eot1
-
Upload
fuzahjamil -
Category
Documents
-
view
215 -
download
0
Transcript of eot1
-
8/2/2019 eot1
1/3
rticleA
By the Entrusty Group
Is The Contractor Obliged To Apply ForExtension Of Time ?
Your Contractual Questions Answered
The Entrusty Group, a multi-disciplinary group of companies, of which, one of their specialisations is inproject, commercial and contractual management, has been running a regular contractual question-and-answer section for MBAM members in Master Builders Journal.
In this instalment of the series, the Entrusty Group will provide the answer to the frequently asked questionabove.
Construction contracts usually have
a fixed time frame for theContractor to complete the works
(i.e. time is of the essence time being a
fundamental term of the contract). PAM
98 cl 21.1, PAM 69 cl 21 (1), JKR 203/A cl 38
(b), IEM cl 38 (a), CIDB cl 17.1 JKR PWD DB/
T cl.39.2 refer to Possession of Site and
Commencement.
Consequently, PAM 98 cl 21.1, PAM 69 cl
21(1), JKR 203/A cl 38 (b), IEM cl 38 (a), CIDB
cl 17.1 (a) and JKR PWD DB/T cl. 39.2 also
specify the Contractors primaryobligation to complete the Works by the
completion date. If the Contractor fails to
complete the Works by the Date for
Completion or within the extended time,
the Contractor is in breach. Under Section
75 of the Contract Acts 1950 (CA 1950) the
Contractor shall bear the damages
suffered by the Employer.
Purpose Of Extension Of Time Clauses
The main provision of EoT clauses is to allowfor any alteration to the completion date. It
is also to preserve the Employers rights to
deduct Liquidated Damages. The two major
effects of time extension clause(s) under
construction contracts are as follow:
(a) The extent to which the Contractor
could be made liable for liquidated
damages in the event of a delay to the
completion of the Works;
(b) The fact that extensions of time aregranted on account of delays
attributable to some act by the
Employer may afford a basis for a
claim by the Contractor against the
Employer for time related damagesand disruption losses.
Hudsons Building and Engineering
Contracts, 11thEdition, p 624explains the
rationale for such clauses:
It has been seen that, for the purpose
of treating the contract as repudiated,
in the rare cases where time is of the
essence, the contract time for
completion may cease to be applicable
for a variety of reasons, including theordering of extras or other interference
or prevention by the employer. In the
case of damages, it is equally obvious
that where the reason is some act of the
employer or his architect or engineer
preventing completion by the due date,
it cannot be the intention of the parties
that liquidated or other damages
should be calculated from that date
even if the act, such as ordering extras,
is not a breach of contract. Liquidated
damages stipulated for at a rate foreach day or week of delay in completing
the works must begin to run from some
definite date. It follows, therefore, that if
the date in the contract has for some
such reason ceased to be the proper
date for the completion of the works,
and no contractual provision exists for
the substitut ion of a new date, there is
such a case no date from which
liquidated damages can run and the
right to liquidated damages will have
gone. This, rather than solicitude for thecontractor, is the reason for the
provision usually known as the
extension of time clause.
EoT and liquidated damages clauses are
closely linked, and failure by the Architect/Engineer/S.O/P.D. to properly exercise his
power to extend time, where any delay is
caused by the Employer (or for which the
Employer is responsible in law), relieves
the Contractor from his liability to pay
liquidated damages. As a result, the courts
have consequently ruled that the clause(s)
are to be interpreted contra proferentum
against the Employer.
Contractual Provisions For EoT
Generally, the Contractor is to give written
notice of delay and cause/s to the
Architect/Engineer/S.O/P.D. when it is
apparent that the progress of works is
delayed for him to assess and grant EoT.
PAM cl 23, IEM/JKR cl 43, CIDB cl 24, and
JKR PWD DB/T cl. 45.1 are the relevant
clauses for EoT.
For the Contractor to claim for EoT, the
grounds for such claim for EoT must fall
within the specific events as listed in thecontract. Any event falling outside the
listed events does not entitle the
Contractor to any EoT. The grounds for EoT
applications can be divided into two basic
categories:
(a) Neutral events, e.g. force majeure,
exceptionally inclement weather, civil
commotion, strike or lockout,
availability of materials not due to the
Contractors fault, etc.
