Environmental Monitoring Report · 2019. 10. 8. · Environmental Monitoring Report # Semi Annual...
Transcript of Environmental Monitoring Report · 2019. 10. 8. · Environmental Monitoring Report # Semi Annual...
Environmental Monitoring Report
# Semi Annual Report (July-December 2018) October 2019
Indonesia: Flood Management in Selected River
Basins Sector Project
Prepared by Directorate General of Water Resources, Ministry of Public Works and Housing for
the Republic of Indonesia and the Asian Development Bank.
CURRENCY EQUIVALENTS (as of 31 December 2018)
Currency unit – rupiah (Rp) Rp1.00 = $0.0000688800
$1.00 = Rp14,518
ABBREVIATIONS
ADB – Asian Development Bank BBWS3 Cis – Balai Besar Wilayah Sungai Cidanau-Ciujung-Cidurian BWSM
DGWR MPWH
– – –
Balai Wilayah Sungai Maluku Directorate General of Water Resources Ministry of Public Works and Housing
NOTES
(i) The fiscal year (FY) of the Government of Indonesia and its agencies ends on 31 December. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2011 ends on 31 December 2011.
(ii) In this report, "$" refers to United States dollars This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
MINISTRY OF PUBLIC WORKS AND HOUSING DIRECTORATE GENERAL OF WATER RESOURCES
D I R E C TO R AT E O F R I V E R AN D C O AS T AL J l .Pa t imura No.20 Kebayoran Baru Jakar ta Se la ta n
FLOOD MANAGEMENT IN SELECTED RIVER BASINS SECTOR PROJECT (FMSRB)
ADB LOAN NO. 3440 INO
Environmental Safeguard Monitoring Report
(July – December 2018)
PT. DUTA CIPTA MANDIRI ENGINEERING CONSULTANT In Joint Venture with
PT. PUSER BUMI MEKON
Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
i
Table of Contents
Table of Contents .................................................................................................................... i
List of Figure .................................................................................................................... iv
List of Table ..................................................................................................................... v
Abbreviations and Acronyms ................................................................................................. vi
Executive Summary ...............................................................................................................1
Chapter 1. Introduction ...........................................................................................................1
1.1. Background ............................................................................................................... 1
1.2. Project Objectives ...................................................................................................... 1
1.3. Project Component .................................................................................................... 1
1.4. Project Scope and Implementation ............................................................................ 6
Chapter 2. Project Organization Structure and Environmental Management Team ...............7
2.1. Environmental Responsibilities .................................................................................. 7
2.2. The Detailed Engineering Design (DED) .................................................................... 7
2.2. Institutional Arrangements ......................................................................................... 8
3. Implementation, Monitoring and Reporting Compliance ........................................... 13
Chapter 3 Project Status of Ongoing Banten Contract Packages ........................................ 15
Chapter 4 Project Status of Ongoing Ambon Contract Packages ....................................... 19
Chapter 5 Environmental Monitoring ................................................................................... 22
5.1 Environmental Evaluation Responsibility ................................................................. 22
5.2 Environmental Approval and Permits ....................................................................... 23
5.3 Environmental Approval and Permits for Support Activities. ..................................... 23
5.2. ADB Assigned Categorization .................................................................................. 26
5.3. ADB Safeguard Policy Statement ............................................................................ 27
5.4. Contract Requirements ............................................................................................ 31
5.4.1 Air Quality ......................................................................................................................... 31
5.4.2 Noise Quality .................................................................................................................... 32
5.4.3 Disposal of Construction Spoil and Debris .................................................................. 33
Chapter 6 Environmental Monitoring Requirements ........................................................... 34
6.1. Environmental Monitoring Requirements ................................................................. 34
6.2. The Banten Province: Environmental Management and Monitoring Status .............. 34
6.2.1. Ciujung Dyke Development EMP Monitoring Progress ........................................... 34
6.2.2. Ambon Flood Control Way Ruhu EMP Monitoring Progress .................................. 35
Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
ii
6.2.3. Environmental Management Plan Implementation ................................................... 36
Chapter 7 Environmental Mitigation Measures Implementation .......................................... 37
7.1. Pre-Operation: Design Stage .................................................................................. 37
7.1.1. Landscape ........................................................................................................................ 37
7.1.2. Consents and NOC’s ...................................................................................................... 37
7.1.3. Existing utilities ............................................................................................................... 37
7.1.4. Construction Work Camps ............................................................................................ 38
7.1.5. Sources of Materials ...................................................................................................... 38
7.1.6. EMP Implementation Training ...................................................................................... 38
7.2. Operation: Construction Stage: Physical Characteristics ......................................... 38
7.2.1. Topography, Landforms, Geology and Soils ............................................................. 38
7.2.2. Water Quality .................................................................................................................. 39
7.2.3. Air Quality ........................................................................................................................ 40
7.2.4. Acoustic Environment .................................................................................................... 41
7.2.5. Aesthetics ......................................................................................................................... 42
7.3. Operation: Construction Stage: Biological Characteristics ........................................ 43
7.3.1. Biodiversity ...................................................................................................................... 43
7.4. Post Construction Stage: Clean-up ........................................................................... 43
7.5. Operation and Maintenance Stage .......................................................................... 44
7.5.1. Physical Characteristics: Acoustic Environment ....................................................... 44
Chapter 8 Key Environmental Issues and Related Action Plan .......................................... 45
8.1. Complaints and Response System ......................................................................... 45
8.2. Environmental Safeguard Compliance & Forthcoming EMP Actions ....................... 45
8.2.1. Dyke Contract Packages ................................................................................................ 46
8.2.2. Dredging, others Contract Packages ........................................................................... 49
8.2.3. Drainage and Flood Control Contract Packages ........................................................ 49
8.2.4. Monitoring activities in the reporting period................................................................. 50
8.3. Items of Focus .......................................................................................................... 51
8.3.1. Continued Application of EMP’s .................................................................................... 51
8.3.2. Compliance with Environmental Loan Covenants ...................................................... 51
8.3.3. Application for Site Clearance ...................................................................................... 52
8.3.4. Land Acquisition Status .................................................................................................. 52
8.4. Concluding Observations .......................................................................................... 53
8.4. Action Plan for Environmental Compliance .............................................................. 53
Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
iii
iv Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Annexes :
Annex 1 ENVIRONMENTAL SAFEGUARD MONITORING STATUS
Annex 2 MINUTE OF MEETING SOCIAL AND ENVIRONMENTAL SAFEGUARD FORFMSRB BATU MERAHAND WAY RUHU SUBPROJECTS AMBON, MALUKU
Annex 3 ENVIRONMENTAL PERMITS OF AMDAL CIUJUNG SERANG BANTEN, WAY BATU MERAH AND WAY RUHU AMBON
Annex 4 FLOOD MANAGEMENT IN SELECTED RIVER BASIN SECTOR PROJECT Form Pemeriksaan Lingkungan (Fase Konstruksi) diisi oleh Konsultan Supervisi dan Kontraktor Paket CW1 DAN CW2
Annex 5. Environmental Monitoring result on the construction of Ciujung Flood Dike in Banten
Annex 6 Estimation and Progress of FMSRB LARP Project Ambon City
Annex 7 Surat Arahan Tindak Lanjut Dokumen Lingkungan dari Propinsi Maluku dan Surat Arahan Dok Lingkungan dari Dinas Lingkungan Serang.
v Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
List of Figure
Figure 1.1 Location of the FMSRB Ciujung Serang ................................................................ 2
Figure 1.2 Location of the FMSRB Ciujung Serang ................................................................ 3
vi Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
List of Table
Table.2.1. Prioritized Civil Works packages to be implemented ............................................. 8
Table 2.2. Environmental Aspects Institutional Set-up ........................................................... 9
Table 2.3. Status of Project Implementation Units and Staffing ........................................... 13
Table 4.1. Estimation and progress of FMSRB LARP project Ambon City ........................... 19
Table 5.1. Applicable GoI Environmental Legislations ......................................................... 23
Table 5.2. ADB Safeguard Policy Status .............................................................................. 30
Table 6.1. Environmental Monitoring Progress ..................................................................... 35
Table 6.2. Environmental Monitoring Progress .................................................................... 36
Table 8.1 Condition of the Project in Banten and Ambon Seram until December 2018 ....... 46
Table 8.2: Component Forthcoming EMP Actions ................................................................ 48
Table 8.3: Dredging Component Forthcoming EMP Actions ................................................ 49
Table 8.4: Drainage & Flood Control Component: Forthcoming EMP Actions ...................... 50
Table 8.5 Environment Effect Monitoring Results in the Reporting Period .......................... 51
Table 8.6. Environmental Loan Covenants with Status Compliance ..................................... 51
Table 8.6. IEE Submission .................................................................................................. 52
Table 8.8: Environmental Compliance Action Plan ............................................................... 53
Table 8.9: Drainage and Flood Control Environmental Compliance Action Plan .................. 54
Table 8.10: Water Supply Environmental Compliance Action Plan ........................................ 55
Table 8.11: IES/SWM Environmental Compliance Action Plan.............................................. 57
Table 8.12 . Environmental Monittoring Plan ........................................................................ 58
vii Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Abbreviations and Acronyms
ADB = Asian Development Bank
BAPPENAS = National Development Planning Agency
BBWS3 Cis = Balai Besar Wilayah Sungai Cidanau-Ciujung-Cidurian
BWSM = Balai Wilayah Sungai Maluku
CBFRM = Community-Based Flood Risk Management
CPP = Community Participation in Procurement CQS
CQS = Consultant Qualification Selection
DED = Detailed Engineering Design
DGAIF = Directorate General of Agricultural Infrastructure and Facility
DSORGA I = Directorate of Synchronization of Regional Government Affairs I
DGWR = Directorate General of Water Resources
DMF = Design and Monitoring Framework
DPMU = District Project Management Unit
DRC = Directorate of River and Coast
DWRD = Directorate of Water Resources Development
DWRI = Directorate for Water Resources and Irrigation
EARF = Environmental Assessment and Review Framework
EIA = Environmental Impact Assessment
EMP = Environmental Management Plan
FRM = Flood Risk Management
FTP = Full Technical Proposal
IOL = Inventory of Losses
IEE = Initial Environmental Examination
IPP = Indigenous People Plan
LAR = Land Acquisition and Resettlement
MOA = Ministry of Agriculture
MOF = Ministry of Finance
MOHA = Ministry of Home Affairs
MPWH = Ministry of Public Works and Housing
NCB = National Competitive Bidding
NGO = Non-Government Organization
O&M = Operation and Maintenance
PAI = Project Administration Instructions
PAM = Project Administration Manual
viiiEnvironmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
PIU = Project Implementation Unit
PPMU = Provincial Project Management Unit
QBS = Quality Based Selection
QCBS = Quality-And Cost Based Selection
RBT = River Basin Territory or Wilayah Sungai
RBO = River Basin Organization or Balai Besar Wilayah Sungai/Balai Wilayah Sungai
RRP = Report and Recommendation of The President to The Board
SBD = Standard Bidding Documents
SES = Social and Economic Survey
SOE = Statement of Expenditure
SPRSS = Summary Poverty Reduction and Social Strategy
SPS = Safeguard Policy Statement
STP = Simplified Technical Proposal
TKPSDA = Tim Koordinasi Pengelolaan Sumber Daya Air (Basin Coordination Forum)
TOR = Terms of Reference
1 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Executive Summary
This ESMR report is a continuation report from the previous Semi Annually report. The report is the period July - December 2018.
Problem in Cidanau- Ciujung-Cidurian RBT, Banten Province
In the downstream area of the Ciujung river basin, the 11 km river reach downstream of the Pamarayan weir remains unprotected, while the other reach downstream of the highway is protected by Dyke structures designed for 5 years return period of flood. This has been the main cause of flooding in the highway and surrounding residential areas in year of 2007- 2008 and the flood occured on July 30, 2017. In some locations, river conveyance capacity needs to be increased to mitigate the flooding. This can be done through river dredging and channel excavation, but also through controlling sources of sediment yields from upper watershed areas.
Problem in Ambon-Seram RBT, Maluku Province
In Ambon, local government is planning to develop the city as a water-front city with emphasis on allocation, formation, sizing, and harmonizing space (land) in a way that helps promote the economic growth including the mitigation of flood hazard, exposure and vulnerability. Therefore, all flood management activities should be consistent with local government plans. There are two rivers to be included in this project, namely the Batu Merah and Way Ruhu Rivers. One main problem for Batu Merah River is some sliding and scouring along the river banks and problem for Way Ruhu Rivers is mainly watershed erosion.
The Problem Mitigation to those 2 RBTs
The 3 Cis RBT is in the specific river reach of Ciujung River, between Pamarayan Weir to the cross of the toll road / highway in Balaraja City. About 11 kilometers of embankment (levees) is to be built along the left and right sides of the Ciujung River. There will be some
other civil work measures, such as some river training structures such as groynes and revetments.
The Ambon-Seram RBT, is resolve plan to handle 2 river problems in surrounding of Ambon City. For Batu Merah River, there will be river training structures, such as groynes and revetments with emphasizing waterfront city concept that probably need some footpath and fences. Whereas for Way Ruhu river will construct some check-dam structures aiming to minimize sediment flow into river mouth that could harm Ambon Bay and to be a diinsentive for tourism.
There might be some complement measures concerning with environment aspects and social and gender development aspects, need to be implemented depending on the issues
2 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
may emerge after reviewing the existing documents and/or in collaborating and coordinating with the detail design processes done by Consulting Services Package-CS-01.
An environmental assessment using ADB’s Rapid Environmental Assessment (REA) checklist for urban development was conducted and the results of the assessment demonstrated that the sub-projects are unlikely to cause significant adverse impacts on the environment. The proposed infrastructure development sub-projects are classified as Environmental Category B as per the ADB SPS 2009 as no significant impacts are envisioned.
The related Initial Environmental Examination (IEE) report have been prepared in accordance with ADB SPS 2009 requirements for environment category B projects and recommends mitigation and monitoring measures to ensure no significant impacts as a result of the subproject.
The environmental mitigation measures, as stipulated in the EMP, as part of the respective Contract Documents and as given in Chapter 6 in this report and in the obtained environmental permit, are monitored during implementation of the proposed infrastructure development program. In order to perform the required contractual monitoring of the respective EMP’s, the contractor has engaged experienced laboratory and third party services in complying with the required environmental testing of parameters, as listed in Chapter 8 in this report.
1 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
FloodManagementin SelectedRiver BasinsSectorProject(FMSRB) ADB Loan No.3440-INO
Chapter 1. Introduction
1.1. Background
1. This report is the Semi-annually Environmental Safeguard Monitoring Report, which
covers the period from July 2018 to December 2018, in compliance with the environmental
scope of the construction supervision.
2. The main purpose of this monitoring is to ensure the implementation of
environmental mitigation measures during the construction phase. Environmental issues
also are anticipated to be identified in advance for avoidance and to ensure timely
completion of the project.
1.2. Project Objectives
3. Flood Management in Selected River Basin Sector Projects will minimize flooding
and also improve the quality of life for both people and the environment, including the Project.
The majority of the population living along crowded rivers, currently living under adverse
environmental conditions, will benefit from improvements better infrastructure and utility
services. As a result, the economy will benefit from increase eficiencies including improved
river infrastructure, land management, safe and sustainable water supply, improved drainage
facilities and improved sanitation services. The enhancement of local government abilities,
including a positive strategy of gender involvement and the participative role of society, in the
operation and maintenance of efficient urban facilities, will build ability for effective municipal
governance in the future.
4. The Subprojects would therefore be instrumental in attaining improved
environmental conditions, which would inspire economic growth and entice the poor people
to actively participate. This will be achieved through strengthened river management and
support for priority investments in river infrastructure and services required to meet basic
human needs, improve quality of life, and stimulate sustainable economic development
through equitable distribution of basic urban services to the residents that are technically
feasible, financially viable, climatically resilient, environmentally sustainable, socially
acceptable and operationally manageable.
1.3. Project Component
5. The Project consist of 2 projects component:
(1) The Development of Dyke left and right of Ciujung River Banten Province, Right
2 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
bank 11 km and Left bank 2 km. AMDAL document has been approved by
Environmental Agency of Serang No 666/97/Penceg/BLH/2014 on 29 October 2014.
Meanwhile Environmental Permit has been issued by Regent of Serang No.
666.1/105/BLH/2014 in November 2014.
