Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction...
Transcript of Environmental Monitoring Report · 17% 1. Construction of RCC box channel/culvert 2. Construction...
Environmental Monitoring Report
Bi-annual ReportCovering the period of July-December 2017
PAK: Jamshoro Power Generation Project
Project Number: 47094-001ADB Loan/Grant Number: L3090/3091/3092-PAKPrepared: January 2018
Prepared by the Jamshoro Power Company Limited (JPCL), with the assistance of MottMacDonald Limited (United Kingdom) in joint venture with MM Pakistan (Pvt) Ltd (Pakistan), forthe Islamic Republic of Pakistan and the Asian Development Bank (ADB).
This environmental monitoring report is a document of the borrower. The views expressed hereindo not necessarily represent those of ADB's Board of Directors, Management, or staff, and maybe preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designationof or reference to a particular territory or geographic area in this document, the AsianDevelopment Bank does not intend to make any judgments as to the legal or other status of anyterritory or area.
Jamshoro Power Generation Project
Bi-annual Environmental Monitoring Report July to December 2017
January 2018
334014-MML-JPCL-R-00639 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 -
Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Mott MacDonald
Mott MacDonald Al Gaith Towers Hamdan Street PO Box 47094, Abu Dhabi United Arab Emirates T +971 (0)2 401 5333 F +971 (0)2 627 0734 mottmac.com
Jamshoro Power Generation
Project
Bi-annual Environmental Monitoring Report July to December 2017
January 2018
Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered office: Mott MacDonald House, 8-10 Sydenham Road, Croydon CR0 2EE, United Kingdom
Mott MacDonald | Jamshoro Power Generation Project Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Issue and Revision Record
Revision Date Originator Checker Approver Description
0 31.01.18 GC JV
TH Final for issue
Information class: Standard
This document is issued for the party which commissioned it and for specific purposes connected with the above-
captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being
used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied
to us by other parties.
This document contains confidential information and proprietary intellectual property. It should not be shown to other
parties without consent from us and from the party which commissioned it.
This report has been pr epared sol el y for use by the party which commissi oned it (the ‘Client’) i n connecti on with the capti oned proj ect. It should not be used for any other purpose. N o person other than the Client or any party who has expressl y agreed ter ms of r eliance with us (the ‘Reci pient(s)’) may rel y on the content, i nformati on or any vi ews expressed i n the repor t. We accept no duty of care, responsi bility or liability to any other r eci pient of thi s document. This r eport is confi denti al and contains pr opri etar y intell ectual property.
statements supplied to us by other par ties incl udi ng the client (‘D ata’). We have not i ndependentl y verified such D ata and ha
Mott MacDonald | Jamshoro Power Generation Project Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Contents
1 Introduction 1
1.1 Overview 1
1.2 Activities during reporting period (July 01 to December 31 2017) 1
1.3 Environmental assessment 6
2 Environmental monitoring and management 7
2.1 Environmental monitoring and management overview 7
2.2 Summary of environmental monitoring during reporting period 7
2.2.1 Lot 1 – Rehabilitation of evaporation ponds 7
2.2.2 Lot 2 - Construction of channel for discharging of cooling tower blow down 9
2.2.3 Lot 3 – Municipal solid waste disposal facility 11
3 Actions during the next reporting period 13
Appendices 15
A. Semi-annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds (Lot 1); July - December 2017 (Sachal) 16
B. Semi-annual Environmental Monitoring and Management Report; Construction of channel for discharging of cooling tower blow down (Lot 2); July – December 2017 (Sachal) 17
C. Semi-annual Environmental Monitoring Report; Construction of Municipal Solid Waste Facility (Lot 3); July - December 2017 (MAJ-IIC) 18
Mott MacDonald | Jamshoro Power Generation Project 1 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
1 Introduction
1.1 Overview
The Government of Pakistan aims to increase the share of coal-based generation from almost
none in 2016 to 15% over the next few years. In support of this initiative Jamshoro Power
Company Limited (JPCL) and Genco Holding Company (GENCO), supported by the Asian
Development Bank (ADB), is planning a brownfield extension of the Jamshoro Power Station to
improve the total plant efficiency and increase the power output. The project is known as the
Jamshoro Power Generation Project (JPGP).
The project site is approximately 15km northwest of Hyderabad, and about 150km northeast of
Karachi in the Sindh Province of Pakistan. The lndus River is about 3.5km east of the power
plant site. Currently there are four fossil fuel-fired electricity generating units installed and
operating at the site (Unit 1 is oil fired and Units 2 – 4 have dual-fuel capability (oil/gas)).
JPGP is proposed to initially comprise of 1x660MW (net) supercritical power plant with facilities
to expand to 2x660MW plants. The project aims to decrease the existing power shortfall in
Pakistan and address environmental concerns from the existing oil-fired power units. The new
boiler(s) will be designed to utilise imported sub-bituminous coal blended at 80/20 with local
lignite as its fuel.
As part of the feasibility study for the project and as required by the ADB an environmental audit
was undertaken of the existing plant. The audit was included as part of the environmental and
social impact assessment (ESIA) for the 2x660MW supercritical power plant (Environmental
Impact Assessment; Jamshoro Power Generation Project; Hagler Bailly Pakistan, October 29,
2013 (the ESIA report)). Section 6 of the ESIA report (Issues Related to Existing Plant and
Corrective Actions) identified several items related to the existing plant that require remediation
or rehabilitation.
The items that were identified are subject to a loan condition applied by ADB that requires the
identified remediation works to have a signed contract in place prior to commencement of works
on the site associated with the new facility (660MW supercritical power plant).
1.2 Activities during reporting period (July 01 to December 31 2017)
At the time of compiling this report (January 2018) JPGP is in the early implementation stage
with the following activities underway:
Final proposals for construction and operation of the 2x660MW (gross) supercritical power plant
have been evaluated and are waiting award. Award is dependent upon the revised Loan
Agreements (i.e. ADB and IDB) being accepted by all parties and the necessary conditions
precedent being accomplished by JPCL. It is currently envisaged that the Contracts will be
awarded by the third quarter of 2018.
The status of the remediation packages is provided data Table 1.
This report is the sixth bi-annual environmental monitoring report for the project covering the
period from July 01, 2017 to December 31, 2017 inclusive. Subsequent bi-annual reports will be
reconfigured as necessary to reflect activities and available information as the project develops.
Mott MacDonald | Jamshoro Power Generation Project 2 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
This page is left intentionally blank
Mott MacDonald | Jamshoro Power Generation Project 3 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Table 1: Remediation status summary Data Date – 27.12.2017
Sr.
No
Name of
contract
Opening
date
Award
date
Comm. date /
duration
Estimate / bid /
contract (in
PKR)
Present status Physical
progress
Activities pending
1 Lot 1.
Renovation of
effluent
evaporation
ponds
31-03-2016 23-11-
2016
Commencement:
01-02-2017
Duration: 180
days (extended
up to 272 days
i.e. 30th
October)
Estimate: 247.61
million
Contract: 190.24
million
1. Construction of
embankments in pond II, III
& IV are in progress (outer
sides).
2. Removal of roots at pond III
& IV are in progress
3. Preparation of construction
joints in PCC & RCC are in
progress.
4. Earth work (key and apron)
at west & north side of pond
III, to rectify the levels
difference between bed &
apron
92% 1. Installation of 12 inch
FRP piping stub
connections at the head
end
2 Lot 2.
Construction
of channel for
discharging of
cooling tower
blow down
31-03-2016 23-11-
2016
Commencement:
01-02-2017
Duration: 180
days
Estimate: 179.59
million
Contract: 219.32
million
1. Access to the site after
boundary wall is still not
clear i.e. 00+0197
2. Resubmitted design
calculations and drawings
are under review
3. Survey work of coagulator
connecting channel at
0+225 is in progress
4. Water diverted after RBOD
14-12-2017.
