EOL Analysts PPT finalJune 2010 - Essar Group · 2010. 7. 27. · 1 Achieved highest throughput of...
Transcript of EOL Analysts PPT finalJune 2010 - Essar Group · 2010. 7. 27. · 1 Achieved highest throughput of...
Essar Oil Limited
A l t P t tiAnalyst PresentationJuly 27, 2010
Essar Oil LimitedEssar Oil Limited
A world-class, low cost Indian integrated energy company
Refining Exploration & Production Marketing
High impact E&P platformLow cost refining complex centred around
Vadinar supersitePan India Presence through Retail Network
1
Capitalise on India’s rapidly growing energy demand
Essar Oil - E&P HighlightsEssar Oil - E&P Highlights
1 Rajmahal block awarded by MoPNG. 3 more blocks from CBM-IV round with in-place resource of 733mmboe also awarded to EOL, execution of contracts expected shortly
Total Reserve Portfolio increased to 2132 mmboe from 1400 mmboe
Gas production from 15 test wells drilled under Phase I being ramped up with progressive dewatering3
2
Gas production from 15 test wells drilled under Phase – I, being ramped up with progressive dewatering
4
3
Test production of gas from Raniganj to commence by Q2 FY2011 & Commercial Production to start by Q3 FY 2011
Drilling activities for Raniganj (phase – II ) commenced with 8 pilot wells & 36 surface holes drilled5
FY 2011
Development Plan envisaging drilling of 500 wells submitted to DGH, under review6
Term Loan of Rs. 575 crore tied up with Bank for phase – I of Raniganj Project7
Essar Oil – Refining Operation, Expansion Project & Retail Business HighlightsRetail Business Highlights
1 Achieved highest throughput of 3.68 MMTPA for Q1 FY2011 against 2.76 MMTPA for Q1FY 2010
2
Achieved highest throughput of 3.68 MMTPA for Q1 FY2011 against 2.76 MMTPA for Q1FY 2010
76% of products slate comprises light & middle distillates & processed 66 % of Heavy or Ultra Heavy crude
3 Supply of Mangala Crude from Cairn India begun with 25000 bpd through heated pipeline at Refinery
4 Refinery Expansion Phase I to increase capacity to 18 mmtpa largely on track, scheduled to start the commercial production on time - Overall progress of 62%
5 Supporting Infrastructures including the pipeline completed to avail the Natural Gas at Refinery Project Site
Deregulation of Motor Spirit price by the Govt of India to provide level playing field6
7 Strategy to increase the Retail outlets to 1700 by March, 2011 to increase retail sales & profitability
C l t d A t ith GAIL f tti CNG tl t ll I di B i t t il tl t8 Completed Agreement with GAIL gas for setting up CNG outlets on all India Basis at our retail outlets
Essar Oil – Financial Highlights ( Q1 FY 2010 – 11)Essar Oil Financial Highlights ( Q1 FY 2010 11)
1 G R f R 12048 D ti & E t R ti 70% & 30%
EBIDTA Rs. 407 crores against Rs 665 crore in corresponding quarter ended June -092
1 Gross Revenue of Rs. 12048 crore; Domestic & Export Ratio : 70% & 30%
EBIDTA Rs. 407 crores against Rs 665 crore in corresponding quarter ended June 092
3 GRM 5.61 $/ bbl as against $ 6.74/bbl for corresponding quarter ended June -09
Essar Energy plc, holding company of Essar’s refinery, E&P and power businesses listed at London Stock Exchange, raised USD 1.95 billion
3
4 Essar Energy Plc infused USD 225 million of Equity and USD 262 million through FCCBs in Essar Oil
5 Funds to be used for Refinery Phase – I Expansion, E&P activities and other corporate purpose
6 Essar Energy Plc included in FTSE – 100 within one month of its listing
Essar Energy London ListingEssar Energy London Listing
5
Essar Energy London ListingEssar Energy London Listing
6
Essar Energy London ListingEssar Energy London Listing
7
Essar Energy London ListingEssar Energy London Listing
8
Industry TrendsIndustry Trends
Gasoil FO Jet Gasoline
Cracks on Products
88
Global Oil Demand
$7.03 $11.33 $7.42 $7.28 $7.33
$9.37 $11.74
$7.00 $9.81 $10
$15 87.44
86.2885.83
85.33 85 28
85.88 86.0785.82
86.987.2
86
87
88
$6.98 $6.22 $8.94
$(3.01)
$7.13
$2.86
$7.37
$-
$5 85.33
84.4784.1
85.28
84
85
$(5.84)$(3.01)
$(4.52)$(6.69)
$(10)
$(5)
April - Jun, 09 Jul - Sept, 09 Oct - Dec,09 Jan - Mar,10 April - Jun,10
82
83
1Q08 2Q08 3Q08 4Q08 1Q09 2Q09 3Q09 4Q09 1Q10 2Q10 3Q10 4Q10
Source :IEA
3.103.00
3.50
16.0 MS (% growth) HSD (% Growth)
April Jun, 09 Jul Sept, 09 Oct Dec,09 Jan Mar,10 April Jun,10
Petro Product Growth in IndiaArab Light & Arab Heavy Difference
1.701.55
1.951.60
1.50
1.95
1 70
1.751.50
2.05
2.80
1.50
2.00
2.50
7.4
11.3
9.0
13.9
11.19.0
8 0
10.0
12.0
14.0
1.50
1.201.70 1.50
0 00
0.50
1.00
1.50
4.54.8
6.9 6.78.4
2.0
4.0
6.0
8.0
9
0.00 1.40.0
2004-05 2005-06 2006-07 2007-08 2008-09 2009-10Source :PPAC
CEO’s MessageCEO s Message
• Petroleum Products demand in India continue to demonstrate strong growthPetroleum Products demand in India continue to demonstrate strong growth
supported by growth in Indian economy, increase in per capita income, growth in
hi l d G t f i f t t divehicles and Govt. focus on infrastructure spending
• India will remain the anchor market for Essar’s expanded refinery capacity
• Deregulation of Gasoline price with a clear roadmap for freeing up of Gasoil price, will
create healthy competition among players and benefit the consumers
• Essar will continue to expand its retail network to realise the deregulated market
opportunities.