(2) Ambon Flood Control Batu Merah and Way Ruhu AMDAL Approval of AMDAL
documents in 2015, Meanwhile Environmental Permit by Mayor of Ambon No. 20
in 16 March 2015 for AMDAL Ambon Flood Control Batu Merah and No 206 in 16
March 2015 for AMDAL Ambon Flood Control Way Ruhu respectively. Copy of
Environmental Permit AMDAL Ciujung Banten, AMDAL Ambon Flood Control Way
Batu Merah and Way Ruhu are attached in appendix 3.
6. The Project will strengthen climate resilience and disaster preparedness in 3 Kabupaten
in Province of Banten and Ambon City in Maluku Province. The 3 kabupaten in Province Banten
includes Kabupaten Serang, Pandeglang, and Lebak, and in Kota Ambon is Way Batu Merah
and Way Ruhu in Kecamatan Sirimau referring to Figure 1.1 and 1.2.
Figure 1.1 Location of the FMSRB Ciujung Serang
3 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Figure 1.2 Location of the FMSRB Ciujung Serang
4 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
(i) Planning for flood risk management enhanced
7. The project will support the RBOs models to (a) improve hydro-meteorological
data management; (b) develop flood as the basis for the preparation of flood risk
management plans (FRMPs); (c) develop flood forecasting, early warning system and
mapping of hazards, exposure, vulnerability, risk, and emergency response; and (d)
establish communication procedures. This will be complemented by institutional
strengthening, planning, and coordination in those provinces and districts that will use
FRMPs in updating provincial, district and/or city government spatial, midterm, and annual
plans.
(ii) Land management improved and flood infrastructure upgraded
8. The project will support RBOs to prepare detailed engineering designs (DEDs); meet
environmental and social safeguards; conduct tendering and O&M planning; and implement
infrastructure subprojects that are technically, socially, environmentally, and economically
justified. The infrastructure subprojects comprise the (a) rehabilitation and upgrading of
existing flood control structures; and (b) construction of new structures such as river Dykes,
spillways, coastal protection, retention basins, and check dams. Through the project,
communities in middle catchments will improve selected degraded land areas by
implementing soil and water conservation measures to reduce soil erosion. The project will
also (a) empower farmers groups in the Cidanau–Ciujung–Cidurian RBT to adopt
sustainable agriculture practices, including terracing and development of retention ponds;
and (b) implement measures to stop landslides and thus reduce sediment yields in both
RBTs.
9. In the next semi-annual report period, it will only discuss environmental management
and monitoring reports for infrastructure sub-projects. Social safeguard and institutional
and capacity building monitoring are separately reported.
(iii) Capacity for community-based flood risk management enhanced
10. To complement structural measures and improve flood resilience, community-based
flood risk management (CBFRM) groups in the flood plains that benefit from the early
warning system will be established, strengthened, and engaged in (a) identifying flood risks
at the local level; (b) prioritizing community-based measures to reduce flood risk; (c)
implementing priority measures to reduce flood risks, such as solid waste management and
construction and repair of small water infrastructure; and (d) improving disaster
preparedness by preparing an emergency response plan and developing corresponding
standard operating procedures.
5 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
(iv) Policy, coordination, and capacity at national level improved
11. To ensure effective policy and planning coordination, the project will support
independent monitoring, evaluation, and strategic coordination under the National Steering
Committee for Water Resources. A national strategy and a set of guidelines will be prepared
to institutionalize the FRM approach. The project will support the executing and implementing
agencies to undertake project supervision and strengthen the planning, implementation, and
management capacities of the implementing agencies.
(v) Environmental Safeguards:
12. This report will focus on implementation of safeguard measures of the Project .It will
report on measures taken to ensure that the Project will meet the government as well as
ADB safeguard policies. The task of supervising the safeguard policy implementation will
be undertaken by an environmental monitoring specialist.
13. The Environmental Safeguard Monitoring Specialist will be responsible in the overall
planning and management of the Safeguards Monitoring of the sub-projects.
14. The Specialist will provide technical guidance, capacity building, support and advice
to the Central Project Management Unit (CPMU), Project Implementation Units (PIUs) under
the BWS/BBWS in all aspects of environmental management and environmental safeguards
in accordance with the ADB Safeguard Policy Statement (SPS) 2009 and the environmental
rules and regulations of the Government of Indonesia. She/he will be responsible for but not
limited to the following:
(i) Review various reports/assessments and other relevant background information
available regarding the project or collect additional information to update him/herself
with the current status of environment related aspects of the Project and familiarize
him/herself with potential environmental issues relevant to the proposed
interventions in each sub-project area;
(ii) Refine the EARF as needed at project start after consultation with CPMU/CPIU and PIUs;
(iii) Carry out a review of the feasibility studies (including the IEE and AMDAL) with
regard to environmental impact and draw attention to changes which may have
become necessary since their preparation;
(iv) Develop strategy to effectively carry out the submission of environmental assessment
documents to the concerned government offices and ADB;
(v) Assist the CPMU in the preparation of the applicable ADB Rapid Environmental
Assessment (REA) checklists and GOI screening criteria and the environmental
categorization forms of the subprojects.;
(vi) Assist the CPMU in contracting, reviewing, submitting and obtaining approval of all
6 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
FloodManagementin SelectedRiver BasinsSectorProject(FMSRB) ADB Loan No.3440-INO
AMDAL and UKL-UPL reports that meet the requirements from the Government of
Indonesia as well as ADB SPS for category A (if one is to be proposed) and B
subprojects;
(vii) Lead in the conduct of capacity building/training of environment personnel in the Project;
(viii) Oversee preparation and approval of the site EMP of construction contractors and
monitor implementation of these for the purposes of quarterly reporting;
(ix) Undertake a review of potential cumulative and induced environmental impacts which
may occur downstream or elsewhere in the selected river basins as a result of project
interventions;
(x) Provide monitoring of project progress with regard to environmental targets and
indicators set out in the Design and Monitoring Framework (DMF);
(xi) Collaborate with provincial and district environmental agencies to include
environmental safeguards and awareness aspects in the capacity building and
awareness building activities;
(xii) Provide technical assistance and capacity building to the CPMU and PIUs in
monitoring the implementation of the IEE, AMDAL, and UKL- UPLs; and
(xiii) Assist the Team Leader in timely preparation of reports. Deliver the environmental
monitoring reports timely as per the guidance from Team Leader Assist the Team
Leader in timely preparation of reports. Deliver the environmental monitoring reports
timely as per the guidance from Team Leader.
1.4. Project Scope and Implementation
15. The Project is to be implemented over a 5.5 years from the date of loan effectiveness,
scheduled for completion by February 2022.
7 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Chapter 2. Project Organization Structure and Environmental Management Team
2.1. Environmental Responsibilities
16. The Department of Public Work and Housing (PWH) is the executing agency. PWH
has constituted a Project Management Unit (PMU) and Project Implementation Unit (PIU).
The PMU is headed by Project Director (PD). In order to put the project to logical conclusion
the PD is assisted by three consultant team to assist and support the PMU and PIU (Project
Implementation Unit). The Consultant teams comprise i) Detailed Design Services Consultant
(DDSC); ii) Project Implementation Management Services (CS02). The PMU based at Jakarta
is the executing agency assisted by the implementing agency PIU. The facilities created
during the sub-project will be operated and maintained by the PIU.
2.2. The Detailed Engineering Design (DED)
17. Component 2-C Detailed Engineering Design (DED) (including Environmental
Impact Assessment (EIA), social safeguards, economic analysis, tender documents and river
operation and maintenance plans) and Construction Supervision for the 3 Cis RBT and
Ambon-Seram RBT (DGWR, BBWS 3 Cis and BWSM)
18. There are originally eight (8) prioritized civil works packages to be implemented.
Based on the MOU ADB and GoI, Dyke planned to be constructed downstream of Ciujung
Flood Dyke (Package 1 and Package 2) to Toll road crossing, named Package 3 (CW3). So
there will be five packages prioritized works in Ciujung and three packages of works in BWSM.
The Ciujung Flood Dyke is situated in Serang District, passing five Sub-districts: (i) Cikeusal
Sub-district through Panyabrangan, Katulisan, Panosogan, and Gandayasa villages, (ii)
Bandung Sub-district through Desa Malabar, and Blokang villages, (iii) Pamarayan Sub-
district through Kampung Baru village, (iv) Keragilan village through Dukuh village, and (v)
Kibin Sub-district through Nagara village. List of Civil Works to be implemented is as follows:
8 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table.2.1. Prioritized Civil Works packages to be implemented
No Code Re-
code Name of Package
Allocated
($) Remark
1 CW1 CW1 Package 1 / Ciujung right side Dyke 9,146,000 11 km length
2 CW2 CW2 Package 2 / Ciujung left side Dyke 10,044,000 2 km
3 CW3 Package 3 / Ciujung Flood Dyke Extension
13,917,111 4.8 km
4 CW3 CW4 Check dams 2,200,000
CW4 CW5 Packages in Ciujung several package 11,143,000
5 1). Pamarayan River Dredging and
Dyke
6 2). Upper Pamarayan River
7 3). Rangkas Bitung, 11.15 km
8 4). Upgrading downstream Ciujung and
Cidurian Rivers
9 CW5 CW6 Packages in BBWS C3 several packages
12,092,000
CW6 CW7 Packages in Ambon Seram RBT 12,340,000
10 1). Batu Merah River Normalization
11 2). Way Ruhu River Normalization
12 3). Way Ruhu River mouth Dredging
13 4). Normalization of other Rivers
14 CW7 CW8 Packages in Ambon Seram RBT 9,890,000
Subtotal 80,772,111
19. Package 1 and Package 2 is the prioritized implementation works under the 3 Cis
RBO. The Overall Project Implementation schedule and the detailed Project Implementation
Schedule are shown in Annex 1.
2.2. Institutional Arrangements
20. Refer to Figure 2.1. There are 5 Consulting Services that assist the CPMU (CS-02)
and 4 CPIUs consisting of CS-05 for CPIU-DLEP, CS-06 for CPIU-DSORGA-1, and CS-04
for CPIU-DWRI Bappenas.
21. This is the Semi-annual Safeguards Monitoring Report covering the period 01 July
to 31 December 2018. It is prepared by the CPMU and submitted to ADB in accordance with
the safeguard monitoring and reporting requirements set out in the Project Administration
Manual, Project FMSRB Loan Agreement, EARF as well as the ADB Safeguard Policy
Statement 2009 (SPS 2009).
9 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
(1) Safeguard Plans Implementation Arrangements
22. The Directorate General of Water Resources Directorate of River and Coastal,
Ministry of Public Work (DGWR-DRC-MPWH) is the executing agency of the FMSRB. It
created a Central Project Management Unit (CPMU) under its Directorate General of Water
Resources (DGWR). The implementing agencies at the subproject level are two units working
together: the Satuan Kerja (SATKER) for the Provinces (Banten Province, and Ambon,
Maluku Province for Ciujung Flood Management in Selected River Basin Subproject, and
Batu Merah and Way Ruhu Sub-projects respectively, and the Provincial Project
Implementation Unit (PPIU); and each of the city’s Local Project Management Units (LPMU).
23. Environmental Aspects. The table below summarizes the institutional arrangement
for the environmental aspects of the project.
Table 2.2. Environmental Aspects Institutional Set-up
Unit Unit Function Responsible for Environmental
Aspects/ Function
Consultants Functions
Construction Phase
Ministry of Public
Work and Housing
Directorate General of
Water Resources
Directorate of River
and Coastal.
Executing Agency for
the FMSRB; provides
Technical
supervision and
responsibility over
the investment
Responsible as
executing Agency to
the Project
The consultant is responsible for PWH in carrying out work to assist PWH
Central Project
Management Unit
(CPMU) will be
created under the
Directorate General of
Water Resources
(DGWR).
Responsible for
FMSRB
Implementation in
Project cities;
coordinates with ADB
and other external
agencies Unit
Functions
CPMU Environment
Officer (to be
designated);
responsible for overall
environmental
supervision of
subprojects;
coordinates with PPIU
and LPMU Environmental Officers
to ensure Responsible for Environmental
Aspects/Functions
Project Implementation Support Consultants (PISC) and the Capacity Building Consultants (CBC); National Environmental Advisor
(part of PISC) will: (i)
review the revised IEEs
prepared during detailed
design stage, (ii) assist
CPMU in ensuring that
Consultants/Functions
SATKER, for the
Provinces as the
Provincial Project
Implementation Unit
Key implementation
unit in the field;
provides construction
closely monitor
Environmental requirements are address effectively; responsible for semi-
EMPs are included in the bidding documents and civil works contracts; (iii) assist the
10 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Unit Unit Function Responsible for Environmental
Aspects/ Function
Consultants Functions
(PPIU) construction progress annual environmental monitoring reports Preparation PPIU Environment Officer; responsible for overall environmental supervision of construction activities; ensures that the Contractor’s EMP is
properly implemented and monitored; prepares monthly environmental monitoring reports; provides input to the CPMU Environment Officer in the preparation of the semi-annual environmental monitoring reports
Preparation
CPMU, PPIU, and LPMU in monitoring of EMP implementation,
(iv) Training of CPMU, PPIU, and LPMU staff in environmental safeguards and monitoring; and (v) assist CPMU in preparation of semi- annual environmental monitoring reports.
FMSRB Training Consultant (part of CBC) shall facilitate hands-on
training of all FMSRB Operators Advisory services to be provided by the National Environmental Advisor (part of PISC)
City’s
Local Project
Management Unit
(LPMU).
Monitors
implementation of
the project in the city
and coordinates the
needed local inputs
and resources;
LPMU Environment
Officer; coordinates
With the city’s environment agency,
Dinas Lingkungan
Hidup (DLH); assists
the PPIU in
monitoring the
implementation of
EMP
assists the CSECC in
Addressing
environmental
complaints; LPMU
Chief sits as the
Chairperson of the
ad hoc City Flood
Management
Environmental
Complaints
Committee
Advisory services to be provided by the National Environmental Advisor (part of PISC)
11 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Unit Unit Function Responsible for Environmental
Aspects/ Function
Consultants Functions
(CFMECC)
Construction
contractors of the City
Flood Management
system
Implement
Construction
activities;
Implement The
Contractor’s
Contractor
Environment Officer
(to be designated);
Responsible for
implementation of the
Contractor’s EMP;
coordinates with
the
PPIU and LPMU
Environment Officers
and assist City DLH
CFMECC in
addressing
environmental
complaints; as the
Construction
Manager or
iinstructions
Superintendent sits
as A member of the
CFMECC
12 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Figure 2.1. Implementation Arrangement Inter Institutions
CS-
CS-06
CS-04
S-01
Figure 2.2. Flow of Communication Among Consultants
Note: Flowchart shows flow of information and does not reflect the level of authority.
CS-02
CS-01 CS-04 CS-06 CS-05
13 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
3. Implementation, Monitoring and Reporting Compliance
24. The existing IEE’s and EMP’s have been updated, based on the finalized detailed
engineering designs, which were prepared in accordance with the EARF and subproject
selection criteria related to safeguards, which were included in the respective Bid Documents
and form part of the respective Contract Documents for the currently awarded and active civil
works packages.
25. The PIU/Contractors are following all environmental mitigation and monitoring
provisions, as detailed in the respective IEE’s and EMP’s, which are being closely
implemented according to the environmental safeguard requirements of the project. This
entails monitoring of the related specific indicators to the current status of the respective
EMP’s for the active contract packages, as reviewed and recorded in this ESMR. See Table
2.3 below:
Table 2.3. Status of Project Implementation Units and Staffing
No PIU Institution Establishment
1 Central Project Management Unit (CPMU)
Ministry of Public Works & Housing
10 March 2017 No:133/KPTS/M/2016
2 Central Project Implementation Unit (CPIU)
Ministry of Agriculture 3 February 2017 No:02/Kpts/SR.160/B/09/2017
3 Central Project implementation Unit (CPIU)
Ministry of Home Affairs 15 June2016 No:610-824/Ket/Bangda/2016
4 Central Project Implementation Unit (CPIU)
Bappenas11
5 Project Implementation Unit (PIU) BBWS12
3C 30 September 2014 No:57/KPTS/BBWC-3/2014
6 Project Implementation Unit (PIU) BWS13
Maluku 3 October 2014 No:UM.01.03/BWS.MAL/X/129
7 Provincial Project Management Unit (PPMU) BANTEN
Bappeda14
Province Banten
8 Provincial Project Implementation Unit (PPIU) BANTEN
Agriculture Agency Banten
9 Provincial Project Implementation Unit (PPIU) BANTEN
Forest & Environment Agency Banten
10 Provincial Project Implementation Unit (PPIU) BANTEN
Public Works Agency Banten
11 Provincial Project Implementation Unit (PPIU) BANTEN
BPBD Banten
12 District Project Management Unit (DPMU)SERANG
Bappeda Serang
13 District Project Implementation Unit (DPIU)SERANG
Agriculture Agency Serang
19 September2014 No:800/455.a/DPKPP/2014
14 District Project Implementation Unit (DPIU) SERANG
Forest & Environment Agency Serang
15 District Project Implementation Unit (DPIU) SERANG
Public Works Agency Serang
14 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
No PIU Institution Establishment
16 District Project Implementation Unit (DPIU) SERANG
BPBD15Serang
17 District Project Management Unit (DPMU) LEBAK
Bappeda Lebak .