5. Site visited on 21-12-2017
jointly with JPCL about
dismantling of RCC
wall/platform to identify the
underneath services and
dismantling of RCC
Abundance walls is in
progress
6. Lean concreted from 0+071
to 0+185 and from 0+220 to
0+350 local stop activity 16-
12-2017
17% 1. Construction of RCC box
channel/culvert
2. Construction of PCC
channel and culverts
3. River end protection
4. Final working drawings
are required after PIC
observations/comments
5. RCC work, bar bending
schedule is to be
submitted
6. Drawing of diversion
channel after boundary
wall is required
Mott MacDonald | Jamshoro Power Generation Project 4 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
7. Preparation of Lean from
0+00 to 0+071 is in
progress
3 Lot 3.
Construction
of municipal
solid waste
disposal
facilities
31-03-2016 07-12-
2016
Commencement:
02-01-2017
Duration: 180
days
Estimate: 63.39
million
Contract: 63.00
million
Landfill area
1. Excavation of landfill area
(east side) is in progress
2. Brick work of boundary wall
up to the bottom of plinth
beam is in progress.
3. Concreting of super column
above plinth beam
boundary wall of landfill
area is in progress
4. Brick work above plinth
beam of boundary wall of
landfill area is in progress
5. Concreting of plinth beam of
section B at grid 3 boundary
wall of landfill area is in
progress
6. Community waste
management awareness’ programme is in progress.
Office block
1. Short columns of boundary
wall and guard room
concreted
2. Reinforcement and
formwork of plinth beam of
boundary wall is in progress
58% Landfill area
1. Design drawings of
Construction of
Municipal solid waste
disposal area after PIC
observations, are
awaited.
2. Disposal of existing
municipal waste of the
colony
4 Lot 4.
Construction
of hazardous
solid waste
facilities
03-04-2017 --- Duration: 180
days
Estimate: 85.00
million
Lowest bid: 85.66
million
Signing of contract agreement
between contractor and JPCL is
awaited.
--- Site supervision
5 Lot 5. Supply
and
construction
10-04-2017 --- Duration: 270
days
Estimate: 81.5
million
BER is with JPCL, must be issued to
ADB.
--- Approvals
Award of contract.
Mott MacDonald | Jamshoro Power Generation Project 5 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Source: Mott MacDonald Project Files
of sewage
treatment
plant
Lowest bid: 109.9
million
Site supervision
6 Lot 6.
Contaminated
soil
remediation
30-05-2017 --- Duration: 365
days
Estimate: 992.09
million
Bid amount: 1053
million
Must be discussed with EPC
contractor, for carrying out the job.
--- Approvals
Award of Contract.
Site supervision
Mott MacDonald | Jamshoro Power Generation Project 6 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
1.3 Environmental assessment
The ESIA study and subsequent ESIA report for the proposed 2x660MW power plant were
developed for the Asian Development Bank and include reference to Pakistan national
standards and regulatory requirements and international guidelines including ADBs Safeguard
Policy Statement (2009) and the World Bank/International Finance Corporation Environment,
Health and Safety Guidelines for Thermal Power Plants (2008) (IFC EHS guidelines).
International treaties that Pakistan is a signatory to are also considered.
The EIA report identifies that both Pakistan national environmental quality standards (NEQS)
and IFC EHS guidelines will have to be complied with. In operation this means that the most
stringent of the NEQA and IFC EHS Guidelines environmental limits/standards/guidelines will
have to be complied with (with the exception of ambient air quality standards where national
standards, where they exist, take precedence over IFC EHS guidelines).
A gap analysis with respect to environmental aspects in the draft bidding documents and
technical specifications was prepared by the project implementation consultant (PIC – Mott
MacDonald) and a number of items were identified that were included in the technical
requirements for the 2x660MW supercritical power plant when the tender documents were
issued.
Mott MacDonald | Jamshoro Power Generation Project 7 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
2 Environmental monitoring and management
2.1 Environmental monitoring and management overview
At the time of compiling this report (January 2018) three work packages were under progress:
Lot 1 – Evaporation pond renovation
Lot 2 – Blow-down channel renovation
Lot 4 – Municipal solid waste disposal facility
Lot 1 and Lot 2 are being undertaken by Sachal Engineering Works (Pvt) Ltd (Sachal).
Construction environmental management plans have been developed and approved for both
lots. The approved CEMPs include details of scheduled environmental monitoring during the
construction process. Monitoring of environmental parameters for Lot 1 and Lot 2 are
summarised in this report. The monitoring reports for Lot 1 and Lot 2 prepared by Sachal are
attached as Appendix A and Appendix B respectively.
Lot 3 being undertaken by a consortium of Mian Abdul Jabbar & Co and Indus Construction Co
(MAJ ICC). A construction environmental management plan has been developed for Lot 3.
Monitoring of environmental parameters for Lot 3 are summarised in this report. The monitoring
report for Lot 3 prepared by MAJ ICC is attached as Appendix C.
2.2 Summary of environmental monitoring during reporting period
2.2.1 Lot 1 – Rehabilitation of evaporation ponds
Lot 1 involves clearing four existing evaporation ponds of heavy vegetation growth and
sediment deposits that have built up over many years of use. Repairs are then to be carried out
to any damage to the structure of the ponds and associated infrastructure as necessary to make
the ponds functional. Mechanical excavators, dozers and haulage trucks, tractors and trailers
are all used for removing and transporting material. Excavated material is deposited at a
designated site within the JPCL site.
The information reported here is extracted from the contractor’s (Sachal) ‘Bi Annual
Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds, July to
December 2017’ a copy of which is attached as Appendix A.
The following parameters are monitored and reported:
(a) Ambient air quality
(b) Traffic safety
(c) Noise Levels
(d) Surface water and soil
(e) Waste management
(f) Cultural heritage management
(g) Occupational health and safety
Many of the parameters are monitored visually on an ongoing basis and reported qualitatively.
Where quantitative data is available it is reported here.
Mott MacDonald | Jamshoro Power Generation Project 8 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
a) Ambient air quality. Taken primarily as dust, visual assessments are made and water
sprays are used to control dust levels routinely and in response to observed excessive
dust levels. No excessive dust issues have been reported during the reporting period.
b) Traffic safety. Traffic safety is controlled on site by imposing speed limits and
instructions to drivers. Traffic activity is routinely monitored by environment, health and
safety personnel on site. No adverse traffic related incidents have been reported during
the reporting period.
c) Noise levels. Noise is monitored on site from a health and safety perspective.
Monitoring data is reported in Table 3.3.1 and Table 3.3.2 of the contactors bi-annual
environmental report for Lot 1 in Appendix A. No breaches of the 85dB health and
safety noise limits were recorded during the reporting period. Noise monitoring is
reported in Table 2 and Table 3.
Table 2: Noise Level Monitoring during 3rd Quarter from July to September 2017
Sampling
locations
GPS
Coordinates Date and Time
Average Noise Level
in dB
01
Lot-I Camp
Office
E 25.477567
N 68.273647
20 September 2017
09:00 am to 05:00 pm 57.28
02
Pond IV E 25.473728 N 68.275454
25 September 2017
09:00 am to 05:00 pm
52.13
Source: Semi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. July - December 2017. Sachal
Table 3: Noise Level Monitoring during 4th Quarter from October to December 2017
Sampling
locations
GPS
Coordinates Date and Time
Average Noise Level
in dB
01
Lot-I Camp
Office
E 25.477284
N 68.273569
20 October 2017 09:00
am to 05:00 pm 54.76
02
Pond IV E 25.473716 N 68.275442
25 October 2017 09:00
am to 05:00 pm
57.27
Source: Semi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. July - December 2017. Sachal
d) Surface water and soil. Samples of surface water and soils from the evaporation ponds
were taken and analysed. No exceedances of prescribed standards are reported.
e) Waste management. Solid waste is reported to be collected and disposed of in a
designated municipal disposal site.
f) Cultural heritage management. During excavations, continual observations are made to
identify culturally important artefacts and a chance-finds procedure is included in the
construction environmental management plan (CEMP). Given the nature of the activities
on Lot 1 it is considered unlikely that any culturally important artefacts will be present.
