PETROBEL

EGYPT

SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT

3467-200 Rev.0

06/07/2011

PJC

01-

B32

74-0

908

NTSCONTE

1.0 EXECUTIVE SUMMARY

1.1 PROJECT DESCRIPTION. 1.2 REPORT PERIOD. 1.3 OVERALL PROJECT PROGRESS SUMMARY. 1.4 QHSE SUMMARY 1.5 AREA OF CONCERN

2.0 ATTACHMENTS

ATTACHMENT (01) Planning portion of monthly external progress report

Page 3: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PETROBEL

EGYPT

SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT

3467-200 Rev.0

06/07/2011

PJC

01-

B32

74-0

908

1.0 EXECUTIVE SUMMARY

Page 4: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PETROBEL

EGYPT

SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT

3467-200 Rev.0

06/07/2011

PJC

01-

B32

74-0

908

1.1 Project Description

PETROBEL is considering the development of new gas field in the RAS EL BARR concession, in the west Nile Delta area (Mediterranean Sea). The gas field SETH is located in water depth 83.3 m in the Mediterranean Sea, 11km west of Denise A, at about 60km off the Egyptian costs, North East of Damietta and North West of Port Said. The production shall be delivered to EL-GAMIL plant. SETH development plan includes D&C of two wells (i.e. SETH West Shallow & SETH West Deep) plus two future wells (SETH East Shallow & SETH East Deep), with total production flow rate of 4.5 MMSCFD.

Project comprises of the following facilities:

1) 4-legged unmanned platform (namely SETH, in approx. 83 m of water).

2) Topside facilities (minimum production facilities).

3) Construction of new dedicated sea line 16”x11 km length.

4) Installation of SSIV close to platform. The battery limit of this project Subsea Tie-in at Tuna PLEM by installation of new Seth PLEM Major Scope Contents

• Project Management & Control. • Design for Piles, Jacket, Risers, J-tube & Pre drilling template. • Design for Deck and TSF. • Construction of Piles, Jacket, Risers, J-tube & Pre drilling template. • Construction of Deck and TSF. • Construction of Pipeline rigid and Spools. • Procurement Service for Subsea Equipment (PLEM & SSIV). • Load-out & Sea-fastening. • Offshore Hook-up & Commissioning.

1.2 Report Period:

This progress report covers the Work Performed during June 2011 Till the Cut-Off Date 25, June2011.

Page 5: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PETROBEL

EGYPT

SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT

3467-200 Rev.0

06/07/2011

PJC

01-

B32

74-0

908

1.3 Overall Project Progress Summary

Item Description RW Planned Actual

ENPPI

44.83%

5.8%

6.5%

PETROJET

41.56%

18.0%

22.2%

TECNOMARE

13.61%

37.7%

39.5%

Total 100.00% 15.2% 17.5%

1.4 QHSE SUMMARY

• Project Quality Plan is issued and in place

• Project Scope and Procedures is issued and in place

• HSE PLAN for engineering is in place

• Project audit schedule is in place (periodical audit)

• Review of Quality, HSE management system in suppliers’ offers is under implementation

1.5 AREA OF CONCERN A) Engineering Activities

• Electrical load trend is showing increase in demand. A technical meeting will be arranged

upon issuing the Electrical Load Analysis Report in order to discuss the possible solutions.

B) Procurement Activities • Due to some delays of bidders response, and in order to avoid impact of August holidays

with suppliers, it is important to maintain target to place FOC’s for critical items before the end of July.

C) Construction Activities

• None.

13631
Line
Page 6: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PETROBEL

EGYPT

SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT

3467-200 Rev.0

06/07/2011

PJC

01-

B32

74-0

908

2.0 ATTACHEMENTS

Page 7: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 17 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4. Attachments

Page 8: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 18 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.1. PROGRESS SUMMARY TABLES WITH RELEVANT S-CURVES

Page 9: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 19 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.1.1 Overall

Page 10: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

ENPPI 44.83% 5.8% 6.5%

PETROJET 41.56% 18.0% 22.2%

TECNOMARE 13.61% 37.7% 39.5%

TOTAL 100.00% 15.2% 17.5%

3467-200, PTB, SETH DEVELOPMENT EPC PROJECTOVERALL PROGRESS AS OF 25-JUNE-11

ITEM DESCRIPTION Relative Weight (%) PLANNED % ACTUAL %

Page 11: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

As of : 25‐Jun‐11

     Project No:3467‐200     PTB, Seth Development EPC Project  Progress Curve

Overall 

50

60

70

80

90

100

ess %

Actual      % = 17.5

Planned   % =15.2

Layout No. 1Data'Nes System Release 2.21

0

10

20

30

40

50

60

70

80

90

100

Mar/11 Apr/11 May/11 Jun/11 Jul/11 Aug/11 Sep/11 Oct/11 Nov/11 Dec/11 Jan/12 Feb/12 Mar/12 Apr/12 May/12 Jun/12 Jul/12

Planned Actual

Progress %

Actual      % = 17.5

Time / Date 

Planned   % =15.2

Page 12: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 20 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.1.2 ENPPI

Page 13: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

3467-200 PTB, SETH OFFSHORE DEVELOPMENT EPC PROJECTDELAY ANALYSISAS OF 25-JUN-11

Discipline Delay % weighted delay % from Overall

ProjectDELAYED ACTIVITIES PLANNED DATE EXPECTED DATE CAUSE OF DELAY

Process 7.9 0.17

Flame arrestor TERSafety equipment and life saving TERFire Fighting package TER 23‐Jun‐11 21‐Jul‐11

Suppliers replies delays on ENPPI clarifications

Pipipng 4.8 0.17

Injection fitting TERInsulation joint Injection fitting TER

15‐Jun‐11 24‐Jul‐11

Delay in receiving  the technical offers due to suppliers response delay

Service water pump TER Nouva oma (one of the bidder) request to submit ISO5199 pump instead of ASME B73.1 as originally request in MR.

Mechanical 7.2 0.08 7‐Jun‐11 10‐Jul‐11

instead of ASME B73.1 as originally request in MR.Received from Nouva Oma complete reply on 1st clarification, his reply based on ISO 5199.Ruhrpumpen (one of the bidder) submit his reply on 1st clarification, his offer based on pump ASME B73.1 .Receive acceptance from PTB on evaluating both pump types ISO5199 and ASME B73.1

Electrical 5.9 0.11

Power system studySingle line diagramElectrical cable list

15‐Jun‐11 17‐Jul‐11

In progress

Choke valve TERElectrical hook‐up DrawingH d li i t t l t

Delay is due to revised H&M balance issued during the detailed engineering phaseTh ff d l h i l l di th i t l

Instrumentation 8.4 0.20Hydraulic instruments layouts

20‐Jun‐11 1‐Aug‐11‐The offered valves have noise levels exceeding the enviromental low‐In progress

Offshore 4.0 0.07

Survival Module TER

13‐Jun‐11 12‐Jul‐11

Suppliers replies delays on ENPPI clarifications

Purchasing 8.4 0.11

Delay in receiving the commercial offers for the folloowing commodities:Safety equipment and life saving ; Flame arrestor; Fire Fighting package ; Injection fitting ; Choke valves ; Electro hydraulic wellhead control panel ; Wing valves & Service water pump

23‐Jun‐11 26‐Jul‐11

Delay of issuance of TERs 

Service water pump

Overall Project Overall project progress is ahead ( 6.52 % vs.5.75 %) because the material supply progress is ahead (1.99 % vs. 00%) 0.9

Page 14: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Progress CurveSETH Offshore EPC Project

25-Jun-11As Of :Overall

3467-200Project No.:

0

10

20

30

40

50

60

70

80

90

100

1-Mar-11

1-Apr-11

1-May-11

1-Jun-11

1-Jul-11 1-Aug-11

1-Sep-11

1-Oct-11 1-Nov-11

1-Dec-11

1-Jan-12 1-Feb-12

1-Mar-12

1-Apr-12

1-May-12

1-Jun-12

1-Jul-12

Time / Date

Prog

ress

%

Actual Planned

Planned % =

Actual % =

5.75

6.52

Layout No. 1

Data'Nes Systems, Release 2.21

Page 15: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Planned%

Actual%

Relative Weight

Item Description During%

Summary ReportSETH Offshore EPC Project

25-Jun-11As Of :

3467-200Project No.:

ENPPI

38.38 32.6013.05%W.P.2 DETAILED ENGINEERING 7.78

22.29 19.003.33%W.P.3 PROCUREMENT SERVICES 7.01

0.00 1.9981.45%W.P.5 DECK AND TSF SUPPLY & FABRICATION

1.99

0.00 0.002.16%W.P.9 OFFSHORE HOOK-UP & COMMISSIONING

0.00

5.75 6.51100.00% 2.87Total

Thursday, June 30, 2011

Page 1 of 1

Layout No. 1

Data'Nes Systems, Release 2.21

Page 16: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Progress CurveSETH Offshore EPC Project

25-Jun-11As OfWork Package

3467-200Project No.:

0

10

20

30

40

50

60

70

80

90

100

Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12

Time / Date

Prog

ress

%

Actual Planned

Planned % =

Actual % =

38.38

32.60

W.P.2 DETAILED ENGINEERING

Layout No. 1

Data'Nes Systems, Release 2.21

Page 17: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Progress CurveSETH Offshore EPC Project

25-Jun-11As OfWork Package

3467-200Project No.:

0

10

20

30

40

50

60

70

80

90

100

Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12

Time / Date

Prog

ress

%

Actual Planned

Planned % =

Actual % =

22.29

19.27

W.P.3 PROCUREMENT SERVICES

Layout No. 1

Data'Nes Systems, Release 2.21

Page 18: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Progress CurveSETH Offshore EPC Project

25-Jun-11As OfWork Package

3467-200Project No.:

0

10

20

30

40

50

60

70

80

90

100

Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12

Time / Date

Prog

ress

%

Actual Planned

Planned % =

Actual % =

0.00

1.99

W.P.5 DECK AND TSF SUPPLY & FABRICATION

Layout No. 1

Data'Nes Systems, Release 2.21

Page 19: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Progress CurveSETH Offshore EPC Project

25-Jun-11As OfWork Package

3467-200Project No.:

0

10

20

30

40

50

60

70

80

90

100

Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12

Time / Date

Prog

ress

%

Actual Planned

Planned % =

Actual % =

0.00

0.00

W.P.9 OFFSHORE HOOK-UP & COMMISSIONING

Layout No. 1

Data'Nes Systems, Release 2.21

Page 20: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Planned%

Actual%

Relative Weight

Item Description During%

Summary ReportSETH Offshore EPC Project

25-Jun-11As Of :

3467-200Project No.:

ENPPIW.P.2 DETAILED ENGINEERING

PROCESS TECHNOLOGY DIVISION 55.58 47.6716.98% 8.06

INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT

47.16 38.7417.92% 17.79

PIPING ENGINEERING DIVISION 28.58 23.7625.94% 3.69

ELECTRICAL ENGINEERING DIVISION 43.90 38.0014.15% 7.97

OFFSHORE ENGINEERING DIVISION 17.00 13.0012.74% 0.00

MECHANICAL ENGINEERING DEPARTMENT

46.42 39.208.49% 10.11

PRESSURE VESSELS ENGINEERING DEPARTMENT

20.00 20.003.77% 0.00

38.38 32.32100.00% 7.50Total

Wednesday, July 06, 2011

Page 1 of 4

Layout No. 1

Data'Nes Systems, Release 2.21

Page 21: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Planned%

Actual%

Relative Weight

Item Description During%

Summary ReportSETH Offshore EPC Project

25-Jun-11As Of :

3467-200Project No.:

ENPPIW.P.3 PROCUREMENT SERVICES

FOREIGN PURCHASING DEPARTMENT 53.17 44.7339.66% 16.83

EXPEDITING DEPART. 3.03 3.1739.64% 0.84

SUPPLIER QUALITY SRVEILLANCE DEPART.

0.00 0.0010.07% 0.00

TRAFFIC & LOGISTICS DEPARTMENT 0.00 0.0010.63% 0.00

22.29 19.00100.00% 7.01Total

Wednesday, July 06, 2011

Page 2 of 4

Layout No. 1

Data'Nes Systems, Release 2.21

Page 22: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Planned%

Actual%

Relative Weight

Item Description During%

Summary ReportSETH Offshore EPC Project

25-Jun-11As Of :

3467-200Project No.:

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATION

METERIAL SUPPLY 0.00 1.99100.00% 1.99

0.00 1.99100.00% 1.99Total

Wednesday, July 06, 2011

Page 3 of 4

Layout No. 1

Data'Nes Systems, Release 2.21

Page 23: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Planned%

Actual%

Relative Weight

Item Description During%

Summary ReportSETH Offshore EPC Project

25-Jun-11As Of :

3467-200Project No.:

ENPPIW.P.9 OFFSHORE HOOK-UP & COMMISSIONING

COMMISSIONING 0.00 0.00100.00% 0.00

0.00 0.00100.00% 0.00Total

Wednesday, July 06, 2011

Page 4 of 4

Layout No. 1

Data'Nes Systems, Release 2.21

Page 24: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 21 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.1.3 TECNOMARE

Page 25: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

OVERALL PROGRESS

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 33,89 3,83 1,66 1,70 7,75 5,14 22,10 1,13 7,71 0,45 0,50 1,54 0,25 11,37 0,00 0,00 0,99

% Monthly Actual 33,89 5,57

% Forecast Monthly

% Cumulative Planned 33,89 37,72 39,38 41,07 48,82 53,96 76,07 77,20 84,91 85,36 85,86 87,40 87,64 99,01 99,01 99,01 100,0

% Cumulative Actual 33,89 39,46

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 26: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve1.1.1 - PROJECT SERVICES

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 33,89 3,83 1,66 1,70 7,75 5,14 22,10 1,13 7,71 0,45 0,50 1,54 0,25 11,37 0,00 0,00 0,99

% Monthly Actual 33,89 5,57

% Forecast Monthly

% Cumulative Planned 33,89 37,72 39,38 41,07 48,82 53,96 76,07 77,20 84,91 85,36 85,86 87,40 87,64 99,01 99,01 99,01 100,0

% Cumulative Actual 33,89 39,46

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 27: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve1.2 - DETAILED ENGINEERING

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 40,05 9,34 3,64 1,42 10,80 11,69 3,48 2,27 0,79 0,29 1,16 0,00 0,58 12,18 0,00 0,00 2,31

% Monthly Actual 40,05 11,60

% Forecast Monthly

% Cumulative Planned 40,05 49,39 53,03 54,45 65,25 76,94 80,42 82,69 83,48 83,77 84,93 84,93 85,51 97,69 97,69 97,69 100,0

% Cumulative Actual 40,05 51,65

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 28: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.2.1.Deck

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 49,82 13,11 5,10 2,00 2,35 16,40 4,88 3,19 1,11 0,41 1,63

% Monthly Actual 49,82 16,28

% Forecast Monthly

% Cumulative Planned 49,82 62,93 68,03 70,03 72,38 88,78 93,66 96,85 97,96 98,37 100,0

% Cumulative Actual 49,82 66,10

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 29: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.2.2 - SSIV/PLEM (TECHNICAL FOLLOW-UP)

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 20,00 0,00 0,00 0,00 80,00

% Monthly Actual 20,00 0,00

% Forecast Monthly

% Cumulative Planned 20,00 20,00 20,00 20,00 100,0

% Cumulative Actual 20,00 20,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 30: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.2.8 - AS BUILT DOSSIER

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 20,00 0,00 0,00 0,00 80,00

% Monthly Actual 0,00 0,00

% Forecast Monthly

% Cumulative Planned 20,00 20,00 20,00 20,00 100,0

% Cumulative Actual 0,00 0,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 31: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.2.9 - CERTIFICATION (ASSISTANCE)

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 20,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 80,00

% Monthly Actual 0,00 0,00

% Forecast Monthly

% Cumulative Planned 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 100,0

% Cumulative Actual 0,00 0,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 32: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.2.10 - TECHNICAL FOLLOW-ON FOR T&I CONTRACTS

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 20,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 80,00

% Monthly Actual 20,00 0,00

% Forecast Monthly

% Cumulative Planned 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 100,0

% Cumulative Actual 20,00 20,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 33: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.3 - PROCUREMENT SERVICES

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 32,01 4,20 5,99 21,77 8,44 8,89 0,00 10,27 6,43

% Monthly Actual 32,01 5,06

% Forecast Monthly

% Cumulative Planned 32,01 36,21 42,60 63,58 74,42 83,30 83,30 93,57 100,0

% Cumulative Actual 32,01 37,07

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 34: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.3.3 - PROCUREMENT SERVICES - PLEM/SSIV

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 20,00 6,00 16,00 48,00 10,00

% Monthly Actual 20,00 6,66

% Forecast Monthly

% Cumulative Planned 20,00 26,00 42,00 90,00 100,0

% Cumulative Actual 20,00 26,66

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 35: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.3.6 - PROCUREMENT SERVICES - PLC/RTU

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 40,00 3,00 0,00 3,00 11,40 14,80 0,00 17,10 10,70

% Monthly Actual 40,00 4,00

% Forecast Monthly

% Cumulative Planned 40,00 43,00 43,00 46,00 57,40 72,20 72,20 89,30 100,0

% Cumulative Actual 40,00 44,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 36: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.4.9 Grout Seals and Schock Cells

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 23,33 11,67 0,00 0,00 65,00

% Monthly Actual 23,33 11,67

% Forecast Monthly

% Cumulative Planned 23,33 35,00 35,00 35,00 100,0

% Cumulative Actual 23,33 35,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 37: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.5.17 Other Instrumentation - PLC/RTU & instrumentation bulks

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 35,00 0,00 0,00 0,00 0,00 0,00 50,00 0,00 15,00

% Monthly Actual 35,00 0,00

% Forecast Monthly

% Cumulative Planned 35,00 35,00 35,00 35,00 35,00 35,00 85,00 85,00 100,0

% Cumulative Actual 35,00 35,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 38: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

40,00

50,00

60,00

70,00

80,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

M

on

thly

% P

rog

ress

Cu

mu

lati

ve

1.8.1.3 - HOOCK-UP, COMMISSIONING ACTIVITIES AND START UP

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Apr-12

May-12

Jun-12

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

% Monthly Planned 20,00 0,00 80,00

% Monthly Actual 0,00 0,00

% Forecast Monthly

% Cumulative Planned 20,00 20,00 100,0

% Cumulative Actual 0,00 0,00

% Forecast Cumulative

0,00

10,00

20,00

30,00

0,00

10,00

20,00

30,00

% P

rog

ress

M

% P

rog

ress

Cu

mu

lati

ve

Page 39: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 22 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.1.4 PETROJET

Page 40: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 2.31% 9.71% 18.00% 24.33% 27.71% 34.62% 41.43% 48.66% 56.35% 64.58% 73.87% 82.79% 88.50% 93.61% 97.39% 100.00%

ACT % 0.00% 4.51% 14.27% 22.34%

SETH DEVELOPM,ENT PROJECTOVER ALL LEVEL I

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

PLAN % ACT %

As of Date : 25-06-2011Plan : 18.00 %Actual : 22.23 %

As of Date : 25-06-2011Plan : 18.00 %Actual : 22.23 %

1/9

Page 41: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 6.00% 12.00% 18.00% 24.00% 30.00% 36.00% 42.00% 48.00% 54.00% 60.00% 66.00% 72.00% 78.00% 84.00% 90.00% 100.00%

ACT % 0.00% 6.00% 12.00% 18.00%

PROJECT MANAGEMENTWP1

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

PLAN % ACT %

As of Date : 25-06-2011Plan : 18.00 %Actual : 22.23 %

As of Date : 25-06-2011Plan : 18.00 %Actual : 18.00 %

2/9

Page 42: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 6.00% 12.00% 18.00% 24.00% 30.00% 36.00% 42.00% 48.00% 54.00% 60.00% 66.00% 72.00% 78.00% 84.00% 90.00% 100.00%

ACT % 0.00% 6.00% 12.00% 18.00%

PROCUREMENT SERVICESWP3

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

PLAN % ACT %

As of Date : 25-06-2011Plan : 18.00 %Actual : 22.23 %

As of Date : 25-06-2011Plan : 18.00 %Actual : 18.00 %

3/9

Page 43: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 9.95% 23.30% 32.53% 42.05% 47.86% 58.92% 68.59% 77.98% 84.58% 89.46% 97.26% 100.00% 100.00% 100.00% 100.00% 100.00%

ACT % 0.00% 10.00% 30.66% 44.27%

SUBSTRUCTURE ( P.D.T, PILES AND JACKET ) FABRICATIONWP4

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

PLAN % ACT %

As of Date : 25-06-2011Plan : 18.00 %Actual : 22.23 %

As of Date : 25-06-2011Plan : 32.53 %Actual : 44.27 %

4/9

Page 44: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 1.11% 2.12% 15.01% 22.13% 24.22% 31.58% 39.16% 48.50% 61.08% 76.63% 92.21% 96.99% 99.69% 100.00% 100.00% 100.00%

ACT % 0.00% 2.12% 10.00% 16.82%

DECK & TSF MATERIAL/EQUIPMENT SUPPLY AND FABRICATIONWP5

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

PLAN % ACT %

As of Date : 25-06-2011Plan : 18.00 %Actual : 22.23 %

As of Date : 25-06-2011Plan : 15.01 %Actual : 16.82 %

5/9

Page 45: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.09% 56.69% 100.00% 100.00% 100.00% 100.00%

ACT % 0.00% 2.12% 10.00% 16.82%

PIPELINE SPOOLS FABRICATIONWP6

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12

PLAN % ACT %

As of Date : 25-06-2011Plan : 00.00 %Actual : 00.00 %

6/9

Page 46: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.06% 3.06% 3.06% 3.06% 3.06% 40.73% 68.56% 100.00% 100.00% 100.00%

ACT %

LOAD OUT AND SEA FASTENINGWP8

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12

PLAN % ACT %

As of Date : 25-06-2011Plan : 00.00 %Actual : 00.00 %

7/9

Page 47: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00%

ACT %

OFFSHORE HOOK‐UP AND COMMISSIONINGWP9

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

25‐Apr‐12 25‐May‐12 25‐Jun‐12

PLAN % ACT %

As of Date : 25-06-2011Plan : 00.00 %Actual : 00.00 %

8/9

Page 48: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

MONTH 25‐Mar‐11 25‐Apr‐11 25‐May‐11 25‐Jun‐11 25‐Jul‐11 25‐Aug‐11 25‐Sep‐11 25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12 25‐Jun‐12 31‐Jul‐12

PLAN % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.00% 30.00% 50.00% 70.00% 90.00% 100.00% 100.00%

ACT %

CRASHING COST

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

25‐Oct‐11 25‐Nov‐11 25‐Dec‐11 25‐Jan‐12 25‐Feb‐12 25‐Mar‐12 25‐Apr‐12 25‐May‐12

PLAN % ACT %

As of Date : 25-06-2011Plan : 00.00 %Actual : 00.00 %

9/9

Page 49: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 23 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.2. CONTROL SHEETS

Page 50: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 24 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.2.1 ENPPI

Page 51: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONDRAWING

9.44%Process flow diagram 70.00%

70.00%

Start 06-Apr-11 2003-Apr-11

Design 21-Apr-11 5010-Apr-11

Final 20-Sep-11 3019-Sep-11

4.17%Utility flow diagram 70.00%

70.00%

Start 03-Apr-11 2006-Apr-11

Design 10-Apr-11 5013-Apr-11

Final 27-Sep-11 3026-Sep-11

1.39%Cause & Effect Chart 70.00%

70.00%

Start 25-Apr-11 2009-May-11

Design 23-Jun-11 5016-May-11

Construction 20-Sep-11 3019-Sep-11

0.56%Process block diagram 70.00%

70.00%

Start 12-Jun-11 2007-Jun-11

Design 20-Jun-11 5014-Jun-11

Construction 27-Sep-11 3026-Sep-11

0.56%Below Cellar deck Escape Route, safety and lifesaving equipment layout 70.00%

70.00%

Start 12-May-11 2031-May-11

Design 17-May-11 5007-Jun-11

Construction 04-Oct-11 3003-Oct-11

0.56%Helideck - Escape way, safety and lifesaving equipment layout 70.00%

70.00%

Start 12-May-11 2031-May-11

Design 17-May-11 5007-Jun-11

Construction 04-Oct-11 3003-Oct-11

0.56%Below Cellar deck - Firefighting System layout 70.00%

70.00%

Start 03-May-11 2005-May-11

Design 08-May-11 5012-May-11

Construction 27-Sep-11 3026-Sep-11

0.56%Cellar Deck - Firefighting System layout 70.00%

70.00%

Start 03-May-11 2005-May-11

Design 08-May-11 5012-May-11

Construction 27-Sep-11 3026-Sep-11

Tuesday, July 05, 2011 Page 1 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 52: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONDRAWING

0.56%Main deck - Firefighting System layout 70.00%

70.00%

Start 03-May-11 2005-May-11

Design 08-May-11 5012-May-11

Construction 27-Sep-11 3026-Sep-11

0.56%Helideck - Firefighting System layout 70.00%

70.00%

Start 03-May-11 2005-May-11

Design 08-May-11 5012-May-11

Construction 27-Sep-11 3026-Sep-11

0.56%Below Cellar deck - Safety signs layout 70.00%

70.00%

Start 09-May-11 2031-May-11

Design 16-May-11 5007-Jun-11

Construction 04-Oct-11 3003-Oct-11

0.56%Cellar deck - Safety signs layout 70.00%

70.00%

Start 09-May-11 2031-May-11

Design 16-May-11 5007-Jun-11

Construction 04-Oct-11 3003-Oct-11

0.56%Main deck - Safety signs layout 70.00%

70.00%

Start 09-May-11 2031-May-11

Design 16-May-11 5007-Jun-11

Construction 04-Oct-11 3003-Oct-11

0.56%Helideck - Safety signs layout 70.00%

70.00%

Start 09-May-11 2031-May-11

Design 16-May-11 5007-Jun-11

Construction 04-Oct-11 3003-Oct-11

70.00% 70.00%21.11%

REPORTS / TECHNICAL LIST

1.94%Basis of design 100.00%

70.00%

Start 08-Apr-11 2010-Apr-11

Design 12-Apr-11 5012-Apr-11

Final 07-Jul-11 3011-Jun-11

1.94%Heat & Material balance report 70.00%

70.00%

Start 04-Apr-11 2003-Apr-11

Design 11-Apr-11 5010-Apr-11

Final 20-Sep-11 3019-Sep-11

Tuesday, July 05, 2011 Page 2 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 53: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONREPORTS / TECHNICAL LIST

1.94%Project master equipment list 70.00%

70.00%

Start 03-May-11 2008-May-11

Design 10-May-11 5015-May-11

Construction 18-Sep-11 3015-Sep-11

1.94%Process & Utilities report 70.00%

20.00%

Start 24-Jun-11 2005-Jun-11

Design 12-Jul-11 5012-Jun-11

Final 20-Sep-11 3019-Sep-11

1.94%Blow down reprot 0.00%

0.00%

Start 26-Jul-11 2003-Jul-11

Design 01-Aug-11 5010-Jul-11

Final 02-Oct-11 3029-Sep-11

1.94%Utilities load summary 20.00%

70.00%

Start 16-Jun-11 2019-Jun-11

Design 23-Jun-11 5026-Jun-11

Final 26-Sep-11 3025-Sep-11

1.94%Hazardous Area classification report 70.00%

70.00%

Start 10-May-11 2026-Apr-11

Design 16-May-11 5004-May-11

Construction 27-Sep-11 3026-Sep-11

2.50%Hazop report 0.00%

0.00%

Start 25-Aug-11 2021-Jul-11

Final 12-Sep-11 8004-Aug-11

1.94%HSE philosophy 70.00%

70.00%

Start 10-May-11 2020-Apr-11

Design 16-May-11 5027-Apr-11

Final 10-Oct-11 3009-Oct-11

50.62% 47.38%18.06%

MRQ

1.67%Chemical injection package MRQ 100.00%

100.00%

Start 01-Apr-11 2003-Apr-11

For inquiry 03-Apr-11 8006-Apr-11

Tuesday, July 05, 2011 Page 3 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 54: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONMRQ

1.67%Flame arrestor MRQ 100.00%

100.00%

Start 15-Apr-11 2020-Apr-11

For inquiry 19-Apr-11 8027-Apr-11

1.67%Vent stack package MRQ 100.00%

100.00%

Start 25-Apr-11 2002-May-11

For inquiry 28-Apr-11 8009-May-11

1.67%Fire Fighting package MRQ 100.00%

100.00%

Start 01-Apr-11 2006-Apr-11

For inquiry 03-Apr-11 8012-Apr-11

1.67%Safety equipment and life saving MRQ 100.00%

100.00%

Start 01-Apr-11 2003-Apr-11

For inquiry 03-Apr-11 8012-Apr-11

100.00% 100.00%8.33%

TER

3.06%Chemical injection package TER 100.00%

100.00%

Start 18-Apr-11 2008-May-11

Finish 01-Jun-11 8019-Jun-11

3.06%Flame arrestor TER 100.00%

20.00%

Start 02-Jun-11 2026-May-11

Finish 21-Jul-11 8023-Jun-11

3.06%Vent stack package TER 20.00%

20.00%

Start 01-Jun-11 2006-Jun-11

Finish 26-Jul-11 8004-Jul-11

3.06%Fire Fighting package TER 100.00%

20.00%

Start 26-Apr-11 2011-May-11

Finish 05-Jul-11 8009-Jun-11

3.06%Safety equipment and life saving TER 100.00%

20.00%

Start 05-Apr-11 2008-May-11

Finish 07-Jul-11 8012-Jun-11

84.00% 36.00%15.28%

Tuesday, July 05, 2011 Page 4 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 55: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONMRP

0.83%Chemical injection package MRP 0.00%

0.00%

Start 03-Jul-11 2010-Jul-11

For Purchase 07-Jul-11 8017-Jul-11

0.83%Flame arrestor MRP 0.00%

0.00%

Start 07-Aug-11 2021-Jul-11

For Purchase 09-Aug-11 8028-Jul-11

0.83%Vent stack package MRP 0.00%

0.00%

Start 21-Aug-11 2003-Aug-11

For Purchase 22-Aug-11 8010-Aug-11

0.83%Fire Fighting package MRP 0.00%

0.00%

Start 20-Jul-11 2005-Jul-11

For Purchase 21-Jul-11 8011-Jul-11

0.83%Safety equipment and life saving MRP 0.00%

0.00%

Start 07-Aug-11 2010-Jul-11

For Purchase 11-Aug-11 8017-Jul-11

0.00% 0.00%4.17%

VENDOR PRINTS REVIEW

5.28%Chemical injection package 0.00%

0.00%

Start 25-Jul-11 2025-Jul-11

Finish 14-Dec-11 8025-Dec-11

2.78%Flame arrestor 0.00%

0.00%

Start 04-Sep-11 2007-Aug-11

Finish 01-Jan-12 8007-Dec-11

2.78%Vent stack package 0.00%

0.00%

Start 20-Sep-11 2023-Aug-11

Finish 17-Jan-12 8026-Dec-11

3.89%Fire Fighting package 0.00%

0.00%

Start 07-Aug-11 2020-Jul-11

Finish 02-Jan-12 8019-Dec-11

3.33%Safety signs,miscellaneous safety and life saving equipment package 0.00%

0.00%

Start 21-Aug-11 2025-Jul-11

Finish 21-Dec-11 8024-Nov-11

Tuesday, July 05, 2011 Page 5 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 56: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONVENDOR PRINTS REVIEW

0.00% 0.00%18.06%

P&ID's

0.69%Symbols for P & ID instrumentation 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0100 - Single completion wellhead DW001 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0120 - Chemical injection system (Methanol skid) 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0120 -Chem. Injec. Sys. (Hydrate inhibitor skid) 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0120 - Chemical injection system (Corrosion inhibitor) 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0130 - Manifold 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0190 - Delivery system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0230 - Blow-down system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

Tuesday, July 05, 2011 Page 6 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 57: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONP&ID's

0.83%Unit 0300 -Test Multiphase Meter 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0420 -Fuel Gas system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0420 -Fuel Gas system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0470- Main Power Generation Package 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0430- Diesel Fuel system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0480- Diesel Electrical Generation Package 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0730- Dry Firefighting system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.83%Unit 0540- Open Drain system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

Tuesday, July 05, 2011 Page 7 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 58: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONP&ID's

0.69%Unit 0730- Helideck Foam Firefighting system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0520- Service water system 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%Unit 0570- Sanitary Discharge treatment package 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

0.69%TUTU Panel & SSIV 70.00%

70.00%

Start 14-Apr-11 2010-Apr-11

Design 21-Apr-11 5017-Apr-11

Construction 13-Sep-11 3012-Sep-11

70.00% 70.00%15.00%

47.67%Total PROCESS TECHNOLOGY DIVISION 55.58%100.00%

Tuesday, July 05, 2011 Page 8 of 59

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 59: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTDRAWING

3.16%Interconnecting Wiring Diagram 70.00%

70.00%

Start 04-May-11 2026-May-11

Design 11-May-11 5002-Jun-11

Construction 15-Nov-11 3014-Nov-11

1.58%Mechanical-Hook-up Drawing 70.00%

70.00%

Start 20-Apr-11 2019-May-11

Design 27-Apr-11 5026-May-11

Construction 13-Nov-11 3010-Nov-11

1.58%Hydraulic hook-up Drawings 70.00%

70.00%

Start 20-Apr-11 2019-May-11

Design 27-Apr-11 5026-May-11

Construction 13-Nov-11 3010-Nov-11

1.58%Electrical hook-up Drawing 70.00%

0.00%

Start 12-Jul-11 2019-May-11

Design 19-Jul-11 5026-May-11

Construction 13-Nov-11 3010-Nov-11

1.84%Electrical instruments layout 70.00%

70.00%

Start 10-May-11 2005-May-11

Design 16-May-11 5012-May-11

Construction 26-Oct-11 3025-Oct-11

1.32%Hydraulic instruments layouts 70.00%

0.00%

Start 06-Jul-11 2005-May-11

Design 13-Jul-11 5012-May-11

Construction 26-Oct-11 3025-Oct-11

2.37%Electrical instrument cable routing layout 70.00%

70.00%

Start 07-Jun-11 2012-May-11

Design 14-Jun-11 5019-May-11

Construction 02-Nov-11 3001-Nov-11

1.32%Hydraulic instruments Tube Routing layouts 70.00%

0.00%

Start 05-Jul-11 2012-May-11

Design 12-Jul-11 5019-May-11

Construction 02-Nov-11 3001-Nov-11

70.00% 50.00%14.74%

Tuesday, July 05, 2011 Page 9 of 59

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMData'Nes Systems, Release 2.21

Page 60: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTREPORTS / TECHNICAL LIST

2.11%Instrument Index 70.00%

70.00%

Start 10-May-11 2026-Apr-11

Design 16-May-11 5004-May-11

Construction 22-Sep-11 3021-Sep-11

2.11%Instrument cable list 70.00%

70.00%

Start 07-Jun-11 2026-May-11

Design 15-Jun-11 5002-Jun-11

Construction 26-Oct-11 3025-Oct-11

70.00% 70.00%4.21%

MRQ

1.05%Multiphase flow meter MRQ 100.00%

100.00%

Start 07-Apr-11 2003-Apr-11

For inquiry 10-Apr-11 8010-Apr-11

1.05%Electro Hydraulic Well Head panel MRQ 100.00%

100.00%

Start 01-Apr-11 2004-Apr-11

For inquiry 03-Apr-11 8012-Apr-11

1.05%Choke valve MRQ 100.00%

100.00%

Start 01-Apr-11 2006-Apr-11

For inquiry 03-Apr-11 8013-Apr-11

1.05%HIPPS System MRQ 100.00%

100.00%

Start 01-Apr-11 2031-Mar-11

For inquiry 03-Apr-11 8007-Apr-11

1.05%Wing valve MRQ 100.00%

100.00%

Start 01-Apr-11 2006-Apr-11

For inquiry 03-Apr-11 8013-Apr-11

0.92%Loose Instrument MRQ 100.00%

100.00%

Start 01-Jun-11 2018-May-11

For inquiry 06-Jun-11 8025-May-11

0.92%Sand & Corrosion probes MRQ 100.00%

20.00%

Start 20-Jun-11 2025-May-11

For inquiry 26-Jun-11 8001-Jun-11

Tuesday, July 05, 2011 Page 10 of 59

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMData'Nes Systems, Release 2.21

Page 61: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTMRQ

0.92%Instrument & Mechanical bulk materialMRQ 100.00%

100.00%

Start 01-May-11 2026-May-11

For inquiry 03-May-11 8002-Jun-11

0.92%Instrument cable and cable glandsMRQ 100.00%

100.00%

Start 15-Jun-11 2016-May-11

For inquiry 22-Jun-11 8023-May-11

0.92%Inst. Junction Box MRQ 100.00%

100.00%

Start 01-Jun-11 2002-Jun-11

For inquiry 06-Jun-11 8009-Jun-11

0.92%Instrument cable trays MRQ 100.00%

20.00%

Start 19-Jun-11 2024-May-11

For inquiry 26-Jun-11 8031-May-11

100.00% 86.34%10.79%

TER

3.95%Multiphase flow meter TER 100.00%

100.00%

Start 28-Apr-11 2015-May-11

Finish 25-May-11 8012-Jun-11

3.95%Electro Hydraulic Well Head panel TER 100.00%

100.00%

Start 10-Apr-11 2015-May-11

Finish 16-Jun-11 8002-Jun-11

2.63%Choke valve TER 100.00%

20.00%

Start 26-Apr-11 2018-May-11

Finish 05-Jul-11 8012-Jun-11

5.00%HIPPS System TER 100.00%

100.00%

Start 10-Apr-11 2003-May-11

Finish 09-Jun-11 8031-May-11

2.63%Wing valve TER 100.00%

100.00%

Start 02-May-11 2016-May-11

Finish 15-Jun-11 8008-Jun-11

1.84%Loose Instrument TER 20.00%

20.00%

Start 20-Jun-11 2012-Jun-11

Finish 24-Jul-11 8026-Jun-11

Tuesday, July 05, 2011 Page 11 of 59

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMData'Nes Systems, Release 2.21

Page 62: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTTER

2.11%Sand & Corrosion probes TER 20.00%

0.00%

Start 11-Jul-11 2016-Jun-11

Finish 04-Aug-11 8007-Jul-11

2.11%Instrument & Mechanical bulk material TER 20.00%

20.00%

Start 26-May-11 2019-Jun-11

Finish 14-Jul-11 8003-Jul-11

2.11%Instrument cable and cable glandsTER 100.00%

0.00%

Start 10-Jul-11 2006-Jun-11

Finish 01-Aug-11 8020-Jun-11

2.11%Inst. Junction Box TER 20.00%

20.00%

Start 21-Jun-11 2023-Jun-11

Finish 21-Jul-11 8007-Jul-11

2.11%Instrument cable trays TER 20.00%

0.00%

Start 03-Jul-11 2014-Jun-11

Finish 28-Jul-11 8028-Jun-11

73.10% 56.55%30.53%

MRP

1.05%Multiphase flow meter MRP 0.00%

100.00%

Start 16-Jun-11 2010-Jul-11

For Purchase 23-Jun-11 8017-Jul-11

1.05%Electro Hydraulic Well Head panel MRP 0.00%

0.00%

Start 13-Jul-11 2004-Jul-11

For Purchase 14-Jul-11 8011-Jul-11

1.05%Choke valve MRP 0.00%

0.00%

Start 27-Jul-11 2005-Jul-11

For Purchase 02-Aug-11 8012-Jul-11

1.05%HIPPS System MRP 0.00%

0.00%

Start 07-Jul-11 2028-Jun-11

For Purchase 13-Jul-11 8005-Jul-11

1.05%Wing valve MRP 0.00%

0.00%

Start 24-Jul-11 2006-Jul-11

For Purchase 28-Jul-11 8013-Jul-11

Tuesday, July 05, 2011 Page 12 of 59

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMData'Nes Systems, Release 2.21

Page 63: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTMRP

1.05%Loose Instrument MRP 0.00%

0.00%

Start 18-Aug-11 2017-Jul-11

For Purchase 21-Aug-11 8024-Jul-11

1.05%Sand & Corrosion probes MRP 0.00%

0.00%

Start 04-Sep-11 2001-Aug-11

For Purchase 06-Sep-11 8008-Aug-11

0.79%Instrument & Mechanical bulk material MRP 0.00%

0.00%

Start 07-Aug-11 2024-Jul-11

For Purchase 11-Aug-11 8031-Jul-11

0.79%Instrument cable and cable glands MRP 0.00%

0.00%

Start 23-Aug-11 2011-Jul-11

For Purchase 25-Aug-11 8018-Jul-11

0.79%Inst. Junction Box MRP 0.00%

0.00%

Start 17-Aug-11 2028-Jul-11

For Purchase 18-Aug-11 8004-Aug-11

0.79%Instrument cable trays MRP 0.00%

0.00%

Start 24-Aug-11 2014-Jul-11

For Purchase 25-Aug-11 8021-Jul-11

0.00% 10.00%10.53%

VENDOR PRINTS REVIEW

0.79%Instrument & Mechanical bulk material Vendor prints review 0.00%

0.00%

Start 21-Aug-11 2008-Aug-11

Finish 07-Dec-11 8024-Nov-11

1.32%Junction boxes Vendor prints review 0.00%

0.00%

Start 28-Aug-11 2014-Aug-11

Finish 14-Dec-11 8030-Nov-11

3.95%HIPPS Vendor prints review 0.00%

0.00%

Start 24-Jul-11 2013-Jul-11

Finish 01-Mar-12 8022-Feb-12

3.16%Choke valves Vendor prints review 0.00%

0.00%

Start 11-Aug-11 2020-Jul-11

Finish 13-Dec-11 8021-Nov-11

Tuesday, July 05, 2011 Page 13 of 59

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMData'Nes Systems, Release 2.21

Page 64: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTVENDOR PRINTS REVIEW

1.84%Loose instrument Vendor prints review 0.00%

0.00%

Start 04-Sep-11 2001-Aug-11

Finish 18-Dec-11 8017-Nov-11

1.05%Instrument cable trays Vendor prints review 0.00%

0.00%

Start 04-Sep-11 2031-Jul-11

Finish 18-Dec-11 8015-Nov-11

3.42%Electro hydraulic wellhead control panel Vendor prints review 0.00%

0.00%

Start 21-Jul-11 2025-Jul-11

Finish 21-Nov-11 8024-Nov-11

3.16%Wing valves Vendor prints review 0.00%

0.00%

Start 07-Aug-11 2021-Jul-11

Finish 07-Dec-11 8022-Nov-11

1.05%Instrument cable and cable glands Vendor prints review 0.00%

0.00%

Start 28-Aug-11 2026-Jul-11

Finish 28-Dec-11 8028-Nov-11

1.84%Sand & Corrosion probes Vendor prints review 0.00%

0.00%

Start 14-Sep-11 2016-Aug-11

Finish 28-Dec-11 8005-Dec-11

3.68%Multi phase flow meter Vendor prints review 0.00%

0.00%

Start 20-Jul-11 2025-Jul-11

Finish 07-Dec-11 8025-Dec-11

3.95%Actuated valves Vendor prints review 20.00%

20.00%

Start 04-May-11 2004-May-11

Finish 01-Mar-12 8010-Jan-12

2.70% 2.70%29.21%

38.74%Total INSTRUMENTATION & CONTROLS ENGI 47.16%100.00%

Tuesday, July 05, 2011 Page 14 of 59

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMData'Nes Systems, Release 2.21

Page 65: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONDRAWING

1.82%Heli deck plot plan 70.00%

70.00%

Start 01-Apr-11 2017-Apr-11

Design 03-Apr-11 5024-Apr-11

Construction 20-Sep-11 3019-Sep-11

1.82%Main deck plot plan 70.00%

70.00%

Start 01-Apr-11 2017-Apr-11

Design 03-Apr-11 5024-Apr-11

Construction 20-Sep-11 3019-Sep-11

1.64%Cellar deck plot plan 70.00%

70.00%

Start 01-Apr-11 2017-Apr-11

Design 03-Apr-11 5024-Apr-11

Construction 20-Sep-11 3019-Sep-11

1.64%Below cellar deck plot plan 70.00%

70.00%

Start 01-Apr-11 2017-Apr-11

Design 03-Apr-11 5024-Apr-11

Construction 20-Sep-11 3019-Sep-11

1.64%Vent boom plot plan 70.00%

70.00%

Start 01-Apr-11 2017-Apr-11

Design 03-Apr-11 5024-Apr-11

Construction 20-Sep-11 3019-Sep-11

1.27%Looking west elevation 0.00%

0.00%

Start 02-Nov-11 2031-Oct-11

Construction 29-Nov-11 8028-Nov-11

1.27%Looking north elevation 0.00%

0.00%

Start 02-Nov-11 2031-Oct-11

Construction 29-Nov-11 8028-Nov-11

0.73%Helideck piping support plan 0.00%

0.00%

Start 14-Dec-11 2012-Dec-11

Construction 20-Dec-11 8019-Dec-11

0.73%Main deck piping support plan 0.00%

0.00%

Start 14-Dec-11 2012-Dec-11

Construction 20-Dec-11 8019-Dec-11

Tuesday, July 05, 2011 Page 15 of 59

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 66: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONDRAWING

0.73%Cellar deck piping support plan 0.00%

0.00%

Start 14-Dec-11 2012-Dec-11

Construction 20-Dec-11 8019-Dec-11

0.73%Below cellar piping support plan 0.00%

0.00%

Start 14-Dec-11 2012-Dec-11

Construction 20-Dec-11 8019-Dec-11

0.73%Vent boom piping support plan 0.00%

0.00%

Start 14-Dec-11 2012-Dec-11

Construction 20-Dec-11 8019-Dec-11

0.73%Helideck piping support location 0.00%

0.00%

Start 21-Dec-11 2019-Dec-11

Construction 27-Dec-11 8026-Dec-11

0.73%Main deck piping support location 0.00%

0.00%

Start 21-Dec-11 2019-Dec-11

Construction 27-Dec-11 8026-Dec-11

0.73%Cellar deck piping support location 0.00%

0.00%

Start 21-Dec-11 2019-Dec-11

Construction 27-Dec-11 8026-Dec-11

0.73%Below cellar piping support location 0.00%

0.00%

Start 21-Dec-11 2019-Dec-11

Construction 27-Dec-11 8026-Dec-11

0.73%Vent boom piping support location 0.00%

0.00%

Start 21-Dec-11 2019-Dec-11

Construction 27-Dec-11 8026-Dec-11

0.73%Helideck piping penetration location 0.00%

0.00%

Start 28-Dec-11 2026-Dec-11

Construction 03-Jan-12 8002-Jan-12

0.73%Main deck piping penetration location 0.00%

0.00%

Start 28-Dec-11 2026-Dec-11

Construction 03-Jan-12 8002-Jan-12

Tuesday, July 05, 2011 Page 16 of 59

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 67: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONDRAWING

0.73%Cellar deck piping penetration location 0.00%

0.00%

Start 28-Dec-11 2026-Dec-11

Construction 03-Jan-12 8002-Jan-12

0.73%Below cellar piping penetration location 0.00%

0.00%

Start 28-Dec-11 2026-Dec-11

Construction 03-Jan-12 8002-Jan-12

0.73%Vent boom piping penetration location 0.00%

0.00%

Start 28-Dec-11 2026-Dec-11

Construction 03-Jan-12 8002-Jan-12

1.82%Hydrotest maps 0.00%

0.00%

Start 24-Nov-11 2022-Nov-11

Construction 05-Dec-11 8004-Dec-11

25.11% 25.11%23.82%

REPORTS / TECHNICAL LIST

4.55%Line designation table 70.00%

70.00%

Start 23-May-11 2012-May-11

Design 01-Jun-11 5019-May-11

Final 20-Sep-11 3019-Sep-11

70.00% 70.00%4.55%

MRQ

2.73%Piping bulk MRQ 100.00%

100.00%

Start 01-Apr-11 2031-Mar-11

For inquiry 03-Apr-11 8007-Apr-11

1.82%Insulation joint MRQ 100.00%

100.00%

Start 01-Apr-11 2013-Apr-11

For inquiry 11-Apr-11 8020-Apr-11

1.82%Injection fitting MRQ 0.00%

100.00%

Start 08-Apr-11 2028-Jul-11

For inquiry 13-Apr-11 8030-Nov-11

71.43% 100.00%6.36%

Tuesday, July 05, 2011 Page 17 of 59

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 68: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONTER

3.64%Piping bulk TER 100.00%

100.00%

Start 26-Apr-11 2010-May-11

Finish 17-May-11 8031-May-11

2.73%Injection fitting TER 100.00%

0.00%

Start 04-Jul-11 2025-May-11

Finish 24-Jul-11 8015-Jun-11

2.73%Insulation joint Injection fitting TER 100.00%

20.00%

Start 02-Jun-11 2019-May-11

Finish 21-Jul-11 8009-Jun-11

100.00% 46.00%9.09%

MRP

1.82%Piping bulk MRP 20.00%

0.00%

Start 05-Jul-11 2019-Jun-11

For Purchase 07-Jul-11 8026-Jun-11

1.45%Insulation Joint MRP 0.00%

0.00%

Start 14-Aug-11 2010-Jul-11

For Purchase 16-Aug-11 8017-Jul-11

1.45%Injection fitting MRP 0.00%

0.00%

Start 18-Aug-11 2013-Jul-11

For Purchase 21-Aug-11 8020-Jul-11

7.69% 0.00%4.73%

VENDOR PRINTS REVIEW

3.64%Piping bulk Vendor prints review 0.00%

0.00%

Start 20-Jul-11 2004-Jul-11

Finish 07-Dec-11 8004-Dec-11

2.73%Insulation Joint Vendor prints review 0.00%

0.00%

Start 06-Sep-11 2025-Jul-11

Finish 03-Jan-12 8024-Nov-11

2.73%Injection fitting Vendor prints review 0.00%

0.00%

Start 06-Sep-11 2028-Jul-11

Finish 03-Jan-12 8030-Nov-11

Tuesday, July 05, 2011 Page 18 of 59

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 69: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONVENDOR PRINTS REVIEW

4.36%Production Manifold Vendor prints review 20.00%

20.00%

Start 20-Jun-11 2004-May-11

Finish 15-Mar-12 8024-Jan-12

6.49% 6.49%13.45%

GA's

2.55%Helideck piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

2.55%Below helideck piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

2.55%Main deck piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

2.55%Below main deck piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

2.55%Celler deck piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

2.18%Below celler deck piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

2.18%Vent boom piping plan GA 0.00%

0.00%

Start 18-Sep-11 2013-Sep-11

Design 27-Sep-11 5025-Sep-11

Construction 29-Nov-11 3028-Nov-11

0.00% 0.00%17.09%

Tuesday, July 05, 2011 Page 19 of 59

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 70: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONISO's

16.36%Piping isometric drawings package 0.00%

0.00%

Start 31-Oct-11 2027-Oct-11

Final 17-Nov-11 8016-Nov-11

0.00% 0.00%16.36%

Specification

4.55%Piping material classes 100.00%

70.00%

Start 17-May-11 2016-May-11

Design 22-May-11 5023-May-11

Final 14-Jul-11 3013-Jun-11

100.00% 70.00%4.55%

23.76%Total PIPING ENGINEERING DIVISION 28.58%100.00%

Tuesday, July 05, 2011 Page 20 of 59

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 71: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONDRAWING

1.67%Helideck lighting & navigational aids layout 70.00%

70.00%

Start 20-Apr-11 2024-Apr-11

Design 26-Apr-11 5002-May-11

Construction 17-Nov-11 3019-Oct-11

1.67%Main deck lighting & navigational aids layout 70.00%

70.00%

Start 20-Apr-11 2024-Apr-11

Design 26-Apr-11 5002-May-11

Construction 17-Nov-11 3019-Oct-11

1.33%Cellar deck lighting layout 70.00%

70.00%

Start 20-Apr-11 2024-Apr-11

Design 26-Apr-11 5002-May-11

Construction 17-Nov-11 3019-Oct-11

1.33%Below cellar deck lighting layout 70.00%

70.00%

Start 20-Apr-11 2024-Apr-11

Design 26-Apr-11 5002-May-11

Construction 17-Nov-11 3019-Oct-11

1.00%Vent boom lighting layout 70.00%

70.00%

Start 20-Apr-11 2024-Apr-11

Design 26-Apr-11 5002-May-11

Construction 17-Nov-11 3019-Oct-11

1.33%Helideck hazard area classification layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 12-Oct-11 3011-Oct-11

1.33%Main deck hazard area classification layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 12-Oct-11 3011-Oct-11

1.33%Cellar deck hazard area classification layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 12-Oct-11 3011-Oct-11

Tuesday, July 05, 2011 Page 21 of 59

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 72: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONDRAWING

1.33%Below cellar deck hazard area classification layout 70.00%

70.00%

Start 13-May-11 2010-May-11

Design 19-May-11 5017-May-11

Construction 12-Oct-11 3011-Oct-11

1.33%Vent boom hazard area classification layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 19-May-11 5017-May-11

Construction 12-Oct-11 3011-Oct-11

1.00%Helideck earthing layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 02-Oct-11 3029-Sep-11

1.00%Main deck earthing layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 02-Oct-11 3029-Sep-11

1.00%Cellar deck earthing layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 02-Oct-11 3029-Sep-11

1.00%Below cellar deck earthing layout 70.00%

70.00%

Start 10-May-11 2010-May-11

Design 16-May-11 5017-May-11

Construction 02-Oct-11 3029-Sep-11

0.83%Helideck cable routing layout 70.00%

70.00%

Start 15-Jun-11 2019-May-11

Design 23-Jun-11 5026-May-11

Construction 04-Oct-11 3003-Oct-11

0.83%Main deck cable routing layout 70.00%

70.00%

Start 15-Jun-11 2019-May-11

Design 23-Jun-11 5026-May-11

Construction 04-Oct-11 3003-Oct-11

Tuesday, July 05, 2011 Page 22 of 59

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 73: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONDRAWING

0.83%Cellar deck cable routing layout 70.00%

70.00%

Start 15-Jun-11 2019-May-11

Design 23-Jun-11 5026-May-11

Construction 04-Oct-11 3003-Oct-11

0.83%Below cellar deck cable routing layout 70.00%

70.00%

Start 15-Jun-11 2019-May-11

Design 23-Jun-11 5026-May-11

Construction 04-Oct-11 3003-Oct-11

0.83%Lighting block diagram 0.00%

0.00%

Start 01-Nov-11 2021-Oct-11

Construction 24-Nov-11 8026-Oct-11

2.00%Single line diagram 70.00%

0.00%

Start 14-Jul-11 2023-May-11

Design 21-Jul-11 5030-May-11

Construction 19-Oct-11 3018-Oct-11

1.67%E&I module equipment layout 0.00%

0.00%

Start 08-Sep-11 2003-Jul-11

Design 08-Sep-11 5003-Jul-11

Construction 29-Jan-12 3025-Nov-11

2.33%Interconnection & wiring diagram 70.00%

70.00%

Start 03-May-11 2017-Jun-11

Design 11-May-11 5024-Jun-11

Construction 05-Oct-11 3004-Oct-11

1.00%Cable sections 20.00%

0.00%

Start 26-Jul-11 2022-Jun-11

Design 21-Aug-11 5029-Jun-11

Construction 05-Oct-11 3004-Oct-11

62.20% 56.65%28.83%

REPORTS / TECHNICAL LIST

1.33%Electrical cable list 70.00%

0.00%

Start 10-Jul-11 2008-Jun-11

Design 17-Jul-11 5015-Jun-11

Construction 04-Oct-11 3003-Oct-11

Tuesday, July 05, 2011 Page 23 of 59

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 74: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONREPORTS / TECHNICAL LIST

2.33%Power system study 70.00%

0.00%

Start 30-Jun-11 2015-May-11

Design 14-Jul-11 5024-May-11

Final 10-Oct-11 3009-Oct-11

70.00% 0.00%3.67%

MRQ

2.00%Electrical cable trays MRQ 100.00%

100.00%

Start 01-Apr-11 2024-Apr-11

For inquiry 03-Apr-11 8002-May-11

2.00%Electrical cables MRQ 100.00%

100.00%

Start 01-Apr-11 2002-May-11

For inquiry 03-Apr-11 8009-May-11

2.00%Navigational aids system MRQ 100.00%

100.00%

Start 24-Apr-11 2009-May-11

For inquiry 27-Apr-11 8016-May-11

2.00%Lighting material MRQ 100.00%

100.00%

Start 15-Jun-11 2026-May-11

For inquiry 22-Jun-11 8002-Jun-11

2.00%Earthing material MRQ 100.00%

100.00%

Start 29-May-11 2030-May-11

For inquiry 20-Jun-11 8006-Jun-11

100.00% 100.00%10.00%

TER

8.33%Navigational aids system TER 20.00%

20.00%

Start 16-May-11 2030-May-11

Finish 10-Jul-11 8027-Jun-11

4.33%Electrical cables TER 100.00%

100.00%

Start 05-Apr-11 2023-May-11

Finish 10-Apr-11 8020-Jun-11

4.33%Electrical cable trays TER 100.00%

100.00%

Start 05-Apr-11 2022-May-11

Finish 10-Apr-11 8019-Jun-11

Tuesday, July 05, 2011 Page 24 of 59

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 75: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONTER

4.33%Lighting material TER 20.00%

0.00%

Start 10-Jul-11 2008-Jun-11

Finish 04-Aug-11 8006-Jul-11

4.33%Earthing material TER 20.00%

0.00%

Start 10-Jul-11 2020-Jun-11

Finish 04-Aug-11 8018-Jul-11

47.01% 40.26%25.67%

MRP

2.00%Electrical cables MRP 0.00%

0.00%

Start 10-Jul-11 2013-Jul-11

For Purchase 14-Jul-11 8020-Jul-11

2.00%Navigational aids system MRP 0.00%

0.00%

Start 07-Aug-11 2019-Jul-11

For Purchase 08-Aug-11 8026-Jul-11

2.00%Electrical Cable trays MRP 0.00%

0.00%

Start 30-Jun-11 2010-Jul-11

For Purchase 30-Jun-11 8017-Jul-11

2.00%Lighting material MRP 0.00%

0.00%

Start 28-Aug-11 2027-Jul-11

For Purchase 04-Sep-11 8001-Aug-11

2.00%Earthing material MRP 0.00%

0.00%

Start 28-Aug-11 2008-Aug-11

For Purchase 06-Sep-11 8015-Aug-11

0.00% 0.00%10.00%

VENDOR PRINTS REVIEW

2.67%Earthing Vendor prints review 0.00%

0.00%

Start 11-Sep-11 2023-Aug-11

Finish 11-Dec-11 8028-Nov-11

2.50%Lighting material Vendor prints review 0.00%

0.00%

Start 11-Sep-11 2011-Aug-11

Finish 08-Jan-12 8014-Dec-11

Tuesday, July 05, 2011 Page 25 of 59

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 76: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONVENDOR PRINTS REVIEW

2.50%Electrical Cable trays Vendor prints review 0.00%

0.00%

Start 18-Jul-11 2025-Jul-11

Finish 02-Nov-11 8024-Nov-11

2.50%Electrical Cables Vendor prints review 0.00%

0.00%

Start 21-Jul-11 2001-Aug-11

Finish 21-Nov-11 8004-Dec-11

5.00%Navigation aids system Vendor prints review 0.00%

0.00%

Start 16-Aug-11 2002-Aug-11

Finish 18-Dec-11 8005-Dec-11

6.67%E&I Module Vendor prints review 20.00%

20.00%

Start 03-May-11 2004-May-11

Finish 29-Mar-12 8024-Jan-12

6.11% 6.11%21.83%

38.00%Total ELECTRICAL ENGINEERING DIVISION 43.90%100.00%

Tuesday, July 05, 2011 Page 26 of 59

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 77: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGOFFSHORE ENGINEERING DIVISIONDRAWING

10.00%Cable trays supports for deck plan at el. +9700 T.O.S. 0.00%

0.00%

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

Construction 01-Dec-11 3001-Dec-11

10.00%Cable trays supports for cellar deck plan at el. +13500 T.O.S. 0.00%

0.00%

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

Construction 01-Dec-11 3001-Dec-11

10.00%Cable trays supports for mezzanine deck plan at el. +16000 T.O.S. 0.00%

0.00%

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

Construction 01-Dec-11 3001-Dec-11

10.00%Cable trays supports for main deck plan at el. +20500 T.O.S. 0.00%

0.00%

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

Construction 01-Dec-11 3001-Dec-11

10.00%Cable trays supports for Helideck plan at el. +26500 T.O.S. 0.00%

0.00%

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

Construction 01-Dec-11 3001-Dec-11

0.00% 0.00%50.00%

MRQ

10.00%Survival module MRQ 100.00%

100.00%

Start 01-Apr-11 2024-Apr-11

For inquiry 03-Apr-11 8028-Apr-11

100.00% 100.00%10.00%

TER

15.00%Survival module TER 20.00%

20.00%

Start 22-May-11 2001-Jun-11

Finish 03-Jul-11 8028-Jun-11

20.00% 20.00%15.00%

Tuesday, July 05, 2011 Page 27 of 59

Layout No. 1* Weights of Activities are calculated relative to (OFFSHORE ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 78: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGOFFSHORE ENGINEERING DIVISIONMRP

5.00%Survival module MRP 0.00%

0.00%

Start 25-Jul-11 2020-Jul-11

For Purchase 31-Jul-11 8026-Jul-11

0.00% 0.00%5.00%

VENDOR PRINTS REVIEW

20.00%Survival module vendor prints review 20.00%

0.00%

Start 04-Aug-11 2031-Mar-11

Finish 20-Sep-11 8026-Jun-11

20.00% 0.00%20.00%

13.00%Total OFFSHORE ENGINEERING DIVISION 17.00%100.00%

Tuesday, July 05, 2011 Page 28 of 59

Layout No. 1* Weights of Activities are calculated relative to (OFFSHORE ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 79: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGMECHANICAL ENGINEERING DEPARTMENTDRAWING

6.00%Material selection guide 70.00%

70.00%

Start 10-May-11 2003-Jun-11

Design 17-May-11 5018-Jun-11

Construction 20-Sep-11 3019-Sep-11

70.00% 70.00%6.00%

REPORTS / TECHNICAL LIST

6.67%Motor load list 50.00%

70.00%

Start 10-Apr-11 2004-Apr-11

1st issue 14-Apr-11 3019-Apr-11

2nd issue 23-Jun-11 2021-Jul-11

Final 25-Sep-11 3022-Sep-11

7.78%Maintenance and handling study 100.00%

50.00%

Start 02-Jul-11 2002-May-11

Design 09-Jun-11 5009-May-11

Final 26-Jul-11 3008-Jun-11

76.92% 59.23%14.44%

MRQ

4.33%Mono rail MRQ 0.00%

0.00%

Start 21-Aug-11 2021-Jul-11

For inquiry 25-Aug-11 8028-Jul-11

4.00%Turret crane MRQ 100.00%

100.00%

Start 01-Apr-11 2006-Apr-11

For inquiry 03-Apr-11 8013-Apr-11

4.00%Service water pump MRQ 100.00%

100.00%

Start 01-Apr-11 2018-Apr-11

For inquiry 03-Apr-11 8025-Apr-11

64.86% 64.86%12.33%

TER

10.00%Turret crane TER 100.00%

100.00%

Start 10-Apr-11 2015-May-11

Finish 04-May-11 8012-Jun-11

Tuesday, July 05, 2011 Page 29 of 59

Layout No. 1* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 80: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGMECHANICAL ENGINEERING DEPARTMENTTER

10.00%Service water pump TER 100.00%

20.00%

Start 28-Apr-11 2017-May-11

Finish 03-Jul-11 8007-Jun-11

5.56%Monorail crane TER 0.00%

0.00%

Start 14-Sep-11 2011-Aug-11

Finish 04-Oct-11 8006-Sep-11

78.26% 46.96%25.56%

MRP

3.33%Turret crane MRP 0.00%

100.00%

Start 16-Jun-11 2004-Jul-11

For Purchase 16-Jun-11 8011-Jul-11

3.33%Service water pump MRP 0.00%

0.00%

Start 26-Jul-11 2011-Jul-11

For Purchase 28-Jul-11 8018-Jul-11

3.33%Monorail crane MRP 0.00%

0.00%

Start 03-Nov-11 2004-Oct-11

For Purchase 13-Nov-11 8010-Oct-11

0.00% 33.33%10.00%

VENDOR PRINTS REVIEW

4.44%Service water pump Vendor prints review 0.00%

0.00%

Start 14-Aug-11 2026-Jul-11

Finish 14-Dec-11 8028-Nov-11

7.78%Turret crane crane Vendor prints review 0.00%

0.00%

Start 13-Jul-11 2019-Jul-11

Finish 07-Dec-11 8019-Dec-11

7.78%Micro Turbine Vendor prints review 20.00%

20.00%

Start 24-May-11 2004-May-11

Finish 15-Mar-12 8024-Jan-12

7.78%Emergency GeneratorVendor prints review 20.00%

20.00%

Start 15-Jun-11 2004-May-11

Finish 29-Mar-12 8024-Jan-12

Tuesday, July 05, 2011 Page 30 of 59

Layout No. 1* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 81: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGMECHANICAL ENGINEERING DEPARTMENTVENDOR PRINTS REVIEW

3.89%Monorail crane Vendor prints review 0.00%

0.00%

Start 03-Nov-11 2004-Oct-11

Finish 01-Mar-12 8001-Feb-12

9.82% 9.82%31.67%

39.20%Total MECHANICAL ENGINEERING DEPARTME 46.42%100.00%

Tuesday, July 05, 2011 Page 31 of 59

Layout No. 1* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 82: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPRESSURE VESSELS ENGINEERING DEPARTMENTVENDOR PRINTS REVIEW

100.00%Pressure vessels 20.00%

20.00%

Start 10-May-11 2010-May-11

Finish 16-Jan-12 8016-Jan-12

20.00% 20.00%100.00%

20.00%Total PRESSURE VESSELS ENGINEERING DE 20.00%100.00%

Tuesday, July 05, 2011 Page 32 of 59

Layout No. 1* Weights of Activities are calculated relative to (PRESSURE VESSELS ENGINEERING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 83: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

3.26%Safety equipment and life saving 60.00%

40.00%

RFQ 03-Apr-11 2012-Apr-11

Tech. offers open 05-Apr-11 2026-Apr-11

Comm. offers open 17-Jul-11 2012-Jun-11

Bid tab 24-Jul-11 1026-Jun-11

F.O.C. 04-Aug-11 2010-Jul-11

P.O. 18-Aug-11 1024-Jul-11

3.26%Flame arrestor 60.00%

40.00%

RFQ 21-Apr-11 2027-Apr-11

Tech. offers open 02-Jun-11 2019-May-11

Comm. offers open 26-Jul-11 2023-Jun-11

Bid tab 02-Aug-11 1007-Jul-11

F.O.C. 07-Aug-11 2021-Jul-11

P.O. 11-Aug-11 1004-Aug-11

4.19%Chemical injection package 60.00%

70.00%

RFQ 03-Apr-11 2006-Apr-11

Tech. offers open 18-Apr-11 2027-Apr-11

Comm. offers open 12-Jun-11 2019-Jun-11

Bid tab 16-Jun-11 1003-Jul-11

F.O.C. 30-Jun-11 2010-Jul-11

P.O. 10-Jul-11 1024-Jul-11

3.49%Fire Fighting package 60.00%

40.00%

RFQ 03-Apr-11 2013-Apr-11

Tech. offers open 26-Apr-11 2026-Apr-11

Comm. offers open 10-Jul-11 2014-Jun-11

Bid tab 14-Jul-11 1028-Jun-11

F.O.C. 20-Jul-11 2004-Jul-11

P.O. 24-Jul-11 1018-Jul-11

3.26%Vent stack tips 40.00%

40.00%

RFQ 09-May-11 2009-May-11

Tech. offers open 01-Jun-11 2006-Jun-11

Comm. offers open 02-Aug-11 2006-Jul-11

Bid tab 10-Aug-11 1020-Jul-11

F.O.C. 21-Aug-11 2003-Aug-11

P.O. 24-Aug-11 1017-Aug-11

Tuesday, July 05, 2011 Page 33 of 59

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 84: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

3.73%Piping bulk 90.00%

90.00%

RFQ 03-Apr-11 2007-Apr-11

Tech. offers open 05-Apr-11 2028-Apr-11

Comm. offers open 12-Jun-11 2030-May-11

Bid tab 15-Jun-11 1013-Jun-11

F.O.C. 22-Jun-11 2019-Jun-11

P.O. 07-Jul-11 1003-Jul-11

3.26%Insulation Joint 60.00%

40.00%

RFQ 11-Apr-11 2020-Apr-11

Tech. offers open 30-May-11 2019-May-11

Comm. offers open 27-Jul-11 2012-Jun-11

Bid tab 04-Aug-11 1026-Jun-11

F.O.C. 14-Aug-11 2010-Jul-11

P.O. 17-Aug-11 1024-Jul-11

3.26%Injection fitting 60.00%

20.00%

RFQ 13-Apr-11 2024-Apr-11

Tech. offers open 04-Jul-11 2023-May-11

Comm. offers open 01-Aug-11 2015-Jun-11

Bid tab 08-Aug-11 1029-Jun-11

F.O.C. 18-Aug-11 2013-Jul-11

P.O. 23-Aug-11 1027-Jul-11

3.49%Earthing material 40.00%

20.00%

RFQ 21-Jun-11 2006-Jun-11

Tech. offers open 07-Jul-11 2020-Jun-11

Comm. offers open 10-Aug-11 2018-Jul-11

Bid tab 21-Aug-11 1001-Aug-11

F.O.C. 25-Aug-11 2008-Aug-11

P.O. 15-Sep-11 1024-Aug-11

3.49%Lighting material 40.00%

20.00%

RFQ 22-Jun-11 2025-May-11

Tech. offers open 07-Jul-11 2008-Jun-11

Comm. offers open 10-Aug-11 2006-Jul-11

Bid tab 21-Aug-11 1020-Jul-11

F.O.C. 25-Aug-11 2027-Jul-11

P.O. 13-Sep-11 1022-Aug-11

Tuesday, July 05, 2011 Page 34 of 59

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 85: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