• Focus on E&P business to transform the image of company from being a pure refiner
to an integrated Oil & Gas player.g p y
• Refinery Phase – I Expansion, focus on Indian Retail Marketing & E&P business will
deliver the growth & value for our stakeholders.
10
deliver the growth & value for our stakeholders.
Exploration & ProductionExploration & Production
11
Essar Oil – Exploration & ProductionEssar Oil – Exploration & Production
Key highlights High impact E&P platform
40176
2500
Oil Gas
Reserves & resources (mmboe)(a)
1 Diverse portfolio of offshore and onshore oil & gas blocks971 2132
931
1762000 Developing as a leading CBM player - lower risk and with
significant demand and exciting growth profile2
Attractive economics for onshore CBM resources versus offshore 3
49
1500
Raniganj –2C and best estimate prospective resources: 993bcf CSG; commercial production by end 2010; gross peak production: 4
Attractive economics for onshore C M resources versus offshoregas in India - favourable fiscal terms and lower opex and capex
3
1012
963
19571000
5
3.5mmscm/d
Rajmahal – Best estimate prospective resources: 4.7tcf (CBM)
87
500
6 Sohagpur, Talcher & IB valley CBM blocks- 4.4 tcf inplace resources as per DGH estimates150
630
2P & 2C Contingent Resources
Best Estimate Prospective Resources
Unrisked / Inplace
Resouces
Total Resources
Total investment to date c.US$160mm
International and other domestic – Unrisked/in-place resources of over 238 mmboe
7
$
(a) Subject to necessary approvals. Please refer to next slide for further details
Source: Company information, ARI, RPS Energy, NSAI
12
A high impact Indian-led E&P platformA high impact, Indian-led E&P platform
Mehsana(a) Rajmahal(b) Vietnam(e)
70% interest (ESU)2P reserves: 2mmbbl (oil)Potentially significant CBM play
100% interest in CBM blockBest estimate prospective resources: 4.7tcf CBM gas (787mmboe)
100% interest in block 114Unrisked/undiscovered in-place resources: 1.0tcf gas (167mmboe)
Nigeria(c)(e)
CPR by ARI (2010)
100% interest in offshore block OPL 226 – in discussion with local partner to farm down to 63%2C and best estimate
O h ASP(NE)-CBM-2008/IV(b)
Ratna /R Series(d)
prospective resources (based on 63% interest): 126mmboe (f)
(48% oil) CPR by NSAI (2010)
Other Assets
Assam (e) (100% interest): Unrisked/undiscovered in-place resources: 10mmboe (oil)
Mumbai Offshore (e) (50% interest): U i k d/ di d i l
( )
100% interest in block
TL-CBM-2008/IV(b)
IB-CBM-2008/IV(b)
50% interest2C resources: 81mmboe (92% oil, 8% gas)Commercial production: Q4 CY2013(d)
d k
Raniganj(c)
100% interest2C and best estimate
Unrisked/undiscovered in-place resources: 186bcf (31mmboe)
Indonesia (e) (49.5% interest): Unrisked/undiscovered in-place resources: 30mmbl (oil)
( )
100% interest in these 2 blocks
Expected gross peak production: 35kbbl/d
prospective resources: 993bcf CBM gas (165mmboe)Trial production: Q2 CY2010Expected gross peak production: 3.5mmscm/d (g)
CPR by NSAI (2010)2P reserves/ 2C and prospective resources
Madagascar(e)
Australia(e)
SP(NE)-CBM-2008/IV, TL-CBM-2008/IV, IB-CBM-2008/IV(b)
Note: Reserves and resources data is working interest, adjusted to reflect Essar Oil’s interest(a) Signed PSC for Oil; CBM rights subject to government approval and modification in government policy(b) Awarded by GOI under CBM IV round (c) Signed PSC
13
Unrisked Rresources
2P reserves/ 2C and prospective resources (d) PSC expected to be signed shortly, which is subject to a government approval process(e) Subject to necessary approval for transfer to Essar Oil(f) c.22mmboe (2C) of gas classified as development not viable(g) Relates to 2C and best estimate prospective resourcesSource: Company information
Details of Major E&P blocks with reserves and resource estimatesestimates
2P/ 2CBest estimate prospective
C C t
Assets Ownership
2P/ 2C resourcesp p
resourcesCapex Comments
Oil Gas Total Oil Gas Total (US$ mn) Opex Peak Prodn.