Mott MacDonald | Jamshoro Power Generation Project 9 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
g) Occupational health and safety. Health and Safety statistics are recorded and reported
in Sachal’s bi-annual environmental report and are shown in Table 4
Table 4: Monthly Occupational Health and Safety measure recorded at project site
Safety Statistics Jul-Aug Sep-Oct Nov-Dec
LTI 0 0 0
TRIR 0.02 0.01 0
Number of days without accident 62 61 61
Number of ill health cases 2 1 0
Overdue preventive open observations 18 20 05
Source: Semi Annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds. July - December 2017. Sachal
2.2.2 Lot 2 - Construction of channel for discharging of cooling tower blow down
The broad scope of work under this contract shall include but is not limited to the following:
● Detailed route elevations/survey for the entire discharge route (i.e. from the existing water
treatment plant to the terminal point on the bank of the Indus River)
● Geotechnical investigations associated with the discharge route associated with the new
reinforced concrete box culvert
● Hydraulic analysis of closed and open channel design
● Analysis of ground water table
● Civil design of channel
● Construction of channel from power plant area to Indus river
● Construction of river embankment protection to avoid washout
● Construction of temporary diversion channels during construction of permanent channel
The information reported here is extracted from the contractor’s (Sachal) ‘Semi-annual
Environmental Monitoring Report for Construction of Channel for the Disposal of Cooling Tower
Blow Down (Lot-2). July-December 2017’ a copy of which is attached as Appendix B.
The following parameters are monitored and reported:
(a) Ambient air quality
(b) Traffic safety
(c) Noise Levels
(d) Surface water and soil
(e) Waste management
(f) Cultural heritage management
(g) Occupational health and safety
Many of the parameters are monitored visually on an ongoing basis and reported qualitatively.
Where quantitative data is available it is reported here.
a) Ambient air quality. Taken primarily as dust, visual assessments are made and water
sprays are used to control dust levels routinely and in response to observed excessive
dust levels. No excessive dust issues have been reported during the reporting period.
Mott MacDonald | Jamshoro Power Generation Project 10 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
b) Traffic safety. Traffic safety is controlled on site by imposing speed limits and
instructions to drivers. Traffic activity is routinely monitored by environment, health and
safety personnel on site. No adverse traffic related incidents have been reported during
the reporting period.
c) Noise levels. Noise is monitored on site from a health and safety perspective.
Monitoring data is reported in Table 3.3.1 and Table 3.3.2 of the contactors bi-annual
environmental report for Lot 2 in Appendix B. No breaches of the 85dB health and
safety noise limits were recorded during the reporting period. Noise monitoring is
reported in Table 5 and Table 6.
Table 5: Noise Level Monitoring during 3rd Quarter from July to September 2017
Sampling
locations
GPS
Coordinates Date and Time
Average Noise Level
in dB
01
Lot-II Camp
Office
E 25.474072
N 68.274292
20 September 2017
09:00 am to 05:00 pm 56.85
02 0+000 KM
E 25.473462
N 68.274699
25 September 2017
09:00 am to 05:00 pm
53.16
Source: Semi Annual Environmental Monitoring and Management Report; Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II). July - December 2017. Sachal
Table 6: Noise Level Monitoring during 4th Quarter from October to December 2017
Sampling
locations
GPS
Coordinates Date and Time
Average Noise Level
in dB
01
Lot-II Camp
Office
E 25.474125
N 68.274368
20 October 2017
09:00 am to 05:00 pm 55.43
02 0+000 KM
E 25.473410
N 68.274533
25 October 2017
09:00 am to 05:00 pm 54.68
Source: Semi Annual Environmental Monitoring and Management Report; Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II). July - December 2017. Sachal
d) Surface water and soil. Samples of surface water and soils from the evaporation ponds
were taken and analysed. No exceedances of prescribed standards are reported.
e) Waste management. Solid waste is reported to be collected and disposed of in a
designated municipal disposal site.
f) Cultural heritage management. During excavations, continual observations are made to
identify culturally important artefacts and a ‘chance-finds’ procedure is included in the construction environmental management plan (CEMP). Given the nature of the activities
on Lot 1 it is considered unlikely that any culturally important artefacts will be present.
g) Occupational health and safety. Health and Safety statistics are recorded and reported
in Sachal’s bi-annual environmental report and are shown in Table 7.
Mott MacDonald | Jamshoro Power Generation Project 11 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
“Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II) project
has achieved 1.525 million Cumulative safe man hours without lost time injury, project
started from 1st February 2017”
Table 7: Monthly Occupational Health and Safety measure recorded at project site
Safety Statistics Jul-Aug Sep-Oct Nov-Dec
LTI 0 0 0
TRIR 0.04 0.01 0
Number of days without accident 62 61 61
Number of ill health cases 1 0 2
Overdue preventive open observations 17 16 8
Source: Semi Annual Environmental Monitoring and Management Report; Construction of Channel for the Disposal of Cooling Tower Blow Down (Lot-II). July - December 2017. Sachal
2.2.3 Lot 3 – Municipal solid waste disposal facility
Lot 3 involves the design and construction of a municipal solid waste facility for the housing
colony; removing municipal waste from the housing colony and depositing in the newly
constructed facility; and capacity building for JPCL employees and colony residents on the
handling and disposal of municipal waste. The information reported here is extracted from the
contractor’s (MAJ-IIC) Semi-Annual Environmental Monitoring Report; Project Site Remediation
Package (Lott 3). July-December 2017. The monitoring report prepared by MAJICC is attached
as Appendix C.
Lot 3 is in the early stages of development. During the reporting period the following activities
have been undertaken or are in progress:
1. Excavation of landfill area (east side) is in progress
2. Brick work of boundary wall up to the bottom of plinth beam is in progress.
3. Concreting of super column above plinth beam boundary wall of landfill area is in
progress
4. Brick work above plinth beam of boundary wall of landfill area is in progress
5. Concreting of plinth beam of section B at grid 3 boundary wall of landfill area is in
progress
6. Community waste management awareness’ programme is in progress. 7. Toolbox talks have been undertaken for company staff on site. Subjects covered are
jungle cutting, proper use of PPE and geotechnical investigations
8. Drinking and water quality sampling and analysis
Water quality monitoring results for October and November 2017 are presented in the MAJ-IIC
consortium Semi-Annual Environmental Monitoring Report; Project Site Remediation Package
(Lott 3). July-December 2017. All reported parameters are within WHO guidelines.
Registers of attendance at toolbox talks on: plastering of the office block; concreting of column
footing; and brick masonry work at the boundary wall are presented in the environmental
monitoring report.
As Lot 3 progresses more detailed environmental monitoring will be required to be reported.
During the next reporting period MAJICC state that they will undertake the following tasks:
● Performance assessment of awareness programmes
Mott MacDonald | Jamshoro Power Generation Project 12 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
● Installation of dustbins
● Collection of MSW
● Transportation of MSW
● Segregation of MSW at site
● Drinking and ground water quality monitoring
● Air quality monitoring
● Noise pollution assessment during excavation work
It is anticipated that Lot 3 detailed design of the municipal waste disposal facility will be agreed
and construction will continue during the next reporting period.
Mott MacDonald | Jamshoro Power Generation Project 13 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
3 Actions during the next reporting period
During the forthcoming period (January to June 2018) the following actions are anticipated for
the remediation packages:
Award of Lots 1, 2, and 3 associated with the 2x660 MW EPC and O&M Contracts.
Remediation Lot 1 will be completed.
Remediation Lot 2 will resume.
Remediation Lot 3 will continue.
