Environmental Safeguard Monitoring Report
2018 Annual Environmental Monitoring Report November 2018 Part 1 of 2: [Main Report]
INO: Loan 2817- Regional Road Development
Project
Prepared by Project Management Unit, Directorate of Road Network Development, for the
Directorate General of Highways, Ministry of Public Works and Housing and the Asian
Development Bank.
NOTES
(i) The fiscal year (FY) of the Government of Indonesia ends on 31 December. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2011 ends on 31 December 2011.
(ii) In this report, "$" refers to US dollars. This environmental safeguard monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
REPUBLIC OF INDONESIA
MINISTRY OF PUBLIC WORKS AND HOUSING
DIRECTORATE GENERAL OF HIGHWAYS
DIRECTORATE OF ROAD NETWORK DEVELOPMENT
TECHNICAL ASSISTANCE FOR SUPPORT OF
PROJECT MANAGEMENT UNIT OF REGIONAL ROADS DEVELOPMENT PROJECT
UNDER: ADB LOAN NUMBER 2817-INO AND IDB FINANCING NUMBER IND-0161
2018 ANNUAL ENVIRONMENTAL
MONITORING REPORT
(January - September 2018)
Joint venture between:
RENARDET S.A. CONSULTING ENGINEERS
In association with
PT. Multi Phi Beta
PT. Widya Graha Asana
PT. Disiplan Consult
PT. Anugerah Kridapradana
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
i
ABBREVIATIONS
ADB Asian Development Bank
AMDAL Indonesian Environmental Impact Assessment (Analisis Mengenai Dampak
Lingkungan Hidup)
ANDAL Indonesian Environmental Impact Statement (Analisis Dampak Lingkungan
Hidup)
BLHD Regional Environmental Agency (Badan Lingkungan Hidup Daerah)
CTC Core Team Consultant
DSC Design and Supervision Consultant
DGH Directorate General of Highway (Direktorat Jenderal Bina Marga)
Dinas PU Provincial Public Works Agency (Dinas Pekerjaan Umum Provinsi)
EMP Environmental Management Plan
EMMP Environmental Management and Monitoring Plan (the checklist issued by DGH
as part of the contract specification)
GOI Government of Indonesia
GRM Grievance Redress Mechanism
IEE Initial Environmental Examination
MPWH Ministry of Public Works and Housing
PIU Project Implementation Unit
PMU Project Management Unit headed by the Director of Road Networks
Development Directorate
RKL Indonesian Environmental Management Plan (Rencana Pengelolaan
Lingkungan)
RPL Indonesian Environmental Monitoring Plan (Rencana Pemantauan Lingkungan)
RRDP Regional Roads Development Project
SDERS Sub-Directorate of Environmental Affairs and Road Safety
SPPL Statement letter to commit conducting environmental management and
monitoring (Surat Pernyataan Kesanggupan Pengelolaan dan Pemantauan
Lingkungan Hidup)
UKL-UPL Indonesian Environmental Management Effort and Environmental Monitoring
Effort Document (Upaya Pengelolaan Lingkungan - Upaya Pemantauan
Lingkungan)
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
ii
TABLE OF CONTENTS
TABLE OF CONTENTS .................................................................................................. II
LIST OF TABLES .......................................................................................................... III
LIST OF FIGURES ......................................................................................................... III
APPENDICES ................................................................................................................ III
PART I. INTRODUCTION ........................................................................................... 1
1.1. Project Background.............................................................................................. 1
1.2. Objectives and Scope of the Monitoring Report ................................................... 1
PART II. ROAD CONSTRUCTION PROGRESS IN 2018 ............................................ 3
PART III. ENVIRONMENTAL MANAGEMENT PLAN................................................... 5
3.1. Roles and Responsibilities ................................................................................... 5
3.2. EMP Implementation by Executing Agencies ....................................................... 9
3.3. EMP Implementation by DSC ............................................................................ 10
3.4. EMP Implementation by Contractors .................................................................. 12
3.5. Public Consultations and Grievance Redress Mechanism ................................. 13
PART IV. ENVIRONMENTAL MONITORING .............................................................. 14
4.1. Environmental Approval and Permit for Road Construction ................................ 14
4.2. Environmental Approval and Permit for AMP and Quarry/Borrow Pit ................. 14
4.3. Monitoring Results ............................................................................................. 15
4.3.1 Ambient Air Quality .................................................................................................... 16
4.3.2 Noise Monitoring Data ............................................................................................... 17
4.4. Environmental Monitoring by the DSC ............................................................... 18
PART V. CTC SITE INSPECTION .............................................................................. 24
PART VI. KEY ISSUES FOR RESOLUTION ............................................................... 27
PART VII. CONCLUSIONS AND RECOMMENDATIONS ............................................ 28
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
iii
LIST OF TABLES
Table 1: Contract Work Packages Completed in 2018 .................................................................... 4
Table 2: EMP Implementation by the DGH, SDERS, PMU, and CTC ............................................ 9
Table 3: EMP Implementation by the DSC .................................................................................... 11
Table 4: Contractor’s EHS Personnel for Ongoing Projects in 2018 ............................................. 12
Table 5: Environmental Approval and Permit of Road Sections (as of September 2018) ............ 14
Table 6: Environmental Approval and Permit for AMP and Quarry (as of September 2018) ........ 15
Table 7: Ambient Air Quality Monitoring Results for CW-01, Central Java ................................... 16
Table 8: Ambient Air Quality Monitoring Results for CW-05, West Kalimantan ............................ 16
Table 9: Ambient Air Quality Monitoring Results for CW-11, North Kalimantan ............................ 17
Table 10: Noise Monitoring Results ............................................................................................... 18
Table 11: Environmental Monitoring Undertaken by DSC ............................................................. 19
Table 12: Non-Compliance/Issues Identified, Corrective Action and Its Status as of 2018 .......... 25
Table 13 : Key Issues and Required Corrective Actions ............................................................... 27
LIST OF FIGURES
Figure 1: RRDP Organizational Structure – National Government Level ........................................ 6
Figure 2: RRDP Organizational Structure – West Kalimantan ........................................................ 7
Figure 3: RRDP Organizational Structure – North Kalimantan ........................................................ 7
Figure 4: RRDP Organizational Structure – Central Java ............................................................... 8
Figure 5: Grievance Redress Mechanism ..................................................................................... 13
APPENDICES
Appendix A Implementation of Environmental Mitigating Measures – Construction Phase
Appendix B CW-01 Quarry Environmental Approvals and Permits
Appendix C Air Quality and Noise Monitoring Results for CW-01, CW-05 and CW-11
Appendix D CW-01 Site Closure Reports and Related Documents
- Validity sheet PT. PP Persero - Environmental Mitigation site Closure - Minutes of Meeting Join Inspection for Confirmation of AMP, Quarry and Base Camp -
Site Map Quarry and Base Camp CW-01 - Picture Evidence for Confirmation of Site Closer - Contactor's Statement Letter about Operation of AMP and Quarry is still on-going - Statement letter from community
Appendix E CW-08 Site Closure Reports and Related Documents
- Picture Evidence of Confirmation of Site Closure - DSC-1 Letter about AEMR Action Plan - Asphalt Drum request by Local Community member
Appendix F CW-09 Site Closure Reports and Related Documents
- Picture Evidence of Confirmation of Site Closure
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
iv
- DSC-1 Letter about AEMR Action Plan - Environmental Permit of Stone Crusher and AMP Plant, Kabupaten Bulungan - Contractor Letter about discontinuity of Base Camp, AMP and Quarry - Contractor Letter about discontinuity of AMP
Appendix G CW-10 Site Closure Reports and Related Documents
- Picture Evidence of Confirmation of Site Closure - DSC-1 Letter about AEMR Action Plan - Contractor Letter about discontinuity of AMP
Appendix H CW-11 Site Closure Reports and Related Documents
- Minutes of Meeting (Berita Acara 29 June 2018) : - Handing Over of Base camp from Halla Corporation to PT. Daya Mulia Turangga - Handing over of AMP, Heavy Equipment from Halla Corporation to PT. Daya Mulia
Turangga - Handing over of stock piles, Jetty Material from Halla Corporation to PT. Daya
Mulia Turangga - Statement Letter from Contractor that AMP will not be used anymore for work package
CW-11 - Photographs of Closed Site - Statement Letter from community that there was no negative environmental impact as
result of the operation of the AMP, base camp and road construction of CW-11 - Statement Letter from Contractor that empty asphalt drums were used for fencing of
base camp and as water containers for watering of palm trees - Request letter from community for empty asphalt drums; and pictures of how they were
used
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
1
PART I. INTRODUCTION
1.1. Project Background
1. The Regional Roads Development Project (RRDP) is financed through a Project Loan
from the Asian Development Bank (ADB) and the Islamic Development Bank (IDB). The
executing agency of the RRDP is the Directorate General of Highways (DGH), known as
Direktorat Jenderal Bina Marga (Ditjen Bina Marga) of the Ministry of Public Works and
Housing (MPWH) also known as Kementerian Pekerjaan Umum dan Perumahan Rakyat.