3.73%Electrical Cable trays 60.00%

90.00%

RFQ 03-Apr-11 2002-May-11

Tech. offers open 05-Apr-11 2016-May-11

Comm. offers open 15-May-11 2019-Jun-11

Bid tab 20-May-11 1003-Jul-11

F.O.C. 30-May-11 2010-Jul-11

P.O. 07-Jul-11 1024-Jul-11

3.49%Electrical Cables 60.00%

70.00%

RFQ 03-Apr-11 2009-May-11

Tech. offers open 05-Apr-11 2023-May-11

Comm. offers open 07-Jun-11 2022-Jun-11

Bid tab 15-Jun-11 1006-Jul-11

F.O.C. 03-Jul-11 2013-Jul-11

P.O. 10-Jul-11 1027-Jul-11

3.49%Navigation aids system 40.00%

40.00%

RFQ 28-Apr-11 2016-May-11

Tech. offers open 16-May-11 2030-May-11

Comm. offers open 17-Jul-11 2027-Jun-11

Bid tab 26-Jul-11 1011-Jul-11

F.O.C. 01-Aug-11 2018-Jul-11

P.O. 10-Aug-11 1002-Aug-11

3.49%Instrument & Mechanical bulk material 40.00%

40.00%

RFQ 04-May-11 2005-Jun-11

Tech. offers open 26-May-11 2019-Jun-11

Comm. offers open 21-Jul-11 2003-Jul-11

Bid tab 31-Jul-11 1017-Jul-11

F.O.C. 04-Aug-11 2024-Jul-11

P.O. 18-Aug-11 1007-Aug-11

3.49%Inst. Junction Box 40.00%

40.00%

RFQ 07-Jun-11 2009-Jun-11

Tech. offers open 20-Jun-11 2023-Jun-11

Comm. offers open 27-Jul-11 2007-Jul-11

Bid tab 07-Aug-11 1021-Jul-11

F.O.C. 17-Aug-11 2028-Jul-11

P.O. 21-Aug-11 1011-Aug-11

Tuesday, July 05, 2011 Page 35 of 59

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 86: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

4.19%HIPPS 70.00%

70.00%

RFQ 03-Apr-11 2007-Apr-11

Tech. offers open 05-Apr-11 2028-Apr-11

Comm. offers open 16-Jun-11 2031-May-11

Bid tab 23-Jun-11 1014-Jun-11

F.O.C. 06-Jul-11 2028-Jun-11

P.O. 14-Jul-11 1012-Jul-11

3.73%Choke valves 60.00%

40.00%

RFQ 03-Apr-11 2013-Apr-11

Tech. offers open 26-Apr-11 2012-May-11

Comm. offers open 12-Jul-11 2014-Jun-11

Bid tab 20-Jul-11 1028-Jun-11

F.O.C. 26-Jul-11 2005-Jul-11

P.O. 09-Aug-11 1019-Jul-11

3.45%Loose instrument 40.00%

40.00%

RFQ 07-Jun-11 2029-May-11

Tech. offers open 20-Jun-11 2012-Jun-11

Comm. offers open 01-Aug-11 2026-Jun-11

Bid tab 10-Aug-11 1010-Jul-11

F.O.C. 21-Aug-11 2017-Jul-11

P.O. 25-Aug-11 1031-Jul-11

3.49%Instrument cable trays 40.00%

0.00%

RFQ 27-Jun-11 2031-May-11

Tech. offers open 04-Jul-11 2014-Jun-11

Comm. offers open 07-Aug-11 2030-Jun-11

Bid tab 16-Aug-11 1014-Jul-11

F.O.C. 24-Aug-11 2014-Jul-11

P.O. 29-Aug-11 1028-Jul-11

3.54%Electro hydraulic wellhead control panel 70.00%

40.00%

RFQ 05-Apr-11 2014-Apr-11

Tech. offers open 05-Apr-11 2015-May-11

Comm. offers open 30-Jun-11 2006-Jun-11

Bid tab 06-Jul-11 1020-Jun-11

F.O.C. 12-Jul-11 2004-Jul-11

P.O. 18-Jul-11 1014-Jul-11

Tuesday, July 05, 2011 Page 36 of 59

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 87: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

3.54%Wing valves 70.00%

40.00%

RFQ 03-Apr-11 2013-Apr-11

Tech. offers open 02-May-11 2012-May-11

Comm. offers open 03-Jul-11 2008-Jun-11

Bid tab 10-Jul-11 1022-Jun-11

F.O.C. 21-Jul-11 2006-Jul-11

P.O. 04-Aug-11 1020-Jul-11

3.49%Instrument cable and cable glands 60.00%

20.00%

RFQ 23-Jun-11 2023-May-11

Tech. offers open 07-Jul-11 2006-Jun-11

Comm. offers open 07-Aug-11 2020-Jun-11

Bid tab 16-Aug-11 1004-Jul-11

F.O.C. 23-Aug-11 2011-Jul-11

P.O. 28-Aug-11 1025-Jul-11

3.49%Sand & Corrosion probes 40.00%

0.00%

RFQ 27-Jun-11 2002-Jun-11

Tech. offers open 10-Jul-11 2016-Jun-11

Comm. offers open 11-Aug-11 2011-Jul-11

Bid tab 23-Aug-11 1025-Jul-11

F.O.C. 29-Aug-11 2001-Aug-11

P.O. 11-Sep-11 1015-Aug-11

3.73%Multi phase flow meter 60.00%

90.00%

RFQ 10-Apr-11 2010-Apr-11

Tech. offers open 28-Apr-11 2009-May-11

Comm. offers open 09-Jun-11 2012-Jun-11

Bid tab 13-Jun-11 1026-Jun-11

F.O.C. 16-Jun-11 2010-Jul-11

P.O. 03-Jul-11 1024-Jul-11

3.49%Service water pump 60.00%

40.00%

RFQ 03-Apr-11 2025-Apr-11

Tech. offers open 28-Apr-11 2017-May-11

Comm. offers open 10-Jul-11 2013-Jun-11

Bid tab 18-Jul-11 1027-Jun-11

F.O.C. 25-Jul-11 2011-Jul-11

P.O. 02-Aug-11 1025-Jul-11

Tuesday, July 05, 2011 Page 37 of 59

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 88: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

4.19%Turret crane crane 60.00%

100.00%

RFQ 03-Apr-11 2013-Apr-11

Tech. offers open 10-Apr-11 2012-May-11

Comm. offers open 11-May-11 2012-Jun-11

Bid tab 03-May-11 1026-Jun-11

F.O.C. 29-May-11 2010-Jul-11

P.O. 21-Jun-11 1018-Jul-11

3.49%Monorail crane 0.00%

0.00%

RFQ 28-Jul-11 2028-Jul-11

Tech. offers open 11-Aug-11 2011-Aug-11

Comm. offers open 06-Sep-11 2006-Sep-11

Bid tab 20-Sep-11 1020-Sep-11

F.O.C. 04-Oct-11 2004-Oct-11

P.O. 17-Oct-11 1017-Oct-11

3.73%Survival module 40.00%

40.00%

RFQ 03-Apr-11 2002-May-11

Tech. offers open 22-May-11 2031-May-11

Comm. offers open 10-Jul-11 2029-Jun-11

Bid tab 18-Jul-11 1013-Jul-11

F.O.C. 24-Jul-11 2019-Jul-11

P.O. 07-Aug-11 1002-Aug-11

53.17% 44.73%100.00%

44.73%Total FOREIGN PURCHASING DEPARTMENT 53.17%100.00%

Tuesday, July 05, 2011 Page 38 of 59

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 89: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESEXPEDITING DEPART.COMMODITIES ONE BY ONE

1.86%Safety equipment and life saving 0.00%

0.00%

Start 04-Aug-11 1010-Jul-11

Receiv. Supp. Key 25-Sep-11 2029-Aug-11

Place Main Mat. S/ 17-Oct-11 1018-Sep-11

Receiv. Main Mat.s 13-Dec-11 2017-Nov-11

Fabrication Finish 01-Jan-12 4007-Dec-11

1.86%Flame arrestor 0.00%

0.00%

Start 11-Aug-11 1021-Jul-11

Receiv. Supp. Key 10-Oct-11 2009-Sep-11

Place Main Mat. S/ 26-Oct-11 1029-Sep-11

Receiv. Main Mat.s 27-Nov-11 2029-Oct-11

Fabrication Finish 26-Dec-11 4028-Nov-11

4.66%Chemical injection package 0.00%

0.00%

Start 05-Jul-11 1010-Jul-11

Receiv. Supp. Key 11-Sep-11 2018-Sep-11

Place Main Mat. S/ 14-Sep-11 1023-Sep-11

Receiv. Main Mat.s 20-Nov-11 2027-Nov-11

Fabrication Finish 27-Dec-11 4006-Jan-12

3.73%Fire Fighting package 0.00%

0.00%

Start 20-Jul-11 1005-Jul-11

Receiv. Supp. Key 19-Sep-11 2003-Sep-11

Place Main Mat. S/ 09-Oct-11 1023-Sep-11

Receiv. Main Mat.s 24-Nov-11 2012-Nov-11

Fabrication Finish 04-Jan-12 4031-Dec-11

1.86%Vent stack tips 0.00%

0.00%

Start 05-Sep-11 1008-Aug-11

Receiv. Supp. Key 06-Nov-11 2007-Oct-11

Place Main Mat. S/ 24-Nov-11 1027-Oct-11

Fabrication Finish 02-Jan-12 4006-Dec-11

Receiv. Main Mat.s 03-Jan-12 2006-Dec-11

3.50%Piping bulk 20.00%

0.00%

Start 26-Jun-11 2019-Jun-11

Fabrication Finish 10-Jan-12 8005-Jan-12

Tuesday, July 05, 2011 Page 39 of 59

Layout No. 1* Weights of Activities are calculated relative to (EXPEDITING DEPART.)Data'Nes Systems, Release 2.21

Page 90: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESEXPEDITING DEPART.COMMODITIES ONE BY ONE

1.86%Insulation Joint 0.00%

0.00%

Start 22-Aug-11 1010-Jul-11

Receiv. Supp. Key 23-Oct-11 2008-Sep-11

Place Main Mat. S/ 31-Oct-11 1018-Sep-11

Receiv. Main Mat.s 30-Nov-11 2018-Oct-11

Fabrication Finish 18-Jan-12 4007-Dec-11

1.86%Injection fitting 0.00%

0.00%

Start 18-Aug-11 1013-Jul-11

Receiv. Supp. Key 23-Oct-11 2011-Sep-11

Place Main Mat. S/ 31-Oct-11 1021-Sep-11

Receiv. Main Mat.s 30-Nov-11 2021-Oct-11

Fabrication Finish 18-Jan-12 4010-Dec-11

1.86%Earthing material 0.00%

0.00%

Start 25-Aug-11 2008-Aug-11

Fabrication Finish 26-Dec-11 8026-Dec-11

2.33%Lighting material 0.00%

0.00%

Start 24-Aug-11 2027-Jul-11

Fabrication Finish 23-Dec-11 8014-Dec-11

1.86%Electrical Cable trays 0.00%

0.00%

Start 06-Jul-11 2010-Jul-11

Fabrication Finish 02-Oct-11 8018-Oct-11

2.33%Electrical Cables 0.00%

0.00%

Start 06-Jul-11 2017-Jul-11

Fabrication Finish 22-Nov-11 8004-Dec-11

3.73%Navigation aids system 0.00%

0.00%

Start 01-Aug-11 1018-Jul-11

Receiv. Supp. Key 27-Sep-11 2016-Sep-11

Place Main Mat. S/ 20-Oct-11 1006-Oct-11

Receiv. Main Mat.s 09-Nov-11 2026-Oct-11

Fabrication Finish 18-Dec-11 4005-Dec-11

1.86%Instrument & Mechanical bulk material 0.00%

0.00%

Start 04-Aug-11 2024-Jul-11

Fabrication Finish 05-Nov-11 8001-Nov-11

Tuesday, July 05, 2011 Page 40 of 59

Layout No. 1* Weights of Activities are calculated relative to (EXPEDITING DEPART.)Data'Nes Systems, Release 2.21

Page 91: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESEXPEDITING DEPART.COMMODITIES ONE BY ONE

1.86%Inst. Junction Box 0.00%

0.00%

Start 17-Aug-11 2028-Jul-11

Finish 09-Nov-11 8005-Nov-11

4.66%HIPPS 0.00%

0.00%

Start 07-Jul-11 1028-Jun-11

Receiv. Supp. Key 06-Nov-11 2026-Oct-11

Place Main Mat. S/ 24-Nov-11 1015-Nov-11

Receiv. Main Mat.s 02-Feb-12 2024-Jan-12

Fabrication Finish 17-Mar-12 4024-Mar-12

3.73%Choke valves 0.00%

0.00%

Start 27-Jul-11 1005-Jul-11

Receiv. Supp. Key 24-Nov-11 2002-Nov-11

Place Main Mat. S/ 14-Dec-11 1022-Nov-11

Receiv. Main Mat.s 22-Feb-12 2031-Jan-12

Fabrication Finish 21-Apr-12 4031-Mar-12

1.86%Loose instrument 0.00%

0.00%

Start 15-Aug-11 2017-Jul-11

Fabrication Finish 20-Feb-12 8013-Jan-12

1.86%Instrument cable trays 0.00%

0.00%

Start 24-Aug-11 2014-Jul-11

Fabrication Finish 18-Nov-11 8022-Oct-11

3.73%Electro hydraulic wellhead control panel 0.00%

0.00%

Start 12-Jul-11 1010-Jul-11

Receiv. Supp. Key 04-Oct-11 2008-Oct-11

Place Main Mat. S/ 03-Nov-11 1007-Nov-11

Receiv. Main Mat.s 13-Dec-11 2017-Dec-11

Fabrication Finish 01-Jan-12 4006-Jan-12

3.26%Wing valves 0.00%

0.00%

Start 24-Jul-11 1006-Jul-11

Receiv. Supp. Key 20-Oct-11 2004-Oct-11

Place Main Mat. S/ 21-Nov-11 1003-Nov-11

Receiv. Main Mat.s 29-Dec-11 2013-Dec-11

Fabrication Finish 16-Apr-12 4001-Apr-12

1.86%Instrument cable and cable glands 0.00%

0.00%

Start 14-Aug-11 2011-Jul-11

Fabrication Finish 08-Nov-11 8028-Nov-11

Tuesday, July 05, 2011 Page 41 of 59

Layout No. 1* Weights of Activities are calculated relative to (EXPEDITING DEPART.)Data'Nes Systems, Release 2.21

Page 92: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESEXPEDITING DEPART.COMMODITIES ONE BY ONE

1.86%Sand & Corrosion probes 0.00%

0.00%

Start 30-Aug-11 1001-Aug-11

Receiv. Supp. Key 27-Oct-11 2030-Sep-11

Place Main Mat. S/ 28-Nov-11 1030-Oct-11

Receiv. Main Mat.s 07-Jan-12 2009-Dec-11

Fabrication Finish 08-Jan-12 4029-Dec-11

3.73%Multi phase flow meter 0.00%

10.00%

Start 20-Jun-11 1010-Jul-11

Receiv. Supp. Key 12-Sep-11 2028-Sep-11

Place Main Mat. S/ 20-Sep-11 1008-Oct-11

Receiv. Main Mat.s 09-Nov-11 2027-Nov-11

Fabrication Finish 21-Dec-11 4006-Jan-12

3.26%Service water pump 0.00%

0.00%

Start 28-Jul-11 1011-Jul-11

Receiv. Supp. Key 06-Oct-11 2019-Sep-11

Place Main Mat. S/ 26-Oct-11 1009-Oct-11

Receiv. Main Mat.s 05-Dec-11 2018-Nov-11

Fabrication Finish 14-Dec-11 4028-Nov-11

4.66%Turret crane crane 0.00%

10.00%

Start 21-Jun-11 1010-Jul-11

Receiv. Supp. Key 27-Sep-11 2001-Nov-11

Place Main Mat. S/ 09-Oct-11 1011-Nov-11

Receiv. Main Mat.s 18-Dec-11 2020-Jan-12

Fabrication Finish 19-Feb-12 4029-Feb-12

1.86%Monorail crane 0.00%

0.00%

Start 04-Oct-11 1004-Oct-11

Receiv. Supp. Key 13-Dec-11 2013-Dec-11

Place Main Mat. S/ 23-Dec-11 1023-Dec-11

Receiv. Main Mat.s 12-Jan-12 2012-Jan-12

Fabrication Finish 01-Feb-12 4001-Feb-12

3.26%Survival module 0.00%

0.00%

Start 28-Jul-11 1011-Jul-11

Receiv. Supp. Key 26-Oct-11 2009-Oct-11

Place Main Mat. S/ 15-Nov-11 1029-Oct-11

Fabrication Finish 14-Dec-11 4028-Nov-11

Receiv. Main Mat.s 25-Dec-11 2008-Dec-11

Tuesday, July 05, 2011 Page 42 of 59

Layout No. 1* Weights of Activities are calculated relative to (EXPEDITING DEPART.)Data'Nes Systems, Release 2.21

Page 93: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESEXPEDITING DEPART.COMMODITIES ONE BY ONE

4.66%Production Manifold 10.00%

10.00%

Start 24-May-11 1019-Apr-11

Receiv. Supp. Key 17-Aug-11 2017-Aug-11

Place Main Mat. S/ 27-Aug-11 1027-Aug-11

Receiv. Main Mat.s 15-Nov-11 2015-Nov-11

Fabrication Finish 15-Dec-11 4015-Dec-11

4.66%E&I Module 10.00%

10.00%

Start 03-May-11 1019-Apr-11

Receiv. Supp. Key 07-Sep-11 2017-Aug-11

Place Main Mat. S/ 27-Aug-11 1027-Aug-11

Receiv. Main Mat.s 15-Nov-11 2015-Nov-11

Fabrication Finish 15-Dec-11 4015-Dec-11

4.66%Actuated valves 10.00%

10.00%

Start 19-Apr-11 1019-Apr-11

Receiv. Supp. Key 05-Sep-11 2017-Aug-11

Place Main Mat. S/ 06-Sep-11 1006-Sep-11

Receiv. Main Mat.s 15-Nov-11 2015-Nov-11

Fabrication Finish 15-Dec-11 4015-Dec-11

4.66%Emergency Generator 10.00%

10.00%

Start 23-May-11 1019-Apr-11

Receiv. Supp. Key 03-Sep-11 2017-Aug-11

Place Main Mat. S/ 06-Sep-11 1006-Sep-11

Receiv. Main Mat.s 15-Nov-11 2015-Nov-11

Fabrication Finish 15-Dec-11 4015-Dec-11

4.66%Micro Turbine 10.00%

10.00%

Start 03-May-11 1019-Apr-11

Place Main Mat. S/ 16-Sep-11 1016-Sep-11

Receiv. Supp. Key 16-Sep-11 2016-Sep-11

Receiv. Main Mat.s 25-Nov-11 2025-Nov-11

Fabrication Finish 15-Dec-11 4015-Dec-11

3.03% 3.17%100.00%

3.17%Total EXPEDITING DEPART. 3.03%100.00%

Tuesday, July 05, 2011 Page 43 of 59

Layout No. 1* Weights of Activities are calculated relative to (EXPEDITING DEPART.)Data'Nes Systems, Release 2.21

Page 94: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESSUPPLIER QUALITY SRVEILLANCE DEPART.COMMODITIES ONE BY ONE

2.75%Safety equipment and life saving 0.00%

0.00%

NFI 25-Dec-11 2030-Nov-11

RFS 01-Jan-12 8007-Dec-11

2.75%Flame arrestor 0.00%

0.00%

NFI 19-Dec-11 2021-Nov-11

RFS 26-Dec-11 8028-Nov-11

4.59%Chemical injection package 0.00%

0.00%

NFI 20-Dec-11 2030-Dec-11

RFS 27-Dec-11 8006-Jan-12

3.67%Fire Fighting package 0.00%

0.00%

NFI 28-Dec-11 2024-Dec-11

RFS 04-Jan-12 8031-Dec-11

2.75%Vent stack tips 0.00%

0.00%

NFI 26-Dec-11 2029-Nov-11

RFS 02-Jan-12 8006-Dec-11

4.59%Piping bulk 0.00%

0.00%

NFI 03-Jan-12 2029-Dec-11

RFS 10-Jan-12 8005-Jan-12

1.83%Insulation Joint 0.00%

0.00%

NFI 11-Jan-12 2030-Nov-11

RFS 18-Jan-12 8007-Dec-11

1.83%Injection fitting 0.00%

0.00%

NFI 11-Jan-12 2003-Dec-11

RFS 18-Jan-12 8010-Dec-11

1.83%Earthing material 0.00%

0.00%

NFI 19-Dec-11 2019-Dec-11

RFS 26-Dec-11 8026-Dec-11

1.83%Lighting material 0.00%

0.00%

NFI 16-Dec-11 2007-Dec-11

RFS 23-Dec-11 8014-Dec-11

Tuesday, July 05, 2011 Page 44 of 59

Layout No. 1* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.)Data'Nes Systems, Release 2.21

Page 95: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESSUPPLIER QUALITY SRVEILLANCE DEPART.COMMODITIES ONE BY ONE

1.83%Electrical Cable trays 0.00%

0.00%

NFI 25-Sep-11 2011-Oct-11

RFS 02-Oct-11 8018-Oct-11

1.83%Electrical Cables 0.00%

0.00%

NFI 15-Nov-11 2027-Nov-11

RFS 22-Nov-11 8004-Dec-11

2.75%Navigation aids system 0.00%

0.00%

NFI 11-Dec-11 2028-Nov-11

RFS 18-Dec-11 8005-Dec-11

1.83%Instrument & Mechanical bulk material 0.00%

0.00%

NFI 25-Oct-11 2025-Oct-11

RFS 03-Nov-11 8001-Nov-11

1.83%Inst. Junction Box 0.00%

0.00%

NFI 02-Nov-11 2029-Oct-11

RFS 09-Nov-11 8005-Nov-11

4.59%HIPPS 0.00%

0.00%

NFI 10-Mar-12 2017-Mar-12

RFS 17-Mar-12 8024-Mar-12

3.67%Choke valves 0.00%

0.00%

NFI 14-Apr-12 2024-Mar-12

RFS 21-Apr-12 8031-Mar-12

1.83%Loose instrument 0.00%

0.00%

NFI 04-Jan-12 2006-Jan-12

RFS 10-Jan-12 8013-Jan-12

1.83%Instrument cable trays 0.00%

0.00%

NFI 08-Nov-11 2015-Oct-11

RFS 18-Nov-11 8022-Oct-11

3.67%Electro hydraulic wellhead control panel 0.00%

0.00%

NFI 25-Dec-11 2030-Dec-11

RFS 01-Jan-12 8006-Jan-12

Tuesday, July 05, 2011 Page 45 of 59

Layout No. 1* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.)Data'Nes Systems, Release 2.21

Page 96: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESSUPPLIER QUALITY SRVEILLANCE DEPART.COMMODITIES ONE BY ONE

3.67%Wing valves 0.00%

0.00%

NFI 09-Apr-12 2025-Mar-12

RFS 16-Apr-12 8001-Apr-12

1.83%Instrument cable and cable glands 0.00%

0.00%

NFI 15-Nov-11 2021-Nov-11

RFS 11-Dec-11 8028-Nov-11

1.83%Sand & Corrosion probes 0.00%

0.00%

NFI 01-Jan-12 2022-Dec-11

RFS 08-Jan-12 8029-Dec-11

3.67%Multi phase flow meter 0.00%

0.00%

NFI 14-Dec-11 2030-Dec-11

RFS 21-Dec-11 8006-Jan-12

2.75%Service water pump 0.00%

0.00%

NFI 07-Dec-11 2021-Nov-11

RFS 14-Dec-11 8028-Nov-11

4.59%Turret crane crane 0.00%

0.00%

NFI 12-Feb-12 2022-Feb-12

RFS 19-Feb-12 8029-Feb-12

2.75%Monorail crane 0.00%

0.00%

NFI 25-Jan-12 2025-Jan-12

RFS 01-Feb-12 8001-Feb-12

3.67%Survival module 0.00%

0.00%

NFI 26-Dec-11 2019-Dec-11

RFS 29-Dec-11 8026-Dec-11

2.75%Production Manifold 0.00%

0.00%

NFI 08-Dec-11 2008-Dec-11

RFS 15-Dec-11 8015-Dec-11

4.59%E&I Module 0.00%

0.00%

NFI 08-Dec-11 2008-Dec-11

RFS 15-Dec-11 8015-Dec-11

Tuesday, July 05, 2011 Page 46 of 59

Layout No. 1* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.)Data'Nes Systems, Release 2.21

Page 97: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESSUPPLIER QUALITY SRVEILLANCE DEPART.COMMODITIES ONE BY ONE

4.59%Actuated valves 0.00%

0.00%

NFI 08-Dec-11 2008-Dec-11

RFS 15-Dec-11 8015-Dec-11

4.59%Emergency Generator 0.00%

0.00%

NFI 08-Dec-11 2008-Dec-11

RFS 15-Dec-11 8015-Dec-11

4.59%Micro Turbine 0.00%

0.00%

NFI 08-Dec-11 2008-Dec-11

RFS 15-Dec-11 8015-Dec-11

0.00% 0.00%100.00%

0.00%Total SUPPLIER QUALITY SRVEILLANCE DEP 0.00%100.00%

Tuesday, July 05, 2011 Page 47 of 59

Layout No. 1* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.)Data'Nes Systems, Release 2.21

Page 98: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESTRAFFIC & LOGISTICS DEPARTMENTCOMMODITIES ONE BY ONE

3.48%Safety equipment and life saving 0.00%

0.00%

Mat. Deliv.to Dest. P 02-Jan-12 2007-Dec-11

Mat. Deliv.to Ship. P 22-Jan-12 3028-Dec-11

Customs Cleared 02-Feb-12 3008-Jan-12

Material At Site 05-Feb-12 2011-Jan-12

3.48%Flame arrestor 0.00%

0.00%

Mat. Deliv.to Dest. P 27-Dec-11 2028-Nov-11

Mat. Deliv.to Ship. P 16-Jan-12 3019-Dec-11

Customs Cleared 27-Jan-12 3030-Dec-11

Material At Site 30-Jan-12 2002-Jan-12

4.35%Chemical injection package 0.00%

0.00%

Mat. Deliv.to Dest. P 28-Dec-11 2006-Jan-12

Mat. Deliv.to Ship. P 17-Jan-12 3027-Jan-12

Customs Cleared 28-Jan-12 3007-Feb-12

Material At Site 31-Jan-12 2010-Feb-12

4.35%Fire Fighting package 0.00%

0.00%

Mat. Deliv.to Dest. P 05-Jan-12 2001-Jan-12

Mat. Deliv.to Ship. P 25-Jan-12 3021-Jan-12

Customs Cleared 05-Feb-12 3001-Feb-12

Material At Site 08-Feb-12 2004-Feb-12

2.61%Vent stack tips 0.00%

0.00%

Mat. Deliv.to Dest. P 03-Jan-12 2006-Dec-11

Mat. Deliv.to Ship. P 23-Jan-12 3027-Dec-11

Customs Cleared 03-Feb-12 3007-Jan-12

Material At Site 06-Feb-12 2010-Jan-12

1.74%Piping bulk 3rd batch 0.00%

0.00%

Mat. Deliv.to Dest. P 11-Jan-12 2005-Jan-12

Mat. Deliv.to Ship. P 31-Jan-12 3026-Jan-12

Customs Cleared 11-Feb-12 3006-Feb-12

Material At Site 14-Feb-12 2009-Feb-12

1.74%Insulation Joint 0.00%

0.00%

Mat. Deliv.to Dest. P 19-Jan-12 2007-Dec-11

Mat. Deliv.to Ship. P 08-Feb-12 3028-Dec-11

Customs Cleared 19-Feb-12 3008-Jan-12

Material At Site 22-Feb-12 2011-Jan-12

Tuesday, July 05, 2011 Page 48 of 59

Layout No. 1* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT)Data'Nes Systems, Release 2.21

Page 99: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESTRAFFIC & LOGISTICS DEPARTMENTCOMMODITIES ONE BY ONE

1.74%Injection fitting 0.00%

0.00%

Mat. Deliv.to Dest. P 19-Jan-12 2010-Dec-11

Mat. Deliv.to Ship. P 08-Feb-12 3031-Dec-11

Customs Cleared 19-Feb-12 3011-Jan-12

Material At Site 22-Feb-12 2014-Jan-12

1.74%Earthing material 0.00%

0.00%

Mat. Deliv.to Dest. P 28-Dec-11 2026-Dec-11

Mat. Deliv.to Ship. P 22-Jan-12 3024-Jan-12

Customs Cleared 12-Feb-12 3011-Feb-12

Material At Site 14-Feb-12 2014-Feb-12

1.74%Lighting material 0.00%

0.00%

Mat. Deliv.to Dest. P 26-Dec-11 2014-Dec-11

Mat. Deliv.to Ship. P 13-Jan-12 3004-Jan-12

Customs Cleared 23-Dec-12 3015-Jan-12

Material At Site 27-Jan-12 2018-Jan-12

1.74%Electrical Cable trays 0.00%

0.00%

Mat. Deliv.to Dest. P 03-Oct-11 2018-Oct-11

Mat. Deliv.to Ship. P 23-Oct-11 3008-Nov-11

Customs Cleared 03-Nov-11 3019-Nov-11

Material At Site 06-Nov-11 2022-Nov-11

1.74%Electrical Cables 0.00%

0.00%

Mat. Deliv.to Dest. P 23-Nov-11 2004-Dec-11

Mat. Deliv.to Ship. P 13-Dec-11 3025-Dec-11

Customs Cleared 22-Dec-11 3005-Jan-12

Material At Site 27-Dec-11 2008-Jan-12

3.48%Navigation aids system 0.00%

0.00%

Mat. Deliv.to Dest. P 19-Dec-11 2005-Dec-11

Mat. Deliv.to Ship. P 08-Jan-12 3026-Dec-11

Customs Cleared 19-Jan-12 3006-Jan-12

Material At Site 22-Jan-12 2009-Jan-12

1.74%Instrument & Mechanical bulk material 0.00%

0.00%

Mat. Deliv.to Dest. P 03-Nov-11 2001-Nov-11

Mat. Deliv.to Ship. P 23-Nov-11 3022-Nov-11

Customs Cleared 07-Dec-11 3003-Dec-11

Material At Site 07-Dec-11 2006-Dec-11

Tuesday, July 05, 2011 Page 49 of 59

Layout No. 1* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT)Data'Nes Systems, Release 2.21

Page 100: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESTRAFFIC & LOGISTICS DEPARTMENTCOMMODITIES ONE BY ONE

1.74%Inst. Junction Box 0.00%

0.00%

Mat. Deliv.to Dest. P 10-Nov-11 2005-Nov-11

Mat. Deliv.to Ship. P 30-Nov-11 3026-Nov-11

Customs Cleared 11-Dec-11 3007-Dec-11

Material At Site 14-Dec-11 2010-Dec-11

4.35%HIPPS 0.00%

0.00%

Mat. Deliv.to Dest. P 18-Mar-12 2024-Mar-12

Mat. Deliv.to Ship. P 07-Apr-12 3014-Apr-12

Customs Cleared 18-Apr-12 3025-Apr-12

Material At Site 21-Apr-12 2028-Apr-12

3.48%Choke valves 0.00%

0.00%

Mat. Deliv.to Dest. P 01-May-12 2010-Mar-12

Mat. Deliv.to Ship. P 22-May-12 3031-Mar-12

Customs Cleared 08-Jun-12 3018-Apr-12

Material At Site 11-Jun-12 2021-Apr-12

1.74%Loose instrument 0.00%

0.00%

Mat. Deliv.to Dest. P 10-Jan-12 2013-Jan-12

Mat. Deliv.to Ship. P 06-Feb-12 3010-Feb-12

Customs Cleared 18-Feb-12 3021-Feb-12

Material At Site 20-Feb-12 2024-Feb-12

1.74%Instrument cable trays 0.00%

0.00%

Mat. Deliv.to Dest. P 18-Nov-11 2022-Oct-11

Mat. Deliv.to Ship. P 17-Nov-11 3029-Oct-11

Customs Cleared 04-Dec-11 3009-Nov-11

Material At Site 04-Nov-11 2012-Nov-11

3.48%Electro hydraulic wellhead control panel 0.00%

0.00%

Mat. Deliv.to Dest. P 02-Jan-12 2006-Jan-12

Mat. Deliv.to Ship. P 22-Jan-12 3027-Jan-12

Customs Cleared 02-Feb-12 3008-Feb-12

Material At Site 05-Feb-12 2011-Feb-12

2.61%Wing valves 0.00%

0.00%

Mat. Deliv.to Dest. P 17-Apr-12 2001-Apr-12

Mat. Deliv.to Ship. P 07-May-12 3022-Apr-12

Customs Cleared 18-May-12 3003-May-12

Material At Site 21-May-12 2006-May-12

Tuesday, July 05, 2011 Page 50 of 59

Layout No. 1* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT)Data'Nes Systems, Release 2.21

Page 101: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESTRAFFIC & LOGISTICS DEPARTMENTCOMMODITIES ONE BY ONE

1.74%Instrument cable and cable glands 0.00%

0.00%

Mat. Deliv.to Dest. P 25-Nov-11 2028-Nov-11

Mat. Deliv.to Ship. P 17-Dec-11 3019-Dec-11

Customs Cleared 11-Jan-12 3030-Dec-11

Material At Site 13-Jan-12 2002-Jan-12

1.74%Sand & Corrosion probes 0.00%

0.00%

Mat. Deliv.to Dest. P 09-Jan-12 2029-Dec-11

Mat. Deliv.to Ship. P 28-Jan-12 3019-Jan-12

Customs Cleared 09-Feb-12 3030-Jan-12

Material At Site 11-Feb-12 2002-Feb-12

3.48%Multi phase flow meter 0.00%

0.00%

Mat. Deliv.to Dest. P 22-Dec-11 2006-Jan-12

Mat. Deliv.to Ship. P 11-Jan-12 3027-Jan-12

Customs Cleared 22-Jan-12 3007-Feb-12

Material At Site 25-Jan-12 2010-Feb-12

2.61%Service water pump 0.00%

0.00%

Mat. Deliv.to Dest. P 15-Dec-11 2028-Nov-11

Mat. Deliv.to Ship. P 04-Jan-12 3019-Dec-11

Customs Cleared 17-Jan-12 3001-Jan-12

Material At Site 20-Jan-12 2004-Jan-12

4.35%Turret crane crane 0.00%

0.00%

Mat. Deliv.to Dest. P 20-Feb-12 2029-Feb-12

Mat. Deliv.to Ship. P 04-Mar-12 3014-Mar-12

Customs Cleared 15-Mar-12 3025-Mar-12

Material At Site 18-Mar-12 2028-Mar-12

2.61%Monorail crane 0.00%

0.00%

Mat. Deliv.to Dest. P 01-Feb-12 2001-Feb-12

Mat. Deliv.to Ship. P 22-Feb-12 3022-Feb-12

Customs Cleared 04-Mar-12 3004-Mar-12

Material At Site 07-Mar-12 2007-Mar-12

3.48%Survival module 0.00%

0.00%

Mat. Deliv.to Dest. P 01-Jan-12 2027-Dec-11

Mat. Deliv.to Ship. P 21-Jan-12 3016-Jan-12

Customs Cleared 01-Feb-12 3027-Jan-12

Material At Site 04-Feb-12 2030-Jan-12

Tuesday, July 05, 2011 Page 51 of 59

Layout No. 1* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT)Data'Nes Systems, Release 2.21

Page 102: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESTRAFFIC & LOGISTICS DEPARTMENTCOMMODITIES ONE BY ONE

1.74%Piping bulk 1st batch 0.00%

0.00%

Mat. Deliv.to Dest. P 10-Oct-11 2009-Oct-11

Mat. Deliv.to Ship. P 30-Oct-11 3030-Oct-11

Customs Cleared 10-Nov-11 3010-Nov-11

Material At Site 13-Nov-11 2013-Nov-11

1.74%Piping bulk 2nd batch 0.00%

0.00%

Mat. Deliv.to Dest. P 22-Nov-11 2016-Nov-11

Mat. Deliv.to Ship. P 12-Dec-11 3007-Dec-11

Customs Cleared 21-Dec-11 3018-Dec-11

Material At Site 26-Dec-11 2021-Dec-11

4.35%Micro Turbine 0.00%

0.00%

Customs Cleared 26-Dec-11 3026-Dec-11

Material At Site 29-Dec-11 2029-Dec-11

Mat. Deliv.to Dest. P 29-Dec-11 2029-Dec-11

Mat. Deliv.to Ship. P 26-Jan-12 3026-Jan-12

4.35%Emergency Generator 0.00%

0.00%

Customs Cleared 26-Dec-11 3026-Dec-11

Mat. Deliv.to Dest. P 29-Dec-11 2029-Dec-11

Material At Site 29-Dec-11 2029-Dec-11

Mat. Deliv.to Ship. P 26-Jan-12 3026-Jan-12

4.35%E&I Module 0.00%

0.00%

Mat. Deliv.to Dest. P 15-Dec-11 2015-Dec-11

Mat. Deliv.to Ship. P 12-Jan-12 3012-Jan-12

Customs Cleared 23-Jan-12 3023-Jan-12

Material At Site 26-Jan-12 2026-Jan-12

4.35%Production Manifold 0.00%

0.00%

Mat. Deliv.to Dest. P 15-Dec-11 2015-Dec-11

Mat. Deliv.to Ship. P 12-Jan-12 3012-Jan-12

Customs Cleared 23-Jan-12 3023-Jan-12

Material At Site 26-Jan-12 2026-Jan-12

4.35%Actuated valves 0.00%

0.00%

Mat. Deliv.to Dest. P 15-Dec-11 2015-Dec-11

Mat. Deliv.to Ship. P 12-Jan-12 3012-Jan-12

Customs Cleared 23-Jan-12 3023-Jan-12

Material At Site 26-Jan-12 2026-Jan-12

0.00% 0.00%100.00%

Tuesday, July 05, 2011 Page 52 of 59

Layout No. 1* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT)Data'Nes Systems, Release 2.21

Page 103: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESTRAFFIC & LOGISTICS DEPARTMENT

0.00%Total TRAFFIC & LOGISTICS DEPARTMENT 0.00%100.00%

Tuesday, July 05, 2011 Page 53 of 59

Layout No. 1* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT)Data'Nes Systems, Release 2.21

Page 104: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATIONMETERIAL SUPPLYCOMMODITIES ONE BY ONE

2.99%Safety equipment and life saving 0.00%

0.00%

P.O. 18-Aug-11 1524-Jul-11

Receiv. Supp. Key 26-Sep-11 2029-Aug-11

Place Main Mat. S/ 16-Oct-11 1518-Sep-11

RFS 01-Jan-12 3507-Dec-11

Material At Site 05-Feb-12 1511-Jan-12

0.17%Flame arrestor 0.00%

0.00%

P.O. 11-Aug-11 1504-Aug-11

Receiv. Supp. Key 10-Oct-11 2009-Sep-11

Place Main Mat. S/ 26-Oct-11 1529-Sep-11

RFS 26-Dec-11 3528-Nov-11

Material At Site 30-Jan-12 1502-Jan-12

9.06%Chemical injection package 0.00%

0.00%

P.O. 10-Jul-11 1524-Jul-11

Receiv. Supp. Key 11-Sep-11 2018-Sep-11

Place Main Mat. S/ 14-Sep-11 1523-Sep-11

RFS 27-Dec-11 3506-Jan-12

Material At Site 31-Jan-12 1510-Feb-12

1.94%Fire Fighting package 0.00%

0.00%

P.O. 24-Jul-11 1518-Jul-11

Receiv. Supp. Key 19-Sep-11 2003-Sep-11

Place Main Mat. S/ 09-Oct-11 1523-Sep-11

RFS 04-Jan-12 3531-Dec-11

Material At Site 08-Feb-12 1504-Feb-12

1.30%Vent stack tips 0.00%

0.00%

P.O. 24-Aug-11 1517-Aug-11

Receiv. Supp. Key 06-Nov-11 2007-Oct-11

Place Main Mat. S/ 24-Nov-11 1527-Oct-11

RFS 02-Jan-12 3506-Dec-11

Material At Site 06-Feb-12 1510-Jan-12

3.48%Piping bulk 3rd batch 0.00%

0.00%

P.O. 07-Jul-11 3503-Jul-11

Place Main Mat. S/ 02-Nov-11 1526-Oct-11

RFS 11-Jan-12 3505-Jan-12

Material At Site 14-Feb-12 1509-Feb-12

Tuesday, July 05, 2011 Page 54 of 59

Layout No. 1* Weights of Activities are calculated relative to (METERIAL SUPPLY)Data'Nes Systems, Release 2.21

Page 105: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATIONMETERIAL SUPPLYCOMMODITIES ONE BY ONE

0.18%Insulation Joint 0.00%

0.00%

P.O. 17-Aug-11 3524-Jul-11

Place Main Mat. S/ 31-Oct-11 1518-Sep-11

RFS 18-Jan-12 3507-Dec-11

Material At Site 22-Feb-12 1511-Jan-12

0.09%Injection fitting 0.00%

0.00%

P.O. 23-Aug-11 3527-Jul-11

Place Main Mat. S/ 31-Oct-11 1521-Sep-11

RFS 18-Jan-12 3510-Dec-11

Material At Site 22-Feb-12 1514-Jan-12

0.15%Earthing material 0.00%

0.00%

P.O. 20-Aug-11 3524-Aug-11

Place Main Mat. S/ 10-Sep-11 1513-Sep-11

RFS 23-Dec-11 3526-Dec-11

Material At Site 22-Jan-12 1514-Feb-12

1.39%Lighting material 0.00%

0.00%

P.O. 13-Sep-11 3522-Aug-11

Place Main Mat. S/ 23-Oct-11 1528-Sep-11

RFS 24-Dec-11 3514-Dec-11

Material At Site 27-Jan-12 1518-Jan-12

2.78%Electrical Cable trays 0.00%

0.00%

P.O. 07-Jul-11 3524-Jul-11

Place Main Mat. S/ 07-Aug-11 1519-Aug-11

RFS 02-Oct-11 3518-Oct-11

Material At Site 06-Nov-11 1522-Nov-11

1.49%Electrical Cables 0.00%

0.00%

P.O. 10-Jul-11 3527-Jul-11

Place Main Mat. S/ 28-Aug-11 1513-Sep-11

RFS 22-Nov-11 3504-Dec-11

Material At Site 27-Dec-11 1508-Jan-12

8.17%Navigation aids system 0.00%

0.00%

P.O. 15-Aug-11 1502-Aug-11

Receiv. Supp. Key 28-Sep-11 2016-Sep-11

Place Main Mat. S/ 20-Oct-11 1506-Oct-11

RFS 18-Dec-11 3505-Dec-11

Material At Site 22-Jan-12 1509-Jan-12

Tuesday, July 05, 2011 Page 55 of 59

Layout No. 1* Weights of Activities are calculated relative to (METERIAL SUPPLY)Data'Nes Systems, Release 2.21

Page 106: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATIONMETERIAL SUPPLYCOMMODITIES ONE BY ONE

1.44%Instrument & Mechanical bulk material 0.00%

0.00%

P.O. 18-Aug-11 3507-Aug-11

Place Main Mat. S/ 05-Sep-11 1530-Aug-11

RFS 06-Nov-11 3501-Nov-11

Material At Site 07-Dec-11 1506-Dec-11

0.33%Inst. Junction Box 0.00%

0.00%

P.O. 21-Aug-11 3511-Aug-11

Place Main Mat. S/ 28-Sep-11 1513-Sep-11

RFS 09-Nov-11 3505-Nov-11

Material At Site 14-Dec-11 1510-Dec-11

7.71%HIPPS 0.00%

0.00%

P.O. 14-Jul-11 1512-Jul-11

Receiv. Supp. Key 01-Nov-11 2023-Oct-11

Place Main Mat. S/ 24-Nov-11 1515-Nov-11

RFS 17-Mar-12 3524-Mar-12

Material At Site 21-Apr-12 1528-Apr-12

3.32%Choke valves 0.00%

0.00%

P.O. 09-Aug-11 1519-Jul-11

Receiv. Supp. Key 24-Nov-11 2002-Nov-11

Place Main Mat. S/ 14-Dec-11 1522-Nov-11

RFS 21-Apr-12 3531-Mar-12

Material At Site 11-Jun-12 1521-Apr-12

0.92%Loose instrument 0.00%

0.00%

P.O. 25-Aug-11 3531-Jul-11

Place Main Mat. S/ 23-Oct-11 1526-Oct-11

RFS 10-Jan-12 3513-Jan-12

Material At Site 20-Feb-12 1524-Feb-12

1.68%Instrument cable trays 0.00%

0.00%

P.O. 05-Aug-11 3528-Jul-11

Place Main Mat. S/ 08-Sep-11 1522-Aug-11

RFS 08-Nov-11 3522-Oct-11

Material At Site 04-Dec-11 1512-Nov-11

5.41%Electro hydraulic wellhead control panel 0.00%

0.00%

P.O. 18-Jul-11 1518-Jul-11

Receiv. Supp. Key 04-Oct-11 2008-Oct-11

Place Main Mat. S/ 03-Nov-11 1507-Nov-11

RFS 01-Jan-12 3506-Jan-12

Material At Site 05-Feb-12 1511-Feb-12

Tuesday, July 05, 2011 Page 56 of 59

Layout No. 1* Weights of Activities are calculated relative to (METERIAL SUPPLY)Data'Nes Systems, Release 2.21

Page 107: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATIONMETERIAL SUPPLYCOMMODITIES ONE BY ONE

2.70%Wing valves 0.00%

0.00%

P.O. 04-Aug-11 1520-Jul-11

Receiv. Supp. Key 20-Oct-11 2004-Oct-11

Place Main Mat. S/ 03-Jan-12 1506-Dec-11

RFS 16-Apr-12 3501-Apr-12

Material At Site 21-May-12 1506-May-12

0.83%Instrument cable and cable glands 0.00%

0.00%

P.O. 28-Aug-11 3525-Jul-11

Place Main Mat. S/ 01-Sep-11 1501-Sep-11

RFS 11-Dec-11 3528-Nov-11

Material At Site 13-Jan-12 1502-Jan-12

0.50%Sand & Corrosion probes 0.00%

0.00%

P.O. 15-Sep-11 3515-Aug-11

Place Main Mat. S/ 09-Nov-11 1530-Oct-11

RFS 09-Jan-12 3529-Dec-11

Material At Site 11-Feb-12 1502-Feb-12

10.97%Multi phase flow meter 0.00%

0.00%

P.O. 03-Jul-11 1524-Jul-11

Receiv. Supp. Key 18-Sep-11 2018-Sep-11

Place Main Mat. S/ 20-Sep-11 1508-Oct-11

RFS 21-Dec-11 3506-Jan-12

Material At Site 25-Jan-12 1510-Feb-12

0.54%Service water pump 0.00%

0.00%

P.O. 02-Aug-11 1502-Aug-11

Receiv. Supp. Key 06-Oct-11 2019-Sep-11

Place Main Mat. S/ 26-Oct-11 1509-Oct-11

RFS 14-Dec-11 3528-Nov-11

Material At Site 20-Jan-12 1504-Jan-12

13.25%Turret crane crane 0.00%

15.00%

P.O. 21-Jun-11 1524-Jul-11

Receiv. Supp. Key 27-Sep-11 2001-Nov-11

Place Main Mat. S/ 09-Oct-11 1511-Nov-11

RFS 19-Feb-12 3529-Feb-12

Material At Site 18-Mar-12 1528-Mar-12

Tuesday, July 05, 2011 Page 57 of 59

Layout No. 1* Weights of Activities are calculated relative to (METERIAL SUPPLY)Data'Nes Systems, Release 2.21

Page 108: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATIONMETERIAL SUPPLYCOMMODITIES ONE BY ONE

0.17%Monorail crane 0.00%

0.00%

P.O. 17-Oct-11 1517-Oct-11

Receiv. Supp. Key 13-Dec-11 2013-Dec-11

Place Main Mat. S/ 23-Dec-11 1523-Dec-11

RFS 01-Feb-12 3501-Feb-12

Material At Site 07-Mar-12 1507-Mar-12

3.10%Survival module 0.00%

0.00%

P.O. 07-Aug-11 1502-Aug-11

Receiv. Supp. Key 26-Oct-11 2009-Oct-11

Place Main Mat. S/ 15-Nov-11 1529-Oct-11

RFS 29-Dec-11 3526-Dec-11

Material At Site 04-Feb-12 1530-Jan-12

8.70%Piping bulk 1st batch 0.00%

0.00%

P.O. 07-Jul-11 3503-Jul-11

Place Main Mat. S/ 04-Sep-11 1528-Aug-11

RFS 10-Oct-11 3509-Oct-11

Material At Site 13-Nov-11 1513-Nov-11

5.22%Piping bulk 2nd batch 0.00%

0.00%

P.O. 07-Jul-11 3503-Jul-11

Place Main Mat. S/ 23-Oct-11 1516-Oct-11

RFS 22-Nov-11 3516-Nov-11

Material At Site 26-Dec-11 1521-Dec-11

0.00% 1.99%100.00%

1.99%Total METERIAL SUPPLY 0.00%100.00%

Tuesday, July 05, 2011 Page 58 of 59

Layout No. 1* Weights of Activities are calculated relative to (METERIAL SUPPLY)Data'Nes Systems, Release 2.21

Page 109: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Issuance Status ReportSETH Offshore EPC Project 25-Jun-11As Of :

3467-200Project No.:

MilestonePlanned Actual Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.9 OFFSHORE HOOK-UP & COMMISSIONINGCOMMISSIONINGSYSTEM BY SYSTEM

100.00%Commissioning activities 0.00%

0.00%

Start 01-Jun-12 2001-Jun-12

Finish 30-Jun-12 8030-Jun-12

0.00% 0.00%100.00%

0.00%Total COMMISSIONING 0.00%100.00%

Tuesday, July 05, 2011 Page 59 of 59

Layout No. 1* Weights of Activities are calculated relative to (COMMISSIONING)Data'Nes Systems, Release 2.21

Page 110: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 25 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.2.2 TECNOMARE

Page 111: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

ITEM DESCRIPTION Weight Progress @ cut-off date

Monthly progress

Previous month

Progress

% % % %

1.1 PROJECT MANAGEMENT 14,17% 39,46% 5,57% 33,89%1.2 DETAILED ENGINEERING 36,71% 51,65% 11,60% 40,05%1.3 PROCUREMENT SERVICES 1,35% 37,07% 5,06% 32,01%1.4 SUBSTRUCTURE ( PREDRILLING TEMPLATE , PILES AND JACKET) FABRICATION 3,91% 35,00% 11,67% 23,33%1.5 DECK AND TSF MATERIAL/EQUIPMENT SUPPLY AND FABRICATION 37,25% 35,00% 0,00% 35,00%1.6 PIPELINE SPOOLS FABRICATION

1.7 LOAD OUT AND SEA FASTENING

1.8 OFFSHORE HOOK-UP AND COMMISSIONING 6,61% 0,00% 0,00% 0,00%

1.9COST IMPACT DUE TO CRASHING THE SCHEDULE TO MEET TARGET DATE INCLUDING (INTERNALS BONUS FOR LABORS , THREE SHIFT WITH COMPLETE NDT , OVERTIME, ADDITIONAL SHIFTS , LABOR DAILY LOGISTICS ,..ETC )

TOTAL 100,00% 39,46% 5,57% 33,89%

1.1. PROJECT MANAGEMENT

1.1.1. PROJECT SERVICES 14,17% 39,46% 5,57% 33,89%1.1.2 QA/QC

1.1.3 HSE

1.1.4 SYSTEM INTEGRITY ASSURANCE

1.1.5 CLIENT FACILITIES

1.1.6 CONSORTIUM FACILITES

SUBTOTAL 1.1 14,17% 39,46% 5,57% 33,89%

1.2. DETAILED ENGINEERING

1.2.1 DECK 26,16% 66,10% 16,28% 49,82%1.2.2 SSIV/PLEM (TECHNICAL FOLLOW UP) 3,90% 20,00% 0,00% 20,00%1.2.4 LOAD OUT AND SEAFASTENING

1.2.5 OFFSHORE TRANSPORTATION

1.2.6 HOOKUP AND COMMISSIONING

1.2.7 MANUALS

1.2.8 AS BUILT DOSSIER 1,06% 0,00% 0,00% 0,00%1.2.9 CERTIFICATION ( ASSISTANCE) 1,14% 0,00% 0,00% 0,00%

1.2.10 TECHNICAL FOLLOW ON FOR T & I CONTRACTS 4,45% 20,00% 0,00% 20,00%

SUBTOTAL 1.2 36,71% 51,65% 11,60% 40,05%

1.3. PROCUREMENT SERVICES

1.3.1 COMPANY PROVIDED ITEMS

1.3.2 CONTRACTOR PROVIDED ITEMS

1.3.3 PLEM/SSIV 0,54% 26,66% 6,66% 20,00%1.3.4 HOOK-UP AND COMMISSIONING

1.3.5 LOAD OUT AND SEA FASTENING

1.3.6 PLC/RTU 0,81% 44,00% 4,00% 40,00%

SUBTOTAL 1.3 1,35% 37,07% 5,06% 32,01%

1.4. SUBSTRUCTURE

1.4.1 YARD MOBILIZATION

1.4.2 PRE_DRILLING TEMPLATE

1.4.3 PILES

1.4.4 JACKET STRUCTURES

1.4.5 BOAT LANDING, BARGE BUMPERS

1.4.6 ANODES INSTALLATION

1.4.7 RISERS, CAISSONS AND SUPPORTS,

1.4.8 BUOYANCY TANKS FABRICATION & ERECTION

1.4.9 GROUT SEALS AND SHOCK CELLS 3,91% 35,00% 11,67% 23,33%1.4.10 WEIGHT CONTROL

1.4.11 SURFACE PREPARATION AND PAINTING

1.4.12 INSPECTIONS, TESTING AND PRE-COMMISSIONING

1.4.13 INSTALLATION AIDS ,BALLASTING AND GROUTING SYSTEM, WALK WAY ,STAIRS UPENDING TRENNIONS

1.4.14 BARGE PREPARATION (BERTHING , CLEANING , BLASTING , TEFLON, GRILLAGE LOAD AND OFFLOAD,..)

1.4.15 GRILLAGE SUPPLY, FABRICATION

SUBTOTAL 1.4 3,91% 35,00% 11,67% 23,33%

Page 112: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

1.5 DECK MATERIAL/EQUIPMENT SUPPLY AND FABRICATION

1.5.1. YARD MOBILIZATION

1.5.2. MAIN STRUCTURES

1.5.3. SECONDARY STRUCTURES

1.5.4. MECHANICAL EQUIPMENT

1.5.5. PIPING AND MANUAL VALVES

1.5.6 ELECTRICAL

1.5.7 INSTRUMENTATION

1.5.8 SURFACE PREPARATION AND PAINTING

1.5.9 INSULATION

1.5.10 MECHANICAL COMPLETION AND PRECOMMISSIONING

1.5.11 WEIGHT CONTROL

1.5.12 INSTALLATION AIDS FABRICATION AND GRILLAGE SUPPLY

1.5.13 BARGE PREPARATION (BERTHING , CLEANING , BLASTING , GRILLAGE LOAD AND OFFLOAD,..)

1.5.14 FIRE FIGHTING AND SAFETY EQUIPMENT

1.5.15 ARCHITECTURE

1.5.16 ELECTRICAL POWER GENERATION

1.5.17 OTHER INSTRUMENTATION

a. MATERIAL/EQUIPMENT SUPPLY

a.1 PLC/RTU 37,25% 35,00% 0,00% 35,00%a.2 NAV AIDS

a.3 INSTRUMENTATION BULKS

b. INSULATION

1.5.18 UTILITY EQUIPMENT, FIRE FIGHTING SYSTEM

SUBTOTAL 1.5 37,25% 35,00% 0,00% 35,00%

1.6 PIPELINE AND SPOOLS

SUBTOTAL 1.6

1.7 LOAD OUT AND SEAFASTENING

SUBTOTAL 1.7

1.8 OFFSHORE HOOK - UP AND COMMISSIONING

1.8.1 OFFSHORE HOOK - UP AND COMMISSIONING� JACKET AND DECK

1.8.1.1 HOOK-UP AND COMMISSIONING SUPPLY OF MATERIALS

1.8.1.2 COMMISSIONING SPARE PARTS

1.8.1.3 HOOK-UP, COMMISSIONING ACTIVITIES AND TESTS 6,61% 0,00% 0,00% 0,00%1.8.1.4 FIRST FILLING FOR DIESEL

1.8.1.5 ASISTANT DURING START UP

SUBTOTAL 1.8 6,61% 0,00% 0,00% 0,00%

Page 113: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 26 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.23 PETROJET

Page 114: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

LEVEL I OVERALL WP

CLIENT :PETROBELWK 14 DATE : 13

ITEM OVERALL ITEM OVERALL

16,500,000€              100% 22.34% 22.34% 18.00% 18.00% 31-Mar-11 31-Oct-12 4.34% 4.34%

WP1 PROJECT MANAGEMENT 2,125,000€ 13% 18.00% 2.32% 18.00% 2.32% 31-Mar-11 31-Oct-12 0.00% 0.00%

WP3 PROCUREMENT SERVICES 100,000€ 1% 18.00% 0.11% 18.00% 0.11% 31-Mar-11 31-Oct-12 0.00% 0.00%

WP4 SUBSTRUCTURE ( P.D.T, PILES AND JACKET ) FABRICATION 5,195,000€ 31% 44.27% 13.94% 32.53% 10.24% 31-Mar-11 15-Mar-12 11.74% 3.69%

WP5 DECK & TSF MATERIAL/EQUIPMENT SUPPLY AND FABRICATION 5,860,000€ 36% 16.82% 5.97% 15.01% 5.33% 31-Mar-11 29-Apr-12 1.81% 0.64%

WP6 PIPELINE SPOOLS FABRICATION 620,000€ 4% 0.00% 0.00% 0.00% 0.00% 23-Feb-12 25-Apr-12 0.00% 0.00%

WP8 LOAD OUT AND SEA FASTENING 1,400,000€ 8% 0.00% 0.00% 0.00% 0.00% 18-Oct-11 08-May-12 0.00% 0.00%

WP9 OFFSHORE HOOK-UP AND COMMISSIONING 900,000€ 5% 0.00% 0.00% 0.00% 0.00% 16-May-12 15-Jun-12 0.00% 0.00%

8 COST IMPACT DUE TO CRASHING THE SCHEDULE TO MEET TARGET DATE…. 300,000€ 2% 0.00% 0.00% 0.00% 0.00% 15-Nov-11 15-Apr-12 0.00% 0.00%

PETROJET WORK PACKAGE

PROJECT : SETH DEVELOPMENT PROJECT 25‐Jun‐11 WEEK NO.

Activity Name Total Budgete Units (Hrs) R.W % R.W %ACTUAL % PLANNED %

Start Date Finish Date DEV/ITEMDEV/ 

OVERALL

PETROJET

1/40

Page 115: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP1 PROGRESS Sheet

CLIENT : PETROBELWK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.1: PROJECT MANAGEMENT 100.00% 580 18.00% 18.00% 18.00% 18.00% 31-Mar-11 31-Oct-12 0.00% 0.00%

M01 Apr-11 6.00% 25 100.00% 6.00% 100.00% 6.00% 31-Mar-11 25-Apr-11 0.00% 0.00%

M02 May-11 6.00% 29 100.00% 6.00% 100.00% 6.00% 26‐Apr‐11 25‐May‐11 0.00% 0.00%

M03 Jun-11 6.00% 30 100.00% 6.00% 100.00% 6.00% 26‐May‐11 25‐Jun‐11 0.00% 0.00%

M04 Jul-11 6.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Jun‐11 25‐Jul‐11 0.00% 0.00%

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PROJECT : SETH DEVELOPMENT PROJECT 25‐Jun‐11 WEEK NO.

Act ID Activity Name R.W %Original Duration

(Days)

PETROJET

M05 Aug-11 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jul‐11 25‐Aug‐11 0.00% 0.00%

M06 Sep-11 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Aug‐11 25‐Sep‐11 0.00% 0.00%

M07 Oct-11 6.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Sep‐11 25‐Oct‐11 0.00% 0.00%

M08 Nov-11 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Oct‐11 25‐Nov‐11 0.00% 0.00%

M09 Dec-11 6.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Nov‐11 25‐Dec‐11 0.00% 0.00%

M10 Jan-12 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Dec‐11 25‐Jan‐12 0.00% 0.00%

M11 Feb-12 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jan‐12 25‐Feb‐12 0.00% 0.00%

M12 Mar-12 6.00% 28 0.00% 0.00% 0.00% 0.00% 26‐Feb‐12 25‐Mar‐12 0.00% 0.00%

M13 Apr-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Mar‐12 25‐Apr‐12 0.00% 0.00%

M14 May-12 4.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Apr‐12 25‐May‐12 0.00% 0.00%

M15 Jun-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐May‐12 25‐Jun‐12 0.00% 0.00%

M16 Jul-12 4.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Jun‐12 25‐Jul‐12 0.00% 0.00%

M17 Aug-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jul‐12 25‐Aug‐12 0.00% 0.00%

M18 Sep-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Aug‐12 25‐Sep‐12 0.00% 0.00%

M19 Oct-12 4.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Sep‐12 25‐Oct‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\2/40

Page 116: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP3 PROGRESS Sheet

CLIENT : PETROBELWK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.3: PROCUREMENT SERVICES 100.00% 580 18.00% 18.00% 18.00% 18.00% 31-Mar-11 31-Oct-12 0.0% 0.0%

M01 Apr-11 6.00% 25 100.00% 6.00% 100.00% 6.00% 31-Mar-11 25-Apr-11 0.0% 0.0%

M02 May-11 6.00% 29 100.00% 6.00% 100.00% 6.00% 26‐Apr‐11 25‐May‐11 0.0% 0.0%

M03 Jun-11 6.00% 30 100.00% 6.00% 100.00% 6.00% 26‐May‐11 25‐Jun‐11 0.0% 0.0%

M04 Jul-11 6.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Jun‐11 25‐Jul‐11 0.0% 0.0%

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PROJECT : SETH DEVELOPMENT PROJECT 25‐Jun‐11 WEEK NO.

Act ID Activity Name R.W %Original Duration

(Days)

PETROJET

M05 Aug-11 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jul‐11 25‐Aug‐11 0.0% 0.0%

M06 Sep-11 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Aug‐11 25‐Sep‐11 0.0% 0.0%

M07 Oct-11 6.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Sep‐11 25‐Oct‐11 0.0% 0.0%

M08 Nov-11 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Oct‐11 25‐Nov‐11 0.0% 0.0%

M09 Dec-11 6.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Nov‐11 25‐Dec‐11 0.0% 0.0%

M10 Jan-12 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Dec‐11 25‐Jan‐12 0.0% 0.0%

M11 Feb-12 6.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jan‐12 25‐Feb‐12 0.0% 0.0%

M12 Mar-12 6.00% 28 0.00% 0.00% 0.00% 0.00% 26‐Feb‐12 25‐Mar‐12 0.0% 0.0%

M13 Apr-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Mar‐12 25‐Apr‐12 0.0% 0.0%

M14 May-12 4.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Apr‐12 25‐May‐12 0.0% 0.0%

M15 Jun-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐May‐12 25‐Jun‐12 0.0% 0.0%

M16 Jul-12 4.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Jun‐12 25‐Jul‐12 0.0% 0.0%

M17 Aug-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jul‐12 25‐Aug‐12 0.0% 0.0%

M18 Sep-12 4.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Aug‐12 25‐Sep‐12 0.0% 0.0%

M19 Oct-12 4.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Sep‐12 25‐Oct‐12 0.0% 0.0%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\3/40

Page 117: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

CLIENT : PETROBELPROJECT : SETH DEVELOPMENT PROJECT WK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.4: SUBSTRUCTURES (PILES, JACKET & PDT) FABRICATION 262712 100.00% 351 44.27% 44.27% 32.53% 32.53% 31-Mar-11 15-Mar-12 11.74% 11.74%

JACKET STRUCTURE FABRICATION 246356 93.77% 351 45.22% 42.41% 34.69% 32.53% 31‐Mar‐11 15‐Mar‐12 10.53% 9.87%

MAIN STRUCTURE FABRICATION 133676 54.26% 344 70.65% 38.33% 54.94% 29.81% 31‐Mar‐11 08‐Mar‐12 15.70% 8.52%

General 864 0.65% 344 0.00% 0.00% 0.00% 0.00% 31-Mar-11 08-Mar-12 0.00% 0.00%

PTJ2000 Jacket main structure fabrication start 0 0.00% 0 100.00% 0.00% 100.00% 0.00% 31-Mar-11 31-Mar-11 0.00% 0.00%

PTJ2210 Jacket main structure fabrication finish 0 0.00% 0 0.00% 0.00% 0.00% 29-Feb-12 29-Feb-12 0.00% 0.00%

PTJ2230 Jacket weighing 864 100 00% 2 0 00% 0 00% 0 00% 07‐Mar‐12 08‐Mar‐12 0 00% 0 00%

Act ID Activity Name Finish Date

25‐Jun‐11 WEEK NO.

