ENVIRONMENTAL IMPACT ASSESSMENT - World Bank · 2015. 6. 14. · i tin nghia corporation industrial...
Transcript of ENVIRONMENTAL IMPACT ASSESSMENT - World Bank · 2015. 6. 14. · i tin nghia corporation industrial...
i
TIN NGHIA CORPORATION
INDUSTRIAL POLLUTION MANAGEMENT
IN THE DONG NAI, NHUE-DAY RIVER BASINS
ENVIRONMENTAL IMPACT ASSESSMENT
Of Project
"BUILDING CENTRAL WASTEWATER
TREATMENT PLANT WITH CAPACITY OF
3000 M3/DAY AT ONG KEO INDUSTRIAL
ZONE-PHASE 1 (MODULE 1)"
PROJECT’S OWNER CONSULTING AGENCY
DONG NAI, APRIL 2015
ii
TIN NGHIA CORPORATION
INDUSTRIAL POLLUTION MANAGEMENT
IN THE DONG NAI, NHUE-DAY RIVER BASIN
ENVIRONMENTAL IMPACT ASSESSMENT Of Project
"BUILDING CENTRAL WASTEWATER
TREATMENT PLANT WITH CAPACITY OF
3.000 M3/DAY AT ONG KEO INDUSTRIALZONE
PHASE 1 (MODULE 1)"
PROJECT’S OWNER CONSULTING AGENCY
DONG NAI, APRIL 2015
i
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................... i
LIST OF TABLES ........................................................................................................ iv
LIST OF FIGURES ...................................................................................................... vi
ABBREVIATION ....................................................................................................... vii
SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT REPORT ..... viii
INTRODUCTION ......................................................................................................... 1
CHAPTER 1 BRIEF DESCRIPTION OF THE PROJECT ................................... 13
1.1. PROJECT OWNER ............................................................................................ 13
1.2. PROJECT LOCATION ...................................................................................... 14
1.2.1. Ong Keo IZ Location................................................................................... 14
1.2.2. Location of Central Wastewater Treatment Plant at Ong Keo IZ ............... 14
1.2.3. CETP service area of Ong Keo IZ ............................................................... 15
1.3. BRIEF DESCRIPTION OF PROJECT ACTVITIES ........................................ 15
1.3.1. Objectives of construction of wastewater treatment plant at Ong Keo IZ .. 15
1.3.2. Requirement on input and output of waste water treatment plant ............... 16
1.3.3. Drainage and wastewater collection system ................................................ 20
1.3.4. Description of wastewater treatment technologies ...................................... 22
1.3.5. Sludge Treatment Technology .................................................................... 41
1.3.6. Transportation system ................................................................................. 41
1.3.7. System of hazardous wastes management at Ong Keo Industrial Zone ..... 44
1.3.8. Risk management in Ong Keo Industrial Zone ........................................... 45
1.4. TOTAL INVESTMENT BUDGET AND IMPLEMENTATION PLAN OF
COMPONENT NO 2 ................................................................................................ 48
1.4.1. Investment budgets ...................................................................................... 48
1.4.2. The Project Implementation Plan ................................................................ 48
CHAPTER 2 NATURAL, ENVIRONMENTAL AND SOCIO-ECONOMIC
CONDITIONS ............................................................................................................. 49
2.1. PHYSICAL CONDITIONS ............................................................................... 49
2.1.1. Geographical conditions .............................................................................. 49
2.1.2. Hydrological Conditions ............................................................................. 49
2.1.3. Climate ........................................................................................................ 50
2.1.4. Environmental State .................................................................................... 54
2.2. BIOLOGICAL CONDITIONS .......................................................................... 56
2.2.1. Mangroves ................................................................................................... 56
2.2.2. Phytoplankton and zooplankton .................................................................. 57
2.2.3. Benthos ........................................................................................................ 63
2.3. SOCIO-ECONOMIC CONDITIONS ................................................................ 65
2.3.1. The Economic Development ....................................................................... 65
2.3.2. The Social Development ............................................................................. 66
2.3.3. Sensitive areas affected by the Wastewater Treatment Project at Ong Keo
Industrial Zone ....................................................................................................... 68
CHAPTER 3 ANALYSIS OF ALTERNATIVES .................................................... 69
3.1. CRITERIA FOR SELECTION OF ALTERNATIVES ..................................... 69
3.2. SELECTION OF WASTEWATER DISCHARGE LOCATION ...................... 69
3.3. SELECTION OF WASTEWATER TREATMENT TECHNOLOGY ............. 70
3.3.1. The processing steps .................................................................................... 71
ii
3.3.2. Flow Diagram of wastewater treatment technology.................................... 71
3.3.3. Description of the technological process ..................................................... 72
3.3.4. Wastewater Treatment effect ....................................................................... 73
3.4. SELECTION OF SLUDGE TREATMENT TECHNOLOGY .......................... 77
3.4.1. Option 1: Treatment at Tai Tien Waste Treatment Plant ............................ 77
3.4.2. Option 2: Treatment at Sao Viet Waste Treatment Plant ............................ 79
CHAPTER 4 ENVIRONMENTAL IMPACT ASSESSMENT .............................. 82
4.1. IMPACT SOURCES, OBJECTS AND SCALE ................................................ 82
4.1.1. Construction Phase ...................................................................................... 82
4.1.2. Operation Phase ........................................................................................... 86
4.2. ENVIRONMENTAL IMPACT ASSESSMENT ............................................... 87
4.2.1. Construction Phase ...................................................................................... 87
4.2.2. Operation Phase ......................................................................................... 100
4.2.3. Risk and Accident Impacts ........................................................................ 111
4.2.4. Socio-economic impacts ............................................................................ 113
4.2.5. Cumulative impacts ................................................................................... 114
4.3. COMMENT ON THE RELIABILITY OF THE USED EIA METHODS ...... 117
CHAPTER 5 MITIGATION MEASURES OF THE NEGATIVE
ENVIROMENTAL IMPACT .................................................................................. 119
5.1. LAND CLEARANCE PHASE ........................................................................ 119
5.2. CONSTRUCTION PHASE .............................................................................. 119
5.2.1. Air pollution control .................................................................................. 119
5.2.2. Water pollution control.............................................................................. 121
5.2.3. Soil contamination control ........................................................................ 121
5.2.4. Traffic Control ........................................................................................... 121
5.2.5. Public Health and Socio- economic Development Protection .................. 122
5.2.6. Solid Waste Management .......................................................................... 122
5.2.7. Risk Mitigation .......................................................................................... 123
5.3. OPERATION PHASE ...................................................................................... 124
5.3.1. Air Pollution Control ................................................................................. 124
5.3.2. Water Pollution Control ............................................................................ 126
5.3.3. Soil contamination control ........................................................................ 129
5.3.4. Negative Environmental Impacts on Ecosystems and Socio-economic
Development ........................................................................................................ 130
5.3.5. Risk Impacts Control ................................................................................. 130
5.3.6. Risk Mitigation Measures in Operation Phase .......................................... 131
CHAPTER 6 ENVIRONMENTAL MANAGEMENT PLAN .............................. 134
6.1. MITIGATION OF NEGATIVE ENVIRONMENTAL IMPACTS ................. 134
6.1.1. Mitigation Measures Performance Plan .................................................... 134
6.1.2. Implementation plan for Safety, Health, Environment and Transport
program ................................................................................................................ 148
6.1.3. The community information and community relations ............................. 151
6.2. ORGANIZATION OF ENVIRONMENTAL MANAGEMENT AND
RESPONSIBILITY ................................................................................................. 151
6.2.1. Environment Department of Ong Keo IZ .................................................. 151
6.2.2. CWTP operation Team .............................................................................. 153
6.3. ENVIRONMENTAL MONITORING PROGRAM ........................................ 154
6.3.1. Environmental monitoring in construction phase ..................................... 154
iii
6.3.2. Environmental monitoring in operation phase .......................................... 156
6.3.3. Monitoring and Reporting Arrangements for ESMF ................................ 158
6.4. TRAINING PROGRAM .................................................................................. 159
6.5. COST ESTIMATION FOR ENVIRONMENTAL MANAGEMENT AND
MONITORING PROGRAM ................................................................................... 160
CHAPTER 7 PUBLIC CONSULTATION ............................................................. 162
7.1. GOALS OF PUBLIC CONSULTATION ....................................................... 162
7.1.1. Appraisal Agency ...................................................................................... 162
7.1.2. The Project Owner ..................................................................................... 162
7.1.3. Consulting Agency .................................................................................... 162
7.1.4. The People’s Committee and Fatherland Front Union .............................. 162
7.1.5. The Affected Public Communities ............................................................ 162
7.2. PUBLIC CONSULTATION ACTIVITIES ..................................................... 163
7.3. RESULTS OF PUBLIC CONSULTATION ................................................... 163
7.3.1. Results of Public Consultation .................................................................. 163
7.3.2. Opinions of Local Government ................................................................. 164
7.4. PUBLIC INFORMATION DISCLOSER ........................................................ 166
7.5. COMMITMENT OF THE PROJECT OWNER .............................................. 166
7.5.1. Undertaking Measures for Adverse Impacts Mitigation ........................... 166
7.5.2. Commitment for Implementation of Environmental Protection Measures
and Provisions ..................................................................................................... 167
iv
LIST OF TABLES
Table 1.1. The from coordinates location border of project area .................................. 14
Table 1.2. The enterprises having leased land in Ong Keo IZ ...................................... 16
Table 1.3. Pretreatment input and output requirements on the quality of wastewater .. 18
Table 1.4. Coefficient Kf regulated in QCVN 40:2011/BTNMT ................................. 19
Table 1.5. Waste water quality requirements after treatment........................................ 19
Table 1.6. The machinery and equipment of Ong Keo Industrial Zone WWTP .......... 30
Table 1.8. The traffic specification ................................................................................ 43
Table 1.9. Estimated total investment of the project ..................................................... 48
Table 2.1. Discharge average of Long Tau river ........................................................... 50
Table 2.2. Location of sampling air environmental status ............................................ 55
Table 2.3. Results of air quality analysis ....................................................................... 55
Table 2.4. Results of water quality analysis .................................................................. 56
Table 2.5. The location samples water quality .............................................................. 56
Table 2.6. Phytoplankton composition in the surface water sampling locations .......... 57
Table 2.7. Composition and distribution of phytoplankton density in the surface water
sampling locations ......................................................................................................... 59
Table 2.8. Composition and percentage distribution of phytoplankton in the surface
water sampling locations ............................................................................................... 59
Table 2.9. Zooplankton composition in the surface water sampling locations ............. 60
Table 2.10. Composition and distribution of zooplankton density in the surface water
sampling locations ......................................................................................................... 62
Table 2.11. Composition and distribution of zooplankton proportion in the surface
water sampling locations ............................................................................................... 63
Table 2.12. Results of benthos analysis......................................................................... 63
Table 2.13. Results of benthos composition and density analysis ................................ 64
Table 3.1. The location of the discharge of waste water treatment plants Ong Keo IZ 70
Table 3.2. Results of wastewater quality analysis in the wastewater treatment plant of
Nhon Trach 3 IZ (September 2014) .............................................................................. 75
Table 3.3. The % of mixing based on mass is as below ................................................ 78
Table 4.1. Sources of waste related environmental impacts in the preparation and
construction phases ........................................................................................................ 82
Table 4.2. Sources of none-waste related environmental impacts in the preparation and
construction phases ........................................................................................................ 83
Table 4.3. Affected Subjects and Scale in the Construction Phase ............................... 84
Table 4.4. Sources of waste related environmental impacts in the operation phase ..... 86
Table 4.5. Sources of none-waste related environmental impacts in the operation phase
....................................................................................................................................... 86
Table 4.6. Affected Subjects and Scale in the Operation Phase.................................... 87
Table 4.7. Air Pollution Loads and Concentration Caused by the Transportation of
Construction Materials .................................................................................................. 89
Table 4.8. Noice levels from machinery and equipment located in 8 m distance from
the construction area ...................................................................................................... 91
Table 4.9. Calculated results of noise level (dBA) during the construction phase ....... 92
Table 4.10. Calculated noise levels from construction activities .................................. 92
Table 4.11. Noise level of the motor vehicles ............................................................... 93
Table 4.12. Vibration level of a typical construction machinery .................................. 93
Table 4.13. The effects of air pollutants ........................................................................ 94
v
Table 4.14. Pollution factors for untreated domestic waste waters ............................... 95
Table 4.15. Estimated pollution loads generated from untreated waste water in the
construction phase ......................................................................................................... 95
Table 4.16. Concentrations of pollutants in waste waters ............................................. 96
Table 4.17. Pollution concentrations of waste waters arising from the process of
cleaning and maintenance of machinery and equipment in the construction phase...... 96
Table 4.18. Estimated concentrations of pollutants in stormwater runoff .................... 97
Table 4.19. Loss of construction materials .................................................................... 99
Table 4.20. Integrated environmental impact assessment in the construction phase .. 100
Table 4.21. Estimated loads and concentrations of exhaust air emission pollutants
generated from the transportation means .................................................................... 101
Table 4.22. Bacterial density in the air at the wastewater treatment plant .................. 102
Table 4.23. Impacts of methane on the environment and human health ..................... 103
Table 4.24. Impact of hydrogen sulfide on the environment and human health ......... 104
Table 4.25. Estimated pollution loads in untreated waste water in the project's
operation phase ............................................................................................................ 106
Table 4.26. Concentrations of pollutants in the waste water treatment plant ............. 106
Table 4.27. Summary of integrated environmental impacts in the operation phase ... 110
Table 4.28. Limit values of water pollutants in Long Tau river ................................. 115
Table 4.29. Maximum pollution load which can be received by water body. ............ 115
Table 4.30. Calculated results of pollutant loads, which are available in the receiving
water body ................................................................................................................... 116
Table 4.31. Calculated results of the pollution load from Ong Keo Industrial Zone
discharging into the Long Tau river ............................................................................ 116
Table 4.32. Carrying capacity of Long Tau river receiving the treated wastewater
discharging from Ong Keo Industrial Zone ................................................................ 117
Table 4.33. Summary of the reliability of the used EIA methods ............................... 117
Table 5.1. The inlet and outlet parameters of the central wastewater treatment plant
according to design ...................................................................................................... 126
Table 5.2. Treatment efficiency of IZ Ong Keo’s central wastewater treatment plant
..................................................................................................................................... 128
Table 6.1. The agencies involved in the environmental management program .......... 134
Table 6.2. Summary of the environmental management program of projects in the
construction phase ....................................................................................................... 138
Table 6.3. Summary of environmental management programs in the project operation
phase WWTP ............................................................................................................... 143
Table 6.4. Summary of counter measures to minimize environmental risks of the
project .......................................................................................................................... 146
Table 6.5. Implementation plan for Safety, Health, Environment and Transport
program in construction phase ..................................................................................... 148
Table 6.6. Program Implementation Plan safety, health, environment and
transportation in the operational phase ........................................................................ 149
Table 6.7. Mitigation, monitoring, responsibility and timeline................................... 158
Table 6.8. Total fund of annual environmental monitoring and management program
..................................................................................................................................... 160
vi
LIST OF FIGURES
Figure 1.1. Location map of Ong Keo Industrial Zone ................................................. 14
Figure 1.2. Location map of the wastewater treatment plant at Ong Keo Industrial
Zone ............................................................................................................................... 15
Figure 1.3. Diagram of wastewater collection to the IZ’s CETP .................................. 22
Figure 1.4. Diagram of wastewater treatment technology of Ong Keo Industrial Zone
....................................................................................................................................... 24
Figure 2.1. Monthly wind .............................................................................................. 54
Figure 3.1. The position wastewater receiving point from the wastewater treatment
plant of Ong Keo Industrial Zone .................................................................................. 69
Figure 3.2. Flow diagram of the wastewater treatment technology of Nhon Trach 3 IZ
....................................................................................................................................... 72
Figure 3.3. Exhibit sludge transport route ..................................................................... 78
Figure 3.4. Sludge solidifying process .......................................................................... 79
Figure 3.5. Exhibit sludge haulage route to Sao Viet Waste Treatment Plant at Toc
Tien Site ......................................................................................................................... 80
Figure 3.6. Process sludge treatment technology .......................................................... 81
Figure 4.1. The main wind direction affects CETP ..................................................... 103
Figure 6.1. Environmental Department Hierarchy of Ong Keo IZ ............................. 153
Figure 6.2. Organization Structure of CWTP operation Team ................................... 154
vii
ABBREVIATION
AMSWW : Automatic Monitoring Stations Of Water Quality
BOD : Biochemical Oxygen Demand
BTNMT : Ministry of Natural Resources and Environment
COD : Chemical Oxygen Demand
Co.Ltd. : Limited company
DO : Dissolved Oxygen
DONRE : Department of Natural Resource and Environment
EA : Executing Agency
EIA : Environmental Impact Assessment
EMP : Environmental Management Plan
ESMF : Environmental and Social Management Framework
EU : Europe
MONRE : Ministry of Natural Resource and Environment
NGO : Non-Government Organization
HW : Hazardous Waste
IZ : Industrial Zone
IZMB : Industrial Zone Management Board
ND : Not Detected
QCVN : National technical regulation
SS : Suspended solid
SPMG : State Programme Management Group
SW : Solid Waste
USA : The United States
WB : World Bank
WWTP : Wastewater Treatment Plant
WWTS : Wastewater Treatment System
viii
SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT REPORT
Project of Investment in construction and business of Ong Keo Industrial Zone
infrastructure in Dong Nai province was approved by the Prime Minister in Decision
No. 284/2006/QD-TTg on 21 December 2006, and the Tin Nghia Corporation was
assigned to the Investment of Ong Keo Industrial Zone by Decision approving the
detailed planning of construction No.2557/QD-UBND dated 10th August, 2007 and
the third adjustment dated 20th January, 2014 by Decision No. 191/QĐ-UBND.
Currently, in order to comply with the law and help protect the environment in and
around the area of Ong Keo Industrial Zone, Tin Nghia Corporation has planned to
invest in the construction of a wastewater treatment plant for Ong Keo Industrial Zone
- phase 1, Module 1, with a capacity of 3,000 m3/day, to meet the need for thorough
handling of wastewater generated from manufacturing activities and business in Ong
Keo Industrial Zone - phase 1, and to meet QCVN 40:2011/BTNMT column B before
discharge into the environment.
I. DESCRIPTION ABOUT WASTEWATER TREATMENT TECHNOLOGY,
WASTEWATER INPUT AND OUTPUT STANDARD OF ONG KEO IZ
WASTEWATER TREATMENT PLANT
1.1. Description about wastewater treatment technology
Process of wastewater treatment for Ong Keo Industrial Park includes 4 phases as
indicated in Figure 0.1.
(1). Mechanical treatment (pit pumps, oil separation tank, and an air conditioning)
Wastewaters from the factories in the industrial zone will be collected to the pump pit
of the wastewater treatment plant. Wastewaters are separated by automatic garbage
separation equipment to remove the garbage, twigs etc. with size >10 mm, then
separated by garbage filters to eliminate garbage with size > 5 mm. Then the
wastewater is pumped to the conditioning tank, which is designed with sufficient
retention time of > 8 hours to balance the volume and concentration.
(2). Chemical handling (flocculation tank, flocculation and primary sedimentation
tanks)
In the flocculation tank, flocculants will be mixed with wastewaters. Flocculation help
to destabilize the sediment particles and stimulate them link with other suspended
sediments to form the larger size particles, where the chemical (polymer) stimulates
the larger size particles. Polymer effect forms a "bridge" to link the small size particles
to form the bigger size particles to improve the efficiency of primary sedimentation
tanks.
Preliminary sedimentation tank is specially designed to make the particles to settle
down. According to the design, sludge will be collected to sludge hole and periodically
ix
pumped to sludge tank. Then wastewater will flow into the next tank to perform
biological treatment process (See Figure 0.1).
Alumin
sink
Axit sinks
Input Flow
Pump
Pump
Pump pit
Conditioning tanks
Coagulation –
Flocculation tank
Pump
Pump
Polymer
Sinks
Output flow
Pump
Pumb
Disinfecti
on sink
Polymer sinks
Dry mud
Aerotank
Primary
sedsedimentation
tank sedimentation
tank sedimentation
tank sedimentation
tank sedimentation
tank sedimention
tank LÝ
Secondary
sedimentation tank
Disinfection tank
Alkaline
Sinks
Slugde tank
Slugde presses
Pump
Pump
Pump
Pump
M
Oil separation tank
Ecological pond
Pump
Pump
Balancing tank
Pump
M
Nutrient
Sinks
Figure 0.1. Diagram of wastewater treatment technology of Ong Keo Industrial Zone
x
(3). Biological treatment methods (Balancing tank + Aerotank tank secondary
sedimentation and disinfection)
After treating at the oil separation tank and primary sedimentation tanks, wastewater
will be treated by biological methods. Then, the wastewater after primary
sedimentation tanks will flow into the balancing tank and will be led through an
Aerotank tank. The wastewater discharged from aerobic biological tank will flow
through the secondary sedimentation tank to remove and dewater sludge. Then the
wastewater will pass through the disinfection tank to kill bacteria to ensure meeting
the effluent regulation.
(4). Biological pond
The pond is designed to store the treated wastewater and to make landscaping, to
rescue incidents as needed.
1.2. Wastewater inputs and outputs standards
The wastewater from enterprises inside the industrial zone is treated to connection
standards of wastewater treatment station Ong Keo Industrial Zone will be discharged
into collection system common of Ong Keo IZ and flow into wastewater treatment
position of Ong Keo IZ.
Treated wastewater will meet the National Technical Regulation QCVN
40:2011/BTNMT, column B with Kq = 0.9, Kf = 0.9.
II. THE IMPACTS ON THE NATURAL ENVIRONMENT, SOCIO-
ECONOMIC CONDITIONS AND MITIGATION MEASURES
The main impacts of the project on the natural environment, socio-economic
development and mitigation measures are summarized in the following table:
Activity Impacts Mitigation Measures of Negative Environmental
Impacts
1. Construction Phase
1.1. Transport -
action of
materials,
equipment and
machinery
1.1.1. Dust
- To use tarpaulin for covering the truck, which
transport building materials while moving on
roads;
- - To provide protective equipment for workers.
1.1.2. Air
emissions
(CO, SOx,
NOx,
THC…)
To select the construction material’s sources near the
project area;
To regularly inspect and maintain machinery and
equipment.
1.1.3. Noise,
traffic jams To arrange the reasonable unloading/loading time.
1.2. Gathering,
storage and 1.2.1. Dust
To cover material storage areas, especially areas
containing cement, sand, stone.
xi
Activity Impacts Mitigation Measures of Negative Environmental
Impacts
preservation of
materials
1.3. Domestic
activities of
worker on the
construction
Site
1.3.1.
Domestic
wastewater
- To put the collective trash and classification;
- To contract with functional units for collection and
treating;
- To use the portable toilets in the construction
areas.
1.3.2.
domestic
solid waste
1.4.
Stormwater
runoff
To arrange the temporary drainage during construction phase and to
regularly clean the construction site every working day.
1.5.
Environmental
incidents in the
construction
phase
1.5.1. Work
accidents
- To establish the safety team at construction sites;
- To issue the safety rules for workers;
- To train the safety rules for construction workers.
1.5.2.
Explosion
incident
- To apply the standards of fire safety when
designing temporary works;
- To develop and promulgate the safety rules for fire
prevention, fire fighting installation of signboards;
- To equip with fire fighting facilities;
- To organize the inspection and supervision.
2. Operation Phase
2.1.
Transportation
means
2.1.1. Air
emissions,
dust, noise
- To make the concrete roads and yard ;
- To control the quality of vehicles, to regularly
maintain the transportation means ;
- To control the speed of vehicles ;
- To plant more trees in the project area.
2.2. Operation
of wastewater
treatment plant
2.2.1. Air
emissions
- To deodorize the wastewater treatment plant
- To transport the sludge and materials to the solid
waste disposal area on appropriate time and to use
special vehicles to avoid odors , dust;
- To plant the green trees around the wastewater
treatment plant
2.2.2. Noise,
vibrations
To regularly inspect and maintain machinery,
equipment.
2.2.3.
Industrial
solid wastes
- To collect the solid waste of industrial zones and
hire the functional units to dispose ;
- To collect sludge and store in the planned place
and sign a contract with the functional units for
disposal
2.3. Activities
of officers and
employees
2.3.1.
Domestic
solid waste
- To put the garbage collectors and to classify the
domestic solid waste of IZ;
- To contract with the functional units for disposal.
- To use septic tanks and connect to the wastewater 2.3.2.
xii
Activity Impacts Mitigation Measures of Negative Environmental
Impacts
Domestic
waste water
treatment plant of IZ.
2.4. Cleaning
and
maintenance of
machinery
2.4.1.
Hazardous
waste, grease
rags
To collect the hazardous waste of IZ and to sign
contracts with the functional units for disposal.
2.5.
Stormwater
runoff
To construct the drainage system and to regularly clean the manholes
and culverts.
2.5.
Environmental
incidents
during
operation phase
2.5.1. The
fires,
explosions,
electrical
incidents
- To train workers on fire fighting, explosion and
electrical safety ;
- To establish the fire fighting team.
- To regularly exercise the fire fighting.
2.5.2. Work
accidents and
occupational
health
- To provide the adequate facilities to ensure the
labor safety;
- To train workers on labor safety and labor safety
instructions before getting work;
- To establish the safety rules for each stage of
production;
- To organize periodical medical examination for
employees.
2.5.3. Risk
related to fuel
leakage
- To strictly follow the regulations during transport,
storage and use;
- To fully equip for vehicles the incident’s response
device;
- To train employees how to rescue when the
incident occurred.
2.5.4.
Interuption of
wastewater
treatment
operation
- The Team Leader must assign personnel to
correctly follow the maintenance schedule;
- The operators must prepare instruments for such
repair;
- The Team Leader shall make the list of
organizations to readily maintain or repair the
system.
- Any operator/or anyone in the treatment plant
discovers any problem
- If the Company’s technicians are unable to restore
the incident, the Chief is entitled to instruct and
contact to the repair and warranty organizations. It
is no more than 6 hours since the system is
defected.
xiii
III. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
III.1. The objective of Public Consultation
The investor had to consult the following objects:
- The surrounding local people who are impacted by the Project in construction
and operation process.
- During the EIA of the overall project Ong Keo IZ (including the build the
CETP - Phase 1 Ong Keo IZ with a capacity of 3,000 m3/day item), the project
owner and consulting agency has consulted the People Committee, Fatherland
Front Union and public communities of Phuoc Khanh commune. Therefore,
when the component build the CETP - Phase 1 of Ong Keo IZ with a capacity
of 3,000 m3/day, the investor has not conducted consultations the People
Committee and Fatherland Front Union again
III.2. Results of Public Consultation
Project Owner – Hoa Mac IZMB has done in consultation with 28 surrounding
local people who are impacted by the Project in construction and operation process.
Comments of the surrounding inhabitants are as follows:Most of them agree (26/28)
with the construction of “CETP Project with capacity of 3.000 m3/day at Ong Keo IZ,
phase 1, module 1”. The others (2/28) have no comment.
III.3. Information Disclosure
The “EMP” of the “Construction CETP Project with capacity of 3000 m3/day at Ong
Keo IZ, Phase I, module 1” will be disclosed in the Headquarter of the People’s
Committee of Phuoc Khanh Commune for public awareness, check and inspection
before and during the construction worksmay commence. In addition, the EMP will be
disclosed in English on the website of Vietnam Environment Protection Fund
(VEPF), Infoshop in Washington DC and at Vietnam Development Information Center
(VDIC).
1
INTRODUCTION
1. PROJECT ORIGIN
1.1. General introduction to the sub-project of industrial pollution management
in the Dong Nai, Nhue - Day river basins
In order to effectively implement the control of industrial pollution at the source and to
strengthen the institutional capacity in the implementation of policy measures for
environmental protection, The Government of Vietnam has approved the project
"Industrial Pollution Management in the Dong Nai, Nhue - Day river basins”
(hereinafter referred to as VIPM Project) by World Bank funding.
The project development objective is to improve the performance and compliance with
prescribed industrial wastewater treatment projects in 04 provinces (Ha Nam, Nam
Dinh, Dong Nai and Ba Ria-Vung Tau). This objective will be achieved by
strengthening the institutional environment and enforcing environmental regulations,
surveillance improvement, financial assistance based on preferential loans to increase
wastewater treatment capacity and to enhance compliance with regulations on
environmental protection, to publicize and monitor information and promote
community involvement in Ha Nam and Nam Dinh Provinces located in the Nhue -
Day river basin, and in Dong Nai and Ba Ria - Vung Tau provinces located in the
Dong Nai river basin - the two most polluted river basins in Vietnam.
The criteria for assessing the industrial pollution management include: (a) the
percentage of IPs complying on implementation of wastewater monitoring, (b) the
level of publicization of pollution information; (c) the ratio of the resolved community
complaints, (d) the percentage of fines collected because of non-compliance, and (e)
the ratio of industrial zones complying on wastewater treatment. Accordingly there
will be about 10 industrial zones in four provinces such as Ha Nam, Nam Dinh, Dong
Nai and Ba Ria - Vung Tau to meet the criteria of the project loans for the construction
of the central wastewater treatment plants and expand the existing wastewater
treatment plant to achieve the national environmental standard. Among those, there are
5 IZs in Dong Nai Province to meet the criteria.
The VIPM project will consist of 03 components as follows:
- Component No1: Strengthening institutional capacity and enforcement;
- Component No2: Pilot investment loan to build the central wastewater
treatment plants in the IZs (will be presented in Section 1.5);
- Component No3: Technical support for IZs and support the project
implementation.
With the objective of strengthening the implementation and monitoring of the
environment, component No1 will have sub-component No1b - the construction of
2
automatic monitoring stations of water quality (AMSWW). In this sub-project, there
are 17 AMSWW proposed (Table 1.1). Each monitoring station requires land area of
50 to 100 m2. Most of this area is owned by the state, so, the relocation and
compensation will be minimized. In some cases, if area permits, sub-component of
AMSWW should have a small lab or security house. Two AMSWW types will be
supported: basic type and extended type. The basic AMSWW will monitor 5 water
quality parameters (i.e. pH/Redox, conductivity, temperature and turbidity). The
extended station will include additional parameters COD/nitrate, NH4+ and total
phosphorus. The information related to monitoring stations in Dong Nai province will
be presented in Figure 2.
Figure 0.2. Locations of industrial zones proposed for loans and the water quality
automatic monitoring stations in the Dong Nai River Basin
3
Component 3 will provide a range of technical assistance to support (a) The IZ
management unit implemented environmental management responsibilities in an
effective manner (b) design more suitable for the work of CETPs, (c) accuracy self-
monitoring and timely reporting of activities of the industry. In addition, this
component will support (d) The activities of project management (including
monitoring and evaluation), (e) research related to project implementation, and (f) the
management awareness operation.
1.2. Summary and description of the component No 2 – Central wastewater
treatment plant
Vietnam Environmental Protection Fund (VEPF) is a unit assigned to perform
component No2 - "Pilot investment loan to build the central wastewater treatment
plant in the industrial zones" of VIPM project with a capital budget of 20.473 million
USD.
This component will focus on the infrastructure of industrial pollution management by
providing loans with preferential interest rates for the construction of 10 wastewater
treatment plants.
Currently, the wastewater treatment plants in Dong Nai province proposed for loans
are presented in Table 0.1.
Table 0.1. Central Wastewater Treatment Plants proposed for loans from the VIPM
project
No. Industrial
Zone Investor
Capacity
(m3/day)
The total
investmen
t (billion
VND)
The loans
(billion
VND)
1 Giang Dien 2
The Industrial Zones
Development Company
9,000 71.0 53.525
2 Nhon Trach 6 Tin Nghia Corporation 7,500 58.7 44.209
3 Nhon Trach 3
- module 2
Tin Nghia Corporation 2,000 22.6 16.943
4 An Phuoc Tin Nghia Corporation 2,000 23.88 23.88
5 Ong Keo Tin Nghia Corporation 3,000 29.2 21.9
Source: Environmental Management Framework and Society "project management of
industrial pollution in the Dong Nai river, Nhue - Day river basin"
Note: NA – under approval process
1.2. GENERAL INTRODUCTION ABOUT ONG KEO INDUSTRIAL ZONE
The Planning for Ong Keo IZ in Phuoc Khanh commune, Nhon Trach district, Dong
Nai province was approved by the Prime Minister in the Decision No. 1107/QĐ-Tg,
and the Tin Nghia Corporation was assigned to the investment in Ong Keo IZ by
4
Decision approving the construction of detailed Planning Ong Keo Industrial Zone No.
2557/QĐ-UBND dated 10th August, 2007 and the adjusted third time by Decision No.
191/QĐ-UBND on 20 January, 2014 about detailed contruction planning. The
Ministry of Natural Resources and Environment has approved the environmental
impact assessment report of Ong Keo Industrial Zone by Decision No. 1294/QD-
BTNMT 29 August 2007 with the investment industries as follows:
- Shipping newly, ship repair and related services (excluding cleaning services
ship);
- Production and processing lubricants, gas, liquefied petroleum gas, petroleum-
based products;
- Metallurgy, chemical (not including basic chemicals), fertilizer, cement;
- Production electricity, postal and telecommunications, construction,
mechanical;
- The production of paper and products of paper (excluding producing pulp from
bamboo, cork, wood);
- The production of plastic products, plastic polymer, natural rubber, synthetic
rubber (not including processing of latex);
- Production raw - materials in the construction sector, civil and industrial;
handicraft products, ceramics, glass; timber, forest products;
- The type of light industry: Textiles (not including dyeing fabric with capacity of
over 10 million m/year), garments, silk, yarn, shoes, leather (no leather stage
before wet blue) seafood processing, agricultural, industrial forms of production
and consumption of goods exported. Food industry, pharmaceuticals, materials,
aromatherapy, cosmetics, beverage, wine, beer;
- The type of mechanical manufacturing, mechanical machining, mechanical
assembly;
- The service sector: bank; post office; office; hotels; eating; sports;
entertainment; public sanitation services, waste disposal; warehouse for rent;
- And the type of industry few influence other ecological environment is not
prohibited.
According to the Decision No. 35/1999/QD-TTg on 05 March, 1999 issued by he
Prime Minister on approving the orientations for urban drainage development of
Vietnam by the year of 2020, industrial zones, export processing zones have to locally
treat industrial wastewater and apply modern technologies for construction of drainage
and wastewater treatment plants to meet the environmental technical regulations
before discharging into receiving waters. The water demand when the IZ fully
occupied is 3,750 m3/day, wastewater flows down the central wastewater treatment
plant is 3,000 m3/day (approximately 80% of the supplied water volume).
5
Currently, Ong Keo Industrial Zone is compensating and deploying procedures for the
construction of infrastructure that promoting the investment in the industrial zone. Tin
Nghia Corporation has a plan to build a central wastewater treatment plant (WWTP) in
Ong Keo industrial zone with a capacity of 3,000 m3/day. The capacity is perfectly
suited to meet the wastewater treatment requirement when businesses started to invest
in industrial zone to ensure all wastewater generated in the industrial zone to meet the
environment regulations before discharging into the Long Tau river.
1.3. ENVIRONMENTAL LEGISLATION AND GUIDELINES
1.3.1. World Bank Policy on Environmental Assessment
The environmental impact assessment study for the wastewater treatment plant’s
project in Ong Keo industrial zone is designed to evaluate its status with respect to all
applicable World Bank safeguard policies and guidelines. The environmental
screening of the subproject has also resulted in categorizing the subproject as a
Category B subproject due to its moderate impacts associated with the construction
and operation of the CETP. In addition, the Bank’s requirements on public
consultation and information disclosure will need to be followed. This subproject
triggers the World Bank policies on Environmental Assessment (OP 4.04) and policy
on Involuntary Resettlement (OP 4.12).