Remediation Lots 4, 5, and 6 will be awarded and work will begin. JPCL will also take action
relating to cessation of oil transfer pollution processes associated with Lot 6.
PIC environmental specialists will:
Respond to queries relating to environmental aspects of all remediation lots.
As appropriate, work with preferred bidders/awarded bidders to establish environmental
management and monitoring plans, programmes and reporting.
The next semi-annual environmental monitoring report will cover the period from January to
June 2018 and will be made available by the end of July 2018.
Mott MacDonald | Jamshoro Power Generation Project 14 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Mott MacDonald | Jamshoro Power Generation Project 15 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
Appendices
A. Semi-annual Environmental Monitoring and Management Report; Rehabilitation of Effluent Ponds (Lot 1); July - December 2017 (Sachal) 16
B. Semi-annual Environmental Monitoring and Management Report; Construction of channel for discharging of cooling tower blow down (Lot 2); July – December 2017 (Sachal) 17
C. Semi-annual Environmental Monitoring Report; Construction of Municipal Solid Waste Facility (Lot 3); July - December 2017 (MAJ-IIC) 18
Mott MacDonald | Jamshoro Power Generation Project 16 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
A. Semi-annual Environmental Monitoring
and Management Report; Rehabilitation of
Effluent Ponds (Lot 1); July - December 2017
(Sachal)
SEMIANNUAL ENVIRONMENTAL
MONITORING & MANAGEMENT REPORT
Project Name: Site Remediation Contract for LOT-I Rehabilitation of Effluent Evaporation Ponds
Period: (July 2017 to December 2017)
Report prepared by: Atif Hussain _____________________
HSE Officer
TABLE OF CONTENTS
Sr. No. Particulars Page
1.0 Project Description
1.1 Project Description 1
1.2 Project Background 1
1.3 Scope of work 4
2.0 Environmental Monitoring Requirements & Parameters
2.1 Environmental Monitoring 4
2.2 Environmental Monitoring during Construction Phase 4
2.3 Project Environmental key personnel 5
3.0 Impact on Environmental Parameters during Construction Phase
3.1 Ambient air quality 5
3.2 Traffic safety 5
3.3 Noise Levels 5
3.4 Surface water and soil 9
3.5 Waste Water Management 9
3.6 Cultural Heritage Management 9
3.7 Impact of OHS at Project Site 9
4.0 Mitigation Measures
4.1 Air Quality 10
4.2 Water Quality 10
4.3 Noise Level 10
4.4 OHS at Project Site 10
5.0 Picture Gallery 11
1
Bi Annual Environmental Monitoring & Management Report
1.1 Project Description
The Jamshoro site is about 20 km northwest of Hyderabad, and about 150 km northeast of Karachi. The Indus River flows about 3.5 km east of the site. Highway N-55, also known as the Indus Highway, runs through the site and has immediate access to the national railway, allowing for the easy delivery of equipment, fuel and other materials. The Jamshoro site consists of four (4) existing fossil fired electricity generating units. Unit 1 (U1) is fired by heavy fuel oil (HFO) with an original nominal rating of 250MW. U1 was originally commissioned in 1990. Units 2 to 4 are dual fuel (oil and gas) fired with an original nominal rating of 210MW (each). Units 2 to 4 were commissioned in 1989,1990 and 1991 respectively. Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds are now completely filled with sludge, silt and clay along with wild bushes and vegetation growth. The evaporation ponds are to be cleared of wild bushes and vegetation. The existing evaporation ponds and associated channels are to be cleaned. The silt/sludge is to be taken out from the evaporation ponds required levels mentioned in as built/tender drawing and will be dumped to the Water Pre Treatment Area (WPTA) south of Evaporation Ponds within the power plant premises. The discarding of silt and sludge shall comply with the applicable provisions within the EIA.
1.2 Project Background
Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds were filled with sludge, silt and clay along with wild bushes and vegetation growth.
2
Bi Annual Environmental Monitoring & Management Report
LOCATION OF THE PROJECT
3
Bi Annual Environmental Monitoring & Management Report
1.3 Scope of work
1.3.1 Performance of materials and services
The scope of work under Lot I, includes procurement, transportation, storage,
construction, repair, installation, all detailed survey and geotechnical investigation, site levelling, and drainage.
1.3.2 Renovation of effluent evaporation ponds
The broad scope of work under this contract shall include but is not limited to
the following:
Removal of all bushes and vegetative growth on existing surface of Evaporation Pond Area
Sludge and Silt removal from four (4ea) existing evaporation ponds Disposal Silt and Sludge in accordance with environmental standards
Assessment of damages to the existing evaporation ponds and connecting channel
Installation of new 12 inch FRP connections at the head end of each pond
for later use Restoration of evaporation ponds to original conditions (as demonstrated
in the tender (“as built” drawing set)
1.3.3 Design and procurement of various equipment and systems
The Contractor shall carry out the basic and detailed design and engineering as applicable; finalize the parameters of all equipment and systems. For those
equipment and systems not falling under the Contractor's manufacturing range, the same shall be procured from reputed sub-vendors. Contractor shall provide document to prove the capability of sub-vendor.
1.3.4 Transportation, receiving, handling and storage at site
The Contractor shall be responsible for proper transportation of all materials, equipment and systems from the point of manufacture/procurement to the
project site and its final location in the plant. It will be the Contractor's responsibility to develop the shipping and transportation logistics. Similarly, it will be the Contractor's responsibility to coordinate with necessary
departments such as Imports, Customs, Port Authorities, Roadways, etc.
Upon receipt of equipment and materials at site, the Contractor shall make arrangements for proper receiving, handling and storage at site. Covered or indoor storage shall be provided by the Contractor, wherever necessary. In
case use of any hazardous material is envisaged, the Contractor shall make necessary arrangements duly complying with the applicable laws or
regulations or ordinance or statutes of the Government.
1.3.5 Construction, erection and testing
The Contractor shall follow standard procedures and instructions by the Employer, if any, for carrying out proper construction, erection and testing of
all the facility. For this purpose, it will be the Contractor's responsibility to ensure availability of construction machinery, cranes, rigging, scaffolding, tool for cutting, welding, erection, etc. as may be required.
4
Bi Annual Environmental Monitoring & Management Report
1.3.6 Commissioning, trial runs and performance guarantee tests
Any pump being provided under the work shall be commissioned and handed over to the client after trial run.
1.3.7 General requirements
The items specifically not mentioned in the specification but needed for the
smooth functioning of the equipment/system and plant requirement shall be deemed included in the scope of Contractor unless otherwise specifically
mentioned under exclusions. In addition to the scope and services mentioned above, the following general supplies and services shall be included in the scope of Contractor.
1.3.8 Paints
The Contractor's scope of works includes supply of paints and painting of all equipment and structures as per the color scheme to be approved by Employer. The painting of various components shall comply with the requirement
stipulated in different parts of this specification.
2.0 Environmental Monitoring
2.1 Environmental Monitoring Requirement & Parameters
The project is committed to monitor and manage its surrounding environment so as
to reduce the negative impacts which may arise from the project activities. To control
the adverse impacts on ambient air quality, traffic safety, noise levels, Surface water and
soil, waste management, cultural heritage management and occupational health & safety
of all personnel on site. The Sachal is regularly monitoring and managing its construction
site by implementing the approved CEMP. The daily, weekly and monthly environmental
inspection records are up to date and have been checked by MML representatives.
Precisely the following pre-determined parameters as indicated below are being regularly
monitored subsequent management program has also taken under consideration for
successful completion of the project.
(a) Ambient air quality
(b) Traffic safety
(c) Noise Levels
(d) Surface water and soil
(e) Waste management
(f) Cultural heritage management
(g) Occupational Health and Safety
2.2 Environmental Monitoring during Construction Phase
According to Table 10-2 environmental monitoring in EIA report by ADB,
during the project activities the visual inspections were carried out on daily
weekly and monthly basis to make sure that all above mentioned parameters
5
Bi Annual Environmental Monitoring & Management Report
are on compliance with EIA and CEMP. The noise level data from the project
area is also collected quarterly. For surface water and soil analysis, the water
and soil samples were collected on different RDs by third party and results of
those tests were submitted to MML.