(b) Defaults by the Employer and/or his
agents, e.g. late decision/information
of the Architect/Engineer/S.O/P.D.,
85
-
8/2/2019 eot1
2/3
rticleA
late site delivery, compliance with the
Architect/Engineer/S.O/P.D., delay by
the Employers agents, delay by
nominated sub-contractors/
suppliers, etc.
PAM/IEM/JKR203/A/PWD DB/T requires
the Contractor to use his best endeavourto prevent delay in the works and do all
that may be reasonably required and
satisfaction of the Architect/ Engineer/
S.O/P.D. to proceed with the works.
CIDB Form is much more procedural and
comprehensive on extension of time
provisions:
Cl 24.1 Extension of Time
Cl 24.2 Notice of Delay
Cl 24.3 Superintending Officers DecisionCl 24.4 Interim Decision of Extension
of Time
Cl 24.5 Superintending Officers
Discretion
Cl 24.6 Certificate of Extension of Time
Cl 24.7 Review of Superintending
Officers Decision
CIDB s/cl 24.3 requires the S.O. to notify
the Contractor in writing within 30 Days
of notice receipt or further information,
whether in his opinion the delay event isone which in principle entitles to an EoT.
Under the CIDB contract, it also allows the
S.O. to grant EoT even when he considers
that there is insufficient information to
decide on the Contractors application.
In general, in deciding any EoT, the S.O.
shall take into account the following
matters:
(a) EoT previously granted, if any;(b) The effect/extent of work omitted or
decrease in the quantity of any work
resulting from re-measurement;
(c) Any concurrent delays with the
delaying event/s including those
due to the Contractors acts or
defaults.
The CIDB contract under s/cl 24.4 allows
the S.O. to make interim decision on EoT
where a delaying event has continuing
effects and to decide an overall EoT on theevent within 30 Days of receipt of final
particulars, by reviewing all the
circumstances.
Whilst s/cl 24.5 allows the S.O. absolute
discretion to grant a fair, reasonable and
necessary EoT even if the Contractor fails
to comply with the EoT provisions.
S/cl 24.6 requires the S.O. to notify the
Contractor of any decision in granting
extension of time in a certificate(Certificate of Extension of Time), copied
to the Employer and nominated sub-
contractors/nominated suppliers.
86
S/cl 24.7 allows the S.O. to review any
previous EoT granted at any time prior to
issuance of Final Certificate either to fix a
Tim e for Com pletion later than that
previously granted or confirm thatpreviously fixed.
Contractors Obligations For Applying
For EoT
Generally, there is a duty imposed on the
Contractor to notify the Architect/
Engineer/S.O. in writing as soon as the
progress is delayed. The objective is to
ensure that the Architect/Engineer/S.O. is
aware that the completion period may not
be met and that the Contractor is pre-warned of the triggers off time whether or
not the reason of such delay is within one
of those grounds or the Contractors own
inefficiencies.
It is desirable that the notice should specify
the cause of the delay but even if the notice
does not contain sufficient details to
enable the Architect/Engineer/S.O. to form
an opinion as to whether the cause of delay
falls within one of those specified grounds,
it is still valid. Thus, the requirement ofnotice of delay is not a condition precedent
to the granting of an extension of time by
the Architect/Engineer/S.O. However, this
could be taken into account in granting an
extension of time.
In London Borough of Mertonv Stanley
Hugh Leach (1985) 32 BLR 51, it was
decided that a written notice is not a
condition precedent to granting EoT. The
Architect is under an independent duty to
do so. Mr Justice Vinelott went on to saythat failure by the contractor to give
notice of delay was itself a breach of
contract and this could have some effect
on his right to an extension of time. If the
architect, because of failure by the
contractor to give notice of delay, was
unable to avoid or reduce a delay to
completion, the contractor should have
no greater extension than if he had given
notice.
The legal principle here is that no oneshould benefit from his own breach of
contract (The Prevention Principle) and is
closely allied to the duty to mitigate.
-
8/2/2019 eot1
3/3
rticleA
MBJ
87
In the next issue of the MBAM journal the article will answer the question on Is the
Contractor still entitle to Extension of Time when there is concurrent delay?
