Environmental Monitoring Report€¦ · SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2 1...
Transcript of Environmental Monitoring Report€¦ · SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2 1...
Environmental Monitoring Report
# 2 Semiannual Report (January-June 2018) January 2019
NEP: SASEC Road Improvement Project
Prepared by the Department of Roads, Ministry of Physical Infrastructure and Transport for the
Government of Nepal and the Asian Development Bank.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
1
January-June 2018
CURRENCY EQUIVALENTS
29 June 2018
Currency unit – Nepalese Rupee (NRs)
NRs1.00 = $ 0.00913409
US $1.00 = NRs 109.48
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
2
January-June 2018
ABBREVIATIONS
ADB Asian Development Bank
ADB –PD Asian Development Bank-Project Directorate
ADF Asian Development Fund
BOQ Bill of Quantity
CDO Chief District Officer
CRE Chief Resident Engineer
CSC Construction Supervision Consultant
CSC-ES Construction Supervision Consultant – Environment Specialist
DCC District Coordination Committee
DFO District Forest Office
DOR Department of Roads
EFP Environmental Focal Person
EIA Environmental Impact Assessment
EMAP Environmental Management Action Plan
EMP Environmental Management Plan
EMR Environmental Monitoring Report
EWH East–West Highway
GDP Gross Domestic Product
GESU Geo-Environmental and Social Unit
GRC Grievance Redress Committee
ICB International Competitive Bidding
IEE Initial Environmental Examination
IOW Inspector of Works
MOFSC Ministry of Forest and Soil Conservation
MoPE Ministry of Population and Environment
MPIT Ministry of Physical Infrastructure and Transport
NCB National Competitive Bidding
NGOs Non-Government Organizations
NH National Highway
PAM Project Administration Manual
PIC/PM Project In charge/Project Manager
PIU Project Implementation Unit
RAP Rural Access Programme
RE Resident Engineer
RM Rural Municipality
SASEC South Asia Sub-Regional Economic Cooperation
SEIA Supplementary Environmental Impact Assessment
SLC Sub-Project Level Committee
SPS Safeguard Policy Statement
SRCP SASEC Road Connectivity Project
SRN Strategic Road Network
TOR Terms of Reference
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
3
January-June 2018
NOTES
(i) The fiscal year (FY) of the Government of Nepal and its agencies ends on 16 July.
FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY
2017/18 ends on 16 July 2018.
(ii) In this report, "$" refers to US dollars.
This environmental monitoring report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,
and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other
status of any territory or area.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
4
January-June 2018
TABLE OF CONTENTS
ABBREVIATIONS 2
EXECUTIVE SUMMARY 6
1. BACKGROUND 9
2. ENVIRONMENTAL SAFEGUARDS IN SRIP 10
3. CHANGES AND ADJUSTED SAFEGUARD MEASURES; 11
4. IMPLEMENTATION ARRANGEMENT 11
5. STATUS OF ENVIRONMENTAL SAFEGUARD IMPLEMENTATION 12
a) Environmental Clearance on IEE/EIA reports 12
b) Capacity Building Activities 12
c) Status of Forest Clearance 12
d) Compensatory plantation 14
e) Status of other local clearances 14
f) Awareness program 14
g) Spoil management 14
h) Drainage management 15
i) Management of Dust 16
j) Slope stabilization and bioengineering activities 16
k) Rehabilitation of community infrastructures and cultural/religious sites 17
l) Quarry site management 17
m) Camp Site Management 17
n) Occupational health and safety (OHS) 17
o) Signboard placing (erection) 17
p) Grievance Redress Committees 18
q) EMP implementation, monitoring and reporting 18
r) Disclosure of Environmental Assessments and Monitoring Reports 18
s) Monitoring of Safeguards Implementation 19
s) Status of Wildlife Baseline Survey 19
6. OVERALL COMPLIANCE WITH EMP 19
7. ISSUES AND WAY FORWARD 20
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
5
January-June 2018
List of Figure
Figure 1: SASEC Road project in Map of Nepal 10
List of Tables
Table 1: Details of SRIP road sub-projects 10
Table 2: Forest Clearance progress during January-June 2018 13
Table 3: Overall Forest Clearance Status 13
Table 4: Status of local clearance and approval 14
Table 5: To date spoil for different sub-projects 15
Table 6: Major Structures with Drainage detail and progress till date 15
Table 7: Overall compliance status of SRIP road projects 19
Table 8: Issues and Corrective Measures 20
List of Annexes
Annex 1: Project Log frame, Environmental Safeguards
Annex 1a: Status of Environmental Safeguard Planning Status
Annex 1b: Environmental Safeguard Implementation Status
Annex 2: Environmental Management Cost
Annex 3: Status of Environmental Safeguard Compliances
Annex 4: Plantation Plan
Annex 5: Implementation Reporting Format
Annex 6: Environmental Monitoring Checklist
Annex 7: Grievance Redress Mechanism Meetings
Annex 7a: Minutes of First GRM Meeting
Annex 7b: Minutes of Second GRM Meeting
Annex 8: Photographs
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
6
January-June 2018
Executive Summary
1. The proposed South Asia Sub Regional Economic Cooperation (SASEC) Road
Improvement Program (SRIP) is undertaking two strategic high priority roads in the Province
4 of Nepal: i) Narayanghat – Butwal Highway, and ii) Bhairahawa-Lumbini-Taulihawa Feeder
Road. The project roads are: (i) Narayanghat-Butwal (115 km - 4 lane highway) Road, and
(ii) Bhairahawa-Lumbini-Taulihawa Road (41.130km). The Department of Roads (DOR)
intends to improve Narayanghat-Butwal Road to all-weather asphalt concrete four-lane
Asian Highway Standard. The 41.130 km Bhairahawa-Lumbini-Taulihawa road has 3
sections: Section 1: 3.68 km, km 0+00 to km 3+680 (Bhairahawa-Airport); Section 2: 14.42
km, 3+680 to Km18.100 (Bhairahawa Airport -Lumbini); and Section 3: km 18+100 to
41+130 (Lumbini - Taulihawa). Section 1 will be improved from the current 2 lanes to an all-
weather bituminous 4 lanes with both sides service roads while section 2 will be improved
from the current 2 lanes to an all-weather bituminous 4 lanes while Section 3 will be
improved from 1 lane to 2 lanes feeder road standards.
2. The Project has been categorized as “A” consistent with the requirements of ADB
SPS 2009 since one of the project components, the East West Highway Narayanghat -
Butwal Section passes through a section of the buffer zone of a Chitwan National park with
major parts bordering the buffer zone. The Bhairahawa - Lumbini - Taulihawa roads
upgrading activities are unlikely to have significant adverse environmental impacts. Impacts,
largely are short-term, reversible and manageable through appropriate mitigation measures
and categorized as “B”.
3. All sub-projects had successfully completed the IEE/ EIA. Due to increase in number
of tree to be cleared for project implementation from 1890 to 2078 (IEE report – After joint
field verification). Approval for clearance is taken from DFO/DOF for increased number of
trees to be cut as found from joint verification survey. The contractor has started tree cutting
along with removal of roots from road area. Till reporting date total 2050 numbers of trees
have been cut-down and 985 roots have been removed.
4. Environmental Clearance Checklist has been prepared and handed over to
EFPs/BLT Civil Contractor for the necessary filling up and regular reporting to the CSC
Environment Specialist. Till this reporting period contractor is regularly submitting
environmental checklist to CSC Environment specialist.
5. SASEC road sub-projects passes through 55 community forests (CFs) in NB road
(Not started) and with total loss of 2078 in BLT road. Compensatory plantation (CP) has to
be done at the ratio of 1:25. Compensatory plantation has not been proceeded. DCC (in the
past DDC) has approved to collect materials for quarry sites from Tinau River, Kundri river &
Dano river. Contractor has started material collection from approved quarry sites. The
materials are used for base, sub-grade and pre-mix / batching works. Borrow pits soil used
for sub-base and embankment construction has been brought from private lands. The
agreement has been done with the private land owners to collect the borrow pits soils.
