Environmental Monitoring Report - adb.org...Prepared by the Irrigation Department, Government of the...
Transcript of Environmental Monitoring Report - adb.org...Prepared by the Irrigation Department, Government of the...
Environmental Monitoring Report
Semiannual Report Project number: 46528–002 Loan Number: 3599 January 2021
Pakistan: Jalalpur Irrigation Project Prepared by the Irrigation Department, Government of the Punjab for the Asian Development Bank (ADB). This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
GOVERNMENT OF THE PUNJAB
IRRIGATION DEPARTMENT
PROJECT MANAGEMENT OFFICE (PMO) CANALS
Loan No. 3599-PK- Project No. 46528-002-PAK
SEMI-ANNUAL ENVIRONMENTAL
MONITORING REPORT # 01
January 2021
(Reporting Period March 2020 to December 2020)
PROJECT IMPLEMENTATION CONSULTANTS OF JALALPUR
IRRIGATION PROJECT (JIP)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
1 | P a g e
SEMI ANNUAL INTERNAL ENVIRONMENTAL SAFEGUARDS MONITORING REPORT
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
2 | P a g e
Table of Contents
Table of Contents __________________________________________________________ 2
List of Exhibits ____________________________________________________________ 5
List of Abbreviation ________________________________________________________ 1
BRIEF SUMMARY _________________________________________________________ 4
1 INTRODUCTION AND BACKGROUND _____________________________________ 8
1.1 General __________________________________________________________ 8
1.2 Background _______________________________________________________ 8
1.3 Project Location ____________________________________________________ 9
1.4 Project Objectives _________________________________________________ 12
1.5 Project Features __________________________________________________ 12
1.6 Description of Civil Works Area _______________________________________ 12
2 DESIGN LEVEL DETAILS OF CONSTRUCTION ACTIVITIES OF ICB-P1, P2 & P3 _ 14
2.1 Project Implementation and Packaging _________________________________ 15
2.2 Punjab Agriculture Department Purview ________________________________ 16
3 PROJECT ORGANIZATION AND ENVIRONMENTAL MANAGEMENT TEAM _____ 17
3.1 Progress of Construction Works ______________________________________ 18
3.2 Reporting Period of the Project _______________________________________ 20
4 ENVIRONMENTAL MANAGEMENT ______________________________________ 21
4.1 General _________________________________________________________ 21
4.2 Site Specific Environmental Management Plan (SSEMP) ___________________ 21
4.3 Health and Safety Plan _____________________________________________ 25
4.4 COVID-19 Management at JIP _______________________________________ 25
4.5 Borrow Area Management Plan ______________________________________ 27
4.6 Traffic Management Plan ___________________________________________ 28
4.7 Grievance Redress Mechanism (GRM Urdu & English) ____________________ 31
4.8 Due Diligence of Project Affected Schools ______________________________ 31
4.9 Public Consultation & Social Framework Agreement (SFA) _________________ 36
4.10 Urdu Brochure for Contractor’s Staff ___________________________________ 38
4.11 Emergency Preparedness & Response ________________________________ 39
4.12 Waste Management _______________________________________________ 40
4.13 Trainings ________________________________________________________ 41
5 ENVIRONMENTAL MONITORING _______________________________________ 43
5.1 Environmental Monitoring ___________________________________________ 43
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
3 | P a g e
5.2 Impact Monitoring _________________________________________________ 43
5.2.1 Site Visits ______________________________________________________ 44
5.2.2 Monitoring Checklists _____________________________________________ 45
5.3 Instrumental Monitoring _____________________________________________ 45
5.3.1 Instrumental Monitoring July 2020 ___________________________________ 45
5.3.2 Instrumental Monitoring December, 2020 _____________________________ 52
5.4 Corrective Action Plan (CAP) ________________________________________ 58
5.4.1 Major Issues / Non-Compliances ____________________________________ 58
5.4.2 Compliances ___________________________________________________ 58
5.4.3 Corrective Action Plan for the Month of March,2020 _____________________ 60
5.4.4 Corrective Action Plan for the Month of April,2020 ______________________ 60
5.4.5 Corrective Action Plan for the Month of May,2020 ______________________ 60
5.4.6 Corrective Action Plan for the Month of June,2020 ______________________ 61
5.4.7 Corrective Action Plan for the Month of July 2020 _______________________ 61
5.4.8 Corrective Action Plan for the Month of August,2020 ____________________ 62
5.4.9 Corrective Action Plan for the Month of September,2020 _________________ 62
5.4.10 Corrective Action Plan for the Month of October,2020 __________________ 63
5.4.11 Corrective Action Plan for the Month of November ,2020 _______________ 63
5.4.12 Corrective Action Plan for the Month of December,2020 ________________ 64
6 EMP COMPLIANCE ___________________________________________________ 65
6.1 Compliance Status from March – Dec 2020 _____________________________ 65
6.1.1 Environmental Compliance Status March-2020 _________________________ 65
6.1.2 Environmental Compliance Status April-2020 __________________________ 67
6.1.3 Environmental Compliance Status May-2020 __________________________ 69
6.1.4 Environmental Compliance Status June-2020 __________________________ 72
6.1.5 Environmental Compliance Status July-2020 __________________________ 74
6.1.6 Environmental Compliance Status Aug-2020 __________________________ 76
6.1.7 Environmental Compliance Status Sep-2020 __________________________ 79
6.1.8 Environmental Compliance Status October-2020 _______________________ 81
6.1.9 Environmental Compliance Status November-2020 _____________________ 83
6.1.10 Environmental Compliance Status December-2020 ___________________ 86
6.2 Trends in EMP Compliance __________________________________________ 89
6.2.1 Trends in Conformance Level ______________________________________ 89
6.2.2 Environmental Conformance Level __________________________________ 89
7 FUNCTIONING OF THE SSEMP _________________________________________ 92
7.1 SSEMP Controls __________________________________________________ 92
8 GOOD PRACTICE AND OPPORTUNITY FOR IMPROVEMENT ________________ 93
8.1 Good Practice ____________________________________________________ 93
8.1.1 Awareness _____________________________________________________ 93
8.1.2 Training _______________________________________________________ 93
8.1.3 Housekeeping __________________________________________________ 94
8.1.4 Communication _________________________________________________ 94
8.1.5 Supervision ____________________________________________________ 94
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
4 | P a g e
8.2 Opportunities for Improvement _______________________________________ 94
8.2.1 Documentation __________________________________________________ 94
9 SUMMARY AND RECOMMENDATIONS __________________________________ 95
PHOTOLOG _____________________________________________________________ 97
Annex-A Sample GRM Record ____________________________________________ 121
Annex- B Social Framework Agreement Malikpur ____________________________ 127
Annex-C Social Framework Agreement at Mouza Shah Kamir ___________________ 130
Annex-D Sample Daily, Weekly & Monthly Checklists __________________________ 134
Annex-E Urdu Brochure for Contractor ______________________________________ 140
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
5 | P a g e
List of Exhibits
Location of the Project ..................................................................................... 9 Project Foot Prints ........................................................................................ 10 Project Layout Plan ........................................................................................ 11 Distribution of Land being Acquired for Jalalpur Irrigation Project .................. 13 List of Proposed Structures of Jalalpur Irrigation Project under ICB-P1.......... 14 List of Proposed Structures of Jalalpur Irrigation Project under ICB-P2.......... 14 List of Proposed Structures of Jalalpur Irrigation Project under ICB-P3.......... 15 Project Implementation and Packaging Detail ................................................ 16 Organizational Setup of the ESMMC ............................................................. 17
The Construction Area ................................................................................... 19 COVID-19 Management at Project Site.......................................................... 27 TMP & Project Access Points ........................................................................ 30 Conformance of EMP of School Demolition ................................................... 33 Information Disclosure before the Start of Construction Works ...................... 37 Consultation with Parents of Students & Teachers of Affected schools in ROW
37 Signing of Social Framework Agreements in Maryala and ShahKamir ........... 38 Construction/ Upgradation of Flood Bund at Camp Site during Torrential Rains
& Flood 40 Training conducted by PIC to site supervisors & by site supervisors to field staff
& Labor 41 Details of HSE Trainings Conducted during March to Dec 2020 .................... 42 Water Sampling for Analysis .......................................................................... 46 Detail of Selected Points Ambient Air and Noise Monitoring .......................... 46 Ambient Air Quality (AAQ) Monitoring ............................................................ 47 Water/ Wastewater Sampling Locations ......................................................... 47 Physical Analysis of Drinking / Ground Water Results ................................... 48 Chemical Analysis of Drinking / Ground Water Results .................................. 48 Microbiological Analysis of Drinking / Ground Water Results ......................... 49 Surface Water Quality Analysis ...................................................................... 49 Wastewater Analysis ...................................................................................... 51 Ambient air Quality Level ............................................................................... 53 Noise and Amabient Air Quality Level ............................................................ 53 Physical & Chemical Analysis of Drinking / Ground Water Results - (GRC- Camp
Site) ............................................................................................................... 54 Microbiological Analysis of Drinking / Ground Water Results - (GRC- Camp Site)
55 Surface Water Analysis -(Rasul Barrage Down Stream) ................................ 55
Table 26: Microbiological Surface Water Analysis - (Rasul Barrage Down Stream) . 56 Table 27: Waste Water Analysis Soakage Pit (GRC Camp) ........................... 57 Overall Compliance Status ............................................................................. 89 Details of Project Conformance Level ............................................................ 89 Project Conformance and Non-Conformance Level March-December 2020 .. 90 Trends in Non-Conformances of EMP Compliance ........................................ 90
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
1 | P a g e
List of Abbreviation
AAS Atomic Absorption Spectroscopy
AAQ Ambient Air Quality
ADB Asian Development Bank
APHA American Public Health Association
ASTM American Society for Testing and Materials
BAMP Borrow Area Management Plan
BOD Biological Oxygen Demand
Cft Cubic Feet
CNIC Computerized National Identity Card
CO Carbon Monoxide
CO2 Carbon Dioxide
COD Chemical Oxygen Demand
COVID-19 Corona Virus Disease
DCR Demolition Completion Report
DDR Due Diligence Report
DEMP Demolition Environmental Management Plan
EA Executing Agency
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMR Environmental Monitoring Report
ERP Emergency Response Plan
ERT Emergency Response Team
E&S Environmental & Social
ES Environment Specialist of Project Implementation Consultants
ESMMC Environmental and Social Management and Monitoring Cell
ESU Environmental and Social Unit
FAO Food and Agriculture Organization
FCC Flood Carrier Channel
FCN Flood Carrier Network
GoP Government of Pakistan
GRC Grievance Redress Committee
GRM Grievance Redress Mechanism
GT Road Grant Trunk Road
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
2 | P a g e
HSE Health, Safety and Environment
IA Implementing Agency
ICB International Competitive Bidding
IEC Information Education & Communication
ILO International Labor Organization
JIC Jalalpur Irrigation Canal
JIP Jalalpur Irrigation Project
LARP Land Acquisition and Resettlement Plan
LPG Liquefied Petroleum Gas
M Meter
mm Milli meter
M-2 Lahore- Islamabad Motorway
M&E Monitoring and Evaluation
MSDS Material safety Data Sheets
NDC National Development Consultants
NESPAK National Engineering Services Pakistan
NO2 Nitrogen Dioxide
NOC No Objection Certificate
O3 Ozone
OSHA Occupational Safety and Health Administration
P-1,2,3 Package 1, 2, 3
PAK Pakistan
PDA Project Design Advance
PD Khan Pind Dadan Khan
PEQS Punjab Environmental Quality Standards
PIC Project Implementation Consultants
PID Punjab Irrigation Department
PM10 Particulate Matter10
PM2.5 Particulate Matter2.5
PM Project Manager
PMO Project Management Office
PPE Personal Protective Equipment
R & D Research and Development
RD Reduced Distance
RHC Rural Health Centre
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
3 | P a g e
RoW Right of Way
SAEMR Semi-Annual Environmental Monitoring Report
SFA Social Framework Agreement
SO2 Sulphur Dioxide
SOPs Standard Operating Procedures
SPM Standard Particulate Matter
SPS Safeguard Policy Statement
SSEMP Site Specific Environmental Management Plan
SWMP Solid Waste Management Plan
TDS Total Dissolved Solids
TMA Tehsil Municipal Administration
TMP Traffic Management Plan
TSS Total Suspended Solids
TVOC Total Volatile Organic Compounds
USEPA United States Environmental Protection Agency
WHO World Health Organization
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
4
BRIEF SUMMARY
1. Jalalpur Irrigation Project (JIP) is funded by Asian Development Bank
(ADB), loan No.3599 PAK with the cost of US$ 274.63 Million, for
construction of Main Canal of 379 RDs length, 23 distributaries, 7 minors
and 16 FCCs for Jalalpur Irrigation Project (JIP). The command area of
JIP is in the form of long strip of land bounded by the salt range hills on
Northern side and right bank of the Jhelum River on its Southern side.
2. Punjab Irrigation Department (PID) is the Executing Agency (EA). The
Consultancy of supervision of construction works have been awarded to
M/S NDC as lead firm with the joint venture of Barqaab Consulting
Engineers and other firms on April 9, 2019. This first Semi-Annual
Environmental Monitoring Report (SAEMR) is prepared from the Months
of March 2020 to December 2020 for the construction of the Jalalpur
Irrigation Project (JIP). This report fulfills the requirements to monitor the
effectiveness of ADB SPS 2009, its implementation and process as well
as to ensure sound environmental planning, for the construction of JIP.
The report is based on accumulative figure, data and information of all
monthly reports of reporting period.. Potential environmental impacts are
identified including indirect and cumulative impacts, and their
significance assessed.
3. For the whole project, the civil works contract packages (ICBs) are
divided into three sections as mentioned below:
• JIP/WKS/ICB-P1, RD 0+000 to RD 52+000: Main Canal, 01
Distributary, and 03 Flood Carrier Channels (FCCs).
• JIP/WKS/ICB-P2, RD 52+000 to RD 225+500: Main Canal, 12
Distributaries, 02 Minor Canals and 05 Flood Carrier Channels
(FCCs).
• JIP/WKS/ICB-P3, RD 225+500 to RD 379+750: Main Canal, 10
Distributaries, 05 Minors and 08 Flood Carrier Channels (FCCs)
4. The Construction works started on JIP/WKS/ICB-P1 on 27-02-2020 from
RD 0+000 to RD 5+000 area. During the month of July 2020, the land
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
5
up to RD 33+750 has been included in the construction area after
clearance and possession of land up to RD 52 is under process.
Construction on JIP/WKS/ICB-P2 and JIP/WKS/ICB-P3 is not started
during the reporting period of first SAEMR.
5. Site Specific Environmental Monitoring Plan including borrow area
management plan, traffic management plan, health environment and
safety plan and waste management plan were formulated for JIP, in
accordance with ADB SPS 2009 requirements. All the plans were
formulated under supervision of PIC and close coordination of PMO and
were updated after the COVID-19 pandemic in the country.
6. This report is based on EMP Compliance data collected from March to
Dec-2020. Following areas have been inspected and monitored for
preparation of this SAEMR
RD 25-Contractor Camp,
Rasul Barrage
RD 0+100 Earthwork,
RD 2+500 Syphon,
RD 3+500 Super passage,
RD 4+600 Super passage,
RD0+500-5 Stone works,
RD 25+250 earthwork,
RD 4+625 to RD 6+000, Canal Plaster Work
RD 19+250 Malikpur Village.
Govt. Schools Demolition Sites
New Schools-Construction Sites,
Demolished School buildings Sites,
Transitional Building for Boys Primary School
Govt. Model Primary School
Along Road from RD 00 to 33+750
Labor and Officers Residence, etc.
7. There is an ongoing pandemic of Novel Coronavirus (COVID-19) in
Pakistan which was first notified on 26 February 2020. By 24th March
2020, the construction works at JIP/WKS/ICB-01 were suspended due
to COVID-19 lockdown 2020. Then the construction works were
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
6
resumed following Standard Operating Procedures (SOPs) on 14th April
2020, after the ease in lockdown for construction industry. Meanwhile,
the contractor was coordinated for official COVID-19 safety
management scenario, provision of disinfectors, safety paraphernalia
and training of staff. These arrangements are covered under the existing
EMP cost and no additional cost is involved. The SSEMP and HSE Plans
were also updated in accordance with COVID-19 pandemic in
accordance with that follow the Centers for Disease Control and
Prevention (CDC), OSHA, state/territorial, and local guidelines for
preventing the spread of COVID-19 infection.
8. A project level Grievance Redress Mechanism (GRM) is established to
address grievances arising from environmental and social impacts. The
GRM is prepared in English and Urdu languages and approved by ADB.
The GRM is fully implemented in the Camp areas and construction sites.
The GRM record is being checked on monthly basis.
9. Consultation was continued in project area during the reporting period.
The additional specific objective of consultations was also included
construction of new schools and demolition of old buildings in project
right of way. Two (02 Nos.) Social Framework Agreements (SFA) were
signed in village Malikpur and Shah Kamir.
10. A good working relationship is being maintained among the Contractor
and the Consultants environmental staff and PMO. Trainings are being
arranged by the PIC and Contractor’s Environmentalist on site for the
capacity building of the Contractor and their relevant staff. They are
briefed on updating the environment monitoring checklists and strictly
follow the EMP, which they submit on weekly basis to adhere
Environmental Management and Monitoring activities. They are also
updated and coordinated for current COVID-19 safety management
scenario, provision of disinfectors, safety paraphernalia and training of
staff. The training guidelines for Buildings Department for demolishing of
two Primary Schools coming in the RoW were also prepared and
conveyed. A brochure in Urdu language is also prepared for the
contractor staff for easy understanding of construction related
environmental issues.
11. The environmental monitoring was carried out by PIC to assess actual
nature and extent of key impacts and the effectiveness of mitigation and
enhancement measures outlined in the EMP and SSEMP. Mitigation
measures are considered so that the projects are designed, constructed,
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
7
and operated in compliance with applicable national and provincial laws
and regulations and meets the requirements of ADB SPS (2009). Further
field inspections are undertaken by the Environmentalists of PIC & PMO.
All the observations in the form of monitoring report will be submitted to
PMO on monthly basis.
12. Mutually agreed Corrective Action Plan is also devised and
communicated to the contractors. PIC has advised the contractor to
address non-compliance as per agreed Corrective Action Plan.
13. The overall compliance status of EMP ranges from 80-90% during the
reporting months, EMP Compliance level is being calculated with the
help of quantitative weekly and monthly checklist. The overall
compliance level was found good and statistics indicate the project level
major conformances decreased with passage of time. This slight
decrease in major nonconformances is associated with the completion
and updation of SSEMP documents and their effective implementation.
It is also noted that minor nonconformances of the project increased
minimally in a few months from May 2020 to Aug 2020, which was due
to lack of good practice measures and poor house keeping with the
increase of work sites and labor.
14. Additional field staff was nominated by Contractors and trainings on
housekeeping including waste management and good practice measure
was provided to all labour and staff, which results in decrease in minor
non conformance levels, as well in later months from Sep to Dec 2020.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
8
1 INTRODUCTION AND BACKGROUND
1.1 General
15. This Semi-Annual Environmental Monitoring Report (SAEMR) is
prepared from the Months of March 2020 to December 2020 for the
construction of the Jalalpur Irrigation Project (JIP).
