Environmental Monitoring Report Semiannual Report March 2015 PRC: Guiyang Integrated Water Resources Management (Sector) Project Internal Environmental Monitoring Report No. 4 Prepared by Artelia International for the Guiyang Municipal Government and the Asian Development Bank.

Transcript of Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED...

Page 1: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

Environmental Monitoring Report Semiannual Report March 2015

PRC: Guiyang Integrated Water Resources Management (Sector) Project Internal Environmental Monitoring Report No. 4 Prepared by Artelia International for the Guiyang Municipal Government and the Asian Development Bank.

Page 2: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

PEOPLE’S REPUBLIC OF CHINA

ASIAN DEVELOPMENT BANK

GUIYANG INTEGRATED WATER RESOURCES

MANAGEMENT PROJECT

ADB LOAN PROJECT 2573-PRC

SEMIANNUAL EMP IMPLEMENTATION

PROGRESS REPORT NO.4

(JULY TO DECEMBER OF 2014)

IDENTIFICATION NO.: CN1004 EMP04

MARCH 2015

Page 4: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

PEOPLE’S REPUBLIC OF CHINA

GUIYANG MUNICIPAL GOVERNMENT ASIAN DEVELOPMENT BANK

GUIYANG INTEGRATED WATER

RESOURCES MANAGEMENT

PROJECT

SEMIANNUAL EMP IMPLEMENTATION

PROGRESS REPORT NO.4

IDENTIFICATION N° : CN1004EMP04 DATE: MARCH 19, 2015

This document has been produced by ARTELIA Consultants as part of Guiyang Integrated Water Resources Management Project to Guiyang Municipal Government (Job Number CN1004)

This document has been prepared by the project team under the supervision of the Project Director following the Quality Assurance Procedures of ARTELIA in compliance with ISO9001.

INDEX PURPOSE OF MODIFICATION DATE AUTHOR CHECKED BY APPROVED BY

A First Issue 2015-3-19 HXD LWS LWS

INDEX DISTRIBUTION LIST CONTACT ADDRESS

1 Guiyang ADB-Loan PMO

(Ms. MENG Jianjian)

Guiyang ADB-Loan PMO, 24th floor, Jinbei Mansion, No.25-16, Jinyang New District, Guiyang, Guizhou Province, P. R. China

2

Page 5: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE I 2015- 3

TABLE OF CONTENTS

TABLE OF CONTENTS................................................................................................................................... I

LIST OF APPENDICES ..................................................................................................................................III

LIST OF TABLES ........................................................................................................................................ IV

LIST OF FIGURES ........................................................................................................................................ V

ABBREVIATIONS ........................................................................................................................................ VI

1. INTRODUCTION ................................................................................................................................ 1

2. PROJECT PROGRESS ...................................................................................................................... 4

2.1. PROJECT BACKGROUND ............................................................................................................................. 4

2.2. PROJECT SUMMARY .................................................................................................................................... 5

2.3. PROJECT IMPLEMENTATION STATUS ............................................................................................................ 6

3. INSTITUTIONAL ARRANGEMENTS AND RESPONSIBILITIES FOR EMP IMPLEMENTATION................................. 8

3.1. INSTITUTIONAL STRUCTURE FOR ENVIRONMENT MANAGEMENT .................................................................... 8

3.2. ENVIRONMENT RESPONSIBILITIES .............................................................................................................. 10

4. REVIEW AND REVISION OF SUBPROJECT EMPS ......................................................................................12

4.1. REVIEW OF EMP ....................................................................................................................................... 12

4.2. REVISION OF SUBPROJECT EMPS ............................................................................................................. 12

5. ENVIRONMENTAL COMPLIANCE .............................................................................................................16

5.1. GENERAL COMPLIANCE ............................................................................................................................ 16

5.2. IMPLEMENTATION OF ENVIRONMENTAL MITIGATION MEASURES FOR CONSTRUCTION PERIOD ..................... 18

5.2.1 YUDONGXIA RESERVOIR* ................................................................................................................. 19

5.2.2 BAI’ANHE RESERVOIR ...................................................................................................................... 24

5.2.3 LIAOJIUZHAI RESERVOIR* ................................................................................................................. 25

5.2.4 JIANCAOGOU RESERVOIR ................................................................................................................. 26

5.2.5 JINJIAQING RESERVOIR .................................................................................................................... 28

5.2.6 JINLONG RESERVOIR ....................................................................................................................... 28

5.2.7 MAOZHULIN RESERVOIR ................................................................................................................... 28

5.3. IMPLEMENTATION OF ENVIRONMENTAL MITIGATION MEASURES FOR OPERATION PERIOD ........................... 29

5.3.1 IMPLEMENTATION OF SUPPORTIVE ENVIRONMENTAL PROTECTION DESIGN ........................................ 29

5.3.2 RESERVOIR CLEARING ..................................................................................................................... 30

5.3.3 UPSTREAM SOURCE PROTECTION .................................................................................................... 30

5.3.4 DAM SAFETY REVIEW ....................................................................................................................... 31

Page 6: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE II 2015- 3

5.4. ENVIRONMENTAL MONITORING RESULTS AND THEIR COMPLIANCE ............................................................. 31

5.2.1 YUDONGXIA RESERVOIR* ................................................................................................................. 31

5.2.2 BAI’ANHE RESERVOIR ...................................................................................................................... 32

5.2.3 LIAOJIUZHAI RESERVOIR* ................................................................................................................. 32

5.2.4 JIANCAOGOU RESERVOIR ................................................................................................................. 32

5.2.5 JINJIAQING RESERVOIR .................................................................................................................... 32

5.2.6 JINLONG RESERVOIR ....................................................................................................................... 32

5.2.7 MAOZHULIN RESERVOIR ................................................................................................................... 32

5.5. INSTITUTIONAL STRENGTHENING AND ENVIRONMENTAL TRAINING .............................................................. 33

5.6. ENVIRONMENTAL REPORTING AND SUPERVISION ....................................................................................... 33

6. EVALUATION OF CUMULATIVE IMPACTS AND IMPLEMENTED MITIGATION MEASURES ..................................34

7. CONCLUSIONS AND RECOMMENDATIONS ................................................................................................35

7.1. CONCLUSIONS .......................................................................................................................................... 35

7.2. RECOMMENDATIONS ................................................................................................................................. 36

Page 7: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE III 2015- 3

LIST OF APPENDICES

Appendix 1: Data Collected during this Reporting Period

Appendix 2: Site Visit Memo (August 2014)

Appendix 3: Environment Monitoring Results during this Reporting Period (Jul. – Dec.

2014)

Page 8: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE IV 2015- 3

LIST OF TABLES

TABLE 1: LIST OF CORE SUBPROJECTS (SOURCE: RRP OF ADB) ............................................................................................................... 6

TABLE 2: PROGRESS OF ONGOING SUBPROJECTS BY DECEMBER 2014 ...................................................................................................... 7

TABLE 3: LIST OF AGENCIES/COMPANIES INVOLVED IN ENVIRONMENTAL MANAGEMENT OF EIGHT ONGOING RESERVOIR

SUBPROJECTS .......................................................................................................................................................................................... 9

TABLE 4: ENVIRONMENTAL RESPONSIBILITIES OF ENVIRONMENTAL MANAGEMENT AGENCIES IN DIFFERENT PROJECT

PHASES .................................................................................................................................................................................................. 11

TABLE 5: AGREED ENVIRONMENTAL MONITORING PLAN FOR YUDONGXIA RESERVOIR PROJECT DURING CONSTRUCTION ........................... 13

TABLE 6: AGREED ENVIRONMENTAL MONITORING PLAN FOR LIAOJIUZHAI RESERVOIR PROJECT IN XIFENG COUNTY

DURING CONSTRUCTION .......................................................................................................................................................................... 13

TABLE 7: AGREED ENVIRONMENTAL MONITORING PLAN FOR JIANCAOGOU RESERVOIR PROJECT IN XIFENG COUNTY

DURING CONSTRUCTION .......................................................................................................................................................................... 13

TABLE 8: AGREED ENVIRONMENTAL MONITORING PLAN FOR JINLONG RESERVOIR PROJECT IN XIUWEN COUNTY DURING

CONSTRUCTION ...................................................................................................................................................................................... 14

TABLE 9: AGREED ENVIRONMENTAL MONITORING PLAN FOR MAOZHULIN RESERVOIR PROJECT IN KAIYANG COUNTY

DURING CONSTRUCTION .......................................................................................................................................................................... 14

TABLE 10: AGREED ENVIRONMENTAL MONITORING PLAN FOR BAI’ANHE RESERVOIR PROJECT IN KAIYANG COUNTY

DURING CONSTRUCTION .......................................................................................................................................................................... 15

TABLE 11: AGREED ENVIRONMENTAL MONITORING PLAN FOR JINJIAQING RESERVOIR PROJECT IN WUDANG DISTRICT

DURING CONSTRUCTION .......................................................................................................................................................................... 15

TABLE 12: EMP COMPLIANCE MATRIX (TILL DECEMBER 2014)................................................................................................................. 16

TABLE 13: IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND WATER USE FOR

ONGOING SUBPROJECTS ......................................................................................................................................................................... 29

Page 9: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE V 2015- 3

LIST OF FIGURES

FIGURE 1: INSTITUTIONAL STRUCTURE FOR ENVIRONMENT MANAGEMENT OF GIWRMP .............................................................................. 9

FIGURE 2: PROGRESS AND SITE MANAGEMENT OF YUDONGXIA SUBPROJECT OBSERVED DURING THIS REPORTING PERIOD......................... 19

FIGURE 3: PROGRESS AND SITE MANAGEMENT OF BAI’ANHE SUBPROJECT OBSERVED DURING THIS REPORTING PERIOD ............................ 25

FIGURE 4: PROGRESS AND SITE MANAGEMENT OF LIAOJIUZHAI SUBPROJECT OBSERVED DURING THIS REPORTING PERIOD ........................ 26

FIGURE 5: PROGRESS AND SITE MANAGEMENT OF JIANCAOGOU SUBPROJECT OBSERVED DURING THIS REPORTING

PERIOD................................................................................................................................................................................................... 27

FIGURE 6: PROGRESS AND SITE MANAGEMENT OF JINJIAQING SUBPROJECT OBSERVED DURING THIS REPORTING PERIOD .......................... 28

FIGURE 7: IMPOUNDMENT OF YUDONGXIA RESERVOIR .............................................................................................................................. 30

FIGURE 8: RESERVOIR CLEARING OF BAI’ANHE SUBPROJECT IN AUG. 2014 .............................................................................................. 30

Page 10: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE VI 2015- 3

ABBREVIATIONS

ADB Asian Development Bank

CED Clean energy development

CSC Construction Supervision Company

EARP Environmental Assessment and Review Procedures

ECAPC Environmental Check-and-Acceptance of Project Completion

EMC Environmental monitoring centre

EMU Environmental Management Unit

EIA Environmental impact assessment

EMP Environmental management plan

EPB Environmental Protection Bureau

GEPB Guiyang Municipal Environmental Protection Bureau

GIWRMP Guiyang Integrated Water Resource Management Project

GMG Guiyang municipal government

GPMO Guiyang Municipal ADB Loan Project Management Office

IA Implementing agency

IEE Initial Environmental Evaluation

IWRM Integrated water resource management

MDG Millennium Development Goal

PIU Project implementation unit

PPTA Project preparatory technical assistance

PRC People’s Republic of China

SEIA Summary environmental impact assessment

SO2 Sulphur dioxide

SWM Solid waste management

WSS Water supply system

WTP Water treatment plant

Page 11: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 1 2015 -3

1. INTRODUCTION

This is the fourth EMP implementation progress report prepared by Guiyang ADB-loan Project Management Office (GPMO) with assistance from Artelia Consultants, for project “Guiyang Integrated Water Resources Management Project (ADB Loan 2573-PRC)”. The report covers the progress for the period from July to D of 2014.

The “Guiyang Integrated Water Resources Management Project” covers 5 sectors of water resource management, including urban water supply, rural water supply and irrigation, irrigation system rehabilitation, soil and water conservation, and small water storage structure, totally loaned $150 million US dollars from ADB. According to the Environmental provisions in the Project Agreement (June 2010, PAL: PRC 38594):

● For those water supply dam Subprojects, particularly the Yudongxia dam, GMG shall ensure an appropriate classification of EPZ and determine and stipulate related regulations for preserving water quality of the respective reservoir. Such regulations may include land use zoning and control of chemical fertilizers/pesticides use, wastewater discharge and aquaculture development in the EPZ area. To ensure the preservation of the income and livelihood of local communities that may be affected by such regulations, GMG shall ensure that a PES mechanism to maintain the agreed level of water quality by providing sufficient compensation to upstream government and affected communities is established and implemented.

● GMG shall cause each local government and the IAs to construct, operate, maintain, and monitor the Project facilities in strict conformity with: (a) all applicable laws and regulations, including national and local regulations and standards for environmental protection, health, labor, and occupational safety; and (b) ADB’s Environment Policy and the environmental mitigation and monitoring measures detailed in the approved EIAs, IEEs, SEIA, SIEE, and EMP for the Project.

● GMG, through the local level PMOs, shall ensure that the IAs: (a) provide monthly environmental progress reports to the Guiyang PMO, which will prepare and submit to ADB semi-annual environmental reports in a format acceptable to ADB until loan closing. The semi-annual reports will address, among other issues, cumulative impacts of the Project; (b) where required, make an SEIA or SIEE available to the general public at least 120 days before each Subproject is approved; and (c) for each Subproject, carry out public consultations during the early stages of the EIA field work and when the draft EIA is available.

To response to the above requirements of ADB focusing on environment protection and environment management, under the supervision and GPMO and the assistance of ARTELIA Consultants, the subproject IAs have endeavored efforts to implement the corresponding EMPs. Through periodical internal inspections and EPB checks, the environment impacts resulting from project implementation have been closely monitored and controlled so as to guarantee subprojects’ smooth implementation.

Due to the subprojects are numerous and dispersed, to timely clarify subprojects’ environment behaviors and performances, GPMO organized regular site-visits (on a monthly basis), periodical document review, and report collection. During this reporting period, GPMO and ARTELIA Consultants had organized one round of site visit for environment inspection of ongoing subprojects in August 2014, especially focusing on the inspection of construction sites, material storage and spoil area

Page 12: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 2 2015 -3

management, wastewater treatment, noise control, solid waste management and on-site health & safety management. In view of difference of subproject progress, during this reporting period, special attention has also been paid to the impoundment for finished reservoir (Yudongxia Reservoir) and documentation preparation of newly proposed subproject (Hongyan Reservoir) in response to ADB mid-term review.