mmbbl Bcf mmboe mmbbl Bcf mmboemmbbl Bcf mmboe mmbbl Bcf mmboe
Raniganj (CBM) 100% - 201 33-
792 132 439$0.43/ mmbtu
3.5 mmscm/dTest production commenced.
Moving to commercial developmentp
Rajmahal (CBM) 100% -- - -
4,723 787 4Large acreage. Situated in rich
coal belt
Potentially significantMehsana 70% (b) 2 - 2 - - - 4 - -
Potentially significantCBM play
Ratna/ R-Series 50% (a) 74 40 81-
- 568 $5.3/bbl 35k bbl/dDiscovered fields.
Development to commence post signing of PSC
Nigeria 63% (c) 11 136 33 49 264 93 16Located in proven Nigerian
petroliferous basin
Total 87 377 149 49 5779 1012
(a) For Ratna / R-Series, balance 50% is held by ONGC (40%) and Premier Oil (10%)
(b) For Mehsana (ESU oil field) balance 30% ownership is held by ONGC
14
(b) For Mehsana (ESU oil field), balance 30% ownership is held by ONGC
(c) In discussion with local partner to farm down to 63%
CBM Projects – location & resources
JAMMU AND KASHMIRJAM M U AN D K ASH M IRRajmahal CBM Block
CBM Projects location & resources
CHANDIGARH
Intern
ation
al Bord
er
PUNJAB
SRINAGAR
SHIMLA
Pithoragarh
UTTARANCHALDEHRADUN
Uttarkashi
HaridwarAlmora
C H A N D IG A R H
Intern
ationa
l Bor
der
PU N JAB
S R IN A G A R
S H IM L A
P itho ragarh
U TTAR AN C H ALD E H R A D U N
U ttarkash i
H a ridw arA lm o ra
DELHIGurgaon
In
Jaisalmer
Udaipur
Amla
RAJASTHANJodhpur
Nagaur
Bikaner
JAIPUR
HARYANA
Banda
GUNA (VIJAIPUR)
Kanpur
Naini Tal
LUCKNOW
Pithoragarh
UTTAR PRADESH
Shanjahenpur
Faridabad
Almora
International Border
Jagdishpur
GayaBIHAR
PATNA
Madhubani
Maharajganj Darjiling
GANGTOK
ARUNACHAL PRADESH
MANIPUR
URA
IMPHAL
ITANAGAR
SHILLONG
DISPUR
MEGHALAYANAGALA
ND
KOHIMA
ASSAM
D E LH IG urgaon
In
Ja isa lm er
U da ipur
A m la
R AJASTH ANJodhpur
N agaur
B ikan er
JA IP U R
H ARYAN A
B anda
G U N A (V IJA IP U R )
K anpur
N ain i T a l
L U C K N O W
P itho ragarh
U TTAR PR AD ESH
S hanjahenpur
F aridabad
A lm o ra
International Border
Jagdishpur
G ayaB IH AR
P A T N A
M adhuban i
M ahara jgan j D a rjiling
G A N G T O K
AR U N AC H AL PR AD ESH
M AN IPU R
URA
IM P H A L
ITA N A G A R
SH ILLO NG
D IS P U R
M E G H ALAYANAGALA
ND
K O H IM A
ASSAM
MAHARASHTRA
Hoshangabad
NashikSILVASSA
GUJARATRajkot
KndlaMundra
JAMNAGAR
BhujGK ON90/2
HAZIRA (HBJ INTERCONNECT)
Vadodara
AHMEDABAD
Dungarpur
Kheda
Bhavnagar
Godhra
GANDHINAGAR
CB ON1Udaipur
Palanpur
UjjainDevas
DharJhabua INDORE
Ratlam
Mandsaur
WARDHA Kendrapara
GarhchiroliChandrapur
Yavatmal
Adilabad
BHUBANESHWAR
BhawanipatnaKhurda
CUTTACK PARADEEPPuri
CHHATISGARH
JabalpurMADHYA PRADESH
Damoh
Betul
Nagpur
(HBJ INTERCONNECT)GUNA (VIJAIPUR)
BHOPAL
Bina
RAIPUR
Bilaspur
Rewa
Bokaro
WEST BENGAL
JHARKHANDAmbikapur
SambalpurORISSA
BIHAR
RANCHI
Jamshedpur
Medinipur
Baleshwar
Baripada
KOLKOTA
DhanbadAGARTALA
TRIP
UR
MIZ
OR
AM
AIZWAL
M AH AR ASH TR A
H oshangabad
N ash ikS IL V A SS A
G U JARATR a jkot
K nd laM undra
JA M N A G A R
B h ujG K O N 90 /2
H A ZIR A (H B J IN T E R C O N N E C T)
V a d od ara
A H M E D A B A D
D unga rpur
K h e da
B havnagar
G odhra
G A N D H IN A G A R
C B O N 1U da ipur
P alanpur
U jja inD evas
D harJhabua IN D O R E
