eot1

download eot1

of 3

Transcript of eot1

  • 8/2/2019 eot1

    1/3

    rticleA

    By the Entrusty Group

    Is The Contractor Obliged To Apply ForExtension Of Time ?

    Your Contractual Questions Answered

    The Entrusty Group, a multi-disciplinary group of companies, of which, one of their specialisations is inproject, commercial and contractual management, has been running a regular contractual question-and-answer section for MBAM members in Master Builders Journal.

    In this instalment of the series, the Entrusty Group will provide the answer to the frequently asked questionabove.

    Construction contracts usually have

    a fixed time frame for theContractor to complete the works

    (i.e. time is of the essence time being a

    fundamental term of the contract). PAM

    98 cl 21.1, PAM 69 cl 21 (1), JKR 203/A cl 38

    (b), IEM cl 38 (a), CIDB cl 17.1 JKR PWD DB/

    T cl.39.2 refer to Possession of Site and

    Commencement.

    Consequently, PAM 98 cl 21.1, PAM 69 cl

    21(1), JKR 203/A cl 38 (b), IEM cl 38 (a), CIDB

    cl 17.1 (a) and JKR PWD DB/T cl. 39.2 also

    specify the Contractors primaryobligation to complete the Works by the

    completion date. If the Contractor fails to

    complete the Works by the Date for

    Completion or within the extended time,

    the Contractor is in breach. Under Section

    75 of the Contract Acts 1950 (CA 1950) the

    Contractor shall bear the damages

    suffered by the Employer.

    Purpose Of Extension Of Time Clauses

    The main provision of EoT clauses is to allowfor any alteration to the completion date. It

    is also to preserve the Employers rights to

    deduct Liquidated Damages. The two major

    effects of time extension clause(s) under

    construction contracts are as follow:

    (a) The extent to which the Contractor

    could be made liable for liquidated

    damages in the event of a delay to the

    completion of the Works;

    (b) The fact that extensions of time aregranted on account of delays

    attributable to some act by the

    Employer may afford a basis for a

    claim by the Contractor against the

    Employer for time related damagesand disruption losses.

    Hudsons Building and Engineering

    Contracts, 11thEdition, p 624explains the

    rationale for such clauses:

    It has been seen that, for the purpose

    of treating the contract as repudiated,

    in the rare cases where time is of the

    essence, the contract time for

    completion may cease to be applicable

    for a variety of reasons, including theordering of extras or other interference

    or prevention by the employer. In the

    case of damages, it is equally obvious

    that where the reason is some act of the

    employer or his architect or engineer

    preventing completion by the due date,

    it cannot be the intention of the parties

    that liquidated or other damages

    should be calculated from that date

    even if the act, such as ordering extras,

    is not a breach of contract. Liquidated

    damages stipulated for at a rate foreach day or week of delay in completing

    the works must begin to run from some

    definite date. It follows, therefore, that if

    the date in the contract has for some

    such reason ceased to be the proper

    date for the completion of the works,

    and no contractual provision exists for

    the substitut ion of a new date, there is

    such a case no date from which

    liquidated damages can run and the

    right to liquidated damages will have

    gone. This, rather than solicitude for thecontractor, is the reason for the

    provision usually known as the

    extension of time clause.

    EoT and liquidated damages clauses are

    closely linked, and failure by the Architect/Engineer/S.O/P.D. to properly exercise his

    power to extend time, where any delay is

    caused by the Employer (or for which the

    Employer is responsible in law), relieves

    the Contractor from his liability to pay

    liquidated damages. As a result, the courts

    have consequently ruled that the clause(s)

    are to be interpreted contra proferentum

    against the Employer.

    Contractual Provisions For EoT

    Generally, the Contractor is to give written

    notice of delay and cause/s to the

    Architect/Engineer/S.O/P.D. when it is

    apparent that the progress of works is

    delayed for him to assess and grant EoT.

    PAM cl 23, IEM/JKR cl 43, CIDB cl 24, and

    JKR PWD DB/T cl. 45.1 are the relevant

    clauses for EoT.

    For the Contractor to claim for EoT, the

    grounds for such claim for EoT must fall

    within the specific events as listed in thecontract. Any event falling outside the

    listed events does not entitle the

    Contractor to any EoT. The grounds for EoT

    applications can be divided into two basic

    categories:

    (a) Neutral events, e.g. force majeure,

    exceptionally inclement weather, civil

    commotion, strike or lockout,

    availability of materials not due to the

    Contractors fault, etc.