Environmental Focal Person has prepared quarry operation plan. Quarrying is done from the
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
7
January-June 2018
environmentally suitable and legally recognized sites identified during detail survey.
Contractor has also identified the private quarry areas (Borrow pits) especially earth for sub-
base material & embankment construction. The approval has been taken from the CSC to
use the mining area as per the approved quarry operation plan.
6. Drinking water and sanitary facilities (toilets) are provided in the camps for each
camp site in BLT road. In camps, workers are using LPG obtained from local market for
cooking purpose. At present contractor is using rental house for camp site workers. Workers
residing in camps are provided with toilet facilities and washrooms / bathrooms for women
and men separately. Other services are of partially satisfactory standard.
7. Occupational health and safety measures have been partially undertaken. Workers
have been partially provided with safety gears like helmet, facemasks, etc. With limited
knowledge of using safety gears, workers are found ignoring its use. Workers group has
been provided with first aid kit having essential medicines and condoms. Group accidental
insurance has been done for all the workers where construction work is going on.
8. Signboards are erected at various places at start and end points of construction sites.
In addition to this, informative signs are kept where construction activities are carried out.
9. During this reporting period of six months, two meetings of Compensation
Determination Committee and Project Level Grievances Redress Committee were held on
23rd January 2018 and on 15th March 2018 at CDO office in Bhairahawa Municipality of
Rupandehi district. In the process of improving and constructing the Bhairahawa-Lumbini-
Taulihawa Road Sub-project, the house and structures within the Right of Way (ROW) of
road will be required to be removed and demolished. For this purpose and to support the
process of compensating the structure owners, the Sub-Committee consisting of 3 members
including the representatives from Rupandehi Urban Development and Building Office,
District Technical Office, and Project Management Office has been formed, 11 numbers of
grievances on resettlement issues have been registered till date so far in BLT road under
SRIP. Valuation of structures has been done. The committee in the process of compensating
have identified/ recorded structures. Total valuation of 11 accounted structures as per
valuation report of the Valuation Committee is NRs. 1,268,368.
10. EMP implementation and monitoring in the SRIP road packages has been observed
satisfactory. The CSC has conducted periodic site inspections to assess Contractor’s
compliance to the EMP, advice corrective measures, and report to PD (ADB), DoR on the
effectiveness of the mitigation measures and overall status of EMP implementation. The
Contractors have been asked to fill up the environmental compliance checklist provided
earlier and submit back to CSC regularly.
Wildlife
11. Cost estimate for camera trap and wildlife baseline survey was completed after
discussion with PD office, ADB Mission members. Number of camera and its potential
sources were explored and confirmed Cuddeback Company.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
8
January-June 2018
12. The rapid sign survey for wildlife was conducted in 20-26 May 2018, where the
presence of Tiger (Panthera Tigris), one-horned rhinoceros (Rhinoceros unicorns), common
leopard (Panthera Pardus)’s pugmarks were recorded.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
9
January-June 2018
1. BACKGROUND
13. The South Asia Sub Regional Economic Cooperation (SASEC) Road Improvement Program (SRIP) is undertaking two strategic high priority roads in the Province 4 of Nepal: i) Narayanghat – Butwal Highway, and ii) Bhairahawa-Lumbini-Taulihawa Feeder Road. The Narayanghat-Butwal Highway is part of the Asian Highway. 14. The Project is consistent with the Government's transport strategy and development plans. Nepal's Three Year Interim Plan (TYIP) 2013/14-2015/16 emphasizes on continuous development of Strategic Road Network (SRN) and strengthening East-West Highway (EWH), while the succeeding plan, the Three-Year Plan Approach Paper (TYPAP) 2013/14-2015/16, aims to: (i) connect the regional centers and all 75-district headquarters; (ii) complete the Mid- Hill East-West Corridor (MHC); and (iii) strengthen the system of regular maintenance and management of road structures by providing regular maintenance of 8,300 km. and periodic maintenance of 1,500 km. roads. The Sector Wide Road Program (SWRP), Priority Investment Plan (PIP) and Strategic Road Network (SRN), currently calls for the expansion of the country’s road improvement program from 7,917 km of the country's total road length of 18,828 km, to 9,900 km by 2016. 15. The project roads are: (i) Narayanghat-Butwal (115 km - 4 lane highway) Road, and (ii) Bhairahawa-Lumbini-Taulihawa Road (41.130km). The Department of Roads (DOR) intends to improve Narayanghat-Butwal Road to an all-weather asphalt concrete four-lane Asian Highway Standard. The 41.130 km Bhairahawa-Lumbini-Taulihawa road has 3 sections: Section 1: 3.68 km, km 0+00 to km 3+680 (Bhairahawa-Airport); Section 2: 14.42 km, 3+680 to Km18.100 (Bhairahawa Airport -Lumbini); and Section 3: km 18+100 to 41+130 (Lumbini - Taulihawa). Section 1 will be improved from the current 2 lanes to an all-weather bituminous 4 lanes with both sides service roads while section 2 will be improved from the current 2 lanes to an all-weather bituminous 4 lanes while Section 3 will be improved from 1 lane to 2 lanes feeder road standards. 16. The Narayanghat-Butwal road is part of NH1 and AH2, the main lifeline of the central, western and mid-western territories. It also links to the Sunauli Border, the second largest trading post of Nepal through the Bhairahawa dry port. The Bhairahawa-Lumbini-Taulihawa road section connects to Lumbini, the birth place of Gautama Buddha, the founder of Buddhism, and a world heritage site. According to Buddhist tradition, Taulihawa is the birthplace of Queen Mayadevi, the mother of Gautama Buddha. These places are important part of the Buddhist pilgrimage. The road also connects to the Gautam Buddha International Airport in Bhairahawa. 17. About 156 km of strategic roads will be upgraded and improved under SASEC SRIP. Project roads and bridges will be upgraded to comply with applicable road standards and enhance road safety and climate resilience. The Department of Roads (DOR) intends to improve the Bhaiwahawa-Lumbini-Taulihawa sub-project road to an all-weather sealed four and double lanes feeder road standards. There will be no land acquisition since the road right-of-way is property of the government. The formation width of the roads varies from 43 m to 12 m and paved shoulders will have minimum width of 2.5 m for 6 lanes road and remaining section gravel shoulders will have minimum width of 1.5 m length of the road originating from Bhairahawa and ending at Taulihawa covering 41.130-km length. Details of the SRIP road projects has provided in table 1 below.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
10
January-June 2018
Table 1: Details of SRIP Road Sub-Projects:
SN
Road Contractor
Name
Commencement
Date
Completion Date
Contract No Length (Km)
Improvement Standard
1
EWH, Narayanghat –Butwal Road, section I
Contract yet to be awarded
SRIP/ICB/NB/01
64.425 Asian Highway 4 lane/3 lane
2
EWH, Narayanghat – Butwal Road, section II
Contract yet to be awarded
SRIP/ICB/NB/02
48.535 Asian Highway 4 lane/3 lane
3 Bhairahawa – Lumbini –Taulihawa Road
M/S GAWAR Construction Limited
14th July
2017
10th
January 2022
SRIP/ICB/BLT/01
41.13 Feeder Road 4 lane/ 2 lanes
18. The project road locations are shown in the Figure 1.
Figure 1: SASEC Road in Map of Nepal
2. ENVIRONMENTAL SAFEGUARDS IN SRIP
19. This report is the 2nd. Semi-annual report on environmental safeguards compliance of the Nepal South Asia Sub Regional Economic Cooperation (SASEC) Road Improvement Project. It describes the implementation of environmental safeguards activities, covering the period from January to June 2018.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
11
January-June 2018
20. The Project has been categorized as “A” consistent with the requirements of ADB SPS 2009 since one of the project components, the East West Highway Narayanghat - Butwal Section passes through a section of the buffer zone of a Chitwan National park with major parts bordering the buffer zone. The Bhairahawa - Lumbini - Taulihawa roads upgrading activities are unlikely to have significant adverse environmental impacts. Impacts, if any, will largely be short-term, reversible and manageable through appropriate mitigation measures and categorized as “B”.