1.2 Background
16. Jalalpur Irrigation Project (JIP) is funded by Asian Development Bank
(ADB), loan No.3599 PAK with the cost of US$ 274.63 Million, for
construction of Main Canal of 379 RDs length, 23 distributaries, 7 minors
and 16 FCCs for Jalalpur Irrigation Project (JIP). The Project is expected
to increase agricultural production with development of sustainable
agriculture to alleviate poverty in Jhelum, Pind Dadan Khan and
Khushab Tehsils of Districts Jhelum and Khushab by providing canal
irrigation supplies during Kharif season and reduce the land degradation
by minimizing the use of marginal quality ground water. Output of the
Project envisages construction of a new irrigation system including a
Main Canal and its system and appurtenant structures to irrigate about
170,000 acres of land in Tehsil Jhelum, Pind Dadan Khan and Khushab
area. It also included the construction of 16 Flood Carrier Channels
(FCCs) network to carry saline flood water of hill torrents (debouching
over the command area) directly to River Jhelum.
17. The command area of JIP is in the form of long strip of land bounded by
the salt range hills on northern side and right bank of the Jhelum River
on its southern side. The Main Canal would off-take from the right bank
of the Rasul Barrage, for which provision for the canal head regulator
already exists. The Main Canal of 1,350 cusecs capacity will be about
116 km long and traverses along the foothills of the Salt Range.
18. Punjab Irrigation Department (PID) is the Executing Agency (EA).
Feasibility study of Jalalpur Irrigation Project was prepared by NESPAK–
ICS Joint Venture Consultants under grant ADB PPTA (8404-PAK) in
2015. Later on, JIP works were divided into three International Contract
Packages (ICBs) and accordingly.
19. The Consultancy of supervision of construction works have been
awarded to M/S NDC as lead firm with the joint venture of Barqaab
Consulting Engineers and other firms on April 9, 2019.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
9
1.3 Project Location
20. The proposed JIP is located between longitude from 72o-20’ to 73o-31’
(East) and latitude from 32o-25' to 32o-43’ (North) along right bank of
River Jhelum from Rasul Barrage in Punjab, Pakistan. The area falls in
Tehsil Jhelum and Tehsil Pind Dadan Khan (PD Khan) of District Jhelum
and Tehsil Khushab of District Khushab. The project area can be
accessed through Lahore-Islamabad Motorway (M-2) by taking exit from
Lillah Interchange. Alternatively, the area may be reached via GT Road
from Jhelum to Rasul Barrage. (see Exhibits 1, 2 & 3)
Location of the Project
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Project Foot Prints
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Project Layout Plan
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 12
1.4 Project Objectives
21. The main objective of this project is to supply irrigation water to an area of
about 170, 000 acres of land sandwiched between Salt Range Hills and
Jhelum River extending from Rasul Barrage to close vicinity of Khushab
Town. Most of the area has unusable to marginally usable ground water.
However, in areas close to river bank, sweet ground water is available and
tube wells are being currently used for irrigation.
22. This basic objective will also contribute to poverty alleviation and
economic growth in the area with other related objectives of overall
growth, while adding to crop produce of the country with resultant benefits.
23. An irrigation canal not only provides irrigation supplies, but also becomes
a source for drinking water where subsurface water is brackish and people
have, as a routine, to walk kilometers at an end to fetch drinking water.
1.5 Project Features
24. Main Canal with design discharge of 1350 cusecs will take-off from right
flank of Rasul Barrage. Distribution System extended upto right bank of
Jhelum River has an estimated length of about 144 Canal miles (219 km)
comprises: twenty three (23) distributaries and seven (7) minors. 544
structures of various types are proposed to be constructed across Main
Canal and distribution system alongwith around 489 irrigation outlets.
Except the head reach upto 84+000, Main Canal and all distributaries and
minors are designed as unlined channels.
25. Head regulator of Main Canal will be constructed at Rasul Barrage by
dismantling a part of right upstream wing wall at the location of expansion
joints.
26. Two escape structures have been proposed at RD 38+750 feet and RD
222+200 feet of Main Canal to serve as relief outlets in case of head.
27. As a number of hill torrents (59) cross the Main Canal, proper cross-
drainage structures such as siphons, aqueducts, depressed culverts,
culverts and super passages were proposed. Design review is in
progress.
1.6 Description of Civil Works Area
28. For the whole project, the civil works contract packages (ICBs) are divided
into three sections as mentioned below:
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 13
• JIP/WKS/ICB-P1, RD 0+000 to RD 52+000: Main Canal, 01
Distributary, and 03 Flood Carrier Channels (FCCs).
• JIP/WKS/ICB-P2, RD 52+000 to RD 225+500: Main Canal, 12
Distributaries, 02 Minor Canals and 05 Flood Carrier Channels
(FCCs).
• JIP/WKS/ICB-P3, RD 225+500 to RD 379+750: Main Canal, 10
Distributaries, 05 Minors and 08 Flood Carrier Channels (FCCs).
29. The Package wise land distribution to be acquired is detailed below in
Exhibit 4:
Distribution of Land being Acquired for Jalalpur Irrigation Project
S.No Tehsil-Channel name ICB-P1 ICB-P2 ICB-P3 Total
1 Tehsil Jhelum Main Canal up to
RD 33+750
228 - - 228
2 Tehsil PD Khan - FCCs (1-3) 65 - - 65
3 Tehsil PD Khan- Canal & Distys 168 1646 932 2746
4 Tehsil PD Khan-FCCs- (4-13) - 2345 1413 3758
5 Tehsil PD Khan- Canal & Distys &
FCCs
- - 1377 1377
6 Tehsil PD Khan- FCC Addendum
of 368 acres
- 313 55 368
7 Tehsil PD Khan-PID staff colony - 16 - 16
Total land 461 4320 3777 8558
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 14
2 DESIGN LEVEL DETAILS OF CONSTRUCTION ACTIVITIES OF
ICB-P1, P2 & P3
30. The scope of works under ICB-P1, P2 & P3 includes the following civil
works of Main Canal of 116 km length, 23 numbers of distribution system,
07 minors and 16 Flood Carrier Channels (FCCs). Apart from these,
following package wise civil works included structures will be constructed
shown in each ICB- Packages.
List of Proposed Structures of Jalalpur Irrigation Project under ICB-P1
Sr. No
Description Main Canal
Disty-1 FCCs Total
1 Intake structure at Rasul Barrage 1 - - 1
2 Distributary/Minor Head Regulator 1 - - 1
3 Vertical Fall Structure - 2 - 2
4 Canal Syphon cum Escape Structure
1 - - 1
5 Mouza Road / Arterial Bridges 5 3 2 10
6 Cross Drainage Structure 27 - - 27
7 Transition - 2 - 2
8 Cattle Ghats - 1 - 1
9 Outlets 5 14 - 19
10 Tail Cluster - 1 - 1
11 FCN (Flood Carrier Network) Outfalls
- - 3 3
Total 40 23 5 68
List of Proposed Structures of Jalalpur Irrigation Project under ICB-P2
Sr. No.
Description Main Canal
Distributaries / Minors
Flood Carrier
Network
Total
1 Distributary Head Regulator 7 - - 7
2 Cross Regulator cum Head Regulator
5 2 - 7
3 Road Bridges
Mouza Road Bridge 11 44 40 95
District Road Bridge 2 9 6 17
Arterial Road Bridge 1 2 4 7
4 Cross Drainage Structures
Depressed Culvert cum Escape
1 - - 1
Canal Syphon - 4 - 4
Depressed Culvert (Type-I)
7 - - 7
Depressed Culvert (Type-II)
17 - - 17
Super Passage 5 - - 5
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 15
Drainage Culvert 2 - - 2
Drainage Pipe Culvert 7 - - 7
5 Watercourse Outlets 22 140 - 162
6 Water Supply Outlets 7 - - 7
7 Tail Clusters - 14 - 14
8 Fall Structures - 55 - 55
9 Cattle Ghats 10 10 - 20
10 Transitions 2 15 - 17
11 Flood Carrier Network’s Outfalls - - 4 4
TOTAL 106 295 54 455
List of Proposed Structures of Jalalpur Irrigation Project under ICB-P3
S. No.
Description Main Canal
Distributaries/
Minors
Flood Carrier
Network
Total
1 Distributary/Minor Head Regulator
9 4 13
2 Vertical Fall Structure 93 93
3 Glacis Fall Structure 17 17
4 Canal Syphon at RD 263+950/ Motorway Crossing
1 1
Canal Syphon under 1 1
5 Bridges Mouza Road Bridges
14 17 35 66
District Road Bridges
2 1 4 7
Arterial Road Bridges
3 2 5
6 Cross Drainage Structures
Depressed Drainage Culvert
8 5 13
Super Passage 1 1
Drainage Culvert 1 1
7 Cattle Ghats 12 11 23
8 Outlets 28 213 241
9 Tail Cluster 15 15
10 FCN Outfalls 9 9
Total 79 377 50 506
2.1 Project Implementation and Packaging
31. For project implementation, three contract packages as shown in Table 2-
2 have been proposed. Bids for the 1st Contract JIP/WKS/ICB-P1 were
received on 22/11/2018 for the 2nd Contract JIP/WKS/ICB-P2 were
received on May 07, 2019 and for the 3rd Contract JIP/WKS/ICB-P3 were
received on October 22, 2019.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 16
Table 2-1 Project Implementation and Packaging Detail Contract
Package
Number
General Description Estimated
Value (US
$ Million)
Procurement
Method
Type of
Bidding
Documents
JIP/WKS/ICB-
P1)
Civil and Mechanical
Works of Intake, Main
Canal, Irrigation and
Drainage System up to
16 km (RD 0 to 52+500
feet)
52 ICB ADB bidding
documents for
large works
JIP/WKS/ICB-
P2
Civil and Mechanical
Works of Main Canal,
Irrigation and Drainage
System from 16 km to
69 km (RD 52+500 to
226+320 feet)
69 ICB ADB bidding
documents for
large works
JIP/WKS/ICB-
P3
Civil and Mechanical
Works of Main Canal,
Irrigation and Drainage
System from 69 km to
116 km (RD 226+320 to
380+480 feet)
55 ICB ADB bidding
documents for
large works
2.2 Punjab Agriculture Department Purview
32. The establishment of Jalalpur irrigation distribution system (Project output
1) is the responsibility of Punjab Irrigation Department (PID) whereas
improvement of water-use capacity in the project area (Project Output 2)
and Improvement in the Farm management capacity in the project area
(Project Output 3) are the responsibility of the Punjab Agriculture
Department (PAD). For working on Outputs 2&3, the PAD is required to
coordinate with PID for achieving the objectives.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 17
3 PROJECT ORGANIZATION AND ENVIRONMENTAL
MANAGEMENT TEAM
33. The Implementing Agency i-e PID formulated an Environmental & Social
Management and Monitoring cell (ESMMC), comprising on following
members.
I. ESMMC Representative nominated by EA (PID)
II. 3rd Party Monitoring and Evaluation (M & E)
III. SC’s Environmentalists
IV. Contractor’s Environmentalist & HSE Staff
34. In order to ensure compliance with ADB Safeguard Policy Statement (SPS
2009), the Implementing Agency (IA) is responsible to ensure the
implementation of the environmental management and monitoring
requirements and procedures for PID.
35. The Project Management Organization (PMO) Irrigation Department is the
Implementing Agency (IA) for PID and it has an Environmental and Social
Unit (ESU). The Environmental Officers from PMO are responsible for the
subproject’s review based on the selection criteria, preparation,
submission, implementation, and environmental management &
monitoring and evaluation.
36. Implementing Agency has engaged Project Implementation Consultants
(PIC) team to strengthen their procurement capacity, support and help
monitor design and construction supervision services, and support the
preparation, implementation, monitoring and compliance of environmental
safeguard action plans.
37. The contractor is responsible for execution of construction activities and
for environmental protection through their environmental and HSE field
staff. The contractor is subject to environmental protection liabilities under
national environmental laws, ADB’s Environmental Safeguards, project
EIA/EMP provisions and under their contract with PID.
Organizational Setup of the ESMMC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 18
3.1 Progress of Construction Works
38. The Construction works started on JIP/WKS/ICB-P1 on 27-02-2020 from
RD 0+000 to RD 5+000 area. During the month of July 2020, the land up
to RD 33+750 has been included in the construction area after clearance
and possession of land up to RD 52 is under process. Construction on
JIP/WKS/ICB-P2 and JIP/WKS/ICB-P3 is not started during the reporting
period of first SAEMR. However, proposes labor camp layout was
received from P3 Contractors, during the month of January, 2021. The
construction area is shown in Exhibit 10 below.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
The Construction Area
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 20
3.2 Reporting Period of the Project
39. The reporting period of the first SAEMR is March to December 2020. This
report fulfills the requirements to monitor the effectiveness of ADB SPS
2009, its implementation and process as well as to ensure sound
environmental planning, for the construction of JIP. The report is based
on accumulative figure, data and information of all monthly reports from
March to December 2020. Potential environmental impacts are identified
including indirect and cumulative impacts, and their significance
assessed.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 21
4 ENVIRONMENTAL MANAGEMENT
4.1 General
40. The Environmental Management Plan (EMP) is an integral part of the
project’s bidding documents and is broadly being followed by the
contractor, while Environmentalist of the contractor`s staff is regularly and
strictly monitoring the overall compliance related to environmental and
safety issues.
41. The overall Environmental and Social Performance is observed
good/satisfactory, while efforts for continuous improvements are being
carried out.
4.2 Site Specific Environmental Management Plan (SSEMP)
42. A Site-Specific Environmental Management Plan (SSEMP) minimizes
negative impacts of construction activities on local communities and the
natural environment, to reduce the induced impacts of construction
activities; to prevent pollution and ensure that construction activities are
planned & there will be no risk to the environment.
43. The SSEMP of the first Package (ICB-I) of JIP has been prepared by the
contractor and reviewed by the Project Implementation Consultant and
approved from the PMO Canals, PID and ADB. SSEMP provides an
approach for managing and monitoring environment and social related
issues and provides a mechanism to address the adverse environmental
impacts of a project during its construction, to accelerate project benefits
and describes the institutional framework and resource allocations
proposed by the PID to implement the SSEMP.
4.3 Camp Management
44. The camp site is located at RD 25 L/S of proposed canal alignment. The camp
is constructed in accordance with Clause 7.12 of EMP, far away from the local
community/settlement to minimize adverse social impacts. The total area of the
leased land is 10 Acres. The Contractor’s camp is temporarily built, will be
restored to its original condition after completion of project and the mosque will
be maintained. Topsoil of agricultural fields is preserved and will stockpiled for
later use depend on the rehabilitation requirement. Topsoil stripping is necessary
wherever land is planned to be disturbed to recover the soil resource for
rehabilitation purposes.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 22
45. The ESMMC, during construction phase is monitoring the camp site
management measure in accordance with EMP, SSEMP and best practices to
monitor/manage potentially adverse impacts on natural environment and
interactions with local communities. These are described in detail in the exhibit
below. All these parameters are being monitored in daily, weekly and monthly
monitoring checklists on the basis of which compliance/noncompliance status is
calculated in each monthly EMR.
Camp Site Management
Issue Management Measures
Construction
Camp Facilities
• Adequate housing for all workers is provided.
• Safe and reliable water supply, which meet NEQS.
• Hygienic sanitary facilities and sewerage system. The toilets and domestic waste water collected through a common sewerage. Separate latrines and bathing places are provided with total isolation by location. (The minimum number of toilet facilities required is one toilet for every ten persons).
• Treatment facilities for sewerage of toilet and domestic wastes are constructed.
• Storm water drainage facilities.
• Paved internal roads.
• Provision of in-house community/common entertainment facilities.
• Kitchens, Mess, Tuck-shop, heating and cooling facilitates are provided.
• Generator Rooms and Workshops are constructed to cater noise, disturbance and spillage issues as per EMP requirements.
• Batching plant is constructed and operated as per SSEMP provisions and risk assessment.
• Dependence of local entertainment outlets by the construction camps to be discouraged/prohibited to the extent possible.
• Disinfecting gates and sanitizing facilities on entrance of the camp are constructed for COVID-19 management details are under Section 4.5.
• Tree plantation and landscaping on empty areas and along the walkways.
• Ambient air and Noise monitoring is being conducted in camp on regular basis as per EMP. (see section-5)
Camp Management
• Camp is managed in accordance with EMP guidelines considering minimum 500 m distance with local settlements in a manner to minimize potential direct and
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 23
and Community Interactions
indirect adverse effects to environment and community, infrastructure and public/private services.
• Interactions with local communities is facilitated through Contractor and ESMMC Community Liaison staff, through which, to the extent practicable, contractor is encouraged to promote positive interactions between employees and local residents.
• Social Framework Agreements are in place. (see section 4.10)
• Grievance Redress/ Complaint Register is placed in Camp Section (see Section 4.8)
Disruption of the natural Environment
• Contractor take all reasonable measures to limit disruption of the natural environment. This includes but is not limited to:
– Creating new vehicle tracks, damages to banks, damage of vegetation, cutting of trees for firewood, activities which would accelerate or otherwise damage the landscape, outside of the direct project impact area
– Prevention uncontrolled fires including instruction as to basic fire prevention methods including proper disposal of cigarette butts, method to thoroughly extinguish open camp fires, etc.
Harassment of Animals and Birds
• Harassment of animals and birds, is not be permitted including chasing animals with cars, snowmobiles, on foot, etc., or otherwise deliberately frightening them with sudden noises and lights.
• Other domestic livestock are not be approached or otherwise disturbed without the permission of the owner, or in the event that there is an immediate threat to the safety of the animal.
Fishing, Gathering and Hunting of Natural Resources
• Implementation of the No fishing, Gathering and Hunting Policy* in rural communities and/or as designated by ESMMC on the basis of community consultation efforts.
• No collection of other natural resources (e.g., plant/animal specimens, geological samples, etc.) unless specifically needed and authorized as part of Project studies and monitoring activities.
*Note: This policy does not apply to situations where there is risk to personal health and safety and/or in survival situation.
Public Behavior • Many Contractor employees are guests of the project area and expected to maintain a high degree of public courtesy and respect.
• Displays of public intoxication and/or otherwise rude behavior, threat of violence, and or displays of public violence is not be tolerated and repeated offences will be grounds for dismissal.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 24
Health and
Hygiene
• Adequate health care facilities within construction sites are available. (see Section 4.4)
• Contractor Provides first aid facility round the clock.
• Maintain stock of medicines in the facility and appoint fulltime designated health services provider.
• A fully equipped Ambulance facility for the laborers during emergency to be transported to nearest hospitals is not available, however a separate vehicle is nominated for this purpose.
• Initial health and body temperature screening of the laborers coming from outside areas is being conducted.
• Trainings of all construction workers in basic sanitation and health care issues and safety matters, and on the specific hazards of their work.
• Adequate drainage facilities and regular mosquito repellant sprays during rainy season in offices and construction camps and yards.
• Display boards at strategic locations within the camps containing messages on best hygienic practices are placed.
Safety • Security guards and enclosures to prevent unauthorized entry in to the camp area are available.
• A register is maintained to keep a track on a head count of persons present in the camp at any given time.
• Proper sign boards and adequate firefighting equipment are available in camp & office areas.
Fuel supplies for cooking
• Contractor provides available fuels like natural gas or kerosene to prevent them using biomass for cooking.
Waste
Management
• Waste segregation by source is being done; organic wastes in one container and inorganic wastes in another container (see Section 4.13)Visual inspection on spoil disposal in accordance with SSEMP Sub plan on Waste Management is continued.
• Noise, ambient air, and wastewater/water quality monitoring is being conducted on quarterly basis by an EPA certified Lab (see Chapter 5).
