EPC Services-Paawan New

12
www.paawan-energy.com PAAWAN ENERGY MNRE, NSIC & MSME CHANNEL PARTNER FEASIBILITY STUDIES PROCUREMENT & SUPPLY SITE SURVEY & RESEARCH LEGAL ASSURANCE VENDOR SELECTION ENGINEERING, PROCUREMENT & CONSTRUCTION

Transcript of EPC Services-Paawan New

Page 1: EPC Services-Paawan New

www.paawan-energy.com

PAAWAN ENERGY

MNRE, NSIC & MSME CHANNEL PARTNER

FEASIBILITY STUDIES PROCUREMENT & SUPPLY

SITE SURVEY & RESEARCH LEGAL ASSURANCE

VENDOR SELECTION ENGINEERING, PROCUREMENT & CONSTRUCTION

Page 2: EPC Services-Paawan New

www.paawan-energy.com

EPC SERVICES-SOLAR PV PROJECTS Our engineering, procurement, and construction (EPC) team provides bankable, innovative, and

reliable solar energy solutions to customers around the world. Offering “turnkey” working systems

due to the set structures Paawan has in place, we are able to provide a complete spectrum of

services for projects from viability studies to commissioning.

Paawan is capable of managing a project through financing, engineering, procurement, construction

and beyond, Paawan’s team of experienced experts can provide:

• Viability Studies

• Financing

• Permitting

• Project Development

• Engineering

• Construction

EPC BENEFITS

Security: Ensure performance security to protect the interests of investors

Experience: In-depth experience in typical and complex installations

Bankability: Provide a bankability contract to our project company satisfying lender

requirements

Page 3: EPC Services-Paawan New

www.paawan-energy.com

EXECUTION SERVICES

Drawings & Documents

Civil work

DC Electrical work (Pre-Inverter)

AC Electrical work (post-Inverter)

Drawings & Documents Layout, SLD etc.

Civil Work

Land Development

Access roads

To facilitate Drainage system

Access module mounting structure

To construct PCU room

DC Electrical Work (Pre-Inverter)

Plot Plan Layout

Module Interconnection by series and parallel combination

String combiner boxes

Cable sizing

Supply to Inverter

SCADA System

AC Electrical Work (Post-Inverter)

Transformer rating LT

and HT Panels

Conductor sizing

Page 4: EPC Services-Paawan New

www.paawan-energy.com

ADVISORY & CONSULTANCY SERVICES

To provide expertise for business development through Govt. policies, schemes,

incentives etc.

Site survey & Research

Feasibility study

System Design & Engineering

To prepare BOQ, Quotation, Proposals etc

To prepare Layout, SLD & Engineering drawings

Drawings-PV Array, PCU, Switch yard, Civil, Mechanical, structural

Get approval from authority & SERC for design

To facilitate Bid Management/PPAs based projects

To deliver the Detailed Project Report & Pre-feasibility Report

To suggest competitive vendors as per requirement

Framework for planning & strategy for Erection & commissioning

Page 5: EPC Services-Paawan New

www.paawan-energy.com

PAAWAN TEAM

Mr. Asgar Ali

Head-I&C; Experience: 30Years

Qualification: B.E (EC)

Implemented approx. 50MW solar projects

Expertise in Project Management, Erection & commissioning, Installation, Operation & Maintenance

Mr. Jitendra Pathak (Sr. Project Manager)

Experience: 6Years

Qualification: B.tech (Electrical Engineering)

Implemented approx. 20MW solar projects

Expertise in Erection & commissioning, O&M

Mr. Chetan Kumar (Sr. Project Manager)

Experience: 6Years

Qualification: PGD (Renewables-MGICC);

B.tech (Mechanical Engg)

Implemented approx. 10MW solar projects

Expertise in Design & Engineering, Consultancy, Erection & commissioning, O&M, Training

Mr. Akshay Deep (Project Engineer)

Experience: 5Years

Qualification: M.tech (Renewable-TERI);

B.tech (Mechanical Engg)