The criteria applied by the EIA include those of the World Bank Group Guidelines on
Environment, Health and Safety (EHS Guidelines): environment, including emissions
and ambient air quality, water quality and waste water environment surrounding noise
management.
Documents related to Component No 2 of the project of industrial pollution
management in the Dong Nai, Nhue Day river basins are as follows:
- Decision No.1932/QD-BTNMT on 12 November 2012 on approving
component No2 - Pilot investment loan to build the central wastewater
treatment plants in industrial zones of the project "Industrial Pollution
Management in the Dong Nai, Nhue-Day river basins";
- Decision No.1953/QDBTNMT on 14 November 2012 on establishment of the
Project Management Board of Component No2 - Pilot investment loan to build
the central wastewater treatment plants in the industrial zones of the project
"Industrial Pollution Management of Dong Nai, Nhue-Day river basins";
- Decision No.1196/QDBKHDT on 17 September 2012 of the Minister of
Planning and Investment on approving the feasibility study report on the project
“Industrial Pollution Management of the Dong Nai, Nhue-Day river basins”;
- Decision No.1403/QDBKHDT on 25 October 2012 on amending and
supplementing a number of articles of Decision No. 1196/QDBKHDT;
6
- Decision No.1205/QDBKHDT on 19 September 2012 on establishment of the
Project Steering Committee for the project “Industrial Pollution Management in
the Dong Nai, Nhue-Day river basins”
- Official Letter No. 13606/BTCQLN on 5 October 2012 on specific lending
conditions for the WB Project “Industrial Pollution Management”.
- Loan Agreement (VIPM Project) between the Socialist Republic of Vietnam
and the International Development Association on 24 September 2012 (No.
5175VN).
- Environment and Social Management Framework, The project “Industrial
Pollution Management in the Dong Nai, Nhue-Day river basins, 2012.
1.3.2. Vietnamese Policy on Environmental Assessment
(1).National Environmental Legislation
- Fire Prevention and Fire Code issued by the National Assembly of the Socialist
Republic of Vietnam on 29 June 2001;
- Construction Law issued by the National Assembly of the Socialist Republic of
Vietnam on 26 November 2003;
- Investment Law issued by the National Assembly of the Socialist Republic of
Vietnam on 29 November 2005;
- Law on Environmental Protection issued by the National Assembly of Vietnam
on 29 November 2005, revised 2014;
- Law on Chemicals issued by the National Assembly of the Socialist Republic of
Vietnam on 21 November 2007;
- Law on Biodiversity issued by National Assembly of the Socialist Republic of
Vietnam on 13 November 2008;
- Urban Planning Act issued by the National Assembly of the Socialist Republic
of Vietnam on June 17, 2009;
- Law on Water Resources issued by the National Assembly of Socialist
Republic of Vietnam on June 21, 2012.
- Decree No.59/2007/NDTTg dated 09 April 2007 issued by the Prime Minister
on the solid waste management.
- Decree No.29/2008/NDCP dated 14 March 2008 issued by the Government on
industrial zones, export processing zones and economic zones;
- Decree No.29/2011/NDCP dated 18 April 2011 issued by the Government on
strategic environmental assessment, environmental impact assessment, and
environmental protection commitments;
7
- Decision No.53/2004/QDTTg dated 08 April 2004 issued by the Prime Minister
promulgating the strategic orientation for sustainable development in Vietnam
(Agenda 21);
- Decision No.81/2006/QDTTg dated 14 April 2006 issued by the Prime Minister
on approving the "National Strategy of environmental protection until 2010
with a vision to 2020 (NSEP)";
- Decision No.851/QDBXD dated 28 May 2004 issued by Ministry of
Construction on the approval of the detailed plan of Ong Keo Industrial Zone,
Nhon Trach District, Dong Nai Province;
- Decision No. 27/2004/QDBXD on 09 November 2004 issued by the Ministry of
Construction on approval TCXDVN 320 2004 "Hazardous waste landfill -
Design Standards";
- Decision No.21/2005/QDBXD dated 22 July 2005 issued by Ministry of
Construction on promulgating regulations on the notation system drawings in
the construction plans.
- Circular No.19/2008/TTBXD dated 20 November 2008 issued by the Ministry
of Construction on "guiding the formulation, appraisal, approval and
management of construction plan of the industrial zones and economic zones."
- Circular No.08/2009/TTBTNMT dated 15 July 2009 issued by the Ministry of
Natural Resources and Environment on environmental protection regulations of
economic zones, high-tech parks, the industrial zones and industrial clusters ;
- Circular No.01/2011/TTBXD dated 27 January 2011 issued by the Ministry of
Construction guiding the strategic environmental assessment;
- Circular No.26/2011/TTBTNMT dated 18 July 2011 issued by the Ministry of
Natural Resources and Environment on detailing a number of articles of Decree
No. 29/2011/NDCP of the Government on the strategic environmental
assessment, environmental impact assessment, environmental protection
commitment.
- Circular No.04/2011/TTBTNMT dated 28 December 2011 issued by the
Ministry of Natural Resources and Environment on amending and
supplementing some articles of - Official Letter No.935/CPCN dated 14 July
2003 issued by the Government on the project of Ong Keo Industrial Zone,
Dong Nai province.
(2).Local Environmental Legislations
- Decision No.243/QD.UBT dated 17 January 1998 issued by the People's
Committee of Dong Nai Province on approval of general plan with scale of
8
1/5000 of Ong Keo Industrial Zone in Phuoc Khanh commune, Nhon Trach
District, Dong Nai province;
- Decision No.2557/QD-UBND on 10 August 2007 issued by the People's
Committee of Dong Nai Province on approval of detailed plan with scale of
1/2000 of Ong Keo Industrial Zone in Phuoc Khanh commune, Nhon Trach
District, Dong Nai province;
- Decision No.1226/QD.CT.UBT dated 20 April 2004 issued by the People's
Committee of Dong Nai Province on approval and recommend locations for Tin
Nghia Company established project planning and infrastructure investment Ong
Keo Industrial Zone in Phuoc Khanh Commune, Nhon Trach District; adjusted
area according documents 7150/CV-UBT 7 December 2004 of the People's
Committee of Dong Nai Province; extended in accordance with Document No.
3443/UBND on 14 May 2007 of the People's Committee of Dong Nai Province;
- Decision No. 1294/QD-BTNMT dated 29 August 2007 issued by the Ministry
of Natural Resources and Environment on approval of the environmental
impact assessment report of Ong Keo Industrial zone.
- Certificate No 1658/SKHCN-QLC dated 15 Octorber 2010 issued by
Department of Science and Technology Department of Dong Nai Province on
evaluation of the waste water treatment technology of Ong Keo Industrial Park
- Certificate of business registration and tax registration of Tin Nghia
Corporation with enterprise code of 3600283394 on 03 November 2004,
registration change time 15 on 28 August 2014).
1.3.3. The environmental standards and regulaions
(1).Water Quality
- QCVN 08:2008/BTNMT - National technical regulation on surface water
quality;
- QCVN 09:2008/BTNMT- National technical regulations on groundwater
quality;
- QCVN 14:2008/BTNMT - National technical regulation on domestic
wastewater quality;
- QCVN 40:2011/BTNMT- National technical regulations on industrial waste
water;
(2). Air Quality
- QCVN 05:2013/BTNMT - Air Quality - National technical regulations on
ambient air quality ;
9
- QCVN 06:2009/BTNMT - Air quality - Allowable maximum concentration of
toxic substances in the ambient air.
(2).Soil Quality
QCVN 03:2008/BTNMT - National technical regulation on the permissible limits of
heavy metals in the soil;
(3).Solid Waste Management
- TCVN 6696:2009 - Solid waste – Sanitary Landfill- General requirements for
the protection of the environment;
- QCVN 07:2009/BTNMT - The national regulation on classification of
hazardous waste;
- QCVN 25:2009/BTNMT - National technical regulation on wastewater leakage
from solid waste landfills;
(4).Noise and vibration
- QCVN 26:2010/BTNMT - National technical regulation on noise;
- QCVN 27:2010/BTNMT - National technical regulation on vibration.
(5).Safety and Occupational Health
Decision No 3733/2002/QD-BYT on 10 October 2002 about applications of 21
standards for safety and health.
1.4. ENVIRONMENTAL IMPACT ASSESSMENT METHODS
The methods are applied in the EIA process including:
(1). Statistical Methods:
Collecting and processing data on meteorological, hydrological conditions, socio-
economic development in the project area.
(2).Survey methods, field sampling and laboratory analysis
Field surveys in the project area, including:
- Topographic survey, engineering geology, hydrogeology;
- Hydro-meteorological Survey;
- Survey of production activities of the enterprises in the industrial zone.
10
Collecting documents on technical infrastructure in the project area, including:
- Survey of the current status of water supply network;
- Survey of the current status of power supply network;
- Survey of the current status of drainage network;
- Survey of the current status of waste water drainage network ;
- Survey of the current status of roads network;
- Survey of the environment status;
- Survey of ambient air quality;
- Survey of groundwater quality;
- Survey of the surface water quality;
- Survey of soil quality;
- Survey of biological resources.
(3).Comparison method
Assessing the impact on the basis of comparison of the analyzed results with the
Vietnam environmental standards/ regulations.
(4).Checklist and matrix method
The method used to establish the relationship between the activities of the project and
the environmental impact.
(5).Rapid assessment method
Estimating the pollution load and concentration of pollutants from project’s activities
in construction and operation phases of the WWTP under the WHO’s pollution
factors.
(6).Public consultation method
The method is used in the interview of leaders and local residents in the project area.
1.5. IMPLEMENTATION ORGANIZATION
Tin Nghia Corporation is the agency responsible for implementation of this EIA report
in consultation with the Environmental Technology Centre (ENTEC).
(1).Responsible agency:
TIN NGHIA CORPORATION
- Address: 96 Ha Huy Giap, Quyet Thang Ward, Bien Hoa City, Dong Nai
Province.
11
- Tel: 061.3824369 - 3822486 Fax: 061.3823747
- Representative: Quach Van Duc
- Position: General Director
(2).Consulting agency
ENVIRONMENTAL TECHNOLOGY CENTRE (ENTEC).
- Address: 463 Phan Van Tri, Ward 5, Go Vap Dist., Ho Chi Minh City.
- Tel: 08. 39850540 Fax: 08. 39850541.
- Representative: Ass. Prof. Phung Chi Sy.
- Position: Acting Director.
Members directly involved in the EIA report preparation include:
Table 2. Members directly involved in the EIA report preparation
No Full name Position/expertise Organization
01
Nguyen Duc Thang Deputy director the
management board of
IZS Tin Nghia
Tin Nghia Corporation
02 Nguyen Do Hoang Thao Staff enviromental Tin Nghia Corporation
03 Phung Chi Sy
Ass.Prof.Dr. of
Environmental Science
and Technology.
ENTEC
04 Vu Thanh Nam
Master of
Environmental
Science.
ENTEC
05 Pham Mai Duy Thong
Master of
Environmental
Science.
ENTEC
06 Vo Nhat Tan Bachelor of
Environmental Science
ENTEC
07 Dang Thi Thom Bachelor of
Environmental Science
ENTEC
08 Hoang Nhat Truong Bachelor of
Environmental Science
ENTEC
09 Le Van Nhat Bachelor of
Environmental Science
ENTEC
10 Luu Duc Trung Bachelor of
Environmental Science
ENTEC
During the EIA report preparation, the project owner have received the guidance and
assistance of the following agencies:
- Department of Natural Resources and Environment of Dong Nai Province;
12
- People Committee and Fatherland Front Union of Phuoc Khanh commune,
Nhon Trach district, Dong Nai province.
13
CHƯƠNG 1 BRIEF DESCRIPTION OF THE PROJECT
1.1. PROJECT OWNER
TIN NGHIA CORPORATION
- Address: 96 Ha Huy Giap, Quyet Thang Dist. Bien Hoa City, Dong Nai
Province.
- Tel: 061.3824369 - 3822486 Fax: 061.3823747
- Representative: Quach Van Duc
- Position: General Director
Tin Nghia Corporation was founded in 1989, after more than 25 years of development
Tin Nghia Corporation is a large corporation in Dong Nai province with 17
subsidiaries (50% contribution), 13 of joint ventures (50% contribution), annual sales
reached 8.000 billion and UNDP have voted as one of 200 largest enterprises in
Vietnam.
Besides, Tin Nghia Corporation is a company with many years experience in the
industrial development, especially in the industrial zones waste water treatment. Up to
now, Tin Nghia Corporation is investing in development of 08 industrial zones with a
total area of 3,518 ha, including Nhon Trach 3, An Phuoc, Tan Phu, Nhon Trach 6,
Tam Phuoc, Bau Xeo, Dat Do and Ong Keo IZs. Currently, these industrial zones are
efficiently operating and exploiting, especially the industrial zone’s wastewater
treatment plants are operating with very good handling performance and always
ensuring the effluent quality standards to meet the regulations before discharging into
the receiving water bodies. In addition, during operation Tin Nghia Corporation
always comply with the laws and regulations and is one of the leading enterprises in
environmental protection and sustainable development. So, Tin Nghia Corporation has
full sufficient experience and capacity to implement the project.
During construction of the central wastewater treatment plant of Ong Keo IZ, Tin
Nghia Corporation has collaborated with SEEN Technologies Corporation, in
consulting, design and construction. SEEN Technologies Corporation had perform
many projects wastewater treatment projects centralized, particularly wastewater
treatment of IZ. SEEN Technologies Corporation have qualified to advise, design and
construction of a waste water treatment station Ong Keo Industrial Zone.
14
1.1. PROJECT LOCATION
1.1.1. Ong Keo IZ Location
Ong Keo IZ has a total area of 855.60 hectares, was planning to build in Phuoc Khanh
commune, Nhon Trach district, Dong Nai province (See Figure 1.1).
Geographic coordinates: the project location from coordinates (589801,1 ; 1148740,1)
to coordinates (595948,7 ; 1152610,7).
Figure 1.1. Location map of Ong Keo Industrial Zone
The boundary of the project is as follows:
- North adjacent to main urban road;
- Northwest adjacent to Cha La Lon canal;
- West and southwest adjacent to Long Tau river;
- East: Next to Ong Keo canal;
- South: Adjacent to Dong Tranh river.
1.1.2. Location of Central Wastewater Treatment Plant at Ong Keo IZ
Geographic coordinates: the project location from coordinates:
Table 1.1. The from coordinates location border of project area
No. Name X Y
1 X1 591351.84 1150475.33
2 X2 591502.11 1150574.86
Ong Keo IZ
15
3 X3 591582.76 1150465.70
4 X4 591436.78 1150360.70
The boundary of the project is as follows:
- North: Adjacent to empty land;
- East: Next to Bang canal;
- West: Next to internal roads of the IZ
- South: Next to internal roads of the IZ.
Figure 1.2. Location map of the wastewater treatment plant at Ong Keo Industrial
Zone
1.1.3. CETP service area of Ong Keo IZ
The IZD plan to construct the CETP with capacity of 6,000 m3/day, classifying into 02
modules with capactiy of 3,000 m3/day for each. The figure shows two service areas:
- CETP module 1 serves for curent area (phase 1 of IZ) with capacy is 3000
m3/day;
- CETP module 2 serves for future area (phase 2 of IZ) with capacy is 3000
m3/day;
1.2. BRIEF DESCRIPTION OF PROJECT ACTVITIES
1.2.1. Objectives of construction of wastewater treatment plant at Ong Keo IZ
Objectives of construction of the wastewater treatment plant in Ong Keo Industrial
Zone are as follows:
Location of
WWTP
X1
X2
2 X3
X4
Bang canal
16
- Construction of the wastewater treatment plant to collect and treat all waste
waters arising during the production of the enterprises in the industrial zones, to
ensure the quality of treated waste water to meet the regulation QCVN
40:2011/BTNMT, Column A, and to prevent and minimize the negative
impacts to the surrounding environment;
- Ong Keo IZ wastewater treatment plant meets the discharge capacity of the
enterprises inside the industrial zones;
- Stable operation of the wastewater treatment plant in strict accordance with the
technology sequence to ensure the current environmental regulations, to help
protecting the environment;
- Location of construction of the wastewater treatment plant must conform to the
general plan of IZ and facilitate the connections between the different stages in
the future.
1.2.2. Requirement on input and output of waste water treatment plant
1.2.2.1. List of industrial establishments, wastewater capability at the sources before
connecting to the Central WWTP
Currently, Ong Keo IZ have 10 enterprises in operation, 2 enterprises are building and
3 enterprises have not yet built, 1 enterprise stopped operation. The total area of the
occupied land is 288.4 ha, equivalent to 59 % of the total area of the IZ. In addition,
enterprises operation and constructing, other enterprises, when investing in Ong Keo
IZ must commit in writing form to carry out installation of the preliminary wastewater
treatment facilities to ensure that the outlet wastewater quality meets the connecting
standard wastewater of Ong Keo IZ before connecting to the central wastewater
treatment plant of Ong Keo IZ.
The list of the enterprises, which have signed contracts for land leases in Ong Keo IZ
by 30 October 2014 (14 enterprises with land rent directly from the PPC), is presented
in table 1.2.
Table 1.2. The enterprises having leased land in Ong Keo IZ
N
o.
Name investor lease
land/factory
Leasing Area
(m2) National
The Products field
production
I. The enterprises are operating
1 Lafarge Cement Company
Limited Vietnam 60,000.0 France
Grinding factory
the cement
17
2 Vopak Viet Nam
Company Limited 87,200.0 Holland Processing lubricants
3 Sanrimjohap Vina
Company Limited 59,507.4 Korea
Production wood chips
for
export
4
PetroVietnam Power
NhonTrach Joint Stock
Company
314,155.0 Viet Nam Power plant
investment
Nhon Trach 1 Road No.13 25,506.0
5
Hong Moc manufacture,
trade and service private
enterprise
46,704.0 Viet Nam Investment repository
LPG
6
Manufactures and Repair
floating facilities Joint
Stock Company (PTSC)
200,252.4 Viet Nam
Processing and
repairing ships
manufacture of
mechanical design,
electrical, hydraulic
installations on board
7
Gas shipping South East
company - Phu My gas
pipeline
99,011.3 Viet Nam Investment station
gas distribution
8
PetroVietnam Power
NhonTrach 2 Joint Stock
Company
452,564.8 Viet Nam
Power plant
investment
Nhon Trach 2
9
Roofing sheet Dong Nai
Joint Stock Company and
Building Materials (Cong
Thanh Cement)
153,496.4 Viet Nam Cement Production
10 Bao Tin Production
Company Limited 74,778.1 Viet Nam
Invest in repair,
product Ship
II. The enterprises are building
1 Sun Steel Company
Limited 500,000.0 Taiwan
Steel billet Factory,
galvanized iron sheet
production
2
Vietnam French Joint
Stock Company
production cattle feed
65,425 France –
Viet Nam
Animal food
production
III. The enterprises are not yet building
1 Traffic Engineering 2
company 505,644.0 Viet Nam
Sản xuất động cơ,
lắp ráp ô tô, xe tải, xe
khách
2 Tram Anh Company
Limited 116,546.0 Viet Nam Processing lubricants
18
3 CPC company 93,980 Taiwan Processing lubricants
IV. The enterprises stop operation
1 Fuel Hoang Viet
Company Limited 29,860.0 Viet Nam Preparing lubricants
Total 2,884,630
Source: Ong Keo IZ Management Board-Tin Nghia Corporation, November 2014.
1.2.2.2. Inputs wastewater requirement
The wastewaters from the enterprises in Ong Keo IZ have to meet the input
requirement standard connecting of Ong Keo IZ before discharging into the drainage
system and connecting to the central wastewater treatment plant.
Then Ong Keo IZ will continue treating to meet QCVN40: 2011/BTNMT, column B
before discharging into the receiving environment. The quality of the treated
wastewater have to comply with the regulations, which is presented in table 1.3.
Table 1.3. Pretreatment input and output requirements on the quality of wastewater
No.
Parameter Unit
Wastewater standard of the
central wastewater treatment
plant of Ong Keo IZ
Input
Output
(QCVN
40:2011/BTNMT
columm B with Kf
= 0,9 and Kq = 0,9)
1 Temperature oC < 45 40
2 The color (pH = 7) Pt/Co - 150
3 pH - 5.5-8 5,5 - 9
4 BOD5 (20oC) mg/l ≤ 300 50
5 COD mg/l ≤ 500 150
6 TSS mg/l ≤ 200 100
7 Arsenic mg/l 0,1 0,1
8 Mercury mg/l 0,01 0,01
9 Lead mg/l 0,5 0,5
10 Cadmium mg/l 0,1 0,1
11 Chrome (VI) mg/l 0,1 0,1
12 Chrome (III) mg/l 1 1
13 Copper mg/l 2 2
14 Zinc mg/l 3 3
15 Niken mg/l 0,5 0,5
16 Manganese mg/l 1 1
17 Iron mg/l 5 5
19
18 Cyanide mg/l 0,1 0,1
19 Phenol mg/l 0,5 0,5
20 Mineral oil mg/l 20 10
21 Sulfide mg/l 0,5 0,5
22 Fluoride mg/l 10 10
23 Ammonia(by nitrogen) mg/l 10 10
24 Total Nitrogen mg/l 40 40
25 Total phosphorus mg/l 8 6
26 Chloride mg/l 1000 1000
27 Chlorine residue mg/l 2 2
28 Plant protection chemicals:
organic Phosphorus mg/l 0,1 0,1
29 Plant protection chemicals:
organic chlorine mg/l 1 1
30 PCBs mg/l 0,01 0,01
31 Coliform Bacteria/100ml - 5000
32 Total radioactivity α Bq/l 0,1 0,1
33 Total radioactivity β Bq/l 1,0 1,0
Source: Ong Keo IZ Management Board-Tin Nghia Corporation, November 2014
1.2.2.3. Outlet wastewater standards
The wastewater has to be treated to meet the National Technical Regulation on
industrial wastewater QCVN 40:2011/BTNMT, column B with Kq = 0.9, Kf = 0.9 .
Kq and Kf factors are selected as follows:
- The receiving water source of the treated wastewater is Long Tau river with Kq
= 0.9;
- Flow coefficient (Kf) is chosen as presented in table 1.3.
Table 1.4. Coefficient Kf regulated in QCVN 40:2011/BTNMT
Waste flow (F)
Unit: cubic meters/day (m3/24h) Coefficient Kf
F ≤ 50 1.2
50 < F ≤ 500 1.1
500 < F ≤ 5.000 1.0
F > 5.000 0.9
For safety of the design work, coefficient Kf = 0.9 is selected. The quality of the
treated wastewater has to comply with the regulations, which is presented in table 1.5.
Table 1.5. Waste water quality requirements after treatment
No. Parameter Unit
Limit value
(QCVN 40:2011/BTNMT, Column B)
C Kq Kf Cmax
1 Temperature 0C 40 - - 40
20
No. Parameter Unit
Limit value
(QCVN 40:2011/BTNMT, Column B)
C Kq Kf Cmax
2 The color (pH = 7) PT/Co 150 - - 150
3 pH - 5.5 to 9 - - 5.5to 9
4 COD mg/l 50 0.9 0.9 40.5
5 BOD5 (200C) mg/l 150 0.9 0.9 121.5
6 TSS mg/l 100 0.9 0.9 81
7 Arsenic mg/l 0.1 0.9 0.9 0.081
8 Mercury mg/l 0.01 0.9 0.9 0.0081
9 Lead mg/l 0.5 0.9 0.9 0.405
10 Cadmium mg/l 0.1 0.9 0.9 0.081
11 Chrome (VI) mg/l 0.1 0.9 0.9 0.081
12 Chrome (III) mg/l 1 0.9 0.9 0.81
13 Copper mg/l 2 0.9 0.9 1.62
14 Zinc mg/l 3 0.9 0.9 2.43
15 Niken mg/l 0.5 0.9 0.9 0.405
16 Manganese mg/l 1 0.9 0.9 0.81
17 Iron mg/l 5 0.9 0.9 4.05
18 Cyanide mg/l 0.1 0.9 0.9 0.081
19 Phenol mg/l 0.5 0.9 0.9 0.405
20 Mineral oil mg/l 10 0.9 0.9 8.1
21 Sulfide mg/l 0.5 0.9 0.9 0.405
22 Fluoride mg/l 10 0.9 0.9 8.1
23 Ammonia(by nitrogen) mg/l 10 0.9 0.9 8.1
24 Total Nitrogen mg/l 40 0.9 0.9 32.4
25 Total phosphorus mg/l 6 0.9 0.9 4.86
26 Chloride mg/l 1000 0.9 0.9 810
27 Chlorine residue mg/l 2 0.9 0.9 1.62
28
Plant protection
chemicals: organic
Phosphorus
mg/l
0.1 0.9 0.9 0.081
29
Plant protection
chemicals: organic
chlorine
mg/l
1 0.9 0.9 0.81
30 PCBs mg/l 0.01 0.9 0.9 0.0081
31 Coliform MPN/100ml 5000 - - 5000
32 Total radioactivity α Bq/l 0.1 - - 0.1
33 Total radioactivity β Bq/l 1.0 - - 1.0
Source: Ong Keo IZ Management Board-Tin Nghia Corporation, November 2014.
1.2.3. Drainage and wastewater collection system
21
Currently, the project area has no sewerage system and storm drain completed.
Rainwater is drained in the natural terrain down the field and flowing into the canal,
then discharged into 2 rivers including Long Tau river and Dong Tranh River.
1.2.3.1. Plant Rainwater drainage system
Rainwater drainage system will be built along the two sides of the internal roads with
manholes, solid waste screeners, storm water naturally filtered and test wells. The
manholes will be periodically dredged. Contracts will be signed with functional units
to periodically collect, transport and dispose the sludge and sediments. Then, the
treated wastewater flows into Bang canals, Long Tau river and Dong Tranh river.
1.2.3.2. Plant Wastewater drainage System
- Wastewater drainage systems including sewage culverts and technical wells
have the function to collect wastewaters and led to the central wastewater
treatment plant. Culvert system is arranged by terrain slope to the treatment
plant center of Ong Keo IZ. Culverts are designed with diameter of 300 mm -
1000 mm and minimum depth of 0.7 m (from the ground to the top of the
culvert). Technical wells with minimum size of 600 mm are arranged along the
sewer line with the normative distances;
- The Central Wastewater Treatment Plant of Ong Keo IZ:
- The wastewater treatment plant is placed in the technical infrastructure area in
the planned western area;
- Treatment capacity is estimated at 3,000 m3/day;
- Planned area for construction of the central wastewater treatment plant is 2.45
hectar and minimum isolation distance to the residental areas outside the IZ is
30 m;
- The central wastewater treatment plant receives waste waters discharged from
enterprises in the industrial zones, which have to meet the requirement for
connecting of KCN Ong Keo central wastewater treatment plant of Ong Keo IZ
(see table 1.3).
- Wastewater treated at the central wastewater treatment plant have to meet the
regulation QCVN 40:2011/BTNMT, column B (Kf=Kq=0,9) before
discharging into the Long Tau river.
- Methods of collection and treatment of wastewater: wastewaters discharged
from enterprises will be connected to the central wastewater treatment plant of
Ong Keo IZ. The project owner will issue the requirement on the limited
concentrations of pollutants for the enterprises to connect into the central
wastewater treatment plant of Ong Keo IZ. If the concentrations are higher than
the limits, enterprises must apply pre-treatment measures before connecting to
the general collection system of IZ.
22
- Currently, the entire system of wastewater collection have been completely
constructed by Tin Nghia Corporation.
Diagram of wastewater collection to the IZ’s wastewater treatment plant is presented
in figure 1.3.
1.2.4. Description of wastewater treatment technologies
1.2.4.1. Wastewater treatment technology process
Wastewater treatment technology process consists of 4 stages, as follows:
(1). Mechanical treatment (pit pumps, oil separation tank, and air conditioning)
Wastewater from these factories in the industrial zone will be collected into the pump
pit of the treatment plant. Before flowing to the pump pit, the garbage, twigs etc, with
size of > 10mm is separated by automatic garbage separation equipment from waste
water. Then the wastewater is pumped into the oil separation tank. Before flowing the
oil separation tank, the fine garbage with size of > 5 mm is separated by garbage filters
The oil separation tank have following advantages:
- To prevent the abrasion of pumping motors in the successive treatment works;
- To prevent the strange substance in biological treatment tank which can cause
agglomeration into the solids floating in biological tank, which leads to less
efficient treatment system.
Wastewater after sludge separation flows into the oil separation tank in order to
remove floating oil and suspended solid particles with less density than wastewater.
The components will be collected by the automatical oil collection device, which is
capable to adjust to ensure the high level of oil removal efficiency. The collected oil
will be stored in the oil tank to handover for the functional units. Also the oil
remaining after passing through the oil separation tank will be further removed in
primary sedimentation tanks behind. Then wastewater will flow into the conditioning
tank.
Balancing tank is designed with sufficient retention time to ensure the flow and
pollution concentration equalizing, therefore, fluctuations in the composition of
wastewater before going into the process units behind should be significantly reduced.
During the peak hours, excess flow will be kept in the balancing tank. In addition, the
balancing tank also has some advantages such as figure 1.4.
- To ensure the continuity of the system;
Wastewater
from
enterprisement
Central
wastewater
treatment plant
of Ong Keo IZ
Source
reception
Handling
local
Figure 1.3. Diagram of wastewater collection to the IZ’s CETP
23
- To control the high toxic substances;
- To relatively deodorize.
This tank may also use as storage one when the system stops for repair or
maintenance. In balancing tank, the air distribution pipe system is arranged to well
regulate the wastewater load and to avoid the sedimentation process in the tank. The
wastewater is then pumped to the physico-chemical treatment system.
24
Figure 1.4. Diagram of wastewater treatment technology of Ong Keo Industrial Zone
Alumin
sink
Axit sinks
Input Flow
Pum
p
Pump
Pump pit
Conditioning tank
Coagulation –
Flocculation tank
Pump
Pump
Alkaline
Sinks
Polymer
Sinks
Output flow
Pump
Pumb
JAVEL
sinks
Polymer sinks
Dry mud
Aerotank
Primary
sedimention tank
LÝ
Secondary
sedimentation tank
Disinfection tank Slugde tank
Slugde presses
Pump
Pump
Pump
Pump
M
Oil separation tank
Ecological pond
Pump
Pump
Balancing tank
25
(2). Physicochemical treatment (Coagulated tank, flocculation and primary
sedimentation tanks)
During this treatment period, waste water from balancing tank is pumped through the
system without dosing of chemicals. In the emergency cases the chemical dosing and
mixing stirs will be operated. The substances, which can be removed from the
wastewaters due to physico-chemical treatment are as follows: COD, SS, heavy metal
compounds and colloids in wastewater. Since COD and suspended solids
concentrations are decreased, the concentration of BOD are also decreased in the
treatment process.
At the coagulation tank, coagulants are added to mix with wastewater. Coagulation
help to destabilize the sediment particles (glue) and stimulate them to stick with the
other suspended sediment to form larger scale particles (polymer). At coagulation
tank, chemicals stimulate the flocculation process to form the larger scale particles,
which are mixed with wastewater. Polymer have the effect forming a "bridge" to link
the small size particles to form the bigger size particles to improve the efficiency of
primary sedimentation tanks behind.
Preliminary sedimentation tanks is specially designed, which create the static media
for settlement of the solid particles. The design of the scraping sludge system helps
automatically collect sludge into sludge containing pit and excess sludge is pumped
periodically to the sludge storage tank.
The wastewater is flowing into next tanks to perform further biological treatment
process.
(3). Treated with biological methods (balancing tank + inflatable tank +
secondary sedimentation and disinfection tank)
After pre-treatment process in oil separation tank and primary sedimentation tank,
wastewater will be treated by biological methods. Wastewater from primary
sedimentation tank will flow into the balancing tank. In normal conditions, this tank
can adjust pH value of wastewater.
In aerobic biological tank, aerobic bacteria (activated sludge) decompose organic
matter (mainly, dissolved organic matter). Oxygen tank is provided in order to
facilitate the process of decomposition of organic matter through the surface aerator,
which is properly installed on the tank. After the biological treatment process, the
majority of organic matter in the wastewater is removed. Wastewater leaving aerobic
biological tank will led through the secondary sedimentation tank to conduct sludge
dewatering process.
Mixture of sludge and wastewater leaving the aerobic biological tank are overflowed
into a rectangular tank to conduct sludge dewatering process. Biological sludge will
settle at the bottom of the secondary sedimentation tank, then collected in sludge
storage tank with brushed device. A defined amount of biological sludge (activated
26
sludge) is recycled to let amount of sludge in aerotank. Periodically, excess sludge in
pit is pumped to the sludge compression tank to conduct dewatering process.
Wastewater after sludge separation in the sedimentation tank is led through the
disinfection tank.
At disinfection tank, wastewater will be mixed with a disinfectant offered by
automatical disinfectant injection system to destroy the bacteria to meet the discharge
standards regulations.
(4). Ecological pond
The pond pays roles of treated wastewater storage as well as landscaping, pool rescue
incidents as needed
1.2.4.2. The main items of the central WWTP
Currently, WWTP of Ong Keo Industrial Zone was built and installed partially
technological pipes, the equipment of the station was sealed and storage, when have
wastewater collection pipelines, we will install and operating system testing before the
system official operation. The works and the equipment of WWTP including:
(1). The construction items
(a). Pump pit (T101)
- Dimensions (DxRxSxC): 6.0x3.7x1.1x5;
- Quantity: 01;
- Total area: 22.2 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(b). Oil separated tank (T102)
- Dimensions (DxRxSxC): 9.0x1.6x4.5x5;
- Quantity: 01;
- Total area: 14.4 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint. .
(c). Regulate tank (T103)
- Dimensions (DxRxSxC): 20.2x9.0x4.5x5;
- Quantity: 01;
- Total area: 181.8 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(d). Coagulated Tank (T201)
27
- Dimensions (DxRxSxC): 2.0x2.0x4.5x5.0;
- Quantity: 01;
- Total area: 4.0 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(e). Flocculation Tank (T202)
- Dimensions (DxRxSxC): 4.1x2.0x4.5x5;
- Quantity: 01;
- Total area: 8.2 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(f). Primary sedimentation Tank (T203)
- Dimensions (DxRxSxC): 9.0x9.0x4.5x5.0
- Quantity: 01
- Total area : 81.0 m2
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(g). Neutralization tank (T204)
- Dimensions (DxRxSxC): 2.5x2.0x4.5x5;
- Quantity: 01;
- Total area: 5.0 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(h). Aeroten Tank (T301A/B)
- Dimensions (DxRxSxC): 16x14.55x4.5x5;
- Quantity: 02;
- Total are : 232.8 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(i). Secondary sedimentation tank (T302)
- Dimensions (DxRxSxC): 15.5x15.5x4.5x5.0
- Quantity: 01
- Total area: 240.25 m2
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(j). Disinfect tank (T401)
28
- Dimensions (DxRxSxC): 9.0x3.5x1.7x2.0;
- Quantity: 01;
- Total area: 31.50 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(k). Sludge tank (T501AB)
- Dimensions physicochemical sludge tank(DxRxSxC): 5.75x5x4.8x5
- Dimensions biological sludge tank: 3x5x4.8x5
- Quantity: 02;
- Total area: 43.75 m2;
- Nails, walls, floors made of reinforced concrete. Inside coated by epoxy anti-
corrosion paint.