The public works and public housing sectors were merged and became MPWH since
October 2014.
2. The RRDP aims to improve important national and strategic road corridors in Northern
Kalimantan and Southern Java to encourage economic growth in these two (2) less
developed areas of Indonesia. The rehabilitation, capacity expansion and construction of
new roads will improve connectivity and access to services in the above-mentioned
provinces. Improved road infrastructure in southern Java is necessary for increased
economic growth to increase access to markets and attract investment in that area. Road
network development in Kalimantan will promote economic and regional development in
currently less developed and remote areas. Further, it will improve access of poor rural
and minority villages to income generating opportunities and social services, particularly in
North Kalimantan.
3. The RRDP consists of eleven (11) construction work (CW) packages/sub-projects,
including rehabilitation, improvement or construction of about 476 km of roads and
bridges distributed in four (4) provinces of Indonesia, namely West Kalimantan, North
Kalimantan, Central Java, and East Java. Further, the works include rehabilitation or
replacement of bridges equal to approximately 3.9-km long and construction of 40.0-km
long of new roads along agricultural areas where there are existing earthen tracks in
some sections.
4. Most of the civil works under the RRDP includes widening and partial reconstruction of
the existing road of more than 400-km long to a minimum width of 6 m with some minor
deviations. All subproject roads are designed as 2-lane and 2-way roads, which consist of
6-m carriage ways plus 2 x 1-m hard shoulder and 2 x 1-m side ditch. New alignment has
also been constructed along existing tracks and/or delineated areas. Rehabilitation,
asphalt pavement, and widening works have been undertaken on existing substandard 2-
lane gravel or asphalt roads which are strategic to meet the national highway standards.
1.2. Objectives and Scope of the Monitoring Report
5. The main objectives of this Annual Environmental Monitoring Report (AEMR) are to
briefly present the progress of RRDP in a period of January to September 2018, marking
completion of the RRDP construction. This report analyzes environmental mitigation and
monitoring activities implemented in this period. Further, the status of corrective actions
undertaken in response to non-compliances identified by Core Team Consultant (CTC)
site inspections for the mentioned period in 2018 is updated in this report, including
community complaints and Grievance Redress Mechanism (GRM) conducted, if any. This
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
2
2018 AEMR is the final environmental monitoring report submitted for the implementation
phase of the RRDP.
6. This 2018 AEMR is prepared based on data and information that are extracted and
analyzed, as available, from: Design and Supervision Consultant (DSC) Monthly
Environmental Reports for the mentioned period; corresponding Core Team Consultant
(CTC) Environmental Specialist Site Visit Reports; and correspondences and verbal
communication among the contractors, DSC, and CTC. In particular, the environmental
mitigation and monitoring described in this AEMR are based on available evidence and
assessed against each aspect detailed in the EMP of the IEE (approved 2011), which is
the key environmental document for the RRDP. The Core Team Consultants (CTC),
comprising Renardet S.A. Consulting Engineers in association with PT. Multi Phi Beta,
PT. Widya Graha Asana, PT. Disiplan Consult, and PT. Anugerah Kridapradana, have
prepared this 2018 AEMR.
7. The contents presented in the 2018 AEMR include:
Part I Introduction
Part II Road construction progress in 2018
Part III Environmental mitigation measures
Part IV Environmental monitoring
Part V CTC site inspection
Part VI Key issues for resolution, and
Part VIII Conclusions.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
3
PART II. ROAD CONSTRUCTION PROGRESS IN 2018
8. As of September 2018, all CW packages finished construction works. These are:
Central Java
CW-01 Tambak Mulyo-Wawar completed on 24 September 2018
West Kalimantan
CW-05 covering: Sosok – Tayan and Tanjung - Batas Kota Sanggau as schedule completed on 13 June 2018, but was 95% complete at end of September 2018.
North Kalimantan
CW-08 covering: Tanjung Selor - Simpang Tiga Tanjung Palas, and Simpang Tiga Tanjung Palas - Sekatak Buji (Section 1) completed on 30 January 2018
CW-11 covering: Simpang Tiga Apas -Simanggaris (Section-2) and Simanggaris – Border (Batas Negara, Serudong) completed on 30 June 2018
9. Based on this, the length of road sections has been changed with a total length of
486.08 km (out of 476 km planned) which includes 501.80 meters of bridges (out of 3.9
km planned) have already been completed. The changes in the road and bridge lengths
during project implementation were due to: a) slight changes in length of some road
sections due to re-measurement, b) changes to road alignment and specifications for
CW-07 (in West Kalimantan) to avoid passing through the protection forest, c) addition
of a new road section, CW-06: Sambas-Tanjung Harapan (12.3 kms.) in West
Kalimantan, and, d) changes in the road alignments for CW-11 Simpang Tiga Apas -
Simanggaris (Sect.-2) and Simanggaris – Batas Negara (Serudong) in North Kalimantan.
The respective project activities of the CW packages for 2018 are presented in Table 1
.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
4
Table 1: Contract Work Packages Completed in 2018
Package No. Road Section Total Length
(km) Contractor Activities and Progress as of September 2018
Central Java
CW-01 Tambak Mulyo – Wawar 38.46 Joint operation of PT Pembangunan
Perumahan (Persero) and PT
Armada Hada Graha
Project completed in September 2018. Works in 2018 covered:
embankment and side drainage works
spreading of Class S aggregate
spreading of AC-WC
installation of road signs and markers
improvement of foundation for Pier-1 and Pier-2 with boulder and geotextile
West Kalimantan
CW-05
Sosok – Tayan 41.60 Joint operation of PT Yasa Patria
Perkasa and PT Budi Bakti Prima
Project completed in June 2018. Works in 2018 covered:
embankment and side ditch works
spreading of Class S aggregate for shoulders
stone masonry and concreting works for retaining wall
pavement marking
Tanjung - Batas Kota Sanggau 37.60
North Kalimantan (This area was part of East Kalimantan Province prior to 2013)
CW-08
Tanjung Selor - Simpang Tiga
Tanjung Palas, and Simpang
Tiga Tanjung Palas - Sekatak
Buji (Section 1)
34.82 PT Waskita Karya Project completed in January 2018. Works in 2018 covered:
spreading of aggregate class S,
installation of road signs and road marking,
pouring of concrete for retaining wall.
spreading of Asphalt Cement-Base Course (AC-BC) and
Asphalt Cement-Wearing Course (AC-WC)
spreading of embankment/shouldering works
CW-11
Simpang Tiga Apas -
Simanggaris (Section-2)
27.15 Halla Corporation Project completed in June 2018. Works in 2018 covered:
spreading of common embankment
preparatory v-ditch works
spreading of class S aggregates for shoulders
spreading of AC-BC and AC-WC
stone masonry works for retaining wall.