Based on the information collected, GPMO has developed the EMP implementation progress reports on a semi-annual basis to:

1) Summarize environment management works which has been implemented by GPMO and IAs in the six-month period;

2) Assess the resulted environmental impacts caused by subproject implementation with reference to the conclusions of subproject EIAs, in terms of resulted and anticipated impacts during both construction and operation periods;

3) Evaluate the effectiveness of mitigation measures already undertaken;

4) Review environment monitoring activities and monitoring results; and

5) Identify key environmental issues and forward suggestions for further improvement and EMP updating.

Accordingly, the Semi-annual Environmental Progress Report mainly covers the following chapters and appendices.

Main text:

Project Progress

Institutional Arrangements and Responsibilities for EMP Implementation

Revision of subproject EMPs

Environmental Compliance

a) Analysis of EMP requirements

b) Resulted environmental impacts and implemented mitigation measures for construction period

c) Anticipated environmental impacts and implemented mitigation measures for operation period

d) Environmental monitoring results and their compliance

Evaluation of Cumulative Impacts and Implemented Mitigation Measures

Conclusions and Recommendations

Appendices:

Data Collected during this Reporting Period

Site visit memo (August 2014)

Page 13: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 3 2015 -3

Environmental monitoring results during this report period (Jul.- Dec. 2014)

Page 14: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 4 2015 -3

2. PROJECT PROGRESS

2.1. PROJECT BACKGROUND

Guizhou Province is one of the poorest provinces in the PRC, with the second lowest rural income after Tibet, and the lowest level of urban income of any province. The capital of the province, Guiyang Municipality (GM), is its political, economic, cultural, technical and service center, and a major transportation hub of southwest PRC. In 2008, GM has an estimated population of 3.6 million, of which about 2.4 million reside in the main urban area, with the remaining 1.2 million in suburban or rural areas. About 574,000 people (16% of the total population) are ethnic minorities who mainly reside in the rural areas. The income differential between the rural and urban population is high, and about 25% of the rural population live on an income of less than CNY1,200 ($158) per capita per year. As the economic hub of the province, GM has a rapidly increasing population and industrial development, and hence increasing demand for water. Servicing this population and related municipal and industrial water demands is causing a severe strain on the existing water supply facilities.

On the other hand, both urban and rural areas of GM are on the mountainous ridge of the watershed boundary between the Yangtze River basin to the north and the Pearl River basin to the south. Annual average precipitation is quite high but large evaporative losses and uneven distribution present particular challenges for capturing and storing water, much of which drains into rivers as quick surface flows through numerous short creeks and streams that run deep in valleys, or through fast-flowing deep aquifers (groundwater rivers) through the limestone layers (karst areas).

The GM urban water supply infrastructure is in poor condition and its rapidly increasing urban population has seriously stretched the existing water supply capacity, resulting in reduced water pressure, and water rationing in dry periods. In the surrounding rural area, shortage of water for potable use and irrigation is perceived as a critical constraint to improving rural incomes and living standards. The current management of the GM water sector is not well integrated. There is vertical fragmentation with different responsibilities between provincial, municipal, and district/county levels and there is also horizontal fragmentation with responsibilities for water sector management split between different government departments.

In recent years, the Government has recognized the need to improve the comprehensive management of water resources, apply approaches consistent with integrated water resources management (IWRM) methodologies, and shift emphasis towards managing demand, including the use of economic mechanisms.

The implementation of “Guiyang Integrated Water Resources Management Project” will contribute solutions to achieve greater coordination and optimization of water supply and demand management activities in line with IWRM principles.

To fund this Project, Guiyang Municipal Government has applied for a loan of $150 million US dollars from ADB’s ordinary capital resources to cover part of the total $439.2million estimated cost. The remaining counterpart funding will come from domestic sources. The ADB loan became effective on 4 January 2011. The loan closing date is 30 June 2016.

In November 2014, a mission from ADB conducted the mid-term reivew for the

Page 15: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 5 2015 -3

project, when 1 core and 49 noncore subprojects have been withdrawn and 2 new noncore subprojects (Hongyan medium-sized reservoir and Hongyan water treatment plant) will be included. Considering the updated project schedule, particularly the schedule for the two new components, the mission and GPMO tentatively agrees to extend the current loan closing date of 30 June 2016 to 30 June 2018, by 2 years. Relevant approval procedure by national authorities and ADB is still ongoing.

2.2. PROJECT SUMMARY

The Project will adopt a sector investment approach with five key infrastructure development activities to be financed.

● Urban Water Supply comprising the establishment of one medium-sized reservoir and two small reservoirs,1 including the construction of dams, water conveyance tunnels, transmission pipelines, four water treatment plants, and the extension of the municipal water distribution networks;

● Rural Water Supply and Irrigation comprising the construction of up to 43 small reservoirs, including about 3 for county water supply, 20 for water supply and irrigation at the township level, and 20 for human and livestock water supply and small irrigation systems. Many of these include investments in water conveyance systems, small township water treatment facilities, and irrigation systems;

● Irrigation System Rehabilitation comprising rehabilitation and upgrading of up to nine irrigation systems covering a total area of 195,447 mu (13,030 hectares [ha]), including installation or repair of intake structures, canals, and aqueducts;

● Soil and Water Conservation comprising farmland restructuring, conversion of sloping farmland to terraces and tree or grass planting, and fruit tree planting, to protect the upper catchments of the water sources (about 800 square kilometers [km2]) from soil and water losses;

● Small Water Storage Structures comprising the provision of up to 105,100 small water storage tanks in rural areas to catch spring water for human consumption, and rainwater for irrigation and livestock consumption.

The project will also address non-structural interventions including institutional development and capacity strengthening, stakeholder participation, water tariff adjustments, and demand-management measures.

Following the sector lending modality, six core subprojects representing the five main types of infrastructure development activities were identified during project preparation. After the midterm review in Nov. 2014, one core subproject is withdrawn. The core subprojects serve as representative models for the design and implementation of similar noncore subprojects to be financed under the Project. The five core subprojects are the Yudongxia reservoir and water treatment subproject for urban water supply, the Jinlong and Liaojiuzai reservoir subprojects for rural water supply and irrigation, the Wudang irrigation rehabilitation subproject, and the Xifeng County small water storage tanks subproject.

1 Ministry of Water Resources. 2000. Standard for Classification and Flood Control of Water Resources and

Hydroelectric Project. Beijing (SL252–2000). A reservoir with a capacity of more than 10 to 100 million m3 is

classified as a medium-sized reservoir and that with a capacity of 0.1 to 10 million m3 is classified as a small

reservoir.

Page 16: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 6 2015 -3

The main features of the five remaining core subprojects are presented in the following table.

TABLE 1: LIST OF CORE SUBPROJECTS (SOURCE: RRP OF ADB)

Segment/Subproject Name Location Features Est. Cost

(CNY million)

I. Urban Water Supply

1a. Yudongxia reservoir

1b. Yudongxia water treatment plant

Wudang District 71.5m high concrete double

curvature arch dam; 18.6 million

m3 reservoir storage capacity;

100,000 m3/day water treatment

capacity.

256.43

163.72

II. Rural Water Supply and Irrigation

2. Jinlong reservoir

3. Liaojiuzai reservoir

Xiuwen County

Xifeng County

52.3 m high concrete faced rockfill

dam; 4.2 million m3 reservoir

storage capacity.

14.5m high geomembrane

anti-leakage earth dam; 0.2 million

m3 reservoir storage capacity.

67.7

5.43

III. Irrigation System Rehabilitation

4. Wudang irrigation system

Wudang District 1,847.4 ha rehabilitation area;

450.8 ha new irrigation area; WUA

establishment.

7.3

V. Small Water Storage Structures

5. Xifeng County small water storage

Xifeng County 250 tanks, 91 covered for water

supply, 159 uncovered for

livestock and irrigation; range in

size from 15 to 100 m3.

2.2

2.3. PROJECT IMPLEMENTATION STATUS

As mentioned above, according to the Aide Memoire of ADB Midterm Review Mission (11-17 November 2014), from the originally planned six core subprojects and sixty non-core subprojects, one core subprojects (Upstream and Midstream of Nanming River Catchment in Huaxi) and 49 non-core subprojects have been or will be withdrawn from the project; However, 2 non-core subprojects (Hongyan medium-sized reservoir and Hongyan water treatment plant) are being proposed.

In particular among the non-core subprojects, the following changes have been made in corresponding sectors:

Reservoir subprojects (urban water supply and rural water supply & irrigation):

39 reservoir sub-projects have been dropped out, and 7 reservoir subprojects

have been kept. Additionally, two new subprojects (Hongyan Reservoir and

Hongyan Water Treatment Plant) are proposed to be added in during the ADB

Mid-term Review;

Irrigation system rehabilitation: 6 irrigation rehabilitation subprojects have been

dropped out, and 1 subprojects (Wengjing and Yangchang) were kept;

Soil & water conservation: The only one core subproject has been withdrawn,

and all the 6 non-core subprojects have been kept;

Page 17: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 7 2015 -3

Small water storage structure: 4 non-core subprojects have been dropped out,

and 2 subprojects have been kept.

The general progress of ongoing subprojects has been summarized in the table below.

TABLE 2: PROGRESS OF ONGOING SUBPROJECTS BY DECEMBER 2014

Project Category

Completed (1) Under Construction

(12) Under Preparation (5)

Urban Water Supply

Yudongxia Reservoir

(90%2)

Hongyan Reservoir

(New Component, 16%) Hongyan Water Treatment Plant (New Component)

Rural Water Supply and Irrigation

Liaojiuzhai Reservoir

of Xifeng County (63%) Maozhulin Reservoir of

Kaiyang County

Jinlong Reservoir of Xiuwen County (39%)

Jiancaogou Reservoir of

Xifeng County (40%)

Bai’anhe Reservoir of Kaiyang County (72%)

Jinjiaqing Reservoir of

Wudang Dis. (56%)

Maozhulin Reservoir of Kaiyang County (24%)

Irrigation System

Rehabilitation

Yangchang and Wengjing

Irrigation System Rehabilitation Subproject

Soil and Water

Conservation

Soil Erosion Control for Wudang, Xifeng,

Xiuwen, Qingzhen, Kaiyang and Huaxi

(96%)

Small Water Storage

Structures

Xifeng Small Water Storage Structure

Subproject

Huaxi Small Water Storage Structure Subproject (87%)

Note: 1. The above information is updated based on the latest quarterly report of 2014 (4th of 2014) currently available; 2. The percentages in the brackets indicate the physical progress of civil works for corresponding subprojects under construction; 3. The subprojects in bold refer to the core subprojects identified during project preparation in 2009.

As shown above, Xifeng Small Water Storage Structure Subproject is the only subproject completed. Among the implemented subprojects, the subprojects for irrigation system rehabilitation and soil & water conservation are being implemented phase by phase without major ongoing construction activities. Therefore, the EMP implementation progress report for this reporting period will focus on the seven ongoing reservoir subprojects, namely Yudongxia, Liaojiuzhai, Jiancaogou, Bai’anhe, Jinjiaqing, Jinlong and Maozhulin. Also, special attention will be paid to the two newly proposed components, Hongyan Reservoir and Hongyan Water Treatment Plant Project, particularly on the progress of their EIA documentation preparation in compliance with both national regulations and ADB environmental safeguard guidelines. For the new Hongyan Reservoir subproject, since only preparatory works (land preparatory activities), instead of substantial physical progress, have been implemented which have not yet triggered substantial EMP implementation, no detailed description on the implementation status of environmental management is included in this report.

Page 18: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 8 2015 -3

3. INSTITUTIONAL ARRANGEMENTS AND RESPONSIBILITIES FOR EMP IMPLEMENTATION

Various organizations with different environmental management responsibilities – GPMO, GEPB, Ias, environmental management consultants, contractors, and construction supervision companies – have been involved during project implementation, and have been involved in the implementation of the EMP, as presented in this chapter.

3.1. INSTITUTIONAL STRUCTURE FOR ENVIRONMENT MANAGEMENT

The PMO, contractors, and Ias will each nominate full-time dedicated, trained, and qualified environment specialists to undertake environmental management activities and ensure the effective implementation of the EMP.

To actively respond the requirements in Project Agreement, in terms of institutional arrangement, a vertical framework with 3 levels had been set up for the project environment management:

Level 1: GPMO, which had set up an Environment Management Unit (EMU) since the beginning of the project, with 2 staff (headed by GPMO Director Ms. Meng Jianjian, daily coordinated by full time staff Mr. Yang Yang).

Level 2: Subproject Implementation Agencies (Ias), which had designated 1~2 employees each in charge of EMP implementation, report to GPMO periodically.

Level 3: Contractors/Supervisors and Operators, which had designated 1~2 n full-time staff in charge of daily environment management, report to Ias periodically.

Besides above three levels on environment protection, Guiyang EPB and County EPBs also organize on-site inspection to subprojects, supervise the fulfillment and effectiveness of environment protection measures, and provide comments and recommendations on periodic or random base.

Environmental specialist from ARTELIA Consultants has also been mobilized since November 2012; assisted GPMO in the preparation of the EMP implementation progress report since September 2013.

The following figure summarizes the institutional structure/relationship of various agencies.

Page 19: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 9 2015 -3

Figure 1: Institutional Structure for Environment Management of GIWRMP

For the eight ongoing reservoir subprojects, the specific agencies/companies involved are listed in the table below.

TABLE 3: LIST OF AGENCIES/COMPANIES INVOLVED IN ENVIRONMENTAL MANAGEMENT OF EIGHT ONGOING

RESERVOIR SUBPROJECTS

Name of Subprojects

Name of Subproject IA

Name of Contractor

Name of Construction Supervision

Company

Supervising EPB

Yudongxia Reservoir

Guiyang Zhushui Water Conservancy

Industry Development.

Co. Ltd.

No. 9 Engineering Bureau of Sinohydro

Corporation

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

Guiyang Municipal

EPB

Liaojiuzhai Reservoir of Xifeng County

Xifeng County Water

Resource Bureau

No. 9 Engineering Bureau of Sinohydro

Corporation

Guizhou Jingquan

Engineering Consultancy

Co., Ltd.

Xifeng County EPB

Jinlong Reservoir of Xiuwen County

Xiuwen County Water

Resource Bureau

Guangxi Haihe Water Conservancy Construction

Co., Ltd.

Guizhou Zhilong Water Conservancy Supervision

Co., Ltd.

Xiuwen County EPB

Jiancaogou Reservoir of Xifeng County

Xifeng County Water

Resource Bureau

No. 9 Engineering Bureau of Sinohydro

Corporation

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

Xifeng County EPB

Guiyang PMO, EMU

IAs

Consultants

Local EPBs

Guiyang EPB

ADB

Contractors Operators

Construction

Supervision Company

Page 20: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 10 2015 -3

Name of Subprojects

Name of Subproject IA

Name of Contractor

Name of Construction Supervision

Company

Supervising EPB

Bai’anhe Reservoir of Kaiyang County

Kaiyang County

Dongfeng United

Irrigation Area Administration

Guangxi Haihe Water Conservancy Construction

Co., Ltd.