(l). (xii).Biological lakes (H1)
- Dimensions (DxRxC): 85.00x24.00x1.50;
- Quantity: 01;
- -Total area: 2040.00 m2;
- Building rubble crater, the bottom, the panels cover 1,500 mm thick HDPE.
(m). The operator (N01)
- Dimensions (DxRxC): 10x15x5.5;
- Quantity: 01;
- Total area: 150 m2;
- Concrete nails. Brick wall. Trusses, purling steel. Tin roof.
(n). Guardhouse (N05)
- - Dimensions (DxRxC): 3x3x5.1;
- Quantity: 01;
- Total area: 9 m2;
- Concrete nails. Brick wall. Trusses, purlins steel. Tin roof.
(o). Garage (N06
- Dimensions (DxRxC): 7x3x3.83;
- Quantity: 01;
- Total area: 21 m2;
- Concrete nails. Brick wall. Trusses, purlins steel. Tin roof.
(p). Chemicals house & sludge dewatering (N08, N09)
- Dimensions (DxRxC): 11.5x7.2x4.2;
- Quantity: 01;
- Total area: 82.80 m2;
- Concrete nails. Brick wall. Trusses, purlins steel. Tin roof.
29
(q). Air blowers house (N03)
Dimensions (DxRxC): 6.2x5.1x4.2;
- Quantity: 01;
- Total area: 31.62 m2;
- Concrete nails. Brick wall. Trusses, purlins steel. Tin roof.
(r). Operation Sidewalks and Internal roads:
- Designed in accordance with overall ground and facilitate the operation and use
of the wastewater treatment plant Ong Keo Industrial Zone modul 1;
- Soil compaction, concrete.
(s). Fence:
- Volume: 302 m;
- Pile reinforced concrete, brick wall paint, bars at.
(2). Equipment and machinery
The machinery and equipment of Ong Keo Industrial Zone WWTP is presented as
follows:
30
Table 1.6. The machinery and equipment of Ong Keo Industrial Zone WWTP
No. Machinery and
equipment Technical characteristics
Manufacturer/quality
assurance Producing country
Unit
Quantity
I LIST OF EQUIPMENT TECHNOLOGY
1.
Sewage pump in
the collection tank
Submersible pump
+ Discharge: 125 m3/h.
+ Pressure head: 9-10m. Motor:
9kw/380V/3phase/50Hz.
+ The humidity sensor DI
+ Temperature sensors TCS
+ Protection function congestion.
+ Autocoupling
+ Batten, chain to move pump SUS304.
Material:
- pump barrel: gray iron
-pump shaft: gray iron
-pump impeller: gray iron
Protection Level: IP 68
ABS – Swedish Ailen
Piece
3
2. Sewage pump in
equalization tank
Submersible pump
+ Flow: 125 m3/h.
+ Pressure head: 5,5 - 6m.
+ Motor: 6kw/380V/3phase/50Hz.
+ The humidity sensor DI
+ Temperature sensors TCS
ABS – Swedish Ailen
Piece 2
31
+ Protection function congestion.
+ Autocoupling
+ Batten, chain to move pump SUS304.
Material:
- pump barrel: gray iron
pump shaft: gray iron
pump impeller: gray iron
Protection Level: IP 68
3.
Sludge pump in
primary settling
tanks
Submersible pump
+ Flow: 15m3/h.
+ Pressure head: 5,5 - 6m.
+ Motor: 1,95kW/380V/3phase/50Hz.
+ The humidity sensor DI
+ Temperature sensors TCS
+ Protection function congestion.
Material:
- pump barrel: FC 200
- pump shaft: SUS 420J2
- pump impeller: FC 200
Protection Level: IP 68
ABS – Swedish Ailen Piece 2
4. Sludge pump
recirculation
Submersible pump
+ Flow: 65m3/h.
+ Pressure head: 5,5 - 6m.
+ Motor: 4kw/380V/3phase/50Hz.
+ The humidity sensor DI
+ Temperature sensors TCS
+ Protection function congestion.
+ Autocoupling.
+ Batten, chain to move pump SUS304.
ABS – Swedish Ailen Piece 2
32
Material:
- pump barrel: gray iron
pump shaft: gray iron
pump impeller: gray iron
Protection Level: IP 68
5. Sludge pump
Submersible pump
+ Flow: 30 m3/h.
+ Pressure head: 6m.
+ Motor: 2.2kw/380V/3phase/50Hz.
+ The humidity sensor DI
+ Temperature sensors TCS
+ Protection function congestion.
Material:
-pump barrel: FC 200
-pump shaft: SUS 420J2
-pump impeller: FC 200
Protection Level: IP 68
ABS – Swedish Ailen Piece 1
6. Sludge pump in
sludge dewatering
Screw pump
+ Discharge: 6m3/h.
+ Pressure head: 2.2 – 3.7kw
+ Power: 380V/3phase/50hz
- Overload protection devices running
dry TSE.
- Button adjust speed motor rotation
-Interlock operation with sludge
dewatering, anti-congestion.
Seepex – Germany Germany Piece 1
7. Sludge
dewatering
Type: Filter Presses
Widely applied in the field of waste
water, designed with high pressure - 15
Netzsch Germany` batch 1
33
bar, ensuring optimal levels of solids in
sludge cake.
Structure:
- Frame: steel
- filter board: cast iron or inox or
equivalent
- Boling fabric: can be made from the
following materials: polyamide,
polypropylene, polyeste.
Flow: 6m3/h
Maximum working pressure: 15bar
8. Blowers
equalization tank
Type: Three - lobe rotors
Flow: 9.57m3/ min.
Pressure head: 500mbar
Pk: 11.1Kw.
Pmot: 15kw
Power:
380V/3phase/50Hz
Dust filters at the input, easily
removable.
Aerzen - Germany Germany appar
atus 2
9. Blowers Aeroten
tank
Type: Three - lobe rotors
Flow: 22.55m3/min.
Pressure head: 500mbar
Pk : 24.6Kw.
Pmot: 30kw
Power:
380V/3phase/50Hz
Dust filters at the input, easily
removable.
Aerzen - Germany Germany appar
atus 3
34
10.
Gas Distribution
System of
equalization tank
Material: Inox SUS304, gas distribution
the form of discs, air bubble kind crude.
Dust filters at the input, easily
removable.
EDI - Hoa Kỳ USA HT 1
11.
Gas Distribution
System of
Aeroten tank
Material: PVC và Inox, gas distribution
the form of discs, air bubble kind fine.
Corrosion resistant EPDM membrane,
oxygen absorption high performance.
Easy disassembly, cleaning.
Evenly distributed.
EDI - USA USA HT 2
12. Flocculation tank
mixers
Motor, vertical axis →
Capacity: 1.1 kw
Speed: 60 – 80 revolution /min.
Power:
380V/3pha/50Hz.
Stirring wing and axis: SUS304 →
Easy to install, easy to maintain
Nord - Germany
SEEN – Viet Nam
Germany /Viet
Nam batch 1
13. Flocculation tank
mixers
Motor, vertical axis →
Capacity: 1.1Kw
Speed: 30 – 40 revolution /min.
Power:
380V/3phase/50Hz.
Blade, axis stirring: SUS304 →
Easy to install, easy to maintain
Nord - Germany
SEEN – Viet Nam
Germany /Viet
Nam batch 2
14.
Agitators
chemical:
nutrition, alkaline,
caustic soda,
polymer
Motor →
Capacity: 0.75Kw
Speed: 80 – 120 revolution /min.
Power:
380V/3pha/50Hz.
Nord - Germany
SEEN – Viet Nam
Germany /Viet
Nam batch 6
35
flocculation +
sludge dewaterin,
disinfectants
Blade, axis stirring : SUS304 →
Easy to install, easy to maintain
15. Dosing pump axit
H2SO4
Diaphragm pump, chemical resistance
Flow: 0- 75 l/h
Pressure head: 5 - 6 bar
Capacity: 0.37Kw.
Power:
380V/3phase/50Hz
Adjust the volume automatically or
manually.
Doseuro - Italy Italy Piece 2
16. Dosing pump
soda
Diaphragm pump, chemical resistance
Flow: 0- 155 l/h
Pressure head: 5 - 6 bar
Capacity: 0.37Kw.
Power: 380V/3phase/50Hz
Adjust the volume automatically or
manually
Doseuro - Italy Italy Piece 2
17. Dosing pump
nourishing
Diaphragm pump, chemical resistance
Flow: 0- 75 l/h
Pressure head: 5 - 6 bar
Capacity: 0.37Kw..
Power: 380V/3phase/50Hz
Adjust the volume automatically or
manually
Doseuro - Italy Italy Piece 2
18. Dosing pump
alum
Diaphragm pump, chemical resistance
Flow: 0 - 320 l/h
Pressure head: 5 – 7bar
Capacity: 0.37Kw.
Doseuro - Italy Italy Piece 2
36
Power: 380V/3phase/50Hz
Adjust the volume automatically or
manually
19.
Dosing pump
polyme
flocculation of
wastewater
Diaphragm pump, chemical resistance
Flow: 0- 197 l/h
Pressure head: 3bar
Capacity: 0.37Kw.
Power: 380V/3phase/50Hz
Adjust the volume automatically or
manually
Doseuro - Italy Italy Piece 2
20. Dosing pump
antirust substance
Diaphragm pump, chemical resistance
Flow: 0- 23 l/h
Pressure head: 5 - 6 bar
Capacity: 0.37Kw.
Power: 380V/3phase/50Hz
Adjust the volume automatically or
manually.
Doseuro - Italy Italy Piece 2
21. Dosing pump
polyme
Piston diaphragm pumps, chemical
resistance
Flow: 400 – 600 l/h
Pressure head: 5bar
Capacity: 0.37Kw.
Power: 380V/3phase/50Hz
Adjust the volume automatically or
manually
Doseuro - Italy Italy Piece 2
22. Garbage splitting
machines fine
Rotary drum, fine sieve
Capacity max: 0 - 160 m3/h
Materials SUS304
Split is the largest object size 2mm
Cosme - Italy Italy Piece 1
37
23.
Equipment
brushed sludge in
Primary
clarifiers tank
Motor→
Công suất : 0.25Kw
Capacity: 0.02 – 0.08 revolution /min.
Power: 380V/3phase/50Hz.
Equipment protection of engine power
vane,axis: SUS304 →
Nord - Germany
SEEN – Viet Nam
Germany/Việt
Nam batch 1
24.
Equipment
brushed sludge in
Secondary
clarifiers tank
Motor→
Capacity: 0.37Kw
The speed of rotation system: 0.01 –
0.1 revolution /min.
Power: 380V/3phase/50Hz.
Equipment protection of engine power
baluster post, bearing bar…
galvannealed sheet.
Nord - Germany
SEEN – Viet Nam
Germany/Viet
Nam batch 1
II LIST OF ELECTRICAL EQUIPMENT - THE AUTOMATIC CONTROL
25.
PLC control
system (including
PC + 01 backup
computer)
Already tropical conditions
conformable with Vietnam, scalability,
good display function and prevention of
incidents, high-speed processing,
human-machine interface, diagnostics
and protection systems.
Designed in accordance with IEC6113-
3.
Standard Ethernet communication
network.
Control, monitoring devices in the
system and data management computer.
Allow observe and operate through
Touch Screen.
Siemens – Germany Germany batch 1
38
26. Software control
SCADA
Leave a software-based root of
SIEMENS. There scalability and
connectivity with other systems
Siemens – Germany Germany batch 1
27.
Flow
measurement
devices
automatically
Professionals for industry. Flow
measurement by magnetic methods.
Show in place and provide control
signals pump.
Measurement range 0-160 m3/h,
Installed directly on exhaust pipes.
Already tropicalize communication
standards Foundation Fieldbus.
Ability to self-diagnose the problem.
Output 4-20mA
Siemens – Germany Germany batch 1
28.
PH measuring
equipment used in
industrial: sensor
and transmiter
Self-laundering probe, for use in
industrial, chemical has tropical.
Measurement range: 0 - 14pH
Temperature Range: -30 to 70oC
Accuracy: 0.01 pH
Communication standards Foundation
Fieldbus.
Endress Hauser –
Germany Germany batch 1
29.
DO measurement
equipment used in
industry : sensor
and transmiter
Professionals for industry.
Temperature Range 0-16mg/l.
Output: 4-20mA
Endress Hauser –
Germany Germany batch 2
30.
Measuring
equipment for
waste water tank
pump set.
Measure the differential pressure
method.
Measured levels, high precision,
tropical; Measurement range: 0.15-
7.5m;
Germany Germany Piece 2
39
Accuracy: 0.25%.
signal 4-20mA
31. Dosing pump
inverter
Full range - providing synchronous
power of Dosing pump. Siemens - Germany Germany Piece 2
32. Inverter Pump Full range - provides synchronization
of pump power conditioning Germany Germany Piece 2
III LAB EQUIPMENT LIST
33. DO meter
handheld
High Accuracy: 0.3mg/l, Measurement
range: 0-20mg/l DO, the smallest share:
0.01mg/l, tropical, easy to use,
supplied with reserve membrane,
carrying suitcases
Aqualytic – Germany Germany Piece 1
34. Portable pH meter
High Accuracy: 0,01pH; measurement
range: 0- 14 pH; temperature: 5-100oC;
can save data, liquid crystal displays,
display easy to read, easy to use,
supplied with the standard solution,
suitcase containing.
Aqualytic – Germany Germany Piece 1
35. Electronic
analytical balance
Weigh accurately 0.001g
Maximum weight: 150g Denver – Germany Germany Piece 1
36.
Colorimeter
analysis COD,
nitrogen,
phosphorus,
chromium ...
Full range Aqualytic – Germany Germany TB 1
37. COD reactor full line Aqualytic – Germany Germany TB 1
38.
BOD analyzers:
Incubator, BOD
measurement
Show results directly. Simultaneous
measurement of 6 samples Aqualytic – Germany Germany TB 1
40
equipment
39. compartment drier Oven to 150oC Memmert - Germany Germany Piece 1
40.
Glassware, and
dedicated enough
instruments for
laboratories
All the glassware enough to analyze the
indicators: COD, BOD, SS, MLSS,
SVI, N, P, K
imported imported batch 1
41.
Laboratory
chemicals
sufficient for 3
months of
operation of the
treatment system
Analysis of indicators COD, BOD, N,
SS (3 times per week analysis: COD,
BOD, N, SS)
Aqualytic - Germany
(synchronized with
laboratory equipment)
Germany batch 1
42. Vacuum filter Pump KNS : Germany
filter funnel: Sartorius - Germany
KNS –
Germany/Sartorius -
Germany
Germany batch 1
41
1.2.5. Sludge Treatment Technology
Excess sludge from the primary and secondary clarifiers will be pumped to the
compressed mud tank periodically, where sewage sludge is concentrated by gravity
sedimentation method, then collected to the tank bottom by the sediment brusher
system. Depending on the concentration of biomass in the sludge tank that total
dissolved solids (TDS) ranging from 2-3% before being pumped into the sludge
dewatering process for separating water from the mud. Sludge after dewatering in the
form of cake will be packaged and stored in a dry mud warehouse before bringing to
sanitary landfills. Wastewater from sludge tank and excess sludge dewatering will be
circulated to the pump pit for reprocessing.
The project owner will sign contracts with Tai Tien Co., Ltd, Sao Viet Joint Stock
Environment Company. Dong Nai Urban Environment Service One Member
Company, Tan Thien Nhien Co, Ltd, Sonadezi Joint Stock Enironment Treatment
Company etc. for collecting and handling whole sludge in accordance with the
provisions of the current law.
Hazardous waste treatment technologies of the mentioned above companies has been
licensed by the Vietnam Environment Administration within Ministry of Natural
Resources and Environment.
1.2.6. Transportation system
1.2.6.1. The current transportation system
Currently, the transport system in the industrial park mainly Ong Keo dike roads
which are used to travel and transport in the industrial zone. When the infrastructure of
Ong Keo Industrial Zone is deployed, this dike will be replaced. In addition, the
current Ong Keo IZ has earth roads, access roads to traffic and road links in the area.
The road links are relatively complete, specifically, as presented below:
(1). External traffic
a). Roads
In the distance from IPZ to the North about 3.5 km have No.19 District road, width of
road is 7m and concrete asphalt structure. No. 19 road is Route 19 is civil road from
longstanding, suround Nhon Trach city and connects with surrounding other area.
Ong Keo dike road around the West, South and East of the IZ, the length of Ong Keo
dyke road is 8.5 kilometer, average elevation 1.5 meter over the sea level, The width
of road is 6 meter.
(a). Waterways
42
In the direction of Southwest of Nhon Trach city and Ong Keo IZ have Long Tau
river and Dong Tranh river. This is an important waterway in the Southern key
economic zone. Currently, cargo ship and passengers ship away from the Ho Chi Minh
city to Vung Tau city are going through here, in that have passenger hydrofoil routes
with high speed. Section the river through Industrial Zone have width of about 600 m,
deep is 9-12 m, routes are designed for vessels up to 30,000 DWT. The currently, on
riverside of Long Tau river and Dong Tranh river constructed many specialized jetty.
(2). Internal Communications
In the area there are only a few earth and gravel roads of about 3m wide being used for
the traffic in residential areas.
1.2.6.2. Planning of transportation infrastructure
(1). External traffic
a). Roads
Ong Keo Industrial Zone is located on the Southern "road Ong Keo Industrial Zone"
and gets this route as the external route of the Industrial Zone. According to the
general planning of Nhon Trach New City, this road connects Ong Keo Industrial
Zone inter-regional highway south, with road limit 61m. The scale following section
(section AA): Pavement separation 15m solution x2 between 3 m, 14 m x2 sidewalk.
Along this route layout 2 green strips reserve for expanding later. Industrial Zone's car
park is located next to the service area, an area of 1.5 ha.
(a). Waterways
Long Tau River runs along the southern boundary is important waterways of Industrial
Zone. Cargo jetty is arranged at the end of No. 9 road with a length of about 300 m,
the scale of 1.8 ha for loading and unloading goods for the entire Industrial Zone.
(2). Transportation infrastructure system Ong Keo Industrial Zone
Based on the shape of the land line, electricity line, the project has provided land and
outbound traffic. The road system in the industrial park is designed as follows:
1) The two main roads connect the Industrial Zone from the North route for foreign
Industrial Zone, acting as the two main roads of East and West of the Industrial Zone.
West route connects to foreign route to harbor, to the east line and runs eastward
drainage business. These road cross-section 1-1: The vehicle is 12m wide double line
on each side, 3m wide strip separating the sidewalk and the industrial engineering strip
10 meters wide, the trees along the canal 3m wide, sidewalks to walk on the technical
side of Industrial Zone strip 3m wide, 40m wide.
43
2) The main roads East – West of IZ along the Dong Tranh River and Long Tau river
connecting the East with the Western region, cross-2-2: Pavement 8x2m, 2m wide
strip separating strip technique 2 x 2 sides 10m, 38 m road limit.
3) The other main route of IZ, have sections 3-3: road surface width of 15m,
engineering range 10 meters wide on each side, walk on pavement engineering 3m
wide strip on each side, 35m wide.
4) The internal roads in clusters of enterprises, road about 24m, sections 4-4, 8m wide
road surface, technical range 2 each side 8m, pavement walking on 3 m wide range
technique each side.
5) The parallel route along the city's Northern IZ (line 1) along the Ong Keo canal,
Muoi canal, Bang canal, rub the incision is large. On this route have a side of land to
build IZ, one side is green strips, road about 19m (sections 5-5), the vehicle 8m strip
8m IZ technical side, inside the range of trees 3m wide, walks on the technical side
range 3m wide.
The traffic specification is shown in Table 1.7.
Diagram traffic planning Ong Keo IZ is presented in Figure II.4 Annex II.
Table 1.7. The traffic specification
No. Specification Unit Planing
1 The total length of roads m 31,368
2 The total land area traffic m2 1,118,439
3 Bordering thereof radii m
Intersection of the main road 15-20
Intersections on local roads 8-10
4 Design speed of the road in the industrial park km/h
The main roads 60
The internal roads 40
5 The vision street corner m
The main roads 56
The internal roads 36
6 Sizes flap angle at the intersection m
Intersection of the main road 8-12
Intersections on local roads 8
7 Axle loads design ton 30
8 Pavement structure Asphalt concrete
Source: Tin Nghia Project Management Company Limited, 06/2007.
44
1.2.7. System of hazardous wastes management at Ong Keo Industrial Zone
The current, manufacture of Ong Keo IZ not yet contruction. However, in the planning
of industrial zone will havearea of solid waste transfer with area of 1,5 ha. For the
enterprises operating in the Industrial Zone (enterprises directly lease by PPC ),
directly contracted with functional units to collect solid waste treatment prescribed. In
the future, management system for hazardous waste Ong Keo Industrial Zone will be
investment and constructed completely. Specifically, this present as follows:
1.2.7.1. Municipal solid waste
- None - hazardous solid waste will be collected and sorted at source by the
sanitary devices as required.
- The project owner will arrange composite containers with a lid in the area of
waste generation (the operating, service areas, transportation routes etc.) and
specialized hygiene team will collect the waste to a transfer station of the
Industrial Zone before contracting the function units to handle and process
periodically. The transfer station has an area of 350m2, which is covered and
concreted. The transfer station is located in the west area next to the wastewater
treatment plant of the IZ to temporarily store the entire municipal waste
generated.
1.2.7.2. Hazardous and non-hazardous industrial solid waste
- Hazardous and non-hazardous industrial solid waste: The project owner
currently is invested to build the warehouse next to the municipal waste transfer
station with an area of 200m2, which is covered and concreted. Particularly,
hazardous waste generated from enterprises in the Industrial Zone will be stored
in the specilized warehouse with separate cells to store different types of
hazardous wastes. The hazardous waste warehouse is located in right places,
which is covered and labeled.
- These wastes must be classified by enterprises at the sources into municipal
waste, non-hazardous waste, and hazardous waste before delivery to functional
units to collect and dispose.
- The project owner will coordinate with the functional authorities to check the
waste management performance of enterprises in the Industrial Zone to comply
with the current regulations.
1.2.7.3. Enterprises in the IZ
The enterprises in the IZ will collect, sort, transport, and treat wastes as regulated,
including:
- Registering the owner of hazardous wastes sources with local environmental
management agencies;
- Non-hazardous solid waste: Carrying out collecting, sorting at the sources by
the hygienic instrument in accordance with the relevant regulation;
45
- Hazardous waste: sorting, packing, preservation and storage in accordance with
the hazardous waste management regulation at the sources, then transported to
the disposal areas. The hazardous waste must be properly labeled and indicated
the necessary information as requested by the regulations;
- Storing the classified wastes in the sanitary containers or in bags with
distinctive colors, disposing the waste into the right places;
- Signing service’s contracts with function units for waste collection,
transportation and disposal ;
- Prohibiting enterprises to dispose waste in the unplanned areas, caused
environmental pollution to the Industrial Zone
1.2.7.4. Investors and IZ infrastructure management (Tin Nghia Corporation)
To perform the collection, transportation and treatment of all types of waste generated
in Industrial Zones, the project owner will implement the following measures:
- Non-hazardous and hazardous industrial solid waste: the company will
construct the transfer station and warehouse to collect and store solid wastes
generated from the enterprises in the IPs
- The waste must be classified by the enterprises at sources into separate types of
domestic waste, non-hazardous waste and hazardous waste before delivery to
the functional units to collect and dispose.
- Coordinate with the functional authorities to check the waste management
performance of enterprises in the Industrial Zone to comply with the current
regulations.
At the present, there has been a number of companies licensed in handling hazardous
waste in Dong Nai province, such as Tai Tien Co., Ltd, Sao Viet Joint Stock
Environment Company, Dong Nai Urban Environment Service One Member
Company, Tan Thien Nhien Co, Ltd, Sonadezi Joint Stock Enironment Treatment
Company etc. The enterprises in the industrial zone can also sign contracts with the
service companies to collect and dispose.
In addition, to strengthen the management and disposal of solid waste as requested by
the People's Committee of Dong Nai Province, the project owner will closely
cooperate with the Dong Nai Industrial Zones Administration and Department of
Natural Resources and Environment in checking and monitoring the solid waste
management performance in the industrial zone.
1.2.8. Risk management in Ong Keo Industrial Zone
The environmental emergency cases may include: Fire and exploitation, chemical and
oil spills, damage of drainage system and the wastewater treatment plant.
1.2.8.1. Explosion and fire prevention
46
(1). Fire due to electricity overload
To avoid electricity overload, the following measures will be applied:
- When designing it must be selected the conductivity wires with cross-section,
that is suitable with the electric current;
- Do not use the equipment with capacity higher that the design capacity;
- Regularly check the temperature of machinery and equipment to avoid the fire
due to overheating;
- Replace leaky piece of wire, which can cause electric shock;
- Installation of automatic power off when electrical power is overloaded;
- Strictly follow the electricity safety regulation.
(1). Fire Prevention by lightning
- Design and installation of lightning rod system for Ong Keo Industrial Zones
with column densities specified by the relevant standards.
- Enterprises in the Industrial Zone have to install lightning protection systems
for their facilities.
1.2.8.2. Leakage of sewer pipelines
- Regulate the safe isolation distance for the water and sewer pipelines;
- Regularly inspect and maintain the joints, valves on the water and sewer
pipelines;
- Prohibit construction of works in the safe isolation area for the water and sewer
pipeline;
1.2.8.3. The problem with the central waste water treatment plant
(1). Prevention
- Use materials with high strength and corrosion resistance;
- Regularly monitor the wastewater quality at the outlet of the wastewater
treatment plant to avoid the serious environmental pollution;
- Make the regular maintenance plan for equipment and machinery.
- Prepare spare parts, spare equipment to proactively and quickly overcome when
the incident occurred
(1). Incidents Rescue
- Build incident scenarios and response plans.
47
- Make the regular plan for checking and repairing the machinery and equipment.
- Build the balance tank to regulate the flow and effluent concentration before
pumping the wastewater treatment system.
- Build the ecological pond to store wastewater when the incident occurred on the
central wastewater treatment systems.
1.2.8.4. Survey of chemical leakage and safe exposure to chemicals
- The chemicals are transported to the wastewater treatment plant with special
facilities provided by the supplier;
- Chemicals are stored appropriately in the warehouse;
- Strictly follow the regulations on storage and use of the chemicals in
accordance to the manufacturer's instructions;
- All workers involved in the chemical industry are guiding safety measures
when exposed to the chemicals;
- When working with chemicals, workers should wear the personal safety
equipment such as masks, glasses, gloves etc.
1.2.8.5. Problem of the Treatment System
(1). Preparation
- The Team Leader must assign personnel to correctly follow the maintenance
schedule;
- The operators must prepare instruments for such repair;
- The Team Leader shall make the list of organizations to readily maintain or
repair the system.
(2). Response
- Any operator/or anyone in the treatment plant discovers any problem (of
the equipment,
- Components of the treatment system, etc), it is required to immediately notify
the person in 21 charge of repairs. The manager in warranty period is
responsible for contact to the warranty institutes.
- If the Company’s technicians are unable to restore the incident, the Chief is
entitled to instruct and contact to the repair and warranty organizations. It is no
more than 6 hours since the system is defected.
Notes:
48
- The Team Leader shall evaluate the results of all practice cases and
require actions for learning experience.
- After each troubleshoot, the individual/organizational facilitators must
ensure to restore it comprehensively to cause no impact on the environment.
1.3. TOTAL INVESTMENT BUDGET AND IMPLEMENTATION PLAN OF
COMPONENT NO 2
1.3.1. Investment budgets
The investment budget of the project is a part of investment budget of infrastructure
construction of Ong Keo Industrial Zone, which has been calculated in the project of
Ong Keo Industrial Zone Investment and loan form the environmental protection
funds. Total investment of the project is presented in Table 1.6.
Table 1.8. Estimated total investment of the project
No. Contents Price
(VNĐ)
1 The cost of construction, equipment
28,549,850.000
2 Other costs (training, operating manuals, test,
test, ...)
227,850,000
3 Design Costs
479,600,000
TOTAL (INCLUDE VAT) 29,257,300,000
In words: Twenty-nine billion, two hundred and fifty-seven million, three hundred
thousand VND.
1.3.2. The Project Implementation Plan
Time of this project follow:
- June, 2011: Completion of the legal documents;
- July, 2011: Construction works;
- May, 2012: Completion construction of building cluster treatment tank;
- June, 2012: Installation pipe Technology;
- July, 2012 to September, 2015: Compensation and construction of wastewater
collection line;
- Octorber, 2015: Complete installation of technological equipment;
- November, 2015: Construction and complete electrical dynamics and automatic
control;
- December, 2015: Commissioning, technology transfer and liquidation.
49
CHƯƠNG 2 NATURAL, ENVIRONMENTAL AND SOCIO-ECONOMIC
CONDITIONS
2.1. PHYSICAL CONDITIONS
2.1.1. Geographical conditions
2.1.1.1. Terrain
According to measurement data, topographic survey of Tin Nghia Company Limited
(2007), Ong Keo industrial zone located between Tuy ha the hilly area, Nha Be River,
Long Tau river, terrain inning every year, the average elevation from +1.0 m to + 1.4
m and lower toward the Ong Keo canal elevation only from + 0.6m to + 0,08m. Along
Ong Keo canal is the end, ground is lower.
In the project area, the system of canals divided into small square with common area
from 5 - 50 hectares, little cell area of 100 hectares.
In general, the entire surface is lower than arising tides and falling tide.
2.1.1.2. Geology
According to measured data, geological surveys of Tin Nghia Co., Ltd. (2007), the
project area is located on the floor young alluvial origin of Quaternary sea river. This
is organic clay sludge on the weak cover with thickness ranging from 6.5 - 20 m.
Geological structure of the area consists of 2 floors:
- Pleitocen Floor: Distribution in altitude from (-10) m – (-17) m or less
including of layers: clay, clay Asia, clay tightly structured, with high bearing
capacity often 10 và C>T/n.c;
- Holocene Floor: weak upper layer consists of organic clay, Asia clay, sandy
loam flexible, soft flowing, natural baby density, high porosity, low bearing
capacity.
Overall, the stratigraphy of the project area is similar sedimentary Mekong Delta.
2.1.2. Hydrological Conditions
Wastewater after treatment of WWTP Ong Keo IZ will discharge to Bang cannal and
then into Long Tau River. Length of Bang cannal is 1.6 kilometter ang width of 5-6 m.
Distance location discharge from Bang cannal to Long Tau River about 450 m. Long
Tau River connect Nha Be river flowing through 2 district is Can Gio of Ho Chi Minh
City and Nhon Trach District of Dong Nai province and into the South China Sea. The
length of the river is about 45 km, the average width 500-600 m, average depth of 10-
12 m. Discharge of Long Tau river presents in the following table:
50
Table 2.1. Discharge average of Long Tau river
Section
8 9 Average
Discharge flood season (m3/s) 1017,3 1055,5 1036,4
Discharge dry season (m3/s) 211,1 292,9 252
Source: "Research Report changes in hydraulic regime of the Long Tau River and Nha
Be river due to excavate Phuoc Hiep canal by using numerical modeling"; Le Song
Giang, Nguyen Thi Phuong; Journal of Science & Technology of the Technical
University No.74, 2009.
According to the field survey, the surface water source of Long Tau River and Bang
cannal affected by alum should be used for purposes domestic water.
2.1.3. Climate
The project area is located in the areas affected by climate of Nhon Trach district,
Dong Nai province. This area has a moderate climate conditions, fluctuations between
the times of year, the day is not high, the humidity is not too high, not directly affected
by the floods. The basic parameters are presented as follows:
2.1.3.1. The air temperature
Air temperature directly affect the metabolism and dispersion of pollutants in the
atmosphere. The higher air temperature, the more rapid rate of chemical reactions
occurred and the small duration of pollutants persisted. The variation of the
temperature affects the spread of dust and gas, the heat exchange process of the body
and health workers. Air temperatures is high and relatively stable throughout the year.
- Average annual temperature: 26.0 ° C
- The highest average temperature of 36 - 38oC
- Average lowest temperature year: 9 - 11oC
- Temperature range is reached during the dry season: 5 - 12oC
- Temperature range is reached during the rainy season: 5.5 - 8oC
2.1.3.2. Solar radiation
Solar radiation is one of the important factors that directly affect the thermal regime in
the region and thereby affect atmospheric stability level and distribution process, the
transformation of pollutants. Solar radiation will directly alter the temperature of an
object, which depends on the ability to reflect and absorb its radiation as coating
surface, paint, surface properties etc.:
- Average sunshine duration from 2000-2200 hours/year;
- Every day is 10-13 hours of sunlight (the dry season);
51
- The intensity of illumination at noon may be up to 100,000 lux.
2.1.3.3. Hours of sunshine
Total sunshine hours are changed from 2000-2700 hours/year. The dry season is also
the sunshine season, which accounts for 56-66% of the total annual hours of sunshine.
The highest average sunshine reachs 9.5 hours/day, the lowest one is 4 hours/day. In
dry season, sunlight may reach to 10-12 hours /day, while the rainy season, there may
be no sunshine in whole day.
2.1.3.4. Air humidity
Air humidity as well as air temperature is one of the natural elements, which directly
affect the metabolism and distribution of pollutants in the atmosphere, the heat
exchange process of the body and health of workers:
- Average annual humidity: 78% - 84%
- Highest annual humidity: 90% - 92%
- Lowest annual humidity: 72% - 76%
2.1.3.5. Evaporation
- The highest monthly average evaporation: 100-250 mm
- The lowest monthly average evaporation: 40-70 mm
- Average annual evaporation: 1,100 mm - 1,300 mm
2.1.3.6. The rainfall regime
The rainfall regime affect air quality. When dropping, the rain washs the dust and
pollutants in the atmosphere as well as the pollutants on the ground where rainwater
falls through. Stormwater quality depends on the quality of the atmosphere and
environment in the region:
- The average rainfall in the district was 1,800 mm. Rainfall is high, but unevenly
distributed in the month of the year;
- The rainy season lasts about six months from May to November, accounting for
87-88% of the annual rainfall. The wettest months are August, September,
October. The wettest month averagely can reach 300 - 400 mm /month;
- In the remaining months of the year, the rainfall is very low, which called dry
season, total rainfall in the dry season (November to May of the next year)
accounts for 12-13% of the annual rainfall. In January and February, there is a
little rain, even in many years, there were no rain.
2.1.3.7. Wind regime
Wind is an important factor in the dispersion and spread of pollutants in the
atmosphere. The greater wind speed, the higher ability to spread dust and pollutants as
far away, the higher ability to dilute pollutants with clean air. Each year there are two
main seasons, dry season have the Northeast monsoon, rain season have the Southwest
52
one. Average annual wind speed is 2.0 to 2.2 m/s, maximum one is 2.5 to 3.0 m/s (9.0
to 11.0 km/h), it is less affected by the storm.
Statistics on wind direction and wind direction frequency of each month at Bien Hoa
meteorological station, recorded by the Southern Hydro-Meteorological Station are
presented as follows:
January
February
0
5
10
15
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
March
0
5
10
15
20
25
30
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
April
0
2
4
6
8
10B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
53
May
0
3
6
9
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
June
0.0
3.0
6.0
9.0
12.0
15.0B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
Junly
0
8
16
24
32
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
August
0
5
10
15
20
25
30
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
September
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
October
0
2
4
6
8
10
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
``
54
November
0
2
4
6
8
10
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
December
0
5
10
15
B
BĐB
ĐB
ĐĐB
Đ
ĐĐN
ĐN
NĐN
N
NTN
TN
TTN
T
TTB
TB
BTB
Figure 2.1. Monthly wind direction and frequency at Bien Hoa station
2.1.3.8. Comment:
(1). Advantages:
- According to the Pasquil classification of atmospheric sustainability, the level
of the atmosphere sustainability in the project area is dominated B and C
classes, in which 75% of the B class or natural conditions in the project area are
favourable for dispersion of gaseous pollutants;
- Thermal regime in the project area is to facilitate the process of biodegradation
of waste.