Road marking and guard rail works
Simanggaris – Border (Batas
Negara, Serudong)
20.80
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
5
PART III. ENVIRONMENTAL MANAGEMENT PLAN
3.1. Roles and Responsibilities
10. There were no changes to the executing agency, contractors and consultants of
RRDP. The DGH is the executing agency responsible for the overall RRDP
implementation and has established the Project Management Unit (PMU) headed by the
Director of the Directorate Road Networks Development. Its function is to facilitate land
acquisition, resettlement, and environmental mitigation. An Officer in Charge has been
designated for the PMU to oversee day-to-day activities and prepare progress reports.
The PMU is assisted by the Core Team Consultant (CTC). The PMU in coordination with
the Project Implementation Units (PIU) and Sub-directorate for Environmental and Road
Safety (SDERS) of the Directorate Road Networks Development ensures that the
environmental management (mitigation and monitoring) plan (EMP) is implemented. The
Design and Supervision Consultants (DSCs) are required to conduct monitoring of the
EMP implemented by the Contractors and submit the corresponding monthly
environmental report to the DGH/PMU and CTC. Figure 1 presents the RRDP
organization structure at the national level.
11. Figure 2 to Figure 4 present the RRDP organization structure in West and North
Kalimantan as well as in Central Java. The RRDP implementation in East Java was
completed in 2016 and therefore no longer described in the 2018 AEMR. During the
construction stage, the Contractors, under the supervision of the DSCs, are primarily
responsible for EMP implementation of their respective CW packages. The DSCs
appointed for the RRDP are:
DSC-1: China Engineering Consultants, Inc., for the CW packages (CW-05 to CW-11)
in West and North Kalimantan; and
DSC-2: Botek Bosphorus Technical Consulting Corp., for the CW packages (CW-01
to CW-03) in Central Java.
12. The DSCs should prepare and submit the monthly environmental reports to the
DGH/PMU and CTC. The CTC appointed for the RRDP is Renardet S.A. and its joint
venture partners. Based on the monthly environmental reports submitted by the DSCs,
the PMU/DGH with the assistance of the CTC prepares the Semi-Annual/Annual
Environmental Monitoring Report (SAEMR/AEMR) for review and disclosure at ADB’s website.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
6
Figure 1: RRDP Organizational Structure – National Government Level
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
7
Figure 2: RRDP Organizational Structure – West Kalimantan
Figure 3: RRDP Organizational Structure – North Kalimantan
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
8
Figure 4: RRDP Organizational Structure – Central Java
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
9
3.2. EMP Implementation by Executing Agencies
13. The EMP of RRDP implemented by the DGH, SDERS, PMU, and CTC is reported in
Table 2. The category used to report the implementation status of the EMP is as follows:
“Implemented” meaning that the agencies have primarily performed and/or
accomplished their EMP responsibilities.
“Partially Implemented” meaning that the agencies have put some or partial efforts to
implement the EMP responsibilities and in some cases in an informal manner (without
documentation).
“Not implemented” meaning that the agencies have not implemented the EMP
responsibilities.
“Not applicable” meaning that the EMP responsibility of the agencies is no longer
relevant due to changes in their mandates or the project is already in the different
phases.
Brief justifications are also described for each of the status assigned in the table below.
Table 2: EMP Implementation by the DGH, SDERS, PMU, and CTC
Agency / Roles and Responsibilities Status as of 2018
Directorate General of Highways (DGH) as the Executing Agency/Project Director
Direct and supervise the Project
Management Unit (PMU)
Implemented – direction and supervision were conducted
through official memoranda and instructions.
Ensure that sufficient funds are available to
properly implement EMP.
Implemented - the cost of implementing the EMP is
included in the unit price of all pay items included in the
contract and deemed as full compensation for
environmental management of RRDP.
Ensure that EMP provisions are
implemented for the entire Project regardless
of financing resources.
Implemented - EMP provisions are integral part of the
General Specifications of the contracts awarded to RRDP
contractors.
Ensure that Project implementation complies
with the GOI and ADB’s environmental policy principles and requirements.
Implemented – implementation with these regards are
reported in the form of checklist and monthly report by
contractors and DSCs.
Ensure that tender and contract documents
include the EMP.
Implemented – EMP is included as part of the
specification of the contract document signed by the
Contractors.
Establish a grievance redress mechanism
(GRM) as described in the IEE
Implemented – GRM is established as part of the RRDP
(described elsewhere in this report).
Submit semi-annual monitoring reports
(SAEMR) on EMP implementation to ADB.
Implemented – semi-annual environmental monitoring
reports and annual environmental monitoring reports
were submitted to ADB.
Sub-directorate of Environmental and Road Safety (SDERS) responsible for environmental and
social monitoring
Set procedures for environmental
management and monitoring based on GOI
and ADB requirements.
Partially Implemented – these procedures were
established by requiring the road construction works,
asphalt mixing plant and quarry operations to secure with
ANDAL and RKL-RPL approvals, UKL-UPL approval, and
Environmental Permit as required by prevailing
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
10
Agency / Roles and Responsibilities Status as of 2018
Indonesian laws and regulations.
Coordinate with PMU to ensure that the EMP
is implemented properly and that required
monitoring and reporting are undertaken as
required.
Implemented – coordination was conducted through both
official communication and regular consultation.
Coordinate with BLHD offices at the District,
City, and Provincial Levels with regard to
compliance of the Project to GOI
environmental requirements.
Partially Implemented – coordination between SDERS
and local/provincial environmental agencies were
undertaken on ad hoc basis in relation to UKL-UPL
approval and Environmental Permit related to the road
sections of RRDP in CW-06, and therefore
documentation with this regard was scarcely produced.
Project Management Unit (PMU) provides day-to-day project management of RRDP
Include the EMP in tender and contract
documents.
Implemented - through the inclusion of Section 1.17
Environmental Safeguards in the RRDP Contract General
Specifications.
Ensure that EMP provisions are strictly
implemented during various project phases.
Implemented – through regular official site visits to each
CW package and site coordination with PPK, Satker
(working unit), and contractor concerned to environmental
mitigation and submission of official site visit reports.
Undertake monitoring of the implementation
of the EMMP (mitigation and monitoring
measures) with assistance from DSC.
Implemented - through site inspections undertaken by
PMU.
Ensure that DSC prepared monthly reports,
environmental monitoring reports for
submission to PMU/CTC.
Implemented - through DSC Monthly Environmental
Monitoring Report submission to PMU.
With support from CTC, prepare semi-annual
environmental monitoring reports for
submission to ADB.
Implemented - semi-annual and annual environmental
monitoring reports were submitted to ADB.
Core Team Consultants (CTC) provides project management support to PMU
Prepare semi-annual reports on EMP
implementation (mitigation measures,
establishment of ambient baseline data
baseline, ambient monitoring, etc.) based on
the monthly monitoring reports submitted by
DSC.
The semi-annual environmental monitoring
reports shall be submitted to ADB through
DGH/PMU.
Implemented - semi-annual and annual environmental
monitoring reports were submitted to ADB via DGH/PMU.