Guizhou Jianghe Water Conservancy Supervision

Co., Ltd.

Kaiyang County EPB

Jinjiaqing Reservoir of Wudang Dis.

Guiyang Xintian

Economic Development

and Investment Company

Guizhou Zhongjin

Water Conservancy

and Hydropower Engineering Construction

Co., Ltd.

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

Wudang District EPB

Maozhulin Reservoir of Kaiyang County

Kaiyang County Water

Resource Bureau

Yulin Water Conservancy and Electricity Construction Engineering Department

Guizhou Jianghe Water Conservancy Supervision

Co., Ltd.

Kaiyang County EPB

3.2. ENVIRONMENT RESPONSIBILITIES

Guiyang EMU, under GPMO, take charge of project administration and coordination, take overall responsibilities for implementing and supervising environment management, environment monitoring, and mitigation works of all subprojects, and report to ADB periodically in accordance with the signed project agreement.

Subproject IAs, carry out detailed management of subproject. From project preparation and engineering design, to civil works construction and project operation, the IAs will be largely responsible for environmental management to ensure that the EMP is carried out effectively and they are also required to report to GPMO and EPB periodically in accordance with the signed project agreement.

Construction Contractors are responsible for implementing mitigation measures during construction, carry out monitoring and control project’s daily environment performance, and, report to IAs periodically.

Construction Supervision Company (CSC), as Supervisors designated by IAs, is responsible for on-site environment management control, supervise the contractors’ environment activities and proper implementation of mitigation measures during project construction.

Operators are responsible for implementing environment protection measures during project operation, carrying out necessary environmental monitoring, supervising in line with environment regulations and standards and reporting to IAs periodically according to the defined subproject EMPs.

Consultants (environmental specialist from ARTELIA) help GPMO to supervise EMP implementation by IAs, prepare required reports for ADB review and approval, and carry out necessary environmental trainings.

EPBs will organize periodically or randomly inspection to both construction sites

Page 21: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 11 2015 -3

(during construction) and operated projects (during operation) to review environmental qualities and environmental management conditions of the implemented subprojects, such as wastewater treatment, solid waste disposal, camp neatness, workers’ healthy situation, and safety situation, and official letters will then be issued to the IAs requesting improvements if any incompliance exists.

The following table summarized the environmental responsibilities of each agency in different phases of the Project.

TABLE 4: ENVIRONMENTAL RESPONSIBILITIES OF ENVIRONMENTAL MANAGEMENT AGENCIES IN DIFFERENT

PROJECT PHASES

Phase Responsible Agencies Environmental Responsibility

Project Preparation

EPBs Review and approval of project EIA

including the EMP

GPMO, ADB Review and approval of the SEIA (IEE)

including the EMP

Engineering Design

GPMO, IAs Updating the EMP, incorporate mitigation measures into engineering detail designs

and contracts

ADB Review and approval of environmental

measures

Tendering GPMO, IAs, Contractors, Incorporate EMP clauses in the bids

Construction

GPMO, IAs, EPB Advise, inspect and control the

implementation of mitigation measures

Contractors Implement mitigation measures

Supervision Company Inspect and control the effectiveness of

mitigation measures

International consultants

Assist GPMO with supervision of EMP implementation by IAs, preparation of

environmental reports to ADB and necessary environmental training

Operation

IAs Daily environmental management

GPMO, EPB Periodically and randomly monitor or inspect the environment compliances

Page 22: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 12 2015 -3

4. REVIEW AND REVISION OF SUBPROJECT EMPS

4.1. REVIEW OF EMP

In August 2006, during the PPTA phase of Project, the SEIA, together with EMP sections and detailed subproject EMP appendices, was prepared by Guiyang municipal government for the Asian Development Bank (ADB).

As an environment commitment of GMG, the EMP,

● Outline the mitigation, monitoring and institutional measures to be taken during project implementation and operation to avoid or control adverse environmental impacts, and the actions needed to implement these measures.

● Establish institutions and mechanisms to monitor and ensure compliance with environmental regulations and implementation of the proposed mitigation measures.

● Seek to ensure continuously improving environmental protection activities during project preparation, construction, and operation.

The EMP mainly includes:

● Summary of potential impacts and mitigation measures,

● Environmental monitoring,

● Planned public consultation,

● Institutional strengthening and training,

● Reporting and supervision.

4.2. REVISION OF SUBPROJECT EMPS

In April 2013, the GPMO officers, together with the environmental specialist from Artelia Consultants visited all the sites of ongoing subprojects and the subprojects to be constructed recently, particularly, the reservoir subprojects under construction and to be constructed soon. According to the observations, the EMPs of visited subproject developed during ADB PPTA phase have been generally implemented in the construction activities. However, it is also noticed that, as part of the EMP, the original environmental monitoring plans (required in ADB SEIA and EMP dated August 2006) was not tailored to the existing conditions of project sites in some cases.

Based on key findings of site visit and discussion with different PIUs, with the assistance of environmental specialist, in May 2013, GPMO has proposed the following adjustments of environmental monitoring plans for the ongoing or recently to-be-constructed subprojects for a more practical and efficient operation. All these adjustments have also been reviewed and put into trial implementation by corresponding PIUs since June 2013 to check their applicability.

With ADB’s no-objection as indicated in the Aide Memoire of Review Mission in November 2013 and with the good operationability and satisfactory monitoring

Page 23: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 13 2015 -3

results indicating the environmental compliance of related subprojects (as presented in the following section), the revised environment monitoring requirements have been officially implemented in a strict way since November 2013. Since then, there is no further EMP revision during this reporting period.

TABLE 5: AGREED ENVIRONMENTAL MONITORING PLAN FOR YUDONGXIA RESERVOIR PROJECT DURING CONSTRUCTION

Env. Aspect Locations (Number) of Monitoring

Points Monitoring Parameters Monitoring Frequency

Air 2 points, respectively at construction

site and Toupu Village TSP

4 times per year, five days per

time

Noise 2 points, respectively at construction

site and Toupu Village Leq dB(A) 4 times a year

Water

Surface water, two monitoring

cross-sections, respectively 500m

upstream and downstream of the dam

SS, pH, BOD5, COD, DO,

NH3-N, TN, TP, faecal

bacteria

3 times a year in wet, normal

and dry seasons, 3 days per

time

Public Health Construction sites (sampling 10% of

workers), resettlement sites

Epidemic situation, and

kind, case and incidence of

diseases

Once a year

Soil erosion As per project soil and water

conservation plan

As per project soil and

water conservation plan

As per project soil and water

conservation plan

TABLE 6: AGREED ENVIRONMENTAL MONITORING PLAN FOR LIAOJIUZHAI RESERVOIR PROJECT IN XIFENG COUNTY

DURING CONSTRUCTION

Env. Aspect Locations (Number) of Monitoring

Points Monitoring Parameters Monitoring Frequency

Air 1 point: near batching plant TSP Twice a year, two days per

time

Noise 1 point: near batching plant Leq dB(A) Twice a year, 2 days per

time, 2 times a day

Water

One cross-section: 500m downstream

of the dam

pH, DO, COD, BOD5,

NH3-N, TP, TN, faecal

bacteria

3 times a year in wet, normal

and dry seasons

Outfall of construction wastewater SS、CODcr、BOD5、NH3-N. Once in construction peak.

Public Health Construction sites (sampling 10% of

workers)

Epidemic situation, and

kind, case and incidence of

diseases

Once a year

Soil Erosion As per project soil and water

conservation plan

As per project soil and

water conservation plan

As per project soil and water

conservation plan

TABLE 7: AGREED ENVIRONMENTAL MONITORING PLAN FOR JIANCAOGOU RESERVOIR PROJECT IN XIFENG COUNTY

DURING CONSTRUCTION

Env. Aspect Locations (Number) of Monitoring

Points Monitoring Parameters Monitoring Frequency

Air 2 points, near dam site and boundary of

construction site TSP

Twice a year, 5 days per time,

could increase in construction

peak.

Noise

3 points, near aggregate processing

system, batching plant and along access

road

Leq dB(A) Twice a year, could increase

in construction peak.

Water 2 cross-sections, respectively 500m

upstream and downstream of dam

T, pH, SS, BOD5, COD,

TN, fecal coliform, NH3-N

3 times a year in wet, normal

and dry seasons, 3 days per

time

Public Health To be arranged by local CDC and

contractor

Epidemic situation, and

kind, case and incidence of

diseases

Once a year

Page 24: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 14 2015 -3

Env. Aspect Locations (Number) of Monitoring

Points Monitoring Parameters Monitoring Frequency

Soil Erosion As per project soil and water

conservation plan

As per project soil and

water conservation plan

As per project soil and water

conservation plan

TABLE 8: AGREED ENVIRONMENTAL MONITORING PLAN FOR JINLONG RESERVOIR PROJECT IN XIUWEN COUNTY DURING

CONSTRUCTION

Env. Aspect Locations (Number) of Monitoring

Points Monitoring Parameters Monitoring Frequency

Air 1 points, near boundary of construction

site TSP Twice a year, 3 days per time

Noise

3 points, respectively near aggregate

processing system, batching plant and

the village near access road

Leq dB(A) Twice a year, could increase

in construction peak.

Water

At the outfall of production wastewater PH, SS, flow rate, discharge

frequency Twice a year

At the outfall of domestic wastewater

DO, CODcr, BOD5, total

bacteria, fecal coliform,

wastewater flow rate

3 times a year in wet, normal

and dry seasons

Surface water: 2 points, respectively

500m upstream of dam and 500m

downstream of construction site.

DO, pH, SS, CODMn,

BOD5, petroleum and fecal

coliform

3 times a year in wet, normal

and dry seasons during

construction peak

Public Health Construction site and resettlement site

Epidemic situation, and

kind, case and incidence of

diseases

Once a year

Soil Erosion As per project soil and water

conservation plan

As per project soil and

water conservation plan

As per project soil and water

conservation plan

TABLE 9: AGREED ENVIRONMENTAL MONITORING PLAN FOR MAOZHULIN RESERVOIR PROJECT IN KAIYANG COUNTY

DURING CONSTRUCTION

Env. Aspect Locations (Number) of Monitoring

Points Monitoring Parameters Monitoring Frequency

Air 1 point: near Leipeng Community of

Heping Village TSP

Twice a year, 5 days per time,

could increase in construction

peak.

Noise 1 point: near Leipeng Community of

Heping Village Leq dB(A)

Twice a year, could increase

in construction peak.

Water

Two cross-sections: respectively 500m

upstream and downstream of dam

Water temperature, pH, SS,

BOD5, CODcr, fecal

coliform, NH3-N

3 times a year in wet, normal

and dry seasons, 3 days per

time

Intake of drinking water source for

construction camp

Colority, turbidity, odor,

visible substance, pH, total

hardness, total fecal

coliform, Fe, Mn, Zn, Cu,

Hg, Pb, chlorine, volatile

phenol, As, Se, Cd, fluoride,

TDS, sulfate.

4 times a year, 3 days per time

Public Health To be arranged by local CDC and

contractor

Epidemic situation, and

kind, case and incidence of

diseases

Once a year

Soil Erosion As per project soil and water

conservation plan

As per project soil and

water conservation plan

As per project soil and water

conservation plan

Page 25: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 15 2015 -3

TABLE 10: AGREED ENVIRONMENTAL MONITORING PLAN FOR BAI’ANHE RESERVOIR PROJECT IN KAIYANG COUNTY

DURING CONSTRUCTION

Env. Aspect Locations (Number) of

Monitoring Points Monitoring Parameters Monitoring Frequency

Water

Two cross-sections: respectively

500m upstream and downstream of

dam

Water temperature, pH, SS,

BOD5, CODcr, fecal coliform,

NH3-N

3 times a year in wet,

normal and dry seasons, 3

days per time

Intake of drinking water source for

construction camp

Colority, turbidity, odor, visible

substance, pH, total hardness,

total fecal coliform, Fe, Mn, Zn,

Cu, Hg, Pb, chlorine, volatile

phenol, As, Se, Cd, fluoride, TDS,

sulfate.

4 times a year, 3 days per

time

Public Health To be arranged by local CDC and

contractor

Epidemic situation, and kind, case

and incidence of diseases Once a year

Soil Erosion As per project soil and water

conservation plan

As per project soil and water

conservation plan

As per project soil and

water conservation plan

TABLE 11: AGREED ENVIRONMENTAL MONITORING PLAN FOR JINJIAQING RESERVOIR PROJECT IN WUDANG DISTRICT

DURING CONSTRUCTION

Env. Aspect Locations (Number) of

Monitoring Points Monitoring Parameters Monitoring Frequency

Air 1 point, near Guangkang

Community of Jiagang Village TSP

Twice a year, 5 days per

time, could increase in

construction peak.

Noise 1 point, near Guangkang

Community of Jiagang Village Leq dB(A)

Twice a year, could increase

in construction peak.

Water

Two cross-sections: respectively

500m upstream and downstream of

dam

Water temperature, pH, SS,

BOD5, CODcr, fecal coliform,

NH3-N

3 times a year in wet,

normal and dry seasons, 3

days per time

Intake of drinking water source for

construction camp

Colority, turbidity, odor, visible

substance, pH, total hardness,

total fecal coliform, Fe, Mn, Zn,

Cu, Hg, Pb, chlorine, volatile

phenol, As, Se, Cd, fluoride, TDS,

sulfate.

4 times a year, 3 days per

time

Public Health To be arranged by local CDC and

contractor

Epidemic situation, and kind, case

and incidence of diseases Once a year

Soil Erosion As per project soil and water

conservation plan

As per project soil and water

conservation plan

As per project soil and

water conservation plan

For the two new subprojects, the EIA report and EMP of Hongyan Reservoir project is to be finally approved by ADB in early 2015, while the EIA of Hongyan Water Treatment Plant project is still ongoing and corresponding EMP will be available to support the project implementation so that the construction of the water treatment plant will be completed and ready at the end of reservoir impounding.

Page 26: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 16 2015 -3

5. ENVIRONMENTAL COMPLIANCE

5.1. GENERAL COMPLIANCE

China has regarded environmental protection as one of its fundamental policies to guarantee a sustainable development of the nation in the 21st century. China’s existing environmental regulatory regime remains multi sourced (international treaties, national environmental laws, regulations, rules, measures and policies, standards and local legislation) but can essentially be classified into two categories: environmental management legislation and environmental pollution prevention and control legislation.

For construction projects in China, Environment Impact Assessment (EIA) and Environment Check & Acceptance of Project Completion (ECAPC) are two most important regulations to be compliant with. These two regulations are regarded as basic references for project environment protection respectively for construction phase and operation phase.