(1). Difficulties:
- Temperature regime is quietly high and stable in whole year, therefore, that
may affect directly to the liquid fuel tank located in the project area;
- High rainfall will affect the stormwater drainage capacity and industrial
hygiene, if there is the absence of appropriate control measures;
- Application of sludge drying yard for excess sludge from the wastewater
treatment plant of the project will be difficult in the rainy season.
2.1.4. Environmental State
To assess the status of regional environmental quality of the project is expected, the
project owner was associated with the Institute for Environment and Resource to
survey, sample and analyze the environmental quality in the area on May 20, 2013.
2.1.4.1. Current status of air quality and noise
55
Air samples are taken at 3 points in the project area, which are described in the
following table 2.1 and table 2.2.
Table 2.2. Location of sampling air environmental status
Samples Location Samples
K1-OK Area between Cong Thanh cement plant and Lafarge Cement
K2-OK Area between the station wastewater treatment and Proconco projects
K3-OK Vopark Company area and Sanrimjohap area
K4-OK Nhon Trach 1 Power Plant area and PetroVietnam Gas South East
transmission company are.
Table 2.3. Results of air quality analysis
No Samples Noise
dBA
Concentration ( g /m3)
Dust SO2 NO2 CO
1 K1-OK 55-57,3 90 35 41 4800
2 K2-OK 46,3-47,9 110 43 52 5300
3 K3-OK 54,7-56 70 25 36 4400
4 K4-OK 55,9-57,9 120 38 46 4900
QCVN 05:2013/BTNMT - 300 350 200 30000
QCVN 26:2010/BTNMT 70 - - -
Note:
- QCVN 05: 2013/BTNMT - National Technical Regulation on ambient air quality;
- QCVN: 2010/BTNMT - National technical regulation on noise
Comment:
- Dust pollution: dust concentrations ranged from 70-120 μg/m3 are lower than
the regulations (<300 μg/m3). The results showed that the dust concentration in
the sampling points meet the regulations QCVN 05:2009/BTNMT;
- Pollution by SO2: SO2 concentrations are ranged from 25 – 43μg/m3. The
analytical results at all monitoring locations within the project area shown that
SO2 concentrations are lower than the regulations many times;
- NO2 pollution: NO2 concentrations are ranged from 36 – 52 µg /m3, which are
lower than the regulations;
- Noise: Noise in the measured locations is ranged from 46.3-57.9 dBA, which
was lower than the regulation.
According to analysis results, ambient air around the proposed project is not polluted.
The process of building infrastructure will impact on the air quality, investor will
interest to control and manage the air quality in the project implementation process.
2.1.4.2. Current of surface water quality
56
While the project is put into operation, wastewater will be discharged into the Long
Tau river. The analysis result of surface water quality in the project area is presented in
Table 2.4:
Table 2.4. Results of water quality analysis
No Indicator Unit
Sample QCVN
08:2008/BTNMT
column B2 NM1 NM2 NM3
1 pH - 6,15 6,32 6,3 5,5 – 9
2 TSS mg/l 142 384 166 100
3 DO mg/l 6,5 6,6 6,3 ≥ 2
4 BOD5 mgO2/l 47 17 7,2 25
5 COD mgO2/l 211 64 31 50
6 N-NO2- mg/l 0,14 0,7 0,16 0,05
7 N-NO3- mg/l 0,3 0,51 0,22 15
8 Amonia mg/l 0,3 0,3 0,6 1
9 Mineral
oil mg/l 1,8 2,1 1,1 0,3
10 Xyanua mg/l KPH KPH KPH 0,02
11 Florua mg/l 0,325 0,75 0,25 2
12 Pb mg/l 0,006 KPH 0,002 0.05
13 Fe mg/l 1,95 0,14 0,61 1
14 Phenol mg/l KPH KPH KPH 0,02
15 Coliform MPN/100ml 460 7 2.1 10000
16 E.coli MPN/100ml 230 260 290 200
Samples positions is follow table 2.5.
Table 2.5. The location samples water quality
No. Sample Location samples
1 NM1 Surface water of the confluence beetwen Long Tau River and
Dong Tranh river
2 NM2 Surface water Long Tau River
3 NM3 Surface water Dong Tranh River
Comment: Comparing the analysis results with QCVN 08:2008/BTNMT Column B2,
except for BOD, COD, Photphat, Phenol which are violated the QCVN
08:2008/BTNMT.
2.2. BIOLOGICAL CONDITIONS
2.2.1. Mangroves
Long Thanh - Nhon Trach mangrove ecosystem has a total natural area about 18,000
ha. This ecosystem is affected by sea water intrusion and salinity of the river was
57
pushed to create a dynamic area - abundant vegetation. In the mangrove areas have
different kinds of trees such as: Avicennia, Rhizophora, shortening, parrots, and
evolved further, when the population decreased salinity coconut water instead. Deep
inland, where land is sour, with the categories: energy, buying growth. The land is less
acidic than the grower, palm, holly, roasted appearance. There is very rich flora, 84
species of vascular plants with 72 genera, 38 families of Magnoliophyta 2 and
Polypodiophyta branch.
There are not only plants but also animals and equally diverse aquatic species.
Through the survey, the presence of more than 20 species of mammals, over 100
species of birds, 30 reptiles and 9 amphibians has been identified. Regarding fisheries,
there are 3 main groups. The first group includes 36 species of mollusks (including 25
species of gastropods, 1 and 2 species of mollusc’s shells), which present some
economic value species such as shrimp, crabs ...). The most abundant group of animals
here is fish: there are 137 species, belonging to 39 families and 13 orders. These are
very specific species of mangrove ecoregions in coastal estuaries. Some fish is very
valuable economically as we know it: pineapple fish, mullet, fish floral, black grouper
etc.
2.2.2. Phytoplankton and zooplankton
2.2.2.1. Phytoplankton
The analytical results of phytoplankton composition recorded shown that there are 75
taxa of 04 phylum: Bacillariophyta (diatoms) Cyanophyta (algae phylum),
Chlorophyta (green algae phylum), Euglenophyta (eyes algae phylum).
Table 2.6. Phytoplankton composition in the surface water sampling locations
No Species composition
Frequency meeting and
individual /m3
M1 M2 M3
Bacillariophyta
1 Bidulphia sp. +
2 Caloneis sp. + +
3 Cocconeis sp. + +
4 Cyclotella comta + + +
5 Cyclotella sp. +
6 Cymbella sp. +
7 Cymbella tumida +
8 Eunotia asterionelloides +
9 Eunotia sp1. + + +
10 Eunotia sp2. + +
11 Demogonium guyanense +
12 Diatoma elongatum + +
13 Fragillaria sp. + + +
14 Gomphonema sphaerophorum + +
58
No Species composition
Frequency meeting and
individual /m3
M1 M2 M3
15 Gyrosigma attenatum + +
16 Melosira granulata var. Angustissma + +
17 Melosira sp. +
18 Navicula dicephala +
19 Navicula grevilleii +
20 Navicula sp1. + +
21 Navicula sp2. + +
22 Nitzschia closterium +
23 Nitzschia sp1. +
24 Nitzschia sp2. + +
25 Pinnularia sp. + +
26 Surirella linearis + +
27 Surirella ovata +
28 Surirella robusta +
29 Surirella sp. +
30 Synedra acus +
31 Triceratium sp. + +
Chlorophyta
32 Actinastrum sp. + +
33 Closterium cornu + +
34 Closterium lunula + +
35 Coelastrum cambricum +
36 Coelastrum microsporum +
37 Coenocystis sp. +
38 Cosmarium sp1. +
39 Cosmarium obtusatum +
40 Crucigenia sp. +
41 Dictyosphaerium sp. +
42 Gonium sp. +
43 Oocystis sp. +
44 Pediastrum boryanum +
45 Pediastrum duplex + +
46 Pediastrum simplex +
47 Pediastrum tetras + + +
48 Senedesmus acuminatus +
49 Senedesmus bicaudatus +
50 Senedesmus bijuga +
51 Senedesmus denticulatus +
52 Senedesmus protuberans + +
53 Senedesmus quadricauda + +
54 Staurastrum sp. + +
55 Tetraedron regulare + +
Cyanophyta
59
No Species composition
Frequency meeting and
individual /m3
M1 M2 M3
56 Aphanocapsa sp. + +
57 Aphanothece sp. +
58 Lyngbya sp. + +
59 Merismopedia minima + +
60 Microcystis aeruginosa +
61 Microcystis wesenbergii +
62 Oscillatoria sp. + + +
63 Oscillatoria sp2. + +
64 Spirulina sp. + +
Euglenophyta
65 Euglena acus +
66 Euglena oxyuris + +
67 Gonyostomum sp. +
68 Lepocinclis fusiformis + +
69 Lepocinclis sp. + +
70 Phacus anocoelus + +
71 Phacus helicoides +
72 Phacus longicauda +
73 Phacus platalea +
74 Trachelomonas oblonga +
75 Trachelomonas sp. +
In particular, the number of phylum with the dominant species is Bacillariophyta (31
species), Chlorophyta (24 species). The recorded algae species are freshwater ones,
which grow well in water flowing environment with relatively organic rich.
Results of quantitative analysis of phytoplankton density, percentage distribution is
presented in Tables 2.7-2.8.
Table 2.7. Composition and distribution of phytoplankton density in the surface water
sampling locations
No
Phylum
Sample
The density of individuals (unit/litter)
M1 M2 M3
1 Bacillariophyta 4.130 1.855 1.515
2 Chlorophyta 16.235 535 240
3 Cyanophyta 48.750 635 5.375
4 Euglenophyta 210 3.600 0
Total 69.325 6.625 7.130
Table 2.8. Composition and percentage distribution of phytoplankton in the surface
water sampling locations
60
No
Phylum
Sample
The density of individuals (%)
M1 M2 M3
1 Bacillariophyta 0,60 28,00 21,25
2 Chlorophyta 23,42 8,08 3,37
3 Cyanophyta 70,32 9,58 75,38
4 Euglenophyta 5,66 54,34 0,00
Total 100 100 100
Results of biological quantitative analysis shown that density fluctuations between the
sampling locations are relatively large from 6,625-69,325 individuals/liter. The density
distribution is quite clear difference between the point M1 (69,325 individuals/litter)
and the location M2 (6,625 individuals/litter). In particular, in the location M1,phylum
Bacillariophyta is diversed in number of species (27/69 species) but the percentage
distribution is lowest comparing with the present phylum in the water basin
(equivalent to 0.60% of total number of individuals recorded at locations M1). At the
same time, the distribution and species composition of phytoplankton at the time of the
survey is influenced mainly from inland freshwater resources with strong currents and
high turbidity.
Number of species present in the locations M1, M2, M3 is ranged from 16-69 species,
showing the diversity of species composition in the study area is relatively high. And
water in the survey watershed is essentially fresh one.
2.2.2.2. Zooplankton
Through surveys at 03 sampling points (M1, M2, M3) in the water basins in Nhon
Trach District, Dong Nai Province it is recorded in the zooplankton composition as
presented in table 2.9.
Table 2.9. Zooplankton composition in the surface water sampling locations
No Species composition
Frequency meeting and
individual /m3
M1 M2 M3
Phylum: Aschelminthes
Class: Monogononta
Order: Ploima
Family: Brachionidae
1 Anuraeopsis fissa Gosse + + +
2 Brachionus angularis Gosse +
3 Brachionus calyciflorus Pallas +
4 Brachionus caudatus Asstein +
5 Brachionus dimidiatus + +
6 Brachionus falcatus Zacharias +
7 Brachionus sp1. +
61
No Species composition
Frequency meeting and
individual /m3
M1 M2 M3
8 Brachionus sp2. +
9 Brachionus sp3. +
Family : Trichocercidae
10 Trichocerca longiseta Scharank + +
11 Trichocerca pusilla Jennings + +
Family : Gastropidae
12 Ascomorpha saltans Bartsch +
Family : Notommatidae
13 Cephalodella misgurnus Wulfert +
Family : Lecanidae
14 Lecane plesia Myers +
15 Lecane ploenensis Voight +
16 Lecane sp. + + +
17 Lecane subtilis Harr. u. Myers +
Family : Colurellidae
18 Lepadella rhomboideas Gosse +
19 Lepadella sp. + +
Family : Synchaetidae
20 Polyarthra sp. + +
Order : Flosculariaceae
Family : Testudinellidae
21 Pompholyx complanata Gosse +
22 Testudinella patina +
Family: (?)
23 Vanoyella globosa Evens + +
Class: Bdelloidae
Order : Bdelloida
Family : Habrotrochidae
24 Habrotrocha sp. +
Branch : Sarcomastigophora
Class: Lobosea
Order: Arcellinida
Family : Diffugiidae
25 Cucurbitella sp. +
26 Difflugia acuminata +
27 Difflugia lebes +
Order : Tintinnida
Family : Codonellidae
28 Tintinnopsis conecus Chiang +
29 Tintinnopsis cylindrata +
30 Tintinnopsis lobiancoi +
31 Tintinnopsis sp. +
Class: Filosea
62
No Species composition
Frequency meeting and
individual /m3
M1 M2 M3
Order: Gromiida
Family : Euglyphidae
32 Euglypha tubercula +
Larva
33 Chironomidae diptera +
34 Nauplius copepoda + +
Note:
(?): Uncompleted properties
+: There is the presence of individuals
The analytical results shown that there were 34 species of the zooplankton recorded,
which belong to 02 phylums Aschelmia (Rotatoria), and Sarcomastigophora
(Protozoa), 04 classes, 06 orders, 13 families, 16 genuses. In particular, the species are
distributed as follows:
- Phylum Aschelminthes : 24 species, accounting for 77.42%;
- Phylum Sarcomastigophora: 7 species accounted for 22.58%.
In addition, the analysis also noted the presence of two species of copepod larvae and
Chironnomidae dipteral Nauplius. In particular, Chironomus larva (red mosquito
larvae of family Chironomidae – two wings insect of Order Diptera) appears only in
the location NM1. The species are indicators for the environment with nutrient-rich
and medium pollution (mesosaprobic).
The distribution of the dominant phylum Aschelminthes is accounting for 77.42%,
showed that the water is completely fresh with high concentration of organic matter
(Hermann, 1997). In particular, in terms of distribution and development of the
number of zooplankton, can see the indicator species for medium pollution water (-
mesosaprobic) such as Polyarthra sp., Brachionus calyciflonus and some species are
indicators of α-mesosaprobic pollution water such as Brachionus angularis in the
location M3 , Habrotrocha sp. in location M2.
Table 2.10. Composition and distribution of zooplankton density in the surface water
sampling locations
No Phylum
Sample
The density of individuals (unit/m3)
M1 M2 M3
1 Aschelminthes 4,500 18,500 15,000
2 Protozoa 5,000 500 2,500
3 Lavar 500 1,500 1,500
Total 10,000 20,500 19,000
63
Table 2.11. Composition and distribution of zooplankton proportion in the surface
water sampling locations
No
Phylum
Sample
The density of individuals (%)
M1 M2 M3
1 Aschelminthes 45.00 90.24 78.95
2 Protozoa 50,00 2.44 13.16
3 Lavar 0.50 7.32 7.89
Total 100 100 100
Results of biological quantitative analysis shown that density fluctuations between the
sampling points are relatively large from 10,000-20,500 individuals/m3. The density
distribution is quite clear difference between point M1 (10,000 individuals/m3) and
point M2 (20,500 individual/m3). In particular, in point M2, ratio of phylum
Aschelminthes is very high (equivalent to 90.24% of total number of recorded
individuals), showed that the water body at the survey time mainly influenced from
inland freshwater with strong currents and high turbidity.
Number of existing species in the locations M1, M2, M3 is ranged from 11-17 species,
showing the diversity of species composition in the study area is relatively low.
Protozoa density in the location M1 is relatively high (50%), shown that in this
watershed have higher nutrients than the other locations - where the presence of the
species of class Protozoa preferred in the sand bottom, strong flowing water.
2.2.3. Benthos
The results of analysis of benthos composition and density are shown in the tables
2.12, 2.13.
Table 2.12. Results of benthos analysis
No The scientific name The number of individuals counted
LT1 LT2 LT3
OLIGOCHAETA
1 Limnodrilus hoffmeisteri 5 12
2 Branchiura sowerbyi 3 7
POLYCHAETA
3 Namalycastis abiuma 4
4 Nephthys polybranchia 6
GASTROPODA
Viviparidae
5 Cipangopaludina leeythoides 2 2
Thiaridae
6 Melanoides tuberculatus 2
PALAEMONIDAE
7 Macrobrachium vienamense 2
64
No The scientific name The number of individuals counted
LT1 LT2 LT3
INSECTA LARVA
8 Tanytarsus sp1 7
Lymnogonus fossarum 3
9 Polypedilum sp 4
ODONATA
Libellulidae
10 Neurothemis fulvia 1
Conagrionidae
11 Coenagrionid cerinorubellum 2 1
12 Coenagrionid sp 2
Total 16 17 32
Table 2.13. Results of benthos composition and density analysis
No The scientific name Individual density (unit/m3)
LT1 LT2 LT3
OLIGOCHAETA
1 Limnodrilus hoffmeisteri 50 120
2 Branchiura sowerbyi 30 70
POLYCHAETA
3 Namalycastis abiuma 40
4 Nephthys polybranchia 60
GASTROPODA
Viviparidae
5 Cipangopaludina leeythoides 20 20
Thiaridae
6 Melanoides tuberculatus 20
PALAEMONIDAE
7 Macrobrachium vienamense 20
INSECTA LARVA
8 Tanytarsus sp1 70
Lymnogonus fossarum 30
9 Polypedilum sp 40
ODONATA
Libellulidae
10 Neurothemis fulvia 10
Conagrionidae
11 Coenagrionid cerinorubellum 20 10
12 Coenagrionid sp 20
Total 160 170 320
Comment:
65
The sample collection and analysis of benthic samples in water bodies in the project
showed that the diversity of benthic species composition is relatively low. With 13
species, including 04 species of worms, 03 species of dragonflies, 02 species of snails,
01 species of shrimp larvae and 03 species of other insects but the density is relatively
low with quantities of 160-320 individuals/m3. By analyzing the species composition
and density we found that, in sampling location LT2 with the presence of most species
are insect larvae (Coenagrionid, Coenagrionid cerinorubellum, Neurothemis Fulvia,
Lymnogonus fossarum, Polypedilum sp, Tanytarsus sp), which show relatively good
water quality. And in the remaining two locations LT1 and LT3 we see the presence of
species such as Limnodrilus hoffmeisteri, Branchiura sowerbyi, Nephthys
polybranchia, Namalycastis abiuma, which representing the species living in
contaminated water with high organic concentration. Therefore, measures should be
taken to reduce pollution to avoid a threat to the diversity of the fauna in the waters
here. Especially the use of plant protection chemicals, sewage and other domestic
wastes as well as the wastewaters from farmer’s households living around the project
area. However, it should be implemented a more intensive study of the fauna in the
locations near to the project to have a solid legal basis for future comparation of the
environmental degradation.
2.3. SOCIO-ECONOMIC CONDITIONS
As of June, 2013 the population of Phuoc Khanh commune is 13,270 people.
According to a report on the resolution implementation of the People's Council on
Social, Economic and Defense Security Indicators in the year of 2013, the socio-
economic situation of Phuoc Khanh commune as follows:
2.3.1. The Economic Development
Phuoc Khanh Commune is the area with large agricultural land, undeveloped
infrastructure. Agricultural and livestock production are main economic sectors with
average income per capita is 29 million/year (according to survey data for the new
rural construction). The commune budget revenue is as follows:
- Total commune budget revenue: 4,171,994,274 VND/ 3,589,000,000 VND
reached 112,5%;
- Total expenses budget: 4,119,577,332 VND/ 3,589,000,000 VND reached
115% .
According to report on the socio-economic situation in 2013 year of the People
Committee of Phuoc Khanh commune, the socio-economic situation status of the
commune is as follows:
2.3.1.1. Agriculture
The total planted area of 1,328 ha, including:
(1). Sugarcane
66
Sugarcane: 1,165ha/1,035ha, reaching 112.56% of the plan:
(2). Perennial crops:
- Now in the commune there is 142 ha of perennial crops of all kinds including
90 hectares of fruit trees and 52 hectares of forest.
- In 2013 due to erratic weather conditions, the first rain of the season early occur
in the flowering period, therefore, the cashew trees is infected with a lot of
diseases, which led to high yield losses of approximately 65% with unstable
prices, that affect to the producers. The area of fruit trees is generally stable.
(3). Forestry
Currently, the total forest area in the commune is 52 ha. In 2013, local authority well
implement the fire fighting measures, therefore, there was not any forest fire case
happened.
(4). Livestock
Currently the local livestock sector is gradually shifting to big scaled farms with a total
herd of 5,705 cows pigs, 15,300 chickens. Number of poultry, cattle herds were
basically managed to prevent the disease. In 2008 there was no unusual infection
disease occurred. However, the livestock branch has many complicated changes,
therefore, the income of producers is only stable. In the middle of the third quarter to
date, the prices of output products suddenly declined, while prices of input foods are
only gradually reduced, therefore, many farmers, especially pig farmers have capital
losses and meet a lot of financial difficulties.
2.3.1.2. The industry - services - commercial – handicraft branches
(1). Industry branch:
In general, the industrial development in the commune is relatively stable. At the
present Ong Keo Industrial Zone and a number of industrial enterprises located outside
IZ are being stably operated.
(2). The service – commercial branch:
Situation of services - commercial branch development is relatively stable, the number
of households operating in this branch is 384, including mainly accommodation for
rent, catering, refreshments.
2.3.2. The Social Development
2.3.2.1. Culture- Information - Sports
(1). Culture- Information
67
The authority of Phuoc Khanh commune have coordinated with the Department of
Culture, Sport and Tourism of Dong Nai province to organize cultural nights, public
holidays, widescreen movies for serving the people and workers.
The commune have participated in the contest organized by the district and joined the
Culture - Arts – Sports exchanges.
(2). Sports
The local authority have organized the traditional games, and participated in the Phu
Dong district’s health festival; organized friendly football matches between secondary
schools, organized the tradition football championship of Phuoc Khanh commune in
2013.
To maintain regular activities, exercise in the tennis clubs, amateurs forum, nursing
teams, the traditional martial arts classes, karatedo at the Cultural and Sports Center of
the commune.
To coordinate with the related authorities, knowledge dissemination on traffic road
laws, laws on compensation and resettlement support etc.
(3). Health, Population and Family Planning
a). The work of children's health care
To organize to vaccinate for 65 children under 5 years with enough doses, injection of
5 in 1 for 22 children, supplying the Health Insurance Card for 1453 children under 6
years old.
(a). The work of school health:
To organize disease examination and tooth extraction for elementary school students.
(b). The medical examination and patient’s treatment
Commune health station in the year have implemented the medical examination for
11,996 visits. To generally ensure the health care for people, regularly monitor the
diseases and infectious diseases.
(4). Education
- The pre-school, elementary, high schools in the commune are being stably
operated, well participated in specialized movements proposed the education
sector.
- Pre-school: Improving the quality of education in according to the childhood
education programs, improving the quality of nutrition and food safety;
68
- Secondary: The results of the academic year 2012 – 2013 shown that the
number of students passing the graduating from secondary schools is 172/172,
equivalent to 100%;
- Education: maintaining universal education activities for 9 children.
(5). Social affairs
- To support for priority and difficult families, families affected by natural
disasters;
- To make sure the monthly salaries, allowances and gifts to priority families and
objects in the national holidays.
Overall Assessment:
Phuoc Khanh Commune is the area with high agriculture land, undeveloped
infrastructure, big number of working-age people, therefore, it is quite appropriate to
industrial development to promote the local economic development. The socio-
economic situation as presented above is relatively favorable for investment in this
industrial zone development in many ways to contribute to shifting economic structure
and to modernize people's lives, to create for people involving in industrial production
and accessing to advanced modern manufacturing technologies, where enterprises
investing in industrial zones bring benefits for the employees.
2.3.3. Sensitive areas affected by the Wastewater Treatment Project at Ong Keo
Industrial Zone
Water users, which may exposure to waste waters discharging from Ong Keo
Industrial Zone are mainly households living in the upstream and downstream areas
along the Long Tau river.
The people living in upstream and downstream areas located in distance of 3-5 km
from the discharge point can not use the Long Tau river water for domestic purposes
and livestock. Beside that the discharge flow of the CETP is not high (about 3,000
m3/day, equivalent to 0.036 m3/s), waste water will be treated to meet QCVN
40:2011/BTNMT, therefore, the impacts of the treatment plant on the residents living
along the Long Tau river are negligible.
69
CHƯƠNG 3 ANALYSIS OF ALTERNATIVES
3.1. CRITERIA FOR SELECTION OF ALTERNATIVES
- The alternative is to ensure effective wastewater treatment, achieving QCVN
40:2011/BTNMT, column A with Kq = 0.9, Kf = 0.9;
- Location of drainage outlet is to ensure the drainage of the waste water
treatment plant, and to minimize the impacts on the environment and the people
living around the area of the waste water drainage outlet;
- Hazardous waste sludge from the wastewater treatment plant is to ensure proper
handling procedures of hazardous waste treatment, to avoid affecting the
environment.
3.2. SELECTION OF WASTEWATER DISCHARGE LOCATION
The feasibility study report of the construction project of the central wastewater
treatment plant of Ong Keo Industrial Zone- Phase 1 have mentioned about 03
alternative locations for discharging wastewater into water bodies:
Treated wastewater meeting QCVN 40:2011/BTNMT column B will be collected into
the sewers with diameters of 400 – 1000 mm, running along the boundary of the
Industrial Zone. The treated wastewater is discharged into Bang canal, connecting with
Long Tau river.
The proposed wastewater receiving point from the wastewater treatment plant of Ong
Keo IZ is show in figure 3.1.
Figure 3.1. The position wastewater receiving point from the wastewater treatment
plant of Ong Keo Industrial Zone
S1
Bang canal
S2
WWTP
70
Thus, from the above analysis, the treated waste water from the WWTP of Ong Keo
Industrial Zone, Phase 1 will be collected into the sewer system into the Bang canal at
S1 point, then discharged in to Long Tau river at S2 with location coordinates are as
follows:
Table 3.1. The location of the discharge of waste water treatment plants Ong Keo IZ
No. Point Location X Y
1 S1 The location of discharge in to Bang canal 398525.73 1176858.06
2 S2 The location of discharge in to Long Tau river 398122.12 1176578.99
3.3. SELECTION OF WASTEWATER TREATMENT TECHNOLOGY
Before implementing investment project of the wastewater treatment plant of Ong Keo
Industrial Zone, Tin Nghia Corporation have conducted reference and draw from the
experience of the others IZs existing wastewater treatment plants. which are operating
in Dong Nai province (i.e. Bien Hoa IZ, Amatra IZ, Long Thanh IZ, Nhon Trach 3,
...), Ho Chi Minh city (Linh Trung export Processing Zone, Tan Thuan Industrial
Zone), etc. After reviewing the composition and nature of inlet wastewater,
effectiveness of practical wastewater treatment, advantages and disadvantages of each
project and the economic efficiency of the existing WWTPs etc. Tin Nghia
Corporation has decided to select the wastewater treatment technology, that have been
successfully applied in Nhon Trach 3- Model 1 IZ for Ong Keo Industrial Zone. The
selection of the Nhon Trach 3 - Model 1 IZ wastewater treatment technology for Ong
Keo IZ is based on the following reasons:
- Nhon Trach 3 IZ invested by Tin Nghia Corporation is the same investor for
Ong Keo IZ. So it have enough experience and capability to continue Ong Keo
Industrial Zone development;
- Nhon Trach 3 IZ wastewater treatment plant is actually operating one with high
effectiveness of wastewater treatment, which usually meet QCVN
40:2011/BTNMT column A;
- Nhon Trach 3 IZ has similar attracted industries and wastewater composition
comparing with those of Ong Keo Industrial Zone;
- Technology applied in Nhon Trach 3 IZ is common one with simple operation,
saving investment, handling and equipment’s maintenance costs;
- CETP is stably operated to meet the changes in flow and pollutant
concentrations, reliability and longevity;
- Sludge treatment technology is thorough including physico-chemical and
biological treatment, which meet the regulations on solid waste management;
- Treatment plant is automatically controlled by PLC, SCADA to use integrated
controls;
- The system has the ability to connect when expanding capacity, synchronization
with the surrounding landscape;
71
- Less odor emitted from the WWTP into the environment;
- Meeting the requirements on the landuse, natural conditions, as well as
economic conditions.
Technology of Nhon Trach 3 IZ wastewater treatment plant is presented as follows:
3.3.1. The processing steps
- Treatment level 1 (preliminary treatment):
+ Separation mineral oil.
+ Removing garbage, coarse and fine particles.
+ Physico-chemical treatment (coagulation, flocculation).
+ Separation of mineral oil.
- Treatment level 2 (biological treatment): Applying the aerobic activated sludge
technology for removal of suspended organic matter, reduction of BOD, COD
concentrations.
- Treatment level 3: Completing wastewater treatment after biological treatment
with biological pond. Wastewater disinfection.
- Residual sludge treatment: Sludge compression and reduction of moisture
content of the sludge by belt press conveyor.
3.3.2. Flow Diagram of wastewater treatment technology
Flow Diagram of wastewater treatment technology is presented in Figure 3.2.
72
Figure 3.2. Flow diagram of the wastewater treatment technology of Nhon Trach 3 IZ
3.3.3. Description of the technological process
- Wastewaters from the plants in the Industrial Zone will be collected into the
sewer system to manholes of the central waste water treatment plant with a
Lassification -
Handling
Form
Hazardous
WASTE
Pum pit
Fine solid waste screen
Balancing tank
Primary sedimention
tank
Oil separation tank
Coagulation tank
Flocculation tank
Aerotank
Biological
Sedimentation Tank
Seconndary sedimenation tank
Ecological pond
Slugde compression
tank
Dry mud
Sludge compression
tank
Antisept
ics
Air blower
Waste water (3.000 m3/d)
Coarse solid waste
screen
Chemical
Air blower
DRAINAGE SYSTEM IZ
Coarse solid waste: 7 – 10
kg/day
Fine solid waste: 5 kg/day
73
maximum flow of 2,000 m3/day in phase 1. Before entering the pumping
station, wastewater is pumped into the coarse solid waste screening equipment
to remove large size solid wastes from the flow. From pumping station,
wastewater is pumped to the fine solid waste screening devices to remove the
solid wastes with size of greater than 1.5 mm, then flow through the balance
tank. Balance tank is equipped with submersible stirs to regulate composition,
properties of wastewater, to avoid sedimentation and anaerobic treatment
occurred, and also in the tank there is chemical dosing system to neutralize pH
of waste water;
- When the inlet waste waters containing heavy metals or colors concentrations
beyond the design parameters will be led through the physico-chemical
treatment unit, including a coagulation tank, where wastewater, chemical
coagulant are mixed, then the flocculation process happen in the flocculation
tank to form sludge particles. Chemical clarifier will separate the sludge from
the wastewater. The sludge will be led to the sludge compression tank, the
wastewater continues to flow through an oil separator;
- When the inlet waste waters containing heavy metals or colors concentrations
within the design parameters will be led through physico-chemical treatment
unit, but coagulant will not be injected, then wastewater will flow through the
oil separator;
- At the oil separator, oil is separated from wastewater and collected in
wastewater storage tank, that continues to flow to aerobic activated sludge
treatment tank;
- Wastewater from aerobic treatment tank flows through the primary
sedimentation tank to separate activated sludge from wastewater, a part of
activated sludge will be circulated back the aerobic treatment tank to maintain
concentrations and types of microbs, which are suitable for the tank operation,
the excess sludge is pumped through the sludge compression tank. Wastewater
from the secondary sedimentation tank flows to disinfection unit and flow will
be measured, where the wastewaters will be injected by disinfection chemicals
to ensure the microbiological parameters before discharging into the biological
pond;
- Biological pond has buffer function and thoroughly treat wastewater before it is
discharged into the environment.
3.3.4. Wastewater Treatment effect
The Nhon Trach 3 IZ wastewater treatment plant is effective. The results of the
wastewater analysis discharging from Nhon Trach 3 IZ WWTP are presented in tables
74
3.1 and 3.2 and the updated results in September and November 2011 presented in the
following table:
Table 3.1. Results of wastewater quality analysis in the wastewater treatment plant of
Nhon Trach 3 IZ (September 2011).
No Indicator Unit
Results June /2014 QCVN
40:2011/BTNMT
column B
Kq=1.1;Kf=1.0
Before
treatment
(balance
tank)
After
treatment
pH - 6.2 7.2 5.5 – 9
COD mg O2/l 760 ND (LOD=10) 165
BOD5 mg O2/l 330 9 55
TSS mg/l 148 48 110
Color Pt-Co 42 13 165
N-NH4+
mg/l 25.8 ND
(LOD=0.056) 11
Total Nitrogen mg/l 27.3 4.8 44
Total Phosphorus mg/l 9.4 1.72 6.6
CN- mg/l 0.013
ND
(LOD=0.005) 0.11
Cr6+ mg/l
ND
(LOD=0.01)
ND
(LOD=0.01) 0.11
Cr3+ mg/l
ND
(LOD=0.025)
ND
(LOD=0.025) 1.1
Fe mg/l 1,37
ND
(LOD=0.06) 5.5
Zn mg/l 0,19 0.21 3.3
Cu mg/l
ND
(LOD=0.1) 0.18 2.2
As mg/l
ND
(LOD=0,001)
ND
(LOD=0,1) 2.2
Hg mg/l
ND
(LOD=0,001) 0.003 0.011
Pb mg/l 0,036
ND
(LOD=0.001) 0.55
Cd mg/l
ND
(LOD=0,005)
ND
(LOD=0.01) 0.11
Ni mg/l
ND
(LOD=0,06)
ND
(LOD=0,005) 0.55
Mineral oil mg/l 12.6 ND (LOD=3) 11
Vegetable Oil
and Fats mg/l 7.26 ND -
S2- mg/l 2.83 ND 0.55
Cl2 mg/l
ND
(LOD=0.1) 1.85 2.2
75
No Indicator Unit
Results June /2014 QCVN
40:2011/BTNMT
column B
Kq=1.1;Kf=1.0
Before
treatment
(balance
tank)
After
treatment
Organophosphate
pesticides µg/L 0.0073
ND
(LOD=0.001) 1.1
Chlorinated
organic
pesticides
µg/L ND
(LDO=0,0005)
ND
(LOD=0.0005) 0.11
Phenol µg/L 0.08
ND
(LOD=0.01) 0.55
Coliforms MPN/
100mL 3.5x106 < 1,8 5500
Source: The report on environmental monitoring of Nhon Trach 3 Industrial Zone,
Phase 2, 2014.