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PETROJET

PTJ2230 Jacket weighing 864 100.00% 2 0.00% 0.00% 0.00% 07‐Mar‐12 08‐Mar‐12 0.00% 0.00%

JACKET LEGS FABRICATION 42224 31.59% 88 94.95% 29.99% 99.86% 31.54% 31-Mar-11 26-Jun-11 -4.91% -1.55%

PTJ5000 PREPARATION OF SKID WAY 1596 3.78% 21 90.00% 3.40% 100.00% 3.78% 31-Mar-11 26-Apr-11 -10.00% -0.38%

PTJ5010 PREPARATION LEG FOR ROW A & B TRIAL FIT 544 1.29% 8 100.00% 1.29% 88.89% 1.15% 18-Jun-11 26-Jun-11 11.11% 0.14%

LEG A1 9992 23.66% 78 91.61% 21.68% 100.00% 23.66% 31-Mar-11 16-Jun-11 -8.39% -1.98%

DIM 1400 5520 55.24% 53 87.50% 48.34% 100.00% 55.24% 31-Mar-11 22-May-11 -12.50% -6.91%

PTJ5160 LEG SPLICE FIT UP 1224 22.17% 9 95.00% 21.07% 100.00% 22.17% 31-Mar-11 10-Apr-11 -5.00% -1.11%

PTJ5170 CANS FIT UP 1224 22.17% 9 80.00% 17.74% 100.00% 22.17% 11-Apr-11 21-Apr-11 -20.00% -4.43%

PTJ5180 LEG SPLICE WELDING & NDT 1536 27.83% 12 95.00% 26.43% 100.00% 27.83% 23-Apr-11 8-May-11 -5.00% -1.39%

PTJ5190 CAN WELDING & NDT 1536 27.83% 12 80.00% 22.26% 100.00% 27.83% 9-May-11 22-May-11 -20.00% -5.57%

DIM 1200 2564 25.66% 47 100.00% 25.66% 100.00% 25.66% 23-Apr-11 8-Jun-11 0.00% 0.00%

PTJ5090 LEG SPLICE FIT UP 612 23.87% 9 100.00% 23.87% 100.00% 23.87% 23-Apr-11 04-May-11 0.00% 0.00%

PTJ5110 CANS FIT UP 272 10.61% 4 100.00% 10.61% 100.00% 10.61% 5-May-11 9-May-11 0.00% 0.00%

PTJ5100 CONE FIT UP 272 10.61% 4 100.00% 10.61% 100.00% 10.61% 10-May-11 14-May-11 0.00% 0.00%

PTJ5120 LEG SPLICE WELDING & NDT 768 29.95% 12 100.00% 29.95% 100.00% 29.95% 15-May-11 28-May-11 0.00% 0.00%

PTJ5130 CONE WELDING & NDT 320 12.48% 5 100.00% 12.48% 100.00% 12.48% 29-May-11 2-Jun-11 0.00% 0.00%

PTJ5140 CAN WELDING & NDT 320 12.48% 5 100.00% 12.48% 100.00% 12.48% 04-Jun-11 08-Jun-11 0.00% 0.00%

DIM 1000 1908 19.10% 33 92.24% 17.61% 100.00% 19.10% 15-May-11 16-Jun-11 -7.76% -1.48%

PTJ5020 LEG SPLICE FIT UP 340 17.82% 5 100.00% 17.82% 100.00% 17.82% 15-May-11 19-May-11 0.00% 0.00%

PTJ5040 CANS FIT UP 272 14.26% 4 75.00% 10.69% 100.00% 14.26% 21-May-11 24-May-11 -25.00% -3.56%

PTJ5030 CONE FIT UP 272 14.26% 4 100.00% 14.26% 100.00% 14.26% 25-May-11 29-May-11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\4/40

Page 118: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ5050 LEG SPLICE WELDING & NDT 384 20.13% 6 100.00% 20.13% 100.00% 20.13% 30-May-11 05-Jun-11 0.00% 0.00%

PTJ5060 CONE WELDING & NDT 320 16.77% 5 100.00% 16.77% 100.00% 16.77% 6-Jun-11 11-Jun-11 0.00% 0.00%

PTJ5070 CAN WELDING & NDT 320 16.77% 5 75.00% 12.58% 100.00% 16.77% 12-Jun-11 16-Jun-11 -25.00% -4.19%

LEG A2 10172 24.09% 78 98.55% 23.74% 100.00% 24.09% 31-Mar-11 16-Jun-11 -1.45% -0.35%

DIM 1400 5556 54.62% 53 100.00% 54.62% 100.00% 54.62% 31-Mar-11 22-May-11 0.00% 0.00%

PTJ5350 LEG SPLICE FIT UP 1260 22.68% 9 100.00% 22.68% 100.00% 22.68% 31‐Mar‐11 10‐Apr‐11 0.00% 0.00%

PTJ5360 CANS FIT UP 1224 22.03% 9 100.00% 22.03% 100.00% 22.03% 11-Apr-11 21-Apr-11 0.00% 0.00%

PTJ5370 LEG SPLICE WELDING & NDT 1536 27.65% 12 100.00% 27.65% 100.00% 27.65% 23-Apr-11 08-May-11 0.00% 0.00%

PTJ5380 CAN WELDING & NDT 1536 27.65% 12 100.00% 27.65% 100.00% 27.65% 09-May-11 22-May-11 0.00% 0.00%

DIM 1200 2772 27.25% 55 100.00% 27.25% 100.00% 27.25% 23‐Apr‐11 16‐Jun‐11 0.00% 0.00%

PTJ5280 LEG SPLICE FIT UP 612 22.08% 9 100.00% 22.08% 100.00% 22.08% 23-Apr-11 04-May-11 0.00% 0.00%

PTJ5300 CANS FIT UP 272 9.81% 4 100.00% 9.81% 100.00% 9.81% 5-May-11 9-May-11 0.00% 0.00%y y

PTJ5290 CONE FIT UP 288 10.39% 8 100.00% 10.39% 100.00% 10.39% 10-May-11 18-May-11 0.00% 0.00%

PTJ5310 LEG SPLICE WELDING & NDT 832 30.01% 13 100.00% 30.01% 100.00% 30.01% 19-May-11 2-Jun-11 0.00% 0.00%

PTJ5320 CONE WELDING & NDT 384 13.85% 6 100.00% 13.85% 100.00% 13.85% 04-Jun-11 09-Jun-11 0.00% 0.00%

PTJ5330 CAN WELDING & NDT 384 13.85% 6 100.00% 13.85% 100.00% 13.85% 11-Jun-11 16-Jun-11 0.00% 0.00%

DIM 1000 1844 18.13% 33 91.97% 16.67% 100.00% 18.13% 10-May-11 11-Jun-11 -8.03% -1.45%

PTJ5210 LEG SPLICE FIT UP 340 18.44% 5 100.00% 18.44% 100.00% 18.44% 10-May-11 15-May-11 0.00% 0.00%

PTJ5230 CANS FIT UP 272 14.75% 4 75.00% 11.06% 100.00% 14.75% 16-May-11 19-May-11 -25.00% -3.69%

PTJ5220 CONE FIT UP 272 14.75% 4 100.00% 14.75% 100.00% 14.75% 21-May-11 24-May-11 0.00% 0.00%

PTJ5240 LEG SPLICE WELDING & NDT 384 20.82% 6 100.00% 20.82% 100.00% 20.82% 25-May-11 31-May-11 0.00% 0.00%

PTJ5250 CONE WELDING & NDT 256 13.88% 4 100.00% 13.88% 100.00% 13.88% 1-Jun-11 5-Jun-11 0.00% 0.00%

PTJ5260 CAN WELDING & NDT 320 17.35% 5 75.00% 13.02% 100.00% 17.35% 06‐Jun‐11 11‐Jun‐11 ‐25.00% ‐4.34%

LEG B1 10072 23.85% 78 91.68% 21.87% 100.00% 23.85% 31-Mar-11 16-Jun-11 -8.32% -1.98%

DIM 1400 5520 54.81% 53 87.50% 47.95% 100.00% 54.81% 31-Mar-11 22-May-11 -12.50% -6.85%

PTJ5540 LEG SPLICE FIT UP 1224 22.17% 9 95.00% 21.07% 100.00% 22.17% 31-Mar-11 10-Apr-11 -5.00% -1.11%

PTJ5550 CANS FIT UP 1224 22.17% 9 80.00% 17.74% 100.00% 22.17% 11-Apr-11 21-Apr-11 -20.00% -4.43%

PTJ5560 LEG SPLICE WELDING & NDT 1536 27.83% 12 95.00% 26.43% 100.00% 27.83% 23-Apr-11 8-May-11 -5.00% -1.39%

PTJ5570 CAN WELDING & NDT 1536 27.83% 12 80.00% 22.26% 100.00% 27.83% 9-May-11 22-May-11 -20.00% -5.57%

DIM 1200 2644 26.25% 50 100.00% 26.25% 100.00% 26.25% 23-Apr-11 11-Jun-11 0.00% 0.00%

PTJ5470 LEG SPLICE FIT UP 612 23.15% 9 100.00% 23.15% 100.00% 23.15% 23‐Apr‐11 04‐May‐11 0.00% 0.00%

PTJ5490 CANS FIT UP 272 10.29% 4 100.00% 10.29% 100.00% 10.29% 05-May-11 09-May-11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\5/40

Page 119: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ5480 CONE FIT UP 272 10.29% 4 100.00% 10.29% 100.00% 10.29% 10-May-11 14-May-11 0.00% 0.00%

PTJ5500 LEG SPLICE WELDING & NDT 768 29.05% 12 100.00% 29.05% 100.00% 29.05% 15-May-11 28-May-11 0.00% 0.00%

PTJ5510 CONE WELDING & NDT 384 14.52% 6 100.00% 14.52% 100.00% 14.52% 29‐May‐11 04‐Jun‐11 0.00% 0.00%

PTJ5520 CAN WELDING & NDT 336 12.71% 6 100.00% 12.71% 100.00% 12.71% 05-Jun-11 11-Jun-11 0.00% 0.00%

DIM 1000 1908 18.94% 33 92.24% 17.47% 100.00% 18.94% 15-May-11 16-Jun-11 -7.76% -1.47%

PTJ5400 LEG SPLICE FIT UP 340 17.82% 5 100.00% 17.82% 100.00% 17.82% 15-May-11 19-May-11 0.00% 0.00%

PTJ5420 CANS FIT UP 272 14.26% 4 75.00% 10.69% 100.00% 14.26% 21-May-11 24-May-11 -25.00% -3.56%

PTJ5410 CONE FIT UP 272 14.26% 4 100.00% 14.26% 100.00% 14.26% 25-May-11 29-May-11 0.00% 0.00%

PTJ5430 LEG SPLICE WELDING & NDT 384 20.13% 6 100.00% 20.13% 100.00% 20.13% 30-May-11 5-Jun-11 0.00% 0.00%

PTJ5440 CONE WELDING & NDT 320 16.77% 5 100.00% 16.77% 100.00% 16.77% 6-Jun-11 11-Jun-11 0.00% 0.00%

PTJ5450 CAN WELDING & NDT 320 16.77% 5 75.00% 12.58% 100.00% 16.77% 12-Jun-11 16-Jun-11 -25.00% -4.19%

LEG B2 9848 23.32% 76 98.50% 22.97% 100.00% 23.32% 31-Mar-11 14-Jun-11 -1.50% -0.35%

DIM 1400 5248 53 29% 50 100 00% 53 29% 100 00% 53 29% 31 M 11 19 M 11 DIM 1400 5248 53.29% 50 100.00% 53.29% 100.00% 53.29% 31-Mar-11 19-May-11 0.00% 0.00%

PTJ5730 LEG SPLICE FIT UP 1088 20.73% 8 100.00% 20.73% 100.00% 20.73% 31-Mar-11 9-Apr-11 0.00% 0.00%

PTJ5740 CANS FIT UP 1088 20.73% 8 100.00% 20.73% 100.00% 20.73% 10-Apr-11 19-Apr-11 0.00% 0.00%

PTJ5750 LEG SPLICE WELDING & NDT 1536 29.27% 12 100.00% 29.27% 100.00% 29.27% 20‐Apr‐11 05‐May‐11 0.00% 0.00%

PTJ5760 CAN WELDING & NDT 1536 29.27% 12 100.00% 29.27% 100.00% 29.27% 07-May-11 19-May-11 0.00% 0.00%

DIM 1200 2692 27.34% 50 100.00% 27.34% 100.00% 27.34% 20-Apr-11 8-Jun-11 0.00% 0.00%

PTJ5660 LEG SPLICE FIT UP 612 22.73% 9 100.00% 22.73% 100.00% 22.73% 20-Apr-11 2-May-11 0.00% 0.00%

PTJ5680 CANS FIT UP 272 10.10% 4 100.00% 10.10% 100.00% 10.10% 03-May-11 07-May-11 0.00% 0.00%

PTJ5670 CONE FIT UP 272 10.10% 4 100.00% 10.10% 100.00% 10.10% 8-May-11 11-May-11 0.00% 0.00%

PTJ5690 LEG SPLICE WELDING & NDT 768 28.53% 12 100.00% 28.53% 100.00% 28.53% 12-May-11 25-May-11 0.00% 0.00%

PTJ5700 CONE WELDING & NDT 384 14.26% 6 100.00% 14.26% 100.00% 14.26% 26‐May‐11 1‐Jun‐11 0.00% 0.00%

PTJ5710 CAN WELDING & NDT 384 14.26% 6 100.00% 14.26% 100.00% 14.26% 2‐Jun‐11 8‐Jun‐11 0.00% 0.00%

DIM 1000 1908 19.37% 34 92.24% 17.87% 100.00% 19.37% 12-May-11 14-Jun-11 -7.76% -1.50%

PTJ5590 LEG SPLICE FIT UP 340 17.82% 5 100.00% 17.82% 100.00% 17.82% 12‐May‐11 17‐May‐11 0.00% 0.00%

PTJ5610 CANS FIT UP 272 14.26% 4 75.00% 10.69% 100.00% 14.26% 18‐May‐11 22‐May‐11 ‐25.00% ‐3.56%

PTJ5600 CONE FIT UP 272 14.26% 4 100.00% 14.26% 100.00% 14.26% 23‐May‐11 26‐May‐11 0.00% 0.00%

PTJ5620 LEG SPLICE WELDING & NDT 384 20.13% 6 100.00% 20.13% 100.00% 20.13% 28‐May‐11 2‐Jun‐11 0.00% 0.00%

PTJ5630 CONE WELDING & NDT 320 16.77% 5 100.00% 16.77% 100.00% 16.77% 4‐Jun‐11 8‐Jun‐11 0.00% 0.00%

PTJ5640 CAN WELDING & NDT 320 16.77% 5 75.00% 12.58% 100.00% 16.77% 9‐Jun‐11 14‐Jun‐11 ‐25.00% ‐4.19%

JACKET BRACING FABRICATION 35012 26.19% 189 86.21% 22.58% 33.60% 8.80% 31-Mar-11 05-Oct-11 52.61% 13.78%

BRACING ROW 1 8996 25.69% 59 88.67% 22.78% 0.00% 0.00% 8‐Aug‐11 5‐Oct‐11 88.67% 22.78%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\6/40

Page 120: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

SPLICING 8996 100.00% 59 88.67% 88.67% 0.00% 0.00% 8‐Aug‐11 5‐Oct‐11 88.67% 88.67%

HORIZONTAL 3304 36.73% 53 100.00% 36.73% 0.00% 0.00% 8‐Aug‐11 29‐Sep‐11 100.00% 36.73%

PTJ3180 FITUP HORIZONTAL BRACES ATELEV ‐56.2 324 9.81% 9 100.00% 9.81% 0.00% 0.00% 8‐Aug‐11 17‐Aug‐11 100.00% 9.81%

PTJ3170 FITUP HORIZONTAL BRACES AT ELEV ‐33.4 324 9.81% 9 100.00% 9.81% 0.00% 0.00% 18‐Aug‐11 28‐Aug‐11 100.00% 9.81%

PTJ3200 FITUP HORIZONTAL BRACES AT ELEV ‐79.0 324 9.81% 9 100.00% 9.81% 0.00% 0.00% 18‐Aug‐11 28‐Aug‐11 100.00% 9.81%

PTJ3270 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐56.2 384 11.62% 12 100.00% 11.62% 0.00% 0.00% 18‐Aug‐11 4‐Sep‐11 100.00% 11.62%

PTJ3160 FITUP HORIZONTAL BRACES AT ELEV ‐10.6 288 8.72% 8 100.00% 8.72% 0.00% 0.00% 29‐Aug‐11 10‐Sep‐11 100.00% 8.72%

PTJ3260 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐33.4 384 11.62% 12 100.00% 11.62% 0.00% 0.00% 29‐Aug‐11 14‐Sep‐11 100.00% 11.62%

PTJ3290 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐79.0 384 11.62% 12 100.00% 11.62% 0.00% 0.00% 29‐Aug‐11 14‐Sep‐11 100.00% 11.62%

PTJ3190 FITUP HORIZONTAL BRACES AT ELEV +6.4 252 7.63% 7 100.00% 7.63% 0.00% 0.00% 11‐Sep‐11 18‐Sep‐11 100.00% 7.63%

PTJ3250 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐10.6 320 9.69% 10 100.00% 9.69% 0.00% 0.00% 11‐Sep‐11 21‐Sep‐11 100.00% 9.69%

PTJ3280 WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4 320 9.69% 10 100.00% 9.69% 0.00% 0.00% 19‐Sep‐11 29‐Sep‐11 100.00% 9.69%

DIAGONAL BRACES 5692 63.27% 49 82.10% 51.95% 0.00% 0.00% 18‐Aug‐11 5‐Oct‐11 82.10% 51.95%

PTJ3140 FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 720 12.65% 20 100.00% 12.65% 0.00% 0.00% 18‐Aug‐11 13‐Sep‐11 100.00% 12.65%

PTJ3150 FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 792 13.91% 22 75.00% 10.44% 0.00% 0.00% 18‐Aug‐11 15‐Sep‐11 75.00% 10.44%

PTJ3130 FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 576 10.12% 16 75.00% 7.59% 0.00% 0.00% 29‐Aug‐11 19‐Sep‐11 75.00% 7.59%

PTJ3120 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 468 8.22% 13 75.00% 6.17% 0.00% 0.00% 11‐Sep‐11 25‐Sep‐11 75.00% 6.17%

PTJ3230 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 896 15.74% 14 100.00% 15.74% 0.00% 0.00% 14‐Sep‐11 29‐Sep‐11 100.00% 15.74%

PTJ3240 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 960 16.87% 15 75.00% 12.65% 0.00% 0.00% 17‐Sep‐11 3‐Oct‐11 75.00% 12.65%

PTJ3220 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 704 12.37% 11 75.00% 9.28% 0.00% 0.00% 20‐Sep‐11 2‐Oct‐11 75.00% 9.28%

PTJ3210 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 576 10.12% 9 75.00% 7.59% 0.00% 0.00% 26‐Sep‐11 5‐Oct‐11 75.00% 7.59%

BRACING ROW 2 9964 28.46% 91 94.38% 26.86% 98.83% 28.13% 31‐Mar‐11 29‐Jun‐11 ‐4.45% ‐1.27%

SPLICING 9964 100.00% 91 94.38% 94.38% 98.83% 98.83% 31‐Mar‐11 29‐Jun‐11 ‐4.45% ‐4.45%

HORIZONTAL 2428 24.37% 20 100.00% 24.37% 100.00% 24.37% 31‐Mar‐11 19‐Apr‐11 0.00% 0.00%

PTJ3340 FITUP HORIZONTAL BRACES AT ELEV ‐10.6 180 7.41% 5 100.00% 7.41% 100.00% 7.41% 31‐Mar‐11 5‐Apr‐11 0.00% 0.00%

PTJ3350 FITUP HORIZONTAL BRACES AT ELEV ‐33.4 252 10.38% 7 100.00% 10.38% 100.00% 10.38% 31‐Mar‐11 7‐Apr‐11 0.00% 0.00%

PTJ3360 FITUP HORIZONTAL BRACES AT ELEV ‐56.2 252 10.38% 7 100.00% 10.38% 100.00% 10.38% 31‐Mar‐11 7‐Apr‐11 0.00% 0.00%

PTJ3370 FITUP HORIZONTAL BRACES AT ELEV +6.4 180 7.41% 5 100.00% 7.41% 100.00% 7.41% 31‐Mar‐11 5‐Apr‐11 0.00% 0.00%

PTJ3380 FITUP HORIZONTAL BRACES AT ELEV ‐79.0 252 10.38% 7 100.00% 10.38% 100.00% 10.38% 31‐Mar‐11 7‐Apr‐11 0.00% 0.00%

PTJ3430 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐10.6 224 9.23% 7 100.00% 9.23% 100.00% 9.23% 6‐Apr‐11 13‐Apr‐11 0.00% 0.00%

PTJ3470 WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4 224 9.23% 7 100.00% 9.23% 100.00% 9.23% 6‐Apr‐11 13‐Apr‐11 0.00% 0.00%

PTJ3440 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐33.4 288 11.86% 9 100.00% 11.86% 100.00% 11.86% 9‐Apr‐11 19‐Apr‐11 0.00% 0.00%

PTJ3450 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐56.2 288 11.86% 9 100.00% 11.86% 100.00% 11.86% 9‐Apr‐11 19‐Apr‐11 0.00% 0.00%

PTJ3460 WELDING & NDT HORIZONTAL BRACES AT ELEV ‐79.0 288 11.86% 9 100.00% 11.86% 100.00% 11.86% 9‐Apr‐11 19‐Apr‐11 0.00% 0.00%

DIAGONAL BRACES 5988 60.10% 65 100.00% 60.10% 100.00% 60.10% 6‐Apr‐11 9‐Jun‐11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\7/40

Page 121: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ3300 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 544 9.08% 8 100.00% 9.08% 100.00% 9.08% 6‐Apr‐11 14‐Apr‐11 0.00% 0.00%

PTJ3310 FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 612 10.22% 9 100.00% 10.22% 100.00% 10.22% 9‐Apr‐11 19‐Apr‐11 0.00% 0.00%

PTJ3320 FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 816 13.63% 12 100.00% 13.63% 100.00% 13.63% 9‐Apr‐11 23‐Apr‐11 0.00% 0.00%

PTJ3330 FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 816 13.63% 12 100.00% 13.63% 100.00% 13.63% 9‐Apr‐11 23‐Apr‐11 0.00% 0.00%

PTJ3390 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 512 8.55% 8 100.00% 8.55% 100.00% 8.55% 16‐Apr‐11 26‐Apr‐11 0.00% 0.00%

PTJ3400 WELDING DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 768 12.83% 12 100.00% 12.83% 100.00% 12.83% 20‐Apr‐11 5‐May‐11 0.00% 0.00%

PTJ3410 WELDING DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 896 14.96% 14 100.00% 14.96% 100.00% 14.96% 7‐May‐11 22‐May‐11 0.00% 0.00%

PTJ3420 WELDING DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 1024 17.10% 16 100.00% 17.10% 100.00% 17.10% 23‐May‐11 9‐Jun‐11 0.00% 0.00%

VERTICAL 1548 15.54% 54 63.84% 9.92% 92.48% 14.37% 7‐May‐11 29‐Jun‐11 ‐28.65% ‐4.45%

PTJ3970 FITUP VERTICAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 180 11.63% 5 75.00% 8.72% 100.00% 11.63% 7‐May‐11 11‐May‐11 ‐25.00% ‐2.91%

PTJ8040 WELDING VERTICAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 224 14.47% 7 55.00% 7.96% 100.00% 14.47% 12‐May‐11 19‐May‐11 ‐45.00% ‐6.51%

PTJ3980 FITUP VERTICAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 252 16.28% 7 75.00% 12.21% 100.00% 16.28% 23‐May‐11 30‐May‐11 ‐25.00% ‐4.07%

PTJ8050 WELDING VERTICAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 320 20.67% 10 55.00% 11.37% 100.00% 20.67% 31‐May‐11 11‐Jun‐11 ‐45.00% ‐9.30%

PTJ3990 FITUP VERTICAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 252 16.28% 7 75.00% 12.21% 100.00% 16.28% 11‐Jun‐11 18‐Jun‐11 ‐25.00% ‐4.07%

PTJ8060 WELDING VERTICAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 320 20.67% 10 55.00% 11.37% 63.64% 13.15% 19‐Jun‐11 29‐Jun‐11 ‐8.64% ‐1.79%

BRACING ROW 3 1716 4.90% 19 75.00% 3.68% 100.00% 4.90% 21‐May‐11 8‐Jun‐11 ‐25.00% ‐1.23%

PTJ8120 FITUP BRACES BETWEEN ELEV ‐10.6 & ‐33.4 252 14.69% 7 75.00% 11.01% 100.00% 14.69% 21‐May‐11 28‐May‐11 ‐25.00% ‐3.67%

PTJ8130 FITUP BRACES BETWEEN ELEV ‐33.4 & ‐56.2 252 14.69% 7 75.00% 11.01% 100.00% 14.69% 21‐May‐11 28‐May‐11 ‐25.00% ‐3.67%

PTJ8140 FITUP BRACES BETWEEN ELEV ‐56.2 & ‐79.0 252 14.69% 7 75.00% 11.01% 100.00% 14.69% 21‐May‐11 28‐May‐11 ‐25.00% ‐3.67%

PTJ8150 WELDING VERTICAL BRACES BETWEEN ELEV +10.6 & ‐33.4 320 18.65% 10 75.00% 13.99% 100.00% 18.65% 29‐May‐11 8‐Jun‐11 ‐25.00% ‐4.66%

PTJ8160 WELDING VERTICAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 320 18.65% 10 75.00% 13.99% 100.00% 18.65% 29‐May‐11 8‐Jun‐11 ‐25.00% ‐4.66%

PTJ8170 WELDING VERTICAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 320 18.65% 10 75.00% 13.99% 100.00% 18.65% 29‐May‐11 8‐Jun‐11 ‐25.00% ‐4.66%

BRACING ROW A 5516 15.75% 59 76.52% 12.05% 0.00% 0.00% 27‐Jun‐11 24‐Aug‐11 76.52% 12.05%

FABRICATION 5516 100.00% 59 76.52% 76.52% 0.00% 0.00% 27‐Jun‐11 24‐Aug‐11 76.52% 76.52%

PTJ8210 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 408 7.40% 6 95.00% 7.03% 0.00% 0.00% 27‐Jun‐11 3‐Jul‐11 95.00% 7.03%

PTJ8220 FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 544 9.86% 8 95.00% 9.37% 0.00% 0.00% 4‐Jul‐11 12‐Jul‐11 95.00% 9.37%

PTJ8250 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 576 10.44% 9 85.00% 8.88% 0.00% 0.00% 4‐Jul‐11 13‐Jul‐11 85.00% 8.88%

PTJ8230 FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 680 12.33% 10 85.00% 10.48% 0.00% 0.00% 13‐Jul‐11 25‐Jul‐11 85.00% 10.48%

PTJ8260 WELDING DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 704 12.76% 11 85.00% 10.85% 0.00% 0.00% 13‐Jul‐11 26‐Jul‐11 85.00% 10.85%

PTJ8240 FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 748 13.56% 11 85.00% 11.53% 0.00% 0.00% 26‐Jul‐11 7‐Aug‐11 85.00% 11.53%

PTJ8270 WELDING DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 896 16.24% 14 65.00% 10.56% 0.00% 0.00% 26‐Jul‐11 10‐Aug‐11 65.00% 10.56%

PTJ8280 WELDING DIAGONAL BRACES BETWEEN ELEV ‐ 56.2 & ‐79.0 960 17.40% 15 45.00% 7.83% 0.00% 0.00% 8‐Aug‐11 24‐Aug‐11 45.00% 7.83%

BRACING ROW B 5516 15.75% 59 83.94% 13.22% 0.00% 0.00% 27‐Jun‐11 24‐Aug‐11 83.94% 13.22%

FABRICATION 5516 100.00% 59 83.94% 83.94% 0.00% 0.00% 27‐Jun‐11 24‐Aug‐11 83.94% 83.94%

PTJ8330 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 408 7.40% 6 100.00% 7.40% 0.00% 0.00% 27‐Jun‐11 3‐Jul‐11 100.00% 7.40%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\8/40

Page 122: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ8340 FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 544 9.86% 8 100.00% 9.86% 0.00% 0.00% 4‐Jul‐11 12‐Jul‐11 100.00% 9.86%

PTJ8370 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6 576 10.44% 9 100.00% 10.44% 0.00% 0.00% 4‐Jul‐11 13‐Jul‐11 100.00% 10.44%

PTJ8350 FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2 680 12.33% 10 100.00% 12.33% 0.00% 0.00% 13‐Jul‐11 25‐Jul‐11 100.00% 12.33%

PTJ8380 WELDING DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4 704 12.76% 11 100.00% 12.76% 0.00% 0.00% 13‐Jul‐11 26‐Jul‐11 100.00% 12.76%

PTJ8360 FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0 748 13.56% 11 65.00% 8.81% 0.00% 0.00% 26‐Jul‐11 7‐Aug‐11 65.00% 8.81%

PTJ8390 WELDING DIAGONAL BRACES BETWEEN ELEV ‐ 33.4 & ‐56.2 896 16.24% 14 100.00% 16.24% 0.00% 0.00% 26‐Jul‐11 10‐Aug‐11 100.00% 16.24%

PTJ8400 WELDING DIAGONAL BRACES BETWEEN ELEV ‐ 56.2 & ‐79.0 960 17.40% 15 35.00% 6.09% 0.00% 0.00% 8‐Aug‐11 24‐Aug‐11 35.00% 6.09%

BRACING ROW C 1856 5.30% 26 85.00% 4.51% 5.16% 0.27% 25‐Jun‐11 20‐Jul‐11 79.84% 4.23%

PTJ8450 FITUP BRACES BETWEEN ELEV ‐10.6 & ‐33.4 252 13.58% 7 85.00% 11.54% 12.50% 1.70% 25‐Jun‐11 2‐Jul‐11 72.50% 9.84%

PTJ8460 FITUP BRACES BETWEEN ELEV ‐33.4 & ‐56.2 360 19.40% 10 85.00% 16.49% 9.09% 1.76% 25‐Jun‐11 5‐Jul‐11 75.91% 14.72%

PTJ8470 FITUP BRACES BETWEEN ELEV ‐56.2 & ‐79.0 252 13.58% 7 85.00% 11.54% 12.50% 1.70% 25‐Jun‐11 2‐Jul‐11 72.50% 9.84%

PTJ8480 WELDING BRACES BETWEEN ELEV ‐10.6 & ‐33.4 288 15.52% 9 85.00% 13.19% 0.00% 0.00% 3‐Jul‐11 12‐Jul‐11 85.00% 13.19%

PTJ8490 WELDING BRACES BETWEEN ELEV ‐56.2 & ‐79.0 288 15.52% 9 85.00% 13.19% 0.00% 0.00% 3‐Jul‐11 12‐Jul‐11 85.00% 13.19%

PTJ8500 WELDING BRACES BETWEEN ELEV ‐33.4 & ‐56.2 416 22.41% 13 85.00% 19.05% 0.00% 0.00% 6‐Jul‐11 20‐Jul‐11 85.00% 19.05%

BRACING ROW D 1448 4.14% 22 75.00% 3.10% 7.18% 0.30% 25‐Jun‐11 16‐Jul‐11 67.82% 2.80%

PTJ8540 FITUP BRACES BETWEEN ELEV ‐10.6 & ‐33.4 180 12.43% 5 75.00% 9.32% 20.00% 2.49% 25‐Jun‐11 29‐Jun‐11 55.00% 6.84%

PTJ8550 FITUP BRACES BETWEEN ELEV ‐33.4 & ‐56.2 288 19.89% 8 75.00% 14.92% 11.11% 2.21% 25‐Jun‐11 3‐Jul‐11 63.89% 12.71%

PTJ8560 FITUP BRACES BETWEEN ELEV ‐56.2 & ‐79.0 180 12.43% 5 75.00% 9.32% 20.00% 2.49% 25‐Jun‐11 29‐Jun‐11 55.00% 6.84%

PTJ8570 WELDING BRACES BETWEEN ELEV ‐10.6 & ‐33.4 224 15.47% 7 75.00% 11.60% 0.00% 0.00% 30‐Jun‐11 7‐Jul‐11 75.00% 11.60%

PTJ8580 WELDING BRACES BETWEEN ELEV ‐56.2 & ‐79.0 224 15.47% 7 75.00% 11.60% 0.00% 0.00% 30‐Jun‐11 7‐Jul‐11 75.00% 11.60%

PTJ8590 WELDING BRACES BETWEEN ELEV ‐33.4 & ‐56.2 352 24.31% 11 75.00% 18.23% 0.00% 0.00% 4‐Jul‐11 16‐Jul‐11 75.00% 18.23%

JACKET ELEVATIONS FABRICATION 31088 23.26% 227 74.72% 17.38% 61.66% 14.34% 31-Mar-11 12-Nov-11 13.05% 3.04%

ELEV + 6400 4280 13.77% 91 100.00% 13.77% 90.51% 12.46% 4‐Apr‐11 3‐Jul‐11 9.49% 1.31%

FITUP 1260 29.44% 34 100.00% 29.44% 100.00% 29.44% 4‐Apr‐11 7‐May‐11 0.00% 0.00%

PTJ8630 FITUP OF SIZE 24" 720 57.14% 20 100.00% 57.14% 100.00% 57.14% 4‐Apr‐11 28‐Apr‐11 0.00% 0.00%

PTJ8640 FITUP OF SIZE 16" 324 25.71% 9 100.00% 25.71% 100.00% 25.71% 23‐Apr‐11 4‐May‐11 0.00% 0.00%

PTJ8650 FITUP OF SIZE 20" 216 17.14% 6 100.00% 17.14% 100.00% 17.14% 30‐Apr‐11 7‐May‐11 0.00% 0.00%

WELDING&NDT 1344 31.40% 23 100.00% 31.40% 100.00% 31.40% 8‐May‐11 30‐May‐11 0.00% 0.00%

PTJ8660 WELDING OF SIZE 24" 768 57.14% 12 100.00% 57.14% 100.00% 57.14% 8‐May‐11 21‐May‐11 0.00% 0.00%

PTJ8670 WELDING OF SIZE 16" 320 23.81% 5 100.00% 23.81% 100.00% 23.81% 22‐May‐11 26‐May‐11 0.00% 0.00%

PTJ8680 WELDING OF SIZE 20" 256 19.05% 4 100.00% 19.05% 100.00% 19.05% 26‐May‐11 30‐May‐11 0.00% 0.00%

CONDUCTORS AT ELEV + 6400 1676 39.16% 44 100.00% 39.16% 75.77% 29.67% 21‐May‐11 3‐Jul‐11 24.23% 9.49%

FITUP 504 30.07% 24 100.00% 30.07% 100.00% 30.07% 21‐May‐11 13‐Jun‐11 0.00% 0.00%

PTJ9100 FITUP OF CONDUCTOR 324 64.29% 9 100.00% 64.29% 100.00% 64.29% 21‐May‐11 30‐May‐11 0.00% 0.00%

PTJ9110 FITUP OF CONDUCTOR SUPPORT 180 35.71% 5 100.00% 35.71% 100.00% 35.71% 8‐Jun‐11 13‐Jun‐11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\9/40

Page 123: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

WELDING & NDT 512 30.55% 21 100.00% 30.55% 100.00% 30.55% 31‐May‐11 20‐Jun‐11 0.00% 0.00%

PTJ9120 WELDING OF CONDUCTOR 320 62.50% 10 100.00% 62.50% 100.00% 62.50% 31‐May‐11 11‐Jun‐11 0.00% 0.00%

PTJ9130 WELDING OF CONDUCTOR SUPPORT 192 37.50% 6 100.00% 37.50% 100.00% 37.50% 14‐Jun‐11 20‐Jun‐11 0.00% 0.00%

CONDUCTORS ERECTION 660 39.38% 13 100.00% 39.38% 38.46% 15.15% 21‐Jun‐11 3‐Jul‐11 61.54% 24.23%

PTJ9140 ERECTION OF CONDUCTOR WITH ELEVATIONS 660 100.00% 11 100.00% 100.00% 38.46% 38.46% 21‐Jun‐11 3‐Jul‐11 61.54% 61.54%

ELEV ‐ 10600 6716 21.60% 148 30.82% 6.66% 62.51% 13.50% 31-Mar-11 25-Aug-11 -31.69% -6.85%

FITUP 2448 36.45% 48 35.00% 12.76% 100.00% 36.45% 31-Mar-11 17-May-11 -65.00% -23.69%

PTJ8700 FITUP OF SIZE 28" 1044 42.65% 29 35.00% 14.93% 100.00% 42.65% 31‐Mar‐11 7‐May‐11 ‐65.00% ‐27.72%

PTJ8710 FITUP OF SIZE 20" 936 38.24% 26 35.00% 13.38% 100.00% 38.24% 12‐Apr‐11 15‐May‐11 ‐65.00% ‐24.85%

PTJ8720 FITUP OF SIZE 16" 288 11.76% 8 35.00% 4.12% 100.00% 11.76% 2‐May‐11 10‐May‐11 ‐65.00% ‐7.65%

PTJ8730 FITUP OF SIZE 14" 180 7.35% 5 35.00% 2.57% 100.00% 7.35% 12‐May‐11 17‐May‐11 ‐65.00% ‐4.78%

WELDING&NDT 2592 38.59% 56 15.00% 5.79% 67.52% 26.06% 18‐May‐11 12‐Jul‐11 ‐52.52% ‐20.27%

PTJ8740 WELDING OF SIZE 28" 1120 43.21% 35 15.00% 6.48% 95.12% 41.10% 18‐May‐11 27‐Jun‐11 ‐80.12% ‐34.62%

PTJ8750 WELDING OF SIZE 20" 992 38.27% 31 15.00% 5.74% 61.11% 23.39% 4‐Jun‐11 9‐Jul‐11 ‐46.11% ‐17.65%

PTJ8760 WELDING OF SIZE 16" 288 11.11% 9 15.00% 1.67% 27.27% 3.03% 23‐Jun‐11 3‐Jul‐11 ‐12.27% ‐1.36%

PTJ8770 WELDING OF SIZE 14" 192 7.41% 6 15.00% 1.11% 0.00% 0.00% 6‐Jul‐11 12‐Jul‐11 15.00% 1.11%

CONDUCTORS AT ELEV ‐ 10600 1676 24.96% 54 49.16% 12.27% 0.00% 0.00% 3‐Jul‐11 25‐Aug‐11 49.16% 12.27%

FITUP 504 30.07% 35 100.00% 30.07% 0.00% 0.00% 3‐Jul‐11 6‐Aug‐11 100.00% 30.07%

PTJ9150 FITUP OF CONDUCTOR 324 64.29% 9 100.00% 64.29% 0.00% 0.00% 3‐Jul‐11 12‐Jul‐11 100.00% 64.29%

PTJ9160 FITUP OF CONDUCTOR SUPPORT 180 35.71% 5 100.00% 35.71% 0.00% 0.00% 1‐Aug‐11 6‐Aug‐11 100.00% 35.71%

WELDING & NDT 512 30.55% 32 62.50% 19.09% 0.00% 0.00% 13‐Jul‐11 13‐Aug‐11 62.50% 19.09%

PTJ9170 WELDING OF CONDUCTOR 320 62.50% 10 100.00% 62.50% 0.00% 0.00% 13‐Jul‐11 25‐Jul‐11 100.00% 62.50%

PTJ9180 WELDING OF CONDUCTOR SUPPORT 192 37.50% 6 0.00% 0.00% 0.00% 0.00% 7‐Aug‐11 13‐Aug‐11 0.00% 0.00%

CONDUCTORS ERECTION 660 39.38% 12 0.00% 0.00% 0.00% 0.00% 14‐Aug‐11 25‐Aug‐11 0.00% 0.00%

PTJ9190 ERECTION OF CONDUCTOR WITH ELEVATIONS 660 100.00% 11 0.00% 0.00% 0.00% 0.00% 14‐Aug‐11 25‐Aug‐11 0.00% 0.00%

ELEV ‐ 33400 7092 22.81% 120 66.64% 15.20% 85.07% 19.41% 31-Mar-11 28-Jul-11 -18.43% -4.20%

FITUP 2664 37.56% 36 100.00% 37.56% 100.00% 37.56% 31-Mar-11 5-May-11 0.00% 0.00%

PTJ8790 FITUP OF SIZE 28" 1008 37.84% 14 100.00% 37.84% 100.00% 37.84% 31‐Mar‐11 16‐Apr‐11 0.00% 0.00%

PTJ8810 FITUP OF SIZE 16" 396 14.86% 11 100.00% 14.86% 100.00% 14.86% 9‐Apr‐11 21‐Apr‐11 0.00% 0.00%

PTJ8800 FITUP OF SIZE 24" 720 27.03% 10 100.00% 27.03% 100.00% 27.03% 17‐Apr‐11 30‐Apr‐11 0.00% 0.00%

PTJ8820 FITUP OF SIZE 20" 288 10.81% 8 100.00% 10.81% 100.00% 10.81% 23‐Apr‐11 3‐May‐11 0.00% 0.00%

PTJ8830 FITUP OF SIZE 18" 252 9.46% 7 100.00% 9.46% 100.00% 9.46% 27‐Apr‐11 5‐May‐11 0.00% 0.00%

WELDING&NDT 2752 38.80% 39 45.00% 17.46% 100.00% 38.80% 7-May-11 14-Jun-11 -55.00% -21.34%

PTJ8840 WELDING OF SIZE 28" 1024 37.21% 16 45.00% 16.74% 100.00% 37.21% 7‐May‐11 24‐May‐11 ‐55.00% ‐20.47%

PTJ8860 WELDING OF SIZE 16" 384 13.95% 6 45.00% 6.28% 100.00% 13.95% 24‐May‐11 30‐May‐11 ‐55.00% ‐7.67%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\10/40

Page 124: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ8850 WELDING OF SIZE 24" 768 27.91% 12 45.00% 12.56% 100.00% 27.91% 26‐May‐11 8‐Jun‐11 ‐55.00% ‐15.35%

PTJ8870 WELDING OF SIZE 20" 320 11.63% 5 45.00% 5.23% 100.00% 11.63% 7‐Jun‐11 12‐Jun‐11 ‐55.00% ‐6.40%

PTJ8880 WELDING OF SIZE 18" 256 9.30% 4 45.00% 4.19% 100.00% 9.30% 11‐Jun‐11 14‐Jun‐11 ‐55.00% ‐5.12%

CONDUCTORS AT ELEV ‐ 33400 1676 23.63% 54 49.16% 11.62% 36.83% 8.70% 5-Jun-11 28-Jul-11 12.33% 2.91%

FITUP 504 30.07% 33 100.00% 30.07% 64.29% 19.33% 5‐Jun‐11 7‐Jul‐11 35.71% 10.74%

PTJ9200 FITUP OF CONDUCTOR 324 64.29% 9 100.00% 64.29% 100.00% 64.29% 5‐Jun‐11 14‐Jun‐11 0.00% 0.00%

PTJ9210 FITUP OF CONDUCTOR SUPPORT 180 35.71% 5 100.00% 35.71% 0.00% 0.00% 3‐Jul‐11 7‐Jul‐11 100.00% 35.71%

WELDING & NDT 512 30.55% 30 62.50% 19.09% 57.29% 17.50% 15‐Jun‐11 14‐Jul‐11 5.21% 1.59%

PTJ9220 WELDING OF CONDUCTOR 320 62.50% 10 100.00% 62.50% 91.67% 57.29% 15‐Jun‐11 26‐Jun‐11 8.33% 5.21%

PTJ9230 WELDING OF CONDUCTOR SUPPORT 192 37.50% 6 0.00% 0.00% 0.00% 0.00% 9‐Jul‐11 14‐Jul‐11 0.00% 0.00%

CONDUCTORS ERECTION 660 39.38% 13 0.00% 0.00% 0.00% 0.00% 16‐Jul‐11 28‐Jul‐11 0.00% 0.00%

PTJ9240 ERECTION OF CONDUCTOR WITH ELEVATIONS 660 100.00% 11 0.00% 0.00% 0.00% 0.00% 16‐Jul‐11 28‐Jul‐11 0.00% 0.00%

ELEV ‐ 56200 7520 24.19% 140 94.34% 22.82% 67.34% 16.29% 31-Mar-11 17-Aug-11 27.00% 6.53%

FITUP 2772 36.86% 54 100.00% 36.86% 100.00% 36.86% 31-Mar-11 23-May-11 0.00% 0.00%

PTJ8900 FITUP OF SIZE 28" 1044 37.66% 29 100.00% 37.66% 100.00% 37.66% 31‐Mar‐11 7‐May‐11 0.00% 0.00%

PTJ8910 FITUP OF SIZE 24" 684 24.68% 19 100.00% 24.68% 100.00% 24.68% 26‐Apr‐11 18‐May‐11 0.00% 0.00%

PTJ8920 FITUP OF SIZE 16" 396 14.29% 11 100.00% 14.29% 100.00% 14.29% 28‐Apr‐11 11‐May‐11 0.00% 0.00%

PTJ8930 FITUP OF SIZE 20" 396 14.29% 11 100.00% 14.29% 100.00% 14.29% 9‐May‐11 21‐May‐11 0.00% 0.00%

PTJ8940 FITUP OF SIZE 18" 252 9.09% 7 100.00% 9.09% 100.00% 9.09% 16‐May‐11 23‐May‐11 0.00% 0.00%

WELDING&NDT 3072 40.85% 42 100.00% 40.85% 73.55% 30.05% 24-May-11 4-Jul-11 26.45% 10.81%

PTJ8950 WELDING OF SIZE 28" 1152 37.50% 18 100.00% 37.50% 100.00% 37.50% 24‐May‐11 13‐Jun‐11 0.00% 0.00%

PTJ8970 WELDING OF SIZE 16" 448 14.58% 7 100.00% 14.58% 100.00% 14.58% 12‐Jun‐11 19‐Jun‐11 0.00% 0.00%

PTJ8960 WELDING OF SIZE 24" 768 25.00% 12 100.00% 25.00% 78.57% 19.64% 15‐Jun‐11 28‐Jun‐11 21.43% 5.36%

PTJ8980 WELDING OF SIZE 20" 448 14.58% 7 100.00% 14.58% 12.50% 1.82% 25‐Jun‐11 2‐Jul‐11 87.50% 12.76%

PTJ8990 WELDING OF SIZE 18" 256 8.33% 4 100.00% 8.33% 0.00% 0.00% 30‐Jun‐11 4‐Jul‐11 100.00% 8.33%

CONDUCTORS AT ELEV ‐ 56200 1676 22.29% 54 74.58% 16.62% 1.93% 0.43% 25-Jun-11 17-Aug-11 72.65% 16.19%

FITUP 504 30.07% 34 100.00% 30.07% 6.43% 1.93% 25‐Jun‐11 28‐Jul‐11 93.57% 28.14%

PTJ9250 FITUP OF CONDUCTOR 324 64.29% 9 100.00% 64.29% 10.00% 6.43% 25‐Jun‐11 4‐Jul‐11 90.00% 57.86%

PTJ9260 FITUP OF CONDUCTOR SUPPORT 180 35.71% 5 100.00% 35.71% 0.00% 0.00% 24‐Jul‐11 28‐Jul‐11 100.00% 35.71%

WELDING & NDT 512 30.55% 31 81.25% 24.82% 0.00% 0.00% 5‐Jul‐11 4‐Aug‐11 81.25% 24.82%

PTJ9270 WELDING OF CONDUCTOR 320 62.50% 10 100.00% 62.50% 0.00% 0.00% 5‐Jul‐11 16‐Jul‐11 100.00% 62.50%

PTJ9280 WELDING OF CONDUCTOR SUPPORT 192 37.50% 6 50.00% 18.75% 0.00% 0.00% 30‐Jul‐11 4‐Aug‐11 50.00% 18.75%

CONDUCTORS ERECTION 660 39.38% 12 50.00% 19.69% 0.00% 0.00% 6‐Aug‐11 17‐Aug‐11 50.00% 19.69%

PTJ9290 ERECTION OF CONDUCTOR WITH ELEVATIONS 660 100.00% 11 50.00% 50.00% 0.00% 0.00% 6‐Aug‐11 17‐Aug‐11 50.00% 50.00%

ELEV ‐ 79000 5480 17.63% 82 92.29% 16.27% 0.00% 0.00% 23-Aug-11 12-Nov-11 92.29% 16.27%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\11/40

Page 125: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

FITUP 2664 48.61% 35 100.00% 48.61% 0.00% 0.00% 23-Aug-11 26-Sep-11 100.00% 48.61%

PTJ9010 FITUP OF SIZE 28" 1080 40.54% 15 100.00% 40.54% 0.00% 0.00% 23‐Aug‐11 12‐Sep‐11 100.00% 40.54%

PTJ9020 FITUP OF SIZE 16" 648 24.32% 9 100.00% 24.32% 0.00% 0.00% 7‐Sep‐11 17‐Sep‐11 100.00% 24.32%

PTJ9030 FITUP OF SIZE 24" 720 27.03% 10 100.00% 27.03% 0.00% 0.00% 13‐Sep‐11 24‐Sep‐11 100.00% 27.03%

PTJ9040 FITUP OF SIZE 20" 216 8.11% 6 100.00% 8.11% 0.00% 0.00% 20‐Sep‐11 26‐Sep‐11 100.00% 8.11%

WELDING&NDT 2816 51.39% 47 85.00% 43.68% 0.00% 0.00% 27-Sep-11 12-Nov-11 85.00% 43.68%

PTJ9050 WELDING OF SIZE 28" 1152 40.91% 18 85.00% 34.77% 0.00% 0.00% 27‐Sep‐11 18‐Oct‐11 85.00% 34.77%

PTJ9060 WELDING OF SIZE 16" 640 22.73% 10 85.00% 19.32% 0.00% 0.00% 13‐Oct‐11 24‐Oct‐11 85.00% 19.32%

PTJ9070 WELDING OF SIZE 24" 768 27.27% 12 85.00% 23.18% 0.00% 0.00% 20‐Oct‐11 2‐Nov‐11 85.00% 23.18%

PTJ9080 WELDING OF SIZE 20" 256 9.09% 4 85.00% 7.73% 0.00% 0.00% 2‐Nov‐11 12‐Nov‐11 85.00% 7.73%

PILE SLEEVES FABRICATION 12832 9.60% 87 7.29% 0.70% 0.00% 0.00% 05-Dec-11 29-Feb-12 7.29% 0.70%

AT LEG B1 3208 25.00% 64 0.22% 0.06% 0.00% 0.00% 5-Dec-11 6-Feb-12 0.22% 0.06%

PTJ9460 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 144 4.49% 4 5.00% 0.22% 0.00% 0.00% 5‐Dec‐11 8‐Dec‐11 5.00% 0.22%

PTJ9500 GIRTH WELD OF PILE SLEEVE 1152 35 91% 24 0 00% 0 00% 0 00% 14‐Dec‐11 11‐Jan‐12 0 00% 0 00% PTJ9500 GIRTH WELD OF PILE SLEEVE 1152 35.91% 24 0.00% 0.00% 0.00% 14‐Dec‐11 11‐Jan‐12 0.00% 0.00%

PTJ9470 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS 144 4.49% 4 0.00% 0.00% 0.00% 8‐Jan‐12 11‐Jan‐12 0.00% 0.00%

PTJ9510 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE 1248 38.90% 12 0.00% 0.00% 0.00% 12‐Jan‐12 25‐Jan‐12 0.00% 0.00%

PTJ9520 ERECTION OF PILE SLEEVE WITH LEGS 520 16.21% 10 0.00% 0.00% 0.00% 26‐Jan‐12 6‐Feb‐12 0.00% 0.00%

AT LEG A1 3208 25.00% 64 28.95% 7.24% 0.00% 0.00% 5-Dec-11 6-Feb-12 28.95% 7.24%

PTJ9320 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 144 4.49% 4 5.00% 0.22% 0.00% 0.00% 5‐Dec‐11 8‐Dec‐11 5.00% 0.22%

PTJ9360 GIRTH WELD OF PILE SLEEVE 1152 35.91% 24 80.00% 28.73% 0.00% 0.00% 14‐Dec‐11 11‐Jan‐12 80.00% 28.73%

PTJ9330 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS 144 4.49% 4 0.00% 0.00% 0.00% 8‐Jan‐12 11‐Jan‐12 0.00% 0.00%

PTJ9370 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE 1248 38.90% 12 0.00% 0.00% 0.00% 12‐Jan‐12 25‐Jan‐12 0.00% 0.00%

PTJ9380 ERECTION OF PILE SLEEVE WITH LEGS 520 16.21% 10 0.00% 0.00% 0.00% 26‐Jan‐12 6‐Feb‐12 0.00% 0.00%

AT LEG A2 3208 25.00% 64 0.00% 0.00% 0.00% 0.00% 28-Dec-11 29-Feb-12 0.00% 0.00%

PTJ9390 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 144 4.49% 4 0.00% 0.00% 0.00% 28‐Dec‐11 1‐Jan‐12 0.00% 0.00%

PTJ9430 GIRTH WELD OF PILE SLEEVE 1152 35.91% 24 0.00% 0.00% 0.00% 8‐Jan‐12 4‐Feb‐12 0.00% 0.00%

PTJ9400 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS 144 4.49% 4 0.00% 0.00% 0.00% 31‐Jan‐12 4‐Feb‐12 0.00% 0.00%

PTJ9440 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE 1248 38.90% 12 0.00% 0.00% 0.00% 5‐Feb‐12 18‐Feb‐12 0.00% 0.00%

PTJ9450 ERECTION OF PILE SLEEVE WITH LEGS 520 16.21% 10 0.00% 0.00% 0.00% 19‐Feb‐12 29‐Feb‐12 0.00% 0.00%

AT LEG B2 3208 25.00% 64 0.00% 0.00% 0.00% 0.00% 28-Dec-11 29-Feb-12 0.00% 0.00%

PTJ9530 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 144 4.49% 4 0.00% 0.00% 0.00% 28‐Dec‐11 1‐Jan‐12 0.00% 0.00%

PTJ9570 GIRTH WELD OF PILE SLEEVE 1152 35.91% 24 0.00% 0.00% 0.00% 8‐Jan‐12 4‐Feb‐12 0.00% 0.00%

PTJ9540 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS 144 4.49% 4 0.00% 0.00% 0.00% 31‐Jan‐12 4‐Feb‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\12/40

Page 126: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ9580 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE 1248 38.90% 12 0.00% 0.00% 0.00% 5‐Feb‐12 18‐Feb‐12 0.00% 0.00%

PTJ9590 ERECTION OF PILE SLEEVE WITH LEGS 520 16.21% 10 0.00% 0.00% 0.00% 19‐Feb‐12 29‐Feb‐12 0.00% 0.00%

JACKET ERECTION 11656 8.72% 257 0.00% 0.00% 3.00% 0.26% 18-Jun-11 29-Feb-12 -3.00% -0.26%

ELEV ‐79.0 476 4.08% 8 0.00% 0.00% 0.00% 0.00% 21-Nov-11 28-Nov-11 0.00% 0.00%

ERECTION ON ROW2 476 100.00% 8 0.00% 0.00% 0.00% 0.00% 21‐Nov‐11 28‐Nov‐11 0.00% 0.00%

PTJ9090 ERECTION OF ELEV AT ‐79 ON ROW 2 476 100.00% 7 0.00% 0.00% 0.00% 21‐Nov‐11 28‐Nov‐11 0.00% 0.00%

ELEV +6.4 476 4.08% 9 0.00% 0.00% 0.00% 0.00% 4-Jan-12 12-Jan-12 0.00% 0.00%

ERECTION ON ROW2 476 100.00% 9 0.00% 0.00% 0.00% 0.00% 4‐Jan‐12 12‐Jan‐12 0.00% 0.00%

PTJ8690 ERECTION OF ELEV AT + 6.4 ON ROW 2 476 100.00% 7 0.00% 0.00% 0.00% 4‐Jan‐12 12‐Jan‐12 0.00% 0.00%

ELEV ‐56.2 476 4.08% 8 0.00% 0.00% 0.00% 0.00% 13-Nov-11 20-Nov-11 0.00% 0.00%

ERECTION ON ROW2 476 100.00% 8 0.00% 0.00% 0.00% 0.00% 13‐Nov‐11 20‐Nov‐11 0.00% 0.00%

PTJ9000 ERECTION OF ELEV AT ‐56.2 ON ROW 2 476 100.00% 7 0.00% 0.00% 0.00% 13‐Nov‐11 20‐Nov‐11 0.00% 0.00%

ELEV ‐ 33.4 476 4.08% 8 0.00% 0.00% 0.00% 0.00% 30-Nov-11 7-Dec-11 0.00% 0.00%

ERECTION ON ROW2 476 100 00% 8 0 00% 0 00% 0 00% 0 00% 30‐Nov‐11 7‐Dec‐11 0 00% 0 00% ERECTION ON ROW2 476 100.00% 8 0.00% 0.00% 0.00% 0.00% 30‐Nov‐11 7‐Dec‐11 0.00% 0.00%

PTJ8890 ERECTION OF ELEV AT ‐33.4 ON ROW 2 476 100.00% 7 0.00% 0.00% 0.00% 30‐Nov‐11 7‐Dec‐11 0.00% 0.00%

ROW 2 2040 17.50% 148 0.00% 0.00% 17.16% 3.00% 18-Jun-11 12-Nov-11 -17.16% -3.00%

ERECTION 2000 98.04% 146 0.00% 0.00% 17.50% 17.16% 18‐Jun‐11 10‐Nov‐11 ‐17.50% ‐17.16%

HORIZONTAL 500 25.00% 17 0.00% 0.00% 52.00% 13.00% 18‐Jun‐11 4‐Jul‐11 ‐52.00% ‐13.00%

PTJ9340 FITUP OF HORIZONTAL ON LEG 180 36.00% 5 0.00% 100.00% 36.00% 18‐Jun‐11 22‐Jun‐11 ‐100.00% ‐36.00%

PTJ9350 WELDING OF HORIZONTAL ON LEG 320 64.00% 10 0.00% 25.00% 16.00% 23‐Jun‐11 4‐Jul‐11 ‐25.00% ‐16.00%

DIAGONAL BRACES 1000 50.00% 36 0.00% 0.00% 9.00% 4.50% 23‐Jun‐11 28‐Jul‐11 ‐9.00% ‐4.50%

PTJ8070 FITUP OF DIAGONAL ON LEG 360 36.00% 10 0.00% 25.00% 9.00% 23‐Jun‐11 4‐Jul‐11 ‐25.00% ‐9.00%

PTJ8080 WELDING OF DIAGONAL ON LEG 640 64.00% 20 0.00% 0.00% 0.00% 5‐Jul‐11 28‐Jul‐11 0.00% 0.00%

VERTICAL 500 25.00% 23 0.00% 0.00% 0.00% 0.00% 19‐Oct‐11 10‐Nov‐11 0.00% 0.00%

PTJ8090 FITUP OF VERTICAL BRACES WITH ROW 2 BRACES 180 36.00% 5 0.00% 0.00% 0.00% 19‐Oct‐11 24‐Oct‐11 0.00% 0.00%

PTJ8100 WELDING OF VERTICAL BRACES WITH ROW 2 BRACES 320 64.00% 10 0.00% 0.00% 0.00% 25‐Oct‐11 10‐Nov‐11 0.00% 0.00%

LIFTING OVER TRUSS RUNNER 40 1.96% 1 0.00% 0.00% 0.00% 0.00% 12‐Nov‐11 12‐Nov‐11 0.00% 0.00%

PTJ8110 LIFTING OVER TRUSS RUNNERS 40 100.00% 1 0.00% 0.00% 0.00% 12‐Nov‐11 12‐Nov‐11 0.00% 0.00%

ELEV ‐10.6 476 4.08% 8 0.00% 0.00% 0.00% 0.00% 18‐Dec‐11 25‐Dec‐11 0.00% 0.00%

ERECTION ON ROW2 476 100.00% 8 0.00% 0.00% 0.00% 0.00% 18‐Dec‐11 25‐Dec‐11 0.00% 0.00%

PTJ8780 ERECTION OF ELEV AT ‐10.6 ON ROW 2 476 100.00% 7 0.00% 0.00% 0.00% 18‐Dec‐11 25‐Dec‐11 0.00% 0.00%

ROW A 1224 10.50% 108 0.00% 0.00% 0.00% 0.00% 13‐Sep‐11 29‐Dec‐11 0.00% 0.00%

ERECTION 1224 100.00% 108 0.00% 0.00% 0.00% 0.00% 13‐Sep‐11 29‐Dec‐11 0.00% 0.00%

PTJ8300 ERECTION X BRACES BETWEEN ‐56.2 & ‐79.0 408 33.33% 6 0.00% 0.00% 0.00% 13‐Sep‐11 19‐Sep‐11 0.00% 0.00%

PTJ8320 ERECTION X BRACES BETWEEN ‐33.4 & ‐56.2 272 22.22% 4 0.00% 0.00% 0.00% 21‐Nov‐11 24‐Nov‐11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\13/40

Page 127: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ8310 ERECTION X BRACES BETWEEN ‐10.6 & ‐33.4 272 22.22% 4 0.00% 0.00% 0.00% 8‐Dec‐11 12‐Dec‐11 0.00% 0.00%

PTJ8290 ERECTION X BRACES BETWEEN +6.4 & ‐10.6 272 22.22% 4 0.00% 0.00% 0.00% 26‐Dec‐11 29‐Dec‐11 0.00% 0.00%

ROW B 1224 10.50% 106 0.00% 0.00% 0.00% 0.00% 20‐Sep‐11 3‐Jan‐12 0.00% 0.00%

ERECTION 1224 100.00% 106 0.00% 0.00% 0.00% 0.00% 20‐Sep‐11 3‐Jan‐12 0.00% 0.00%

PTJ8420 ERECTION X BRACES BETWEEN ‐56.2 & ‐79.0 408 33.33% 6 0.00% 0.00% 0.00% 20‐Sep‐11 26‐Sep‐11 0.00% 0.00%

PTJ8440 ERECTION X BRACES BETWEEN ‐33.4 & ‐56.2 272 22.22% 4 0.00% 0.00% 0.00% 26‐Nov‐11 29‐Nov‐11 0.00% 0.00%

PTJ8430 ERECTION X BRACES BETWEEN ‐10.6 & ‐33.4 272 22.22% 4 0.00% 0.00% 0.00% 13‐Dec‐11 17‐Dec‐11 0.00% 0.00%

PTJ8410 ERECTION X BRACES BETWEEN +6.4 & ‐10.6 272 22.22% 4 0.00% 0.00% 0.00% 31‐Dec‐11 3‐Jan‐12 0.00% 0.00%

ROW C 816 7.00% 22 0.00% 0.00% 0.00% 0.00% 21‐Nov‐11 12‐Dec‐11 0.00% 0.00%

PTJ8510 ERECTION ROW C BRACES BETWEEN ‐56.2 & ‐79.0 272 33.33% 4 0.00% 0.00% 0.00% 21‐Nov‐11 24‐Nov‐11 0.00% 0.00%

PTJ8520 ERECTION ROW C BRACES BETWEEN ‐33.4 & ‐56.2 272 33.33% 4 0.00% 0.00% 0.00% 8‐Dec‐11 12‐Dec‐11 0.00% 0.00%

PTJ8530 ERECTION ROW C BRACES BETWEEN ‐ 10.6 & ‐33.4 272 33.33% 4 0.00% 0.00% 0.00% 8‐Dec‐11 12‐Dec‐11 0.00% 0.00%

ROW D 408 3.50% 29 0.00% 0.00% 0.00% 0.00% 29‐Nov‐11 27‐Dec‐11 0.00% 0.00%

PTJ8600 ERECTION ROW D BRACES BETWEEN ‐56.2 & ‐79.0 136 33.33% 2 0.00% 0.00% 0.00% 29‐Nov‐11 30‐Nov‐11 0.00% 0.00%

PTJ8610 ERECTION ROW D BRACES BETWEEN ‐33.4 & ‐56.2 136 33.33% 2 0.00% 0.00% 0.00% 8‐Dec‐11 10‐Dec‐11 0.00% 0.00%

PTJ8620 ERECTION ROW D BRACES BETWEEN ‐10.6 & ‐33.4 136 33.33% 2 0.00% 0.00% 0.00% 26‐Dec‐11 27‐Dec‐11 0.00% 0.00%

ROW 3 816 7.00% 5 0.00% 0.00% 0.00% 0.00% 2‐Feb‐12 6‐Feb‐12 0.00% 0.00%

PTJ8180 ERECTION ROW 3 BRACES BETWEEN ‐10.6 & ‐33.4 272 33.33% 4 0.00% 0.00% 0.00% 2‐Feb‐12 6‐Feb‐12 0.00% 0.00%

PTJ8190 ERECTION ROW 3 BRACES BETWEEN ‐33.4 & ‐56.2 272 33.33% 4 0.00% 0.00% 0.00% 2‐Feb‐12 6‐Feb‐12 0.00% 0.00%

PTJ8200 ERECTION ROW 3 BRACES BETWEEN ‐56.2 & ‐79.0 272 33.33% 4 0.00% 0.00% 0.00% 2‐Feb‐12 6‐Feb‐12 0.00% 0.00%

ROW 1 2748 23.58% 152 0.00% 0.00% 0.00% 0.00% 1‐Oct‐11 29‐Feb‐12 0.00% 0.00%

HORIZONTAL 500 18.20% 18 0.00% 0.00% 0.00% 0.00% 1‐Oct‐11 18‐Oct‐11 0.00% 0.00%

PTJ9480 FITUP OF HORIZONTAL ON LEG 180 36.00% 5 0.00% 0.00% 0.00% 1‐Oct‐11 5‐Oct‐11 0.00% 0.00%

PTJ9490 WELDING OF HORIZONTAL ON LEG 320 64.00% 10 0.00% 0.00% 0.00% 8‐Oct‐11 18‐Oct‐11 0.00% 0.00%

DIAGONAL BRACES 1000 36.39% 40 0.00% 0.00% 0.00% 0.00% 8‐Oct‐11 16‐Nov‐11 0.00% 0.00%

PTJ9410 FITUP OF DIAGONAL ON LEG 360 36.00% 10 0.00% 0.00% 0.00% 8‐Oct‐11 18‐Oct‐11 0.00% 0.00%

PTJ9420 WELDING OF DIAGONAL ON LEG 640 64.00% 20 0.00% 0.00% 0.00% 19‐Oct‐11 16‐Nov‐11 0.00% 0.00%

ERECTION ROW 1 1248 45.41% 23 0.00% 0.00% 0.00% 0.00% 7‐Feb‐12 29‐Feb‐12 0.00% 0.00%

PTJ8000 LIFTING OF ROW 1 OVER ELAVATIONS & ROW A,B 128 10.26% 1 0.00% 0.00% 0.00% 7‐Feb‐12 7‐Feb‐12 0.00% 0.00%

PTJ8010 FITUP OF ROW 1 OVER ELAVATIONS & ROW A,B 160 12.82% 4 0.00% 0.00% 0.00% 8‐Feb‐12 12‐Feb‐12 0.00% 0.00%

PTJ8020 WELDING OF ROW 1 OVER ELAVATIONS & ROW A,B 960 76.92% 15 0.00% 0.00% 0.00% 13‐Feb‐12 29‐Feb‐12 0.00% 0.00%

JACKET MISCELLANEOUS FABRICATION 108888 44.20% 342 15.59% 6.89% 11.04% 4.88% 31‐Mar‐11 06‐Mar‐12 4.55% 2.01%

PTJ9600 Jacket miscellaneous fabrication start 0 0.00% 0 0.00% 0.00% 0.00% 3‐Sep‐11 3‐Sep‐11 0.00% 0.00%

PTJ11020 Jacket miscellaneous fabrication finish 0 0.00% 0 0.00% 0.00% 0.00% 6‐Mar‐12 6‐Mar‐12 0.00% 0.00%

BOAT LAND 8804 8.09% 65 0.00% 0.00% 0.00% 0.00% 02-Jan-12 06-Mar-12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\14/40

Page 128: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

Main Legs 236 2.68% 5 0.00% 0.00% 0.00% 0.00% 2‐Jan‐12 6‐Jan‐12 0.00% 0.00%

BL1000 Cutting & Assembly 108 45.76% 3 0.00% 0.00% 0.00% 2‐Jan‐12 4‐Jan‐12 0.00% 0.00%

BL1010 Welding & NDT 128 54.24% 4 0.00% 0.00% 0.00% 3‐Jan‐12 6‐Jan‐12 0.00% 0.00%

Back Elevation 880 10.00% 20 0.00% 0.00% 0.00% 0.00% 7‐Jan‐12 26‐Jan‐12 0.00% 0.00%

BL1040 Cutting & Assembly 400 45.45% 10 0.00% 0.00% 0.00% 7‐Jan‐12 16‐Jan‐12 0.00% 0.00%

BL1050 Welding & NDT 480 54.55% 15 0.00% 0.00% 0.00% 12‐Jan‐12 26‐Jan‐12 0.00% 0.00%

Front Elevation 3552 40.35% 21 0.00% 0.00% 0.00% 0.00% 11‐Feb‐12 2‐Mar‐12 0.00% 0.00%

BL1020 Cutting & Assembly 1632 45.95% 12 0.00% 0.00% 0.00% 11‐Feb‐12 22‐Feb‐12 0.00% 0.00%

BL1030 Welding & NDT 1920 54.05% 15 0.00% 0.00% 0.00% 17‐Feb‐12 2‐Mar‐12 0.00% 0.00%

Plan at Elev. +2.6 336 3.82% 14 0.00% 0.00% 0.00% 0.00% 28‐Jan‐12 10‐Feb‐12 0.00% 0.00%

BL1060 Cutting & Assembly 144 42.86% 4 0.00% 0.00% 0.00% 28‐Jan‐12 31‐Jan‐12 0.00% 0.00%

BL1070 Welding & NDT 192 57.14% 6 0.00% 0.00% 0.00% 5‐Feb‐12 10‐Feb‐12 0.00% 0.00%

Plan at Elev. +2.4 404 4.59% 15 0.00% 0.00% 0.00% 0.00% 27‐Jan‐12 10‐Feb‐12 0.00% 0.00%

BL1080 Cutting & Assembly 180 44.55% 5 0.00% 0.00% 0.00% 27‐Jan‐12 31‐Jan‐12 0.00% 0.00%

BL1090 Welding & NDT 224 55.45% 7 0.00% 0.00% 0.00% 4‐Feb‐12 10‐Feb‐12 0.00% 0.00%

Plan at Elev. ‐30 404 4.59% 15 0.00% 0.00% 0.00% 0.00% 27‐Jan‐12 10‐Feb‐12 0.00% 0.00%

BL1100 Cutting & Assembly 180 44.55% 5 0.00% 0.00% 0.00% 27‐Jan‐12 31‐Jan‐12 0.00% 0.00%

BL1110 Welding & NDT 224 55.45% 7 0.00% 0.00% 0.00% 4‐Feb‐12 10‐Feb‐12 0.00% 0.00%

Boat landing Sections (a,b.c,d,e) 336 3.82% 10 0.00% 0.00% 0.00% 0.00% 1‐Feb‐12 10‐Feb‐12 0.00% 0.00%

BL1120 Cutting & Assembly 144 42.86% 4 0.00% 0.00% 0.00% 1‐Feb‐12 4‐Feb‐12 0.00% 0.00%

BL1130 Welding & NDT 192 57.14% 6 0.00% 0.00% 0.00% 5‐Feb‐12 10‐Feb‐12 0.00% 0.00%

Grating 56 0.64% 18 0.00% 0.00% 0.00% 0.00% 18‐Feb‐12 6‐Mar‐12 0.00% 0.00%

BL1140 Trial Fit and Grating Stopper Fixation 36 64.29% 1 0.00% 0.00% 0.00% 18‐Feb‐12 18‐Feb‐12 0.00% 0.00%

BL1150 Final Installation 20 35.71% 1 0.00% 0.00% 0.00% 6‐Mar‐12 6‐Mar‐12 0.00% 0.00%

Stairs & Ladders 268 3.04% 8 0.00% 0.00% 0.00% 0.00% 24‐Feb‐12 2‐Mar‐12 0.00% 0.00%

BL1160 Fabrication 160 59.70% 5 0.00% 0.00% 0.00% 24‐Feb‐12 28‐Feb‐12 0.00% 0.00%

BL1170 Installation 108 40.30% 3 0.00% 0.00% 0.00% 29‐Feb‐12 2‐Mar‐12 0.00% 0.00%

Handrails 200 2.27% 16 0.00% 0.00% 0.00% 0.00% 20‐Feb‐12 6‐Mar‐12 0.00% 0.00%

BL1200 Fabrication 128 64.00% 4 0.00% 0.00% 0.00% 20‐Feb‐12 23‐Feb‐12 0.00% 0.00%

BL1210 Installation 72 36.00% 2 0.00% 0.00% 0.00% 5‐Mar‐12 6‐Mar‐12 0.00% 0.00%

Mooring Cleat 68 0.77% 2 0.00% 0.00% 0.00% 0.00% 1‐Mar‐12 2‐Mar‐12 0.00% 0.00%

BL1220 Fabrication 32 47.06% 1 0.00% 0.00% 0.00% 1‐Mar‐12 1‐Mar‐12 0.00% 0.00%

BL1230 Installation 36 52.94% 1 0.00% 0.00% 0.00% 2‐Mar‐12 2‐Mar‐12 0.00% 0.00%

Rubber 72 0.82% 1 0.00% 0.00% 0.00% 0.00% 6‐Mar‐12 6‐Mar‐12 0.00% 0.00%

BL1240 Installation of Rubber & Tightening 72 100.00% 1 0.00% 0.00% 0.00% 6‐Mar‐12 6‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\15/40

Page 129: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

Lower Support 716 8.13% 27 0.00% 0.00% 0.00% 0.00% 5‐Feb‐12 2‐Mar‐12 0.00% 0.00%

Fabrication 540 75.42% 16 0.00% 0.00% 0.00% 0.00% 5‐Feb‐12 20‐Feb‐12 0.00% 0.00%

BL1250 Cutting & Assembly 252 46.67% 7 0.00% 0.00% 0.00% 5‐Feb‐12 11‐Feb‐12 0.00% 0.00%

BL1260 Welding & NDT 288 53.33% 9 0.00% 0.00% 0.00% 12‐Feb‐12 20‐Feb‐12 0.00% 0.00%

Installation with Jacket legs 176 24.58% 4 0.00% 0.00% 0.00% 0.00% 28‐Feb‐12 2‐Mar‐12 0.00% 0.00%

BL1270 Profiling Template & Assembly with Legs 80 45.45% 2 0.00% 0.00% 0.00% 28‐Feb‐12 29‐Feb‐12 0.00% 0.00%

BL1280 Welding & NDT 96 54.55% 3 0.00% 0.00% 0.00% 29‐Feb‐12 2‐Mar‐12 0.00% 0.00%

Upper Support 972 11.04% 23 0.00% 0.00% 0.00% 0.00% 9‐Feb‐12 2‐Mar‐12 0.00% 0.00%

Fabrication 636 65.43% 19 0.00% 0.00% 0.00% 0.00% 9‐Feb‐12 27‐Feb‐12 0.00% 0.00%

BL1290 Cutting & Assembly 252 39.62% 7 0.00% 0.00% 0.00% 9‐Feb‐12 15‐Feb‐12 0.00% 0.00%

BL1300 Welding & NDT 384 60.38% 12 0.00% 0.00% 0.00% 16‐Feb‐12 27‐Feb‐12 0.00% 0.00%

Installation with Jacket legs 336 34.57% 4 0.00% 0.00% 0.00% 0.00% 28‐Feb‐12 2‐Mar‐12 0.00% 0.00%

BL1310 Profiling Template & Assembly with Legs 144 42.86% 2 0.00% 0.00% 0.00% 28‐Feb‐12 29‐Feb‐12 0.00% 0.00%

BL1320 Welding & NDT 192 57.14% 3 0.00% 0.00% 0.00% 29‐Feb‐12 2‐Mar‐12 0.00% 0.00%

Boat landing trial fit 304 3.45% 2 0.00% 0.00% 0.00% 0.00% 3‐Mar‐12 4‐Mar‐12 0.00% 0.00%

BL1330 Boat Landing Trial Fit 304 100.00% 2 0.00% 0.00% 0.00% 3‐Mar‐12 4‐Mar‐12 0.00% 0.00%

BARGE BUMPER 2952 2.71% 30 0.00% 0.00% 0.00% 0.00% 06-Feb-12 06-Mar-12 0.00% 0.00%