Develop an environmental auditing protocol
for the construction period for DSC’s guidance.
Implemented – through the use of EMMP as
environmental auditing instrument for the construction
period.
3.3. EMP Implementation by DSC
14. Table 3 presents the status of the DSCs on their responsibility in implementing the
EMP. The criteria used to determine the implementation status of the EMP are the same
as those used in Table 2. For this report and the succeeding environmental monitoring
reports, the status for DSC-3 is not presented since it has already been demobilized in
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
11
May 9, 2016 after the lone CW package under its supervision, CW-04, finished
construction activities in 2016.
15. The EHS engineer of DSC-2 previously mobilized in September 2017 has already
resigned in February 2018 while the EHS engineer of DSC-1 is still on the project. Be that
as it may, there are still EMP responsibilities of both DSC-1 and DSC-2 that remain either
partially implemented or not implemented.
Table 3: EMP Implementation by the DSC
Responsibilities DSC – 1: China Engineering Consultants Inc. (West and
North Kalimantan)
DSC – 2: Botek Bosphorus Consulting (Central Java)
Undertake regular monitoring of the
contractor’s implementation of the environmental mitigation measures
specified in the EMP
Partially Implemented –
environmental monitoring were
partially undertaken.
Partially Implemented - the
EHS engineer resigned in
February 2018. There is
improvement in environmental
monitoring reports that were
submitted to the PMU/CTC
Prepare monthly environmental
monitoring reports for submission to
DGH/PMU and CTC. Such reports
shall be the basis for the semi-
annual environmental monitoring
reports to be prepared by CTC for
submission to ADB.
Partially Implemented – the
monthly environmental
monitoring reports were
submitted by DSC to
PMU/CTC in the form of
checklist without adequate
supporting documents.
Partially Implemented – the
observation of DSC-2 with this
regard is the same as that of
DSC-1.
Engage an accredited/licensed
laboratory or institution to undertake
establishment of baseline data on air
quality, noise, and surface water
quality prior to commencement of
site works based on the EMMP.
Prepare corresponding reports for
submission to DGH/PMU and CTC.
Not applicable – since the
project was already in
construction phase in 2016,
and therefore environmental
baseline data was no longer
required.
Not applicable – the
observation of DSC-2 with this
regard is the same as that of
DSC-1.
Engage an accredited/licensed
laboratory or institution to conduct
sampling during construction phase
and in response to complaints or
when there are pollution events.
Prepare corresponding reports for
submission to DGH/PMU and CTC.
Implemented – air quality and
noise monitoring were
conducted by CW-05 and CW-
11 and the results were
presented in this report.
CW-08 finished construction
works in January 2018 which
did not give ample time for the
3rd
party provider to conduct
the sampling considering the
remoteness of the project site.
Implemented - air quality and
noise monitoring were
conducted by CW-01 and the
results are presented in this
report.
Review and approve the specific
environmental management plans
(Dust Suppression Program,
Sewage Management Plan, Solid
Waste Management Plan) to be
prepared by the contractors as
specified in the EMP
Not implemented - no specific
management plans as required
has been prepared by the
contractors.
Not implemented - the
observation of DSC-2 with this
regard is the same as that of
DSC-1.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
12
Responsibilities DSC – 1: China Engineering Consultants Inc. (West and
North Kalimantan)
DSC – 2: Botek Bosphorus Consulting (Central Java)
Provide on-the-job training to PU
Office, P2JN staff, provincial and
district DGH staff as well as to
province and district environmental
staff on monitoring of contractor's
environmental performance and
preparation of monitoring reports
Not implemented – no
evidence that this activity has
been undertaken.
Not implemented - the
observation of DSC-2 with this
regard is the same as that of
DSC-1.
Supervise civil works to ensure
compliance with the EMP
Partially Implemented - the
DSC site engineer provides
limited supervision on EMP
compliance.
Partially Implemented – the
observation of DSC-2 with this
regard is the same as that of
DSC-1.
Recruit an EHS manager who will be
responsible in ensuring that
environmental mitigation measures
specified in the EMP are
implemented properly
Partially Implemented – there
is an EHS engineer but there
is no proof that environmental
mitigation measures are
implemented properly
Partially Implemented - the
EHS engineer resigned in
February 2018.
Implement and provide sufficient
funding and human resources for
proper and timely implementation of
required mitigation measures in the
EMP
Partially Implemented - funding
and human resources were
provided for EMP
implementation, but this was
inadequate as mitigation
measures were partly
implemented.
Partially Implemented - the
observation of DSC-2 with this
regard is the same as that of
DSC-1.
Review and approve environmental
assessment reports required by the
Government.
Not applicable – the
environmental assessment
reports required for the project
were handled by the proponent
and SDERS.
Not applicable – the
environmental assessment
reports required for the project
were handled by the proponent
and SDERS.
Undertake monitoring of the project’s environmental performance based
on their mandate
Implemented – the DSC site
engineer monitored the project
environmental performance
and reported in the DSC’s monthly report submitted to
PMU/CTC.
Implemented - the observation
of DSC-2 with this regard is the
same as that of DSC-1.
3.4. EMP Implementation by Contractors
16. Table 4 presents the EHS personnel of the remaining Contractors for the RRDP
construction works in 2018. These contractors are responsible for the EMP
implementation of the road construction, AMP and quarry operations.
Table 4: Contractor’s EHS Personnel for Ongoing Projects in 2018
Package / Road Section (Contractor) EHS Personnel
Central Java
CW-01: Tambak Mulyo – Wawar
(PT Pembangunan Perumahan & PT Armada Hada Graha) Muhammad Iso
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
13
Package / Road Section (Contractor) EHS Personnel
West Kalimantan
CW-05: Sosok – Tayan; and Tanjung – Batas Kota
(PT Yasa Patria Perkasa & PT Budi Bakti Prima) Juliusman Laia
North Kalimantan
CW-08: Tanjung Selor - Intersection Tiga Tanjung Palas; Intersection Tiga
Tanjung Palas - Sekatak Buji (Section 1) (PT Waskita Karya)
Dhika Fatkhur Rakhman,
Fahrial
CW-11: Simpang Tiga Apas - Simanggaris (Section 2); and Simanggaris –
Batas Negara (Serudong) - (Halla Corporation) Sugiyana
3.5. Public Consultations and Grievance Redress Mechanism
17. No public consultations were conducted and also no public complaints formally
reported with regard to RRDP implementation in 2018. Nevertheless, the Grievance
Redress Mechanism (GRM) has been established as per Figure 5 below to address
public complaints or concerns related to the project, if any.
Figure 5: Grievance Redress Mechanism
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
14
PART IV. ENVIRONMENTAL MONITORING
4.1. Environmental Approval and Permit for Road Construction
18. As of September 2018, the AMDAL and UKL-UPL approval and the Environmental
Permit remain incomplete for few sections of CW-06 as presented in Table 5, whereas
the road construction of this package has been completed in December 2017.
Table 5: Environmental Approval and Permit of Road Sections (as of September 2018)
Package / Road Section Status
CW-06 in West Kalimantan
Tebas - Singkawang Section 1
(previously Singkawang overlay)
Length: 3.60 km
AMDAL approval No. 154/BLHD/2013 (dated 18 February
2013) granted by the Governor of West Kalimantan.
However, there is no record indicating whether the
corresponding Environmental Permit has been granted. Tebas - Singkawang (Section 2)
Length: 26.20 km
Sambas Bypass
Length: 6.10 km
There is no record indicating whether the UKL-UPL approval
and Environmental Permit for this road section exist.