    (b) Defaults by the Employer and/or his

    agents, e.g. late decision/information

    of the Architect/Engineer/S.O/P.D.,

    85

  • 8/2/2019 eot1

    2/3

    rticleA

    late site delivery, compliance with the

    Architect/Engineer/S.O/P.D., delay by

    the Employers agents, delay by

    nominated sub-contractors/

    suppliers, etc.

    PAM/IEM/JKR203/A/PWD DB/T requires

    the Contractor to use his best endeavourto prevent delay in the works and do all

    that may be reasonably required and

    satisfaction of the Architect/ Engineer/

    S.O/P.D. to proceed with the works.

    CIDB Form is much more procedural and

    comprehensive on extension of time

    provisions:

    Cl 24.1 Extension of Time

    Cl 24.2 Notice of Delay

    Cl 24.3 Superintending Officers DecisionCl 24.4 Interim Decision of Extension

    of Time

    Cl 24.5 Superintending Officers

    Discretion

    Cl 24.6 Certificate of Extension of Time

    Cl 24.7 Review of Superintending

    Officers Decision

    CIDB s/cl 24.3 requires the S.O. to notify

    the Contractor in writing within 30 Days

    of notice receipt or further information,

    whether in his opinion the delay event isone which in principle entitles to an EoT.

    Under the CIDB contract, it also allows the

    S.O. to grant EoT even when he considers

    that there is insufficient information to

    decide on the Contractors application.

    In general, in deciding any EoT, the S.O.

    shall take into account the following

    matters:

    (a) EoT previously granted, if any;(b) The effect/extent of work omitted or

    decrease in the quantity of any work

    resulting from re-measurement;

    (c) Any concurrent delays with the

    delaying event/s including those

    due to the Contractors acts or

    defaults.

    The CIDB contract under s/cl 24.4 allows

    the S.O. to make interim decision on EoT

    where a delaying event has continuing

    effects and to decide an overall EoT on theevent within 30 Days of receipt of final

    particulars, by reviewing all the

    circumstances.

    Whilst s/cl 24.5 allows the S.O. absolute

    discretion to grant a fair, reasonable and

    necessary EoT even if the Contractor fails

    to comply with the EoT provisions.

    S/cl 24.6 requires the S.O. to notify the

    Contractor of any decision in granting

    extension of time in a certificate(Certificate of Extension of Time), copied

    to the Employer and nominated sub-

    contractors/nominated suppliers.

    86

    S/cl 24.7 allows the S.O. to review any

    previous EoT granted at any time prior to

    issuance of Final Certificate either to fix a

    Tim e for Com pletion later than that

    previously granted or confirm thatpreviously fixed.

    Contractors Obligations For Applying

    For EoT

    Generally, there is a duty imposed on the

    Contractor to notify the Architect/

    Engineer/S.O. in writing as soon as the

    progress is delayed. The objective is to

    ensure that the Architect/Engineer/S.O. is

    aware that the completion period may not

    be met and that the Contractor is pre-warned of the triggers off time whether or

    not the reason of such delay is within one

    of those grounds or the Contractors own

    inefficiencies.

    It is desirable that the notice should specify

    the cause of the delay but even if the notice

    does not contain sufficient details to

    enable the Architect/Engineer/S.O. to form

    an opinion as to whether the cause of delay

    falls within one of those specified grounds,

    it is still valid. Thus, the requirement ofnotice of delay is not a condition precedent

    to the granting of an extension of time by

    the Architect/Engineer/S.O. However, this

    could be taken into account in granting an

    extension of time.

    In London Borough of Mertonv Stanley

    Hugh Leach (1985) 32 BLR 51, it was

    decided that a written notice is not a

    condition precedent to granting EoT. The

    Architect is under an independent duty to

    do so. Mr Justice Vinelott went on to saythat failure by the contractor to give

    notice of delay was itself a breach of

    contract and this could have some effect

    on his right to an extension of time. If the

    architect, because of failure by the

    contractor to give notice of delay, was

    unable to avoid or reduce a delay to

    completion, the contractor should have

    no greater extension than if he had given

    notice.

    The legal principle here is that no oneshould benefit from his own breach of

    contract (The Prevention Principle) and is

    closely allied to the duty to mitigate.

  • 8/2/2019 eot1

    3/3

    rticleA

    MBJ

    87

    In the next issue of the MBAM journal the article will answer the question on Is the

    Contractor still entitle to Extension of Time when there is concurrent delay?