Main Pipe 504 17.07% 15 0.00% 0.00% 0.00% 0.00% 6‐Feb‐12 20‐Feb‐12 0.00% 0.00%

BB1000 Cutting & Assembly 216 42.86% 6 0.00% 0.00% 0.00% 6‐Feb‐12 11‐Feb‐12 0.00% 0.00%

BB1010 Welding & NDT 288 57.14% 9 0.00% 0.00% 0.00% 12‐Feb‐12 20‐Feb‐12 0.00% 0.00%

Upper Support 1312 44.44% 28 0.00% 0.00% 0.00% 0.00% 6‐Feb‐12 4‐Mar‐12 0.00% 0.00%

Fabrication 976 74.39% 23 0.00% 0.00% 0.00% 0.00% 6‐Feb‐12 28‐Feb‐12 0.00% 0.00%

BB1060 Cutting & Assembly 432 44.26% 12 0.00% 0.00% 0.00% 6‐Feb‐12 17‐Feb‐12 0.00% 0.00%

BB1070 Welding & NDT 544 55.74% 17 0.00% 0.00% 0.00% 12‐Feb‐12 28‐Feb‐12 0.00% 0.00%

Installation with Jacket legs 336 25.61% 5 0.00% 0.00% 0.00% 0.00% 29‐Feb‐12 4‐Mar‐12 0.00% 0.00%

BB1080 Profiling Template & Assembly with Legs 144 42.86% 2 0.00% 0.00% 0.00% 29‐Feb‐12 1‐Mar‐12 0.00% 0.00%

BB1090 Welding & NDT 192 57.14% 3 0.00% 0.00% 0.00% 2‐Mar‐12 4‐Mar‐12 0.00% 0.00%

Lower Support 976 33.06% 24 0.00% 0.00% 0.00% 0.00% 10‐Feb‐12 4‐Mar‐12 0.00% 0.00%

Installation with Jacket legs 336 34.43% 5 0.00% 0.00% 0.00% 0.00% 29‐Feb‐12 4‐Mar‐12 0.00% 0.00%

BB1040 Profiling Template & Assembly with Legs 144 42.86% 2 0.00% 0.00% 0.00% 29‐Feb‐12 1‐Mar‐12 0.00% 0.00%

BB1050 Welding & NDT 192 57.14% 3 0.00% 0.00% 0.00% 2‐Mar‐12 4‐Mar‐12 0.00% 0.00%

Fabrication 640 65.57% 19 0.00% 0.00% 0.00% 0.00% 10‐Feb‐12 28‐Feb‐12 0.00% 0.00%

BB1020 Cutting & Assembly 288 45.00% 8 0.00% 0.00% 0.00% 10‐Feb‐12 17‐Feb‐12 0.00% 0.00%

BB1030 Welding & NDT 352 55.00% 11 0.00% 0.00% 0.00% 18‐Feb‐12 28‐Feb‐12 0.00% 0.00%

Barge Bumper Trial Fit 160 5.42% 2 0.00% 0.00% 0.00% 0.00% 5‐Mar‐12 6‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\16/40

Page 130: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

BB1100 Barge Bumper Trial Fit 160 100.00% 2 0.00% 0.00% 0.00% 5‐Mar‐12 6‐Mar‐12 0.00% 0.00%

RISER 16" & CLAMPS 2472 2.27% 62 0.00% 0.00% 0.00% 0.00% 03-Sep-11 03-Nov-11 0.00% 0.00%

PTJ10590 RISER 16 " FABRICATION 792 32.04% 22 0.00% 0.00% 0.00% 3‐Sep‐11 27‐Sep‐11 0.00% 0.00%

PTJ10620 CLAMPS FOR RISER 16 " FABRICATION 648 26.21% 18 0.00% 0.00% 0.00% 3‐Sep‐11 22‐Sep‐11 0.00% 0.00%

PTJ10600 RISER COATING 168 6.80% 7 0.00% 0.00% 0.00% 28‐Sep‐11 5‐Oct‐11 0.00% 0.00%

PTJ10630 CLAMPS FOR RISER 16 " INSTALLATION 504 20.39% 14 0.00% 0.00% 0.00% 8‐Oct‐11 23‐Oct‐11 0.00% 0.00%

PTJ10610 RISER 16 " INSTALLATION 360 14.56% 10 0.00% 0.00% 0.00% 24‐Oct‐11 3‐Nov‐11 0.00% 0.00%

J‐TUBE 16 " & CLAMPS 1440 1.32% 51 0.00% 0.00% 0.00% 0.00% 03-Sep-11 23-Oct-11 0.00% 0.00%

PTJ10640 J‐TUBE16 " FABRICATION 504 35.00% 14 0.00% 0.00% 0.00% 3‐Sep‐11 18‐Sep‐11 0.00% 0.00%

PTJ10650 CLAMPS FOR J‐TUBE16 " FABRICATION 432 30.00% 12 0.00% 0.00% 0.00% 3‐Sep‐11 15‐Sep‐11 0.00% 0.00%

PTJ10660 CLAMPS FOR J‐TUBE16 " INSTALLATION 360 25.00% 10 0.00% 0.00% 0.00% 8‐Oct‐11 18‐Oct‐11 0.00% 0.00%

PTJ10680 J‐TUBE16 " INSTALLATION 144 10.00% 4 0.00% 0.00% 0.00% 19‐Oct‐11 23‐Oct‐11 0.00% 0.00%

FUTURE J‐TUBE CLAMPS 504 0.46% 41 0.00% 0.00% 0.00% 0.00% 03-Sep-11 13-Oct-11 0.00% 0.00%

PTJ10690 CLAMPS FOR FUTURE J‐TUBE FABRICATION 288 57.14% 8 0.00% 0.00% 0.00% 3‐Sep‐11 11‐Sep‐11 0.00% 0.00%

PTJ10700 CLAMPS FOR FUTURE J‐TUBE INSTALLATION 216 42.86% 6 0.00% 0.00% 0.00% 8‐Oct‐11 13‐Oct‐11 0.00% 0.00%

SUMP CAISSON 30" 1384 1.27% 21 0.00% 0.00% 0.00% 0.00% 14-Feb-12 05-Mar-12 0.00% 0.00%

PTJ10710 SUMP CAISSON 30 " FABRICATION 952 68.79% 14 0.00% 0.00% 0.00% 14‐Feb‐12 29‐Feb‐12 0.00% 0.00%

PTJ10720 SUPPORTS SUMP CAISSON 30 " FABRICATION 72 5.20% 2 0.00% 0.00% 0.00% 21‐Feb‐12 22‐Feb‐12 0.00% 0.00%

PTJ10730 SUPPORTS SUMP CAISSON 30 " INSTALLATION 216 15.61% 6 0.00% 0.00% 0.00% 23‐Feb‐12 29‐Feb‐12 0.00% 0.00%

PTJ10740 SUPPORTS SUMP CAISSON 30 " INSTALLATION 144 10.40% 4 0.00% 0.00% 0.00% 1‐Mar‐12 5‐Mar‐12 0.00% 0.00%

MUD MAT 2880 2.64% 100 0.00% 0.00% 0.00% 0.00% 03-Sep-11 11-Dec-11 0.00% 0.00%

PTJ10750 MUD MAT FABRICATION 2160 75.00% 60 0.00% 0.00% 0.00% 3‐Sep‐11 17‐Nov‐11 0.00% 0.00%

PTJ10760 MUD MAT INSTALLATION 720 25.00% 20 0.00% 0.00% 0.00% 19‐Nov‐11 11‐Dec‐11 0.00% 0.00%

WALK WAY & STAIRS 1712 1.57% 55 0.00% 0.00% 0.00% 0.00% 03-Sep-11 27-Oct-11 0.00% 0.00%

PTJ10350 FITUP OF WALK WAY & STARIR 384 22.43% 12 0.00% 0.00% 0.00% 3‐Sep‐11 15‐Sep‐11 0.00% 0.00%

PTJ10360 WELDING & NDT OF WALK WAY & STARIRS 512 29.91% 16 0.00% 0.00% 0.00% 17‐Sep‐11 4‐Oct‐11 0.00% 0.00%

PTJ10370 ERECTION WALK WAY ON TOP ELEVATION 816 47.66% 12 0.00% 0.00% 0.00% 15‐Oct‐11 27‐Oct‐11 0.00% 0.00%

LAUNCH RUNNERS 19224 17.65% 141 85.67% 15.13% 62.53% 11.04% 31-Mar-11 18-Aug-11 23.14% 4.09%

AT ROW D 9612 50.00% 141 85.67% 42.84% 62.53% 31.27% 31-Mar-11 18-Aug-11 23.14% 11.57%

FROM EL. ‐33400 TO ‐10600 3204 33.33% 59 85.67% 28.56% 100.00% 33.33% 31-Mar-11 28-May-11 -14.33% -4.78%

PTJ9820 FITUP OF LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6 2100 65.54% 35 95.00% 62.27% 100.00% 65.54% 31‐Mar‐11 14‐May‐11 ‐5.00% ‐3.28%

PTJ9830 WELDING & NDT LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6 1000 31.21% 25 75.00% 23.41% 100.00% 31.21% 26‐Apr‐11 25‐May‐11 ‐25.00% ‐7.80%

PTJ9840 LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY 104 3.25% 2 0.00% 100.00% 3.25% 26‐May‐11 28‐May‐11 ‐100.00% ‐3.25%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\17/40

Page 131: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

FROM EL. ‐56200 TO ‐33400 3204 33.33% 54 85.67% 28.56% 85.99% 28.66% 15-May-11 7-Jul-11 -0.32% -0.11%

PTJ9790 FITUP OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4 2100 65.54% 35 95.00% 62.27% 100.00% 65.54% 15‐May‐11 23‐Jun‐11 ‐5.00% ‐3.28%

PTJ9800 WELDING & NDT OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4 1000 31.21% 25 75.00% 23.41% 65.52% 20.45% 7‐Jun‐11 5‐Jul‐11 9.48% 2.96%

PTJ9810 LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY 104 3.25% 2 0.00% 0.00% 0.00% 6‐Jul‐11 7‐Jul‐11 0.00% 0.00%

FROM EL. ‐79000 TO ‐56200 3204 33.33% 55 85.67% 28.56% 1.60% 0.53% 25-Jun-11 18-Aug-11 84.08% 28.03%

PTJ9760 FITUP OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 2100 65.54% 35 95.00% 62.27% 2.44% 1.60% 25‐Jun‐11 4‐Aug‐11 92.56% 60.67%

PTJ9770 WELDING & NDT OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 1000 31.21% 25 75.00% 23.41% 0.00% 0.00% 18‐Jul‐11 16‐Aug‐11 75.00% 23.41%

PTJ9780 LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY 104 3.25% 2 0.00% 0.00% 0.00% 17‐Aug‐11 18‐Aug‐11 0.00% 0.00%

AT ROW C 9612 50.00% 141 85.67% 42.84% 62.53% 31.27% 31-Mar-11 18-Aug-11 23.14% 11.57%

FROM EL. ‐33400 TO ‐10600 3204 33.33% 59 85.67% 28.56% 100.00% 33.33% 31-Mar-11 28-May-11 -14.33% -4.78%

PTJ9730 FITUP OF LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6 2100 65.54% 35 95.00% 62.27% 100.00% 65.54% 31‐Mar‐11 14‐May‐11 ‐5.00% ‐3.28%

PTJ9740 WELDING & NDT LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6 1000 31.21% 25 75.00% 23.41% 100.00% 31.21% 26‐Apr‐11 25‐May‐11 ‐25.00% ‐7.80%

PTJ9750 LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY 104 3.25% 2 0.00% 100.00% 3.25% 26‐May‐11 28‐May‐11 ‐100.00% ‐3.25%

FROM EL. ‐79000 TO ‐56200 3204 33.33% 55 85.67% 28.56% 1.60% 0.53% 25-Jun-11 18-Aug-11 84.08% 28.03%

PTJ9670 FITUP OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 2100 65.54% 35 95.00% 62.27% 2.44% 1.60% 25‐Jun‐11 4‐Aug‐11 92.56% 60.67%

PTJ9680 WELDING & NDT OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 1000 31.21% 25 75.00% 23.41% 0.00% 0.00% 18‐Jul‐11 16‐Aug‐11 75.00% 23.41%

PTJ9690 LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY 104 3.25% 2 0.00% 0.00% 0.00% 17‐Aug‐11 18‐Aug‐11 0.00% 0.00%

FROM EL. ‐56200 TO ‐33400 3204 33.33% 54 85.67% 28.56% 85.99% 28.66% 15-May-11 7-Jul-11 -0.32% -0.11%

PTJ9700 FITUP OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4 2100 65.54% 35 95.00% 62.27% 100.00% 65.54% 15‐May‐11 23‐Jun‐11 ‐5.00% ‐3.28%

PTJ9710 WELDING & NDT OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4 1000 31.21% 25 75.00% 23.41% 65.52% 20.45% 7‐Jun‐11 5‐Jul‐11 9.48% 2.96%

PTJ9720 LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY 104 3.25% 2 0.00% 0.00% 0.00% 6‐Jul‐11 7‐Jul‐11 0.00% 0.00%

ANODES 3564 3.27% 195 14.04% 0.46% 0.00% 0.00% 25-Aug-11 06-Mar-12 14.04% 0.46%

PTJ10000 INSTALL ANODES FOR ROW A 468 13.13% 13 0.00% 0.00% 0.00% 25‐Aug‐11 12‐Sep‐11 0.00% 0.00%

PTJ10140 INSTALL ANODES FOR ROW B 576 16.16% 8 65.00% 10.51% 0.00% 0.00% 11‐Sep‐11 19‐Sep‐11 65.00% 10.51%

PTJ10220 INSTALL ANODES FOR ELEV ‐56.2 252 7.07% 7 0.00% 0.00% 0.00% 30‐Oct‐11 12‐Nov‐11 0.00% 0.00%

PTJ10230 INSTALL ANODES FOR ELEV ‐79.0 252 7.07% 7 0.00% 0.00% 0.00% 13‐Nov‐11 20‐Nov‐11 0.00% 0.00%

PTJ10180 INSTALL ANODES FOR ROW C 216 6.06% 6 0.00% 0.00% 0.00% 14‐Nov‐11 20‐Nov‐11 0.00% 0.00%

PTJ10190 INSTALL ANODES FOR ROW D 216 6.06% 6 0.00% 0.00% 0.00% 22‐Nov‐11 28‐Nov‐11 0.00% 0.00%

PTJ10210 INSTALL ANODES FOR ELEV ‐33.4 180 5.05% 5 0.00% 0.00% 0.00% 24‐Nov‐11 29‐Nov‐11 0.00% 0.00%

PTJ10200 INSTALL ANODES FOR ELEV ‐10.6 180 5.05% 5 0.00% 0.00% 0.00% 12‐Dec‐11 17‐Dec‐11 0.00% 0.00%

PTJ10150 INSTALL ANODES FOR ROW 1 360 10.10% 10 0.00% 0.00% 0.00% 18‐Jan‐12 29‐Jan‐12 0.00% 0.00%

PTJ10170 INSTALL ANODES FOR ROW 3 216 6.06% 6 0.00% 0.00% 0.00% 26‐Jan‐12 1‐Feb‐12 0.00% 0.00%

PTJ10160 INSTALL ANODES FOR ROW 2 360 10.10% 10 35.00% 3.54% 0.00% 0.00% 11‐Feb‐12 21‐Feb‐12 35.00% 3.54%

PTJ10240 INSTALL ANODES FOR MUD MAT 252 7.07% 7 0.00% 0.00% 0.00% 28‐Feb‐12 6‐Mar‐12 0.00% 0.00%

PTJ10250 INSTALL ANODES FOR SUMP CASSOIN 36 1.01% 1 0.00% 0.00% 0.00% 6‐Mar‐12 6‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\18/40

Page 132: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

BOUNCY TANKS 47488 43.61% 102 0.00% 0.00% 0.00% 0.00% 03-Sep-11 13-Dec-11 0.00% 0.00%

AT LEG A1 11872 25.00% 102 0.00% 0.00% 0.00% 0.00% 3-Sep-11 13-Dec-11 0.00% 0.00%

PTJ9850 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 408 3.44% 6 0.00% 0.00% 0.00% 3‐Sep‐11 8‐Sep‐11 0.00% 0.00%

PTJ9860 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPORTS & STIFFENERS 816 6.87% 12 0.00% 0.00% 0.00% 3‐Sep‐11 15‐Sep‐11 0.00% 0.00%

PTJ9870 ROLLING OF BOUNCY TANK PLATE 720 6.06% 20 0.00% 0.00% 0.00% 10‐Sep‐11 2‐Oct‐11 0.00% 0.00%

PTJ9880 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 2304 19.41% 24 0.00% 0.00% 0.00% 14‐Sep‐11 12‐Oct‐11 0.00% 0.00%

PTJ9890 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUNCY TANK 3744 31.54% 24 0.00% 0.00% 0.00% 13‐Oct‐11 15‐Nov‐11 0.00% 0.00%

PTJ9900 GIRTH WELD OF BOUNCY TANK 3360 28.30% 24 0.00% 0.00% 0.00% 16‐Nov‐11 13‐Dec‐11 0.00% 0.00%

PTJ9910 ERECTION OF BOUNCY TANK WITH LEGS 520 4.38% 10 0.00% 0.00% 0.00% 16‐Nov‐11 27‐Nov‐11 0.00% 0.00%

AT LEG A2 11872 25.00% 102 0.00% 0.00% 0.00% 0.00% 3-Sep-11 13-Dec-11 0.00% 0.00%

PTJ9920 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 408 3.44% 6 0.00% 0.00% 0.00% 3‐Sep‐11 8‐Sep‐11 0.00% 0.00%

PTJ9930 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPORTS & STIFFENERS 816 6.87% 12 0.00% 0.00% 0.00% 3‐Sep‐11 15‐Sep‐11 0.00% 0.00%

PTJ9940 ROLLING OF BOUNCY TANK PLATE 720 6.06% 20 0.00% 0.00% 0.00% 10‐Sep‐11 2‐Oct‐11 0.00% 0.00%

PTJ9950 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 2304 19.41% 24 0.00% 0.00% 0.00% 14‐Sep‐11 12‐Oct‐11 0.00% 0.00%

PTJ9960 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUNCY TANK 3744 31.54% 24 0.00% 0.00% 0.00% 13‐Oct‐11 15‐Nov‐11 0.00% 0.00%

PTJ9970 GIRTH WELD OF BOUNCY TANK 3360 28.30% 24 0.00% 0.00% 0.00% 16‐Nov‐11 13‐Dec‐11 0.00% 0.00%

PTJ9980 ERECTION OF BOUNCY TANK WITH LEGS 520 4.38% 10 0.00% 0.00% 0.00% 16‐Nov‐11 27‐Nov‐11 0.00% 0.00%

AT LEG B1 11872 25.00% 102 0.00% 0.00% 0.00% 0.00% 3-Sep-11 13-Dec-11 0.00% 0.00%

PTJ10010 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPRTS & STIFFENERS 816 6.87% 12 0.00% 0.00% 0.00% 3‐Sep‐11 15‐Sep‐11 0.00% 0.00%

PTJ9990 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 408 3.44% 6 0.00% 0.00% 0.00% 3‐Sep‐11 8‐Sep‐11 0.00% 0.00%

PTJ10020 ROLLING OF BOUNCY TANK PLATE 720 6.06% 20 0.00% 0.00% 0.00% 10‐Sep‐11 2‐Oct‐11 0.00% 0.00%

PTJ10030 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 2304 19.41% 24 0.00% 0.00% 0.00% 14‐Sep‐11 12‐Oct‐11 0.00% 0.00%

PTJ10040 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUNCY TANK 3744 31.54% 24 0.00% 0.00% 0.00% 13‐Oct‐11 15‐Nov‐11 0.00% 0.00%

PTJ10050 GIRTH WELD OF BOUNCY TANK 3360 28.30% 24 0.00% 0.00% 0.00% 16‐Nov‐11 13‐Dec‐11 0.00% 0.00%

PTJ10060 ERECTION OF BOUNCY TANK WITH LEGS 520 4.38% 10 0.00% 0.00% 0.00% 16‐Nov‐11 27‐Nov‐11 0.00% 0.00%

AT LEG B2 11872 25.00% 102 0.00% 0.00% 0.00% 0.00% 3-Sep-11 13-Dec-11 0.00% 0.00%

PTJ10070 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 408 3.44% 6 0.00% 0.00% 0.00% 3‐Sep‐11 8‐Sep‐11 0.00% 0.00%

PTJ10080 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPORTS & STIFFENERS 816 6.87% 12 0.00% 0.00% 0.00% 3‐Sep‐11 15‐Sep‐11 0.00% 0.00%

PTJ10090 ROLLING OF BOUNCY TANK PLATE 720 6.06% 20 0.00% 0.00% 0.00% 10‐Sep‐11 2‐Oct‐11 0.00% 0.00%

PTJ10100 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 2304 19.41% 24 0.00% 0.00% 0.00% 14‐Sep‐11 12‐Oct‐11 0.00% 0.00%

PTJ10110 ERECTION OF SUPPORTS& STIFFENERS PLATE WITH BOUNCY TANK 3744 31.54% 24 0.00% 0.00% 0.00% 13‐Oct‐11 15‐Nov‐11 0.00% 0.00%

PTJ10120 GIRTH WELD OF BOUNCY TANK 3360 28.30% 24 0.00% 0.00% 0.00% 16‐Nov‐11 13‐Dec‐11 0.00% 0.00%

PTJ10130 ERECTION OF BOUNCY TANK WITH LEGS 520 4.38% 10 0.00% 0.00% 0.00% 16‐Nov‐11 27‐Nov‐11 0.00% 0.00%

BALLASTING & GROUTING SYSTEM 2160 1.98% 40 0.00% 0.00% 0.00% 0.00% 15-Jan-12 23-Feb-12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\19/40

Page 133: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ10790 BALASTING INSTALLATION 720 33.33% 20 0.00% 0.00% 0.00% 15‐Jan‐12 6‐Feb‐12 0.00% 0.00%

PTJ10970 GROUTING INSTALLATION ON ROW 1 720 33.33% 20 0.00% 0.00% 0.00% 15‐Jan‐12 6‐Feb‐12 0.00% 0.00%

PTJ10980 GROUTING INSTALLATION ON ROW 2 720 33.33% 20 0.00% 0.00% 0.00% 1‐Feb‐12 23‐Feb‐12 0.00% 0.00%

GRILLAGE & SEA FASTENING 12000 11.02% 148 0.00% 0.00% 0.00% 0.00% 15-Sep-11 09-Feb-12 0.00% 0.00%

PTJ10800 GRILLAGE & SEA FASTENING FABRICATION 12000 100.00% 120 0.00% 0.00% 0.00% 0.00% 15‐Sep‐11 9‐Feb‐12 0.00% 0.00%

INSTALLATION AIDS 1152 1.06% 38 0.00% 0.00% 0.00% 0.00% 03-Sep-11 10-Oct-11 0.00% 0.00%

PTJ10770 INSTALLATION AIDS FABRICATION 792 68.75% 22 0.00% 0.00% 0.00% 3‐Sep‐11 27‐Sep‐11 0.00% 0.00%

PTJ10780 INSTALLATION AIDS INSTALLATION 360 31.25% 10 0.00% 0.00% 0.00% 28‐Sep‐11 10‐Oct‐11 0.00% 0.00%

PREBENT CONDUCTOR 1152 1.06% 19 0.00% 0.00% 0.00% 0.00% 14-Jan-12 01-Feb-12 0.00% 0.00%

PTJ9300 FITUP OF PREBENT CONDUCTOR 576 50.00% 8 0.00% 0.00% 0.00% 14‐Jan‐12 22‐Jan‐12 0.00% 0.00%

PTJ9310 WELDING OF PREBENT CONDUCTOR 576 50.00% 9 0.00% 0.00% 0.00% 23‐Jan‐12 1‐Feb‐12 0.00% 0.00%

PAINTING 3312 1.34% 163 0.00% 0.00% 0.00% 0.00% 05‐Oct‐11 15‐Mar‐12 0.00% 0.00%

PTJ10320 SPLASH PAINTING FOR MISC (H R STAIRS ETC) 168 5 07% 7 0 00% 0 00% 0 00% 5 Oct 11 13 Oct 11 0 00% 0 00% PTJ10320 SPLASH PAINTING FOR MISC. (H.R, STAIRS, ...ETC) 168 5.07% 7 0.00% 0.00% 0.00% 5‐Oct‐11 13‐Oct‐11 0.00% 0.00%

PTJ10300 SPLASH PAINTING FOR ROW A 168 5.07% 7 0.00% 0.00% 0.00% 18‐Dec‐11 25‐Dec‐11 0.00% 0.00%

PTJ10310 SPLASH PAINTING FOR ROW B 168 5.07% 7 0.00% 0.00% 0.00% 22‐Dec‐11 29‐Dec‐11 0.00% 0.00%

PTJ10340 ATMOSPHERIC PAINTING FOR TOP ELEV 336 10.14% 7 0.00% 0.00% 0.00% 27‐Dec‐11 3‐Jan‐12 0.00% 0.00%

PTJ10280 SPLASH PAINTING FOR ROW 1 168 5.07% 7 0.00% 0.00% 0.00% 30‐Jan‐12 6‐Feb‐12 0.00% 0.00%

PTJ10330 PILE MARKING 1344 40.58% 28 0.00% 0.00% 0.00% 13‐Feb‐12 15‐Mar‐12 0.00% 0.00%

PTJ10260 SPLASH PAINTING FOR BOAT LAND 672 20.29% 14 0.00% 0.00% 0.00% 19‐Feb‐12 5‐Mar‐12 0.00% 0.00%

PTJ10290 SPLASH PAINTING FOR ROW 2 168 5.07% 7 0.00% 0.00% 0.00% 22‐Feb‐12 29‐Feb‐12 0.00% 0.00%

PTJ10270 SPLASH PAINTING FOR BARGE BUMPER 120 3.62% 5 0.00% 0.00% 0.00% 11‐Mar‐12 15‐Mar‐12 0.00% 0.00%

INSPECTION, TESTING & PRE‐COMMISIONING 480 0.19% 11 0.00% 0.00% 0.00% 0.00% 25‐Feb‐12 06‐Mar‐12 0.00% 0.00%

PTJ10990 RISER HYDRO TEST 160 33.33% 10 0.00% 0.00% 0.00% 25‐Feb‐12 6‐Mar‐12 0.00% 0.00%

PTJ11000 BALLASTING SYSTEM TEST 160 33.33% 10 0.00% 0.00% 0.00% 25‐Feb‐12 6‐Mar‐12 0.00% 0.00%

PTJ11010 GROUTING SYSTEM TEST 160 33.33% 10 0.00% 0.00% 0.00% 25‐Feb‐12 6‐Mar‐12 0.00% 0.00%

PILES FABRICATION 11872 4.52% 178 15.95% 0.72% 0.00% 0.00% 02‐Jul‐11 26‐Dec‐11 15.95% 0.72%

PTJ2030 Piiles fabrication start 0 0.00% 0 100.00% 0.00% 0.00% 0.00% 2‐Jul‐11 2‐Jul‐11 100.00% 0.00%

PTJ10380 Piiles fabrication finish 0 0.00% 0 0.00% 0.00% 0.00% 26‐Dec‐11 26‐Dec‐11 0.00% 0.00%

AT LEG A1 2968 25.00% 66 51.48% 12.87% 0.00% 0.00% 02‐Jul‐11 05‐Sep‐11 51.48% 12.87%

PTJ10390 Manual fitup & welding 8 joints 1440 48.52% 24 50.00% 24.26% 0.00% 0.00% 2‐Jul‐11 30‐Jul‐11 50.00% 24.26%

PTJ10420 Automatic welding 4 joints 576 19.41% 24 100.00% 19.41% 0.00% 0.00% 6‐Jul‐11 3‐Aug‐11 100.00% 19.41%

PTJ10430 back weld manual 4 joints 192 6.47% 16 100.00% 6.47% 0.00% 0.00% 17‐Jul‐11 4‐Aug‐11 100.00% 6.47%

PTJ10410 Welding beads (41 joints) 160 5.39% 10 25.00% 1.35% 0.00% 0.00% 4‐Aug‐11 15‐Aug‐11 25.00% 1.35%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\20/40

Page 134: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ10400 Welding for manual joint (4 joints) 600 20.22% 10 0.00% 0.00% 0.00% 22‐Aug‐11 5‐Sep‐11 0.00% 0.00%

AT LEG A2 2968 25.00% 102 0.00% 0.00% 0.00% 0.00% 02‐Jul‐11 11‐Oct‐11 0.00% 0.00%

PTJ10440 Manual fitup & welding 8 joints 1440 48.52% 24 0.00% 0.00% 0.00% 2‐Jul‐11 30‐Jul‐11 0.00% 0.00%

PTJ10450 Automatic welding 4 joints 576 19.41% 24 0.00% 0.00% 0.00% 11‐Aug‐11 11‐Sep‐11 0.00% 0.00%

PTJ10460 back weld manual 4 joints 192 6.47% 16 0.00% 0.00% 0.00% 22‐Aug‐11 12‐Sep‐11 0.00% 0.00%

PTJ10480 Welding beads (41 joints) 160 5.39% 10 0.00% 0.00% 0.00% 12‐Sep‐11 22‐Sep‐11 0.00% 0.00%

PTJ10470 Welding for manual joint (4 joints) 600 20.22% 10 0.00% 0.00% 0.00% 29‐Sep‐11 11‐Oct‐11 0.00% 0.00%

AT LEG B1 2968 25.00% 143 12.33% 3.08% 0.00% 0.00% 02‐Jul‐11 21‐Nov‐11 12.33% 3.08%

PTJ10490 Manual fitup & welding 8 joints 1440 48.52% 24 23.75% 11.52% 0.00% 0.00% 2‐Jul‐11 30‐Jul‐11 23.75% 11.52%

PTJ10500 Automatic welding 4 joints 576 19.41% 24 0.00% 0.00% 0.00% 0.00% 19‐Sep‐11 17‐Oct‐11 0.00% 0.00%

PTJ10510 back weld manual 4 joints 192 6.47% 16 0.00% 0.00% 0.00% 0.00% 29‐Sep‐11 18‐Oct‐11 0.00% 0.00%

PTJ10530 Welding beads (41 joints) 160 5.39% 10 15.00% 0.81% 0.00% 0.00% 18‐Oct‐11 29‐Oct‐11 15.00% 0.81%

PTJ10520 Welding for manual joint (4 joints) 600 20.22% 10 0.00% 0.00% 0.00% 10‐Nov‐11 21‐Nov‐11 0.00% 0.00% PTJ10520 Welding for manual joint (4 joints) 600 20.22% 10 0.00% 0.00% 0.00% 10 Nov 11 21 Nov 11 0.00% 0.00%

AT LEG B2 2968 25.00% 178 0.00% 0.00% 0.00% 0.00% 02‐Jul‐11 26‐Dec‐11 0.00% 0.00%

PTJ10540 Manual fitup & welding 8 joints 1440 48.52% 24 0.00% 0.00% 0.00% 2‐Jul‐11 30‐Jul‐11 0.00% 0.00%

PTJ10550 Automatic welding 4 joints 576 19.41% 24 0.00% 0.00% 0.00% 25‐Oct‐11 27‐Nov‐11 0.00% 0.00%

PTJ10560 back weld manual 4 joints 192 6.47% 16 0.00% 0.00% 0.00% 10‐Nov‐11 28‐Nov‐11 0.00% 0.00%

PTJ10580 Welding beads (41 joints) 160 5.39% 10 0.00% 0.00% 0.00% 28‐Nov‐11 8‐Dec‐11 0.00% 0.00%

PTJ10570 Welding for manual joint (4 joints) 600 20.22% 10 0.00% 0.00% 0.00% 15‐Dec‐11 26‐Dec‐11 0.00% 0.00%

PRE‐DRILLING TEMPLATE 4484 1.71% 85 66.77% 1.14% 0.00% 0.00% 16‐Jul‐11 08‐Oct‐11 66.77% 1.14%

PTD000 Pre‐drilling template fabrication start 0 0.00% 0 100.00% 0.00% 0.00% 0.00% 16‐Jul‐11 16‐Jul‐11 100.00% 0.00%

PTJ10810 cutting & assembly of bottom plate 300 6.69% 5 100.00% 6.69% 0.00% 0.00% 16‐Jul‐11 20‐Jul‐11 100.00% 6.69%

PTJ10900 fabrication of cones 1020 22.75% 15 100.00% 22.75% 0.00% 0.00% 16‐Jul‐11 2‐Aug‐11 100.00% 22.75%

PTJ10820 welding & NDT of bottom plate 240 5.35% 6 100.00% 5.35% 0.00% 0.00% 3‐Aug‐11 9‐Aug‐11 100.00% 5.35%

PTJ10830 cutting, rolling and assembly of outer frame 360 8.03% 6 100.00% 8.03% 0.00% 0.00% 3‐Aug‐11 9‐Aug‐11 100.00% 8.03%

PTJ10840 welding & NDT of outer frame 200 4.46% 5 95.00% 4.24% 0.00% 0.00% 10‐Aug‐11 15‐Aug‐11 95.00% 4.24%

PTJ10850 fabrication of beams ( built up section ) 360 8.03% 10 95.00% 7.63% 0.00% 0.00% 16‐Aug‐11 27‐Aug‐11 95.00% 7.63%

PTJ10860 installation of beams with bottom frame 252 5.62% 7 55.00% 3.09% 0.00% 0.00% 28‐Aug‐11 7‐Sep‐11 55.00% 3.09%

PTJ10870 cutting of conductor pipe 120 2.68% 2 75.00% 2.01% 0.00% 0.00% 8‐Sep‐11 10‐Sep‐11 75.00% 2.01%

PTJ10920 fabrication of pad eyes 180 4.01% 5 35.00% 1.40% 0.00% 0.00% 8‐Sep‐11 13‐Sep‐11 35.00% 1.40%

PTJ10880 fabrication & installation of shims plates 144 3.21% 4 25.00% 0.80% 0.00% 0.00% 11‐Sep‐11 14‐Sep‐11 25.00% 0.80%

PTJ10930 installation of pad eyes 180 4.01% 5 0.00% 0.00% 0.00% 14‐Sep‐11 19‐Sep‐11 0.00% 0.00%

PTJ10890 installation of conductor pipe 180 4.01% 5 35.00% 1.40% 0.00% 0.00% 15‐Sep‐11 20‐Sep‐11 35.00% 1.40%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\21/40

Page 135: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP4 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name Finish Date

ACTUAL % PLANNED %Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)DEV/ITEM

DEV/ OVERALL

Start Date

PTJ10940 fabrication of lifting tool 360 8.03% 10 0.00% 0.00% 0.00% 18‐Sep‐11 28‐Sep‐11 0.00% 0.00%

PTJ10910 installation of cones 252 5.62% 7 60.00% 3.37% 0.00% 0.00% 21‐Sep‐11 28‐Sep‐11 60.00% 3.37%

PTJ10950 painting of template 336 7.49% 7 0.00% 0.00% 0.00% 29‐Sep‐11 8‐Oct‐11 0.00% 0.00%

PTJ2010 Pre‐drilling template fabrication finish 0 0.00% 0 0.00% 0.00% 0.00% 8‐Oct‐11 8‐Oct‐11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\22/40

Page 136: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

CLIENT : PETROBEL

PROJECT : SETH DEVELOPMENT PROJECT WK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.5: DECK & TSF FABRICATION 165152 100.00% 396 16.82% 16.82% 15.01% 15.01% 31-Mar-11 29-Apr-12 1.81% 1.81%

DECK FABRICATION 129068 78.15% 396 21.52% 16.82% 19.20% 15.01% 31‐Mar‐11 29‐Apr‐12 2.32% 1.81%

General Activities 8768 6.79% 337 0.00% 0.00% 0.00% 0.00% 28‐May‐11 28‐Apr‐12 0.00% 0.00%

PTJ2040 Deck primary structure fabrication start 0 0.00% 0 100.00% 0.00% 100.00% 0.00% 28-May-11 28-May-11 0.00% 0.00%

PTJ1150 Static equipment (by petrojet) 0 0.00% 120 0.00% 0.00% 0.00% 10-Aug-11 08-Dec-11 0.00% 0.00%

PTJ2160 Deck secondray structure fabrication start 0 0.00% 0 100.00% 0.00% 0.00% 0.00% 03-Sep-11 03-Sep-11 100.00% 0.00%

Act ID Activity NameTotal

Budgete Units (Hrs)

R.W %Original Duration

(Days)

25‐Jun‐11 WEEK NO.

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PETROJET

PTJ1160 Piping & E&I supports (by petrojet) 0 0.00% 30 0.00% 0.00% 0.00% 16‐Nov‐11 16‐Dec‐11 0.00% 0.00%

PTJ2060 Deck pre-commisioning 6400 72.99% 40 0.00% 0.00% 0.00% 11-Feb-12 27-Mar-12 0.00% 0.00%

PTJ2090 Deck commisioning 2080 23.72% 26 0.00% 0.00% 0.00% 28-Mar-12 28-Apr-12 0.00% 0.00%

PTJ2065 Crane assembly and erection 0 0.00% 20 0.00% 0.00% 0.00% 28-Mar-12 21-Apr-12 0.00% 0.00%

PTJ2220 Deck weighing 288 3.28% 1 0.00% 0.00% 0.00% 21-Apr-12 22-Apr-12 0.00% 0.00%

Deck Structure Fabrication 104416 80.90% 395 26.60% 21.52% 23.74% 19.20% 31‐Mar‐11 29‐Apr‐12 2.86% 2.32%

Deck Legs Fabrication 3504 3.36% 56 100.00% 3.36% 100.00% 3.36% 31-Mar-11 25-May-11 0.00% 0.00%

PTD1000 Cutting & Assembly 1584 45.21% 22 100.00% 45.21% 100.00% 45.21% 31-Mar-11 27-Apr-11 0.00% 0.00%

PTD1005 Welding & NDT 1920 54.79% 30 100.00% 54.79% 100.00% 54.79% 19-Apr-11 25-May-11 0.00% 0.00%

Braces Below Cellar 728 0.70% 241 7.03% 0.05% 17.58% 0.12% 28-May-11 23-Jan-12 -10.55% -0.07%

PTJD1020 Profiling Template 128 17.58% 4 40.00% 7.03% 100.00% 17.58% 28-May-11 31-May-11 -60.00% -10.55%

PTD1030 Assembly 216 29.67% 6 0.00% 0.00% 0.00% 05-Jan-12 12-Jan-12 0.00% 0.00%

PTD1040 Welding & NDT 384 52.75% 12 0.00% 0.00% 0.00% 10-Jan-12 23-Jan-12 0.00% 0.00%

Cellar Deck Fabrication (+11.000) 20912 20.03% 186 44.70% 8.95% 45.70% 9.15% 28-May-11 29-Nov-11 -1.00% -0.20%

Joints Fabrication 3776 18.06% 30 86.02% 15.53% 97.85% 17.67% 28-May-11 26-Jun-11 -11.83% -2.14%

PTD1050 Cutting & Assembly 1664 44.07% 16 100.00% 44.07% 100.00% 44.07% 28-May-11 14-Jun-11 0.00% 0.00%

PTD1060 Welding & NDT 2112 55.93% 22 75.00% 41.95% 96.15% 53.78% 01-Jun-11 26-Jun-11 -21.15% -11.83%

Main Beams Fabrication 10784 51.57% 61 45.40% 23.41% 54.36% 28.03% 28-May-11 27-Jul-11 -8.96% -4.62%

PTD1070 Cutting & Assembly 4896 45.40% 36 100.00% 45.40% 70.73% 32.11% 28-May-11 7-Jul-11 29.27% 13.29%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\23/40

Page 137: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PTD1080 Welding & NDT 5888 54.60% 46 0.00% 40.74% 22.24% 4-Jun-11 27-Jul-11 -40.74% -22.24%

Secondary Beams Fabrication 3376 16.14% 40 35.66% 5.76% 0.00% 0.00% 3-Sep-11 12-Oct-11 35.66% 5.76%

PTD1090 Cutting & Assembly 1584 46.92% 22 76.00% 35.66% 0.00% 0.00% 03-Sep-11 27-Sep-11 76.00% 35.66%

PTD1100 Welding & NDT 1792 53.08% 28 0.00% 0.00% 0.00% 10-Sep-11 12-Oct-11 0.00% 0.00%

Embossed Plates 2976 14.23% 48 0.00% 0.00% 0.00% 0.00% 13-Oct-11 29-Nov-11 0.00% 0.00%

PTD1110 Cutting & Assembly 1440 48.39% 20 0.00% 0.00% 0.00% 13-Oct-11 10-Nov-11 0.00% 0.00%

PTD1120 Welding & NDT 1536 51.61% 24 0.00% 0.00% 0.00% 27-Oct-11 29-Nov-11 0.00% 0.00%

PLAN AT EL. + 9.200 716 0.69% 19 34.36% 0.24% 0.00% 0.00% 03‐Sep‐11 21‐Sep‐11 34.36% 0.24%

Main Beams Fabrication 236 32.96% 8 49.32% 16.26% 0.00% 0.00% 03-Sep-11 10-Sep-11 49.32% 16.26%

PTD1710 Cutting & Assembly 108 45.76% 3 90.00% 41.19% 0.00% 0.00% 03-Sep-11 05-Sep-11 90.00% 41.19%

PTD1720 Welding & NDT 128 54.24% 4 15.00% 8.14% 0.00% 0.00% 06-Sep-11 10-Sep-11 15.00% 8.14%

Secondary Beams Fabrication 240 33.52% 5 54.00% 18.10% 0.00% 0.00% 11-Sep-11 15-Sep-11 54.00% 18.10%

PTD1730 Cutting & Assembly 144 60.00% 2 90.00% 54.00% 0.00% 0.00% 11-Sep-11 12-Sep-11 90.00% 54.00%

PTD1740 Welding & NDT 96 40.00% 3 0.00% 0.00% 0.00% 13-Sep-11 15-Sep-11 0.00% 0.00%

GRATING 240 33.52% 5 0.00% 0.00% 0.00% 0.00% 17-Sep-11 21-Sep-11 0.00% 0.00%

PTD1750 Cutting & Assembly 144 60.00% 2 0.00% 0.00% 0.00% 17-Sep-11 18-Sep-11 0.00% 0.00%

PTD1760 Welding & NDT 96 40.00% 3 0.00% 0.00% 0.00% 19-Sep-11 21-Sep-11 0.00% 0.00%

PLAN AT EL. + 9.700 1824 1.75% 44 33.95% 0.59% 0.00% 0.00% 03‐Sep‐11 16‐Oct‐11 33.95% 0.59%

Main Beams Fabrication 1184 64.91% 20 41.35% 26.84% 0.00% 0.00% 03-Sep-11 22-Sep-11 41.35% 26.84%

PTD1630 Cutting & Assembly 544 45.95% 8 90.00% 41.35% 0.00% 0.00% 3-Sep-11 11-Sep-11 90.00% 41.35%

PTD1640 Welding & NDT 640 54.05% 10 0.00% 0.00% 0.00% 12-Sep-11 22-Sep-11 0.00% 0.00%

Secondary Beams Fabrication 336 18.42% 11 38.57% 7.11% 0.00% 0.00% 24-Sep-11 04-Oct-11 38.57% 7.11%

PTD1650 Cutting & Assembly 144 42.86% 4 90.00% 38.57% 0.00% 0.00% 24-Sep-11 27-Sep-11 90.00% 38.57%

PTD1660 Welding & NDT 192 57.14% 6 0.00% 0.00% 0.00% 28-Sep-11 4-Oct-11 0.00% 0.00%

GRATING 304 16.67% 12 0.00% 0.00% 0.00% 0.00% 05-Oct-11 16-Oct-11 0.00% 0.00%

PTD1670 Cutting & Assembly 144 47.37% 4 0.00% 0.00% 0.00% 5-Oct-11 10-Oct-11 0.00% 0.00%

PTD1680 Welding & NDT 160 52.63% 5 0.00% 0.00% 0.00% 11-Oct-11 16-Oct-11 0.00% 0.00%

WELL HEAD MEZZANINE AT (+ 16.000) 2704 2.59% 71 0.00% 0.00% 0.00% 0.00% 03‐Sep‐11 12‐Nov‐11 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\24/40

Page 138: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

Joints Fabrication 548 20.27% 12 0.00% 0.00% 0.00% 0.00% 03-Sep-11 14-Sep-11 0.00% 0.00%

PTD1530 Cutting & Assembly 260 47.45% 5 0.00% 0.00% 0.00% 3-Sep-11 7-Sep-11 0.00% 0.00%

PTD1540 Welding & NDT 288 52.55% 6 0.00% 0.00% 0.00% 8-Sep-11 14-Sep-11 0.00% 0.00%

Main Beams Fabrication 1380 51.04% 26 0.00% 0.00% 0.00% 0.00% 15-Sep-11 10-Oct-11 0.00% 0.00%

PTD1550 Cutting & Assembly 612 44.35% 9 0.00% 0.00% 0.00% 15‐Sep‐11 25‐Sep‐11 0.00% 0.00%

PTD1560 Welding & NDT 768 55.65% 12 0.00% 0.00% 0.00% 26-Sep-11 10-Oct-11 0.00% 0.00%

Secondary Beams Fabrication 404 14.94% 14 0.00% 0.00% 0.00% 0.00% 11-Oct-11 24-Oct-11 0.00% 0.00%

PTD1570 Cutting & Assembly 180 44.55% 5 0.00% 0.00% 0.00% 11-Oct-11 16-Oct-11 0.00% 0.00%

PTD1580 Welding & NDT 224 55.45% 7 0.00% 0.00% 0.00% 17‐Oct‐11 24‐Oct‐11 0.00% 0.00%

GRATING 372 13.76% 19 0.00% 0.00% 0.00% 0.00% 25-Oct-11 12-Nov-11 0.00% 0.00%

PTD1590 C tti  & A bl 180 48 39% 5 0 00% 0 00% 0 00% 25 O t 11 30 O t 11 0 00% 0 00% PTD1590 Cutting & Assembly 180 48.39% 5 0.00% 0.00% 0.00% 25-Oct-11 30-Oct-11 0.00% 0.00%

PTD1600 Welding & NDT 192 51.61% 6 0.00% 0.00% 0.00% 31-Oct-11 12-Nov-11 0.00% 0.00%

Braces & Legs between Cellar and Main 6592 6.31% 187 0.00% 0.00% 27.18% 1.72% 28-May-11 30-Nov-11 -27.18% -1.72%

PTD1130 Profiling Template 1792 27.18% 14 0.00% 100.00% 27.18% 28-May-11 12-Jun-11 -100.00% -27.18%

PTD1140 Assembly 1728 26.21% 24 0.00% 0.00% 0.00% 4-Oct-11 1-Nov-11 0.00% 0.00%

PTD1150 Welding & NDT 3072 46.60% 32 0.00% 0.00% 0.00% 19-Oct-11 30-Nov-11 0.00% 0.00%

Main Deck Fabrication (+17.000) 21696 20.78% 170 37.79% 7.85% 28.38% 5.90% 28-May-11 13-Nov-11 9.41% 1.96%

Joints Fabrication 4576 21.09% 53 78.18% 16.49% 56.36% 11.89% 28-May-11 19-Jul-11 21.82% 4.60%

PTD1160 Cutting & Assembly 2080 45.45% 20 100.00% 45.45% 100.00% 45.45% 28-May-11 19-Jun-11 0.00% 0.00%

PTD1170 Welding & NDT 2496 54.55% 26 60.00% 32.73% 20.00% 10.91% 20-Jun-11 19-Jul-11 40.00% 21.82%

Main Beams Fabrication 11040 50.88% 80 35.48% 18.05% 32.41% 16.49% 30-May-11 17-Aug-11 3.06% 1.56%

PTD1180 Cutting & Assembly 4896 44.35% 36 80.00% 35.48% 64.29% 28.51% 30‐May‐11 10‐Jul‐11 15.71% 6.97%

PTD1190 Welding & NDT 6144 55.65% 48 0.00% 7.02% 3.91% 22-Jun-11 17-Aug-11 -7.02% -3.91%

Secondary Beams Fabrication 3104 14.31% 38 22.73% 3.25% 0.00% 0.00% 3-Sep-11 10-Oct-11 22.73% 3.25%

PTD1200 Cutting & Assembly 1440 46.39% 20 49.00% 22.73% 0.00% 0.00% 3-Sep-11 25-Sep-11 49.00% 22.73%

PTD1210 Welding & NDT 1664 53.61% 26 0.00% 0.00% 0.00% 10-Sep-11 10-Oct-11 0.00% 0.00%

Embossed Plates 2976 13.72% 50 0.00% 0.00% 0.00% 0.00% 25-Sep-11 13-Nov-11 0.00% 0.00%

PTD1220 Cutting & Assembly 1440 48.39% 20 0.00% 0.00% 0.00% 25-Sep-11 18-Oct-11 0.00% 0.00%

PTD1230 Welding & NDT 1536 51.61% 24 0.00% 0.00% 0.00% 11‐Oct‐11 13‐Nov‐11 0.00% 0.00%

Braces & Legs Above Main 2048 1.96% 255 0.00% 0.00% 25.00% 0.49% 28-May-11 6-Feb-12 -25.00% -0.49%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\25/40

Page 139: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PTD1240 Profiling Template 512 25.00% 8 0.00% 100.00% 25.00% 28-May-11 5-Jun-11 -100.00% -25.00%

PTD1250 Assembly 576 28.13% 8 0.00% 0.00% 0.00% 24‐Jan‐12 1‐Feb‐12 0.00% 0.00%

PTD1260 Welding & NDT 960 46.88% 10 0.00% 0.00% 0.00% 26‐Jan‐12 6‐Feb‐12 0.00% 0.00%

Braces Below Heli Deck 9328 8.93% 207 42.29% 3.78% 15.09% 1.35% 28-May-11 20-Dec-11 27.20% 2.43%

PTD1270 Profiling Template 1408 15.09% 22 92.00% 13.89% 100.00% 15.09% 28‐May‐11 21‐Jun‐11 ‐8.00% ‐1.21%

PTD1280 Assembly 2880 30.87% 40 92.00% 28.40% 0.00% 0.00% 18‐Oct‐11 8‐Dec‐11 92.00% 28.40%

PTD1290 Welding & NDT 5040 54.03% 35 0.00% 0.00% 0.00% 10‐Nov‐11 20‐Dec‐11 0.00% 0.00%

Heli Deck Fabrication (+29.125) 9440 9.04% 136 19.73% 1.78% 0.00% 0.00% 07-Aug-11 20-Dec-11 19.73% 1.78%

Joints Fabrication 704 7.46% 33 50.91% 3.80% 0.00% 0.00% 7‐Aug‐11 8‐Sep‐11 50.91% 3.80%

PTD1300 Cutting & Assembly 320 45.45% 8 100.00% 45.45% 0.00% 0.00% 7‐Aug‐11 15‐Aug‐11 100.00% 45.45%

PTD1310 Welding & NDT 384 54.55% 12 10.00% 5.45% 0.00% 0.00% 23‐Aug‐11 8‐Sep‐11 10.00% 5.45%

Main Beams Fabrication 1408 14.92% 38 45.45% 6.78% 0.00% 0.00% 16‐Aug‐11 22‐Sep‐11 45.45% 6.78%

PTD1320 Cutting & Assembly 640 45 45% 16 100 00% 45 45% 0 00% 0 00% 16 Aug 11 6 Sep 11 100 00% 45 45% PTD1320 Cutting & Assembly 640 45.45% 16 100.00% 45.45% 0.00% 0.00% 16‐Aug‐11 6‐Sep‐11 100.00% 45.45%

PTD1330 Welding & NDT 768 54.55% 24 0.00% 0.00% 0.00% 23‐Aug‐11 22‐Sep‐11 0.00% 0.00%

Secondary Beams Fabrication 3776 40.00% 45 22.88% 9.15% 0.00% 0.00% 3‐Sep‐11 17‐Oct‐11 22.88% 9.15%

PTD1340 Cutting & Assembly 1728 45.76% 24 50.00% 22.88% 0.00% 0.00% 3‐Sep‐11 29‐Sep‐11 50.00% 22.88%

PTD1350 Welding & NDT 2048 54.24% 32 0.00% 0.00% 0.00% 10‐Sep‐11 17‐Oct‐11 0.00% 0.00%

Covering Plates 2832 30.00% 40 0.00% 0.00% 0.00% 0.00% 12‐Oct‐11 20‐Nov‐11 0.00% 0.00%

PTD1360 Cutting & Assembly 1296 45.76% 18 0.00% 0.00% 0.00% 12‐Oct‐11 1‐Nov‐11 0.00% 0.00%

PTD1370 Welding & NDT 1536 54.24% 24 0.00% 0.00% 0.00% 18‐Oct‐11 20‐Nov‐11 0.00% 0.00%

Gutter 472 5.00% 16 0.00% 0.00% 0.00% 0.00% 21‐Nov‐11 6‐Dec‐11 0.00% 0.00%

PTD1380 Cutting & Assembly 216 45.76% 6 0.00% 0.00% 0.00% 21‐Nov‐11 27‐Nov‐11 0.00% 0.00%

PTD1390 Welding & NDT 256 54.24% 8 0.00% 0.00% 0.00% 28‐Nov‐11 6‐Dec‐11 0.00% 0.00%

Landing Area 248 2.63% 30 0.00% 0.00% 0.00% 0.00% 21‐Nov‐11 20‐Dec‐11 0.00% 0.00%

PTD1400 Cutting & Assembly 120 48.39% 6 0.00% 0.00% 0.00% 21‐Nov‐11 27‐Nov‐11 0.00% 0.00%

PTD1410 Welding & NDT 128 51.61% 8 0.00% 0.00% 0.00% 12‐Dec‐11 20‐Dec‐11 0.00% 0.00%

Misellaneuos 15820 15.15% 162 0.00% 0.00% 0.00% 0.00% 19-Nov-11 29-Apr-12 0.00% 0.00%

Fabrication 10656 67.36% 155 0.00% 0.00% 0.00% 0.00% 19‐Nov‐11 22‐Apr‐12 0.00% 0.00%

PTMD1010 Handrails & Cups 1536 14.41% 24 0.00% 0.00% 0.00% 19‐Nov‐11 15‐Dec‐11 0.00% 0.00%

PTMD1060 Safety Net 1792 16.82% 28 0.00% 0.00% 0.00% 21‐Nov‐11 22‐Dec‐11 0.00% 0.00%

PTMD1040 Monorail Beam 720 6.76% 10 0.00% 0.00% 0.00% 30‐Nov‐11 11‐Dec‐11 0.00% 0.00%

PTMD1020 Hatches 640 6.01% 20 0.00% 0.00% 0.00% 22‐Dec‐11 15‐Jan‐12 0.00% 0.00%

PTMD1090 Fire Wall 2448 22.97% 18 0.00% 0.00% 0.00% 25‐Dec‐11 15‐Jan‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\26/40

Page 140: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PTMD1050 Name Plate 256 2.40% 8 0.00% 0.00% 0.00% 2‐Jan‐12 11‐Jan‐12 0.00% 0.00%

PTMD1000 Stairs & Walkways 2400 22.52% 24 0.00% 0.00% 0.00% 3‐Jan‐12 31‐Jan‐12 0.00% 0.00%

PTMD1030 Crane Boom Rest 192 1.80% 6 0.00% 0.00% 0.00% 9‐Jan‐12 15‐Jan‐12 0.00% 0.00%

PTMD1070 Pad Eyes 672 6.31% 6 0.00% 0.00% 0.00% 15‐Apr‐12 22‐Apr‐12 0.00% 0.00%

Installation 5164 32.64% 139 0.00% 0.00% 0.00% 0.00% 12‐Dec‐11 29‐Apr‐12 0.00% 0.00%

PTMD1140 Monorail Beam 360 6.97% 10 0.00% 0.00% 0.00% 12‐Dec‐11 22‐Dec‐11 0.00% 0.00%

PTMD1110 Handrails & Cups 864 16.73% 24 0.00% 0.00% 0.00% 2‐Jan‐12 30‐Jan‐12 0.00% 0.00%

PTMD1160 Safety Net 1152 22.31% 16 0.00% 0.00% 0.00% 4‐Jan‐12 23‐Jan‐12 0.00% 0.00%

PTMD1100 Stairs & Walkways 1080 20.91% 15 0.00% 0.00% 0.00% 24‐Jan‐12 9‐Feb‐12 0.00% 0.00%

PTMD1120 Hatches 288 5.58% 8 0.00% 0.00% 0.00% 24‐Jan‐12 1‐Feb‐12 0.00% 0.00%

PTMD1130 Crane Boom Rest 72 1.39% 2 0.00% 0.00% 0.00% 24‐Jan‐12 25‐Jan‐12 0.00% 0.00%

PTMD1150 Name Plate 144 2.79% 4 0.00% 0.00% 0.00% 24‐Jan‐12 28‐Jan‐12 0.00% 0.00%

PTMD1190 Fire Wall 864 16.73% 12 0.00% 0.00% 0.00% 24‐Jan‐12 6‐Feb‐12 0.00% 0.00%

PTMD1170 Pad Eyes 340 6.58% 5 0.00% 0.00% 0.00% 22‐Apr‐12 29‐Apr‐12 0.00% 0.00%

Deck Flare 952 0.91% 79 0.00% 0.00% 0.00% 0.00% 24‐Jan‐12 11‐Apr‐12 0.00% 0.00%

PTD1500 Cutting & Assembly 400 42.02% 20 0.00% 0.00% 0.00% 24‐Jan‐12 15‐Feb‐12 0.00% 0.00%

PTD1510 Welding & NDT 512 53.78% 32 0.00% 0.00% 0.00% 16‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PTD1520 Trial Fit 40 4.20% 2 0.00% 0.00% 0.00% 10‐Apr‐12 11‐Apr‐12 0.00% 0.00%

Deck Assembly 8152 7.81% 241 0.00% 0.00% 21.20% 1.65% 28‐May‐11 23‐Jan‐12 ‐21.20% ‐1.65%

Skid Beams & Shoes Preparation 1728 21.20% 27 0.00% 0.00% 100.00% 21.20% 28‐May‐11 23‐Jun‐11 ‐100.00% ‐21.20%

PTD1420 Skid Beams & Shoes Preparation 1728 100.00% 24 0.00% 100.00% 100.00% 28‐May‐11 23‐Jun‐11 ‐100.00% ‐100.00%

Lifting Deck Legs Over Skid Beams & Skid Shoes 304 3.73% 2 0.00% 0.00% 0.00% 0.00% 17‐Dec‐11 18‐Dec‐11 0.00% 0.00%

PTD1430 Lifting Deck Legs Over Skid Beams & Skid Shoes 304 100.00% 2 0.00% 0.00% 0.00% 17‐Dec‐11 18‐Dec‐11 0.00% 0.00%

Lifting Cellar Deck Over Deck Legs 1584 19.43% 17 0.00% 0.00% 0.00% 0.00% 19‐Dec‐11 4‐Jan‐12 0.00% 0.00%

PTD1440 Lifting 592 37.37% 1 0.00% 0.00% 0.00% 19‐Dec‐11 19‐Dec‐11 0.00% 0.00%

PTD1450 Assembly 480 30.30% 6 0.00% 0.00% 0.00% 20‐Dec‐11 26‐Dec‐11 0.00% 0.00%

PTD1460 Welding & NDT 512 32.32% 8 0.00% 0.00% 0.00% 27‐Dec‐11 4‐Jan‐12 0.00% 0.00%

lifting of plan at + 9.2 692 8.49% 6 0.00% 0.00% 0.00% 0.00% 5‐Jan‐12 10‐Jan‐12 0.00% 0.00%

PTD1700 Lifting 592 85.55% 1 0.00% 0.00% 0.00% 5‐Jan‐12 5‐Jan‐12 0.00% 0.00%

PTD1770 Assembly 36 5.20% 1 0.00% 0.00% 0.00% 8‐Jan‐12 8‐Jan‐12 0.00% 0.00%

PTD1780 Welding & NDT 64 9.25% 2 0.00% 0.00% 0.00% 9‐Jan‐12 10‐Jan‐12 0.00% 0.00%

lifting of plan at + 9.7 692 8.49% 6 0.00% 0.00% 0.00% 0.00% 5‐Jan‐12 10‐Jan‐12 0.00% 0.00%

PTD1610 Lifting 592 85.55% 1 0.00% 0.00% 0.00% 5‐Jan‐12 5‐Jan‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\27/40

Page 141: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PTD1620 Assembly 36 5.20% 1 0.00% 0.00% 0.00% 8‐Jan‐12 8‐Jan‐12 0.00% 0.00%

PTD1690 Welding & NDT 64 9.25% 2 0.00% 0.00% 0.00% 9‐Jan‐12 10‐Jan‐12 0.00% 0.00%

lifting of mezzanine deck at + 16 800 9.81% 6 0.00% 0.00% 0.00% 0.00% 5‐Jan‐12 10‐Jan‐12 0.00% 0.00%

PTD1790 Lifting 592 74.00% 1 0.00% 0.00% 0.00% 5‐Jan‐12 5‐Jan‐12 0.00% 0.00%

PTD1800 Assembly 80 10.00% 1 0.00% 0.00% 0.00% 8‐Jan‐12 8‐Jan‐12 0.00% 0.00%

PTD1810 Welding & NDT 128 16.00% 2 0.00% 0.00% 0.00% 9‐Jan‐12 10‐Jan‐12 0.00% 0.00%

Lifting Main Deck Over cellar Deck 2352 28.85% 13 0.00% 0.00% 0.00% 0.00% 11‐Jan‐12 23‐Jan‐12 0.00% 0.00%

PTD1470 Lifting 736 31.29% 1 0.00% 0.00% 0.00% 11‐Jan‐12 11‐Jan‐12 0.00% 0.00%

PTD1480 Assembly 720 30.61% 5 0.00% 0.00% 0.00% 12‐Jan‐12 17‐Jan‐12 0.00% 0.00%

PTD1490 Welding & NDT 896 38.10% 7 0.00% 0.00% 0.00% 16‐Jan‐12 23‐Jan‐12 0.00% 0.00%

Atmosphric Painting 15548 12.05% 201 0.00% 0.00% 0.00% 0.00% 22‐Sep‐11 09‐Apr‐12 0.00% 0.00%

PT1110 Plane at + 9.2 960 6.17% 5 0.00% 0.00% 0.00% 22‐Sep‐11 27‐Sep‐11 0.00% 0.00%

PT1120 Plane at + 9 7 960 6 17% 5 0 00% 0 00% 0 00% 17 Oct 11 22 Oct 11 0 00% 0 00% PT1120 Plane at + 9.7 960 6.17% 5 0.00% 0.00% 0.00% 17‐Oct‐11 22‐Oct‐11 0.00% 0.00%

PT1130 Wellhead mezzanine 1920 12.35% 10 0.00% 0.00% 0.00% 13‐Nov‐11 23‐Nov‐11 0.00% 0.00%

PT1030 Cellar Deck & Braces Above Cellar 2880 18.52% 15 0.00% 0.00% 0.00% 1‐Dec‐11 18‐Dec‐11 0.00% 0.00%

PT1080 Piping Support 108 0.69% 9 0.00% 0.00% 0.00% 6‐Dec‐11 17‐Dec‐11 0.00% 0.00%

PT1010 Deck Legs 432 2.78% 6 0.00% 0.00% 0.00% 10‐Dec‐11 15‐Dec‐11 0.00% 0.00%

PT1020 Braces Below Cellar 120 0.77% 5 0.00% 0.00% 0.00% 13‐Dec‐11 18‐Dec‐11 0.00% 0.00%

PT1050 Heli Deck & Braces Below Heli 1728 11.11% 12 0.00% 0.00% 0.00% 21‐Dec‐11 3‐Jan‐12 0.00% 0.00%

PT1040 Main Deck 2880 18.52% 15 0.00% 0.00% 0.00% 24‐Dec‐11 10‐Jan‐12 0.00% 0.00%

PT1090 Cable Trays Supports 120 0.77% 10 0.00% 0.00% 0.00% 11‐Jan‐12 23‐Jan‐12 0.00% 0.00%

PT1045 Braces Above Main 80 0.51% 5 0.00% 0.00% 0.00% 18‐Jan‐12 23‐Jan‐12 0.00% 0.00%

PT1070 Piping painting 1008 6.48% 14 0.00% 0.00% 0.00% 18‐Jan‐12 4‐Feb‐12 0.00% 0.00%

PT1060 Miscellaneous (Stairs,H/R,...etc) 1344 8.64% 14 0.00% 0.00% 0.00% 22‐Jan‐12 6‐Feb‐12 0.00% 0.00%

PT1100 Deck Flare 1008 6.48% 14 0.00% 0.00% 0.00% 25‐Mar‐12 9‐Apr‐12 0.00% 0.00%

Anti Skid Painting 336 0.26% 9 0.00% 0.00% 0.00% 0.00% 21‐Apr‐12 29‐Apr‐12 0.00% 0.00%

PT1000 Heli Deck 336 100.00% 7 0.00% 0.00% 0.00% 21‐Apr‐12 29‐Apr‐12 0.00% 0.00%

E & I 13280 8.04% 84 0.00% 0.00% 0.00% 0.00% 16‐Dec‐11 09‐Mar‐12 0.00% 0.00%

PTJ2080 E & I Work start 0 0.00% 0 0.00% 0.00% 0.00% 16‐Dec‐11 16‐Dec‐11 0.00% 0.00%

PTJ2100 E & I Work finish 0 0.00% 0 0.00% 0.00% 0.00% 9‐Mar‐12 9‐Mar‐12 0.00% 0.00%

E&I (onshore) 13280 100.00% 84 0.00% 0.00% 0.00% 0.00% 16‐Dec‐11 09‐Mar‐12 0.00% 0.00%

Instrumentation 6424 48.37% 84 0.00% 0.00% 0.00% 0.00% 16-Dec-11 09-Mar-12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\28/40

Page 142: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

Cable Trays Supports 1336 20.80% 52 0.00% 0.00% 0.00% 0.00% 16‐Dec‐11 6‐Feb‐12 0.00% 0.00%

E&I1090 Fabrication 832 62.28% 26 0.00% 0.00% 0.00% 16‐Dec‐11 11‐Jan‐12 0.00% 0.00%

E&I1100 Installation 504 37.72% 14 0.00% 0.00% 0.00% 23-Jan-12 06-Feb-12 0.00% 0.00%

Cable Trays 1248 19.43% 26 0.00% 0.00% 0.00% 0.00% 23‐Jan‐12 18‐Feb‐12 0.00% 0.00%

E&I1110 Installation 1248 100.00% 26 0.00% 0.00% 0.00% 23‐Jan‐12 18‐Feb‐12 0.00% 0.00%

Tubing Activities 800 12.45% 20 0.00% 0.00% 0.00% 0.00% 10‐Feb‐12 1‐Mar‐12 0.00% 0.00%

E&I1120 Installation 800 100.00% 20 0.00% 0.00% 0.00% 10‐Feb‐12 1‐Mar‐12 0.00% 0.00%

HCU & Local Panels Activities 256 3.99% 16 0.00% 0.00% 0.00% 0.00% 18‐Feb‐12 5‐Mar‐12 0.00% 0.00%

E&I1130 HCU & Local Panels Activities 256 100.00% 16 0.00% 0.00% 0.00% 18‐Feb‐12 5‐Mar‐12 0.00% 0.00%

Fusible Plug & ESD Puch Bottons 720 11.21% 18 0.00% 0.00% 0.00% 0.00% 6‐Feb‐12 24‐Feb‐12 0.00% 0.00%

E&I1140 Fusible Plug & ESD Puch Bottons 720 100.00% 18 0.00% 0.00% 0.00% 6‐Feb‐12 24‐Feb‐12 0.00% 0.00%

J. Box Activities 320 4.98% 20 0.00% 0.00% 0.00% 0.00% 6‐Feb‐12 26‐Feb‐12 0.00% 0.00%

E&I1150 J Box Activities 320 100 00% 20 0 00% 0 00% 0 00% 6 Feb 12 26 Feb 12 0 00% 0 00% E&I1150 J. Box Activities 320 100.00% 20 0.00% 0.00% 0.00% 6‐Feb‐12 26‐Feb‐12 0.00% 0.00%

Instrument Installation & Calibration 160 2.49% 10 0.00% 0.00% 0.00% 0.00% 25‐Feb‐12 6‐Mar‐12 0.00% 0.00%

E&I1160 Instrument Installation & Calibration 160 100.00% 10 0.00% 0.00% 0.00% 25‐Feb‐12 6‐Mar‐12 0.00% 0.00%

Air Gas Header 128 1.99% 8 0.00% 0.00% 0.00% 0.00% 24‐Feb‐12 3‐Mar‐12 0.00% 0.00%

E&I1170 Air Gas Header 128 100.00% 8 0.00% 0.00% 0.00% 24‐Feb‐12 3‐Mar‐12 0.00% 0.00%

Cable Laying & Termination 1200 18.68% 25 0.00% 0.00% 0.00% 0.00% 12‐Feb‐12 8‐Mar‐12 0.00% 0.00%

E&I1180 Cable Laying & Termination 1200 100.00% 25 0.00% 0.00% 0.00% 12‐Feb‐12 8‐Mar‐12 0.00% 0.00%

Fire & Gas activities 128 1.99% 8 0.00% 0.00% 0.00% 0.00% 1‐Mar‐12 9‐Mar‐12 0.00% 0.00%

E&I1190 Fire & Gas activities 128 100.00% 8 0.00% 0.00% 0.00% 1‐Mar‐12 9‐Mar‐12 0.00% 0.00%

Telecommunication System 128 1.99% 8 0.00% 0.00% 0.00% 0.00% 1-Mar-12 9-Mar-12 0.00% 0.00%

E&I1200 Telecommunication System 128 100.00% 8 0.00% 0.00% 0.00% 1-Mar-12 9-Mar-12 0.00% 0.00%

Electrical 6856 51.63% 76 0.00% 0.00% 0.00% 0.00% 16-Dec-11 01-Mar-12 0.00% 0.00%

Cable Trays Supports 1336 19.49% 52 0.00% 0.00% 0.00% 0.00% 16-Dec-11 6-Feb-12 0.00% 0.00%

E&I1000 Fabrication 832 62.28% 26 0.00% 0.00% 0.00% 16‐Dec‐11 11‐Jan‐12 0.00% 0.00%

E&I1010 Installation 504 37.72% 14 0.00% 0.00% 0.00% 23‐Jan‐12 6‐Feb‐12 0.00% 0.00%

Cable Trays 1248 18.20% 26 0.00% 0.00% 0.00% 0.00% 23-Jan-12 18-Feb-12 0.00% 0.00%

E&I1020 Installation 1248 100.00% 26 0.00% 0.00% 0.00% 23‐Jan‐12 18‐Feb‐12 0.00% 0.00%

Conduit Activities 912 13.30% 38 0.00% 0.00% 0.00% 0.00% 16-Dec-11 23-Jan-12 0.00% 0.00%

E&I1030 Installation 912 100.00% 38 0.00% 0.00% 0.00% 16‐Dec‐11 23‐Jan‐12 0.00% 0.00%

Lighting Activities 1000 14.59% 25 0.00% 0.00% 0.00% 0.00% 31-Dec-11 25-Jan-12 0.00% 0.00%

E&I1040 Lighting Activities 1000 100.00% 25 0.00% 0.00% 0.00% 31‐Dec‐11 25‐Jan‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\29/40

Page 143: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP5 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

Navigation Aids 240 3.50% 15 0.00% 0.00% 0.00% 0.00% 16-Dec-11 31-Dec-11 0.00% 0.00%

E&I1050 Navigation Aids 240 100.00% 15 0.00% 0.00% 0.00% 16‐Dec‐11 31‐Dec‐11 0.00% 0.00%

Earthing Activities 280 4.08% 14 0.00% 0.00% 0.00% 0.00% 16-Feb-12 1-Mar-12 0.00% 0.00%

E&I1060 Earthing Activities 280 100.00% 14 0.00% 0.00% 0.00% 16‐Feb‐12 1‐Mar‐12 0.00% 0.00%

Power & Small Equip. Inst. 240 3.50% 12 0.00% 0.00% 0.00% 0.00% 16-Feb-12 28-Feb-12 0.00% 0.00%

E&I1070 Power & Small Equip. Inst. 240 100.00% 12 0.00% 0.00% 0.00% 16‐Feb‐12 28‐Feb‐12 0.00% 0.00%

Cable Laying & Termination 1600 23.34% 25 0.00% 0.00% 0.00% 0.00% 31-Jan-12 25-Feb-12 0.00% 0.00%

E&I1080 Cable Laying & Termination 1600 100.00% 25 0.00% 0.00% 0.00% 31‐Jan‐12 25‐Feb‐12 0.00% 0.00%

EQUIPMENT 5232 3.17% 71 0.00% 0.00% 0.00% 0.00% 07‐Dec‐11 16‐Feb‐12 0.00% 0.00%

PTJ2070 Equipment installation start 0 0.00% 0 0.00% 0.00% 0.00% 23-Dec-11 23-Dec-11 0.00% 0.00%

PTJ2130 Equipment installation finish 0 0.00% 0 0.00% 0.00% 0.00% 16‐Feb‐12 16‐Feb‐12 0.00% 0.00%

Equipement Installation (onshore) 5232 100.00% 71 0.00% 0.00% 0.00% 0.00% 07‐Dec‐11 16‐Feb‐12 0.00% 0.00%

TSF1110 Installation of production manifold module on celler deck 288 5.50% 4 0.00% 0.00% 0.00% 7‐Dec‐11 10‐Dec‐11 0.00% 0.00%

TSF1090 Equipment Installation on Heli Deck 288 5.50% 4 0.00% 0.00% 0.00% 23‐Dec‐11 27‐Dec‐11 0.00% 0.00%

TSF1100 Installation of E & I module on main deck 288 5.50% 4 0.00% 0.00% 0.00% 7‐Jan‐12 10‐Jan‐12 0.00% 0.00%

TSF1070 Equipment Installation on Cellar Deck 2040 38.99% 15 0.00% 0.00% 0.00% 1-Feb-12 16-Feb-12 0.00% 0.00%

TSF1080 Equipment Installation on Main Deck 2040 38.99% 15 0.00% 0.00% 0.00% 1‐Feb‐12 16‐Feb‐12 0.00% 0.00%

TSF1060 Equipment Installation Below Cellar Deck 288 5.50% 4 0.00% 0.00% 0.00% 12‐Feb‐12 16‐Feb‐12 0.00% 0.00%

PIPING 17572 10.64% 113 0.00% 0.00% 0.00% 0.00% 19‐Nov‐11 11‐Mar‐12 0.00% 0.00%

PTJ2050 Piping & piping support fabrication start 0 0.00% 0 0.00% 0.00% 0.00% 19‐Nov‐11 19‐Nov‐11 0.00% 0.00%

PTJ2110 Piping & piping support erection finish 0 0.00% 0 0.00% 0.00% 0.00% 11‐Mar‐12 11‐Mar‐12 0.00% 0.00%

C.S Piping Fab. & Erec., Valves Erection (onshore) 17572 100.00% 113 0.00% 0.00% 0.00% 0.00% 19‐Nov‐11 11‐Mar‐12 0.00% 0.00%

TSF1000 Piping Fabrication 8960 50.99% 70 0.00% 0.00% 0.00% 19‐Nov‐11 28‐Jan‐12 0.00% 0.00%

TSF1010 Piping Supports Fabrication 1408 8.01% 22 0.00% 0.00% 0.00% 19‐Nov‐11 11‐Dec‐11 0.00% 0.00%

TSF1020 Piping Erection 4760 27.09% 35 0.00% 0.00% 0.00% 26‐Jan‐12 1‐Mar‐12 0.00% 0.00%

TSF1030 Piping Supports Erection 800 4.55% 20 0.00% 0.00% 0.00% 10‐Feb‐12 1‐Mar‐12 0.00% 0.00%

TSF1040 Valve Installation 300 1.71% 15 0.00% 0.00% 0.00% 15‐Feb‐12 1‐Mar‐12 0.00% 0.00%

PTJ2120 Piping hydrotest 1344 7.65% 21 0.00% 0.00% 0.00% 19‐Feb‐12 11‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\30/40

Page 144: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

CLIENT : PETROBELPROJECT : SETH DEVELOPMENT PROJECT WK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.6: PIPELINE SPOOLS FABRICATION 21752 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 25-Apr-12 0.00% 0.00%

SETH PLEM & EXISTING TUNA PLEM 10992 50.53% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 25‐Apr‐12 0.00% 0.00%

SPOOL NO. S1 (CLOSING) ( P.L ‐ S2 ) 1948 17.72% 59 0.00% 0.00% 0.00% 0.00% 24‐Mar‐12 25‐Apr‐12 0.00% 0.00%

BEFORE METROLOGY 1652 84.80% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

PIPE LINE & BENDS 1652 100.00% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

SS740 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.91% 48 0.00% 0.00% 0.00% 16-Apr-12 18-Apr-12 0.00% 0.00%

Act ID Activity NameTotal

Budgete Units (Hrs)

R.W %Original Duration

(Days)

25‐Jun‐11 WEEK NO.