Demobilization • Stockpiling, Stabilization, e-g. re-vegetation/compaction of disturbed areas, should be undertaken on demobilization of the field camp to avoid its footprint will not leave disturbed areas of land which generate dust that affects local people and/or crops and construction
• Sanitation facilities should be decommissioned and sealed, e-g. landfills, sewage treatment, etc.
• The demobilization will be in accordance with SSEMP and agreement with land owners.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 25
4.4 Health and Safety Plan
46. Contractor submitted comprehensive Health, Safety and Environment
(HSE) Plan on provided format. The draft HSE plan submitted by the
Contractor is updated and approved. A comprehensive HSE report on
COVID-19 Management of JIP was also prepared.
47. The main objective of HSE plan is to strictly enforce the provisions and
mitigation measures for potential impacts throughout the entire
construction period. Other objectives are:
• Preventing accidents, diseases and harmful impacts on the health of
workers arising from employment in construction areas.
• Providing means of analyzing from the point of view of safety, health
and working conditions, construction processes, activities,
technologies and operations, and of taking appropriate measures of
planning, control and enforcement.
• Implement training programs that support the achievement of the
personnel competency in relation to health, safety and environment.
4.5 COVID-19 Management at JIP
48. There is an ongoing pandemic of Novel Coronavirus (COVID-19) in
Pakistan which was first notified on 26 February 2020. As of 14 April 2020,
over 5,719 cases with 96 deaths (CFR 1.68%) had been reported. The
pandemic has spread to all provinces in Pakistan with over 115 districts
affected, largely in Punjab and Sindh. ERT will thoroughly review and
adopt preparedness plan in light of the COVID-19 Pakistan Preparedness
and Response Plan (PPRP) (available at
https://reliefweb.int/report/pakistan/pakistan-preparedness-response-
plan-covid-19).
49. By 24th March 2020, the construction works at JIP/WKS/ICB-01 were
suspended due to COVID-19 lockdown 2020. Then the construction works
were resumed following Standard Operating Procedures (SOPs) on 14th
April 2020, after the ease in lockdown for construction industry.
Meanwhile, the contractor was coordinated for official COVID-19 safety
management scenario, provision of disinfectors, safety paraphernalia and
training of staff. These arrangements are covered under the existing EMP
cost and no additional cost is involved. The SSEMP and HSE Plans were
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 26
also updated in accordance with COVID-19 pandemic in accordance with
that follow the Centers for Disease Control and Prevention (CDC), OSHA,
state/territorial, and local guidelines for preventing the spread of COVID-
19 infection. SOPs for workplaces and offices to prevent COVID-19
Spread (Notified by Primary & Secondary Healthcare Department Govt of
the Punjab on 23rd June 2020, available at
https://pshealthpunjab.gov.pk/Home/Covid19SopsGuidelines).
50. During July & August, before and after Eid-ul-Azha Holidays, the
Employees Screening Record was maintained, in accordance with
SSEMP and HSE Plan. The screening record comprised of employees
thermo-screening and disinfection, mode of transportation and screening
performa signed by each employee and Environment/Health officer.
Moreover, a refreshing training on Social Distancing and COVID-19 SOPs
to all employees was provided before their departure to their hometowns
and arrival to worksite.
51. Regular Disinfection and screening are being conducted at all work sites,
camp and offices; a temporary isolation room was provided for suspected
cases of COVID-19 before sending to proper medical facility. However,
fortunately and with strict implementation of COVID-19 SOPs, no case
was reported at site or any work area till date. The extracts of COVID-19
precautionary measures, Risk Assessment, and Guidance to Staff, etc.
from SSEMP and HSE plan are being annexed as Annex-1, 2 & 3. A few
photographs regarding the implementation status of COVID-19 SOPs are
also attached as Annex-4, hereunder.
52. The implementation status of COVID-19 SOPs and their monitoring are
also being recorded in monthly HSE progress reports and Environmental
monitoring reports by Contractor and PIC, respectively.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 27
COVID-19 Management at Project Site
4.6 Borrow Area Management Plan
53. For the construction of canal embankment as per contract provisions,
material will be borrowed from the following sources at different locations
and these are defined as Borrow Areas.
• Canal Excavations
• Stockpiles of excavated materials
• Structural excavations
• Private lands if required
54. A Comprehensive Borrow Area Management and Disposal Plan (BAMDP)
for the identification, development and maintenance of borrow areas is
prepared to ensure the implementation of Environmental Management
Plan (EMP) guidelines. The scope of this plan is to provide guidelines and
outline strategies for the management of borrow area across the project.
The plan will be continually updated to incorporate successful construction
procedures in accordance with each new borrow area identified during the
construction of the project. The scope of the plan not only covers borrow
area development including its identification and operation, but also
includes the material borrowing process considering the aesthetic values
of the local areas and safety of local flora and fauna abiding by laws.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 28
55. For the execution of canal earthwork, material is borrowed from natural
elevation within ROW (Right of Way) of canal. Private land is acquired for
excavation of earthen material where canal cutting / Excavation is not
available. At RD 3 & 22 of JIP private natural elevation /earthen hills
acquired for borrow area. Written consent obtained from land owner
before excavation of earthen material. Total quantity of earthen material
Excavation, in irrigation channel is 89,05,000 Cft, whereas, quantity of
earthen material excavated from Borrow Pit is 1,15,70,000 Cft
4.7 Flagmen were deputed at entrance and exit point of borrow area to control
roadside and company traffic. Water sprinkling is carried out within ROW
and at haulage routes to minimize dust pollution. Top un consolidated soil
on ramps and haulage routes removed by grader to minimize dust. Traffic
Management Plan
56. Pursuant to the Environmental Management Plan (EMP) and Site-Specific
Environmental Management Plan (SSEMP) for Package 1 (P1), Traffic
Management Plan (TMP) is prepared to ensure effective implementation
and continued improvement in traffic flow. TMP will provide guidelines and
set the criteria for safe plying of traffic during the execution of construction
works and partial /full closure of road for safety of transporters, road users,
assets and general public, for which the Contractor is committed to deliver
the following:
➢ To ensure that vehicular movement will not cause any adverse
impacts.
➢ To ensure that vehicular movement will not result into disturbances for
the local community residing in the vicinity of the project as far as
possible.
➢ To ensure the site activities as per guidelines of TMP and all regulatory
requirements.
57. The Jalalpur canal off takes from right flank of Rasul Barrage. There is a
single carriage way at Rasul Barrage for public transport. For the
execution of civil works of canal headwork, the main road i-e P.D Khan to
Mandi Bahauddin road will be dismantled to undertake construction works
and remain closed until the completion of canal Head Regulator.
58. Analysis of traffic counts from the Rasul Barrage has revealed that Light
Transport Vehicles (LTV) i.e, cars and vans and Heavy Transport Vehicles
(HTV) i-e truck and trailer etc, use the bridge for river crossing and the
vehicular count over Rasul barrage is approximately 300 vehicles/day. For
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC 29
the execution of civil works and safe and smooth flow of traffic, alternate
diversion route has been constructed at the R/S of P.D Khan to Mandi
Bahauddin road. This temporary diversion route ultimately connects the
P.D Khan Road to existing Rasul Barrage. The salient features of this
temporary diversion route are given as.
➢ This temporary diversion route is constructed for LTV and HTV traffic.
➢ The traffic flow is approximately 300 Vehicles.
➢ Length of temporary diversion route is 635 RFT.
➢ Total width of existing road is 24 ft.
➢ Total width of temporary diversion route is 36 ft.
➢ Top level of diversion route will be provided with one ft compacted sub-
base material.
➢ Barrier will be fixed on both sides of diversion road.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
TMP & Project Access Points
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
31
4.8 Grievance Redress Mechanism (GRM Urdu & English)
59. A project level Grievance Redress Mechanism (GRM) is established to
address grievances arising from environmental and social impacts. The
GRM is prepared in English and Urdu languages and approved by ADB.
The GRM is fully implemented in the Camp areas and construction sites,
complaint offices have been established at Camp Site and Khewra Office
and complaints will be resolved and grievance record will be established
in accordance with the GRM. The GRM record is being checked on
monthly basis. Summary of total complaints is shown in exhibit below.
On the basis of complaints received internally, externally and noted
during the monitoring a detailed Corrected Action Plan (CAP) is being
prepared narrating the total complaints, nature of complaint, corrective
action/mitigation, required time-line and compliance status. Details are
given in Section 5.4 of this SAEMR. There is no open
complain/unresolved issue regarding project’s environmental
management till date. A few pages from GRM register are also attached
as sample at the end of this report as Annex-A
Summary of Complaints Received March-December 2020
Month No of Complaints/Issues
Rectified within
Timeline
Rectified after
Timeline
Non-Rectified
March 6 6 0 0
April 8 8 0 0
May 7 6 1 0
June 7 6 0 0
July 6 4 2 0
August 7 7 0 0
September 6 6 0 0
October 8 7 1 0
November 6 5 1 0
December 4 3 1 0
Total 41 37 6 0
4.9 Due Diligence of Project Affected Schools
60. The Environment Due Diligence Report is prepared for 2 Nos.
Government Schools Demolishing. The 2 Nos. existing schools in the
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
32
RoW 10+800 & 20+250 of the main canal will require demolishing for the
construction of the project. The DDR is approved by ADB and
communicated to Buildings Department, District Jhelum for effective
implementation. The Demolition Environmental Management Plan
(DEMP) will be compiled and implemented by the demolition contractor
of Buildings Department, before demolition activity. A Site-Specific
Environmental Management Plan is established for the Demolition
Contractors of the Buildings Department, Jhelum. This SSEMP is also
reviewed by PMO canals and further submitted to ADB. Moreover, a
training guide for the contractors for effective implementation of SSEMP
and DDR was also established and provided to the concerned
Contractors.
61. During the demolition process, both of the schools were demolished to
clear the RoW keeping in view not to disturb the community and to
maintain minimum disturbance level with applying health & safety rules.
Both schools were small single-storey buildings, consisting five and two
rooms, respectively. Demolition was carried out manually using
hammers, spade, shovel, trowel, chisel, hoes, saw, wheel, barrel, etc.
The workforce required for the demolition of Girls Model School was 5-7
persons, while 7-9 persons on the average, required for the demolition
of Boys School. Demolishing period of both schools was approx. 10
days.
62. The Govt. Girls Model School building comprising two rooms and
bathroom was additional building to the main Girls School building
situated at a distance of 300m. However, the new Girls school building
constructed adjacent to the main building as a separate block. The
demolition of Girls school was completed on 20th of September 2020.
The demolition was conducted manually, the total manpower deployed
ranges from 5-7 persons daily.
63. The demolition of Boys school was done in two phases from approx. 20th
to 25th of September 2020 and then from approx. 8th to 16th October
2020. The demolition was done manually and the total manpower
deployed ranges from 7-9 persons daily. The construction and
demolition contractors are same i-e., M/s Arshad Builders, who did not
establish a separate labor camp and two rooms of Boys school were
being used as temporary office and accommodation by the demolition
contractor
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
33
64. Site inspections were conducted by environmental teams of PIC and
PMO Canals, Buildings Department, Jhelum and Demolition Contractors
during the Planning, Clearing, implementation and final stages of the
projects, in accordance with the Due Diligence and SSEMP
requirements. The final inspection of the work was completed on
October 16, 2020. The Demolition Contractors had addressed the punch
list items from the pre-final inspections. No other unresolved issues or
work items remained at the time of the final inspection, except
transportation of bricks from demolished waste, which was being carried
out by the contractor to accomplish the works.
65. The demolition monitoring checklists prepared during the Due Diligence
stage were filled and results/ observations are discussed in Demolition
Completion Report (DCR), which is already submitted to PMO for further
submission in ADB.
66. The demolition process was regularly checked and monitored by Project
Implementation Consultants (PIC) and PMO Canals. The approved daily
checklists were filled regularly. Abstract of daily monitoring at both the
demolition sites is provided hereunder:
Conformance of EMP of School Demolition
Environmental
/Social
Concerns
Implementation of
Mitigation Measures
Girls School Boys School
Yes No Some
-
times
Ye
s
No Som
etime
s
Effects on rural
communities
and means of
livelihood
If there is any damage to
the Shrine? (Boys school)
If there is any impact on the
means of livelihood of the
community?
To watch
community
Safeguards
Involvement of V-GRC to
oversee all social
safeguards
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
34
Environmental
/Social
Concerns
Implementation of
Mitigation Measures
Girls School Boys School
Yes No Some
-
times
Ye
s
No Som
etime
s
Inform the
locals about the
time //day of
demolishing
The neighboring
households are well
informed about the
demolishing of schools.
Dust and noise
generate
The neighboring
households are well
informed to be cautioned.
Social
Safeguards of
minors/children
The parents are informed to
stop their minors to go to
the site
Encroachment
Historical/
Cultural/
Archeological
sites
If there is any damage to
the Archeological
/Religious/Cultural or
Historical sites?
Impact on
Vegetation
If demolition activities
involve removal of
vegetation cover?
If any trees cutting is
required?
Surface and
Ground water
contamination/
Drainage
If any surface water or
ground water contamination
reported due to oil spillages,
solid waste dumping or
asphalt laying?
If fuel/Oil storage areas are
far away from
watercourses?
Impact on
adjacent
Communities
If project site is fenced to
prevent trespassing?
Community consultation
has been carried out for
project activities/concerns?
If project activities are
displayed at proper
locations?
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
35
Environmental
/Social
Concerns
Implementation of
Mitigation Measures
Girls School Boys School
Yes No Some
-
times
Ye
s
No Som
etime
s
If safety signs are properly
placed?
If any complaint registered
in the Grievance Log:
Dust generation If there is any record of dust
generation during the
demolition
If proper sprinkling is done?
Safety impacts
due to building
demolition
If safety signs are properly
displayed?
If construction machinery is
parked at designated
areas?
If any complaints registered
regarding traffic issues?
Noise and
Vibration
If any complaints due to
noise and vibration?
67. Buildings Department assured to complete construction work before the
demolition of Schools. As schools were already closed due to COVID-
19 pandemic period during construction phase of affected schools.
Initially, it was anticipated that, no separate, rented building was required
during the transition period, however, it was assured by the Deputy
Commissioner Jhelum that interim arrangements for academic purpose
in a rented building would be arranged, if the construction delays.
68. The educational institutions in Punjab were closed in March, 2020 to
curb the spread of COVID-19. However, the government decided to
reopen primary institutes from September 30, 2020 after a steady
decline was recorded in virus infected cases all over the country. The
demolition was already started during the closure of Schools due to
COVID-19 and alternate arrangements were made for students after
reopening of schools, as the construction of new buildings is supposed
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
36
to be completed by 15th of November 20201. Meanwhile, students of
Girls School will use main school building (as only two separately
constructed rooms of Girls School were demolished and new building is
being constructed adjacent to the main building). For the Boys School, a
local person Mr. Haji Shabbir, Mauza Maryala, Tehsil Jhelum, provided
a private building comprised 4 rooms free of rent situated near by the
existing new school.
4.10 Public Consultation & Social Framework Agreement (SFA)
69. Public consultation started at the project design and feasibility studies is
continued during the construction stage. Along with the stakeholder
consultations and departmental and GRC level, there is a continuous
disclosure of information regarding the construction impacts and their
mitigation on community, engaging general public and stakeholders at
all levels.
70. Consultation was continued in project area during the reporting period.
The additional specific objective of consultations was also included
construction of new schools and demolition of old buildings in project
right of way. Two (02 Nos.) Social Framework Agreements (SFA) were
signed in village Malikpur and Shah Kamir. The signed SFAs are
attached as Annex-A
71. The Social Framework Agreement (SFA) is an agreement developed for
better understanding of Project sitting, equality of opportunity, social
programs, local residents’ rights including social, mobility and other
rights, including following other objectives:
• Better relationship between Project Contractor and locals through
the Framework Agreement and continued consultations.
• Minimizes duplication of effort and time taken within the project area
• A clear, straightforward mechanism for engaging Consultants,
Contractor and locals
• Early Consultant engagement facilitating rapid project start up and
continuity
1 Communicated by Education & Building Departments, Jhelum
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
37
• More timely and efficient progress
• Reduced overall construction impacts from improved relationships
• Greater sharing of Stakeholders/Consultant intelligence
• The established Framework is fully compliant with the Project GRM
• The Framework will be managed and monitored by PIC and PMO
Canals
Information Disclosure before the Start of Construction Works
Consultation with Parents of Students & Teachers of Affected schools in ROW
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
38
Signing of Social Framework Agreements in Maryala and ShahKamir
4.11 Urdu Brochure for Contractor’s Staff
72. A brochure in Urdu language is prepared for the contractor staff for easy
understanding of construction related environmental issues. The
brochure is attached at the end of this report. This brochure helps
improve the contractor’s understanding of the E&S requirements for the
project and provide an overall framework of the Client’s expectations on
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
39
Environmental matters. The Brochure is also attached at the end of this
report
4.12 Emergency Preparedness & Response
73. Emergency Response Team (ERT) is formatted at camp site, led by the
Camp Manager and HSE officer. The Emergency Response Plan (ERP)
is prepared as a part of SSEMP, corresponding response procedures
and mechanism, which will ensure emergency preparedness and
provide means for mitigating the consequences of emergencies,
including very low probability events, in order to protect the health and
safety of the general public and working personnel. The ERP is
developed to address following list of the hazards and emergency
situations, which need planning and proper handling to minimize their
risks:
• Fire
• Road Traffic Accidents
• COVID-19 Pandemic
• Materials/ effluents spills i.e. chemical, POL, etc.,
• Natural disasters i.e. torrential rains, floods, earthquakes,
• Occupational accidents
• Terrorist attacks, etc.
74. During the COVID-19 pandemic, the ERP were also updated in
accordance with that follow the Centers for Disease Control and
Prevention (CDC), OSHA, state/territorial, and local guidelines for
preventing the spread of COVID-19 infection. SOPs for workplaces and
offices to prevent COVID-19 Spread (Notified by Primary & Secondary
Healthcare Department Govt of the Punjab on 23rd June 2020, available
at https://pshealthpunjab.gov.pk/Home/Covid19SopsGuidelines). The
contractor was coordinated for official COVID-19 safety management
scenario, provision of disinfectors, safety paraphernalia and training of
staff. Regular Disinfection and screening are being conducted at all work
sites, camp and offices; a temporary isolation room was provided for
suspected cases of COVID-19 before sending to proper medical facility.
However, fortunately and with strict implementation of COVID-19 SOPs,
no case was reported at site or any work area till date.
75. Emergency Response Team (ERT) was high alert during the heavy
rainfall of August-2020. Emergency response training were conducted.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
40
Raising and rehabilitation of flood protection bund, for the camp was
done before the heavy rain as per flood forecast, following the plan. The
project manager was in close coordination with Rasul Barrage
management, who are taking flood data and forecast on hourly basis
from Mangla Dam.
76. During the torrential rains and flood forecast, Project and HSE mangers
were alerted and flood workers were trained to mobilize the equipment
and workforce to safe places prior to the impact. The concerned HSE
Officer/ Environmentalist has been visiting and inspecting all the
worksites, plants, machines, workshop, laboratories, working platforms,
safety equipment, etc., on regular basis, record and notify findings to the
concerned Project Manager/ person in-charge. Safety drills were
conducted. However, no damage and emergency evacuation occurred
during the month of August, where 147,000 cusecs flood passed through
the River, while all the vehicles and machinery were placed at safe place,
according to the plan.