For GIWRMP, all the implemented subprojects had strictly followed national EIA procedures, completed EIA reports and obtained EPB approval. During subproject bidding process, the EMP requirements for construction period have been included as part of contractual obligations for the contractors. For the only completed subproject, Xifeng Small Water Storage Structure Subproject, the Environment Check & Acceptance of Project Completion (ECAPC) has been implemented and approved by local EPB.

As per the EARP formulated during project preparation in 2009, following the environmental requirements of ADB, all the investments under this project are subject to categorization to determine environmental assessment requirements. If the subprojects are identified as Category A or Category B, either an Environmental Impact Assessment (EIA, for category A) or an Initial Environmental Examination (IEE, for category B) will be required for ADB review and no objection before the subproject implementation.

As detailed in Section 2.3, based on current project progress, this semi-annual environmental report will focus on the EMP implementation of seven reservoir subprojects under construction. According to the results of desk review and site visit, the general EMP compliance of involved subprojects by December 2014 is summarized in the Matrix below. More details are presented in the following sections.

TABLE 12: EMP COMPLIANCE MATRIX (TILL DECEMBER 2014)

Subprojects

Project

County/Di

s.

EIA

Cate

-gor

y

ADB

Review

(Approval

date)

Adoption of

Mitigation

Measures

Results of Env.

Monitoring

Institutional

Strengthening

and Training

Reporting

and

Supervision

Under Construction (8)

Page 27: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 17 2015 -3

Subprojects

Project

County/Di

s.

EIA

Cate

-gor

y

ADB

Review

(Approval

date)

Adoption of

Mitigation

Measures

Results of Env.

Monitoring

Institutional

Strengthening

and Training

Reporting

and

Supervision

1. Yudongxia Reservoir

Municipal

Level A

SEIA (during PPTA

implementation)

×Approval

to be

acquired

from local

environment

al protection

authority for

implemented

variation

orders to be

obtained.

×TN and NH3-N

for surface water

quality; Fecal

coliform at at

drinking water

feed inlet

√ √

2. Liaojiuzhai Reservoir

Xifeng County

A

SEIA (during PPTA

implementation)

×To speed

up reservoir

clearing.

/4 √ √

3. Jiancaogou Reservoir3

Xifeng County

B SIEE

(05/10/10)

×TSP

concentration at

dam site and TN

of surface water

near dam site

√ √

4. Bai’anhe Reservoir

Kaiyang County

A SEIA

(24/01/13)

×To speed

up reservoir

clearing

√ √ √

5. Jinjiaqing Reservoir

Wudang Dis.

B SIEE

(05/10/10)

×To speed

up reservoir

clearing; to

strengthen

workers

safety

arrangement

; to expand

spoil area.

√ √ √

6. Jinlong

Reservoir

Xiuwen

County A

SEIA (during PPTA

implementation)

×To expand

spoil area. / √ √

7. Maozhulin Reservoir

Kaiyang

County B

SIEE (05/10/10

) √ / / /

Under Preparation (2)

8. Hongyan Reservoir

(New)

Municipal

Level A

SEIA to be

finalized with ADB approval in early 2015

/ / / /

9. Hongyan

WTP (New)

Municipal

Level B

Domestic EIA under preparatio

n

/ / / /

Note: √, means full compliance with EMP requirements, or basically ok, judged from site visits and

review of EMP reports,

×, means with incompliance, to be improved.

1. Those in bold refer to core subprojects. 2. Compared to the list of No.3 Semi-annual EMP project report, Hongyan WTP has been confirmed to be added into the project package according to the Aide Memoire of ADB mission dated November 2014.

Page 28: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 18 2015 -3

3. Since the pending civil works of Maozhulin subproject was only resumed since late December 2014, there is no practical implementation of EMP for the subproject during this reporting period. 4. The civil works of Liaojiuzhai subproject has been completed in September 2014; therefore, there is no environmental monitoring during this reporting period.

EIA Preparation Progress of Hongyan Reservoir Subproject

Among others, Hongyan Reservoir subproject, the newly added project, has been identified as a Category A subproject for EIA preparation. This means a Chinese EIA and an English SEIA would be required respectively for domestic and ADB approval, covering the examination of the project’s potential impacts, recommendation of environmentally sound project design by comparing all possible alternatives and at least twice of public consultation during EIA preparation. The mitigation measures and monitoring plan proposed in the EIA will be incorporated into the Environmental Management Plan (EMP).

With the support of international environmental consultant, the entrusted domestic EIA consulting team, Guiyang Survey and Design Research Institute under China Hydropower Consulting Group completed Chinese EIA report in late October 2013. Its final revision was approved by the Guiyang Municipal Environmental Protection Bureau on 24 February 2014.

Accordingly, the TA consulting team has developed the SEIA and submitted to ADB for review and information disclosure in June 2014. In consultation with Regional and Sustainable Development Department of ADB, it was agreed that an SEIA report will be prepared and disclosed on ADB’s website, while the domestic EIA report in Chinese will count as the original EIA report. Final comments of ADB on these documents will be provided by ADB before the finalization and disclosure of SEIA on ADB website in early 2015. Considering the 120-day disclosure requirements, the official approval of the SEIA report by ADB is expected in July 2015.

EIA Preparation Progress of Hongyan Water Treatment Plant Subproject

For the Hongyan water treatment plant, no domestic environmental assessment has been completed yet. It was agreed that the PMO will prepare a categorization form, indicatively for a Category B project. The required environmental safeguards documents will an English SIEE report, complimented with an English translation of the domestic EIA report. The SIEE and domestic EIA reports will be prepared in a timely manner so that the construction of the water treatment plant will be completed and ready at the end of reservoir impounding. It is noted that land clearing has started already. Although this is allowed by the Chinese system, the assessment will include the impacts of land and forest clearing, including a review of the necessary domestic approvals (e.g., cutting of trees), and cultural relics (e.g., the site is immediately beside tombstones).

5.2. IMPLEMENTATION OF ENVIRONMENTAL MITIGATION MEASURES FOR CONSTRUCTION PERIOD

The proper implementation of environment impact mitigation measures, which will give direct impacts to the projects’ environmental performance, is always a key issue tracked and supervised by GPMO.

To achieve a better understanding on the practical environment status of each subproject, GPMO, with the support of consultants, organized site-visits, meetings and interviews to subprojects in August and November 2014. During the visits and meetings, the EMP implementation status of each ongoing subproject has been reviewed for continuous improvements.

In general, all the reviewed subproject construction has been implemented together

Page 29: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 19 2015 -3

with the corresponding EMPs and Environmental Management Rules for Project Construction developed during project preparation in 2009. The description specific to each ongoing subproject is presented in the following sections. With the continuous commitments of subproject IAs on the implementation of corrective measures, it is notable that most of the previously detected incompliances have been corrected during this reporting period. The details are presented below.

5.2.1 YUDONGXIA RESERVOIR*2

The construction of Yudongxia Reservoir subproject was started in December 2011. To strengthen environmental management of the subproject, the contracted external environmental supervision team from Guizhou Province Environmental Engineering Evaluation Center has been mobilized since October 2012. Before the formal mobilization, the supervision team has developed a detailed environmental supervision plan based on the subproject EMP, which has been approved by the project owner in Sep. 2012.

During this reporting period, the team has submitted another six monthly environmental supervision reports (No.22~No.27) for the project based on their routine supervision work according to the environmental supervision plan. There are four main civil works contracts implemented for the subproject, namely:

Contract 1: Water diversion system (including steel pipes, power house, water diversion tunnel and so on) and supportive works;

Contract 2: Main dam and auxiliary dam, curtain grouting in head area, access tunnel on left bank, adit in head area, upstream and downstream cofferdam;

Contract 3: Curtain grouting on left bank, temporary road works.

Contract 4: Buildings and structure of water treatment plant, pipelines and high-level tanks

In the last six months, the first three contracts have been generally complemented, including main dam, curtain grouting and water treatment plant; the laying of associated distribution network is still ongoing and mostly done. With impounding, the reservoir storage level has reached the normal storage level of 1075m, while the WTP has been put into commissioning since July 2014 with good results.

FIGURE 2: PROGRESS AND SITE MANAGEMENT OF YUDONGXIA SUBPROJECT OBSERVED DURING THIS

REPORTING PERIOD

Discharged Flow downstream of main dam

Tailrace of constructed power station

2 The subproject marked with * is a core subproject, otherwise, it will be a non-core subproject.

Page 30: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 20 2015 -3

Current water storage level in Yudongxia Reservoir

(1075m)

Reservoir area near original Jinlong Scenic Zone

Laying of associated distribution network

Completed WTP

WTP in commissioning

Wastewater treatment facilities and sludge tank for the

WTP

Securely covered piping shaft

Resettlement Site (Mitangjing) under construction.

Page 31: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 21 2015 -3

Water supply pipes being laid for Mitangjing

Resettlement Site

High-level water tank and water supply station constructed for Mitangjing Resettlement Site

Public square being constructed for Mitangjing

Resettlement Site No.1 of three replanted ancient trees (survived)

No.2 of three replanted ancient trees (survived)

No.3 of three replanted ancient trees (to be further

observed)

Rehabilitation of spoil disposal site near auxilary dam

Page 32: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 22 2015 -3

Rehabilitation of spoil disposal site near auxilary dam

The provided environmental supervision reports clearly show that environmental mitigation measures specific to each construction site have been continuously implemented by the contractors during this reporting period based on subproject progress, including:

- Wastewater management (mainly for Contract 4 during this reporting period):

o Domestic wastewater: Dry latrines have been installed in the worker camps,

which (or septic tanks when available) are used for domestic wastewater

treatment with regular cleaning by local farmers;

- Air quality control (mainly for Contract 4 during this reporting period):

o The unpaved access roads are sprinkled with water and swept from time to

time by the contractors;

o Construction equipment and vehicles are regularly and properly maintained;

o It is forbidden to incinerate domestic solid waste within the construction area;

o Open sand and stone dumps are regularly sprinkled with water.

- Noise control (mainly for Contract 4 during this reporting period):

o Speed limit signs has been installed along access roads;

o No horn is allowed within the project site;

o Low-noise and low-vibration construction equipment are selected;

o No construction is allowed at night and between noon and 2pm.

- Solid waste management (mainly for Contract 4 during this reporting period):

o For this reporting period, spoil is mainly from pipeline excavation, which is

dumped along the pipelines for later backfilling;

o Domestic solid waste is collected and regularly cleared.

- Ecology:

o The excavation is implemented by strictly following the design;

o For all the sites, the greening works of excavated side slopes is being

implemented as designed;

o The discharge pipe at subsidiary dam and tailrace of power station is used

for the discharge of ecological flow during impoundment;

o The site and vegetation rehabilitation of closed spoil disposal site and

construction camps is being implemented by respective contractors.

- Health and safety: A dedicated health and safety supervision team under the

contracted construction supervision company has been working on site with

regular inspection for earlier detection of any potential health and safety risk

during construction and to follow up corresponding correction actions. All the

detected health and safety issues have been formally reported and filed, and

active measures have been taken accordingly with following-up inspection.

- Historic site: For the only identified ancient stone bridge (built in early years of

the Republic of China), relevant records (mainly photos) have been taken as per

the original EMP during reservoir clearing.

Page 33: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 23 2015 -3

As observed in the field visit in August 2014, the environmental management of Yudongxia Reservoir subproject site is generally satisfactory with proper mitigation measures taken against construction impacts. In particular, the following observations related to the environmental performance of the subproject has been made:

1) Replantation of ancient trees in reservoir area: As part of reservoir clearing, the replantation plan for affected ancient trees has been partly modified compared with the EIA phase and implemented with the guidance of local forestry department in May 2014 before reservoir impoundment. According to the modified replantation plan, there were totally 15 ancient trees in the project-affected area, in which three have been replanted successfully, four un-flooded ones have been protected in situ, and the other eight have been felled and cleared based on their conditions. The implementation of replantation plan has been validated by forestry professionals from the provincial forestry department and Guizhou University. The site visit in August 2015 showed that two of three replanted had survived and the other one had not yet grown with new branches and leaves. Following-up observations and nursing are required in the coming months.

2) Environmental Mitigation Measures for Resettlement Sites: During the visit, it was understood from the IA that the environmental protection measures for resettlement sites proposed in the original subproject EIA had been implemented or were being implemented. One resettlement site of Mitangjing under construction (serving 17 households) was visited. The resettlement site was completed at the end of 2014. The following environmental mitigation measures were being implemented for the specific resettlement site:

- Water source: A high-level water tank and water supply station with the

treatment capacity of 25m3/d has been constructed for the site on the top of

a nearby hill, which is connected with the site by DN90 water supply pipes.

- Domestic wastewater treatment: To protect the reservoir water quality from

being polluted, a supporting wastewater treatment plant will be built with

domestic fund near the resettlement site.

- Public education on environmental and health protection: A community

square was being constructed near the residential houses, which will

provide a suitable space for public recreation and education on

environmental and health protection.

3) Vegetation rehabilitation of spoil disposal site: The original spoil disposal site near auxiliary dam was visited during the August visit, which has been levelled and compacted with the sowing of grass seeds in June 2014. Due to high gravel content of the site, it was observed that grass growth was not good during the visit. Additional sowing may be necessary.

4) Commissioning of Yudongxia Water Treatment Planta: Yudongxia Water Treatment Plant has been completed and put into commissioning since July 2014. The plant has been fully staffed as scheduled (about 20 managers and operators). The treatment capacity during the August visit was about 10,000t/d. The operational results were generally good with the compliance of all the water quality indicators except slightly high residual chlorine in treated water. The water treatment plant was actively applying for hygiene license for earlier water sale.

Page 34: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 24 2015 -3

5) Approval to be acquired from local environmental protection authority for implemented variation orders: It is understood that several changes have been made during project implementation, for example, addition of power generation system, changes of high-level water tank and distribution pipelines, adjustments of dam height and crest width, etc. According to the national environmental impact assessment regulations, these project changes need to be reported to local environmental protection authorities for approval before the final environmental protection inspection and acceptance for project completion. According to the IA, the environmental protection inspection and acceptance procedure will be implemented for the whole subproject, instead of for Yudongxia Reservoir component and WTP component respectively, which will therefore formally started upon the completion of the whole subproject and the acceptance inspection of associated water and soil conservation works in early 2015. Relevant progress will be updated in the next semi-annual report.

According to the provided monthly environmental supervision reports (No.22-No.27), since Jul. 2014, no rectification notice on environmental incompliance has been issued by environmental supervisor. By the end of December 2014, there is neither environmental conflict/accident nor any environment complains received from local residents related to the subproject.