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PETROJET

p p

SS750 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.87% 48 0.00% 0.00% 0.00% 18‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SS690 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.81% 48 0.00% 0.00% 0.00% 24-Mar-12 26-Mar-12 0.00% 0.00%

SS760 APPLY SHRINKABLE SLEEVE 128 7.75% 60 0.00% 0.00% 0.00% 21-Apr-12 23-Apr-12 0.00% 0.00%

SS700 CUTTING & BEVELING BEFORE METROLOGY 180 10.90% 48 0.00% 0.00% 0.00% 26-Mar-12 29-Mar-12 0.00% 0.00%

SS710 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 240 14.53% 48 0.00% 0.00% 0.00% 29-Mar-12 4-Apr-12 0.00% 0.00%

SS730 COATING OF BENDS 384 23.24% 48 0.00% 0.00% 0.00% 14‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SS720 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY 512 30.99% 48 0.00% 0.00% 0.00% 04-Apr-12 14-Apr-12 0.00% 0.00%

AFTER METROLOGY 296 15.20% 59 0.00% 0.00% 0.00% 0.00% 15-Apr-12 25-Apr-12 0.00% 0.00%

SS770 RECEVING METROLOGY 0 0.00% 60 0.00% 0.00% 0.00% 15-Apr-12 15-Apr-12 0.00% 0.00%

SS810 APPLY SHRINKABLE SLEEVE 32 10.81% 60 0.00% 0.00% 0.00% 23-Apr-12 24-Apr-12 0.00% 0.00%

SS800 PIGGING & HYDRO TEST 32 10.81% 60 0.00% 0.00% 0.00% 21-Apr-12 23-Apr-12 0.00% 0.00%

SS820 LIFTING TEST 32 10.81% 60 0.00% 0.00% 0.00% 24-Apr-12 25-Apr-12 0.00% 0.00%

SS780 FIT UP AFTER METROLOGY 72 24.32% 60 0.00% 0.00% 0.00% 15-Apr-12 17-Apr-12 0.00% 0.00%

SS790 WELDING & NDT AFTER METROLOGY 128 43.24% 60 0.00% 0.00% 0.00% 17-Apr-12 21-Apr-12 0.00% 0.00%

SPOOL NO. S2 ( S1 ‐ S3 ) 1716 15.61% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS910 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22-Mar-12 23-Mar-12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\31/40

Page 145: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

SS920 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24-Mar-12 24-Mar-12 0.00% 0.00%

SS880 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18-Mar-12 19-Mar-12 0.00% 0.00%

SS890 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20-Mar-12 21-Mar-12 0.00% 0.00%

SS830 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23-Feb-12 25-Feb-12 0.00% 0.00%

SS900 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22-Mar-12 23-Mar-12 0.00% 0.00%

SS840 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26-Feb-12 28-Feb-12 0.00% 0.00%

SS850 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29-Feb-12 5-Mar-12 0.00% 0.00%

SS870 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15-Mar-12 21-Mar-12 0.00% 0.00%

SS860 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 6-Mar-12 14-Mar-12 0.00% 0.00%

SPOOL NO. S3 (CLOSING) ( S2 ‐ S4 ) 1948 17.72% 59 0.00% 0.00% 0.00% 0.00% 24‐Mar‐12 25‐Apr‐12 0.00% 0.00%

BEFORE METROLOGY 1652 84.80% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

& 1652 100 00% 59 0 00% 0 00% 0 00% 0 00% 24 12 23 A 12 0 00% 0 00% PIPE LINE & BENDS 1652 100.00% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

SS980 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.91% 48 0.00% 0.00% 0.00% 16-Apr-12 18-Apr-12 0.00% 0.00%

SS990 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.87% 48 0.00% 0.00% 0.00% 18-Apr-12 21-Apr-12 0.00% 0.00%

SS930 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.81% 48 0.00% 0.00% 0.00% 24-Mar-12 26-Mar-12 0.00% 0.00%

SS1000 APPLY SHRINKABLE SLEEVE 128 7.75% 60 0.00% 0.00% 0.00% 21-Apr-12 23-Apr-12 0.00% 0.00%

SS940 CUTTING & BEVELING BEFORE METROLOGY 180 10.90% 48 0.00% 0.00% 0.00% 26-Mar-12 29-Mar-12 0.00% 0.00%

SS950 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 240 14.53% 48 0.00% 0.00% 0.00% 29-Mar-12 4-Apr-12 0.00% 0.00%

SS970 COATING OF BENDS 384 23.24% 48 0.00% 0.00% 0.00% 14-Apr-12 21-Apr-12 0.00% 0.00%

SS960 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY 512 30.99% 48 0.00% 0.00% 0.00% 04‐Apr‐12 14‐Apr‐12 0.00% 0.00%

AFTER METROLOGY 296 15.20% 59 0.00% 0.00% 0.00% 0.00% 15-Apr-12 25-Apr-12 0.00% 0.00%

SS1010 RECEVING METROLOGY 0 0.00% 60 0.00% 0.00% 0.00% 15-Apr-12 15-Apr-12 0.00% 0.00%

SS1050 APPLY SHRINKABLE SLEEVE 32 10.81% 60 0.00% 0.00% 0.00% 23-Apr-12 24-Apr-12 0.00% 0.00%

SS1040 PIGGING & HYDRO TEST 32 10.81% 60 0.00% 0.00% 0.00% 21-Apr-12 23-Apr-12 0.00% 0.00%

SS1060 LIFTING TEST 32 10.81% 60 0.00% 0.00% 0.00% 24-Apr-12 25-Apr-12 0.00% 0.00%

SS1020 FIT UP AFTER METROLOGY 72 24.32% 60 0.00% 0.00% 0.00% 15-Apr-12 17-Apr-12 0.00% 0.00%

SS1030 WELDING & NDT AFTER METROLOGY 128 43.24% 60 0.00% 0.00% 0.00% 17-Apr-12 21-Apr-12 0.00% 0.00%

SPOOL NO. S4 ( S4 ‐ SETH PLEM ) 1716 15.61% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\32/40

Page 146: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS1150 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS1160 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24-Mar-12 24-Mar-12 0.00% 0.00%

SS1120 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18-Mar-12 19-Mar-12 0.00% 0.00%

SS1130 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20-Mar-12 21-Mar-12 0.00% 0.00%

SS1070 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23-Feb-12 25-Feb-12 0.00% 0.00%

SS1140 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS1080 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26-Feb-12 28-Feb-12 0.00% 0.00%

SS1090 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29-Feb-12 05-Mar-12 0.00% 0.00%

SS1110 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15-Mar-12 21-Mar-12 0.00% 0.00%

SS1100 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 06‐Mar‐12 14‐Mar‐12 0.00% 0.00%

SPOOL NO. S5 ( SETH PLEM ‐ S6 ) 1716 15.61% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS1250 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22-Mar-12 23-Mar-12 0.00% 0.00%

SS1260 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24-Mar-12 24-Mar-12 0.00% 0.00%

SS1220 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18-Mar-12 19-Mar-12 0.00% 0.00%

SS1230 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20-Mar-12 21-Mar-12 0.00% 0.00%

SS1170 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23-Feb-12 25-Feb-12 0.00% 0.00%

SS1240 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22-Mar-12 23-Mar-12 0.00% 0.00%

SS1180 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26-Feb-12 28-Feb-12 0.00% 0.00%

SS1190 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29-Feb-12 5-Mar-12 0.00% 0.00%

SS1210 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15-Mar-12 21-Mar-12 0.00% 0.00%

SS1200 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 6-Mar-12 14-Mar-12 0.00% 0.00%

SPOOL NO. S6 (CLOSING) ( S5 ‐ TUNA PLEM ) 1948 17.72% 59 0.00% 0.00% 0.00% 0.00% 24‐Mar‐12 25‐Apr‐12 0.00% 0.00%

BEFORE METROLOGY 1652 84.80% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

PIPE LINE & BENDS 1652 100.00% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

SS1320 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.91% 48 0.00% 0.00% 0.00% 16-Apr-12 18-Apr-12 0.00% 0.00%

SS1330 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.87% 48 0.00% 0.00% 0.00% 18-Apr-12 21-Apr-12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\33/40

Page 147: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

SS1270 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.81% 48 0.00% 0.00% 0.00% 24-Mar-12 26-Mar-12 0.00% 0.00%

SS1340 APPLY SHRINKABLE SLEEVE 128 7.75% 60 0.00% 0.00% 0.00% 21-Apr-12 23-Apr-12 0.00% 0.00%

SS1280 CUTTING & BEVELING BEFORE METROLOGY 180 10.90% 48 0.00% 0.00% 0.00% 26‐Mar‐12 29‐Mar‐12 0.00% 0.00%

SS1290 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 240 14.53% 48 0.00% 0.00% 0.00% 29-Mar-12 4-Apr-12 0.00% 0.00%

SS1310 COATING OF BENDS 384 23.24% 48 0.00% 0.00% 0.00% 14-Apr-12 21-Apr-12 0.00% 0.00%

SS1300 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY 512 30.99% 48 0.00% 0.00% 0.00% 4‐Apr‐12 14‐Apr‐12 0.00% 0.00%

AFTER METROLOGY 296 15.20% 59 0.00% 0.00% 0.00% 0.00% 15-Apr-12 25-Apr-12 0.00% 0.00%

SS1350 RECEVING METROLOGY 0 0.00% 60 0.00% 0.00% 0.00% 15-Apr-12 15-Apr-12 0.00% 0.00%

SS1390 APPLY SHRINKABLE SLEEVE 32 10.81% 60 0.00% 0.00% 0.00% 23‐Apr‐12 24‐Apr‐12 0.00% 0.00%

SS1380 PIGGING & HYDRO TEST 32 10.81% 60 0.00% 0.00% 0.00% 21‐Apr‐12 23‐Apr‐12 0.00% 0.00%

SS1400 LIFTING TEST 32 10.81% 60 0.00% 0.00% 0.00% 24‐Apr‐12 25‐Apr‐12 0.00% 0.00%

SS1360 FIT UP AFTER METROLOGY 72 24.32% 60 0.00% 0.00% 0.00% 15-Apr-12 17-Apr-12 0.00% 0.00%

SS1370 WELDING & NDT AFTER METROLOGY 128 43.24% 60 0.00% 0.00% 0.00% 17‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SETH P/F & NEW SSIV 10760 49.47% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 25‐Apr‐12 0.00% 0.00%

SPOOL NO. S6 (CLOSING) ( S5 ‐ SETH P/F ) 1948 18.10% 59 0.00% 0.00% 0.00% 0.00% 24‐Mar‐12 25‐Apr‐12 0.00% 0.00%

BEFORE METROLOGY 1652 84.80% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

PIPE LINE & BENDS 1652 100.00% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

SS600 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.91% 48 0.00% 0.00% 0.00% 16‐Apr‐12 18‐Apr‐12 0.00% 0.00%

SS610 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.87% 48 0.00% 0.00% 0.00% 18‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SS550 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.81% 48 0.00% 0.00% 0.00% 24‐Mar‐12 26‐Mar‐12 0.00% 0.00%

SS620 APPLY SHRINKABLE SLEEVE 128 7.75% 60 0.00% 0.00% 0.00% 21‐Apr‐12 23‐Apr‐12 0.00% 0.00%

SS560 CUTTING & BEVELING BEFORE METROLOGY 180 10.90% 48 0.00% 0.00% 0.00% 26‐Mar‐12 29‐Mar‐12 0.00% 0.00%

SS570 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 240 14.53% 48 0.00% 0.00% 0.00% 29‐Mar‐12 4‐Apr‐12 0.00% 0.00%

SS590 COATING OF BENDS 384 23.24% 48 0.00% 0.00% 0.00% 14‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SS580 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY 512 30.99% 48 0.00% 0.00% 0.00% 4‐Apr‐12 14‐Apr‐12 0.00% 0.00%

AFTER METROLOGY 296 15.20% 59 0.00% 0.00% 0.00% 0.00% 15-Apr-12 25-Apr-12 0.00% 0.00%

SS630 RECEVING METROLOGY 0 0.00% 60 0.00% 0.00% 0.00% 15‐Apr‐12 15‐Apr‐12 0.00% 0.00%

SS670 APPLY SHRINKABLE SLEEVE 32 10.81% 60 0.00% 0.00% 0.00% 23‐Apr‐12 24‐Apr‐12 0.00% 0.00%

SS660 PIGGING & HYDRO TEST 32 10.81% 60 0.00% 0.00% 0.00% 21‐Apr‐12 23‐Apr‐12 0.00% 0.00%

SS680 LIFTING TEST 32 10.81% 60 0.00% 0.00% 0.00% 24‐Apr‐12 25‐Apr‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\34/40

Page 148: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

SS640 FIT UP AFTER METROLOGY 72 24.32% 60 0.00% 0.00% 0.00% 15-Apr-12 17-Apr-12 0.00% 0.00%

SS650 WELDING & NDT AFTER METROLOGY 128 43.24% 60 0.00% 0.00% 0.00% 17‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SPOOL NO. S2 ( S1 ‐ SSIV ) 1716 15.95% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS230 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS240 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24‐Mar‐12 24‐Mar‐12 0.00% 0.00%

SS200 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18‐Mar‐12 19‐Mar‐12 0.00% 0.00%

SS210 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS150 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23‐Feb‐12 25‐Feb‐12 0.00% 0.00%

SS220 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS160 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26‐Feb‐12 28‐Feb‐12 0.00% 0.00%

SS170 FIT UP FOR LINE PIPE & BENDS 240 13 99% 47 0 00% 0 00% 0 00% 29 Feb 12 5 Mar 12 0 00% 0 00% SS170 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29‐Feb‐12 5‐Mar‐12 0.00% 0.00%

SS190 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS180 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 6‐Mar‐12 14‐Mar‐12 0.00% 0.00%

SPOOL NO. S3 ( SSIV ‐S4 ) 1716 15.95% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS330 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS340 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24‐Mar‐12 24‐Mar‐12 0.00% 0.00%

SS300 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18‐Mar‐12 19‐Mar‐12 0.00% 0.00%

SS310 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS250 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23‐Feb‐12 25‐Feb‐12 0.00% 0.00%

SS320 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS260 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26‐Feb‐12 28‐Feb‐12 0.00% 0.00%

SS270 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29‐Feb‐12 5‐Mar‐12 0.00% 0.00%

SS290 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS280 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 6‐Mar‐12 14‐Mar‐12 0.00% 0.00%

SPOOL NO. S1 (CLOSING) ( P.L ‐ SETH PLEM ) 1948 18.10% 59 0.00% 0.00% 0.00% 0.00% 24‐Mar‐12 25‐Apr‐12 0.00% 0.00%

BEFORE METROLOGY 1652 84.80% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

PIPE LINE & BENDS 1652 100.00% 59 0.00% 0.00% 0.00% 0.00% 24-Mar-12 23-Apr-12 0.00% 0.00%

SS060 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.91% 48 0.00% 0.00% 0.00% 16‐Apr‐12 18‐Apr‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\35/40

Page 149: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

SS070 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.87% 48 0.00% 0.00% 0.00% 18‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SS 10 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.81% 48 0.00% 0.00% 0.00% 24‐Mar‐12 26‐Mar‐12 0.00% 0.00%

SS080 APPLY SHRINKABLE SLEEVE 128 7.75% 60 0.00% 0.00% 0.00% 21‐Apr‐12 23‐Apr‐12 0.00% 0.00%

SS020 CUTTING & BEVELING BEFORE METROLOGY 180 10.90% 48 0.00% 0.00% 0.00% 26‐Mar‐12 29‐Mar‐12 0.00% 0.00%

SS030 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 240 14.53% 48 0.00% 0.00% 0.00% 29‐Mar‐12 4‐Apr‐12 0.00% 0.00%

SS050 COATING OF BENDS 384 23.24% 48 0.00% 0.00% 0.00% 14‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SS040 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY 512 30.99% 48 0.00% 0.00% 0.00% 4‐Apr‐12 14‐Apr‐12 0.00% 0.00%

AFTER METROLOGY 296 15.20% 59 0.00% 0.00% 0.00% 0.00% 15-Apr-12 25-Apr-12 0.00% 0.00%

SS090 RECEVING METROLOGY 0 0.00% 60 0.00% 0.00% 0.00% 15‐Apr‐12 15‐Apr‐12 0.00% 0.00%

SS130 APPLY SHRINKABLE SLEEVE 32 10.81% 60 0.00% 0.00% 0.00% 23‐Apr‐12 24‐Apr‐12 0.00% 0.00%

SS120 PIGGING & HYDRO TEST 32 10.81% 60 0.00% 0.00% 0.00% 21‐Apr‐12 23‐Apr‐12 0.00% 0.00%

SS140 LIFTING TEST 32 10.81% 60 0.00% 0.00% 0.00% 24‐Apr‐12 25‐Apr‐12 0.00% 0.00%

SS100 FIT UP AFTER METROLOGY 72 24.32% 60 0.00% 0.00% 0.00% 15‐Apr‐12 17‐Apr‐12 0.00% 0.00%

SS110 WELDING & NDT AFTER METROLOGY 128 43.24% 60 0.00% 0.00% 0.00% 17‐Apr‐12 21‐Apr‐12 0.00% 0.00%

SPOOL NO. S5 ( S4 ‐ S6 ) 1716 15.95% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS530 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS540 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24‐Mar‐12 24‐Mar‐12 0.00% 0.00%

SS500 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18‐Mar‐12 19‐Mar‐12 0.00% 0.00%

SS510 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS450 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23‐Feb‐12 25‐Feb‐12 0.00% 0.00%

SS520 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS460 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26‐Feb‐12 28‐Feb‐12 0.00% 0.00%

SS470 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29‐Feb‐12 5‐Mar‐12 0.00% 0.00%

SS490 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS480 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 6‐Mar‐12 14‐Mar‐12 0.00% 0.00%

SPOOL NO. S4 ( S3 ‐ S5 ) 1716 15.95% 59 0.00% 0.00% 0.00% 0.00% 23‐Feb‐12 24‐Mar‐12 0.00% 0.00%

PIPE LINE & BENDS 1716 100.00% 59 0.00% 0.00% 0.00% 0.00% 23-Feb-12 24-Mar-12 0.00% 0.00%

SS430 PIGGING & HYDRO TEST 32 1.86% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS440 LIFTING TEST 32 1.86% 60 0.00% 0.00% 0.00% 24‐Mar‐12 24‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\36/40

Page 150: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP6 PROGRESS Sheet

ITEM OVERALL ITEM OVERALLAct ID Activity Name

Total Budgete

Units (Hrs)R.W %

Original Duration

(Days)

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

SS400 FIT UP FLANGES AND FITTING WITH LINE PIPE 48 2.80% 47 0.00% 0.00% 0.00% 18‐Mar‐12 19‐Mar‐12 0.00% 0.00%

SS410 WELDING & NDT FOR FLANGES WITH LINE PIPE 64 3.73% 47 0.00% 0.00% 0.00% 20‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS350 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 96 5.59% 47 0.00% 0.00% 0.00% 23‐Feb‐12 25‐Feb‐12 0.00% 0.00%

SS420 APPLY SHRINKABLE SLEEVE 128 7.46% 60 0.00% 0.00% 0.00% 22‐Mar‐12 23‐Mar‐12 0.00% 0.00%

SS360 CUTTING & BEVELING 180 10.49% 47 0.00% 0.00% 0.00% 26‐Feb‐12 28‐Feb‐12 0.00% 0.00%

SS370 FIT UP FOR LINE PIPE & BENDS 240 13.99% 47 0.00% 0.00% 0.00% 29‐Feb‐12 05‐Mar‐12 0.00% 0.00%

SS390 COATING OF BENDS 384 22.38% 47 0.00% 0.00% 0.00% 15‐Mar‐12 21‐Mar‐12 0.00% 0.00%

SS380 WELDING & NDT FOR LINE PIPE & BENDS 512 29.84% 47 0.00% 0.00% 0.00% 06‐Mar‐12 14‐Mar‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\37/40

Page 151: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP8 PROGRESS Sheet

CLIENT : PETROBELPROJECT : SETH DEVELOPMENT PROJECT WK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.8: LOAD‐OUT, SEA‐FASTENING, TRANSPORTATION & INSTALLATION 27456 100.00% 204 0.00% 0.00% 0.00% 0.00% 18-Oct-11 08-May-12 0.00% 0.00%

PTJ1070 Pre-drilling template seafastening and load out 840 3.06% 7 0.00% 0.00% 0.00% 18‐Oct‐11 24‐Oct‐11 0.00% 0.00%

PTJ1170 Sub Sea Spools Load out first trip 840 3.06% 7 0.00% 0.00% 0.00% 25‐Mar‐12 31‐Mar‐12 0.00% 0.00%

PTJ1180 Sub Sea Spools Load out second trip for closing spools 840 3.06% 7 0.00% 0.00% 0.00% 25-Apr-12 02-May-12 0.00% 0.00%

PTJ1060 Deck seafastening and load out 7896 28.76% 7 0.00% 0.00% 0.00% 02-May-12 08-May-12 0.00% 0.00%

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

25‐Jun‐11 WEEK NO.

Act ID Activity NameTotal

Budgete Units (Hrs)

R.W %Original Duration

(Days)

PETROJET

PTJ1050 Jacket & Piles seafastening and load out 17040 62.06% 15 0.00% 0.00% 0.00% 17-Mar-12 31-Mar-12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\38/40

Page 152: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

WP9 PROGRESS Sheet

CLIENT : PETROBELPROJECT : SETH DEVELOPMENT PROJECT WK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.9: OFFSHORE HOOKUP, COMMISSIONING AND ASSISTANT FOR START UP 100.00% 46 0.00% 0.00% 0.00% 0.00% 15-May-12 30-Jun-12 0.00% 0.00%

M01 May-12 50.00% 16 0.00% 0.00% 0.00% 0.00% 15-May-12 31-May-12 0.00% 0.00%

M02 Jun-12 50.00% 30 0.00% 0.00% 0.00% 0.00% 01-Jun-12 30-Jun-12 0.00% 0.00%

Act ID Activity Name R.W %Original Duration

(Days)

25‐Jun‐11 WEEK NO.

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

PETROJET

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\39/40

Page 153: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

CRASHING COST

CLIENT : PETROBELPROJECT : SETH DEVELOPMENT PROJECT WK DATE : 13

ITEM OVERALL ITEM OVERALL

W.P.1: PROJECT MANAGEMENT 100.00% 182 0.00% 0.00% 0.00% 0.00% 01-Nov-11 01-May-12 0.00% 0.00%

M01 Nov-11 10.00% 24 0.00% 0.00% 0.00% 0.00% 01-Nov-11 25-Nov-11 0.00% 0.00%

M02 Dec-11 20.00% 29 0.00% 0.00% 0.00% 0.00% 26‐Nov‐11 25‐Dec‐11 0.00% 0.00%

M03 Jan-12 20.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Dec‐11 25‐Jan‐12 0.00% 0.00%

ACTUAL % PLANNED %Start Date Finish Date DEV/ITEM

DEV/ OVERALL

25‐Jun‐11 WEEK NO.

Act ID Activity Name R.W %Original Duration

(Days)

PETROJET

M04 Feb-12 20.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Jan‐12 25‐Feb‐12 0.00% 0.00%

M05 Mar-12 20.00% 28 0.00% 0.00% 0.00% 0.00% 26‐Feb‐12 25‐Mar‐12 0.00% 0.00%

M06 Apr-12 10.00% 30 0.00% 0.00% 0.00% 0.00% 26‐Mar‐12 25‐Apr‐12 0.00% 0.00%

ص 02/07/201110:32 E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\40/40

Page 154: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 27 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.3. UPDATED SCHEDULE

Page 155: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SETH OFFSSETH OFFSHORE EPC PROJECT UPDATED SCHEDULE 335 31-Mar-11 31-Jul-12 28-Mar-11 A 31-Jul-12

CONTRACTCONTRACTUAL MILESTONES 335 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

A1 Project start 0 31-Mar-11 31-Mar-11 A

A1030 Finishing the basic engineering review and Endorsement report iss... 0 31-Mar-11 31-Mar-11 A

A2320 Recieve PTB LLI's Technical Offers from PTB 0 31-Mar-11 31-Mar-11 A

A17 Recieving LOI from PTB 0 31-Mar-11 31-Mar-11 A

A2290 All LLI's awarded (By Petrobel) 0 19-Apr-11 19-Apr-11 A

A2330 PTB LLI's TER's by Enppi 0 19-Apr-11 19-Apr-11 A

A2360 EPC Contract Signature 0 29-Apr-11 29-Apr-11 A

ART6.1 Authorization for Predrilling template ready for sail out: transportati... 0 24-Oct-11 24-Oct-11*

ART6.7 Pipeline spools ready for load out in four weeks from company req... 0 23-Mar-12 23-Mar-12

ART6.3 Deck Mechanical Completion 0 01-Apr-12 31-Mar-12*

ART6.2.1 Jacket and Piles ready for load out 0 14-Apr-12 14-Apr-12*

ART6.2.2 Company Authorization for Jacket & Piles ready for Sail out 0 21-Apr-12 21-Apr-12*

ART6.4.1 Deck and Flare Ready for Load out 0 01-May-12 30-Apr-12*

ART6.4.2 Company authorization for ready for sail out of Deck and flare 0 10-May-12 08-May-12

ART6.5 Offshore hook up and Final commissioning 0 02-Jul-12 30-Jun-12

A6.6 Assistance for start up (1) week from Company request 0 31-Jul-12 30-Jul-12

A2 Project completion 0 31-Jul-12 31-Jul-12*

ENPPIENPPI 335 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

W.P.1: PROW.P.1: PROJECT MANAGEMENT 335 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

A2380 Design review (Internal meeting) 3 07-Jul-11 12-Jul-11 21-Aug-11 23-Aug-11

A1010 Management activities 335 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

W.P.2: ENGW.P.2: ENGINEERING 255 31-Mar-11 21-Mar-12 31-Mar-11 A 08-Apr-12

PROCESSPROCESS 254 03-Apr-11 21-Mar-12 03-Apr-11 A 08-Apr-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 1 of 64

Remaining Level of Effort

Primary Baseline

Actual Work

Remaining...

Critical Re...

Baseline ...

Start Date:28-Mar-11Finish Date:31-Jul-12Data Date:25-Jun-11

By: Haytham A.RahmanDate Revision Checked Approved

25-May-11 Rev.0 A.Maghawry A.Fathy

Page 156: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A2230 HAZOP meeting 0 13-Jun-11 16-Jun-11 21-Jul-11 21-Jul-11

DrawingsDrawings 129 03-Apr-11 05-Oct-11 03-Apr-11 A 04-Oct-11

A2420 UFD's IFD 5 06-Apr-11 13-Apr-11 06-Apr-11 A 10-Apr-11 A

A1410 PFD's IFD 5 03-Apr-11 10-Apr-11 03-Apr-11 A 10-Apr-11 A

A2430 Heat and material balance IFD 5 03-Apr-11 10-Apr-11 03-Apr-11 A 10-Apr-11 A

A1420 P&ID's IFD 5 10-Apr-11 17-Apr-11 10-Apr-11 A 21-Apr-11 A

A2570 Escape route and safety signs layouts IFD 5 31-May-11 07-Jun-11 10-May-11 A 16-May-11 A

A2560 Fire fighting and safety layouts IFD 5 05-May-11 12-May-11 05-May-11 A 17-May-11 A

A2410 Process block diagram IFD 5 07-Jun-11 14-Jun-11 12-Jun-11 A 20-Jun-11 A

A2190 Cause & Effect IFD 5 09-May-11 16-May-11 19-May-11 A 23-Jun-11 A

A1570 P&ID's IFC 7 05-Sep-11 14-Sep-11 05-Sep-11 13-Sep-11

A2200 Cause & Effect IFC 5 14-Sep-11 21-Sep-11 14-Sep-11 20-Sep-11

A1560 PFD's IFF 5 14-Sep-11 21-Sep-11 14-Sep-11 20-Sep-11

A4750 UFD's IFF 5 21-Sep-11 28-Sep-11 21-Sep-11 27-Sep-11

A4760 Fire fighting and safety layouts IFC 5 21-Sep-11 28-Sep-11 21-Sep-11 27-Sep-11

A4740 Process block flow diagram IFF 5 21-Sep-11 28-Sep-11 21-Sep-11 27-Sep-11

A4770 Escape route and safety signs layouts IFC 5 28-Sep-11 05-Oct-11 28-Sep-11 04-Oct-11

Technical Technical Lists 249 10-Apr-11 21-Mar-12 10-Apr-11 A 08-Apr-12

A5320 Design basis IFD 3 10-Apr-11 12-Apr-11 10-Apr-11 A 12-Apr-11 A

A2550 Safety philosophy IFD 5 20-Apr-11 27-Apr-11 20-Apr-11 A 27-Apr-11 A

A2540 Hazardous area classification schedule IFD 5 26-Apr-11 04-May-11 26-Apr-11 A 05-May-11 A

A2210 Equipment list IFD 5 08-May-11 15-May-11 08-May-11 A 11-May-11 A

A2460 Utility load summary IFD 3 19-Jun-11 26-Jun-11 15-Jun-11 A 23-Jun-11 A

A2440 Process report IFD 13 05-Jun-11 12-Jun-11 26-Jun-11 12-Jul-11

A2450 Blow down report IFD 5 03-Jul-11 10-Jul-11 26-Jul-11 01-Aug-11

A2240 HAZOP Report 10 21-Jul-11 04-Aug-11 25-Aug-11 12-Sep-11

A2220 Equipment list IFF 5 12-Sep-11 19-Sep-11 12-Sep-11 18-Sep-11

A4790 Process report IFF 5 14-Sep-11 21-Sep-11 14-Sep-11 20-Sep-11

A4810 Utility load summary IFF 5 20-Sep-11 27-Sep-11 20-Sep-11 26-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 2 of 64

Page 157: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A4820 Hazardous area classification schedule IFC 5 21-Sep-11 28-Sep-11 21-Sep-11 27-Sep-11

A4800 Blow down report IFF 5 26-Sep-11 03-Oct-11 26-Sep-11 02-Oct-11

A4830 Safety philosophy IFF 5 03-Oct-11 11-Oct-11 03-Oct-11 10-Oct-11

A2580 Precommissioning procedures IFD 5 22-Feb-12 29-Feb-12 11-Mar-12 15-Mar-12

A2590 Plant operating guide IFD 5 29-Feb-12 07-Mar-12 18-Mar-12 22-Mar-12

A4840 Precommissioning procedures IFF 5 07-Mar-12 14-Mar-12 25-Mar-12 29-Mar-12

A4850 Plant operating guide IFF 5 14-Mar-12 21-Mar-12 01-Apr-12 08-Apr-12

MRQ'sMRQ's 52 03-Apr-11 09-May-11 03-Apr-11 A 29-May-11 A

A2470 Chemical injection package MRQ 3 03-Apr-11 06-Apr-11 03-Apr-11 A 06-Apr-11 A

A2490 Safety equipment and life saving MRQ 7 03-Apr-11 12-Apr-11 03-Apr-11 A 12-Apr-11 A

A2480 Fire protection system MRQ 5 06-Apr-11 12-Apr-11 06-Apr-11 A 12-Apr-11 A

A2510 Flame arrestor MRQ 5 20-Apr-11 27-Apr-11 13-Apr-11 A 17-Apr-11 A

A2500 Vent stack tips MRQ 5 02-May-11 09-May-11 01-May-11 A 09-May-11 A

A1440 Process commodities MRQ's (Other equipment) 15 10-Apr-11 02-May-11 06-Apr-11 A 29-May-11 A

TER'sTER's 78 08-May-11 11-Jul-11 18-Apr-11 A 26-Jul-11

A2600 Chemical injection package TER 30 08-May-11 19-Jun-11 18-Apr-11 A 01-Jun-11 A

A2610 Fire protection system TER 25 11-May-11 14-Jun-11 26-Apr-11 A 05-Jul-11

A2620 Safety equipment and life saving TER 25 08-May-11 12-Jun-11 26-Apr-11 A 07-Jul-11

A2640 Flame arrestor TER 20 26-May-11 23-Jun-11 26-Jun-11 21-Jul-11

A1450 Process commodities TER's 45 09-May-11 11-Jul-11 22-Apr-11 A 26-Jul-11

A2630 Vent stack tips TER 13 06-Jun-11 04-Jul-11 01-Jun-11 A 26-Jul-11

MRPMRP 43 10-Jul-11 29-Aug-11 03-Jul-11 04-Sep-11

A2660 Chemical injection package MRP 5 10-Jul-11 17-Jul-11 03-Jul-11 07-Jul-11

A2670 Fire protection system MRP 5 10-Jul-11 14-Jul-11 19-Jul-11 25-Jul-11

A2680 Safety equipment and life saving MRP 5 10-Jul-11 17-Jul-11 07-Aug-11 11-Aug-11

A2700 Flame arrestor MRP 5 21-Jul-11 28-Jul-11 21-Aug-11 25-Aug-11

A1460 Process commodities MRP's 25 25-Jul-11 29-Aug-11 27-Jul-11 04-Sep-11

A2690 Vent stack tips MRP 5 03-Aug-11 10-Aug-11 24-Aug-11 04-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 3 of 64

Page 158: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Vendor prVendor prints review 119 24-Jul-11 26-Dec-11 17-Jul-11 10-Jan-12

A2720 Chemical injection package Vendor prints review 100 25-Jul-11 25-Dec-11 17-Jul-11 14-Dec-11

A2740 Safety equipment and life saving Vendor prints review 80 25-Jul-11 24-Nov-11 21-Aug-11 21-Dec-11

A1470 Vendor prints review 100 25-Jul-11 25-Dec-11 26-Jul-11 25-Dec-11

A2760 Flame arrestor Vendor prints review 80 07-Aug-11 07-Dec-11 04-Sep-11 01-Jan-12

A2730 Fire protection system Vendor prints review 100 24-Jul-11 21-Dec-11 03-Aug-11 02-Jan-12

A2750 Vent stack tips Vendor prints review 80 23-Aug-11 26-Dec-11 13-Sep-11 10-Jan-12

PIPINGPIPING 240 31-Mar-11 24-Jan-12 31-Mar-11 A 03-Jan-12

DrawingsDrawings 178 17-Apr-11 04-Jan-12 05-Apr-11 A 03-Jan-12

A1660 Plot Plan IFD 5 17-Apr-11 24-Apr-11 05-Apr-11 A 10-Apr-11 A

A1670 Plot Plan IFC 5 14-Sep-11 21-Sep-11 14-Sep-11 20-Sep-11

A6220 GA's IFD 8 15-Sep-11 27-Sep-11 18-Sep-11 27-Sep-11

A1680 ISO's 10 31-Oct-11 20-Nov-11 31-Oct-11 17-Nov-11

A1690 GA's IFC 15 02-Nov-11 30-Nov-11 02-Nov-11 29-Nov-11

A2790 Hydro test maps IFC 7 24-Nov-11 06-Dec-11 24-Nov-11 05-Dec-11

A6190 Piping support plan IFC 5 14-Dec-11 21-Dec-11 14-Dec-11 20-Dec-11

A6200 Piping support location IFC 5 21-Dec-11 28-Dec-11 21-Dec-11 27-Dec-11

A6210 Piping penetration location IFC 5 28-Dec-11 04-Jan-12 28-Dec-11 03-Jan-12

Technical Technical Lists 145 12-May-11 14-Dec-11 19-May-11 A 13-Dec-11

A2780 Line Designation table (LDT) IFD 5 12-May-11 19-May-11 19-May-11 A 01-Jun-11 A

A4920 Line Designation table (LDT) IFC 5 14-Sep-11 21-Sep-11 14-Sep-11 20-Sep-11

A6180 Piping support list IFC 5 07-Dec-11 14-Dec-11 07-Dec-11 13-Dec-11

SpecificatSpecifications 44 16-May-11 13-Jun-11 16-May-11 A 14-Jul-11

A6230 Piping material classes IFD 5 16-May-11 23-May-11 16-May-11 A 23-May-11 A

A6240 Final Piping material classes 15 06-Jun-11 13-Jun-11 26-Jun-11 14-Jul-11

ModelModel 100 23-May-11 23-Nov-11 26-Jun-11 22-Nov-11

A1990 Model Review (30%) 14 23-May-11 26-May-11 26-Jun-11 13-Jul-11

A2000 Model Review (60%) 3 21-Jul-11 26-Jul-11 13-Sep-11 15-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 4 of 64

Page 159: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A2010 Model Review (90%) 3 20-Nov-11 23-Nov-11 20-Nov-11 22-Nov-11

MRQ'sMRQ's 16 31-Mar-11 24-Apr-11 31-Mar-11 A 29-May-11 A

A1720 Piping bulk MRQ 5 31-Mar-11 07-Apr-11 31-Mar-11 A 07-Apr-11 A

A5410 Injection fitting MRQ 5 17-Apr-11 24-Apr-11 17-Apr-11 A 24-Apr-11 A

A5400 Insulation Joint MRQ 5 13-Apr-11 20-Apr-11 22-May-11 A 29-May-11 A

TER'sTER's 55 10-May-11 15-Jun-11 28-Apr-11 A 24-Jul-11

A1730 Piping bulk TER 15 10-May-11 31-May-11 28-Apr-11 A 17-May-11 A

A5420 Insulation Joint TER 15 19-May-11 09-Jun-11 30-May-11 A 21-Jul-11

A5430 Injection fitting TER 19 25-May-11 15-Jun-11 28-Jun-11 24-Jul-11

MRPMRP 46 20-Jun-11 20-Jul-11 26-Jun-11 28-Aug-11

A1740 Piping bulk MRP 5 20-Jun-11 27-Jun-11 26-Jun-11 30-Jun-11

A5530 Injection fitting MRP 5 13-Jul-11 20-Jul-11 22-Aug-11 28-Aug-11

A5540 Insulation Joint MRP 5 10-Jul-11 17-Jul-11 22-Aug-11 28-Aug-11

Vendor prVendor prints review 180 04-May-11 24-Jan-12 14-Jun-11 A 03-Jan-12

A6110 Production Manifold Vendor prints review 180 04-May-11 24-Jan-12 14-Jun-11 A 05-Dec-11

A1750 Piping bulk Vendor prints review 100 05-Jul-11 05-Dec-11 10-Jul-11 07-Dec-11

A5550 Injection fitting Vendor prints review 80 28-Jul-11 30-Nov-11 06-Sep-11 03-Jan-12

A5560 Insulation Joint Vendor prints review 80 25-Jul-11 24-Nov-11 06-Sep-11 03-Jan-12

ELECTRICELECTRICAL 224 24-Apr-11 24-Jan-12 04-Apr-11 A 08-Jan-12

DrawingsDrawings 141 24-Apr-11 20-Oct-11 20-Apr-11 A 17-Nov-11

A3210 Lighting and navigational aids layouts IFD 5 24-Apr-11 02-May-11 20-Apr-11 A 26-Apr-11 A

A5290 Earthing layouts IFD 5 10-May-11 17-May-11 10-May-11 A 16-May-11 A

A3190 Hazardous area classification layout IFD 5 10-May-11 17-May-11 10-May-11 A 19-May-11 A

A1240 Electrical layouts IFD 15 09-May-11 30-May-11 25-May-11 A 23-Jun-11 A

A3200 Cable routing layouts IFD 5 19-May-11 26-May-11 16-Jun-11 A 23-Jun-11 A

A1230 Single line diagram IFD 20 23-May-11 30-May-11 26-Jun-11 21-Jul-11

A3220 Earthing layouts IFC 5 21-Sep-11 28-Sep-11 21-Sep-11 27-Sep-11

A1600 Electrical layouts IFC 8 21-Sep-11 03-Oct-11 21-Sep-11 02-Oct-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 5 of 64

Page 160: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A5310 Cable routing layouts IFC 5 28-Sep-11 05-Oct-11 28-Sep-11 04-Oct-11

A5300 Interconnecting wiring diagram IFC 5 29-Sep-11 09-Oct-11 29-Sep-11 05-Oct-11

A5270 Hazardous area classification schedule IFC 5 05-Oct-11 13-Oct-11 05-Oct-11 12-Oct-11

A1590 Single line diagram IFF 7 11-Oct-11 20-Oct-11 11-Oct-11 19-Oct-11

A5280 Lighting and navigational aids layouts IFC 5 12-Oct-11 19-Oct-11 13-Nov-11 17-Nov-11

Technical Technical Lists 73 15-May-11 11-Oct-11 26-Jun-11 10-Oct-11

A1580 Power system study IFD 15 15-May-11 24-May-11 26-Jun-11 14-Jul-11

A1250 Power system study IFF 10 26-Sep-11 11-Oct-11 26-Sep-11 10-Oct-11

MRQ'sMRQ's 52 24-Apr-11 20-Jun-11 04-Apr-11 A 22-Jun-11 A

A3030 Electrical Cables MRQ 5 02-May-11 09-May-11 04-Apr-11 A 10-Apr-11 A

A3040 Electrical Cable trays MRQ 5 24-Apr-11 02-May-11 05-Apr-11 A 10-Apr-11 A

A3050 Navigation aids system MRQ 5 09-May-11 16-May-11 20-Apr-11 A 26-Apr-11 A

A6130 Earthing material MRQ 17 30-May-11 06-Jun-11 29-May-11 A 20-Jun-11 A

A1980 Electrical commodities MRQ 15 30-May-11 20-Jun-11 10-Apr-11 A 22-Jun-11 A

A3060 Lighting material MRQ 18 26-May-11 02-Jun-11 25-May-11 A 22-Jun-11 A

TER'sTER's 55 22-May-11 18-Jul-11 20-Apr-11 A 04-Aug-11

A3080 Electrical Cable trays TER 20 22-May-11 19-Jun-11 20-Apr-11 A 02-May-11 A

A3070 Electrical Cables TER 20 23-May-11 20-Jun-11 25-Apr-11 A 29-May-11 A

A3090 Navigation aids system TER 20 30-May-11 27-Jun-11 16-May-11 A 10-Jul-11

A1210 Electrical commodities TER 25 13-Jun-11 18-Jul-11 03-Jul-11 04-Aug-11

A3100 Lighting material TER 20 08-Jun-11 06-Jul-11 10-Jul-11 04-Aug-11

A6250 Earthing material TER 20 20-Jun-11 18-Jul-11 10-Jul-11 04-Aug-11

MRPMRP 75 10-Jul-11 15-Sep-11 19-Jun-11 A 04-Oct-11

A3110 Electrical Cables MRP 5 13-Jul-11 20-Jul-11 19-Jun-11 A 20-Jun-11 A

A3120 Electrical Cable trays MRP 8 10-Jul-11 17-Jul-11 26-Jun-11 05-Jul-11

A3130 Navigation aids system MRP 5 19-Jul-11 26-Jul-11 02-Aug-11 08-Aug-11

A3140 Lighting material MRP 3 27-Jul-11 01-Aug-11 28-Aug-11 04-Sep-11

A6310 Earthing material MRP 5 08-Aug-11 15-Aug-11 28-Aug-11 06-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 6 of 64

Page 161: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A1700 Electrical commodities MRP 15 22-Aug-11 15-Sep-11 14-Sep-11 04-Oct-11

Vendor prVendor prints review 170 04-May-11 24-Jan-12 09-Jun-11 A 08-Jan-12

A3640 Electrical Cable trays Vendor prints review 80 25-Jul-11 24-Nov-11 10-Jul-11 02-Nov-11

A3150 Electrical Cables Vendor prints review 80 01-Aug-11 04-Dec-11 21-Jul-11 21-Nov-11

A6100 E&I Module Vendor prints review 170 04-May-11 24-Jan-12 09-Jun-11 A 05-Dec-11

A3250 Earthing Vendor prints review 60 23-Aug-11 28-Nov-11 11-Sep-11 11-Dec-11

A3170 Navigation aids system Vendor prints review 80 02-Aug-11 05-Dec-11 16-Aug-11 18-Dec-11

A3180 Lighting material Vendor prints review 80 11-Aug-11 14-Dec-11 11-Sep-11 08-Jan-12

INSTRUMEINSTRUMENTATION 235 31-Mar-11 22-Feb-12 31-Mar-11 A 08-Mar-12

DrawingsDrawings 131 05-May-11 16-Nov-11 20-Apr-11 A 16-Nov-11

A3280 Instrumenthook up drawing IFD 5 19-May-11 26-May-11 20-Apr-11 A 28-Apr-11 A

A3310 Instrument junction box and wiring diagram IFD 5 26-May-11 02-Jun-11 02-May-11 A 08-May-11 A

A3290 Field instrument layout IFD 5 05-May-11 12-May-11 05-May-11 A 19-May-11 A

A3300 Cable drawings IFD 16 12-May-11 19-May-11 25-May-11 A 14-Jun-11 A

A1270 Instrument Layouts & Wiring drawings IFD 15 19-May-11 09-Jun-11 20-Apr-11 A 15-Jun-11 A

A5660 Field instrument layout IFC 5 20-Oct-11 27-Oct-11 20-Oct-11 26-Oct-11

A5670 Cable drawings IFC 5 27-Oct-11 03-Nov-11 27-Oct-11 02-Nov-11

A5690 Instrumenthook up drawing IFC 5 01-Nov-11 14-Nov-11 01-Nov-11 13-Nov-11

A5680 Instrument junction box and wiring diagram IFC 5 03-Nov-11 16-Nov-11 03-Nov-11 15-Nov-11

A1280 Instrument Layouts & Wiring drawings IFC 15 20-Oct-11 16-Nov-11 20-Oct-11 16-Nov-11

Technical Technical Lists 104 26-Apr-11 25-Sep-11 26-Apr-11 A 22-Sep-11

A1290 Instrument Index IFD 5 26-Apr-11 04-May-11 26-Apr-11 A 03-May-11 A

A2250 Instrument data sheets 8 26-May-11 07-Jun-11 01-Jun-11 A 12-Jun-11 A

A3320 Instrument cable schedule IFD 0 26-May-11 02-Jun-11 08-Jun-11 A 15-Jun-11 A

A1610 Instrument Index IFC 7 14-Sep-11 25-Sep-11 14-Sep-11 22-Sep-11

MRQ'sMRQ's 74 31-Mar-11 09-Jun-11 31-Mar-11 A 26-Jun-11

A3330 HIPPS MRQ 5 31-Mar-11 07-Apr-11 01-Apr-11 A 03-Apr-11 A

A3340 Electro hydraulic wellhead control panel MRQ 5 04-Apr-11 12-Apr-11 31-Mar-11 A 07-Apr-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 7 of 64

Page 162: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A1310 Instrument commodities MRQ (HIPPS , Multiphase Flow Meter .....) 10 03-Apr-11 17-Apr-11 02-Apr-11 A 10-Apr-11 A

A3350 Multi phase f low meter MRQ 5 03-Apr-11 10-Apr-11 03-Apr-11 A 10-Apr-11 A

A3360 Wing valves MRQ 5 06-Apr-11 13-Apr-11 03-Apr-11 A 10-Apr-11 A

A3370 Choke valves MRQ 5 06-Apr-11 13-Apr-11 03-Apr-11 A 10-Apr-11 A

A5710 Instrument & Mechanical bulk material MRQ 5 26-May-11 02-Jun-11 25-Apr-11 A 03-May-11 A

A3380 Loose instrument MRQ 9 18-May-11 25-May-11 25-May-11 A 06-Jun-11 A

A5720 Junction boxes MRQ 0 02-Jun-11 09-Jun-11 25-May-11 A 06-Jun-11 A

A3390 Instrument cable and cable glands MRQ 22 16-May-11 23-May-11 25-May-11 A 23-Jun-11 A

A2310 Instrument commodities MRQ (Trays ,Bulks ,Cables .....) 35 20-Apr-11 09-Jun-11 25-May-11 A 26-Jun-11

A3400 Instrument Cable trays MRQ 20 24-May-11 31-May-11 31-May-11 A 26-Jun-11

A2820 Sand & Corrosion probes MRQ 22 25-May-11 01-Jun-11 25-May-11 A 26-Jun-11

TER'sTER's 73 24-Apr-11 07-Jul-11 02-Apr-11 A 18-Aug-11

A3430 Multi phase f low meter TER 20 15-May-11 12-Jun-11 28-Apr-11 A 25-May-11 A

A3410 HIPPS TER 20 03-May-11 31-May-11 26-Apr-11 A 09-Jun-11 A

A3440 Wing valves TER 20 16-May-11 13-Jun-11 02-May-11 A 15-Jun-11 A

A3420 Electro hydraulic wellhead control panel TER 20 15-May-11 12-Jun-11 21-Apr-11 A 16-Jun-11 A

A3450 Choke valves TER 20 18-May-11 15-Jun-11 26-Apr-11 A 05-Jul-11

A5950 Instrument & Mechanical bulk material TER 10 19-Jun-11 03-Jul-11 26-May-11 A 14-Jul-11

A3470 Instrument cable and cable glands TER 10 06-Jun-11 20-Jun-11 10-Jul-11 21-Jul-11

A5780 Junction boxes TER 10 23-Jun-11 07-Jul-11 21-Jun-11 A 21-Jul-11

A3460 Loose instrument TER 10 12-Jun-11 26-Jun-11 20-Jun-11 A 24-Jul-11

A3480 Instrument Cable trays TER 25 14-Jun-11 28-Jun-11 26-Jun-11 28-Jul-11

A5870 Sand & Corrosion probes TER 20 16-Jun-11 07-Jul-11 10-Jul-11 04-Aug-11

A2300 Instrument commodities TER's (Trays ,Bulks ,Cables .....) 35 19-May-11 07-Jul-11 26-Jun-11 11-Aug-11

A1340 Instrument commodities TER's (HIPPS , Multiphase Flow Meter .....) 40 24-Apr-11 20-Jun-11 02-Apr-11 A 18-Aug-11

MRPMRP 57 16-Jun-11 08-Aug-11 22-Jun-11 A 13-Sep-11

A3510 Multi phase f low meter MRP 5 10-Jul-11 17-Jul-11 22-Jun-11 A 23-Jun-11 A

A3500 Electro hydraulic wellhead control panel MRP 5 12-Jul-11 19-Jul-11 06-Jul-11 12-Jul-11

A3490 HIPPS MRP 5 28-Jun-11 05-Jul-11 07-Jul-11 13-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 8 of 64

Page 163: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A3520 Wing valves MRP 5 11-Jul-11 18-Jul-11 24-Jul-11 28-Jul-11

A3530 Choke valves MRP 5 10-Jul-11 17-Jul-11 27-Jul-11 02-Aug-11

A5960 Instrument & Mechanical bulk material MRP 5 24-Jul-11 31-Jul-11 07-Aug-11 11-Aug-11

A5790 Junction boxes MRP 5 28-Jul-11 04-Aug-11 14-Aug-11 18-Aug-11

A3550 Instrument cable and cable glands MRP 5 11-Jul-11 18-Jul-11 14-Aug-11 18-Aug-11

A3540 Loose instrument MRP 5 17-Jul-11 24-Jul-11 15-Aug-11 21-Aug-11

A3560 Cable trays MRP 5 14-Jul-11 21-Jul-11 16-Aug-11 22-Aug-11

A5380 Instrument cable trays MRP 5 14-Jul-11 21-Jul-11 16-Aug-11 22-Aug-11

A5880 Sand & Corrosion probes MRP 5 01-Aug-11 08-Aug-11 28-Aug-11 06-Sep-11

A1350 Instrument commodities MRP's 35 16-Jun-11 04-Aug-11 24-Jul-11 13-Sep-11

Vendor prVendor prints review 175 04-May-11 22-Feb-12 13-Jun-11 A 08-Mar-12

A3580 Electro hydraulic wellhead control panel Vendor prints review 80 27-Jul-11 29-Nov-11 21-Jul-11 21-Nov-11

A3600 Wing valves Vendor prints review 80 26-Jul-11 28-Nov-11 04-Aug-11 06-Dec-11

A6120 Shutdown and blowdown valves Vendor prints review 170 04-May-11 10-Jan-12 13-Jun-11 A 07-Dec-11

A3590 Multi phase f low meter Vendor prints review 100 25-Jul-11 25-Dec-11 10-Jul-11 07-Dec-11

A5970 Instrument & Mechanical bulk material Vendor prints review 70 08-Aug-11 24-Nov-11 21-Aug-11 07-Dec-11

A3610 Choke valves Vendor prints review 80 25-Jul-11 24-Nov-11 11-Aug-11 13-Dec-11

A5800 Junction boxes Vendor prints review 70 14-Aug-11 30-Nov-11 28-Aug-11 14-Dec-11

A3620 Loose instrument Vendor prints review 70 01-Aug-11 17-Nov-11 04-Sep-11 18-Dec-11

A5770 Instrument cable trays Vendor prints review 70 31-Jul-11 15-Nov-11 04-Sep-11 18-Dec-11

A5890 Sand & Corrosion probes Vendor prints review 70 16-Aug-11 05-Dec-11 11-Sep-11 25-Dec-11

A3630 Instrument cable and cable glands Vendor prints review 80 26-Jul-11 28-Nov-11 28-Aug-11 28-Dec-11

A3570 HIPPS Vendor prints review 150 13-Jul-11 22-Feb-12 24-Jul-11 01-Mar-12

A1360 Vendor prints Review 120 04-Aug-11 01-Feb-12 14-Sep-11 08-Mar-12

MECHANICMECHANICAL 239 03-Apr-11 01-Feb-12 03-Apr-11 A 01-Feb-12

Technical Technical Lists 120 04-Apr-11 26-Sep-11 04-Apr-11 A 25-Sep-11

A1050 Issue motor load list 1st issue 10 04-Apr-11 19-Apr-11 04-Apr-11 A 14-Apr-11 A

A6320 Issue motor load list 2nd issue 0 07-Jul-11 21-Jul-11 14-Jun-11 A 23-Jun-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 9 of 64

Page 164: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A5480 Handling Study 0 02-May-11 09-May-11 26-Jun-11 26-Jun-11

A2390 Issue motor load list IFF 10 12-Sep-11 26-Sep-11 12-Sep-11 25-Sep-11

MRQ'sMRQ's 84 03-Apr-11 28-Jul-11 03-Apr-11 A 28-Jul-11

A3670 Turret crane MRQ 5 06-Apr-11 13-Apr-11 03-Apr-11 A 10-Apr-11 A

A1060 Mechanical commodities MRQ's (Excluding Monorail crane) 10 03-Apr-11 17-Apr-11 03-Apr-11 A 25-Apr-11 A

A3650 Service water pump MRQ 5 18-Apr-11 25-Apr-11 18-Apr-11 A 25-Apr-11 A

A3680 Monorail crane MRQ 5 21-Jul-11 28-Jul-11 24-Jul-11 28-Jul-11

TER'sTER's 84 08-May-11 06-Sep-11 20-Apr-11 A 06-Sep-11

A3710 Turret crane TER 20 15-May-11 12-Jun-11 20-Apr-11 A 04-May-11 A

A3690 Service water pump TER 15 17-May-11 07-Jun-11 10-May-11 A 03-Jul-11

A1070 Mechanical commodities TER (Excluding Monorail crane) 25 08-May-11 12-Jun-11 20-Apr-11 A 04-Jul-11

A3720 Monorail crane TER 15 11-Aug-11 06-Sep-11 14-Aug-11 06-Sep-11

MRPMRP 92 10-Jul-11 10-Oct-11 10-May-11 A 10-Oct-11

A3750 Turret crane MRP 5 10-Jul-11 17-Jul-11 10-May-11 A 15-Jun-11 A

A1100 Mechanical commodities MRP 10 10-Jul-11 24-Jul-11 21-Jul-11 03-Aug-11

A3730 Service water pump MRP 5 11-Jul-11 18-Jul-11 28-Jul-11 03-Aug-11

A3760 Monorail crane MRP 3 04-Oct-11 10-Oct-11 05-Oct-11 10-Oct-11

Vendor prVendor prints review 181 04-May-11 01-Feb-12 26-May-11 A 01-Feb-12

A6330 Receiving final weights and dimensions for mechanical equipment 0 20-Sep-11 21-Sep-11

A3810 Micro Turbine Vendor prints review 180 04-May-11 24-Jan-12 26-May-11 A 22-Nov-11

A3820 Emergency GeneratorVendor prints review 160 04-May-11 24-Jan-12 12-Jun-11 A 05-Dec-11

A3790 Turret crane crane Vendor prints review 100 25-Jul-11 25-Dec-11 10-Jul-11 07-Dec-11

A3770 Service water pump Vendor prints review 80 26-Jul-11 28-Nov-11 14-Aug-11 14-Dec-11

A1120 Vendor prints review 100 25-Jul-11 25-Dec-11 15-Aug-11 12-Jan-12

A3800 Monorail crane Vendor prints review 80 04-Oct-11 01-Feb-12 05-Oct-11 01-Feb-12

OFFSHOROFFSHORE 155 31-Mar-11 05-Dec-11 10-Apr-11 A 04-Dec-11

DrawingsDrawings 126 30-May-11 05-Dec-11 30-May-11 A 04-Dec-11

A2350 Tray / Piping Supports Drawings IFD 10 30-May-11 13-Jun-11 30-May-11 A 13-Jun-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 10 of 64

Page 165: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A5340 Tray / Piping Supports Drawings IFC 10 20-Nov-11 05-Dec-11 20-Nov-11 04-Dec-11

ModelModel 145 18-Apr-11 20-Nov-11 18-Apr-11 A 17-Nov-11

A5350 Generate PDS Modeling For Topsides 20 18-Apr-11 17-May-11 18-Apr-11 A 17-May-11 A

A5360 Finalize PDS Modeling For Topsides based on Tecnomare IFC dw... 15 24-Oct-11 20-Nov-11 24-Oct-11 17-Nov-11

MRQ'sMRQ's 5 24-Apr-11 28-Apr-11 10-Apr-11 A 14-Apr-11 A

A1490 Survival module MRQ 5 24-Apr-11 28-Apr-11 10-Apr-11 A 14-Apr-11 A

TER'sTER's 20 01-Jun-11 28-Jun-11 22-May-11 A 03-Jul-11

A1500 Survival module TER 20 01-Jun-11 28-Jun-11 22-May-11 A 03-Jul-11

MRPMRP 5 20-Jul-11 26-Jul-11 25-Jul-11 31-Jul-11

A1510 Survival module MRP 5 20-Jul-11 26-Jul-11 25-Jul-11 31-Jul-11

Vendor prVendor prints review 60 31-Mar-11 26-Jun-11 26-Jun-11 20-Sep-11

A1530 Vendor prints review 60 31-Mar-11 26-Jun-11 26-Jun-11 20-Sep-11

W.P.3: PROW.P.3: PROCUREMENT SERVICES & MATERIAL SUPPLY 261 06-Apr-11 11-May-12 03-Apr-11 A 21-Apr-12

EQUIPMENEQUIPMENT 261 06-Apr-11 28-Apr-12 03-Apr-11 A 21-Apr-12

ENPPI LOENPPI LONG LEAD ITEMS (Cranes ,Chemical unjec.,Fire protec. , Survival M... 261 06-Apr-11 28-Apr-12 03-Apr-11 A 21-Apr-12

PURCHAPURCHASING 87 06-Apr-11 02-Aug-11 03-Apr-11 A 07-Aug-11

A3860 Chemical injection package Bidding 15 06-Apr-11 27-Apr-11 06-Apr-11 A 18-Apr-11 A

A4610 Turret crane Bidding 20 13-Apr-11 12-May-11 10-Apr-11 A 20-Apr-11 A

A4360 Electro hydraulic wellhead control panel Bidding 15 14-Apr-11 15-May-11 07-Apr-11 A 21-Apr-11 A

A4350 HIPPS Bidding 15 07-Apr-11 28-Apr-11 03-Apr-11 A 26-Apr-11 A

A3870 Fire protection system Bidding 10 13-Apr-11 26-Apr-11 13-Apr-11 A 26-Apr-11 A

A4370 Multi phase f low meter Bidding 20 10-Apr-11 09-May-11 10-Apr-11 A 28-Apr-11 A

A2080 Bidding (Multi phase f low , Chemical unjec.,Fire protec. , Survival ... 30 19-Apr-11 31-May-11 19-Apr-11 A 22-May-11 A

A4710 Survival module Bidding 22 02-May-11 31-May-11 14-Apr-11 A 22-May-11 A

A5140 Turret crane Issue Fax of commitment 3 12-Jun-11 10-Jul-11 25-May-11 A 29-May-11 A

B1040 Turret crane Issue PO 5 17-Jul-11 24-Jul-11 15-Jun-11 A 21-Jun-11 A

A5130 Multi phase f low meter Issue Fax of commitment 20 12-Jun-11 10-Jul-11 25-May-11 A 21-Jun-11 A

A4860 Chemical injection package Issue Fax of commitment 15 19-Jun-11 10-Jul-11 12-Jun-11 A 30-Jun-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 11 of 64

Page 166: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A1000 Multi phase f low meter Issue PO 6 17-Jul-11 24-Jul-11 26-Jun-11 03-Jul-11

A5250 Electro hydraulic wellhead control panel Issue Fax of commitment 8 14-Jun-11 12-Jul-11 26-Jun-11 05-Jul-11

A5120 HIPPS Issue Fax of commitment 20 31-May-11 28-Jun-11 20-Jun-11 A 06-Jul-11

B1050 Chemical injection package Issue PO 1 17-Jul-11 24-Jul-11 10-Jul-11 10-Jul-11

B1010 HIPPS Issue PO 0 05-Jul-11 12-Jul-11 14-Jul-11 14-Jul-11

A5330 Fire protection system Issue Fax of commitment 9 19-Jun-11 07-Jul-11 06-Jul-11 18-Jul-11

A5150 Survival module Issue Fax of commitment 15 29-Jun-11 19-Jul-11 04-Jul-11 24-Jul-11

A1020 Fire protection system Issue PO 5 17-Jul-11 21-Jul-11 26-Jul-11 01-Aug-11

A2090 Issue Fax of commitments (Multi phase f low , Chemical unjec.,Fir... 30 08-Jun-11 19-Jul-11 03-Apr-11 A 04-Aug-11

B1030 Survival module Issue PO 5 27-Jul-11 02-Aug-11 01-Aug-11 07-Aug-11

FABRICAFABRICATION 267 28-Jun-11 24-Mar-12 25-Jun-11 17-Mar-12

A4450 Multi phase f low meter Fabrication up to release for shipment 180 10-Jul-11 06-Jan-12 25-Jun-11 21-Dec-11

A3920 Chemical injection package Fabrication up to release for shipment 180 10-Jul-11 06-Jan-12 01-Jul-11 27-Dec-11

A4720 Survival module Fabrication up to release for shipment 160 20-Jul-11 26-Dec-11 25-Jul-11 31-Dec-11

A4440 Electro hydrolic wellhead control panel Fabrication up to release fo... 180 12-Jul-11 08-Jan-12 06-Jul-11 01-Jan-12

A3930 Fire protection system Fabrication up to release for shipment 170 08-Jul-11 03-Jan-12 19-Jul-11 04-Jan-12

A2100 Fabrication up to release for shipment (Multi phase f low , Chemica... 200 29-Jun-11 14-Jan-12 26-Jun-11 11-Jan-12

A4650 Turret crane Fabrication up to release for shipment 240 10-Jul-11 06-Mar-12 25-Jun-11 19-Feb-12

A2260 Fabrication up to release for shipment (HIPPS) 255 28-Jun-11 24-Mar-12 07-Jul-11 17-Mar-12

SHIPPINSHIPPING 144 30-Nov-11 28-Apr-12 30-Nov-11 21-Apr-12

A4480 Multi phase f low meter Shipping 21 06-Jan-12 27-Jan-12 22-Dec-11 11-Jan-12

A5210 Chemical injection package Shipping 21 06-Jan-12 27-Jan-12 28-Dec-11 17-Jan-12

A4730 Survival module Shipping 21 27-Dec-11 16-Jan-12 01-Jan-12 21-Jan-12

A4470 Electro hydraulic wellhead control panel Shipping 21 08-Jan-12 29-Jan-12 02-Jan-12 22-Jan-12

A5170 Multi phase f low meter Custom clearance & inland transportation 14 27-Jan-12 10-Feb-12 12-Jan-12 25-Jan-12

A2110 Shipping (Multi phase f low ,Chemical unjec.,Fire protec. , Survival... 60 30-Nov-11 29-Jan-12 30-Nov-11 28-Jan-12