18 District Project Implementation Unit (DPIU) LEBAK
Agriculture Agency Lebak
19 District Project Implementation Unit (DPIU) LEBAK
Public Works Agency Lebak
20 District Project Implementation Unit (DPIU) LEBAK
Forest & Environment Agency Lebak
21 District Project Implementation Unit (DPIU) LEBAK
BPBD Lebak
22 District Project Management Unit (DPMU) PANDEGLANG
Bappeda Pandeglang
23 District Project Implementation Unit (DPIU) PANDEGLANG
Agriculture Agency Pandeglang
24 District Project Implementation Unit (DPIU) PANDEGLANG
Forest & Environment Agency Pandeglang
25 District Project Implementation Unit (DPIU) PANDEGLANG
Public Works Agency Pandeglang
26 District Project Implementation Unit (DPIU) PANDEGLANG
BPBD Pandeglang
27 Provincial Project Management Unit (PPMU) MALUKU
Bappeda Province Maluku
28 Provincial Project Implementation Unit (PPIU) MALUKU
Forest & Environment Agency Province Maluku
29 September 2014 No:522.4/SK/ Dishut-Mal/151/2014
29 Provincial Project Implementation Unit (PPIU) MALUKU
BPBD Province Maluku
29 September 2014 No:991/360.13/IX/2014
30 Provincial Project Implementation Unit (PPIU) MALUKU
Public Works Agency Maluku
31 District Project Management Unit (DPMU) AMBON
Bappeda Kota Ambon
32 District Project Implementation Unit (DPIU) AMBON
Public Works Agency Kota Ambon
33 District Project Implementation Unit (DPIU) AMBON
Forestry Agency Kota Ambon
34 District Project Implementation Unit (DPIU) AMBON
BPBD Kota Ambon
11Bappenas; Badan Perencanaan Pembangunan Nasional / National Planning & Development Agency 12BBWS:Balai Besar Wilayah Sungai 13BWS:Balai Wilayah Sungai 14Bappeda Badan Perencanaan Pembangunan Daerah / Region Planning & Development Agency 15BPBD:Badan Pencegahan Bencana Daerah / Region Disaster Mitigation Agency
15 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
FloodManagementin SelectedRiver BasinsSectorProject(FMSRB) ADB Loan No.3440-INO
Chapter 3 Project Status of Ongoing Banten Contract Packages
3.1. Monitoring on the Environmental preparation in BBWS C3, Banten
According to the Regulation of Ministry of Environment, Permen. LH No.16/2012, an
AMDAL/EIA is required for the construction of Ciujung Flood Dike package 1 (CW1) and
Package 2 (CW2). The AMDAL of the proposed construction has been prepared and endorsed
by the Government through the Notice No. 666/97/Penceg/BLH/2014 dated 29 October 2014,
and the Environmental Permit Certificate No.666.1/105/BLH/2014 has been issued on 3
November 2014.
Immediately after the mobilization of the new CS02 Consultant’s Environmental Specialist, he reviewed the status of the both subprojects. It was found that the AMDAL shall be still valid
because in fact the subprojects still under process of the land acquisition.
The Serang District Environment Agency has issued recommendation letter No.
660/1681/Penceg/DLH/2018 dated 29 June 2018 regarding the proposed construction of
Ciujung Flood Dike package 3 (CW3), for the extension of the Flood Dike(s) to the toll road of
about 4.5km at the downstream, the Project (BBWSC3) shall prepare and submit an addendum
of the AMDAL, and the RKL/RPL. The assessment and the endorsement of the addendum will
be provided by the Serang District Environmental Agency and the Environmental Permit
Certificate will be issued by the One-gate Integrated Services of Serang District.
Based on ADB SPS 2009, the construction of the Ciujung Flood Control can only be carried
out whenever the Environmental Permit was issued and the process of land acquisition and
compensation of the affected land have been completely paid.
According to the requirement of Serang District Environment Office, a semiannual monitoring
(RKL/RPL) shall be prepared and submitted by the BBWS C3.
3.1. Land Acquisition Progress in C3 Serang
For the CW1 and CW2 Subprojects, the land acquisition process has been almost completed,
while for the CW3 Subproject, the land acquisition is still under the process of survey and
mapping of the affected land.
The CS02 Consultant will assist the CS01 Consultant to prepare the TOR for the selection of
an accredited AMDAL Consultants to carry out the preparation of the AMDAL Addendum
document.
26. Until December 2018 land acquisition is still in process, especially at the CW1 and
CW2 project locations. At present the data on the recipient's compensation and the amount
is still in the calculation process. Planning for payment of land acquisition in the CW1 and
16 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
CW2 projects for the 2018 budget will be released around 128 hectares of the acquired area
of 156 hectares, with a total budget estimated at IDR182 billion.
27. BBWS C3 continues the LARP process for the construction of prioritized works of
Ciujung Flood Dike CW3, at the downstream of CW1 and CW2 to the highway bridge. Budget
for the Land Acquisition prepared by The BBWS C3 is IDR 186,782,030,000.
28. Since 2013 to 2017, consultation with the APs/WTD had beed conducted by the
Government for preparation of Land acquisition frameworks, and the LARP. Determination of
location were issued by the Governor in 2015 for the construction of CW1 and CW2. The
payment for the land compensation had been conducted for 1,394 households / 5,576
residents.
29. Budget for the Land Acquisition prepared by The BBWS C3 is IDR 186,782,030,000
(FY 2017 of IDR 185,882,030,000 and FY 2018 of IDR 900,000,000) and prepared by BWSM
of IDR 5,854,655,000 (FY 2017 of IDR 4,854,655,000 and FY 2018 of IDR 1,000,000,000).
Realization of the Land compensation payment can be summarized as Table 3.1 as follows:
30. Table 3.1. Summary of Realization of land compensation payment of FMSRB
BBWS/BWS
2017 2018
Plan Realization Plan Realization
DIPA (IDR) Ha IDR Ha DIPA (IDR) Ha IDR Ha
BBWS C3 185,882,030,000 158 182,244,006,000 128.8 Ha 900,000,000 30.00 0 21
BWSM 4,854,655,000 41/ 1,140,826,000 8,093m2 1,000,000,000 0.75 339,288,000 NA
1/ for the proposed 5 check-dams
31. Land acquisition for CW1 and CW2 until December j2018 in 5 sub-districts and 9
villages have been completed on 1,359 plots of lands out of a total of 1,625 plots of land. The
area of land acquired is approximately 128 ha out of an estimated total of 158 ha. The cost of
this acquisition is IDR 182,225,055,546.
Table 3.2 describes the amount of land that has been cleared and the area, buildings and trees
that have been compensated:
17 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 3.2.: The Implementation of land procurement until jDecember 2018 at Ciujung
Notes : Until December 2018 the compensation is not completed yet
3.2. Implementation of CW1 and CW2 Construction
32. In December 2018 a contract was signed for the construction of CW1 and CW2
Construction of Levees in Sungai Ciujung, Kabupaten Serang, Banten Province. The CW1
and CW2 construction contracts were signed between the CPMU and the Contractor: PT.
PT. Saca – PT. DutaRaya Jo for (right river bank CW1 and PT Basuki Rahmanta Putra (left
bank). Signing of the Contract on 5 December 2018.
33. At the end of December 2018 the Contractor has begun surveying and measuring the
project site at the construction sites of embankments CW1 and CW2.
34. In December 2018, a TOR was also prepared for the Addendum of the AMDAL
Ciujung River Flood Management in Banten. The addendum based on the Letter from the
Environmental Agency District of Serang, by representing the construction of CW3
representing the length of the embankment on the left and right of the Ciujung River is 4.8
km as shown in Figure 3.1.
Rencana Realisasi (SPM) Selisih
(Rp) (Rp) (Rp)
1 3 4 5 6 7 8 9=(7-8) 10
KABUPATEN SERANG
I. Kecamatan Cikeusal
1. Desa Gandayasa 167 154 21.06 20 19,787,485,478 19,787,485,478 0
2. Desa Panosogan 190 152 20.35 12 18,013,522,833 17,262,895,236 750,627,597
3. Desa Panyabrangan 232 102 24.24 13 19,921,171,958 19,972,524,366 (51,352,408)
1 0,20 2,512,777,807 2,512,777,807 0
4. Desa Katulisan 202 165 18.95 16 34,672,466,838 34,672,466,838 0
3,239,400 3,239,400 0
II. Kecamatan Bandung
1. Desa Malabar 147 145 13.04 13 15,905,663,890 15,905,663,890 0
2. Desa Blokang 181 176 18.56 18 18,675,170,803 18,675,170,803 0
III. Kecamatan Kragilan
1. Desa Dukuh 98 96 7.97 3 8,836,347,832 8,836,347,832 0
IV. Kecamatan Pamarayan
1. Desa Kampung Baru 166 158 13.73 13 15,928,754,030 15,928,754,030 0
V. Kecamatan Kibin
1. Desa Nagara 241 210 20.13 20 28,667,729,866 28,667,729,866 0
1624 1359 158.03 128 182,924,330,734 182,225,055,546
Realisasi
2
NO
LOKASI BIDANG LUAS (Ha) KEUANGAN
KET.(Kabupaten, Kecamatan, dan Desa) Rencana Realisasi Rencana
18 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Figure 3.1. Location of CW3 – FMSRB Ciujung Serang.
35. On 28 November 2018 a contract was signed with CS08, Contract No
1137/KTR/PPK-Ad.Satker/10/2018 with PT. Intersys Kelola Maju, CS08 serves as an external
consultant who will conduct an assessment of social safeguards in the CW1 and CW2
development projects in Cis3 Banten.
19 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Chapter 4 Project Status of Ongoing Ambon Contract Packages
36. For the Ambon-Seram, RBT Maluku, Stage I Contract Packages, until December
2018 there is no contract package in RBT Ambon-Seram. So there is no contract signed to
date, meaning that the implementation phase has not changed. There are 2 AMDAL
Documents that has been approved for two sub-projects of Ambon Flood Control. Namely
AMDAL for Flood Management in the Batu Merah River and Way Ruhu River located in Ambon
City, Maluku Province.
(i) Public Consultation
37. Implementation of community participation in the context of the Ambon AMDAL Study
Way Batu Merah Flood Control are as follows:
• The announcement of the AMDAL Study was in the form of a Sub-District Office
Pamphlet and at the Batu Merah District Office in the Sirimau District area.
• The implementation of the Socialization and Public Consultation activities directly,
in October 2013 took place at the District Meeting Hall.
• During the dissemination of this socialization activity participants included
representatives from the government as well as community leaders, youth and
community representatives from the Country in the Sirimau District area.
38. Construction of Check Dam Petra and Check Dam Yakobus (BWSM).
- Land acquisition has been completed as shown in Table 4.1 and Table 4.2.
- Need to accelerate the measurement and design review process. - Accelerate the
implementation of tenders and physical development).
Table 4.1. Estimation and progress of FMSRB LARP project Ambon City
No Description
Land Required
Realization The Rest Remarks
m² m² m²
I WAY RUHU LARPDATA 2014 : 19.095,94
1 Check Dam Hative Kecil 8.100,00 0,00 8.100,00 New Check Dam
2 Distribution Width (River + Dyke)
10.955,94 233,00 10.722,94 River Width = Variable
20 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
No Description
Land Required
Realization The Rest Remarks
m² m² m²
II SUB TOTAL I ( 1 + 2 ) 19.055,94 233,00 18.822,94 Length = 1,570.85m
= 1.57km
WAY BATU MERAH LARPDATA 2014 : 25.723,30
1 New Check DamYakobus 960,00 960,00 0,00 New Check Dam
2 Check Dam Petra 2.231,00 2.231,00 0,00 New Check Dam
3 Check Dam Rinjani 8.090,00 8.090,00 0,00 Rehabilitation Check
Dam Excisting
4 Check Dam Goa Maria (Plan) 6.000,30 0,00 6.000,30 New Check Dam
5 Check Dam Rinjani Atas (Plan) 3.100,00 0,00 3.100,00 New Check Dam
6 Distribution Width (River + Dyke 5.342,00 0,00 5.342,00 River Width = Varieties
SUB TOTAL I ( 1 + 2 + 3 + 4 + 5 + 6 ) 25.723,30 11.281,00 14.442,30 Length = 1,068.40m=
1.07 km
*Source; Bappeda Ambon, 2015.
Table 4.2. The status of the impelementation of the LARP is as follows:
N
o Location
Land
plots
Area, sqM Structure
Area,
sqM Status
Plan Actual Plan Actual Plan Actual
1 Kampong Rinjani, Batu Merah village, Sinmau Subdistrict,
1 1 8,093 8,093 0 0 Compensated and certified
2 Sungai Petra, Wahoka village, Sinmau Subdistrict,
3 3 2,231 2,231 0 0 Compensated. 2 plots was compensated in 2015, 1 plot was compensated on Dec 2017.
3 Ahuru River, Galala village.
2 2 960 960 0 0 Compensated. 1 plot was compensated in 2015, 1 other plot was compensated on Dec 2017.Under process of certification.
4 Way Ruhu River, Galala village
9 4 450 233 278 105 Compensated. 3 plots were compensated on Dec 2017 and 1 1 plot was compensated on May 2018.
Total 15 10 11,734 11,517 278 105
21 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Monitoring on the Environmental preparation in Ambon-Seram RBT, Maluku
39. The EIA (AMDAL) for the construction of Way Batumerah river flood control under
BWSM has been endorsed by the Mayor of Ambon, and an Environmental Permit Certificate
No. 206/2015 has been issued on 16 March 2015.
40. For the construction of Yacobus and Petra Check-dams (Package CW4), the Maluku
Provincial Environmental Agency has provided a recommendation by the letter No.
No.660/134.a/DLH/VII/2018, dated 27 July 2018 that BWSM has to prepare and submit an
addendum document of the endorsed AMDAL and the RKL/RPL due to the changes on the
subprojects location.
41. In the Addendum of the Batu Merah AMDAL, thr study shall present the detailed
engineering data (specific conditions) including quantities and sizes of the two checkdams.
22 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Chapter 5 Environmental Monitoring
5.1 Environmental Evaluation Responsibility
42. Based on Government Regulation No 27/2012 Regarding Environmental Permit, the
Authority to Assess AMDAL or UKL UPL Documents in the Environment Ministry and its services
below is:
a. Minister, for businesses and/or activities located:
1. in more than 1 (one) province;
2. in the territory of the Republic of Indonesia which is in dispute with other
countries;
3. in sea areas of more than 12 (twelve) nautical miles measured from the
coastline towards the high seas; and / or
4. across the borders of the Unitary State of the Republic of Indonesia with other
countries.
b. governor, for businesses and/or activities located:
1. in more than 1 (one) district / city in 1 (one) province;
2. across districts / cities; and / or
3. in the sea area at most 12 (twelve) miles from the coastline towards the open
sea and / or towards the islands waters.
c. regent/mayor, for businesses and / or activities located in 1 (one) regency / city area
and in the sea area at most 1/3 (one third) of the territorial sea of the province
1. Based on Government of Republic Indonesia Regulation No. 27/2012
concerning Environmental Permits, ANDAL and RKL-RPL that have been
prepared as referred to in Article 27 are submitted to:
a. The Minister through the Central EIA Assessment Commission secretariat,
for the Terms of Reference assessed by the Central EIA Assessment
Commission;
b. the governor through the provincial AMDAL Assessment Commission
Secretary, for the Terms of Reference assessed by the provincial AMDAL
Assessment Commission; or
c. the regent / mayor through the secretariat of the district / city AMDAL
Assessment Commission, for the Terms of Reference assessed by the
district / city AMDAL Assessment Commission.
23 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
5.2 Environmental Approval and Permits
43. Section 5.2 on Environmental Approval and Permits for Subproject Construction
presents the status of various permits of the subproject construction as well as environmental
permit.