4.2. Environmental Approval and Permit for AMP and Quarry/Borrow Pit
19. The asphalt mixing plants (AMP) and quarries/borrow pits owned/managed by the
RRDP contractors are required to secure UKL-UPL approval and Environmental Permit
from respective local environmental agency and/or local government. The status of these
approvals and permits as of September 2018 is presented in Table 6.
20. CW-01, CW-08 and CW-09 presented the environmental approval and
environmental permit for their quarry and AMP (please see Appendix B, E and
F). No evidences whether the UKL-UPL approval and environmental permit of the quarry
and AMP for CW-03 (Central Java), CW-04 (East Java) and CW-10 (North Kalimantan)
exists as of September 2018.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
15
Table 6: Environmental Approval and Permit for AMP and Quarry (as of September 2018)
CW Package/Road Section Status
Asphalt Mixing Plant Quarry/Borrow Pit
Central Java UKL-UPL
approval
Environmental
Permit
UKL-UPL
approval
Environmental
Permit
CW-01: Tambak Mulyo – Wawar Secured Secured Secured Secured
CW-02: Giriwoyo - Duwet Secured Secured Secured Secured
CW-03: Wawar – Congot Secured None None None
East Java
CW-04: Jolosutro – Sendang Biru None None None None
West Kalimantan
CW-05: Sosok – Tayan; Tanjung –
Batas Kota Sanggau
Secured Secured Secured Secured
CW-06: Tebas – Singkawang
(Sections 1 and 2); Sambas bypass;
Sambas – Tanjung Harapan; Galing
– Tanjung Harapan
Secured Secured Secured Secured
CW-07: Intersection Tanjung –
Galing; Aruk – Intersection Tanjung
Secured Secured Secured Secured
North Kalimantan
CW-08: Tanjung Selor – Intersection
Tiga Tanjung Palas – Sekatak Buji
(Section 1)
Secured Secured Secured Secured
CW-09: Intersection Tiga Tanjung
Palas – Sekatak Buji (Section 2)
None Secured None Secured
CW-10: Intersection Tiga Apas –
Simanggaris (Sections 1 and 2)
None None Not applicable as the
quarry material is
purchased from elsewhere
CW-11: Simpang Tinga Apas -
Simanggaris – Batas Negara
(Serudong)
SPPL (instead of UKL-UPL and
Environmental Permit) secured
Not applicable as the quarry
material is purchased from
elsewhere
4.3. Monitoring Results
21. There were four CW packages with ongoing construction works in 2018 required to
conduct an annual ambient air quality and semi-annual noise level monitoring. Three CW
packages conducted this monitoring. The results of this monitoring are described in the
following paragraphs. However, the lone CW package that did not conduct the
monitoring, CW-08, finished construction activities in January 2018 which did not give
enough time for the hiring and conduct of sampling by the 3rd party provider considering
the remote location of the project site. However, quality test results of ambient water, air
and noise tests conducted in 2017 have been provided.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
16
22. There were no complaints on water pollution reported in 2018, and therefore no water
quality sampling is required according to the IEE of RRDP (2011).
4.3.1 Ambient Air Quality
23. The ambient air quality monitoring results and corresponding interpretation for the
ongoing CW packages in Central Java, West Kalimantan and North Kalimantan (for 2018)
are described in the following paragraphs. The Government Regulation No. 41 of 1999
(GR 41/1999) on Air Pollution Control stipulates threshold values of selected air pollutant
parameters and are used as the reference for interpreting the analytical results presented
herein.
24. Central Java: CW-01. One-hour sampling of ambient air quality was conducted at
CW-01 at the Luk Ulo bridge construction site, and the samples were analyzed for total
suspended particulates (TSP) and particulate matter (PM10) as required by the IEE of
RRDP. The sampling location is located near residential areas. Vehicular traffic in this
area is minimal since this is a new road alignment and is still closed to motorists. The GR
41/1999 stipulates the threshold value of TSP and PM10 for 24-hour sampling is 230
µg/Nm3 and 150 µg/Nm3 respectively, but there is no stipulation for 1-hour sampling.
Therefore, the analytical results presented in Table 7 only provide a brief condition of the
TSP and PM10 concentration at a particular time and location within the road alignment.
25. For CW-01, the TSP and PM10 concentration of 21.11 µg/Nm3 and 29.33 µg/Nm3
respectively, were measured for 1-hour sampling at the specified sampling point and
these results are well below the threshold value stipulated in GR 41/1999.
Table 7: Ambient Air Quality Monitoring Results for CW-01, Central Java
No Road Section / Sampling Point (Sampling Date) TSP (µg/Nm3)1 PM10 (µg/Nm
3)1
CW-01: Tambak Mulyo – Wawar (Sampled on 17 April 2018)
1 Luk Ulo Bridge STA 17+250 21.11 29.33
Note: 1No threshold concentration of TSP and PM10 stipulated for 1-hour sampling in GR 41/1999.
26. West Kalimantan: CW-05. CW-05 conducted ambient air quality sampling for TSP
and PM10. It was not specified in the analytical results whether this sampling was
conducted for 1-hour or 24-hour period. The corresponding analytical results are
presented in Table 8.
27. At CW-05, the TSP and PM10 concentrations measured at three locations in 2018
were below the threshold value of 230 µg/Nm3 and 150 µg/Nm3, for TSP and PM10
respectively as stipulated in GR 41/1999
Table 8: Ambient Air Quality Monitoring Results for CW-05, West Kalimantan
No Road Section / Sampling Point (Sampling Date) TSP (µg/Nm3) PM10 (µg/Nm
3)
CW-05: Sosok – Tayan; Tanjung – Batas Kota Sanggau (Sampled 9 June 2018)
1 Aggregate Blending Plant in Bodok 118 99.7
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
17
No Road Section / Sampling Point (Sampling Date) TSP (µg/Nm3) PM10 (µg/Nm
3)
2 Quarry area `near house of Warga in Bunut 63.5 42.1
3 Sosok – Tayan road section 122 106
28. North Kalimantan: CW-11. CW-11 conducted 1-hour ambient air quality sampling for
TSP in front of the contractor’s compound where the AMP is also located. As shown in
the map, the area is sparsely populated with the few residences located nearby. As
previously mentioned, GR 41/1999 stipulates the threshold value of TSP for 24-hour
sampling as 230 µg/Nm3, but there is no stipulation for 1-hour sampling. Therefore, the
analytical results presented in Table 9 only provide a brief condition of the TSP
concentration at a particular time and location.
29. For CW-11, the TSP concentration of 36.45 µg/Nm3 measured for 1-hour sampling at
the specified sampling point is well below the threshold value of 230 µg/Nm3 stipulated in
GR 41/1999. No sampling result was presented for PM10.
Table 9: Ambient Air Quality Monitoring Results for CW-11, North Kalimantan
No Road Section / Sampling Point (Sampling Date) TSP (µg/Nm3) PM10 (µg/Nm
3)
CW-11: Simanggaris – Batas Negara (Serudong) (Sampled 6 April 2018)
1 Infront of contractor’s (Halla Corporation) offices 36.45 -
4.3.2 Noise Monitoring Data
30. The noise monitoring results for Central Java, West Kalimantan and North Kalimantan
CW packages are presented in Table 10, and are interpreted as follows:
31. Central Java: CW-01. The results of the noise sampling at Station 1: Luk Ulo bridge
shows that the noise level of 69.1 dB(A) is within the standard of 70 dB(A) as stipulated in
Ministry of Environment Decree No. Kep-48/MENLH/11/1996 on Ambient Noise
Standards. There is very minimal vehicular traffic and therefore the exceedance can be
attributed mainly to the ongoing construction works at the bridge.