Monitoring and Management
Parameters (July 2017 - Dec 2017)
Ambient air quality Done with visual inspections
Traffic safety Implemented and monitored
Noise Levels Visual inspections and measurements Surface water and soil Tests conducted & Submitted
Waste management Implemented & Monitored
Cultural heritage management Visual Inspections
Occupational Health and Safety Implemented and monitored
2.3 Project Environmental key personnel;
Sr. No.
Project Key personnel Name of Key
personnel Telephone No.
01 HSE Officer LOT-I. Atif Hussain 03332401024
3.0 Impact on Environmental Parameters during construction phase
3.1 Ambient Air Quality
During the construction activities vehicles are carrying employees and tools to the
site. Construction equipment, such as stone (aggregate) crushers is not being used
at the site which could create significant emission of particulate matters. Since
rehabilitation of evaporation ponds would most likely involve significant earth works,
increase in particulate matter in the air from wind-blown dust is also a concern,
especially considering the close proximity of the villages (Local stake holders) to the
project site. Ambient Air Quality was monitored by daily and weekly environmental
inspections at site.
3.2 Traffic Safety During project activities vehicle movement is a huge risk to environment as well as the personnel health on site for reducing the risk we put speed limit signs at different roads and drivers are instructed to follow the speed limits strictly. Furthermore, Environmental and health and safety inspections are carried out on regular basis to make sure that the controls are in place and complied properly.
3.3 Noise Levels During project activities, major source of noise is expected to be generated from
transport vehicles which include cranes excavator, trucks, LTVs etc. Regular
inspections of all equipment and vehicles are carried out to make sure the noise levels
are below 85 db.
6
Bi Annual Environmental Monitoring & Management Report
Table: 3.3.1. Noise Level Monitoring during 3rd Quarter from July to September 2017
Table: 3.3.2. Noise Level Monitoring during 4th Quarter from October to December 2017
Sampling locations GPS
Coordinates Date and Time
Average Noise Level in dB
01 Lot-I Camp Office E 25.477284 N 68.273569
20th October 2017 09:00 am to 05:00 pm
54.76
02 Pond IV E 25.473716 N 68.275442
25th October 2017
09:00 am to 05:00 pm
57.27
To assess the noise generated by different activities and equipment to be used at
various stages of the construction work without proper measures the workers and
officers may face partial or permanent hearing loss. The graphical presentation of
noise is depicted in the following pages of report (Figure-1, 2, 3, 4)
Sampling locations GPS Coordinates Date and Time
Average Noise Level in dB
01 Lot-I Camp Office E 25.477567 N 68.273647
20th September 2017 09:00 am to 05:00 pm
57.28
02 Pond IV E 25.473728 N 68.275454
25th September 2017
09:00 am to 05:00 pm
52.13
7
Bi Annual Environmental Monitoring & Management Report
Noise Level Monitoring during 3rd Quarter from July 2017 to September 2017
Lot-I Camp Office
Figure 1 Pond IV
Figure 2
8
Bi Annual Environmental Monitoring & Management Report
Noise Level Monitoring during 4th Quarter from October 2017 to December 2017 Lot-I Camp Office
Figure 3
Pond IV
Figure 4
9
Bi Annual Environmental Monitoring & Management Report
3.4 Surface water & soil
The surface water & soil sample were collected from evaporation ponds at different
locations. The samples were collected by third party for analysis and testing and water &
soil analysis report is submitted to MML.
3.5 Waste Management
The solid wastes of domestic nature generated mainly in the labor sheds are regularly
being collected in separate bins and being disposed through municipal cleaners and
being dumping in a designated municipal dumping place. In addition, a small amount of
solid kitchen waste is generated during day time which are also being disposed in
methodic way through municipal cleaner. The environmental and health and safety
inspections are carried out on regular basis to check the compliance.
3.6 Cultural Heritage management During project activities (excavation) and manual digging continual supervision is carried out throughout the project and environmental inspections are carried out regularly. Also chance find procedure is established and implemented as stated in CEMP.
3.7 Impact of OHS at project site Personal Protective Equipment (PPEs): During project activities, the workers may face
minor injuries due to accidental negligence. The regular provided services are depicted
in the following table-5.
Table-5: Monthly Occupational Health and Safety measure recorded at project site
“The Renovation of Evaporation Ponds (LOT-I) project has achieved 3.211 million Cumulative safe man hours without lost time injury, project started from 1st February 2017”
Safety Statistics Jul-Aug Sep-Oct Nov-Dec
LTI 0 0 0
TRIR 0.02 0.01 0
Number of days without accident 62 61 61
Number of ill health cases 2 1 0
Overdue preventive open observations
18 20 05
10
Bi Annual Environmental Monitoring & Management Report
4.0 Mitigation measures
4.1 Air Quality
To reduce the generation of dust owing to movement of construction materials
including vehicles, regular water spray are being accomplished at construction
site. Movement of construction debris are being covered while hauled and
stored, roads properly cleaned and water sprayed in order to minimize dust
in air. To reduce generation of dust the stone crusher and batching plant have
not been allowed at construction site.
4.2 Water Quality
The camp is outside the project boundary and from that place possible
management has been ensured to avoid any contamination of any sort around
the project boundary. During the day time, small quantity of office waste is
generated (approximately 2kg) per day which is properly disposed-off through
designated municipal corporation locations.
4.3 Noise Level
Use equipment i.e., designed with noise-control provision;
Route truck traffic away from noise-sensitive areas, where feasible;
Unnecessary vehicle movement has been avoided at project site;
Switch off the engines while remain unused.
4.4 OHS at project site
Personal Safety Equipment (PSE): Use appropriate personal protection
equipment, such as safety boots, helmets, gloves, protective clothing, goggles
and ear protection to comply HSE obligation during construction phase.
11
Bi Annual Environmental Monitoring & Management Report
4.0 Pictures gallery
Evaporation Pond 1 south side (Dated :24/10/2017.)
Mr. Adnan Visited Site with MMP Team
Toolbox Talk
First Aid given by Medical Officer
12
Bi Annual Environmental Monitoring & Management Report
Speed Limit Signboards on Activity Route
Parking Area
Barricaded Walkways
13
Bi Annual Environmental Monitoring & Management Report
Assembly Point
Emergency Drill
Water Sprinkling on Activity Route
Mott MacDonald | Jamshoro Power Generation Project 17 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
B. Semi-annual Environmental Monitoring
and Management Report; Construction of
channel for discharging of cooling tower
blow down (Lot 2); July – December 2017
(Sachal)
___________________________________________________________________________________________________________
Islamabad: 59E, Street No.7, I-10/3, Islamabad. Tel: 0514446837-74, Fax: (92-51) 4431774, Email: [email protected]
Karachi: Business Avenue, Sharah-e-faisal, Karachi. Tel: 021-34536952, Fax: (92-21) 34322283, Email: [email protected]
No. SACHAL/JAM/JPCL/2017/0171 Date: 29th Dec, 2017 Timothy Mark Hulme, Team Leader Mott Macdonald Limited 2x660 MW Coal Power Project Jamshoro.
Project: Site Remediation Package (LOT-II) – 2 x 660 MW Coal Fired
Power Project Jamshoro.
Subject: REF: No. SACHAL/JAM/JPCL/2017/0171, SUBMISSION
OF SEMIANNUAL ENVIRONMENTAL MONITORING REPORT FOR CONSTRUCTION OF CHANNEL FOR THE DISPOSAL OF COOLING TOWER BLOW DOWN (LOT-II).