3. CHANGES AND ADJUSTED SAFEGUARD MEASURES;
21. The project is in the mid-way of the construction stage. As the changes and adjustment required for safeguards measures have are not been observed, no changes and adjustments on safeguards measures have been done except the revised number of tree cutting along the right of way of BLT Road. The revised number of trees along the right of way found after the joint survey is 2078. Any further change in the tree cutting data will be reported.
4. IMPLEMENTATION ARRANGEMENT
22. The DOR Project Directorate (PD) through Environmental External Monitor will coordinates and ensures that all environment safeguard requirements under the project are met1. He/she may take technical assistance from GESU and DOR as and when necessary. The EMP for all subprojects is attached to respective contract documents. The contractors are liable for implementation of all items in the EMP. The DOR PD through Construction Supervision Consultant, M/s Korea Engineering Consultants Ltd. Crop. - Kyong Dong Engineering Co. Ltd JV, in association with Soil Test, MEH Consultants (P) Ltd., and MULTI – Disciplinary Consultants (P) Ltd.(CSC) monitors directly and reports on the environmental compliance of contractors with the EMP. Key implementation activities for each of sub-project are as follow:
a) Pre-construction:
23. BLT’s Contractors had completed the following activities no later than 30 days from the DOR issuance of Notice to Proceed: 1.) Submit appointment letter and resume of the Contractor’s Environmental Focal Person (EFP) to CSC; 2) EFP had discussed in detail regarding the EMP with CSC's Environment Specialist (ES) and proposes revision if necessary; 3) Monitoring formats and action plan has been supplied to field personnel (EFP) which will be timely filled by them and same will be basis for of report preparation for a particular period deadlines (e.g. i- operation of crushers and hot mix plants, ii- transport and storage of hazardous materials, iii- waste disposal sites, and temporary storage location, iv) water use, v) arrangements to link with government health programs (if any at subproject level) on hygiene, sanitation, and prevention of communicable diseases etc.).
b) Construction:
24. DOR PD through the CSC monitor Contractor’s compliance to EMP, audit construction activities, and evaluate monitoring program, 25. In case of non-compliance, the contractor will be instructed to correct deficiencies applying the required corrective measures., and
1 Project Administration Manual, SASEC Road Connectivity Road Project of GoN funded by ADB, July 2013
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
12
January-June 2018
26. if serious unanticipated impacts happen the EMP will be updated and mitigation measures will be fix to address the new impacts as identified.
c) Post-construction:
27. DOR PD through the External Monitor keep evaluating that works completed are in accordance with EMP and all construction sites are satisfactorily rehabilitated and restored, otherwise may initiate the action against the non-complying contractors.
5. STATUS OF ENVIRONMENTAL SAFEGUARD IMPLEMENTATION
a) Environmental Clearance on IEE/EIA reports
28. Based on the IEE report of BLT road, field verification of tree cutting requirements was done, which recorded the increase in number of trees from 1890 to 2078 to be cleared for project implementation. IEE report has been revised after joint field verification. Clearance has been taken from DFO & DOF for cutting new numbers of trees to be cut. Till the reporting date, the contractor has cut a total 2050 numbers of trees with removal of 985 roots. Now, due to monsoon rain, tree cutting and root removal process have stopped.
b) Capacity Building Activities
29. No capacity building activities were carried out during this reporting period. Capacity building plan has been prepared to carry out after rainy season. Some of the contractor’s key personals are on leave due to off-working season. The civil Contractor of BLT road appointed Mr. Gangadhar Babu Gandham as Environmental Focal Person (EFP). In his absence Mr. Ramesh Ch. is deputed.
30. Orientation on "Environmental safeguards compliances including gender concerns in the road project" was provided on November 15 - 16, 2017 to the EFP and other concerned personnel including the Contract Manager, field engineers and staffs of contractors. 31. Environmental Clearance Checklist has been prepared and handed over to EFPs for the necessary filling up and regular reporting to the CSC Environment Specialist. Till this reporting period, the contractor is regularly submitting environmental checklist to CSC Environment Specialist. Environmental Monitoring Checklist is given in the Annex 6.
c) Status of Forest Clearance
32. According to Forest Act, 2049 BS (1993) and Government Forest Work Procedure 2071 BS (2014 AD), forestry clearance has to be obtained from the MoFSC. Narayanghat – Butwal (EWH) of the SRIP road subprojects passes through national and community forests and needs to obtain forestry clearance from government authority i.e. DFO and DOF. The forestry clearance process in NB road has not yet started due to delay in contracting process. Tree cutting is done along the RoW of BLT road, till this reporting period 2050 numbers of trees cut down out of 2078 numbers to be cut. Total 985 roots have been removed from 2050 trees cut. Remaining roots will be removed before starting embanking works.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
13
January-June 2018
Table 2: Forest Clearance progress during January - June 2018
Contract Package Number
of CF
Progress up to June 2018
Remarks
Target Achieved Progress
(%)
EWH, Narayanghat –
Butwal Road I & II 55 0 0 0
Contract yet to be
awarded
Bhairahawa – Lumbini –
Taulihawa Road 0 51,950 0 0
No Community
Forest exist in BLT
road.
Joint survey for trees
counting within RoW
- (2078) has been
counted by involving
Forest Office.
33. Note: Trees cutting has been started in BLT Road along the right of way till the reporting date total 2050 trees out of 2078 trees had cut down.
Table 3: Overall Forest Clearance Status
S.N.
Name of
Road
Package
Verification of
No. of Trees to
be cut down
after
IEE/EIA/SEIA
approval
submission
of letter to
DFO for the
permission
of tree
cutting
Status of
process for
the
permission
from MoFSC
for tree
cutting
Marking of
trees
(Chhapan)
by DFO
Office for
the cutting
Cutting
trees
Activities
1.
EWH,
Narayanghat
–Butwal
Road I
Contract yet to
be awarded Not started Not started Not started Not started
2.
EWH,
Narayanghat
– Butwal
Road II
Contract yet to
be awarded Not started Not started Not done Not started
3. Bhairahawa
– Lumbini –
Taulihawa
Road
All verification
completed
Permission
granted
Permission
granted
2078 2050 nos.
of trees
cutting
completed
34. Note: Total 985 nos. of roots has been removed out of 2050 tree cutting.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
14
January-June 2018
d) Compensatory plantation
35. In BLT road, for total loss of 2078 trees, a total of 51950 compensatory plantation (CP) of seedlings has to be done at the ratio of 1:25. Compensatory plantation process is not started.
e) Status of other local clearances
36. Approval of layout plan for campsite, quarry and crusher plant is necessary. Status of these clearance and approval is given below in table 4:
Table 4: Status of Local Clearances and approval
Clearance
details BLT NB Road I NB Road II Remarks
Construction
Camp and
Storage site
1. Camp construction in 7+500 is
completed and some technical staff
shifted and some are using rental
camp in Bhairahawa.
Contract yet to
be awarded
Contract yet to
be awarded
Quarry sites
DDC approved of Tinau River,
Kundri river & Dano river.
Contractor has started material
collecting from approved quarry
sites (river materials are used for
base, sub-grade and pre-mix /
batching purpose). Borrow pits for
sub-base material has been
brought from private land holder,
whose agreement is completed
(Material used for sub- base filling).
Not started Not started
Contractor
has submitted
EMP including
quarry site
operation plan
Crusher
plant
Established at 9 +500 at private
land holder, construction is
completed and now crusher plant
in operation with labor camp
facilities.
Not started Not started
Concrete
mixing
Plant/
Batching
plant
Establishing in 4+900 in private
land holder, construction is
completed and now batching plant
in operation with labor camp
facilities.