32. Noise sampling result for Station 2 of 75.1 dB(A) is slightly above the standard of 70
dB(A). Since the Tambak Mulyo-Wawar road is still closed to traffic, the increase in noise
levels are mainly due to the heavy equipment operation and ongoing road construction
works.
33. West Kalimantan: CW-05. The results of the noise level measurements for CW-05
indicate that the noise levels for all 3 sampling stations are slightly higher than the
standard of 70 dB(A). For station 1 and 2, the sampling stations are located at the
entrances of the contractor’s facilities and are near the road. Thus, the sources of noise
are mainly the operation of the plants (AMP and stone crusher and asphalt blending),
trucks transporting materials to and from the plants and vehicular traffic. For station 3, the
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
18
noise comes from both vehicular traffic and the operation of equipment for construction
works.
34. North Kalimantan: CW-11. The ambient noise sampling result for CW-11 of 67 dB(A)
is within the standard. The noise sampling station is inside the contractor’s camp located
in a sparsely populated area. Thus, the main source of noise is the trucks hauling
materials and the AMP operation.
Table 10: Noise Monitoring Results
Station Road Section / Sampling Point Noise level [(db)A]
Central Java - CW-01: Tambak Mulyo-Wawar
sampled in 17 April 2018
1 Luk Ulo Bridge STA 17+250 69.1
2 Road alignment: Tambak Mulyo-Wawar STA 38+00 75.1
West Kalimantan - CW-05: Sosok – Tayan; Tanjung – Batas Kota Sanggau
sampled in November 16, 2018
1 Entrance to contractor’s camp, AMP and stone crusher compound in Bunut
74.2
2 Entrance to Asphalt Blending Plant in Bodok 75.6
3 Along Tanjung-Sanggau road section 72.7
CW-11: Simanggaris – Batas Negara (Serudong)
Sampled in March 7, 2018
1 In front of contractor’s (Halla Corporation) offices 67
Note: Ministry of Environment Decree No. Kep-48/MENLH/11/1996 on Ambient Noise Standards: Residential area: 55 dB(A); Commercial/industrial area: 70 dB(A)
4.4. Environmental Monitoring by the DSC
35. DSC-2 reported that their environmental engineer/specialist has already resigned in
February 2018. However, it was noted that whilst the DSC-1 have still an environmental
engineer/specialist in their employ, the monthly Environmental Monitoring reports
containing the related checklists prepared by the contractors were still not supported by
site inspection, monitoring reports or photographs. On the other hand, the monthly
environmental monitoring reports submitted by DSC-2 contained some environmental
monitoring and mitigation activities with photographs.
36. In view of this deficiency, the actual observations of the CTC during the site visits and
ad-hoc communication between the PMU/CTC, DSC and contractors were applied to
present the overall status of the environmental monitoring conducted by the DSC for the
RRDP. Based on these information and observations, the status of environmental
monitoring conducted by DSC is categorized as ‘implemented, partially implemented, not
implemented or not applicable as presented in Table 11.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
19
Table 11: Environmental Monitoring Undertaken by DSC
Aspect / Location Parameters Monitoring Means/
Frequency Guideline Values/Standards/
Indicators Status in 2018 and Justifications
1. Quarries and borrow operation
Quarry and borrow
sites
Undertaken in
designated areas duly
licensed/ approved by
concerned authority.
Monthly visual
inspection to ensure fill
is only obtained from
licensed designated
sites
(i) Environmental permit/
approval from concerned
agency.
Implemented –All UKL-UPL approval and Environmental
Permit for the quarries operated to support the construction
works in 2018 have been secured.
(ii) Activities shall be limited to licensed designated areas only.
Implemented –All UKL-UPL approval and Environmental Permit for the quarries operated to support the construction works in 2018 have been secured.
Quarry and borrow sites
Implementation of erosion control
Monthly visual inspection
(i) No evidence of water ponding or presence of fresh gullies.
Implemented – quarry and borrow sites are already existing and not owned by the contractors and are/should be monitored by GOI mandated agencies.
(ii) No increased visual turbidity of surface water.
Implemented – the same justification as for point (i).
Quarry and borrow sites
Proper site closure as specified in the environmental mitigation plan.
Monthly visual inspection
(i) Pre-quarry conditions Implemented –pre-quarry conditions are typically documented in the UKL-UPL document. Quarry and borrow sites are already existing and not owned by the contractors and will continue to operate after the project.
(ii) Site left in a tidy state with stable side slopes, proper drainage and provided with vegetation cover.
Implemented –pre-quarry conditions are typically
documented in the UKL-UPL document. Quarry and borrow
sites are already existing and not owned by the contractors
and will continue to operate after the project
(iii) DSC’s report testifying to completion of restoration work
Implemented – the same justification as for point (ii).
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
20
Table 11: Environmental Monitoring Undertaken by DSC
Aspect / Location Parameters Monitoring Means/
Frequency Guideline Values/Standards/
Indicators Status in 2018 and Justifications
2. Material storage sites
Project alignment, construction yard
Compliance with requirements
Monthly visual inspection
(i) Activities shall be limited to designated areas only
Implemented – the activities are delineated as part of construction activities.
(ii) Materials management procedures implemented.
Partially Implemented – Total site closure reports submitted are 8 of 11 CW packages but only 5 of 11 CW packages have proper site closure reports and
(iii) No visible puddles of oil or oil contaminated soil.
Partially Implemented – Total site closure reports submitted are 8 of 11 CW packages but only 5 of 11 CW packages have proper site closure reports
4. Landslide/Rockfall
Active landslide/ rock fall sections and steep mountainous slopes
Vegetation cover is maintained.
Monthly visual Inspection
(i) Identified areas during detailed design phase.
Implemented – areas for vegetation cover is identified and included in the contract for some CW packages.
(ii) Adequacy, quality, and specifications of planting; Survival rate of plants.
Not implemented – there is no data available as to the actual survival rate of plants since only the planting is included in the contract.
Slope stabilization engineering structures
Slope stabilization measures, landslide/ rockfall protection measures
Monthly visual inspection
Adequacy, quality, and specifications of landslide/rock fall protection measures.
Implemented – construction of landslide/rock fall protection measures are completed as per contract.
5. Hydrocarbon and chemical storage
Construction camps
Compliance with environmental mitigation requirements
Monthly visual Inspection of storage facilities
Provision of adequate storage facilities
Partially Implemented – Only 5 out of 11 CW packages have site closure reports which certified by DSC submitted indicating that storage facilities for lubricant, fuel and asphalt drums have been cleaned-up.
Material storage areas of the CW packages with construction works in 2018, for hydrocarbon materials have concrete flooring with embankment and roof.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
21
Table 11: Environmental Monitoring Undertaken by DSC
Aspect / Location Parameters Monitoring Means/
Frequency Guideline Values/Standards/
Indicators Status in 2018 and Justifications
6. Waste management
Construction camps
Cleanliness of workers’ camps
Monthly visual inspection
(i) Proper collection, storage, and disposal of solid waste.
Partially Implemented – storage and disposal of solid wastes is implemented but needs improvement.
(ii) Provision of clean and adequate sanitation facilities.
Partially Implemented – sanitation facilities are provided but maintenance needs improvement.
Proper site closure
Monthly visual inspection
(i) Timely and effective waste disposal.
Partially Implemented –8 out of 11 CW packages submitted site closure reports certified by DSC submitted).
(ii) Site appearance restored. As above
(iii) DSC’s report testifying restoration of site.
As above.
7. Surface water quality
Bridge construction sites
Local surface waters are protected
Monthly visual inspection of water management
(i) Project activities do not cause turbidity/siltation and flow obstruction of surface waters.
Implemented – no public complaints were received or reported about surface water.