44. The permits held in the subprojects currently running are AMDAL for Dyke in the
Ciujung River along 11.8 km and AMDAL of Ambon Flood Control in Way Ruhu, Maluku
Province. as detailed as described in Table 1 Appendix 1. For other subprojects that are still in
the process where the status will be explained in the Next Period Safeguard Monitoring Report
(January - June 2018).
5.3 Environmental Approval and Permits for Support Activities.
45. Environmental Aapprovals’ and Permits for Support activities in FMSRB subprojects
are listed as follow:
• During the construction process if the supply of fuel is for heavy equipment and
transport vehicles (trucks), including heavy equipment maintenance workshops
on site, the contractor is required to obtain permission regarding storage of toxic
and hazardous waste material (B3 waste).
• If in the construction process of the sub-project in the FMSRB project takes
quarry and borrow at a particular location, the contractor must have an
environmental permit for the location to be quarried or borrowed.
• If the use of quarry or borrow is provided by a third party, then the third party must
have an environmental permit for the quarry or borrow mining location.
Table 5.1. Applicable GoI Environmental Legislations
No
Legislation Requirement for the Project
Relevance
1 Act of the Republic of Indonesia No.5 of 1990 concerning Conservation of Living Resources and their Ecosystems
- Restriction on operation and process, which can be continued or can not be initiated in the ecologically critical areas
- Regulation on vehicles emitting smoke harmful to the environment
- Remedial measures for injuries to ecosystems
- Standards for quality of air, water, noise and soil for different areas and limits for discharging and emitting Waste
- Environmental guidelines
- The provisions of the Act apply to the entire subproject in the construction and operation and maintenance (O&M) phases.
2 Act of the Republic of Indonesia No. 32/2009 concerning
- Protection and management of the environment in project area. and integrated effort carried out
- The provisions of the Act apply to the entire subprojects in the
24 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
No
Legislation Requirement for the Project
Relevance
environmental protection and management.
to preserve environmental functions live.
- Prevent pollution and / or environmental damage covering planning, utilization, control, maintenance, supervision and law enforcement.
- Sustainable development and planned to integrate environmental aspects life, social, and economic strategy development to ensure integrity environment and safety, ability, welfare, and quality of life of the present generation and future generations.
construction and operation and maintenance (O&M) phases.
3
Act of the Republic of Indonesia No. 2/2012 concerning Land Procurement for Development for Public Interest
- All subprojects that are part of the FMSRB project that require land for Dyke and check dam must follow this law.
- Land Acquisition is an activity to provide land by giving proper compensation fair to those who have the right.
- The Eligible Party is the party who controls or have land acquisition objects.
- All subprojects that are part of the FMSRB project that require land for Dyke and check dam must follow this law.
4 Act of the Republic of Indonesia No. 13/2003 concerning Manpower.
- Compliance to the provisions on employment standards, occupational safety and health, welfare and social protection, labor relations and social dialogue, and enforcement
- Prohibition of employment of children and adolescent
- The provisions of the act apply to the entire subproject in the construction and O&M phases. Provides for safety of workforce during construction phase.
5 Government of Republic Indonesia Regulation No. 27/2012 concerning Environmental Permits.
- Regarding the procedures for the AMDAL assessment process at the central government, provincial and district / city levels
- Authority of the relevant Environmental Service Technical Team in evaluating AMDAL
- Duration of document completion.
- Requirements for obtaining an environmental permit.
- If the project location is in the district / city, then the authority to evaluate Environmental Documents (AMDAL and UKL-UPL) recommendations for Environmental Feasibility Documents (SKKL) and
- All subprojects in FMSRB may only carry out physical or construction work if the subproject has obtained an environmental permit.
25 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
No
Legislation Requirement for the Project
Relevance
environmental permits are issued by the Regent / Mayor.
- If the project location is in two regencies / cities, then the evaluation of the document, then the authority of the SKKL recommendation and environmental permit is issued by the Governor. (province)
- If the project location is in two provinces, then the evaluation of environmental documents, SKKL and environmental permits is the authority of the Central Ministry of Environment.
- Implications for the project monitoring and reporting supervision processes are carried out at the district / provincial / central level where environmental permits are issued.
6 Ministry of Environment Regulation No. 17/2012 Regarding community involvement in AMDAL
- Explain the importance of community involvement in the AMDAL preparation process
- Community rights and obligations, especially in providing input, opinions, direction and recommendation of AMDAL documents
- The community is involved in all steps in the preparation of the AMDAL starting from announcements, Public Consultations, to attending as representatives of the community at the Commission Session.
- Principles of justice and information disclosure.
7 Ministry of Environment Regulation No. 16/2012 Regarding the procedures for preparing AMDAL documents
- Explain in detail the preparation of the AMDAL document, starting from the preparation of the ToR, AMDAL to preparing the RKL-RPL.
- Explain the Scoping Process in AMDAL, Impact Evaluation and Holistic Evaluation. up to AMDAL and RKL RPL recommendations
- Evaluation of Physical, Chemical, Geological, Flora and Fauna, Socio-Economic and Community Health.
Systematics in preparing iAMDAL documents:
1. TOR AMDAL
2. AMDAL documents and
3. RKL RPL.
4. Permits required by proponents in preparing AMDAL. (i.e. principle permission, location permit, etc.).
8 Ministry of Environment Regulation No. 05/2012 About the types of business plans that require AMDAL studies.
- Criteria for a business to be classified as AMDAL / UKL-UPL or SPPL based on the size or extent and the important nature of the impact. - Screening method to determine whether a project must prepare an AMDAL or UKL-UPL.
- For FMSRB projects that have an important impact, they must prepare an EIA, while subprojects that have no significant impact must form a UKL-UPL.
26 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
No
Legislation Requirement for the Project
Relevance
9 Government
Regulation No.
41/1999 on Air
Pollution Control.
- Most subprojects must carry out air quality testing at the project location in accordance with RKL RPL or UKL UPL to determine air pollution levels during construction and Operation
- This government regulation is the standard quality of air pollution.
10 .Government
Regulation No.
48/1996 regarding
Noise Quality Level
- Most subprojects must carry out air quality testing at the project location in accordance with RKL RPL or UKL UPL to determine noise pollution levels during construction and Operation
- This government regulation is the standard quality of noise pollution.
11 Government Regulation of Republic Indonesia No 82/2001 Regarding Management of Water Quality and Water Pollution Control
- Most subprojects must carry out air quality testing at the project location in accordance with RKL RPL or UKL UPL to determine water pollution levels during construction and Operation
- This government regulation is the standard quality of water pollution.
12 ADB”s Good Practice on “Occupational and Community Health and Safety”, 2012
Occupational and Community Health and Safety consist of
1 Water Quality and Availability
2 Structural Safety of Project Infrastructure
3. Life and Fire Safety (L&FS)
4. Traffic Safety
5. Transport of Hazardous Materials
6. Disease Prevention Emergency Preparedness and Response
46.
Part of environmental management and monitoring FMSRB projects
39. The Ministry of Environment & Forestry (MoEF) is the government agency in the
administrative structure of the Central Government for the planning, promotion, co- ordination
and overseeing the implementation of environmental and forestry programs. MoEF oversees
all environmental matters in the country and is a permanent member of the Executive
Committee of the National Economic Council. The Ministry also plays a pivotal role as
pparticipant of the United Nations Environment Program (UNEP). The principal activities
undertaken by Ministry of Environment & Forests consist of conservation & survey of flora,
fauna, forests and wildlife, prevention & control of pollution, forestation & regeneration of
degraded areas and protection of environment, in the framework of legislations.
5.2. ADB Assigned Categorization
40. Asian Development Bank (ADB) requires the consideration of environmental issues in
27 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
all aspects of ADB’s operations, and the requirements for environmental assessment are
described in ADB SPS, 2009.This states that ADB requires environmental assessment of all
project loans, program loans, sector loans, sector development program loans, loans involving
financial intermediaries, and private sector loans.
41. The nature of the environmental assessment required for a project depends on the
significance of its environmental impacts, which are related to the type and location of the
project; the sensitivity, scale, nature and magnitude of its potential impacts; and the availability
of cost-effective mitigation measures.
42. Projects are screened for their expected environmental impacts and areas signed to
one of the following four categories:
• Category A. Projects could have significant adverse environmental impacts.
An EIA is required to address significant impacts.
• Category B. Projects could have some adverse environmental impacts but of lesser degree or significance than those in category A. An IEE is required to determine whether are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.
• Category C. Projects are unlikely to have adverse environmental impacts.
No EIA or IEE is required although environmental implications are reviewed.
• Category FI. Projects involve a credit line through a financial intermediary or an equity
investment in a financial intermediary. The financial intermediary must apply an
environmental management system unless all projects will result in insignificant
impacts.
43. As per above ADB environmental classification the development of Dyke in Ciujung
River and Ambon Flood Control in Way Ruhu sub-projects, considering the project activities,
and the scale of the project, as well as the significance of environmental impacts, the Project
has been classified as environmental category B which requires the preparation of an initial
environmental examination (IEE).
44. Meanwhile based on Ministry of Environment No.05/2012 Regarding types of
business plan and/or activities which must have analysis of environmental impacts, both
of subproject classified as AMDAL.
5.3. ADB Safeguard Policy Statement
45. Compensation to replace lost assets, livelihood, and income; The important elements
of ADB’s resettlement policy statement (APS2009) include the following:
(ii) Assistance for relocation, including provision of relocation sites with appropriate
facilities and services; and
28 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
(iii) Assistance for rehabilitation to achieve at least the same level of well-being with
the project as without it.
46. For any ADB operation requiring involuntary resettlement. Resettlement planning is an
integral part of project design, to be dealt with from the earliest stages of the project cycle
taking into account the following basic principles:
(i) Involuntary resettlement will be avoided whenever feasible. (ii) Where population displacement is unavoidable, it should be minimized. (iii) All lost assets acquired or affected will be compensated. Compensation is based
on the principle of replacement cost.
(iv) Involuntary resettlement is conceived and executed as part of a development
project or program. Affected persons need to be provided with sufficient resources
to re-establish their livelihoods and homes with time-bound action in co-ordination
with civil works.
(v) Affected persons are to be fully informed and closely consulted. (vi) Affected persons are to be assisted to integrate economically and socially into
host communities so that adverse impacts on the host communities are minimized
and social harmony is promoted.
(vii) The absence of a formal title to land is not a bar to ADB policy entitlements. (viii) Affected persons are to be identified and recorded as early as possible to
establish their eligibility, through a census which serves as a cut-off date, and
prevents subsequent influx of encroachers.
(ix) Particular attention will be paid to vulnerable groups including those without legal
title to land or other assets; households headed by women; the elderly or
disabled; and indigenous groups. Assistance must be provided to help them
improve their socio-economic status.
(x) The full resettlement costs will be included in the presentation of project costs and
benefits.
47. Refer to Table 5.2 for the status of the respective component sub-projects with regard to
compliance status to ADB’s policy statement (APS2009).
48. The Project is committed to ensuring the social and environmental sustainability of the
projects it supports. text as follows:
49. The goal of the policy is to promote the sustainability of project outcomes by protecting
the environment and people from projects’ potential adverse impacts. To achieve this
objective, policy principles have been formulated which will be adhered during project
implementation, as follow.
29 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
50. The elements of ADB environmental policy that should be considered during project
implementation as follow:
(i) Conduct an environmental assessment for each proposed sub-project to identify
potential direct, indirect, cumulative, and induced impacts and risks to physical,
biological, socioeconomic, and physical cultural resources.
(ii) Examine alternatives to the project’s location, design, technology, and components and their potential environmental and social impacts. Also consider
the no project alternative.
(iii) Avoid, and where avoidance is not possible, minimize, mitigate, and/or offset
adverse impacts and enhance positive impacts. Prepare an environmental
management plan (EMP) including cost estimates, and performance indicators.
(iv) Carry out meaningful consultation with affected people and other stakeholders,
and facilitate their informed participation. Establish a grievance redress
mechanism on subprojects’ environmental performance.
(v) Disclose a draft environmental assessment (including the EMP) in a timely
manner. Disclose the final environmental assessment, and its updates if any, to
affected people and other stakeholders.
(vi) Implement of the EMP and monitor its effectiveness. Document monitoring
results, including the development and implementation of corrective actions, and
disclose monitoring reports.
(vii) Do not implement project activities in areas of critical habitats, and in an area of
natural habitats, there must be no significant conversion or degradation, unless
it can meet requirements of safeguard policy.
(viii) Apply pollution prevention and control technologies and practices consistent with
international good practices.
(ix) Provide workers with safe and healthy working conditions and prevent accidents,
injuries, and disease. Establish preventive and emergency preparedness and
response measures to avoid adverse impacts and risks to the health and safety
of local communities.
(x) Conserve physical cultural resources and avoid destroying or damaging them.
30 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 5.2. ADB Safeguard Policy Status
ADB Safeguard Policy
Statement
Contract Package Status
Dyke Sub-
project in
Ciujung Sub-Project
Ambon Flood Control Way Ruhu Sub-
project
Check
Dam
Yakobus
Subproject
Check Dam
Petra Sub-project
Check
Dam
Rinjani Sub-project
(i) Involuntary resettlement will be avoided whenever feasible.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(ii) Where population displacement is unavoidable, it should be minimized.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(iii) All lost assets acquired or affected will be compensated. Compensation is based on the principle of replacement cost.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(iv) Each involuntary resettlement is conceived and executed as part of a development project or program. Affected persons need to be provided with sufficient resources to re- establish their livelihoods and homes with time-bound action in co-ordination with civil works.
Have been fulfilled
to be fulfilled
to be fulfilled
to be fulfilled
to be fulfilled
(v) Affected persons are to be fully informed and closely consulted.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(vi) Affected persons are to be assisted to integrate economically and socially into host communities so that adverse impacts on the host communities are minimized and social harmony is promoted.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(vii) The absence of a formal title to land is not a bar to ADB policy entitlements.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(viii) Affected persons are to be identified and recorded as early as possible to establish their eligibility, through a census which serves as a cut-off date, and prevents subsequent influx of encroachers.
Have been implemented through the installation of a notice board regarding ownership of the land and the boundary limit
Will be implemented through the installation of a notice board regarding ownership of the land and the boundary limit
Will be implemented through the installation of a notice board regarding ownership of the land and the boundary limit
Will be implemented through the installation of a notice board regarding ownership of the land and the boundary limit
Will be implemented through the installation of a notice board regarding ownership of the land and the boundary limit
31 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
ADB Safeguard Policy Statement
Contract Package Status
Dyke Sub-
project in Ciujung
Sub-Project
Ambon Flood
Control Way Ruhu Sub-
project
Check
Dam Yakobus
Sub-project
Check Dam
Petra Sub-project
Check
Dam
Rinjani Sub-project
(ix) Particular attention will be paid to vulnerable groups including those without legal title to land or other assets; households headed by women; the elderly or disabled; and indigenous groups. Assistance must be provided to help them improve their socio- economic status.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
(x) The full resettlement costs will be included In the presentation of project costs and benefits.
Have been implemented
Will be implemented
Will be implemented
Will be implemented
Will be implemented
Notes: During the safeguard reporting period the land acquisition process in the subprojects are underway. ADB regulation in SPS 2009 if possible will be implemented.
5.4. Contract Requirements
51. The following documents, relating to the identified environmental safeguards, form part
of the Contract Package and are part of the monitoring requirements in ascertaining the degree
of compliance:
a) Initial Environmental Examination (IEE) attached hereto as Appendix A to the Contract; b) Environmental Management Plan (EMP) attached hereto as Appendix B to the Contract;
and c) Quality Control / Quality Assurance (QA/QC) Plan: refer to Subsection 4 of the Contract.
5.4.1 Air Quality
52. During construction period the impact on air quality is mainly due to the material
movement. However air quality over a small area is affected, though, not in significant levels.
There is an increase in the dust levels all along the haul roads, the borrow areas and dumping
areas. The emissions from the construction machinery are the source of ambient air pollution
during the actual construction. Continuous use of generators, bulldozers, rollers, crane, trucks
etc. give rise to the ambient levels.