R a tlam
M andsaur
W A R D H A K endrapa ra
G arhch iro liC handrapur
Y ava tm a l
A d ilabad
B H U B A N E S H W AR
B haw an ipatnaK hurda
C U TT A C K P A R A D E E PP uri
C H H ATISG AR H
Jaba lpurM AD H Y A PRAD ESH
D am oh
B e tu l
N agpur
(H B J IN TE R C O N NE C T)G U N A (V IJA IP U R )
B H O P A L
B ina
R A IP U R
B ilaspu r
R ew a
B okaro
W EST B EN G AL
JH ARK H AN DA m b ikapu r
S am ba lpurO R ISSA
B IH AR
R A N C H I
Jam shedpur
M ed in ipur
B aleshw ar
B aripada
K O L KO T A
D hanbadA G A R TA LA
TRIP
UR
MIZ
OR
AM
A IZ W A L
Raniganj CBM Block
Anantapur
Bellary
Zahirabad
Raichur
GOA
Karwar KARNATAKA
KOLHAPUR
Pune
RatnagiriDABHOL
Kudal
TROMBAYURAN
Alibag
Thane
Osmanbad
Sangli
GokakBijapur
Bid
KAKINADARajahmundry
ANDHRA PRADESH Ongole
Guntur
Khammam
KondapalleVIJAYAWADA
Kurnool
Mahbubnagar
HYDERABAD
DundigalBidar
Nizamabad
Adilabad
Eluru Yanam
Uppada
Vizianagaram
VISHAKHAPATNAM
A nan tapu r
B e lla ry
Z ah irabad
R a ichur
G O A
K arw ar KAR N ATAKA
K O L H A P U R
P u ne
R a tnag iriD A B H O L
K udal
T R O M B A YU R A N
A liba g
T ha ne
O sm anbad
S angli
G okakB ijapur
B id
K A K IN A D AR a jahm undry
AN D H R A PRAD ESH O ngo le
G un tur
K ham m am
K o nd a pa lleV IJA Y A W A D A
K urnoo l
M ahbubnagar
H Y D E R A B A D
D und iga lB ida r
N izam abad
A d ilabad
E lu ru Y anam
U ppada
V iz ia nagaram
V IS H A K H A P A TN A M
Sohagpur CBM BlockTalchir CBM Block
Coimbatore
Udhagamandalam
p
KE
RALA
Ernakulam
KK08
SURATHKAL Hassan
MadikeriMangaloreKasargod
NagapattinamThanjavur
Nellore
Kanchipuram
Cuddalore
ENNOREKolar
TiruchirappalliTAMILNADU
BANGALORE
PONDICHERRYVillupuram
Vellore
Chittoor
C o im batore
U dh agam anda lam
p
KE
RALA
E rnaku lam
K K 08
S U R A T H K A L H assan
M ad ikeriM anga loreK asa rgod
N agapa ttinamThanjavur
N ello re
K anch ipuram
C udda lo re
E N N O R EK o lar
T iruch irappa lliTAM ILN AD U
B A N G A LO R E
PO N D IC H E RR YV illupu ram
V e llore
C hittoor
IB Valley CBM Block
15
AlappuzhaKAYANKULAM
Kollam
Ramanathapuram
TUTICORINTiruneveli
A la pp u zhaK A Y A N K U LA M
K ollam
R am ana thapuram
T U T IC O R INT iruneve li
Emerging as a significant player in CBM segment in the country
15
15Emerging as a significant player in CBM segment in the country
Leading CBM gas player in IndiaLeading CBM gas player in India
Details of CBM Block Place Ownership Acreage2P/ 2C
resources
Best estimate prospective
Unrisked in-place resource
TotalRemarksDetails of CBM Block Place Ownership Acreage resources
resourcesplace resource Remarks
Bcf Bcf Bcf Bcf
Raniganj Calcutta 100% 500 Sq km 201 792 - 993 CPR by NSAI (2010)
R j h l Jh kh d 100% 1128 k 4 723 4 723 CPR b ARI (2010)Rajmahal Jharkhand 100% 1128 sq. km - 4,723 - 4,723 CPR by ARI (2010)
SohagpurM.P. &
Chhattisgarh100% 339 sq. km 600 600 As per DGH
Talche Orissa 100% 557 sq. km 2,600 2,600 As per DGH
500 sq. km
q p
IB Valley Orissa 100% 209 sq. km - - 1,200 1,200 As per DGH
Total 2733 sq km 201 5,515 4,400 10,116
Leading CBM player in the country with 2733 sq km of acreage & more than 10 TCF of reserve
and resources in place under five blocks.
