Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction...

84
Environmental Monitoring Report Bi-annual Report Covering the period of July-December 2017 PAK: Jamshoro Power Generation Project Project Number: 47094-001 ADB Loan/Grant Number: L3090/3091/3092-PAK Prepared: January 2018 Prepared by the Jamshoro Power Company Limited (JPCL), with the assistance of Mott MacDonald Limited (United Kingdom) in joint venture with MM Pakistan (Pvt) Ltd (Pakistan), for the Islamic Republic of Pakistan and the Asian Development Bank (ADB). This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction...

Page 1: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Environmental Monitoring Report

Bi-annual ReportCovering the period of July-December 2017

PAK: Jamshoro Power Generation Project

Project Number: 47094-001ADB Loan/Grant Number: L3090/3091/3092-PAKPrepared: January 2018

Prepared by the Jamshoro Power Company Limited (JPCL), with the assistance of MottMacDonald Limited (United Kingdom) in joint venture with MM Pakistan (Pvt) Ltd (Pakistan), forthe Islamic Republic of Pakistan and the Asian Development Bank (ADB).

This environmental monitoring report is a document of the borrower. The views expressed hereindo not necessarily represent those of ADB's Board of Directors, Management, or staff, and maybe preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designationof or reference to a particular territory or geographic area in this document, the AsianDevelopment Bank does not intend to make any judgments as to the legal or other status of anyterritory or area.

Page 2: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Jamshoro Power Generation Project

Bi-annual Environmental Monitoring Report July to December 2017

January 2018

Page 3: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are
Page 4: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

334014-MML-JPCL-R-00639 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 -

Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Mott MacDonald

Mott MacDonald Al Gaith Towers Hamdan Street PO Box 47094, Abu Dhabi United Arab Emirates T +971 (0)2 401 5333 F +971 (0)2 627 0734 mottmac.com

Jamshoro Power Generation

Project

Bi-annual Environmental Monitoring Report July to December 2017

January 2018

Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered office: Mott MacDonald House, 8-10 Sydenham Road, Croydon CR0 2EE, United Kingdom

Page 5: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are
Page 6: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Issue and Revision Record

Revision Date Originator Checker Approver Description

0 31.01.18 GC JV

TH Final for issue

Information class: Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-

captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being

used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied

to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other

parties without consent from us and from the party which commissioned it.

This report has been pr epared sol el y for use by the party which commissi oned it (the ‘Client’) i n connecti on with the capti oned proj ect. It should not be used for any other purpose. N o person other than the Client or any party who has expressl y agreed ter ms of r eliance with us (the ‘Reci pient(s)’) may rel y on the content, i nformati on or any vi ews expressed i n the repor t. We accept no duty of care, responsi bility or liability to any other r eci pient of thi s document. This r eport is confi denti al and contains pr opri etar y intell ectual property.

statements supplied to us by other par ties incl udi ng the client (‘D ata’). We have not i ndependentl y verified such D ata and ha

Page 7: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Contents

1 Introduction 1

1.1 Overview 1

1.2 Activities during reporting period (July 01 to December 31 2017) 1

1.3 Environmental assessment 6

2 Environmental monitoring and management 7

2.1 Environmental monitoring and management overview 7

2.2 Summary of environmental monitoring during reporting period 7

2.2.1 Lot 1 – Rehabilitation of evaporation ponds 7

2.2.2 Lot 2 - Construction of channel for discharging of cooling tower blow down 9

2.2.3 Lot 3 – Municipal solid waste disposal facility 11

3 Actions during the next reporting period 13

Appendices 15

A. Semi-annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds (Lot 1); July - December 2017 (Sachal) 16

B. Semi-annual Environmental Monitoring and Management Report; Construction of channel for discharging of cooling tower blow down (Lot 2); July – December 2017 (Sachal) 17

C. Semi-annual Environmental Monitoring Report; Construction of Municipal Solid Waste Facility (Lot 3); July - December 2017 (MAJ-IIC) 18

Page 8: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 1 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

1 Introduction

1.1 Overview

The Government of Pakistan aims to increase the share of coal-based generation from almost

none in 2016 to 15% over the next few years. In support of this initiative Jamshoro Power

Company Limited (JPCL) and Genco Holding Company (GENCO), supported by the Asian

Development Bank (ADB), is planning a brownfield extension of the Jamshoro Power Station to

improve the total plant efficiency and increase the power output. The project is known as the

Jamshoro Power Generation Project (JPGP).

The project site is approximately 15km northwest of Hyderabad, and about 150km northeast of

Karachi in the Sindh Province of Pakistan. The lndus River is about 3.5km east of the power

plant site. Currently there are four fossil fuel-fired electricity generating units installed and

operating at the site (Unit 1 is oil fired and Units 2 – 4 have dual-fuel capability (oil/gas)).

JPGP is proposed to initially comprise of 1x660MW (net) supercritical power plant with facilities

to expand to 2x660MW plants. The project aims to decrease the existing power shortfall in

Pakistan and address environmental concerns from the existing oil-fired power units. The new

boiler(s) will be designed to utilise imported sub-bituminous coal blended at 80/20 with local

lignite as its fuel.

As part of the feasibility study for the project and as required by the ADB an environmental audit

was undertaken of the existing plant. The audit was included as part of the environmental and

social impact assessment (ESIA) for the 2x660MW supercritical power plant (Environmental

Impact Assessment; Jamshoro Power Generation Project; Hagler Bailly Pakistan, October 29,

2013 (the ESIA report)). Section 6 of the ESIA report (Issues Related to Existing Plant and

Corrective Actions) identified several items related to the existing plant that require remediation

or rehabilitation.

The items that were identified are subject to a loan condition applied by ADB that requires the

identified remediation works to have a signed contract in place prior to commencement of works

on the site associated with the new facility (660MW supercritical power plant).

1.2 Activities during reporting period (July 01 to December 31 2017)

At the time of compiling this report (January 2018) JPGP is in the early implementation stage

with the following activities underway:

Final proposals for construction and operation of the 2x660MW (gross) supercritical power plant

have been evaluated and are waiting award. Award is dependent upon the revised Loan

Agreements (i.e. ADB and IDB) being accepted by all parties and the necessary conditions

precedent being accomplished by JPCL. It is currently envisaged that the Contracts will be

awarded by the third quarter of 2018.

The status of the remediation packages is provided data Table 1.

This report is the sixth bi-annual environmental monitoring report for the project covering the

period from July 01, 2017 to December 31, 2017 inclusive. Subsequent bi-annual reports will be

reconfigured as necessary to reflect activities and available information as the project develops.

Page 9: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 2 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

This page is left intentionally blank

Page 10: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 3 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Table 1: Remediation status summary Data Date – 27.12.2017

Sr.

No

Name of

contract

Opening

date

Award

date

Comm. date /

duration

Estimate / bid /

contract (in

PKR)

Present status Physical

progress

Activities pending

1 Lot 1.

Renovation of

effluent

evaporation

ponds

31-03-2016 23-11-

2016

Commencement:

01-02-2017

Duration: 180

days (extended

up to 272 days

i.e. 30th

October)

Estimate: 247.61

million

Contract: 190.24

million

1. Construction of

embankments in pond II, III

& IV are in progress (outer

sides).

2. Removal of roots at pond III

& IV are in progress

3. Preparation of construction

joints in PCC & RCC are in

progress.

4. Earth work (key and apron)

at west & north side of pond

III, to rectify the levels

difference between bed &

apron

92% 1. Installation of 12 inch

FRP piping stub

connections at the head

end

2 Lot 2.

Construction

of channel for

discharging of

cooling tower

blow down

31-03-2016 23-11-

2016

Commencement:

01-02-2017

Duration: 180

days

Estimate: 179.59

million

Contract: 219.32

million

1. Access to the site after

boundary wall is still not

clear i.e. 00+0197

2. Resubmitted design

calculations and drawings

are under review

3. Survey work of coagulator

connecting channel at

0+225 is in progress

4. Water diverted after RBOD

14-12-2017.