Construction/ Upgradation of Flood Bund at Camp Site during Torrential Rains & Flood
77. ERT is active and organized for precautionary arrangement for dengue,
focusing their checks at areas, where there could be potential breeding
habitats. ERT is also provides advice on steps to prevent mosquito
breeding to labor and other staff.
4.13 Waste Management
78. Waste Management Plan has been prepared and implemented.
I. Segregation at Site
II. Transportation of Solid Waste as per SOPs
III. Agreement for Medical waste disposal with RHC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
41
IV. Construction & Operation of Septic Tank & Sockage Pit
V. Effluents are suitable for disposal as per Water Quality Analysis
Report
4.14 Trainings
79. A good working relationship is being maintained among the Contractor
and the Consultants environmental staff. Trainings are being arranged
by the PIC and Contractor’s Environmentalist on site for the capacity
building of the Contractor and their relevant staff. They are briefed on
updating the environment monitoring checklists and strictly follow the
EMP, which they submit on weekly basis to adhere Environmental
Management and Monitoring activities. They are also updated and
coordinated for current COVID-19 safety management scenario,
provision of disinfectors, safety paraphernalia and training of staff. The
training guidelines for Buildings Department for demolishing of two
Primary Schools coming in the RoW were also prepared and conveyed.
Training conducted by PIC to site supervisors & by site supervisors to field staff & Labor
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
42
80. Details of training to Contractor Staff is enlisted below:
Details of HSE Trainings Conducted during March to Dec 2020
Sr. No
Training Topics Training Date No. of Participants
1 Fire Fighting and Emergency Response 03-03-2020 16
2 Awareness and Preventive Measures SOPs of COVID-19 27-04-2020 12
3 Traffic Management and Machinery Operation 29-05-2020 11
4 Waste Segregation and Housekeeping Inside the Camp. 24-06-2020 19
5 Electrical Safety and Hazard Associated with Electricity 28-07-2020 13
6 Covid-19 Preventive Measures and Travel Advise during Eid-ul-Adha Holidays
29-07-2020 44
7 Emergency Preparedness & Response Procedures 04-08-2020 18
8 Housekeeping & Waste Management 15-09-2020 28
9 Sustainable Batching Plant Operations 16-10-2020 07
10 Traffic Management & Road Safety 16-10-2020 18
11 Safe and Defense Driving , safe operation of equipment use for earthwork
29-11-2020 14
12 Safe Dumping Operation for the construction of flood protection bund
18-12-2020 08
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
43
5 ENVIRONMENTAL MONITORING
5.1 Environmental Monitoring
81. Environmental monitoring will be consisted of two types. The first type
requires field sampling and lab analysis for example water quality, air
quality and noise levels. The second type refers impact monitoring to
visual inspections of such as soil erosion, restoration of vegetation, solid
waste disposal and so on. Field inspections have been undertaken by
the on-site Project Manager of the Contractor on regular basis.
Environmentalist of PIC undertook field inspections on daily basis, while
Senior and Principal Environmentalists of PIC also inspected the project
activities on periodical basis. PMO Environmental team also supervise
and monitor construction and HSE activities on regular basis. All the
observations in the form of monitoring report are being submitted to PMO
on monthly basis.
5.2 Impact Monitoring
82. The environmental monitoring was carried out by PIC to assess actual
nature and extent of key impacts and the effectiveness of mitigation and
enhancement measures outlined in the EMP and SSEMP. Mitigation
measures are considered so that the projects are designed, constructed,
and operated in compliance with applicable national and provincial laws
and regulations and meets the requirements of ADB SPS (2009).
83. Further field inspections are undertaken by the Environmentalists of PIC
& PMO. All the observations in the form of monitoring report will be
submitted to PMO on monthly basis.
84. The parameters of Impact monitoring are as follows:
I. Workers and Community Safety
II. Environmental Protection
III. Physical and Cultural Relics
IV. Soil Erosion
V. Natural Habitat Protection
VI. Contractor’s Camp
VII. Flora and Fauna
VIII. Waste Management
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
44
5.2.1 Site Visits
85. Regular site visits are being conducted, during the Contractor’s camp
and project sites visits, improvement in environmental safeguards is
mutually discussed with Contractor and their field staff and they are
advised to follow the EMP & SSEMP. The following activities are
conducted during the camp and worksite visits.
i. Inspection of Working Site
ii. Visit to Construction Site and Borrow Site
iii. Observation of Earth and Civil Works
iv. Meetings and filling of checklists with contractor.
v. Meeting and consultation with labor and supervisory staff
regarding PPEs and HSE.
vi. Visit to Schools construction and demolition sites, when
required.
vii. Acquisition and review of HSE record for further analysis and
cunning of compliance
viii. Meeting and consultation with labor and supervisory staff
ix. Visit to Camp Site, Offices, Kitchen, Residential Area, etc.
x. Review of HSE data and toolbox talks.
xi. Meetings and signing of Social Framework Agreements (SFA)
in Malikpur and Shahkamir Villages
xii. Scrutiny of Contractor’s staff/labor data and checking of CNIC
of staff with respect to Contract specifications, SSEMP and ILO
requirements (Occasionally).
xiii. Review of HSE data and toolbox talks.
xiv. Evaluation of environmental compliance record and cross check
of monitoring checklists.
xv. Visit to dispensary, record inspection and consultation with staff.
xvi. Checking of the screening record of employees thermo-
screening and disinfection, mode of transportation and
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
45
screening performa signed by each employee and
Environment/Health officer, after the Eid holidays induction.
xvii. Evaluation of environmental compliance record and cross check
of monitoring checklists.
xviii. Visit to dispensary, record inspection and consultation with staff.
xix. Scrutiny of labors daily temperature sheets and other COVID-
19 Measures.
xx. Visit to complaint office and GRM record checking.
xxi. Observation and inspection of waste disposal site, soakage pit,
walkways, disinfector gates, laboratory, generator room, fuel
storage area, plantation sites and discussion with relevant staff.
xxii. Planning for in-house trainings, HSE activities and COVID-19
management trainings with Contractor’s Environmentalists.
xxiii. Checking of previous compliance/non-compliance status.
xxiv. Checking of implementation of Corrective Action Plan
5.2.2 Monitoring Checklists
86. Daily and weekly Monitoring Checklists are developed for regular
monitoring, while a quantitative environmental compliance monitoring
checklist is also developed in close coordination with Contractor,
Implementation Consultants and PMO. They are being filled, signed and
compliance status is calculated throughout the monitoring period.
5.3 Instrumental Monitoring
87. The field sampling and lab analysis, including air, noise and water quality
were conducted during the July and December, 2020.
5.3.1 Instrumental Monitoring July 2020
88. Ambient Air Quality (AAQ) Monitoring was completed from 16th July to
18th July 2020. For ambient air, the sampling data collection was carried
out at four locations, selected with mutual discussion and site visit of
senior and junior environmentalists of consultant (PIC) and contractor
environmentalist.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
46
Water Sampling for Analysis
Detail of Selected Points Ambient Air and Noise Monitoring
Location Coordinates Criteria of Selection of Point
RD-0+10 Rasul Barrage
32°41'8.31"N, 73°30'56.09"E
Main Road/ Transportation Route, Active Construction Site
RD-20+00 Malikpur 32°40'8.00"N, 73°27'59.00"E
Background Impacts on nearest communities
RD-25+500 GRC Camp Area
32°39'49.00"N, 73°27'2.00"E
Camp, Offices, Residence of Labor, Batching Plant and Generator Impacts
RD-47+600 Moza Chitti
32°39'52.72"N, 73°23'2.02"E
Main Road, Area with heavy traffic, commercial activities and close settlements
along the project footprints
89. Average Concentrations of CO, NO, NO2, SO2, CO2, PM10, PM2.5, TVOC,
O3, Pb and noise for four selected locations of JIP were taken to assess
the AAQ level as shown below in Exhibit:
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
47
Ambient Air Quality (AAQ) Monitoring
Parameter PEQS2 Unit RD-0+10
Rasul Barrage
RD-25+500 GRC Camp
Area
RD-20+00 Malikpur
RD-47+600 Moza Chitti
CO 5 (mg/m3) 2.15 1.08 1.17 2.43
NO 40 (µg/m3) 13.99 13.64 10.55 13.913
NO2 80 (µg/m3) 25.05 11.63 12.89 22.92
SO2 120 (µg/m3) 16.95 17.21 13.57 25.56
CO2 3503 (µg/m3) 254.02 268.38 229.2 408.59
PM10 150 (µg/m3) 126.29 134.81 88.09 152.79
PM2.5 35 (µg/m3) 26.22 29.15 14.63 30.16
SPM 500 (µg/m3) 265.66 296.53 121.01 349.5
O3 130 (µg/m3) 8.54 11.95 8.36 17.16
TVOC 3.34 (µg/m3) 0.056 0.048 0.02 0.03
Lead 1.5 (µg/m3) 0.89 0.65 0.21 1.1
Noise 75 dB(A) 70.11 67.46 54.1 73.49
90. Exhibit shows the results are within the limits except 8 hours average
concentration of PM10 and CO2 at Moza Chiti. (47+600). The reason and
factor behind this increased value include, heavy traffic on main road,
hotels, shops, ice factory and plain agriculture field, as any project
related activity, construction, land clearance, etc. activity is not started
at this point. It is required to carefully monitor the same point in upcoming
quarterly monitoring. Moreover, the provisions of SSEMP, may also be
updated in accordance with these elevated values. It is anticipated that
with the help of effective implementation of provisions of SSEMP and
continued monitoring, JIP will provide ‘better than baseline conditions’
during the construction in such area.
91.
92. The Sampling of surface, waste and drinking water was carried out at
following locations:
Water/ Wastewater Sampling Locations
2 Punjab Environmental Quality Standards (PEQS) were taken for comparison of Air contamination level. WHO and OSHA standards were considered where PEQS are silent, i-e., carbon dioxide and Total Volatile Organic Compounds 3 WHO standards 4 OSHA Standards
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
48
Location Coordinates
Surface Water River Jhelum Downstream Jalalpur Sharif 32°37'54"N, 73°23'59"E
Drinking Water Jalalpur City 32°39'24"N, 73°24'28"E
Surface Water Rasul Barrage Downstream 32°41'07"N, 73°30'53"E
Drinking Water / Ground Water Camp Site 32°39'43"N, 73°26'57"E
Wastewater Septic Tank (Camp Site) 32°39'43"N, 73°26'53"E
Wastewater Soakage Pit (Camp Site) 32°39'41"N, 73°26'54"E
93. All drinking water analysis parameters (Physical, chemical and
microbiological) in Jalalpur city and GRC Camp area found within limit in
accordance with the Punjab Environmental Quality Standards (PEQS).
The results of water quality analysis are provided, hereunder:
Physical Analysis of Drinking / Ground Water Results
Parameter Unit PEQS GRC Camp
Site Jalalpur City Reference Method
Turbidity NTU ‹ 5 0.5 0.3 APAHA-2130 B
Total hardness as
CaCO3 mg/l < 500 126.5 139.2 APHA-2340 C
TDS mg/l ‹ 1000 496 483 APHA-2540 C
Odour - Acceptable/Non-
Acceptable Acceptable Acceptable In-House
Taste - Acceptable/Non-
Acceptable Acceptable Acceptable In-House
Color TCU 15 6.0 5.0 ASTM D 1209
pH - 6.5-8.5 7.1 7.3 APHA-4500H+ B
Chemical Analysis of Drinking / Ground Water Results
Parameter Unit GRC- Camp Site
Jalalpur City
PEQS Method Reference Method
Aluminum mg/l 0.009 0.007 <0.2 AAS APHA-3111B
Arsenic mg/l BDL BDL < 0.05 AAS APHA-3111B
Antimony mg/l BDL BDL <0.005 AAS APHA-3114B
Barium mg/l 0.05 0.02 0.7 AAS APHA-3111B
Boron mg/l 0.02 0.05 0.3 AAS APHA-3111 B
Cadmium mg/l BDL BDL 0.01 AAS APHA-3111B
Chloride mg/l 128.3 147.6 <250 Titration APHA-4500 Cl- B
Chromium mg/l BDL BDL <0.05 AAS APHA-3111
Copper mg/l 1.0 1.2 2.0 AAS APHA-3111
Cyanide mg/l ND ND <0.05 Spectrophotometric APHA-4500 CN- E
Fluoride mg/l 0.6 0.8 <1.5 Spectrophotometric APHA-4500 F-/C
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
49
Lead mg/l BDL BDL <0.05 AAS APHA-3111
Manganese mg/l BDL BDL < 0.5 AAS APHA-3111
Nitrate mg/l 9.4 10.2 <50 Spectrophotometric APHA-4500 NO3-
Nitrite mg/l 0.6 0.9 <3 Spectrophotometric APHA-4500 NO2-
Zinc mg/l 1.7 1.2 5.0 AAS APHA-3111
Nickel mg/l BDL BDL <0.02 AAS APHA-3111
Mercury mg/l BDL BDL <0.001 AAS APHA-3111
Selenium mg/l BDL BDL 0.01 AAS APHA-3114 B
Iodine mg/l BDL BDL 0.018 Idiomatric Analysis APHA I-4500 B
TSS mg/l BDL 15.8 --- Gravimetric APHA-2540 D
Ammonia mg/l 8.29 8.21 40 Titration APHA 4500 NH3 C,
Sulphate mg/l 226 219 600 Gravimetric APHA 4500 SO42- C
Conductivity µS 813 820 --- Conductivity meter ---
Bicarbonate mg/l 2.6 2.3 --- Titration APHA-2340 C
Magnesium (Mg)
mg/l 29.3 31.6 --- Titration APHA-2340 C
Calcium (Ca) mg/l 44.7 0.9 --- Titration APHA-2340 C
Phosphate mg/l 0.04 0.03 --- Titration APHA 4500 P
Potassium mg/l 0.05 42.5 --- Titration APHA 4500 P
Sodium mg/l 7.1 BDL 20 Flame Photometer APHA 4500 Na-C
Iron mg/l 4.2 4.9 8.0 AAS APHA-3111
Microbiological Analysis of Drinking / Ground Water Results
94. Exhibit below shows that, all waste water analysis parameters at GRC
Septic Tank and Sockage are within the set limits of the Punjab
Environmental Quality Standards.
Surface Water Quality Analysis
Parameter Unit FAO D/S
River Jhelum
Rasul Barrage
D/S Method
Reference Method
Parameter Unit NEQS Jalalpur
City
GRC
Camp Reference
Coliform Cfu/100ml Must not be detectable
in 100 ml of sample Nil Nil APHA-9222 B
Fecal
Coliform Cfu/100ml
Must not be detectable
in 100 ml of sample
Nil
Nil
APHA-9222 D
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
50
pH - 6.4-8.5 6.8 6.7 Electrometer APHA-4500 H+ B
Turbidity NTU --- 33.7 18.4 Nephelometric APAHA-2130 B
Color TCU 15 7 8 Pt-Co ASTM D 1209
COD mg/l --- 64 76 Digestion Titration APHA-5220 B
BOD mg/l --- 18 22 5days incubation APHA-5210 B
TDS mg/l 2000 1820 1740 Gravimetric APHA-2500 C
DO - 5.7 6.9 DO Meter EZDO Do meter
TSS mg/l 200 108 98 Gravimetric APHA-2540 D
Chloride mg/l 1000 149.2 128.5 Titration APHA-4500 B
Sulphide mg/l 1 0.8 0.6 Iodometric Titration APHA 4500 S2- E
Aluminium mg/l 5 0.009 0.03 AAS APHA-3111 B
Cadmium mg/l 0.1 0.006 0.05 AAS APHA-3111 B
Chromium mg/l 1 0.08 0.07 AAS APHA-3111 B
Copper mg/l 1 BDL BDL AAS APHA-3111 B
Lead mg/l 5 0.09 0.07 AAS APHA-3111 B
Mercury mg/l --- BDL BDL AAS APHA-3112 B
Selenium mg/l 0.02 BDL BDL AAS APHA-3114 B
Nickel mg/l 0.2 0.04 0.02 AAS APHA-3111 B
Silver mg/l --- BDL BDL AAS APHA-3111 B
Total toxic metals
mg/l --- 0.9 0.8 Based on Calculations -
Zinc mg/l 2 1 1.6 AAS APHA-3111 B
Arsenic mg/l 0.1 0.03 0.05 AAS APHA-3111 B
Barium mg/l --- 0.01 0.03 AAS APHA-3111 B
Iron mg/l --- 4.9 3.7 AAS APHA-3111 B
Manganese mg/l 0.2 0.16 0.12 AAS APHA-3111 B
Boron mg/l 0.7 0.4 0.5 AAS APHA-3111 B
Oil and Grease
mg/l --- 2.1 1.8 Solvent Extraction USEPA method
1664
Sulphate mg/l --- 219 235 Gravimetric APHA 4500 SO4
2- C
Chlorine mg/l --- 0.04 0.01 Calorimetric/Iodometric APHA 4500 Cl B
& C
Fluoride mg/l 1 0.8 0.6 Spectrophotometric APHA-4500 F-/C
Ammonia (NH3)
mg/l --- 8.21 7.39 Titration APHA 4500 NH3
C,
Pesticides mg/l --- 0.08 0.08 GC-MS USEPA-
8081A/EPA 3510
Anionic Compounds
mg/l --- BDL BDL Spectrophotometric APHA 5540 C
Phenolic Compounds
mg/l --- BDL BDL Spectrophotometric APHA-5530 C
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
51
Cyanides mg/l --- 0.01 0.02 Spectrophotometric APHA 4500 CN E
Antimony mg/l --- BDL BDL AAS Method APHA 4500-Sb
Nutrient as (K) mg/l --- 0.04 0.03 AAS Method APHA 4500-K
Nutrient as (N) mg/l --- 0.01 0.02 AAS Method APHA 4500NH3-B
Nutrient as (P) mg/l --- 0.007 0.009 AAS Method APHA PO4-C
Wastewater Analysis
Parameter Unit Septic Tank
Sockage Pit
PEQS Method Reference
Temperature Co 30.4 32.7 40±<3 Thermometer
pH - 7.1 6.8 6-9 Electrometer APHA-4500 H+ B
COD mg/l 134 123 150 Digestion Titration APHA-5220 B
BOD mg/l 51 48 80 5days incubation APHA-5210 B
TDS mg/l 1,827 1,793 3500 Gravimetric APHA-2500 C
TSS mg/l 92 86 150 Gravimetric APHA-2540 D
Chloride mg/l 138.5 129.1 1000 Titration APHA-4500 B
Oil & Grease mg/l 1.7 1.3 10 Solvent Extraction USEPA method 1664
Anionic Detergents
mg/l 2.3 2.8 20 Spectrophotometric APHA 5540 C
Phenols mg/l 0.09 0.07 0.1 Solvent Extraction APHA 5530 A
Fluorides mg/l 3.7 3.2 10 Spectrophotometric APHA 4500 F- C
Cyanide mg/l 0.3 0.4 1 Spectrophotometric APHA 4500 CN E
Sulfates mg/l 207 190 600 Gravimetric APHA 4500 SO42- C
Chlorine mg/l 0.3 0.5 1 calorimetric/Iodometric APHA 4500 Cl B & C
Ammonia mg/l 4.3 4.1 40 Titration APHA 4500 NH3 C,
Sulphide mg/l 0.7 0.6 1 Iodometric Titration APHA 4500 S2- E
Cadmium mg/l 0.09 0.07 0.1 AAS APHA-3111 B
Chromium mg/l 0.05 0.03 1 AAS APHA-3111 B
Copper mg/l BDL BDL 1 AAS APHA-3111 B
Lead mg/l 0.09 0.2 0.5 AAS APHA-3111 B
Mercury mg/l BDL BDL 0.01 AAS APHA-3112 B
Selenium mg/l BDL 0.1 0.5 AAS APHA-3114 B
Nickel mg/l 0.05 0.09 1 AAS APHA-3111 B
Silver mg/l BDL BDL 1 AAS APHA-3111 B
Total toxic metals
mg/l 1 0.9 2 Based on Calculations -
Zinc mg/l 1.8 1.4 5 AAS APHA-3111 B
Arsenic mg/l 0.07 0.02 1 AAS APHA-3111 B
Barium mg/l 0.01 0.03 1.5 AAS APHA-3111 B
Iron mg/l 5.2 4.8 8 AAS APHA-3111 B
Manganese mg/l 1.1 0.7 1.5 AAS APHA-3111 B
Boron mg/l 0.3 0.5 6 AAS APHA-3111 B
Antimony mg/l --- --- BDL AAS Method APHA 4500-Sb
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
52
Pesticides mg/l --- --- 0.08 GC-MS USEPA-8081A/EPA
3510
5.3.2 Instrumental Monitoring December, 2020
95. Water, Wastewater and Ambient Air Quality Monitoring was completed
from 23rd December to 24th December 2020. The observed
concentrations for Ambient air quality parameters (PM10, PM2.5, CO, NO,
NO2, SPM, O3 SO2, Pb) are compared with the Punjab Environmental
Quality Standards (PEQS). CO2 values were compared with the WHO
standards. OSHA standards were used for the comparison of TVOC’s.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
53
Ambient air Quality Level
Locations CO
(mg/m3) NO
(µg/m3) NO2
(µg/m3) SO2
(µg/m3) CO2
(mg/m3) PM10
(µg/m3)
PEQS 5 40 80 120 3505 150
RD-23+00 GRC Camp Area
0.82 23.64 27.11 22.49 268.93 136.14
Borrow Area 2.01 24.24 27.38 24.58 309.63 143.25
RD-0+10 Rasul Barrage
0.91 23.12 26.67 21.73 243.68 141.45
Noise and Amabient Air Quality Level
Locations PM2.5
(µg/m3) SPM
(µg/m3) O3
(µg/m3) TVOC
(mg/m3) Lead
(µg/m3) Noise dB(A)
PEQS 35 500 130 3.36 1.5
RD-23+00 GRC Camp Area
31.32 297.69 11.44 0.05 0.29 70.11
Borrow Area 33.84 324.23 16.53 0.073 0.93 73.85
RD-0+10 Rasul Barrage
31.47 264.18 12.61 0.049 1.0 67.73
96. The average measured values of air contamination at above mentioned
three locations was found in limit in accordance with PEQS. In
comparison with the above three locations, average concentration of
Particulate Matter and CO was found high at Borrow area as compared
to other two locations because point was measured at near road side
and bulk traffic movement creates impact on increase in PM and CO
level, but all the results at monitored locations were in limit in accordance
with the PEQS.