Presence in major key market having deficit of unconventional gases
Experience Team of 100 engineers & technical staffs with avg. experience of more than 8 years
in the field of execution & operation of CBM project.
Deployment of innovative industry standard technologies for drilling & production from CBM Wells
16
Essar owns a versatile fleet of oil well rigs, core hole rings, air drilling rigs & other critical equipment
Raniganj – low risk development to serve customers in Eastern India’s gas deficit industrial beltEastern India s gas deficit industrial belt
Field overview
Resources
Onshore block, located in Damodar Valley coal field in the Raniganj region of West Bengal
Resources993bcf (165mmboe) of 2C and best estimate prospective resources (CBM gas), CPR by NSAI (2010)
Interest /operator
100% interest, Essar Oil is operator
Current status17 information wells 15 test wells drilled; gas flow startedAwaiting approval of development plan
Key milestones500 wells to be drilled over the life of the assetTrial production sales planned for Q2 FY2010Key milestones Trial production sales planned for Q2 FY2010Commercial production expected by December 2010
Government take and pricing
Royalty at the rate of 10% of well-head price is payable to the government of West Bengal. Production level payments (PLP) linked to a percentage of revenue are
Production profile
4.0
and pricing also payable to the Government of India, based on a formula
Capex to full d l t
Capex to full development: c.US$439mn– to be funded 70/30 debt/equity
1 5
2.0
2.5
3.0
3.5
n (m
msc
m/d
)
development – capex figure reflects estimated expenditure for both 2C and prospective resources
Opex guidance US$0.43/mmbtu
Capex guidance and CY 2010 : c US$97mn (net share)
0.0
0.5
1.0
1.5
09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
Pro
duct
ion Capex guidance and
phasingCY 2010 : c.US$97mn (net share)CY 2011 : c.US$131mn (net share)
Other Cost/well: US$0.63mn
Evacuation Pipeline being built (48 KM)
17
Source: Company information, NSAINote: FY ended March 31st. Production profile reflects both 2C and best estimate prospective resources
FY0
FY1
FY1
FY1
FY1
FY1
FY1
FY1
FY1
FY1
FY1
FY2
FY2
FY2
FY2
FY2
FY2
FY2
FY2
FY2
FY2
FY3
FY3
FY3
FY3
FY3
FY3
FY3
FY3
FY3
FY3
FY4
FY4
FY4 Evacuation Pipeline being built (48 KM)
Customers Philips Carbon, Matix Fertilizers already signed up
Pictorial progressPictorial progress… Raniganj… Raniganj (From Well to Market)(From Well to Market)Pictorial progressPictorial progress… Raniganj … Raniganj (From Well to Market)(From Well to Market)
Air Drilling Rig For CBMAir Drilling Rig For CBM PC Pumps running at test wellsPC Pumps running at test wells Separators installed at test wellsSeparators installed at test wells
Pipe line ConstructionPipe line Construction Plantation at test well sitePlantation at test well site Gas flareGas flare
18
Refining & MarketingRefining & Marketing
19
Operational Performancep
Crude Throughput Crude Mix
120%13.50
12
14
25% 22% 28%19%
100%
120%
Ultra Heavy Heavy Light
6
8
10
52% 51%46%
47%
28%
60%
80%
2.76 3.60 3.68
2
4
6
24% 27% 26%34%
20%
40%
-QE0609 Full Year-10 QE0310 QE0610
0%
QE0609 Full Year-10 QE0310 QE0610
Processed more than 20 types of crudesProcessed 3.68 Million ton of crude, highest Processed more than 20 types of crudes
during the Quarter including ultra heavy &
tough crudes like Ras Gharib, Merey etc.
throughput for any quarter as against 2.76
million ton in corresponding previous quarter
Avg. API (Density) – 32.4 , Avg. Sulphur % –
1.70 and Avg. TAN – 0.30
( due to shut down)
Continuous to optimise the capacity utilization
ith li d it tili ti th
20
Beginning the processing of Mangla crudewith annualized capacity utilization more than
14 mmtpa)
Operational Performancep
Sales MixProduct Slate
23% 24% 25% 28%
100%
Light Middle Heavy
52% 49% 44%
24% 25% 28%
60%
80%
31%
52% 49% 44%46%
20%
40%
26% 27% 31% 26%
0%
QE0609 FY 2010 QE0310 QE0610
Optimised production of middle & light distillates – High margin segment
Continue to focus on domestic market due to
better price realization of petro products
Heavy Distillates includes positive margin Bitumen converted from low margin FO.
Captured 14% share of bitumen market in India
Reduction in retail sales due to increase in petro
21
Reduction in retail sales due to increase in petro
product prices in international market
Retail Marketing : Pan India Presence with Flexiblebusiness modelbusiness model
1First private company in India to enter petro retailing sector (2003) through a franchisee model
( Capex investment by Dealers)
Deregulation of MS prices by GOI to provide level playing field, expecting freeing up of HSD prices shortly
Expansion of Retail outlets to 1700 by March 2011 from existing 1344 Retail outlets3
2
Expansion of Retail outlets to 1700 by March, 2011 from existing 1344 Retail outlets.