Not started Not started
f) Awareness program
37. No formal awareness program has been initiated except informal awareness messages provided during the consultation activities.
g) Spoil management
38. Spoils have been managed in specified disposal sites to the possible extent. Table 5 below shows the spoil generated from the road construction. Contractors has been instructed to prepare spoil management plan to balance cut and fill volume considering
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
15
January-June 2018
haulage, spoil disposal sites with toe walls to retain the spoil materials if necessary. Quantity shown in table 5 is based on the approved BOQ. Contractor is re-using spoils such as aggregate, broken bitumen & cement concrete and brick bats in diversion road and sub-base preparation.
Table 5: To date spoil for different sub-projects
Sub-Project Dismantling
works (m3)
Fill Volume
(m3)
Spoil to be
managed Managed by
BLT Road 113373 351418 Need to be
managed Contractor
NB Road I 59,322 1,246,369 Need to be
managed Contractor
NB Road II 66,382 560,989
Re-using in
diversion &
sub-base filling
Contractor
(Quantity as per
approved BOQ)
39. Note: The contract awards of NB road package 01 and 02 have not yet been done.
h) Drainage management
40. Adequate and appropriate numbers of drainage structures are being provided in accordance with the design of the road in order to minimize interference and impact on natural drainage pattern of the area. Likewise, surface water discharge into farmland or risky locations and blockage or diversion of natural channels due to construction of road and disposal of spoils has been avoided. No incidents of blockage of natural streams have been reported on all road packages even though the drainage rehabilitation/ reconstruction is in process, contractor has recently started construction works and reached to pick level. Table 6 shows the list of drainage designed and progress achieved till date.
Table 6: Major Structures with Drainage detail and progress till date
Description Unit Proposed Progress till date Percentage
(%)
BLT Road
Urban section with Service
Road Km 3.7
(70% C&G work done 0.001
Rural Road without Service
Road Km 14.4
60% embankment
done 3.33
Carriage way 7 m Km 23.03 50% gravel sub-
base done 50
Hume Pipe culvert Nos. 45 27 completed, 5
unit in progress 71
RCC slab/Box Culverts Nos. 69 21 in progress 30
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
16
January-June 2018
Description Unit Proposed Progress till date Percentage
(%)
Road side Drain Km 21.5 600 m in progress 2.8
NB Road I
Urban section with Service
Road Km 17.6 NA 0
Rural Road without Service
Road Km 42.7 NA 0
Carriage way 3 lane KM. 4.1 NA 0
Hume Pipe culvert Nos. 121 NA 0
RCC slab/Box Culverts Nos. 87 NA 0
Major Bridges Nos. 12 NA 0
Minor Bridges Nos. 19 NA 0
NB Road II
Urban section with Service
Road Km 11.6 NA 0
Rural Road without Service
Road Km 27 NA 0
Carriage way 3 lane Km 9.9 NA 0
Hume Pipe culvert Nos. 159 NA 0
RCC slab/Box Culverts Nos. 30 NA 0
Major Bridges Nos. 9 NA 0
Minor Bridges Nos. 21 NA 0
41. Note: NB road Packages I & II, contract not awarded (NA)
i) Management of Dust
42. Management of dust during dry season was found prominent in the project area. Sprinkling of water near from settlement area has done by the contractor, four water sprinkling vehicles are using in dust control, till now management of dust pollution control found satisfactory.
j) Slope stabilization and bioengineering activities
43. Unstable slopes that could be stabilized using the bioengineering will be identified. Identification for bioengineering activities has not yet started. Bio-engineering works in the BLT road has also not yet started. Alignment passes through Terai region. Bio-engineering
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
17
January-June 2018
solution required only in the embankment and near to the cross drainage works in the BLT road. 44. BLT Road: Alignment passage through Terai region, bio-engineering solution
required only in high embankment and near to the cross drainage works.
NB Road I: Not started yet, NB Road II: Not started yet.
k) Rehabilitation of community infrastructures and cultural/religious sites
45. Community infrastructures especially damaged to the trail, damage stepping stairs, electric poles, water supply pipes etc. need to be reconstructed and will be continued till the completion of project, as and when required.
l) Quarry site management
46. Quarries are finalized and approval received from DCC for three quarry sites. For the use of quarry sites as mentioned in Table :4, Environmental Focal Persons has prepared quarry operation plan and submitted to CSC. Quarrying is done from the environmentally suitable and legally recognized sites. BLT Road project is using the materials from nearby natural drains/rivers identified during detail survey. Contractors have also identified the private quarry areas (Borrow pitas) especially earth for sub-base material & embankment construction. They are use after approval from the CSC as per the approved quarry operation plan. Details of the approved all three-existing quarry is provided in table 4 above.
m) Camp Site Management
47. Drinking water and sanitary facilities (toilets) are provided in the camps for each camp site in BLT road. In camps, workers are using LPG for cooking purpose which is obtained from local market. At present contractor is using rental house, since all camp site is not in operation, camp construction is going on. Workers residing in camp are also facilitated with toilet and bathroom services with partially satisfactory standard and newly under construction camp also has all facilities as per environmental requirements. Existing campsite areas from contractor and consultant are provided in table 4 above.
n) Occupational health and safety (OHS)
48. Occupational health and safety measures have been partially followed. Workers have been partially provided with safety gears like helmet, facemasks, etc. It is essential to make utilization of the safety gears by the workers. With limited knowledge of using safety gears, workers are found ignoring the use. Workers group was provided with first aid kit having essential medicines and condoms however there is necessity to specifically orient and assign a focal person. Group accidental insurance has been done for all the workers.
o) Signboard placing (erection)
49. Signboards with project information are erected at from start to end. In addition, informative signs and signage are kept where construction activities are carried out.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
18
January-June 2018
p) Grievance Redress Committees
50. During this six month period two Grievance Redress meeting and compensation proceeding meeting was held on 23rd January 2018 and on 15th March 2018 at CDO office in Bhairahawa Municipality of Rupandehi district. The meetings were chaired by Deputy CDO Mr. Sambhu Prasad Regmi. The meetings were participated by the representative of District Land Revenue office; Project manager of BLT Road, Senior engineer of Bhairahawa Municipality, representatives of Maya Devi VDC, Rupandehi; Lumbini Sanskritik Municipality, District technical office; District Urban Development office, Kosh tatha Lekha Niyantran Karyalay; Environment Safeguard Specialist, SRIP, CSC; RE from SRIP, CSC, Social Safeguard Specialist, SRIP, CSC: BLT and Lumbini Municipality. 51. In the process of improving and constructing the Bhairahawa-Lumbini-Taulihawa Road Sub-project, the house and structures within the Right of Way (ROW) of road will be required to be removed and demolished. For this purpose and to support the process of compensating the structure owners, the Sub-Committee consisting of 3 members including the representatives from Rupandehi Urban Development and Building Office, District Technical Office, and Project Management Office was formed. The Sub-Committee assessed and valuated the structures and submitted the report to the Compensation Determination Committee formed as per Land Acquisition Act 2034 clause 13. 52. Grievance Redress Committee (GRC) was established on October 2017. A total of 11 numbers of grievances on resettlement issues have been registered till date so far in BLT road. Evaluation for structures has been completed now. Total valuation of 11 accounted structures as per valuation report of Valuation Committee is NRs. 1,268,368. Minutes of GRM meeting with details are presented in ANNEX 7.
q) EMP implementation, monitoring and reporting
53. EMP implementation and monitoring in the SRIP road packages has been observed satisfactory. Implementation monitoring format has been sent to sub-project as given in Annex 5. Reporting on environmental monitoring by contractors is regular and satisfactory. 54. The Project Directorate (ADB), DoR through CSC is responsible for the regular monitoring and reporting to ADB on the implementation of environmental mitigation measures described in the EMP and the findings of the environmental monitoring. PD - ADB reviews the monitoring reports to determine if the safeguards requirements are satisfactorily met. CSC has conducted periodic site inspections to assess Contractor’s compliance to the EMP, advised the corrective measures, and reported to PD (ADB) DoR on the effectiveness of the mitigation measures and overall status of EMP implementation. Further, Contractors were asked to fill up the environmental compliance checklist that was provided earlier and submitted back to CSC regularly.