32 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
53. The mitigation measures are as follows:
i) In order to curb the increased fugitive dust emissions in the area due to
vehicular movement and raw material transport, provisions should be made for
sprinkling of water on the haul roads in the area. Sprinkling of water should be
carried out at least once a day on a regular basis during the entire construction
period. Special attention should be given to all the haul roads passing through
residential areas in the region. Daily inspection at haul roads and at construction
site should be carried out to ensure removal of construction debris to the landfill
sites. ii) Covered trucks shall be used for transportation of materials prone to fugitive
dust emissions. Additionally materials which may collect on the horizontal
surfaces of these trucks during loading should be removed before transportation. iii) Idling of delivery trucks or other equipment should not be permitted when not in
active use. iv) The emission levels from diesel vehicles being used should be checked on
monthly basis and brought to the required levels of emission standards. v) Proper care should be taken for storage of furnace oil, diesel, petrol etc. vi) Work schedule and the operation time of construction machinery should be
suitably modified to exercise a control on ambient air quality standards. vii) To ensure the efficacy of the mitigation measures suggested, air quality
monitoring shall be carried out as per environmental monitoring plan; viii) As soon as the construction activity is over the surplus earth should be utilized to
fill up the low lying areas, if any.
5.4.2 Noise Quality
54. Noise quality is also important for the construction phase. During the construction
phase, there would be an increase in ambient noise levels due to construction machinery
operation and movement of construction vehicles. Noise quality levels will be checked using
Government Regulation No. 48/1996 regarding Noise Quality Level.
55. The following mitigation measures may be adopted:
i) Construction yard shall be established at least 200m away from any residential
area. This will allow the noise to attenuate.
ii) Special acoustic enclosures should be provided for individual noise generating
equipment. Enclosures may be provided by way of noise shields, which can be
either brick masonry structure or any other physical barrier which is effective in
adequate attenuation of noise levels. A 3m structure made up of brick and mud
with internal plastering and of non-reflecting surface will be very effective in this
33 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
regard.
iii) Noise measurements should be conducted during construction to assess the
prevailing noise levels. Earplugs should be provided to those workers who will
be working very close to noise generating construction machinery.
iv) The exposure of workers to high noise levels especially near the construction
site needs to be minimized during construction period. This could be achieved
by: Job rotation Protective devices and Noise barriers. Stationery construction
equipment should not be located near human habitation in particular schools,
hospitals and institutions.
v) Noise levels from loading and unloading can be reduced by usage of various
types of cranes and by placing materials on sand or on the beds of sandy bags.
vi) Noisy construction equipment should not be permitted during night hours near
residential areas or sensitive areas. 5.4.3 Disposal of Construction Spoil and Debris
56. During construction about 15% of gravel, sand, bricks and cement is left as construction
spoils. It is advocated that construction spoils shall be disposed off at a site, as approved by
the PPK (Pejabat Pembuat Komitmen) or Commitment Maker Official. The Contractor shall
prepare a spoils management plan, which shall include the following:
i) Spoils Information:
Materials Type; Potential Contamination; Expected Volume and Sources; Spoil Classification
ii) Spoils Management:
Transportation of Spoil; Storage of Spoil; Contamination of Spoil; Approved Reuse and/or Disposal Sites
iii) Records of Reuse and/or Disposal
34 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Flood Management in Selected River Basins Sector Project (FMSRB) ADB Loan No. 3440-INO
Chapter 6 Environmental Monitoring Requirements
6.1. Environmental Monitoring Requirements
57. An environmental assessment using ADB’s Rapid Environmental Assessment (REA) checklist for urban development, was conducted and the results of the assessment
demonstrated that the subprojects will not cause significant adverse impacts. The proposed
infrastructure development program is classified as Environmental Category B as per the
ADB’s SPS 2009, as have significant impacts are envisioned. The related initial environmental examination (IEE) reports has been prepared in accordance with ADB SPS 2009 requirements
for environment category B projects and provide mitigation and monitoring measures, for no
envisaged significant impacts, as a result of implementing the subprojects.
58. The environmental mitigation measures, as stipulated in the respective EMP’s and in the obtained environmental permit, are monitored during the implementation program. In order
to monitor the respective EMP’s, the contractor has engaged laboratory and third party
services, in accordance with the provisions of the Contract Document and in complying with
the required environmental testing of parameters.
59. There are no indigenous people present in the subproject areas and so no impact on
Indigenous peoples (IPs). These subprojects are hence categorized as Category C for
Indigenous People. Therefore, no Indigenous Peoples Development Plan (IPDP) is required
for this sub-project.
60. The environmental mitigation measures, as stipulated in respective EMP’s for the
currently active civil works contract packages, are monitored as part of this ESMR.
6.2. The Banten Province: Environmental Management and Monitoring Status
61. Table 6.1 and Table 6.2 are still empty because there has been no progress that can
be reported. In this reporting period there was no physical work that could be carried out. But
tables are prepared so that in time the tools for monitoring are available.
6.2.1. Ciujung Dyke Development EMP Monitoring Progress
62. The progress, in imparting the required environmental mitigation measures and the
related monitoring for the active contract packages is shown in Table 6.1:
35 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 6.1. Environmental Monitoring Progress
Contract Packages
Civil
Works
Progress
(%)
Environmental Management and Testing
EMP
Progress
(%) Contract Amount
(USD)
Actual Expended
(USD)
Ciujung, Stage I:
1
2
3
4
5
Sub-totals
63. The overall progress to date, in implementing the EMP for the Ciujung Dyke
Development contract packages under FMSRB for Ciujung Stage I stands at 0%, in terms of
the expended contracted amount of USD …(TBD)………, of the total Environmental mitigation and monitoring requirement of USD…(TBD)…….. The physical progress made for the civil works associated contracts currently stands at (TBD) …..%. To date, no contract package has
been completed.
6.2.2. Ambon Flood Control Way Ruhu EMP Monitoring Progress
64. The progress, in imparting the required environmental mitigation measures and the
related monitoring for the 5 active contract packages being implemented
under……………(TBD)…………., in accordance with the contracted EMP, is shown in Table
6.2:
36 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 6.2. Environmental Monitoring Progress
Contract Packages
Civil
Works
Progress
(%)
Environmental Management and Testing
EMP
Progres
s (%)
Contract Amount
(USD)
Actual Expended
(USD)
……….., Stage I:
1
2
3
4
5
Sub-totals
65. The overall progress in implementing the EMP, for the Ambon Flood Control Way Ruhu
contract packages under FMSRB for ……(TBD)……….., stands at 0 %, in terms of the expended contracted …(TBD)…….., of the total Environmental mitigation and
monitoring requirement of USD……………(TBD)……….. The physical progress made for the civil works associated contracts currently stands at 0%. One package.
6.2.3. Environmental Management Plan Implementation
66. Refer to Annexure 1 for the record of the status of the Environmental Management and
Monitoring Plan, based on the Project description, Environmental Baseline Data and
Environmental Impacts for Contract Packages and the respective infrastructural component of
the FMSRB implementation program.
37 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Chapter 7 Environmental Mitigation Measures Implementation
67. The proposed Dyke in Ciujung, dredging, Dyke in Way Ruhu, etc, subprojects have
been designed and planned to minimize any adverse environmental impacts, and adequate
provisions have been incorporated into the project design to mitigate the impacts.
68. Preliminary design, field visits and results of the rapid environmental assessment
completed by DDSC indicate that the subproject implementation program will not have major
negative impacts as activities will be localized / site-specific and of short duration.
69. Several aspects of the environment, that are not expected to be affected by the
proposed subprojects, can be screened out of the assessment at this stage according due to
the following mitigation requirements:
7.1. Pre-Operation: Design Stage
7.1.1. Landscape
Impact : Adverse effects on aesthetics
Mitigation Measure : Development of the designs for the Dyke, others are compatible
with the surrounding environment.
7.1.2. Consents and NOC’s
Impact: : Failure to obtain necessary consents, permits, NOC’s can result in design revisions and/or stoppage of the works.
Mitigation Measure : Obtain all necessary consents, clearances, permits, NOC’s prior to start of the Works.
- Acknowledge in writing and provide report on compliance all
obtained on consents, clearances, permits, NOC’s.
- Include in detailed design drawings and documents all
conditions and provisions if necessary.
7.1.3. Existing utilities
Impact: : Disruption of services.
Mitigation Measure : - Identify and include locations and operators of theses utilities
in detailed design documents to prevent unnecessary
disruption of services during construction activities.
- Require construction contractors to prepare contingency plan
to include actions to be done in case of unintentional interruption
of services.
38 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
- Require construction contractors to prepare spoils management
plan:
i) Spoils Information:
Materials Type; Potential Contamination; Expected Volume
and Sources; Spoil Classification.
ii) Spoils Management:
Transportation of Spoil; Storage of Spoil; Contamination of
Spoil; Approved Reuse and/or Disposal Sites.
iii) Records of Reuse and/or Disposal.
7.1.4. Construction Work Camps
Impact : Stockpile areas, storage disposal areas, heavy metal, disruption to
traffic flow and sensitive receptors
Mitigation Measure: Determine locations prior to award of construction contracts.
7.1.5. Sources of Materials
Impact : Extraction of material can disrupt natural land contours and vegetation
resulting in accelerated erosion, disturbance in natural drainage,
patterns, ponding and water logging and water pollution.
Mitigation Measure: Prepare list of approved quarry sites and sources of materials.
7.1.6. EMP Implementation Training
Impact : Negative irreversible impact to the environment, Negative irreversible
impact to the environment, construction schedule, and EMP reporting.
Mitigation Measure: Project manager and all key workers will be required to undergo EMP
implementation including spoils management, Standard Operating
Procedures (SOP) for construction works; health and safety (H&S),
core labor laws, and applicable environmental laws.
70. The EMP implementation training for the active contracts has been completed where all
the contractor representatives and PPK and Consultant Engineers were present.
7.2. Operation: Construction Stage: Physical Characteristics 7.2.1. Topography, Landforms, Geology and Soils
Impact : Significant amount of gravel, sand, and cement will be required for this
subproject. Extraction of construction materials may cause localized
changes in topography and landforms. The impacts are negative but
short-term, site-specific within a relatively small area and reversible
by mitigation measures.
39 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Mitigation Measure :
- Utilize readily available sources of materials. If contractor procures
materials from existing burrow pits and quarries, ensure these
conform to all relevant regulatory requirements.
- Borrow areas and quarries (If these are being opened up
exclusively for the subproject) must comply with environmental
requirement as applicable. No activity will be allowed until formal
agreement is signed between PIU,land owner and contractor.
7.2.2. Water Quality Impact : Excavation, run-off from stockpiled materials, and chemical
contamination from fuels and lubricants may result to silt-laden
runoff during rainfall which may cause siltation and reduction in the
quality of adjacent bodies of water. The impacts are negative but
short term, site- specific within a relatively small area and
reversible by mitigation measures.
Mitigation Measure : -
Prepare and implement a spoils management plan.
- Prioritize re-use of excess spoils and materials in construction
activities. If spoils will be disposed, consult with Local Authority
on designated disposal areas.
- All earthworks must to be conducted during dry season to
maximum extent possible to avoid the difficult working
conditions that prevail during monsoon season such as
problems from runoff.
- Location for stockyards for construction materials shall be
identified at least 300m away from watercourses. Place storage
areas for fuels and lubricants away from any drainage leading
to water bodies.
- Take all precautions to minimize the wastage of water in the
construction activities.
- Take all precautions to prevent entering of wastewater into
streams, watercourses, or irrigation system. Install temporary
silt traps or sedimentation basins along the drainage leading to
the water bodies.
- Ensure diverting storm water flow during construction shall
not lead to inundation and other nuisances in low lying areas.
- While working across or close to any water body, the flow
40 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
of water must not be obstructed. Ensure no construction
materials like earth, stone, or appendage are disposed of in
a manner that may block the flow of water of any watercourse
and cross drainage channels.
- Monitor water quality according to the environmental
management plan.
- To evaluate water quality, use quality standards referring to
Government Regulation of Republic Indonesia No. 82/2001
Regarding Management of Water Quality and Water Pollution
Control
7.2.3. Air Quality Impact : Conducting works at dry season and moving large quantity of
materials may create dusts and increase in concentration of
vehicle-related pollutants (such as carbon monoxide, sulfure
oxides, particulate matter, nitrous oxides, and hydrocarbons) which
will affect people who live and work near the sites. The impacts
are negative but short-term, site-specific within a relatively small
area and reversible by mitigation measures.
Mitigation Measure :
- Damp down exposed soil and any sand stockpiled on site by
spraying with water during dry weather.
- Use tarpaulins to cover soils, sand and other loose material when
transported by trucks.
- Unpaved surfaces used for haulage of materials within settlements
shall be maintained dust-free.
- Arrangements to control dust through provision of windscreens,
water sprinklers, and dust extraction systems shall be provided at
all hot-mix plants, batching plants and crushers (if these
establishments are being set up exclusively for the subproject).
- Monitor air quality.
- To measure air quality, use quality standards referring to
Government Regulation No. 41/1999 on Air Pollution Control.
41 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
7.2.4. Acoustic Environment Impact : Construction activities will be on settlements, in and near schools, and
areas with small-scale businesses. Temporary increase in noise
level and vibrations may be caused by excavation equipment, and
the transportation of equipment, materials, and people. The
impacts are negative but short-term, site-specific within a relatively
small area and reversible by mitigation measures.
Mitigation Measure : - Involve the community in planning the work program so that
any particularly noisy or otherwise invasive activities can be
scheduled to avoid sensitive times.
- Plan activities in consultation with Local Authority so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance.
- Use of high noise generating equipment shall be stopped during night time.
- Horns should not be used unless it is necessary to warn other
road users or animals of the vehicle’s approach.
- Utilize modern vehicles and machinery with the requisite
adaptations to limit noise and exhaust emissions, and ensure that
these are maintained to manufacturers’ specifications at all times.
- All vehicles and equipment used in construction shall be fitted
with exhaust silencers. Use silent-type generators (if required).
- Monitor noise levels. Maintain maximum sound levels not
exceeding 80 decibels (dBA) when measured at a distance of
10 m or more from the vehicle/s.
- If it is not practicable to reduce noise levels to or below noise
exposure limits, the contractor must post warning signs in the
noise hazard areas. Workers in a posted noise hazard area
must wear hearing protection.
- Identify any buildings at risk from vibration damage and
avoiding any use of pneumatic drills or heavy vehicles in the
vicinity. Complete work in these areas quickly.
42 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
7.2.5. Aesthetics
Impact : The construction activities do not anticipate any cutting of trees
but will produce excess excavated earth (spoils), excess
construction materials, and solid waste such as removed
concrete, wood, packaging materials, empty containers,
spoils, oils, lubricants, and other similar items. The impacts
are negative but short-term, site-specific within a relatively
small area and reversible by mitigation
measures.
Mitigation Measure : - Prepare the Debris Disposal Plan.
- Remove all construction and demolition wastes on a daily
basis.
- Coordinate with Local Authority for beneficial uses of
excess excavated soils or immediately dispose to
designated areas avoid stockpiling of any excess spoils.
- Suitably dispose of collected materials from drainages,
unutilized materials and debris either through filling up of
pits/wasteland or at pre-designated disposal locations.
- All vehicles delivering fine materials to the site and carrying
waste debris for disposal shall be covered to avoid spillage
of materials. All existing roads used by vehicles of the
contractor, shall be kept clear of all dust/mud or other
extraneous materials dropped by such vehicles.
- Lighting on construction sites shall be pointed downwards
and away from oncoming traffic and nearby houses.
- In areas where the visual environment is particularly
important or privacy concerns for surrounding buildings
exist, the site may require screening. This could be in the
form of shade cloth, temporary walls, or other suitable
materials prior to the beginning of construction.
- The site must be kept clean to minimize the visual impact
of the site. Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas.
43 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
7.3. Operation: Construction Stage: Biological Characteristics
7.3.1. Biodiversity Impact : Activities being located in the built-up area of
Ciujung Stage I, There are no protected areas in or around
subproject sites, and no known areas of ecological interest.
There are no trees at the site that need to be removed.
Mitigation Measure : - Check if t r e e -cutting will be J equired during detailed
design stage. No trees, shrubs, or groundcover may be
removed or vegetation stripped without the prior
permission of the environment management specialist.
- If during detailed design cutting of trees will be required,
compensatory plantation for trees lost at a rate of standard
goverment price of trees for every tree cut, in addition to tree
plantation as specified in the design, will be implemented by
the contractor, who will also maintain the saplings for the
duration of his contract.
- All efforts shall be made to preserve trees by evaluation of
minor design adjustments/ alternatives (as applicable) to save
trees.
- Special attention shall be given for protecting giant trees
and locally-important trees (with religious importance) during
implementation.
- Prevent workers or any other person from removing and
damaging any flora (plant/vegetation) and fauna (animal)
including fishing in any water body in the subproject vicinity.