5. Site visited on 21-12-2017

jointly with JPCL about

dismantling of RCC

wall/platform to identify the

underneath services and

dismantling of RCC

Abundance walls is in

progress

6. Lean concreted from 0+071

to 0+185 and from 0+220 to

0+350 local stop activity 16-

12-2017

17% 1. Construction of RCC box

channel/culvert

2. Construction of PCC

channel and culverts

3. River end protection

4. Final working drawings

are required after PIC

observations/comments

5. RCC work, bar bending

schedule is to be

submitted

6. Drawing of diversion

channel after boundary

wall is required

Page 11: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 4 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

7. Preparation of Lean from

0+00 to 0+071 is in

progress

3 Lot 3.

Construction

of municipal

solid waste

disposal

facilities

31-03-2016 07-12-

2016

Commencement:

02-01-2017

Duration: 180

days

Estimate: 63.39

million

Contract: 63.00

million

Landfill area

1. Excavation of landfill area

(east side) is in progress

2. Brick work of boundary wall

up to the bottom of plinth

beam is in progress.

3. Concreting of super column

above plinth beam

boundary wall of landfill

area is in progress

4. Brick work above plinth

beam of boundary wall of

landfill area is in progress

5. Concreting of plinth beam of

section B at grid 3 boundary

wall of landfill area is in

progress

6. Community waste

management awareness’ programme is in progress.

Office block

1. Short columns of boundary

wall and guard room

concreted

2. Reinforcement and

formwork of plinth beam of

boundary wall is in progress

58% Landfill area

1. Design drawings of

Construction of

Municipal solid waste

disposal area after PIC

observations, are

awaited.

2. Disposal of existing

municipal waste of the

colony

4 Lot 4.

Construction

of hazardous

solid waste

facilities

03-04-2017 --- Duration: 180

days

Estimate: 85.00

million

Lowest bid: 85.66

million

Signing of contract agreement

between contractor and JPCL is

awaited.

--- Site supervision

5 Lot 5. Supply

and

construction

10-04-2017 --- Duration: 270

days

Estimate: 81.5

million

BER is with JPCL, must be issued to

ADB.

--- Approvals

Award of contract.

Page 12: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 5 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Source: Mott MacDonald Project Files

of sewage

treatment

plant

Lowest bid: 109.9

million

Site supervision

6 Lot 6.

Contaminated

soil

remediation

30-05-2017 --- Duration: 365

days

Estimate: 992.09

million

Bid amount: 1053

million

Must be discussed with EPC

contractor, for carrying out the job.

--- Approvals

Award of Contract.

Site supervision

Page 13: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 6 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

1.3 Environmental assessment

The ESIA study and subsequent ESIA report for the proposed 2x660MW power plant were

developed for the Asian Development Bank and include reference to Pakistan national

standards and regulatory requirements and international guidelines including ADBs Safeguard

Policy Statement (2009) and the World Bank/International Finance Corporation Environment,

Health and Safety Guidelines for Thermal Power Plants (2008) (IFC EHS guidelines).

International treaties that Pakistan is a signatory to are also considered.

The EIA report identifies that both Pakistan national environmental quality standards (NEQS)

and IFC EHS guidelines will have to be complied with. In operation this means that the most

stringent of the NEQA and IFC EHS Guidelines environmental limits/standards/guidelines will

have to be complied with (with the exception of ambient air quality standards where national

standards, where they exist, take precedence over IFC EHS guidelines).

A gap analysis with respect to environmental aspects in the draft bidding documents and

technical specifications was prepared by the project implementation consultant (PIC – Mott

MacDonald) and a number of items were identified that were included in the technical

requirements for the 2x660MW supercritical power plant when the tender documents were

issued.

Page 14: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 7 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

2 Environmental monitoring and management

2.1 Environmental monitoring and management overview

At the time of compiling this report (January 2018) three work packages were under progress:

Lot 1 – Evaporation pond renovation

Lot 2 – Blow-down channel renovation

Lot 4 – Municipal solid waste disposal facility

Lot 1 and Lot 2 are being undertaken by Sachal Engineering Works (Pvt) Ltd (Sachal).

Construction environmental management plans have been developed and approved for both

lots. The approved CEMPs include details of scheduled environmental monitoring during the

construction process. Monitoring of environmental parameters for Lot 1 and Lot 2 are

summarised in this report. The monitoring reports for Lot 1 and Lot 2 prepared by Sachal are

attached as Appendix A and Appendix B respectively.

Lot 3 being undertaken by a consortium of Mian Abdul Jabbar & Co and Indus Construction Co

(MAJ ICC). A construction environmental management plan has been developed for Lot 3.

Monitoring of environmental parameters for Lot 3 are summarised in this report. The monitoring

report for Lot 3 prepared by MAJ ICC is attached as Appendix C.

2.2 Summary of environmental monitoring during reporting period

2.2.1 Lot 1 – Rehabilitation of evaporation ponds

Lot 1 involves clearing four existing evaporation ponds of heavy vegetation growth and

sediment deposits that have built up over many years of use. Repairs are then to be carried out

to any damage to the structure of the ponds and associated infrastructure as necessary to make

the ponds functional. Mechanical excavators, dozers and haulage trucks, tractors and trailers

are all used for removing and transporting material. Excavated material is deposited at a

designated site within the JPCL site.

The information reported here is extracted from the contractor’s (Sachal) ‘Bi Annual

Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds, July to

December 2017’ a copy of which is attached as Appendix A.

The following parameters are monitored and reported:

(a) Ambient air quality

(b) Traffic safety

(c) Noise Levels

(d) Surface water and soil

(e) Waste management

(f) Cultural heritage management

(g) Occupational health and safety

Many of the parameters are monitored visually on an ongoing basis and reported qualitatively.

Where quantitative data is available it is reported here.

Page 15: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 8 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

a) Ambient air quality. Taken primarily as dust, visual assessments are made and water

sprays are used to control dust levels routinely and in response to observed excessive

dust levels. No excessive dust issues have been reported during the reporting period.

b) Traffic safety. Traffic safety is controlled on site by imposing speed limits and

instructions to drivers. Traffic activity is routinely monitored by environment, health and

safety personnel on site. No adverse traffic related incidents have been reported during

the reporting period.

c) Noise levels. Noise is monitored on site from a health and safety perspective.

Monitoring data is reported in Table 3.3.1 and Table 3.3.2 of the contactors bi-annual

environmental report for Lot 1 in Appendix A. No breaches of the 85dB health and

safety noise limits were recorded during the reporting period. Noise monitoring is

reported in Table 2 and Table 3.

Table 2: Noise Level Monitoring during 3rd Quarter from July to September 2017

Sampling

locations

GPS

Coordinates Date and Time

Average Noise Level

in dB

01

Lot-I Camp

Office

E 25.477567

N 68.273647

20 September 2017

09:00 am to 05:00 pm 57.28

02

Pond IV E 25.473728 N 68.275454

25 September 2017

09:00 am to 05:00 pm

52.13

Source: Semi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. July - December 2017. Sachal

Table 3: Noise Level Monitoring during 4th Quarter from October to December 2017

Sampling

locations

GPS

Coordinates Date and Time

Average Noise Level

in dB

01

Lot-I Camp

Office

E 25.477284

N 68.273569

20 October 2017 09:00

am to 05:00 pm 54.76

02

Pond IV E 25.473716 N 68.275442

25 October 2017 09:00

am to 05:00 pm

57.27

Source: Semi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. July - December 2017. Sachal

d) Surface water and soil. Samples of surface water and soils from the evaporation ponds

were taken and analysed. No exceedances of prescribed standards are reported.

e) Waste management. Solid waste is reported to be collected and disposed of in a

designated municipal disposal site.

f) Cultural heritage management. During excavations, continual observations are made to

identify culturally important artefacts and a chance-finds procedure is included in the

construction environmental management plan (CEMP). Given the nature of the activities

on Lot 1 it is considered unlikely that any culturally important artefacts will be present.