Dear Sir, In pursuance of subject mentioned, we hereby submit semiannual environmental monitoring report for construction of channel for the disposal of Cooling Tower blow down (LOT-II). Yours truly, Kazim Ali Shah Project Manager Enclosed: as stated
Cc:
PIU/Project Director, Coal Fired Power Project @ Jamshoro
Local Team Leader Mott Macdonald Limited @ Site
Sachal Head Office
SEMIANNUAL ENVIRONMENTAL
MONITORING & MANAGEMENT REPORT
Project Name: Site Remediation Contract for LOT-II Construction of Channel for the Disposal of Cooling Tower Blow Down
Period: (July 2017 to December 2017)
Report prepared by: Atif Hussain _____________________
HSE Officer
TABLE OF CONTENTS
Sr. No. Particulars Page
1.0 Project Description
1.1 Project Description 1
1.2 Project Background 1
1.3 Scope of work 4
2.0 Environmental Monitoring Requirements & Parameters
2.1 Environmental Monitoring 5
2.2 Environmental Monitoring during Construction Phase 5
2.3 Project Environmental key personnel 6
3.0 Impact on Environmental Parameters during Construction Phase
3.1 Ambient air quality 6
3.2 Traffic safety 6
3.3 Noise Levels 6
3.4 Surface water and soil 10
3.5 Waste Water Management 10
3.6 Cultural Heritage Management 10
3.7 Impact of OHS at Project Site 10
4.0 Mitigation Measures
4.1 Air Quality 11
4.2 Water Quality 11
4.3 Noise Level 11
4.4 OHS at Project Site 11
5.0 Picture Gallery 12
Bi Annual Environmental Monitoring & Management Report
1
1.1 Project Description
The Jamshoro site is about 20 km northwest of Hyderabad, and about 150 km northeast of Karachi. The Indus River flows about 3.5 km east of the site. Highway N-55, also known as the Indus Highway, runs through the site and has immediate access to the national railway, allowing for the easy delivery of equipment, fuel and other materials. The Jamshoro site consists of four (4) existing fossil fired electricity generating units. Unit 1 (U1) is fired by heavy fuel oil (HFO) with an original nominal rating of 250MW. U1 was originally commissioned in 1990. Units 2 to 4 are dual fuel (oil and gas) fired with an original nominal rating of 210MW (each). Units 2 to 4 were commissioned in 1989, 1990 and 1991 respectively. The scope of work under Site Remediation Package Lot II, includes procurement, transportation, storage, construction, repair, installation, all detailed survey and geotechnical investigation, site levelling, and drainage.
1.2 Project Background
Plant effluents from existing plant including boiler blowdown, laboratory waste, plant washing waste water, and water drainage from cooling towers are led to the existing 4 effluent evaporation ponds. These evaporation ponds were filled with sludge, silt and clay along with wild bushes and vegetation growth.
Bi Annual Environmental Monitoring & Management Report
2
LOCATION OF THE PROJECT
Bi Annual Environmental Monitoring & Management Report
4
1.3 Scope of work
1.3.1 Performance of materials and services
The scope of work under Lot II, includes procurement, transportation,
storage, construction, repair, installation, all detailed survey and geotechnical investigation, site levelling, and drainage.
1.3.2 Construction of a cooling tower blow down channel
The broad scope of work under this contract shall include but is not limited to the following:
Detailed route elevations/survey for the entire discharge route (i.e.
from the existing water treatment plant to the terminal point on the bank of the Indus River)
Geotechnical investigations associated with the discharge route associated with the new reinforced concrete box culvert
Hydraulic analysis of closed and open channel design
Analysis of ground water table Civil design of channel
Construction of channel from power plant area to Indus river Construction of river embankment protection to avoid washout Construction of temporary diversion channels during construction of
permanent channel
1.3.3 Design and procurement of various equipment and systems
The Contractor shall carry out the basic and detailed design and engineering as applicable; finalize the parameters of all equipment and
systems. For those equipment and systems not falling under the Contractor's manufacturing range, the same shall be procured from
reputed sub-vendors. Contractor shall provide document to prove the capability of sub-vendor.
1.3.4 Transportation, receiving, handling and storage at site
The Contractor shall be responsible for proper transportation of all
materials, equipment and systems from the point of manufacture/procurement to the project site and its final location in the plant. It will be the Contractor's responsibility to develop the shipping
and transportation logistics. Similarly, it will be the Contractor's responsibility to coordinate with necessary departments such as
Imports, Customs, Port Authorities, Roadways, etc. Upon receipt of equipment and materials at site, the Contractor shall
make arrangements for proper receiving, handling and storage at site. Covered or indoor storage shall be provided by the Contractor, wherever
necessary. In case use of any hazardous material is envisaged, the Contractor shall make necessary arrangements duly complying with the
applicable laws or regulations or ordinance or statutes of the Government.
1.3.5 Construction, erection and testing
The Contractor shall follow standard procedures and instructions by the
Employer, if any, for carrying out proper construction, erection and
Bi Annual Environmental Monitoring & Management Report
5
testing of all the facility. For this purpose, it will be the Contractor's responsibility to ensure availability of construction machinery, cranes, rigging, scaffolding, tool for cutting, welding, erection, etc. as may be
required.
1.3.6 Commissioning, trial runs and performance guarantee tests
Any pump being provided under the work shall be commissioned and handed over to the client after trial run.
1.3.7 General requirements
The items specifically not mentioned in the specification but needed for
the smooth functioning of the equipment/system and plant requirement shall be deemed included in the scope of Contractor unless otherwise specifically mentioned under exclusions.
In addition to the scope and services mentioned above, the following general supplies and services shall be included in the scope of
Contractor.
1.3.8 Paints
The Contractor's scope of works includes supply of paints and painting of all equipment and structures as per the colour scheme to be approved by
Employer. The painting of various components shall comply with the requirement stipulated in different parts of this specification.
2.1 Environmental Monitoring Requirement & Parameters
The project is committed to monitor and manage its surrounding environment so
as to reduce the negative impacts which may arise from the project activities.
To control the adverse impacts on ambient air quality, traffic safety, noise levels,
Surface water and soil, waste management, cultural heritage management and
occupational health & safety of all personnel on site. The Sachal is regularly
monitoring and managing its construction site by implementing the approved
CEMP. The daily, weekly and monthly environmental inspection records are up to
date and have been checked by MML representatives. Precisely the following pre-
determined parameters as indicated below are being regularly monitored
subsequent management program has also taken under consideration for
successful completion of the project.
(a) Ambient air quality
(b) Traffic safety
(c) Noise Levels
(d) Surface water and soil
(e) Waste management
(f) Cultural heritage management
(g) Occupational Health and Safety
2.2 Environmental Monitoring during Construction Phase
According to Table 10-2 environmental monitoring in EIA report by ADB,
during the project activities the visual inspections were carried out on daily
Bi Annual Environmental Monitoring & Management Report
6
weekly and monthly basis to make sure that all above mentioned parameters
are on compliance with EIA and CEMP. The noise level data from the project
area is also collected quarterly. For surface water and soil analysis, the water
and soil samples were collected on different RDs by third party and results of
those tests were submitted to MML.
Monitoring and Management
Parameters (July 2017 - Dec 2017)
Ambient air quality Done with visual inspections
Traffic safety Implemented and monitored
Noise Levels Visual inspections and measurements
Surface water and soil Tests conducted & Submitted
Waste management Implemented & Monitored
Cultural heritage management Visual Inspections
Occupational Health and Safety Implemented and monitored
2.3 Project Environmental key personnel;
Sr. No. Project Key personnel Name of Key personnel Telephone No.