97. The Sampling of surface, waste and drinking water was carried out at
following locations on 24th of December 2020.
I. Waste Water Septic Tank GRC Camp Site
II. Drinking / Ground Water Camp site
III. Surface Water Rasul Barrage Down Stream
5 WHO Standards 6 OSHA Standards
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
54
98. Exhibits below shows that, all drinking water analysis parameters
(Physical, chemical and microbiological) at GRC Camp Site are within
the set limits of the Punjab environmental quality standards (PEQs).
Physical & Chemical Analysis of Drinking / Ground Water Results - (GRC- Camp Site)
Parameter Unit PEQS Result Reference Method
Turbidity NTU ‹ 5 0.42 APAHA-2130 B
Total hardness as CaCO3
mg/l < 500 135.2 APHA-2340 C
TDS mg/l ‹ 1000 503 APHA-2540 C
Odour - Acceptable/Non-
Acceptable Acceptable In-House
Taste - Acceptable/Non-
Acceptable Acceptable In-House
Color TCU 15 4.0 ASTM D 1209
pH - 6.5-8.5 7.2 APHA-4500H+ B
Parameter Unit Results PEQS Method Reference
Method
Aluminium mg/l 0.006 <0.2 AAS APHA-3111B
Arsenic mg/l BDL < 0.05 AAS APHA-3111B
Antimony mg/l BDL <0.005 AAS APHA-3114B
Barium mg/l 0.07 0.7 AAS APHA-3111B
Boron mg/l 0.05 0.3 AAS APHA-3111 B
Cadmium mg/l BDL 0.01 AAS APHA-3111B
Chloride mg/l 117.9 <250 Titration APHA-4500 Cl-
B
Chromium mg/l BDL <0.05 AAS APHA-3111
Copper mg/l 0.7 2.0 AAS APHA-3111
Cyanide mg/l ND <0.05 Spectrophotometric APHA-4500
CN- E
Fluoride mg/l 0.4 <1.5 Spectrophotometric APHA-4500 F-
/C
Lead mg/l BDL <0.05 AAS APHA-3111
Manganese mg/l BDL < 0.5 AAS APHA-3111
Nitrate mg/l 10.1 <50 Spectrophotometric APHA-4500
NO3-
Nitrite mg/l 0.3 <3 Spectrophotometric APHA-4500
NO2-
Zinc mg/l 1.9 5.0 AAS APHA-3111
Nickel mg/l BDL <0.02 AAS APHA-3111
Mercury mg/l BDL <0.001 AAS APHA-3111
Selenium mg/l BDL 0.01 AAS APHA-3114 B
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
55
Iodine mg/l BDL 0.018 Idiomatric Analysis APHA I-4500 B
TSS mg/l BDL --- Gravimetric APHA-2540 D
Ammonia mg/l 7.3 40 Titration APHA 4500
NH3 C,
Sulphate mg/l 231 600 Gravimetric APHA 4500
SO42- C
Conductivity µS 912 --- Conductivity meter ---
Bicarbonate mg/l 2.1 --- Titration APHA-2340 C
Magnesium (Mg)
mg/l 24.5 --- Titration APHA-2340 C
Calcium (Ca) mg/l 39.2 --- Titration APHA-2340 C
Phosphate mg/l 0.07 --- Titration APHA 4500 P
Potassium mg/l 0.03 --- Titration APHA 4500 P
Sodium mg/l 6.8 20 Flame Photometer APHA 4500
Na-C
Iron mg/l 3.7 8.0 AAS APHA-3111
Microbiological Analysis of Drinking / Ground Water Results - (GRC- Camp Site)
Surface Water Analysis -(Rasul Barrage Down Stream)
Parameter Unit FAO Results Method
pH - 6.4-8.5 6.4 Electrometer
Turbidity NTU --- 17.5 Nephelometric
Color TCU 15 9.0 Pt-Co
COD mg/l --- 83 Digestion Titration
BOD mg/l --- 29 5days incubation
TDS mg/l 2000 1,897 Gravimetric
DO - 6.4 DO Meter
TSS mg/l 200 103 Gravimetric
Chloride mg/l 1000 136.2 Titration
Sulphide mg/l 1.0 0.51 Iodometric Titration
Aluminum mg/l 5.0 0.07 AAS
Cadmium mg/l 0.1 0.03 AAS
Chromium mg/l 1.0 0.09 AAS
Copper mg/l 1.0 BDL AAS
Parameter Unit NEQS Result Reference
Coliform Cfu/100ml Must not be
detectable in 100 ml of sample
0.0 APHA-9222 B
Feacal Coliform Cfu/100ml Must not be
detectable in 100 ml of sample
0.0 APHA-9222 D
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
56
Lead mg/l 5.0 0.05 AAS
Mercury mg/l --- BDL AAS
Selenium mg/l 0.02 BDL AAS
Nickel mg/l 0.2 0.03 AAS
Silver mg/l --- BDL AAS
Total toxic
metals mg/l --- 0.7 Based on Calculations
Zinc mg/l 2.0 1.2 AAS
Arsenic mg/l 0.1 0.08 AAS
Barium mg/l --- 0.05 AAS
Iron mg/l --- 4.2 AAS
Manganese mg/l 0.2 0.1 AAS
Boron mg/l 0.7 0.2 AAS
Oil and Grease mg/l --- 1.5 Solvent Extraction
Sulphate mg/l --- 228 Gravimetric
Chlorine mg/l --- 0.03 Calorimetric/Iodometric
Fluoride mg/l 1.0 0.7 Spectrophotometric
Ammonia (NH3) mg/l --- 8.12 Titration
Pesticides mg/l --- 0.09 GC-MS
Anionic
Compounds mg/l --- BDL Spectrophotometric
Phenolic
Compounds mg/l --- BDL Spectrophotometric
Cyanides mg/l --- 0.06 Spectrophotometric
Antimony mg/l --- BDL AAS Method
Nutrient as (K) mg/l --- 0.05 AAS Method
Nutrient as (N) mg/l --- 0.03 AAS Method
Nutrient as (P) mg/l --- 0.007 AAS Method
Table 2: Microbiological Surface Water Analysis - (Rasul Barrage Down
Stream)
Parameter Unit NEQS Result Reference
Total Coliform Cfu/100ml Must not be detectable in
100 ml of sample 35.0 APHA-9222 B
Feacal Coliform Cfu/100ml Must not be detectable in
100 ml of sample 13.0 APHA-9222 D
E.Coli Cfu/100ml Must not be detectable in
100 ml of sample 5.0 APHA-9222 D
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
57
Table 3: Waste Water Analysis Soakage Pit (GRC Camp)
Parameter Unit Results PEQS Reference
Temperature oC 26.9 40±<3 -
pH - 6.9 6-9 APHA-4500 H+ B
COD mg/l 142 150 APHA-5220 B
BOD mg/l 57 80 APHA-5210 B
TDS mg/l 2,016 3500 APHA-2500 C
TSS mg/l 103 150 APHA-2540 D
Chloride mg/l 123.8 1000 APHA-4500 B
Oil & Grease mg/l 1.4 10 USEPA method 1664
Anionic Detergents mg/l 1.9 20 APHA 5540 C
Phenols mg/l 0.07 0.1 APHA 5530 A
Fluorides mg/l 2.8 10 APHA 4500 F- C
Cyanide mg/l 0.1 1.0 APHA 4500 CN E
Sulfates mg/l 219 600 APHA 4500 SO42- C
Chlorine mg/l 0.27 1.0 APHA 4500 Cl B & C
Ammonia mg/l 4.1 40 APHA 4500 NH3 C,
Sulphide mg/l 0.9 1.0 APHA 4500 S2- E
Cadmium mg/l 0.05 0.1 APHA-3111 B
Chromium mg/l 0.07 1.0 APHA-3111 B
Copper mg/l BDL 1.0 APHA-3111 B
Lead mg/l 0.06 0.5 APHA-3111 B
Mercury mg/l BDL 0.01 APHA-3112 B
Selenium mg/l BDL 0.5 APHA-3114 B
Nickel mg/l 0.07 1.0 APHA-3111 B
Silver mg/l BDL 1.0 APHA-3111 B
Total toxic metals mg/l 0.9 2.0 -
Zinc mg/l 1.5 5.0 APHA-3111 B
Arsenic mg/l 0.09 1.0 APHA-3111 B
Barium mg/l 0.03 1.5 APHA-3111 B
Iron mg/l 4.8 8.0 APHA-3111 B
Manganese mg/l 0.6 1.5 APHA-3111 B
Boron mg/l 0.5 6.0 APHA-3111 B
Aluminum
Antimony mg/l --- BDL APHA 4500-Sb
Pesticides mg/l --- 0.08 USEPA-8081A/EPA 3510
Fecal Coliform Cfu/100ml 119 - APHA-9222 B
E.Coli Cfu/100ml 93 -
Total Coliform Cfu/100ml 176 - APHA-9222 D
99. Table shows that, all waste water analysis parameters (Physical,
chemical) at GRC Camp (Soakage Pit) are within the set limits of the
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
58
Punjab environmental quality standards (PEQs) except microbial
parameters.
5.4 Corrective Action Plan (CAP)
5.4.1 Major Issues / Non-Compliances
100. The following issues and area of concerns are observed at the site.
I. Ambulance is not provided at camp, permanently.
II. Quarterly Environmental Monitoring is delayed due to COVID-19.
III. PPEs are not fully used by labors at all times but the contractor is
improving by creating awareness among the labor through trainings.
IV. Fugitive and ambient dust issues at a few sites.
V. Trespassing of domestic animals and locals is observed at the
working area, occasionally.
5.4.2 Compliances
I. Barricading has been done at all arears.
II. Sanitizer bottles and disinfection gates are properly managed.
III. Caution tapes are installed on the entrance of cofferdam to avoid
trespassing of visitors.
IV. Monthly training was held.
V. Fortnightly Noise Monitoring is being completed.
VI. Tool Box Talk was held at site.
VII. Sign boards near alternative route are fitted at designated location.
VIII. Medicines were provided in First Aid Kit at site.
IX. Flagmen were deputed for traffic management.
X. Contractor instructed the workers to wear face masks.
XI. Face masks are provided by the contractor to employees.
XII. Shoe Plugs of electrical equipment are installed on some electrical
appliances, front protection of fan is installed and Air cooler is
removed.
XIII. Quarantine/ Isolation cell is established.
XIV. One person is deputed to check the temperature and disinfect the
hands of everyone who enter in the camp.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
59
XV. Disinfection walk through gates are working for the disinfection.
XVI. Hand Sanitizers are placed in the office, store, laboratory, kitchen
and workshop.
XVII. Face masks are provided by the contractor to all employees.
XVIII. Grievances register is placed in the camp and signboard is installed
at the entrance gate for the guidance where to record the grievance.
XIX. Regular sprinkling of water on the walk ways to avoid dust pollution.
XX. New trees are planted at camp.
XXI. Dispensary, equipped with required medicines, equipment, furniture
and First Aid kit and labeled, is operational under the role of qualified
male nurse / Dispenser.
XXII. A specific area is assigned and labeled for the collection,
segregation and safe disposal of solid waste of camp.
XXIII. Septic Tanks and Soakage Pits are constructed and functional.
XXIV. Precautionary awareness signs are installed at the sites.
XXV. Cleanliness and housekeeping are doing regularly.
XXVI. Fire Extinguishers are installed near fuel storage area.
XXVII. Main Electric Cables are covered and underground.
XXVIII. According to the Layout, Location of Electric Cables are marked and
labeled.
XXIX. Portable water is available inside the site.
XXX. Assembly Point is demarcated and labelled inside the camp.
XXXI. No Tree cutting is observed for fuel wood.
XXXII. Construction Material is completely stockpiled.
XXXIII. Workers are working with site-specific PPEs.
XXXIV. Fuel Storage Area is free from Combustible Material.
XXXV. The Construction Machinery Parked at designated location.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
60
5.4.3 Corrective Action Plan for the Month of March,2020
Issue Description of Non-Compliance/Complaint
Timeline Monitoring Indicator Compliance Status
1 Water Sprinkling inside the camp
Immediate Photographic Record Compliance
2 Repair water pump installed near General Mess
1 Day Visual Inspection Compliance
3 Provide missing medicine in the 1st Aid Box
1 day Photographic Record Compliance
4 Make sure the cleanliness of washrooms
1 day Visual Inspection Compliance
5 Provide dust bins for supervisory building
1 day Visual Inspection Compliance
6 Provide face mask immediate Photographic Record Compliance
5.4.4 Corrective Action Plan for the Month of April,2020
Issue Description of Non-
Compliance/Complaint Timeline
Monitoring Indicator
Compliance Status
1
Please make sure Housekeeping inside the camp
2 days Visual
Inspection
Compliance One more extra
sweeper has been appointed to keep the camp in better
living condition
2
Please provide hand sanitizer bottle in for Material Testing Laboratory
Immediate Visual
Inspection Compliance
3 Please provide face mask for workshop workers
Immediate Visual
Inspection Compliance
4 Please disinfect the rooms 1 Day
Daily Photographic
Record Compliance.
5 Please refill the sanitizer bottle placed in Material Store.
Immediate Refilled Compliance
6 Please provide hand washing facility at site
1 week Visual
Inspection Compliance
7 Please installed sanitizer gates
2 week Photographic
Record Compliance
8 Please provide soap for and hand sanitizer for site
Immediate Visual
Inspection Compliance
5.4.5 Corrective Action Plan for the Month of May,2020
Issue Description of Non-
Compliance/Complaint Timeline
Monitoring Indicator
Compliance Status
1 Please make sure water sprinkling inside the camp.
Immediate Photographic
Record Compliance
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
61
2 Please refill the 1st Aid box placed at site with missing medicines.
1 day Photographic
Record Compliance
3 Please provide face Mask
Immediate Visual
Inspection Compliance
4
Due to intense storm, sanitizer gate installed near material testing laboratory has been damaged. Please repaired this gate and reinstalled it.
2 days Photographic
Record Compliance
5 Please provide face mask at site
Immediate Visual
Inspection Compliance
6
Please make sure cleanliness of washrooms
Immediate Visual
Inspection
Compliance Washrooms has
been cleaned and sweepers are strictly instructed to make sure cleanliness of
washrooms.
7 Refrigerator has become out of order placed in general mess
2 days Visual
Inspection Compliance
5.4.6 Corrective Action Plan for the Month of June,2020
Issue Description of Non-
Compliance/Complaint Timeline
Monitoring Indicator
Compliance Status
1 Please provide dustbins in Labor Accommodations
1 week Visual
Inspection compliance
2 Please refill hand sanitizer bottle for store.
immediate Visual
Inspection compliance
3 Please provide cotton gloves
One day Visual
Inspection compliance
4 Please provide water coolers at site 3 days
Visual inspection
compliance
5 Please install electric water cooler for General Mess
1 week Photographic
record compliance
6 Please provide face mask at site
immediate Visual
inspection compliance
5.4.7 Corrective Action Plan for the Month of July 2020
Issue Description of Non-
Compliance/Complaint Timeline
Monitoring Indicator
Compliance Status
1
Isolation room is not available in camp for temporary isolation of COVID-19 suspected cases. Contractor was advised to immediately arrange isolated rooms or containers.
1 week Isolation room
is available Compliance
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
62
2
It was found that new workers at an earthwork site were deployed on work without training on PPEs & prevention measures for COVID-19. Contractor is advised to provide and strictly monitor compliance of PPEs and conduct detailed in house training and awareness on COVID-19 prevention measures at each work site.
Provision of Masks= Immediate
Training 1
week
Training Record
Pending
3 Baseline Environmental Monitoring is still not conducted.
Third week of July
Baseline Environmental
Monitoring
Pending, Compliance
4
A switch board and fan in the workshop was not properly installed and may cause electric/fire hazard. Contractor is advised to fix this issue and mark those appliances ‘out of order’ till proper repair
Immediate Repair time 1 week
Repaired Electrical
appliances
Switch boards are installed but front protection of fan and air
cooler is still not present.
5
A disinfection gate was not working. Contractor is advised to fix this issue and mark those appliances ‘out of order’ till proper repair and use a second/alternate gate for all staff.