- Prohibit employees from poaching wildlife and cutting of
trees for firewood.
7.4. Post Construction Stage: Clean-up
Impact : Damage due to debris, spoils, excess construction materials. Mitigation Measure :
- Remove all spoils wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required.
- All excavated roads shall be reinstated to original condition.
- All disrupted utilities restored.
- All affected structures rehabilitated/compensated.
44 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
- The area that previously housed the construction camp is to be
checked for spills of substances such as oil, paint, etc. and
these shall be cleaned up.
- All hardened surfaces within the construction camp area shall
be ripped.
- All imported materials removed and the area shall be top soiled
and regressed using guidelines set out in the re-vegetation
specification that forms part of this document.
- The contractor must arrange the cancellation of all
temporary services.
- Request PMU/PMSC to report in writing that worksites and
camps have been vacated and restored to pre- project conditions
before acceptance of work.
7.5. Operation and Maintenance Stage
7.5.1. Physical Characteristics: Acoustic Environment Impact : Temporary increase in noise level and vibrations. The impacts are
negative but short-term, site- specific within a relatively small area
and reversible by mitigation measures.
Mitigation Measure: - Plan activities in consultation with the Local Authority so that
activities with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance.
- Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity complete work in these areas quickly.
45 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
FloodManagementin SelectedRiver BasinsSectorProject(FMSRB) ADB Loan No.3440-INO
Chapter 8 Key Environmental Issues and Related Action Plan
8.1. Complaints and Response System
71. Records are kept by the respective PIU’s of all grievances received, including contact details of complainant, date the complaint was received, nature of grievance, agreed
corrective actions and the date these were affected and final outcome. The number of
grievances recorded and resolved and the outcomes are displayed/disclosed in the PMU, PIU
offices, as applicable.
72. All costs involved in resolving complaints (meetings, consultations, communication
and reporting / information dissemination) are borne by the concerned PIU at town-level.
Costs related to unresolved and/or escalated grievances are to be met by the PMU.
73. The Grievance Redressed Mechanisms have been established in the respective PIU
for pre-FMSRB resolutions of problems. Based on this established mechanism, the PIU have
the provision of interaction with registered complaints and the requisite response sensitivity.
8.2. Environmental Safeguard Compliance & Forthcoming EMP Actions
74. Through the monitoring checklists preparation is being developed as per the
contracted Environmental Monitoring and Management Plan for each contract package, the
compliance with the application of the EMP, by the respective Contractors, are presently
under scrutiny, which are in line with the specific scope of work, as defined by the respective
Contract Packages and prevailing field conditions.
75. The respective PIU and Consultant teams are to continue their vigilance in
identification of the related environmental safeguard issues/problems. The contractors are
regularly being directed to ensure proper implementation of the respective EMPs, inclusive of
their contractual obligations regarding the environmental management, frequency and nature
of the sample testing and monitoring requirements, as per ADB guidelines and Contract
provisions.
76. Á designated Nodal Environmental Officer (PMU)/Consultant has the overall
responsible for implementation of the respective EMP’s and sample testing of the contracted environmental monitoring parameters, which continues to be conducted through external
testing agencies for the respective contract packages.
46 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
77. Related training, in terms of the Environmental Management and Testing, as part of
the mitigation and monitoring processes, needs to be constantly arranged. This is of
particularly importance as additional contract packages are awarded throughout the course of
the FMSRB development program.
8.2.1. Dyke Contract Packages
78. The Development of Dyke Ciujung still Pre-Construction Phase so no physical Activity.
The Monitoring for physical such as air quality, water quality in and others environmental
component during construction activity. The condition of the project in Banten, Ambon Seram
until the end of December 2018 sees Table 8.1.
Table 8.1 the Condition of the Project in Banten and Ambon Seram until December 2018
A. Cidanau-Ciujung-Cidurian (3 Cis) River Basin Territory1
No
Physical Intervention
Potential Potential Social Impact
Readiness Description FS/DED Environmental
Impact
1 Upstream and
downstream of Pamarayan weir (Ciujung)
River Dredging, Dyke,
Emergency Spill W ay
Detail Design was contracted in 2015
No significant
impact, B
Classification
Requires land
acquisition for dumping site,
AMDAL and
LARP to be prepared
2 Rangkas bitung
(Ciujung) 5.6 Km of new Dykes located upstream of
Pamarayan weir
Completed (2009). Requires review
No significant impact, B
Classification
Requires land acquisition
Private land,
AMDAL approved in December 2014, LARP
was prepared in 2015
3 Ciujung river mouth Dredging of river 3- 4 km up to the
mouth
Completed (2012) No significant impact, B
Classification
No significant impact, B
Addendum AMDAL to be prepared
4 Check Dams
(upper Ciujung) At different Locations
8 as per planning and 4 additional
Completed (2009) and 2010) Review design 2015-2016
No significant Impact B
Classification
To be confirmed
AMDAL to be prepared, review design (2016)
5 Retention basins
along the 11km Dyke (additional) + spill way?
49 Ha Identified
and investigate
d during TA
No significant
Impact B
Classification
Requires land
Acquisition -AMDAL approved in December 2014 -LARP to be prepared in 2017
Determination location to be prepared in 2017
6 Cidurian sediment control
Construction of 8 check dams to
reduce the
sediment yield and reduce the runoff
Completed AMDAL to be prepared
TBD TBD
7 Implementation of the retention
basins
Long storage development in
Ciujung
Available TBD TBD TBD
1
BBWS 3CIs = Balai Besar Wilayah Sungai Cidanau-Ciujung-Cidurian, BWSM = Balai Wilayah Sungai Maluku, CBFRM = Community-basedflood risk management, DGWR =Directorate General of Water Resources, MOA = Ministry of Agriculture, MOHA = Ministry of Home Affairs, MPW = Ministry of Public Works, RBT = River Basin Territory
47 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
No
Physical Intervention
Potential Potential Social Impact
Readiness Description FS/DED Environmental
Impact
Lama, and W TP 8 Construction of the
new drainage network and rehabilitation of existing drainage
system in Serang,
Lebak, Pandeglang and Tangerang
Rearranging and building a micro urban drainage systems and industries that are connected to the drainage system macro
To be prepared
No significant impacts,
No significant impacts
TBD
B. Ambon – Seram River Basin Territory
Priority Given by BWS Maluku
ID
Physical Intervention
Description
FS/DED
Potential Environmental
Impact Potential
Social Impact
Readiness
1 Check Dam
Systems 4 No in each of 5 rivers
Partially/ To be revised
To be confirmed Requires land acquisition. Two area check dams in Batu Merah under land acquisition process.
To be prepared.
2 River normalization and Dyke construction
TBD To be Prepared To be confirmed Requires land acquisition
AMDAL and
LARP was prepared in 2013 need to be updated
3 River normalization and Dyke construction
TBD To be Prepared To be confirmed Requires land acquisition
AMDAL completed LARAP Preparation in
2015
4 River normaliza- tion and Dyke
construction
TBD To be Prepared To be confirmed Requires land acquisition
To be prepared
5 River dredging in
W ay Ruhu 2.5 km from the river mouth
Completed AMDAL No land acquisition
DED completed,
AMDAL Completed
6 River dredging in
Batu Merah 1.6 km from the river mouth
Completed AMDAL No land acquisition
DED completed,
AMDAL Completed
7 Improve the drainage system surrounding Batu Merah and W ay Ruhu
To discharge the flood or storm water to the sea directly via artificial drainage
To be prepared TBD TBD TBD
8 Flood Control Project: Diversion Tunnel
Flood Mitigation in Batu Merah
To be prepared TBD
TBD
TBD
9 Development of retention ponds
Flood Mitigation in Batu Merah
To be prepared TBD
TBD
TBD
10 Flood control structure
Way Ruhu Existing Dyke Heightening and Riverbank Improvement/ Rehabilitation
To be prepared TBD
TBD
TBD
48 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
ID
Physical Intervention
Description
FS/DED
Potential Environmental
Impact Potential
Social Impact
Readiness
11 Flood Control Project
Batu Gajah, Existing Dyke Heightening and Riverbank
To be prepared TBD
TBD
TBD
Improvement/ Rehabilitation
12
River restoration and rehabilitation
Batu Gajah upstream river sections improvement
To be prepared TBD
TBD
TBD
13
River restoration and rehabilitation
Batu Gantung upstream river sections improvement
To be prepared TBD
TBD
TBD
79. For the project during construction phase, have some impact to the environment for
example impact to air, water, etc. Table 8.2 informs the Active EMP, Status of EMP and
Actions Proposed. The resulting specific actions proposed, along with details of the
additional corrective measures required, to be applied during the next monitoring period
(July to December 2018) are given in Table 8.2:
Table 8.2: Component Forthcoming EMP Actions
Name of Sub Project
Active EMP
Status of EMP
See Note
Actions Proposed/ Additional Corrective Measures Required
Ciujung Banten Development Program: 3.packages for a total of 3…)
1 TBD TBD TBD
• Enforce dust suppression measures;
• Proper disposal of debris;
• Personal Protective Equipment (PPE) needs constant vigilance for improvement;
• Maintaining of records;
• Disposal of old filter media at designated location;
• Continue regime of sample testing;
• Strict surveillance by PIU/Consultant; required on EMP implementation;
• Safety barriers need to be maintained
2 TBD TBD TBD
3 TBD TBD TBD
4 TBD TBD TBD
5 TBD TBD TBD
49 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
8.2.2. Dredging, others Contract Packages
80. The summary of compliance level of EMP application, for the active Dredging
Contract Packages, as stipulated in the contracted EMP and in compliance with ADB
guidelines, given in Table 8.3
Table 8.3: Dredging Component Forthcoming EMP Actions
Name of Sub Project Active
EMP
Status of EMP
See Note
Actions Proposed/ Additional Corrective Measures Required
Ciujung Banten Development Program: (… Dredging packages)
1 TBD TBD TBD
o Enforce dust suppression measures;
o Proper disposal of debris; o Personal Protective Equipment
(PPE) needs constant vigilance for improvement;
o Maintaining of records; o Disposal of old filter media at
designated location; o Continue regime of sample
testing; o Strict surveillance by
PIU/Consultant; required on EMP implementation;
o Safety barriers need to be maintained
2 TBD TBD TBD
TBD TBD TBD
3 TBD TBD TBD
TBD TBD TBD
4
TBD TBD TBD
5 TBD TBD TBD
Note: EMP Rating: Poor (0); Below Satisfactory (1); Partially Satisfactory (2); Satisfactory (3 - 4); Excellent (5)
8.2.3. Drainage and Flood Control Contract Packages
81. The summary of compliance level of EMP application, for the active Drainage and
Flood Control Contract Packages, as stipulated in the contracted EMP and in compliance
with ADB guidelines, are given in Table 8.4:
50 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 8.4: Drainage & Flood Control Component: Forthcoming EMP Actions
Name of Sub Project Active
EMP
Status of EMP
See Note
Actions Proposed/ Additional Corrective Measures Required
Ciujung Banten Development Program: (Drainage and Flood Control packages)
1 TBD TBD TBD • Enforce dust suppression
measures;
• Proper disposal of debris;
• Personal Protective Equipment
• (PPE) needs constant vigilance
for improvement;
• Maintaining of records;
•
2 TBD TBD TBD
3 TBD TBD TBD
4 TBD TBD TBD
• Continue regime of sample
testing;
• Strict surveillance by
PIU/Consultant; required on EMP
implementation;
• Safety barriers need to be
maintained ……………… Development Program: (………. Drainage and Flood Control packages)
1 TBD TBD TBD
• Enforce dust suppression
measures;
• Proper disposal of debris;
• Personal Protective Equipment
• (PPE) needs constant vigilance
for improvement;
• Maintaining of records;
• Disposal of old filter media at
designated location;
• Continue regime of sample
testing;
• Strict surveillance by
PIU/Consultant; required on EMP
•
2 TBD TBD TBD
3 TBD TBD TBD
4 TBD TBD TBD
5 TBD TBD TBD
Note: EMP Rating: Poor (0); Below Satisfactory (1); Partially Satisfactory (2); Satisfactory (3 - 4); Excellent (5)
8.2.4. Monitoring activities in the reporting period
82. No field monitoring activities related to the construction activities had been
conducted since there were no civil works contracts awarded yet. Compliance monitoring
during this reporting period related to the pre-construction phase activities ensuring that
mitigation measures will be included during the detailed engineering design and in the
tender documentation. In addition, with detailed engineering design still being undertaken,
the IEE will be updated accordingly.
51 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 8.5 Environment Effect Monitoring Results in the Reporting Period
Location Parameter Date Monitoring
Value Relevant Gov
standard Not applicable yet during this reporting period. Information in this table will be provided when construction activities commence.
8.3. Items of Focus
8.3.1. Continued Application of EMP’s
83. Application of the respective EMP is to be achieved through continuous monitoring
in the field, followed by satisfactory completion of all identified mitigation measures for the
related environmental impact requirements, in accordance with the appropriate monitoring
checklist and generated environmental baseline data for this semi-annual ESMR-, dated
June 2018.
8.3.2. Compliance with Environmental Loan Covenants
84. The status of compliance of ADB’s major Environmental Loan Covenants shown in Table 8.6. below:
Table 8.6. Environmental Loan Covenants with Status Compliance
Environmental Loan Covenants Status of Compliance
a. Environmental Management Plan :
The State and the project proponent shall ensure that the Project is carried out in accordance with the existing environmental laws and regulations
Under compliance in accordance with ADB Environmental Policy and Environmental Assessment Guidelines 2009.
Environmental Loan Covenants Status of Compliance
Indonesia and ADB’s environmental guidelines, in particular the Asian Development Bank (ADB) safeguard policy statement (SPS), 2009;
(a) All monitoring and mitigation steps shown in the Initial Environmental Examination, which are provided for inclusion in the Environmental Management Plan carried out for the Project
Under compliance: IEE screening of potential environmental impact and mitigation measures applied according to project location, specific sector development and associated design requirements.
52 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Environmental Loan Covenants Status of Compliance
(b) Project implementation shall include consultation with local communities on environmental issues;
Under compliance: completed under the design stage, which is ongoing by DDSC. This is also forming part of the ongoing PMSC/ICCDC public awareness campaign requirements
During construction consultation with local communities on environmental issues are being considered.
(c) PIU shall take a proactive role in environmental planning, management and monitoring;
Under compliance: initiated as the concept and detailed design stages have been progressed.
(a) Clearances shall be obtained for all applicable Project components prior to commencement of work on those components;
Under compliance: all necessary clearances and land acquisition issues resolved. Specific clearance details are now complied for appropriate contract packages.
b. Operation & Maintenance :
The State shall ensure that each Project undertakes operation and
maintenance of project facilities in
accordance with good practice for Dyke,
dredging and others, and in accordance
with the regulations of Indonesia.
Shall be ensured as required
Will form part of the training requirement in effective O&M practices by PMSC
O&M Manuals to be prepared by PMSC.
8.3.3. Application for Site Clearance
85. The applications have been progressed to various stages of completion for Ciujung
Dyke Development, according to ADB guidelines and Indonesia statutory regulations and
requirements, in obtaining final site clearance, refer to Table 8.6 for a summary of the
current status of the IEE submission:
Table 8.6 IEE Submission
No IEE Submission Date Remark
1 Lower Batu Merah River
Normalization
December
2013 Ambon Province
2 Initial Environmental Examination
Ciujung River
December
2013 Banten Province
3 Summary of IEE Ciujung River December
2013 Banten Province
4 TBD
8.3.4. Land Acquisition Status
86. Land acquisition procedures have been developed during the period pertaining to
53 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
develop of Dyke and dredging, which has been progressed to various stages of completion
for Banten and Ambon, according to ADB guidelines and Indonesia statutory regulations
and requirements.
87. Refer to for the details of the respective land acquisition requirements and the
staged progress will be reported in the next period of Environmental Safeguard Monitoring
Report,
8.4. Concluding Observations
88. Implementation of RKL RPL the Development of Dyke in Ciujung River at
present is land acquis i t ion. This activity is a part of pre-construction.
89. Implementation of RKL- RPL, The Development of Ambon Flood Control Way
Ruhu at present is land acquisition. This activity is a part of pre – construction.