4
3
Existing Indian PSUs sales per retail outlet per month : 153 KL ( MS : 37 KL and HSD : 116 KL)
Avg. sales of Petro Products at our Retail outlet to increase to 100 KL perm month per outlet from existing 40KL subject to deregulation of HSD prices by GOI
5
g p p ( )
Focus on Gujarat & Western India Market due to Sales Tax benefit & logistic advantage6
Focus on Non Fuel Retail services like Lubricants, Batteries, Ticket Booking, ATM, Food Parlor, Agro Productsetc to generate additional revenue stream for both the Company & the franchisee
7
Refinery ExpansionRefinery Expansion
23
Essar Energy – Refiningssa e gy e g
Key highlights Increasing capacity and complexity
1 Low cost, safe and efficient operations – refinery operating cost US$1-2 per barrel lower than global peers
Capacity (MT)Current March 2011
36
Strategically located on the west coast of India2
1418
Crude slate geared towards heavy crudes (89% of crude mix
Increasing complexity from 6.1 to 11.8 following Phase 1, enhancing crude and product flexibility
3
T t l l tiToday
Post Phase I
Post Phase II
Vadinar currently one of India’s largest refineries: will be 5
Crude slate geared towards heavy crudes (89% of crude mix comprises of heavy and ultra-heavy crude) post phase - I
4Total cumulative capex( US$2.7bn US$4.4bn US$9.15bn
Total incrementalcapex – US$1.7bn US$4.75bn
y gamongst the top 5 globally at 750k bbl/d post Phase 2
5
Timing for Phase 2 to be determined based on a review of k di i d i f fi i l l
6
Complexity: 6.1 11.8 12.8
API (density) avg.: 31.3 24.8 24.0
Sulphur % avg.: 1.6% 3.0% 3.0%
Expansion at competitive capex cost; cost/complexity/bbl of $1011 and $962 post Phase I & Phase II respectively
7
market conditions and attainment of financial closure6
Product grade: Euro III/IV Euro IV/V Euro V/ US Spec/
CARB
24
Expansion at highly competitive capexpa s o at g y co pet t e cape
New grass roots refineries – capacity vs capex New refineries capex – country average
60,000 30,000
40 000
50,000
20 000
25,000
30,000
40,000
$/bp
d)
15,000
20,000
$/bp
d)
20,000
Cap
ex ($
World average: US$23,400/bpd
10,000
Cap
ex ($
10,000
Essar Energy currentEssar Energy post phase 1
Essar Energy post phase 2
5,000
00 100 200 300 400 500 600 700 800
0World
averageChina Saudi
ArabiaIndia Essar
Energy current
Essar Energy
post
Essar Energy
post
25
Note: The timing for Phase 2 will be finished based on a review of market condition and attainment of financial closureSource: KBC, Company information
Capacity (kbp/d)current post
phase Ipost
phase II
Top quartile cost performer globallyTop quartile cost performer globally
43.65
3
3.5
2.25
2
2.5
(US
$/bb
l)
1.331.15 1.06
0 741
1.5
Cos
t (
0.70
0.30
0.64
0.15
0.74
0.450.31 0.39 0.39
0.26 0.310.20 0.19
0
0.5
Lagg
ards
Aver
age
Essa
r Ene
rgy
Lagg
ards
Aver
age
Essa
r Ene
rgy
Lagg
ards
Aver
age
Essa
r Ene
rgy
Lagg
ards
Aver
age
Essa
r Ene
rgy
Lagg
ards
Essa
r Ene
rgy
Aver
age
Lagg
ards
Aver
age
Essa
r Ene
rgy
Total costs (US$/bbl) Manpower costs (US$/bbl)
Operations variable costs (US$/bbl)
Asset management costs (US$/bbl)
Purchased energy costs (US$/bbl)
Other overhead costs(a) (US$/bbl)
(a) In addition to the above refinery operating costs, additional costs of US$0.96/bbl were incurred for product handling charges and other corporate and marketing expenses during FY09Note: Categorisation of average and Laggard refineries as per KBC analysis Laggards representative of fourth quartile performance Essar Energy costs relate to 2009/10 operational costs as estimated by KBC
26
Note: Categorisation of average and Laggard refineries as per KBC analysis. Laggards representative of fourth quartile performance. Essar Energy costs relate to 2009/10 operational costs as estimated by KBC. Asset management costs comprise costs of shutdown, turnaround, equipment maintenance and repair, and other routine maintenance. Operations costs relate to costs associated with catalysts, chemicals and demurrages
Source: KBC
Competitive gross refining margin
Indian Complex Refinery Singapore Complex Margin
Competitive gross refining margin
11.60
15.00
12 20
14.00
16.00 Average premium: US$5.23/bbl
10.30 12.20
8 00