Immediate Repaired gate Compliance
6 Dust bins are not labeled for the separation of solid waste
1 week Labeled bins Pending,
Compliance
5.4.8 Corrective Action Plan for the Month of August,2020
Issue Description of Non-
Compliance/Complaint Timeline
Monitoring Indicator
Compliance Status
1 Please provide gloves for workshop workers
immediate Visual
Inspection Compliance
2 Please make sure cleanliness of washroom
immediate Visual
Inspection Compliance
3 Please repaired water pump installed for service station
2 days Visual
Inspection Compliance
4 Please provide cotton gloves
immediate Visual
Inspection Compliance
5 Please provide face mask to the workforce
immediate Visual
Inspection Compliance
6 Please repair electric fan of room
1 day Visual
Inspection Compliance
7 Please make sure water sprinkling at grey roads.
daily Visual
Inspection Compliance
5.4.9 Corrective Action Plan for the Month of September,2020
Issue Description of Non-Compliance/
Complaint Timeline
Monitoring Indicator
Compliance Status
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
63
1 Please barricade the excavated area.
1 day Photographic
Record Compliance
2 Please provide hard gloves
Immediate Visual
Inspection Compliance
3 Please control oil spillage inside the camp
2 days Photographic
Record Compliance
4 Please provide 1st Aid Boxes for site RD 0+000
2 days Photographic
Record Compliance
5 Please demark the canal area in front of each ramp/ access road to the site.
1 day Photographic
Record Compliance
6 Please installed sign board at RD 21, 23 and 24
1 week Photographic
Record Compliance
5.4.10 Corrective Action Plan for the Month of October,2020
Sr. No.
Non Compliance / Issues Time line Monitoring Indicator
Compliance Status
1 Cleanliness issues of general Washrooms.
Immediate Clean Washrooms
Rectified
2 Barricading in front of RD 4+625
Immediate Barrication in front of RD 4+625
Barricading has been done
3 A few medicines are not re stocked in First Aid Box
One Day Provision of Medicines
Medicine has been Provided
4 Taste of Drinking water used at general Mess has been changed,
2 days Drinking Water Analysis, Alternate Arrangements
New drinking water supply line has been provided to general mess .
5 Sanitizer Bottles are empty in meeting rooms
Immediate Refilling of bottles
Rectified
6 water cooler in workshop need to be replaced
Immediate Provision of Water Cooler
Replaced
7 Requisite for installation of Barbed wire at left side of Excavation of Head Regulator at RD 0+000
One day installation of Barbed wire
Barbed wire has been installed.
8 Installed signboard to aware and control access of unauthorized person in working area
3 days installation of Sign Boards
Signboard has been installed.
5.4.11 Corrective Action Plan for the Month of November ,2020
Issue Description of Non-Compliance/Complaint
Timeline Monitoring Indicator
Compliance Status
1 Please review the officer mess food menu and make necessary changing in it.
1 week Interviews of workers
Compliance
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
64
Food menu has been up dated of officer
mess.
2 Please make sure cleanliness of washrooms
Immediate Visual Inspection
Compliance Sweeper has been strictly instructed to
make sure cleanliness of washrooms
3 Please install caution sign board before entrance point of camp
3 days Photographic Record
Compliance Caution sign boards have been install at main road L/S & R/S before entrance point
of camp.
4 Please barricade the excavated area
1 day Photographic Record
Compliance Excavated has been
barricaded immediately after completion of
Excavation.
5 Provision of facemask for batching plant workers.
Immediate Visual Inspection
Compliance
6 Please depute flagman at RD 23+000
immediate Visual Inspection
Compliance
5.4.12 Corrective Action Plan for the Month of December,2020
Issue Description of Non-Compliance/Complaint
Timeline Monitoring Indicator
Compliance Status
1 Dust issues at RD -22 Immediate Visual Inspection
Partially Compliance
2 Installation of Sign board is required at RD-8 to restrict the Public entry
3 days Visual Inspection
3 Public vehicles are entering in ROW and construction area at RD 6. instruct flagman to restrict the entry of public vehicles at site
3 days Visual Inspection
Compliance
4 Cleanliness Issues in labor colony
Immediate Photographic Record
Compliance Sweeper has been instructed to make sure cleanliness of
rooms
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
65
6 EMP COMPLIANCE
6.1 Compliance Status from March – Dec 2020
101. The compliance statistics/ is shown hereunder., the overall conformance
and nonconformance levels are calculated on the basis of monthly
quantitative checklist.
6.1.1 Environmental Compliance Status March-2020
Sr. Description
Week7 Monthly Avg
1 2 3 4 Mar-20
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3
2 The EMP instructions are understood? 3 3 3
3 An individual is nominated for implementation of EMP? 3 3 3
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
1 1 1
5 Assembly Point is demarcated, alarming system. 1 1 1
6 Recreational Activities for staff & labor 0 0 0
7 Contractor provided PPE to their workforce and they are being used?
1 1 1
8 Potable water is available to labor? 3 3 3
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
2 3 2.5
10 Contractors maintained Environmental Monitoring Record and submits monthly monitoring reports?
NA NA N/A
11 Contractors maintained Grievances Log and registered the complaints from community?
2 3 2.5
12 Contractors prohibited child labor and forced labor? 3 3 3
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
3 3 3
14 Septic Tank and Soak Pits are designed for treatment of effluents?
1 1 1
15 No complaint filed regarding transmission of Communicable diseases
3 3 3
Moderate Adverse Impacts (weightage 0-2) 0
16 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2
17 No wood cutting for fuel? 2 2 2
7 Monthly Compliance Status is measured on the basis of monitoring data of two weeks due to lockdown/ COVID-19
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
66
Sr. Description
Week7 Monthly Avg
1 2 3 4 Mar-20
18 LPG cylinders are provided for cooking or heating purposes? 2 2 2
19 Arrangement for proper storage and disposal for solid waste is planned?
1 2 1.5
20 Safety signs are properly displayed? 1 2 1.5
21 Contractors provided training to workers to effectively implement project specific EMP?
2 2 2
22 Contractors has shown HSE plan and Emergency Response Procedures
1 1 1
23 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1 1 1
24 Natural areas with high elevation are normally selected as borrow areas?
2 2 2
25 Minimum damage to the agriculture land due to borrow pits on agriculture land?
NA NA NA
26 Top 300 mm are stripped and stockpiled for redressing? NA NA NA
27 Stockpiling of Material, Construction Material Management 1 1 1
28 Waste being stored temporarily on camp & sites only within the designated area
2 2 2
29 Fuel/oil storage areas are away from watercourses? 2 2 2
30 Fuel/oil storage areas are paved & ventilated 1 2 1.5
31 Fire Extinguisher is placed near Fuel Storage area 2 2 2
32 No vegetation covers aside from that required as part of construction and inside the RoW removed?
2 2 2
33 Tree cutting restricted to RoW and shoulder areas only? 2 2 2
34 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2
35 Batching Plant Material is taken from existing approved plants?
2 2 2
36 Batching Plant properly managed, no complaints 2 2 2
37 Project activities are displayed at proper locations 2 2 2
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
0
38 No complaints were made due to noise and vibration? 1 1 1
39 Fire Extinguisher are placed and checked properly 1 1 1
40 Contractors hiring of local labor? 1 1 1
41 Project site is fenced to prevent trespassing? 0 0 0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
67
Sr. Description
Week7 Monthly Avg
1 2 3 4 Mar-20
42 Generator in the construction camp properly maintained 1 1 1
43 Community consultation has been carried out for project activities/concerns?
0 1 0.5
44 Spilled oil or fuel and used clean up material being disposed of properly
1 1 1
45 Waste segregation at source 1 1 1
46 Construction & Maintenance of Walkways 0 0 0
47 Dust Generation during construction well managed 1 1 1
48 number of routes kept to a minimum 1 1 1
49 Proper sprinkling is done on regular basis? Record is available 1 1 1
50 spills and leak thoroughly cleaned 1 1 1
51 Construction machinery parked at designated areas? 1 1 1
52 Traffic issues managed well, no complaints on record 1 1 1
53 Construction activities carried out in daylight to reduce the impact of noise?
1 1 1
Total Weightage (out of 98) 76 82 0 0 79
Monthly Percentage Compliance 78% 84% 81%
Key: (Percentage)
6.1.2 Environmental Compliance Status April-2020
Sr. Description Week8
Monthly Avg
1 2 3 4 April-20
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3
2 The EMP instructions are understood? 3 3 3
3 An individual is nominated for implementation of EMP? 3 3 3
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 3
5 Assembly Point is demarcated, alarming system. 2 2 2
6 Recreational Activities for staff & labor 0 0 0
7 Contractor provided PPE to their workforce and they are being used?
1 2 1.5
8 Monthly Compliance Status is measured on the basis of monitoring data of two weeks due to lockdown/ COVID-19
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
68
8 Potable water is available to labor? 3 3 3
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 3
10 Contractors maintained Environmental Monitoring Record and submits monthly monitoring reports?
3 3 3
11 Contractors maintained Grievances Log and registered the complaints from community?
3 3 3
12 Contractors prohibited child labor and forced labor? 3 3 3
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
3 3 3
14 Septic Tank and Soak Pits are designed for treatment of effluents?
3 3 3
15 No complaint filed regarding transmission of Communicable diseases
3 3 3
Moderate Adverse Impacts ( weightage 0-2) 0
16 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2
17 No wood cutting for fuel? 2 2 2
18 LPG cylinders are provided for cooking or heating purposes?
2 2 2
19 Arrangement for proper storage and disposal for solid waste is planned?
1 2 1.5
20 Safety signs are properly displayed? 2 2 2
21 Contractors provided training to workers to effectively implement project specific EMP?
2 2 2
22 Contractors has shown HSE plan and Emergency Response Procedures
1 1 1
23 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1 2 1.5
24 Natural areas with high elevation are normally selected as borrow areas?
25 Minimum damage to the agriculture land due to borrow pits on agriculture land?
26 Stockpiling of Material, Construction Material Management
2 2 2
27 Waste being stored temporarily on camp & sites only within the designated area
2 2 2
28 Fuel/oil storage areas are away from watercourses? 2 2 2
29 Fuel/oil storage areas are paved & ventilated 1 1 1
30 Fire Extinguisher is placed near Fuel Storage area 2 2 2
31 No vegetation covers aside from that required as part of construction and inside the RoW removed?
2 2 2
32 Tree cutting restricted to RoW and shoulder areas only?
2 2 2
33 No Contamination of surface or GW by oil spillage, solid waste dumping
2 2 2
34 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
69
35 Batching Plant Material is taken from existing approved plants?
2 2 2
36 Batching Plant properly managed, no complaints 2 2 2
37 Project activities are displayed at proper locations 2 2 2
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
38 No complaints were made due to noise and vibration? 1 1 1
39 Fire Extinguisher are placed and checked properly 1 1 1
40 Contractors hiring of local labor? 1 1 1
41 Project site is fenced to prevent trespassing? 0.5 0.5 0.5
42 Generator in the construction camp properly maintained 0.5 1 0.75
43 Community consultation has been carried out for project activities/concerns?
1 1 1
44 Spilled oil or fuel and used clean up material being disposed of properly
1 1 1
45 Waste segregation at source 1 1 1
46 Construction & Maintenance of Walkways 0.5 0.5 0.5
47 Dust Generation during construction well managed and record exists
5 1 3
48 number of routes kept to a minimum 1 1 1
49 Proper sprinkling is done on regular basis? 1 1 1
50 spills and leak thoroughly cleaned 1 1 1
51 Construction machinery parked at designated areas? 1 1 1
52 Traffic issues managed well, no complaints on record 1 1 1
53 Construction activities carried out in daylight to reduce the impact of noise?
1 1 1
Total Weightage (out of 101) 92.5 92 93.25
Monthly Percentage 92% 91% 92%
6.1.3 Environmental Compliance Status May-2020
Sr No. Description Week Monthly Avg
1 2 3 4 May-20 Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3 3 3
2 The EMP instructions are understood? 3 3 2 2 2.5
3 An individual is nominated for implementation of EMP?
3 3 3 3 3
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 2 2 2.5
5 Assembly Point is demarcated, alarming system.
2 2 2 2 2
6 Recreational Activities for staff & labor 0 0 0 0 0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
70
Sr No. Description Week Monthly Avg
1 2 3 4 May-20 7 Contractor provided PPE to their workforce and
they are being used? 2 2 1 1 1.5
8 Potable water is available to labor? 3 3 3 3 3
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3 3
10 Contractors maintained Environmental Monitoring Record and submits monthly monitoring reports?
3 3 2 1 2.25
11 Contractors maintained Grievances Log and registered the complaints from community?
3 3 3 3 3
12 Contractors prohibited child labor and forced labor?
3 3 3 3 3
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
3 3 3 3 3
14 Septic Tank and Soak Pits are designed for treatment of effluents?
3 3 3 3 3
15 No complaint filed regarding transmission of Communicable diseases
3 3 3 3 3
Moderate Adverse Impacts ( weightage 0-2)
16 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2
17 No wood cutting for fuel? 2 2 2 2 2
18 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2 2
19 Arrangement for proper storage and disposal for solid waste is planned?
1 1 1 1 1
20 Safety signs are properly displayed? 2 1 2 1 1.5
21 Contractors provided training to workers to effectively implement project specific EMP?
2 2 1 2 1.75
22 Contractors has shown HSE plan and Emergency Response Procedures
1 1 1 1 1
23 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1 1 0 0 0.5
24 Natural areas with high elevation are normally selected as borrow areas?
2 2 2 2 2
25 Minimum damage to the agriculture land due to borrow pits on agriculture land?
N/A N/A N/A N/A N/A
26 Top 300 mm are stripped and stockpiled for redressing?
N/A N/A N/A N/A N/A
27 Stockpiling of Material, Construction Material Management
1 2 1 2 1.5
28 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2 2
29 Fuel/oil storage areas are away from watercourses?
2 2 2 2 2
30 Fuel/oil storage areas are paved & ventilated 2 2 2 2 2
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
71
Sr No. Description Week Monthly Avg
1 2 3 4 May-20 31 Fire Extinguisher is placed near Fuel Storage
area 2 2 2 1 1.75
32 No vegetation covers aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2
33 Tree cutting restricted to RoW and shoulder areas only?
2 2 2 2 2
34 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2
35 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2
36 Batching Plant properly managed, no complaints
2 2 2 2 2
37 Project activities are displayed at proper locations
2 2 2 1 1.75
Minor Adverse Impacts & Good Practice Measures ( weightage 0-1)
38 No complaints were made due to noise and vibration?
1 1 1 1 1
39 Fire Extinguisher are placed and checked properly
1 1 1 0 0.75
40 Contractors hiring of local labor? 1 1 1 1 1
41 Project site is fenced to prevent trespassing? 0.5 0.5 0.5 1 0.625
42 Generator in the construction camp properly maintained
1 1 1 1 1
43 Community consultation has been carried out for project activities/concerns?
0.5 0.5 0.5 0.5 0.5
44 Spilled oil or fuel and used clean up material being disposed of properly
1 1 1 0.5 0.875
45 Waste segregation at source 1 1 1 1 1
46 Construction & Maintenance of Walkways 0.5 0.5 0.5 1 0.625
47 Dust Generation during construction well managed and record exists
0.5 0.5 0.5 1 0.625
48 number of routes kept to a minimum 1 1 1 1 1
49 Water Sprinkling Record is available 1 0 0 1 0.5
50 spills and leak thoroughly cleaned 1 1 1 1 1
51 Construction machinery parked at designated areas?
1 1 1 1 1
52 Traffic issues managed well, no complaints on record
1 1 1 1 1
53 Construction activities carried out in daylight to reduce the impact of noise?
1 1 1 1 1
Total Weightage (out of 105) 90 89 83 82 86
Monthly Percentage 89% 88% 82% 81% 85%
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
72
6.1.4 Environmental Compliance Status June-2020
Sr. No
Description
Week Monthly Avg
1 2 3 4 Jun-20
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractor’s office?
3 3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3 3.0
3 An individual is nominated for implementation of EMP?
3 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 2 2 2.5
5 Assembly Point is demarcated, alarming system. 2 2 2 2 2.0
6 Recreational Activities for staff & labor 0 0 0 0 0.0
7 Contractor provided PPE to their workforce and they are being used?
2 1 2 2 1.8
8 Potable water is available to labor? 3 3 3 3 3.0
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3 3.0
10 Contractor maintained Environmental Monitoring Record and submits monthly monitoring reports?
1.5 1.5 1.5 1.5 1.5
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3 3.0
12 Contractor prohibited child labor and forced labor? 3 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
NA NA NA NA NA
14 Septic Tank and Soakage Pits are designed for treatment of effluents?
3 3 3 3 3.0
15 No complaint filed regarding transmission of communicable diseases
3 3 3 3 3.0
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic
1 1 1 1 1.0
17 Availability of an updated emergency vehicle (Ambulance)
0 0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2 2.0
21 Arrangement for proper storage and disposal for solid waste is planned?
1.5 1 2 1 1.4
22 Safety signs are properly displayed? 2 1 2 2 1.8
23 Contractor provided training to workers to effectively implement project specific EMP?
2 2 1 2 1.8
24 Contractor followed HSE plan and Emergency Response Procedures
2 2 2 2 2.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
73
25 Contractor properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1 1 1 1 1.0
26 Natural areas with high elevation are normally selected as borrow areas?
NA NA NA NA NA
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
NA NA NA NA NA
28 Top 300 mm are stripped and stockpiled for redressing?
NA NA NA NA NA
29 Stockpiling of Material, Construction Material Management
1 2 2 2 1.8
30 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses? 2 2 2 2 2.0
32 Fuel/oil storage areas are paved & ventilated 2 2 2 2 2.0
33 Fire Extinguisher is placed near Fuel Storage area 2 2 2 2 2.0
34 No vegetation covers aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only?
2 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2.0
38 Batching Plant properly managed, no complaints 2 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system
2 2 1 2 1.8
40 Project activities are displayed at proper locations 2 2 2 1 1.8
41 No complaints were made due to noise and vibration?
1 1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
1 1 1 1 1.0
43 Lamour Screening at the time of Induction 1 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 1 1 1 1.0
45 Contractors hiring of local labor? 1 1 1 1 1.0
46 Project site is fenced to prevent trespassing? 1 1 1 1 1.0
47 Generator in the construction camp properly maintained
1 1 1 1 1.0
48 Community consultation has been carried out for project activities/concerns?
1 1 1 1 1.0
49 Adequate barriers are provided around areas where hazards may exist
1 1 1 0.5 0.9
50 Spilled oil or fuel and used clean up material being disposed of properly
1 1 1 1 1.0
51 Waste segregation at source 1 1 1 1 1.0
52 Construction & Maintenance of Walkways 0.5 1 1 1 0.9
53 Dust Generation during construction well managed and record exists
0.5 1 1 1 0.9
54 Number of routes kept to a minimum 1 1 1 1 1.0
55 Water Sprinkling Record is available 1 1 1 1 1.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
74
56 Provided lighting is adequate (minimum of 100 lux) and that personnel are not working in a shadow.
1 1 1 1 1.0
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0 0.0
58 Materials will be stacked or stored in a safe manner that prevents sliding, falling or collapse
1 1 1 1 1.0
59 Spills and leak thoroughly cleaned 1 1 1 1 1.0
60 Construction machinery parked at designated areas? 1 1 1 1 1.0
61 Traffic issues managed well, no complaints on record 1 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly
1 1 1 1 1.0
63 Storage of Hazardous Material in designated areas. MSDS available
1 1 1 1 1.0
64 Social Framework Agreement is prepared and signed 1 1 1 1 1.0
65 Construction activities carried out in daylight to reduce the impact of noise?
1 1 1 1 1.0
Total Weightage (out of 117) 97 96.5 96.5 96 96.5
Monthly Percentage 83% 82% 82% 82% 82.5%
6.1.5 Environmental Compliance Status July-2020
Environmental Compliance Checklist: Package No.JIP/WKS/ICB-P1
Sr. No.