01 HSE Officer LOT-II. Atif Hussain 03332401024
3.0 Impact on Environmental Parameters during construction phase
3.1 Ambient Air Quality
During the construction activities vehicles are carrying employees and tools to the
site. Construction equipment, such as stone (aggregate) crushers is not being used
at the site which could create significant emission of particulate matters. Since
rehabilitation of evaporation ponds would most likely involve significant earth works,
increase in particulate matter in the air from wind-blown dust is also a concern,
especially considering the close proximity of the villages (Local stake holders) to the
project site. Ambient Air Quality was monitored by daily and weekly environmental
inspections at site.
3.2 Traffic Safety During project activities vehicle movement is a huge risk to environment as well as the personnel health on site for reducing the risk we put speed limit signs at different roads and drivers are instructed to follow the speed limits strictly. Furthermore, Environmental and health and safety inspections are carried out on regular basis to make sure that the controls are in place and complied properly. 3.3 Noise Levels During project activities, major source of noise is expected to be generated from
transport vehicles which include cranes excavator, trucks, LTVs etc. Regular
inspections of all equipment and vehicles are carried out to make sure the noise levels
are below 85 db.
7
Bi Annual Environmental Monitoring & Management Report
Table: 3.3.1. Noise Level Monitoring during 3rd Quarter from July to September 2017
Table: 3.3.2. Noise Level Monitoring during 4th Quarter from October to December 2017
Sampling locations GPS
Coordinates Date and Time
Average Noise Level in dB
01 LOT-II Camp Office E 25.474125 N 68.274368
20th October 2017 09:00 am to 05:00 pm
55.43
02 0+000 KM E 25.473410 N 68.274533
25th October 2017
09:00 am to 05:00 pm
54.68
To assess the noise generated by different activities and equipment to be used at
various stages of the construction work without proper measures the workers and
officers may face partial or permanent hearing loss. The graphical presentation of
noise is depicted in the following pages of report (Figure-1, 2, 3, 4)
Sampling locations GPS Coordinates Date and Time
Average Noise Level in dB
01 LOT-II Camp Office E 25.474072 N 68.274292
20th September 2017 09:00 am to 05:00 pm
56.85
02 0+000 KM E 25.473462 N 68.274699
25th September 2017
09:00 am to 05:00 pm
53.16
8
Bi Annual Environmental Monitoring & Management Report
Noise Level Monitoring during 3rd Quarter from July 2017 to September 2017
LOT-II Camp Office
Figure 1 0+000 KM
Figure 2
9
Bi Annual Environmental Monitoring & Management Report
Noise Level Monitoring during 4th Quarter from October 2017 to December 2017 LOT-II Camp Office
Figure 3
0+000 KM
Figure 4
10
Bi Annual Environmental Monitoring & Management Report
3.4 Surface water & soil
The surface water & soil sample were collected from Channel at different locations.
The samples were collected by third party for analysis and testing and water & soil
analysis report is submitted to MML.
3.5 Waste Management
The solid wastes of domestic nature generated mainly in the labor sheds are regularly
being collected in separate bins and being disposed through municipal cleaners
and being dumping in a designated municipal dumping place. In addition, a small
amount of solid kitchen waste is generated during day time which are also being
disposed in methodic way through municipal cleaner. The environmental and health
and safety inspections are carried out on regular basis to check the compliance.
3.6 Cultural Heritage management During project activities (excavation) and manual digging continual supervision is carried out throughout the project and environmental inspections are carried out regularly. Also chance find procedure is established and implemented as stated in CEMP. 3.7 Impact of OHS at project site Personal Protective Equipment (PPEs): During project activities, the workers may
face minor injuries due to accidental negligence. The regular provided services
are depicted in the following table-5.
Table-5: Monthly Occupational Health and Safety measure recorded at project site
“Construction of Channel for the Disposal of Cooling Tower Blow Down (LOT-II) project has achieved 1.525 million Cumulative safe man hours without lost time injury, project started from 1st February 2017”
Safety Statistics Jul-Aug Sep-Oct Nov-Dec
LTI 0 0 0
TRIR 0.04 0.01 0
Number of days without accident 62 61 61
Number of ill health cases 1 0 2
Overdue preventive open observations
17 16 08
11
Bi Annual Environmental Monitoring & Management Report
4.0 Mitigation measures
4.1 Air Quality
To reduce the generation of dust owing to movement of construction materials
including vehicles, regular water spray are being accomplished at construction
site. Movement of construction debris are being covered while hauled and
stored, roads properly cleaned and water sprayed in order to minimize dust
in air. To reduce generation of dust the stone crusher and batching plant have
not been allowed at construction site.
4.2 Water Quality
The camp is outside the project boundary and from that place possible
management has been ensured to avoid any contamination of any sort around
the project boundary. During the day time, small quantity of office waste is
generated (approximately 2kg) per day which is properly disposed-off through
designated municipal corporation locations.
4.3 Noise Level
Use equipment i.e., designed with noise-control provision;
Route truck traffic away from noise-sensitive areas, where feasible;
Unnecessary vehicle movement has been avoided at project site;
Switch off the engines while remain unused.
4.4 OHS at project site
Personal Safety Equipment (PSE): Use appropriate personal protection
equipment, such as safety boots, helmets, gloves, protective clothing, goggles
and ear protection to comply HSE obligation during construction phase.
12
Bi Annual Environmental Monitoring & Management Report
4.0 Pictures gallery
Site visit
Toolbox Talk
Toolbox Talk
13
Bi Annual Environmental Monitoring & Management Report
Vehicle Inspection
PPEs Compliance at Site
PPEs Compliance at Site
Mott MacDonald | Jamshoro Power Generation Project 18 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
C. Semi-annual Environmental Monitoring
Report; Construction of Municipal Solid
Waste Facility (Lot 3); July - December 2017
(MAJ-IIC)
Jamshoro Power Company Limited
Project Site Remediation Package (Lot-III)
2 X 660 MW Coal Fired Power Project Jamshoro
December, 2017
Semi-Annual Environmental Progress Report
1 2 5 4 8
D:\_Thar Coal\Reports to be formatted\Baseline Reports\HK --Draft Baseline Report for Flora and 05 October 2012
Semi-Annual Environmental
Progress Report
Project Site Remediation Package (Lot-III)
2 X 660 MW Coal Fired Power Project Jamshoro
From July to December 2017
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
i
Issue and revision record
Revision Date Originator Checker Approver Description
A Dec, 2017 Engr Muhammad Safar Korai
Engr. Khan Muhammad Rajar
Engr. Abdul
Jabbar
Major (R)
Muhammad Salim
Khan
Submission
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
2
1. INTRODUCTION 4
1.1. General Information About The Back Ground Of Project 4
1.2. Project Location 5
1.3. Employer (Client) 5
1.4. Engineer (Consultants) 5
1.5. Contractor 5
2. ACTIVITIES THAT HAVE BEEN UNDERTAKEN DURING THE REPORTING PERIOD 6
2.1. Awareness Program 6
2.2. Water Quality Analysis 21
2.2.1. Drinking Water Quality 21
3. COPIES OF ALL ENVIRONMENTAL MONITORING DATA AND CHECKLISTS 23
4. DETAIL OF ANY ENVIRONMENTAL INCIDENTS DURING THE REPORTING PERIOD 24
5. ANY OTHER DOCUMENTS AND RELEVANT DATA 25
6. CONCLUSIONS AND ACTION PLAN FOR THE NEXT PERIOD 25
6.1. Conclusions And Recommendations 25
6.2. Action Plan For The Next Period 25
Contents
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
3
Abbreviations
ADB Asian Development Bank
GOP Government of Pakistan
ICC Indus Construction Company
JPCL Jamshoro Power Company Limited
JTPS Jamshoro Thermal Power Station
MAJ Main Abdul Jabbar
MSW Municipal Solid Waste
WHO World Health Organization
PIC Project Implementation consultant
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
4
1. Introduction
1.1. General Information About the Back Ground of Project
The Government of Pakistan (GoP) is planning to set up a super-critical coal fired power plant at
Jamshoro (the ‘Jamshoro Power Generation Project’ or the ‘Project’) to be financed by the Asian
Development Bank (ADB). The power plant will be setup within the premises of the existing
Jamshoro Thermal Power Station (JTPS). The gross generation capacity of the Project will be 660
MW in the First Stage and 1,320 MW after expansion. The plant will be owned and operated by the
Jamshoro Power Company Limited (JPCL), the implementing agency of the Project.