Page 16: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 9 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

g) Occupational health and safety. Health and Safety statistics are recorded and reported

in Sachal’s bi-annual environmental report and are shown in Table 4

Table 4: Monthly Occupational Health and Safety measure recorded at project site

Safety Statistics Jul-Aug Sep-Oct Nov-Dec

LTI 0 0 0

TRIR 0.02 0.01 0

Number of days without accident 62 61 61

Number of ill health cases 2 1 0

Overdue preventive open observations 18 20 05

Source: Semi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. July - December 2017. Sachal

2.2.2 Lot 2 - Construction of channel for discharging of cooling tower blow down

The broad scope of work under this contract shall include but is not limited to the following:

● Detailed route elevations/survey for the entire discharge route (i.e. from the existing water

treatment plant to the terminal point on the bank of the Indus River)

● Geotechnical investigations associated with the discharge route associated with the new

reinforced concrete box culvert

● Hydraulic analysis of closed and open channel design

● Analysis of ground water table

● Civil design of channel

● Construction of channel from power plant area to Indus river

● Construction of river embankment protection to avoid washout

● Construction of temporary diversion channels during construction of permanent channel

The information reported here is extracted from the contractor’s (Sachal) ‘Semi-annual

Environmental Monitoring Report for Construction of Channel for the Disposal of Cooling Tower

Blow Down (Lot-2). July-December 2017’ a copy of which is attached as Appendix B.

The following parameters are monitored and reported:

(a) Ambient air quality

(b) Traffic safety

(c) Noise Levels

(d) Surface water and soil

(e) Waste management

(f) Cultural heritage management

(g) Occupational health and safety

Many of the parameters are monitored visually on an ongoing basis and reported qualitatively.

Where quantitative data is available it is reported here.

a) Ambient air quality. Taken primarily as dust, visual assessments are made and water

sprays are used to control dust levels routinely and in response to observed excessive

dust levels. No excessive dust issues have been reported during the reporting period.

Page 17: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 10 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

b) Traffic safety. Traffic safety is controlled on site by imposing speed limits and

instructions to drivers. Traffic activity is routinely monitored by environment, health and

safety personnel on site. No adverse traffic related incidents have been reported during

the reporting period.

c) Noise levels. Noise is monitored on site from a health and safety perspective.

Monitoring data is reported in Table 3.3.1 and Table 3.3.2 of the contactors bi-annual

environmental report for Lot 2 in Appendix B. No breaches of the 85dB health and

safety noise limits were recorded during the reporting period. Noise monitoring is

reported in Table 5 and Table 6.

Table 5: Noise Level Monitoring during 3rd Quarter from July to September 2017

Sampling

locations

GPS

Coordinates Date and Time

Average Noise Level

in dB

01

Lot-II Camp

Office

E 25.474072

N 68.274292

20 September 2017

09:00 am to 05:00 pm 56.85

02 0+000 KM

E 25.473462

N 68.274699

25 September 2017

09:00 am to 05:00 pm

53.16

Source: Semi Annual Environmental Monitoring and Management Report; Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II). July - December 2017. Sachal

Table 6: Noise Level Monitoring during 4th Quarter from October to December 2017

Sampling

locations

GPS

Coordinates Date and Time

Average Noise Level

in dB

01

Lot-II Camp

Office

E 25.474125

N 68.274368

20 October 2017

09:00 am to 05:00 pm 55.43

02 0+000 KM

E 25.473410

N 68.274533

25 October 2017

09:00 am to 05:00 pm 54.68

Source: Semi Annual Environmental Monitoring and Management Report; Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II). July - December 2017. Sachal

d) Surface water and soil. Samples of surface water and soils from the evaporation ponds

were taken and analysed. No exceedances of prescribed standards are reported.

e) Waste management. Solid waste is reported to be collected and disposed of in a

designated municipal disposal site.

f) Cultural heritage management. During excavations, continual observations are made to

identify culturally important artefacts and a ‘chance-finds’ procedure is included in the construction environmental management plan (CEMP). Given the nature of the activities

on Lot 1 it is considered unlikely that any culturally important artefacts will be present.

g) Occupational health and safety. Health and Safety statistics are recorded and reported

in Sachal’s bi-annual environmental report and are shown in Table 7.

Page 18: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 11 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

“Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II) project

has achieved 1.525 million Cumulative safe man hours without lost time injury, project

started from 1st February 2017”

Table 7: Monthly Occupational Health and Safety measure recorded at project site

Safety Statistics Jul-Aug Sep-Oct Nov-Dec

LTI 0 0 0

TRIR 0.04 0.01 0

Number of days without accident 62 61 61

Number of ill health cases 1 0 2

Overdue preventive open observations 17 16 8

Source: Semi Annual Environmental Monitoring and Management Report; Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II). July - December 2017. Sachal

2.2.3 Lot 3 – Municipal solid waste disposal facility

Lot 3 involves the design and construction of a municipal solid waste facility for the housing

colony; removing municipal waste from the housing colony and depositing in the newly

constructed facility; and capacity building for JPCL employees and colony residents on the

handling and disposal of municipal waste. The information reported here is extracted from the

contractor’s (MAJ-IIC) Semi-Annual Environmental Monitoring Report; Project Site Remediation

Package (Lott 3). July-December 2017. The monitoring report prepared by MAJICC is attached

as Appendix C.

Lot 3 is in the early stages of development. During the reporting period the following activities

have been undertaken or are in progress:

1. Excavation of landfill area (east side) is in progress

2. Brick work of boundary wall up to the bottom of plinth beam is in progress.

3. Concreting of super column above plinth beam boundary wall of landfill area is in

progress

4. Brick work above plinth beam of boundary wall of landfill area is in progress

5. Concreting of plinth beam of section B at grid 3 boundary wall of landfill area is in

progress

6. Community waste management awareness’ programme is in progress. 7. Toolbox talks have been undertaken for company staff on site. Subjects covered are

jungle cutting, proper use of PPE and geotechnical investigations

8. Drinking and water quality sampling and analysis

Water quality monitoring results for October and November 2017 are presented in the MAJ-IIC

consortium Semi-Annual Environmental Monitoring Report; Project Site Remediation Package

(Lott 3). July-December 2017. All reported parameters are within WHO guidelines.

Registers of attendance at toolbox talks on: plastering of the office block; concreting of column

footing; and brick masonry work at the boundary wall are presented in the environmental

monitoring report.

As Lot 3 progresses more detailed environmental monitoring will be required to be reported.

During the next reporting period MAJICC state that they will undertake the following tasks:

● Performance assessment of awareness programmes

Page 19: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 12 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

● Installation of dustbins

● Collection of MSW

● Transportation of MSW

● Segregation of MSW at site

● Drinking and ground water quality monitoring

● Air quality monitoring

● Noise pollution assessment during excavation work

It is anticipated that Lot 3 detailed design of the municipal waste disposal facility will be agreed

and construction will continue during the next reporting period.

Page 20: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 13 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

3 Actions during the next reporting period

During the forthcoming period (January to June 2018) the following actions are anticipated for

the remediation packages:

Award of Lots 1, 2, and 3 associated with the 2x660 MW EPC and O&M Contracts.

Remediation Lot 1 will be completed.

Remediation Lot 2 will resume.

Remediation Lot 3 will continue.

Remediation Lots 4, 5, and 6 will be awarded and work will begin. JPCL will also take action

relating to cessation of oil transfer pollution processes associated with Lot 6.

PIC environmental specialists will:

Respond to queries relating to environmental aspects of all remediation lots.

As appropriate, work with preferred bidders/awarded bidders to establish environmental

management and monitoring plans, programmes and reporting.

The next semi-annual environmental monitoring report will cover the period from January to

June 2018 and will be made available by the end of July 2018.