Description Week Monthly
1 2 3 4 Avg
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3 3.0
3 An individual is nominated for implementation of EMP? 3 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping.
3 3 2.5 2.5 2.8
5 Assembly Point is demarcated, alarming system. 2 2 2 2 2.0
6 Recreational activities for staff & labor. 0 0 0 0 0.0
7 Contractor provided PPE to their workforce and they are being used?
2 2 2 2 2.0
8 Potable water is available to labor? 3 3 3 3 3.0
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 2 2 2.5
10 Contractor maintained Environmental Monitoring Record and submits monthly monitoring reports?
2 1 3 3 2.3
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3 3.0
12 Contractors prohibited child labor and forced labor? 3 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
NA NA NA NA NA
14 Septic Tank and Soakage Pits are designed for treatment of effluents?
3 3 3 3 3.0
15 No complaint filed regarding transmission of communicable diseases.
3 3 3 3 3.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
75
Moderate Adverse Impacts (weightage 0-2)
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic.
2 1 2 2 1.8
17 Availability of an updated emergency vehicle (Ambulance).
0 0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2 2.0
21 Arrangement for proper storage and disposal for solid waste is planned?
1.5 1 1.5 1.5 1.4
22 Safety signs are properly displayed? 2 1 2 1.5 1.6
23 Contractor provided training to workers to effectively implement project specific EMP?
1.5 2 1 2 1.6
24 Contractors followed HSE plan and Emergency Response Procedures.
2 2 2 2 2.0
25 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1 1 1 1 1.0
26 Natural areas with high elevation are normally selected as borrow areas?
NA NA NA NA NA
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
NA NA NA NA NA
28 Top 300 mm are stripped and stockpiled for redressing? NA NA NA NA NA
29 Stockpiling of Material, Construction Material Management.
2 2 2 2 2.0
30 Waste being stored temporarily on camp & sites only within the designated area.
2 2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses? 2 2 2 2 2.0
32 Fuel/oil storage areas are paved & ventilated. 2 2 2 2 2.0
33 Fire Extinguisher is placed near Fuel Storage area. 2 2 2 2 2.0
34 No vegetation cover aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only? 2 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2.0
38 Batching Plant properly managed, no complaints. 2 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system.
1 1 1 1 1.0
40 Project activities are displayed at proper locations. 2 1 2 1 1.5
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
41 No complaints were made due to noise and vibration? 1 1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
1 1 1 1 1.0
43 Labor Screening at the time of Induction. 1 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 1 1 1 1.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
76
45 Contractors hiring of local labor? 1 1 1 1 1.0
46 Project site is fenced to prevent trespassing? 1 1 1 1 1.0
47 Generator in the construction camp properly maintained. 0.5 0.5 0.5 0.5 0.5
48 Community consultation has been carried out for project activities/concerns?
0.5 0.5 0.5 0.5 0.5
49 Adequate barriers are provided around areas where hazards may exist.
1 1 1 1 1.0
50 Spilled oil or fuel and used clean up material being disposed of properly.
1 1 0.5 1 0.9
51 Waste segregation at source. 1 1 0.5 1 0.9
52 Construction & Maintenance of Walkways. 0.5 1 1 1 0.9
53 Dust Generation during construction well managed and record exists.
0.5 0.5 0.5 0.5 0.5
54 Number of routes kept to a minimum. 1 1 1 1 1.0
55 Water Sprinkling Record is available. 0.5 0.5 0.5 0.5 0.5
56 Provided lighting is adequate (minimum of 100 lux) and that personnel are not working in a shadow.
1 1 1 1 1.0
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0 0.0
58 Materials will be stacked or stored in a safe manner that prevents sliding, falling or collapse.
1 1 1 1 1.0
59 Spills and leak thoroughly cleaned. 1 1 1 1 1.0
60 Construction machinery parked at designated areas? 1 1 1 1 1.0
61 Traffic issues managed well, no complaints on record. 1 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly. 1 1 1 1 1.0
63 Storage of Hazardous Material in designated areas. MSDS available.
1 1 1 1 1.0
64 Social Framework Agreement (SFA) is prepared and signed.
0 0 0 0 0.0
65 Construction activities carried out in daylight to reduce the impact of noise.
1 1 1 1 1.0
Total Weightage (out of 111) 95.5 92 94 94.5 94.0
Monthly Percentage 86% 83% 85% 85% 84.7%
6.1.6 Environmental Compliance Status Aug-2020
Sr. No.
Description Week
Monthly Avg
1 2 3 4 Aug-20
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
Eid
Ho
lydays
3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3.0
3 An individual is nominated for implementation of EMP? 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 3 3.0
5 Assembly Point is demarcated, alarming system. 1.5 1.5 1.5 1.5
6 Workforce use PPE at site? 0.5 0.75 0.5 0.6
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
77
7 Contractor provided PPE to their workforce? 2 2.75 2.5 2.4
8 Potable water is available to labor? 3 3 3 3.0
9 Medical facilities, first aid kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3.0
10 Contractor maintained environmental monitoring record and submits monthly monitoring reports?
1 1 1 1.0
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3.0
12 Contractors prohibited child labor and forced labor? 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
0 0 0 0.0
14 Septic Tank and Soak Pits are designed for treatment of effluents?
3 3 3 3.0
15 No complaint filed regarding transmission of communicable diseases
3 3 3 3.0
Moderate Adverse Impacts (weightage 0-2)
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic
Eid
Ho
lydays
2 2 2 2.0
17 Availability of an updated emergency vehicle (Ambulance)
0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2.0
21 Arrangement for proper storage and disposal for solid waste is planned?
2 2 2 2.0
22 Safety signs are properly displayed? 1 1.5 1.5 1.3
23 Contractor provided training to workers to effectively implement project specific EMP?
2 2 2 2.0
24 Contractors followed HSE plan and Emergency Response Procedures
2 2 2 2.0
25 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
0 0 0 0.0
26 Natural areas with high elevation are normally selected as borrow areas?
2 2 2 2.0
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
N/A N/A N/A 0.0
28 Top 300 mm are stripped and stockpiled for redressing? N/A N/A N/A 0.0
29 Stockpiling of Material, Construction Material Management
2 2 2 2.0
30 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses? 2 2 2 2.0
32 Fuel/oil storage areas are paved & ventilated 2 2 2 2.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
78
33 Fire Extinguisher is placed near Fuel Storage area 2 2 2 2.0
34 No vegetation cover aside from that required as part of construction and inside the RoW removed?
2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only? 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2.0
38 Batching Plant properly managed, no complaints 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system
1 1.5 1 1.2
40 Project activities are displayed at proper locations 2 2 2 2.0
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
41 No complaints were made due to noise and vibration?
Eid
Ho
lydays
1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
0.5 0 0.5 0.3
43 Labour Screening at the time of Induction 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 1 1 1.0
45 Contractors hiring of local labor? 1 1 1 1.0
46 Project site is fenced to prevent trespassing? 1 1 1 1.0
47 Generator in the construction camp properly maintained 1 1 1 1.0
48 Community consultation has been carried out for project activities/concerns?
1 1 1 1.0
49 Adequate barriers are provided around areas where hazards may exist
1 1 1 1.0
50 Spilled oil or fuel and used clean up material being disposed of properly
1 1 1 1.0
51 Waste segregation at source 1 1 1 1.0
52 Construction & Maintenance of Walkways 1 1 1 1.0
53 Dust Generation during construction well managed and record exists
1 1 1 1.0
54 Number of routes kept to a minimum 1 1 1 1.0
55 Water Sprinkling Record is available 1 1 1 1.0
56 Provided lighting is adequate (minimum of 100 lux) and that personnel are not working in a shadow.
1 1 1 1.0
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0.0
58 Materials will be stacked or stored in a safe manner that prevents sliding, falling or collapse.
1 1 1 1.0
59 Spills and leak thoroughly cleaned 1 1 1 1.0
60 Construction machinery parked at designated areas? 1 1 1 1.0
61 Traffic issues managed well, no complaints on record 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly 1 1 1 1.0
63 Storage of Hazardous Material in designated areas. MSDS available
1 1 1 1.0
64 Social Framework Agreement is prepared and signed 1 1 1 1.0
65 Construction activities carried out in daylight to reduce the impact of noise
1 1 1 1.0
Total Weightage (out of 116) 98.5 100 99.5 99.3
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
79
Monthly Percentage 85% 86% 86% 85.6%
6.1.7 Environmental Compliance Status Sep-2020
Sr. No.
Description
Week Monthly Avg
1 2 3 4 Sep-20
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3 3.0
3 An individual is nominated for implementation of EMP? 3 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 3 3 3.0
5 Assembly Point is demarcated, alarming system. 2 2 2 2 2.0
6 Workforce use PPE at site? 2 1.75 1.5 1.8 1.8
7 Contractor provided PPE to their workforce? 3 3 3 3 3.0
8 Potable water is available to labor? 3 3 3 3 3.0
9 Medical facilities, first aid kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3 3.0
10 Contractor maintained environmental monitoring record and submits monthly monitoring reports?
3 3 3 3 3.0
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3 3.0
12 Contractor prohibited child labor and forced labor? 3 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
0 0 0 0 0.0
14 Septic Tank and Soakage Pits are designed for treatment of effluents?
3 3 3 3 3.0
15 No complaint filed regarding transmission of communicable diseases
3 3 3 3 3.0
Moderate Adverse Impacts (weightage 0-2)
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic
1.5 2 1.75 1 1.6
17 Availability of an updated emergency vehicle (Ambulance)
0 0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 1 2 1.8
21 Arrangement for proper storage and disposal for solid waste is planned?
2 2 2 2 2.0
22 Safety signs are properly displayed? 2 2 1 2 1.8
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
80
23 Contractor provided training to workers to effectively implement project specific EMP?
2 2 2 2 2.0
24 Contractor followed HSE plan and Emergency Response Procedures
2 2 2 2 2.0
25 Contractor properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1 1 1 1 1.0
26 Natural areas with high elevation are normally selected as borrow areas?
2 2 2 2 2.0
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
N/A N/A N/A N/A 0.0
28 Top 300 mm are stripped and stockpiled for redressing? N/A N/A N/A N/A 0.0
29 Stockpiling of Material, Construction Material Management
2 2 2 2 2.0
30 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses? 2 2 2 2 2.0
32 Fuel/oil storage areas are paved & ventilated 2 2 2 2 2.0
33 Fire Extinguisher is placed near Fuel Storage area 2 2 2 2 2.0
34 No vegetation cover aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only? 2 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2.0
38 Batching Plant properly managed, no complaints 2 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system
0 0 0 0 0.0
40 Project activities are displayed at proper locations 2 2 2 2 2.0
Minor Adverse Impacts & Good Practice Measures ( weightage 0-1)
41 No complaints were made due to noise and vibration? 1 1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
1 1 1 1 1.0
43 Labour Screening at the time of Induction 1 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 1 1 1 1.0
45 Contractors hiring of local labor? 1 1 1 1 1.0
46 Camp site is fenced to prevent trespassing? 1 1 1 1 1.0
47 Generator in the construction camp properly maintained 1 1 1 1 1.0
48 Community consultation has been carried out for project activities/concerns?
1 1 1 1 1.0
49 Adequate barriers are provided around areas where hazards may exist
1 1 1 1 1.0
50 Spilled oil or fuel and used clean up material being disposed of properly
1 1 1 1 1.0
51 Waste segregation at source 1 1 1 1 1.0
52 Construction & Maintenance of Walkways 1 1 1 1 1.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
81
53 Dust Generation during construction well managed and record exists
1 1 1 1 1.0
54 Number of routes kept to a minimum 1 1 1 1 1.0
55 Water Sprinkling Record is available 0.5 0.5 0.5 0.5 0.5
56 Provided lighting is adequate (minimum of 100 lux) and that personnel are not working in a shadow.
1 1 1 1 1.0
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0 0.0
58 Materials will be stacked or stored in a safe manner that prevents sliding, falling or collapse
1 1 0.5 1 0.9
59 Spills and leak thoroughly cleaned 1 0.5 1 1 0.9
60 Construction machinery parked at designated areas? 1 1 1 1 1.0
61 Traffic issues managed well, no complaints on record 1 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly 0.5 1 0.5 1 0.8
63 Storage of Hazardous Material in designated areas. MSDS available
1 1 1 1 1.0
64 Social Framework Agreement is prepared and signed 1 1 1 1 1.0
65 Construction activities carried out in daylight to reduce the impact of noise
1 1 1 1 1.0
Total Weightage (out of 116) 104 104 101 103 102.8
Monthly Percentage 89% 89% 87% 89% 88.6%
6.1.8 Environmental Compliance Status October-2020
Sr. No.
Description Week Monthly Avg
1 2 3 4 October,2020
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3 3.0
3 An individual is nominated for implementation of EMP?
3 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 2.5 2.25 2.5 2.6
5 Assembly Point is demarcated, alarming system. 2 2 2 2 2.0
6 Workforce use PPE at site? 1.75 2 1.75 2.25 1.9
7 Contractor provided PPE to their workforce? 2.75 2.5 2.75 2.75 2.7
8 Potable water is available to labor? 3 3 3 3 3.0
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3 3.0
10 Contractor maintained Environmental Monitoring Record and submits monthly monitoring reports?
3 3 3 3 3.0
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3 3.0
12 Contractors prohibited child labor and forced labor? 3 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
2 2 2 2 2.0
14 Septic Tank and Soak Pits are designed for treatment of effluents?
3 3 3 3 3.0
15 No complaint filed regarding transmission of communicable diseases
3 3 3 3 3.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
82
Moderate Adverse Impacts ( weightage 0-2)
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic
2 2 2 2 2.0
17 Availability of an updated emergency vehicle (Ambulance)
0 0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2 2.0
21 Arrangement for proper storage and disposal for solid waste is planned?
1.5 1.25 1.25 2 1.5
22 Safety signs are properly displayed? 2 1.5 2 1.75 1.8
23 Contractor provided training to workers to effectively implement project specific EMP?
2 2 2 2 2.0
24 Contractors followed HSE plan and Emergency Response Procedures
1.5 1.5 1.5 1.5 1.5
25 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1.5 1.5 1.5 1.5 1.5
26 Natural areas with high elevation are normally selected as borrow areas?
2 2 2 2 2.0
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
N/A N/A N/A N/A 0.0
28 Top 300 mm are stripped and stockpiled for redressing?
N/A N/A N/A N/A 0.0
29 Stockpiling of Material, Construction Material Management
2 2 2 2 2.0
30 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses?
2 2 2 2 2.0
32 Fuel/oil storage areas are paved & ventilated 2 2 2 2 2.0
33 Fire Extinguisher is placed near Fuel Storage area 2 2 2 2 2.0
34 No vegetation cover aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only?
2 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2.0
38 Batching Plant properly managed, no complaints 2 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system
1 1 1 1 1.0
40 Project activities are displayed at proper locations 1.25 1 1.5 1.5 1.3
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
41 No complaints were made due to noise and vibration?
1 1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
1 1 1 1 1.0
43 Labor Screening at the time of Induction 1 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 1 1 1 1.0
45 Contractors hiring of local labor? 1 1 1 1 1.0
46 Project site is fenced to prevent trespassing? 1 1 1 1 1.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
83
47 Generator in the construction camp properly maintained
0.75 0.75 0.75 0.75 0.8
48 Community consultation has been carried out for project activities/concerns?
1 1 1 1 1.0
49 Adequate barriers are provided around areas where hazards may exist
1 0.75 1 0.5 0.8
50 Spilled oil or fuel and used clean up material being disposed of properly
1 0.5 0.5 0.75 0.7
51 Waste segregation at source 1 1 1 1 1.0
52 Construction & Maintenance of Walkways 1 1 1 1 1.0
53 Dust Generation during construction well managed and record exists
0.5 0.75 0.5 0.75 0.6
54 Number of routes kept to a minimum 1 1 1 1 1.0
55 Water Sprinkling Record is available 1 1 1 1 1.0
56 Provided lighting is adequate (minimum of 100 lux) and that personnel are not working in a shadow.
0.75 1 0.75 0.5 0.8
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0 0.0
58 Materials will be stacked or stored in a safe manner that prevents sliding, falling or collapse
1 1 1 1 1.0
59 Spills and leak thoroughly cleaned 0.75 0.5 0.5 0.75 0.6
60 Construction machinery parked at designated areas?
1 1 1 1 1.0
61 Traffic issues managed well, no complaints on record
1 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly
1 1 1 1 1.0
63 Storage of Hazardous Material in designated areas. MSDS available
1 1 1 1 1.0
64 Social Framework Agreement is prepared and signed
1 1 1 1 1.0
65 Construction activities carried out in daylight to reduce the impact of noise
1 1 1 1 1.0
Total Weightage (out of 116) 105 103 104 105 104.1
Monthly Percentage 91% 89% 89% 90% 89.7%
6.1.9 Environmental Compliance Status November-2020
Sr. No.
Description Week Monthly
Avg 1 2 3 4
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3 3.0
3 An individual is nominated for implementation of EMP? 3 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 3 3 3.0
5 Assembly Point is demarcated, alarming system. 2 2 2 2 2.0
6 Workforce use PPE at site? 1.3 1.5 1.5 2 1.6
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
84
Sr. No.
Description Week Monthly
Avg 1 2 3 4
7 Contractor provided PPE to their workforce? 2 2.5 2,5 2.5 1.8
8 Potable water is available to labor? 3 3 3 3 3.0
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3 3.0
10 Contractor maintained Environmental Monitoring Record and submits monthly monitoring reports?
3 3 3 3 3.0
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3 3.0
12 Contractors prohibited child labor and forced labor? 3 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
3 3 3 3 3.0
14 Septic Tank and Soak Pits are designed for treatment of effluents?
3 3 3 3 3.0
15 No complaint filed regarding transmission of communicable diseases
3 3 3 3 3.0
Moderate Adverse Impacts (weightage 0-2)
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic
2 1.5 2 2 1.9
17 Availability of an updated emergency vehicle (Ambulance)
0 0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2 2.0
21 Arrangement for proper storage and disposal for solid waste is planned?
1.5 1.25 1.25 1.5 1.4
22 Safety signs are properly displayed? 2 2 2 1.5 1.9
23 Contractor provided training to workers to effectively implement project specific EMP?
2 2 2 2 2.0
24 Contractors followed HSE plan and Emergency Response Procedures
1.75 1.75 1.75 1.75 1.8
25 Contractors properly disposes debris materials in approved barren land/ TMA facilities preferably recycling, reuse process?
1.5 1.5 1.5 1.5 1.5
26 Natural areas with high elevation are normally selected as borrow areas?
2 2 2 2 2.0
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
N/A N/A N/A N/A N/A
28 Top 300 mm are stripped and stockpiled for redressing?
N/A N/A N/A N/A N/A
29 Stockpiling of Material, Construction Material Management
2 2 2 2 2.0
30 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses? 2 2 2 2 2.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
85
Sr. No.