The JTPS staff housing colony generates an estimated 750 1tons of solid waste annually. As there is
no proper disposal system, the waste is scattered around the colony. There is currently no solid
waste management system in place at the power plant either to manage waste generated in the plant
offices. The waste dumps can be seen in different location of the plant and the colony. There is no
municipal solid waste disposal facility available in the vicinity of the plant where the waste can be sent
for disposal. Aspects resulting from improper solid waste management are:
Contamination of surface and sub-surface soil by leaching from the dumps
Contamination of surface water in case of runoff
Transportation of contamination from leaching to the ground water aquifer
Possible attraction of scavengers to the solid waste dumps
Attraction of pests to the waste dumps resulting in spread of disease vectors
General nuisance and odor.
To overcome these issues, the mitigation measures are required which include:
Collection of waste on daily basis from the colony houses and office premises of the plant
Placement of bins in the key area with proper labelling for the type of waste to be thrown in the
bin and segregation of waste
Awareness campaigns on municipal waste management including segregation, reuse and
recycling
A properly designed landfill to cater for the plant needs will be developed.
1 Environmental Impact Assessment of Jamshoro Generation Project by Hagler Bailly Pakistan 2013
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
5
1.2. Project Location
The JTPS is located north of Jamshoro town in the Jamshoro district of Sindh province, Pakistan. The
power plant is about 10 kilometer (km) northwest of Hyderabad and about 150 km northeast of
Karachi. It is located on N-55, also known as Indus Highway. N-55 is one of the two main highways of
the country which connect Karachi, the main port and industrial hub of the country, with the rest of the
country.
1.3. Employer (Client)
Jamshoro Power Company Limited (JPCL), the implementing agency (IA) of the Project.
GENCO Holding Company Limited (GHCL), the parent company of JPCL will be the
executing agency (EA).
1.4. Engineer (Consultants)
Mott Macdonald Ltd in association with MM Pakistan Pvt Limited (The Project Implementation
Consultant)
1.5. Contractor
M/S MAJ-ICC (JV) Bungalow No.C-20, Qasimabad, Hyderabad, Sindh, Pakistan
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
6
2. Activities that Have Been Undertaken During The Reporting Period
Following activities have been performed from July to December 2017.
Awareness program
Water quality analysis
All these are discussed as under:
2.1. Awareness Program
Raising awareness about municipal solid waste management is a critical component of effective
waste management. It is important for key stakeholders to be aware of a city’s waste management
activities and have a strong understanding of the benefits of proper solid waste management.
Following are the main objectives of awareness program.
To motivate the local people to practice 3Rs (Reduce, Reuse and recycle)
To develop the sense of commitment among people to protect the environment
To imbibe among people the essence of environmental values and ethics and live in harmony
with nature a God’s gift.
Awareness program regarding proper management of MSW was initiated among the residents of the
colony. Followings figures show the awareness regarding benefits of proper management of MSW
and draw backs of improper management of MSW.
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
7
Figure 2.1. Awareness Programme-I (Auditorium Hall of JPCL, Jamshoro)
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
8
Figure 2.2. Awareness Programme-II (Door to Door)-Block-A/B of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
9
Figure 2.3. Awareness Programme-III (Door to Door)-Block-C of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
10
Figure 2.4. Awareness Programme-IV (Door to Door)-Block-D of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
11
Figure 2.5. Awareness Programme-V (Door to Door)-Block-E of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
12
Figure 2.6. Awareness Programme-IV (Door to Door)-Block-F of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
13
Figure 2.7. Awareness Programme-IIV (Market-1) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
14
Figure 2.8. Awareness Programme-IIIV (Market-2) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
15
Figure 2.9. Awareness Programme-IX (Masjid-1) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
16
Figure 2.10. Awareness Programme-X (Masjid-2) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
17
Figure 2.11. Awareness Programme-XI (Masjid-3) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
18
Figure 2.12. Awareness Programme-XII (Play Ground) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
19
Figure 2.13. Awareness Programme-XIII (WAPDA High School) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
20
Figure 2.14. Awareness Programme-XIV (Iqra High School) of TPS Colony, Jamshoro
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
21
2.2. Water Quality Analysis
Drinking and ground water quality were analysed as discussed below.
2.2.1. Drinking Water Quality
Water is one of the most essential elements to health and is so important that human body actually
has a specific drought management system in place to prevent dehydration and ensure survival.
Water might be everywhere, but one must never take it for granted. Water makes up more than two
thirds of human body weight, and without water, we would die in a few days. The human brain is
made up of 95% water, blood is 82% and lungs 90%. Water serves as a lubricant in digestion and
almost all other body processes. Our bodies can control over-heating through perspiration from sweat
glands in the skin and from evaporation which produces a cooling effect. Blood is also routed into
areas close to the surface of the skin where it can be cooled and then carried back to the interior of
the body. Conversing in a cold environment, the skin maintains proper body temperature by shunting
the blood away from the exterior surface thereby conserving heat within the body. The movement of
water within our cellular systems also transports vital blood plasma which is 92% made of water.
Blood plasma play a critical role in buffering the body’s pH, circulating antibodies from the immune
system, and regulating osmotic balance which all helps to maintain proper body temperature. In this
regard, drinking water quality was analysed in order to meet international as well as national standard
and World Health Organization (WHO) guidelines. Figure 2.15 shows the drinking water quality. At
site, clean and fresh water is provided to every worker. The result regarding water parameter are
within the WHO guidelines.
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
22
Figure 2.15. Drinking water quality
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
23
3. Copies of All Environmental Monitoring Data And Checklists
Figure 3.1 and 3.2 represent the copies of all environmental monitoring data and checklist
respectively.
Figure 3.1. Environmental Monitoring Data
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
24
(a)
(b)
(c)
(d)
Figure 3.2. Environmental Checklist
4. Detail of Any Environmental Incidents During The Reporting Period
Until no any environmental incident like spills, excessive emissions to atmosphere, water quality
contamination have been determined. Each and every thing is smoothly going on. At site pure
Project Site Remediation Package (Lot-III)
Semi-Annual Environmental Monitoring Report
25
drinking water is provided to all workers. At site, all workers are satisfied and environment friendly
atmosphere is provided. Only in October and November 2017, two minor case happened as given in
Annexure I and II.
5. Any Other Documents and Relevant Data
At this stage, there is no any other documents and data relevant to the environmental and social
management of the project.
6. Conclusions and Action Plan For The Next Period
6.1. Conclusions and Recommendations
During the reporting period, it has been concluded that project activities are environment smoothly
going. Until no any unpleasant event has been occurred. Awareness program has been finalized and
it was observed that residents of the colony are very much interested in proper waste management
system. Drinking water quality assessment show that water quality parameters were within the range
of WHO guidelines for water quality parameters.
6.2. Action Plan For The Next Period
Following activities would be performed during the next reporting period
Performance Assessment of Awareness programs
Instalment of dustbins
Collection of MSW
Transportation of MSW
Segregation of MSW at site
Drinking and ground water quality monitoring
Air quality monitoring
Noise pollution assessment during excavation work
Mott MacDonald | Jamshoro Power Generation Project 19 Bi-annual Environmental Monitoring Report July to December 2017
334014-MML-JPCL-R-00639 | January 2018 P:\Abu Dhabi\ARO\Environment\Projects\334014 - Jamshoro ESIAs\06 - Reports\01 - Semi-annual environmental monitoring reports\2017\July to December 2017\06 - Semi-annual environmental monitoring report July to December 2017
mottmac.com