Page 21: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 14 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Page 22: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 15 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

Appendices

A. Semi-annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds (Lot 1); July - December 2017 (Sachal) 16

B. Semi-annual Environmental Monitoring and Management Report; Construction of channel for discharging of cooling tower blow down (Lot 2); July – December 2017 (Sachal) 17

C. Semi-annual Environmental Monitoring Report; Construction of Municipal Solid Waste Facility (Lot 3); July - December 2017 (MAJ-IIC) 18

Page 23: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 16 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

A. Semi-annual Environmental Monitoring

and Management Report; Rehabilitation of

Effluent Ponds (Lot 1); July - December 2017

(Sachal)

Page 24: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

SEMIANNUAL ENVIRONMENTAL

MONITORING & MANAGEMENT REPORT

Project Name: Site Remediation Contract for LOT-I Rehabilitation of Effluent Evaporation Ponds

Period: (July 2017 to December 2017)

Report prepared by: Atif Hussain _____________________

HSE Officer

Page 25: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

TABLE OF CONTENTS

Sr. No. Particulars Page

1.0 Project Description

1.1 Project Description 1

1.2 Project Background 1

1.3 Scope of work 4

2.0 Environmental Monitoring Requirements & Parameters

2.1 Environmental Monitoring 4

2.2 Environmental Monitoring during Construction Phase 4

2.3 Project Environmental key personnel 5

3.0 Impact on Environmental Parameters during Construction Phase

3.1 Ambient air quality 5

3.2 Traffic safety 5

3.3 Noise Levels 5

3.4 Surface water and soil 9

3.5 Waste Water Management 9

3.6 Cultural Heritage Management 9

3.7 Impact of OHS at Project Site 9

4.0 Mitigation Measures

4.1 Air Quality 10

4.2 Water Quality 10

4.3 Noise Level 10

4.4 OHS at Project Site 10

5.0 Picture Gallery 11

Page 26: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

1

Bi Annual Environmental Monitoring & Management Report

1.1 Project Description

The Jamshoro site is about 20 km northwest of Hyderabad, and about 150 km northeast of Karachi. The Indus River flows about 3.5 km east of the site. Highway N-55, also known as the Indus Highway, runs through the site and has immediate access to the national railway, allowing for the easy delivery of equipment, fuel and other materials. The Jamshoro site consists of four (4) existing fossil fired electricity generating units. Unit 1 (U1) is fired by heavy fuel oil (HFO) with an original nominal rating of 250MW. U1 was originally commissioned in 1990. Units 2 to 4 are dual fuel (oil and gas) fired with an original nominal rating of 210MW (each). Units 2 to 4 were commissioned in 1989,1990 and 1991 respectively. Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds are now completely filled with sludge, silt and clay along with wild bushes and vegetation growth. The evaporation ponds are to be cleared of wild bushes and vegetation. The existing evaporation ponds and associated channels are to be cleaned. The silt/sludge is to be taken out from the evaporation ponds required levels mentioned in as built/tender drawing and will be dumped to the Water Pre Treatment Area (WPTA) south of Evaporation Ponds within the power plant premises. The discarding of silt and sludge shall comply with the applicable provisions within the EIA.

1.2 Project Background

Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds were filled with sludge, silt and clay along with wild bushes and vegetation growth.

Page 27: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

2

Bi Annual Environmental Monitoring & Management Report

LOCATION OF THE PROJECT

Page 28: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

3

Bi Annual Environmental Monitoring & Management Report

1.3 Scope of work

1.3.1 Performance of materials and services

The scope of work under Lot I, includes procurement, transportation, storage,

construction, repair, installation, all detailed survey and geotechnical investigation, site levelling, and drainage.

1.3.2 Renovation of effluent evaporation ponds

The broad scope of work under this contract shall include but is not limited to

the following:

Removal of all bushes and vegetative growth on existing surface of Evaporation Pond Area

Sludge and Silt removal from four (4ea) existing evaporation ponds Disposal Silt and Sludge in accordance with environmental standards

Assessment of damages to the existing evaporation ponds and connecting channel

Installation of new 12 inch FRP connections at the head end of each pond

for later use Restoration of evaporation ponds to original conditions (as demonstrated

in the tender (“as built” drawing set)

1.3.3 Design and procurement of various equipment and systems

The Contractor shall carry out the basic and detailed design and engineering as applicable; finalize the parameters of all equipment and systems. For those

equipment and systems not falling under the Contractor's manufacturing range, the same shall be procured from reputed sub-vendors. Contractor shall provide document to prove the capability of sub-vendor.

1.3.4 Transportation, receiving, handling and storage at site

The Contractor shall be responsible for proper transportation of all materials, equipment and systems from the point of manufacture/procurement to the

project site and its final location in the plant. It will be the Contractor's responsibility to develop the shipping and transportation logistics. Similarly, it will be the Contractor's responsibility to coordinate with necessary

departments such as Imports, Customs, Port Authorities, Roadways, etc.

Upon receipt of equipment and materials at site, the Contractor shall make arrangements for proper receiving, handling and storage at site. Covered or indoor storage shall be provided by the Contractor, wherever necessary. In

case use of any hazardous material is envisaged, the Contractor shall make necessary arrangements duly complying with the applicable laws or

regulations or ordinance or statutes of the Government.

1.3.5 Construction, erection and testing

The Contractor shall follow standard procedures and instructions by the Employer, if any, for carrying out proper construction, erection and testing of

all the facility. For this purpose, it will be the Contractor's responsibility to ensure availability of construction machinery, cranes, rigging, scaffolding, tool for cutting, welding, erection, etc. as may be required.

Page 29: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

4

Bi Annual Environmental Monitoring & Management Report

1.3.6 Commissioning, trial runs and performance guarantee tests

Any pump being provided under the work shall be commissioned and handed over to the client after trial run.

1.3.7 General requirements

The items specifically not mentioned in the specification but needed for the

smooth functioning of the equipment/system and plant requirement shall be deemed included in the scope of Contractor unless otherwise specifically

mentioned under exclusions. In addition to the scope and services mentioned above, the following general supplies and services shall be included in the scope of Contractor.

1.3.8 Paints

The Contractor's scope of works includes supply of paints and painting of all equipment and structures as per the color scheme to be approved by Employer. The painting of various components shall comply with the requirement

stipulated in different parts of this specification.

2.0 Environmental Monitoring

2.1 Environmental Monitoring Requirement & Parameters

The project is committed to monitor and manage its surrounding environment so as

to reduce the negative impacts which may arise from the project activities. To control

the adverse impacts on ambient air quality, traffic safety, noise levels, Surface water and

soil, waste management, cultural heritage management and occupational health & safety

of all personnel on site. The Sachal is regularly monitoring and managing its construction

site by implementing the approved CEMP. The daily, weekly and monthly environmental

inspection records are up to date and have been checked by MML representatives.

Precisely the following pre-determined parameters as indicated below are being regularly

monitored subsequent management program has also taken under consideration for

successful completion of the project.

(a) Ambient air quality

(b) Traffic safety

(c) Noise Levels

(d) Surface water and soil

(e) Waste management

(f) Cultural heritage management

(g) Occupational Health and Safety

2.2 Environmental Monitoring during Construction Phase

According to Table 10-2 environmental monitoring in EIA report by ADB,

during the project activities the visual inspections were carried out on daily

weekly and monthly basis to make sure that all above mentioned parameters

Page 30: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

5

Bi Annual Environmental Monitoring & Management Report

are on compliance with EIA and CEMP. The noise level data from the project

area is also collected quarterly. For surface water and soil analysis, the water

and soil samples were collected on different RDs by third party and results of

those tests were submitted to MML.

Monitoring and Management

Parameters (July 2017 - Dec 2017)

Ambient air quality Done with visual inspections

Traffic safety Implemented and monitored

Noise Levels Visual inspections and measurements Surface water and soil Tests conducted & Submitted

Waste management Implemented & Monitored

Cultural heritage management Visual Inspections

Occupational Health and Safety Implemented and monitored

2.3 Project Environmental key personnel;

Sr. No.