5.2.2 BAI’ANHE RESERVOIR

As one of the non-core subproject, Bai’anhe Reservoir is still under construction and has been completed by 72% by December 2014. As reported by the project supervisor in the monthly construction supervision reports (dated Jul.-Dec. 2014), applicable environmental mitigation measures have been taken in accordance with the subproject EMP, including the treatment of construction wastewater with settling tank on site before discharge, regular cleaning of construction vehicles and water sprinkling within construction site to reduce flying dust, noise control by using low-noise equipment with regular maintenance, proper collection and disposal of domestic solid waste and close monitoring on the effectiveness of epidemic disease control. It is understood that the operation of rock quarry has been stopped and the spoil disposal site has been properly managed. By the end of December 2014, there is neither environmental conflict/accident nor any environment complains received from local residents during construction. During the reporting period, the subproject IA has been reminded to pay high attention to reservoir clearing, site rehabilitation (in particular, spoil disposal site) and re-vegetation works in the last phase of project construction, which will be the focus of environmental management during next reporting period.

Page 35: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 25 2015 -3

FIGURE 3: PROGRESS AND SITE MANAGEMENT OF BAI’ANHE SUBPROJECT OBSERVED DURING THIS

REPORTING PERIOD

Completed Dam (1123.8m high)

Progress of water intake tower

Management of Spoil Disposal Site

5.2.3 LIAOJIUZHAI RESERVOIR*

The construction of Liaojiuzhai Reservoir subproject (core subproject) was started in March 2013 and main works (including main dam, flood discharge channels and downstream irrigation channels and the upstream flood diversion channels) has been completed in September 2014. It is understood in the Aug visit that, since most of land downstream of the reservoir has been changed from agricultural use to industrial use, the irrigation area targeted by the subproject has been reduced from the original 1700mu to about 100mu and the total length of irrigation channels implemented in the subproject is accordingly reduced to about 800m, which is sufficiently to meet future irrigation needs downstream. The reservoir is now waiting for the raining season for impounding. During this reporting period, the ongoing construction mainly focused on the construction of flood discharge channel and associated irrigation channel. Accordingly proper environmental mitigation measures have been taken against adverse environmental impact. For example, the construction wastewater is intercepted for settling treatment in the reservoir area; no construction works is scheduled at night; in coming spring, grass seeds will be sowed over the dam slope for greening. As confirmed by the results of environmental monitoring (as shown in Section 5.4.3), the environmental mitigation measures taken are sufficient to minimize the project impacts on surrounding environment and residents. By the end of December 2014, there is neither environmental conflict/accident nor any environmental complaints received from local residents.

Page 36: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 26 2015 -3

FIGURE 4: PROGRESS AND SITE MANAGEMENT OF LIAOJIUZHAI SUBPROJECT OBSERVED DURING THIS

REPORTING PERIOD

Completed Dam

Constructed flood discharge channel and bridge

for pedestrians

Diversion of grouting wastewater upstream in reservoir

area for settling treatment before discharge

Constructed flood diversion channel

5.2.4 JIANCAOGOU RESERVOIR

The construction of Jiancaogou Reservoir subproject was started in March 2013, however, little progress has been made until Mar. 2014 due to resettlement issues and conflict between the proposed blasting activities for dam excavation and the presence of nearby railway bridge. With the subproject IA’s coordination on design variation, the construction was restarted in Apr. 2014, and the method of stone excavation was changed from the proposed blasting and normal mechanical excavation to minimize the impacts on ongoing high-speed railway construction nearby. According to the provided monthly construction supervision reports (dated Jul., Aug., Sep. and Dec. 2014), during this reporting period, the dam excavation has been completed in late November 2014, and the concreting and grouting works have been started in December 2014. The foundation excavation of associated WTP has been completed in December 2014. During construction, the following environmental mitigation measures have been taken, including protection of surrounding vegetation during excavation, and the installation of safety fencing and warning signs around the site. Additionally, the following findings have been identified during this reporting period in relation to environmental management of the subproject:

1) A Φ300 water supply pipeline of local water supply company going through the

dam site was noticed to be cut off by project construction during last reporting period. With active coordination of subproject IA, contractor, construction supervisor and relevant local authorities, an emergency action plan has been developed and implemented to address this issue by adding a section of bypass elbow pipe to guarantee the downstream water use.

2) With the completion of excavation at dam site, all the generated spoil at dam site

Page 37: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 27 2015 -3

has been properly disposed at the designated spoil disposal site and partly utilized for road pavement. During the excavation in raining season, the contractor and construction supervisor have closely monitored the upstream the flow rate and site conditions. No barrier lake and flooding risk has ever occurred to the construction site.

3) A path costing RMB 200,000 has been constructed by the subproject IA specially for the villagers living on the hill top near the construction site.

4) As the dam is situated near existing railway bridge and ongoing construction site of high-speed railway project, it is suggested to strength the inspection and monitoring of dam safety during the subproject construction and future operation.

FIGURE 5: PROGRESS AND SITE MANAGEMENT OF JIANCAOGOU SUBPROJECT OBSERVED DURING THIS

REPORTING PERIOD

Completed excavation of dam foundation

Ongoing concreting at dam site

Site excavation for associated WTP

Constructed path for nearby villagers

Installed bypass elbow pipe for Φ300 water supply

pipe cut-off by subproject construction

Page 38: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 28 2015 -3

The only environmental complaint during this reporting period was received from nearby villagers in July 2014 in relation to the impacts of excavation noise at night. The subproject IA has taken immediate action to stop all the construction activities at night to address the issue.

5.2.5 JINJIAQING RESERVOIR

The construction of Jinjiaqing Reservoir project was started in March 2013 with slow progress due to the geological conditions found during excavation of diversion tunnel different from design document. By the end of December 2014, the subproject has been completed by 69%. The ongoing construction activities mainly focus on curtain grouting and water-taking tower. Applicable environmental mitigation measures have been taken in accordance with subproject EMP, respectively on wastewater collection and treatment, noise control, solid waste management and vegetation rehabilitation. By the end of December 2014, there is neither environmental conflict/accident nor any environmental complaints received from local residents. However, minor issues were observed during site visit, including the needs to speed up the reservoir clearing, to expand the area for spoil disposal at the Jinjiaqing Reservoir and to improve the workers’ safety arrangements on the site. The following-up information will be provided in the next semi-annual environmental report.

FIGURE 6: PROGRESS AND SITE MANAGEMENT OF JINJIAQING SUBPROJECT OBSERVED DURING THIS

REPORTING PERIOD

Geomembrane laying over the dam

Spillway

5.2.6 JINLONG RESERVOIR

The construction of Jinlong Reservoir was started in the beginning of 2014, and the physical progress of the subproject is 58% by December 2014. The ongoing construction activities during this reporting period mainly focus on dam site excavation and diversion tunnel. As reported by the project supervisor in the monthly construction supervision reports (Jul.-Dec. 2014), applicable environmental mitigation measures have been taken in accordance with subproject EMP, including treatment of construction wastewater by settling tank on the site, proper scheduling of construction works (no high-noise operation after 10pm) for noise control, disposal of spoil soil at designated spoil area, appropriate collection and disposal of domestic solid waste, safety management of explosive storage and use by professional blasting company and soil erosion control. By the end of December 2014, there is neither environmental conflict/accident nor any environmental complaints received from local residents.

5.2.7 MAOZHULIN RESERVOIR

The construction of Maozhulin Reservoir was started in Dec. 2013, however, the

Page 39: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 29 2015 -3

completed works by December 2014 are only limited to access road, excavation of inlet and outlet and bolting-shortcrete support for diversion tunnel due to slow land acquisition progress and shortage of counterpart fund. During this reporting period, the construction works was suspended during July-November 2014 and was not resumed until Dec. 13th, 2014 with excavation of diversion tunnel. As reported by the subproject IA, with the construction resuming, appropriate environmental mitigation measures have been implemented by the contractor, and the details will be presented in the next semi-annual environmental report. By the end of December 2014, there is neither environmental conflict/accident nor any environmental complaints received from local residents.

5.3. IMPLEMENTATION OF ENVIRONMENTAL MITIGATION MEASURES FOR OPERATION PERIOD

Although none of the subproject has been put into operation so far, preparatory works has started to be implemented during construction as planned in the project design and project EIA report. The specific environmental mitigation measures undertaken for operation period during this reporting period are summarized in the sections below.

5.3.1 IMPLEMENTATION OF SUPPORTIVE ENVIRONMENTAL PROTECTION DESIGN

During subproject construction, the supportive design for environmental benefits has been implemented, including:

Stratified water intake: As per the original EIA report, a stratified water intake (three levels respectively at 1065m, 1050m and 1032m) has been constructed for Yudongxia Subproject to avoid the impacts of too low water temperature on the growth of downstream rice paddy during irrigation.

Supportive environmental protection facilities for WTP: The canteen of the WTP for Yudongxia Subproject has been installed with oil separator and septic tank; wastewater collection tank, sludge filter press workshop, garbage tank and greening belt have been constructed for the WTP.

Guarantee of downstream environmental flow and water use: For all the ongoing subprojects, the designed engineering measures to guarantee downstream environmental flow and water use (irrigation, drinking and fish ponds) have been implemented during construction, as listed in the table below.

TABLE 13: IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND WATER

USE FOR ONGOING SUBPROJECTS

Name of Ongoing

Subproject

Designed Environmental Flow

(m3/s) Implemented Engineering Measures

Yudongxia Reservoir

0.2 Pipes laid in the dam plus original water

diversion canal

Bai’anhe Reservoir

0.066 (only during Nov. – Apr.)

Steel pipe is laid beside the outfall of water intake with gate valve for flow regulation.

Jinjiaqing Reservoir

0.012 (only during Nov. – Apr.)

The environmental flow will be regulated by a gate valve.

Liaojiuzhai Reservoir

0.0008 Steel pipe is laid beside the outfall of water intake with gate valve for flow regulation.

Jiancaogou Reservoir

0.0332 (only during Nov. – Apr.)

Not yet to this part.

Jinlong Reservoir 0.013 (by average) Construction just started, not yet to this part.

Page 40: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 30 2015 -3

Name of Ongoing

Subproject

Designed Environmental Flow

(m3/s) Implemented Engineering Measures

Maozhulin Reservoir

0.025 (during Nov. – Apr.) Construction just started, not yet to this part.

5.3.2 RESERVOIR CLEARING

To facilitate the beneficial use of the reservoir after impoundment, the bottom clearing of Yudongxia Reservoir was started in late September/early October 2013 and has been completed by Jul. 2014 before reservoir impoundment, involving three districts/counties in the project area. By December 2014, the storage water level of Yudongxia reservoir has reached normal storage level, 1075m. According to the site visit, the good quality of reservoir water has indicated good practice of implemented reservoir clearing.

FIGURE 7: IMPOUNDMENT OF YUDONGXIA RESERVOIR

Since July 2014, with good project progress, Bai’anhe Subproject has also started reservoir clearing in the reservoir area. It is expected to be completed before reservoir impoundment. Further progress will be updated in the next semi-annual report.

FIGURE 8: RESERVOIR CLEARING OF BAI’ANHE SUBPROJECT IN AUG. 2014

With the coming project completion, it is also necessary to speed up the reservoir clearing of Liaojiuzhai and Jinjiaqing subprojects before their impounding.

5.3.3 UPSTREAM SOURCE PROTECTION

The upstream water source protection has already been considered in the EMPs for all the reservoir subprojects during project preparation. With the completion of

Page 41: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 31 2015 -3

project dam, some subproject, for example, Yudongxia Reservoir, have started the preparation for the implementation of originally proposed mitigation measures for the protection of upstream water resource: to discuss with local authorities to understand relevant plans and arrangements on the establishment of water source protection zone and non-point pollution control in the river basin; to maintain the septic tank near the reservoir for future treatment of domestic wastewater generated by reservoir management staff during operation.

For Bai’anhe Reservoir Subproject, it is noticed that a specific water source protection zoning plan for the subproject was developed in Dec. 2007. As the main drinking water source of Kaiyang County in the near future, local county government has paid high attention to the protection of water source protection for Bai’anhe Reservoir. The above-mentioned “Drinking Water Source Protection Zone Planning for Bai’anhe Reservoir of Kaiyang County” has been updated in June 2008, which follows the original planning for Grade I and Grade II drinking water resource protection zone. The county water resource bureau and county environmental protection bureau will be jointly in charge of its implementation. It is told that Kaiyang County used to propose to develop a culture and education zone within the proposed protection zone; however, the proposal has been withdrawn for the protection of drinking water source. In addition, the associated Bai’anhe water treatment plant financed by local government (with the treatment capacity of 10,000m3/d) has almost been completed, which is expected to be put into use together with the reservoir.

5.3.4 DAM SAFETY REVIEW

Following ADB safeguard policies, for all the ongoing reservoir subprojects (Yudongxia, Bai’anhe, Jijiangqing, Jinlong and so on), the preliminary design documents and/or detailed construction drawings have been reviewed by the designated dam safety panel for GIWRMP before subproject construction. The expert comments on dam safety issues have been provided in formal reports. Necessary supervision and advisory services have been continuously provided by the panel during project implementation in view of specific subproject progress.

5.4. ENVIRONMENTAL MONITORING RESULTS AND THEIR COMPLIANCE

Based on the accepted revisions of environmental monitoring plans for ongoing subprojects (as detailed in Section 4.2), the IAs of relevant subprojects has continued with the cooperation with contracted environmental monitoring institutions to implement routine environmental monitoring during this reporting period. The monitoring reports have been submitted to GPMO and the key conclusions and findings from the monitoring activities have been summarized in this section. The detailed results have been attached to this report as Appendix 4.

5.2.1 YUDONGXIA RESERVOIR*

Following the agreed monitoring plan, the contracted environmental monitoring institution, Changsha Environmental Protection Vocational and Technical College, has implemented monthly environmental monitoring (Jul.-Dec. 2014) during this reporting period, covering the parameters on noise level, air quality and the quality of surface water and drinking water source.

During this reporting period, the monitoring results are generally satisfactory, as listed below:

Drinking water supply: The results are generally compliant with Class III of Surface Water Environmental Quality Standard (GB838-2002) except the indicator of fecal coliform. Since the drinking water at the construction site is

Page 42: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 32 2015 -3

pumped from Yudong River, continuous non-compliance of fecal coliform has been detected; however, the results have indicated an improving trend compared to last semi-annual report.

Surface Water: In comparison with Class II of Surface Water Environmental Quality Standard (GB838-2002), only the non-compliance of TN and NH3-N was detected in both September and December 2014 at the dam site, particularly in December, the dry season. According to local environmental monitoring station, it is more related to the high nitrogen baseline level for surface water in Guizhou Province.

Air quality: Fully compliant with Grade II limit of “Environmental Air Quality Standard” (GB3095-1996).

Noise level: Generally compliant with Grade 2 limit of “Acoustic Environmental Quality Standard”.

5.2.2 BAI’ANHE RESERVOIR

In September and December 2014, according to the revised environmental monitoring plan, the water quality at the project site has been tested, and the current water quality was found to be compliant with Class III requirements of “Surface Water Environmental Quality Standard” (GB3838-2002).