r) Disclosure of Environmental Assessments and Monitoring Reports
55. PD (ADB) DoR have disclosed the reports including IEE/EIA in their respective websites in compliance to SPS2009 information disclosure requirements. Semi-annual monitoring reports will be submitted by DoR for disclosure on the ADB website.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
19
January-June 2018
s) Monitoring of Safeguards Implementation
56. PD (ADB)/ DOR assisted by Resettlement Specialist, Environmental Expert, and GESI Specialist of CSC are responsible for monitoring of the social including gender, resettlement and environment aspects of the Projects. External Social and Environmental Monitor has already been appointed to carry out independent monitoring of the implementation of the Environmental Management Plan and Social RP and GAP implementation including the Biodiversity Conservation activities under the EMP.
t) Status of Wildlife Survey
57. Wildlife baseline survey completed and information on camera trap gathered. Rapid sign survey for wildlife was conducted in May 2018, in the six forest patches along the NB highway from Gaidakot to Bardaghat. Field data collected and draft report shared to environmental officer, PD office and ADB Manila for their comments. Wildlife technicians and students were used for reporting. Proposal and estimate for the wildlife baseline survey drafted revised and approval received. Presence of tiger (Panthera Tiris) in Chormara to Daunne block towards south from the highway in Community was recorded and verified by the communities, community forest of Lokaha to Kawasoti area found utilized by one-horned rhinoceros (Rhinoceros Unicornis) across the highway towards north, common leopard (Panthera Pardus) sign recorded in two of the six forest patches-Thumse to Sisnedanda and Arun Khola to Belani towards north of highway respectively. 58. Availability of camera trap for renting was assessed, locally available equipment and logistics required for the conduction of wildlife baseline survey searched, rate of the camera trap from the manufacturer Reconyx and Cuddeback was received.
6. OVERALL COMPLIANCE WITH EMP
59. Table 7 given below shows the overall compliance status of EMP in all road packages of SRIP.
Table 7: Overall compliance status of SRIP road projects
No
.
Road Package
Name
EMP Part
of
Contract
Docume
nts (Y/N)
EMP
Being
Impleme
nted
(Y/N)
Status of
Implementation
(Excellent/
Satisfactory/ Partially
Satisfactory/ Below
Satisfactory)
Action Proposed
and Additional
Measures
Required
Bhairahawa – Lumbini – Taulihawa
Road
Y Y Satisfactory follow up for further
necessary improvement
1. NB Road I Y Contract yet to be
awarded
2. NB Road II Y Contract yet to be
awarded
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
20
January-June 2018
7. ISSUES AND WAY FORWARD
60. Table 8 below shows the main environmental issues and way forward for the effective implementation of environmental safeguard measures. Other specific issues relating to environmental compliance in road project and corrective actions to be taken are given in table 8 below:
Table 8: Issues and corrective measures
SN ISSUE CORRECTIVE MEASURES
1 Identification of
community structures
in Right of way is
completed
• Re-allocation works will be carried out after completion of
the road construction works after close coordination with
concerned communities.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
21
January-June 2018
Annexes
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-1
January-June 2018
Annex 1a: Environmental Safeguard Planning Status
S
N
Name of
Road
Packages
Environ
mental
Screeni
ng Is
Carried
Out?
(Yes/
No)
Environme
nt
Category
of The
Project /
Subproject
(A/B/C/Fi)
Earf Is
Prepared
(If
Applicab
le)
(Yes/No)
EIA/IEE
/DDR
With
EMP Is
Prepar
ed
(Yes/
No)
ADB
Approved
EIA/IEE With
EMP
(Yes / Under
Review / Not
Yet
Due/Over
Due)
Governmen
t
Approved
EIA/IEE
With EMP
(Yes /
Under
Review /
Not Yet
Submitted)
Safeguard
Monitorin
g And
Coordinati
on
Mechanis
m
Establish
ed
(Yes/No)
GRC Is
Establi
shed
(Yes
/No)
Automate
d
Safeguard
Monitorin
g System
Customiz
ed
(Yes/No)
EMP
Cost in
Approve
d
Docume
nt Is
Included
In
BoQ As
an
Individua
l Item
(Yes/No)
1. BLT Road Y B Y Y Y Y Y Y N Y
2. NB Road I Y A N Y Y Y N N N N
3. NB Road II Y A N Y Y Y N N N N
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-2
January-June 2018
Annex 1b: Environmental Safeguard Implementation Status (Reporting period: January to June, 2018)
Name of Project: SASEC Road Improvement Project (SRIP)
S
N
Name of
Sub-project
Compliance to Environmental Management Plan*
Grievances
Correc
tive
Action
Plans
are
prepar
ed and
imple
mente
d (Y/N)
Env.
compli
ance
reporti
ng is
maintai
ned
(Y/N)
Rem
arks Physical Biological Socio-economic
Spoil
Manag
ement
complia
nce in
%
Landslid
e
protectio
n with
Bio-engg
(complia
nce in
%)
Drainag
e
Manage
ment
(compli
ance in
%)
Others as
per EMP
(specify)
Compensatory
Plantation Firewood
is used
for
cooking
and
heating
(Y/N)
Others as
per EMP
(specify)
Occupational Health and
Safety Community
structures are
compensated /
reconstructed
(progress in %
of total
estimated
work)
Others
as per
EMP
(specify
)
No of
grieva
nces
docum
ented
No of
grievan
ces
resolve
d
No of
grieva
nces
under
proces
sing
Target
(Nos.)
Replant
ed
(Nos.)
Safety
Gears
are
sufficient
and used
(Y/N)
Labors
are
insured
(Y/N)
Labor and
work camps
are healthy
and have
sanitary
facilities
(Y/N)
1 BLT Feeder
Road
Not
start
ed
Not
starte
d
30%
CD &
RSD
*
No 52,2
00 No No No Y Y Y
Compensati
on In
process
No 11 NO 11 No Yes
2 EWH NB
Road I CNA CNA CNA CNA
CN
A CNA CNA CNA CNA CNA CNA CNA CNA
CN
A CNA
CN
A CNA
CN
A
3 EWH NB
Road II CNA CNA CNA CNA
CN
A CNA CNA CNA CNA CNA CNA CNA CNA
CN
A CNA
CN
A CNA
CN
A
• Note: CNA: Contract not yet awarded
• CD: Cross drainage works; RSD: Road side drainage works
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-3
January-June 2018
Annex 2: Environmental Management Cost (NRs)
Details of Provisional Sums (ICB and NCB Contracts)
Budget included under BOQ & Provisional sum for environmental mitigation and Enhancement
Status of Implementation of proposed Enhancement
measure/mitigations BLT NB road I NB Road II
Re-allocation of passenger shades & Services 3,400,000
Bio-engineering and civil engineering structures for stabilization of the
land & Slope 8,189,985 (PS) 15,000,000 (PS) 15,000,000
Compensatory tree plantation (PS) 5,091,075 6,318,922 6,318,922
Supply and erect traffic signs and safety measures 155,302,000
Relocation of services (PS) 40,090,000 136,320,000 136,320,000
Supply of safety gears to the workers (PPE) 450,000
Environment Mitigation works (Engineers instruction) (PS) 1,300,000 2,500,000 2,500,000
Not specified (Offsite verification testing by engineer) 500,000
Social compliance as instructed by engineer (PS) 2,500,000 2,500,000 2,500,000
Bio- diversity conservation & Enhancement Measure (PS)
50,000,000
Total cost for Environmental Mitigation and Enhancement 216,823,060 212,638,922 162,638,922
Note: EWH Narayanghat – Butwal Road I & II contract yet to be awarded.