Project Key personnel Name of Key

personnel Telephone No.

01 HSE Officer LOT-I. Atif Hussain 03332401024

3.0 Impact on Environmental Parameters during construction phase

3.1 Ambient Air Quality

During the construction activities vehicles are carrying employees and tools to the

site. Construction equipment, such as stone (aggregate) crushers is not being used

at the site which could create significant emission of particulate matters. Since

rehabilitation of evaporation ponds would most likely involve significant earth works,

increase in particulate matter in the air from wind-blown dust is also a concern,

especially considering the close proximity of the villages (Local stake holders) to the

project site. Ambient Air Quality was monitored by daily and weekly environmental

inspections at site.

3.2 Traffic Safety During project activities vehicle movement is a huge risk to environment as well as the personnel health on site for reducing the risk we put speed limit signs at different roads and drivers are instructed to follow the speed limits strictly. Furthermore, Environmental and health and safety inspections are carried out on regular basis to make sure that the controls are in place and complied properly.

3.3 Noise Levels During project activities, major source of noise is expected to be generated from

transport vehicles which include cranes excavator, trucks, LTVs etc. Regular

inspections of all equipment and vehicles are carried out to make sure the noise levels

are below 85 db.

Page 31: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

6

Bi Annual Environmental Monitoring & Management Report

Table: 3.3.1. Noise Level Monitoring during 3rd Quarter from July to September 2017

Table: 3.3.2. Noise Level Monitoring during 4th Quarter from October to December 2017

Sampling locations GPS

Coordinates Date and Time

Average Noise Level in dB

01 Lot-I Camp Office E 25.477284 N 68.273569

20th October 2017 09:00 am to 05:00 pm

54.76

02 Pond IV E 25.473716 N 68.275442

25th October 2017

09:00 am to 05:00 pm

57.27

To assess the noise generated by different activities and equipment to be used at

various stages of the construction work without proper measures the workers and

officers may face partial or permanent hearing loss. The graphical presentation of

noise is depicted in the following pages of report (Figure-1, 2, 3, 4)

Sampling locations GPS Coordinates Date and Time

Average Noise Level in dB

01 Lot-I Camp Office E 25.477567 N 68.273647

20th September 2017 09:00 am to 05:00 pm

57.28

02 Pond IV E 25.473728 N 68.275454

25th September 2017

09:00 am to 05:00 pm

52.13

Page 32: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

7

Bi Annual Environmental Monitoring & Management Report

Noise Level Monitoring during 3rd Quarter from July 2017 to September 2017

Lot-I Camp Office

Figure 1 Pond IV

Figure 2

Page 33: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

8

Bi Annual Environmental Monitoring & Management Report

Noise Level Monitoring during 4th Quarter from October 2017 to December 2017 Lot-I Camp Office

Figure 3

Pond IV

Figure 4

Page 34: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

9

Bi Annual Environmental Monitoring & Management Report

3.4 Surface water & soil

The surface water & soil sample were collected from evaporation ponds at different

locations. The samples were collected by third party for analysis and testing and water &

soil analysis report is submitted to MML.

3.5 Waste Management

The solid wastes of domestic nature generated mainly in the labor sheds are regularly

being collected in separate bins and being disposed through municipal cleaners and

being dumping in a designated municipal dumping place. In addition, a small amount of

solid kitchen waste is generated during day time which are also being disposed in

methodic way through municipal cleaner. The environmental and health and safety

inspections are carried out on regular basis to check the compliance.

3.6 Cultural Heritage management During project activities (excavation) and manual digging continual supervision is carried out throughout the project and environmental inspections are carried out regularly. Also chance find procedure is established and implemented as stated in CEMP.

3.7 Impact of OHS at project site Personal Protective Equipment (PPEs): During project activities, the workers may face

minor injuries due to accidental negligence. The regular provided services are depicted

in the following table-5.

Table-5: Monthly Occupational Health and Safety measure recorded at project site

“The Renovation of Evaporation Ponds (LOT-I) project has achieved 3.211 million Cumulative safe man hours without lost time injury, project started from 1st February 2017”

Safety Statistics Jul-Aug Sep-Oct Nov-Dec

LTI 0 0 0

TRIR 0.02 0.01 0

Number of days without accident 62 61 61

Number of ill health cases 2 1 0

Overdue preventive open observations

18 20 05

Page 35: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

10

Bi Annual Environmental Monitoring & Management Report

4.0 Mitigation measures

4.1 Air Quality

To reduce the generation of dust owing to movement of construction materials

including vehicles, regular water spray are being accomplished at construction

site. Movement of construction debris are being covered while hauled and

stored, roads properly cleaned and water sprayed in order to minimize dust

in air. To reduce generation of dust the stone crusher and batching plant have

not been allowed at construction site.

4.2 Water Quality

The camp is outside the project boundary and from that place possible

management has been ensured to avoid any contamination of any sort around

the project boundary. During the day time, small quantity of office waste is

generated (approximately 2kg) per day which is properly disposed-off through

designated municipal corporation locations.

4.3 Noise Level

Use equipment i.e., designed with noise-control provision;

Route truck traffic away from noise-sensitive areas, where feasible;

Unnecessary vehicle movement has been avoided at project site;

Switch off the engines while remain unused.

4.4 OHS at project site

Personal Safety Equipment (PSE): Use appropriate personal protection

equipment, such as safety boots, helmets, gloves, protective clothing, goggles

and ear protection to comply HSE obligation during construction phase.

Page 36: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

11

Bi Annual Environmental Monitoring & Management Report

4.0 Pictures gallery

Evaporation Pond 1 south side (Dated :24/10/2017.)

Mr. Adnan Visited Site with MMP Team

Toolbox Talk

First Aid given by Medical Officer

Page 37: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

12

Bi Annual Environmental Monitoring & Management Report

Speed Limit Signboards on Activity Route

Parking Area

Barricaded Walkways

Page 38: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

13

Bi Annual Environmental Monitoring & Management Report

Assembly Point

Emergency Drill

Water Sprinkling on Activity Route

Page 39: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 17 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

B. Semi-annual Environmental Monitoring

and Management Report; Construction of

channel for discharging of cooling tower

blow down (Lot 2); July – December 2017

(Sachal)

Page 40: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

___________________________________________________________________________________________________________

Islamabad: 59E, Street No.7, I-10/3, Islamabad. Tel: 0514446837-74, Fax: (92-51) 4431774, Email: [email protected]

Karachi: Business Avenue, Sharah-e-faisal, Karachi. Tel: 021-34536952, Fax: (92-21) 34322283, Email: [email protected]

No. SACHAL/JAM/JPCL/2017/0171 Date: 29th Dec, 2017 Timothy Mark Hulme, Team Leader Mott Macdonald Limited 2x660 MW Coal Power Project Jamshoro.

Project: Site Remediation Package (LOT-II) – 2 x 660 MW Coal Fired

Power Project Jamshoro.

Subject: REF: No. SACHAL/JAM/JPCL/2017/0171, SUBMISSION

OF SEMIANNUAL ENVIRONMENTAL MONITORING REPORT FOR CONSTRUCTION OF CHANNEL FOR THE DISPOSAL OF COOLING TOWER BLOW DOWN (LOT-II).