A3990 Fire protection system Shipping 21 04-Jan-12 24-Jan-12 08-Jan-12 28-Jan-12

A3980 Chemical injection package Custom clearance & inland transportat... 14 27-Jan-12 10-Feb-12 18-Jan-12 31-Jan-12

A5200 Survival module Custom clearance & inland transportation 14 17-Jan-12 30-Jan-12 22-Jan-12 04-Feb-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 12 of 64

Page 167: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A5700 Electro hydraulic wellhead control panel Custom clearance & inla... 14 29-Jan-12 12-Feb-12 23-Jan-12 05-Feb-12

A2120 Custom clearance & inland transportation (Multi phase f low ,Che... 45 29-Dec-11 12-Feb-12 29-Dec-11 11-Feb-12

A5190 Fire protection system Custom clearance & inland transportation 14 25-Jan-12 07-Feb-12 29-Jan-12 11-Feb-12

A4690 Turret crane Shipping 14 06-Mar-12 20-Mar-12 20-Feb-12 04-Mar-12

A5180 Turret crane Custom clearance & inland transportation 14 20-Mar-12 03-Apr-12 05-Mar-12 18-Mar-12

A4460 HIPPS Shipping 21 24-Mar-12 14-Apr-12 18-Mar-12 07-Apr-12

A2280 HIPPS Custom clearance & inland transportation 14 14-Apr-12 28-Apr-12 08-Apr-12 21-Apr-12

OTHER EOTHER EQUIPMENT (Service pumps,Flame arrestor,Vent ,....). 226 12-Apr-11 07-Mar-12 12-Apr-11 A 07-Mar-12

PURCHAPURCHASING 129 12-Apr-11 17-Oct-11 12-Apr-11 A 17-Oct-11

A3880 Safety equipment and life saving Bidding 10 12-Apr-11 26-Apr-11 12-Apr-11 A 26-Apr-11 A

A3910 Service water pumps Bidding 15 25-Apr-11 17-May-11 25-Apr-11 A 10-May-11 A

A3900 Flame arrestor Bidding 15 27-Apr-11 19-May-11 17-Apr-11 A 19-May-11 A

A3890 Vent stack tips Bidding 20 09-May-11 06-Jun-11 09-May-11 A 01-Jun-11 A

B1060 Electro hydraulic wellhead control panel Issue PO 5 19-Jul-11 26-Jul-11 13-Jul-11 19-Jul-11

A1370 Bidding (Service pumps,Flame arrestor,Vent ,....). 25 02-May-11 06-Jun-11 25-Apr-11 A 21-Jul-11

A4900 Service water pumps Issue Fax of commitment 18 13-Jun-11 11-Jul-11 04-Jul-11 27-Jul-11

A4870 Safety equipment and life saving Issue Fax of commitment 20 12-Jun-11 10-Jul-11 10-Jul-11 04-Aug-11

B1080 Service water pumps Issue PO 5 18-Jul-11 25-Jul-11 04-Aug-11 10-Aug-11

A4620 Monorail crane Bidding 10 28-Jul-11 11-Aug-11 31-Jul-11 11-Aug-11

A4890 Flame arrestor Issue Fax of commitment 20 23-Jun-11 21-Jul-11 24-Jul-11 18-Aug-11

B1070 Safety equipment and life saving Issue PO 5 17-Jul-11 24-Jul-11 14-Aug-11 18-Aug-11

A1380 Issue Fax of commitments(Service pumps,Flame arrestor,Vent ,....). 25 29-Jun-11 03-Aug-11 20-Jul-11 23-Aug-11

A4880 Vent stack tips Issue Fax of commitment 20 06-Jul-11 03-Aug-11 27-Jul-11 23-Aug-11

B1090 Flame arrestor Issue PO 5 28-Jul-11 04-Aug-11 28-Aug-11 06-Sep-11

B1100 Issue POs (HCU.,Sea water pumps....). 25 13-Jul-11 17-Aug-11 03-Aug-11 11-Sep-11

B1110 Vent stack tips Issue PO 5 10-Aug-11 17-Aug-11 05-Sep-11 11-Sep-11

A5230 Monorail crane Issue Fax of commitment 20 06-Sep-11 04-Oct-11 07-Sep-11 04-Oct-11

B1120 Monorail crane Issue PO 5 10-Oct-11 17-Oct-11 11-Oct-11 17-Oct-11

FABRICAFABRICATION 189 10-Jul-11 01-Feb-12 28-Jul-11 01-Feb-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 13 of 64

Page 168: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A4630 Service water pump Fabrication up to release for shipment 140 11-Jul-11 28-Nov-11 28-Jul-11 14-Dec-11

A3950 Vent stack tips Fabrication up to release for shipment 120 08-Aug-11 06-Dec-11 29-Aug-11 26-Dec-11

A3960 Flame arrestorFabrication up to release for shipment 130 21-Jul-11 28-Nov-11 19-Aug-11 26-Dec-11

A1390 Fabrication up to release for shipment (Service pumps,Flame arre... 150 10-Jul-11 07-Dec-11 05-Aug-11 01-Jan-12

A3940 Safety equipment and life saving Fabrication up to release for ship... 150 10-Jul-11 07-Dec-11 05-Aug-11 01-Jan-12

A4660 Monorail crane Fabrication up to release for shipment 120 04-Oct-11 01-Feb-12 05-Oct-11 01-Feb-12

SHIPPINSHIPPING 88 15-Nov-11 07-Mar-12 11-Dec-11 07-Mar-12

A4670 Service water pump Shipping 21 28-Nov-11 19-Dec-11 15-Dec-11 04-Jan-12

A4010 Vent stack tips Shipping 21 06-Dec-11 27-Dec-11 27-Dec-11 16-Jan-12

A4020 Flame arrestor Shipping 21 28-Nov-11 19-Dec-11 27-Dec-11 16-Jan-12

A6030 Service water pump Custom clearance & inland transportation 14 21-Dec-11 04-Jan-12 07-Jan-12 20-Jan-12

A4000 Safety equipment and life saving Shipping 21 07-Dec-11 28-Dec-11 02-Jan-12 22-Jan-12

A1400 Shipping (Service pumps,Flame arrestor,Vent ,....). 50 15-Nov-11 04-Jan-12 11-Dec-11 29-Jan-12

A5510 Flame arrestor Custom clearance & inland transportation 14 19-Dec-11 02-Jan-12 17-Jan-12 30-Jan-12

A5520 Vent stack tips Custom clearance & inland transportation 14 27-Dec-11 10-Jan-12 17-Jan-12 30-Jan-12

A5500 Safety equipment and life saving Custom clearance & inland trans... 14 28-Dec-11 11-Jan-12 23-Jan-12 05-Feb-12

A1710 Custom clearance & inland transportation (Service pumps,Flame a... 35 14-Dec-11 18-Jan-12 09-Jan-12 12-Feb-12

A4700 Monorail crane Shipping 21 01-Feb-12 22-Feb-12 02-Feb-12 22-Feb-12

A6040 Monorail crane Custom clearance & inland transportation 14 22-Feb-12 07-Mar-12 23-Feb-12 07-Mar-12

PETROBEPETROBEL LONG LEAD ITEMS 318 19-Apr-11 26-Jan-12 29-Apr-11 A 01-Mar-12

FABRICAFABRICATION 307 19-Apr-11 15-Dec-11 29-Apr-11 A 15-Dec-11

A6150 Manual Valves Fabrication up to release for shipment 240 19-Apr-11 15-Dec-11 23-Jun-11 A 12-Dec-11

A2160 Fabrication up to release for shipment 240 19-Apr-11 15-Dec-11 25-May-11 A 15-Dec-11

A4040 Micro Turbine Fabrication up to release for shipment 240 19-Apr-11 15-Dec-11 26-May-11 A 15-Dec-11

A4050 Diesel generator Fabrication up to release for shipment 240 19-Apr-11 15-Dec-11 20-Jun-11 A 15-Dec-11

A4060 E&I Module Fabrication up to release for shipment 240 19-Apr-11 15-Dec-11 21-Jun-11 A 15-Dec-11

A4070 Production Manifold Fabrication up to release for shipment 240 19-Apr-11 15-Dec-11 26-May-11 A 15-Dec-11

A4080 Shutdown and blowdown valves Fabrication up to release for ship... 240 19-Apr-11 15-Dec-11 29-Apr-11 A 15-Dec-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 14 of 64

Page 169: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SHIPPINSHIPPING 77 15-Dec-11 26-Jan-12 16-Dec-11 01-Mar-12

A6050 Micro Turbine Custom clearance & inland transportation 14 12-Jan-12 26-Jan-12 16-Dec-11 29-Dec-11

A6060 Diesel generator Custom clearance & inland transportation 14 12-Jan-12 26-Jan-12 16-Dec-11 29-Dec-11

A4130 Shutdown and blowdown valves Shipping 21 15-Dec-11 12-Jan-12 16-Dec-11 05-Jan-12

A6160 Manual Valves Shipping 21 15-Dec-11 05-Jan-12 16-Dec-11 05-Jan-12

A4110 E&I Module Shipping 28 15-Dec-11 12-Jan-12 16-Dec-11 12-Jan-12

A4120 Production Manifold Shipping 28 15-Dec-11 12-Jan-12 16-Dec-11 12-Jan-12

A6090 Shutdown and blowdown valves & inland transportation 14 12-Jan-12 26-Jan-12 06-Jan-12 19-Jan-12

A6170 Manual Valves & inland transportation 14 05-Jan-12 19-Jan-12 06-Jan-12 19-Jan-12

A4090 Micro Turbine Shipping 28 15-Dec-11 12-Jan-12 30-Dec-11 26-Jan-12

A4100 Diesel generator Shipping 28 15-Dec-11 12-Jan-12 30-Dec-11 26-Jan-12

A6070 E&I Module Custom clearance & inland transportation 14 12-Jan-12 26-Jan-12 13-Jan-12 26-Jan-12

A6080 Production Manifold Custom clearance & inland transportation 14 12-Jan-12 26-Jan-12 13-Jan-12 26-Jan-12

A2170 Shipping 35 15-Dec-11 19-Jan-12 20-Jan-12 23-Feb-12

A2180 Custom clearance & inland transportation 25 01-Jan-12 26-Jan-12 06-Feb-12 01-Mar-12

E&I BULKE&I BULK 259 13-Apr-11 11-May-12 09-Apr-11 A 21-Apr-12

PURCHAPURCHASING 111 13-Apr-11 25-Aug-11 09-Apr-11 A 15-Sep-11

A5390 Electrical Cable trays Bidding 10 02-May-11 16-May-11 10-Apr-11 A 20-Apr-11 A

A4240 Electrical Cables Bidding 10 09-May-11 23-May-11 09-Apr-11 A 25-Apr-11 A

A4390 Choke valves Bidding 20 13-Apr-11 12-May-11 10-Apr-11 A 26-Apr-11 A

A4380 Wing valves Bidding 20 13-Apr-11 12-May-11 10-Apr-11 A 02-May-11 A

A4250 Navigation aids system Bidding 10 16-May-11 30-May-11 26-Apr-11 A 16-May-11 A

A5980 Instrument & Mechanical bulk material Bidding 10 05-Jun-11 19-Jun-11 03-May-11 A 26-May-11 A

A5070 Electrical Cable trays Issue Fax of commitments 15 19-Jun-11 10-Jul-11 02-May-11 A 30-May-11 A

A4400 Loose instrument Bidding 10 29-May-11 12-Jun-11 09-Jun-11 A 20-Jun-11 A

A5810 Junction boxes Bidding 10 09-Jun-11 23-Jun-11 07-Jun-11 A 20-Jun-11 A

A4420 Instrument Cable trays Bidding 10 31-May-11 14-Jun-11 23-Jun-11 A 26-Jun-11

A5080 Electrical Cables Issue Fax of commitments 6 22-Jun-11 13-Jul-11 26-Jun-11 03-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 15 of 64

Page 170: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A4410 Instrument cable and cable glands Bidding 10 23-May-11 06-Jun-11 26-Jun-11 07-Jul-11

A4260 Lighting material Bidding 10 25-May-11 08-Jun-11 22-Jun-11 A 07-Jul-11

A5900 Sand & Corrosion probes Bidding 10 02-Jun-11 16-Jun-11 27-Jun-11 A 07-Jul-11

A6260 Earthing material Bidding 10 06-Jun-11 20-Jun-11 21-Jun-11 A 07-Jul-11

C1040 Electrical Cables P.O 5 20-Jul-11 27-Jul-11 04-Jul-11 10-Jul-11

A1880 Bidding 35 09-May-11 27-Jun-11 20-Apr-11 A 11-Jul-11

C1020 Electrical Cable trays P.O 5 17-Jul-11 24-Jul-11 06-Jul-11 12-Jul-11

A5030 Wing valves Issue Fax of commitments 20 13-Jun-11 11-Jul-11 26-Jun-11 21-Jul-11

A5040 Choke valves Issue Fax of commitments 15 19-Jun-11 10-Jul-11 06-Jul-11 26-Jul-11

A5100 Navigation aids system Issue Fax of commitments 15 27-Jun-11 18-Jul-11 11-Jul-11 31-Jul-11

A5990 Instrument & Mechanical bulk material Issue Fax of commitments 15 03-Jul-11 24-Jul-11 17-Jul-11 04-Aug-11

C1000 Wing valves P.O 5 18-Jul-11 25-Jul-11 31-Jul-11 04-Aug-11

C1010 Choke valves P.O 5 17-Jul-11 24-Jul-11 03-Aug-11 09-Aug-11

A5060 Instrument cable and cable glands Issue Fax of commitments 15 20-Jun-11 11-Jul-11 24-Jul-11 11-Aug-11

A5830 Junction boxes Issue Fax of commitments 15 07-Jul-11 28-Jul-11 24-Jul-11 11-Aug-11

A5050 Loose instrument Issue Fax of commitments 15 26-Jun-11 17-Jul-11 25-Jul-11 14-Aug-11

A5090 Instrument Cable trays Issue Fax of commitments 10 30-Jun-11 14-Jul-11 02-Aug-11 15-Aug-11

C1060 Navigation aids system P.O 5 26-Jul-11 02-Aug-11 09-Aug-11 15-Aug-11

C1030 Instrument & Mechanical bulk material P.O 5 31-Jul-11 07-Aug-11 14-Aug-11 18-Aug-11

A5110 Lighting material Issue Fax of commitments 15 06-Jul-11 27-Jul-11 07-Aug-11 25-Aug-11

A5910 Sand & Corrosion probes Issue Fax of commitments 15 11-Jul-11 01-Aug-11 07-Aug-11 25-Aug-11

A6270 Earthing material Issue Fax of commitments 15 18-Jul-11 08-Aug-11 07-Aug-11 25-Aug-11

C1070 Instrument cable and cable glands P.O 5 18-Jul-11 25-Jul-11 21-Aug-11 25-Aug-11

C1050 Junction boxes P.O 5 04-Aug-11 11-Aug-11 21-Aug-11 25-Aug-11

A1890 E&I Bulk issue Fax of commitments 30 14-Jul-11 25-Aug-11 18-Jul-11 28-Aug-11

C1090 Loose instrument P.O 5 24-Jul-11 31-Jul-11 22-Aug-11 28-Aug-11

C1100 Instrument Cable trays P.O 5 21-Jul-11 28-Jul-11 23-Aug-11 29-Aug-11

C1080 Lighting material P.O 5 15-Aug-11 22-Aug-11 07-Sep-11 13-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 16 of 64

Page 171: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

C1110 Sand & Corrosion probes P.O 5 08-Aug-11 15-Aug-11 07-Sep-11 13-Sep-11

C1120 Earthing material P.O 5 17-Aug-11 24-Aug-11 11-Sep-11 15-Sep-11

FABRICAFABRICATION 267 10-Jul-11 06-Apr-12 25-Jun-11 17-Mar-12

A4530 Electrical Cable trays Fabrication up to release for shipment 100 10-Jul-11 18-Oct-11 25-Jun-11 02-Oct-11

A6000 Instrument & Mechanical bulk material Fabrication up to release fo... 90 24-Jul-11 01-Nov-11 05-Aug-11 02-Nov-11

A5820 Junction boxes Fabrication up to release for shipment 90 28-Jul-11 05-Nov-11 12-Aug-11 09-Nov-11

A4280 Instrument Cable trays Fabrication up to release for shipment 90 14-Jul-11 22-Oct-11 16-Aug-11 13-Nov-11

A4270 Electrical Cables Fabrication up to release for shipment 140 17-Jul-11 04-Dec-11 06-Jul-11 22-Nov-11

A4520 Instrument cable and cable glands Fabrication up to release for shi... 120 11-Jul-11 28-Nov-11 12-Aug-11 09-Dec-11

A4290 Navigation aids system Fabrication up to release for shipment 140 18-Jul-11 05-Dec-11 01-Aug-11 18-Dec-11

A4300 Lighting material Fabrication up to release for shipment 120 27-Jul-11 14-Dec-11 26-Aug-11 23-Dec-11

A6280 Earthing material Fabrication up to release for shipment 120 08-Aug-11 26-Dec-11 26-Aug-11 23-Dec-11

A5920 Sand & Corrosion probes Fabrication up to release for shipment 135 01-Aug-11 29-Dec-11 26-Aug-11 07-Jan-12

A4510 Loose instrument Fabrication up to release for shipment 155 17-Jul-11 13-Jan-12 15-Aug-11 16-Jan-12

A1900 E&I Bulk Fabrication up to release for shipment 180 20-Jul-11 16-Jan-12 22-Jul-11 17-Jan-12

A4500 Choke valves Fabrication up to release for shipment 210 10-Jul-11 05-Apr-12 27-Jul-11 21-Feb-12

A4490 Wing valves Fabrication up to release for shipment 240 11-Jul-11 06-Apr-12 22-Jul-11 17-Mar-12

SHIPPINGSHIPPING 136 18-Oct-11 11-May-12 03-Oct-11 21-Apr-12

A4320 Electrical Cable trays Shipping 21 18-Oct-11 08-Nov-11 03-Oct-11 23-Oct-11

A4580 Electrical Cable trays Custom clearance & inland transportation 14 08-Nov-11 22-Nov-11 24-Oct-11 06-Nov-11

A5750 Instrument Cable trays Shipping 7 22-Oct-11 29-Oct-11 14-Nov-11 20-Nov-11

A6010 Instrument & Mechanical bulk material Shipping 21 01-Nov-11 22-Nov-11 03-Nov-11 23-Nov-11

A1910 1st batch of the E&I Bulk Shipping 21 05-Nov-11 26-Nov-11 10-Nov-11 30-Nov-11

A5840 Junction boxes Shipping 21 05-Nov-11 26-Nov-11 10-Nov-11 30-Nov-11

A5760 Instrument Cable trays Custom clearance & inland transportation 14 29-Oct-11 12-Nov-11 21-Nov-11 04-Dec-11

A6020 Instrument & Mechanical bulk material Custom clearance & inland ... 14 22-Nov-11 06-Dec-11 24-Nov-11 07-Dec-11

A4310 Electrical Cables Shipping 21 04-Dec-11 25-Dec-11 23-Nov-11 13-Dec-11

A1920 1st batch of the E&I Bulk Custom clearance & inland transportation 14 26-Nov-11 10-Dec-11 01-Dec-11 14-Dec-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 17 of 64

Page 172: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A5850 Junction boxes Custom clearance & inland transportation 14 26-Nov-11 10-Dec-11 01-Dec-11 14-Dec-11

A5630 Electrical Cables Custom clearance & inland transportation 14 25-Dec-11 08-Jan-12 14-Dec-11 27-Dec-11

A4570 Instrument cable and cable glands Shipping 21 28-Nov-11 19-Dec-11 10-Dec-11 30-Dec-11

A4330 Navigation aids system Shipping 21 05-Dec-11 26-Dec-11 19-Dec-11 08-Jan-12

A4340 Lighting material Shipping 21 14-Dec-11 04-Jan-12 24-Dec-11 13-Jan-12

A5740 Instrument cable and cable glands Custom clearance & inland tran... 14 19-Dec-11 02-Jan-12 31-Dec-11 13-Jan-12

A5640 Navigation aids system Custom clearance & inland transportation 14 26-Dec-11 09-Jan-12 09-Jan-12 22-Jan-12

A6300 Earthing material Shipping 21 26-Dec-11 24-Jan-12 25-Dec-11 22-Jan-12

A5650 Lighting material Custom clearance & inland transportation 14 04-Jan-12 18-Jan-12 14-Jan-12 27-Jan-12

A5930 Sand & Corrosion probes Shipping 21 29-Dec-11 19-Jan-12 08-Jan-12 28-Jan-12

A4560 Loose instrument Shipping 21 13-Jan-12 10-Feb-12 17-Jan-12 06-Feb-12

A5940 Sand & Corrosion probes Custom clearance & inland transportation 14 19-Jan-12 02-Feb-12 29-Jan-12 11-Feb-12

A6290 Earthing material Custom clearance & inland transportation 14 24-Jan-12 14-Feb-12 23-Jan-12 12-Feb-12

A2020 2nd batch of the E&I Bulk Shipping 40 06-Jan-12 15-Feb-12 08-Jan-12 16-Feb-12

A5860 Loose instrument Custom clearance & inland transportation 14 10-Feb-12 24-Feb-12 07-Feb-12 20-Feb-12

A2030 2nd batch of the E&I Bulk Custom clearance & inland transportation 28 02-Feb-12 01-Mar-12 04-Feb-12 02-Mar-12

A6340 Choke valves Shipping 21 22-Feb-12 21-Mar-12

A4540 Wing valves Shipping 21 06-Apr-12 27-Apr-12 18-Mar-12 07-Apr-12

A4550 Choke valves Custom clearance & inland transportation 21 05-Apr-12 26-Apr-12 22-Mar-12 11-Apr-12

A5730 Wing valves Custom clearance & inland transportation 14 27-Apr-12 11-May-12 08-Apr-12 21-Apr-12

PIPING BUPIPING BULK 220 07-Apr-11 10-Feb-12 07-Apr-11 A 22-Feb-12

PURCHAPURCHASING 106 07-Apr-11 27-Jul-11 07-Apr-11 A 07-Sep-11

A4930 Piping Bulk Bidding 15 07-Apr-11 28-Apr-11 07-Apr-11 A 28-Apr-11 A

A5440 Insulation Joint Bidding 20 20-Apr-11 19-May-11 29-May-11 A 30-May-11 A

A1940 Piping Bulk Issue Fax of commitment 14 31-May-11 20-Jun-11 05-Jun-11 A 22-Jun-11 A

A5450 Injection fitting Bidding 20 24-Apr-11 23-May-11 24-Apr-11 A 26-Jun-11

C2000 Piping Bulk P.O 5 27-Jun-11 04-Jul-11 03-Jul-11 07-Jul-11

A5470 Insulation Joint Issue Fax of commitment 20 12-Jun-11 10-Jul-11 25-Jul-11 21-Aug-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 18 of 64

Page 173: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A5460 Injection fitting Issue Fax of commitment 20 15-Jun-11 13-Jul-11 25-Jul-11 21-Aug-11

C2010 Insulation Joint P.O 5 17-Jul-11 24-Jul-11 29-Aug-11 07-Sep-11

C2020 Injection fitting P.O 5 20-Jul-11 27-Jul-11 29-Aug-11 07-Sep-11

FABRICAFABRICATION 208 20-Jun-11 06-Jan-12 25-Jun-11 18-Jan-12

A1950 piping Bulk Fabrication up to release for shipment 200 20-Jun-11 06-Jan-12 25-Jun-11 10-Jan-12

A5570 Insulation Joint Fabrication up to release for shipment 150 10-Jul-11 07-Dec-11 22-Aug-11 18-Jan-12

A5580 Injection fitting Fabrication up to release for shipment 150 13-Jul-11 10-Dec-11 22-Aug-11 18-Jan-12

SHIPPINGSHIPPING 136 10-Oct-11 10-Feb-12 10-Oct-11 22-Feb-12

A1960 1st batch of the piping Bulk Shipping 21 10-Oct-11 31-Oct-11 10-Oct-11 30-Oct-11

A1970 1st batch of the piping Bulk Custom clearance & inland transport... 14 31-Oct-11 14-Nov-11 31-Oct-11 13-Nov-11

A2050 2nd batch of the piping Bulk Shipping 21 17-Nov-11 08-Dec-11 22-Nov-11 12-Dec-11

A2060 2nd batch of the piping Bulk Custom clearance & inland transport... 14 08-Dec-11 22-Dec-11 13-Dec-11 26-Dec-11

A2040 Last batch of the piping Bulk Shipping 21 06-Jan-12 27-Jan-12 11-Jan-12 31-Jan-12

A5590 Insulation Joint Shipping 21 07-Dec-11 28-Dec-11 19-Jan-12 08-Feb-12

A5620 Injection fitting Shipping 21 10-Dec-11 31-Dec-11 19-Jan-12 08-Feb-12

A2070 Last batch of the piping Bulk Custom clearance & inland transport... 14 27-Jan-12 10-Feb-12 01-Feb-12 14-Feb-12

A5600 Insulation Joint Custom clearance & inland transportation 14 28-Dec-11 11-Jan-12 09-Feb-12 22-Feb-12

A5610 Injection fitting Custom clearance & inland transportation 14 31-Dec-11 14-Jan-12 09-Feb-12 22-Feb-12

W.P.5: DECW.P.5: DECK & TSF FABRICATION 26 31-Mar-11 30-Apr-11 25-Jun-11 24-Jul-11

PTJ2200 Deck commisioning (Onshore) 26 31-Mar-11 30-Apr-11 25-Jun-11 24-Jul-11

W.P.9: OFFW.P.9: OFFSHORE HOOK-UP, COMMISSIONING AND ASSISTANCE TO STA... 30 02-Jun-12 02-Jul-12 01-Jun-12 30-Jun-12

A2370 Deck Offshore Commissioning 30 02-Jun-12 02-Jul-12 01-Jun-12 30-Jun-12

TECNOMARTECNOMARE 315 31-Mar-11 04-Jul-12 28-Mar-11 A 02-Jul-12

2 Start of project 0 31-Mar-11 31-Mar-11 A

TECNOMARTECNOMARE DRIVING MILESTONES 293 31-Mar-11 04-Jun-12 28-Mar-11 A 03-Jun-12

STRUCTUSTRUCTURAL 293 31-Mar-11 04-Jun-12 31-Mar-11 A 03-Jun-12

19 Soil Data (PTB) 0 31-Mar-11 31-Mar-11 A

16 input - deck plot plan & equipment list IFD (ENPPI) 0 24-Apr-11 24-Apr-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 19 of 64

Page 174: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

59 Input- T&I contract ITT (PTB) 0 26-Jun-11 26-Jun-11*

64 Pressure Vessels Vendor Print out review (ENPPI) 0 31-Mar-11 26-Jun-11

69 Piping bulk & Valves MRP's (ENPPI) 0 27-Jun-11 03-Jul-11

54 Process Commodities MRP's (ENPPI) 0 29-Aug-11 05-Sep-11

17 input - deck final plot plan & equipment list (ENPPI) 0 21-Sep-11 21-Sep-11

13 input - crane barge (PTB) 0 24-Sep-11 24-Sep-11*

14 input - launching barge for jacket (PTB) 0 24-Sep-11 24-Sep-11*

79 Mechanical Vendor print review (ENPPI) 0 25-Dec-11 15-Jan-12

300 As built Markup documents (PTJ) for Jacket 0 07-May-12 07-May-12*

9 Load out structures 0 10-May-12 09-May-12*

310 As built Markup documents (PTJ) for deck 0 04-Jun-12 03-Jun-12

INSTRUMEINSTRUMENTATION 160 31-Mar-11 23-Nov-11 28-Mar-11 A 22-Nov-11

276 Plot Plan IFD (ENPPI) 0 24-Apr-11 28-Mar-11 A

106 Review of Basic Documents (Consortium feed endorsement) 0 31-Mar-11 31-Mar-11 A

158 SSIV vendor documents (PTB) 0 31-Mar-11 31-Mar-11 A

107 P & ID's ( IFD ) (ENPPI/PTB for LLI) 0 17-Apr-11 27-Apr-11 A

148 fire and gas requirements- HSE philosophy Fire Fighting Safety La... 0 24-Apr-11 02-May-11 A

112 C & E - issue for Design (ENPPI/PTB for LLI) 0 16-May-11 08-May-11 A

206 junction box wiring diagram for control & safety system IFD (ENPPI) 0 09-Jun-11 08-May-11 A

302 T4 for Radio Bridge (PTB) 0 08-Jun-11 08-Jun-11 A

128 Electrical interface with PLC/RTU (I/O list) (ENPPI) 0 30-May-11 08-Jun-11 A

138 Control and safety cable routing IFD (ENPPI) 0 09-Jun-11 20-Jun-11 A

136 Instrument TDS (ENPPI) 0 07-Jun-11 26-Jun-11

208 P & ID's ( IFC) (ENPPI/PTB for LLI) 0 14-Sep-11 13-Sep-11

286 Plot Plan IFC (ENPPI) 0 21-Sep-11 20-Sep-11

117 C & E - Issue for Construction (ENPPI/PTB for LLI) 0 21-Sep-11 20-Sep-11

198 3D model Review 90% Report (ENPPI) 0 23-Nov-11 22-Nov-11

W.P.1: PROW.P.1: PROJECT MANAGEMENT 444 31-Mar-11 17-Jun-12 31-Mar-11 A 15-Jun-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 20 of 64

Page 175: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

18 technical coordination 444 31-Mar-11 17-Jun-12 31-Mar-11 A 15-Jun-12

43 engineering assistance to fab, load out & transportation home off ice 428 15-Apr-11 17-Jun-12 14-Apr-11 A 15-Jun-12

305 project services 444 31-Mar-11 17-Jun-12 31-Mar-11 A 15-Jun-12

W.P.2: ENGW.P.2: ENGINEERING 315 31-Mar-11 04-Jul-12 31-Mar-11 A 02-Jul-12

20 weight control 196 31-Mar-11 01-Feb-12 31-Mar-11 A 31-Jan-12

STRUCTUSTRUCTURAL 306 31-Mar-11 21-Jun-12 31-Mar-11 A 19-Jun-12

MILESTOMILESTONES 209 31-Mar-11 01-Feb-12 31-Mar-11 A 31-Jan-12

4 jacket main structure AFC dwg.s + MTO 0 31-Mar-11 31-Mar-11 A

6 deck AFC dwg.s + MTO main structure 0 04-Jul-11 12-Jul-11

5 jacket secondary structures AFC dwg.s + MTO 0 31-Jul-11 31-Jul-11*

7 deck AFC + MTO secondary structures (no equip. supports) 0 25-Sep-11 25-Sep-11

28 Weight Control Report 1st issue 0 25-Sep-11 25-Sep-11

8 deck AFC + MTO equip. supports 0 24-Oct-11 23-Oct-11

10 weight control report 2nd issue 0 24-Oct-11 23-Oct-11

11 weight control report 3rd issue 0 01-Feb-12 31-Jan-12

DECK DEDECK DETAIL DESIGN 127 24-Apr-11 24-Oct-11 21-Apr-11 A 23-Oct-11

31 deck in service final analysis 15 24-Apr-11 16-May-11 21-Apr-11 A 09-Jun-11 A

29 deck & helideck lifting final analysis 20 24-Apr-11 23-May-11 21-Apr-11 A 15-Jun-11 A

32 deck seismic analysis 15 16-May-11 06-Jun-11 15-May-11 A 16-Jun-11 A

30 deck & helideck load out & transportation structural analysis updat... 15 23-May-11 13-Jun-11 22-May-11 A 22-Jun-11 A

33 deck & helideck joints local checks 15 13-Jun-11 04-Jul-11 23-Jun-11 A 11-Jul-11

34 deck main structure AFC dwg.s & MTO 50 24-Apr-11 04-Jul-11 24-Apr-11 A 11-Jul-11*

35 deck secondary structures design (no equipment support) 50 04-Jul-11 25-Sep-11 20-Jun-11 A 18-Sep-11

36 deck secondary structure AFC dwg.s & MTO (no equipment support) 100 24-Apr-11 25-Sep-11 24-Apr-11 A 22-Sep-11

45 Deck equipment supports design 15 21-Sep-11 13-Oct-11 21-Sep-11 12-Oct-11

44 Deck equipment supports & AFC dwg and MTO 22 21-Sep-11 24-Oct-11 21-Sep-11 23-Oct-11

ASSISTANASSISTANCE TO COMPANY 178 25-Sep-11 21-Jun-12 25-Sep-11 19-Jun-12

38 liaison with Certifying Authority 105 25-Sep-11 06-Mar-12 25-Sep-11 06-Mar-12*

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 21 of 64

Page 176: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

39 liason with Marine Warranty Surveyor 105 23-Jan-12 21-Jun-12 22-Jan-12 19-Jun-12

FOLLOWFOLLOW-ON OF T&I CONTRACT 293 31-Mar-11 21-Jun-12 21-Apr-11 A 19-Jun-12

Analysis Analysis Finalization 101 25-Sep-11 01-Mar-12 25-Sep-11 29-Feb-12

26 jacket launching naval final analysis 20 25-Sep-11 20-Oct-11 25-Sep-11 20-Oct-11

24 jacket launching structural analysis updating 15 23-Oct-11 10-Nov-11 23-Oct-11 10-Nov-11

25 jacket docking naval f inal analysis 20 13-Nov-11 08-Dec-11 13-Nov-11 08-Dec-11

27 jacket free floating & upending naval analysis - final analysis 20 01-Feb-12 01-Mar-12 31-Jan-12 29-Feb-12

Follow-upFollow-up 293 31-Mar-11 21-Jun-12 21-Apr-11 A 19-Jun-12

49 ITT scope of work for T&I Contract 20 31-Mar-11 28-Apr-11 21-Apr-11 A 17-Jul-11

50 technical evaluation of the offers, clarification meetings & KOM 50 26-Jun-11 14-Sep-11 18-Jul-11 06-Oct-11

52 installation - transportation & installation procedures/manuals 39 17-Nov-11 29-Jan-12 16-Nov-11 25-Jan-12

51 post-award assistance 120 15-Sep-11 19-Mar-12 09-Oct-11 11-Apr-12

53 installation - engineering assistance during installation (at home of... 30 10-May-12 21-Jun-12 09-May-12 19-Jun-12

INSTRUMEINSTRUMENTATION 205 31-Mar-11 26-Jan-12 31-Mar-11 A 25-Jan-12

PLC/RTU PLC/RTU - Telecom System 205 31-Mar-11 26-Jan-12 31-Mar-11 A 25-Jan-12

CONTROCONTROL 205 31-Mar-11 26-Jan-12 31-Mar-11 A 25-Jan-12

108 Review of PLC/RTU -ICSS Spec's 20 31-Mar-11 28-Apr-11 31-Mar-11 A 28-Apr-11 A

336 Junction Box wiring Diagram for SSIV issue for Design 21 17-Apr-11 17-May-11 14-Apr-11 A 17-May-11 A

246 F&G system layout issue for Design 22 02-May-11 01-Jun-11 21-Apr-11 A 24-May-11 A

156 ESD System Layout- issue for design 22 02-May-11 01-Jun-11 21-Apr-11 A 25-May-11 A

111 Functional / logic diagrams - issue for design 35 26-Apr-11 15-Jun-11 26-Apr-11 A 20-Jun-11 A

346 Junction Box wiring diagram for Seth ESD Pushbuttons issue for d... 26 18-May-11 23-Jun-11 10-May-11 A 22-Jun-11 A

188 Operator console - issue for design 18 29-May-11 22-Jun-11 22-May-11 A 22-Jun-11 A

110 I / O Database - issue for design 17 23-May-11 15-Jun-11 10-May-11 A 26-Jun-11

113 Simplified loop diagrams - issue for design 16 24-May-11 15-Jun-11 25-May-11 A 26-Jun-11

133 ESD/F&G - cable list issue for design 20 01-Jun-11 29-Jun-11 25-May-11 A 26-Jun-11

168 F&G cable routing layout - issue for design 22 09-Jun-11 11-Jul-11 01-Jun-11 A 19-Jul-11

178 ESD Pushbuttons cable routing layout - issue for design 22 09-Jun-11 11-Jul-11 01-Jun-11 A 19-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 22 of 64

Page 177: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

116 Functional / Logic diagrams - issue for construction 19 14-Sep-11 11-Oct-11 13-Sep-11 10-Oct-11

356 Junction Box wiring Diagram for SSIV issue for Construction 18 14-Sep-11 11-Oct-11 14-Sep-11 10-Oct-11

266 F&G system layout issue for Construction 18 21-Sep-11 18-Oct-11 21-Sep-11 17-Oct-11

386 ESD System Layout- issue for construction 18 21-Sep-11 18-Oct-11 21-Sep-11 17-Oct-11

115 I / O database - issue for construction 20 27-Sep-11 25-Oct-11 26-Sep-11 24-Oct-11

118 Simplified loop diagrams - issue for construction 14 12-Oct-11 01-Nov-11 11-Oct-11 31-Oct-11

121 Operator Console Layout - issue for construction 18 25-Oct-11 20-Nov-11 24-Oct-11 17-Nov-11

396 Junction Box wiring diagram for Seth ESD Pushbuttons issue for c... 21 28-Nov-11 26-Dec-11 28-Nov-11 26-Dec-11

236 F&G cable routing layout- issue for construction 23 23-Nov-11 11-Jan-12 22-Nov-11 10-Jan-12

326 ESD Pushbuttons cable routing layout- issue for construction 29 23-Nov-11 19-Jan-12 22-Nov-11 18-Jan-12

131 ESD / F&G - cable list - issue for construction 18 02-Jan-12 26-Jan-12 02-Jan-12 25-Jan-12

TELECOTELECOM 105 10-Apr-11 18-Aug-11 10-Apr-11 A 15-Sep-11

256 Review of Telecom Specs 23 10-Apr-11 11-May-11 10-Apr-11 A 10-May-11 A

166 J. B Wiring Diagram for Telecom System for Seth 23 08-May-11 07-Jun-11 10-May-11 A 20-May-11 A

126 Telecom System Layout for Seth 23 28-Apr-11 31-May-11 24-Apr-11 A 24-May-11 A

296 Telecommunication Cables List 20 31-May-11 28-Jun-11 19-May-11 A 21-Jun-11 A

226 Telecom cable routing layout 22 12-Jun-11 12-Jul-11 21-Jun-11 A 19-Jul-11

366 TDS for electrical bulk material/ Telecom Bulks 25 07-Jun-11 12-Jul-11 05-Jul-11 22-Aug-11

196 Electrical Bulk Material Requisition for Telecom Sys. Seth 23 03-Jul-11 16-Aug-11 31-Jul-11 13-Sep-11

306 SOW of Modification on El Gamil Plant 24 04-Jul-11 18-Aug-11 14-Aug-11 15-Sep-11

RADIO LIRADIO LINK ON T4 35 08-Jun-11 28-Jul-11 15-May-11 A 15-Aug-11

186 J. B Wiring Diagram for Telecom System for Temsah - 4 23 08-Jun-11 10-Jul-11 15-May-11 A 20-Jul-11

176 Telecom System Layout for Temsah - 4 23 08-Jun-11 10-Jul-11 26-Jun-11 26-Jul-11

297 SOW of Modification of Bridge Platform 24 27-Jun-11 28-Jul-11 20-Jun-11 A 15-Aug-11

TECHNICTECHNICAL FOLLOW-UP 114 31-May-11 13-Dec-11 26-Jun-11 13-Dec-11

122 Vendor Print Review 114 31-May-11 13-Dec-11 26-Jun-11 13-Dec-11

AS-BUILT AS-BUILT DRAWINGS 41 07-May-12 04-Jul-12 07-May-12 02-Jul-12

46 template, piles, jacket 22 07-May-12 05-Jun-12 07-May-12 05-Jun-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 23 of 64

Page 178: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

47 deck, helideck & flare 30 04-Jun-12 04-Jul-12 03-Jun-12 02-Jul-12

SUBSEA SSUBSEA SYSTEM 119 31-Mar-11 28-Sep-11 31-Mar-11 A 27-Sep-11

103 Vendor Print Review 119 31-Mar-11 28-Sep-11 31-Mar-11 A 27-Sep-11

W.P.3: PROW.P.3: PROCUREMENT SERVICES & MATERIAL SUPPLY 269 31-Mar-11 29-Apr-12 31-Mar-11 A 26-Apr-12

PLC/RTUPLC/RTU 261 13-Apr-11 29-Apr-12 13-Apr-11 A 26-Apr-12

142 Technical Evaluation for PLC/RTU 15 13-Apr-11 04-May-11 13-Apr-11 A 03-May-11 A

143 Revised commercial submission by supplier 5 05-May-11 11-May-11 05-May-11 A 11-May-11 A

144 Commercial Evaluation 5 12-May-11 18-May-11 12-May-11 A 18-May-11 A

145 PO issuance for PLC/RTU 9 19-May-11 31-May-11 19-May-11 A 31-May-11 A

195 Submital of C&E IFD , Instrument commodities vendor print review... 0 04-Sep-11 14-Aug-11

185 Submital of I/O list IFD, TDS, JB wiring diag to th PLC/RTU Vendor 0 04-Sep-11 18-Aug-11

376 FAT Test 11 20-Dec-11 22-Jan-12 09-Jan-12 23-Jan-12

146 Expediting & Inspection for PLC/RTU 133 20-Jun-11 22-Jan-12 15-Jun-11 A 23-Jan-12

216 Delivery to Construction Yard 28 23-Jan-12 23-Feb-12 24-Jan-12 25-Feb-12

137 Onshore Precommissioning / Commissioning Assistance 42 11-Mar-12 29-Apr-12 10-Mar-12 26-Apr-12

TELECOMTELECOM BULK MATERIALS 116 13-Jul-11 11-Jan-12 31-Jul-11 19-Jan-12

189 RFQ Issuance for Telecom materials 7 13-Jul-11 24-Jul-11 31-Jul-11 09-Aug-11

190 Bidding for Telecom materials 10 24-Jul-11 07-Aug-11 09-Aug-11 23-Aug-11

241 Technical Evaluation for Telecom materials 7 07-Aug-11 16-Aug-11 23-Aug-11 01-Sep-11

202 Revised commercial submission by supplier 7 16-Aug-11 25-Aug-11 01-Sep-11 12-Sep-11

213 Commercial Evaluation 5 25-Aug-11 01-Sep-11 12-Sep-11 19-Sep-11

214 PO issuance for Telecom materials 3 01-Sep-11 06-Sep-11 19-Sep-11 22-Sep-11

235 Expediting & Inspection for Telecom materials 56 06-Sep-11 23-Nov-11 22-Sep-11 11-Dec-11

265 Transportation to site 28 23-Nov-11 10-Jan-12 11-Dec-11 18-Jan-12

275 Delivery to yard 0 11-Jan-12 19-Jan-12

GROUT SEGROUT SEALS 119 31-Mar-11 28-Sep-11 31-Mar-11 A 28-Sep-11

150 Bidding for G S 5 31-Mar-11 07-Apr-11 31-Mar-11 A 07-Apr-11 A

151 Technical Evaluation for G S 5 10-Apr-11 14-Apr-11 10-Apr-11 A 14-Apr-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 24 of 64

Page 179: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

152 Revised commercial submission by supplier 5 17-Apr-11 21-Apr-11 17-Apr-11 A 21-Apr-11 A

153 Commercial Evaluation 5 24-Apr-11 28-Apr-11 24-Apr-11 A 28-Apr-11 A

154 PO issuance for G S 11 02-May-11 16-May-11 02-May-11 A 16-May-11 A

155 Expediting & Inspection for G S 68 17-May-11 31-Aug-11 25-May-11 A 31-Aug-11

165 Transportation to site 20 01-Sep-11 28-Sep-11 01-Sep-11 28-Sep-11

175 Delivery to yard 0 28-Sep-11 28-Sep-11

SHOCK CESHOCK CELLS 117 31-Mar-11 28-Sep-11 31-Mar-11 A 26-Sep-11

179 RFQ Issuance for Shock Cells 5 31-Mar-11 07-Apr-11 31-Mar-11 A 07-Apr-11 A

180 Bidding for Shock Cells 15 10-Apr-11 28-Apr-11 10-Apr-11 A 28-Apr-11 A

191 Technical Evaluation for Shock Cells 7 02-May-11 10-May-11 02-May-11 A 10-May-11 A

192 Revised commercial submission by supplier 5 11-May-11 17-May-11 11-May-11 A 17-May-11 A

203 Commercial Evaluation 7 18-May-11 26-May-11 18-May-11 A 26-May-11 A

204 PO issuance for Shock Cells 3 29-May-11 31-May-11 25-May-11 A 29-May-11 A

225 Expediting & Inspection for Shock Cells 57 01-Jun-11 31-Aug-11 30-May-11 A 29-Aug-11

245 Transportation to site 20 01-Sep-11 28-Sep-11 30-Aug-11 26-Sep-11

255 Delivery to yard 0 28-Sep-11 26-Sep-11

W.P.9: OFFW.P.9: OFFSHORE HOOK-UP, COMMISSIONING AND ASSISTANCE TO STA... 50 19-Apr-12 17-Jun-12 19-Apr-12 17-Jun-12

ONSHOREONSHORE FACILITIES 50 19-Apr-12 17-Jun-12 19-Apr-12 17-Jun-12

A1650 Installation Telephone System Uopgrading in El Gamil Plant 30 19-Apr-12 24-May-12 19-Apr-12* 24-May-12

A1640 Installation of Radio Link Upgrading in El gamil Plant 30 19-Apr-12 24-May-12 19-Apr-12 24-May-12

A1620 Installation of DCS Node Upgrading in El gamil Plant 30 19-Apr-12 24-May-12 19-Apr-12 24-May-12

A1630 Installation of CCTV Upgrading in El gamil Plant 30 19-Apr-12 24-May-12 19-Apr-12 24-May-12

A1040 Connecting cables (Including Emergency, control and F&G signals) 30 13-May-12 17-Jun-12 13-May-12 17-Jun-12

PETROJETPETROJET 335 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

PETROJETPETROJET DRIVING MILESTONES 340 31-Mar-11 01-Mar-12 31-Mar-11 A 02-Mar-12

PROCUREPROCUREMENT 339 31-Mar-11 01-Mar-12 31-Mar-11 A 02-Mar-12

PTJ1000 Structural material 1st & 2 nd batch (jacket primary, pile & deck leg... 0 31-Mar-11 31-Mar-11 A

PTJ1015 Structural material 3 rd batch (PDT) (PTB) 0 28-Apr-11 28-Apr-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 25 of 64

Page 180: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ1010 Structural material 4 rd batch, deck primary (main beams, legs, no... 0 21-May-11 30-Apr-11 A

PTJ1020 Structural material 5 th batch (jacket secondary & deck secondary)... 0 31-Aug-11 31-Aug-11*

PTJ1080 Piping bulk material (1st batch) (ENPPI) 0 14-Nov-11 14-Nov-11

PTJ1110 E & I 1st batch) (ENPPI) 0 10-Dec-11 15-Dec-11

PTJ1100 Start receiving equipment (ENPPI) 0 17-Dec-11 12-Jan-12

PTJ1120 Equipment (100%) (PTB) 0 24-Jan-12 24-Jan-12*

PTJ4010 Equipment by (100%) (ENPPI) 0 12-Feb-12 11-Feb-12

PTJ4000 Piping bulk material (Last batch) (ENPPI) 0 10-Feb-12 14-Feb-12

PTJ4020 E & I (Last batch) (ENPPI) 0 01-Mar-12 02-Mar-12

DESIGNDESIGN 234 31-Mar-11 20-Nov-11 31-Mar-11 A 18-Nov-11

PTJ150 Pre-drilling template AFC dwg's (by techno) 0 31-Mar-11 31-Mar-11 A

PTJ100 Jacket main structure AFC dwg's (by techno) 0 31-Mar-11 31-Mar-11 A

PTJ110 Deck main structure AFC dwg's (by techno) 0 04-Jul-11 15-Apr-11 A

PTJ140 Jacket secondary structure AFC dwg's (by techno) 0 31-Jul-11 31-Jul-11

PTJ130 E & I AFC dwg's (by ENPPI) 0 16-Nov-11 16-Nov-11

PTJ120 Piping AFC dwg's (by ENPPI) 0 20-Nov-11 18-Nov-11

W.P.1: PROW.P.1: PROJECT MANAGEMENT 490 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

PTJ000 Project managment 490 31-Mar-11 31-Jul-12 31-Mar-11 A 31-Jul-12

W.P.2: ENGW.P.2: ENGINEERING 222 15-Sep-11 04-Jun-12 15-Sep-11 02-Jun-12

JACKETJACKET 15 01-Apr-12 17-Apr-12 01-Apr-12 17-Apr-12

PTJ2170 Jacket main structure mark up drawing drawing 15 01-Apr-12 17-Apr-12 01-Apr-12 17-Apr-12

TSFTSF 222 15-Sep-11 04-Jun-12 15-Sep-11 02-Jun-12

PTJ2240 Rec final weight & dimension for static equipment 0 15-Sep-11 15-Sep-11*

PTJ2190 TSF mark up drawing 21 10-May-12 04-Jun-12 09-May-12 02-Jun-12

DECKDECK 16 10-May-12 29-May-12 09-May-12 27-May-12

PTJ2180 Deck structure mark up drawing 16 10-May-12 29-May-12 09-May-12 27-May-12

W.P.4: SUBW.P.4: SUBSTRUCTURES (PILES, JACKET & PDT) FABRICATION 240 31-Mar-11 15-Mar-12 31-Mar-11 A 15-Mar-12

JACKET SJACKET STRUCTURE FABRICATION 240 31-Mar-11 15-Mar-12 31-Mar-11 A 15-Mar-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 26 of 64

Page 181: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

MAIN STRMAIN STRUCTURE FABRICATION 259 31-Mar-11 23-Feb-12 31-Mar-11 A 29-Jan-12

GeneralGeneral 259 31-Mar-11 23-Feb-12 31-Mar-11 A 29-Jan-12

PTJ2000 Jacket main structure fabrication start 0 31-Mar-11 31-Mar-11 A

PTJ2210 Jacket main structure fabrication finish 0 15-Feb-12 21-Jan-12

PTJ2230 Jacket weighing 2 22-Feb-12 23-Feb-12 28-Jan-12 29-Jan-12

JACKET JACKET LEGS FABRICATION 75 31-Mar-11 22-Jun-11 31-Mar-11 A 29-Jun-11

PTJ5010 PREPARATION LEG FOR ROW A & B TRIAL FIT 8 14-Jun-11 22-Jun-11 15-May-11 A 08-Jun-11 A

PTJ5000 PREPARATION OF SKID WAY 20 31-Mar-11 24-Apr-11 31-Mar-11 A 26-Jun-11

LEG A1LEG A1 67 31-Mar-11 13-Jun-11 31-Mar-11 A 29-Jun-11

DIM 14DIM 1400 45 31-Mar-11 18-May-11 31-Mar-11 A 29-Jun-11

PTJ51 LEG SPLICE FIT UP 9 31-Mar-11 10-Apr-11 31-Mar-11 A 25-Jun-11

PTJ51 CANS FIT UP 8 11-Apr-11 20-Apr-11 11-Apr-11 A 27-Jun-11

PTJ51 LEG SPLICE WELDING & NDT 10 21-Apr-11 04-May-11 23-Apr-11 A 27-Jun-11

PTJ51 CAN WELDING & NDT 12 05-May-11 18-May-11 09-May-11 A 29-Jun-11

DIM 12DIM 1200 41 21-Apr-11 05-Jun-11 23-Apr-11 A 04-Jun-11 A

PTJ50 LEG SPLICE FIT UP 7 21-Apr-11 01-May-11 23-Apr-11 A 31-May-11 A

PTJ51 CANS FIT UP 4 02-May-11 05-May-11 05-May-11 A 31-May-11 A

PTJ51 CONE FIT UP 4 07-May-11 10-May-11 10-May-11 A 01-Jun-11 A

PTJ51 LEG SPLICE WELDING & NDT 12 11-May-11 24-May-11 15-May-11 A 02-Jun-11 A

PTJ51 CONE WELDING & NDT 5 25-May-11 30-May-11 22-May-11 A 02-Jun-11 A

PTJ51 CAN WELDING & NDT 5 31-May-11 05-Jun-11 19-May-11 A 04-Jun-11 A

DIM 10DIM 1000 36 11-May-11 13-Jun-11 15-Apr-11 A 29-Jun-11

PTJ50 CONE WELDING & NDT 5 02-Jun-11 07-Jun-11 07-May-11 A 11-May-11 A

PTJ50 LEG SPLICE WELDING & NDT 6 26-May-11 01-Jun-11 30-Apr-11 A 12-May-11 A

PTJ50 CONE FIT UP 4 22-May-11 25-May-11 18-May-11 A 24-May-11 A

PTJ50 LEG SPLICE FIT UP 5 11-May-11 16-May-11 15-Apr-11 A 02-Jun-11 A

PTJ50 CANS FIT UP 4 17-May-11 21-May-11 21-May-11 A 28-Jun-11

PTJ50 CAN WELDING & NDT 5 08-Jun-11 13-Jun-11 12-May-11 A 29-Jun-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 27 of 64

Page 182: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

LEG A2LEG A2 67 31-Mar-11 13-Jun-11 31-Mar-11 A 28-Jun-11

DIM 14DIM 1400 45 31-Mar-11 18-May-11 31-Mar-11 A 01-Jun-11 A

PTJ53 LEG SPLICE FIT UP 9 31-Mar-11 10-Apr-11 31-Mar-11 A 26-May-11 A

PTJ53 CANS FIT UP 8 11-Apr-11 20-Apr-11 11-Apr-11 A 28-May-11 A

PTJ53 LEG SPLICE WELDING & NDT 10 21-Apr-11 04-May-11 23-Apr-11 A 30-May-11 A

PTJ53 CAN WELDING & NDT 12 05-May-11 18-May-11 09-May-11 A 01-Jun-11 A

DIM 12DIM 1200 48 21-Apr-11 13-Jun-11 23-Apr-11 A 19-Jun-11 A

PTJ52 LEG SPLICE FIT UP 7 21-Apr-11 01-May-11 23-Apr-11 A 30-May-11 A

PTJ53 CANS FIT UP 4 02-May-11 05-May-11 05-May-11 A 30-May-11 A

PTJ52 CONE FIT UP 8 07-May-11 15-May-11 10-May-11 A 31-May-11 A

PTJ53 LEG SPLICE WELDING & NDT 13 16-May-11 30-May-11 19-May-11 A 02-Jun-11 A

PTJ53 CAN WELDING & NDT 6 07-Jun-11 13-Jun-11 14-May-11 A 05-Jun-11 A

PTJ53 CONE WELDING & NDT 6 31-May-11 06-Jun-11 19-Jun-11 A 19-Jun-11 A

DIM 10DIM 1000 28 07-May-11 07-Jun-11 17-Apr-11 A 28-Jun-11

PTJ52 CONE FIT UP 4 17-May-11 21-May-11 07-May-11 A 02-Jun-11 A

PTJ52 LEG SPLICE WELDING & NDT 6 22-May-11 28-May-11 15-May-11 A 02-Jun-11 A

PTJ52 CONE WELDING & NDT 4 29-May-11 01-Jun-11 17-Apr-11 A 04-Jun-11 A

PTJ52 LEG SPLICE FIT UP 5 07-May-11 11-May-11 10-May-11 A 25-Jun-11

PTJ52 CANS FIT UP 4 12-May-11 16-May-11 16-May-11 A 26-Jun-11

PTJ52 CAN WELDING & NDT 5 02-Jun-11 07-Jun-11 06-May-11 A 28-Jun-11

LEG B1LEG B1 67 31-Mar-11 13-Jun-11 31-Mar-11 A 29-Jun-11

DIM 14DIM 1400 45 31-Mar-11 18-May-11 31-Mar-11 A 29-Jun-11

PTJ55 LEG SPLICE FIT UP 9 31-Mar-11 10-Apr-11 31-Mar-11 A 25-Jun-11

PTJ55 CANS FIT UP 8 11-Apr-11 20-Apr-11 11-Apr-11 A 27-Jun-11

PTJ55 LEG SPLICE WELDING & NDT 10 21-Apr-11 04-May-11 23-Apr-11 A 27-Jun-11

PTJ55 CAN WELDING & NDT 12 05-May-11 18-May-11 09-May-11 A 29-Jun-11

DIM 12DIM 1200 43 21-Apr-11 07-Jun-11 23-Apr-11 A 04-Jun-11 A

PTJ54 LEG SPLICE FIT UP 7 21-Apr-11 01-May-11 23-Apr-11 A 29-May-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 28 of 64

Page 183: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ54 CANS FIT UP 4 02-May-11 05-May-11 05-May-11 A 30-May-11 A

PTJ54 CONE FIT UP 4 07-May-11 10-May-11 10-May-11 A 30-May-11 A

PTJ55 LEG SPLICE WELDING & NDT 12 11-May-11 24-May-11 15-May-11 A 01-Jun-11 A

PTJ55 CONE WELDING & NDT 6 25-May-11 31-May-11 14-May-11 A 02-Jun-11 A

PTJ55 CAN WELDING & NDT 6 01-Jun-11 07-Jun-11 20-May-11 A 04-Jun-11 A

DIM 10DIM 1000 29 11-May-11 13-Jun-11 14-May-11 A 29-Jun-11

PTJ54 LEG SPLICE FIT UP 5 11-May-11 16-May-11 15-May-11 A 31-May-11 A

PTJ54 CONE FIT UP 4 22-May-11 25-May-11 16-May-11 A 02-Jun-11 A

PTJ54 LEG SPLICE WELDING & NDT 6 26-May-11 01-Jun-11 19-May-11 A 02-Jun-11 A

PTJ54 CONE WELDING & NDT 5 02-Jun-11 07-Jun-11 14-May-11 A 04-Jun-11 A

PTJ54 CANS FIT UP 4 17-May-11 21-May-11 21-May-11 A 28-Jun-11

PTJ54 CAN WELDING & NDT 5 08-Jun-11 13-Jun-11 18-May-11 A 29-Jun-11

LEG B2LEG B2 65 31-Mar-11 11-Jun-11 31-Mar-11 A 27-Jun-11

DIM 14DIM 1400 43 31-Mar-11 16-May-11 31-Mar-11 A 31-May-11 A

PTJ57 LEG SPLICE FIT UP 8 31-Mar-11 09-Apr-11 31-Mar-11 A 26-May-11 A

PTJ57 CANS FIT UP 7 10-Apr-11 18-Apr-11 10-Apr-11 A 28-May-11 A

PTJ57 LEG SPLICE WELDING & NDT 10 19-Apr-11 02-May-11 20-Apr-11 A 30-May-11 A

PTJ57 CAN WELDING & NDT 12 03-May-11 16-May-11 07-May-11 A 31-May-11 A

DIM 12DIM 1200 43 19-Apr-11 05-Jun-11 20-Apr-11 A 18-Jun-11 A

PTJ56 LEG SPLICE FIT UP 8 19-Apr-11 28-Apr-11 20-Apr-11 A 29-May-11 A

PTJ56 CANS FIT UP 4 30-Apr-11 03-May-11 03-May-11 A 30-May-11 A

PTJ56 CONE FIT UP 4 04-May-11 08-May-11 08-May-11 A 30-May-11 A

PTJ56 LEG SPLICE WELDING & NDT 12 09-May-11 22-May-11 12-May-11 A 01-Jun-11 A

PTJ57 CONE WELDING & NDT 6 23-May-11 29-May-11 21-May-11 A 02-Jun-11 A

PTJ57 CAN WELDING & NDT 6 30-May-11 05-Jun-11 18-Jun-11 A 18-Jun-11 A

DIM 10DIM 1000 29 09-May-11 11-Jun-11 12-May-11 A 27-Jun-11

PTJ55 LEG SPLICE FIT UP 5 09-May-11 14-May-11 12-May-11 A 31-May-11 A

PTJ56 CONE FIT UP 4 19-May-11 23-May-11 19-May-11 A 02-Jun-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 29 of 64

Page 184: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ56 LEG SPLICE WELDING & NDT 6 24-May-11 30-May-11 21-May-11 A 04-Jun-11 A

PTJ56 CONE WELDING & NDT 5 31-May-11 05-Jun-11 18-Jun-11 A 18-Jun-11 A

PTJ56 CANS FIT UP 4 15-May-11 18-May-11 18-May-11 A 25-Jun-11

PTJ56 CAN WELDING & NDT 5 06-Jun-11 11-Jun-11 21-May-11 A 27-Jun-11

JACKET JACKET BRACING FABRICATION 161 31-Mar-11 28-Sep-11 31-Mar-11 A 16-Jul-11

BRACINBRACING ROW 1 50 03-Aug-11 28-Sep-11 11-Apr-11 A 14-Jul-11

SPLICSPLICING 50 03-Aug-11 28-Sep-11 11-Apr-11 A 14-Jul-11

HORIHORIZONTAL 45 03-Aug-11 22-Sep-11 11-Apr-11 A 18-Jun-11 A

PTJ3 FITUP HORIZONTAL BRACES ATELEV -56.2 9 03-Aug-11 13-Aug-11 08-May-11 A 26-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -79.0 9 14-Aug-11 23-Aug-11 18-May-11 A 30-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -33.4 9 14-Aug-11 23-Aug-11 18-May-11 A 03-Jun-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES ATN ELEV -56.2 10 14-Aug-11 27-Aug-11 18-May-11 A 03-Jun-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -79.0 10 24-Aug-11 07-Sep-11 21-May-11 A 07-Jun-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -10.6 6 24-Aug-11 03-Sep-11 29-Apr-11 A 10-Jun-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV +6.4 7 04-Sep-11 11-Sep-11 11-Apr-11 A 13-Jun-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -33.4 10 24-Aug-11 07-Sep-11 21-May-11 A 13-Jun-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -10.6 10 04-Sep-11 14-Sep-11 11-May-11 A 14-Jun-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4 10 12-Sep-11 22-Sep-11 19-May-11 A 18-Jun-11 A

DIAGDIAGONAL BRACES 41 14-Aug-11 28-Sep-11 18-Apr-11 A 14-Jul-11

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2 18 14-Aug-11 06-Sep-11 18-May-11 A 09-Jun-11 A

PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV -33.4 ... 14 07-Sep-11 22-Sep-11 14-May-11 A 20-Jun-11 A

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 13 04-Sep-11 18-Sep-11 11-May-11 A 07-Jul-11

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 14 24-Aug-11 12-Sep-11 14-May-11 A 09-Jul-11

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0 20 14-Aug-11 08-Sep-11 18-Apr-11 A 10-Jul-11

PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV +6.4 &... 9 19-Sep-11 28-Sep-11 15-May-11 A 11-Jul-11

PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV -10.6 ... 11 13-Sep-11 25-Sep-11 20-May-11 A 11-Jul-11

PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV -56.2 ... 15 10-Sep-11 26-Sep-11 17-May-11 A 14-Jul-11

BRACINBRACING ROW 2 78 31-Mar-11 26-Jun-11 31-Mar-11 A 02-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 30 of 64

Page 185: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SPLICSPLICING 78 31-Mar-11 26-Jun-11 31-Mar-11 A 02-Jul-11

HORIHORIZONTAL 15 31-Mar-11 18-Apr-11 31-Mar-11 A 28-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV +6.4 5 31-Mar-11 05-Apr-11 31-Mar-11 A 25-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -10.6 5 31-Mar-11 05-Apr-11 31-Mar-11 A 25-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -33.4 7 31-Mar-11 07-Apr-11 31-Mar-11 A 26-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -56.2 7 31-Mar-11 07-Apr-11 31-Mar-11 A 26-May-11 A

PTJ3 FITUP HORIZONTAL BRACES AT ELEV -79.0 7 31-Mar-11 07-Apr-11 31-Mar-11 A 26-May-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4 7 06-Apr-11 13-Apr-11 06-Apr-11 A 26-May-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -10.6 7 06-Apr-11 13-Apr-11 06-Apr-11 A 26-May-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -33.4 8 09-Apr-11 18-Apr-11 09-Apr-11 A 28-May-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -56.2 8 09-Apr-11 18-Apr-11 09-Apr-11 A 28-May-11 A

PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -79.0 8 09-Apr-11 18-Apr-11 09-Apr-11 A 28-May-11 A

DIAGDIAGONAL BRACES 56 06-Apr-11 06-Jun-11 06-Apr-11 A 25-Jun-11

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 8 06-Apr-11 14-Apr-11 06-Apr-11 A 31-May-11 A

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 8 09-Apr-11 18-Apr-11 09-Apr-11 A 31-May-11 A

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2 11 09-Apr-11 21-Apr-11 09-Apr-11 A 02-Jun-11 A

PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0 11 09-Apr-11 21-Apr-11 09-Apr-11 A 02-Jun-11 A

PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 7 16-Apr-11 24-Apr-11 16-Apr-11 A 05-Jun-11 A

PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 10 19-Apr-11 02-May-11 20-Apr-11 A 08-Jun-11 A

PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2 14 03-May-11 18-May-11 07-May-11 A 18-Jun-11 A

PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0 16 19-May-11 06-Jun-11 23-May-11 A 25-Jun-11

VERTVERTICAL 47 03-May-11 26-Jun-11 07-May-11 A 02-Jul-11

PTJ3 FITUP VERTICAL BRACES BETWEEN ELEV -10.6 & -33.4 5 03-May-11 08-May-11 07-May-11 A 26-Jun-11

PTJ3 FITUP VERTICAL BRACES BETWEEN ELEV -33.4 & -56.2 7 19-May-11 26-May-11 23-May-11 A 26-Jun-11

PTJ3 FITUP VERTICAL BRACES BETWEEN ELEV -56.2 & -79.0 7 07-Jun-11 14-Jun-11 11-Jun-11 A 26-Jun-11

PTJ8 WELDING VERTICAL BRACES BETWEEN ELEV -10.6 & -33.4 7 09-May-11 16-May-11 12-May-11 A 29-Jun-11

PTJ8 WELDING VERTICAL BRACES BETWEEN ELEV -33.4 & -56.2 10 28-May-11 07-Jun-11 31-May-11 A 02-Jul-11

PTJ8 WELDING VERTICAL BRACES BETWEEN ELEV -56.2 & -79.0 10 15-Jun-11 26-Jun-11 19-May-11 A 02-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 31 of 64

Page 186: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

BRACINBRACING ROW 3 17 17-May-11 05-Jun-11 21-May-11 A 29-Jun-11

PTJ812 FITUP BRACES BETWEEN ELEV -10.6 & -33.4 7 17-May-11 24-May-11 21-May-11 A 26-Jun-11

PTJ813 FITUP BRACES BETWEEN ELEV -33.4 & -56.2 7 17-May-11 24-May-11 21-May-11 A 26-Jun-11

PTJ814 FITUP BRACES BETWEEN ELEV -56.2 & -79.0 7 17-May-11 24-May-11 21-May-11 A 26-Jun-11

PTJ815 WELDING VERTICAL BRACES BETWEEN ELEV +10.6 & -33.4 10 25-May-11 05-Jun-11 21-May-11 A 29-Jun-11

PTJ816 WELDING VERTICAL BRACES BETWEEN ELEV -33.4 & -56.2 10 25-May-11 05-Jun-11 22-May-11 A 29-Jun-11

PTJ817 WELDING VERTICAL BRACES BETWEEN ELEV -56.2 & -79.0 10 25-May-11 05-Jun-11 22-May-11 A 29-Jun-11

BRACINBRACING ROW A 51 23-Jun-11 20-Aug-11 27-Apr-11 A 13-Jul-11

FABRIFABRICATION 51 23-Jun-11 20-Aug-11 27-Apr-11 A 13-Jul-11

PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 6 23-Jun-11 29-Jun-11 27-Apr-11 A 30-Jun-11

PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 8 30-Jun-11 09-Jul-11 04-May-11 A 30-Jun-11

PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 9 30-Jun-11 10-Jul-11 04-May-11 A 02-Jul-11

PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2 9 10-Jul-11 20-Jul-11 13-May-11 A 02-Jul-11

PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 10 10-Jul-11 21-Jul-11 13-May-11 A 03-Jul-11

PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0 11 21-Jul-11 02-Aug-11 15-May-11 A 04-Jul-11

PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2 14 21-Jul-11 06-Aug-11 14-May-11 A 07-Jul-11

PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV - 56.2 & -79.0 15 03-Aug-11 20-Aug-11 08-May-11 A 13-Jul-11

BRACINBRACING ROW B 103 23-Jun-11 20-Aug-11 13-Apr-11 A 16-Jul-11

FABRIFABRICATION 103 23-Jun-11 20-Aug-11 13-Apr-11 A 16-Jul-11

PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 5 23-Jun-11 29-Jun-11 27-Apr-11 A 09-Jun-11 A

PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 8 30-Jun-11 09-Jul-11 04-May-11 A 12-Jun-11 A

PTJ83 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6 9 30-Jun-11 10-Jul-11 04-May-11 A 12-Jun-11 A

PTJ83 WELDING DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4 10 10-Jul-11 21-Jul-11 13-Apr-11 A 15-Jun-11 A

PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2 9 10-Jul-11 20-Jul-11 13-Apr-11 A 18-Jun-11 A

PTJ83 WELDING DIAGONAL BRACES BETWEEN ELEV - 33.4 & -56.2 14 21-Jul-11 06-Aug-11 10-May-11 A 29-Jun-11

PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0 11 21-Jul-11 02-Aug-11 16-May-11 A 04-Jul-11

PTJ84 WELDING DIAGONAL BRACES BETWEEN ELEV - 56.2 & -79.0 15 03-Aug-11 20-Aug-11 08-May-11 A 16-Jul-11

BRACINBRACING ROW C 23 21-Jun-11 17-Jul-11 25-Apr-11 A 28-Jun-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 32 of 64

Page 187: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ845 FITUP BRACES BETWEEN ELEV -10.6 & -33.4 7 21-Jun-11 28-Jun-11 25-Apr-11 A 26-Jun-11

PTJ847 FITUP BRACES BETWEEN ELEV -56.2 & -79.0 7 21-Jun-11 28-Jun-11 25-Apr-11 A 26-Jun-11

PTJ846 FITUP BRACES BETWEEN ELEV -33.4 & -56.2 10 21-Jun-11 02-Jul-11 25-Apr-11 A 26-Jun-11

PTJ848 WELDING BRACES BETWEEN ELEV -10.6 & -33.4 9 29-Jun-11 09-Jul-11 03-May-11 A 27-Jun-11

PTJ849 WELDING BRACES BETWEEN ELEV -56.2 & -79.0 9 29-Jun-11 09-Jul-11 03-May-11 A 27-Jun-11

PTJ850 WELDING BRACES BETWEEN ELEV -33.4 & -56.2 13 03-Jul-11 17-Jul-11 06-May-11 A 28-Jun-11