5.2.3 LIAOJIUZHAI RESERVOIR*

Since the subproject has been generally completed in September 2014, no environmental monitoring was implemented during this reporting period. With reservoir impoundment in the near future, the environmental monitoring will then follow the environmental monitoring plan for operational phase.

5.2.4 JIANCAOGOU RESERVOIR

In December 2014, the county environmental monitoring station was entrusted to implement the monitoring of air quality, surface water quality and noise level around the project site. The only two non-compliances detected from the monitoring results are the TSP concentration at dam site due to construction activities and the TN level in sampled surface water considering high TN baseline level for surface water in Guizhou Province.

5.2.5 JINJIAQING RESERVOIR

The environmental monitoring of Jinjiaqing Reservoir Subproject was implemented by local environmental monitoring station in September 2014 on surface water quality. Full compliance has been obtained.

5.2.6 JINLONG RESERVOIR

According to the implementation schedule of environmental monitoring for Jinling Reservoir, the next round of environmental monitoring will be carried out in early 2015, whose results will be included in the next semi-annual environmental report.

5.2.7 MAOZHULIN RESERVOIR

The construction of Maozhulin reservoir subproject was suspended until November 2014. Accordingly, the next round of environmental monitoring will be carried out in early 2015, whose results will be included in the next semi-annual environmental report.

Page 43: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 33 2015 -3

5.5. INSTITUTIONAL STRENGTHENING AND ENVIRONMENTAL TRAINING

In August 2014, the environmental consultant has provided project-specific on-the-job environmental training to the individual IAs, contractors and project supervisors for the ongoing Yudongxia, Liaojiuzhai, Jiancaogou, Jinjiaqing, Bai’anhe and Jinlong subprojects to emphasize their respective duties on daily environment management, including implementation of mitigation measures, environmental monitoring, environmental supervision, site inspection and environmental reporting. The scope of training mainly covers the following documents:

- EMP implementation requirements as per ADB loan agreement and project agreement;

- Subproject EMP approved by ADB;

- Environmental Management Rules for Project Construction;

- Implementation of corrective measures taken against earlier detected environmental incompliances.

For Yudongxia and Bai’anhe subproject, special training has been provided on environmental management during the coming project operation.

5.6. ENVIRONMENTAL REPORTING AND SUPERVISION

As presented above, regular environmental supervision has been implemented during the construction of all the ongoing subprojects under GIWRMP.

Following the loan agreement of GIWRMP, GPMO is required to develop and submit the semi-annual environmental report to ADB for review; accordingly, the subproject IAs are submitting the following environmental reports to GPMO at the required deadline:

- Monthly project supervision report (including required section on implemented environmental management) or Monthly Environmental Supervision Reports (for Yudongxia Reservoir Subproject) in the first week of next month;

- Semi-annual environmental monitoring reports for each ongoing subproject for every six months.

With the assistance of environmental consultant, GPMO has formatted the environmental management section of monthly project supervision reports and the semi-annual environmental monitoring reports for subproject IAs to use since July 2013.

This semi-annual report is developed based on subproject environmental reports and relevant documents collected from the IAs by February 2014, as listed in Appendix 1.

Page 44: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 34 2015 -3

6. EVALUATION OF CUMULATIVE IMPACTS AND IMPLEMENTED MITIGATION MEASURES

Under a sector loan modality, GIWRMP has a large number of small subprojects, involving water storage, dam construction, water supply, irrigation, soil and water conservation, flood control and hydropower, which are expected to have low possibility of significant adverse impacts from any one subproject. However, a large number of subprojects to be undertaken in relatively small geographic area in a relatively short period of time may cause significant cumulative impacts, which have been assessed in a general way in the sector EIA (dated Sep. 2006) in compliance with the ADB Environmental Assessment Guidelines (Manila, 2003).

According to the sector EIA, the cumulative impacts of GIWRMP are only expected with the subprojects’ operation based on the actual operation performance/data of implemented subprojects. So far only one subproject has been completed under GIWRMP, namely, Xifeng Small Water Storage Structure Subproject. It is still too early to analyse the resulted cumulative impacts of the project.

During ADB review mission in Nov. 2013, the PMO and mission agreed that it is too early to discuss the details of such assessment, as (i) almost no subprojects are completed, (ii) many subprojects dropped out, and (iii) the confirmed subprojects are far apart and not linked. As such, the assessment will primarily focus on the experiences gained in the project with the design, implementation, and operation of the facilities. The cumulative impacts will be discussed during subsequent semi-annual reports.

However, to facilitate the evaluation of cumulative impacts from GIWRMP implementation, the environmental consultant has assisted the GPMO to start the work with data collection, which includes, but not limited to, the last available version of local water resource management master plans. Once possible, more analysis will be provided on cumulative impacts and implemented mitigation measures of the project.

Page 45: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 35 2015 -3

7. CONCLUSIONS AND RECOMMENDATIONS

7.1. CONCLUSIONS

For GIWRMP, all the implemented investments had strictly followed national and ADB EIA procedures. The required EIA documents (domestic EIA report and SEIA required by ADB) for the new subproject, Hongyan Reservoir, are currently under preparation in compliance with both national and ADB environmental policies. Based on updated project schedule, the domestic EIA report has been approved by the Guiyang Municipal Environmental Protection Bureau in February 2014, the SEIA is expected to be updated and disclosed in March 2015. Considering the 120-day disclosure requirements, ADB may be able to approve the SEIA report in July 2015. The new Hongyan WTP component is classified as a Category B project, which requires domestic EIA report and an English SIEE report prepared in a timely manner to ensure the project completion at the end of reservoir impounding.

During this reporting period, the seven reservoir subprojects under construction, namely, Yudongxia, Bai’anhe, Liaojiuzhai, Jiancaogou, Jinjiaqing, Jinlong and Maozhulin, have been reviewed in terms of their environmental management performance during construction. General speaking, the construction of all the reviewed subprojects has been implemented together with their corresponding EMPs and Environmental Management Rules for Project Construction developed during project preparation in 2009. In accordance with subproject EMPs, the mitigation measures have been implemented to minimize project impacts in terms of noise control, air quality control, wastewater management, water quality protection, solid waste management and ecological protection for construction phase. No major issue has been detected.

The proper implementation of mitigation measures, which will give direct impact to the projects’ environmental performance, is always a key issue tracked and supervised by GPMO. With the assistance of TA environmental consultants, the GPMO has organized the site visits together with environmental consultant to review EMP implementation status of ongoing subprojects in August 2014. With the assistance of environmental consultant, on-the-job environmental training has been provided to the IAs, contractors and project supervisors for six ongoing subprojects (Yudongxia, Liaojiuzhai, Jiancaogou, Jinjiaqing, Bai’anhe and Jinlong) during this reporting period. The formats and requirements of environmental reporting have also been followed by all the stakeholders.

It is notable that continuous environmental improvements have been achieved during this reporting period. Corresponding correction actions will be followed up in the next semi-annual environmental report.

The monitoring results still show a few cases of environmental non-compliance in terms of air quality, surface water quality and drinking water source quality, and the trend of improvements has been noticed even for the still incompliant monitoring results.

For the subprojects in construction phase, by the end of December 2014, there is neither environmental conflict/accident nor any environment complains received from local residents, except for Jiancaogou subproject. The only environmental complaint during this reporting period was received from the villagers living near construction site of Jiancaogou subproject in July 2014 in relation to the impacts of excavation noise at night, which has been immediately and properly addressed by stopping all the construction activities at night.

Page 46: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 36 2015 -3

7.2. RECOMMENDATIONS

Based on the observations during the reporting period, the following observations and recommendations have been made on environmental management of next phase:

(1) Joint efforts of GPMO and environmental consultant have shown positive impacts on continuous improvements of environmental management on the construction sites in terms of implemented mitigation measures, environmental supervision, environmental monitoring and environmental reporting;

(2) With ongoing progress of subproject construction, the assistance tailored to specific progress of each subproject should be provided by GPMO and environmental consultant, for example, on coming impoundment of Yudongxia, Bai’anhe and Liaojiuzhai subprojects;

(3) It is noticed that there were still some non-compliance of environment monitoring results detected during this reporting period, however, the trend of improvements has been observed in these incompliant results, which indicates the effectiveness of corresponding mitigation measures taken by the IAs and contractors. For further improvements, more targeted mitigation measures are needed;

(4) For two new components confirmed after mid-term review, namely Hongyan reservoir and Hongyan WTP, the environmental safeguard documentation will be developed in compliance with both national and ADB requirements. The environmental consultant will work in close collaboration with domestic EIA institute to get the required documents prepared in a timely manner to facilitate the project implementation.

Page 47: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 37 2015 -3

APPENDIX 1: DATA COLLECTED DURING THIS

REPORT PERIOD

Page 48: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 38 2015 -3

No. Documents Submitted by Date and Author

1

Monthly Environmental Supervision

Report for Construction Phase for

Yudongxia Reservoir Project

(No.22)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Jul. 2014

Guizhou Provincial

Environmental

Engineering Assessment

Centre

2

Monthly Environmental Supervision

Report for Construction Phase for

Yudongxia Reservoir Project

(No.23)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Aug. 2014

Guizhou Provincial

Environmental

Engineering Assessment

Centre

3

Monthly Environmental Supervision

Report for Construction Phase for

Yudongxia Reservoir Project

(No.24)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Sep. 2014

Guizhou Provincial

Environmental

Engineering Assessment

Centre

4

Monthly Environmental Supervision

Report for Construction Phase for

Yudongxia Reservoir Project

(No.25)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Oct. 2014

Guizhou Provincial

Environmental

Engineering Assessment

Centre

5

Monthly Environmental Supervision

Report for Construction Phase for

Yudongxia Reservoir Project

(No.26)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Nov. 2013

Guizhou Provincial

Environmental

Engineering Assessment

Centre

6

Monthly Environmental Supervision

Report for Construction Phase for

Yudongxia Reservoir Project

(No.27)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Dec. 2014

Guizhou Provincial

Environmental

Engineering Assessment

Centre

7

Monthly Construction Supervision

Report of Water Distribution

Network and High-level Water Tank

for Yudongxia Reservoir Project

(No.7-9, for Jul.-Sep. 2014)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Jul.-Sep. 2014

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

8

Monthly Construction Supervision

Report of Water Source Works for

Yudongxia Reservoir Project

(No.43, for Jul. 2014)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

Jul. 2014

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

Page 49: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 39 2015 -3

No. Documents Submitted by Date and Author

9

Environmental Monitoring Report for

Yudongxia Reservoir Project during

Construction

(ChangHuanYuanWeiJian [2014]

Q007)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

23/07/2014

Changsha Env. Protection

Vocational and Technical

College

10

Environmental Monitoring Report for

Yudongxia Reservoir Project during

Construction

(ChangHuanYuanWeiJian [2014]

Q008)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

18/08/2014

Changsha Env. Protection

Vocational and Technical

College

11

Environmental Monitoring Report for

Yudongxia Reservoir Project during

Construction

(ChangHuanYuanWeiJian [2014]

Q009)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

24/09/2014

Changsha Env. Protection

Vocational and Technical

College

12

Environmental Monitoring Report for

Yudongxia Reservoir Project during

Construction

(ChangHuanYuanWeiJian [2014]

Q010)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

21/10/2014

Changsha Env. Protection

Vocational and Technical

College

13

Environmental Monitoring Report for

Yudongxia Reservoir Project during

Construction

(ChangHuanYuanWeiJian [2014]

Q011)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

14/11/2014

Changsha Env. Protection

Vocational and Technical

College

14

Environmental Monitoring Report for

Yudongxia Reservoir Project during

Construction

(ChangHuanYuanWeiJian [2014]

Q012)

Guiyang Zhushui Water

Resource Ind. Dev. Co.,

Ltd.

20/12/2014

Changsha Env. Protection

Vocational and Technical

College

15

Environmental Monitoring Report of

Surface Water Quality for Kaiyang

Bai’anhe Reservoir Project

(KYS2014-272)

Kaiyang County Water

Resource Bureau

12/09/2014

Kaiyang County CDC

16

Environmental Monitoring Report of

Surface Water Quality for Kaiyang

Bai’anhe Reservoir Project

(KYS2014-296)

Kaiyang County Water

Resource Bureau

29/12/2014

Kaiyang County CDC

17

Environmental Monitoring Report for

Jinjiaqing Reservoir Project in

Wudang District (2014S91)

Wudang District Water

Resource Bureau

12/09/2014

Wudang District CDC

Page 50: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 40 2015 -3

No. Documents Submitted by Date and Author

18

Environmental Monitoring Report for

Jiancaogou Reservoir Project in

Xifeng District (XiHuanJianJian

WT2014005)

Xifeng County Water

Resource Bureau

26/12/2014

Xifeng County

Environmental Monitoring

Station

19

Monthly Construction Supervision

Report of Xifeng County Liaojiuzhai

Reservoir Project (No.13-15, for

Jul.-Sep. 2014)

Xifeng County Water

Resource Bureau

Jul.-Sep. 2014

Guizhou Jingquan

Engineering Consultancy

Co., Ltd.

20

Monthly Construction Supervision

Report for Contract 1 of Wudang

District Jinjiaqing Reservoir Project

(No.17-19 and No.22, for Jul.-Sep.

and Dec. 2014)

Wudang District Water

Resource Bureau

Jul.-Sep. and Dec. 2014

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

21

Monthly Construction Supervision

Report of Kaiyang County Bai’anhe

Reservoir Project (No.17-19 and

No.22, for Jul.-Sep. and Dec. 2014)

Kaiyang County Water

Resource Bureau

Jul.-Sep. and Dec. 2014

Guizhou Jianghe Water

Conservancy Supervision

Co., Ltd.

22

Monthly Construction Supervision

Report of Jiancaogou Reservoir

Project (No.7-9 and No.12, for

Jul.-Sep. and Dec. 2014)

Xifeng County Water

Resource Bureau

Jul.-Sep. and Dec. 2014

Guizhou Qianshui

Engineering Supervision

Co., Ltd.

23

Monthly Construction Supervision

Report of Maozhulin Reservoir

Project (No.5, for Dec. 2014)

Kaiyang County Water

Resource Bureau

Dec. 2014

Guizhou Jianghe

Engineering Supervision

Co., Ltd.

24

Monthly Construction Supervision

Report of Jinlong Reservoir Project

(No.8, No.9 and No.13, for Jul., Aug.

and Dec. 2014)

Xiuwen County Water

Resource Bureau

Jun., Aug. and Dec. 2014

Guizhou Zhilong Water

Conservancy Supervision

Co., Ltd.