Dear Sir, In pursuance of subject mentioned, we hereby submit semiannual environmental monitoring report for construction of channel for the disposal of Cooling Tower blow down (LOT-II). Yours truly, Kazim Ali Shah Project Manager Enclosed: as stated

Cc:

PIU/Project Director, Coal Fired Power Project @ Jamshoro

Local Team Leader Mott Macdonald Limited @ Site

Sachal Head Office

Page 41: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

SEMIANNUAL ENVIRONMENTAL

MONITORING & MANAGEMENT REPORT

Project Name: Site Remediation Contract for LOT-II Construction of Channel for the Disposal of Cooling Tower Blow Down

Period: (July 2017 to December 2017)

Report prepared by: Atif Hussain _____________________

HSE Officer

Page 42: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

TABLE OF CONTENTS

Sr. No. Particulars Page

1.0 Project Description

1.1 Project Description 1

1.2 Project Background 1

1.3 Scope of work 4

2.0 Environmental Monitoring Requirements & Parameters

2.1 Environmental Monitoring 5

2.2 Environmental Monitoring during Construction Phase 5

2.3 Project Environmental key personnel 6

3.0 Impact on Environmental Parameters during Construction Phase

3.1 Ambient air quality 6

3.2 Traffic safety 6

3.3 Noise Levels 6

3.4 Surface water and soil 10

3.5 Waste Water Management 10

3.6 Cultural Heritage Management 10

3.7 Impact of OHS at Project Site 10

4.0 Mitigation Measures

4.1 Air Quality 11

4.2 Water Quality 11

4.3 Noise Level 11

4.4 OHS at Project Site 11

5.0 Picture Gallery 12

Page 43: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Bi Annual Environmental Monitoring & Management Report

1

1.1 Project Description

The Jamshoro site is about 20 km northwest of Hyderabad, and about 150 km northeast of Karachi. The Indus River flows about 3.5 km east of the site. Highway N-55, also known as the Indus Highway, runs through the site and has immediate access to the national railway, allowing for the easy delivery of equipment, fuel and other materials. The Jamshoro site consists of four (4) existing fossil fired electricity generating units. Unit 1 (U1) is fired by heavy fuel oil (HFO) with an original nominal rating of 250MW. U1 was originally commissioned in 1990. Units 2 to 4 are dual fuel (oil and gas) fired with an original nominal rating of 210MW (each). Units 2 to 4 were commissioned in 1989, 1990 and 1991 respectively. The scope of work under Site Remediation Package Lot II, includes procurement, transportation, storage, construction, repair, installation, all detailed survey and geotechnical investigation, site levelling, and drainage.

1.2 Project Background

Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds were filled with sludge, silt and clay along with wild bushes and vegetation growth.

Page 44: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Bi Annual Environmental Monitoring & Management Report

2

LOCATION OF THE PROJECT

Page 45: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Bi Annual Environmental Monitoring & Management Report

4

1.3 Scope of work

1.3.1 Performance of materials and services

The scope of work under Lot II, includes procurement, transportation,

storage, construction, repair, installation, all detailed survey and geotechnical investigation, site levelling, and drainage.

1.3.2 Construction of a cooling tower blow down channel

The broad scope of work under this contract shall include but is not limited to the following:

Detailed route elevations/survey for the entire discharge route (i.e.

from the existing water treatment plant to the terminal point on the bank of the Indus River)

Geotechnical investigations associated with the discharge route associated with the new reinforced concrete box culvert

Hydraulic analysis of closed and open channel design

Analysis of ground water table Civil design of channel

Construction of channel from power plant area to Indus river Construction of river embankment protection to avoid washout Construction of temporary diversion channels during construction of

permanent channel

1.3.3 Design and procurement of various equipment and systems

The Contractor shall carry out the basic and detailed design and engineering as applicable; finalize the parameters of all equipment and

systems. For those equipment and systems not falling under the Contractor's manufacturing range, the same shall be procured from

reputed sub-vendors. Contractor shall provide document to prove the capability of sub-vendor.

1.3.4 Transportation, receiving, handling and storage at site

The Contractor shall be responsible for proper transportation of all

materials, equipment and systems from the point of manufacture/procurement to the project site and its final location in the plant. It will be the Contractor's responsibility to develop the shipping

and transportation logistics. Similarly, it will be the Contractor's responsibility to coordinate with necessary departments such as

Imports, Customs, Port Authorities, Roadways, etc. Upon receipt of equipment and materials at site, the Contractor shall

make arrangements for proper receiving, handling and storage at site. Covered or indoor storage shall be provided by the Contractor, wherever

necessary. In case use of any hazardous material is envisaged, the Contractor shall make necessary arrangements duly complying with the

applicable laws or regulations or ordinance or statutes of the Government.

1.3.5 Construction, erection and testing

The Contractor shall follow standard procedures and instructions by the

Employer, if any, for carrying out proper construction, erection and

Page 46: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Bi Annual Environmental Monitoring & Management Report

5

testing of all the facility. For this purpose, it will be the Contractor's responsibility to ensure availability of construction machinery, cranes, rigging, scaffolding, tool for cutting, welding, erection, etc. as may be

required.

1.3.6 Commissioning, trial runs and performance guarantee tests

Any pump being provided under the work shall be commissioned and handed over to the client after trial run.

1.3.7 General requirements

The items specifically not mentioned in the specification but needed for

the smooth functioning of the equipment/system and plant requirement shall be deemed included in the scope of Contractor unless otherwise specifically mentioned under exclusions.

In addition to the scope and services mentioned above, the following general supplies and services shall be included in the scope of

Contractor.

1.3.8 Paints

The Contractor's scope of works includes supply of paints and painting of all equipment and structures as per the colour scheme to be approved by

Employer. The painting of various components shall comply with the requirement stipulated in different parts of this specification.

2.1 Environmental Monitoring Requirement & Parameters

The project is committed to monitor and manage its surrounding environment so

as to reduce the negative impacts which may arise from the project activities.

To control the adverse impacts on ambient air quality, traffic safety, noise levels,

Surface water and soil, waste management, cultural heritage management and

occupational health & safety of all personnel on site. The Sachal is regularly

monitoring and managing its construction site by implementing the approved

CEMP. The daily, weekly and monthly environmental inspection records are up to

date and have been checked by MML representatives. Precisely the following pre-

determined parameters as indicated below are being regularly monitored

subsequent management program has also taken under consideration for

successful completion of the project.

(a) Ambient air quality

(b) Traffic safety

(c) Noise Levels

(d) Surface water and soil

(e) Waste management

(f) Cultural heritage management

(g) Occupational Health and Safety

2.2 Environmental Monitoring during Construction Phase

According to Table 10-2 environmental monitoring in EIA report by ADB,

during the project activities the visual inspections were carried out on daily

Page 47: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Bi Annual Environmental Monitoring & Management Report

6

weekly and monthly basis to make sure that all above mentioned parameters

are on compliance with EIA and CEMP. The noise level data from the project

area is also collected quarterly. For surface water and soil analysis, the water

and soil samples were collected on different RDs by third party and results of

those tests were submitted to MML.

Monitoring and Management

Parameters (July 2017 - Dec 2017)

Ambient air quality Done with visual inspections

Traffic safety Implemented and monitored

Noise Levels Visual inspections and measurements

Surface water and soil Tests conducted & Submitted

Waste management Implemented & Monitored

Cultural heritage management Visual Inspections

Occupational Health and Safety Implemented and monitored

2.3 Project Environmental key personnel;

Sr. No. Project Key personnel Name of Key personnel Telephone No.

01 HSE Officer LOT-II. Atif Hussain 03332401024

3.0 Impact on Environmental Parameters during construction phase

3.1 Ambient Air Quality

During the construction activities vehicles are carrying employees and tools to the

site. Construction equipment, such as stone (aggregate) crushers is not being used

at the site which could create significant emission of particulate matters. Since

rehabilitation of evaporation ponds would most likely involve significant earth works,

increase in particulate matter in the air from wind-blown dust is also a concern,

especially considering the close proximity of the villages (Local stake holders) to the

project site. Ambient Air Quality was monitored by daily and weekly environmental

inspections at site.