Table 3.2. Results of wastewater quality analysis in the wastewater treatment plant of
Nhon Trach 3 IZ (September 2014)
No Indicator Unit
Results September/2014 QCVN
40:2011/BTNMT
column B
Kq=1.1;Kf=1.0
Before
treatment
After
treatment
1 pH - 6.69 8.47 5.5 – 9
2 Color Pt-Co 278 13 165
3 BOD5 mg/l 192 18 55
4 COD mg/l 104 39 110
5 TSS mg/l 55 25 165
6 N-NH4 + mg/l 34.2 ND (<0,5) 11
7 Total Nitrogen mg/l 46.2 18.1 44
8 Total
phosphorous
mg/l 8.18 1.58 6,6
9 CN- mg/l ND (<0.005) ND (<0.005) 0.11
10 Cr6+ mg/l ND (<0.01) ND (<0.01) 0.11
11 Cr3+ mg/l 0.024 0.009 1.1
12 Ni mg/l 2.199 0.017 5.5
13 Fe mg/l 0.081 0.619 3.3
14 Zn mg/l 0.098 0.011 2.2
15 Cu mg/l 0.017 0.076 2.2
16 As mg/l ND (<0.004) ND (<0.004) 0.011
17 Hg mg/l 0.167 ND (<0.004) 0.55
18 Pb mg/l ND
(<0.0002)
0.026 0.11
19 Cd mg/l ND (<0.001) ND (<0.0002) 0.55
20 mineral oil mg/l 1.7 ND (<0.01) 11
76
No Indicator Unit
Results September/2014 QCVN
40:2011/BTNMT
column B
Kq=1.1;Kf=1.0
Before
treatment
After
treatment
21 Oil and grease
interviewer
mg/l 3.3 ND (<0.01) -
22 S2- mg/l 2.0 ND (<0.1) 0.55
23 Cl2 mg/l - ND (<0.1) 2.2
24 Organophosphate
pesticides
mg/l ND (<0.1) ND (<0.1) 1.1
25 Chlorinated
organic
pesticides
mg/l ND (<0.1) ND (0.1) 0.11
26 Phenol mg/l 0.052 ND (<0.005) 0.55
27 Coliform MPN/
100mL
43x103 ND (<3) 5500
Source: The report on environmental monitoring of Nhon Trach 3 Industrial Zone,
Phase 2, 2014.
Note:
- Sampling and analysis in June, 2014 implemented by Sonadezi Service
Corporation.
- Sampling and analysis in September, 2014 implemented by the Center for
Environmental Technology and Management.
- QCVN 40:2011/BTNMT - National technical regulation on industrial
wastewater, column B, with Kq = 1.1 (Thi Vai river flow> 200 m3/s) and Kf =
1.0 (Wastewater flow ≤ 2,000 m3/day).
The results of water quality monitoring shown that the indicator parameters of the
outlet waste water of the Nhon Trach 3 wastewater treatment plant are lower than the
allowable limits of QCVN 40:2011/BTNMT.
Thus, the application of the Nhon Trach 3-Module 1 IZ wastewater treatment
technology for Ong Keo IZ is fully consistent with the actual condition and outlet
wastewater will meet the national technical regulation before discharging into the
receiving water body. Wastewater treatment plant of Ong Keo Industrial Zone will
also be studied further improvements to improve the efficiency of wastewater
treatment than to ensure effluent quality standards before reaching receiving water
discharge in a good way most. Specifically, Oil separation tank was moving forward
Balancing tank with the main purpose: To prevent the abrasion of pumping motors in
the successive treatment works; To prevent the strange substance in biological
treatment tank which can cause agglomeration into the solids floating in biological
tank, which leads to less efficient treatment system .
77
3.4. SELECTION OF SLUDGE TREATMENT TECHNOLOGY
Sludge treatment technology generated from the wastewater treatment plant of Ong
Keo Industrial Zone-Phase 1 (Module 1): Excess sludge from the primary and
secondary clarifiers will be pumped to the compressed mud tank periodically, where
sewage sludge is concentrated by gravity sedimentation method, then collected to the
tank bottom by the sediment brusher system. Depending on the concentration of
biomass in the sludge tank that total dissolved solids (TDS) ranging from 2-3% before
being pumped into the sludge dewatering process for separating water from the mud.
Sludge after dewatering in the form of cake will be packaged and stored in a dry mud
warehouse before bringing to sanitary landfills. Wastewater from sludge tank and
excess sludge dewatering will be circulated to the pump pit for reprocessing.
The project owner will sign contracts with Tai Tien Co., Ltd, Sao Viet Joint Stock
Environment Company, for collecting and handling whole sludge in accordance with
the provisions of the current law.
Hazardous waste treatment technologies of the mentioned above companies has been
licensed by the Vietnam Environment Administration within Ministry of Natural
Resources and Environment.
Hazardous sludge generated from the CETP operation will be treated by one of two
companies with full compliance regulation.
3.4.1. Option 1: Treatment at Tai Tien Waste Treatment Plant
3.4.1.1. The capacity of Tai Tien for sludge disposal of CETP Ong Keo IZ
- Incinerators dedicated capacity 3,600 kg/day;
- Hazardous waste incinerator capacity 36,000 kg/day;
- The system unfired brick production capacity of sludge treatment 31,920
kg/hour, capacity pressed brick 2000 tablets/day;
- Landfill area is 5,000 m2.
The capacity of Tai Tien company is capable of handling the amount of sludge
generated from 1.5 to 2 tons/day of Ong Keo IZ CWTP.
3.4.1.2. Sludge transport route
- Sludge transport route: Ong Keo IZ – Pham Thai Buong road – No.51 Highway
- Tai Tien hazardous treatment plant (59 kilometer).
78
Figure 3.3. Exhibit sludge transport route
- Sludge Treatment Technology at Tai Tien Ltd. Co.
+ The dried and dewatered sludge contains hazardous substances will be mixed
with cement, then compressed into blocks to reduce pollution disperse into the
environment. As cement has high alkalinity, the heavy metals will kept under
hydroxide or carbonate salts.
+ The compressing often also often include Ca(OH)2 solution (to increase its
acidity), or coal slag. Coal slag and Ca(OH)2 can stabilize As, Cd, Cr, Cu, Fe,
Pb, Mg, Se, Ag, Zn…The blocks will then be landfilled under required
standard inside the treatment plant border, rather than hand it to third party.
Table 3.3. The % of mixing based on mass is as below
Hazardous Wastes Incineration Slag Cement Lime Sand Water
100 20 35 10 100 65
30% 6% 10% 3% 30% 19%
The diagram for solidifying process can be seen as below:
Tài Tiến Co, Ltd
Ong Keo IZ
79
Figure 3.4. Sludge solidifying process
3.4.1.3. Tai Tien landfill site
Tai Tien landfill site is constructed based on design TCXDVN 261:2001 with double
layers and 2 trends to collect landfill leachate.
- Total potential landfill volume: 61,378 m3
- Filled duration: 8 years (if the landfilling rate of hazardous solid wastes is 10
tons/day).
- Actual landfilling rate at this point: 380 kg/day or around 10 tons per months
3.4.2. Option 2: Treatment at Sao Viet Waste Treatment Plant
3.4.2.1. The capacity of Sao Viet company for sludge disposal of Ong Keo IZ CETP
- Sao Viet company have two static incinerator to handle of hazardous waste with
a capacity of 1000 kg/hour;
- The system of concrete, fixed-ash waste.
The capacity of Sao Viet company is capable of handling the amount of sludge
generated from 1.5 to 2 tons/day of Ong Keo IZ CWTP.
3.4.2.2. Sludge Route
Sao Viet waste treatment plant is located inside Toc Tien disposal site with total lengh
road is 56 km.
80
Figure 3.5. Exhibit sludge haulage route to Sao Viet Waste Treatment Plant at Toc
Tien Site
3.4.2.3. Sludge Treatment Technology
Sao Viet applies incinerator for waste treatment, and wet cyclone and absorption tower
for treating flue gas. The treatment process is presented in Figure 8. Its capacity is
1,000 kg/h. Here are some representative parameters for the treatment system:
- Primary combustion: to = 500-600oC;
- Secondary combustion: to = 1,100-1,200oC, t = 4-5s;
- Oxidation/catalyst: enhance the oxidation of CO, CxHy to CO2 and H2O;
- Wet cyclone: reduce dust ≥ 20µm;
Ong Keo IZ
Sao Viet Co, Ltd
81
Waste FeedPrimary
Combustion
Secondary
Combustion
Supplementary
Combustion
Oxidation –
Catalyst
Heat Exchange
Absorption
Tower
Induced Draft
Fan
Stack
Automatic control
system
Oxygen
SupplyAir
Absorption
Solution
Storage Tank
Residues
Figure 3.6. Process sludge treatment technology
82
CHƯƠNG 4 ENVIRONMENTAL IMPACT ASSESSMENT
4.1. IMPACT SOURCES, OBJECTS AND SCALE
The investment in the construction of the waste water treatment plant with capacity of
3,000 m3/day is entirely consistent with the policy of socio-economic development and
environmental protection, which contribute to solving the environmental problems of
the Industrial Zone. However, in addition to the positive impacts, construction and
operation of the project may cause negative impacts on the environment and the socio-
economic development if there are without the mitigation and appropriate treatment
measures. The environmental impact of the project arises primarily in two phases:
- Preparation and construction phase;
- Operation phase.
On that basis, the project’s activities which may cause negative environmental impacts
to natural and socio-economic development can be identified and evaluated as follows:
4.1.1. Construction Phase
4.1.1.1. Impact Sources
(1). Waste related impacts
The project’s activities and waste related impact sources in construction phase are
presented in Table 4.1.
Table 4.1. Sources of waste related environmental impacts in the preparation and
construction phases
No. The activities Impact sources
01 Leveling, worker camp
preparation, road
construction.
- Dust emissions arising from the transport,
machinery and construction equipment.
- Storm water runoff, localized flooding, mud
02 Construction - Dust arising from leveling the ground.
- Solid waste arising from the construction process.
- Stormwater runoff over the entire project area
swept by the soil, rocks, greasy water in the
streams.
03 Active transport
construction materials
such as iron, sand,
bricks, cement, iron,
steel, ...
- Dust emissions from trucks;
- Increasing the density of traffic on the road
transport (road embankment Ong Keo);
- Noise generated by truck
04 Installation of
equipment in process
- Dust, fumes arising from the construction process
with heating: cutting, welding metal etc.
83
No. The activities Impact sources
technology and backend
parts such as electrical
systems, water,
chemical suppliers etc,
- Dust emissions from the transport device.
- Solid waste such as viscous oily rags, chemicals
containers, metal blanks etc.
05 Activity gathering,
storing fuel, raw
materials.
- Dust from unloading construction materials.
- Vapors of gasoline, paint from gasoline, paint
containers.
06 Activities of
construction workers
Wastewater and solid waste generated from activities
of construction workers.
(1). The none-waste related impact sources
The none-waste related impact sources in the preparation and construction phases are
presented in Table 4.3.
Table 4.2. Sources of none-waste related environmental impacts in the preparation and
construction phases
No. Impact Sources
1 Change of land use purposes.
2 Erosion, sedimentation of the Long Tau river at the segment flowing through the
project area.
3 Noise and vibration from construction activities and equipment installation.
4 Residual heat pollution
5 Local flooding
6 Fire incidents, accidents in the construction process.
7 The workers going in and out the project area may cause disturbance of the local
life
(2). Affected objects and scales
Affected objects and scales in the preparation and construction phases are presented in
Table 4.3.
84
Table 4.3. Affected Subjects and Scale in the Construction Phase
No. Activity Affected objects Effected Scales Duration of
impact Level of impact
1
Leveling the
construction area.
Preparing camps,
road construction
- Impact on the ambient air environment ;
- Impact on water: rainwater runoff entrained
dirt, garbage, oil spillage, domestic
wastewater of workers;
- Impact on land environment: Construction
solid waste generation , domestic solid waste
from activities of workers
- Health workers and community around the
project area
The project area
and adjacent,
during
construction of
the project
During
construction
- Inevitably,
insignifica
nt;
- Light,
temporary
2 Transportation of
raw materials
- Air pollution (dust, gases, noise and
vibration).
- Environmental pollution to water: rainwater
runoff entrained dirt, garbage, oil leakage or
spillage of materials;
- Health workers and community around the
project area.
The project area
and the
surrounding
areas and
transport routes.
During
construction
Inevitably,
insignificant
temporary.
3
- Developing the
technical
infrastructure,
including the
treatment tank,
pipeline
systems, power
supply, water
supply and
drainage,
- Air pollution (dust emission).
- Pollution of water: rainwater runoff, domestic
wastewater of construction workers.
- Impact on land environment: Solid waste
generation, solid waste of workers.
- Changing the scenery and beauty of the entire
area
- Health workers and community around the
project area
The project area
and the
surrounding area
during the
construction
process
During
construction
Inevitably,
insignificant
Light, temporary;
85
ancillary works,
...
- Installation of
equipment.
4
Welding, cutting,
painting, metal
spraying
- Air pollution (dust emission).
- Workers health The project area
During project
construction
Inevitably,
insignificant;
Light, temporary
5 Activities of
concrete mixers ...
- Air pollution
- Water pollution: stormwater runoff entrained
dirt, garbage, spilled oil increases the turbidity
of surface water
- Workers health
The project area During project
construction Light, temporary
6 Activities in the
field of workers
- Water pollution
- Soil pollution.
The project area
and surrounding
areas
During project
construction
Inevitably, not
great;
Light, temporary.
7
Cleaning up the
landscaping after
construction
Air pollution The project area During project
construction Light, temporary.
86
4.1.2. Operation Phase
4.1.2.1. Impact sources
(1). Waste related impact sources
During the project’s operation phase, possible waste related impact sources are
presented in Table 4.4.
Table 4.4. Sources of waste related environmental impacts in the operation phase
No. Activity Impact Sources
I Impact on air quality
I.1 Transportation activities ,
transportation of chemicals,
sludge
Odor, gases, dust, chemical fumes leakage.
I.2 Wastewaters - Odor due to fermentation and anaerobic
decomposition of organic matter in the
wastewater treatment process.
- The odor of the sludge from the sludge drying
yards.
II Impact on the water quality
II.1 Wastewaters - Wastewater Treatment Plant.
- Sewage leakages, overflow due to malfunction.
II.2 Activities of the operators. Domestic wastewater of officers and employees
may contain impurities, suspended solids, organic
matter, nutrients and micro-organisms.
II.3 Stormwater runoff Rain water flowing through the project area
swept dirt, garbage spilled into water.
III Solid waste generation
III.1 Wastewaters Garbage, sludge from operating activities of the
central wastewater treatment plant
III.2 Activities of employees Domestic wastes
(2). The none-waste related impact sources
During the project’s operation phase, the non-waste related impact sources are
identified in Table 4.5.
Table 4.5. Sources of none-waste related environmental impacts in the operation
phase
No. Impact Sources
1 Noise, vibration from the sewage pumps, agitators, air blowers.
2 Residual heat from the operation of machinery, equipment of the central
87
wastewater treatment plant
3 Sedimentation of the Long Tau river in the project’s area
(3). Affected objects and scales
Affected objects and scales during the project’s operation are presented in Table 4.6.
Table 4.6. Affected Subjects and Scale in the Operation Phase
No. Affected
objects Affected Scale
Duration of
impact
Level of
impact
1 The air The ambient air in the areas
surrounding the wastewater
treatment plant
During
Operation
Moderate,
long-term
2 Surface water The Long Tau river is the
receiving water after handling
wastewater and stormwater
runoff.
During
Operation
Moderate,
long-term
3 Groundwater The project area and vicinity. During
Operation
Moderate,
long-term
4 Road
infrastructure
Transportation system in the
project area would be degraded
by chemical transport activities
During
Operation
Light, long-
term
5 Employee The entire operation of the
project staff and staff working in
the waste water treatment plant
During
Operation
Moderate,
long-term
6 Households live
two roads
Road routine of vehicle
activities.
During
Operation
Light,
instant
7 Local Residents Around the area of the
wastewater treatment plant
During
Operation
Moderate,
long-term
4.2. ENVIRONMENTAL IMPACT ASSESSMENT
4.2.1. Construction Phase
4.2.1.1. Impact on air environment
The activities and sources impacts during construction and installation of equipment
for the project is presented in Table 4.1 above, the activities caused air pollution are as
follows:
- Dust by ground leveling and project’s construction;
- The dust arising during transportation and loading and unloading of materials:
- Raw materials for construction and installation of waste water treatment plant
(stone, sand, bricks, cement, iron and steel);
88
- Equipment and machinery for the construction and installation of the central
waste water treatment plant.
- Dust, oil vapors arising in the process regrouped, storing fuel, raw materials;
- Coal dust and gases SO2, NO2, CO, THC because the exhaust fumes of vehicles
transporting sand, stones, bricks, cement, steel, equipment, fuel etc., smoke
exhaust devices for construction machinery (concrete mixers, cranes);
- Fuel, spilled materials (sand, stone, cement, oil, paint);
- Radiation from the construction process with heating, welding fumes (such as
the process of cutting, welding steel, cutting, welding equipment for assembly);
These project have impacts on the environment and worker health. In particular, the
impact of dust, vehicle exhaust and noise is shipping three main impacts of the
construction process. These effects will be detailed evaluated as follows:
(1). Impact of ground leveling
The area selected for project’s construction is relatively flat. The total area of waste
water treatment plant is 2,5ha. Thus the soil volume for ground leveling is very little.
Therefore, the effect of ground leveling on the air environment is negligible.
(2). The impact of emissions from the transportation of raw materials and equipment
The transportation of materials and equipment will generate dust and pollutants such
as COx, NOx, SOx, and THC etc. This kind of pollution sources is scattered and
difficult to control.
According to the report "Research on control measures of air pollution in the road
traffic in Ho Chi Minh City "shows the average amount of fuel is consumed for the
vehicles as follows:
- 2 wheel motorcycles : 0.03 liters/km;
- Gasoline cars : 0.15 liters/km;
- Diesel cars : 0.3 liters/km.
The transportation means, which regrouped materials for the construction of technical
infrastructure, equipment installation of the waste water treatment plant are used as oil
fuel and vehicles with payloads of 10 tons/car .
Estimates of total number of vehicles transporting raw materials and equipment going
in and out the project area is about Nt = 5 times/day.
The number of construction workers is about 120 people, all of them are not living in
the field.
Number of motorcycles going in and out the project area is about: Nm = 30 times/day.
The diameter of the area affected by traffic emissions range l = 2 km:
89
- Total number of the vehicles going in and out the project area in 01 day is: N =
(Nt + Nm) = 35 vehicles/day;
- The total distance of trucks travelling in 01 day is Lt = Nt x 2 = 10 km/day;
- The total distance of motorcycles running in 01 day is Lm = Nm x 2 = 60
km/day;
- The total amount of fuel (oil) providing trucks is: Qt = 0.3 (l/km) x 10 (km/day)
= 3 liters/day;
- The total amount of fuel (petrol) providing the motorcycles is: Qm = 0.03
(l/km) 60 (km /day) = 1.8 liters/day;
- The total amount of fuel used is: Q = 4.8 l/day, rounded up to 5 liters/day.
Based on the pollution factors of the World Health Organization (WHO), the daily
average emissions caused by transport activities are presented in Table 4.7.
Table 4.7. Air Pollution Loads and Concentration Caused by the Transportation of
Construction Materials
No. Pollutants
Pollution
coefficient
(kg/liter)
Pollution load
(kg/day)
Concentration
(mg/m3/1h)
QCVN
05:2013/BTNMT
(mg/m3/1h)
01 Dust 0.005 0,025 11.14 0,3
02 SO2 0.00625 0,008 3.57 0,35
03 NO2 0.01 0,05 22.28 0,2
04 CO 0.075 0,375 167.11 30
05 THC 0.01 0,05 22.28 5(*)
Note:
- The total amount of fuel used is: 5 liters/day;
- Sulfur content in oil: 0.25%;
- Save emissions: When the engine is burning 01 kg of fuel, volume of air
emission generated 22 m3;
- Density of DO oil: 1 liter = 0.85 kg diesel oil ;
- The total volume of diesel oil used: 4.25 kg/h;
- Total emissions arising from the transportation of garbage: 93.5 m3;
- QCVN 05:2013/BTNMT - National technical regulation on ambient air quality.
- (*) QCVN 06:2009/BTNMT - National technical regulations on hazardous
substances in the ambient air.
Comment:
Comparing the concentrations of pollutants in the exhaust gas with the ambient air
quality regulations shown that concentrations of all pollutants will exceed the traffic
air emissions regulations. However, the concentration of pollutants in Table 3.4 are
calculated at the point of emission (exhausted pipe of the car). Concentrations of
pollutants in the air will be reduced by the following factors such as the concentration
dilution; respiratory process of trees. On the other hand, the project is located within
90
Ong Keo Industrial Zone away from the nearest residential area approximately 1.2 km
to the north-east. Thus, the level of impact of this pollution source has been reduced.
(3). Impact due to welding operations, cutting, painting, metal spraying
During the construction of the central wastewater treatment plant, welding, cutting,
painting, metal spraying activities occurs frequently. These processes are used the
following devices such as welding, gas welding, the materials (iron, steel, etc.), which
cause the negative impact on the environment.
Toxic welding emissions generated during welding will impact on the surrounding air
quality and impact directly on the health of workers. Most of the toxic emissions
contains heavy metals such as Zn, Cu, Hg, Cr with highly toxicity and very persistent.
Also the materials used in the coating, plating processes such as metal particles,
chemicals, paints, solvents, etc. will emit the vapor, mist, dust, rust, and little of
substance chemical, which also cause negative impacts on the ambient air quality and
health of construction workers.
Due to the effects of the welding process, cutting, painting, metal spraying occurs
frequently in the construction phase, the project owner will adopt measures to
minimize adverse effects, such as arrangement of paint, spraying processes in the
areas with little workers and providing the labor protection devices for construction
workers
(4). Impacts due to staying and living of workers in the field
The number of employees working in the field is around 30 people. The process of the
daily worker’s activities cause the impacts on air quality due to the following reasons:
- Odor (NH3, H2S, mercaptan HS-R) generated from domestic wastewater;
- The gas generated by the decomposition of organic waste;
- The odor emanating from the septic tank, the organic waste.
In general, the level of impact on regional air quality due to activities of workers is
negligible and time of impact is short.
(1). Noise impacts from project construction activities
For the project, the construction activities will cause noise pollution, including:
- Leveling for project’s construction (graders, rollers);
- The construction and installation of the central waste water treatment plant
(concrete mixers, trucks, forklifts);
- Landscape and cleaning (bulldozer, bucket back, spreaders, trucks, forklifts).
91
Noise from construction equipment is generally not continuous, depending on the type
of activities and the machinery and equipment used. The machinery and equipment
used in the construction of the individual are considered as point sources.
Specific noise standards for the machinery and equipment used for traffic works "U.S.
Environmental Protection Agency- Noise from construction equipment and
construction machinery NJID, 300.1, 31 - 12-1971 " are presented in Table 4.8.
Table 4.8. Noice levels from machinery and equipment located in 8 m distance from
the construction area
No. Machinery and equipment Noise level (dBA)
The process of leveling and compaction
1 Bulldozers 80
2 Truck 83 – 94
3 Grabs 72 – 93
4 Scaler 80 – 93
Paving process
1 Paver 86 – 88
2 Truck 83 – 94
3 Compactors 74 – 77
Landscape and cleanup
1 Bulldozers 80
2 reverse Bucket 72 – 93
3 Truck 83 – 94
4 Forklift 72 – 84
The process of digging and transporting soil
1 Bulldozers 80
2 Truck 83 – 94
3 Grabs 72 – 93
4 Scaler 80 – 93
Construction
1 Cranes 75 – 77
2 Welder 71 – 82
3 Concrete mixers 74 – 88
4 concrete Pump 81 – 84
5 Concrete vibrator 76
6 Air Compressors 74 – 87
7 Pneumatic tools 81 – 98
8 Bulldozers 80
9 Truck 83 – 94
10 Forklift 72 – 84
11 Paver 86 – 98
12 Punchers 81 – 98
Source: Environmental Protection Commission U.S.
92
From sources that predicted noise levels and noise levels calculated in the recipients
by the following formula:
n
i
Li.1,010lg10L
- L : Is the total noise level;
- Li: is the noise source i;
- n: the total number of noise sources.
Calculated results of the noise level of the source are presented in Table 4.9.
Table 4.9. Calculated results of noise level (dBA) during the construction phase
No. Activity The noise from the construction site
8m (dBA)
01 Activities of ground breaking 85 – 95
02 Excavating and earth moving
construction 86 – 98
03 Construction of buildings 86 – 93
04 Leveling and road works 87 – 96
05 Sprinkle the road surface and
building 88 – 95
06 Landscape and cleanup 89 – 97
During construction, the sound characteristics of noise sources are usually identified at
an altitude of 1.2 to 1.5 m above the road surface at a range of noise sources from r1
(m) already know, usually 8 m for the noise source. The noise level in the range r2> r1
will reduce the noise level in more than one value is approximately r1 L (dB)
according to the following formula:
)dB(lg20L
a1
1
2
r
r
Among them: a system is affected by the topography of the ground to absorb and
reflect noise, with:
- A = - 0.1 with asphalt and concrete;
- A = 0 for bare ground without vegetation;
- A = 0.1 with grazing land.
Results of noise reduction with distance from the source of noise in construction, in
the case of empty ground, no barriers, presented in Table 4.10.
Table 4.10. Calculated noise levels from construction activities
Description of activities
Source
noise
level
(dBA)
Noise levels decrease with distance
(dBA)
32 m 64 m 128 m 256 m
Activities of ground breaking 85 – 95 79 – 89 73 – 83 67 – 77 61 – 71
Excavating and earth moving 86 – 98 80 – 92 74 – 86 68 – 80 62 – 74
93
Description of activities
Source
noise
level
(dBA)
Noise levels decrease with distance
(dBA)
32 m 64 m 128 m 256 m
construction
Construction of buildings 86 – 93 80 – 87 74 – 81 68 – 75 62 – 69
San dress and road works 87 – 96 81 – 90 75 – 84 69 – 78 63 – 72
Sprinkle the road surface and
building
88 – 95 82 – 89 76 – 83 70 – 77 64 – 71
Landscape and cleanup 89 – 97 83 – 91 77 – 85 71 – 79 65 – 73
In our country there were no specified standards for noise levels for construction work
in general. However, according to standards issued for allowable noise level in the
labor workplaces (According to Decision No 3733/2002/BYT-QD) and the maximum
permissible limit of noise in public and residential areas (QCVN 26:2010/BTNMT),
the maximum allowable noise level is 70 dBA in residential areas, private homes,
motels, administrative agencies and the lowest noise level of 45 dBA at hospitals,
libraries, nursing homes, school from 21 pm to 6 am. Maximum noise levels of the
motor vehicles are presented in Table 4.11.
Table 4.11. Noise level of the motor vehicles
No. Type of vehicle Noise level (dBA) QCVN 26:2010
(from 6h to 21h)
01 Trucks 93
70 (dBA) 02 4-stroke motorcycles 94
03 2- stroke motorcycles 80
According to the results of Table 3.6, the maximum noise level of the trucks (93 dBA)
exceeded the allowable standards for residential areas. However, the project is located
within the Industrial Zone with trees and far away from the nearest residential area of
about 100m to the west. Beside that, the time for the project’s construction is short (06
months) so that the level of noise impacts are assessed to be negligible.
(2). Vibration level in the process construction.
The vibration emission characteristics of equipment used in construction are shown in
Table 4.12. This is the source of vibration generated from the operation of equipment
and machinery for the construction works of the wastewater treatment plant.
Table 4.12. Vibration level of a typical construction machinery
No. Activity
Reference vibration level (dB)
10m away from the sources 30m away from the
sources
01 Dredges 80 71
94
02 Bulldozers 79 69
03 Truck freight service 74 64
04 Wheelchairs 82 71
05 Compressors 81 71
Source: Mackernize, 1985.
According to QCVN 27:2010/BTNMT on the vibration acceleration level, the
regulations on the vibration level for the construction activities in the residential areas,
where there are commercial, manufacturing and services and shall not exceed 75 dB.
(3). Assessment of the air pollution impacts
Impacts of air pollutants are shown in Table 4.13.
Table 4.13. The effects of air pollutants
No. Parameter Impact
01 Dust - Respiratory stimulates, lung sclerotherapy, lung cancer;
- Injury to the skin, cornea, digestive diseases.
02 Acid gases
(SOx, NOx).
- Influencing the respiratory system, blood scattered on;
- SO2 poisoning through skin, reducing blood, alkaline reserve;
- Acid rain adversely affect the growth of vegetation and crops;
- To enhance the corrosion, material degradation of concrete and
buildings;
- Bad influence on climate, ecosystems and the ozone layer.
03 Carbon oxide
(CO)
Reducing ability of blood to transport oxygen organizations cells
due to CO combines with hemoglobin-hemoglobin cacboxy.
04 Carbon dioxide
(CO2)
- Causing pulmonary respiratory disorders;
- Causing the greenhouse effect;
- Impact on ecosystems.
05 Hydrocarbons Induction of acute poisoning: debilitating, dizziness, headache,
senses disturbances sometimes fatal.
4.2.1.2. Impacts on the water quality:
The factors causing water pollution during project construction are:
o Domestic wastewater workers;
o Stormwater runoff over the entire area swept by dust, soil, sand, rock, raw
materials such as cement, oil, paint, etc. dropping down to affect the Lòng Tàu
water quality stream.
(1). Impact of domestic waste water by construction workers:
Impact sources on water quality during project construction is mainly due to domestic
waste water of workers. Composition of the major pollutants in domestic waste water
95
include: The solid residue, suspended solids (SS), organic compounds (BOD/COD),
nutrients (N, P) and pathogens (Coliform, E. Coli), which can lead to contamination of
surface water and groundwater if that is not treated.
Domestic wastewater flow is calculated on the basis of the water demand and the
number of workers. According to the construction standards the norms of living water
is 120 liters/person.day. The level of wastewater generated is 96 liters/person/day
(equivalent to about 80% supplied water).
During the project’s construction daily average number of workers can be estimated
about 30 workers. However worker stay at place, therefore all of the construction
workers are not staying at the site so the water level supplied for the worker’s
activities will be less, the amount of the supplied water is estimated about 60
liters/person.day. Thus, the total flow of waste water generated in the process of the
project’s construction is approximately 1.44 m3.
According to statistical calculations, for the developing countries, the pollution factors
per person daily discharging into the environment (when the waste water is untreated)
are shown in Table 4.14.
Table 4.14. Pollution factors for untreated domestic waste waters
No. Pollutants Pollution Factor
(g/person/day)
01 BOD5 45 – 54
02 COD (dicromate) 72 – 102
03 SS 70 – 145
04 NH3 2,4 – 4,8
05 Total nitrogen (N) 6 – 12
06 Total phosphorus (P) 0,8 – 4,0
Source: Rapid Environmental Assessment, WHO, 1993.
Based on the pollution factors estimated by the rapid assessment method, the pollutant
loads generated from domestic wastewater in the construction phase can be predicted
as in table 4.15.
Table 4.15. Estimated pollution loads generated from untreated waste water in the
construction phase
No. Pollutants Load (g/person/day)
01 BOD5 1,35 – 1,62
02 COD (Dicromate) 2,16 – 3,06
03 SS 2,10 –4,35
04 NH3 0,07 – 0,14
05 Total nitrogen (N) 0,18 – 0,36
06 Total phosphorus (P) 0,02 – 0,12
96
The concentrations of pollutants in the waste water are calculated based on the
pollution load, wastewater discharge flow and effectiveness of 3 compartment septic
tanks (the treatment efficiency is about 55-65%), the results are presented in Table
4.16.
Table 4.16. Concentrations of pollutants in waste waters
No. Pollutants
The concentration of pollutants (mg/l)
Untreated Treatment in
septic tanks
QCVN 14:
2008/BTNMT
(Column B2)
01 BOD5 938 – 1.125 375 – 450 60
02 COD (Dicromate) 1.500 – 2.125 600 – 850 -
03 SS 1.458 – 3.021 583 – 1.208 120
04 NH3 50 - 100 20 – 40 12
05 Total nitrogen (N) 125 - 250 50 – 100 -
06 Total phosphorus (P) 17 - 83 7 – 33 -
Note: QCVN 14: 2008/BTNMT - National technical regulation on domestic
wastewater, column B, with K = 1.2.
Comments: Comparing with the regulations shown that, concentrations of the
untreated waste water or wastewater after septic tank treatment are exceeded pollution
regulations. However, all construction workers will use the temporary latrines or
mobile toilets. Thus, the level of domestic wastewater impacts caused by construction
workers is minimized to the lowest level.
(1). Impacts arising from waste water cleaning processes, machinery maintenance
The process of cleaning and maintenance of machinery and equipment in the
construction area will generate a certain amount of wastewater containing organic
matter, suspended solids and oil. Volume and loads of pollutants at each stages are
shown in Table 4.17.
Table 4.17. Pollution concentrations of waste waters arising from the process of
cleaning and maintenance of machinery and equipment in the construction phase
Process arising
Flow
(m3/day)
The pollution concentrations (mg/l)
COD oil and
grease SS
Maintenance of
machinery
1 20 - 30 - 50 - 80
Cleaning machines 50 - 80 1,0 - 2,0 150 - 200
QCVN 40:2011/BTNMT 100 5 100
Source: ENTEC, 2012.
97
Wastewater flow arising from this process is not much, as pollution indicators COD,
SS, oil and grease are lower than the regulation QCVN 40:2011/BTNMT.
(2). Impacts on groundwater quality
The process of construction is generally not greatly affect groundwater resources.
However, the construction process can lower the water level, contaminating the
groundwater surface. In addition, the composition of fuels (gas, oil, organic solvents,
etc.) can leak from the vehicle and the equipment used, the storage warehouses in the
field will swept the rain water into the rivers, then penetrate into the soil causing
groundwater contamination in the project area. In addition, water leaks from concrete
mixing and piles, cleaning equipment can also contaminate the ground water.
(3). Impact due to stormwater runoff
Average flow of rainwater runoff in an area of 01 ha project is estimated to reach 98.6
m3/rainy day (the average rainfall in the project area is 1,800 mm/year, not including
evaporation) and can cause negative effects such as:
- Rain water retention in the soil and wetland projects;
- Rain water swept waste, oil sludge, dirt, rocks etc. down the rivers in the project
area which increase turbidity, surface water pollution and sedimentation.
Estimate of the concentration of pollutants in stormwater runoff through the
implementation of the project area as shown in Table 4.18.
Table 4.18. Estimated concentrations of pollutants in stormwater runoff
Stt Pollutants Units Concentration
1 Total nitrogen (N) mg/l 0,5 -1,5
2 Total phosphorus (P) mg/l 0,004 - 0,03
3 COD mg/l 10 – 20
4 TSS mg/l 10 – 20
Stagnant of rain water may cause the suitable environment for parasitic disease
development. However, this impact will be limited if the project owner to build
sewers and drains to avoid flooding during the rainy season.
4.2.1.3. Impact on land resources and soil quality
Since the project area is located in the land planned for the industrial zone
development of the Dong Nai province so there are no impact on landuse purposes,
whereas it can increase the value of land resource in the planned areas.
During the construction phase, the potential effects caused soil pollution are mainly
fluctuations in the construction area, land disturbance, erosion increase and pollution
impacts caused by domestic and construction wastes.
98
Activities during the construction phase can cause the land disturbance, the impacts on
the soil environment due to soil excavation activities, grading and erosion of the
construction area. With the mentioned above activities, it can see that the impact on
the soil environment during construction is not small, which lead to the terrain change
and the landscape of the construction region.
Impact on soil environment due to worker’s domestic waste, construction wastes and
grease from construction equipment and machinery at the site: During construction,
the construction activities will generate solid waste and waste water from construction
workers' camps; the construction waste or excess losses to the environment during the
construction, oil and grease from automobiles, construction machinery, which cause
the significant impact on soil quality, contaminate the soil if there are no effective
measures implemented.