Page 51: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 41 2015 -3

APPENDIX 2: SITE VISIT MEMO (AUG. 2014)

Page 52: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG INTEGRATED WATER

RESOURCES MANAGEMENT PROJECT, LOAN NO. 2573-PRC PROJECT MANAGEMENT SUPPORT

MEMO

PAGE 1/14

Subject: Site Visit Report in August 2014 Date: 03/09/2014

File: REF. GUIYANG/1231022/ M0028

To: Guiyang PMO

From: ARTELIA CHINA

Dear PMO,

During Aug. 24-29, 2014, environmental specialist, Mrs. Huang Xiaodan, was assigned by our

company to pay site visit to Guiyang, covering the construction sites of several reservoir subporjects in

Xiuwen, Xifeng, Kaiyang and Yudongxia, to understand the subproject progress and the

implementation of environmental management plan for ongoing subprojects. With communication with

subproject IAs and site visits, the key environmental issues identified are summarized below.

1. SITE VISIT AGENDA

The detailed agenda and activities of Mrs. Huang Xiaodan, environmental specialist of the consulting team, during Aug. 24-29 are shown below:

Date Time Activities

8/24/2014 Sunday

pm Flight to Guiyang

8/25/2014 Monday

All day

Site visit of Jinlong reservoir subproject in Xiuwen County

8/26/2014 Tuesday

am Site visit of Liaojiuzhai reservoir subproject in Xifeng County

pm Site visit of Jiancaogou reservoir subproject in Xifeng County

8/27/2014 Wednesday

All day

Preparation of site visit report.

8/28/2014 Thursday

am Site visit of Yudongxia reservoir and Yudongxia WTP

pm Visit of Yudongxia resettlement site, replantation site of ancient trees and spoil

area

8/29/2014 Friday

am Site visit of Bai’anher reservoir subproject in Kaiyang County

pm Back to Guiyang and flight back to Shanghai

Page 53: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 2/14

2. SITE VISIT FINDINGS

2.1. JINLONG RESERVOIR IN XIUWEN COUNTY

On Aug. 25th, 2014, the consultant visited the construction site of Jinlong reservoir in Xiuwen County. According to the site conditions and communication with the subproject IA and contractor, currently the ongoing works still focus on the excavation of side slope and flood ditch. Due to lack of counterpart fund and absence of partial construction drawings, it makes reimbursement of ADB loan and blasting and excavation of tunnel impossible.

Overall Construction Site

Excavation of side slope and flood ditch Excavated entrance to diversion tunnel

Side slope on right bank

The key findings during the site visit of Jinlong subproject mainly include :

Page 54: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 3/14

1) Considering limitation of acquired land and remaining excavation of about 30,000m3, the expansion of spoil area noticed during last site visit remains an urgent issue. Despite great efforts of the subproject IA, it has been confirmed that further acquisition of downstream land is impossible for the expansion of spoil area. Therefore, in consultation with the design institute, it is initially planned to expand based on existing spoil area, and the retaining wall in the original design will be accordingly displaced outwards. The design institute is now justifiying the capacity of spoil area with such expansion and its impacts on downstream river cross section. The detailed design is still under preparation.

Status of spoil area in Mar. 2014 Status of spoil area in Aug. 2014

Current status of spoil area Initial plan of spoil area expansion

2) The blasting operation will be used in the coming rock excavation for diversion tunnel. According to the site visit, in the collaboration with local professional blasting company, the contractor has implemented necessary safety management measures on the construction site, for example to post safety notice on blasting operation around the site;

Page 55: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 4/14

Safety notice on blasting operation around the site

3) The first round of environmental monitoring has been implemented in early June 2014 covering the monitoring of surface water quality, air quality and noise level around the project site. The results are compliant with applicable standards. The subproject IA has submitted the first environmental monitoring report for the subproject to Guiyang PMO.

4) In terms of soil erosion, according to the site conditions, after raining season this year, by strengthening soil conservation measures and related monitoring, the soil erosion on the construction site is under good control. Except the excavated area, there is no significant increase of soil erosion.

Side slope in Mar. 2014 Side slope in Aug. 2014

2.2. LIAOJIUZHAI RESERVOIR IN XIFENG COUNTY

In the morning of Aug. 26th, the environmental specialist visited construction site of Liaojiuzhai Reservoir in Xifeng County. Since the beginning of project construction in March 2013, the main dam, including the spillway, has been generally completed. Currently the dam is completing the grouting, and the upstream spillway is under construction. The office building for the reservoir has completed site preparation. Except the spillway, it is expected that the main works (including the office building) will be completed in two months.

Page 56: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 5/14

Completed dam, spillway and irrigation channel Water surface upstream of the reservoir after

raining season

Cross section of spillway Constructed spillway and newly added access

bridge

The key findings during the site visit of Liaojiuzhai subproject mainly include :

1) The site visit found that the main ongoing construction activities was dam grouting. The generated wastewater from grouting is diverted into the upstream reservoir area for settling treatment before being discharged downstream.

Treatment of wastewater from grouting

2) It is understood that the subproject IA plans to sow grass seeds over the slope of dam for greening after the completion of main dam.

Page 57: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 6/14

3) The upstream flood diversion channel as the water source of Liaojiuzhai Reservoir is being constructed as per the design, which is expected to be completed soon. The completed channel will be sufficient to meet the design water storage demand for the reservoir.

Constructed flood diversion channel Flood diversion channel under construction

4) Since most of the land downstream of the reservoir has been changed from original farmland to industrial land, which has reduced the irrigation area targeted by the subproject from the original 1700mu to 100mu, accordingly, the length of irrigation channel included in the project design is accordingly reduced to about 800m, which has been completed and put into use to deliver required flow rate for downstream farmland irrigation.

Gate house and irrigation channel Constructed irrigation channel

5) With the change of land use downstream, in order to sufficiently utilize the original design reservoir capacity, it is initially planned by the subproject IA to add its function to supply human drinking water. A village water treatment plant will be constructed to supply about 2000 residents of nearby Shiqiao Village, which will be financed by local fund. With the change of reservoir function, the environmental specialist urges the subproject IA to further strengthen the monitoring of reservoir water quality, to meet at least Class III surface water quality requirements. In addition, before reservoir impounding (planned in 2016), the reservoir clearing shall be appropriately implemented to avoid any impact on water quality.

Page 58: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 7/14

2.3. JIANCAOGOU RESERVOIR IN XIFENG COUNTY

In the afternoon of Aug. 26, the environmental specialist visited the construction site of Jiancaogou Reservoir in Xifeng County. Since the commencement of its construction on Dec. 31st, 2013, after addressing the problems of resettlement and access road to the site and the spoil area, now the dam abutment is under excavation. Since there is high-speed railway project ongoing nearby, the method of rock excavation has changed from blasting to normal mechanical excavation. Currently the site excavation is as follows :

Excavation of right dam abutment Excavation of left dam abutment

Currently the 10000m3/d WTP contract has also started site preparation, which is situated on the top of a hill not far away from the reservoir. The water supply from the reservoir will be pumped once and then sent to the WTP. After treatment, the water will supply the low-lying area covering about 2/3 of the urban area in Xifeng County by gravity.

WTP site under excavation (close to high-speed railway bridge under construction)

Location of proposed pumping station

Page 59: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 8/14

Service area of the WTP

The key findings from site visit of Jiancaogou Reservoir are as follows:

1) Path for villagers: To solve daily traffic problem for the villagers living on the top of hill affected by subproject construction activities, the subproject IA invested 200,000RMB to construct the path for the villagers to the hilltop.

Constructed path for villagers to hilltop to facilitate the daily traffic of the villagers with the investment from

subproject IA

2) Implemented emergency plan for the cutting off of Φ300 water supply pipe: With the

discussion of subproject IA, contractor, construction supervisor and relevant local authorities, for the section of water supply pipe belonging to the county water supply company which has been cut off by dam site excavation, a bypass elbow pipe has been installed to ensure the downstream water use.

Emergency plan for cutting-off of Φ300 water

Page 60: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 9/14

supply pipe

3) Disposal of spoil soil: According to the site conditions, there still remains high quantities of excavation for dam abutments and foundation. Now part of spoil soil is used for the pavement of temporary road. The remaining spoil soil is transported to the spoil area behind the hill through the access road. According to the site visit, although the river has been dug through and the concern of barrier lake observed during previous excavation has been addressed, the generated spoil soil has affected the river cross section to some extent. The clearance of spoil soil needs to be accelerated, and the site monitoring needs to be strengthened to avoid any new barrier lake.

River cross section at dam excavation site

4) Dam safety: Since the dam location is close to existing railway bridge, ongoing construction of high-speed railway bridge (see the picture below) and urban area of Xifeng County, it is recommended to strengthen the inspection, assessment and monitoring of dam safety during project construction and operation.

Environment of project site

2.4. YUDONGXIA RESERVOIR

On Aug. 28th, together with the representative of subproject IA, the environmental specialist and environmental supervisor visited the sites of WTP under commissioning, reservoir area with impounding, resettlement site and spoil area for Yudongxia subproject. The key findings from site visit are as follows:

Page 61: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 10/14

1) Water source works: Currently, the impounding of Yudongxia Reservoir has reached the level of 1071.5m, but part of land acquisition for flooded area of the reservoir still remains to be finished. With its completion, the storage water level will soon reach the design level of 1075m. The power house and metallic structure of the power station have been completed and the supply of main equipment has been completed. Part of associated equipment, such as cables, remains to be purchased and installed. The water flow used for power generation in the original design is now directly discharged downstream. Since it is in rainy season, the current discharge flow rate (including that from flushing sluice and power station) is generally high.

Main dam of Yudongxia Discharge flow from downstream power station

(equipment installation not yet completed, no power generation)

Reservoir area near Mitangjing resettlement area Reservoir area near original Jinlong Scenic Zone

2) WTP: The civil works and equipment installation of the WTP have been completed, with about 10% of water supply pipes remaining to be completed. The WTP has been put into commissioning since July with full staffing of operators (about 20 staffs). The current treatment capacity is about 10,000m3/d. The operation is generally good. The lab of the WTP has put into opeartion staffed with 3 technicians. Nine water samples are analyzed everyday for 21 indicators including turbidity, colority, odor, pH, chloride, CODMn, total hardness and NH3-N. According to a copy of weekly report on monitoring results in August, all the water quality indicators are compliant with standard requirements except slightly high residual chlorine. Now the WTP is actively applying for the hygenie license for early water sale.

Page 62: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 11/14

WTP under commissioning Associated wastewater and sludge treatment

facilities for the WTP

Safety measures in the site : all the piping shafts

are covered Water quality analysis weekly report from the WTP

lab

3) Rehabilitation of spoil area: The environmental specialist visited the original spoil area near auxilliary dam of Yudongxia Reservoir. According to site conditions, the original spoil area has been compacted, leveled and sowed with grass seeds around June 2014. However, due to low earth content in the spoil area, the current growth of grass is not so good. Replanting may be needed as required.

Rehabilitation of spoil area near auxiliary dam Rehabilitation of spoil area near auxiliary dam

Page 63: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 12/14

4) Supporting environmental protection measures for resettlement area: Since it was found that the supporting environmental protection measures proposed for resettlemnt site in the subproject EIA had not yet been implemented during last site visit, the environmental specialist visited a resettlement site of Mitangjing during this visit. The resettlement site is a centralized resettlement site constructed based on the willingness of resettled villagers in Mitangjing, consisting of 17 households of resettled villagers. Currently the site is under construction and is expected to be put into use at the end of the year. According to the requirements of subproject EMP, the subproject IA has laid DN90 water supply pipes for the resettlement site, which connects the constructed high-level water tank and water supply station on the top of nearby hill. The water supply station has the treatment capacity of 25m3/d, which is sufficient to meet the water demand of resettlement site; at the same time, the township government will use domestic fund to construct a nearby wastewater treatment plant for the resettlement site for wastewater treatment of the resettlement site.

Houses under construction in Mitangjing

resettlement site Water supply pipe laid for Mitangjing resettlement

site

High-level water tank adnd water supply station for

the resettlement site Community square under construction

5) As part of reservoir clearing, the replantation plan of ancient trees updated based on site conditions has been implemented in May 2014. For totally 15 ancient trees in the project-affected area, based on their growth conditions, three have been replanted, four unflooded ones have been protected in situ, and the other eight were cut off since it was impossible to replant them during reservoir clearing. The replantation and protection was implemented under the guidance of local forestry department. After the implementation of ancient tree disposal plan, the results have been inspected and accepted by forestry specialists from the provincial forestry department and Guizhou University. According to the site visit, two of the three replanted ancient trees have survived and the other one has not yet grown with new leaves and branches.

Page 64: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 13/14

1st of replanted ancient trees (survived) 2nd of replanted ancient trees (survived)

3rd of replanted ancient trees (without new branches and leaves)

6) Environmental protection approval procedure for project variation : With project variations during its implementation, for example, the addition of power generation system, change of high-level water tank and water distribution pipes and adjustments of dam height and dam top width, in accordance with the requirements of national EIA law, the above-mentioned project variations need to be approved by local environmental protection authority before the inspection and acceptance of environmental protection for project completion. This issue has been clearly raised by the environmental supervisor in the monthly environmetnal supervision report, which is still waiting for the feedback of subproject IA. During the site visit, the environmental specialist requests the subproject IA to send the feedback to Guiyang PMO to update the progress.

7) Progress of inspection and acceptance of environmental protection for project completion: It is understood that, the water source and WTP components of Yudongxia Reservoir will accept the inspection for project completion as a whole. With the completion of remaining works and based on the special inspection and acceptance of soil conservation, the preparation for the inspection and acceptance of environmental protection for project completion will be carried out, which will be expected at the end of this year or early next year.

2.5. BAI’ANHE RESERVOIR IN KAIYANG COUNTY

On Aug. 29th, the environmental specialist visited the construction site of Bai’anhe Reservoir in Kaiyang County. Currently the main dam only has 50cm to be completed, and the water intake will soon be completed. The access road and some grouting works have not yet been completed. In July 2014, the contractor has started the reservoir clearing and the impounding will be in late Sep. or Oct. The inspection and acceptance of environmental protection for project completion will be done at the end of the year. According to the subproject IA, based on current project progress, the subproject is generally within the original budget.

Page 65: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

ARTELIA REF NO. : M029 HXD PAGE : 14/14

Dam of Bai’anhe Reservoir Water intake under construction

Starting of reservoir clearing Spoil area

As the main drinking water source for Kaiyang County in the future, the local government pays high attention to the protection of water source for Bai’anhe Reservoir. Currently Bai’anhe Reservoir has almost been completed, and the local water resource bureau and environmental protection bureau have started to jointly implement the original “Plan of drinking water source protection zone for Bai’anhe reservoir of Kaiyang County” (updated in June 2008). The Grade I and Grade II drinking water protection zones have been defined as per the original plan. In the future, its implementation will under joint administration of the county water resource bureau and environmental protection bureau. Kaiyang County used to propose to construct a culture and education zone within the proposed protection zone; however, the proposal has been withdrawn for the protection of water source. Additionally, to support Bai’anhe reservoir, Bai’anhe WTP financed by local government (with the treatment capacity of 10000 m3/d) has almost been completed, which is expected to be put into use together with the reservoir. At the end of project construction, the environmetnal specialist reminded the subproject IA and the contractor to pay special attention to reservoir clearing, site rehabilitation (in particular, the spoil area) and re-vegetation before reservoir impounding which are the focus of envirionemtnal management in next phase. Additionally, the environmental specialist has also reminded the subproject IA to timely switch into the implementation of EMP for operational phase after impounding, in particular, the monitoring of water quality in various cross sections of the reservoir.