3.2 Traffic Safety During project activities vehicle movement is a huge risk to environment as well as the personnel health on site for reducing the risk we put speed limit signs at different roads and drivers are instructed to follow the speed limits strictly. Furthermore, Environmental and health and safety inspections are carried out on regular basis to make sure that the controls are in place and complied properly. 3.3 Noise Levels During project activities, major source of noise is expected to be generated from

transport vehicles which include cranes excavator, trucks, LTVs etc. Regular

inspections of all equipment and vehicles are carried out to make sure the noise levels

are below 85 db.

Page 48: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

7

Bi Annual Environmental Monitoring & Management Report

Table: 3.3.1. Noise Level Monitoring during 3rd Quarter from July to September 2017

Table: 3.3.2. Noise Level Monitoring during 4th Quarter from October to December 2017

Sampling locations GPS

Coordinates Date and Time

Average Noise Level in dB

01 LOT-II Camp Office E 25.474125 N 68.274368

20th October 2017 09:00 am to 05:00 pm

55.43

02 0+000 KM E 25.473410 N 68.274533

25th October 2017

09:00 am to 05:00 pm

54.68

To assess the noise generated by different activities and equipment to be used at

various stages of the construction work without proper measures the workers and

officers may face partial or permanent hearing loss. The graphical presentation of

noise is depicted in the following pages of report (Figure-1, 2, 3, 4)

Sampling locations GPS Coordinates Date and Time

Average Noise Level in dB

01 LOT-II Camp Office E 25.474072 N 68.274292

20th September 2017 09:00 am to 05:00 pm

56.85

02 0+000 KM E 25.473462 N 68.274699

25th September 2017

09:00 am to 05:00 pm

53.16

Page 49: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

8

Bi Annual Environmental Monitoring & Management Report

Noise Level Monitoring during 3rd Quarter from July 2017 to September 2017

LOT-II Camp Office

Figure 1 0+000 KM

Figure 2

Page 50: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

9

Bi Annual Environmental Monitoring & Management Report

Noise Level Monitoring during 4th Quarter from October 2017 to December 2017 LOT-II Camp Office

Figure 3

0+000 KM

Figure 4

Page 51: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

10

Bi Annual Environmental Monitoring & Management Report

3.4 Surface water & soil

The surface water & soil sample were collected from Channel at different locations.

The samples were collected by third party for analysis and testing and water & soil

analysis report is submitted to MML.

3.5 Waste Management

The solid wastes of domestic nature generated mainly in the labor sheds are regularly

being collected in separate bins and being disposed through municipal cleaners

and being dumping in a designated municipal dumping place. In addition, a small

amount of solid kitchen waste is generated during day time which are also being

disposed in methodic way through municipal cleaner. The environmental and health

and safety inspections are carried out on regular basis to check the compliance.

3.6 Cultural Heritage management During project activities (excavation) and manual digging continual supervision is carried out throughout the project and environmental inspections are carried out regularly. Also chance find procedure is established and implemented as stated in CEMP. 3.7 Impact of OHS at project site Personal Protective Equipment (PPEs): During project activities, the workers may

face minor injuries due to accidental negligence. The regular provided services

are depicted in the following table-5.

Table-5: Monthly Occupational Health and Safety measure recorded at project site

“Construction of Channel for the Disposal of Cooling Tower Blow Down (LOT-II) project has achieved 1.525 million Cumulative safe man hours without lost time injury, project started from 1st February 2017”

Safety Statistics Jul-Aug Sep-Oct Nov-Dec

LTI 0 0 0

TRIR 0.04 0.01 0

Number of days without accident 62 61 61

Number of ill health cases 1 0 2

Overdue preventive open observations

17 16 08

Page 52: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

11

Bi Annual Environmental Monitoring & Management Report

4.0 Mitigation measures

4.1 Air Quality

To reduce the generation of dust owing to movement of construction materials

including vehicles, regular water spray are being accomplished at construction

site. Movement of construction debris are being covered while hauled and

stored, roads properly cleaned and water sprayed in order to minimize dust

in air. To reduce generation of dust the stone crusher and batching plant have

not been allowed at construction site.

4.2 Water Quality

The camp is outside the project boundary and from that place possible

management has been ensured to avoid any contamination of any sort around

the project boundary. During the day time, small quantity of office waste is

generated (approximately 2kg) per day which is properly disposed-off through

designated municipal corporation locations.

4.3 Noise Level

Use equipment i.e., designed with noise-control provision;

Route truck traffic away from noise-sensitive areas, where feasible;

Unnecessary vehicle movement has been avoided at project site;

Switch off the engines while remain unused.

4.4 OHS at project site

Personal Safety Equipment (PSE): Use appropriate personal protection

equipment, such as safety boots, helmets, gloves, protective clothing, goggles

and ear protection to comply HSE obligation during construction phase.

Page 53: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

12

Bi Annual Environmental Monitoring & Management Report

4.0 Pictures gallery

Site visit

Toolbox Talk

Toolbox Talk

Page 54: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

13

Bi Annual Environmental Monitoring & Management Report

Vehicle Inspection

PPEs Compliance at Site

PPEs Compliance at Site

Page 55: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 18 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

C. Semi-annual Environmental Monitoring

Report; Construction of Municipal Solid

Waste Facility (Lot 3); July - December 2017

(MAJ-IIC)

Page 56: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Jamshoro Power Company Limited

Project Site Remediation Package (Lot-III)

2 X 660 MW Coal Fired Power Project Jamshoro

December, 2017

Semi-Annual Environmental Progress Report

Page 57: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are
Page 58: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

1 2 5 4 8

D:\_Thar Coal\Reports to be formatted\Baseline Reports\HK --Draft Baseline Report for Flora and 05 October 2012

Semi-Annual Environmental

Progress Report

Project Site Remediation Package (Lot-III)

2 X 660 MW Coal Fired Power Project Jamshoro

From July to December 2017

Page 59: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

i

Issue and revision record

Revision Date Originator Checker Approver Description

A Dec, 2017 Engr Muhammad Safar Korai

Engr. Khan Muhammad Rajar

Engr. Abdul

Jabbar

Major (R)

Muhammad Salim

Khan

Submission

Page 60: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

2

1. INTRODUCTION 4

1.1. General Information About The Back Ground Of Project 4

1.2. Project Location 5

1.3. Employer (Client) 5

1.4. Engineer (Consultants) 5

1.5. Contractor 5

2. ACTIVITIES THAT HAVE BEEN UNDERTAKEN DURING THE REPORTING PERIOD 6

2.1. Awareness Program 6

2.2. Water Quality Analysis 21

2.2.1. Drinking Water Quality 21

3. COPIES OF ALL ENVIRONMENTAL MONITORING DATA AND CHECKLISTS 23

4. DETAIL OF ANY ENVIRONMENTAL INCIDENTS DURING THE REPORTING PERIOD 24

5. ANY OTHER DOCUMENTS AND RELEVANT DATA 25

6. CONCLUSIONS AND ACTION PLAN FOR THE NEXT PERIOD 25

6.1. Conclusions And Recommendations 25

6.2. Action Plan For The Next Period 25

Contents

Page 61: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

3

Abbreviations

ADB Asian Development Bank

GOP Government of Pakistan

ICC Indus Construction Company

JPCL Jamshoro Power Company Limited

JTPS Jamshoro Thermal Power Station

MAJ Main Abdul Jabbar

MSW Municipal Solid Waste

WHO World Health Organization

PIC Project Implementation consultant

Page 62: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

4

1. Introduction

1.1. General Information About the Back Ground of Project

The Government of Pakistan (GoP) is planning to set up a super-critical coal fired power plant at

Jamshoro (the ‘Jamshoro Power Generation Project’ or the ‘Project’) to be financed by the Asian

Development Bank (ADB). The power plant will be setup within the premises of the existing

Jamshoro Thermal Power Station (JTPS). The gross generation capacity of the Project will be 660

MW in the First Stage and 1,320 MW after expansion. The plant will be owned and operated by the

Jamshoro Power Company Limited (JPCL), the implementing agency of the Project.