Implemented approx. 10MW solar projects

Expertise in Design & Engineering, Project Management, Procurement, Installation & commissioning

Mr. Harvendra kumar (Project Engineer)

Experience: 5Years

Qualification: B.tech (EC-UPTU)

Implemented approx. 10MW solar projects

Expertise in Project Management, Installation & commissioning

Mr. Raj Bahadur (Technician)

Experience: 10years

Qualification: ITI

Implemented approx. 20MW solar projects

Expertise in Installation & commissioning

Page 6: EPC Services-Paawan New

www.paawan-energy.com

Mr. Rajesh kumar (Technician)

Experience: 10years

Qualification: ITI

Implemented approx. 20MW solar projects

Expertise in Installation & commissioning

Mr. Omveer Singh (Supervisor & Technician)

Experience: 8years

Qualification: ITI

Implemented approx. 10MW solar projects

Expertise in Installation & commissioning

Mr. Ravi Yadav (Technician)

Experience: 5years

Qualification: ITI

Implemented approx. 10MW solar projects

Expertise in Installation & commissioning

Mr. Indresh Kumar (Site Engineer)

Experience: 3years

Qualification: B.tech (EC-UPTU)

Implemented approx. 5MW solar projects

Expertise in Installation & commissioning, O&M

Mr. Surjeet Kumar (Site Engineer)

Experience: 3years

Qualification: B.tech (EC-UPTU)

Implemented approx. 5MW solar projects

Expertise in Installation & commissioning, O&M

Mr. Rahul Yadav (Site Engineer)

Experience: 3years

Qualification: B.tech (EE-UPTU)

Implemented approx. 5MW solar projects

Expertise in Installation & commissioning, O&M

Page 7: EPC Services-Paawan New

www.paawan-energy.com

Details of the Projects-EPC/Installation & commissioning

S.No. Name of the

client/customer

Project Description Total Capacity

1. The Energy Resource

Institute (TERI), IHC, New

Delhi

Setting up of Solar Micro grid Project

under LaBL Programme

10kWp

2. Gyandeep sr. sec school

shikohabad

Setting up solar power project of 5kWp;

Module-5kWp; Inverter-192V 10kVA,

Battery-12V 150Ah * 16nos.

5kWp

3. M/s Unify Disposable, Delhi Setting up of solar power plant-1kWp;

Module-250Wp * 4nos; Inverter-1kVA;

Battery-2nos. -12V 150Ah

1kWp

4. M/s Su-Kam Power Systems

Ltd, New delhi

50 kWp (3 No`s) SPV power Plant at IANA

Assam Riffles Camp and Shivalic Public

School 100 kWp (5 No`s) SPV Power Plant

at ASEB Ghuwati and Assam Riffles

102 kWp Spv power plant at Su Kam

Office

252kWp

5. M/s Larsen & Toubro Ltd

95 kWp SPV Power Plant at CSTI Pilkua Hapur Uttar Pradesh 125 kWP roof top project CM house PATNA Bihar

5 MWp SPV Power Plant at Village

Ghator Phalodi District Jodhpur Rajasthan

3.18 MWp SPV Power Plant at site

Village Dhurser Pokhran District. Jaislmer

Rajasthan

Roof-top-220kW

Grid-connected

capacity: 8.18MW

6. Reliance Industries Ltd.

1MW Solar Power Plant for the first time in India in solar lighting section in March 2010 at Kidwai Nagar Thayag Raj Stadium for Common Wealth Games 2010 New Delhi.

Roof top Grid-

connected-1MW

7. Lanco Solar Energy Pvt Ltd- 120 Kwp SPV Power Plant at National Institute of solar energy, Gurgoan

Roof top Off-grid-

Page 8: EPC Services-Paawan New

www.paawan-energy.com

120kW

8. Punjl loyd Pvt Ltd, New

delhi

50kWP SPV Power Plant at site PAU Ludhiana.