10.00
12.00
M (U
S$/b
bl)
US$ 7.34/bbl
6.60 6.48 6.11
7.66
5.79 4.00
6.00
8.00
GRM
3.49
-
2.00
4.00
2006 2007 2008 2009 2010
GRMs expected to improve with increased complexity and capacity
Utilization of Mangla Crude, Natural Gas & Coal to further boost the GRM
27
g ,
Global refining margin outlookGlobal refining margin outlook
Benchmark refining margins
14
16
10
12
14
(US
$/bb
l)
6
8
10
finin
g m
argi
ns (
2
4
6
Gro
ss re
f
0
2
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024
North West European Brent Singapore-Dubai US Gulf Coast WT I Reliance Industries Indian margin (a)
Refining margins expected to recover from 2011 onwards
28Source: KBC, Reliance Industries
Refining margins expected to recover from 2011 onwards
(a) Forecast made prior to Union Budget
Expansion to provide crude as well as product flexibility
Light6%
Light11%
Ultra-heavy
Expansion to provide crude as well as product flexibility
6%
Heavy31%
11%
Heavy25%
Light28%
heavy20%
e m
ix
Ultra-heavy63%
Ultra-heavy64%
Heavy52%
Crud
14MT 18MT 36MT
Light Heavy end
15%Light
distillatesHeavy end
15%Light di till t
Heavy end
14MT(current)
18MT(expected post phase 1 expansion)
36MT(expected post phase 2 expansion)
distillates29%
Propylene3%Middl
15%22%
VGO10%Middl
15%distillates22%
Fuel loss6%
y25%
uct
yiel
d
3%
Fuel loss5%
Middle distillates
48%
10%
Fuel loss4%
Middle distillates
49%
Middle distillates
47%Prod
u
14MT 18MT 36MT
Processing an increasingly high proportion of high sulphur and low API crudes
Focus on delivery of higher margin products (middle/light distillates)
(current) (expected post phase 1 expansion) (expected post phase 2 expansion)
29
Note: Ultra-heavy crude defined as having API<25, heavy crude with API 25 – 33, light crude with API>33Dar and Mangala crude with high tan and wax content classified as heavy crudeProduct yield – fuel and loss does not include natural gas
Source: Company information
Yield to shift to higher grade products…optimal for export markets
Conversion of entire negative margin fuel oil into high value added products and pet coke
Building higher flexibility between light and middle distillates
export markets
1 5
g g y g
Flexibility to produce petrochemical feed stock
Euro IV & V grade at 87% in Gasoline pool and 78.4% in Diesel pool
8.8
1.5
LPG/Naptha
Gasoline
Euro III13.0%
Euro V49 9%
Gasoline: 8.8 MT
Diesel
Jet/Kero
Euro IV37.0%
49.9%
Euro IIIDiesel: 13.6 MT
13.6
2.5
1.4
Jet/Kero
Fuel Oil
21.5%
Euro IV47.2%`
0 6
3.9
5 6
7.7
2.30.7Coke
Propylene
Euro V31.2%
0.9 1 92.0 0.5
1.01.8
4.1
2.7
0.6
0.6
1.01.2
5.6
Others
Fuel& Loss / Residue
30
0.7 1.90.8
14 MT 18MT 36 MTNote: Others include bitumen, sulphur and HDT VGOSource: Company information
Phase 1 – Refinery Expansion Project Status : 62%
Basic E i i
Detailed E i i Procurement Construction
Phase 1 Refinery Expansion Project Status : 62%
All long lead items orderedBalance items to be
OSBL pipe racks are in advanced stage of completion
Engineering Engineering Construction
Model reviews completed
All Basic Engineering C l d Balance items to be
ordered by July-10.87 % Piping Bulk material ordering Completed & 41 % f i i l
advanced stage of completion & piping erection progressing in various fronts.ISBL Pipe rack , Technological structures & Heater works are
completed
Drawings released for all major civil
Completed
Short / Long Lead items’ Datasheets
% of pipes materials received at site.Total 579 out of 1523 Nos of Mechanical Tagged
structures & Heater works are progressing in full swing.Structural Steel fabricated & 5458 MT erected
Structure, Heater, Piping & Tankages works
Drawings for E & I works
issuedfor procurement
Schedule A packageEquipment received at site.
22673 MT of Tankages Fabrication & 19317 MT Erection Completed.
gare in Progress.
Schedule A package for all Units received.
31
Heavy Lift erection in the operational area (CDU/VDU/SGU)- 153 MT y p
32
OVERALL VIEW – PROCESS UNITS (REFINERY EXPANSION PROJECT)
33
DELAYED COKER UNIT- CIVIL WORKS FOR COKE DRUM STRUCTURE
34
1st Heavy Lift for Expansion Project - 342 MT & CHIMNEY WORKS AT 325 MW POWER PLANT 62 MTR OUT OF 220 MTR325 MW POWER PLANT- 62 MTR. OUT OF 220 MTR.