The JTPS staff housing colony generates an estimated 750 1tons of solid waste annually. As there is

no proper disposal system, the waste is scattered around the colony. There is currently no solid

waste management system in place at the power plant either to manage waste generated in the plant

offices. The waste dumps can be seen in different location of the plant and the colony. There is no

municipal solid waste disposal facility available in the vicinity of the plant where the waste can be sent

for disposal. Aspects resulting from improper solid waste management are:

Contamination of surface and sub-surface soil by leaching from the dumps

Contamination of surface water in case of runoff

Transportation of contamination from leaching to the ground water aquifer

Possible attraction of scavengers to the solid waste dumps

Attraction of pests to the waste dumps resulting in spread of disease vectors

General nuisance and odor.

To overcome these issues, the mitigation measures are required which include:

Collection of waste on daily basis from the colony houses and office premises of the plant

Placement of bins in the key area with proper labelling for the type of waste to be thrown in the

bin and segregation of waste

Awareness campaigns on municipal waste management including segregation, reuse and

recycling

A properly designed landfill to cater for the plant needs will be developed.

1 Environmental Impact Assessment of Jamshoro Generation Project by Hagler Bailly Pakistan 2013

Page 63: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

5

1.2. Project Location

The JTPS is located north of Jamshoro town in the Jamshoro district of Sindh province, Pakistan. The

power plant is about 10 kilometer (km) northwest of Hyderabad and about 150 km northeast of

Karachi. It is located on N-55, also known as Indus Highway. N-55 is one of the two main highways of

the country which connect Karachi, the main port and industrial hub of the country, with the rest of the

country.

1.3. Employer (Client)

Jamshoro Power Company Limited (JPCL), the implementing agency (IA) of the Project.

GENCO Holding Company Limited (GHCL), the parent company of JPCL will be the

executing agency (EA).

1.4. Engineer (Consultants)

Mott Macdonald Ltd in association with MM Pakistan Pvt Limited (The Project Implementation

Consultant)

1.5. Contractor

M/S MAJ-ICC (JV) Bungalow No.C-20, Qasimabad, Hyderabad, Sindh, Pakistan

Page 64: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

6

2. Activities that Have Been Undertaken During The Reporting Period

Following activities have been performed from July to December 2017.

Awareness program

Water quality analysis

All these are discussed as under:

2.1. Awareness Program

Raising awareness about municipal solid waste management is a critical component of effective

waste management. It is important for key stakeholders to be aware of a city’s waste management

activities and have a strong understanding of the benefits of proper solid waste management.

Following are the main objectives of awareness program.

To motivate the local people to practice 3Rs (Reduce, Reuse and recycle)

To develop the sense of commitment among people to protect the environment

To imbibe among people the essence of environmental values and ethics and live in harmony

with nature a God’s gift.

Awareness program regarding proper management of MSW was initiated among the residents of the

colony. Followings figures show the awareness regarding benefits of proper management of MSW

and draw backs of improper management of MSW.

Page 65: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

7

Figure 2.1. Awareness Programme-I (Auditorium Hall of JPCL, Jamshoro)

Page 66: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

8

Figure 2.2. Awareness Programme-II (Door to Door)-Block-A/B of TPS Colony, Jamshoro

Page 67: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

9

Figure 2.3. Awareness Programme-III (Door to Door)-Block-C of TPS Colony, Jamshoro

Page 68: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

10

Figure 2.4. Awareness Programme-IV (Door to Door)-Block-D of TPS Colony, Jamshoro

Page 69: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

11

Figure 2.5. Awareness Programme-V (Door to Door)-Block-E of TPS Colony, Jamshoro

Page 70: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

12

Figure 2.6. Awareness Programme-IV (Door to Door)-Block-F of TPS Colony, Jamshoro

Page 71: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

13

Figure 2.7. Awareness Programme-IIV (Market-1) of TPS Colony, Jamshoro

Page 72: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

14

Figure 2.8. Awareness Programme-IIIV (Market-2) of TPS Colony, Jamshoro

Page 73: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

15

Figure 2.9. Awareness Programme-IX (Masjid-1) of TPS Colony, Jamshoro

Page 74: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

16

Figure 2.10. Awareness Programme-X (Masjid-2) of TPS Colony, Jamshoro

Page 75: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

17

Figure 2.11. Awareness Programme-XI (Masjid-3) of TPS Colony, Jamshoro

Page 76: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

18

Figure 2.12. Awareness Programme-XII (Play Ground) of TPS Colony, Jamshoro

Page 77: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

19

Figure 2.13. Awareness Programme-XIII (WAPDA High School) of TPS Colony, Jamshoro

Page 78: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

20

Figure 2.14. Awareness Programme-XIV (Iqra High School) of TPS Colony, Jamshoro

Page 79: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

21

2.2. Water Quality Analysis

Drinking and ground water quality were analysed as discussed below.

2.2.1. Drinking Water Quality

Water is one of the most essential elements to health and is so important that human body actually

has a specific drought management system in place to prevent dehydration and ensure survival.

Water might be everywhere, but one must never take it for granted. Water makes up more than two

thirds of human body weight, and without water, we would die in a few days. The human brain is

made up of 95% water, blood is 82% and lungs 90%. Water serves as a lubricant in digestion and

almost all other body processes. Our bodies can control over-heating through perspiration from sweat

glands in the skin and from evaporation which produces a cooling effect. Blood is also routed into

areas close to the surface of the skin where it can be cooled and then carried back to the interior of

the body. Conversing in a cold environment, the skin maintains proper body temperature by shunting

the blood away from the exterior surface thereby conserving heat within the body. The movement of

water within our cellular systems also transports vital blood plasma which is 92% made of water.

Blood plasma play a critical role in buffering the body’s pH, circulating antibodies from the immune

system, and regulating osmotic balance which all helps to maintain proper body temperature. In this

regard, drinking water quality was analysed in order to meet international as well as national standard

and World Health Organization (WHO) guidelines. Figure 2.15 shows the drinking water quality. At

site, clean and fresh water is provided to every worker. The result regarding water parameter are

within the WHO guidelines.

Page 80: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

22

Figure 2.15. Drinking water quality

Page 81: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

23

3. Copies of All Environmental Monitoring Data And Checklists

Figure 3.1 and 3.2 represent the copies of all environmental monitoring data and checklist

respectively.

Figure 3.1. Environmental Monitoring Data

Page 82: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

24

(a)

(b)

(c)

(d)

Figure 3.2. Environmental Checklist

4. Detail of Any Environmental Incidents During The Reporting Period

Until no any environmental incident like spills, excessive emissions to atmosphere, water quality

contamination have been determined. Each and every thing is smoothly going on. At site pure

Page 83: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Project Site Remediation Package (Lot-III)

Semi-Annual Environmental Monitoring Report

25

drinking water is provided to all workers. At site, all workers are satisfied and environment friendly

atmosphere is provided. Only in October and November 2017, two minor case happened as given in

Annexure I and II.

5. Any Other Documents and Relevant Data

At this stage, there is no any other documents and data relevant to the environmental and social

management of the project.

6. Conclusions and Action Plan For The Next Period

6.1. Conclusions and Recommendations

During the reporting period, it has been concluded that project activities are environment smoothly

going. Until no any unpleasant event has been occurred. Awareness program has been finalized and

it was observed that residents of the colony are very much interested in proper waste management

system. Drinking water quality assessment show that water quality parameters were within the range

of WHO guidelines for water quality parameters.

6.2. Action Plan For The Next Period

Following activities would be performed during the next reporting period

Performance Assessment of Awareness programs

Instalment of dustbins

Collection of MSW

Transportation of MSW

Segregation of MSW at site

Drinking and ground water quality monitoring

Air quality monitoring

Noise pollution assessment during excavation work

Page 84: Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction of PCC channel and culverts 3. River end protection 4. Final working drawings are

Mott MacDonald | Jamshoro Power Generation Project 19 Bi-annual Environmental Monitoring Report July to December 2017

334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017

mottmac.com