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-4
January-June 2018
Annex 3: Status of Environmental Safeguard Compliances
SN Road
Packages Status Environmental Compliance Measures Compliance Status
1 Bhairahawa
– Lumbini –
Taulihawa
Feeder Road
Under
Construction
Camp site Layout preparation and approval
Camp site Layout plan is prepared and approved. As per contractor’s
assurance Camp site is provisioned with:
• cooking gas, food items, electricity, water supply, waste management,
transportation, and medical facilities
• Effective barricading of the camp area for unauthorized access
• Camp site is located in lease land of private land holder
• Camp site is far from dense settlement area.
• To avoid the conflict on local resources uses, contractor has
provisioned the camp with its own water supply, sanitation and
cooking energy.
• Both the camps are facilitated with well-spaced/equipped kitchen and
dining facilities restrict them from using firewood for cooking.
• Regular monitoring of their activity by the Environmental Focal Person
• No govt. and community forest in the 1 km periphery.
• Underground water only after proper treatment is used for drinking
purpose.
• All the camps are facilitated with adequate toilet facilities
• 1 septic tank/ soak pit toilets in Sr. staff quarter and toilet in Jr. staff
quarter are of adequate sizes & 1 – 1 unit in crushing and mixing
plant.
• Camp sites are provided with LPG to avoid firewood dependency.
• Solid wastes are segregated as decomposable and non-
decomposable wastes before disposal.
Satisfactory
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-5
January-June 2018
SN Road
Packages Status Environmental Compliance Measures Compliance Status
• Sewages from the daily activities are treated safety tank &disposal in
sock pits.
• Sewage is not disposed into the river courses.
• All the construction related waste is disposed in designated/safe
places in direct consultation with the local people and stakeholder
authorities
Lease agreement with land owner in case of private land and
permission from concerned agency (VDC/Municipality Office) in case
of public land
• Land lease agreement has been done with the respective land owners
Satisfactory
Removal of Vegetation Clearance including tree cutting and land
clearing activities
• Avoid tree felling as far as possible to ensure the minimum loss of
Tree, cutting (as minimum as possible) shall be done after approval.
• Shifting of cultural properties like small temples/shrines coming within
the road land width to adjacent areas in consultation with local
community.
• Inventory of all public utilities like power transmission cables,
telephone cables, water/sewerage lines, drains, tube wells, etc., falling
within road land width and arrangement for relocation/shifting to
adjacent areas in consultation with the respective agencies/
authorities.
Identification is
completed but
reallocation is not
started but assurance
received from
Environment & safety
focal person.
Establishment of site office, officers' quarter and laboratory
• Temporary site office with accommodation facilities is under
constructed at 7+500 km and approval has been taken.
• Land lease agreement has been done with all the land owners
Satisfactory
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-6
January-June 2018
SN Road
Packages Status Environmental Compliance Measures Compliance Status
• The temporary office and storage area for construction works is
located away from human settlement areas (minimum 500 m) and
forest areas (minimum 1 km). However, proper mitigation measures
(fencing of the construction area, water sprinkling in the dust prone
areas, use of resources such as: water, fuels from the sources other
than the resources being used by the locals, etc.) has been done by
the contractor to avoid conflict between local people and the
contractor.
• Storage yard is located in private lease land
• Land lease agreement has been done with the respective land owners
• Restoration of the leased land shall be done after completion of
construction works
• Spillage and leakage of oil/lubricants are readily being cleaned/
removed immediately.
• Used oils shall be stored separately and shall be sold to the
scavengers.
• Storage tanks are shield and informative boards are kept.
• Underground water is used with proper treatment for drinking purpose.
• All camps are facilitated with adequate toilet (Separate unit
constructed for ladies & Gents)
• Proper care shall be provided in storage of fuel tanks, oil and greases
• Regular monitoring and inspection to ensure “No leakage” of
flammable and hazardous materials from well trained personnel
• Immediate clean-up of the leaked oil and flammable liquids
• Proper fencing of the storage areas
• Post placards clearly marking “fire escape route” and emergency
staging area” and keep the area clear of all materials, especially
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-7
January-June 2018
SN Road
Packages Status Environmental Compliance Measures Compliance Status
hazardous and inflammable ones
• Install a direct phone line with nearby Fire Department
• Install siren in different locations and post “No Smoking” sign in all fire
hazardous areas
Quarry Site/Borrow pit construction materials, i.e., boulders,
aggregates, earth and water for construction work
• Quarry sites have been selected as per the EIA/IEE report
• Adequate coordination has been done with Material Engineer/RE
office and DDC office.
• No material shall be burrowed unless it is approved by authorized
bodies
• Approval of 3 quarry sites have been taken
• Proposed burrow areas are rich in boulders and gravels so topsoil
restoration is not applicable. However, bank protection works are
being taken into account.
• No agricultural land is proposed for the material burrowing purpose.
• Required water for construction is managed from the sources other
than the resources currently being used by the local people.
• Final lease agreement/approval with DDC has been completed and
material collection from quarry sites is started. (At present, collection
from quarry sites are stopped due to rainy season)
Partially Satisfactory
Operation of crusher plant
• Crusher plant is located in Private lease land. Away from settlement
area. ( 9+500)
• Land lease agreement has been done with the respective land owners
• All the construction works area are fenced for unauthorized access
Satisfactory
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-8
January-June 2018
SN Road
Packages Status Environmental Compliance Measures Compliance Status
• Operation of crusher plant not started, (Plant under construction)
• Labor camp facilitate with gas, drinking water, fan etc.
Occupational Health and Safety
• Adequate PPEs shall be provided for the workers
• OHS Training.
(Construction work started recently, training not provided)
Partially Satisfactory
(OHS Training Not
Provided)
Mobilization of construction machineries and vehicles
• Regular inspection and maintenance of the vehicles
• Control of oil and grease leakage
• All the vehicles carrying materials are covered
• Regular monitoring and take necessary corrective measures if any
spills are recorded
• Regular monitoring to ensure no child labor and pregnant woman in
construction work
• Awareness program for the locals about not involving “Children &
Pregnant Women at Work”
• Ear plugs and mufflers are provisioned for the workers at high noise
• Rotation of Work Shift to avoid long term exposure.
• Underground water is used for drinking purpose after treatment.
• All camps are facilitated with adequate toilet facilities
• Health kits availability in the camp sites with adequate medical
facilities for first aid treatment.
Satisfactory
2 EWH NB
Road I &II
Contract yet to
be awarded
Camp site Layout preparation and approval
Lease agreement with land owner in case of private land and
permission from concerned agency (VDC/Municipality Office) in case
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-9
January-June 2018
SN Road
Packages Status Environmental Compliance Measures Compliance Status
of public land
Removal of Vegetation Clearance including tree cutting and land
clearing activities
•
Establishment of temporary site office and material storage areas
Quarry Site/Borrow pit construction materials, i.e., boulders,
aggregates, earth and water for construction work
Operation of crusher plant
Occupational Health and Safety
Mobilization of construction machineries and vehicles
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-10
January-June 2018
Annex 4: Plantation Plan
Development projects passing through Agriculture land and settlement areas are far from forest area. Appropriate mitigation measures have been recommended in the already approved Initial Environment Examination (IEE)/Environmental Impact Assessment (EIA) report and main mitigation measures related to vegetation loss, slope stabilization and pollution are compensatory plantation, roadside plantation, plantation in private land and bioengineering. According to the Government of Nepal (2071/01/12 BS): Standard for Removing
Government Trees, 2071 BS (2014 AD), each road projects has to carry out plantation (with protection for five years) at the ratio of 1:25 plants or pay for the plantation and protection cost to the concerned community forest user groups (CFUGs)/District Forest Office. In private land, trees will be planted at the ratio of 1:1. Table 1 will be used to manage the planting stock for plantation for different purposes. Table 1: Type of plantation and planting stock
Type of plantation
Number of
plants
needed
Costs of plants
including
transportation
Sources of
planting
stock
Remarks
Compensatory plantation
51,950 5,091,075
allocated in PS
Verification completed.