(1). Impact due to solid waste
During construction, solid wastes will be generated from the construction of the main
works and ancillary works, including cement, bricks, sand, stone, wood, scrap
material and waste (scrap metal, paint, solvents etc.) from the welding work, cutting,
painting or spraying of metal. The concentration of more construction workers can
generate domestic solid waste.
This domestic solid wastes generally contains the organic biodegradable matter
(except packaging, plastic, metal cans).
(2). Impact due to households waste
It is estimated that each worker working in the project area emitted from 0.3 to 0.5 kg
of waste per day. So with 30 officers and employees at the site each day, the total
amount of waste generated during construction of the project is about 9-15 kg /day.
Although the volume of domestic solid waste is not too big, but if no measures
collected and treated properly, the ability to accumulate in time and build more and
more impact on air quality due to decay organic waste and surface water impacts due
to increase of water turbidity, hindering the flow, causing sedimentation. Also
facilitate the pathogenic microorganism growth, and risk arising transmitted disease
affecting the health of workers and further construction of residential areas.
(3). Impacts due to construction waste
During the construction process, the construction solid waste will be generated
including cement, bricks, sand, stone, wood, paper, scrap material spillage.
Solid waste generated during construction was not much. Norm of construction
material losses is presented in Table 4.19.
99
Based on the volume of construction materials one can estimate material losses,
equivalent to the daily average amount of construction waste discharge into the
environment. The construction solid waste consist of inert ingredients. But if it is not
collected, which will affect the construction activities on the site.
(4). Impact of hazardous waste
The hazardous solid wastes include rags grease, glue, paint, paint containers, gasoline,
battery, accumulator with negligible quantity. As some practical experience,
hazardous solid waste occupies about 5% of construction waste, which estimate about
01-02 kg/day. The amount of this waste contains harmful ingredients that can cause
negative impacts on human health and the environment if it is not collected and
properly disposed.
Table 4.19. Loss of construction materials
No. Type of material The loss of the original construction
by weight (%)
01 Yellow sand 2.0
02 Fine sand 2.0
03 Cable types 2,.0
04 Paint 2.0
05 Gravel and stone 2.0
06 Iron and steel 0.5
07 Cement 1.0
08 Wooden sleepers 0.5
09 Panels 3.0
Source: Environmental Technology Center (ENTEC), 2014.
4.2.1.4. The impact on socio-economic development
(1). The beneficial effects
Construction phase of the project could bring a positive impact to the socio-economic
development as follows:
- Mobilizing an idle workforce in the project area;
- Contributing to increasing labour and temporary income for workers;
- Stimulating development of some types of food services, activities, and other
entertainment to cater to the demand of the people living in the project area.
(2). The harmful effects
- The concentration of a construction work force (approximately 30 construction
workers per day) during the construction period may cause negative impacts to the
social order and security in the region;
100
- During construction, number of vehicles going in and out the project area will be
increased. Therefore, increasing the traffic density in the area, leading to increase risk
of traffic accidents;
Therefore, the project owner will take care, arrange the construction plan, mobilize
machinery, vehicles, equipment and techniques in a scientific way and manage road
safety in order to minimize the adverse effects on environmental and socio-economic
conditions.
4.2.1.5. Integrated assessment of the environmental impact caused by the activities
of the project construction phase
The environmental impact caused by the activities of the construction phase of the
project are summarized in Table 4.20.
Table 4.20. Integrated environmental impact assessment in the construction phase
No. Activity assessment
Land Water Air Biological
Resources
Economic
and social
1 Leveling ** * *** ** ***
2 Transportation, gathering,
storage of materials * * *** * **
3 Building WWTP * ** ** ** **
4 Activities of workers in the
field. * ** * * **
Source: Environmental Technology Center (ENTEC), 2012.
Note:
*: Detrimental effects mild;
**: Harmful impact on the average level;
***: Detrimental effects at strong.
4.2.2. Operation Phase
Operating process of the central wastewater treatment plant will give rise to the cause
of environmental pollution: air emissions, waste water and solid waste (hazardous and
non-hazardous) with scale and different components, which are specifically evaluated
as follows:
4.2.2.1. Impact on air environment
(1). Air emissions from transportation activities
Activity of transport, passenger transport chemicals, sewage sludge and garbage out
on the project will generate dust emissions, SOx, NOx, CO, THC,..
According to estimates, the number of vehicles to transport chemicals (about 3
tons/day), and sewage sludge (about 1.5 to 2 tons/day) average vehicle about 2
101
times/day (average weight per truck use of 3.5 tons). Average transport distance for
each vehicle turns within the Industrial Zone about 1km.
According to the report "Research on control measures of air pollution in the road
traffic in Ho Chi Minh City "shows average fuel consumption of 0.3 liters of diesel
vehicles/km.
Characteristics of the types of vehicles that are using diesel oil fuel. It is estimated that
the total amount of oil used for transportation activities as the project moved into
operation about 0.6 liters/day. Based on the coefficient of pollution World Health
Organization (WHO) set up for transport vehicles using diesel oil fuel, the load from
3.5 to 16.0 tons, can estimate the total load of pollutants in emissions arising from the
transport process of the project in operation is shown in Table 4.21.
Table 4.21. Estimated loads and concentrations of exhaust air emission pollutants
generated from the transportation means
No. Pollutants
Pollution
coefficient
(kg/kg of
fuel)
Pollution
load
(kg/day)
Concentration
(mg/m3/1h)
QCVN
05:2013/BTNMT
(mg/m3/1h)
01 Dust 0,0043 0,0022 8 0,3
02 SO2 0,005 0,0026 9 0,35
03 NO2 0,07 0,0357 133 0,3
04 CO 0,014 0,0071 27 30
05 THC 0,004 0,0020 8 5(*)
Note:
- Total fuel use is 0.6 liters/day;
- Sulfur content in the oil is 0.25%;
- Save emissions: When the engine is burning 01 kg of fuel gas generated 22 m3;
- Density of DO oil: 1 liter = 0.85 kg diesel oil diesel oil;
- The total volume of diesel oil used: 0.51 kg/h;
- Total emissions arising from transport: 11.2 m3;
- QCVN 05:2013/BTNMT - National Technical Regulation on ambient air
quality;
- (*)QCVN 06:2009/BTNMT - National technical regulation on hazardous
substances in the ambient air.
Comment:
Concentrations of pollutants in emissions arising from the transport vehicle at the
table at 5:21 is the result of emission sources (vehicle exhaust). Therefore, when
102
released into the surrounding environment pollutants concentration is much lower, due
to be reduced by environmental factors such as the absorption capacity of trees,
thinning etc. Thus, the level of resources that impact was minimized.
(2). Vapours
Vapours in the operational phase of major projects arising from the pumping, mixing
chemicals. Due to the use of chemicals NaOH, H2SO4 and liquid chlorine should be
pumping process can cause losses. However, the process of pumping, mixing
chemicals made secret, should not affect the environment significantly. Forecast
evaporation rate of about 0.05 to 0.1%, or about 0.2 to 0.5 kg/day.
(3). Aerosols, odors from the process
Wastewater treatment plant was found to be the arising of aerosols can spread by wind
within a few tens to a few hundred meters. In aerosols, people often encounter
bacteria, mold etc. and they could be pathogens or cause allergies inhalation, by skin
contact.
The formation of aerosols affect air quality around the area of the wastewater
treatment plant. For the CWTP, aerosol emission sources mainly from the tank and an
aerobic conditioning. According to a study of air quality around the wastewater
treatment plant, the density of airborne bacteria in the wastewater treatment plant is
presented in table 4.22.
Table 4.22. Bacterial density in the air at the wastewater treatment plant
No Bacteria Value
(CFU/m3)
Mean
(CFU/m3)
1 Total bacteria 0 - 1.290 168
2 E.Coli 0 - 240 24
3 Intestinal Bacteria and other
species
0 - 160 145
4 Mushrooms 0 - 40 16
Source: 7th International conference on Environmental Science and Technology –
Ermoupolis, Bioaerosol formation near wastewater treatment facilities, 2001.
Comment:
The odor from the treatment tank arises mainly from the tank as the conditioned tank,
Aerotank, compressed mud tank, aeration tank. However, this odor is only temporary
in nature, arising from the period of trial operation of the station.
Aerotank bubbles arising from an aeration tank bottom and the steam carries bacteria,
the bubbles generated mainly during adaptation, even when stable operation is not a
significant amount of foam.
103
Fifty households are living in the Northest that far from 500m of CETP, the distance
between households is large. In addition, Ong Keo IZ is influenced by two main wind
directions: Northeast in the dry season and Southwest in the rainy season. However,
CETP is located at the downwind, so the impact of odors and sol gas effect to fifty
households is negligible. Diagrams on CETP’s location and the nearest residential
area as well the prevailing wind direction are shown in Figure 4.1.
Figure 4.1. The main wind direction affects CETP
(4). The effects of air pollutants
In addition to the effects of air pollutants are shown in Table 4.23, as described above,
notably the impact of 02 key pollutants during operation of the project are: methane,
hydrogen sulfide.
(a). Methane (CH4)
Methane gas is colorless, odorless and extremely flammable (explosive limit of 5 -
15% volume in air). The effect of methane on the environment and humans are shown
in Table 4.23.
Table 4.23. Impacts of methane on the environment and human health
No. Subjects Impact
1
Impact on
environmental
quality
As a greenhouse gas, 23 times higher than CO2
2 Impact on human Methane is present in high concentrations in the
Residential communities
Southwest direction on rain season
North East direction on dry season
104
No. Subjects Impact
health atmosphere will become of asphyxiation. Quality
asphyxiation replaces oxygen in the air and can cause
symptoms of oxygen deficiency. When the oxygen
concentration in the air from:
- 12-16%: Makes breathing and heart rate increases
and slight muscle contraction.
- 10-14%: disruptors and respiratory sensation,
unusual fatigue, respiratory disorders.
- 6-20%: May cause nausea and vomiting, loss of
motor skills, may be unconscious.
- Greater than 6%: Causes seizures, shortness of
breath, respiratory possible and die.
Source: Environmental Technology Center (ENTEC), 2013
(b). Hydrogen sulfide (H2S):
Hydrogen sulfide is a colorless gas that smells of rotten eggs; toxic and extremely
flammable (explosive limit from 4.3 to 46% by volume in air). The effects of H2S on
the environment and humans are shown in Table 4.24.
Table 4.24. Impact of hydrogen sulfide on the environment and human health
No. Subjects Impact
1
Impact on
environment
The substance is toxic to aquatic species.
- Combined with water vapor in the atmosphere SO2
converted to form acid rain.
2
Impact on
human health
Acute: Acute toxicity H2S in the following concentrations:
- From 0.01 to 0.3 ppm: can recognize by smell.
- 1-20 ppm: odor can smell nausea, watery eyes, headache
lasts.
- 20 - 50ppm: irritation of nose, throat and lungs, digestive
disorders, loss of appetite, loss of sense of smell begins,
can cause acute conjunctivitis.
- 100 - 200ppm: irritation of nose, throat and lungs serious,
completely lost their sense of smell.
- 250-500 ppm: it cause edema (fluid in the lungs plays).
- 500 - 1000ppm: Respiratory Paralysis, rhythm disorders
and death within hours.
- Greater than 1000 ppm: quick death.
- Chronic poisoning:
- Reduced lung function.
- Neurological effects: headaches, nausea, fatigue.
105
No. Subjects Impact
- Irritating to eyes and mucous membranes.
- Damage to heart.
Source: Environment Technology Center (ENTEC), May 12/2013.
(5). The impact of physical factors in the work environment:
(1). Noise Pollution:
During the operational phase of the project, noise arising from sources such as pumps,
compressors, generators. The noise level generated relatively frequent and continuous
higher (average 80-85 dBA). Also, depending on the operational life cycle of
equipment, the local noise can be> 90dBA exceeds permitted standards in production.
The frequent exposure to 80 dBA noise source above to inhibit the central nervous
system, causing fatigue state of discomfort and reduce labor productivity, leading to
accidents.
(2). Thermal pollution balance:
Normally on hot days the temperature in the region of the central wastewater
treatment plant often allow higher standards from 1 - 30C (Interim Provisions of the
Ministry of Health - 505 BYT/QD dated 13.04.1992: 18 - 320C) .
4.2.2.2. Impact on the water environment
The source of water pollution in the operational phase of the project is defined as:
wastewater from domestic activities of operators and stormwater runoff over the entire
project area, wastewater from the central wastewater treatment plant.
(1). Domestic wastewater
Essential components of the contaminants causing waste water including impurities,
suspended solids (SS), organic compounds (BOD/COD), nutrients (N, P) and harmful
bacteria.
When the project is put into operation stability, estimated the total number of
employees is 05 persons. If the average 1 per day plant employees use 120 liters of
water, the waste water flow of the project is about 0.5 m3 (water flow for 80% of
water use).
Based on the coefficient of pollution each daily activities into the environment
(without treatment) by the World Health Organization (WHO) set up as shown in
Table 4.24, can predict pollutant load wastewater generated from operating activities
of workers in Table 4.25.
106
Table 4.25. Estimated pollution loads in untreated waste water in the project's
operation phase
No. Pollutants Load (kg/day)
Tải lượng trung bình(kg/ngày)
Limit Average
01 BOD5 0.180 - 0.216 0.198
02 COD 0.288 - 0.408 0.348
03 TSS 0.280 - 0.580 0.430
04 Oil and grease 0.040 - 0.120 0.080
05 Total nitrogen(N) 0.024 - 0.048 0.036
06 Ammonia (N-NH4) 0.001 - 0.019 0.014
07 Total phosphorus (P) 0.003 - 0.016 0.010
Based on the pollutant load (kg/day) and water flow (m3/day) can calculate the
concentration of pollutants in waste water as shown in Table 4.26.
Table 4.26. Concentrations of pollutants in the waste water treatment plant
No Pollutants
The concentration of pollutants (mg/l)
No treatment Treatment in
septic tanks
QCVN
14:2008/BTNMT
, column B, K=
1,2
01 pH - - 5 – 9
02 BOD5 495 198 60
03 COD 870 348 -
04 TSS 1.075 430 120
05 Oil and grease 200 80 24
06 Total nitrogen (N) 90 36 -
07 Ammonium
(N-NH4) 36 14,4 12
08 Total phosphorus 24 9,6 -
Note:
QCVN 14:2008/BTNMT - National technical regulation on domestic wastewater,
apply column B with K = 1.2.
Comment:
Compared with QCVN 14:2008/BTNMT (apply column B with coefficient K = 1.2)
showed that the concentration of pollutants after treatment with 3-compartment septic
tank (processing efficiency of about 60-70 %) are higher than standards allow.
However, during project operation, domestic wastewater after treatment area through
107
septic tanks will be collected on the station's processing system of the central
wastewater treatment plant.
(2). Stormwater runoff
Stormwater runoff through the project will be carried away by the sand, garbage, oil,
grease and other contaminants spilled on the ground and stick on the roof, tanks, water
to spread out. If rainfall is not well managed will cause negative impacts to surface
water, groundwater and aquatic life in the area. Estimate the concentration of
pollutants in the average stormwater runoff as follows:
- Suspended solids (SS): 10-30 mg/l;
- Chemical oxygen demand (COD): 10-20 mg/l;
- Total Nitrogen (N): 0.5 to 1.5 mg/l;
- Phosphorus (P): from 0.004 to 0.03 mg/l.
Thus, compared with other emission sources, stormwater runoff is relatively clean.
Therefore, the drainage system will be totally separated from the sewage system, the
system through manholes, but the trash before running the external environment
through the drainage system of the industrial zone.
(3). Wastewater Treatment Plant
Wastewater generated by the operation of the central wastewater treatment plant
multiple sources including:
- Separated from the waste water treatment sludge, scum and grease: Major
component contains suspended sediment, bacteria and other pollutants;
- Water hygiene: washing pumping equipment, chemical tank, filter cleaning,
floor cleaning,... This kind of waste water can be contaminated by oil, though
the amount is not significant;
- All waste water is collected and brought back to the station's tanks of the
central wastewater treatment plant.
(4). The impact of pollutants in wastewater
Wastewater generated from the operation of the project containing pollutants such as
suspended solids (SS), organic matter (COD/BOD), nutrients (total N, total P), the
metal seriously pathogenic microorganisms, toxic chemicals .... other polluting agents
are different, the level of impact is also different, as follows:
a). For pH:
The pH of water is too high (> 8) or too low (<6) will lose self-cleaning ability of the
receiving water, due to the beneficial microbes in the water inhibited viability. The pH
of water is too low or too high will increase the mobility of metal ions in the water,
108
the stronger the activation of ion will easily react with other substances to create a
beneficial product for aquatic life.
(a). For temperature:
Water temperature plays an important role in the biochemical processes, changes in
water temperature can affect the influence of dissolved oxygen concentration (DO) in
water is also affected by temperature decide which species survive and develop
advantages in aquatic ecosystems.
(b). For organic compounds:
The organic matter in the wastewater is mainly carbohydrates. This is easily oxidized
compounds by microorganisms using oxygen dissolved in the water. This factor
reduces the concentration of dissolved oxygen in the water (DO) in the water. If you
DO <5 will hamper the development of the aquatic ecosystem. On the other hand,
waste water containing organic compounds as long stagnation of the environment will
generate unpleasant odor caused by organic compounds with anaerobic digestion.
(c). For suspended solids:
The suspended solids discharged into the environment as part of water will float to the
surface creating a scum layer, preventing the diffusion of oxygen and light
transmission in water, increase water turbidity sensory loss. On the other hand, a result
of sediment settle to the bottom.
(d). For nutrients:
The nutrients in the aquatic environment is highly conducive environment for algae
growth, causing eutrophication of water resources (water bloom). At the end of the
process of eutrophication, algae die will increase the concentration of organic matter
in the water, affecting water quality and aquatic life.
(e). For heavy metals:
Most heavy metals are toxic to humans and animals. The heavy metal commonly
found in industrial effluents, such as Pb, Hg, Cr, Cd, As:
- Pb: Pb likely to accumulate in vivo long-term, heavy metal Pb is highly toxic
and may be fatal if severe poisoning. Pb reduced ability to synthesize glucose
and pyruvate metabolism, increases the excretion of glucose in urine. 50%
lethal concentration (LC50 96 h) of lead salt for fish is 1-27 mg/l (in soft water)
and 440-550 mg/l (in hard water). The organic compounds Pb toxicity than
from 10-100 times higher than for inorganic Pb species;
- Hg: Hg metal can be made in the form of salt ions, Hg is present in organic
compounds, mercury is used in agriculture (fungicides) and in industry (for
109
electrodes). Hg in the aquatic environment can be absorbed into the aquatic
body, especially the kind of river invertebrates. Fish also absorbed and
metabolized into methyl mercury Mercury;
- As: As the heavy metals can exist in many forms of inorganic and organic
substances. As a highly toxic substance, the ability to accumulate a long and
potentially carcinogenic;
- Cr: heavy metal Cr is highly toxic to humans and animals. High toxicity of
Cr6+, Cr3+ than. According to WHO allows maximum chromium
concentrations in drinking water is 0.05 mg/l;
- Cd: Cd heavy metal is highly toxic to humans and aquatic life. Kidney is the
most vulnerable, Cd concentrations harmful renal threshold of 20 g/l.
(f). For phenol:
Phenol and phenol derivatives in wastewater of some industries such as manufacturing
perfume, cosmetics etc. The phenolic compounds make water smell and also harms
the aquatic ecosystem and human health, a number of phenol derivatives have the
potential to cause cancer.
According to WHO levels of 2,4-trichlcphenol and pentachlorophenol in drinking
water not exceed 10 g/l.
(g). For grease:
Grease being discharged into the water will spill over the water forming oil film, a
water-soluble fraction in the water or in the form of emulsions. Oily residue settles
down to rivers and streams will accumulate in sediment. Grease is not only difficult
hydrocarbon compounds biodegradable, but also contain harmful additives such as
derivatives of phenol, water pollution, negative impacts to aquatic life including both
fish and affect water supply purposes, aquaculture. When the oil content in the water
is higher than 0.2 mg/l water odor can not be used for food purposes.
Oil pollution caused depletion of dissolved oxygen in the water, leading to reduced
self-cleaning ability of the water by killing plankton organisms, benthos engage in
self-cleaning process.
When the oil content in water from 0.1 to 0.5 mg/l will reduce yield and quality of the
fish. Standard Oil in water fish do not exceed 0.05 mg/l, dissolved oxygen standard
is> 4 mg O2/l. Sulfur-rich oil pollution can kill fish if Na2S in water content reaches 3
- 4 mg/l. Some sensitive species may be killed as soon as Na2S concentrations less
than 1 mg/l.
In addition, the domestic oil will be converted into other compounds toxic to humans
and aquatic life such as phenol, chlorine derivatives of phenol. Standard phenol to
give living water is 0.001 mg/l, tolerance of fish is 10-15 mg/l.
110
4.2.2.3. The impact to soil
(1). Solid waste impact during operation of the central wastewater treatment plant
Solid wastes during project operation mostly packaging waste, packaging and
chemical waste container in the central wastewater treatment plant, but waste from
sewage, sewage sludge from the tank etc. The volume of solid waste during project
operation are listed as follows:
- Packaging and storage of chemicals (hazardous wastes): 15-20 kg/day;
- Sludge from the central wastewater treatment plant about 1.5 to 2 tons/day;
(1). Solid waste activities
With the number of operators in the central wastewater treatment plant is 05 people,
with the emission factor is 0.3 to 0.5 kg /person /day estimated volume of solid waste
activities range from 1.5 to 2.5 kg/days.
Solid waste workers' activities mainly biodegradable organic matter and biological
fraction of paper, glass, metal,... will be collected in containers at the central
wastewater treatment plant then collected with waste of the entire industrial zone. The
amount of solid waste dosmetic are company rent functional units collected,
transported and treatment prescribed.
(2). The impact of solid waste
Domestic solid wastes such as plastic, metal, nylon ... when released into the
environment will be difficult to biodegrade, causing accumulation in soil, water,
aesthetic loss, affecting transportation. In the long run, these substances will
decompose generating inorganic compounds, organic toxic etc. pollution of land,
water, affecting the growth of microorganisms on land and water.
The process of decomposing waste generated gases cause bad smelling (H2S,
mercaptans), impact to regional air quality, affect people's health in surrounding areas.
In addition, hazardous waste if not collected, managed and appropriate treatment will
also affect the environment and human health.
4.2.2.4. Integrated assessment of environmental impacts during project operation
The impact on the environment during the operational phase has been studied in the
central wastewater treatment plant, analyze and evaluate detailed above, can be
evaluated by the method of synthetic matrix environment without weights as shown in
Table 4.27.
Table 4.27. Summary of integrated environmental impacts in the operation phase
111
No. Origin impact Land Water Air Biological
Resources
Economic
and social
01 Emissions * * *** * **
02 Wastewater * *** * *** **
03 Solid waste and hazardous wastes *** * ** * **
04 Thermal pollution * * ** * *
05 Noise pollution and vibration * * ** * ***
06 Environmental incidents ** ** *** ** **
Note:
- *: Less harmful effects;
- **: Harmful impact on the average level;
- ***: Detrimental effects at strong.
4.2.3. Risk and Accident Impacts
4.2.3.1. During the construction phase
(1). Work accidents
Overall, accidents can occur at any stage of the construction project. The cause of the
accident cases work on the construction site are:
- Environmental pollution can cause fatigue, dizziness, or fainting while workers
labor;
- Installation works, execution and process materials transport vehicle density,
higher can cause accidents, traffic accidents, ...
- Accidents due to the negligence of workers, lack of protective equipment, or
due to lack of awareness about the strict compliance with safety rules of
construction workers.
Investors will be interested in the application of measures to ensure the safety of
workers.
(1). Explosion Incident
Fire Incidents can occur in the case of transportation and storage of fuels, or due to the
lack of safe temporary power supply system, causing loss of life and property during
construction. Maybe the reason determined as follows:
- The fuel storage resources for temporary construction (gasoline, diesel oil, fuel
oil, paint, glue ...) are possible sources of ignition. When problems occur that
can cause serious damage to the economy and the environment;
- Temporary power supply system for the machinery, construction equipment
malfunction can cause electrocution, shock, fire ... economic damages or
accidents to workers;
- The use of heating equipment during construction (heating, asphalt, soldering
...) can cause fire, burns or accidents if no preventive measures.
112
- Due to the circumstances of this incident can happen at any time, so investors
will adopt measures to prevent, control efficient to minimize the negative
impact.
(2). Traffic accidents
Traffic accident risk occurred in the construction process, damage to property and
lives. The cause may be due to transportation is not guaranteed by the technical or
non-compliance with the control of traffic safety rules. This incident was entirely
preventable by checking the technical condition of transport and communication to
raise awareness observance of traffic rules by drivers and transport workers.
(3). The risk of subsidence collapsed during the construction works
The process of construction of earthwork construction solid waste burial pit potential
subsidence risks collapsed buildings. When incidents occur, not only harmful effects
on the environment and also threatens human lives.
Incidents landslides during the rainy season may occur during excavation, foundation
construction of tanks.
4.2.3.2. During the operation phase
(1). Work accidents
- Work accidents can occur during operation at the central wastewater treatment
plant. The main cause of accidents is:
- The observance of safety rules and poor labours.
- The carelessness of workers in the process control machinery, equipment and
vehicles;
- Health status of workers are not well lead to fall asleep at work or due to
overwork.
(1). Leaking fuel and raw material
Leaking fuel, liquid or gas chemicals will affect human health, impact on flora and
fauna. Leaks can lead to accidents that cause fire, explosion, oil spills, chemical spills
etc.. causing major economic damage - social as well as ecological systems in the
region and surrounding areas.
(2). Fire Incidents by storing fuel chemical
Fire Incidents can occur in the case of transportation and storage of fuel or electric
shock, causing loss of life and property of the business and residential communities
around. It is possible to identify the source of ignition is as follows:
113
- The storage of fuel (gasoline, diesel oil, fuel oil, natural gas ...), the storage of
chemicals (paints, glues, varnishes ...);
- Transformers, Power Supply System in the central wastewater treatment plant.
Investors will apply the integrated measures to prevent and timely rescue incidents to
minimize the negative impact on the environment.
(3). The fixed stations cessation in the central wastewater treatment plant
Incidents in the central wastewater treatment plant suspended operations may occur
due to the station's equipment such as pumps, agitators, chemical plant lit ...
discontinued operations (due to malfunction or power failure). The other reason is
because the operators did not ensure that digital organisms are killed, the station must
suspend operations of the central wastewater treatment plant to culture the bacteria.
The central wastewater treatment plant suspended operations will cause a large
amount of stagnant water, untreated, can cause environmental pollution.
This problem can be prevented by regularly checking the technical condition of the
equipment is operating; replaced promptly repair damaged machinery, workers are
fully trained technicians. In addition, investors will invest in the construction works of
the central wastewater treatment plant
4.2.4. Socio-economic impacts
4.2.4.1. Construction phase of the project
- The concentration of a construction work force (approximately 30 construction
workers per day) during the construction period may cause negative impacts to
the social order and security in the region;
- During construction, the project to build the car turn into the school will
increase. Therefore, increasing the density of traffic in the area, leading to an
increased risk of traffic accidents.
Therefore, the project owner will care, construction layout plan, mobilize machinery,
vehicles, equipment and techniques in a scientific way and road safety management in
order to minimize the adverse effects on environmental and socio-economic
conditions.
4.2.4.2. Operation phase of the project
(1). The positive impact
When the central waste water treatment plant with capacity of 3,000 m3/day at Ong
Keo Industrial Zone going into operation will contribute to socio-economic
development, as follows:
114
- Wastewater treatment at QCVN 40:2011/BTNMT column A, Kq = 0.9, Kf = 0.9
contribute to the protection of surface water in the water stream;
- Operation of the project will create jobs, generate income stability for workers,
poverty contributing to erosion, improve the environment, improve the educational
level of the people.
(1). The negative impact
Along with the benefits of economic growth - social, the project will also cause a
number of negative effects, such as changing living conditions, increased activity of
mosquitoes because of the treatment tank.
4.2.5. Cumulative impacts
Long Tau river is the water body, which receive wastewaters from Ong Keo IZ.
According to the local authority, Long Tau river water is not used for domestic
purposes, so the quality of wastewater being discharged into the stream basin to reach
the standard QCVN 40:2011/BTNMT column B, corresponding to Kq = 0,9 and Kf
depending on the actual amount of emissions per unit discharge (Based on Annex 1 of
Decision No. 16/2010/QD-UBND dated 19 March 2010 on environmental zoning to
the surface waters receiving industrial effluents). When the central wastewater
treatment plant of Ong Keo Industrial Zone - Phase 1 discharge with an average
largest wastewater flow of 6,000 m3/day. With effluent discharge permit of
3,000m3/day, the central wastewater treatment plant was achieved QCVN 40:2011/
BTNMT, column B, Kq = 0.9; Kf = 0.9, so it is in accordance with the conditions of
discharging wastewater into water sources.
However, the discharge of wastewater into water sources Ong Keo Industrial Zone-
Phase 1 (module 1) will have an impact on water quality, flow of Long Tau river. Due
to the station's wastewater flow from the central wastewater treatment plant of Ong
Keo Industrial Zone - Phase 1 (module 1) is small compared to the flow stream and
treated to meet the national technical regulations on the environment before discharge
to the receiving water the impact is negligible.
To assess the cumulative impacts to the operation of treatment plants discharge
wastewater concentration of Ong Keo Industrial Zone - Phase 1 (module 1) for water
in river, we will evaluate the ability of the receiving of Long Tau river streams
receiving wastewater from the central wastewater treatment plant of Ong Keo
Industrial Zone - Phase 1 (module 1). The evaluation will follow 02/2009/TT-BTNMT
Circular dated 03.19.2009 of the Ministry of Natural Resources and Environment
Regulations to assess the possibility of getting effluent water.
Wastewater from the waste water treatment of Ong Keo Industrial Zone - Phase 1
(module 1) is treated with the central wastewater treatment plant of Ong Keo
Industrial Zone - Phase 1 (module 1) at QCVN 40:2011/BTNMT - National Technical
115
Regulation on waste water industry (column B), Kq = 0.9, Kf = 0.9 when released into
the Long Tau river.
Limit values of pollutants in the Long Tau river are presented in the following table
4.28:
Table 4.28. Limit values of water pollutants in Long Tau river
Parameters BOD COD TSS Amoni Pb Fe Total oil
grease
Ctc limit values (mg /l) 25 50 100 1 0,05 2 0,3
Note: The limit value determined by Ctc QCVN 08:2008 /BTNMT, Column B2.
4.2.5.1. Maximum pollution load
Maximum pollution load can receive water for contaminants is calculated by the
following formula:
Ltd = (Qs + Qt) x Ctc x 86,4
Among them:
- Ltd: maximum pollution load of water for contaminants;
- Q: discharge of Long Tau river, Q = 43.11 m3/s (Decision 16/2010/QD-UBND dated
19/3/2010 of PPC to the Partitioning the water environment present to receive
industrial effluents);
- Qt: Wastewater Flow, Qt = 0.034 m3/s (up WWTP of Ong Keo Industrial Zone -
Phase 1 (module 1);
- 86.4 is the conversion factor from the first unit (m3/s) x (mg/l) to (kg/day).
- Results calculated maximum pollution load can receive water for contaminants is
presented in the following table.
Table 4.29. Maximum pollution load which can be received by water body.
Parameters BOD COD SS Amoni Pb Fe Total oil
grease
Qs + Qt
(m3/s) 43.14 43.14 43.14 43.14 43.14 43.14 43.14
Ctc (mg/l) 25 50 100 1 0.05 2 0.3
Ltd (kg/day) 93,182.4 186,364.8 372,729.6 3,727.3 186.4 7,454.6 1,118.2
4.2.5.2. Load pollutant available
Load pollutant sources available in the host country is calculated using the formula:
Ln = Qs x Cs x 86.4
Among them:
- Ln: pollution load available in the receiving water;
116
- Qs: Discharge of Long Tau river, Q = 43.11 m3/s (Decision 16/2010/QD-UBND
dated 19/3/2010 of Dong Nai province about Partitioning the water environment
present to receive industrial effluents);
- Cs: the maximum value of the concentration of pollutants in water before receiving
water;
- 86.4 is the conversion factor from the first unit (m3/s) x (mg /l) to (kg/day).
Results calculated pollutant load sources available in the host country are presented in
the following table.
Table 4.30. Calculated results of pollutant loads, which are available in the receiving
water body
Parameters BOD COD SS Amoni Pb Fe Total oil
grease
Qs (m3/s) 43.11 43.11 43.11 43.11 43.11 43.11 43.11
Cs (mg/l) 23.73 102 230 0.4 0.004 0.9 1.67
Ln (kg/day) 88,387.2 379,919.8 856,681.9 1,489.9 14.9 3,352.2 6,220.3
Note: Cs is the average value of the analysis results of Long Tau river water quality
made by investor at June, 2014.
4.2.5.3. Load of the discharge of pollutants from sources
Load of the discharge of pollutants from the source to the receiving water is calculated
using the formula:
Lt = Qt x Ct x 86.4
Among them:
- Lt: Load emission sources of pollution;
- Qt: Wastewater Flow, Qt = 0.034 m3/s;
- Ct: the maximum value of the concentration of pollutants in waste water;
- 86.4 is the conversion factor from the first unit (m3/s) x (mg/l) to (kg/day).
Load calculation results from the discharge of pollutants into receiving water bodies
are shown in the following table.
Table 4.31. Calculated results of the pollution load from Ong Keo Industrial Zone
discharging into the Long Tau river
Parameters BOD COD SS Amoni Pb Fe Total oil
grease
Qt (m3/s) 0.034 0.034 0.034 0.034 0.034 0.023 0.023
Ct (mg/l) 40.50 121.50 81.00 8.10 0.41 4.05 8.10
Lt (kg/day) 118.97 356.92 237.95 23.79 1.19 11.90 23.79
Note:
117
Ct: concentration of treated wastewater taken from Ong Keo Industrial Zone, which
equal the maximum concentrations of QCVN 40:2011/BTNMT, kq = 0.9, kf = 0.9,
column B.
4.2.5.4. Capacity to receive emissions sources of Long Tau river
The ability to recognize pollution load of Long Tau river is calculated by the
following formula:
Ltn = (Ltd - Ln - Lt) x Fs
Among them:
Ltn: Absorption capacity of the pollutant load Long Tau river (kg/day);
Ltd: maximum load of pollutants to water pollutants (kg/day);
Ln: pollution load available in the receiving water (kg/day);
Lt: Download the source of pollution emissions (kg/day);
Fs: safety factor, Fs = 0.3 to 0.7, Fs = 0.5 chosen.
Absorption capacity of Long Tau receiving wastewater after Ong Keo Industrial Zone
are presented in the following table.
Table 4.32. Carrying capacity of Long Tau river receiving the treated wastewater
discharging from Ong Keo Industrial Zone
Parameter BOD COD SS Amoni Pb Fe Total oil
grease Ltd (kg/day) 93,182.40 186,364.80 372,729.60 3,727.30 186.36 7,454.59 1,118.19
Ln (kg/day) 88,387.23 379,919.81 856,681.92 1,489.88 14.90 3,352.23 6,220.26
Lt (kg/day) 118.97 356.92 237.95 23.79 1.19 11.90 23.79
Ltn(kg/day) 2,338.10 (96,955.96) (242,095.13) 1,106.81 85.14 2,045.23 (2,562.93)
Comment: Long Tau river after receiving wastewater from Ong Keo Industrial Zone
still have the receiving capacity for BOD, Amoni, Pb, Fe. Therefore, Long Tau river
can still receive the wastewater from Ong Keo Industrial Zone.