    The Entrusty Group includes Entrusty Consultancy SdnBhd (formerly known as J.D. Kingsfield (M) Sdn Bhd), BK

    Burns & Ong Sdn Bhd (a member of the Asia wide group BK

    Asia Pacific) , Pro-Value Management, Proforce Management Services Sdn Bhd/Agensi

    Pekerjaan Proforce Sdn Bhd and International Master Trainers Sdn Bhd. Apart from

    project, commercial and contractual management services, the group also provides risk,

    resources, quality and value management, recruitment consultancy services and

    corporate training programmes to various industries, particularly in construction and

    petrochemical, both locally and internationally.

    Entrusty Group will provide 30 minutes of free consultancy with prior appointment to

    MBAM members on their contractual questions. The Group also provides both in-house

    and public seminars/workshops in its various areas of expertise. For further details,please visit website: www.entrusty.com. or contact HT Ong or Wing Ho at 22-1& 2 Jalan

    2/109E, Desa Business Park, Taman Desa, 58100 Kuala Lumpur, Malaysia. Tel: 6(03)-7982

    2123 Fax: 6(03)-7982 3122 Email:[email protected]

    There is also an obligation imposed on

    the Contractor to constantly use his best

    endeavour to prevent delay. Th e

    Contractor shall also do all that may

    reasonably be required to thesatisfaction of the Architect/Engineer/

    S.O. to proceed with the work.

    There are two issues to be considered

    when deal with timing for granting

    extension of time:

    (a) EoT must not be granted too late to

    be effective in keeping liquidated

    damages provisions alive; and

    (b) EoT must not be granted too late to

    allow the contractor to re-programme his work.

    In the case ofMillerv LCC (1934) 151 Lt

    425, the contract provided for the whole

    of the work to be completed by 15

    November 1931. There was a provision

    for the Engineer to grant extension of

    time retrospectively. Work was

    completed on 25 July 1932. On 17 Nov

    1932 Engineer issued Certificate

    granting extension to 7 February 1932.

    It was held that the phrase to assignsuch other time for completion

    contemplated exercise of the power

    within a reasonable time of the delay

    and a retrospective extension came too

    late to be effective. A power to extend

    the time had therefore not been

    exercised within the time limited by the

    contract, the building owner has lost the

    benefit of the clause, i.e. there was no

    date from which penalties could run

    and no liquidated damages could be

    recovered.

    In Amalgamated Building Contractorsv

    Waltham (1952) 2 AER 452, Lord Justice

    Denning declined to follow Millerwhich

    he said turned on its particular wording

    of the clause and the time fixed for

    completion of work had been validly

    extended.

    In the relatively recent case of City Inn

    Ltdv Shepherd Construction Ltd, Outer

    House [2001], 2001 Greens Weekly Digest26-999, it was held that any EoT must be

    condition on the Contractor putting in

    the relevant application notice.

    The contract was the Joint Contracts

    Tribunal (JCT) Standard Form of Building

    Contract Private Edition with Quantities

    1980 edition (PAM form of contract is

    based on JCT 63), with a schedule ofamendments appended. This schedule

    inserted into the conditions an additional

    clause 13.8.

    The most relevant par t of the clause,

    clause 13.8.5 stated:

    If the Contractor fails to comply with

    one or more of the provisions of Clause

    13.8.1, where the Architect has not

    dispensed with such compliance under

    Clause 13.8.4, the Contractor shall notbe entitled to any extension of time

    under Clause 25.3.

    Lord MacFadyen said:

    For present purposes, what is

    significant is that the clause 13.8.5

    clearly states that the consequence of

    failure on the part of the Contractor to

    comply with any one or more of the

    provisions of clause 13.8.1 is loss of

    entit lement to an extension of time.

    Further, he stated:

    I am therefore of the opinion that

    failure on the part of the Contractor to

    comply with one or more of the

    provisions of clause 13.8.1 is probably

    to be regarded as a breach of contract

    on his part.

    Conclusion

    Generally, the Contractor ought to submit

    to the S.O./Engineer/Architect /P.D. the

    relevant notices to inform about the

    delaying event(s) and that the Contractor

    will be seeking the corresponding EoT

    within the timeframe set down under the

    relevant contract. A failure to do so on the

    part of the Contractor may deprive

    (dependent on the wording of the

    relevant clauses for EoT under thecontract) the Contractor of any EoT.

    The advice to any Contractor is to ensure

    that the notice of delay is submitted

    within the timeframe to avoid being in a

    situation where due to his not compliance

    will be considered a breach of contract

    and therefore the Contractor is disallowed

    for EoT for such a breach.

    If in the unfortunate event that the

    Contractor failed to submit in the relevantnotice of delay, the only obvious possible

    argument for getting the appropriate EoT

    is to raise the Prevention Principle where

    the Employer cannot take advantage of its

    own wrong in enforcing a contract.