Road Side Plantation 5,432 2,172,000.00 Allocated in
BoQ Bio-engineering and civil engineering structures for stabilization of the land & Slope
9,867,185 Allocated in
BoQ
A. Compensatory plantation
Requirements for plantation activities
1. Process not yet started.
B. Roadside plantation
1. Process not started
C. Plantation in private land
1. Process not started
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-11
January-June 2018
Annex 5: Implementation Reporting Format
Reporting period: Up to June 2018
Road Package:
Name of Environmental Focal Person: Ramesh Ch., DCM, GAWAR Construction BLT
S.N. Description Indicator Status Remarks
1 IEE/EIA report
Completed/ongoing/proposed Completed
2 Awareness raising orientation training
Number of events and Participants
Not provided
3 Spoil disposal Management
Preparation of spoil disposal management plan
Done
Volume of spoil disposed (m3) Safely
0
Remaining excavated materials (m3)
0
4 Toe walls for safe disposal of excavated materials
Number and volume (m3) 3778 Not started
5 Bioengineering Works
Location Not started Area (m2)
Type of measures taken
6 Quarry site Management
Location
Rehabilitation carried out or not Not started
Volume of aggregates supplied (m3)
24,403
7 Campsite Management
Number of Workers (M/F) 52
Supply of safe drinking water Yes
No. of temporary toilets in camp Sites
8 units
Open defecation in percentage No
Cooking energy used (fuel wood, kerosene, LPG, electricity)
Yes
8 Quality of surface water observed in road side
Good Good
Polluted No
9 Land slide and erosion control measures
Type of measures taken Not done
Number
10 Compensatory plantation in forest area
Number of plants felled Not started
Plantation carried out (number of plants/area in ha)
Name & location of forest
Plantation survival rate (%)
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-12
January-June 2018
S.N. Description Indicator Status Remarks
Establishment of nursery (number & location)
11 Tree cutting status from community forest
Number of trees to be cut 2078
Number of tree fell down 2050
Number of re-plantation Not started
12 Compensatory plantation in private land
Number of plants felled 2050
Plantation carried out (number of plants)
Not started
13 Road side plantation Plantation carried out (number of plants)
Not started
Location
14
Rehabilitation of community infrastructure along road side
Name Not started
Location
15
Protection/ Rehabilitation of culturally & religiously sensitive spots (Temple, Mane, cremation sites etc.)
Name Not started
Location
16
Occupational health & safety
Number of safety gears provided (helmet, facemasks etc.)
100
Use of safety gears by workers in percentage
30%
First aid kit provided with medicines (number)
3
Replacement of medicines
Accidental insurance (number of workers)
done
Type & number of accident Occurred
Not reported
Compensation provided
Number of workers fallen sick
17 Pollution Management
Air Pollution:
Pollution monitoring as per ‘Pollution Monitoring Plan’
Good
Date of monitoring
Remedial measures taken up (based on monitoring result).
Dust Pollution
SEMI-ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-13
January-June 2018
S.N. Description Indicator Status Remarks
Measures taken up for dust control at site
Yes
Noise Pollution Controlled
Measures taken up for noise control at site
Yes
18 Signboard erected Number 16
Location Different locations
19 Meeting convened by safeguard desk
Number of meeting held Every visit Environmental monitoring done Yes
20 Grievances received and addressed
Received number 11
Addressed number In process
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-14
January-June 2018
Annex 6: Environmental Monitoring Checklist
Bhairahawa - Lumbini – Taulihawa (BLT) Road SASEC Road Improvement Project (SRIP)
Site Location: BLT Road Construction Stage/ Stage during inspection: Construction Stage Inspection Date: 26th June 2018 Inspection Time: Morning- Evening Inspected By: Ramesh CH. Weather: Sunny (Clear Sky)
Inspection Item
Implemented (Quantify if possible)
Remarks (i.e. Specify location good practice, problems
observed conformity and or proposed corrective/ preventative actions) Yes No NA *
1 2 3 4 5 1. Air Pollution Control
1.1 Are the construction site watered to minimize dust generated?
√
1.2 Are Stoke Material of dusty Materials (Size more than 20 bags cement) covered or watered?
√
1.3 Cement debagging process undertaken in sheltered area?
√ Cement mixing plant located far from resident/sensitive area.
1.4 Are all Vehicles Carrying dusty loads covered/watered over prior to leaving the site?
√
1.5 Are demolition work area watered? (E.g. trimming activities by using breakers?)
√ Not yet started
1.6 Are dusty road paved and or sprayed with water?
√
1.7 Are dust controlled during percussive drilling or rock breaking?
√
1.8 Are plant and equipment well maintained? (Any black smock observed, please indicate the plant/ equipment and locations)
√ 1. Km 4 +800 RHS (Batching Plant) 2.Km 7+400 LHS (Camp office) 3.Km 9+400 RHS (Crusher) 4. 27+500 RHS Batching Plant
1.9 Is dark smoke controlled from plant? √ 1.10 Are there enclosures around the main dust-generating activities?
√
1.11 Hoarding (not<2.4) provided along boundaries and properly maintained (any damage/opening observed, please indicate the locations)?
√ Not damaged
1.12 Are speed control measures applied? (e.g. speed limit sign)
√
1.14 Are vehicle using for construction have environment clearance received for
√
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-15
January-June 2018
Inspection Item
Implemented (Quantify if possible)
Remarks (i.e. Specify location good practice, problems
observed conformity and or proposed corrective/ preventative actions) Yes No NA *
1 2 3 4 5 government (Green sticker label)? 1.13 Other (Please specify)
2. Water pollution Control 2.1 Are there any waste water discharge to the storm drains? Is the waste water being treated? (Camp site)
√ Camp facilitating with suck pits & temporary site if well maintained.
2.2 Are water pollution control measures provided properly?
√
2.3 Are sand bags /earth bund adopted to prevent washing away of sand/silt and waste water to drain, catch pits, public road and footpath?
√
2.4 Are vehicle and plants cleaned before leaving the sites?
√
2.5 Are wheel washing facilities well maintained to prevent flooding sediment?
√ Vehicle maintenance unit not completed
2.6 Is sand and silt settled out in wheel washing bay and removed?
√ Vehicle maintenance unit not completed
2.7 Is the public road/ area around the site entrance and site hoarding kept clean and free of muddy water?
√
2.8 Is domestic waste water directed to septic tanks or chemical toilets in camp site?
√ Septic Tank
3. Noise Control
3.1 Is the CNP (Construction Noise Permit) valid for work during restricted hours?
√
3.2 Are copies of the valid Construction Noise Permit posted at site entrance/exit?
√
3.3 Do air compressor and generator operate with doors closed?
√ Silent generator used & Sufficient buffer area maintained
3.4 Is idle plant/equipment turned off or throttled down?
√
3.5 Do air compressor and handheld breakers have valid noise emission level (NEL)?
√
3.6 Any noise mitigation measures adopted (e.g. use noise barrier/enclosure)?
√ Plant under construction
3.7 Are silenced equipment utilized? √ 4. Waste Management in camp
4.1 Is the site kept clean and tidy? (e.g. litter free good housekeeping)
√
4.2 Are separate chutes used for inert and non-inert waste?
√
4.3 Are separate labeled containers/areas provided for facilitating recycling and waste segregation?
√
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-16
January-June 2018
Inspection Item
Implemented (Quantify if possible)
Remarks (i.e. Specify location good practice, problems
observed conformity and or proposed corrective/ preventative actions) Yes No NA *
1 2 3 4 5 4.4 Are construction wastes/recyclable wastes and general refuse removed off site regularly?
√
4.5 Are construction waste collected and disposed of properly by licensed collectors?
√ Sent to Bhairahawa Municipality waste disposal system.
4.6 Are chemical waste, if any, collected and disposed of properly by licensed collectors?
√ No hazardous chemical used in this project.
