/load/eils/keydocs/IDR%20Data%20Format%20Example.csv

Page 39: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

39EILS Technical WorkshopJuly 17, 2009 39

39

Non-ERCOT Interval Data (continued)

• Timing for submitting interval data – Must accompany EILS Resource Submission form for either Preliminary

Baseline Review or Resource ID • 12 to 24 months of data needed if a default baseline assignment is desired• No affidavit required

– For Contract Performance, deadline for submitting 35 days after end of Contract Period

• Affidavit required at time of submission

• Data Validation– Unique Meter ID (UMI) in interval data file must match the UMI provided

on the EILS Resource Submission Form – Interval data will be checked for:

• Gaps and duplicate days• Correct number of intervals per day including DST days• Comparability with ERCOT monthly NIDR (kWh and kW values) if applicable• Comparability with ERCOT IDR interval settlement data

– Missing data and unresolved discrepancies will be treated as zeros for contract performance

Page 40: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

40EILS Technical WorkshopJuly 17, 2009 40

References & Additional Information

• EILS page at ERCOT.com– http://www.ercot.com/services/programs/load/eils/index.html– Includes:

• Technical Requirements & Scope of Work

• Reports of procurement results from previous Contract Periods

• Forms and other supporting documents

• Description of factors used in determining reasonableness of bids

• Annual report to the Public Utility Commission

• PUC Substantive Rule §25.507– http://www.puc.state.tx.us/rules/subrules/electric/25.507/25.507ei.cfm

• ERCOT Protocols– http://www.ercot.com/mktrules/protocols/current

Page 41: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

41EILS Technical WorkshopJuly 17, 2009 41

Contacts

• Questions should be submitted to [email protected]

• EILS contacts at ERCOT:– Paul Wattles, [email protected]– Steve Krein, [email protected]– Thelma Garza, [email protected]– Carl Raish, [email protected]– Diana Ott, [email protected]

• Market Participants may also contact their Client Services account manager

Page 42: ERCOT Emergency Interruptible Load Service EILS Technical Workshop Commissioners Hearing Room, PUC July 17, 2009.

42EILS Technical WorkshopJuly 17, 2009 42

ON

OFF