Roof top off-grid-

50kW

9. Ritika Systems Pvt Ltd,

Noida

30 No`s of 2.8 kWp SPV power plant at site Various District in Haryana and 5X10 Kwp SPV Power Plant at Site Tiloniya Rajasthan

Roof top off-grid

134kWp

10. M/s Tata B P Solar India

Ltd, New delhi

67.2kWP solar power plant in .Ian.2008 at NBCC plaza site Saket, New Delhi

Roof top off-grid

67.2kWp

11. M/s Vikram Solar Pvt Ltd,

Kolkata

I&C-2MW (Grid-connected); DC & AC Electrical work at Baap, Rajasthan

Grid-connected

capacity: 2MW

EXECUTION PLAN-Engineering, Procurement & Construction

Solar Project Execution Plan Activity Expected Time Period

Project Zero date 1 week

Land rights and free access to land

Allocation of PV Modules and tie-up with OEM

Allocation of inverters and tie-up with OEM

In-principle fund tie-up

NoC from Village panchyat and application for land conversion

Land demarkation

Soil investigation and soil test report

Pre-execution activity 1 week

Land contour survey

Boundary demarkation with Govt surveyor

Layout drawing with area grading & drainage

Application to Getco for connectivity and finalise their s/s

Page 9: EPC Services-Paawan New

www.paawan-energy.com

Creation of open store area for module Finalisation of module mounting structure design for MB modules

Finalisation of painting / GI for mounting structure

Procurement of Components 2-3weeks

Civil Contractor Finalization

Mounting structural for modules

AC package

DC cables

Connectors

Fastners / hardwares for mounting structure

SCB

Installers

SCADA

Earthing and lighting protection of PV yard

Illumination package

Engineering 2-3weeks (Execute parallel with Procurement)

Approval of Layout

Foundation design for module mounting structure

Fianlisation of 33/66 kV S/S, main control room along with DISCOM

Approval of SLD / Plan - section of 66 kV s/s

Foundation plan & design of 66 kV S/S

Approval of SY. MOM for Structure, Inverter & transformer

Foundation design of structure, inverter & transformer

Mounting structure design approval

DC Engg fianlisation

Finalisation of internal roads, drains, fencing, crossings etc

Freezing of engg (supply code) for inverters

Page 10: EPC Services-Paawan New

www.paawan-energy.com

Approval of engg drawing for Switchgear/cable/C&R panel/CT/PT/LA/Breaker

Supply of equipments at site 2-3weeks

Mounting structure

PV modules

Inverters

Transformers

Switchgear/C&R panel/CT/PT/LA/Breaker

DC cables

Connectors

Fastners / hardwares for mounting structure

SCB

SCADA

Switch yard structures

Civil / Construction 2week

Mobilisation of civil contractor at site

Fencing

Release of civil foundation drawings for

Internal roads, drains

66 kV s/s design drawing

HT control room

LT control room

Transformers

Foundation of PV modules

HT control room (one no)

LT control room

S/S equipment and tower, cable trench

Page 11: EPC Services-Paawan New

www.paawan-energy.com

Transformer

Internal roads, drains

Erection of DC system 4-5weeks

Mobilisation of installers at site

Module structure

Module erection

Laying / termination of DC cable

Erection of inverters/VCB/LT panel

Testing of arrays

Erection of AC system 4weeks

Mobilisation of AC package contractor at site

Switch Yard structures

Switch Yard Equipment

Transformer

HT board

C&R panel

Testing of Electrical system 4-5days

Availability of DISCOM line 10-12days

Approval of CEI/DISCOM 1-2week

Charging of 33/66 kVA substation 1-2days

Charging of 11 kVA Switchboard 1-2days

Charging of inverter & Transformer 1-2days

Testing/commissioning of inverters 1-2days

Power injection into grid 1-2days

CoD (Commercial operation Date) 1day

Submission of as-built drawing 2days

Handover with identified punch points 2days

Page 12: EPC Services-Paawan New

www.paawan-energy.com

EPC COSTING

S. No. Capacity Range Amount INR

(Crore/MW) 01 1-10MW 6crore

02 10-50W 5.5crore

Power Purchase Agreement-Solar Projects