90. There is no information yet about kind of document (AMDAL or UKL UPL) and
information about of project:
(a) In Banten: (1) Check Dams; (2) Pamarayan River Dredging and Dyke;
(3) Upper Pamarayan River; (4) Rangkas bitung (11.15 km); (5)
Upgrading downstream Ciujung and Cidurian River
(b) In Maluku: (1) Batu Merah River Normalization; (2) Way Ruhu
River Normalization; (3) Way Ruhu River Mouth Dredging; (4) and
Normalization of other Rivers
8.4. Action Plan for Environmental Compliance
91. According to the current status of the Environmental Management Plan for the
monitored Contract Packages to date, for forthcoming activities in attaining compliance
at “satisfactory/excellent” level, the following Action Plan requirements are to be followed,
refer to Tables 8.8 to 8.12:
Table 8.8: Environmental Compliance Action Plan
Action Responsibility Timeframe Level of Compliance
…………Contract Packages: 5 ……1, Stage I packages:
……………………………………
…….. 2, Stage I packages:
Instruction to contractors for implementation/ compliance and to PIU/Consultant for enforcement monitoring for:
• Proper disposal of debris
PIU, PMSC, Contractors
Continuous
54 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Action Responsibility Timeframe Level of Compliance
Correct maintained records regarding ESMR;
• Restoration of road/lane after sectional completion – at earliest Camp site management;
• Water sprinkling during dry period;
• Implementation of spoils management plan;
Contract Packages:…..Ciujung Dike Development, Stage I: packages: ……………….
…….. 2, Stage … packages: ………………………
• Due attention to increase in noise level and vibrations caused by excavation equipment, and the transportation of equipment, materials, and people;
• Coordinate with local authorities and prepare prior approved Traffic Management Plan;
• Enforcement Gender protocol according to the Gender Action Plan;
• Appointment of qualified supervisor
Action Responsibility Timeframe
to ensure EMP implementation.
Continued Focus Group Discussion (FGD) / Public consultation during construction
PIU, PMSC, Contractors
On regular basis: at least once in a month
Sample monitoring and testing of the designated Environmental Parameters in full accordance with the contracted financing plan and testing requirements
Contractors Immediate action, notwithstanding possible closure of sites
Follow up action for completion of the verified monitoring for the ESMR
PIU, PMSC, Contractors
Immediate
Grievance Redress Mechanism: To implement according to EMP
PIU Contractor Ongoing
EMP implementation and monitoring Training
PIU, PMSC, Contractors
Ongoing
Table 8.9: Drainage and Flood Control Environmental Compliance Action Plan
Action
Responsibility
Timeframe Level of
Compliance
55 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Drainage and Flood Control Contract Packages : Ciujung Dike Development, Stage I packages :………………………
…………………………………….
………, Stage I packages: ……………………………………… ……………………………………
Instruction to contractors for implementation/ compliance and to PIU/Consultant for enforcement monitoring for: • Proper disposal of debris
Correct maintained records regarding ESMR;
• Restoration of road/lane after sectional completion – at earliest Camp site management;
• Water sprinkling during dry period;
• Appointment of qualified supervisor to ensure EMP implementation.
PIU, PMSC,
Contractors
Continuous
Action Responsibility Timeframe
Continued Focus Group Discussion (FGD) / Public consultation during construction
PIU, PMSC, Contractors
At least once in a month
Sample monitoring and testing of the designated Environmental Parameters in full accordance with the contracted financing plan and testing requirements
Contractors Immediate action, notwithstanding possible closure of sites
Follow up action for completion of the verified monitoring for the ESMR
PIU, PMSC, Contractors
Immediate
Grievance Redressal Mechanism: To implement according to EMP
PIU Contractor Ongoing
EMP implementation and monitoring Training
PIU, PMSC, Contractors Ongoing
Table 8.10: Water Supply Environmental Compliance Action Plan
Action Responsibility Timeframe Level of Compliance
Water Supply Contract Packages: …. Ciujung Dike Development, Stage … packages: ……………………….
….. …….., Stage I packages: …………………………………
Instruction to contractors for implementation/ compliance and to PIU/Consultant for enforcement monitoring for:
• Proper disposal of debris
PIU, PMSC,
Contractors
Continuous
56 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Action Responsibility Timeframe Level of Compliance
• Correct maintained records regarding ESMR;
• Restoration of road/lane after sectional completion – at earliest
• Camp site management;
• Water sprinkling during dry period;
• Monitoring and sample testing of environmental parameters;
Action Responsibility Timeframe
• Appointment of qualified supervisor to ensure EMP implementation.
Continued Focus Group Discussion
(FGD) / Public consultation during
construction
PIU, PMSC,
Contractors
At least once in a month
Sample monitoring and testing of
the designated Environmental
Parameters in full accordance with
the contracted financing plan and
testing
Contractors Immediate action, notwithstanding possible closure of sites
Follow up action for completion of
the verified monitoring for the ESMR
PIU, PMSC, Contractors
Immediate
Grievance Redress Mechanism: To
implement according to EMP
PIU Contractor Ongoing
EMP implementation and monitoring
Training
PIU, PMSC, Contractors
Ongoing
57 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 8.11: IES/SWM Environmental Compliance Action Plan
Action Responsibility Timeframe Level of Compliance
Integrated Environmental …………. Contract Package:……………..
Instruction to contractors for implementation/ compliance and to enforcement monitoring for:
• Proper disposal of debris Correct maintained records ESMR;
• Restoration of road/lane after sectional completion – at earliest Camp site management;
• Appointment of qualified supervisor to ensure EMP implementation.
PIUPMC, Conracors
Continuous
Action Responsibility Timeframe
Integrated Environmental …………. Contract Package: FMSRB/PIR/PT/01
Focus Group Discussion (FGD) PIU, PMSC, Contractors
At least once in a month
Sample monitoring and testing of the designated Environmental Parameters in full accordance with the contracted financing plan and testing Requirements
Contractors
Immediate action, notwithstanding possible closure of sites
Follow up action for completion of the verified monitoring for the ESMR
PU,PMSC, Contractors
Immediate
Grievance Redressal Mechanism: To implement according to EMP
PIU Contractor
Ongoing
EMP implementation and monitoring
Training
PIU, PMSC, Contractors
Ongoing
Non-compliance
Contract Package: ……………………..:
Obtain all necessary consents, clearances, permits, NOC’s prior to start of the Works;
Action/Responsibility: District to submit IEE with application to DoE for Site Clearance Certificate.
Immediate requirement
58 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Table 8.12 . Environmental Monittoring Plan
Project stage Prohect Activity
Potential Environmental
Impact
Proposed Mitigation Measures
Institutional Responsibilities
Cost
Pre Construction Phase
Construction Phase
Operation and Maintenance Phase
Mitigation Measure
Parameter to be
Monitored Location Measurement Frequency Responsibility Cost
Pre-Construction Phase
a) Changes in people's attitudes and perceptions
Construction Phase
a) Decreasing ambient air quality
b) Increased Noise and Vibration Intensity
c) Decrease in surface water quality
d) Slope erosion and sedimentation
e) Increased community income
f) There is a business opportunity
g) There are job opportunities
59 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Mitigation Measure
Parameter to be
Monitored Location Measurement Frequency Responsibility Cost
h) Public Health Disorders
i) Increased traffic density
j) Aesthetic changes and
environmental cleanliness
Operation and Maintenance Phase
a) Slope erosion and sedimentation
b) Decreasing the quality of surface water
c) Changes in people's attitudes and perceptions
60 Environmental Safeguard Monitoring Report (July to December 2018)
Project Implementation Management Services (CS02) Flood Management in Selected River Basins Sector Project (FMSRB)
ADB Loan No. 3440-INO
Annex
Annex 1
ENVIRONMENTAL SAFEGUARD MONITORING STATUS
The development of the Flood Management project either in Banten or in Ambon
Maluku as per December 2018 which is related to environmental aspects are as follows:
A. In Ciujung, Cidurian and Cidanau River, Banten Province
Table 1. Project Progress until June 2018 in Ciujung Banten
No
Name of Project Kind of
Document
Phase
Status
Note
1 The Development of Dyke (11 km) • Right bank 11 km • Left bank 2 km
AMDAL • Pre Construction
• Approval of AMDAL documents 2015
• Environmental Permit by Bupati Serang No. 666.1/105/BLH/2014 in November 2014
There is no Implementation on Report of RKL RPL yet
2 The Development of Dyke (continue to toll way 6 km)
AMDAL DED - -
3 Check Dams AMDAL Review design - - 4 Pamarayan River
Dredging and Dyke AMDAL DED - -
5 Upper Pamarayan River AMDAL / UKL UPL
DED - -
6 Rangkasbitung (11.15 km)
AMDAL / UKL UPL
DED - -
7 Upgrading downstream Ciujung and Cidurian Rivers
AMDAL / UKL UPL
DED - -
In detail according to RKL RPL of The Development of Dyke in Ciujung, the
Environmental Monitoring have to give monitoring as shown in Table below.
Table 2. The Environmental Monitoring Result of The Development of Dyke in Ciujung
Type of Work
Length (Km)
Safeguard Document Required
Activities
Environmental Monitoring Result
Environmental Issues
Mitigation Action
Location
Status
New construction
of Dyke
11 km AMDAL Land compensati
on
•Change of Perception Society
• before the Dyke is implemented, the implementing contractor will conduct more detailed socialization of the planned activities to the affected communities
• accommodate suggestions and responses from surrounding communities delivered during the socialization of the activity plan
• Coordinate with relevant agencies to follow up on responses, suggestions from the community and coordinate with landholders whose land will be used as access roads for vehicles
• Installation of bulletin boards at the construction site of the Ciujung embankment
•GRM (Grievance Redress Management) Unit to receive feedback and complaints from surrounding communities
• Coordinate / approach the relevant government
At social boundaries, that are Kecamatan: (i) Bandung, (ii) Pamarayan, (iii) Keragilan, and (iv) Cikesal Kabupaten Serang, Banten Province
• Approval of AMDAL documents
•environmental permit
B. In Ambon, Maluku Province
Table 3. Project Progress until the end of 2018 in Ambon, Maluku
No
Name of Project
Kind of Document
Phase
Status
Note
1 Ambon Flood Control Way Ruhu
AMDAL • Pre Construction
• Approval of AMDAL documents 2015
• Environmental Permit by Walikota Ambon No. 20 in March 2015
There is no Implementation Report of RKL RPL yet
2 Checkdam 1 (8.093
m2) Location Kampung
Rinjani Batu Merah Village and Way Hoka Kecamatan Sirimau Kota Ambon
UKL UPL / AMDAL
• Pre Construction
- Land acquisition Process -
3 Check dam 2 Petra River (1.000 M2), Way Hoka Village, Kec Srimau Kota Ambon (front ground)
UKL UPL • Pre Construction
- Land acquisition Process -
Petra River (529 M2), Way Hoka Village, Kec Srimau Kota Ambon Petra River (723 M2), Way Hoka Village, Kec Srimau Kota Ambon
4 Check dam 3 UKL UPL • Pre Construction
- Land acquisition Process
Ahuru River in Wai Hoka and Batu merah Village, Kec Sirimau Ambon City Ahuru River in Waihoka and batumareah Village, Kec Sirimau Ambon City 5 Batu Merah River Normalization
ADMAL / UKL UPL
DED - -
6 Way Ruhu River Normalization
AMDAL / UKL UPL
DED - -
7 Way Ruhu River Mouth Dredging
AMDAL UKL UPL
DED - -
8 Normalization of other Rivers
AMDAL / UKL UPL
DED - -
In detail according to RKL RPL of The Ambon Flood Control Way Ruhu the
Environmental Monitoring have to give monitoring as shown in Table below.
Table 4. The Environmental Monitoring Result of The Development of Ambon Flood
Control Way Ruhu
Type of Work
Length
(Km)
Safeguard
Document
Required
Activities
Environmental Monitoring Result
Environmental
Issues
Mitigation
Action
Location Status
New
construction
of Dyke
….km AMDAL Land
compensati
on
• Change of
Perception
Society
• before the
Dyke is
implemented
, the
implementing
contractor
will conduct
more
detailed
socialization
of the
planned
activities to
the affected
communities
• accommodate
suggestions
and
responses
from
surrounding
communities
delivered
during the
socialization
of the activity
plan
• Coordinate
with relevant
agencies to
follow up on
responses,
suggestions
from the
•
Way Ruhu • Approval of
AMDAL
documents
• environment
al permit
Type of
Work
Length
(Km)
Safeguard
Document
Required
Activities
Environmental Monitoring Result
Environmental
Issues
Mitigation
Action
Location Status
at the
construction
site of the
Ciujung
embankmen
t
• GRM
(Grievance
Redress
Management)
Unit to receive
feedback and
complaints
from
surrounding
communities
• Coordinate
/ approach
the relevant
• New
Check
dam (5
location)
• Rehabilitati
on check
… m AMDAL Land
acquisition •Compensation
value
• Discussion
between
local
government
with
Affected
Persons
(APs)
Way
Batumerah
• Approval of
AMDAL
documents
• environment
al permit
• New
Check
dam (2
location)
… m AMDAL Land
acquisition •Compensation
value
• Discussion
between
local
government
with
Affected
Persons
(APs)
Way Ruhu • Approval of
AMDAL
documents
• environment
al permit
(iii) In accordance with RKL, already do:
o Re-measurement of ownership of land and building boundaries to be displaced / relocated;
o Socialize the plan of land acquisition to the community so that people get clear information about the building boundaries that will be evicted;
o Establish good communication links with communities with information disclosure of relocation and compensation activities;
o Approach the owner of the building / land through the musyarawah in the agreement;
o The owner of the building / land through consultation in the determination of the agreement;
o Coordination and cooperation with the government in the implementation of value or price agreements, and to prevent the inclusion of provocateurs in the community;
o Formation of Team to arrange land, building and other price;
o Coordination and cooperation with the National Land Agency (BPN) in the management of the land.
(iv) However, in accordance with the contents of the RPL document that has been
approved has not been conducted since the environmental permit issued in March 2015.
(v) Estuary of Batu Merah River:
• Many small shop along the river bank and Inspection road;
• There is coffee shop cover estuary, right part;
• There are domestic waste almost along the river
• Land acquisition still process
• There have been many land cover changes in the upland before by vegetation had changed and covered by buildings, without mitigation of rainwater management
(vi) Estuary of Way Ruhu:
• Left site of estuary need be Need coordination with PU Bina Marga Ambon City to improve the right of river bank at estuary
• There is domestic waste almost along the river • there have been many land cover changes in the upland before by
vegetation had covered by buildings, without mitigation of rainwater management
Annex 2
FMSRB ENVIRONMENTAL MONITORING CHECKLIST
MINUTE OF MEETING
SOCIAL AND ENVIRONMENTAL SAFEGUARD FORFMSRB
BATU MERAHAND WAY RUHU SUBPROJECTS AMBON, MALUKU
Date : Thursday,18Oct 2018
Time : 10.00-14.00
Place : ADB Office Kalimantan Room
Attendees : 1. Eric Quincieu (ADB) 2. Naning Mardiniah (ADB) 3. Suharyani (ADB) 4. Edi Broto (ADB) 5. Neneng Nurbaeti (ADB) hp.: 082116871227 6. Ari (CPMU) 7. Yance (BWSM) 8. Ruslan Malik (BWSM) 9. Taswin Sahfi (CS01) 10. Ahmad Budiman (CS01) hp.: 08122253079 11. Hamami (CS01) 12. Retno (CS01) 13. Soleh (CS02) hp.: 085722063413 14. Rika Komalasari (CS02) hp.:081573059676 15. Akhmad Supiarma (CS02) Environmental Safeguard Sp.
081246525553
I. Introduction and topic discussed:
• The meeting was opened by Mrs. Naning Mardiniah. • Introduction by Naning Mardiniah
This discussion was held to determine the progress of the implementation of activities in Ambon. The discussion to resolve the issue of land acquisition implementation in CW4, the all requirements for submission of loans to ADB were fulfilled. The report that has been submitted for Petra and Yacobus is still need to improve.
II. Presentation By Taswin Sahfy (CS01):
Some important points, progress and loans in Ambon:
• Land acquisition has been completed is Petra and Jacobus. • The problems in land acquisition in Way Ruhu and Batu Merah (left and
right sides) there are still residents who refuse to plan activities, namely people who live in Hative Kecil Village, Galala Village, also in the downstream settlements in Batu Merah Village and Amantelu Village. The solution is to conduct socialization on an ongoing basis by related parties, especially the Ambon City Government and BWSM.
• Priority for the implementation of land acquisition other than the Check Dam area, will also be carried out exemptions on the Way Ruhu River and Batu Merah (left and right sides of the river), for that BWSM will coordinate and propose additional budgeting.