4.3. COMMENT ON THE RELIABILITY OF THE USED EIA METHODS
The level of detail, reliability of the methods used are given in Table 4.33.
Table 4.33. Summary of the reliability of the used EIA methods
No. Method Reliability Cause
01 Statistical Methods Migh Based on official statistics of the
province.
118
No. Method Reliability Cause
02
The method of field
sampling and laboratory
analysis
High
- Equipment for sampling and
analysis of new and modern
- Based on standard sampling
methods
03
Rapid assessment method
by using pollution factor
established by WHO in
1993
Medium
Based on the coefficient of pollution
World Health Organization set up is
not really consistent with the
conditions of Vietnam
04 Comparison method High The analytical results have high
reliability
05 The method of checklist and
matrix Medium
The method evaluates only semi-
quantitative or qualitative, based on
the subjective evaluation
06 Modeling method High Calculation results are high reliability
07 Public consultation method High
Based on the opinion of the
Fatherland Front Union and People
Committee of commune
Source: Environmental Technology Center (ENTEC), 2014.
EIA report for the project "Investment in the construction of the central waste water
treatment plant with capacity of 3,000 m3/day" of Ong Keo IZ, Tin Nghia Corporation
have prepared by an investor with the advice of the Environment Technology Center
(ENTEC) within Vietnam Association of Conservation of Nature and Environment
(VACNE). With many years experience in EIA, ENTEC have fully assessed with the
necessary reliability on impacts of the proposed projects and feasible measures to limit
the harmful effects.
Besides the data resources, reference, the Corporation also receive the consultation of
the People's Committee and the Fatherland Front Union at the project site, therefore,
the impact assessment presented in the report meet the actual requirements of the local
authorities.
However, the some assessments of the EIA report are also qualitative or semi-
quantitative due to there is not enough information, detailed data for quantitative
assessment.
119
CHƯƠNG 5 MITIGATION MEASURES OF THE NEGATIVE
ENVIROMENTAL IMPACT
5.1. LAND CLEARANCE PHASE
CETP has been built on industrial land based on land acquisition/resettlement plan was
implemented through the Decision approved by the People’s Committee of Dong Nai
province (Decision No. 3481/QD-UBND) dated 22 October 2008 in which land acquisition
carried out by the Center for Land Fund Development of Nhon Trach District commenced in
2008. Therefore, the construction works do not affect the structure of land-use. Nhon
Trach District People’s Committee land handed over to Tin Nghia Company. Therefore,
land clearance phase almost does not impact to environment as well as local
residential.
5.2. CONSTRUCTION PHASE
5.2.1. Air pollution control
During the construction phase, rock excavation, transport vehicles and construction
equipment are major sources of air pollution. The following counter measures are
implemented to mitigate the impact of air pollution, noise and vibration.
5.2.1.1. Air pollution control
Implementation the target minimize air pollution, investors proposes to apply the
following measures:
- To only use the registered vehicles, which has met the standards and
regulations on air emissions
- High amount of dusts are generated by the intense traffics of construction
materials transports, which may seriously affect air quality in the region.
Therefore, the need to maintain water spray 2 times/day at the construction site,
surrounding the transport route and gathering of materials, machinery,
construction entrances, dumping area and traffic hubs . This reduce the loose
dust, soil sand which can be dispersed by wind into the air (especially during
the dry season in the sunny and windy days);
- Cover the top of the transport equipment, construction materials storage sites
and rinsed through before leaving the site;
- Planning schedule to avoid transport during sensitive hours (e.g.: peak hours,
mid-night). Regulating the speed for vehicles (<30km/h) to minimize noise
120
generation, especially when passing through residential areas during such
hours;
- To carry maintenance on vehicles and construction equipment to acquire valid
inspection certificate, and minimize noise, vibration and emissions arising out.
- To organize the traffic in and out the construction site in accordance with
regulation of MONRE.
- Provide temporary covers (e.g., tarpaulins, grass, etc.) on long term materials
stockpiles.
- Vehicles has been provided temporary covers (e.g., tarpaulins, grass, etc.) and
cleaned before go out construction sites.
- To minimize the dust pollution caused by the transportation of materials and
equipment to residential, the project also upgrade and build transportation
routes to and from the project area;
- The machines are regularly maintained, runs well with the valid inspection
certificate, which allow participating in the construction.
- Do not incinerate wastes in the project area.
Noise pollution and vibrations control
The construction areas have intense traffics and construction equipment activities
(such as rollers, bulldozers, excavators, cranes, excavators etc.). This generates high
levels of noise and vibrations affecting on surrounding environment. To minimize the
effects of noise and vibrations from vehicles and machinery, the following counter-
measures are carried out:
- Do not use old vehicles, construction machines, which are not licensed by the
Registration Stations and generate noise and vibrations above allowable limits;
- To thoroughly comply with the standards and maintenance schedules to reduce
air pollution.
- To regulate the speed of vehicles and machinery, which operating within the
construction area to less than 5km/h;
- For the machines with high noise levels, such as excavators, compressors,
excavator etc. noise isolation devices will be installed. When excessive noises
can't be avoided, appropriate noise protection gears (helmet, ear plug) will be
enforced surrounding the area.
- Do not exceed freight tonnage regulations;
- Check the level of noise, vibration during construction, thereby setting the
appropriate schedule to achieve noise levels, vibration as permitted by
regulations QCVN 26:2010/BTNMT, QCVN 27:2010/BTNMT;
121
- Avoid the intensive use of heavy machines in the same time and space which
may cause resonance of noise and vibration;
5.2.2. Water pollution control
- During the construction phase, generated wastewater will be not directly
discharged into the Bang canal in the project area. Construction unit will
construct water pits for sludge and sediment treatment;
- The types of wastewater generated during the construction of the central
wastewater treatment plant are collected and treated before discharging into the
environment. Project investors will closely manage and monitor the contractors
to ensure no wastewater will be discharged directly into the regional surface
and groundwater;
- To construct the temporary wastewater treatment (i.e. septic tank) or arrange 2-
3 portable toilets for construction workers, and solid waste storage area
- Only use biodegradable chemical that non-toxic to the environment. The waste
water containing chemicals, oil and grease are collected and thoroughly treated
to ensure for safe discharge.
- Wastewater from the cleaning of vehicles will be collected into the
sedimentation tank before discharging into the Long Tau river
- To design the run-off drainage in the construction field with collection points
consist of sediment manholes and grease trap to prevent oil pollution in the
Long Tau river in the project area.
5.2.3. Soil contamination control
Due to the nature of construction activities (excavation and building construction),
insignificant amount of chemicals will be stored on site. Hence risk of soil
contamination is negligible during the project’s construction phase. Therefore, the
project owner will not implement any counter measures here
5.2.4. Traffic Control
- Only use the vehicle with the valid registration certificate to meet the standards
and regulations
- As stated earlier, the speed of vehicles and machinery within the construction
area is limited to 5km/h;
- Do not exceed freight tonnage regulations;
122
- Set up transportation plan, with coordination of vehicle traffic within the
appropriate area to avoid the high concentration of transportation at the same
time or the same location.
5.2.5. Public Health and Socio- economic Development Protection
- Training workers about workplace safety in the CETP. The company will also
cooperate with the Occupational Safety Division within Department of Labor,
War Invalids and Social Affairs of Dong Nai province to organize the training
on safety rules and equipment operation;
- Enforcing the wearing of protective gear (PPE) for employees in accordance
with the specific works;
- Developing the plan to reduce the impact of pollutants on worker’s health at
the CETP;
- Carry out periodic health examination program for workers in the CETP;
- Ensuring the microclimate factors and working conditions to meet the
standards and regulation issued by the Ministry of Health to protect the
worker’s health;
- - Controlling noise levels according to noise standards and regulations to
prevent associated occupational diseases;
5.2.6. Solid Waste Management
5.2.6.1. Domestic solid waste
To minimize pollution from domestic solid waste, the project owner and the
contractor will implement the following measures:
- Enforce rules of hygiene and environmental protection in workers amps,
including financial sanctions if violated;
- To organize the training for workers on environmental protection regulations;
- Domestic solid waste generated will be collected in appropriate container
within the project area. At the worker’s camps two to three 100L garbage bins
with be provided, and toilets for personal hygiene;
- To contract with functional units to collect, and transport solid wastes to the
waste disposal according to current regulations.
5.2.6.2. Construction solid waste
123
Construction solid wastes are mainly damaged materials such as rubble, sand, gravel,
concrete scrap, damaged wood planking, broken protective devices etc. and domestic
solid waste generated from construction workers on the field. The treatment of solid
wastes is regularly conducted, focusing on waste reuse. Wastes such as cement bags,
protective gear, head piece of steel, welding rods collected at the specified location on
the site can be resold as recyclable materials. The types of rubble, rocks etc. will be
used for foundation levelling.
5.2.6.3. Hazardous waste
The hazardous wastes including oily rags, wasted oil are collected in special tanks and
contain on the cans having lids for further disposal in compliance with Circular
12/2011/TT-BTNMT on hazardous waste regulations.
5.2.7. Risk Mitigation
Since the short duration and small scale of construction activities, the work risks and
incidents should be easy to control and prevent:
5.2.7.1. Fire prevention
- Workers in the construction site will be trained in response to fire-related
incidents; fully equip with fire prevention equipment in accordance with the
applicable law;
- The types of solvents and flammable fuel will be stored in separate isolation
repositories, away from potential sources of ignition and spark-ignition;
- Issue rules on prohibiting employees to smoke, or cause ignition in these areas
with high risk of flammable;
- Apply explosive mitigation devices at the fuel storage area at the project’s site;
- When the fire and explosion incident happens, the company will immediately
collaborate with Fire Prevention and Fighting Department of Nhon Trach
District to respond.
5.2.7.2. Traffic risk prevention
- Regulating the transportation means in and out the project areas reasonably,
carrying within limited transport loads;
- Organizing advocacy for officials and employees and owner of transportation
means to implement the traffic safety law.
5.2.7.3. Measures to ensure the safety, health protection
124
- To comply with regulations on labor safety when established construction
projects organization; machinery layout; accidents preventive measures,
workers in the construction site used equipment such as protective headgear,
masks, gloves, protective clothing, goggles, shoes, boots;
- Closely monitoring the construction process, minimize the extent of
occupational accidents; including electrical safety and traffic accidents;
- Limit storage of explosive or flammable resources or chemicals. Establish
barriers to isolate dangerous areas such as power transformers, power supply
systems, flammable materials (such as fuel storage gasoline, paint materials,
equipment, ...);
To build fire prevention programs and provide specialized protection gear to handle
when problem occurs.
5.3. OPERATION PHASE
5.3.1. Air Pollution Control
5.3.1.1. General measures to reduce air pollution
The integrated measures to limit air pollution and effects on health workers applied by
Tin Nghia Corporation during the operation as follows:
- To build the waste water treatment plant in accordance with industry safety,
industrial hygiene, to maintain the necessary ventilation with natural ventilation
and cooling fans;
- Clean the wastewater treatment, operating rooms after each shift;
- Provide labor protection under the provisions for workers and supervise the use
of personal protective equipment during work;
- Provide sufficient information about sanitation, occupational safety for
workers.
5.3.1.2. Measures to control and reduce air pollution concentration at the central
waste water treatment plant.
The Company will apply the probiotics (GEM-P, K-GEM, GEM, CTA-T, CTA-8T
produced by Bien Co Company Ltd. based on a survey of micro-organisms in
Vietnam) and chemical agents (Tocazeo produced by Thanh Chuong Production -
Services - Commerce Co.Ltd) to reduce odors arising from the waste sector,
wastewater treatment, sludge dump etc. In addition, the plan to using a more pleasant
smell (masking agents) will also be applied in the area of waste water treatment.
125
How to use probiotics (GEM-P, P1-GEM, GEM-K, GEM, CTA-T, CTA-8T of Bien
Co Company Ltd.:
- Estimated amount of probiotics used for the central waste water treatment plant
capacity in the first 30 days: 6,000 litter K-GEM, GEM-P1 4.500 kg;
- From 31 to 60 days: reduce 20% of the composition;
- From the day 61 onwards of the composition to about 60%;
- From the day 91 onwards of the composition to about 50%;
- Installation of automatic sprinkler systems;
- Dilute 1 litter of GEM-K with 100 litters of water and spray over places with
strong odour.
- For emissions resulting from anaerobic decomposition of organic matter in
wastewater, this type of odour is very difficult to control. The best mitigation
measures are frequent sanitation, garbage collection from solid waste trap,
dredged sludge and sludge from the sludge tanks and sent them for compressed
and treatment regularly.
In addition to limit the smell arising from waste water treatment station, Investor
Industrial Zone will use the following measures:
- Planting tree with large canopy to create landscapes and mitigate the odour;
- Use oxidative agents: The nature of odors will be destroyed by strong oxidizing
agents such as H2O2 or ozone (O3). Therefore, the management board can
periodically spray H2O2 solution in the region or install arising ozone
generators for odor treatment. Currently ozone generators have been applied
for many other case studies in Vietnam.
5.3.1.3. To control air pollution caused by traffic activities
- Concretise the roads within the central wastewater treatment plant, frequent
sanitation of roads and installation of automatic sprinkler systems for roads
within the central waste water treatment plant;
- Do not start the engine of the car while waiting for materials, chemicals,
sewage sludge, garbage;
- Regular inspection and maintenance of transport vehicles, ensuring well
technical condition.
5.3.1.4. Reducing noise pollution
126
- Installation of anti-vibration cushion around machinery that produce loud
noise. Compressors will be located in soundproof chambers;
- Soundproof the major noise source (usually 200 mm thick layer of the wall,
next to 100 mm thick foam sound insulation, window layout with sound
absorption wall leaning, wooden door closed and heavy);
- Inspection and routine maintenance of machinery and equipment. Normally
maintenance cycles for new devices is every 4-6 months, old devices is every 3
months;
- Planting more trees on the campus to spread out the sound waves.
5.3.1.5. Reduce excess heat pollution
On hot days the temperature in the area of the waste water treatment plant is usually
higher than standards by 1 - 30C. The project investor will provide internal cooling
devices and cooling beverage with added sugar and mineral salts for the operators
working onsite.
5.3.2. Water Pollution Control
5.3.2.1. Road and drainage collection
(1). Domestic wastewater
Waste water from toilets of employees is collected and treated by a septic tank, then
discharged along treated effluent from WWTP.
(1). Stormwater runoff
Stormwater runoff is collected through expensive collecting pipeline network. Solid
wastes and particles will be separated for collection before the runoff will be
discharged into storm drains of the Industrial Park.
5.3.2.2. Technology and efficiency
The design parameters of the input and output of the central waste water treatment
plant are presented in Table 5.1.
Table 5.1. The inlet and outlet parameters of the central wastewater treatment plant
according to design
No. Parameter Unit
Ong Keo industrial zone
Input
Output
(QCVN 40:2011/BTNMT
Column B with Kf = 0,9 and
Kq = 0,9)
127
1 Temperature oC < 45 40
2 Color Pt/Co - 150
3 pH - 5.5-8 5.5 to 9
4 BOD5 (20oC) mg/l ≤ 300 40.5
5 COD mg/l ≤ 500 121.5
6 TSS mg/l ≤ 200 81
7 Asen mg/l 0,1 0.081
8 Mercuri mg/l 0,01 0.0081
9 Lead mg/l 0,5 0.405
10 Cadimi mg/l 0,1 0.081
11 Crom (VI) mg/l 0,1 0.081
12 Crom (III) mg/l 1 0.81
13 Copper mg/l 2 1.62
14 zinc mg/l 3 2.43
15 Niken mg/l 0,5 0.405
16 Mangan mg/l 1 0.81
17 Iron mg/l 5 4.05
18 Tổng xianua mg/l 0,1 0.081
19 Total phenol mg/l 0,5 0.405
20 Total mineral oil mg/l 20 8.1
21 Sunfua mg/l 0,5 0.405
22 Florua mg/l 10 8.1
23 Ammonium (calculated as
N)
mg/l 10 8.1
24 Nito total mg/l 40 32.4
25 Total phosphorus (in P) mg/l 8 4.86
26 Chloride (does not apply to
the discharge of seawater,
brackish water)
mg/l 1000
810
27 Residual chlorine mg/l 2 1.62
28 Total plant protection
chemicals organochlorine
mg/l 0,1 0.081
29 Total plant protection mg/l 1 0.81
128
chemicals
organophosphorus
30 PCB total mg/l 0,01 0.0081
31 Coliform Bacteria
/100ml
- 5000
32 Total radioactivity α Bq/l 0,1 0.1
33 Total radioactivity β Bq/l 1.0 1.0
Treatment efficiency of IZ Ong Keo’s central wastewater treatment plant is presented
in Table 5.2.
Table 5.2. Treatment efficiency of IZ Ong Keo’s central wastewater treatment plant
No. Parameters Unit Input Output
Treatment
efficiency
(%)
1. 1 Temperation oC < 45 40 -
2. 2 Color Pt/Co - 121.5 -
3. 3 pH - 5.5-8 5.5 đến 9 -
4. 4 BOD5 (20oC) mg/l ≤ 300 40.5 86.5
5. 5 COD mg/l ≤ 500 121.5 75.7
6. 6 TSS mg/l ≤ 200 81 59.5
7. 7 Asen mg/l 0.1 0.081 19
8. 8 Hg mg/l 0.01 0.0081 19
9. 9 Pb mg/l 0.5 0.405 19
10. 1
0
Cadimi mg/l 0.1 0.081 19
11. 1
1
Crom (VI) mg/l 0.1 0.081 19
12. 1
2
Crom (III) mg/l 1 0.81 19
13. 1
3
Cu mg/l 2 1.62 19
14. 1
4
Zn mg/l 3 2.43 19
15. 1
5
Niken mg/l 0.5 0.405 19
16. 1
6
Mangan mg/l 1 0.81 19
17. 1
7
Fe mg/l 5 4.05 19
18. 1
8
Total xianua mg/l 0.1 0.081 19
129
No. Parameters Unit Input Output
Treatment
efficiency
(%)
19. 1
9
Total phenol mg/l 0.5 0.405 19
20. 2
0
Total grase mg/l 20 8.1 59.5
21. 2
1
Sunfua mg/l 0.5 0.405 19
22. 2
2
Florua mg/l 10 8.1 19
23. 2
3
Amoni (follow
N)
mg/l 10 8.1 19
24. 2
4
Total nito mg/l 40 32.4 19
25. 2
5
Total P mg/l 8 4.86 39.25
26. 2
6
Clorua ( mg/l 1000 810 19
27. 2
7
Residual
chlorine
mg/l 2 1.62 19
28. 2
8
Total of plant
protection
chemicals
organochlorine
mg/l 0.1
0.081 19
29. 2
9
Total of plant
protection
chemicals
organic
phosphorus
mg/l 1
0.81 19
30. 3
0
Total PCB mg/l 0.01 0.0081 19
31. 3
1
Coliform vi
khuẩn/10
0ml
-
4050 -
32. 3
2
Total radiation
level α
Bq/l 0.1 0.1 -
33. 3
3
Total radiation
level β
Bq/l 1.0 1.0 -
5.3.3. Soil contamination control
Due to the nature of operational activities, insignificant amount of chemicals will be
stored on site. Hence risk of soil contamination is negligible here.
130
5.3.4. Negative Environmental Impacts on Ecosystems and Socio-economic
Development
5.3.4.1. Minimize impact to ecological systems
The impacts to ecosystems when operating, mainly impact to upstream and
downstream aquatic ecosystems from discharge point of Ong Keo Industrial Zone
both due to water flow discharge and concentrations of pollutants if discharge
standards were violated. So following measures were implemented:
- Strict control of flow and wastewater discharge should be implemented,
especially during sudden change of river flow like heavy rain. The discharge
point is equipped with meter to control the flow of constant discharge;
- The quality of treated effluent will be closely monitored to ensure consistently
achieved QCVN 40:2011/BTNMT, column B standard. The central waste
water treatment plant is installed with automatic monitoring devices to daily
monitor important indicators. In the case of incident shows ineffective
treatment due to microbiology or damaged equipment, the treatment operation
will immediately be stopped and fix will be immediately carried out.
- Applications for discharge of wastewater into water sources for the central
waste water treatment plant will be logged to the authority, and only fully
qualified and capable worker will get the position
5.3.4.2. Minimization of socio-economic impact
The socio-economic impact caused by the WWTP mainly will affect people living in
downstream area of the discharge point if discharge standards were violated. So
similarly, the investors will also closely manage and monitor the flow and quality of
discharged wastewater according to QCVN 40:2011/BTNMT, column B.
5.3.5. Risk Impacts Control
- Apply measures deodorizing and disinfecting in every stage of the central
waste water treatment plant;
- The investor committed to applying technical measures necessary to ensure
emissions after treatment in accordance with QCVN 19:2009 BTNMT and
QCVN 20: 2009 BTNMT;
- Planting trees in high density around the central waste water treatment plant
(within the safety corridor from the station to the nearest residential area) to
prevent diffused dust toward residential areas. By design, green corridor is 10
m thickness;
- Moving out of the mud of the central waste water treatment plant; in
appropriate time and when the traffic density is lowest. Need specialized
vehicles used to transport sludge to reduce odor and dust emissions during
transportation.
131
5.3.6. Risk Mitigation Measures in Operation Phase
5.3.6.1. Sanitary and labor safety
Safety equipment
- For safety and security for the plant to work, lightning protection system will
be installed at the highest position of the central waste water treatment plant.
This will ensure safety against lightning strikes during the rainy season;
- For devices that use electrical power, fully equipped security system, wiring
and grounding safety are installed, inspected prior to operation. Also, IZ
Management Board will also set up building regulations on electrical grid
system of the WWTP;
- Industrial Zone management boards will grade each machines and devices
based on structure and other features, and are build safety rules for each
specific device
(1). Labor safety for workers
- Train workers about labor safety in the station. The Company will cooperate
will cooperate with the Department of Labor, War Invalids and Social Affairs
of Dong Nai to province safety training to workers in each operating stage;
- Based on the arranged of each stage of the production, tools and labor
protective gears for workers will be provided.
- In addition to the pollution control methods mentioned above, the plan to
reduce the impact of pollutants on the health of workers in the station will be
fully applied as follows:
- Perform well testing program and periodic health surveillance for workers,
- Ensure microclimate factors and working conditions to meet the standard
issued by the Ministry of Health to protect the health of workers;
- To control noise standards regulations to prevent occupational diseases caused
by the manufacturing process;
- Training and provide information on safety.
-
5.3.6.2. Fire and explosion Safety
(1). Fire safety measures
- Provide fire fighting equipment; fire protection systems around the area.
- Workers will be provided with directly training to handle and response against
fire and explosion threats;
- The combustible fuels will be stored in separate isolated locations, away from
potential sources of ignition. The solvent storage tank will be installed with
safety valves, temperature monitoring devices degrees, fire alarm and
automatic fire sprinkle;
132
- There are fire alarm systems, communication systems, alarm. The fire fighting
vehicles will be checked and in maintenance regularly;
- In areas with explosive or flammable risks, workers can't smoke, do not carry
lighters, matches, instrument that ignition, sparks, ...;
(1). Equipment
- Water valves for fire fighting; including the water tower and pond with fire
pumps
- Personal foam extinguisher; and other fire fighting equipment in all functional
areas;
- For the operator:
- Equip hood and exhaust fan for ventilation;
- Design and installation of safety devices for electrical system, regular
inspection to prevent short-circuit;
- The storage area of flammable materials and chemical ... will be installed with
fire alarm systems, water tanks, sand bags, fire extinguishers and protection
gears.
(2). Fire and explosion incident’s rescue :
- In places with flammable risks, fire alarm systems are installed, with
communication systems, alarm and is periodically test, under maintenance and
always in a state of operational readiness;
- The machinery working at high temperatures and pressures required routine
checked, and registered;
- The fuel is stored in isolated repositories, away from potential sources of
ignition and spark. Safe distance between the buildings is 12-20m for fire truck
to easily access;
- Prohibit smoking workers, bringing lighters, fire appliances emit flammable
region.
- Coordinate with the FPF Company in Dong Nai province plans to FPF, arrange
for the workers and volunteer team rehearse the plan was established.
5.3.6.3. Measures to prevent and respond to fuel leaks
To prevent and respond to fuel leaks (diesel oil), the investor will cooperate with the
authorities to examine the systems, storage tanks, and transport vehicles to set up
response plans as follows:
- Regularly check the safety of the fuel tank to repair, replace and fix leaks
promptly fuel;
- Fences surrounding areas fuel tank, tank placement by5-10m. Placing warning
signs, prohibition signs of fire, combustible materials close to the area;
133
- The transport of petroleum, chemicals, etc. (such as trucks, ...) must have
sufficient legal status, as well as to meet safety standards, technical regulations
applicable to transportation on roads;
- Remind employees to comply with FPF regulations during work.
Preparation for prevention, rescue incidents, under supervision and strict inspection
systems
5.3.6.4. Lightning protection
Installation of lightning protection systems on the highest position of the station to
attract lightning arresters, lightning pillars are arranged to protect all structures with
high protection calculation is 10 -14m;
5.3.6.5. Respond to the emergency from wastewater treatment plant
Incidents includes the breakdown of equipment such as pumps, agitators, chemical
magnet machines, (due to malfunction or power failure etc. ) or the death of
microbiology cultures may discontinue the operations. This will cause a large amount
of stagnant water, not treated can cause environmental pollution.
This problem can be prevented by regular inspection of the equipment’s technical
condition, repairing or replacing damaged machinery, and close monitoring to forecast
and intervening microbiological failure.
134
CHƯƠNG 6 ENVIRONMENTAL MANAGEMENT PLAN
6.1. MITIGATION OF NEGATIVE ENVIRONMENTAL IMPACTS
The management unit of the wastewater treatment plant of Ong Keo IZ is Tin Nghia
Corporation, who will be responsible for ensuring the requirements of standards/
regulations on environmental protection during the project’s construction and
operation.
The independent monitoring consultant unit will be hired by Tin Nghia Corporation to
directly supervise, manage, and monitor the environment.
Department of Natural Resources and Environment of Dong Nai province will
monitor the environmental protection activities in the province.
The units involved in the project’s environmental management program are described
in Table 6.1.
Table 6.1. The agencies involved in the environmental management program
No Unit Major Responsibilities
1 Construction
contractors
Implementing the proposed mitigation measures.
Reporting to Tin Nghia Corporation.
2 Implementation
Consultants
Monitoring and evaluating the implementation of the
environmental management plan proposed in the EIA report.
Reporting to Tin Nghia Corporation
3 Environmental
Monitoring
Consultant
Implementing and monitoring the environmental quality
assessment based on the monitoring parameters proposed in
the report.
Implementing the public consultation meetings to record
feedback and evaluation of the local people about the
project’s environmental management plan.
Reporting to Tin Nghia Corporation.
4 Department of
Natural Resources
and Environment
Monitoring and evaluating the mitigation measures proposed
in the construction phase through the report of Tin Nghia
Corporation and actual test results.
6.1.1. Mitigation Measures Performance Plan
6.1.1.1. Construction phase
(1). The organizational structure
The environmental issues will be controlled and monitored for:
135
- The process of foundation levelling;
- The construction and installation of machinery and equipment of the waste
water treatment plant;
- The process of building the infrastructure and support facilities;
- The process of transporting, storing equipment, materials, fuels;
- Activities in the field of workers.
(1). The specific items
The specific items in the environmental management plan in the construction phase of
WWTP include:
- Management of construction works;
- Management of dust pollution mitigation;
- Safety plan for the construction works;
- Management of sludge and waste water sedimentation;
- Management of noise pollution mitigation;
- Management of traffic and transportation facilities;
- Management of construction materials, equipment and warehouses, storage
yards;
- Management of municipal and construction wastes;
- Management of hazardous wastes
- Management of plan and construction progress of the works;
- Management of plan and schedule of installation of machinery and excavation;
- Planning for fire prevention and safety in construction;
- Plan to prevent and limit the adverse impacts;
- Communicate, educate, raise awareness of environmental protection for
workers;
- Implementation of the reporting system under the provisions of environmental
legislation on environmental protection;
- Complying the procedures for inspection of environmental protection;
- Implementation of environmental protection measures outlined in the approved
EIA report and complying with the Vietnam Environmental
standards/regulations;
- Complying with the provisions of the law on environmental protection.
Operational phase, in operation
136
(1). The organizational structure
The organizational structure of environmental management in the operational phase of
the waste water treatment plant is established before the operation. Staff in charge of
the environment will coordinate with the relevant units in the management of the
environment in every stage. The management program includes:
-
- Management of the station operation system in accordance with the technical
procedure;
- Management of technical infrastructure, machinery and equipment of the
station;
- Management and operation of the system in environmental treatment facilities;
- Management of waste, environmental risk and incidents.
(2). Management method
- Monitoring of emissions and waste sources in the station area;
- Management of solid and hazardous waste and waste waters;
- Developing the environmental monitoring plan in the project’s area;
- Developing and establishing the plan for the incident response;
- Training on safety and environment for employees;
- To monitor and store the operational results related to the environmental safety
of the WWT plant and ancillary facilities;
- Regularly reviewing and examining the effectiveness of the environmental
management plan and revising the plan as needed;
- The main waste treatment facilities in this phase are as follows:
Drainage system and wastewater collection;
Garbage bins (5-10 garbage bins with 200 litter capacity placed in the
gathering area and 10-20 garbage bin with 10 litter capacity located in
the office’s areas);
Lightning and fire protection system;
All environmental treatment facilities will be completed before the time
when the waste water treatment plant have been officially operated.
6.1.1.2. Summary of plans and mitigation measure
137
Environmental management program during construction and operational phases and
preventing risks of the project are summarized in Table 6.2, Table 6.3 and Table 6.4
below:
138
Table 6.2. Summary of the environmental management program of projects in the construction phase
Problems/im
pacts Code Mitigation measures applied
Laws document/regulations
referenced
Air Pollution
A1
The construction vehicles are regularly checked and have " quality control,
technical safety and environmental protection certificate" follow Decision
No. 35/2 5/QD-BGTVT on 21/07/2005
- TCVN 6438-2005: road
transport. Maximum
allowable limit of
emissions;
- Decision 35/2005/QD-
BGTVT - Decision issued
regulations on quality
control, technical safety and
environmental protection of
vehicles imported into
Vietnam
- QCVN 05: 2009/BTNMT-
national technical standards
for the ambient air quality
A2 Maintenance of vehicles and equipment daily and 6 months/time (or 8,000
km of road)
A3 Do not incinerate waste onsite
A4 Monitoring air quality emissions, dust, noise onsite and in surrounding area
Dust
Emissions
D1 Transporting waste outside construction work as soon as possible
- QCVN 05: 2009/BTNMT
- National Technical
Regulation on the ambient
air quality
D2 Cover trucks to prevent spillage of soil, sand, or dust materials in transit.
D3 The Contractor shall be responsible for compliance with national regulation
for the ambient air quality.
D4
The Contractor shall ensure that dust emission is minimal and does not
become a nuisance to local residents. Contractor shall implement dust
control plan to maintain safe working environments and minimize
disturbance to the residential/housing around.
139
D5
Contractor shall implement measures to minimize dust emissions when
necessary (such as spraying water on the road construction, cover material
storage areas, etc.)
D6
Excavated soil and material stockpiles should be covered to prevent
dispersal by wind and the positions of the stockpile material must consider
wind direction and the location of sensitive areas.
The
disturbance
of vegetation
and
ecosystems
TR1
The Contractor shall prepare measures to protect vegetation outlined in the
environmental management plan approved by the building construction
engineer, according to relevant regulations. Clearance plan must be
approved by the Construction Supervision Consultant and strict compliance
by the contractor
The Environmental
Protection Law No
52/2005/QH11
Noise and
vibration
N1 Avoid building at night (01 am to 6 am) - QCVN 26:2010/BTNMT -
National technical
regulation on noise
-QCVN 27:2010/BTNMT:
National Technical
Regulation on vibration
N2 The contractor is responsible for compliance with the laws of Vietnam on
noise and vibration.
N3
All cars must have "Certificates of quality control, technical safety and
environmental protection" Decision No. 35/2 5/QD-BGTVT avoid excess
emissions noise from the old machine, the hips are appropriate renovations.
Increased
turbidity in
surface
water
TU1 Ensuring the technical requirements for waste water treatment and runoff
TU2 Better management of soil erosion and sediment
Domestic
wastewater
from
workers
WW1 Construction and use of temporary portable toilets in the Industrial Zone - QCVN 14:2008/BTNMT:
National technical
regulation on domestic
wastewater
WW2 Building a septic tank and wastewater collection and sewage when
completed
WW3 The Contractor shall be responsible for compliance with the laws of
Vietnam regarding wastewater into water sources
140
WW4
Wastewater exceeded the value allowed by Vietnam standards/laws must be
collected in a septic tank and transported outside by units licensed
collection
Drainage
and
sedimentatio
n control
SW1 Periodic dredging of drains
- TCVN 4447:1987 The
scope of construction and
acceptance
- Circular 22/2010/TT-BXD
of safety in construction
- QCVN 08:2008/BTNMT
- National Technical
Regulation on surface water
quality
SW2
To avoid runoff containing sediment can affect water sources, construction
of the sludge collectors, slow flowing stream or divert the flow affect the
vegetation.
SW3 Ensure drainage system is always maintained, Clean mud and obstacles,
check the condition of the drainage system periodically
SW4 To maintain the existing conditions and not disturb the position of the area
by the construction activities
SW5 Slope must be maintained with the appropriate technical characteristics of
the outfall construction
SW6
The Contractor shall comply with the detailed design of the drainage system
included in the plans, proposals to prevent rain causing local flooding or
erosion, resulting in sediment affect local water resources
Groundwater
pollution due
sewage leak
GW1 Leaks in the drainage system must be detected and repaired promptly
- QCVN 09:2008/BTNMT:
National Technical
Regulation on groundwater
quality
Solid Waste
Management
W1
Before construction, process control of solid waste shall be prepared by the
contractor and environmental management plan includes the construction
management and monitoring plans. Decree 59/2007/ND-CP on
the management of solid
waste W2 Before to construction, all discharge permits must be passed
W3 No burning, burying or dumping of solid waste onside
141
Chemicals
and
hazardous
waste
HW1
Chemical waste in any form must be disposed in appropriate landfills and
approved at the request of local authorities. The contractor must have a
certificate of treatment.
Circular No. 12/2011/TT-
BTNMT on Hazardous
Waste Management
HW2
Oils, lubricants, cleaning materials, etc. from vehicle maintenance and
machinery will be collected in the tank and recycled or disposed by
registered hazardous waste contractors.
HW3
The relevant authorities (IZ Management Board and the Department of
Natural Resources and Environment) will be notified in the case of oil, or
chemical spills. Remedial measures after oil spills or accidents must be
carried out immediately. In this case, the contractor shall provide a report
explaining why oil spills or accidents, state out the done remedial work, the
consequences/damage from the spill, and proposed measures overcome.
HW4 Toxic chemicals stored properly and labelled containers and lock
HW5 Train and raise awareness for workers to respond against toxic chemicals in
the workplace
Traffic
Management T1
Prior to construction, consult with local governments, communities and the
traffic police
- Road Traffic Law No.