BRACINBRACING ROW D 19 21-Jun-11 12-Jul-11 25-Apr-11 A 29-Jun-11

PTJ854 FITUP BRACES BETWEEN ELEV -10.6 & -33.4 5 21-Jun-11 26-Jun-11 25-Apr-11 A 26-Jun-11

PTJ856 FITUP BRACES BETWEEN ELEV -56.2 & -79.0 5 21-Jun-11 26-Jun-11 25-Apr-11 A 26-Jun-11

PTJ855 FITUP BRACES BETWEEN ELEV -33.4 & -56.2 8 21-Jun-11 29-Jun-11 25-Apr-11 A 26-Jun-11

PTJ857 WELDING BRACES BETWEEN ELEV -10.6 & -33.4 7 27-Jun-11 04-Jul-11 30-Apr-11 A 27-Jun-11

PTJ858 WELDING BRACES BETWEEN ELEV -56.2 & -79.0 7 27-Jun-11 04-Jul-11 30-Apr-11 A 27-Jun-11

PTJ859 WELDING BRACES BETWEEN ELEV -33.4 & -56.2 11 30-Jun-11 12-Jul-11 04-May-11 A 29-Jun-11

JACKET JACKET ELEVATIONS FABRICATION 185 31-Mar-11 30-Oct-11 31-Mar-11 A 03-Oct-11

ELEV + ELEV + 6400 78 04-Apr-11 29-Jun-11 04-Apr-11 A 23-Jun-11 A

FITUPFITUP 28 04-Apr-11 03-May-11 04-Apr-11 A 02-Jun-11 A

PTJ86 FITUP OF SIZE 24" 18 04-Apr-11 26-Apr-11 04-Apr-11 A 26-May-11 A

PTJ86 FITUP OF SIZE 16" 7 21-Apr-11 01-May-11 23-Apr-11 A 31-May-11 A

PTJ86 FITUP OF SIZE 20" 5 27-Apr-11 03-May-11 30-Apr-11 A 02-Jun-11 A

WELDWELDING&NDT 17 04-May-11 26-May-11 08-May-11 A 14-Jun-11 A

PTJ86 WELDING OF SIZE 24" 12 04-May-11 17-May-11 08-May-11 A 05-Jun-11 A

PTJ86 WELDING OF SIZE 16" 5 18-May-11 23-May-11 22-May-11 A 11-Jun-11 A

PTJ86 WELDING OF SIZE 20" 4 23-May-11 26-May-11 08-May-11 A 14-Jun-11 A

CONDCONDUCTORS AT ELEV + 6400 38 17-May-11 29-Jun-11 08-May-11 A 23-Jun-11 A

WELDWELDING & NDT 18 28-May-11 16-Jun-11 14-May-11 A 20-Jun-11 A

PTJ9 WELDING OF CONDUCTOR 10 28-May-11 07-Jun-11 19-May-11 A 16-Jun-11 A

PTJ9 WELDING OF CONDUCTOR SUPPORT 6 11-Jun-11 16-Jun-11 14-May-11 A 20-Jun-11 A

CONDCONDUCTORS ERECTION 11 18-Jun-11 29-Jun-11 21-May-11 A 23-Jun-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 33 of 64

Page 188: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS 11 18-Jun-11 29-Jun-11 21-May-11 A 23-Jun-11 A

FITUPFITUP 21 17-May-11 09-Jun-11 08-May-11 A 19-Jun-11 A

PTJ9 FITUP OF CONDUCTOR 9 17-May-11 26-May-11 18-May-11 A 14-Jun-11 A

PTJ9 FITUP OF CONDUCTOR SUPPORT 5 05-Jun-11 09-Jun-11 08-May-11 A 19-Jun-11 A

ELEV - ELEV - 10600 159 31-Mar-11 21-Aug-11 31-Mar-11 A 03-Oct-11

FITUPFITUP 41 31-Mar-11 14-May-11 31-Mar-11 A 24-Jul-11

PTJ87 FITUP OF SIZE 28" 26 31-Mar-11 03-May-11 31-Mar-11 A 13-Jul-11

PTJ87 FITUP OF SIZE 16" 8 28-Apr-11 07-May-11 02-May-11 A 17-Jul-11

PTJ87 FITUP OF SIZE 20" 23 12-Apr-11 11-May-11 12-Apr-11 A 21-Jul-11

PTJ87 FITUP OF SIZE 14" 5 09-May-11 14-May-11 12-May-11 A 24-Jul-11

WELDWELDING&NDT 48 15-May-11 09-Jul-11 15-May-11 A 13-Sep-11

PTJ87 WELDING OF SIZE 28" 35 15-May-11 23-Jun-11 18-May-11 A 28-Aug-11

PTJ87 WELDING OF SIZE 16" 9 20-Jun-11 29-Jun-11 23-May-11 A 04-Sep-11

PTJ87 WELDING OF SIZE 20" 31 31-May-11 05-Jul-11 15-May-11 A 10-Sep-11

PTJ87 WELDING OF SIZE 14" 6 03-Jul-11 09-Jul-11 15-May-11 A 13-Sep-11

CONDCONDUCTORS AT ELEV - 10600 79 29-Jun-11 21-Aug-11 13-May-11 A 03-Oct-11

FITUPFITUP 30 29-Jun-11 01-Aug-11 15-May-11 A 18-Jun-11 A

PTJ9 FITUP OF CONDUCTOR 9 29-Jun-11 09-Jul-11 15-May-11 A 15-Jun-11 A

PTJ9 FITUP OF CONDUCTOR SUPPORT 5 27-Jul-11 01-Aug-11 15-May-11 A 18-Jun-11 A

WELDWELDING & NDT 59 10-Jul-11 08-Aug-11 13-May-11 A 20-Sep-11

PTJ9 WELDING OF CONDUCTOR 9 10-Jul-11 20-Jul-11 13-May-11 A 23-Jun-11 A

PTJ9 WELDING OF CONDUCTOR SUPPORT 6 02-Aug-11 08-Aug-11 13-Sep-11 20-Sep-11

CONDCONDUCTORS ERECTION 11 09-Aug-11 21-Aug-11 20-Sep-11 03-Oct-11

PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS 11 09-Aug-11 21-Aug-11 20-Sep-11 03-Oct-11

ELEV - ELEV - 33400 117 31-Mar-11 24-Jul-11 31-Mar-11 A 14-Aug-11

FITUPFITUP 30 31-Mar-11 02-May-11 31-Mar-11 A 21-Jun-11 A

PTJ87 FITUP OF SIZE 28" 14 31-Mar-11 16-Apr-11 31-Mar-11 A 05-Jun-11 A

PTJ88 FITUP OF SIZE 16" 10 09-Apr-11 20-Apr-11 09-Apr-11 A 09-Jun-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 34 of 64

Page 189: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ88 FITUP OF SIZE 24" 8 17-Apr-11 27-Apr-11 17-Apr-11 A 16-Jun-11 A

PTJ88 FITUP OF SIZE 20" 6 21-Apr-11 30-Apr-11 23-Apr-11 A 19-Jun-11 A

PTJ88 FITUP OF SIZE 18" 6 25-Apr-11 02-May-11 27-Apr-11 A 21-Jun-11 A

WELDWELDING&NDT 34 03-May-11 11-Jun-11 24-Apr-11 A 25-Jul-11

PTJ88 WELDING OF SIZE 28" 16 03-May-11 21-May-11 07-May-11 A 04-Jul-11

PTJ88 WELDING OF SIZE 16" 6 21-May-11 26-May-11 24-Apr-11 A 10-Jul-11

PTJ88 WELDING OF SIZE 24" 12 23-May-11 05-Jun-11 26-Apr-11 A 19-Jul-11

PTJ88 WELDING OF SIZE 20" 5 04-Jun-11 08-Jun-11 07-May-11 A 23-Jul-11

PTJ88 WELDING OF SIZE 18" 4 07-Jun-11 11-Jun-11 11-May-11 A 25-Jul-11

CONDCONDUCTORS AT ELEV - 33400 61 01-Jun-11 24-Jul-11 05-May-11 A 14-Aug-11

FITUPFITUP 29 01-Jun-11 04-Jul-11 05-May-11 A 19-Jun-11 A

PTJ9 FITUP OF CONDUCTOR 9 01-Jun-11 11-Jun-11 05-May-11 A 18-Jun-11 A

PTJ9 FITUP OF CONDUCTOR SUPPORT 5 29-Jun-11 04-Jul-11 08-May-11 A 19-Jun-11 A

WELDWELDING & NDT 41 12-Jun-11 11-Jul-11 15-May-11 A 01-Aug-11

PTJ9 WELDING OF CONDUCTOR 10 12-Jun-11 22-Jun-11 15-May-11 A 20-Jun-11 A

PTJ9 WELDING OF CONDUCTOR SUPPORT 6 05-Jul-11 11-Jul-11 25-Jul-11 01-Aug-11

CONDCONDUCTORS ERECTION 11 12-Jul-11 24-Jul-11 01-Aug-11 14-Aug-11

PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS 11 12-Jul-11 24-Jul-11 01-Aug-11 14-Aug-11

ELEV - ELEV - 56200 133 31-Mar-11 13-Aug-11 31-Mar-11 A 03-Aug-11

FITUPFITUP 46 31-Mar-11 19-May-11 31-Mar-11 A 22-Jun-11 A

PTJ89 FITUP OF SIZE 28" 26 31-Mar-11 03-May-11 31-Mar-11 A 15-Jun-11 A

PTJ89 FITUP OF SIZE 24" 18 24-Apr-11 15-May-11 26-Apr-11 A 16-Jun-11 A

PTJ89 FITUP OF SIZE 16" 10 26-Apr-11 08-May-11 28-Apr-11 A 20-Jun-11 A

PTJ89 FITUP OF SIZE 20" 11 05-May-11 17-May-11 09-May-11 A 21-Jun-11 A

PTJ89 FITUP OF SIZE 18" 7 12-May-11 19-May-11 16-May-11 A 22-Jun-11 A

WELDWELDING&NDT 36 21-May-11 30-Jun-11 07-May-11 A 13-Jul-11

PTJ89 WELDING OF SIZE 28" 18 21-May-11 09-Jun-11 17-May-11 A 22-Jun-11 A

PTJ89 WELDING OF SIZE 24" 12 12-Jun-11 25-Jun-11 15-May-11 A 24-Jun-11 A

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 35 of 64

Page 190: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ89 WELDING OF SIZE 16" 7 08-Jun-11 15-Jun-11 12-May-11 A 28-Jun-11

PTJ89 WELDING OF SIZE 20" 7 21-Jun-11 28-Jun-11 14-May-11 A 11-Jul-11

PTJ89 WELDING OF SIZE 18" 4 27-Jun-11 30-Jun-11 07-May-11 A 13-Jul-11

CONDCONDUCTORS AT ELEV - 56200 60 21-Jun-11 13-Aug-11 15-May-11 A 03-Aug-11

FITUPFITUP 30 21-Jun-11 24-Jul-11 15-May-11 A 24-Jun-11 A

PTJ9 FITUP OF CONDUCTOR 9 21-Jun-11 30-Jun-11 15-May-11 A 23-Jun-11 A

PTJ9 FITUP OF CONDUCTOR SUPPORT 5 19-Jul-11 24-Jul-11 19-May-11 A 24-Jun-11 A

WELDWELDING & NDT 38 02-Jul-11 31-Jul-11 21-May-11 A 27-Jul-11

PTJ9 WELDING OF CONDUCTOR 10 02-Jul-11 12-Jul-11 21-May-11 A 13-Jul-11

PTJ9 WELDING OF CONDUCTOR SUPPORT 6 25-Jul-11 31-Jul-11 22-Jun-11 A 27-Jul-11

CONDCONDUCTORS ERECTION 13 01-Aug-11 13-Aug-11 22-Jun-11 A 03-Aug-11

PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS 11 01-Aug-11 13-Aug-11 22-Jun-11 A 03-Aug-11

ELEV - ELEV - 79000 61 18-Aug-11 30-Oct-11 07-Apr-11 A 09-Aug-11

FITUPFITUP 29 18-Aug-11 19-Sep-11 07-Apr-11 A 18-Jul-11

PTJ90 FITUP OF SIZE 28" 13 18-Aug-11 05-Sep-11 23-Apr-11 A 12-Jun-11 A

PTJ90 FITUP OF SIZE 16" 9 31-Aug-11 10-Sep-11 07-Apr-11 A 17-Jun-11 A

PTJ90 FITUP OF SIZE 24" 10 06-Sep-11 17-Sep-11 13-Apr-11 A 16-Jul-11

PTJ90 FITUP OF SIZE 20" 6 13-Sep-11 19-Sep-11 20-Apr-11 A 18-Jul-11

WELDWELDING&NDT 32 20-Sep-11 30-Oct-11 02-May-11 A 09-Aug-11

PTJ90 WELDING OF SIZE 28" 18 20-Sep-11 11-Oct-11 21-May-11 A 21-Jul-11

PTJ90 WELDING OF SIZE 16" 10 05-Oct-11 17-Oct-11 13-May-11 A 27-Jul-11

PTJ90 WELDING OF SIZE 24" 12 13-Oct-11 26-Oct-11 20-May-11 A 06-Aug-11

PTJ90 WELDING OF SIZE 20" 2 26-Oct-11 30-Oct-11 02-May-11 A 09-Aug-11

PILE SLEPILE SLEEVES FABRICATION 72 22-Nov-11 15-Feb-12 07-May-11 A 21-Jan-12

AT LEGAT LEG A1 46 22-Nov-11 23-Jan-12 07-May-11 A 28-Dec-11

PTJ932 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 4 22-Nov-11 26-Nov-11 19-Jun-11 A 23-Nov-11

PTJ933 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL... 4 25-Dec-11 28-Dec-11 29-Nov-11 03-Dec-11

PTJ936 GIRTH WELD OF PILE SLEEVE 23 01-Dec-11 28-Dec-11 07-May-11 A 03-Dec-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 36 of 64

Page 191: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ937 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE... 12 29-Dec-11 11-Jan-12 04-Dec-11 17-Dec-11

PTJ938 ERECTION OF PILE SLEEVE WITH LEGS 10 12-Jan-12 23-Jan-12 18-Dec-11 28-Dec-11

AT LEGAT LEG B1 52 22-Nov-11 23-Jan-12 20-Jun-11 A 28-Dec-11

PTJ946 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 4 22-Nov-11 26-Nov-11 20-Jun-11 A 31-Oct-11

PTJ947 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL... 4 25-Dec-11 28-Dec-11 29-Nov-11 03-Dec-11

PTJ950 GIRTH WELD OF PILE SLEEVE 24 01-Dec-11 28-Dec-11 06-Nov-11 03-Dec-11

PTJ95 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE... 12 29-Dec-11 11-Jan-12 04-Dec-11 17-Dec-11

PTJ952 ERECTION OF PILE SLEEVE WITH LEGS 10 12-Jan-12 23-Jan-12 18-Dec-11 28-Dec-11

AT LEGAT LEG A2 54 15-Dec-11 15-Feb-12 20-Nov-11 21-Jan-12

PTJ939 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 4 15-Dec-11 19-Dec-11 20-Nov-11 23-Nov-11

PTJ940 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL... 4 17-Jan-12 21-Jan-12 22-Dec-11 26-Dec-11

PTJ943 GIRTH WELD OF PILE SLEEVE 24 25-Dec-11 21-Jan-12 29-Nov-11 26-Dec-11

PTJ944 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE... 12 22-Jan-12 04-Feb-12 27-Dec-11 09-Jan-12

PTJ945 ERECTION OF PILE SLEEVE WITH LEGS 10 05-Feb-12 15-Feb-12 10-Jan-12 21-Jan-12

AT LEGAT LEG B2 54 15-Dec-11 15-Feb-12 20-Nov-11 21-Jan-12

PTJ953 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE 4 15-Dec-11 19-Dec-11 20-Nov-11 23-Nov-11

PTJ954 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL... 4 17-Jan-12 21-Jan-12 22-Dec-11 26-Dec-11

PTJ957 GIRTH WELD OF PILE SLEEVE 24 25-Dec-11 21-Jan-12 29-Nov-11 26-Dec-11

PTJ958 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE... 12 22-Jan-12 04-Feb-12 27-Dec-11 09-Jan-12

PTJ959 ERECTION OF PILE SLEEVE WITH LEGS 10 05-Feb-12 15-Feb-12 10-Jan-12 21-Jan-12

JACKET JACKET ERECTION 176 14-Jun-11 15-Feb-12 28-Jun-11 21-Jan-12

ELEV +ELEV +6.4 7 22-Dec-11 29-Dec-11 26-Oct-11 02-Nov-11

ERECTERECTION ON ROW2 7 22-Dec-11 29-Dec-11 26-Oct-11 02-Nov-11

PTJ86 ERECTION OF ELEV AT + 6.4 ON ROW 2 7 22-Dec-11 29-Dec-11 26-Oct-11 02-Nov-11

ELEV -5ELEV -56.2 7 31-Oct-11 07-Nov-11 09-Aug-11 17-Aug-11

ERECTERECTION ON ROW2 7 31-Oct-11 07-Nov-11 09-Aug-11 17-Aug-11

PTJ90 ERECTION OF ELEV AT -56.2 ON ROW 2 7 31-Oct-11 07-Nov-11 09-Aug-11 17-Aug-11

ELEV -7ELEV -79.0 7 08-Nov-11 15-Nov-11 17-Aug-11 25-Aug-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 37 of 64

Page 192: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

ERECTERECTION ON ROW2 7 08-Nov-11 15-Nov-11 17-Aug-11 25-Aug-11

PTJ90 ERECTION OF ELEV AT -79 ON ROW 2 7 08-Nov-11 15-Nov-11 17-Aug-11 25-Aug-11

ELEV - ELEV - 33.4 7 17-Nov-11 24-Nov-11 27-Aug-11 05-Sep-11

ERECTERECTION ON ROW2 7 17-Nov-11 24-Nov-11 27-Aug-11 05-Sep-11

PTJ88 ERECTION OF ELEV AT -33.4 ON ROW 2 7 17-Nov-11 24-Nov-11 27-Aug-11 05-Sep-11

ELEV -1ELEV -10.6 7 05-Dec-11 12-Dec-11 03-Oct-11 12-Oct-11

ERECTERECTION ON ROW2 7 05-Dec-11 12-Dec-11 03-Oct-11 12-Oct-11

PTJ87 ERECTION OF ELEV AT -10.6 ON ROW 2 7 05-Dec-11 12-Dec-11 03-Oct-11 12-Oct-11

ROW 2ROW 2 37 14-Jun-11 30-Oct-11 28-Jun-11 09-Aug-11

ERECTERECTION 36 14-Jun-11 29-Oct-11 28-Jun-11 08-Aug-11

HORIHORIZONTAL 15 14-Jun-11 30-Jun-11 28-Jun-11 16-Jul-11

PTJ9 FITUP OF HORIZONTAL ON LEG 5 14-Jun-11 19-Jun-11 28-Jun-11 04-Jul-11

PTJ9 WELDING OF HORIZONTAL ON LEG 10 20-Jun-11 30-Jun-11 04-Jul-11 16-Jul-11

DIAGDIAGONAL BRACES 30 20-Jun-11 24-Jul-11 04-Jul-11 08-Aug-11

PTJ8 FITUP OF DIAGONAL ON LEG 10 20-Jun-11 30-Jun-11 04-Jul-11 16-Jul-11

PTJ8 WELDING OF DIAGONAL ON LEG 20 02-Jul-11 24-Jul-11 16-Jul-11 08-Aug-11

VERTVERTICAL 15 12-Oct-11 29-Oct-11 21-Jul-11 08-Aug-11

PTJ8 FITUP OF VERTICAL BRACES WITH ROW 2 BRACES 5 12-Oct-11 17-Oct-11 21-Jul-11 27-Jul-11

PTJ8 WELDING OF VERTICAL BRACES WITH ROW 2 BRACES 10 18-Oct-11 29-Oct-11 27-Jul-11 08-Aug-11

LIFTINLIFTING OVER TRUSS RUNNER 1 30-Oct-11 30-Oct-11 08-Aug-11 09-Aug-11

PTJ81 LIFTING OVER TRUSS RUNNERS 1 30-Oct-11 30-Oct-11 08-Aug-11 09-Aug-11

ROW CROW C 19 08-Nov-11 29-Nov-11 17-Aug-11 10-Sep-11

PTJ85 ERECTION ROW C BRACES BETWEEN -56.2 & -79.0 4 08-Nov-11 12-Nov-11 17-Aug-11 22-Aug-11

PTJ853 ERECTION ROW C BRACES BETWEEN - 10.6 & -33.4 4 26-Nov-11 29-Nov-11 05-Sep-11 10-Sep-11

PTJ852 ERECTION ROW C BRACES BETWEEN -33.4 & -56.2 4 26-Nov-11 29-Nov-11 05-Sep-11 10-Sep-11

ROW AROW A 67 06-Sep-11 17-Dec-11 28-Jul-11 17-Oct-11

ERECTERECTION 67 06-Sep-11 17-Dec-11 28-Jul-11 17-Oct-11

PTJ83 ERECTION X BRACES BETWEEN -56.2 & -79.0 6 06-Sep-11 12-Sep-11 28-Jul-11 04-Aug-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 38 of 64

Page 193: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ83 ERECTION X BRACES BETWEEN -33.4 & -56.2 4 08-Nov-11 12-Nov-11 17-Aug-11 22-Aug-11

PTJ83 ERECTION X BRACES BETWEEN -10.6 & -33.4 4 26-Nov-11 29-Nov-11 05-Sep-11 10-Sep-11

PTJ82 ERECTION X BRACES BETWEEN +6.4 & -10.6 4 13-Dec-11 17-Dec-11 12-Oct-11 17-Oct-11

ROW BROW B 65 13-Sep-11 21-Dec-11 04-Aug-11 22-Oct-11

ERECTERECTION 65 13-Sep-11 21-Dec-11 04-Aug-11 22-Oct-11

PTJ84 ERECTION X BRACES BETWEEN -56.2 & -79.0 6 13-Sep-11 19-Sep-11 04-Aug-11 11-Aug-11

PTJ84 ERECTION X BRACES BETWEEN -33.4 & -56.2 4 13-Nov-11 16-Nov-11 22-Aug-11 27-Aug-11

PTJ84 ERECTION X BRACES BETWEEN -10.6 & -33.4 4 30-Nov-11 04-Dec-11 10-Sep-11 14-Sep-11

PTJ84 ERECTION X BRACES BETWEEN +6.4 & -10.6 4 18-Dec-11 21-Dec-11 17-Oct-11 22-Oct-11

ROW DROW D 41 16-Nov-11 14-Dec-11 25-Aug-11 15-Oct-11

PTJ860 ERECTION ROW D BRACES BETWEEN -56.2 & -79.0 2 16-Nov-11 17-Nov-11 25-Aug-11 28-Aug-11

PTJ86 ERECTION ROW D BRACES BETWEEN -33.4 & -56.2 2 26-Nov-11 27-Nov-11 05-Sep-11 07-Sep-11

PTJ862 ERECTION ROW D BRACES BETWEEN -10.6 & -33.4 2 13-Dec-11 14-Dec-11 12-Oct-11 15-Oct-11

ROW 3ROW 3 4 19-Jan-12 23-Jan-12 23-Nov-11 27-Nov-11

PTJ818 ERECTION ROW 3 BRACES BETWEEN -10.6 & -33.4 4 19-Jan-12 23-Jan-12 23-Nov-11 27-Nov-11

PTJ819 ERECTION ROW 3 BRACES BETWEEN -33.4 & -56.2 4 19-Jan-12 23-Jan-12 23-Nov-11 27-Nov-11

PTJ820 ERECTION ROW 3 BRACES BETWEEN -56.2 & -79.0 4 19-Jan-12 23-Jan-12 23-Nov-11 27-Nov-11

ROW 1ROW 1 170 24-Sep-11 15-Feb-12 04-Jul-11 21-Jan-12

HORIZHORIZONTAL 15 24-Sep-11 11-Oct-11 04-Jul-11 21-Jul-11

PTJ94 FITUP OF HORIZONTAL ON LEG 5 24-Sep-11 28-Sep-11 04-Jul-11 10-Jul-11

PTJ94 WELDING OF HORIZONTAL ON LEG 10 29-Sep-11 11-Oct-11 10-Jul-11 21-Jul-11

DIAGODIAGONAL BRACES 30 29-Sep-11 03-Nov-11 10-Jul-11 14-Aug-11

PTJ94 FITUP OF DIAGONAL ON LEG 10 29-Sep-11 11-Oct-11 10-Jul-11 21-Jul-11

PTJ94 WELDING OF DIAGONAL ON LEG 20 12-Oct-11 03-Nov-11 21-Jul-11 14-Aug-11

ERECTERECTION ROW 1 20 24-Jan-12 15-Feb-12 29-Dec-11 21-Jan-12

PTJ80 LIFTING OF ROW 1 OVER ELAVATIONS & ROW A,B 1 24-Jan-12 24-Jan-12 29-Dec-11 29-Dec-11

PTJ80 FITUP OF ROW 1 OVER ELAVATIONS & ROW A,B 4 25-Jan-12 29-Jan-12 31-Dec-11 03-Jan-12

PTJ80 WELDING OF ROW 1 OVER ELAVATIONS & ROW A,B 15 30-Jan-12 15-Feb-12 04-Jan-12 21-Jan-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 39 of 64

Page 194: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

JACKET MJACKET MISCELLANEOUS FABRICATION 206 31-Mar-11 21-Feb-12 31-Mar-11 A 26-Jan-12

PTJ9600 Jacket miscellaneous fabrication start 0 31-Aug-11 31-Aug-11

PTJ11020 Jacket miscellaneous fabrication finish 0 21-Feb-12 26-Jan-12

BOAT LABOAT LAND 65 19-Dec-11 21-Feb-12 23-Nov-11 26-Jan-12

Main LeMain Legs 5 19-Dec-11 23-Dec-11 23-Nov-11 27-Nov-11

BL1000 Cutting & Assembly 3 19-Dec-11 21-Dec-11 23-Nov-11 25-Nov-11

BL1010 Welding & NDT 4 20-Dec-11 23-Dec-11 24-Nov-11 27-Nov-11

Back ElBack Elevation 20 24-Dec-11 12-Jan-12 28-Nov-11 17-Dec-11

BL1040 Cutting & Assembly 10 24-Dec-11 02-Jan-12 28-Nov-11 07-Dec-11

BL1050 Welding & NDT 15 29-Dec-11 12-Jan-12 03-Dec-11 17-Dec-11

Front ElFront Elevation 21 28-Jan-12 17-Feb-12 02-Jan-12 22-Jan-12

BL1020 Cutting & Assembly 12 28-Jan-12 08-Feb-12 02-Jan-12 13-Jan-12

BL1030 Welding & NDT 15 03-Feb-12 17-Feb-12 08-Jan-12 22-Jan-12

Plan at Plan at Elev. +2.6 14 14-Jan-12 27-Jan-12 19-Dec-11 01-Jan-12

BL1060 Cutting & Assembly 4 14-Jan-12 17-Jan-12 19-Dec-11 22-Dec-11

BL1070 Welding & NDT 6 22-Jan-12 27-Jan-12 27-Dec-11 01-Jan-12

Plan at Plan at Elev. +2.4 15 13-Jan-12 27-Jan-12 18-Dec-11 01-Jan-12

BL1080 Cutting & Assembly 5 13-Jan-12 17-Jan-12 18-Dec-11 22-Dec-11

BL1090 Welding & NDT 7 21-Jan-12 27-Jan-12 26-Dec-11 01-Jan-12

Plan at Plan at Elev. -30 15 13-Jan-12 27-Jan-12 18-Dec-11 01-Jan-12

BL1100 Cutting & Assembly 5 13-Jan-12 17-Jan-12 18-Dec-11 22-Dec-11

BL1110 Welding & NDT 7 21-Jan-12 27-Jan-12 26-Dec-11 01-Jan-12

Boat lanBoat landing Sections (a,b.c,d,e) 10 18-Jan-12 27-Jan-12 23-Dec-11 01-Jan-12

BL1120 Cutting & Assembly 4 18-Jan-12 21-Jan-12 23-Dec-11 26-Dec-11

BL1130 Welding & NDT 6 22-Jan-12 27-Jan-12 27-Dec-11 01-Jan-12

GratingGrating 18 04-Feb-12 21-Feb-12 09-Jan-12 26-Jan-12

BL1140 Trial Fit and Grating Stopper Fixation 1 04-Feb-12 04-Feb-12 09-Jan-12 09-Jan-12

BL1150 Final Installation 1 21-Feb-12 21-Feb-12 26-Jan-12 26-Jan-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 40 of 64

Page 195: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Stairs &Stairs & Ladders 8 10-Feb-12 17-Feb-12 15-Jan-12 22-Jan-12

BL1160 Fabrication 5 10-Feb-12 14-Feb-12 15-Jan-12 19-Jan-12

BL1170 Installation 3 15-Feb-12 17-Feb-12 20-Jan-12 22-Jan-12

HandraiHandrails 16 06-Feb-12 21-Feb-12 11-Jan-12 26-Jan-12

BL1200 Fabrication 4 06-Feb-12 09-Feb-12 11-Jan-12 14-Jan-12

BL1210 Installation 2 20-Feb-12 21-Feb-12 25-Jan-12 26-Jan-12

MooringMooring Cleat 2 16-Feb-12 17-Feb-12 21-Jan-12 22-Jan-12

BL1220 Fabrication 1 16-Feb-12 16-Feb-12 21-Jan-12 21-Jan-12

BL1230 Installation 1 17-Feb-12 17-Feb-12 22-Jan-12 22-Jan-12

RubberRubber 1 21-Feb-12 21-Feb-12 26-Jan-12 26-Jan-12

BL1240 Installation of Rubber & Tightening 1 21-Feb-12 21-Feb-12 26-Jan-12 26-Jan-12

Lower SLower Support 27 22-Jan-12 17-Feb-12 27-Dec-11 22-Jan-12

InstallaInstallation with Jacket legs 4 14-Feb-12 17-Feb-12 19-Jan-12 22-Jan-12

BL127 Profiling Template & Assembly with Legs 2 14-Feb-12 15-Feb-12 19-Jan-12 20-Jan-12

BL128 Welding & NDT 3 15-Feb-12 17-Feb-12 20-Jan-12 22-Jan-12

FabricaFabrication 16 22-Jan-12 06-Feb-12 27-Dec-11 11-Jan-12

BL125 Cutting & Assembly 7 22-Jan-12 28-Jan-12 27-Dec-11 02-Jan-12

BL126 Welding & NDT 9 29-Jan-12 06-Feb-12 03-Jan-12 11-Jan-12

Upper SUpper Support 23 26-Jan-12 17-Feb-12 31-Dec-11 22-Jan-12

FabricaFabrication 19 26-Jan-12 13-Feb-12 31-Dec-11 18-Jan-12

BL129 Cutting & Assembly 7 26-Jan-12 01-Feb-12 31-Dec-11 06-Jan-12

BL130 Welding & NDT 12 02-Feb-12 13-Feb-12 07-Jan-12 18-Jan-12

InstallaInstallation with Jacket legs 4 14-Feb-12 17-Feb-12 19-Jan-12 22-Jan-12

BL131 Profiling Template & Assembly with Legs 2 14-Feb-12 15-Feb-12 19-Jan-12 20-Jan-12

BL132 Welding & NDT 3 15-Feb-12 17-Feb-12 20-Jan-12 22-Jan-12

Boat lanBoat landing trial fit 2 18-Feb-12 19-Feb-12 23-Jan-12 24-Jan-12

BL1330 Boat Landing Trial Fit 2 18-Feb-12 19-Feb-12 23-Jan-12 24-Jan-12

BARGE BBARGE BUMPER 30 23-Jan-12 21-Feb-12 28-Dec-11 26-Jan-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 41 of 64

Page 196: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Main PiMain Pipe 15 23-Jan-12 06-Feb-12 28-Dec-11 11-Jan-12

BB1000 Cutting & Assembly 6 23-Jan-12 28-Jan-12 28-Dec-11 02-Jan-12

BB1010 Welding & NDT 9 29-Jan-12 06-Feb-12 03-Jan-12 11-Jan-12

Upper SUpper Support 28 23-Jan-12 19-Feb-12 28-Dec-11 24-Jan-12

FabricaFabrication 23 23-Jan-12 14-Feb-12 28-Dec-11 19-Jan-12

BB10 Cutting & Assembly 12 23-Jan-12 03-Feb-12 28-Dec-11 08-Jan-12

BB10 Welding & NDT 17 29-Jan-12 14-Feb-12 03-Jan-12 19-Jan-12

InstallaInstallation with Jacket legs 5 15-Feb-12 19-Feb-12 20-Jan-12 24-Jan-12

BB10 Profiling Template & Assembly with Legs 2 15-Feb-12 16-Feb-12 20-Jan-12 21-Jan-12

BB10 Welding & NDT 3 17-Feb-12 19-Feb-12 22-Jan-12 24-Jan-12

Lower SLower Support 24 27-Jan-12 19-Feb-12 01-Jan-12 24-Jan-12

InstallaInstallation with Jacket legs 5 15-Feb-12 19-Feb-12 20-Jan-12 24-Jan-12

BB10 Profiling Template & Assembly with Legs 2 15-Feb-12 16-Feb-12 20-Jan-12 21-Jan-12

BB10 Welding & NDT 3 17-Feb-12 19-Feb-12 22-Jan-12 24-Jan-12

FabricaFabrication 19 27-Jan-12 14-Feb-12 01-Jan-12 19-Jan-12

BB10 Cutting & Assembly 8 27-Jan-12 03-Feb-12 01-Jan-12 08-Jan-12

BB10 Welding & NDT 11 04-Feb-12 14-Feb-12 09-Jan-12 19-Jan-12

Barge BBarge Bumper Trial Fit 2 20-Feb-12 21-Feb-12 25-Jan-12 26-Jan-12

BB1100 Barge Bumper Trial Fit 2 20-Feb-12 21-Feb-12 25-Jan-12 26-Jan-12

RISER 1RISER 16" & CLAMPS 42 31-Aug-11 27-Oct-11 31-Aug-11 19-Oct-11

PTJ106 CLAMPS FOR RISER 16 " FABRICATION 18 31-Aug-11 20-Sep-11 31-Aug-11 20-Sep-11

PTJ105 RISER 16 " FABRICATION 22 31-Aug-11 25-Sep-11 31-Aug-11 25-Sep-11

PTJ106 RISER COATING 7 26-Sep-11 03-Oct-11 26-Sep-11 03-Oct-11

PTJ106 CLAMPS FOR RISER 16 " INSTALLATION 14 29-Sep-11 16-Oct-11 21-Sep-11 08-Oct-11

PTJ106 RISER 16 " INSTALLATION 10 17-Oct-11 27-Oct-11 09-Oct-11 19-Oct-11

J-TUBE J-TUBE 16 " & CLAMPS 26 31-Aug-11 16-Oct-11 31-Aug-11 29-Sep-11

PTJ106 CLAMPS FOR J-TUBE16 " FABRICATION 12 31-Aug-11 13-Sep-11 31-Aug-11 13-Sep-11

PTJ106 J-TUBE16 " FABRICATION 14 31-Aug-11 15-Sep-11 31-Aug-11 15-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 42 of 64

Page 197: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ106 CLAMPS FOR J-TUBE16 " INSTALLATION 10 29-Sep-11 11-Oct-11 14-Sep-11 25-Sep-11

PTJ106 J-TUBE16 " INSTALLATION 4 12-Oct-11 16-Oct-11 26-Sep-11 29-Sep-11

FUTUREFUTURE J-TUBE CLAMPS 14 31-Aug-11 05-Oct-11 31-Aug-11 15-Sep-11

PTJ106 CLAMPS FOR FUTURE J-TUBE FABRICATION 8 31-Aug-11 08-Sep-11 31-Aug-11 08-Sep-11

PTJ107 CLAMPS FOR FUTURE J-TUBE INSTALLATION 6 29-Sep-11 05-Oct-11 10-Sep-11 15-Sep-11

SUMP CSUMP CAISSON 30" 18 31-Jan-12 20-Feb-12 05-Jan-12 25-Jan-12

PTJ107 SUPPORTS SUMP CAISSON 30 " FABRICATION 2 07-Feb-12 08-Feb-12 12-Jan-12 14-Jan-12

PTJ107 SUMP CAISSON 30 " FABRICATION 14 31-Jan-12 15-Feb-12 05-Jan-12 21-Jan-12

PTJ107 SUPPORTS SUMP CAISSON 30 " INSTALLATION 6 09-Feb-12 15-Feb-12 15-Jan-12 21-Jan-12

PTJ107 SUPPORTS SUMP CAISSON 30 " INSTALLATION 4 16-Feb-12 20-Feb-12 22-Jan-12 25-Jan-12

MUD MAMUD MAT 80 31-Aug-11 03-Dec-11 31-Aug-11 03-Dec-11

PTJ107 MUD MAT FABRICATION 60 31-Aug-11 09-Nov-11 31-Aug-11 09-Nov-11

PTJ107 MUD MAT INSTALLATION 20 10-Nov-11 03-Dec-11 10-Nov-11 03-Dec-11

WALK WWALK WAY & STAIRS 47 31-Aug-11 25-Oct-11 31-Aug-11 25-Oct-11

PTJ103 FITUP OF WALK WAY & STARIR 12 31-Aug-11 13-Sep-11 31-Aug-11 13-Sep-11

PTJ103 WELDING & NDT OF WALK WAY & STARIRS 16 14-Sep-11 02-Oct-11 14-Sep-11 02-Oct-11

PTJ103 ERECTION WALK WAY ON TOP ELEVATION 12 12-Oct-11 25-Oct-11 12-Oct-11 25-Oct-11

LAUNCHLAUNCH RUNNERS 118 31-Mar-11 14-Aug-11 31-Mar-11 A 14-Jul-11

AT ROWAT ROW D 118 31-Mar-11 14-Aug-11 31-Mar-11 A 14-Jul-11

FROM FROM EL. -33400 TO -10600 87 31-Mar-11 24-May-11 31-Mar-11 A 10-Jul-11

PTJ98 FITUP OF LUNCH TRUSS FROM EL -33.4 UP TO -10.6 32 31-Mar-11 10-May-11 31-Mar-11 A 26-Jun-11

PTJ98 WELDING & NDT LUNCH TRUSS FROM EL -33.4 UP TO -10.6 24 24-Apr-11 22-May-11 26-Apr-11 A 07-Jul-11

PTJ98 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... 2 23-May-11 24-May-11 07-Jul-11 10-Jul-11

FROM FROM EL. -56200 TO -33400 50 11-May-11 04-Jul-11 15-Apr-11 A 12-Jul-11

PTJ97 FITUP OF LUNCH TRUSS FROM EL -56 UP TO -33.4 35 11-May-11 20-Jun-11 15-Apr-11 A 28-Jun-11

PTJ98 WELDING & NDT OF LUNCH TRUSS FROM EL -56 UP TO -33.4 25 04-Jun-11 02-Jul-11 07-May-11 A 10-Jul-11

PTJ98 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... 2 03-Jul-11 04-Jul-11 10-Jul-11 12-Jul-11

FROM FROM EL. -79000 TO -56200 45 21-Jun-11 14-Aug-11 25-Apr-11 A 14-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 43 of 64

Page 198: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ97 FITUP OF LUNCH TRUSS FROM EL -79 UP TO -56 34 21-Jun-11 31-Jul-11 25-Apr-11 A 30-Jun-11

PTJ97 WELDING & NDT OF LUNCH TRUSS FROM EL -79 UP TO -56 24 14-Jul-11 11-Aug-11 18-May-11 A 12-Jul-11

PTJ97 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... 2 13-Aug-11 14-Aug-11 12-Jul-11 14-Jul-11

AT ROWAT ROW C 118 31-Mar-11 14-Aug-11 31-Mar-11 A 14-Jul-11

FROM FROM EL. -33400 TO -10600 87 31-Mar-11 24-May-11 31-Mar-11 A 10-Jul-11

PTJ97 FITUP OF LUNCH TRUSS FROM EL -33.4 UP TO -10.6 32 31-Mar-11 10-May-11 31-Mar-11 A 26-Jun-11

PTJ97 WELDING & NDT LUNCH TRUSS FROM EL -33.4 UP TO -10.6 24 24-Apr-11 22-May-11 26-Apr-11 A 07-Jul-11

PTJ97 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... 2 23-May-11 24-May-11 07-Jul-11 10-Jul-11

FROM FROM EL. -79000 TO -56200 45 21-Jun-11 14-Aug-11 25-Apr-11 A 14-Jul-11

PTJ96 FITUP OF LUNCH TRUSS FROM EL -79 UP TO -56 34 21-Jun-11 31-Jul-11 25-Apr-11 A 30-Jun-11

PTJ96 WELDING & NDT OF LUNCH TRUSS FROM EL -79 UP TO -56 24 14-Jul-11 11-Aug-11 18-May-11 A 12-Jul-11

PTJ96 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... 2 13-Aug-11 14-Aug-11 12-Jul-11 14-Jul-11

FROM FROM EL. -56200 TO -33400 50 11-May-11 04-Jul-11 01-May-11 A 12-Jul-11

PTJ97 FITUP OF LUNCH TRUSS FROM EL -56 UP TO -33.4 35 11-May-11 20-Jun-11 01-May-11 A 28-Jun-11

PTJ97 WELDING & NDT OF LUNCH TRUSS FROM EL -56 UP TO -33.4 25 04-Jun-11 02-Jul-11 14-May-11 A 10-Jul-11

PTJ97 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... 2 03-Jul-11 04-Jul-11 10-Jul-11 12-Jul-11

ANODESANODES 167 21-Aug-11 21-Feb-12 11-Jun-11 A 26-Jan-12

PTJ100 INSTALL ANODES FOR ROW A 13 21-Aug-11 05-Sep-11 13-Jul-11 28-Jul-11

PTJ101 INSTALL ANODES FOR ROW B 8 04-Sep-11 12-Sep-11 14-Jun-11 A 04-Aug-11

PTJ102 INSTALL ANODES FOR ELEV -56.2 7 23-Oct-11 30-Oct-11 01-Aug-11 09-Aug-11

PTJ101 INSTALL ANODES FOR ROW C 6 01-Nov-11 07-Nov-11 10-Aug-11 17-Aug-11

PTJ102 INSTALL ANODES FOR ELEV -79.0 7 31-Oct-11 07-Nov-11 09-Aug-11 17-Aug-11

PTJ101 INSTALL ANODES FOR ROW D 6 09-Nov-11 15-Nov-11 18-Aug-11 25-Aug-11

PTJ102 INSTALL ANODES FOR ELEV -33.4 5 12-Nov-11 16-Nov-11 21-Aug-11 27-Aug-11

PTJ102 INSTALL ANODES FOR ELEV -10.6 5 29-Nov-11 04-Dec-11 27-Sep-11 03-Oct-11

PTJ101 INSTALL ANODES FOR ROW 3 6 12-Jan-12 18-Jan-12 16-Nov-11 22-Nov-11

PTJ101 INSTALL ANODES FOR ROW 1 10 04-Jan-12 15-Jan-12 10-Dec-11 20-Dec-11

PTJ101 INSTALL ANODES FOR ROW 2 10 28-Jan-12 07-Feb-12 11-Jun-11 A 12-Jan-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 44 of 64

Page 199: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ102 INSTALL ANODES FOR MUD MAT 7 14-Feb-12 21-Feb-12 19-Jan-12 26-Jan-12

PTJ102 INSTALL ANODES FOR SUMP CASSOIN 1 21-Feb-12 21-Feb-12 26-Jan-12 26-Jan-12

BOUNCYBOUNCY TANKS 82 31-Aug-11 05-Dec-11 31-Aug-11 05-Dec-11

AT LEGAT LEG A1 82 31-Aug-11 05-Dec-11 31-Aug-11 05-Dec-11

PTJ985 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 6 31-Aug-11 06-Sep-11 31-Aug-11 06-Sep-11

PTJ986 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPOR... 12 31-Aug-11 13-Sep-11 31-Aug-11 13-Sep-11

PTJ987 ROLLING OF BOUNCY TANK PLATE 20 07-Sep-11 29-Sep-11 07-Sep-11 29-Sep-11

PTJ988 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 24 12-Sep-11 10-Oct-11 12-Sep-11 10-Oct-11

PTJ989 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUN... 24 11-Oct-11 07-Nov-11 11-Oct-11 07-Nov-11

PTJ99 ERECTION OF BOUNCY TANK WITH LEGS 10 08-Nov-11 19-Nov-11 08-Nov-11 19-Nov-11

PTJ990 GIRTH WELD OF BOUNCY TANK 24 08-Nov-11 05-Dec-11 08-Nov-11 05-Dec-11

AT LEGAT LEG A2 82 31-Aug-11 05-Dec-11 31-Aug-11 05-Dec-11

PTJ992 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 6 31-Aug-11 06-Sep-11 31-Aug-11 06-Sep-11

PTJ993 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPOR... 12 31-Aug-11 13-Sep-11 31-Aug-11 13-Sep-11

PTJ994 ROLLING OF BOUNCY TANK PLATE 20 07-Sep-11 29-Sep-11 07-Sep-11 29-Sep-11

PTJ995 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 24 12-Sep-11 10-Oct-11 12-Sep-11 10-Oct-11

PTJ996 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUN... 24 11-Oct-11 07-Nov-11 11-Oct-11 07-Nov-11

PTJ998 ERECTION OF BOUNCY TANK WITH LEGS 10 08-Nov-11 19-Nov-11 08-Nov-11 19-Nov-11

PTJ997 GIRTH WELD OF BOUNCY TANK 24 08-Nov-11 05-Dec-11 08-Nov-11 05-Dec-11

AT LEGAT LEG B1 82 31-Aug-11 05-Dec-11 31-Aug-11 05-Dec-11

PTJ999 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 6 31-Aug-11 06-Sep-11 31-Aug-11 06-Sep-11

PTJ100 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPRT... 12 31-Aug-11 13-Sep-11 31-Aug-11 13-Sep-11

PTJ100 ROLLING OF BOUNCY TANK PLATE 20 07-Sep-11 29-Sep-11 07-Sep-11 29-Sep-11

PTJ100 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 24 12-Sep-11 10-Oct-11 12-Sep-11 10-Oct-11

PTJ100 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUN... 24 11-Oct-11 07-Nov-11 11-Oct-11 07-Nov-11

PTJ100 ERECTION OF BOUNCY TANK WITH LEGS 10 08-Nov-11 19-Nov-11 08-Nov-11 19-Nov-11

PTJ100 GIRTH WELD OF BOUNCY TANK 24 08-Nov-11 05-Dec-11 08-Nov-11 05-Dec-11

AT LEGAT LEG B2 82 31-Aug-11 05-Dec-11 31-Aug-11 05-Dec-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 45 of 64

Page 200: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ100 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE 6 31-Aug-11 06-Sep-11 31-Aug-11 06-Sep-11

PTJ100 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPOR... 12 31-Aug-11 13-Sep-11 31-Aug-11 13-Sep-11

PTJ100 ROLLING OF BOUNCY TANK PLATE 20 07-Sep-11 29-Sep-11 07-Sep-11 29-Sep-11

PTJ10 SEAM WELD & REROLLING OF BOUNCY TANK PLATE 24 12-Sep-11 10-Oct-11 12-Sep-11 10-Oct-11

PTJ10 ERECTION OF SUPPORTS& STIFFENERS PLATE WITH BOUN... 24 11-Oct-11 07-Nov-11 11-Oct-11 07-Nov-11

PTJ10 ERECTION OF BOUNCY TANK WITH LEGS 10 08-Nov-11 19-Nov-11 08-Nov-11 19-Nov-11

PTJ10 GIRTH WELD OF BOUNCY TANK 24 08-Nov-11 05-Dec-11 08-Nov-11 05-Dec-11

BALLASBALLASTING & GROUTING SYSTEM 35 01-Jan-12 09-Feb-12 06-Dec-11 15-Jan-12

PTJ107 BALASTING INSTALLATION 20 01-Jan-12 23-Jan-12 06-Dec-11 28-Dec-11

PTJ109 GROUTING INSTALLATION ON ROW 1 20 01-Jan-12 23-Jan-12 06-Dec-11 28-Dec-11

PTJ109 GROUTING INSTALLATION ON ROW 2 20 18-Jan-12 09-Feb-12 24-Dec-11 15-Jan-12

GRILLAGGRILLAGE & SEA FASTENING 120 22-Sep-11 09-Feb-12 08-Sep-11 26-Jan-12

PTJ108 GRILLAGE & SEA FASTENING FABRICATION 120 22-Sep-11 09-Feb-12 08-Sep-11 26-Jan-12

INSTALLINSTALLATION AIDS 32 31-Aug-11 08-Oct-11 31-Aug-11 08-Oct-11

PTJ107 INSTALLATION AIDS FABRICATION 22 31-Aug-11 25-Sep-11 31-Aug-11 25-Sep-11

PTJ107 INSTALLATION AIDS INSTALLATION 10 26-Sep-11 08-Oct-11 26-Sep-11 08-Oct-11

PREBENPREBENT CONDUCTOR 17 31-Dec-11 18-Jan-12 03-Nov-11 22-Nov-11

PTJ9300 FITUP OF PREBENT CONDUCTOR 8 31-Dec-11 08-Jan-12 03-Nov-11 12-Nov-11

PTJ9310 WELDING OF PREBENT CONDUCTOR 9 09-Jan-12 18-Jan-12 13-Nov-11 22-Nov-11

PAINTINGPAINTING 141 03-Oct-11 15-Mar-12 03-Oct-11 15-Mar-12

PTJ10320 SPLASH PAINTING FOR MISC. (H.R, STAIRS, ...ETC) 7 03-Oct-11 11-Oct-11 03-Oct-11 11-Oct-11

PTJ10300 SPLASH PAINTING FOR ROW A 7 05-Dec-11 12-Dec-11 03-Oct-11 12-Oct-11

PTJ10310 SPLASH PAINTING FOR ROW B 7 10-Dec-11 17-Dec-11 09-Oct-11 17-Oct-11

PTJ10340 ATMOSPHERIC PAINTING FOR TOP ELEV 7 14-Dec-11 21-Dec-11 18-Oct-11 25-Oct-11

PTJ10280 SPLASH PAINTING FOR ROW 1 7 16-Jan-12 23-Jan-12 21-Dec-11 28-Dec-11

PTJ10290 SPLASH PAINTING FOR ROW 2 7 08-Feb-12 15-Feb-12 14-Jan-12 21-Jan-12

PTJ10260 SPLASH PAINTING FOR BOAT LAND 14 05-Feb-12 20-Feb-12 10-Jan-12 25-Jan-12

PTJ10270 SPLASH PAINTING FOR BARGE BUMPER 5 11-Mar-12 15-Mar-12 11-Mar-12 15-Mar-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 46 of 64

Page 201: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ10330 PILE MARKING 28 13-Feb-12 15-Mar-12 13-Feb-12 15-Mar-12

INSPECTINSPECTION, TESTING & PRE-COMMISIONING 10 11-Feb-12 21-Feb-12 16-Jan-12 26-Jan-12

PTJ10990 RISER HYDRO TEST 10 11-Feb-12 21-Feb-12 16-Jan-12 26-Jan-12

PTJ11000 BALLASTING SYSTEM TEST 10 11-Feb-12 21-Feb-12 16-Jan-12 26-Jan-12

PTJ11010 GROUTING SYSTEM TEST 10 11-Feb-12 21-Feb-12 16-Jan-12 26-Jan-12

PILES FABPILES FABRICATION 123 02-Jul-11 17-Dec-11 15-Apr-11 A 17-Nov-11

PTJ2030 Piiles fabrication start 0 02-Jul-11 15-Apr-11 A

PTJ10380 Piiles fabrication finish 0 17-Dec-11 17-Nov-11

AT LEG A1AT LEG A1 39 02-Jul-11 31-Aug-11 15-Apr-11 A 28-Jul-11

PTJ10420 Automatic welding 6 joints 24 06-Jul-11 02-Aug-11 24-Apr-11 A 11-Jun-11 A

PTJ10430 back weld manual 6 joints 16 16-Jul-11 02-Aug-11 02-May-11 A 12-Jun-11 A

PTJ10390 Manual fitup & welding 6 joints 23 02-Jul-11 28-Jul-11 15-Apr-11 A 06-Jul-11

PTJ10410 Welding beads (41 joints) 10 03-Aug-11 14-Aug-11 04-May-11 A 19-Jul-11

PTJ10400 Fitup & welding for manual joint (2 joints) 10 20-Aug-11 31-Aug-11 17-Jul-11 28-Jul-11

AT LEG A2AT LEG A2 61 02-Jul-11 04-Oct-11 25-Jun-11 05-Sep-11

PTJ10440 Manual fitup & welding automatic 6 joints 24 02-Jul-11 28-Jul-11 25-Jun-11 21-Jul-11

PTJ10460 back weld manual 6 joints 16 18-Aug-11 06-Sep-11 19-Jul-11 07-Aug-11

PTJ10450 Automatic welding 6 joints 24 10-Aug-11 07-Sep-11 11-Jul-11 08-Aug-11

PTJ10480 Welding beads (41 joints) 10 08-Sep-11 19-Sep-11 08-Aug-11 20-Aug-11

PTJ10470 Fitup & welding for manual joint (2 joints) 10 24-Sep-11 04-Oct-11 23-Aug-11 05-Sep-11

AT LEG B1AT LEG B1 87 02-Jul-11 12-Nov-11 02-May-11 A 13-Oct-11

PTJ10490 Manual fitup & welding automatic 6 joints 23 02-Jul-11 28-Jul-11 02-May-11 A 14-Jul-11

PTJ10500 Automatic welding 6 joints 24 15-Sep-11 13-Oct-11 15-Aug-11 13-Sep-11

PTJ10510 back weld manual 6 joints 16 26-Sep-11 15-Oct-11 25-Aug-11 14-Sep-11

PTJ10530 Welding beads (41 joints) 10 15-Oct-11 25-Oct-11 06-Jun-11 A 22-Sep-11

PTJ10520 Fitup & welding for manual joint (2 joints) 10 01-Nov-11 12-Nov-11 01-Oct-11 13-Oct-11

AT LEG B2AT LEG B2 123 02-Jul-11 17-Dec-11 25-Jun-11 17-Nov-11

PTJ10540 Manual fitup & welding automatic 6 joints 24 02-Jul-11 28-Jul-11 25-Jun-11 21-Jul-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 47 of 64

Page 202: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ10550 Automatic welding 6 joints 24 22-Oct-11 17-Nov-11 20-Sep-11 19-Oct-11

PTJ10560 back weld manual 6 joints 16 01-Nov-11 19-Nov-11 01-Oct-11 20-Oct-11

PTJ10580 Welding beads (41 joints) 10 19-Nov-11 29-Nov-11 19-Oct-11 31-Oct-11

PTJ10570 Fitup & welding for manual joint (2 joints) 10 06-Dec-11 17-Dec-11 06-Nov-11 17-Nov-11

PRE-DRILPRE-DRILLING TEMPLATE 79 16-Jul-11 03-Oct-11 02-Apr-11 A 17-Jul-11

PTD000 Pre-drilling template fabrication start 0 16-Jul-11 02-Apr-11 A

PTJ10810 cutting & assembly of bottom plate 5 16-Jul-11 20-Jul-11 02-Apr-11 A 07-Apr-11 A

PTJ10820 welding & NDT of bottom plate 6 02-Aug-11 08-Aug-11 03-May-11 A 25-May-11 A

PTJ10830 cutting, rolling and assembly of outer frame 6 02-Aug-11 08-Aug-11 03-May-11 A 25-May-11 A

PTJ10900 fabrication of cones 14 16-Jul-11 01-Aug-11 16-Apr-11 A 25-May-11 A

PTJ10840 welding & NDT of outer frame 5 09-Aug-11 14-Aug-11 10-May-11 A 25-Jun-11

PTJ10850 fabrication of beams ( built up section ) 10 15-Aug-11 25-Aug-11 16-May-11 A 25-Jun-11

PTJ10860 installation of beams with bottom frame 5 27-Aug-11 04-Sep-11 14-May-11 A 27-Jun-11

PTJ10870 cutting of conductor pipe 2 05-Sep-11 06-Sep-11 08-May-11 A 28-Jun-11

PTJ10920 fabrication of pad eyes 5 05-Sep-11 10-Sep-11 08-May-11 A 02-Jul-11

PTJ10880 fabrication & installation of shims plates 4 07-Sep-11 11-Sep-11 11-May-11 A 02-Jul-11

PTJ10890 installation of conductor pipe 5 12-Sep-11 17-Sep-11 15-May-11 A 05-Jul-11

PTJ10930 installation of pad eyes 5 11-Sep-11 15-Sep-11 02-Jul-11 07-Jul-11

PTJ10910 installation of cones 7 18-Sep-11 25-Sep-11 21-May-11 A 09-Jul-11

PTJ10940 fabrication of lif ting tool 10 14-Sep-11 25-Sep-11 27-Jun-11 09-Jul-11

PTJ2010 Pre-drilling template fabrication finish 0 03-Oct-11 17-Jul-11

PTJ10950 painting of template 7 26-Sep-11 03-Oct-11 09-Jul-11 17-Jul-11

W.P.5: DECW.P.5: DECK & TSF FABRICATION 271 31-Mar-11 03-May-12 31-Mar-11 A 01-May-12

DECK FABDECK FABRICATION 271 31-Mar-11 03-May-12 31-Mar-11 A 01-May-12

General AGeneral Activities 268 28-May-11 29-Apr-12 03-Apr-11 A 26-Apr-12

PTJ2040 Deck primary structure fabrication start 0 28-May-11 03-Apr-11 A

PTJ2160 Deck secondray structure fabrication start 0 31-Aug-11 19-May-11 A

PTJ1150 Static equipment (by petrojet) 120 10-Aug-11 07-Dec-11 10-Aug-11 07-Dec-11*

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 48 of 64

Page 203: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ1160 Piping & E&I supports (by petrojet) 30 20-Nov-11 20-Dec-11 18-Nov-11 17-Dec-11

PTJ2060 Deck pre-commisioning 40 12-Feb-12 29-Mar-12 11-Feb-12 27-Mar-12

PTJ2065 Crane assembly and erection 20 03-Apr-12 26-Apr-12 19-Mar-12 10-Apr-12

PTJ2220 Deck weighing 1 26-Apr-12 28-Apr-12 11-Apr-12 11-Apr-12

PTJ2090 Deck commisioning 26 29-Mar-12 29-Apr-12 28-Mar-12 26-Apr-12

Deck StruDeck Structure Fabrication 327 31-Mar-11 03-May-12 31-Mar-11 A 17-Apr-12

Deck LegDeck Legs Fabrication 46 31-Mar-11 22-May-11 31-Mar-11 A 31-May-11 A

PTD100 Cutting & Assembly 20 31-Mar-11 25-Apr-11 31-Mar-11 A 27-Apr-11 A

PTD100 Welding & NDT 28 18-Apr-11 22-May-11 19-Apr-11 A 31-May-11 A

Braces BBraces Below Cellar 199 28-May-11 14-Jan-12 25-May-11 A 14-Jan-12

PTJD10 Profiling Template 4 28-May-11 31-May-11 25-May-11 A 27-Jun-11

PTD103 Assembly 6 28-Dec-11 03-Jan-12 28-Dec-11 03-Jan-12

PTD104 Welding & NDT 12 01-Jan-12 14-Jan-12 01-Jan-12 14-Jan-12

Cellar DeCellar Deck Fabrication (+11.000) 145 28-May-11 21-Nov-11 28-Apr-11 A 14-Nov-11

Joints FJoints Fabrication 26 28-May-11 26-Jun-11 28-Apr-11 A 30-Jun-11

PTD10 Cutting & Assembly 16 28-May-11 14-Jun-11 28-Apr-11 A 30-May-11 A

PTD10 Welding & NDT 22 01-Jun-11 26-Jun-11 01-May-11 A 30-Jun-11

Main BeMain Beams Fabrication 70 28-May-11 26-Jul-11 28-Apr-11 A 16-Aug-11

PTD10 Cutting & Assembly 36 28-May-11 07-Jul-11 28-Apr-11 A 06-Jun-11 A

PTD10 Welding & NDT 46 04-Jun-11 26-Jul-11 25-Jun-11 16-Aug-11

SecondSecondary Beams Fabrication 28 31-Aug-11 10-Oct-11 19-May-11 A 02-Oct-11

PTD10 Cutting & Assembly 22 31-Aug-11 25-Sep-11 19-May-11 A 06-Sep-11

PTD11 Welding & NDT 28 07-Sep-11 10-Oct-11 31-Aug-11 02-Oct-11

EmbossEmbossed Plates 36 11-Oct-11 21-Nov-11 03-Oct-11 14-Nov-11

PTD11 Cutting & Assembly 20 11-Oct-11 02-Nov-11 03-Oct-11 26-Oct-11

PTD11 Welding & NDT 24 25-Oct-11 21-Nov-11 18-Oct-11 14-Nov-11

PLAN ATPLAN AT EL. + 9.200 10 31-Aug-11 19-Sep-11 19-May-11 A 13-Sep-11

Main BeMain Beams Fabrication 7 31-Aug-11 07-Sep-11 19-May-11 A 04-Sep-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 49 of 64

Page 204: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTD17 Cutting & Assembly 3 31-Aug-11 03-Sep-11 19-May-11 A 31-Aug-11

PTD17 Welding & NDT 4 04-Sep-11 07-Sep-11 21-May-11 A 04-Sep-11

SecondSecondary Beams Fabrication 7 08-Sep-11 13-Sep-11 19-May-11 A 07-Sep-11

PTD17 Cutting & Assembly 2 08-Sep-11 10-Sep-11 19-May-11 A 04-Sep-11

PTD17 Welding & NDT 3 11-Sep-11 13-Sep-11 04-Sep-11 07-Sep-11

GRATINGRATING 5 14-Sep-11 19-Sep-11 07-Sep-11 13-Sep-11

PTD17 Cutting & Assembly 2 14-Sep-11 15-Sep-11 07-Sep-11 10-Sep-11

PTD17 Welding & NDT 3 17-Sep-11 19-Sep-11 10-Sep-11 13-Sep-11

PLAN ATPLAN AT EL. + 9.700 25 31-Aug-11 13-Oct-11 19-May-11 A 01-Oct-11

Main BeMain Beams Fabrication 10 31-Aug-11 20-Sep-11 19-May-11 A 12-Sep-11

PTD16 Cutting & Assembly 8 31-Aug-11 08-Sep-11 19-May-11 A 31-Aug-11

PTD16 Welding & NDT 10 10-Sep-11 20-Sep-11 31-Aug-11 12-Sep-11

SecondSecondary Beams Fabrication 8 21-Sep-11 02-Oct-11 18-Jun-11 A 20-Sep-11

PTD16 Cutting & Assembly 4 21-Sep-11 25-Sep-11 18-Jun-11 A 13-Sep-11

PTD16 Welding & NDT 6 26-Sep-11 02-Oct-11 13-Sep-11 20-Sep-11

GRATINGRATING 9 03-Oct-11 13-Oct-11 20-Sep-11 01-Oct-11

PTD16 Cutting & Assembly 4 03-Oct-11 08-Oct-11 20-Sep-11 25-Sep-11

PTD16 Welding & NDT 5 09-Oct-11 13-Oct-11 25-Sep-11 01-Oct-11

WELL HWELL HEAD MEZZANINE AT (+ 16.000) 55 31-Aug-11 03-Nov-11 31-Aug-11 03-Nov-11

Joints FJoints Fabrication 11 31-Aug-11 12-Sep-11 31-Aug-11 12-Sep-11

PTD15 Cutting & Assembly 5 31-Aug-11 05-Sep-11 31-Aug-11 05-Sep-11

PTD15 Welding & NDT 6 06-Sep-11 12-Sep-11 06-Sep-11 12-Sep-11

Main BeMain Beams Fabrication 21 13-Sep-11 08-Oct-11 13-Sep-11 08-Oct-11

PTD15 Cutting & Assembly 9 13-Sep-11 22-Sep-11 13-Sep-11 22-Sep-11

PTD15 Welding & NDT 12 24-Sep-11 08-Oct-11 24-Sep-11 08-Oct-11

SecondSecondary Beams Fabrication 12 09-Oct-11 22-Oct-11 09-Oct-11 22-Oct-11

PTD15 Cutting & Assembly 5 09-Oct-11 13-Oct-11 09-Oct-11 13-Oct-11

PTD15 Welding & NDT 7 15-Oct-11 22-Oct-11 15-Oct-11 22-Oct-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 50 of 64

Page 205: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

GRATINGRATING 11 23-Oct-11 03-Nov-11 23-Oct-11 03-Nov-11

PTD15 Cutting & Assembly 5 23-Oct-11 27-Oct-11 23-Oct-11 27-Oct-11

PTD16 Welding & NDT 6 29-Oct-11 03-Nov-11 29-Oct-11 03-Nov-11

Braces &Braces & Legs between Cellar and Main 128 28-May-11 22-Nov-11 25-Jun-11 22-Nov-11

PTD113 Profiling Template 14 28-May-11 12-Jun-11 25-Jun-11 10-Jul-11

PTD114 Assembly 24 02-Oct-11 30-Oct-11 02-Oct-11 30-Oct-11

PTD115 Welding & NDT 32 17-Oct-11 22-Nov-11 17-Oct-11 22-Nov-11

Main DecMain Deck Fabrication (+17.000) 131 28-May-11 05-Nov-11 28-Apr-11 A 29-Oct-11

Joints FJoints Fabrication 46 28-May-11 19-Jul-11 28-Apr-11 A 06-Jul-11

PTD11 Cutting & Assembly 20 28-May-11 19-Jun-11 28-Apr-11 A 31-May-11 A

PTD11 Welding & NDT 26 20-Jun-11 19-Jul-11 07-May-11 A 06-Jul-11

Main BeMain Beams Fabrication 70 30-May-11 16-Aug-11 30-Apr-11 A 18-Aug-11

PTD11 Cutting & Assembly 36 30-May-11 10-Jul-11 30-Apr-11 A 03-Jul-11

PTD11 Welding & NDT 48 22-Jun-11 16-Aug-11 25-Jun-11 18-Aug-11

SecondSecondary Beams Fabrication 26 31-Aug-11 08-Oct-11 21-May-11 A 29-Sep-11

PTD12 Cutting & Assembly 20 31-Aug-11 22-Sep-11 21-May-11 A 12-Sep-11

PTD12 Welding & NDT 26 07-Sep-11 08-Oct-11 31-Aug-11 29-Sep-11

EmbossEmbossed Plates 37 22-Sep-11 05-Nov-11 15-Sep-11 29-Oct-11

PTD12 Cutting & Assembly 20 22-Sep-11 16-Oct-11 15-Sep-11 09-Oct-11

PTD12 Welding & NDT 24 09-Oct-11 05-Nov-11 01-Oct-11 29-Oct-11

Braces &Braces & Legs Above Main 185 28-May-11 28-Jan-12 25-Jun-11 28-Jan-12

PTD124 Profiling Template 8 28-May-11 05-Jun-11 25-Jun-11 03-Jul-11

PTD125 Assembly 8 15-Jan-12 23-Jan-12 15-Jan-12 23-Jan-12

PTD126 Welding & NDT 10 17-Jan-12 28-Jan-12 17-Jan-12 28-Jan-12

Braces BBraces Below Heli Deck 164 28-May-11 12-Dec-11 25-May-11 A 17-Nov-11

PTD127 Profiling Template 22 28-May-11 21-Jun-11 25-May-11 A 26-Jun-11

PTD128 Assembly 40 16-Oct-11 30-Nov-11 13-Jun-11 A 12-Oct-11

PTD129 Welding & NDT 35 02-Nov-11 12-Dec-11 09-Oct-11 17-Nov-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 51 of 64

Page 206: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Heli DecHeli Deck Fabrication (+29.125) 90 07-Aug-11 12-Dec-11 07-May-11 A 21-Nov-11

Joints FJoints Fabrication 24 07-Aug-11 06-Sep-11 07-May-11 A 22-Aug-11

PTD13 Cutting & Assembly 8 07-Aug-11 15-Aug-11 07-May-11 A 14-Jun-11 A

PTD13 Welding & NDT 12 23-Aug-11 06-Sep-11 18-Jun-11 A 22-Aug-11

Main BeMain Beams Fabrication 24 16-Aug-11 20-Sep-11 16-May-11 A 06-Sep-11

PTD13 Cutting & Assembly 14 16-Aug-11 04-Sep-11 16-May-11 A 23-Jun-11 A

PTD13 Welding & NDT 24 23-Aug-11 20-Sep-11 09-Aug-11 06-Sep-11

SecondSecondary Beams Fabrication 32 31-Aug-11 15-Oct-11 21-May-11 A 08-Oct-11

PTD13 Cutting & Assembly 24 31-Aug-11 27-Sep-11 21-May-11 A 13-Sep-11

PTD13 Welding & NDT 32 07-Sep-11 15-Oct-11 31-Aug-11 08-Oct-11

CoverinCovering Plates 29 10-Oct-11 12-Nov-11 02-Oct-11 05-Nov-11

PTD13 Cutting & Assembly 18 10-Oct-11 30-Oct-11 02-Oct-11 23-Oct-11

PTD13 Welding & NDT 24 16-Oct-11 12-Nov-11 09-Oct-11 05-Nov-11

GutterGutter 14 13-Nov-11 28-Nov-11 06-Nov-11 21-Nov-11

PTD13 Cutting & Assembly 6 13-Nov-11 19-Nov-11 06-Nov-11 12-Nov-11

PTD13 Welding & NDT 8 20-Nov-11 28-Nov-11 13-Nov-11 21-Nov-11

LandingLanding Area 14 13-Nov-11 12-Dec-11 06-Nov-11 21-Nov-11

PTD14 Cutting & Assembly 6 13-Nov-11 19-Nov-11 06-Nov-11 12-Nov-11

PTD14 Welding & NDT 8 04-Dec-11 12-Dec-11 13-Nov-11 21-Nov-11

MisellaneMisellaneuos 153 10-Nov-11 03-May-12 23-Oct-11 17-Apr-12

InstallatInstallation 117 04-Dec-11 03-May-12 04-Dec-11 17-Apr-12

PTMD Monorail Beam 10 04-Dec-11 14-Dec-11 04-Dec-11 14-Dec-11

PTMD Safety Net 16 27-Dec-11 14-Jan-12 06-Dec-11 24-Dec-11

PTMD Crane Boom Rest 2 15-Jan-12 16-Jan-12 15-Jan-12 16-Jan-12

PTMD Name Plate 4 15-Jan-12 18-Jan-12 15-Jan-12 18-Jan-12

PTMD Handrails & Cups 24 25-Dec-11 21-Jan-12 25-Dec-11 21-Jan-12

PTMD Hatches 8 15-Jan-12 23-Jan-12 15-Jan-12 23-Jan-12

PTMD Fire Wall 12 15-Jan-12 28-Jan-12 15-Jan-12 28-Jan-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 52 of 64