• For the Ambon-Seram Project Location, Social Action Plan (SAP) activities do not yet exist. For this reason, it is necessary to immediately prepare the Ambon City Government and be supported by the Maluku Provincial Government. There are no SAP allocations until 2018
2. CheckDam: Rinjani Atas
Rinjani Atas does not need to be redesigned, because the existing checkdams already need only dredging or normalizing the river. Wait for the DED. This is the responsibility: CS 01, Estimated Critical Date: 1 November 2018.
III. Discussion :
1) Land Acquisition for Petra and Yacobus Subprojects locations (Ambon CW4). Land has been acquired and has been certified.
Land acquisition has no problem, unless the DED needs to be reviewed because it has been long (2014). This is the responsibility of CS 01.
2) It is necessary to immediately report the Second Due Diligent project. Estimated Critical Date on January 15, 2019. Task CS02 to review the Draft Report Document. In the Draft Report Document must contain: Budget Inventory Details and Strategic Gender, is it already included in the spatial plan? There is something in the upper reaches of Petra.
3) Check dam: Rinjani Atas does not need to be redesigned, because the existing check dams already need only dredging or normalizing the river. Wait for the DED. This is the responsibility: CS 01, Estimated Critical Date: 1 November 2018.
4) Batu Merah and Way Ruhu
Many people in the lower reaches of Batu Merah and Way Ruhu reject the land acquisition (left and right of the river).Batu Merah and Way Ruhu which have been released to be made Due Diligent Documents or Resetlement Plan Documents. The LARP has not been released yet. CS 01 needs the design to be completed first, because the determination of the land boundary in the inundation area is based on the stakes that are determined by the design.
For the Grievance Redress Mechanism process, it is made based on the derivative regulations not only based on Law No. 2/2012. So in RP there must be gender, restoration income, and relocation (if any). Have Petra and James entered the Spatial Planning? It should be explained in the report on the Resetlement Plan.
5). Checkdam Rinjani and Goa Maria. For Checkdam Rinjani, the community has occupied. CS 01: Need additional resttlement expert. Because it is a social consideration, and needs engineering consideration, how to mitigate it.The community occupying 46 HH of land. Land owners are willing to release their land.
6) Land status is customary land. Special Soya land has been released. The HH transfer process must also be in accordance with ADB regulations. Rinjani needs to do a survey even though only 2 Ha and location determination needs to be done.
7) Does the AMDAL / UKL-UPL environmental document for Rinjani already exist? The draft study should be sent to ADB. Land area: 2 Ha, then Involuntary Resettlement (LARP document) is needed. The Rinjani Atas section has been released: 3000 m.
8) Environmental Documents for Jacobus and Petra; The AMDAL for Batu Merah has been made in 2014.The AMDAL document will be carried out by Addendum, because it has been more than 3 years. In the AMDAL document specifically Petra and Yacobus have not been included in the Batu Merah AMDAL in detail. So it is necessary to include Petra and Yacobus's checkdams, the details of the design, its impact, its mitigation and the costs.
9) Way Ruhu There is already being freed up in the upper part of Way Ruhu (there are 3 owners who have acquired their land. Land acquisition in downstream Way Ruhu will be carried out on the 2019 budget.
10) Due Diligent Report ADB recommend that Rinjani, Hative Kecil, Way Ruhu Resettlement Plan be made in one document. Likewise for Galala, Petra, Yacobus Resettlement Plan documents are made in one document.
11) Hybrid AMDAL process in Ciujung FMSRB and Ambon projects. Refer to ADB and MPWH agreements. Compilation of AMDAL Documents for the FMSRB Project is prepared based on the provisions that currently apply in Indonesia. AMDAL or UKL-UPL is written in Indonesian (bahasa). Assessed by the Environmental Service at the Provincial or District level according to their authority.
12) For the requirements of AMDAL or UKL - UPL (EIA or IEE) documents required by ADB, it is necessary to harmonize the AMDAL or UKL UPL documents in accordance with the above GoI regulations by adding items to the AMDAL requirements in accordance with ADB SPS 2009 provisions that have not been included in the AMDAL or UKL - UPL requirements above. After the AMDAL or UKL - UPL in Indonesian language (bahasa) has received SKKL (Environmental Feasibility Certificate and Environmental Permit issued by the relevant institution, the AMDAL or UKL-UPL document must be translated into English, the document is officially recognized as the EIA document or IEE according to ADB requirements.
13) If there are differences in the quality standard values that differ between the GoI regulations and ADB Standards, the standard used is the one that has the most stringent values among the regulations.
IV. Follow Up :
1. CS01: Resettlement Specialist of Ambon-Seram will prepare the Resettlement
Plan Document for Rinjani on 10 January 2019. 2. CS01: The Social Safeguard Report of Yacobus and Petra will complete on 30
October 2018 3. For the next meeting ADB will invite the engineer 4. CS02 will prepare Social safeguard monitoring report for 2017 on 30 October
2018 5. TOR needs to be made for the Addendum of Ciujung Banten, Batu Merah and
Rinjani Ambon. Based on the EIA Hybrid. ECD: Nov. 2, 2018
Annex 3
ANNEX .3 ENVIRONMENTAL PERMITS OF AMDAL CIUJUNG SERANG BANTEN, WAY BATU MERAH AND WAY RUHU AMBON.
FLOOD MANAGEMENT IN SELECTED RIVER BASIN SECTOR PROJECT
Form Pemeriksaan Lingkungan (Fase Konstruksi) diisi oleh Konsultan Supervisi dan Kontraktor
Paket CW1 DAN CW2
Proyek : FMSRB CIUJUNG BANTEN
Subproject : CW1 DAN CW2
Location : Tanggul Sungai Ciujung
Contractor(s) :
Tanggal Monitoring : 02 Jan – 06 Januari 2019
Periode Pelaporan : Januari 2019
1. Pra-Konstruksi
Kesiapan Kontraktor dalam Monitoring
Lingkungan Ya / Tidak Tindakan yang diperlukan Tanggapan / Catatan Kontraktor
Apakah kontraktor memiiki kesiapsiagaan
dalam menangani lingkungan dan keselamatan
kerja.
Ya 1 Menyiapkan perlengkapan safety pekerja
2 Melakukan test udara, kebisingan, dll
(sesuai jadwal)
(Perlu pendampingan/ -perlu penjelasan)
Apakah kontraktor telah memiliki copy dari
Dokumen IEE / UKL – UPL./ AMDAL
Ya/Tidak (Contoh: Masih dalam proses pengurusan di
BBWS Kota Serang)
............................................................)
Apakah kontraktor telah mendapat pelatihan
dari ahli lingkungan untuk mengisi form ini?
Ya/Tidak ( Contoh: Belum mendapatkan pelatihan)
......................................................... )
Annex 4
2.Inspeksi Pemenuhan Persyaratan Lingkungan Selama Konstruksi
Dampak / Upaya
Mitigasi (Peringanan)
Apakah Mitigasi di
Implementasi?
Mitigations Effective?
(1 to 5)*
Dampak yang terpantau /
Lokasi
Tindakan yang dilakukan Respons /Catatan
Kontraktor
Pengangkutan Material untuk proyek seperti : kerikil, pasir, semen, pipa,dll.
Pengangkutan sisa galian dan lumpur ke lokasi yang telah ditetapkan untuk pembuangan sisa galian
Pencucian Ban Truck dan penutupan memakai terpal saat mengangkut material pasir, batu atau lumpur.
Apakah dilakukan pengetesan untuk debu, kebisingan dan getaran?
Adakah kerusakan pada jalan inspeksi atau jalan desa yang dilalui?
Adakah pengecekan kemacetan lalulintas di lokasi konstruksi proyek?
Apakah Aksesibilitas penduduk/masyarakat menuju mesjid rumah/pasar/sekolah terganggu?
Adakah pemotongan pohon untuk keperluan proyek?
Adakah tanah masyarakat yang dibebaskan untuk proyek?
Adakah Warung atau took milik warga yang terganggu? Sebutkan jumlahnya dan jenis usahanya
Adakah took/warung yang harus ditutup atau dipindahkan sementara?
Adakah terjadi banjir atau genangan pada jalan atau drainase di sekitar lokasi proyek
Apakah pada saat penggalian terjadi kemacetan lalu lintas ?
Bagaimana penanganan jalan yang basah, licin dan berlumpur?
Adakah rambu dan petugas bendera?
Apakah penggalian dan pengangkutan tanah telah menggunakan metoda metoda yang sesuai berdasarkan teknik teknik yang ramah lingkungan?
Adakah Operasi Standard Prosedure (SOP) untuk
mengektraksi dan pengambilan lumpur dari galian serta bahan baku pasir dan batuan lainnya?
Apakah dilakukan pengetesan kualitas air untuk mengetahui akibatnya seperti pencemaran sungai dan badan badan air atau penyempitan aliran sungai/ air.
Apakah upaya pencegahan erosi di tebing galian dilaksanakan?
Bagaimana penstabilan lereng/kemiringan galian tebing atau tanggul di proteksi?
Penanganan dan penyimpanan bahan bakar dan limbah oli
Apakah lokasi gudang peralatan dan material bersrih dari kebocoran oli dan minyak pelumas?
Adakah Pemisah oli (Oil Separator)?
Jumlah tenaga lokal yang bekerja di proyek, apakah kualitikasinya, asal tempat pekerja dan berapa kasus kecelakaan dalam periode bulan ini ?
Apakah fasilitas kebersihan dan kesehatan cukup memadai di base camp? (kamar mandi dan septic tank). Adakah air tergenang yang memungkinkan nyamuk bersarang?
Adakah Tempat pengumpulan sampah sementara di lokasi base camp dan di lokasi proyek?
Adakah sampah dipisahkan berdasarkan prinsip 3 R.
3. Kecelakaan berkaitan dengan Lingkungan Selama Periode Pelaporan (Jika Ada)
Environmental Incidents
(longsor, oli bocor, keluhan warga, dll)
Tanggal Dilaporkan
Oleh
Deskripsi/Lokasi Tindakan yang
dilakukan
Tindakan lebih
lanjut
Catatan
NA
NA NA NA NA NA NA
Rating untuk Keefektifan Upaya Pencegahan ( Mitigation effectiveness rating) criteria:
5. Sangat BaikVery Good (seluruh upaya pencegahan diimplementasi)
4. Baik Good (Sebagian besar pencegahan diimplementasi)
3. Cukup/ Fair (Pencegahan cukup diimplementasi)
2. Kurang / Poor (Sedikit upaya pencegahan diimplementasi)
1. Buruk / Very Poor (sedikit atau tanpa pencegahan diimplementasi)
Catatan tambahan mengenai hal hal yang belum tercantum dapat ditambahkan:
4. Ringkasan mengenai Tindakan yang harus dilaksanakan kontraktor pada periode bulan Januari 2019 (Sesuai bulan monitoring)
Tindakan lanjut yang diperlukan Jangka Waktu
(e.g. within one
week)
Lembaga yang
bertanggung
Jawab
CatatanTindak Lanjut (Perlu dilengkapi catatan apabila suatu aksi dilakukan)
1. Kontraktor harus dapat menjamin bahwa material pasir, batu dan bahan lainnya berasal dari sumber yang legal.
2. Penyimpanan tanah dan lumpur dari galian ditempatkan pada tempat yang telah diberi izin serta dilakukan pemadatan dan meratakannya agar tidak longsor atau terbawa air saat hujan.
3. Penyaring lumpur yang sederhana perlu disiapkan agar lumpur tidak mengalir ke badan air pada saat musim hujan tiba
4. Penyimpan oli dan solar harus di gudang dengan penanganan dari kebocoran yang memadai
5. Bangun WC di lokasi base camp.
((Diisi)
(Diisi)
...............................
(Pemilik Tanah dan jontraktor)
(Pelaksana)
Tindakan lebih lanjut yang diperlukan: ...............................................
Efektivitas: ...............................................
Tindakan selanjutnya
Disiapkan Oleh : .................................................
Tanggal : ......................................i
............................i
.............................i
(Logistik)
(K3)
Annex 5. Environmental Monitoring result on the construction of Ciujung Flood Dike in Banten
Type of work volume
Safeguard
Document
Required
Activities
Environmental Monitoring Result
Environmental Issues
Mitigation Action Location Status
New
construction
of Dike
11 km AMDAL Land compensation
• Change of Perception Society
• before the dredging is implemented, the implementing contractor will conduct more detailed socialization of the planned activities to the affected communities
• accommodate suggestions and responses from surrounding communities delivered during the socialization of the activity plan
• Coordinate with relevant agencies to follow up on responses, suggestions from the community and coordinate with landholders whose land will be used as access roads for vehicles
• Installation of bulletin boards at the construction site of the Ciujung embankment
• GRM (Grievance Redress Management) Unit to receive feedback and complaints from surrounding communities
• Coordinate / approach the relevant government agencies and the surrounding community
At social boundaries, that are
Kecamatan:
(i) Bandung, (ii)Pamarayan, (iii) Keragilan, and (iv)Cikesal Kabupaten Serang, Banten Province
• Approval of AMDAL documents
• environmental permit issued by the Regent of Serang District on 3 November 2014.
Annex 5
Environmental Monitoring on the proposed Civil Works in BWSM, Ambon
Type of work volume
Safeguard
Document
Required
Activities
Environmental Monitoring Result
Environmental Issues
Mitigation Action Location Status
New
construction
of Checkdam
Petra-1
1,000 sqm
UKL UPL/ AMDAL
Land compensation
Compensation value
Discussion between local government with Affected Persons (APs)
Way Batumerah •
New
construction
of Checkdam
Yakobus
UKL UPL Land compensation
Compensation value
Discussion between local government with Affected Persons (APs)
Way Batumerah •
New Check
dam (5
location)
UKL UPL Way Batumerah •
Rehabilitation
check dam (1
location)
UKL UPL Way Batumerah •
New Check
dam (2
location)
UKL UPL Way Ruhu •
Page 99 of 114
Annex 6
Annex 6 Estimation and Progress of FMSRB LARP Project Ambon City
I. Estimation and progress of FMSRB LARP project Ambon City
No Description
Land Required
Realization The Rest Remarks
m² m² m²
I WAY RUHU LARPDATA 2014 : 19.095,94
1 Check Dam Hative Kecil 8.100,00 0,00 8.100,00 New Check Dam
2 Distribution Width (River + Dyke)
10.955,94 233,00 10.722,94 River Width = Variable
II SUB TOTAL I ( 1 + 2 ) 19.055,94 233,00 18.822,94 Length = 1,570.85m
= 1.57km
II WAY BATU MERAH LARPDATA 2014 : 25.723,30
1 New Check DamYakobus 960,00 960,00 0,00 New Check Dam
2 Check Dam Petra 2.231,00 2.231,00 0,00 New Check Dam
3 Check Dam Rinjani 8.090,00 8.090,00 0,00 Rehabilitation Check
Dam Excisting
4 Check Dam Goa Maria (Plan) 6.000,30 0,00 6.000,30 New Check Dam
5 Check Dam Rinjani Atas (Plan) 3.100,00 0,00 3.100,00 New Check Dam
6 Distribution Width (River + Dyke 5.342,00 0,00 5.342,00 River Width = Varieties
SUB TOTAL I ( 1 + 2 + 3 + 4 + 5 + 6 ) 25.723,30 11.281,00 14.442,30 Length = 1,068.40m=
1.07 km
*Source; Bappeda Ambon, 2015.
II. The status of the impelementation of the LARP
No Location
Land
plots
Area, sqM Structure
Area, sqM Status
Plan Actual Plan Actual Plan Actual
1 Kampong Rinjani, Batu Merah village, Sinmau Subdistrict,
1 1 8,093 8,093 0 0 Compensated and certified
2 Sungai Petra, Wahoka village, Sinmau Subdistrict,
3 3 2,231 2,231 0 0 Compensated. 2 plots was compensated in 2015, 1 plot was compensated on Dec 2017.
3 Ahuru River, Galala village.
2 2 960 960 0 0 Compensated. 1 plot was compensated in 2015, 1 other plot was compensated on Dec 2017.Under process of certification.
Page 100 of 114
No Location
Land
plots
Area, sqM Structure
Area, sqM Status
Plan Actual Plan Actual Plan Actual
4 Way Ruhu River, Galala village
9 4 450 233 278 105 Compensated. 3 plots were compensated on Dec 2017 and 1 1 plot was compensated on May 2018.
Total 15 10 11,734 11,517 278 105
*Source; Bappeda Ambon, 2015.
Page 101 of 114
Annex 7
Page 102 of 114
Page 103 of 114