Description Week Monthly
Avg 1 2 3 4
32 Fuel/oil storage areas are paved & ventilated 2 2 2 2 2.0
33 Fire Extinguisher is placed near Fuel Storage area 2 2 2 2 2.0
34 No vegetation covers aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only?
2 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2.0
38 Batching Plant properly managed, no complaints 2 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system
1 1 1 1 1.0
40 Project activities are displayed at proper locations 1.5 1.5 1.5 1.5 1.5
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
41 No complaints were made due to noise and vibration? 1 1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
1 1 1 1 1.0
43 Labor Screening at the time of Induction 1 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 0.5 1 1 0.9
45 Contractors hiring of local labor? 1 1 1 1 1.0
46 Project site is fenced to prevent trespassing? 1 1 1 1 1.0
47 Generator in the construction camp properly maintained
0.75 0.5 0.5 0.75 0.6
48 Community consultation has been carried out for project activities/concerns?
1 1 1 1 1.0
49 Adequate barriers are provided around areas where hazards may exist
1 0.5 1 0.5 0.8
50 Spilled oil or fuel and used clean up material being disposed of properly
0.75 0.5 0.75 0.5 0.6
51 Waste segregation at source 1 0.5 0.5 1 0.8
52 Construction & Maintenance of Walkways 1 1 1 1 1.0
53 Dust Generation during construction well managed and record exists
1 1 0.75 0.75 0.9
54 Number of routes kept to a minimum 1 1 1 1 1.0
55 Water Sprinkling Record is available 1 1 1 1 1.0
56 Provided lighting is adequate (minimum of 100 lux) and that personnelare not working in a shadow.
0.75 1 1 0.5 0.8
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0 0.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
86
Sr. No.
Description Week Monthly
Avg 1 2 3 4
58 Materials will be stacked or stored in a safe manner that prevents sliding,falling or collapse
1 0.5 1 1 0.9
59 Spills and leak thoroughly cleaned 0.5 1 1 1 0.9
60 Construction machinery parked at designated areas? 1 1 1 1 1.0
61 Traffic issues managed well, no complaints on record 1 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly 1 1 1 1 1.0
63 Storage of Hazardous Material in designated areas. MSDS available
1 1 1 1 1.0
64 Social Framework Agreement is prepared and signed 1 1 1 1 1.0
65 Construction activities carried out in daylight to reduce the impact of noise
1 1 1 1 1.0
Total Weightage (out of 116) 105 104 103 105 104.3
Monthly Percentage 91% 89% 89% 91% 89.9%
6.1.10 Environmental Compliance Status December-2020
Sr. No.
Description Week Monthly
1 2 3 4 Average
Major Adverse Impacts (weightage 0-3)
1 Copy of the Site specific EMP is provided at the camp site/contractors office?
3 3 3 3 3.0
2 The EMP instructions are understood? 3 3 3 3 3.0
3 An individual is nominated for implementation of EMP? 3 3 3 3 3.0
4 Camp Management, Health & Hygiene/ Heating, Cooling, Lighting and Housekeeping
3 3 3 3 3.0
5 Assembly Point is demarcated, alarming system. 2.5 2.5 2.5 2.5 2.5
6 Workforce use PPE at site? 1.3 1.5 1.5 1.5 1.5
7 Contractor provided PPE to their workforce? 2 2 2 2 2.0
8 Potable water is available to labor? 3 3 3 3 3.0
9 Medical Facilities, First Aid Kit is provided at camp and individual nominated for addressing emergency?
3 3 3 3 3.0
10 Contractor maintained Environmental Monitoring Record and submits monthly monitoring reports?
3 3 3 3 3.0
11 Contractor maintained Grievances Log and registered the complaints from community?
3 3 3 3 3.0
12 Contractors prohibited child labor and forced labor? 3 3 3 3 3.0
13 Borrow area is leased and the landowner is compensated as per a lease agreement?
3 3 3 3 3.0
14 Septic Tank and Soak Pits are designed for treatment of effluents?
3 3 3 3 3.0
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
87
15 No complaint filed regarding transmission of communicable diseases
3 3 3 3 3.0
Moderate Adverse Impacts ( weightage 0-2)
16 Provision of necessary welfare and hygiene requirements for the prevention of epidemic
1.5 1.5 1.5 1.5 1.5
17 Availability of an updated emergency vehicle (Ambulance)
0 0 0 0 0.0
18 Site selected for camp is 500 m from the human settlements and wildlife habitats?
2 2 2 2 2.0
19 No wood cutting for fuel? 2 2 2 2 2.0
20 LPG cylinders are provided for cooking or heating purposes?
2 2 2 2 2.0
21 Arrangement for proper storage and disposal for solid waste is planned?
1.5 1.25 1.25 1.5 1.4
22 Safety signs are properly displayed? 1.5 1.5 1.5 1.5 1.5
23 Contractor provided training to workers to effectively implement project specific EMP?
2 2 2 2 2.0
24 Contractors followed HSE plan and Emergency Response Procedures
1.75 1.75 1.75 1.75 1.8
25 Contractors properly disposes debris materials, preferably recycling, reuse process?
1.5 1.5 1.5 1.5 1.5
26 Natural areas with high elevation are normally selected as borrow areas?
2 2 2 2 2.0
27 Minimum damage to the agriculture land due to borrow pits on agriculture land?
N/A N/A N/A N/A 0.0
28 Top 300 mm are stripped and stockpiled for redressing?
N/A N/A N/A N/A 0.0
29 Stockpiling of Material, Construction Material Management
2 2 2 2 2.0
30 Waste being stored temporarily on camp & sites only within the designated area
2 2 2 2 2.0
31 Fuel/oil storage areas are away from watercourses? 2 2 2 2 2.0
32 Fuel/oil storage areas are paved & ventilated 2 2 2 2 2.0
33 Fire Extinguisher is placed near Fuel Storage area 2 2 2 2 2.0
34 No vegetation covers aside from that required as part of construction and inside the RoW removed?
2 2 2 2 2.0
35 Tree cutting restricted to RoW and shoulder areas only?
2 2 2 2 2.0
36 No damage reported to public services like electric, water, gas, sewer or telephone lines?
2 2 2 2 2.0
37 Batching Plant Material is taken from existing approved plants?
2 2 2 2 2.0
38 Batching Plant properly managed, no complaints 2 2 2 2 2.0
39 Maintenance of Roads, Hospitals, Buildings. Sewage facilities, Electric and water supply system
1 1 1 1.5 1.1
40 Project activities are displayed at proper locations 1 1 1 1 1.0
Minor Adverse Impacts & Good Practice Measures (weightage 0-1)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
88
41 No complaints were made due to noise and vibration? 1 1 1 1 1.0
42 Contractor conduct Information, Education and Communication (IEC) campaign
1 1 1 1 1.0
43 Labour Screening at the time of Induction 1 1 1 1 1.0
44 Fire Extinguisher are placed and checked properly 1 1 1 1 1.0
45 Contractors hiring of local labor? 1 1 1 1 1.0
46 Project site is fenced to prevent trespassing? 1 1 1 1 1.0
47 Generator in the construction camp properly maintained
0.75 0.5 0.5 0.75 0.6
48 Community consultation has been carried out for project activities/concerns?
1 1 1 1 1.0
49 Adequate barriers are provided around areas where hazards may exist
1 0.5 1 0.5 0.8
50 Spilled oil or fuel and used clean up material being disposed of properly
0.75 0.5 0.75 0.5 0.6
51 Waste segregation at source 0.5 0.75 0.75 0.5 0.6
52 Construction & Maintenance of Walkways 1 1 1 1 1.0
53 Dust Generation during construction well managed and record exists
0.75 0.75 0.75 0.75 0.8
54 Number of routes kept to a minimum 1 1 1 1 1.0
55 Water Sprinkling Record is available 1 1 1 1 1.0
56 Provided lighting is adequate (minimum of 100 lux) and that personnel are not working in a shadow.
1 0.75 1 1 0.9
57 Photographic Record of Roads and agricultural fields is being maintained.
0 0 0 0 0.0
58 Materials will be stacked or stored in a safe manner that prevents sliding, falling or collapse
0.5 0.5 0.5 0.5 0.5
59 Spills and leak thoroughly cleaned 1 0.5 0.5 1 0.8
60 Construction machinery parked at designated areas? 1 1 1 1 1.0
61 Traffic issues managed well, no complaints on record 1 1 1 1 1.0
62 Daily, Weekly & Monthly Checklists are filled regularly 1 1 1 1 1.0
63 Storage of Hazordous Materal in designated areas. MSDS available
1 1 1 1 1.0
64 Social Framwork Agreement is prepared and signed 1 1 1 1 1.0
65 Construction activities carried out in daylight to reduce the impact of noise
1 1 1 1 1.0
Total Weightage (out of 116) 104 102 103 104 103.3
Monthly Percentage 89% 88% 89% 89% 89.0%
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
89
6.2 Trends in EMP Compliance
6.2.1 Trends in Conformance Level
102. Exhibit 36 shows overall compliance status with positive trend, which
indicates improvement in overall EMP implementation at site.
Overall Compliance Status
6.2.2 Environmental Conformance Level
103. Non-conformances are defined as a failure to conform, or non-fulfilment
of specified requirements. The details of major, moderate & minor were
calculated on the basis of systematic and quantitative checklists (6.1.1-
6.1.10), is shown in Exhibits Below.
Details of Project Conformance Level
Month Conformance Non Conformance %
2020 % Total Major Moderate Minor
Mar 80.6 19.4 11.3 5.1 3.0
April 92.0 8.0 2.6 2.6 2.8
May 85.1 14.9 7.1 3.0 4.8
June 82.5 17.5 9.8 3.1 4.6
July 84.7 15.3 6.1 4.1 5.1
Aug 85.6 14.4 5.4 3.6 5.8
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
90
Sep 88.6 11.4 3.8 3.2 4.4
Oct 89.7 10.3 2.3 4.2 3.8
Nov 89.9 10.1 2.3 4.1 3.7
Dec 89.0 11.0 2.5 4.5 4.0
Total 86.77 13.23 5.32 3.75 4.2
Project Conformance and Non-Conformance Level March-December 2020
104. EMP Compliance indicate the project level major conformances
decreased with passage of time. This slight decrease in major
nonconformances is associated with the completion and updation of
SSEMP documents and their effective implementation. It is also noted
that minor nonconformances of the project increased minutely in a few
months from May 2020 to Aug 2020, which was due to lack of good
practice measures and poor house keeping with the increase of work
sites and labor.
Trends in Non-Conformances of EMP Compliance
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
91
0.0
2.0
4.0
6.0
8.0
10.0
12.0
Mar April May June July Aug Sep Oct Nov Dec
% N
on
Co
nfo
rman
ce
Non Conformance % Major Non Conformance % Moderate
Non Conformance % Minor Linear (Non Conformance % Major )
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
92
7 FUNCTIONING OF THE SSEMP
7.1 SSEMP Controls
105. Contractor was required to prepare Site Specific Environmental
Monitoring Plan including borrow area management plan, traffic
managed plan health environment and safety plan and waste
management plan. All the plans were formulated under supervision of
PIC and close coordination of PMO and were updated after the COVID-
19 pandemic in the country.
106. As per as functioning and control of the SSEMP is concerned, and
Environmental and Social Cell comprising following staff was designated
in EMP for implementation.
a. ESMMC Representative nominated by EA (PID)
b. PIC’s Environmentalists
c. Contractor’s Environmentalist and HSE Officer & Allied Staff
107. The daily monitoring and daily checklists are being filled by Contractor’s
Environmentalist with online coordination with PIC Sr. Environmentalist.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
93
8 GOOD PRACTICE AND OPPORTUNITY FOR IMPROVEMENT
8.1 Good Practice
108. At construction sites, accidents have the potential to be life threatening.
With every new story about environmental disasters and trapped
laborer’s, construction sites become less and less appealing. Regarded
as one of the most dangerous professions, construction work on the job
site can be considered anything but entirely safe. Obviously, the
employers do need to mitigate safety hazards to construction workers,
but the workers need to keep in mind a lot of precautions themselves
when working in such hazardous conditions.
109. Thus, construction sites must be strived to safeguard their employees if
not for the ethical reasons, then for the economic ones and good practice
measures enlisted below are effective to increase overall conformance
level of the JIP.
8.1.1 Awareness
110. Regular awareness and trainings including tool box talk must be
continued. Before any worker — no matter his role or experience level
— can set foot on a construction site, he must be fully recognizant of the
possible hazards. Ignorant workers are perhaps the biggest dangers at
any construction sight, as their unknowing mistakes put everyone else
at risk. Understanding of perils at hand and sustaining a perpetual state
of alertness is perhaps the number-one best way to prevent accidents
for which awareness campaign and risk assessment of each activity is
done before start of the new activity for the staff.
8.1.2 Training
111. Though most of a construction worker’s skills can be gained on the job,
safety is one skill set that is best learned before works enter the
construction site. Regular trainings are held on all sites for the labourers
on standard safety and security practices. Experienced workers were
also provided with same trainings to refresh their knowledge of standard
safety by attending regular training sessions throughout the project
cycle.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
94
8.1.3 Housekeeping
112. The contractors` staff was persuaded to maintain good house-keeping
and waste generation/ management with the increase in labor and start
of working at new locations.
8.1.4 Communication
113. Accidents are more likely to occur when workers are unsure what to
expect. Direct communication regarding the day’s goals and activities
resulted in cut down on surprises that could cause bodily harm.
Construction workers and supervisors are equipped and trained for fast
and efficient communication among team members.
8.1.5 Supervision
114. Ideally, construction workers would fully understand the ramifications of
inadequate safety precautions and thus act in a manner to ensure site-
wide well-being — but this is not a perfect world. So, every site must
have a strong supervisor who is willing and capable of enforcing safety
standards with no exceptions. Such supervision is provided in almost all
the sites (giving the best conformance level of +90%).
8.2 Opportunities for Improvement
8.2.1 Documentation
115. It is noticed, although the most of the environmental issues are being
catered but documentation and record keeping is not up to the mark,
especially daily tool box talks and monitoring checklists are not being
maintained as per standards. Daily Checklists are being filled online with
the help of real time photographs and online communications, while it is
also noted that all tool box talks are not being documented. Documenting
all work in the field will make issues easier than ever before to mitigate.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
95
9 SUMMARY AND RECOMMENDATIONS
116. The contractor has been directed to prepare SSEMP before execution
of the project to make sure environmentally friendly construction
followed be regular noise, air and water quality monitoring and submit
essential reports.
117. The environmental monitoring was carried out by PIC to assess actual
nature and extent of key impacts and the effectiveness of mitigation and
enhancement measures outlined in the EMP and SSEMP. Mitigation
measures are considered so that the projects are designed, constructed,
and operated in compliance with applicable national and provincial laws
and regulations and meets the requirements of ADB SPS (2009). Further
field inspections are undertaken by the Environmentalists of PIC & PMO.
All the observations in the form of monitoring report will be submitted to
PMO on monthly basis.
118. Mutually agreed Corrective Action Plan is also devised and
communicated to the contractors. PIC has advised the contractor to
address noncompliance as per agreed Corrective Action Plan.
119. During December, 2020, Ambient air quality was monitored at three
selected locations to conduct a comparison of pollutants level with
respective standards. Graphical representation of above mentioned
three sites results show that the levels of parameters (CO, NO, NO2,
SO2, CO2, PM2.5, TVOC, O3 and lead) were within the limits of their
respective standards.PM values at Borrow area and Rasul Barrage were
relatively higher than the other 3rd point. Main reason for these higher
values is that, this point is established at main road where flow of heavy
traffic and public transport is regular at the road which causes the
maximum values of PM. As a result, PM values are a little higher than
the other sites. Water analysis results show that drinking water quality at
GRC Camp site are within the limit of PEQS standards. As surface water
quality at downstream of Rasul Barrage results shows that the physical
and chemical parameters are within the limits of FAO and NEQS while
microbial parameters are out of the limit. In waste water analysis at GRC
soakage pit, all waste water analysis parameters are within the limits of
PEQS.
120. Second Water, Wastewater and Ambient Air Quality Monitoring was
completed from 23rd December to 24th December 2020. The observed
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
96
concentrations for Ambient air quality parameters water and wastewater
quality are compared with the Punjab Environmental Quality Standards
(PEQS) and found within the limits.
121. EMP Compliance level is being calculated with the help of quantitative
weekly and monthly checklist. The overall compliance level was found
good and statistics indicate the project level major conformances
decreased with passage of time. This slight decrease in major
nonconformances is associated with the completion and updation of
SSEMP documents and their effective implementation. It is also noted
that minor nonconformances of the project increased minutely in a few
months from May 2020 to Aug 2020, which was due to lack of good
practice measures and poor house keeping with the increase of work
sites and labor.
122. Additional field staff was nominated by Contractors and trainings on
housekeeping including waste management and good practice measure
was provided to all labour and staff, which results in decrease in minor
non conformance levels, as well in later months from Sep to Dec 2020.
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
PHOTOLOG
Construction Works at Site
Training of Staff at Field
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Construction Works with PPEs
Construction Works
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Another Picture of Workers on Job
Site Inspection
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
A view of Activities
Another View of Construction Activities
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Plaster of Canal Lining
Diversion Route
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Animal Trespassing in ROW
Govt. Model Girls Primary School: Buildings Demolished
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Construction of New Girls Primary School
Construction of New Girls Primary School
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Demolition of Boys Primary School
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Demolition Waste Segregated for Sale in Market
Segregation and Transportation of Waste without PPEs
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Land Clearing and Waste Segregation-Boys School
Construction of Boundary Wall of Boys School
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Govt. Boys Primary School, Transitional/Temporary Building
PMO, PIC Environmentalists, Contractor and Boys School Teachers
Baseline Environmental Monitoring with all COVID-19 SOPs
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Toolbox Talks with all COVID-19 SOPs
Labor travelling and Office Working following all Precautionary Measures for COVID-19
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Workers Induction on Earth work with Environmental Team combating COVID-19
COVID-19 precautionary measures dedicated to Work
Training of Supervisors and HSE inspectors on COVID-19 Pandemic
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
COVID-19 Safety Measures for Store (Urdu Language)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
COVID-19 Safety Precautions for Camp and Offices (Urdu Language)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
COVID-19 Precautionary Measures for Laboratory (Urdu Language)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
COVID-19 Precautionary Instructions for Mess (Urdu Language)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Disinfecting Gates and temperature checking using Infrared Thermometer for Labor
Camp
Temperature Checking of Visitors before entering Camp
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Isolation Room for COVID-19 Suspected Patient
Disinfection of Camp Offices, etc
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Sample Daily Temperature Sheet of Emplyees
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Sample Temperature Record and Screening of symptoms with travel history on arrival after Eid Holidays
following COVID-19 SOPs. (Selected Sample Sheet, from Monitoring Report)
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Copy of Check Request before Land Clearing
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Land fill site for Solid Waste Management
Solid Waste Management; Land filling
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
MOU with RHC Jalalpur for Medical Waster Management
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
Annex-A Sample GRM Record
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
127
Annex- B Social Framework Agreement Malikpur
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
128
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
129
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
130
Annex-C Social Framework Agreement at Mouza
Shah Kamir
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
131
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
132
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
133
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
134
Annex-D Sample Daily, Weekly & Monthly
Checklists
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
135
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
136
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
137
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
138
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
139
JALALPUR IRRIGATION PROJECT
Semi Annual Environmental Monitoring Report #01
S A E M R - M a r c h - D e c e m b e r 2 0 2 0
JIPIC
140
Annex-E Urdu Brochure for Contractor
Page 141 of 155
Page 142 of 155
Page 143 of 155
Page 144 of 155
Page 145 of 155
Page 146 of 155
Page 147 of 155
Page 148 of 155
Page 149 of 155