Page 207: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTMD Stairs & Walkways 15 15-Jan-12 31-Jan-12 15-Jan-12 31-Jan-12

PTMD Pad Eyes 5 28-Apr-12 03-May-12 12-Apr-12 17-Apr-12

FabricaFabrication 148 10-Nov-11 28-Apr-12 23-Oct-11 11-Apr-12

PTMD Safety Net 28 13-Nov-11 14-Dec-11 23-Oct-11 23-Nov-11

PTMD Monorail Beam 10 22-Nov-11 03-Dec-11 22-Nov-11 03-Dec-11

PTMD Handrails & Cups 24 10-Nov-11 07-Dec-11 10-Nov-11 07-Dec-11

PTMD Name Plate 8 25-Dec-11 02-Jan-12 25-Dec-11 02-Jan-12

PTMD Hatches 20 14-Dec-11 05-Jan-12 14-Dec-11 05-Jan-12

PTMD Crane Boom Rest 6 31-Dec-11 05-Jan-12 31-Dec-11 05-Jan-12

PTMD Fire Wall 18 17-Dec-11 05-Jan-12 17-Dec-11 05-Jan-12

PTMD Stairs & Walkways 24 26-Dec-11 22-Jan-12 26-Dec-11 22-Jan-12

PTMD Pad Eyes 6 21-Apr-12 28-Apr-12 05-Apr-12 11-Apr-12

Deck FlaDeck Flare 68 29-Jan-12 17-Apr-12 28-Jan-12 15-Apr-12

PTD150 Cutting & Assembly 20 29-Jan-12 21-Feb-12 28-Jan-12 19-Feb-12

PTD151 Welding & NDT 32 21-Feb-12 29-Mar-12 20-Feb-12 27-Mar-12

PTD152 Trial Fit 2 15-Apr-12 17-Apr-12 14-Apr-12 15-Apr-12

Deck AssDeck Assembly 173 28-May-11 14-Jan-12 25-Jun-11 14-Jan-12

Skid BeSkid Beams & Shoes Preparation 24 28-May-11 23-Jun-11 25-Jun-11 21-Jul-11

PTD14 Skid Beams & Shoes Preparation 24 28-May-11 23-Jun-11 25-Jun-11 21-Jul-11

Lifting DLifting Deck Legs Over Skid Beams & Skid Shoes 2 08-Dec-11 10-Dec-11 08-Dec-11 10-Dec-11

PTD14 Lifting Deck Legs Over Skid Beams & Skid Shoes 2 08-Dec-11 10-Dec-11 08-Dec-11 10-Dec-11

Lifting CLifting Cellar Deck Over Deck Legs 15 11-Dec-11 27-Dec-11 11-Dec-11 27-Dec-11

PTD14 Lifting 1 11-Dec-11 11-Dec-11 11-Dec-11 11-Dec-11

PTD14 Assembly 6 12-Dec-11 18-Dec-11 12-Dec-11 18-Dec-11

PTD14 Welding & NDT 8 19-Dec-11 27-Dec-11 19-Dec-11 27-Dec-11

lifting oflifting of plan at + 9.2 4 28-Dec-11 01-Jan-12 28-Dec-11 01-Jan-12

PTD17 Lifting 1 28-Dec-11 28-Dec-11 28-Dec-11 28-Dec-11

PTD17 Assembly 1 29-Dec-11 29-Dec-11 29-Dec-11 29-Dec-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 53 of 64

Page 208: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTD17 Welding & NDT 2 31-Dec-11 01-Jan-12 31-Dec-11 01-Jan-12

lifting oflifting of plan at + 9.7 4 28-Dec-11 01-Jan-12 28-Dec-11 01-Jan-12

PTD16 Lifting 1 28-Dec-11 28-Dec-11 28-Dec-11 28-Dec-11

PTD16 Assembly 1 29-Dec-11 29-Dec-11 29-Dec-11 29-Dec-11

PTD16 Welding & NDT 2 31-Dec-11 01-Jan-12 31-Dec-11 01-Jan-12

lifting oflifting of mezzanine deck at + 16 4 28-Dec-11 01-Jan-12 28-Dec-11 01-Jan-12

PTD17 Lifting 1 28-Dec-11 28-Dec-11 28-Dec-11 28-Dec-11

PTD18 Assembly 1 29-Dec-11 29-Dec-11 29-Dec-11 29-Dec-11

PTD18 Welding & NDT 2 31-Dec-11 01-Jan-12 31-Dec-11 01-Jan-12

Lifting MLifting Main Deck Over cellar Deck 11 02-Jan-12 14-Jan-12 02-Jan-12 14-Jan-12

PTD14 Lifting 1 02-Jan-12 02-Jan-12 02-Jan-12 02-Jan-12

PTD14 Assembly 5 03-Jan-12 08-Jan-12 03-Jan-12 08-Jan-12

PTD14 Welding & NDT 7 07-Jan-12 14-Jan-12 07-Jan-12 14-Jan-12

AtmosphrAtmosphric Painting 181 20-Sep-11 15-Apr-12 13-Sep-11 12-Apr-12

PT1110 Plane at + 9.2 5 20-Sep-11 25-Sep-11 13-Sep-11 19-Sep-11

PT1120 Plane at + 9.7 5 15-Oct-11 19-Oct-11 01-Oct-11 08-Oct-11

PT1130 Wellhead mezzanine 10 05-Nov-11 15-Nov-11 05-Nov-11 15-Nov-11

PT1050 Heli Deck & Braces Below Heli 12 13-Dec-11 26-Dec-11 22-Nov-11 05-Dec-11

PT1010 Deck Legs 6 01-Dec-11 07-Dec-11 01-Dec-11 07-Dec-11

PT1020 Braces Below Cellar 5 05-Dec-11 10-Dec-11 05-Dec-11 10-Dec-11

PT1030 Cellar Deck & Braces Above Cellar 15 23-Nov-11 10-Dec-11 23-Nov-11 10-Dec-11

PT1080 Piping Support 9 06-Dec-11 17-Dec-11 06-Dec-11 17-Dec-11

PT1040 Main Deck 15 15-Dec-11 01-Jan-12 15-Dec-11 01-Jan-12

PT1045 Braces Above Main 5 09-Jan-12 14-Jan-12 09-Jan-12 14-Jan-12

PT1090 Cable Trays Supports 10 15-Jan-12 26-Jan-12 16-Jan-12 26-Jan-12

PT1060 Miscellaneous (Stairs,H/R,...etc) 14 12-Jan-12 28-Jan-12 12-Jan-12 28-Jan-12

PT1070 Piping painting 14 19-Jan-12 05-Feb-12 19-Jan-12 04-Feb-12

PT1100 Deck Flare 14 29-Mar-12 15-Apr-12 28-Mar-12 12-Apr-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 54 of 64

Page 209: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Anti Skid PAnti Skid Painting 7 25-Apr-12 03-May-12 24-Apr-12 01-May-12

PT1000 Heli Deck 7 25-Apr-12 03-May-12 24-Apr-12 01-May-12

E & IE & I 80 16-Dec-11 11-Mar-12 21-Dec-11 09-Mar-12

PTJ2080 E & I Work start 0 16-Dec-11 21-Dec-11

PTJ2100 E & I Work finish 0 11-Mar-12 09-Mar-12

E&I (onshE&I (onshore) 80 16-Dec-11 11-Mar-12 21-Dec-11 09-Mar-12

ElectricalElectrical 72 16-Dec-11 02-Mar-12 21-Dec-11 01-Mar-12

Cable TCable Trays Supports 51 20-Dec-11 09-Feb-12 21-Dec-11 09-Feb-12

E&I100 Fabrication 26 20-Dec-11 15-Jan-12 21-Dec-11 15-Jan-12

E&I101 Installation 14 26-Jan-12 09-Feb-12 27-Jan-12 09-Feb-12

Cable TCable Trays 26 24-Jan-12 19-Feb-12 24-Jan-12 18-Feb-12

E&I102 Installation 26 24-Jan-12 19-Feb-12 24-Jan-12 18-Feb-12

ConduitConduit Activities 38 16-Dec-11 23-Jan-12 21-Dec-11 27-Jan-12

E&I103 Installation 38 16-Dec-11 23-Jan-12 21-Dec-11 27-Jan-12

LightingLighting Activities 25 31-Dec-11 25-Jan-12 05-Jan-12 29-Jan-12

E&I104 Lighting Activities 25 31-Dec-11 25-Jan-12 05-Jan-12 29-Jan-12

NavigatNavigation Aids 15 16-Dec-11 31-Dec-11 21-Dec-11 04-Jan-12

E&I105 Navigation Aids 15 16-Dec-11 31-Dec-11 21-Dec-11 04-Jan-12

EarthingEarthing Activities 14 17-Feb-12 02-Mar-12 17-Feb-12 01-Mar-12

E&I106 Earthing Activities 14 17-Feb-12 02-Mar-12 17-Feb-12 01-Mar-12

Power &Power & Small Equip. Inst. 12 17-Feb-12 29-Feb-12 17-Feb-12 28-Feb-12

E&I107 Power & Small Equip. Inst. 12 17-Feb-12 29-Feb-12 17-Feb-12 28-Feb-12

Cable LCable Laying & Termination 25 01-Feb-12 26-Feb-12 01-Feb-12 25-Feb-12

E&I108 Cable Laying & Termination 25 01-Feb-12 26-Feb-12 01-Feb-12 25-Feb-12

InstrumeInstrumentation 80 20-Dec-11 11-Mar-12 21-Dec-11 09-Mar-12

Cable TCable Trays Supports 51 20-Dec-11 09-Feb-12 21-Dec-11 09-Feb-12

E&I109 Fabrication 26 20-Dec-11 15-Jan-12 21-Dec-11 15-Jan-12

E&I110 Installation 14 26-Jan-12 09-Feb-12 27-Jan-12 09-Feb-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 55 of 64

Page 210: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Cable TCable Trays 26 24-Jan-12 19-Feb-12 24-Jan-12 18-Feb-12

E&I111 Installation 26 24-Jan-12 19-Feb-12 24-Jan-12 18-Feb-12

Tubing ATubing Activities 20 12-Feb-12 03-Mar-12 11-Feb-12 01-Mar-12

E&I112 Installation 20 12-Feb-12 03-Mar-12 11-Feb-12 01-Mar-12

HCU & HCU & Local Panels Activities 16 20-Feb-12 07-Mar-12 19-Feb-12 05-Mar-12

E&I113 HCU & Local Panels Activities 16 20-Feb-12 07-Mar-12 19-Feb-12 05-Mar-12

Fusible Fusible Plug & ESD Puch Bottons 18 09-Feb-12 27-Feb-12 10-Feb-12 27-Feb-12

E&I114 Fusible Plug & ESD Puch Bottons 18 09-Feb-12 27-Feb-12 10-Feb-12 27-Feb-12

J. Box AJ. Box Activities 20 09-Feb-12 29-Feb-12 10-Feb-12 29-Feb-12

E&I115 J. Box Activities 20 09-Feb-12 29-Feb-12 10-Feb-12 29-Feb-12

InstrumInstrument Installation & Calibration 10 27-Feb-12 08-Mar-12 26-Feb-12 06-Mar-12

E&I116 Instrument Installation & Calibration 10 27-Feb-12 08-Mar-12 26-Feb-12 06-Mar-12

Air Gas Air Gas Header 8 26-Feb-12 05-Mar-12 25-Feb-12 03-Mar-12

E&I117 Air Gas Header 8 26-Feb-12 05-Mar-12 25-Feb-12 03-Mar-12

Cable LCable Laying & Termination 25 14-Feb-12 10-Mar-12 13-Feb-12 08-Mar-12

E&I118 Cable Laying & Termination 25 14-Feb-12 10-Mar-12 13-Feb-12 08-Mar-12

Fire & GFire & Gas activities 8 03-Mar-12 11-Mar-12 02-Mar-12 09-Mar-12

E&I119 Fire & Gas activities 8 03-Mar-12 11-Mar-12 02-Mar-12 09-Mar-12

TelecomTelecommunication System 8 03-Mar-12 11-Mar-12 02-Mar-12 09-Mar-12

E&I120 Telecommunication System 8 03-Mar-12 11-Mar-12 02-Mar-12 09-Mar-12

EQUIPMENEQUIPMENT 72 07-Dec-11 17-Feb-12 07-Dec-11 16-Feb-12

PTJ2070 Equipment installation start 0 23-Dec-11 18-Jan-12

PTJ2130 Equipment installation finish 0 17-Feb-12 16-Feb-12

EquipemeEquipement Installation (onshore) 72 07-Dec-11 17-Feb-12 07-Dec-11 16-Feb-12

TSF1110 Installation of production manifold module on celler deck 4 07-Dec-11 10-Dec-11 07-Dec-11* 10-Dec-11

TSF1100 Installation of E & I module on main deck 4 07-Jan-12 10-Jan-12 07-Jan-12* 10-Jan-12

TSF1090 Equipment Installation on Heli Deck 4 23-Dec-11 27-Dec-11 18-Jan-12 21-Jan-12

TSF1060 Equipment Installation Below Cellar Deck 4 13-Feb-12 17-Feb-12 13-Feb-12 16-Feb-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 56 of 64

Page 211: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

TSF1070 Equipment Installation on Cellar Deck 15 02-Feb-12 17-Feb-12 02-Feb-12 16-Feb-12

TSF1080 Equipment Installation on Main Deck 15 02-Feb-12 17-Feb-12 02-Feb-12 16-Feb-12

PIPINGPIPING 113 20-Nov-11 13-Mar-12 20-Nov-11 11-Mar-12

PTJ2050 Piping & piping support fabrication start 0 20-Nov-11 20-Nov-11

PTJ2110 Piping & piping support erection finish 0 13-Mar-12 11-Mar-12

C.S PipingC.S Piping Fab. & Erec., Valves Erection (onshore) 113 20-Nov-11 13-Mar-12 20-Nov-11 11-Mar-12

TSF1010 Piping Supports Fabrication 22 20-Nov-11 12-Dec-11 20-Nov-11 11-Dec-11

TSF1000 Piping Fabrication 70 20-Nov-11 29-Jan-12 20-Nov-11 28-Jan-12

TSF1020 Piping Erection 35 28-Jan-12 03-Mar-12 27-Jan-12 01-Mar-12

TSF1030 Piping Supports Erection 20 12-Feb-12 03-Mar-12 11-Feb-12 01-Mar-12

TSF1040 Valve Installation 15 17-Feb-12 03-Mar-12 16-Feb-12 01-Mar-12

PTJ2120 Piping hydrotest 21 21-Feb-12 13-Mar-12 20-Feb-12 11-Mar-12

W.P.6: PIPEW.P.6: PIPELINE SPOOLS FABRICATION 44 23-Feb-12 25-Apr-12 23-Feb-12 25-Apr-12

SETH PLESETH PLEM & EXISTING TUNA PLEM 44 23-Feb-12 25-Apr-12 23-Feb-12 25-Apr-12

SPOOL NSPOOL NO. S1 (CLOSING) ( P.L - S2 ) 23 24-Mar-12 25-Apr-12 24-Mar-12 25-Apr-12

BEFOREBEFORE METROLOGY 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

PIPE LIPIPE LINE & BENDS 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

SS690 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 24-Mar-12 26-Mar-12 24-Mar-12 26-Mar-12

SS700 CUTTING & BEVELING BEFORE METROLOGY 3 26-Mar-12 29-Mar-12 26-Mar-12 29-Mar-12

SS710 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 5 29-Mar-12 04-Apr-12 29-Mar-12 04-Apr-12

SS720 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL... 8 04-Apr-12 14-Apr-12 04-Apr-12 14-Apr-12

SS740 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 16-Apr-12 18-Apr-12 16-Apr-12 18-Apr-12

SS730 COATING OF BENDS 6 14-Apr-12 21-Apr-12 14-Apr-12 21-Apr-12

SS750 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 18-Apr-12 21-Apr-12 18-Apr-12 21-Apr-12

SS760 APPLY SHRINKABLE SLEEVE 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

AFTER MAFTER METROLOGY 11 15-Apr-12 25-Apr-12 15-Apr-12 25-Apr-12

SS770 RECEVING METROLOGY 0 15-Apr-12 15-Apr-12

SS780 FIT UP AFTER METROLOGY 3 15-Apr-12 17-Apr-12 15-Apr-12 17-Apr-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 57 of 64

Page 212: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SS790 WELDING & NDT AFTER METROLOGY 4 17-Apr-12 21-Apr-12 17-Apr-12 21-Apr-12

SS800 PIGGING & HYDRO TEST 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

SS810 APPLY SHRINKABLE SLEEVE 1 23-Apr-12 24-Apr-12 23-Apr-12 24-Apr-12

SS820 LIFTING TEST 1 24-Apr-12 25-Apr-12 24-Apr-12 25-Apr-12

SPOOL NSPOOL NO. S2 ( S1 - S3 ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS830 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS840 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS850 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS860 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS880 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

SS870 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS890 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS900 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS910 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS920 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S3 (CLOSING) ( S2 - S4 ) 23 24-Mar-12 25-Apr-12 24-Mar-12 25-Apr-12

BEFOREBEFORE METROLOGY 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

PIPE LIPIPE LINE & BENDS 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

SS930 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 24-Mar-12 26-Mar-12 24-Mar-12 26-Mar-12

SS940 CUTTING & BEVELING BEFORE METROLOGY 3 26-Mar-12 29-Mar-12 26-Mar-12 29-Mar-12

SS950 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 5 29-Mar-12 04-Apr-12 29-Mar-12 04-Apr-12

SS960 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL... 8 04-Apr-12 14-Apr-12 04-Apr-12 14-Apr-12

SS980 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 16-Apr-12 18-Apr-12 16-Apr-12 18-Apr-12

SS970 COATING OF BENDS 6 14-Apr-12 21-Apr-12 14-Apr-12 21-Apr-12

SS990 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 18-Apr-12 21-Apr-12 18-Apr-12 21-Apr-12

SS1000 APPLY SHRINKABLE SLEEVE 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

AFTER MAFTER METROLOGY 11 15-Apr-12 25-Apr-12 15-Apr-12 25-Apr-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 58 of 64

Page 213: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SS1010 RECEVING METROLOGY 0 15-Apr-12 15-Apr-12

SS1020 FIT UP AFTER METROLOGY 3 15-Apr-12 17-Apr-12 15-Apr-12 17-Apr-12

SS1030 WELDING & NDT AFTER METROLOGY 4 17-Apr-12 21-Apr-12 17-Apr-12 21-Apr-12

SS1040 PIGGING & HYDRO TEST 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

SS1050 APPLY SHRINKABLE SLEEVE 1 23-Apr-12 24-Apr-12 23-Apr-12 24-Apr-12

SS1060 LIFTING TEST 1 24-Apr-12 25-Apr-12 24-Apr-12 25-Apr-12

SPOOL NSPOOL NO. S4 ( S4 - SETH PLEM ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS1070 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS1080 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS1090 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS1100 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS1120 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

SS1110 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS1130 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS1140 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS1150 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS1160 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S5 ( SETH PLEM - S6 ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS1170 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS1180 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS1190 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS1200 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS1220 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

SS1210 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS1230 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS1240 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 59 of 64

Page 214: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SS1250 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS1260 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S6 (CLOSING) ( S5 - TUNA PLEM ) 23 24-Mar-12 25-Apr-12 24-Mar-12 25-Apr-12

BEFOREBEFORE METROLOGY 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

PIPE LIPIPE LINE & BENDS 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

SS1270 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 24-Mar-12 26-Mar-12 24-Mar-12 26-Mar-12

SS1280 CUTTING & BEVELING BEFORE METROLOGY 3 26-Mar-12 29-Mar-12 26-Mar-12 29-Mar-12

SS1290 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 5 29-Mar-12 04-Apr-12 29-Mar-12 04-Apr-12

SS1300 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL... 8 04-Apr-12 14-Apr-12 04-Apr-12 14-Apr-12

SS1320 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 16-Apr-12 18-Apr-12 16-Apr-12 18-Apr-12

SS1310 COATING OF BENDS 6 14-Apr-12 21-Apr-12 14-Apr-12 21-Apr-12

SS1330 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 18-Apr-12 21-Apr-12 18-Apr-12 21-Apr-12

SS1340 APPLY SHRINKABLE SLEEVE 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

AFTER MAFTER METROLOGY 11 15-Apr-12 25-Apr-12 15-Apr-12 25-Apr-12

SS1350 RECEVING METROLOGY 0 15-Apr-12 15-Apr-12

SS1360 FIT UP AFTER METROLOGY 3 15-Apr-12 17-Apr-12 15-Apr-12 17-Apr-12

SS1370 WELDING & NDT AFTER METROLOGY 4 17-Apr-12 21-Apr-12 17-Apr-12 21-Apr-12

SS1380 PIGGING & HYDRO TEST 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

SS1390 APPLY SHRINKABLE SLEEVE 1 23-Apr-12 24-Apr-12 23-Apr-12 24-Apr-12

SS1400 LIFTING TEST 1 24-Apr-12 25-Apr-12 24-Apr-12 25-Apr-12

SETH P/F SETH P/F & NEW SSIV 44 23-Feb-12 25-Apr-12 23-Feb-12 25-Apr-12

SPOOL NSPOOL NO. S3 ( SSIV -S4 ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS250 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS260 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS270 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS280 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS300 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 60 of 64

Page 215: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SS290 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS310 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS320 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS330 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS340 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S2 ( S1 - SSIV ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS150 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS160 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS170 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS180 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS200 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

SS190 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS210 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS220 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS230 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS240 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S4 ( S3 - S5 ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS350 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS360 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS370 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS380 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS400 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

SS390 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS410 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS420 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS430 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 61 of 64

Page 216: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SS440 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S5 ( S4 - S6 ) 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

PIPE LINPIPE LINE & BENDS 21 23-Feb-12 24-Mar-12 23-Feb-12 24-Mar-12

SS450 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 23-Feb-12 25-Feb-12 23-Feb-12 25-Feb-12

SS460 CUTTING & BEVELING 3 26-Feb-12 28-Feb-12 26-Feb-12 28-Feb-12

SS470 FIT UP FOR LINE PIPE & BENDS 5 29-Feb-12 05-Mar-12 29-Feb-12 05-Mar-12

SS480 WELDING & NDT FOR LINE PIPE & BENDS 8 06-Mar-12 14-Mar-12 06-Mar-12 14-Mar-12

SS500 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 18-Mar-12 19-Mar-12 18-Mar-12 19-Mar-12

SS490 COATING OF BENDS 6 15-Mar-12 21-Mar-12 15-Mar-12 21-Mar-12

SS510 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 20-Mar-12 21-Mar-12 20-Mar-12 21-Mar-12

SS520 APPLY SHRINKABLE SLEEVE 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS530 PIGGING & HYDRO TEST 2 22-Mar-12 23-Mar-12 22-Mar-12 23-Mar-12

SS540 LIFTING TEST 1 24-Mar-12 24-Mar-12 24-Mar-12 24-Mar-12

SPOOL NSPOOL NO. S1 (CLOSING) ( P.L - SETH PLEM ) 23 24-Mar-12 25-Apr-12 24-Mar-12 25-Apr-12

BEFOREBEFORE METROLOGY 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

PIPE LIPIPE LINE & BENDS 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

SS 10 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 24-Mar-12 26-Mar-12 24-Mar-12 26-Mar-12

SS020 CUTTING & BEVELING BEFORE METROLOGY 3 26-Mar-12 29-Mar-12 26-Mar-12 29-Mar-12

SS030 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 5 29-Mar-12 04-Apr-12 29-Mar-12 04-Apr-12

SS040 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL... 8 04-Apr-12 14-Apr-12 04-Apr-12 14-Apr-12

SS060 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 16-Apr-12 18-Apr-12 16-Apr-12 18-Apr-12

SS050 COATING OF BENDS 6 14-Apr-12 21-Apr-12 14-Apr-12 21-Apr-12

SS070 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 18-Apr-12 21-Apr-12 18-Apr-12 21-Apr-12

SS080 APPLY SHRINKABLE SLEEVE 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

AFTER MAFTER METROLOGY 11 15-Apr-12 25-Apr-12 15-Apr-12 25-Apr-12

SS090 RECEVING METROLOGY 0 15-Apr-12 15-Apr-12

SS100 FIT UP AFTER METROLOGY 3 15-Apr-12 17-Apr-12 15-Apr-12 17-Apr-12

SS110 WELDING & NDT AFTER METROLOGY 4 17-Apr-12 21-Apr-12 17-Apr-12 21-Apr-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 62 of 64

Page 217: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SS120 PIGGING & HYDRO TEST 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

SS130 APPLY SHRINKABLE SLEEVE 1 23-Apr-12 24-Apr-12 23-Apr-12 24-Apr-12

SS140 LIFTING TEST 1 24-Apr-12 25-Apr-12 24-Apr-12 25-Apr-12

SPOOL NSPOOL NO. S6 (CLOSING) ( S5 - SETH P/F ) 23 24-Mar-12 25-Apr-12 24-Mar-12 25-Apr-12

BEFOREBEFORE METROLOGY 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

PIPE LIPIPE LINE & BENDS 21 24-Mar-12 23-Apr-12 24-Mar-12 23-Apr-12

SS550 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS 2 24-Mar-12 26-Mar-12 24-Mar-12 26-Mar-12

SS560 CUTTING & BEVELING BEFORE METROLOGY 3 26-Mar-12 29-Mar-12 26-Mar-12 29-Mar-12

SS570 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY 5 29-Mar-12 04-Apr-12 29-Mar-12 04-Apr-12

SS580 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL... 8 04-Apr-12 14-Apr-12 04-Apr-12 14-Apr-12

SS600 FIT UP FLANGES AND FITTING WITH LINE PIPE 2 16-Apr-12 18-Apr-12 16-Apr-12 18-Apr-12

SS590 COATING OF BENDS 6 14-Apr-12 21-Apr-12 14-Apr-12 21-Apr-12

SS610 WELDING & NDT FOR FLANGES WITH LINE PIPE 2 18-Apr-12 21-Apr-12 18-Apr-12 21-Apr-12

SS620 APPLY SHRINKABLE SLEEVE 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

AFTER MAFTER METROLOGY 11 15-Apr-12 25-Apr-12 15-Apr-12 25-Apr-12

SS630 RECEVING METROLOGY 0 15-Apr-12 15-Apr-12

SS640 FIT UP AFTER METROLOGY 3 15-Apr-12 17-Apr-12 15-Apr-12 17-Apr-12

SS650 WELDING & NDT AFTER METROLOGY 4 17-Apr-12 21-Apr-12 17-Apr-12 21-Apr-12

SS660 PIGGING & HYDRO TEST 2 21-Apr-12 23-Apr-12 21-Apr-12 23-Apr-12

SS670 APPLY SHRINKABLE SLEEVE 1 23-Apr-12 24-Apr-12 23-Apr-12 24-Apr-12

SS680 LIFTING TEST 1 24-Apr-12 25-Apr-12 24-Apr-12 25-Apr-12

W.P.7: CERW.P.7: CERTIFICATION 61 21-Feb-12 29-Mar-12 26-Jan-12 27-Mar-12

PTJ1130 Jacket completion certificate 0 21-Feb-12 26-Jan-12

PTJ1090 Deck completion certif icate 0 29-Mar-12 27-Mar-12

W.P.8: LOAW.P.8: LOAD-OUT, SEA-FASTENING, TRANSPORTATION & INSTALLATION 204 18-Oct-11 10-May-12 18-Oct-11 08-May-12

PTJ1070 Pre-drilling template seafastening and load out 7 18-Oct-11 24-Oct-11 18-Oct-11 24-Oct-11*

PTJ1050 Jacket & Piles seafastening and load out 15 17-Mar-12 31-Mar-12 17-Mar-12 31-Mar-12*

PTJ1170 Sub Sea Spools Load out first trip 7 25-Mar-12 31-Mar-12 25-Mar-12 31-Mar-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 63 of 64

Page 218: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ1180 Sub Sea Spools Load out second trip for closing spools 7 25-Apr-12 02-May-12 25-Apr-12 02-May-12*

PTJ1060 Deck seafastening and load out 7 03-May-12 10-May-12 02-May-12 08-May-12*

W.P.9: OFFW.P.9: OFFSHORE HOOK-UP, COMMISSIONING AND ASSISTANCE TO STA... 31 17-May-12 17-Jun-12 16-May-12 15-Jun-12

PTJ1140 TSF Offshore hook-up activities 31 17-May-12 17-Jun-12 16-May-12 15-Jun-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

UPDATED SCHEDULE AS OF 25-JUNE-11

Page 64 of 64

Page 219: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 28 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.4. CRITICAL AND NEAR CRITICAL ACTIVITIES

Page 220: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

SETH OFFSSETH OFFSHORE EPC PROJECT UPDATED SCHEDULE 311 11-May-11 31-Jul-12 26-Apr-11 A 31-Jul-12

CONTRACTCONTRACTUAL MILESTONES 122 01-Apr-12 31-Jul-12 31-Mar-12 31-Jul-12

ART6.3 Deck Mechanical Completion 0 01-Apr-12 31-Mar-12*

ART6.4.1 Deck and Flare Ready for Load out 0 01-May-12 30-Apr-12*

A2 Project completion 0 31-Jul-12 31-Jul-12*

ENPPIENPPI 199 11-May-11 05-Apr-12 26-Apr-11 A 21-Feb-12

W.P.2: ENGW.P.2: ENGINEERING 164 11-May-11 21-Dec-11 26-Apr-11 A 02-Jan-12

PROCESSPROCESS 163 11-May-11 21-Dec-11 26-Apr-11 A 02-Jan-12

DrawingsDrawings 7 05-Sep-11 14-Sep-11 05-Sep-11 13-Sep-11

A1570 P&ID's IFC 7 05-Sep-11 14-Sep-11 05-Sep-11 13-Sep-11

TER'sTER's 25 11-May-11 14-Jun-11 26-Apr-11 A 05-Jul-11

A2610 Fire protection system TER 25 11-May-11 14-Jun-11 26-Apr-11 A 05-Jul-11

Vendor prVendor prints review 100 24-Jul-11 21-Dec-11 03-Aug-11 02-Jan-12

A2730 Fire protection system Vendor prints review 100 24-Jul-11 21-Dec-11 03-Aug-11 02-Jan-12

PIPINGPIPING 42 14-Sep-11 20-Nov-11 14-Sep-11 17-Nov-11

DrawingsDrawings 42 14-Sep-11 20-Nov-11 14-Sep-11 17-Nov-11

A1670 Plot Plan IFC 5 14-Sep-11 21-Sep-11 14-Sep-11 20-Sep-11

A1680 ISO's 10 31-Oct-11 20-Nov-11 31-Oct-11 17-Nov-11

INSTRUMEINSTRUMENTATION 144 18-May-11 24-Nov-11 26-Apr-11 A 13-Dec-11

TER'sTER's 20 18-May-11 15-Jun-11 26-Apr-11 A 05-Jul-11

A3450 Choke valves TER 20 18-May-11 15-Jun-11 26-Apr-11 A 05-Jul-11

Vendor prVendor prints review 80 25-Jul-11 24-Nov-11 11-Aug-11 13-Dec-11

A3610 Choke valves Vendor prints review 80 25-Jul-11 24-Nov-11 11-Aug-11 13-Dec-11

MECHANICMECHANICAL 81 26-Jul-11 28-Nov-11 14-Aug-11 14-Dec-11

Vendor prVendor prints review 81 26-Jul-11 28-Nov-11 14-Aug-11 14-Dec-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11

Page 1 of 5

Remaining Level of Effort

Primary Baseline

Actual Work

Remaining...

Critical Re...

Baseline ...

Start Date:28-Mar-11Finish Date:31-Jul-12Data Date:25-Jun-11

By: Haytham A.RahmanDate Revision Checked Approved

25-May-11 Rev.0 A.Maghawry A.Fathy

Page 221: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

A6330 Receiving final weights and dimensions for mechanical equipment 0 20-Sep-11 21-Sep-11

A3770 Service water pump Vendor prints review 80 26-Jul-11 28-Nov-11 14-Aug-11 14-Dec-11

OFFSHOROFFSHORE 15 24-Oct-11 20-Nov-11 24-Oct-11 17-Nov-11

ModelModel 15 24-Oct-11 20-Nov-11 24-Oct-11 17-Nov-11

A5360 Finalize PDS Modeling For Topsides based on Tecnomare IFC dw... 15 24-Oct-11 20-Nov-11 24-Oct-11 17-Nov-11

W.P.3: PROW.P.3: PROCUREMENT SERVICES & MATERIAL SUPPLY 164 19-Jun-11 05-Apr-12 25-Jun-11 21-Feb-12

EQUIPMENEQUIPMENT 148 19-Jun-11 12-Feb-12 06-Jul-11 11-Feb-12

ENPPI LOENPPI LONG LEAD ITEMS (Cranes ,Chemical unjec.,Fire protec. , Survival M... 148 19-Jun-11 12-Feb-12 06-Jul-11 11-Feb-12

PURCHAPURCHASING 9 19-Jun-11 07-Jul-11 06-Jul-11 18-Jul-11

A5330 Fire protection system Issue Fax of commitment 9 19-Jun-11 07-Jul-11 06-Jul-11 18-Jul-11

FABRICAFABRICATION 170 08-Jul-11 03-Jan-12 19-Jul-11 04-Jan-12

A3930 Fire protection system Fabrication up to release for shipment 170 08-Jul-11 03-Jan-12 19-Jul-11 04-Jan-12

SHIPPINSHIPPING 45 29-Dec-11 12-Feb-12 29-Dec-11 11-Feb-12

A3990 Fire protection system Shipping 21 04-Jan-12 24-Jan-12 08-Jan-12 28-Jan-12

A2120 Custom clearance & inland transportation (Multi phase f low ,Che... 45 29-Dec-11 12-Feb-12 29-Dec-11 11-Feb-12

A5190 Fire protection system Custom clearance & inland transportation 14 25-Jan-12 07-Feb-12 29-Jan-12 11-Feb-12

E&I BULKE&I BULK 156 19-Jun-11 05-Apr-12 06-Jul-11 21-Feb-12

PURCHAPURCHASING 15 19-Jun-11 10-Jul-11 06-Jul-11 26-Jul-11

A5040 Choke valves Issue Fax of commitments 15 19-Jun-11 10-Jul-11 06-Jul-11 26-Jul-11

FABRICAFABRICATION 210 10-Jul-11 05-Apr-12 27-Jul-11 21-Feb-12

A4500 Choke valves Fabrication up to release for shipment 210 10-Jul-11 05-Apr-12 27-Jul-11 21-Feb-12

PIPING BUPIPING BULK 200 20-Jun-11 06-Jan-12 25-Jun-11 10-Jan-12

FABRICAFABRICATION 200 20-Jun-11 06-Jan-12 25-Jun-11 10-Jan-12

A1950 piping Bulk Fabrication up to release for shipment 200 20-Jun-11 06-Jan-12 25-Jun-11 10-Jan-12

SHIPPINGSHIPPING 35 10-Oct-11 14-Nov-11 10-Oct-11 13-Nov-11

A1960 1st batch of the piping Bulk Shipping 21 10-Oct-11 31-Oct-11 10-Oct-11 30-Oct-11

A1970 1st batch of the piping Bulk Custom clearance & inland transport... 14 31-Oct-11 14-Nov-11 31-Oct-11 13-Nov-11

TECNOMARTECNOMARE 22 21-Sep-11 24-Oct-11 21-Sep-11 23-Oct-11

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11

Page 2 of 5

Page 222: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

TECNOMARTECNOMARE DRIVING MILESTONES 0 21-Sep-11 21-Sep-11 21-Sep-11 21-Sep-11

STRUCTUSTRUCTURAL 0 21-Sep-11 21-Sep-11 21-Sep-11 21-Sep-11

17 input - deck final plot plan & equipment list (ENPPI) 0 21-Sep-11 21-Sep-11

W.P.2: ENGW.P.2: ENGINEERING 22 21-Sep-11 24-Oct-11 21-Sep-11 23-Oct-11

STRUCTUSTRUCTURAL 22 21-Sep-11 24-Oct-11 21-Sep-11 23-Oct-11

DECK DEDECK DETAIL DESIGN 22 21-Sep-11 24-Oct-11 21-Sep-11 23-Oct-11

44 Deck equipment supports & AFC dwg and MTO 22 21-Sep-11 24-Oct-11 21-Sep-11 23-Oct-11

PETROJETPETROJET 169 31-Aug-11 10-May-12 31-Aug-11 08-May-12

PETROJETPETROJET DRIVING MILESTONES 165 31-Aug-11 12-Feb-12 31-Aug-11 11-Feb-12

PROCUREPROCUREMENT 165 31-Aug-11 12-Feb-12 31-Aug-11 11-Feb-12

PTJ1020 Structural material 5 th batch (jacket secondary & deck secondary)... 0 31-Aug-11 31-Aug-11*

PTJ1080 Piping bulk material (1st batch) (ENPPI) 0 14-Nov-11 14-Nov-11

PTJ1120 Equipment (100%) (PTB) 0 24-Jan-12 24-Jan-12*

PTJ4010 Equipment by (100%) (ENPPI) 0 12-Feb-12 11-Feb-12

W.P.2: ENGW.P.2: ENGINEERING 0 15-Sep-11 15-Sep-11 15-Sep-11 15-Sep-11

TSFTSF 0 15-Sep-11 15-Sep-11 15-Sep-11 15-Sep-11

PTJ2240 Rec final weight & dimension for static equipment 0 15-Sep-11 15-Sep-11*

W.P.4: SUBW.P.4: SUBSTRUCTURES (PILES, JACKET & PDT) FABRICATION 28 13-Feb-12 15-Mar-12 13-Feb-12 15-Mar-12

JACKET SJACKET STRUCTURE FABRICATION 28 13-Feb-12 15-Mar-12 13-Feb-12 15-Mar-12

PAINTINGPAINTING 28 13-Feb-12 15-Mar-12 13-Feb-12 15-Mar-12

PTJ10270 SPLASH PAINTING FOR BARGE BUMPER 5 11-Mar-12 15-Mar-12 11-Mar-12 15-Mar-12

PTJ10330 PILE MARKING 28 13-Feb-12 15-Mar-12 13-Feb-12 15-Mar-12

W.P.5: DECW.P.5: DECK & TSF FABRICATION 114 20-Nov-11 03-May-12 20-Nov-11 01-May-12

DECK FABDECK FABRICATION 89 19-Jan-12 03-May-12 19-Jan-12 01-May-12

General AGeneral Activities 66 12-Feb-12 29-Apr-12 11-Feb-12 26-Apr-12

PTJ2060 Deck pre-commisioning 40 12-Feb-12 29-Mar-12 11-Feb-12 27-Mar-12

PTJ2090 Deck commisioning 26 29-Mar-12 29-Apr-12 28-Mar-12 26-Apr-12

Deck StruDeck Structure Fabrication 68 29-Jan-12 17-Apr-12 28-Jan-12 15-Apr-12

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11

Page 3 of 5

Page 223: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

Deck FlaDeck Flare 68 29-Jan-12 17-Apr-12 28-Jan-12 15-Apr-12

PTD150 Cutting & Assembly 20 29-Jan-12 21-Feb-12 28-Jan-12 19-Feb-12

PTD151 Welding & NDT 32 21-Feb-12 29-Mar-12 20-Feb-12 27-Mar-12

PTD152 Trial Fit 2 15-Apr-12 17-Apr-12 14-Apr-12 15-Apr-12

AtmosphrAtmosphric Painting 73 19-Jan-12 15-Apr-12 19-Jan-12 12-Apr-12

PT1070 Piping painting 14 19-Jan-12 05-Feb-12 19-Jan-12 04-Feb-12

PT1100 Deck Flare 14 29-Mar-12 15-Apr-12 28-Mar-12 12-Apr-12

Anti Skid PAnti Skid Painting 7 25-Apr-12 03-May-12 24-Apr-12 01-May-12

PT1000 Heli Deck 7 25-Apr-12 03-May-12 24-Apr-12 01-May-12

EQUIPMENEQUIPMENT 72 07-Dec-11 17-Feb-12 07-Dec-11 16-Feb-12

EquipemeEquipement Installation (onshore) 72 07-Dec-11 17-Feb-12 07-Dec-11 16-Feb-12

TSF1110 Installation of production manifold module on celler deck 4 07-Dec-11 10-Dec-11 07-Dec-11* 10-Dec-11

TSF1100 Installation of E & I module on main deck 4 07-Jan-12 10-Jan-12 07-Jan-12* 10-Jan-12

TSF1060 Equipment Installation Below Cellar Deck 4 13-Feb-12 17-Feb-12 13-Feb-12 16-Feb-12

TSF1070 Equipment Installation on Cellar Deck 15 02-Feb-12 17-Feb-12 02-Feb-12 16-Feb-12

TSF1080 Equipment Installation on Main Deck 15 02-Feb-12 17-Feb-12 02-Feb-12 16-Feb-12

PIPINGPIPING 113 20-Nov-11 13-Mar-12 20-Nov-11 11-Mar-12

PTJ2050 Piping & piping support fabrication start 0 20-Nov-11 20-Nov-11

C.S PipingC.S Piping Fab. & Erec., Valves Erection (onshore) 113 20-Nov-11 13-Mar-12 20-Nov-11 11-Mar-12

TSF1000 Piping Fabrication 70 20-Nov-11 29-Jan-12 20-Nov-11 28-Jan-12

TSF1020 Piping Erection 35 28-Jan-12 03-Mar-12 27-Jan-12 01-Mar-12

TSF1040 Valve Installation 15 17-Feb-12 03-Mar-12 16-Feb-12 01-Mar-12

PTJ2120 Piping hydrotest 21 21-Feb-12 13-Mar-12 20-Feb-12 11-Mar-12

W.P.7: CERW.P.7: CERTIFICATION 0 29-Mar-12 29-Mar-12 27-Mar-12 27-Mar-12

PTJ1090 Deck completion certif icate 0 29-Mar-12 27-Mar-12

W.P.8: LOAW.P.8: LOAD-OUT, SEA-FASTENING, TRANSPORTATION & INSTALLATION 204 18-Oct-11 10-May-12 18-Oct-11 08-May-12

PTJ1070 Pre-drilling template seafastening and load out 7 18-Oct-11 24-Oct-11 18-Oct-11 24-Oct-11*

PTJ1050 Jacket & Piles seafastening and load out 15 17-Mar-12 31-Mar-12 17-Mar-12 31-Mar-12*

A M J Jul A S O N D J F M A M J JulA2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11

Page 4 of 5

Page 224: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Activity ID Activity Name OriginalDuration

BL Project Start

BL Project Finish

Start Finish

PTJ1060 Deck seafastening and load out 7 03-May-12 10-May-12 02-May-12 08-May-12*A M J Jul A S O N D J F M A M J JulA

2011 2012

3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT

CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11

Page 5 of 5

Page 225: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 29 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.5. ONE MONTH LOOKAHEAD SCHEDULE

Page 226: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPROCESS TECHNOLOGY DIVISIONREPORTS / TECHNICAL LIST

100.00% 70.00%1.94%Basis of design

Final 07-Jul-11 3011-Jun-11

70.00% 20.00%1.94%Process & Utilities report

Design 12-Jul-11 5012-Jun-11

TER

100.00% 20.00%3.06%Flame arrestor TER

Finish 21-Jul-11 8023-Jun-11

100.00% 20.00%3.06%Fire Fighting package TER

Finish 05-Jul-11 8009-Jun-11

100.00% 20.00%3.06%Safety equipment and life saving TER

Finish 07-Jul-11 8012-Jun-11

MRP

0.00% 0.00%0.83%Chemical injection package MRP

Start 03-Jul-11 2010-Jul-11

For Purchase 07-Jul-11 8017-Jul-11

0.00% 0.00%0.83%Fire Fighting package MRP

Start 20-Jul-11 2005-Jul-11

For Purchase 21-Jul-11 8011-Jul-11

VENDOR PRINTS REVIEW

0.00% 0.00%5.28%Chemical injection package

Start 25-Jul-11 2025-Jul-11

Tuesday, July 05, 2011 Page 1 of 12

Layout No. 1* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION)Data'Nes Systems, Release 2.21

Page 227: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTDRAWING

70.00% 0.00%1.58%Electrical hook-up Drawing

Start 12-Jul-11 2019-May-11

Design 19-Jul-11 5026-May-11

70.00% 0.00%1.32%Hydraulic instruments layouts

Start 06-Jul-11 2005-May-11

Design 13-Jul-11 5012-May-11

70.00% 0.00%1.32%Hydraulic instruments Tube Routing layouts

Start 05-Jul-11 2012-May-11

Design 12-Jul-11 5019-May-11

TER

100.00% 20.00%2.63%Choke valve TER

Finish 05-Jul-11 8012-Jun-11

20.00% 20.00%1.84%Loose Instrument TER

Finish 24-Jul-11 8026-Jun-11

20.00% 0.00%2.11%Sand & Corrosion probes TER

Start 11-Jul-11 2016-Jun-11

20.00% 20.00%2.11%Instrument & Mechanical bulk material TER

Finish 14-Jul-11 8003-Jul-11

100.00% 0.00%2.11%Instrument cable and cable glandsTER

Start 10-Jul-11 2006-Jun-11

20.00% 20.00%2.11%Inst. Junction Box TER

Finish 21-Jul-11 8007-Jul-11

20.00% 0.00%2.11%Instrument cable trays TER

Start 03-Jul-11 2014-Jun-11

MRP

0.00% 0.00%1.05%Electro Hydraulic Well Head panel MRP

Start 13-Jul-11 2004-Jul-11

For Purchase 14-Jul-11 8011-Jul-11

Tuesday, July 05, 2011 Page 2 of 12

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMEData'Nes Systems, Release 2.21

Page 228: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGINSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENTMRP

0.00% 0.00%1.05%HIPPS System MRP

Start 07-Jul-11 2028-Jun-11

For Purchase 13-Jul-11 8005-Jul-11

0.00% 0.00%1.05%Wing valve MRP

Start 24-Jul-11 2006-Jul-11

VENDOR PRINTS REVIEW

0.00% 0.00%3.95%HIPPS Vendor prints review

Start 24-Jul-11 2013-Jul-11

0.00% 0.00%3.42%Electro hydraulic wellhead control panel Vendor prints review

Start 21-Jul-11 2025-Jul-11

0.00% 0.00%3.68%Multi phase flow meter Vendor prints review

Start 20-Jul-11 2025-Jul-11

Tuesday, July 05, 2011 Page 3 of 12

Layout No. 1* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMEData'Nes Systems, Release 2.21

Page 229: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGPIPING ENGINEERING DIVISIONTER

100.00% 0.00%2.73%Injection fitting TER

Start 04-Jul-11 2025-May-11

Finish 24-Jul-11 8015-Jun-11

100.00% 20.00%2.73%Insulation joint Injection fitting TER

Finish 21-Jul-11 8009-Jun-11

MRP

20.00% 0.00%1.82%Piping bulk MRP

Start 05-Jul-11 2019-Jun-11

For Purchase 07-Jul-11 8026-Jun-11

VENDOR PRINTS REVIEW

0.00% 0.00%3.64%Piping bulk Vendor prints review

Start 20-Jul-11 2004-Jul-11

Specification

100.00% 70.00%4.55%Piping material classes

Final 14-Jul-11 3013-Jun-11

Tuesday, July 05, 2011 Page 4 of 12

Layout No. 1* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 230: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONDRAWING

70.00% 0.00%2.00%Single line diagram

Start 14-Jul-11 2023-May-11

Design 21-Jul-11 5030-May-11

REPORTS / TECHNICAL LIST

70.00% 0.00%1.33%Electrical cable list

Start 10-Jul-11 2008-Jun-11

Design 17-Jul-11 5015-Jun-11

70.00% 0.00%2.33%Power system study

Start 30-Jun-11 2015-May-11

Design 14-Jul-11 5024-May-11

TER

20.00% 20.00%8.33%Navigational aids system TER

Finish 10-Jul-11 8027-Jun-11

20.00% 0.00%4.33%Lighting material TER

Start 10-Jul-11 2008-Jun-11

20.00% 0.00%4.33%Earthing material TER

Start 10-Jul-11 2020-Jun-11

MRP

0.00% 0.00%2.00%Electrical cables MRP

Start 10-Jul-11 2013-Jul-11

For Purchase 14-Jul-11 8020-Jul-11

0.00% 0.00%2.00%Electrical Cable trays MRP

Start 30-Jun-11 2010-Jul-11

For Purchase 30-Jun-11 8017-Jul-11

VENDOR PRINTS REVIEW

0.00% 0.00%2.50%Electrical Cable trays Vendor prints review

Start 18-Jul-11 2025-Jul-11

0.00% 0.00%2.50%Electrical Cables Vendor prints review

Start 21-Jul-11 2001-Aug-11

Tuesday, July 05, 2011 Page 5 of 12

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 231: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGELECTRICAL ENGINEERING DIVISIONVENDOR PRINTS REVIEW

Tuesday, July 05, 2011 Page 6 of 12

Layout No. 1* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 232: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGOFFSHORE ENGINEERING DIVISIONDRAWING

0.00% 0.00%10.00%Cable trays supports for deck plan at el. +9700 T.O.S.

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

0.00% 0.00%10.00%Cable trays supports for cellar deck plan at el. +13500 T.O.S.

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

0.00% 0.00%10.00%Cable trays supports for mezzanine deck plan at el. +16000 T.

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

0.00% 0.00%10.00%Cable trays supports for main deck plan at el. +20500 T.O.S.

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

0.00% 0.00%10.00%Cable trays supports for Helideck plan at el. +26500 T.O.S.

Start 03-Jul-11 2028-Jun-11

Design 10-Jul-11 5005-Jul-11

TER

20.00% 20.00%15.00%Survival module TER

Finish 03-Jul-11 8028-Jun-11

MRP

0.00% 0.00%5.00%Survival module MRP

Start 25-Jul-11 2020-Jul-11

Tuesday, July 05, 2011 Page 7 of 12

Layout No. 1* Weights of Activities are calculated relative to (OFFSHORE ENGINEERING DIVISION)Data'Nes Systems, Release 2.21

Page 233: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.2 DETAILED ENGINEERINGMECHANICAL ENGINEERING DEPARTMENTTER

100.00% 20.00%10.00%Service water pump TER

Finish 03-Jul-11 8007-Jun-11

VENDOR PRINTS REVIEW

0.00% 0.00%7.78%Turret crane crane Vendor prints review

Start 13-Jul-11 2019-Jul-11

Tuesday, July 05, 2011 Page 8 of 12

Layout No. 1* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 234: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

60.00% 40.00%3.26%Safety equipment and life saving

Comm. offers open 17-Jul-11 2012-Jun-11

Bid tab 24-Jul-11 1026-Jun-11

60.00% 70.00%4.19%Chemical injection package

F.O.C. 30-Jun-11 2010-Jul-11

P.O. 10-Jul-11 1024-Jul-11

60.00% 40.00%3.49%Fire Fighting package

Comm. offers open 10-Jul-11 2014-Jun-11

Bid tab 14-Jul-11 1028-Jun-11

F.O.C. 20-Jul-11 2004-Jul-11

P.O. 24-Jul-11 1018-Jul-11

90.00% 90.00%3.73%Piping bulk

P.O. 07-Jul-11 1003-Jul-11

60.00% 20.00%3.26%Injection fitting

Tech. offers open 04-Jul-11 2023-May-11

40.00% 20.00%3.49%Earthing material

Tech. offers open 07-Jul-11 2020-Jun-11

40.00% 20.00%3.49%Lighting material

Tech. offers open 07-Jul-11 2008-Jun-11

60.00% 90.00%3.73%Electrical Cable trays

P.O. 07-Jul-11 1024-Jul-11

60.00% 70.00%3.49%Electrical Cables

F.O.C. 03-Jul-11 2013-Jul-11

P.O. 10-Jul-11 1027-Jul-11

40.00% 40.00%3.49%Navigation aids system

Comm. offers open 17-Jul-11 2027-Jun-11

40.00% 40.00%3.49%Instrument & Mechanical bulk material

Comm. offers open 21-Jul-11 2003-Jul-11

Tuesday, July 05, 2011 Page 9 of 12

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 235: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESFOREIGN PURCHASING DEPARTMENTCOMMODITIES ONE BY ONE

70.00% 70.00%4.19%HIPPS

F.O.C. 06-Jul-11 2028-Jun-11

P.O. 14-Jul-11 1012-Jul-11

60.00% 40.00%3.73%Choke valves

Comm. offers open 12-Jul-11 2014-Jun-11

Bid tab 20-Jul-11 1028-Jun-11

40.00% 0.00%3.49%Instrument cable trays

Tech. offers open 04-Jul-11 2014-Jun-11

70.00% 40.00%3.54%Electro hydraulic wellhead control panel

Comm. offers open 30-Jun-11 2006-Jun-11

Bid tab 06-Jul-11 1020-Jun-11

F.O.C. 12-Jul-11 2004-Jul-11

P.O. 18-Jul-11 1014-Jul-11

70.00% 40.00%3.54%Wing valves

Comm. offers open 03-Jul-11 2008-Jun-11

Bid tab 10-Jul-11 1022-Jun-11

F.O.C. 21-Jul-11 2006-Jul-11

60.00% 20.00%3.49%Instrument cable and cable glands

Tech. offers open 07-Jul-11 2006-Jun-11

40.00% 0.00%3.49%Sand & Corrosion probes

Tech. offers open 10-Jul-11 2016-Jun-11

60.00% 90.00%3.73%Multi phase flow meter

P.O. 03-Jul-11 1024-Jul-11

60.00% 40.00%3.49%Service water pump

Comm. offers open 10-Jul-11 2013-Jun-11

Bid tab 18-Jul-11 1027-Jun-11

F.O.C. 25-Jul-11 2011-Jul-11

40.00% 40.00%3.73%Survival module

Comm. offers open 10-Jul-11 2029-Jun-11

Bid tab 18-Jul-11 1013-Jul-11

F.O.C. 24-Jul-11 2019-Jul-11

Tuesday, July 05, 2011 Page 10 of 12

Layout No. 1* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT)Data'Nes Systems, Release 2.21

Page 236: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.3 PROCUREMENT SERVICESEXPEDITING DEPART.COMMODITIES ONE BY ONE

0.00% 0.00%4.66%Chemical injection package

Start 05-Jul-11 1010-Jul-11

0.00% 0.00%3.73%Fire Fighting package

Start 20-Jul-11 1005-Jul-11

0.00% 0.00%1.86%Electrical Cable trays

Start 06-Jul-11 2010-Jul-11

0.00% 0.00%2.33%Electrical Cables

Start 06-Jul-11 2017-Jul-11

0.00% 0.00%4.66%HIPPS

Start 07-Jul-11 1028-Jun-11

0.00% 0.00%3.73%Electro hydraulic wellhead control panel

Start 12-Jul-11 1010-Jul-11

0.00% 0.00%3.26%Wing valves

Start 24-Jul-11 1006-Jul-11

Tuesday, July 05, 2011 Page 11 of 12

Layout No. 1* Weights of Activities are calculated relative to (EXPEDITING DEPART.)Data'Nes Systems, Release 2.21

Page 237: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Lookahead Report25-Jun-11As Of :25-Jul-11Forecast Date :

SETH Offshore EPC Project3467-200Project No.:

MilestonePlanned Expected

Milestone Value

* Relative Weight

Planned Progress%

Dates Actual Progress%

ENPPIW.P.5 DECK AND TSF SUPPLY & FABRICATIONMETERIAL SUPPLYCOMMODITIES ONE BY ONE

0.00% 0.00%9.06%Chemical injection package

P.O. 10-Jul-11 1524-Jul-11

0.00% 0.00%1.94%Fire Fighting package

P.O. 24-Jul-11 1518-Jul-11

0.00% 0.00%3.48%Piping bulk 3rd batch

P.O. 07-Jul-11 3503-Jul-11

0.00% 0.00%2.78%Electrical Cable trays

P.O. 07-Jul-11 3524-Jul-11

0.00% 0.00%1.49%Electrical Cables

P.O. 10-Jul-11 3527-Jul-11

0.00% 0.00%7.71%HIPPS

P.O. 14-Jul-11 1512-Jul-11

0.00% 0.00%5.41%Electro hydraulic wellhead control panel

P.O. 18-Jul-11 1518-Jul-11

0.00% 0.00%10.97%Multi phase flow meter

P.O. 03-Jul-11 1524-Jul-11

0.00% 0.00%8.70%Piping bulk 1st batch

P.O. 07-Jul-11 3503-Jul-11

0.00% 0.00%5.22%Piping bulk 2nd batch

P.O. 07-Jul-11 3503-Jul-11

Tuesday, July 05, 2011 Page 12 of 12

Layout No. 1* Weights of Activities are calculated relative to (METERIAL SUPPLY)Data'Nes Systems, Release 2.21

Page 238: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 30 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.6. PROCUREMENT STATUS

Page 239: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 31 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.6.1 ENPPI

Page 240: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

ProcessVENT STOCK TIPS PL

EXP

ACT(112-04)

09-May-11

09-May-11

04-Jul-11

26-Jul-11

03-Aug-11

23-Aug-11

17-Aug-11

11-Sep-11

06-Dec-11

26-Dec-11

27-Dec-11

16-Jan-12

10-Jan-12

30-Jan-12

CHEMICAL INJECTION PACKAGE

PL

EXP

ACT(115-01)

06-Apr-11

06-Apr-11

19-Jun-11

01-Jun-11

10-Jul-11

30-Jun-11

24-Jul-11

10-Jul-11

06-Jan-12

27-Dec-11

27-Jan-12

17-Jan-12

10-Feb-12

31-Jan-12

FLAME ARRESTORS

PL

EXP

ACT(119-02)

27-Apr-11

17-Apr-11

23-Jun-11

21-Jul-11

21-Jul-11

18-Aug-11

04-Aug-11

06-Sep-11

28-Nov-11

26-Dec-11

19-Dec-11

16-Jan-12

02-Jan-12

30-Jan-12

FIRE PROTECTION SYSTEM PACKGE

PL

EXP

ACT(190-01)

12-Apr-11

12-Apr-11

14-Jun-11

05-Jul-11

07-Jul-11

18-Jul-11

21-Jul-11

01-Aug-11

03-Jan-12

04-Jan-12

24-Jan-12

28-Jan-12

07-Feb-12

11-Feb-12

LIFE SAVING EQUIPMENT

PL

EXP

ACT(190-03)

12-Apr-11

12-Apr-11

12-Jun-11

07-Jul-11

10-Jul-11

04-Aug-11

24-Jul-11

18-Aug-11

07-Dec-11

01-Jan-12

28-Dec-11

22-Jan-12

11-Jan-12

05-Feb-12

Tuesday, July 05, 2011 Page 1 of 7PL: Planned EXP: ExpectACT: Actual

Page 241: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

SURVIVAL MODULE

PL

EXP

ACT(197-02)

28-Apr-11

14-Apr-11

28-Jun-11

03-Jul-11

19-Jul-11

24-Jul-11

02-Aug-11

07-Aug-11

26-Dec-11

31-Dec-11

16-Jan-12

21-Jan-12

30-Jan-12

04-Feb-12

MechanicalSERVICE WATER PUMPS

PL

EXP

ACT(131-15)

25-Apr-11

25-Apr-11

07-Jun-11

03-Jul-11

11-Jul-11

27-Jul-11

25-Jul-11

10-Aug-11

28-Nov-11

14-Dec-11

19-Dec-11

04-Jan-12

04-Jan-12

20-Jan-12

DIESEL GENERATOR

PL

EXP

ACT(135-03)

15-Dec-11

15-Dec-11

12-Jan-12

26-Jan-12

26-Jan-12

29-Dec-11

MONORAIL CRANE

PL

EXP

ACT(137-01)

28-Jul-11

28-Jul-11

06-Sep-11

06-Sep-11

04-Oct-11

04-Oct-11

17-Oct-11

17-Oct-11

01-Feb-12

01-Feb-12

22-Feb-12

22-Feb-12

07-Mar-12

07-Mar-12

TURRENT CRANE PL

EXP

ACT(137-02)

13-Apr-11

10-Apr-11

12-Jun-11

04-May-11

10-Jul-11

29-May-11

24-Jul-11

21-Jun-11

06-Mar-12

19-Feb-12

20-Mar-12

04-Mar-12

03-Apr-12

18-Mar-12

Tuesday, July 05, 2011 Page 2 of 7PL: Planned EXP: ExpectACT: Actual

Page 242: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

MICROTURBINE PL

EXP

ACT(172-01)

15-Dec-11

15-Dec-11

12-Jan-12

26-Jan-12

26-Jan-12

29-Dec-11

ElectricalELECTRICAL CABLE TRAYS

PL

EXP

ACT(500-02)

02-May-11

10-Apr-11

19-Jun-11

02-May-11

10-Jul-11

30-May-11

24-Jul-11

12-Jul-11

18-Oct-11

02-Oct-11

08-Nov-11

23-Oct-11

22-Nov-11

06-Nov-11

NAVIGATIONAL AIDS

PL

EXP

ACT(510-10)

16-May-11

26-Apr-11

27-Jun-11

10-Jul-11

18-Jul-11

31-Jul-11

02-Aug-11

15-Aug-11

05-Dec-11

18-Dec-11

26-Dec-11

08-Jan-12

09-Jan-12

22-Jan-12

E& I MODULE PL

EXP

ACT(510-16)

15-Dec-11

15-Dec-11

12-Jan-12

12-Jan-12

26-Jan-12

26-Jan-12

ELECTRICAL CABLES

PL

EXP

ACT(510-22)

09-May-11

10-Apr-11

20-Jun-11

29-May-11

13-Jul-11

03-Jul-11

27-Jul-11

10-Jul-11

04-Dec-11

22-Nov-11

25-Dec-11

13-Dec-11

08-Jan-12

27-Dec-11

Tuesday, July 05, 2011 Page 3 of 7PL: Planned EXP: ExpectACT: Actual

Page 243: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

LIGHTING MATERIAL

PL

EXP

ACT(529-01)

02-Jun-11

22-Jun-11

06-Jul-11

04-Aug-11

27-Jul-11

25-Aug-11

22-Aug-11

13-Sep-11

14-Dec-11

23-Dec-11

04-Jan-12

13-Jan-12

18-Jan-12

27-Jan-12

EARTHING MATERIAL

PL

EXP

ACT(550-01)

06-Jun-11

20-Jun-11

18-Jul-11

04-Aug-11

08-Aug-11

25-Aug-11

24-Aug-11

15-Sep-11

26-Dec-11

23-Dec-11

24-Jan-12

22-Jan-12

14-Feb-12

12-Feb-12

InstrumentLOOSE INSTRUMENT

PL

EXP

ACT(210-01)

25-May-11

06-Jun-11

26-Jun-11

24-Jul-11

17-Jul-11

14-Aug-11

31-Jul-11

28-Aug-11

13-Jan-12

16-Jan-12

10-Feb-12

06-Feb-12

24-Feb-12

20-Feb-12

MANUAL VALVES PL

EXP

ACT(212-01)

15-Dec-11

12-Dec-11

05-Jan-12

05-Jan-12

19-Jan-12

19-Jan-12

SHUTDOWN & BLOWDOWN VALVES

PL

EXP

ACT(212-04)

15-Dec-11

15-Dec-11

12-Jan-12

05-Jan-12

26-Jan-12

19-Jan-12

Tuesday, July 05, 2011 Page 4 of 7PL: Planned EXP: ExpectACT: Actual

Page 244: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

MULTIPHASE FLOW METERS

PL

EXP

ACT(221-06)

10-Apr-11

10-Apr-11

12-Jun-11

25-May-11

10-Jul-11

21-Jun-11

24-Jul-11

03-Jul-11

06-Jan-12

21-Dec-11

27-Jan-12

11-Jan-12

10-Feb-12

25-Jan-12

CHOKE VALVES PL

EXP

ACT(234-06)

13-Apr-11

10-Apr-11

15-Jun-11

05-Jul-11

10-Jul-11

26-Jul-11

24-Jul-11

09-Aug-11

05-Apr-12

21-Feb-12

26-Apr-12

11-Apr-12

WING VALVES PL

EXP

ACT(239-02)

13-Apr-11

10-Apr-11

13-Jun-11

15-Jun-11

11-Jul-11

21-Jul-11

25-Jul-11

04-Aug-11

06-Apr-12

17-Mar-12

27-Apr-12

07-Apr-12

11-May-12

21-Apr-12

WELLHEAD CONTROL PANEL

PL

EXP

ACT(252-10)

12-Apr-11

07-Apr-11

12-Jun-11

16-Jun-11

12-Jul-11

05-Jul-11

26-Jul-11

19-Jul-11

08-Jan-12

01-Jan-12

29-Jan-12

22-Jan-12

12-Feb-12

05-Feb-12

HIGH INTEGRITY PRESSURE PROTECTION

PL

EXP

ACT(252-14)

07-Apr-11

03-Apr-11

31-May-11

09-Jun-11

28-Jun-11

06-Jul-11

12-Jul-11

14-Jul-11

24-Mar-12

17-Mar-12

14-Apr-12

07-Apr-12

28-Apr-12

21-Apr-12

Tuesday, July 05, 2011 Page 5 of 7PL: Planned EXP: ExpectACT: Actual

Page 245: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

SAND PROBES PL

EXP

ACT(281-08)

01-Jun-11

26-Jun-11

07-Jul-11

04-Aug-11

01-Aug-11

25-Aug-11

15-Aug-11

13-Sep-11

29-Dec-11

07-Jan-12

19-Jan-12

28-Jan-12

02-Feb-12

11-Feb-12

INSTRUMENT/MECHANICAL BULK MATERIAL

PL

EXP

ACT(291-01)

02-Jun-11

03-May-11

03-Jul-11

14-Jul-11

24-Jul-11

04-Aug-11

07-Aug-11

18-Aug-11

01-Nov-11

02-Nov-11

22-Nov-11

23-Nov-11

06-Dec-11

07-Dec-11

JUNCTION BOXES PL

EXP

ACT(295-01)

09-Jun-11

06-Jun-11

07-Jul-11

21-Jul-11

28-Jul-11

11-Aug-11

11-Aug-11

25-Aug-11

05-Nov-11

09-Nov-11

26-Nov-11

30-Nov-11

10-Dec-11

14-Dec-11

INSTRUMENT CABLES

PL

EXP

ACT(298-01)

23-May-11

23-Jun-11

20-Jun-11

21-Jul-11

11-Jul-11

11-Aug-11

25-Jul-11

25-Aug-11

28-Nov-11

09-Dec-11

19-Dec-11

30-Dec-11

02-Jan-12

13-Jan-12

INSTRUMENT CABLE TRAYS / CHANNELS

PL

EXP

ACT(298-03)

31-May-11

26-Jun-11

28-Jun-11

28-Jul-11

14-Jul-11

15-Aug-11

28-Jul-11

29-Aug-11

22-Oct-11

13-Nov-11

29-Oct-11

20-Nov-11

12-Nov-11

04-Dec-11

Piping

Tuesday, July 05, 2011 Page 6 of 7PL: Planned EXP: ExpectACT: Actual

Page 246: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Commodity Name

(Supplier)

As of: 25-Jun

Procurement Status RepoProject: 3467-200

PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM

PTB

MRQ TER F.O.C P.O Fab. Upto RFS

Shipping Delivery at Site

PIPING BULK MATERIAL

PL

EXP

ACT(400-01)

07-Apr-11

07-Apr-11

31-May-11

17-May-11

20-Jun-11

22-Jun-11

04-Jul-11

07-Jul-11

06-Jan-12

10-Jan-12

27-Jan-12

31-Jan-12

10-Feb-12

14-Feb-12

INJECTION FITTINGS

PL

EXP

ACT(400-02)

24-Apr-11

24-Apr-11

15-Jun-11

24-Jul-11

13-Jul-11

21-Aug-11

27-Jul-11

07-Sep-11

10-Dec-11

18-Jan-12

31-Dec-11

08-Feb-12

14-Jan-12

22-Feb-12

PipelineINSULATING JOINTS (Pipeline)

PL

EXP

ACT(612-03)

20-Apr-11

29-May-11

09-Jun-11

21-Jul-11

10-Jul-11

21-Aug-11

24-Jul-11

07-Sep-11

07-Dec-11

18-Jan-12

28-Dec-11

08-Feb-12

11-Jan-12

22-Feb-12

PRODUCTION MANIFOLD

PL

EXP

ACT(642-03)

15-Dec-11

15-Dec-11

12-Jan-12

12-Jan-12

26-Jan-12

26-Jan-12

Tuesday, July 05, 2011 Page 7 of 7PL: Planned EXP: ExpectACT: Actual

Page 247: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

PAGE 32 OF 33

PTB

Egypt

SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT

3467-200

Rev. (0)

Jun 2011

GFL

003

-040

5

4.6.2 TECNOMARE

Page 248: EPC-3467-200-MONTHLY PROGRESS REPORT NO.1.pdf

Sr. Commodity PhaseRFQ's 

Issued DateTech. Open Tech. Report

Comm. Open

Comm. Report

Fax Of Comm.

MRP Issued P.O. DateDelivery Ex‐

WorkDelivery FOB

Delivery at site

Plan 11‐Mar‐11 13‐Apr‐11 3‐May‐11 11‐May‐11 17‐May‐11 30‐May‐11 30‐May‐11 30‐May‐11 12‐Jan‐12 27‐Jan‐12 25‐Feb‐12

Forecast 23‐Feb‐12

Actual 11‐Mar‐11 25‐Mar‐11 20‐Apr‐11 21‐Apr‐11 29‐Apr‐11 2‐May‐11 2‐May‐11 2‐May‐11

Plan 31‐Mar‐11 10‐Apr‐11 14‐Apr‐11 24‐Apr‐11 28‐Apr‐11 15‐May‐11 15‐May‐11 15‐May‐11 4‐Sep‐11 18‐Sep‐11 28‐Sep‐11

Forecast

Actual 15‐Mar‐11 5‐Apr‐11 14‐Apr‐11 14‐Apr‐11 26‐May‐11 26‐May‐11 26‐May‐11 26‐May‐11

Plan 31‐Mar‐11 29‐Apr‐11 9‐May‐11 17‐May‐11 25‐May‐11 30‐May‐11 30‐May‐11 30‐May‐11 4‐Sep‐11 18‐Sep‐11 28‐Sep‐11

Forecast

Actual 21‐Mar‐11 14‐Apr‐11 4‐May‐11 9‐May‐11 6‐Jun‐11 9‐Jun‐11 9‐Jun‐11 9‐Jun‐11

3

GROUT SEALS

SHOCK CELLS

SETH DEVELOPMENT PROJECTProcurement Summary Status Report

PLC /RTU1

2

as of June 25th, 2011