35
MAIN INTERCONNECTING PIPERACK ‘C’
36
REFORMER & EQUIPMENT ERECTION WORKS AT HYDROGEN MFG. UNIT
37
TANKAGE & PIPING WORKS FOR BS III
38
PIPING WORKS AT PIPERACK ‘K’PIPING WORKS AT PIPERACK K
39
Vadinar Power Plant Expansion : Bird eye view of GTG 1 & 2 AreaVadinar Power Plant Expansion : Bird eye view of GTG 1 & 2 Area
HRSG 1HRSG 2
HRSG 1
GTG 1
GTG 2
GTG-1
GTG-2
Supporting Infrastructure : Port / Jetty (Earlier)Supporting Infrastructure : Port / Jetty (Earlier)
41
Simultaneous loading operations ongoing at Berths A & B t V di ( t i )A & B at Vadinar (post expansion)
42
Financial HighlightsFinancial Highlights
43
Financial ResultsFinancial Results
ParticularsQE FY QE QE
Particulars 2009-10Jun-09 Mar-10 Jun-10Throughput - Million Tones 2.76 13.50 3.60 3.68 INCOME Income from operation 7 876 42 303 11 886 12 024Income from operation 7,876 42,303 11,886 12,024 Less : Excise duty & Taxes 1,334 5,897 1,489 1,517 Net Income from operation 6,542 36,406 10,397 10,507 Other Income 39 200 92 24 Total Income 6,580 36,606 10,489 10,531 EXPENDITURE Cost of Goods Sold 5,825 34,263 9,781 9,834 Operating Expenditure 256 1 077 285 281Operating Expenditure 256 1,077 285 281 Forex Loss/( Gain) (166) (661) (246) 9 Total Expenditure 5,915 34,679 9,819 10,124
EBITDA 665 1,927 670 407
Interest & Finance Charges 282 1,170 310 299 Operational Cash Profit 383 757 359 108Operational Cash Profit 383 757 359 108 Depreciation 179 728 182 181 PBT 203 29 178 (73)Tax 34 (1) - (3)
44
PAT 170 29 178 (70)GRM (USD/bbl) $ 6.74 $ 4.38 $ 5.12 $ 5.61
Comparative GRMComparative GRM
45
• Health Safety Environment
• Corporate Social Responsibilityp p y
46
Safe and efficient operationsSafe and efficient operations
The Refinery achieved 14.34+ Million Man Hours of Safe Operation with out any Lost Time Incident.
820 Lost Time Incident free da s on 30th J ne 2010 No fatalities at refiner since start of commercial
Safety
820 Lost Time Incident free days on 30th June, 2010, No fatalities at refinery since start of commercial production from 1 May 2008
Refinery received GREENTECH Safety Gold Award in Petroleum Refining Sector for outstanding achievement in Safety Management
Refinery received ISO 9001 and 14001 and OHSAS 18001 certification & Won British Safety Council International Award for 2009
Compliant with all the concerned environmental regulations
R i d 2 d i i th “F /B il I l ti Eff ti ” t f th MOPNG’ (a) Oil &
Reliability
Received 2nd prize in the “Furnace/Boiler Insulation Effectiveness” category of the MOPNG’s(a) Oil &
Gas Conservation Awards (2008) in its very first year of operation
The refinery’s laboratory has participated in an international Inter Laboratory Cross Check Programme (ILCP) conducted by ASTM committee, to benchmark to international standardsyPlanning and execution of major shutdowns on schedule
Received ‘Golden Peacock Award” for Occupational Health & Safety for the year 2010’ by the Golden Peacock Jury
On-stream factor of c100% in fiscal year ended March 2009
ff
Laboratory is ISO certified
Refinery capable of consistently operating at 14MT with simultaneous operation of all secondary processing plants at more than 100% capacity
Efficiencyp g p p y
Fuel and losses reduced from c7% in FY08 to c6% currently
High quality, bespoke MIS system – the Essar Refinery Integrated Management Systems (ERIMS)
Kitchen waste bio gas plant was inaugurated on 24th June’10 generating about 20kg of LPG per day.
(a) Ministry of Petroleum and Natural Gas
47
CSR - Community Development Program at VadinarCSR - Community Development Program at Vadinar
Operate 24hrs
operative Essar
Community
Health
Center, Mobile
Clinic, Mother &
Child C dChild Care and
OPD Centers.
Eye diagnosis and
surgery camp
organized jointly g j y
with District
Blindness
EradicationEradication
committee and
Shivand
Mission, Virnagar
48
Key Value DriversKey Value Drivers
E&P
CBM – Raniganj to
start commercial
Significant potential
of other CBM and Oil Execution of PSC for Ratna E&P start commercial
production by Q4
CY2010
of other CBM and Oil
& Gas blocks & R-series
Refining
Refinery Optimization started with processing of 25000 bpd Mangla Crude &
Phase – I Expansion to increase the
Phase – II expansion to increase throughput to 36Refining 25000 bpd Mangla Crude &
utilization of Natural Gas to begin in Q3 CY, 2010
to increase the throughput to 18 MMTPA
increase throughput to 36 MMTPA
Di t ib tiExpansion of Retail Outlets to 1700 by
Build on International Deregulation of S d l l l iDistribution Outlets to 1700 by
March, 2011distribution capabilityMS, created level playing
field for private sector
49
50