4.7 Does chemical waste producer license cover all major chemical waste produces on site?
√ ″
4.8 Are chemical waste properly stored and labeled?
√ ″
4.9 Are oil drums and plant/equipment provided with drip trays?
√ Maintenance plant not in operation but provision is made.
4.10 Are drip trays free of oil and water? √ ″
4.11 Is there any oil spillage? Clean up the contaminated soil immediately?
√
4.12 Is liter, foam or other objectionable matters in nearby water drain/sewer cleaned?
√
4.13 Are demolished waste disposed properly?
√
4.14 Others (Please specify) 5. Storage of Chemicals and Dangerous Goods
5.1 Are chemical stored and labeled properly?
√
5.2 Doe storage of DG complies with license conditions (include type and quantities if DG store is available check the DG store license)?
√ No hazardous chemical used
5.3 Are proper measure to control oil spillage during maintenance or to control other chemical spillage? (e.g. provide drip trays)
√ Maintenance plant not in operation
5.4 Are spill kits/sand/saw dust used for absorbing chemicals spillage readily accessible?
√
5.5 Others (Please specify) 6. Protection of Flora, Fauna and Historical Heritage
6.1 Are disturbance to terrestrial flora minimized (e.g. plants to be preserved)?
√
6.2 Are disturbance to terrestrial fauna minimized (if rare species identified?)
√
6.3 Any historical heritage exists on site? If yes, ensure appropriate measures taken to preserve it.
√ Sufficient distance maintained from Lumbini’s historical heritage site.
6.4 Is road side plantation done √ 2,050 trees were cut down
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-17
January-June 2018
Inspection Item
Implemented (Quantify if possible)
Remarks (i.e. Specify location good practice, problems
observed conformity and or proposed corrective/ preventative actions) Yes No NA *
1 2 3 4 5 6.5 Is compensatory plantation done? √ Not started 6.6 Others (Please specify)
7. Resource Conservations 7.1 Is water recycled wherever possible for dust suppression?
√ Not started / camp under construction
7.2 Is water pipe leakage and wastage prevented?
√
7.3 Are diesel-powered plants and Equipment shutoff while not in use to reduce excessive use?
√
7.4 Are energy conservation practices adopted?
√ Energy saving LED light are used
7.5 Are metal or other alternatives used to minimize the use of timber?
√
7.6 Are pesticides used under the requirement of agriculture, fishers and Conservation Department?
√
7.7 Others (Please specify) 8. Emergency Preparedness and Response
8.1 Are fire extinguisher/ fighting facilities properly maintained and not expired? Escape not blocked/obstructed?
√
8.2 Are accidents and incidents reported and reviewed and corrective and preventive actions identified and recorded?
√
8.3 Are Workers provided with Personal Protective Equipment (PPE) like boot, gloves, helmet?
√
8.4 Is First –Aid Kit maintained at Site? √ 8.5 Any fatal injury so far? √ 8.6 Others (Please specify)
9. Social inclusion and safety 9.1 Employment opportunity for local people √ 58 nos.,
9.2 Do health and safety awareness program conducted (HIV /AIDS, STD)?
√ To be conducted
9.4 Is community infrastructure relocation started? Specify progress status?
√ 18Km – 41: km Identification completed
*Note: NA (Not Applicable) Progress status and Issue in Brief.
1. Labor camp, stone crushing plant and concrete mixing plant are completed and now all are well working.
2. Batching plant is in operation and camp facilities also completed. 3. Identification of community infrastructure reallocation completed from Chainage 18 km
to 41 Km. 4. Approval for tree cutting is completed and 2,050 nos. of trees cutting completed, 5. 4 water spiking vehicles are in operation to control dust pollution at construction site.
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-18
January-June 2018
Annex 7: Grievance Redress Mechanism (GRM) Meetings
Total two Grievance Redress Mechanism (GRM) meeting held during this semi-annual
Reporting period as follows: First Grievance Redress Mechanism (GRM) meeting was held on 23rd January 2018 at CDO office in Bhairahawa Municipality of Rupandehi district. This meeting was chaired by Deputy CDO Mr. Sambhu Prasad Regmi. Following participant was present in discussion: Representatives from: District Land Revenue office; Project Manager from Bhairahawa – Lumbini – Taulihawa Road improvement project, Senior engineer, Bhairahawa Municipality, Maya Devi VDC, Rupandehi; Lumbini Sanskritik Municipality, technical office; District Urban Development office; Kos tatha Lekha; Environment Safeguard Specialist, SRIP, CSC, Social Safeguard Specialist, SRIP, CSC: and Lumbini Municipality. In the process of improving and constructing the Bhairahawa-Lumbini-Taulihawa Road Sub-project, the house and structures within the Right of Way (ROW) of road will be required to be removed and demolished. For this purpose and to support the process of compensating the structure owners, the Sub-Committee consisting of 3 members including the representatives from Rupandehi Urban Development and Building Office, District Technical Office, and Project Management Office has been formed. The Sub-Committee will assess and valuate the structures and submit the report in the next meeting to the Compensation Determination Committee formed as per Land Acquisition Act 2034 clause 13. Second Grievance Redress Mechanism (GRM) meeting was held on 23rd January 2018 at CDO office in Bhairahawa Municipality of Rupandehi district. This meeting was chaired by CDO Mr. Hari Prasad Mainali, as per land acquisition act 2034 clause 13. Following participant was present in discussion: Representatives from: CDO (Chairman), members: District Land Revenue office; Project manager from Bhairahawa – Lumbini – Taulihawa Road improvement project, Bhairahawa Municipality, Education Officer, Mayadevi VDC and Lumbini Culture Municipality. During this meeting following invited persons also Participated: Deputy CDO, Rupandehi; representatives from District technical office, Rupandehi, District Urban Development office CDO office; Kos tatha Lekha; Resident Engineer, SRIP, CSC; Social Safeguard Specialist, SRIP, CSC: BLT road improvement project and Social Mobilizer, Bhairahawa Lumbini Taulihawa Road project. During this meeting Following discussion was made: Report was presented by valuation sub-committee. In the process of improving and constructing the Bhairahawa-Lumbini-Taulihawa Road Sub-project, the house and structures within the Right of Way (ROW) of road will be required to be removed and demolished. For this purpose and to support the process of compensating the structure owners, the Sub-Committee consisting of 3 has submitted their valuation report. Meeting also decided that the required legal documents need to be collected by social mobilizer.
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-19
January-June 2018
Annex 7.a. Minutes of First GRM Meeting:
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-20
January-June 2018
Annex 7.b. Minutes of second GRM Meeting:
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-21
January-June 2018
ANNEX 8: Photographs
Photo 1: Concrete mixing plant (Batching Plant) at 4+900
Photo 2: Pre-cast drain molded at Batching Plant at KM 4+900
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-22
January-June 2018
Photo 3: Toilet and labor camp in Batching Plant
Photo 4: Cooking and drinking water inside labor camp in Batching Plant
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-23
January-June 2018
Photo5: Road side drainage under construction at Muglaha in BLT Road
Photo 6: Diversion made during RCC Box culvert construction in BLT road
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-24
January-June 2018
Photo 7: Tree logs stocked at DFO compound of Rupandehi district office
Photo 8: Fire extinguisher placed at contractor’s office at KM 7+500
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-25
January-June 2018
Photo 9: Water sprinkled in Gravel road during day time to control dust pollution
Photo 10: Ladies and Gents toilet separate at site office at KM 7+ 500
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-26
January-June 2018
Photo 11: Temporary stocking of tree logs in contractor’s compound due to
insufficient space available in DFO office compound.
Photo 12: Contractor’s Main Kitchen for officers
SEMI ANNUAL (ENVIRONMENTAL MONITORING) REPORT 2
A-27
January-June 2018
Photo 13: Stone crushing plant in operation at KM 9 +500
Photo 14: Crushed material and raw material stocked at crushing plant at KM 9 +500