23/2008/QH12
- Construction Law
No16/2003/QH11
- Circular No. 22/2010/TT-
BYT: Regulations on
occupational safety in
construction work
Temporary
stop
providing
utility
services
U1 Provide information to the affected families about work schedule as well as
suspended plans
Decree No. 73/2010/ND-
CP: The sanctioning of
administrative violations in
the field of security and
order, social security
Safety and HS1 Limiting speed at construction site Circular No. 22/2010/TT-
142
community
workers
HS2 Avoid transport during peak hours BYT: Regulations on
occupational safety in
construction
- Directive 02/2008/CT-
BXD on reorganizing and
strengthening security
measures ensure
occupational safety,
occupational health units in
the building industry
- TCVN 5308-91: Technical
regulations for safety in
construction
- Decision No. 96/2008/
QD-TTg about demining.
HS3 Installation of lighting at night
HS4 Equip workers with protective equipment
HS5 Training workers on safety regulations and ensure their compliance
HS6 Ensure construction site safety, security and order
HS7 Provide protective clothing or protective gloves if they may be exposed to
chemicals and sludge
HS8 Prepare and implement action plans to deal with risks and emergency
situations as well as prepare emergency services at construction site
HS9 The Contractor shall comply with the regulations of Vietnam about labor
safety.
Communicat
ion with the
local
community
C1 Provide local communities and workers at the site the ECOP (Vietnamese)
and the Environmental Protection documents related.
- Decree No. 73/2010/ND-
CP: The sanctioning of
administrative violations in
the field of security and
order, social security
C2
- Provide information for the groups affected by the project (such as local
governments, businesses and households affected, etc.) through
community meetings before starting construction. Supply contact
information to interested parties so they can get information about the
active site, project status and results of the project;
- Provide all information, especially technical solutions, with language
understandable to the general public. Inform interested citizens and
officials through the preparation of an information sheet. Inform the
press, while conducting the work of the project.
C3 Allow community supervision and publish related information requirements
as well as the progress of the project;
C4 Feedback is written form in timely and accurate manner;
143
Table 6.3. Summary of environmental management programs in the project operation phase WWTP
No Impacts Intensity Mitigation Measures Monitoring Unit Funds
1 Pollution at the outlet Long-term - Regularly monitor
- Construction warning signs
at appropriate locations
- Regular manhole, sewer
- Reduce the risk of sewage
spill
- Monitor discharged flow
from each business
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
The operating budget
of the water
company, WWTP
2 Groundwater
Pollution
Long-term - Monitoring and control of
groundwater quality in the
area
- Prevent leakage of
anaerobic tank
- Prevent leaks at the
connection point or
transition within the
sewage pipe
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
The operating budget
of the WWTP
144
3 Groundwater
Pollution
Long-term - Train O & M to monitoring
workers to assess quality
monitoring and evaluate the
performance of the WWTP
- Construction signs warning
people about the risks related
to water environment
- Focus on public
communication
- Respond and repair
immediately if accident
occurred
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
4 Smell Long-term - Ensure radius of at least 300
m buffer zone
- Planting trees in the buffer
zone to create landscapes and
prevent odor dispersion
- Regular maintenance of the
processing unit
- Solve problems or accidents
during operation
- Clearance of the environment
around the pond
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
5 Noise Long-term - Planting tress
- Carry out proper
maintenance on equipment
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
145
6 WWTP Team Long-term - Plan to collect and handle
solid waste
- Train workers to deal with
wastes appropriately
- Regularly collecting mud
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
7 Sludge Management Long-term - Quality control mud to plan
appropriate treatment
- Dry and use as fertilizer or
landfill treatment based on the
quality of sludge
- Reducing spills along the
transport routes especially for
dusts what may contain heavy
metals and pathogens (risks of
food contamination, skin-
related disease, and respiratory
system)
- Workers must be equipped
with appropriate safety
clothing to prevent direct
contact
- Dried sludge will be dumped
at the landfill or specially
buried in case it does not meet
quality standards.
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
8 Health and safety Long-term
and frequent
- Training safety and industrial
hygiene
- Health checks for all
employees, provide good
personal hygiene
IZ Management Board, the
Department of Natural
Resources and Environment,
IZ Infrastructure Development
Company
146
- At least two workers
working in a shift
- Prepare specific H&S
guidelines for operating
WWTP
Table 6.4. Summary of counter measures to minimize environmental risks of the project
No. Circumstance Action Plan Responsibilities
1 Complaints from nearby industrial
facilities and the community about
environmental issues of construction
activities and operation
- Immediately implement remedial measures if
possible
- Discuss with investors, local authorities to thoroughly
resolve conflicts
- Recorded in the log
Contractor
2 Incident or accident construction,
operation
First aid and immediate transport to the nearest
hospital if necessary
Workers and residents
- There are warning signs in dangerous locations
- Make records of incidents or accidents
The contractor, WWTP, IZ
infrastructure development
company, IZ Management
Board
3 WWTP stops operation Store untreated sewage, build biological tank if
possible
WWTP, IZ infrastructure
development company, IZ
Management Board
Regular inspect and backup systems/devices data
There are danger signs and report to the authorities
Avoid overloading wastewater from business
Training of operational staff regularly monitor
Check out the design and participate on plan to build
new WWTP by the Industrial Zone
Prepare for an action plan to respond randomly
4 Improper discharge of sludge Contracts with agencies concerned are properly WWTP
147
No. Circumstance Action Plan Responsibilities
discharged mud if found harmful to the environment
and human health
Prepare reports and regular inspection of all generated
sludge
Issuing strict penalties for violations IZ Management Board, the
Department of Natural
Resources and Environment
5 Fire - Notify authorities (especially the fire station).
- Rescue trapped people in the danger zone.
- Actively isolate the flame with available equipment
Contractors, industrial
establishments/enterprises,
WWTP, IZ Infrastructure
Development Company, IZ
Management Board
Follow according to guidance until authorized unit
arrive (especially in the case of explosions caused by
chemicals ...).
The contractor, WWTP, IZ
infrastructure development
company, IZ Management
Board
Supporting the functional unit, local government to
establish security belt around dangerous zones.
- Check the condition and safety of fire or explosion in
the area; make sure this problem does not persist.
- Suspend operations if violation of fire safety
conditions is persisted.
The contractor, WWTP, IZ
infrastructure development
company, IZ Management
Board
148
No. Circumstance Action Plan Responsibilities
6
Electrical-related accidents
- Disconnect the power source from problem area and
the surrounding area
- Immediate rescue people from the danger zone
according to guideline
- Find out the cause of the incident or accident, check
the power source, wires and contacts ...
The contractor, WWTP, IZ
infrastructure development
company, IZ Management
Board
Making records the incident or accident case
6.1.2. Implementation plan for Safety, Health, Environment and Transport program
Implementation plan for Safety, Health, Environment and Transport program during construction phase shown as in Table 6.5.
Table 6.5. Implementation plan for Safety, Health, Environment and Transport program in construction phase
Issues Mitigation measures Vietnamese
code/regulation Execution Supervision
Traffic
management
- Cooperation with local government, community, and
traffic police to manage the traffic density;
- If number of vehicle trips significantly increase, the
construction plan should be previously approved.
Determination of transportation route, especially of
heavy vehicles away from sensitive sites such as schools,
hospitals, and markets;
- Avoiding transportation during peak hours and
arranging transportation instructors at the start and the
end of construction areas to avoid congestion at peak
hours;
- Law on traffic and
transportation No.
23/2008/QH12
- Law on construction
No. 16/2003/QH11
- Decree No.
22/2010/TT-BXD on
regulation of
construction safety
Contractors Investors +
supervision
consultants
149
Issues Mitigation measures Vietnamese
code/regulation Execution Supervision
- Install the lighting system at night time if this is
necessary to ensure the safe traffic circulation;
Health and safety
working
- Limiting speed at the construction site;
- Avoiding transportation in the peak hours;
- Providing temporary passage through the dug trench as
needed;
- Installing the lighting system for night time;
- Equipping workers with labor protection instruments;
- Avoiding long exposure to wastes;
- Training workers on occupational safety regulations;
- Preparing and implementing action plan to cope with
risk and emergency as well as prepare emergency aid
service at construction site;
- Installing fences, barriers, dangerous warning site
around the construction area which showing potential
danger to public p.
- Putting signals or warning symbols near the outlets of
WWTP
- Decree No.
22/2010/TT-BXD on
regulation of
construction safety
- Instruction No.02
/2008/CT-BXD on
safety and sanitation
issues in construction
agencies
- TCVN 5308-91:
Standard on safety in
construction
- Decision No.
96/2008/QD-TTg on
land clearance
Contractors Investors +
supervision
consultants
Program Implementation Plan safety, health, environment and transportation operations in the period expressed as:
Table 6.6. Program Implementation Plan safety, health, environment and transportation in the operational phase
Contents Mitigation Measures Laws/Regulations Monitoring
150
Contents Mitigation Measures Laws/Regulations Monitoring
Health and safety
working
- Training and provide adequate equipment to protect the
health of workers;
- Laborers working in wastewater treatment station is equipped
with earplugs to reduce noise;
- Check the periodic health workers to operate the wastewater
treatment station.
Management
Board of
wastewater
treatment station
Management Board of
wastewater treatment
station
151
6.1.3. The community information and community relations
During construction and operation of wastewater treatment plant Ong Keo Industrial
Zone, Phase 1, the project formulation, approval and publicly listed environmental
management plans at the headquarters of the commune People's Committee Phuoc
Khanh to get the inspection and supervision of residents. Environmental management
plan is established including the following content:
- The organization operation of the department responsible for environmental
protection projects;
- Planning of education and raising awareness of environmental protection
projects;
- Responsibilities of the project in implementing the solutions and measures to
minimize negative impacts and prevent and respond to environmental incidents
during the construction phase and operation of the wastewater treatment plant;
- Planning operation of environmental protection;
- Planning monitoring of waste generated sources; ambient monitoring and
environmental monitoring content other in the construction phase and phase
wastewater treatment station officially went into operation.
6.2. ORGANIZATION OF ENVIRONMENTAL MANAGEMENT AND
RESPONSIBILITY
6.2.1. Environmental Department of Ong Keo IZ
6.2.1.1. Functions and Tasks
(1). Functions
- To advise the corporation manager on environmental management, and
wastewater treatment facility as well as to provide environmental consulting
services for the customers.
- To elaborate and propose environmental management plans, schemes and
measures; the centralized wastewater treatment facility operation plan and to
provide environmental consultation services for enterprises in and outside Ong
Keo IZ.
- To cooperate with other competent agencies and customers in management the
industrial park environment in compliance with “the Regulation on industrial
parks, export processing zone and high-tech parks” which was promulgated
together with Decree No.36/CP in April 24, 1997 of the Government as well as
other related regulations.
- To operate the centralized wastewater treatment system and other activities
152
related to environment in the industrial park.
- To inspect, supervise, operate the centralized wastewater treatment facility and
wastewater quality of enterprises in Ong Keo and conduct repairing in case of
failure.
- To treat wastewater of Ong Keo IZ meeting Vietnam standard prior
discharging to the environment.
- To manage, operate and utilize the centralized wastewater facility effectively
and efficiently.
(1). Tasks
- Organise plans and required activities of the treatment plants, monitor
business-related environmental contracts, and propose the Director for approval
and implementation;
- Supervise land-renting investors on their contract to meet Environmental
Protection laws;
- Ultilise the available resources, apply technology creativities on the
managements of the treatment plants effectively;
- Supervise the effluent quality standard to ensure the treated waste water from
Nhon Trach 3 meet all regulations before being released into the environments;
- Cooperate with Technical – Infrastructure Departments to maintain the plant
and immediately repair any faults of the systems onsite;
- Hold responsibilities over the contract with environmental consultants; wastes
treatments agencies, plant designers, drainage system supervisors and other
economical-technical- environmental customers;
- Implements tasks from the Directors;
- Follow Organisational Regulations and Activities to promote company
business;
- Implement operation plans and business developing activities as assigned by
the company directors;
- Ultilise available resources, promote upgrades, apply scientific and technical
innovations during the plant operation phase;
- Implement applied designs for the investors of company within Ong Keo IZ;
- Maintenance the infrastructures of the centralised waste water treatment plant;
- Ultilise the assets, budgets of the company to continuously increase the
efficiency of the business;
- Commit to provide and update information as requests by the company
(2). Organization Structure
153
Figure 6.1. Environmental Department Hierarchy of Ong Keo IZ
6.2.2. CETP operation Team
6.2.2.1. Function and Task
(1). Function
- To manage and monitor compliance with the environment regulations
stipulated at Decree No. 36/CP dated April 24, 1997 of the Government on
“Regulation on industrial parks, export processing zones and high-tech parks”.
To advise the corporation director on issues related to environment of Nhon
Trach IZ; to perform activities of the treatment facilities and other related
activities related to environment in the industrial park.
- To inspect, monitor, operate the system and take remedial measures of the
station and enterprises in Dat Do I IZ prior transferring to the centralized
treatment system.
- To treat wastewater of Ong Keo IZ, Phase 1 in compliance with Vietnam
standards prior discharge into environment.
- To manage, operate functions of the treatment facility effectively and
efficiently. .
(2). Tasks
- To perform the regulation on the Corporation organization and operation to
promote business;
- To develop proper operation and business promotion plan, and submit to the
corporation director for approval and organize the implementation;
- To exploit available resources effectively, R&D activities to improve the
operation efficiency;
Team leader
Env Consultants
Lab staffs
Supervisor
Operating Staffs
Maintenance
Staffs
154
- To provide consulting services in designing, connecting, construction and
supervision for investors in Ong Keo IP, Phase 1;
- To operate, maintain and repair the wastewater discharge infrastructure and
centralized treatment system properly;
- To manage and develop the assigned fund effectively;
- To be compliance with information and reporting policy of the company as
well as existing regulation;
- To perform other assigned tasks.
6.2.2.2. Organization Structure of CETP operation Team
Figure 6.2. Organization Structure of CWTP operation Team
6.3. ENVIRONMENTAL MONITORING PROGRAM
6.3.1. Environmental monitoring in construction phase
6.3.1.1. Waste Monitoring
(1). Solid Waste Monitoring
Domestic wastewater volume would be recorded dailty. It should be reported
periodically (one in every three monts) to the environment administration agency.
(2). Wastewater Monitoring
- Selected parameters: pH, BOD5, COD, SS, Ammonia, Phosphate, Chloride,
surfactant, mineral oil;
- Monitoring location: 01 locations at worker camp;
- Monitoring frequency: One in every three months;;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 14:2008/BTNMT, column B.
6.3.1.2. Ambient Environment Monitoring
Site supervisor
01 person
Lab staff
01 person
Operating staffs
03 peple
Maintenance staffs
01 person
155
(1). Air Quality Monitoring
- Selected parameters: Temperature, humidity, wind velocity, dust, SO2, NO2,
CO, THC, H2S, noise, vibration;
- Monitoring location: 01 locations in the project area and 01 locations in
surrounding residential quarters;
- Monitoring frequency: One in every six months;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 05:2013/BTNMT, QCVN 06:2009/BTNMT,
QCVN 26:2010/BTNMT, QCVN 27:2010/BTNMT.
(2). Surface Water Quality Monitoring
- Selected parameters: Temperature, pH, turbidity, DO, BOD5, COD, SS, N-
NH4, N-NO3, NO2, total N, total P, total Fe, Pb, oil and grease, foamer, E.
Coli, total Coliform;
- Monitoring sample number: 02 samples.
- Monitoring location: 01 locations in Bang canal and 01 location in Long Tau
river ;
- Monitoring frequency: One in every six months;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 08:2008/BTNMT, column B2.
(3). Groundwater Quality Monitoring
- Selected parameters: pH, color, hardness, SS, Cl-, NH4+, Cyanic, NO3-, NO2-,
Sulfate, Fe, Mn, As, E.Coli, Total Coliform;
- Monitoring sample number: 01 samples.
- Monitoring location: 01 locations in the project area;
- Monitoring frequency: One in every six months;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 09:2008/BTNMT.
(4). Soil and Sediment Quality Monitoring
Selected parameters: Cadmic, Chrome, As, Pb, Hg, Zn, Oil, total hydrocarbon;
- Monitoring sample number: 01 samples.
156
- Monitoring location of soil quality: 01 locations in the project area.
- Monitoring location of sediment quality: 01 locations in Long Tau river;
- Monitoring frequency: One in every six months;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 03:2008/BTNMT and refer to Nederland
Standard (VROM -1994).
6.3.1.3. Monitoring of hydrology, erosion, sedimentation of the project area
- Monitoring of hydrology, deposition process, erosion, canals in the project
area, flooding;
- Monitoring frequency: One in every six months
6.3.2. Environmental monitoring in operation phase
6.3.2.1. Waste Monitoring
(1). Wastewater Monitoring
- Selected parameters: pH, color, BOD5, COD, SS, Ammonia, total N, total P,
mineral oil, total phenols, Pb, Cd, Cr3 +, Cr6 +), E. coli, total coliforms;
- Monitoring sample number: 02 samples.
- Monitoring location: 01 locations at the influent of CWTP and 01 locations at
the effluent of CWTP;
- Monitoring frequency: One in every three months;;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 40:2011/BTNMT (Column B, Kq=0.9, kf=0.9).
(2). Solid Waste Monitoring
Domestic solid waste volume will be collected daily. The recorded volume will be
reported to the environmental administration agency periodically (one in every three
months).
(3). Sludge Monitoring
- Selected parameters: mineral oil, organic matter, heavy metals (As, Cd, Cu, Pb,
Zn, Hg);
- Monitoring location: sludge of CWTP;
- Monitoring frequency: One in every three months;;
157
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 07:2008/BTNMT; QCVN 50 : 2013/BTNMT
6.3.2.2. Ambient Environment Monitoring
(1). Air Quality Monitoring
- Selected parameters: Temperature, humidity, wind velocity, dust, SO2, NO2,
CO, THC, H2S, noise, vibration.
- Monitoring sample number: 02 samples.
- Monitoring location: 01 in the project areas and 01 in the surrounding
residential quarters.
- Monitoring frequency: One in every six months.
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 05:2013/BTNMT, QCVN 06:2009/BTNMT,
QCVN 26:2010/BTNMT, and QCVN 27:2010/BTNMT.
(2). Surface Water Quality Monitoring
- Selected parameters: Temperature, pH, turbidity, DO, BOD5, COD, SS, N-
NH4, N-NO3, NO2, total N, total P, Total Iron, Pb, Oil and grease, foamert, E.
Coli, total Coliform.
- Monitoring sample number: 02 samples.
- Monitoring location: 02 location distance 300m to upstream and dowstream of
point discharge
- Monitoring frequency: One in every six months.
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 08:2008/BTNMT (column B2).
(3). Groundwater Quality Monitoring
- Selected parameters: pH, turbidity, hardness, SS, Cl-, NH4+, Cyanide, NO3-,
NO2-, Sulfate, Fe, Mn, As, E.Coli, Total Coliform.
- Monitoring sample number: 01 samples.
- Monitoring location: 01 in the project area.
- Monitoring frequency: One in every six months.
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 09:2008/BTNMT.
158
(4). Soil and Sediment Quality Monitoring
- Selected parameters: Cadmic, Chrome, As, Pb, Hg, Zn, Oil, total hydrocarbon;
- Monitoring sample number: 02 samples.
- Monitoring location of soil quality: 01 locations in the project area.
- Monitoring location of sediment quality: 01 locations in Long Tau river;
- Monitoring frequency: One in every six months;
- Sampling equipment and analysis method: Standard method;
- Comparison standard: QCVN 03:2008/BTNMT and refer to Nederland
Standard (VROM -1994).
6.3.2.3. Hydrology, erosion and sedimentation monitoring
- Monitoring of hydrology, deposition process, erosion, canals in the project
area, flooding;
- Monitoring frequency: One in every six months.
6.3.3. Monitoring and Reporting Arrangements for ESMF
Project construction of Ong Keo IZ wastewater treatment plants is VIPM Project by
the World Bank funding to build a system to wastewater treatment for industrial areas
of the participating local.
During implementation, meetings will be organized by the SPMGs inviting all EAs in
the state for providing information on the progress of the project work. The project
cycle for an investment under the NGRBA program and the interface with the ESMF
requirements are summarized Table 6.7.
Table 6.7. Mitigation, monitoring, responsibility and timeline
No. Impact Monitoring Measures Responsible
Agency
Timeline
1 Land
acquisition
Regular internal
monitoring by the
EA and SPMG and
periodic evaluation
EA 12 months from the
start date.
Compensation to be
paid before the start of
civil works. 2 Acquisition of
house/
structure
Regular internal
monitoring by the
EA , SPMG and
periodic evaluation
3 Loss of
livelihood or
source of
Regular
internal monitoring
by EA; midterm and
EA 12 months from the
start date of the
activities of the priority
159
livelihood end term evaluation investment. Assistance
to be paid before the
start of civil works.
4 Loss of access
to private and/
or common
property
Regular internal
monitoring by the
EA; ; midterm and
end term evaluation
EA, ESMF
Auditors
12 months from the
start date of the
activities of the priority
nvestment.
Assistance to be paid
before the start of civil
works.
5 Displacement
of
Non
Titleholders
Regular internal
monitoring by the
EA; a; midterm and
end term evaluation
EA, ESMF
Auditors
6 Group support
to Tribal
community
Regular internal
monitoring by
the social
development
professional of EA
along with NGO;
midterm and end
term evaluation
EA; District
Administrati
on; ESMF
auditors
12 months from the
start date of the
activities of the priority
nvestment,
followed by annual
audit
7 Gender Action
Plan
Regular internal
monitoring by the
social development
professional of EA
along with NGO;
midterm and end
term
evaluation
EA, ESMF
Auditors
12 months from the
start date of the
activities of the priority
nvestment,
followed by annual
audit
6.4. TRAINING PROGRAM
To enhance the capacity to cope with environmental problems that may occur in the
central wastewater treatment plant of Ong Keo Industrial Zone, Phase 1, the project
owner will implement the following measures:
- Periodically, the staffs directly working in the central wastewater treatment
plant will be trained and guided on fire and exploitation control methods;
- Organizing the training, assigning response tasks when incidents results in
shutting down of the WWTP happened. This problem can be further prevented
by periodic inspection of the technical condition of the equipment, promptly
repairing and replacing the damaged machinery, the operators are trained
adequately;
160
- Equipping with tools and protective gear for employees working in accordance
with their works;
- Training workers about labor safety in the WWTP. The company will also
cooperate with the Occupational Safety Division within Department of Labor,
War Invalids and Social Affairs of Dong Nai province to organize training on
safety rules and operating equipment;
- In addition to the above measures, the plan to reduce the impact of pollutants
on the health of workers at the central wastewater treatment plant will be fully
applied as follows;
- Have periodic health examination for staffs working in the factory;
- To ensure the microclimate factors and working conditions complying with the
standard issued by the Ministry of Health to protect the worker’s health;
- To control the noise level to meet the standards and regulations to prevent
occupational diseases caused by the manufacturing process;
- To provide training and information on sanitation and safety.
6.5. COST ESTIMATION FOR ENVIRONMENTAL MANAGEMENT AND
MONITORING PROGRAM
Total fund for implementation of the environmental monitoring and management plan
is presented in the following table:
Table 6.8. Total fund of annual environmental monitoring and management program
Item Cost (VND/year)
Environmental Management Program 71,000,000
Environmental Monitoring Program
I Construction Stage 64,160,000
01 Wastewater monitoring 4,040,000
02 Solid waste monitoring 5,000,000
03 Air quality monitoring 16,880,000
04 Surface water quality monitoring 14,320,000
05 Groundwater quality monitoring 3,320,000
06 Soil and sediment quality monitoring 15,600,000
07 Hydrology, erosion and sedimentation monitoring 5,000,000
II Operation Stage 49,300,000
01 Wastewater monitoring 8,080,000
02 Solid waste monitoring 10,000,000
03 Sludge monitoring 3,760,000
04 Air quality monitoring 8,440,000
05 Groundwater quality monitoring 1,660,000
06 Surface water quality monitoring 7,160,000
161
Item Cost (VND/year)
07 Soil and sediment quality monitoring 5,200,000
08 Hydrology, erosion and sedimentation monitoring 5,000,000
Total 184,460,000
So the total fund for the environmental management is 71 million VND and the
environmental monitoring is 113.460 million VND. In particular, fund for the annual
environmental monitoring is 64.16 million VND during the construction phase and is
49.3 million VND during the operation phase.
162
CHƯƠNG 7 PUBLIC CONSULTATION
7.1. GOALS OF PUBLIC CONSULTATION
7.1.1. Appraisal Agency
Based on the consulting from local authorities and the public communities from the
affected areas, this activity will assist the Appraisal Agency to have a more completed
view over the project, and make it easy for project evaluation
7.1.2. The Project Owner
The project owner will receive feedback from local government and the public
communities then provide realistic assessments and effective mitigation proposals. In
the same time, the project owner will hold up responsibilities to carry out mitigation to
reduce long and short-term negative impacts from the projects
Furthermore, the project owner will create understandings between the public and the
WWTP staffs.
7.1.3. Consulting Agency
Consulting agency will receive feedback from local government and the public
communities from affected areas then provide realistic assessments and effective
mitigation proposals.
7.1.4. The People’s Committee and Fatherland Front Union
Public consultation will assist the Commune People Committee and Fatherland Front
Union more understandings on the projects through these points: benefits from
carrying out the Project, the environment impacts, and negative effects mitigation
measures.
This will create more understanding from local government toward the project
7.1.5. The Affected Public Communities
Public consultation will help the public communities understand more on the projects:
the benefits this Project will bring, the environment impacts, and counter measures on
negative impacts.
This will create more understanding from the public communities; including their
raise of concerns toward the project
163
7.2. PUBLIC CONSULTATION ACTIVITIES
During the EIA of the overall project Ong Keo IZ (including the build the CWTP -
Phase 1 Ong Keo IZ with a capacity of 3,000 m3/day item), the project owner and
consulting agency has consulted the People Committee, Fatherland Front Union and
public communities of Phuoc Khanh commune. However, when the component build
the CWTP - Phase 1 of Ong Keo IZ with a capacity of 3,000 m3/day, the investor has
not conducted consultations the People Committee and Fatherland Front Union again.
The contents needed for public consultation in the EIA process are including:
- Consultations on the scale and nature of the project;
- Consultations on the project’s impact on the natural and socio-economic
environment;
- Consultation on measures to minimize the project’s adverse impacts;
- Consultations on other matters (if any).
-
- Project owner have consulted these groups:
- People Committee and Fatherland Front Union of Phuoc Khanh commune (the
project location);
- The public communities, including residents lives nearby and will be affected
by the projects.
The planned activities are:
- Toward the People Committee and Fatherland Front Union of Phuoc Khanh
commune, the project owner has sent official dispatch to these local
governmental bodies. The official dispatch is attached along with this report;
- Towards the residents who living nearby and under effects of the project, the
project owner have directly reviewed and sent a survey questionnaire to take
their opinions and feedbacks about the projects. The survey questionnaire is
also attached with this report.
Note: Results consultation of Phuoc Khanh Commune People’s Committee are
presented in the Appendix II.
7.3. RESULTS OF PUBLIC CONSULTATION
7.3.1. Results of Public Consultation
Results of the household’s survey about the central wastewater treatment plant are
presented in the Appendix:
According to the results of consultation of public:
164
- Supply water: all residents (28/28) were using well drilling waters. Long Tau
river water is absolutely not used for domestic, irrigation and livestock
purposes;
- Status of air pollution: according to feelings of the majority of people (24/28),
the air is not polluted. Among those, there are some people (4/28) felt
unpleasant dust during dry season by vehicles through;
- State of water pollution of the Long Tau river: According to the majority of
people (27/28), The water quality of Long Tau river is not polluted. Among
those, there are some people (1/28) living near with Long Tau river, who found
to have grease and oil on Long Tau river at some time and flood in tidal;
- For groundwater quality: According to the majority of people (28/28) who
extracted groundwater contaminated with alum.
- For health situation: the majority of people (26/28) have no respiratory-related
issues, intestinal or skin diseases. But there are some people (2/28) to have
sinus disease or dengue fever;
- For proposals: the majority of people (28/28) who did not have
recommendations about the state of the environment in which they live.
Through investigations, public consultation of people living in the downstream and
upstream along the Long Tau river and Bang canal, there were a lot of different
opinions on their actual sense about the current status of air, water, groundwater and
health. However, at the present, the WWTP of Ong Keo IZ has not come into
operation; therefore, the wastewater is not discharged into Bang canal and Long Tau
river. The project owner of the central waste water treatment plant of Ong Keo
Industrial Zone has some explanations are as follows:
This phenomenon is caused by Ong Keo Industrial Zone is located in the Long Tau
river downstream, Long Tau river flow entrained waste from upstream, or Long Tau
river is polluted due to untreated wastewater thoroughly of businesses in the industrial
park Ong Keo or stormwater runoff. About this problems, Management Board of Ong
Keo industrial zone will select time discharge and thoroughly treat wastewater before
it is discharged into the receiving water Long Tau river.
7.3.2. Opinions of Local Government
7.3.2.1. Opinions of Phuoc Khanh Commune People’s Committee
After reviewing the notice of the project’s main investment categories, environmental
issues, the environmental protection measures, Phuoc Khanh Commune People’s
Committee has the following comments:
7.3.2.2. Comments on the project's adverse impacts to the natural environment and
165
socio-economic conditions:
The People Committee of Phuoc Khanh Commune approve the impact assessment of
pollution concentrations and waste loads discharged by the WWTP to natural
conditions and environment.
7.3.2.3. Opinions about the plan to minimize the project’s impacts on natural
environment and the socio-economic development:
The People Committee of Phuoc Khanh Commune recommend the project owner to
effectively implement the stated plan to minimize the potential impacts such as solid
waste, wastewater, air emission, security and social order during the construction and
operation of the project as committed as in the EIA report.
7.3.2.4. Recommendations for project owners:
The People Committee of Phuoc Khanh Commune recommended the project owner to
implement as the commitments in the EIA report. During the construction phase, if
any risk arising, the responding measures should be quickly applied.
The project owner should have good relationships with local authorities to manage the
related issues to provide new jobs for the local people living in the project area.
7.3.2.5. Opinions of Phuoc Khanh Commune Fatherland Front Union
After reviewing the notice of the project’s main investment categories, environmental
issues, the environmental protection measures, Phuoc Khanh Commune Fatherland
Front Union has the following comments:
Comments on the project's adverse impacts to the natural, environment and socio-
economic conditions:
Phuoc Khanh Commune Fatherland Front Union agrees with the impact assessment of
pollution concentrations and waste loads discharged by the WWTP to natural
conditions and environment.
(1). Opinions about the plan to minimize the project’s impacts on natural
environment and the socio-economic development:
Phuoc Khanh Commune Fatherland Front Union recommend the project owner to
effectively implement the stated plan to minimize the adverse impacts such as waste
water, air emission, security and social order during the construction and operation of
the project as committed in the EIA report.
(2). Recommendations for project owners:
166
Phuoc Khanh Commune Fatherland Front Union recommend the project owner to
effectively implement the stated plan to minimize the potential impacts such as solid
waste, wastewater, air emission, security and social order during the construction and
operation of the project as committed as in the EIA report.
The project owner should have good relationships with local authorities to manage the
related issues to provide new jobs for the local people living in the project area.
7.4. PUBLIC INFORMATION DISCLOSER
During the construction and operation of the central wastewater treatment plant of
Ong Keo IZ, Phase 1, the project owner will prepare, and publicize the environmental
management plan at the office of the People's Committee of Phuoc Khanh Commune
for public monitoring on the contruction phase and operation phase of the project.
In addition, EIA report English version will publish on the Web site of the
Environmental Protection Fund Vietnam (PPF), Infoshop on Washington DC and
Vietnam Development Information Centre (VDIC).
7.5. COMMITMENT OF THE PROJECT OWNER
7.5.1. Undertaking Measures for Adverse Impacts Mitigation
Tin Nghia Corporation- the project owner of construction of the central wastewater
treatment plant with capacity of 3,000 m3/day commits to implement the measures to
control and minimize the adverse impacts on the environment and the socio-economic
development during construction and operation phases as specified in the EIA report.
Project owner will adopt the measures to prevent incidents and reduce pollution as
outlined in the EIA report, while to enhance the staff training to improve the
environmental management capacity of the project, to ensure that no environmental
pollution problems arising .
During the project operation, Tin Nghia Corporation will establish a management
board, which is responsible for the activities such as management of project activities,
ensuring environmental sanitation and repairing infrastructure systems, ensuring
regional security etc.
The project owner will coordinate with agencies specializing in the design and
construction of pollution control systems to achieve the level of pollution in
accordance with environmental regulations and response against environmental
incidents.
During the project construction as well as operation phases, if the incident arise and
cause the damage to residential areas surrounding the project, the project owner will
commit to compensate the damage caused by the project.
167
The project owner commits to obey the legal regulations on the management of waste
and hazardous waste before the project went into operation.
The project owner commits to complete the environmental pollution treatment
facilities and the environment pollution control systems before the project went into
operation.
The project owner commits to seriously operate the central wastewater treatment
plant, regularly monitor and report to the functional agencies.
7.5.2. Commitment for Implementation of Environmental Protection Measures
and Provisions
7.5.2.1. Commitment to meet Vietnam environmental standards/regulations during
construction and operation phases:
The project owner commit to ensure the Vietnam environmental standards/regulations
compliance during the project’s construction and operation, including:
(1). Noise, vibration:
To ensure noise generated from the project’s construction and operation will achieve
the following criteria:
Maximum permissible limit of noise in the labor areas (TCVS 3733/2002/QD-BYT:
occupational health standards, regulations on noise level and maximum concentration
of pollutants in the labor areas);
QCVN 26:2010/BTNMT: Maximum allowable limit of noise intensity in public and
residential areas;
QCVN 27:2010/BTNMT: Maximum allowable limit of vibration intensity in public
and residential areas.
(2). Wastewater:
Treated wastewater to reach Vietnam regulation QCVN 40:2011/BTNMT–National
regulation about industrial discharge, Column A, Kf=0,9, Kq=0,9 before discharging
into the Lòng Tàu stream.
(3). Domestic solid waste and hazardous waste:
Collecting and transporting the solid wastes to the disposal area in compliance with
requirements on environment sanitation;
Solid waste: All solid waste volume (domestic and production solid wastes ) will be
collected, sorted and contracted with Dong Nai Urban Environment Service Company
Limited or authorised companies for collecting, transporting and processing in
accordance with safety requirements;
168
Hazardous and non-hazardous solid wastes will be collected and transported to the
disposing site in accordance with safety requirements to commit compliance with
Decree 59/2007/ND-CP on the management of solid waste; Circular 12/2011/TT-
BTNMT dated 14 April 2011 on hazardous waste management;
Sludge from the central wastewater treatment plant will be tested in the analysis
laboratories then be disposed according to the regulations.
7.5.2.2. Commitment to implement all environmental protection measures and
general provisions:
Project owner commit to meet the requirements on environmental protection as
follows:
- To implement fully and accurately the contents of the approved environmental
impact assessment report;
- To meet the requirements of the environmental landscape, to protect public and
worker’s health;
- There is a professional division qualified to perform the task of environmental
protection;
- To undertake the environmental protection measures and to complete those
during the preparation and construction phases before the project operation
starts;
- To commit the compensation and remediation of environmental pollution in
case of environmental risks occurred when implementing the project;
- To commit the environmental restoration in accordance with the law on
environmental protection after the project operation ended.
Project owner commit to take full legal responsibility before Vietnam law for
violations of the International Convention, Vietnam Standards and Regulations if
incident happened to cause environmental pollution.