In addition, it is understood that, the construction of Maozhulin reservoir in Kaiyang County has been suspended since Jun. 2014 due to resettlement issue and lack of counterpart fund. Recently, 41million RMB loan from the bank of agriculture is in place, resettlement work is also progressing, and the resuming of construction is expected shortly.

Page 66: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 42 2015 -3

APPENDIX 3: ENVIRONMENT MONITORING

RESULTS DURING THIS REPORTING PERIOD

(JUL.-DEC. 2014)

Page 67: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 43 2015 -3

1. Yudongxia Reservoir Subproject*

Following the agreed monitoring plan, the environmental monitoring has been regularly implemented during this reporting period covering the parameters on noise level, air quality and the quality of surface water, drinking water source and domestic wastewater. Six detailed monitoring reports (Jul.-Dec. 2014) have been provided to GPMO with the results as detailed below.

Noise monitoring

Unit: Leq dB(A)

Date Time

Monitoring Location

Dam site Toupu Village near

WTP site

Jul. 22, 2014 Daytime 56.2 53.8

Night 45.7 43.2

Jul. 23, 2014 Daytime 56.4 53.6

Night 46.8 43.6

Aug. 14, 2014 Daytime 52.3 52.6

Night 44.1 40.3

Aug. 15, 2014 Daytime 53.5 53.7

Night 43.2 40.2

Sep. 15, 2014 Daytime 57.1 53.5

Night 46.8 42.7

Sep. 16, 2014 Daytime 57.7 56.9

Night 47.5 43.3

Oct. 13, 2014 Daytime 52.6 58.3

Night 41.6 44.5

Oct. 14, 2014 Daytime 53.5 56.4

Night 42.3 45.8

Nov. 6, 2014 Daytime 55.3 55.4

Night 43.3 44.6

Nov. 7, 2014 Daytime 53.9 52.8

Night 42.4 42.9

Dec. 10, 2014 Daytime 54.4 55.8

Night 44.5 42.6

Dec. 11, 2014 Daytime 54.1 53.7

Night 43.8 45.3

Limit Value (GB

GB12523—90 &

GB3096-2008)

Daytime 70 60

Night 55 50

* GB12523-90 for dam site & Grade II of GB3096-2008 for Toupu Village. Air Quality Monitoring

Unit: mg/m3

Date Monitoring Locations

Monitoring Parameters

NO2 TSP

15/09/2014 Dam site 0.015 0.122

Toupu Village 0.022 0.159

Page 68: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 44 2015 -3

Date Monitoring Locations

Monitoring Parameters

NO2 TSP

near WTP site

16/09/2014 Dam site 0.017 0.113

Toupu Village near WTP site

0.024 0.137

17/09/2014 Dam site 0.018 0.103

Toupu Village near WTP site

0.020 0.144

18/09/2014 Dam site 0.016 0.125

Toupu Village near WTP site

0.023 0.137

19/09/2014 Dam site 0.019 0.131

Toupu Village near WTP site

0.021 0.122

10/12/2014 Dam site 0.018 0.116

Toupu Village near WTP site

0.021 0.132

11/12/2014 Dam site 0.015 0.125

Toupu Village near WTP site

0.025 0.146

12/12/2014 Dam site 0.020 0.142

Toupu Village near WTP site

0.023 0.157

13/12/2014 Dam site 0.022 0.137

Toupu Village near WTP site

0.017 0.139

14/12/2014 Dam site 0.023 0.134

Toupu Village near WTP site

0.026 0.142

Limit value (Class II, GB3095-1996) 0.080 0.300

Surface Water Quality Monitoring

Unit: mg/L

Monitoring Parameters

Limit Value (Class II, GB3838-2002)

Cross section at dam site

2014-9-15 2014-9-16 2014-9-17 Mean

pH 6~9 6.88 6.91 6.93 6.88~6.93

SS / 10 7 7 8

DO ≥6 6.3 6.6 6.2 6.4

COD ≤15 5L 5L 5L 5L

BOD5 ≤3 0.5L 0.5L 0.5L 0.5L

NH3-N ≤0.5 0.042 0.037 0.029 0.036

TN ≤0.5 0.63 0.6 0.66 0.63

TP ≤0.1 0.02 0.01 0.02 0.02

Fe ≤0.3 0.03L 0.03L 0.03L 0.03L

Mn ≤0.1 0.01L 0.01L 0.01L 0.01L

Pb ≤0.01 0.001L 0.001L 0.001L 0.001L

Hg ≤0.00005 0.00004L 0.00004L 0.00004L 0.00004L

Fecal coliform (No./L)

≤2000 1100 790 1400 1097

Page 69: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 45 2015 -3

Water

temperature (℃) / 16.8 17.1 16.6 16.8

Monitoring Parameters

Limit Value (Class II, GB3838-2002)

Cross section at dam site

2014-12-10 2014-12-11 2014-12-12 Mean

pH 6~9 6.76 6.87 6.83 6.76~6.87

SS / 4L 4L 4L 4L

DO ≥6 7.2 7.0 7.2 7.1

COD ≤15 5L 5L 5L 5L

BOD5 ≤3 0.5L 0.5L 0.5L 0.5L

NH3-N ≤0.5 0.896 0.908 0.914 0.906

TN ≤0.5 2.11 1.92 2.09 2.04

TP ≤0.1 0.05 0.06 0.04 0.05

Fe ≤0.3 0.03L 0.03L 0.03L 0.03L

Mn ≤0.1 0.01L 0.01L 0.01L 0.01L

Pb ≤0.01 0.001L 0.001L 0.001L 0.001L

Hg ≤0.00005 0.00004L 0.00004L 0.00004L 0.00004L

Fecal coliform (No./L)

≤2000 1300 940 1100 1113

Water

temperature (℃) / 15.2 13.2 14.3 14.2

Monitoring Parameters

Limit Value (Class II, GB3838-2002)

Cross section upstream of the confluence of Yudong River and Yuliang River

2014-9-15 2014-9-16 2014-9-17 Mean

pH 6~9 6.78 6.76 6.81 6.78~6.81

SS / 4 5 4 4

DO ≥6 6.8 6.9 6.5 6.7

COD ≤15 5L 5L 5L 5L

BOD5 ≤3 0.5L 0.5L 0.5L 0.5L

NH3-N ≤0.5 0.033 0.058 0.046 0.046

TN ≤0.5 0.44 0.41 0.49 0.45

TP ≤0.1 0.03 0.01 0.02 0.02

Fe ≤0.3 0.03L 0.03L 0.03L 0.03L

Mn ≤0.1 0.01L 0.01L 0.01L 0.01L

Pb ≤0.01 0.001L 0.001L 0.001L 0.001L

Hg ≤0.00005 0.00004L 0.00004L 0.00004L 0.00004L

Fecal coliform (No./L)

≤2000 940 1300 700 980

Water

temperature (℃) / 21.3 18.6 19.5 19.8

Note: The cells in grey indicate the incompliant monitoring results.

Page 70: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 46 2015 -3

Drinking Water Quality Monitoring Unit: mg/L

Monitoring Parameters Limit Value (GB5749-

2006)

Drinking water feed inlet in work camp

2014-9-15 2014-9-16 2014-9-17 Mean

pH 6.5~8.5 6.92 6.94 6.89 6.91 6.93 6.92 6.89~6.94

Colority (degree) 15 2 2 2 2 2 2 2

Turbidity (NTU) 1 3L 3L 3L 3L 3L 3L 3L

Odor No No No No No No No No

Visible substance No No No No No No No No

Total hardness 450 196 199 198 197 201 193 197

TDS 1000 213 219 210 203 214 200 210

Sulfate 250 32.49 32.43 32.38 32.41 32.52 32.39 32.44

Nitrate 10 1.18 1.15 1.11 1.13 1.17 1.16 1.15

Chloride 250 3.40 3.38 3.42 3.43 3.37 3.39 3.40

Fluoride 1.0 0.12 0.14 0.11 0.09 0.13 0.14 0.12

Fe 0.3 0.03L 0.03L 0.03L 0.03L 0.03L 0.03L 0.03L

Mn 0.1 0.01L 0.01L 0.01L 0.01L 0.01L 0.01L 0.01L

Cu 1.0 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L

Zn 1.0 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L

Total bacteria (No./mL) 100 43 48 44 41 37 44 43

Fecal coliform (No./L) ND 70 60 92 120 70 69 80

Monitoring Parameters Limit Value (GB5749-

2006)

Drinking water feed inlet in work camp

2014-12-10 2014-12-11 2014-12-12 Mean

pH 6.5~8.5 6.78 6.84 6.83 6.81 6.85 6.83 6.78~6.85

Colority (degree) 15 3 4 5 3 6 5 4

Turbidity (NTU) 1 0.5 0.3 0.8 0.6 0.3 0.4 0.5

Odor No No No No No No No No

Visible substance No No No No No No No No

Total hardness 450 194 190 185 182 196 200 191

TDS 1000 220 215 209 205 222 225 216

Sulfate 250 31.77 31.73 31.45 31.52 31.60 31.56 31.60

Nitrate 10 0.91 0.87 0.88 0.82 0.88 0.90 0.88

Page 71: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 47 2015 -3

Monitoring Parameters Limit Value (GB5749-

2006)

Drinking water feed inlet in work camp

2014-6-16 2014-6-17 2014-6-18 Mean

Chloride 250 3.73 3.75 3.77 3.72 3.78 3.74 3.75

Fluoride 1.0 0.09 0.07 0.12 0.10 0.12 0.13 0.10

Fe 0.3 0.03L 0.03L 0.03L 0.03L 0.03L 0.03L 0.03L

Mn 0.1 0.01L 0.01L 0.01L 0.01L 0.01L 0.01L 0.01L

Cu 1.0 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L

Zn 1.0 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L 0.05L

Total bacteria (No./mL) 100 52 48 45 43 36 42 44

Fecal coliform (No./L) ND 70 92 69 60 120 92 84

Note: The cells in grey indicate the incompliant monitoring results.

2. Bai’anhe Reservoir Subproject

In September and December 2014, according to the revised environmental monitoring plan, the water quality at the project site has been tested and the results are detailed below. Surface water quality

Unit: mg/L

No. Monitoring Parameters

2014-9-2 2014-12.22 Class III of

GB3838-2002

1 Colority (degree) <5 7 -

2 Turbidity (NTU) 2.3 5.4 -

3 Odor No No -

4 Visible substance No Dust -

5 pH 8.25 7.23 6.0-9.0

6 Total hardness 295.3 325.2 -

7 TDS 328 394 -

8 Volatile phenol (in phenol)

<0.002 <0.002 ≤0.002

9 Sulfate 26.9 36.2 ≤250

10 Chloride <1.0 2.9 ≤250

11 Fluoride <0.1 0.2 ≤1.0

12 Fe <6*10-3 8.9*10-3 ≤0.3

Page 72: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 48 2015 -3

No. Monitoring Parameters

2014-9-2 2014-12.22 Class III of

GB3838-2002

13 Mn <7*10-3 <7*10-3 ≤0.1

14 Cu <5.0*10-2 9.8*10-2 ≤1.0

15 Zn <5.0*10-3 <5.0*10-3 ≤1.0

16 Pb <5.0*10-3 <5.0*10-3 ≤0.05

17 As <5.0*10-3 9.4*10-4 ≤0.05

18 Cd <1.0*10-3 <1.0*10-3 ≤0.005

19 Se <2.0*10-5 <2.0*10-5 ≤0.01

20 Hg <5.0*10-6 <5.0*10-6 ≤0.0001

21 Fecal coliform (No./L) >1600 1600 ≤10000

3. Jiancaogou Reservoir

In December 2014, the IA has entrusted the county environmental monitoring station to implement the monitoring of air quality, surface water quality and noise level around the project site. The monitoring results are shown below. Noise monitoring

Unit: Leq dB(A)

Date Time House 1 House 2

Dec. 15, 2014 Daytime 59.5 /

58.9 /

Dec. 16, 2014 Daytime / 58.6

/ 58.4

Limit Value (GB

GB12523—90) 70

Air Quality Monitoring (TSP)

Unit: mg/m3

Date Dam Site Reservoir Area

Dec. 15, 2014 0.432 0.212

Dec. 16, 2014 0.465 0.232

Dec. 17, 2014 0.512 0.226

Average 0.469 0.223

Page 73: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 49 2015 -3

Date Dam Site Reservoir Area

Limit value (Class II, GB3095-1996)

0.300

Surface Water Quality Monitoring

Unit: mg/L

Monitoring Parameters

Jiancaogou Water Source

100m downstream of iron bridge

Class III of GB3838-2002

2014-12-15

2014-12-16

2014-12-17

2014-12-15

2014-12-16

2014-12-17

pH 7.82 7.84 7.90 7.90 7.91 7.92 6.0-9.0

SS 8 9 9 10 10 9 /

COD 5L 5L 5L 5L 5L 5L ≤20

BOD5 2L 2L 2L 2L 2L 2L ≤4

NH3-N 0.12 0.11 0.10 0.12 0.12 0.11 ≤1.0

TN 4.30 4.22 4.26 4.32 4.28 4.30 ≤1.0

Fecal coliform (No./L)

<20 - - <20 - - ≤10000

Note: The cells in grey indicate the incompliant monitoring results.

4. Jinjiaqing Reservoir

In September 2014, the IA has entrusted Wudang District Disease Control Centre to implement the monitoring of surface water quality downstream of the dam. The monitoring results are shown below.

Page 74: Environmental Monitoring Report - adb.org · A First Issue 2015-3-19 HXD LWS LWS ... IMPLEMENTED ENGINEERING MEASURES FOR DOWNSTREAM ENVIRONMENT FLOW AND W ... PES …

GUIYANG ADB-LOAN PROJECT MANAGEMENT OFFICE

GUIYANG INTEGRATED WATER RESOURCES MANAGEMENT PROJECT

SEMI-ANNUAL EMP IMPLEMENTATION PROGRESS REPORT NO.4

ARTELIA PAGE 50 2015 -3

Surface Water Quality Monitoring

Unit: mg/L

Monitoring Parameters 04/09/2014 Class III of GB3838-2002

pH 7.58 6.0-9.0

Odor and taste No /

Visible substance No /

Turbidity (NTU) 0.3 /

Total coliform (MPN/100mL) >1500 ≤10000

Note: The cells in grey indicate the incompliant monitoring results.