The Entrusty Group includes Entrusty Consultancy SdnBhd (formerly known as J.D. Kingsfield (M) Sdn Bhd), BK
Burns & Ong Sdn Bhd (a member of the Asia wide group BK
Asia Pacific) , Pro-Value Management, Proforce Management Services Sdn Bhd/Agensi
Pekerjaan Proforce Sdn Bhd and International Master Trainers Sdn Bhd. Apart from
project, commercial and contractual management services, the group also provides risk,
resources, quality and value management, recruitment consultancy services and
corporate training programmes to various industries, particularly in construction and
petrochemical, both locally and internationally.
Entrusty Group will provide 30 minutes of free consultancy with prior appointment to
MBAM members on their contractual questions. The Group also provides both in-house
and public seminars/workshops in its various areas of expertise. For further details,please visit website: www.entrusty.com. or contact HT Ong or Wing Ho at 22-1& 2 Jalan
2/109E, Desa Business Park, Taman Desa, 58100 Kuala Lumpur, Malaysia. Tel: 6(03)-7982
2123 Fax: 6(03)-7982 3122 Email:[email protected]
There is also an obligation imposed on
the Contractor to constantly use his best
endeavour to prevent delay. Th e
Contractor shall also do all that may
reasonably be required to thesatisfaction of the Architect/Engineer/
S.O. to proceed with the work.
There are two issues to be considered
when deal with timing for granting
extension of time:
(a) EoT must not be granted too late to
be effective in keeping liquidated
damages provisions alive; and
(b) EoT must not be granted too late to
allow the contractor to re-programme his work.
In the case ofMillerv LCC (1934) 151 Lt
425, the contract provided for the whole
of the work to be completed by 15
November 1931. There was a provision
for the Engineer to grant extension of
time retrospectively. Work was
completed on 25 July 1932. On 17 Nov
1932 Engineer issued Certificate
granting extension to 7 February 1932.
It was held that the phrase to assignsuch other time for completion
contemplated exercise of the power
within a reasonable time of the delay
and a retrospective extension came too
late to be effective. A power to extend
the time had therefore not been
exercised within the time limited by the
contract, the building owner has lost the
benefit of the clause, i.e. there was no
date from which penalties could run
and no liquidated damages could be
recovered.
In Amalgamated Building Contractorsv
Waltham (1952) 2 AER 452, Lord Justice
Denning declined to follow Millerwhich
he said turned on its particular wording
of the clause and the time fixed for
completion of work had been validly
extended.
In the relatively recent case of City Inn
Ltdv Shepherd Construction Ltd, Outer
House [2001], 2001 Greens Weekly Digest26-999, it was held that any EoT must be
condition on the Contractor putting in
the relevant application notice.
The contract was the Joint Contracts
Tribunal (JCT) Standard Form of Building
Contract Private Edition with Quantities
1980 edition (PAM form of contract is
based on JCT 63), with a schedule ofamendments appended. This schedule
inserted into the conditions an additional
clause 13.8.
The most relevant par t of the clause,
clause 13.8.5 stated:
If the Contractor fails to comply with
one or more of the provisions of Clause
13.8.1, where the Architect has not
dispensed with such compliance under
Clause 13.8.4, the Contractor shall notbe entitled to any extension of time
under Clause 25.3.
Lord MacFadyen said:
For present purposes, what is
significant is that the clause 13.8.5
clearly states that the consequence of
failure on the part of the Contractor to
comply with any one or more of the
provisions of clause 13.8.1 is loss of
entit lement to an extension of time.
Further, he stated:
I am therefore of the opinion that
failure on the part of the Contractor to
comply with one or more of the
provisions of clause 13.8.1 is probably
to be regarded as a breach of contract
on his part.
Conclusion
Generally, the Contractor ought to submit
to the S.O./Engineer/Architect /P.D. the
relevant notices to inform about the
delaying event(s) and that the Contractor
will be seeking the corresponding EoT
within the timeframe set down under the
relevant contract. A failure to do so on the
part of the Contractor may deprive
(dependent on the wording of the
relevant clauses for EoT under thecontract) the Contractor of any EoT.
The advice to any Contractor is to ensure
that the notice of delay is submitted
within the timeframe to avoid being in a
situation where due to his not compliance
will be considered a breach of contract
and therefore the Contractor is disallowed
for EoT for such a breach.
If in the unfortunate event that the
Contractor failed to submit in the relevantnotice of delay, the only obvious possible
argument for getting the appropriate EoT
is to raise the Prevention Principle where
the Employer cannot take advantage of its
own wrong in enforcing a contract.