(ii) Adequacy, quality, and specifications of protection measures provided against washouts.
Implemented – protection measures such as retaining walls were provided at the time of bridge construction and included in contract.
All bridge construction sites – upstream and directly downstream of major rivers or after a pollution event
(i) Total suspended solids (TSS)
(ii) Oil and grease,
(iii) Turbidity,
(iv) pH
Water sample collection and analyses by accredited laboratory
(i) once before commencement of construction works (baseline); and
(ii) subsequently after a reported pollution event and/or complaints)
Standardization of River Categories II based on Governmental Regulation No. 82 of 2001
Not applicable –There are no reported water pollution events or community complaints. The IEE of RRDP only requires water sampling if these conditions exist.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
22
Table 11: Environmental Monitoring Undertaken by DSC
Aspect / Location Parameters Monitoring Means/
Frequency Guideline Values/Standards/
Indicators Status in 2018 and Justifications
8. Air quality
Sensitive sites e.g. settlements, schools, hospitals, etc., close to construction sites and other project-related facilities where emission of high dust levels occur
(i) TSP
(ii) PM10
Air sample collection and analyses by accredited laboratory
(i) once before commencement of construction works; and
(ii) subsequently 1 time a year
Government Regulation No. 41 of 1999 on Air Pollution Control
Partially Implemented-3 of 4 CW packages with construction works in 2018 conducted air quality sampling.
CW-08 completed in January 2018 and did not allow enough time to prepare and conduct the sampling through a 3
rd party
provider considering also the remote location of the project.
CW-11 analyzed TSP parameter only.
Asphalt mixing plant Designated areas
Monthly visual inspection to ensure asphalt plant is located >1 km from residential areas
i) Environmental approval/permit from concerned agency.
Implemented – All CW packages with ongoing works in 2018 have secured UKL-UPL approval, Environmental Permit and SPPL.
ii) Activities shall be limited to designated areas only
Implemented - activities are limited to designated areas inside the asphalt mixing plant compound.
Dust
Compliance with required mitigation measures
Monthly visual inspection to ensure dust suppression work plan is being implemented
i) Measures, location, and schedule for dust suppression activities
Implemented – dust suppression activities were implemented, and no complaints were received.
ii) Air pollution control
equipment installed on
vehicles
Implemented – the construction vehicles have installed air
pollution control in their exhaust system.
iii) No complaints from
residents
Implemented - no formal complaints were received from
residents.
9. Noise
Sensitive areas
Noise levels in dB(A)
Noise level measurement:
(i) Once before commencement of construction activities; and
(ii) Subsequently twice per year
i) Government Regulation No. 41 of 1999 on Air Pollution Control.
Implemented-3 of 4 CW packages with construction works in 2018 conducted noise sampling.
CW-08 completed in January 2018 and did not allow enough time to prepare and conduct the sampling through a 3
rd party
provider considering also the remote location of the project.
ii) Complaints from residents Implemented - no complaints were received from residents.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
23
Table 11: Environmental Monitoring Undertaken by DSC
Aspect / Location Parameters Monitoring Means/
Frequency Guideline Values/Standards/
Indicators Status in 2018 and Justifications
10. Vibration
Sensitive areas
Compliance with required mitigation measures
Monthly visual inspection
Complaints from residents Implemented - no complaints were received from nearby residents.
11. Landscaping/Reforestation
Project alignment
Progress of reforestation activities
Monthly visual inspection
i) Adequacy, quality, and specifications of planting
Not implemented – this guideline is not specified in the construction contract of RRDP.
ii) Survival rate of plants Not implemented – this guideline is not specified in the construction contract of RRDP.
iii) Watchman on site Not implemented – this guideline is not specified in the construction contract of RRDP.
12. Community
Project alignment
(i) Consultations
(ii) Information disclosure
Ongoing consultation with government and community groups along the alignment to monitor environmental concerns
(i) Number of public consultations conducted
Partially implemented – informal communication was reportedly made with local residents prior to start of construction activities.
(ii) Recipients of project-related documents
Partially implemented - project related documents are only for contractor and local government
(iii) Number of complaints Implemented - no community complaints were reported in 2018
13. Traffic management
Project alignment
(i) Number of complaints
(ii) Number of traffic enforcers in place
(iii) Number of traffic and warning signs in place
Ongoing visual inspection to strict adherence to applicable environmental mitigation measures
Number of complaints and accidents
Implemented – no complaints were received. Traffic signs are in place as per specification in the contract.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
24
PART V. CTC SITE INSPECTION
37. There was no ADB Project Review Missions conducted during the RRDP
implementation in the period of January to September 2018 as the project has been
officially completed as of end September 2018. However, a Project Closure Review
Mission is reportedly scheduled for October 2018.
38. The CTC International and National Environmental Specialists conducted
environmental monitoring in Central Java, West Kalimantan and North Kalimantan CW
packages. Key non-compliances with the IEE of RRDP identified at these site inspections
including corresponding corrective actions and its implementation status are presented in
Table 12.
39. In general, there were only a few key issues identified during the CTC site visits.
However, since only 8 of 11 CW packages have submitted site closure/hand-over reports
i.e. : CW-01, CW-02, CW-06, CW-07, CW-08, CW-09, CW-10 and CW-11, it cannot be
determined if proper site closure, clean-up activities and proper disposal of spilled asphalt
and petroleum-based products were implemented.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
25
Table 12: Non-Compliance/Issues Identified, Corrective Action and Its Status as of 2018
Package Non-Compliance/Issue Identified by Corrective Actions Status
Central Java
CW-01 The new road alignment is still closed to motorists, but some locals already use the road in going to their farms exposing them to road construction hazards.
CTC Improve installed road/warning signs at
beginning and end of new road
alignment.
Implemented- Road/warning signs improved to forewarn
and dissuade motorists from entering the closed road. Site
closure report with clean-up photographs has already been
submitted. Please see Appendix E.
CW-01 Not all workers are wearing PPEs. CTC Implement wearing of PPEs as required
in the contract and EMP
Implemented- Field personnel are instructed during
toolbox meetings to wear PPEs
CW-01 Previous concern on replacement of trees which has been cut along the project alignment.
CTC The contractor has already planted 3,000 albizia trees
along the project alignment.
West Kalimantan
CW-05 Workers are not wearing PPEs. No warning signs and flagmen during asphalt paving. The work area is a busy thoroughfare.
CTC Implement wearing of PPEs. Install
appropriate road signs/warning signs as
specified in the contract and EMP.
Implemented- Warning signs and flagman were immediately provided at working areas.
CW-05 Dense dust during stone crushing operations. Wind direction is observed to be downward towards the vegetated areas and away from settlements.
CTC Implement water spraying of source
aggregates and conduct air quality
monitoring as soon as possible to
ascertain dust pollution levels
especially near sensitive
receptors/residences.
Implemented- Air quality monitoring conducted on June 9, 2018 at the entrance to the stone crusher plant and quarry which is beside residential areas showed TSP and PM10 results of 63.5 µg/Nm
3 and 42.1 µg/Nm
3 respectively
which were below the threshold value of 230 µg/Nm3 and
150 µg/Nm3, for TSP and PM10 respectively as stipulated in
GR 41/1999 (please see Appendix C.2).
North Kalimantan
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
26
Table 12: Non-Compliance/Issues Identified, Corrective Action and Its Status as of 2018
Package Non-Compliance/Issue Identified by Corrective Actions Status
CW-11 The old bridge and construction debris at
Bridge Sta 12 + 600 has not yet been
removed and may cause obstruction to
the free flow of water.
CTC Remove debris and perform clean-up
activities.
Implemented - the old bridge has already been removed in
coordination with the PPK for the equipment to be used for
removal of the bridge and transfer to the contractor’s base camp.
CW-11 Thick white smoke which was darker than
usual was observed coming out of the
AMP stack. Air quality sampling was
already conducted on April 6, 2018 but the
results were not yet available at the time
of the site visit.
CTC Conduct air quality monitoring as soon
as possible to determine pollution
especially since the sensitive
receptors/residences are beside the
contractor’s camp.
Implemented - Air quality monitoring conducted on April 6,
2018 at the contractor’s camp and AMP compound showed
TSP values of 36.45 µg/Nm3 which is below the threshold
value of 230 µg/Nm3 as stipulated in GR 41/1999. Please
see Appendix C.3.
CW-11 Minimal diesel spills were observed below
the diesel tank. Asphalt spills were
observed at the vicinity of the asphalt
mixing plant.
CTC Despite the small volume, these should
still be cleaned up regularly to avoid
water pollution downhill when it rains
since the AMP area is located at a
higher elevation.
Implemented – Site closure report with clean-up
photographs have already been submitted. Please see
Appendix D.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
27
PART VI. KEY ISSUES FOR RESOLUTION
40. Table 13 summarizes the key issues identified in 2016, 2017 and 2018 (as of
September 2018) that should be resolved by the parties identified. Issues or gaps
regarding the EMP implementation that are described in the earlier tables should also be
resolved since it is noted that some of the key issues have been recurring since 2015.
Table 13 : Key Issues and Required Corrective Actions
Key issues as of
September 2018 Corrective Action
Responsible
Party
Status (as of
September 2018)
Incomplete
environmental
approval and
permits for the
road construction
The Environmental Permit (Izin
Lingkungan) of CW-06: Tebas -
Singkawang - Section 1 and Section 2
The UKL-UPL approval and
Environmental Permit of CW-06:
Sambas Bypass road section
Directorate
General of
Highways
Acquisition of
environmental
approvals and
permits are in
progress
Absence of
environmental
approval and
permits for AMP
and/or Quarry
Provide evidences that the environmental
approval and permits for the quarry and
asphalt mixing plant (AMP) have been
acquired and include in the site closure
report of completed road package CW-04
DSC-3 (PT
Perentjana
Djaja)
Not Available as
DSC-3 has been
demobilized and
construction
completed on 9
April 2016
Provide evidences that the environmental
approval and permits for the quarry and
asphalt mixing plant (AMP) have been
acquired and include in the site closure
report of completed road package CW-03.
DSC-2 (Botek
Bosphorus
Technical
Consulting)
Environmental Site
closure report is
not available. The
AMP operations
are currently being
forwarded by other
project. The
material of quarry
was purchased by
contractor as
reported by DSC
Provide evidences that the environmental
approval and permits for the quarry and
asphalt mixing plant (AMP) have been
acquired and include in the site closure
report of completed road packages CW-09,
and CW-10.
DSC-1 (China
Engineering
Consultants)
Not implemented,
Contractors have
demobilized in
2017 and AMPs
have been closed.
Proper site
closure report and
compliance to
Government
Regulation No
101/2014 on the
management of
hazardous/toxic
wastes
Identify final disposal method for waste
asphalt and empty asphalt drums, used oil
and other waste petroleum-based products
that comply with the mentioned regulation
and include in site closure report.
Contractors for
CW-03, CW-04,
CW-05, CW-08,
CW-09 and CW-
10
DSC-1 and
DSC-2 to certify
proper site
closure report
Partially
implemented,
DSC-1 preparing
site closure for
Work Packages
CW-08, CW-09
and CW-10 (see
appendices F, G,
H) and for CW-05
construction not
completed yet.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
28
PART VII. CONCLUSIONS AND RECOMMENDATIONS
41. This 2018 Annual Environmental Monitoring Report describes the implementation on
environmental management plan (mitigation and monitoring) by the Executing Agency,
including respective contractors, DSCs, and PMU/CTC, as integral part of the execution
of RRDP. The 2018 report serves as the final environmental monitoring report covering
January to September 2018, which is the completion date of the RRDP. The key
conclusions drawn from this report are presented in the following:
42. Implementation of Environmental Management Plan including Monitoring.
Incomplete environmental checklists, including the absence of its supporting information
and documents (e.g., written justification, inspection reports, and photos) is ongoing issue
encountered until the project completion.
43. The DSC-1 (for Kalimantan) and DSC-2 (for Central Java) have only mobilized their
Environmental Specialists since September 2017. The DSC-2 Environmental Specialist
resigned thereafter in February 2018 and DSC-1 Environmental Specialist will be
demobilized until end of DSC-1 contract.
44. The implementation of corrective actions and environmental mitigating measures by
the contractors improved compared to that in the previous years, particularly for CW-01
(Central Java), CW-05 (West Kalimantan), and CW-08 and CW-11 (North Kalimantan)
completed in 2018. The improvements included, among others:
Dust suppression measures such as water spraying and maintenance of construction
facilities and equipment as well as AMP’s air pollution control devices were more
regularly conducted.
Air quality sampling for total suspended solids and particulate matters (PM10), and
noise monitoring were conducted for the works packages constructed and completed
in 2018. The monitoring results indicate values that are generally within the threshold
values stipulated by the Indonesian Government.
Relatively small quantities of spilled asphalt, and other hydrocarbon materials remain
at the AMP. Spilled asphalt is reused for improving village roads and contractor’s camp
areas. Used oil are reused for equipment maintenance while minimal quantities of
spilled oil are collected and used as cooking fuel.
Empty drums formerly used to storage asphalt and hydrocarbon materials for the
RRDP works in West Kalimantan were reportedly collected back by the supplier and
shipped to a central drum collection entity in Pontianak. In contrast, those of the RRDP
works in North Kalimantan are reportedly donated to the local governments and local
villagers for limited use such as collecting water for watering palm trees or used for
fencing. There is no information as to how these empty drums have been managed for
the RRDP works in Central and East Java.
The AMPs equipped with settling pond with concrete flooring were visually monitored
and the sludge accumulated was regularly removed.
No significant and formal complaints were received during the project execution.
2018 Annual Environmental Monitoring Report (AEMR)
Regional Roads Development Project (RRDP)
29
45. Approval and Permit for Road Construction. At the end of the RRDP completion,
most of the roads constructed/operated under the RRDP have secured their respective
AMDAL and UKL-UPL approvals as well as the Environmental Permit, except for the
Sambas – Tanjung Harapan and Tebas – Singkawang road sections (CW-06 in West
Kalimantan).
46. Approval and Permit for Asphalt Mixing Plant (AMP) and Quarry. At the end of
the RRDP completion, most of the AMPs and quarries road operated under the RRDP
have secured their respective UKL-UPL approvals and Environmental Permits or SPPL.
However, there is no information whether those of CW-03 (Central Java), CW-04 (East
Java), and CW-09 and CW-10 (North Kalimantan) have been secured.
47. Site closure/hand over reports of the AMPs and/or quarries operated for the RRDP
have been submitted for 8 out of 11 CW packages, and these are for CW-01, CW-02,
CW-06, CW-07, CW-08, CW-09, CW-10 and CW-11 as included in the 2017 and 2018
environmental monitoring reports. Similar reports have not been submitted for the other
CWs.
48. Recommendations. The gaps as described earlier should be completed as part of
the project closure report and RRDP monitoring for the operation phase.
49. The Environmental Management Plan of the RRDP’s IEE (2011) requires the DGH/Dinas PU to conduct a regular environmental monitoring of the roads for the first
three years of operation. Subsequently, an annual monitoring report should be submitted
to ADB.